of 70
7/28/2019 Sec 500 (Most Version)
1/70
Base and Surface Courses (Bituminous) Section 500
Base and Surface Courses (Bituminous)
500
Base and Surface Courses (Bituminous)
- 1 -
7/28/2019 Sec 500 (Most Version)
2/70
Base and Surface Courses (Bituminous) Section
500
501. PREPARATION OF SURFACE
501.1 . Scope
This work shall consist of preparing an existing granular or black-topped surface
to specified lines, grades and cross-sections in advance of laying a bituminous course.The work shall be performed on such widths and lengths as shown in applicable drawing
and consist of scarifying and re-laying the granular base course and/or scarifying the
existing surface, filling of potholes, sealing of cracks and/or application of a profilecorrective course (levelling course) as necessary.
501.2. Materials
501.2.1. For scarifying and re-laying the granular surface: The materials used
shall be coarse aggregates salvaged from scarification of the existing granular base coursesupplemented by fresh coarse aggregates and screenings so that aggregates and screening
thus supplemented correspond to Clause 404: Water Bound Macadam or Clause 406: WetMix Macadam, as the case may be.
501.2.2. For patching potholes and sealing cracks: For patching potholes,
approved material having same specification as that of profile corrective course shall be
used. For sealing small cracks finer than 3 mm, a fog seal conforming to Section 3000shall be applied while larger cracks wider than 3 mm shall be treated with an emulsion
slurry seal, conforming to Clause 516.
501.2.3. For profile corrective course: A profile corrective course (levelling
course) is essentially a pavement base material course for correcting the existing
pavement profile which has either lost its shape or has to be given a new shape to meetthe requirement of specified lines, grades and cross-sections.
It shall be differentiated from the strengthening course or other type of structural
pavement course needed for upgrading as a remedial measure against inherently deficientand/or distressed pavement. It is meant to remove the irregularity in the existing road
profile only.
501.2.4. Profile corrective course and its application: The type of material for
profile corrective course shall be as shown on the drawing. If it is to be laid as part of the
overlay/strengthening course, the profile corrective course material shall be of the same
specification as that of the overlay/strengthening course. However, if provided as aseparate layer, it may be of the same specification as the layer over which it is to be laid
or intermediate between underlying layers, as shown on the Drawing.
(i) Wherever isolated high spots projecting over the pavement surface do
exist, the same shall be cut by milling machine or any other approved
method, to minimise the profile corrective course requirement. If, in the
- 2 -
7/28/2019 Sec 500 (Most Version)
3/70
Base and Surface Courses (Bituminous) Section
500
process, the bottom layer gets disturbed, the local area shall be cut and
filled with profile with profile corrective course material.
(ii) Where the maximum profile corrective course thickness works out to be
not more than 40 mm, it shall be done as an integral part of the overlaycourse. In other cases, the profile corrective course shall be provided as a
separate layer adopting such construction procedures and using such
equipment as may be appropriate to the specified type of material andthickness of the course to be provided.
501.3. Construction Operations
501.3.1. Preparing existing granular surface: Where the existing surface is
granular, all loose and disintegrated materials shall be removed and the surface lightlywatered if the profile corrective course to be provided as a separate layer is also granular.
If, however, over the existing granular surface, a profile corrective course of bituminousmaterial is to be laid, the existing granular surface shall be primed as per Clause 502.
501.3.2.Scarifying existing bituminous surface: Where necessary, the existing
bituminous layer in the specified width shall be removed with care without causing undue
disturbance to the underlying layer by suitable method approved by the Engineer. Afterremoving it, all loose and disintegrated materials of underlying layer which might have
been disturbed in the process of removal shall, before laying of the overlay course, be
reset properly by spreading/hand packing of aggregates and compacting with suitableroller/heavy hand rammers/approved mechanical tamper so that the level of the top
surface of such scarified area shall be even and properly graded with respect to adjoining
surface. Where applicable, the granular surface, after removal of the existing bituminouslayer, shall be primed as per Clause 502 to receive a bituminous profile corrective course.
Reusable materials shall be stacked as directed by the Engineer with all lift and lead of
1000 m.
501.3.3. Patching of potholes and sealing of cracks: Before providing profile
corrective course on the existing pavement, potholes, if any, shall be drained of water, cut
to regular shape with sides vertical upto the affected depth and slightly beyond the limitsof affected area and dried. All loose and disintegrated materials from it shall be removed.
The potholes shall then be filled with material as per Clause No.501.2.2 in layers not
exceeding 75 mm after painting the sides and bottom with a thin layer of hot straight-run
bitumen/emulsion and each layer shall be compacted with approved mechanical tampers/small vibratory roller and the top layer shall be flush with the existing bituminous
surface. All loose and/or surplus materials on the surface after making good the potholes,
shall be removed.
The cracks in the old pavement surface shall be sealed with a fog seal if cracks are
small (less than 3 mm width); fog seal consist of a spray of a bituminous cutback or aslow-setting bitumen emulsion diluted with an equal amount of water, the rate of spray
- 3 -
7/28/2019 Sec 500 (Most Version)
4/70
Base and Surface Courses (Bituminous) Section
500
being 0.5 to 1.0 litre/sq.m depending upon the texture and dryness of the existing
bituminous surface. The spray is allowed to set to a firm condition and traffic is allowedonly thereafter so as to ensure that the material is not picked up by traffic. For large
cracks, the sealing shall be done with emulsion slurry seal as per Clause 516 of these
Specifications.
501.3.4 Laying the profile corrective course
501.3.4.1. After preparing the granular surface as in Clauses 501 3.1 and 501.3.2,the profile corrective course with material as per Clause 501.2.3/501.2.4 shall be laid and
compacted to the requirement of particular Specification clause. Where a bituminous
profile corrective course is to be laid over a primed granular surface, a tack coatconforming to Clause 503 shall be applied prior to laying profile corrective course.
501.3.4.2. An existing bituminous surface shall be prepared as per Clause 501.3.3.and after applying a tack coat conforming to Clause 503, the bituminous profile
corrective course shall be laid and compacted to the requirement of particularSpecification clause.
501.3.5. In specific situation of short sags or depressions in the pavement, it may
become necessary to provide corrective course in the form of flat wedges. Normally,
layers in maximum thickness at any point more than 100 mm shall not be provided. Inplacing multiple lifts, the lift of shortest length (at the lowest portion of the
sag/depression) should be provided first, with successive lifts extending over and fully
covering underneath layer, precluding development of a series of joints on the topsurfaces, as illustrated in Fig. 500-1.
For camber correction or correction of superelevation of the existing carriageway,method as shown in the illustrative Fig. 500-2 shall be adopted depending on the profile
of the existing carriageway.
See diagrams on pages 142 and 143 of Specifications.
501.3.6. Covering the profile corrective course: Work of Profile CorrectiveCourse shall be so planned that it shall be covered by the designed base/wearing course at
the earliest, before opening to regular traffic.
501.4. Surface Finish and Quality Control of Work
Relevant provisions of Section 900 shall be exercised by the Engineer.
501.5. Arrangement for Traffic
During the construction operations, arrangement of traffic shall be done to Clause112.
- 4 -
7/28/2019 Sec 500 (Most Version)
5/70
Base and Surface Courses (Bituminous) Section
500
501.6.Measurements for Payment
501.6.1. The work of filling potholes shall be considered incidental to the
construction of Profile Corrective Course/bituminous course for which the existing
pavement surface is prepared.
The work of filling cracks by applying fog seal or emulsion slurry seal shall be
measured in square metres, and paid separately.
501.6.2. Scarifying existing bituminous surface shall be measured in square
metre.
501.6.3. Profile Corrective Course shall be measured as volume compacted in
position in cubic metres or in tonnage as specified in the contract. The volume shall beworked out by plotting the exact profile of Profile Corrective Course as built up at site
and superimposed on the existing pavement profile.
501.7. Rates
501.7.1. Contract unit rate for scarifying of existing bituminous surface including
repairing/resetting disturbed underlying layer and also removing and stacking reusable/unusable materials shall include cost of all labour, supply of materials needed for
repair/resetting, hire charges of tools and plant and transportation of scarified materials
with all lifts and upto a lead of 1000 m.
501.7.2. The contract unit rate for Profile Corrective Course shall be payment in
full for carrying out the required operations including full compensation for:
(i) Making arrangements for traffic to Clause 112;
(ii) Providing all materials to be incorporated in the work including anyroyalties, fees, rents (where applicable) and all leads and lifts, unless the
contract specifically excludes any item of material required for the work
or provides for separate payment in accordance with Clause 514;
(iii) Preparation of the exposed surface/existing surface including filling of pot
holes, all cleaning operations and application of track coat;
(iv) All labour, tools, equipment and incidentals necessary to complete the
work to the Specifications; and
(v) Carrying out the work in part widths of road where directed by the
Engineer.
- 5 -
7/28/2019 Sec 500 (Most Version)
6/70
Base and Surface Courses (Bituminous) Section
500
501.7.3. The contract unit rate for sealing cracks by applying fog seal shall be
inclusive of providing all materials and tools and plant and carrying out the work. Thecontract unit rate for sealing cracks by providing emulsion slurry seal shall be as set forth
in Clause 516.9.
502. PRIME COAT OVER GRANULAR BASE
502.1. Scope
This work shall consist of application of single coat of low viscosity liquid
bituminous material to an absorbent granular surface preparatory to any superimposed
bituminous treatment or construction.
502.2.1. Materials
502.2.1. The choice of a bituminous primer shall depend upon the porosity
characteristics of the surface to be primed as classified in IRC : 16. These are:
(i) Surfaces of low porosity; such as wet mix macadam andwater bound macadam,,
(ii) Surfaces of medium porosity; such ascement stabilized soil base,
(iii) Surfaces of high porosity; such as a gravelbase .
502.2.2. The different ranges of viscosity requirements for the primers to be usedfor the different types of surfaces to be primed as classified in 502.2.1, are given in Table
500-1.
TABLE 500-1. VISCOSITY REQUIREMENT AND QUANTITY OF
BITUMINOUS PRIMER
Type of surface Kinematic Viscosity of
Primer at 60o C
(Centistokes)
Quantity per
10 sq. m
(kg)
Low porosity 30-60 6 to 9
Medium porosity 70-140 9 to 12
High porosity 250-500 12 to 15
502.2.3. The bituminous primer shall be Medium Curing Cutback (MC) producedby fluxing, in an approved manner, bitumen of 80/100 penetration grade with kerosene.
- 6 -
7/28/2019 Sec 500 (Most Version)
7/70
Base and Surface Courses (Bituminous) Section
500
The cutback shall be free from water and shall not show any signs of separation prior to
use. Slow setting Cationic emulsion as per IS : 8887 may also be used, but the particulargrade to be used for the work shall be got approved by the Engineer.
Sampling and testing of bituminous primer shall be as per IS : 217; IS : 454 and
IS : 8887.
502.3. Weather and Seasonal Limitations
The bituminous primer shall not be applied on a wet surface or during dust storm
or when the weather is foggy, rainy or windy. The prime coat for surface treatment
should not be applied when the temperature in the shade is less than 10oC.
502.4. Construction
502.4.1. Equipment: The primer distributor shall be pneumatic tyred self-
propelled pressure distributor equipped for spraying the material uniformly at thespecified rates and temperatures. Spraying by manual methods may be allowed for small
areas at the discretion of the Engineer. Power broom and/or blowers may besupplemented by hand brooms as directed by the Engineer.
502.4.2. Preparation of road surface: The surface to be primed shall be sweptclean, free from dust and shall be dry . It shall be shaped to the specified grades and
section. It shall also be free from ruts, any other irregularities and segregated materials.
Minor depressions and potholes may be ignored until the surface is primed, after whichthey shall be patched with a suitable premix material prior to the surface treatment.
502.4.3. Application of bituminous primer: The bituminous primer shall besprayed/distributed uniformly over the dry surface, prepared as per Clause 502.4.2 using
self-propelled sprayer equipped with self-heating arrangement, suitable pump, adequate
capacity compressor and spraying bar with nozzles having constant volume or pressure
system capable of supplying primer at specified rates and temperatures so as to provide auniformly unbroken spread of primer. If the surface to be primed is so dry or dusty as to
cause freckling of bituminous material, it shall be lightly and uniformly sprinkled with
water immediately prior to priming; however, the bituminous material shall not beapplied till such time as no surface water is visible. The primer shall be applied at the rate
as specified in Table 500-1.
Temperature of application of a primer need only be high enough to permit theprimer to be effectively sprayed through the jets of the spray bar and to cover the
granular base surface uniformly in the desired quantity.
The desirable range of temperatures at the time application of MC-30, MC-70 and
MC-250 grades shall be 30 to 550 C; 50 to 80 0 C and 75 to 100 0 C respectively. For a
bituminous emulsion primer , the range of spraying temperature may be 20 to 60 0 C.
- 7 -
7/28/2019 Sec 500 (Most Version)
8/70
Base and Surface Courses (Bituminous) Section
500
Following the application of bituminous material, the surface shall be allowed to
cure for at least 24 hours or for any other period so as to allow penetration into the basecourse and aeration of volatiles from the primer material. If it is not absorbed within 24
hours after application, sand shall be spread over the surface to blot the excess primer.
Care shall be taken to prevent over-priming; any pools of excess primer left on any part
of the surface shall be swept out over the adjacent surface before spreading sand.
The primer coat shall be applied only on the topmost water bound macadam or any
granular layer, over which the bituminous base course/wearing course is to be laid.
502.4.4. Curing of primer and opening to traffic: It shall always be ensured that
while opening to any kind of traffic, the primed surface is fully cured and is not sticky toavoid being picked up by traffic. Normally, the primed surface shall be allowed to cure
for not less than 24 hours and during this period no traffic of any kind shall be permitted.
502.4.5. Laying of bituminous course over primed surface: Bituminous base
course or wearing course shall be laid over the primed water bound macadam, wet mixmacadam or any other granular base course, in the usual manner as per relevant
Specification for the same including the requirement of tack coat as per Clause 503.
502.5. Quality Control of Work
Control on the quality of materials and work shall be exercised by the Engineer in
accordance with Section 900.
502.6. Arrangement for Traffic
During the construction operations, arrangement of traffic shall be done as perClause 112.
502.7. Measurements for Payment
Prime coat shall be measured in terms of surface area of application in squaremetres.
502.8. Rate
The contract unit rate for prime coat shall be payment in full for carrying out the
required operations including full compensation for all components listed in Clause 401.8
(i) to (v) and as applicable to the work specified in these Specifications.
503. TACK COAT
503.1. Scope
This work shall consist of application of a single coat of low viscosity liquid
bituminous material to an existing road surface preparatory to another bituminousconstruction over it.
- 8 -
7/28/2019 Sec 500 (Most Version)
9/70
Base and Surface Courses (Bituminous) Section
500
503.2. Materials
Binder: The binder used for tack coat shall be a bituminous emulsion or cutback
as specified in the Contract.
503.3. Construction Operation
503.3.1. Preparation of base: The surface on which the tack coat is to be appliedshall be cleaned of dust and any extraneous material before the application of the binder,
by using a mechanical broom or any other approved equipment/method as specified by
the Engineer.
503.3.2. Application of binder: Binder may be heated to the temperature
appropriate to the grade of cutback used and approved by the Engineer and sprayed onthe base at the rate specified in Table 500-2. The normal range of spraying temperature
for a bituminous emulsion shall be 20 0 C - 60 0 C and for a cutback 50 0 C 80 0C if RC-70/MC-70 grade is used. It shall be the responsibility of the Contractor to carefully
handle the inflammable bituminous cutback material so as to safeguard against any firemishap. The binder shall be applied uniformly with the aid of either self-propelled or
towed bitumen pressure sprayer with selfheating arrangement and spraying bar with
nozzles having constant volume or pressure system, capable of spraying bitumen atspecified rates and temperature so as to provide a uniformly unbroken spread of bitumen.
Work should be planned so that no more than the necessary tack coat for the days
operation is placed on the surface. After application and prior to succeeding constructionallow the tack coat to cure, without being disturbed, until the water/cutter has completely
evaporated, as determined by the Engineer.
TABLE 500-2. RATE OF APPLICATION OF TACK COAT
Type Surface Quantity of liquid
Bituminous material in kg per 10 sq. m. area
i) Normal bituminous surfaces 2.0 to 2.5
ii) Dry and hungry bituminoussurfaces
2.5 to 3.0
iii) Granular surfaces treated with
primer
2.5 to 3.0
iv) Non bituminous surfacesa) Granular base (not primed)
b) Cement concrete pavement3.5 to 4.0
3.0 to 3.5
Note : There is no need to apply a tack coat on a freshly laid bituminous course if thesubsequent bituminous course is overlaid the same day without opening it to
traffic .
- 9 -
7/28/2019 Sec 500 (Most Version)
10/70
Base and Surface Courses (Bituminous) Section
500
503.4.Quality Control of Work
Control on the quality of materials and works shall be exercised by the Engineer
in accordance with Section 900.
503.5.Arrangements for Traffic
During the period of construction, the arrangement of traffic shall be done toClause 112.
503.6. Measurement for Payment
Tack coat shall be measured in terms of surface area of application in square
metres.
503.7. Rate
The contract unit rate for tack coat shall be payment in full for carrying out therequired operations including full compensation for all components listed in Clause 401.8
(i) to (v) as applicable to the work specified in these Specifications.
504. BITUMINOUS MACADAM
504.1. Scope
The work shall consist of construction, in a single course, of compacted crushed
aggregates premixed with a bituminous binder, to serve as base/binder course, laidimmediately after mixing, on a base prepared previously in accordance with the
requirement of these Specifications and in conformity with the lines, grades and cross-
sections shown on the drawing or as directed by the Engineer.
504.2. Materials
504.2.1. Bitumen: The bitumen shall be paving bitumen of suitable penetrationgrade (30/40 to 80/100) as per IS : 73. The actual grade of bitumen to be used shall be
decided by the Engineer appropriate to the region, traffic, rainfall and other
environmental conditions. Guidelines on selection of the grade of bitumen are given in
Appendix-4.
504.2.2. Aggregates
504.2.2.1. The aggregates shall consist of crushed stone, crushed gravel/shingle
or other stones. They shall be clean, strong, durable, of fairly cubical shape and free from
disintegrated pieces, organic or other deleterious matter and adherent coating. If crushedshingle/gravel is used, not less than 90 per cent by weight of the gravel/shingle pieces
- 10 -
7/28/2019 Sec 500 (Most Version)
11/70
Base and Surface Courses (Bituminous) Section
500
retained on 4.75 mm sieve shall have at least two fractured faces. The aggregates shall
preferably be hydrophobic and of low porosity. If hydrophilic aggregates are to be used,the bitumen shall preferably be treated with anti-stripping agents of approved quality in
suitable dose as Appendix-5. The aggregates shall satisfy the physical requirements set
forth in Table 500-3.
TABLE 500-3. PHYSICAL REQUIREMENTS OF AGGREGATES FOR
BITUMINOUS MACADAM
S.No. Test Test Method Requirement
1. Los Angeles Abrasion Value* IS : 2386 (Part-4) 40 per cent Maximum
2. Aggregate Impact Value * IS : 2386 (Part-4) 30 per cent Maximum
3. Flakiness and Elongation
Indices (Total) **
IS : 2386 (Part-1) 30 per cent Maximum
4. Coating and Stripping of
Bitumen Aggregate Mixtures
AASHTO T 182 Minimum retained coating
95 per cent
5. Soundness
(i) Loss with SodiumSulphate 5 cycles
(ii) Loss with Magnesium
Sulphate 5 cycles
IS : 2386 (Part-5) 12 per cent Maximum
18 per cent Maximum
6.Water absorption
IS : 2386 (Part-3) per cent Maximum
* Aggregates may satisfy requirements for either of the two tests.
** To determine this combined proportion, the flaky stone from a representative
sample should first be separated out. Flakiness index is weight of flaky stone
metal divided by weight of stone sample. Only the elongated particles beseparated out from the remaining (non-flaky) stone metal. Elongation index is
weight of elongated particles divided by total non-flaky particles. The value of
flakiness index and elongation index so found are added up.
Note : If crushed slag is used, Clause 404.2.3. shall apply.
504.2.2.2. The aggregate for bituminous macadam shall conform to one of the twogradings in Table 500-4, depending on the compacted thickness; the actual grading shall
be as specified in the Contract.
504.2.3. Proportioning of materials: The bitumen content for premixing shall
be 3 to 3.5 per cent by weight of the total mix except when otherwise directed by the
Engineer.
- 11 -
7/28/2019 Sec 500 (Most Version)
12/70
Base and Surface Courses (Bituminous) Section
500
TABLE 500-4. AGGREGATE GRADING FOR BITUMINOUS MACADAM
IS Sieve Designation Grading 1 Grading 2
45.0 mm 100 -
26.5 mm 75-100 100
22.4 mm 60-95 75-100
11.2 mm 30-55 50-85
5.6 mm 15-35 20-40
2.8 mm 5-20 5-20
90.0 micron 0-5 0-5
The maximum compacted thickness of a layer shall be 100 mm.
The quantities of aggregates to be used shall be sufficient to yield the specifiedthickness after compaction.
504.2.4. Variation in proportioning of material: The Contractor shall have theresponsibility for ensuring proper proportioning of materials and producing a uniform
mix. A variation in binder content 0.3 per cent by weight of total mix shall, however, be
permissible for individual specimens taken for quality control tests vide Section 900.
504.3. Construction Operations
504.3.1. Weather and seasonal limitations: The work of laying shall not be
taken up during rainy or foggy weather or when the base course is damp or wet, or during
dust storm or when the atmospheric temperature in shade is 10oC or less.
504.3.2. Preparation of the base: The base on which bituminous macadam is to
be laid shall be prepared, shaped and conditioned to the specified lines, grades and cross-sections in accordance with Clause 501, and a priming coat where needed shall be
applied in accordance with Clause 502 as directed by the Engineer.
504.3.3. Tack coat: A tack coat as per Clause 503 shall be applied over the base.
504.3.4. Preparation and transport of mix: Bituminous macadam mix shall be
prepared in a hot mix plant of adequate capacity and capable of yielding a mix of properand uniform quality with thoroughly coated aggregates.
Hot mix plant shall be of suitable capacity preferably of batch mix type. Totalsystem for crushing of stone aggregates and feeding of aggregate fractions in required
proportions to achieve the desired mix, deployed by the Contractor must be capable of
- 12 -
7/28/2019 Sec 500 (Most Version)
13/70
Base and Surface Courses (Bituminous) Section
500
meeting the overall Specification requirements under stringent quality control. The plant
shall have the following essential features:
A General
(a) The plant shall have coordinated set of essential units capable of producinguniform mix as per the job mix formula.
(b) Cold aggregate feed system with minimum 4 bins having belt conveyorarrangement for initial proportioning of aggregates from each bin in the required
quantities. In order to have free flow of fines from the bin, it is advisable to have
vibrator fitted on bin to intermittently shake it.
(c) Belt conveyers below each bin should have variable speed drive motors. There
should be electronic load sensor on the main conveyer for measuring the flow ofaggregates.
(d) Dryer unit with burner capable of heating the aggregate to the required
temperature without any visible unburnt fuel or carbon residue on the aggregateand reducing the moisture content of the aggregate to the specified minimum.
(e) The plant shall be fitted with suitable type of thermometric instruments atappropriate places so as to indicate or record/register the temperature of heated
aggregate, bitumen and mix.
(f) Bitumen supply unit capable of heating, measuring/metering and spraying of
bitumen at specified temperature with automatic synchronisation of bitumen and
aggregate feed in the required proportion.
(g) A filler system suitable to receive bagged or bulk supply of filler material and its
incorporation to the mix in the correct quantity wherever required.
(h) A suitable built-in dust control system for the dryer to contain/recycle permissible
fines into the mix. It should be capable of preventing the exhaust of fine dust into
atmosphere for environmental control wherever so specified by the Engineer.
(i) The plant should have centralised control panel/cabin capable of presetting,
controlling/synchronising all operations starting from feeding of cold aggregates
to the discharge of the hot mix to ensure proper quality of mix. It should haveindicators for any malfunctioning in the operation.
(j) Every hot mix plant should be equipped with siren or horn so that the operatormay use the same before starting the plant every time in the interest of safety of
staff.
B - For Batch Type Plant
- 13 -
7/28/2019 Sec 500 (Most Version)
14/70
Base and Surface Courses (Bituminous) Section
500
(i) Gradation control unit having minimum four deck vibratory screens for accurate
sizing of hot aggregate and storing them in separate bins. This unit should be fullycovered to reduce the maintenance cost and for better environmental condition.
(ii) Proper arrangement for accurate weighing of each size of hot aggregate from the
control panel before mixing.
(iii) Paddle mixer unit shall be capable of producing a homogeneous mix with uniform
coating of all particles of the mineral aggregate with binder.
C - For Continuous Type Plant
(i) Gradation control unit having vibratory screens for accurate sizing of hot
aggregate and storing them in separate bins. This unit should be fully covered to
reduce the maintenance cost and for better environmental condition.
(ii) There should be appropriate arrangement for regulating and volumetric control ofthe flow of hot aggregate from each bin to achieve the required proportioning.
(iii) Paddle mixer unit shall be capable of producing a homogeneous mix with uniform
coating of all particles of the mineral aggregate with binder.
D - For Drum Mix Plant
(i) It is a prerequisite that only properly screened and graded materials are fed to thebins. If required, a vibratory screening unit shall be installed at the plant site to
ensure the same.
A primary 4-deck vibratory screening unit shall be installed before the multiple
bin cold feed system for screening the aggregates and grading the same.
(ii) Belt conveyers below each bin should have variable speed drive motors. Thereshould be electronic load sensor on the main conveyer for measuring the flow of
aggregate.
(iii) There should be arrangement to measure moisture content of the aggregate(s) so
that moisture correction may be applied for working out requirements of binder
and filler.
The temperature of binder at the time of mixing shall be in the range of 150 oC to
163oC and that of the aggregate in the range of 155 oC-163oC. provided that the difference
in temperature between the binder and aggregate at no time exceeds 14oC.
Mixing shall be thorough to ensure that a homogeneous mixture is obtained in
which all particles of the aggregates are coated uniformly, and the discharge temperatureof mix shall be between 130oC to 160 0 C.
- 14 -
7/28/2019 Sec 500 (Most Version)
15/70
Base and Surface Courses (Bituminous) Section
500
The mixture shall be transported from the mixing plant to the point of use insuitable tipper vehicles. The vehicles employed for transport shall be clean and be
covered in transit if so directed by the Engineer. Any tipper causing excessive
segregation of materials by its spring suspension or other contributing factors or that
which shows undue delay shall be removed from the work unit such conditions arecorrected.
504.3.5. Spreading: The mix transferred from the tipper at site to the paver shallbe spread immediately by means of self-propelled mechanical paver with suitable screeds
capable of spreading, tamping, and finishing the mix true to the specified lines, grades
and cross-sections. The paver finisher shall have the following essential features:
(a) Loading hoppers and suitable distributing mechanism.
(b) All drives having hydrostatic drive/control.
(c) The machine shall have a hydraulically extendable screed for appropriate
width requirement.
(d) The screed shall have tamping and vibrating arrangement for initial
compaction to the layer as it is spread without rutting of otherwise marringthe surface. It shall have adjustable amplitude and variable frequency.
(e) The paver shall be equipment with necessary control mechanism so as toensure that the finished surface is free from surface blemishes.
(f) The paver shall be fitted with an electronic sensing device for automaticlevelling and profile control within the specified tolerances.
(g) The screed shall have the internal heating arrangement.
(h) The paver shall be capable of laying either 2.5 to 4.0 m width or 4.0 to 7.0
m width as stipulated in the Contract.
(i) The paver shall be so designed as to eliminate skidding/slippage of the
tyres during operation.
However, in restricted locations and in narrow widths where the available plantcannot be operated in the opinion of the Engineer, he may permit manual laying of the
mix.
The temperature of the mix at the time of laying shall be in the range of 120 0C to
160 0C. In multi-layer construction, the longitudinal joint in one layer shall offset that in
the layer below by about 150 mm. However, the joint in the top-most layer shall be at thelane line of the pavement.
- 15 -
7/28/2019 Sec 500 (Most Version)
16/70
Base and Surface Courses (Bituminous) Section
500
Longitudinal joints and edges shall be constructed true to the delineating lineparallel to the centre line of the road . All joints shall be cut vertical to the full thickness
of the previously laid mix and the surface painted with hot bitumen before placing fresh
material. Longitudinal and transverse joints shall be offset by at least 250 mm from those
in the lower courses and the joint on the top-most layer shall not be allowed to fall withinthe wheel path. All transverse joints shall be cut vertically to the full thickness of the
previously laid mix with asphalt cutter/pavement breaker and surface painted with hot
bitumen before placing fresh material. Longitudinal joints shall be preferably hot joints.Cold longitudinal joints shall be properly heated with joint heater to attain a suitable
temperature of about 800C before laying of adjacent material.
504.3.6. Compaction: After the spreading of mix, rolling shall be done by 80 to
100 kN rollers or other approved equipment. Rolling shall start as soon as possible after
the material has been spread deploying a set of rollers as the rolling is to be completed inlimited time frame.
The roller shall move at a speed not more than 5 km/h. Rolling shall be done with
care to avoid unduly roughening of the pavement surface.
Rolling of the longitudinal joints shall be done immediately behind the paving
operation. After this, the rolling shall commence at the edges and progress towards thecentre longitudinally except that on superelevated and uni-directional cambered portions,
it shall progress from the lower to the upper edge parallel to the centre line of the
pavement.
The initial or break-down rolling shall be done with 80-100 kn static weight
smooth wheel roller (3 wheels or tandem), as soon as it is possible to roll the mix withoutcracking the surface or having the mix pick up on the roller wheels. The second or
intermediate rolling shall follow the break-down rolling with vibratory roller of 80 to 100
kN static weight or pneumatic tyred roller of 150 to 250 kN weight, with minimum 7
wheels and minimum tyre pressure of 0.7 MPa as closely as possible to the paver and bedone while the paving mix is still at a temperature that will result in maximum density.
The final rolling shall be done while material is still workable enough for removal of
roller marks, with 6080 kN tandem roller. During the final rolling, vibratory systemshall be switched off. The joints and edges shall be rolled with a 80 to 100 kN static
roller.
When the roller has passed over the whole area once, any high spots ordepressions which become apparent shall be corrected by removing or adding mix
material. The rolling shall then be continued till the entire surface has been rolled to 95
per cent of the average laboratory density (obtained from Marshall specimens compactedas defined in Table 500-10), there is no crushing of aggregates and all roller marks have
been eliminated. Each pass of the roller shall uniformly overlap not less than one-third of
the track made in the preceding pass. The roller wheel shall be kept damp if necessary toavoid bituminous material from sticking to the wheels and being picked up. In no case
- 16 -
7/28/2019 Sec 500 (Most Version)
17/70
Base and Surface Courses (Bituminous) Section
500
shall fuel, lubricating oil be used for this purpose, nor excessive water poured on the
wheels.
Rolling operations shall be completed in every respect before the temperature of
the mix falls below 100 0 C.
Roller(s) shall not stand on newly laid material while there is a risk that surface
will be deformed thereby. The edges along and transverse of the bituminous macadam
laid and compacted earlier shall be cut to their full depth so as to expose fresh surfacewhich shall be painted with a thin surface coat of appropriate binder before the new mix
is placed against it.
504.4 Surface Finish and Quality Control of Work
The surface finish of construction shall conform to the requirements of Clause902. Control on the quality of materials and works shall be exercised by the Engineer in
accordance with Section 900.
504.5. The bituminous macadam shall be covered with either the next pavementcourse or wearing course, as the case may be, without any delay. If there is to be any
delay, the course shall be covered by a seal coat to the requirement of Clause 513 before
allowing any traffic over it. The seal coat in such cases shall be considered incidental tothe work and shall not be paid for separately.
504.6. Arrangements of Traffic
During the period of construction, arrangement of traffic shall be done to Clause
112.
504.7. Measurements for Payment
The work shall be measured as finished work in cubic metres or by weight inmetric tonnes as provided in the Contract.
504.8. Rate
The contract unit rate for the work shall be payment in full for carrying out the
required operations including full compensation for:
(j) Making arrangements for traffic to Clause 112 except for initial treatment
to verge, shoulders and construction of diversions;
(ii) Preparation of base except for laying of profile corrective course but
including filling of potholes;
- 17 -
7/28/2019 Sec 500 (Most Version)
18/70
Base and Surface Courses (Bituminous) Section
500
(iii) Providing all materials to be incorporated in the work including
arrangement for stock yards, all royalties, fees, rents where necessary andall leads and lifts;
(iv) All labour, tools, equipment, plant including installation of hot mix plant,
power supply units and all machineries, incidental to complete the work tothe Specifications;
(v) Carrying out the work in part widths of the road where directed;
(vi) Carrying out all tests for control of quality; and
(vii) The rate shall cover the provision of bitumen at 3.25 per cent of weight of
total mix, with the provision that the variation of quantity of bitumen will
be assessed and the payment adjusted as per the rate of bitumen quoted.
505. BITUMINOUS PENETRATION MACADAM
505.1. Scope
The work shall consist of construction of one or more layers of compacted
crushed coarse aggregates with alternate applications of bituminous binder and keyaggregates in accordance with the requirements of these Specifications to serve as
base/binder course and in conformity with the lines, grades and cross-sections shown on
the drawings or as directed by the Engineer. Thickness of an individual course shall notexceed 75 mm.
505.2. Materials
505.2.1. Bitumen: The binder shall be paving bitumen of suitable penetration
grade within the range of S-35 to S-90 or A-35 to A-90 (30/40 to 80/100) as per Indian
Standards Specifications for Paving Bitumen IS : 73, or approved cutbacks satisfying
the requirements of IS : 73, 217 or 454. The actual grade of bitumen or cut backs to beused shall be decided by the Engineer, appropriate to the region, traffic, rainfall and other
environmental conditions. Guidance in this regard may be obtained from Appendix-4.
505.2.2. Aggregates
505.2.2.1. The aggregates shall satisfy the physical requirements set forth inClause 504.2.2.1. and Table 500-3.
505.2.2.2. The coarse and key aggregates shall conform to the grading given in
Table 500-5.
505.2.3. Quantities of materials: The quantities of materials used for this work
shall be as specified in Table 500-6.
- 18 -
7/28/2019 Sec 500 (Most Version)
19/70
Base and Surface Courses (Bituminous) Section
500
505.3. Construction Operations
505.3.1. Weather and seasonal limitations: Clause No. 504.3.1. shall apply.
505.3.2. Preparation of the base: The base on which the Penetration macadamcourse is to be laid shall be prepared, shaped and conditioned to the specified lines,
grades and sections to Clause 501 or as directed by the Engineer. A priming coat where
needed shall be applied over the base in accordance with Clause 502 or as directed by theEngineer. A tack coat as per Clause 503 shall be applied.
TABLE 500-5. GRADING REQUIREMENTS OF COARSE AGGREGATES
AND KEY AGGREGATES FOR BITUMINOUS
PENETRATION MACADAM
IS Sieve
Designation
Per cent by weight passing the Sieve
For 50mm compacted thickness For 75mm compacted thickness
Coarse Aggregate Key Aggregate Coarse Aggregate Key Aggregate
63 mm - - 100 -
53 mm - - - -
45 mm 100 - 58-82 -
26.5 mm 37-72 - - 100
22.4 mm - 100 5-27 50-75
13.2 mm 2-20 50-75 - -
11.2 mm - - - 5-25
5.6 mm - 5-25 - -
2.8 mm 0-5 0-5 0-5 0-5
TABLE 500-6. QUANTITIES OF MATERIALS REQUIRED FOR 10 sq.m.
OF ROAD SURFACE FOR BITUMINOUS PENETRATION
MACADAM BASE/BINDER COURSE
Compacted
thickness
Binder
Straight run
bitumen
Coarse Aggregate Key Aggregate
50 mm 50kg 0.60 cu.m. 0.15 cu.m.
75 mm 68kg 0.90 cu.m. 0.18 cu.m.
505.3.3.Spreading and compacting coarse aggregates: The coarse aggregate
in a dry and clean form shall be spread uniformly and evenly at the rate specified in Table500-6 preferably with the help of a self-propelled or tipper tail mounted aggregate
spreader capable of spreading aggregate uniformly at the specified rates over the required
- 19 -
7/28/2019 Sec 500 (Most Version)
20/70
Base and Surface Courses (Bituminous) Section
500
widths. The surface of the layer shall be carefully checked with camber templates and all
high and low spots remedied by removing or adding aggregates as may be required. Thespreading shall be carried no further in advance of the rolling and penetrating operations
than can be completed in one average days work. Segregated aggregates or aggregates
mixed with earth or other foreign substances shall be removed and replaced with graded
aggregates.
505.3.4. Compaction: After the spreading of coarse aggregates, dry rolling shall
be done by 80-100 kN smooth-wheeled steel roller. Rolling shall start as soon as possibleafter the material has been spread. The rolling shall commence at the edges, parallel to
the centre line of the road and progress towards the centre longitudinally except on
superelevated and uni-directional cambered portions, where it shall progress from thelower to the upper edge after the edges have been rolled. For superelevated portions, the
overlapping should be approximately one-third of the width of the rear wheel on each
trip.
After initial dry rolling, the surface shall be checked with a crown template and a3 metre straight-edge. The surface shall not vary more than 10 mm from the template or
straight-edge. All surface irregularities exceeding the above limit shall be corrected byremoving or adding aggregates as required.
The rolling shall be done until the compacted coarse aggregate has firm surfacetrue to the cross section shown on the plans and that it has a texture that will allow free
and uniform penetration of the bituminous material.
505.3.5. Application of bituminous material: After the coarse aggregate has
been rolled and checked, the bituminous binder shall be applied at specified temperatures
as directed by the Engineer. The rate of application shall be as specified in Table 500-6.
At the time of applying the binder, the aggregates shall be surface dry for full
depth of the layer.
The bituminous material shall preferably be applied by a pressure distributor
uniformly over the surface at the specified rate. Over small areas, where the use of a
spray bar is impracticable, the bituminous material shall be applied by the nozzleattachment. Only when permitted, pouring pots may be used according to the directions
of the Engineer.
505.3.6. Application of key aggregates: Immediately after the first penetrationof bitumen, the key aggregates in a clean and dry state shall be spread uniformly over the
surface by means of an approved mechanical spreader or by approved manual methods at
the rate specified in Table 500-6.
If necessary, the surface shall be broomed to ensure uniform application of the
key aggregates. The entire surface shall then be rolled with a 80-100 kN smooth steel
- 20 -
7/28/2019 Sec 500 (Most Version)
21/70
Base and Surface Courses (Bituminous) Section
500
wheel roller (along with vibratory roller if available) to the Specifications conforming to
Clause 505.3.4.
505.4. Surface Finish and Quality Control
The surface finish of construction shall conform to the requirements of Clause902.
Controls on the quality of materials and works shall be exercised by the Engineerin accordance with Section 900.
505.5. The Penetration Macadam shall be provided with final surfacing(binder/wearing course) without any delay. If there is to be any delay, the course shall be
covered by a seal coat to the requirements of Clause 513 before allowing any traffic over
it. The seal coat in such cases shall be considered incidental to the work and shall not bepaid for separately.
505.6. Arrangements for Traffic
During the period of construction, arrangements for traffic shall be done to Clause
112.
505.7. Measurements for Payment
Penetration Macadam Base/Binder Course shall be measured as finished work insquare metres.
505.8. Rate
The contract unit rate for Penetration Macadam Course shall be payment in full
for carrying out the required operations including full compensation for all components
listed in Clause 504.8 (i) to (vi).
506. BUILT-UP SPRAY GROUT
506.1 Scope
This work shall consist of a two-layer composite construction of compacted
crushed coarse aggregates with application of bituminous binder after each layer and keyaggregates on top for the second layer, in accordance with the requirements of these
Specifications to serve as a base course and in conformity with the lines, grades and
cross-sections shown on the drawings or as directed by the Engineer. Thickness of thecourse shall be 75mm.
Built-up spray grout shall be used in a single course in a pavement structure.
- 21 -
7/28/2019 Sec 500 (Most Version)
22/70
Base and Surface Courses (Bituminous) Section
500
506.2. Materials
506.2.1. Bitumen: Clause 504.2.1 shall apply.
506.2.2. Aggregates: The coarse aggregate shall conform to Clause 504.2.2.1.
The aggregate shall satisfy the physical requirements set out in Table 500-3 .The
coarse and key aggregates for built-up spray grout shall conform to the grading given in
Table 500-7.
TABLE 500-7. GRADING REQUIREMENTS OF COARSE AND KEY
AGGREGATES FOR BUILT-UP SPRAY GROUT
IS Sieve
Designation
Per cent by weight passing the Sieve
Coarse Aggregate Key Aggregate
53.0 mm 100 -
26.5 mm 40-75 -22.4 mm - 100
13.2 mm 0-20 40-75
5.6 mm - 0-20
2.8 mm 0-5 0-5
506 .3. Construction Operations
506.3.1. Weather and seasonal limitations: Clause 504.3.1. shall apply.
506.3.2. Preparation of base: The base on which the built-up spray grout
course is to be laid shall be prepared, shaped and conditioned to the specified lines,grades and cross-sections in accordance with Clause 501. A priming coat where needed
shall be applied in accordance with Clause 502 with suitable primer as directed by the
Engineer.
506.3.3. Tack coat: A tack coat over the base shall be applied as per Clause
503.
506.3.4. Spreading and rolling coarse aggregates for the first layer:Immediately after the application of tack coat, the coarse aggregates in a dry and clean
form shall be spread uniformly and evenly preferably by mechanical means at the rate of
0.5 cu.m. per 10 sq.m area. The surface of the layer shall be carefully checked withtemplates and all high and low spots remedied by removing or adding aggregates as may
be required.
Immediately after spreading of the aggregates, the entire surface shall be rolled
with a 80-100 kN smooth-wheeled roller. Rolling shall commence at the edges andprogress towards the centre except in superelevated and uni-directional cambered
portions where it shall proceed from the lower edge to the higher edge. Each pass of the
- 22 -
7/28/2019 Sec 500 (Most Version)
23/70
Base and Surface Courses (Bituminous) Section
500
roller shall uniformly overlap not less than one-third of the track made in the preceding
pass.
After initial rolling, the surface shall be checked transversely and longitudinally
with templates and any irregularities corrected by loosening the surface, adding or
removing necessary amounts of aggregate, followed by rolling.
Rolling shall be stopped before voids in the aggregate layer are closed to such an
extent as to prevent free and uniform penetration of the binder.
506.3.5. Application of binder-first spray: The binder shall be heated to the
temperature appropriate to grade of bitumen approved by the Engineer and sprayed onaggregate layer at the rate of 15 kg/10 sq. m. (in terms of straight-run bitumen) in a
uniform manner with the help of mechanical sprayers capable of spraying bitumen
uniformly at specified rates and temperatures. Excessive deposits of binder caused bystopping or starting of the sprayers or through leakage or any other reason shall be
corrected promptly.
506.3.6. Spreading and rolling of coarse aggregate for the second layer:Immediately after the first application of the binder, the second layer of coarse aggregates
shall be spread and rolled to Clause 506.3.4.
506.3.7. Application of binder-second spray: The second aggregate layer shall
then be given a binder spray at the rate of 15 kg/10 sq.m. (in terms of straight-run
bitumen) to Clause 506.3.5.
506.3.8. Application of key aggregate: Immediately after second application of
the binder, key aggregates in a clean and dry state shall be spread uniformly and evenly,preferably by mechanical means at the rate of 0.13 cu.m./10 sq.m. so as to cover the
surface completely. If necessary, the surface shall be broomed to ensure uniform
application of the key aggregates. The entire surface shall then be rolled with a 80-100
kN smooth-wheeled roller to Clause 506.3.4. While rolling is in progress, additional keyaggregates, where required, shall be spread by hand. Rolling shall continue until the
entire course is thoroughly compacted and key aggregates are firmly in position.
506.4. Surface Finish and Quality Control
The surface finish of construction shall conform to the requirements of Clause
902.
Control on the quality of materials and works shall be exercised by the Engineer
in accordance with Section 900.
506.5. The built-up-spray-grout shall be provided with final surfacing without any
delay. If there is to be any delay, the course shall be covered by a seal coat to the
- 23 -
7/28/2019 Sec 500 (Most Version)
24/70
Base and Surface Courses (Bituminous) Section
500
requirement of Clause 513 before allowing any traffic over it. The seal coat in such cases
shall be considered incidental to the work and shall not be paid for separately.
506.6. Arrangements for Traffic
During the period of construction, arrangement of traffic shall be done to Clause112.
506.7. Measurements for Payment
Built-up spray grout shall be measured as finished work in square metres.
506.8. Rate
The contract unit rate for built-up spray grout shall be payment in full for carryingout the required operations including full compensation for all components listed in
Clause 504.8 (i) to (vi).
507. DENSE BITUMINOUS MACADAM
507.1. Scope
This work shall consist of construction in a single course of 50 to 100 mm thick
base/binder course to the following Specifications on a previously prepared base.
507.2. Materials
507.2.1. Bitumen: The bitumen shall be paving bitumen of Penetration Grade S65 or A 65 (60/70) as per Indian Standard Specifications for Paving Bitumen IS : 73.
In case of non-availability of bitumen of this grade, S 90 (80/100) grade bitumen may be
used with the approval of the Engineer. Guidance to selection of the grade of bitumen
may be taken from Appendix-4.
507.2.2. Coarse aggregates: The coarse aggregates shall consist of crushed
stone, crushed gravel/shingle or other stones. They shall be clean, strong, durable, offairly cubical shape and free from disintegrated pieces, organic or other deleterious
matter and adherent coating. The aggregates shall preferably be hydrophobic and of low
porosity. If hydrophilic aggregates are to be used, the bitumen shall be treated with
antistripping agents of approved quality in suitable doses. The aggregates shall satisfy thephysical requirements set forth in Table 500-8.
If crushed gravel/shingle is used, not less than 90 per cent by weight of thegravel/shingle pieces retained on 4.75 mm sieve shall have at least two fractured faces.
The portion of the total aggregate passing 4.75mm sieve shall have a sand equivalent
value of not less than 50 when tested in accordance with the requirement of IS : 2720(Part-37).
- 24 -
7/28/2019 Sec 500 (Most Version)
25/70
Base and Surface Courses (Bituminous) Section
500
The plasticity index of the fraction passing the 425 micron sieve shall not exceed4.
TABLE 500.8. PHYSICAL REQUIREMENTS OF AGGREGATES FOR DENSE
BITUMINOUS MACADAMS.No. Test Test Method Requirement
1. Los Angles Abrasion * Value IS : 2386 (Part-4) 40 per cent Maximum
2. Aggregate Impact value * IS : 2386 (Part-4) 30 per cent Maximum3. Flakiness and Elongation**
Indices (Total)
IS : 2386 (Part-1) 30 per cent Maximum
4. Coating and Stripping of BitumenAggregate Mixtures
AASHTO T 182 Minimum retainedcoating 95 per cent
5. Soundness
(i) Loss with Sodium Sulphate(ii) Loss of Magnesium Sulphate
IS : 2386 (Part-5)
5 cycles5 cycles
12 per cent Maximum18 per cent Maximum
6. Water absorption IS : 2386 (Part-3) 2 per cent Maximum
* Aggregates may satisfy requirements of either of the two tests.
** To determine this combined proportion, the flaky stone from a representative sample
should first be separated out. Flakiness index is weight of flaky stone metal divided
by weight of stone sample. Only the elongated particles be separated out from theremaining (non-flaky) stone metal. Elongation index is weight of elongated particles
divided by total non-flaky particles. The value of flakiness index and elongation
index so found are added up.
507.2.3. Fine aggregates: Fine aggregates shall be the fraction passing 2.36 mm
sieve and retained on 75 micron sieve, consisting of crusher-run screening , gravel , sandor a mixture of both. These shall be clean, hard, durable, uncoated, dry and free from any
injurious, soft or flaky pieces and organic or other deleterious substances.
507.2.4. Filler: Filler shall consist of finely divided mineral matter such as rockdust, hydrated lime or cement as approved by the Engineer.
The filler shall be graded within the following limits:
IS Sieve Per cent passing by weight
600 Micron 100
300 Micron 95 - 10075 Micron 85 100
The filler shall be free from organic impurities and have a Plasticity Index notgreater than 4. The Plasticity Index requirement shall not apply if filter is cement or lime.
When the coarse aggregate is gravel, 2 per cent by mass of total aggregate of portland
cement or hydrated lime shall be added and the percentage of fine aggregate reduced
accordingly. Cement or hydrated lime is not required when the gravel is limestone.
- 25 -
7/28/2019 Sec 500 (Most Version)
26/70
Base and Surface Courses (Bituminous) Section
500
507.2.5. Aggregate gradation: The combined coarse and fine aggregates andfiller (when used) shall produce a mixture to conform to the grading set forth in Table
500-9.
Table 500-9. AGGREGATE GRADATION FOR DENSE BITUMINOUSMACADAM
Sieve Designation Percentage passing the sieve by weight
37.5 mm 10026.5 mm 90-100
13.2 mm 56-80
4.75 mm 29-592.36 mm 19-45
300 micron 5-17
75 micron 1-7
The aggregate mix, as used in work, shall not vary from the low limit on one sieve to the
high limit on the adjacent sieve but shall be well graded.
507.3. Mix Design
507.3.1. Requirement of mix: Apart from conformity with grading and quality
requirements of individual ingredients, the mix shall meet the requirements set out in
Table 50010.
Table 500-10. REQUIREMENTS OF DENSE BITUMINOUS MACADAM MIX
S. No. Description Requirements
1. Marshall stability (ASTM Designation-D-1559) 820 kg (1800 lb)
determined on Marshall specimens compacted minimumby 75 compaction blows on each end
2. Marshall flow (mm) 2-4
3. Per cent Air voids 3-5
4. Minimum voids in mineral aggregates (VMA) 10 per cent-12 per cent5. Per cent voids in mineral aggregates filled
by bitumen (VFB) 65-756. Binder content per cent by weight of total mix Not less than 4.0 per cent
507.3.2. Binder content: The binder content shall be so fixed as to achieve the
requirements of the mix set out in Table 500-10. Marshall method for arriving at the
binder content shall be adopted, replacing the aggregates retained on 26.5 mm sieve bythe aggregates passing 26.5 mm sieve and retained on 22.4 mm sieve.
- 26 -
7/28/2019 Sec 500 (Most Version)
27/70
Base and Surface Courses (Bituminous) Section
500
507.3.3. Job mix formula: The Contractor shall intimate to the Engineer inwriting, atleast 20 days before the start of the work, the job mix formula proposed to be
used by him for the work and shall give the following details:
i) Source and location of all materials;
ii) Proportions of all materials expressed as follows where each is applicable;
(a) Binder, as percentage by weight of total mix;
(b) Coarse aggregate/Fine aggregate/Mineral filler as percentage byweight of total aggregate including mineral filler;
iii) A single definite percentage passing each sieve for the mixed aggregate;
iv) The results of tests enumerated in Table 500-10 as obtained by the Contractor;
v) Test results of physical characteristics of aggregates to be used;
vi) Mixing temperature and compacting temperature.
While working out the job mix formula, the Contractor shall ensure that it is
based on a correct and truly representative sample of the materials that will actually be
used in the work and that the mix and its different ingredients satisfy the physical andstrength requirements of these Specifications.
Approval of the job mix formula shall be based on independent testing by theEngineer for which samples of all ingredients of the mix shall be furnished by the
Contractor as required by the former.
The approved job mix formula shall remain effective unless and until modified bythe Engineer. Should a change in the source of materials be proposed, a new job mix
formula shall be established and got approved from the Engineer before actually using
the materials.
507.3.4. Permissible variation from job mix formula: It shall be the
responsibility of the Contractor to produce a uniform mix conforming to the approved job
mix formula subject to the permissible variations of the individual percentages of thevarious ingredients in the actual mix from the job mix formula to be used within the
limits as specified in Table 500-11. These variations are intended to apply to individual
specimens taken for quality control tests vide Section 900.
TABLE 500-11. PERMISSIBLE VARIATIONS FROM THE JOB MIX
FORMULA
- 27 -
7/28/2019 Sec 500 (Most Version)
28/70
Base and Surface Courses (Bituminous) Section
500
S. No. Description of Ingredients Permissible variation
by weight of total
mix-in per cent
1. Aggregate passing 13.2 mm sieve and larger sieves + 82. Aggregate passing 11.2 mm sieve and 5.6 mm sieve + 7
3. Aggregate passing 2.80 mm sieve and 1.40 mm sieve + 6
4. Aggregate passing 710 micron sieve and 355 micron sieve + 55. Aggregate passing 180 micron sieve + 4
6. Aggregate passing 90 micron sieve + 2
7. Binder + 0.38. Mixing temperature + 10oC
507.4. Construction Operations
507.4.1. Weather and seasonal limitations: Clause 504.3.1. shall apply.
507.4.2. Preparation of base: The base on which Dense Bituminous Macadam
is to be laid shall be prepared, shaped and conditioned to the specified lines, grades and
cross sections in accordance with Clause 501 or as directed by the Engineer . The surfaceshall be thoroughly swept clean free from dust and foreign matter using mechanical
broom and dust removed or blown off by compressed air. In portions where mechanical
means cannot reach, other approved method shall be used. A priming coat where needed,shall be applied in accordance with Clause 502 or as directed by the Engineer.
507.4.3. Tack coat : A tack coat over the base shall be applied as per Clause 503.
507.4.4. Preparation of mix: Clause 504.3.4. shall apply.
507.4.5. Spreading: The mix transported from the hot mix plant to the site shallbe spread by means of a self-propelled paver with suitable screeds capable of spreading,
tamping and finishing the mix to specified grade, lines and cross-section. Paver Finisher
shall have the essential features as spelt out in Clause 504.3.5. However, in restrictedlocations and in narrow widths where the available equipment cannot be operated in the
opinion of the Engineer, he may permit manual laying of the mix. Similarly for smaller
jobs, mechanical paver may be used with the approval of the Engineer.
The temperature of mix at the time of laying shall be in the range of 1200-160 0 C.
Mixes with a temperature of less than 120 0 C shall not be put into paver spreader.Longitudinal joints and edges shall be constructed true to the delineating lines parallel to
the centre line of the road. Longitudinal and transverse joints shall be offset by at least
250 mm from those in the lower courses and the joint on the top most layer shall not beallowed to fall within the wheel path. All transverse joints shall be cut vertically to the
- 28 -
7/28/2019 Sec 500 (Most Version)
29/70
Base and Surface Courses (Bituminous) Section
500
full thickness of the previously laid mix with asphalt cutter and the surface painted with
hot bitumen before placing fresh material. Longitudinal joints shall be preferably hotjoints. Cold longitudinal joints shall be properly heated with joint heater to attain a
suitable temperature of about 80 0 C laying of adjacent material.
507.4.6. Rolling: After spreading the mix by paver, it shall be thoroughlycompacted by rolling with a set of rollers moving at a speed not more than 5 km/h,
immediately following close to the paver. Generally the initial or breakdown rolling shall
be done with 80-100 kN static weight smooth-wheeled roller. The intermediate rollingshall be done with 80-100 kN static weight vibratory roller or with a pneumatic tyred
roller of 150-250 kN weight having a tyre pressure of at least 0.7 MPa. The finish rolling
shall be done with 60-80 kN weight smooth wheeled tandem roller. All the compactionoperations, i.e., breakdown rolling and intermediate rolling can be accomplished by using
vibratory tandem roller of 80-100 kN static weight. During initial breakdown rolling and
finish rolling, no vibratory compaction shall be resorted to. The exact pattern of rollingshall be established after trial compaction as approved by the Engineer. Any
displacement occurring as a result of reversing of the direction of a roller or from anyother cause shall be corrected at once as specified and/or removed and made good. The
rollers shall not be permitted to stand on pavement which has not been fully compactedand where temperature is still more than 70oC. Necessary precautions shall be taken to
prevent dropping of oil, grease, petrol or other foreign matter on the pavement either
when the rollers are operating or standing.
The wheels of roller shall be kept moist to prevent the mix from adhering to them.
But in no case shall fuel/lubricating oil be used for this purpose nor excessive waterpoured on the wheels. Rolling shall commence longitudinally from edges and proceed
towards the centre, except that on superelevated and unidirectional cambered portions, it
shall progress from the lower to upper edge parallel to the centre line of the pavement.The roller shall proceed on the fresh material with rear or fixed wheel leading so as to
minimise the pushing of the mix and each pass of the roller shall overlap the preceding
one by half the width of the rear wheel.
Rolling shall be continued till the density achieved is at least 98 per cent of that of
laboratory Marshall specimen (compacted as defined in Table 500-10) and all roller
marks are eliminated. Skin patching of an area that has been rolled will not be permitted.Rolling operations shall be completed in all respects before the temperature of the mix
falls below 1000C.
507.5. Opening to Traffic
Traffic may be allowed after completion of the final rolling when the mix has
cooled down to the surrounding temperature. The Dense Bituminous Macadam shall be
- 29 -
7/28/2019 Sec 500 (Most Version)
30/70
Base and Surface Courses (Bituminous) Section
500
provided with an appropriate wearing course as early as possible prior to regular opening
to normal traffic and/or impending rain.
507.6. Surface Finish and Quality Control of Work
The surface finish of construction shall conform to the requirements of Clause902.
Control on the quality of materials and work shall be exercised by the Engineer inaccordance with Section 900.
507.7. Arrangements for Traffic
During the period of construction, arrangements for the traffic shall be done to
Clause 112.
507.8. Measurements for Payment
Dense Bituminous Macadam shall be measured as finished work in cubic metresor tonnes as directed by the Engineer.
507.9. Rate
The contract unit rate for Dense Bituminous Macadam shall be payment in full for
carrying out the required operations including full compensation for all components listedin Clause 504.8 (i) to (vi). The rate shall cover the provision of bitumen in the mix at 4.5
per cent of the weight of the total mix, with the provision that the variation of quantity of
bitumen will be assessed and the payment adjusted as per the rate of bitumen quoted.
508. SURFACE DRESSING
508.1. Single and Two-Coat Surface Dressing using Bitumen
508.1.1. Description: This work shall consist of the application of one coat or
two coats of surface dressing, each coat consisting of a layer of bituminous bindersprayed on base prepared previously, followed by a cover of stone chippings properly
rolled to form a wearing course to the requirements of these Specifications.
508.1.2. Materials
508.1.2.1 Binder: The binder shall be straight-run bitumen of a suitable grade
appropriate to the region, traffic, rainfall and other environmental conditions as directedby the Engineer and conforming to IS : 73. Guidance in this regard may be obtained
from Appendix-4.
- 30 -
7/28/2019 Sec 500 (Most Version)
31/70
Base and Surface Courses (Bituminous) Section
500
508.1.2.2. Stone chippings: The stone chippings shall conform to Clause
504.2.2.1. The Stone Polishing Value as measured by BS 812 (Part 114), shall not beless than 55. The stone chippings shall also conform to the quality requirements of Table
500-3 except that water absorption shall be restricted to a maximum of 1 per cent. The
size of stone chippings shall be in accordance with Table 500-12.
508.1.2.3. Quantities of materials: The quantities of materials used for this work
shall be as specified in a Table 500-13.
TABLE 500-12. SIZE REQUIREMENTS OF STONE CHIPPINGS FOR
SURFACE DRESSING USING BITUMEN
S.
No.
Type of construction Normal size of
stone chippings
Specifications
1. Single coat surface dressing
or the first coat of two-coatsurface dressing
13.2 mm 100 per cent passing through
22.4 mm sieve & retained on11.2 mm sieve.
2. Second coat of two-coat
surface dressing (also used as
a renewal coat)
11.2 mm 100 per cent passing through
13.2 mm sieve & retained on
5.6 mm sieve.
TABLE 500-13. QUANTITIES OF MATERIALS REQUIRED FOR 10 sq. m. OF
ROAD SURFACE FOR SURFACE DRESSING USING
BITUMEN
S. No. Type of construction Binder Stone chippings
1. Single coat surface dressing or thefirst coat of the two-coat surface
dressing
18.0 kg 0.15 cu.m
2. Second coat of the two-coat surface
dressing (also used as a renewal coat)
10.0 kg 0.10 cu.m
508.1.3. Construction operations
508.1.3.1. Weather and seasonal limitations: Clause 504.3.1. shall apply.
508.1.3.2. Preparation of base: The base on which the surface dressing is to be
laid shall be prepared, shaped and conditioned to the specified lines, grade and cross-section in accordance with Clause 501 and as directed by the Engineer. Priming coat,
- 31 -
7/28/2019 Sec 500 (Most Version)
32/70
Base and Surface Courses (Bituminous) Section
500
where needed, shall be provided as per Clause 502 and as directed by the Engineer.
Where the existing surface shows signs of fatting up, this shall be rectified. Thebituminous primed surface to be dressed shall be thoroughly cleaned either by using a
mechanical broom or any other approved equipment/method as specified by the Engineer.
Dust removed in the process shall be blown off with the help of compressed air.
508.1.3.3. Application of binder: Bitumen shall be heated to 150oC-163oC and
sprayed on the dry surface in a uniform manner with the help of self-propelledmechanical sprayers having self-heating arrangement and bitumen pressure pump and
spraying bar with nozzles having constant volume or pressure system capable of spraying
bitumen uniformly at the rates specified in Table 500-13 and above mentionedtemperature. Excessive deposits of binder caused by stopping or starting of the sprayer or
through leakages or any other reason shall be corrected by blotting with sand before the
stone chippings are spread.
508.1.3.4. Application of stone chippings: Immediately after the application ofbinder, stone chippings in a dry and clean state shall be spread uniformly on the surface
by means of a self-propelled or towed mechanical grit spreader capable of sprayinguniformly at rates specified in Table 500-13 so as to cover the surface completely. If
necessary, the surface shall be broomed to ensure uniform spread of chippings.
508.1.3.5. Rolling: Immediately after the application of the cover material, the
entire surface shall be rolled with a 80-100 kN smooth wheeled steel roller, 80-100 kN
static weight vibratory roller, or other approved equipment. Rolling shall commence atthe edges and progress towards the centre except in superelevated and uni-directional
cambered portions where it shall proceed from the lower edge to the higher edge. Each
pass of the roller shall uniformly overlap not less than one-third of the track made in thepreceding pass. While rolling is in progress, additional chippings shall be spread by hand
in necessary quantities required to make up irregularities. Rolling shall continue until all
aggregate particles are firmly embedded in the binder and present a uniform closed
surface.
508.1.3.6. Application of second coat of surface dressing: Where surface
dressing in two coats is specified, the second coat shall be applied immediately afterlaying of the first coat. The construction operations for the second coat shall be the same
as described in Clause 508.1.3.3. to 508.1.3.5.
508.1.4. Opening to traffic: Traffic shall not be permitted to run on any newlysurface dressed area until the following day. In special circumstances, however, the
Engineer may open the road to traffic immediately after rolling, but in such cases traffic
speed shall be limited to 16 km per hour till the following day.
508.1.5. Surface finish and quality control of work: The surface finish of
construction shall conform to the requirements of Clause 902.
- 32 -
7/28/2019 Sec 500 (Most Version)
33/70
Base and Surface Courses (Bituminous) Section
500
Control on the quality of materials and works shall be exercised by the Engineer
in accordance with Section 900.
508.1.6. Arrangements for traffic: During the period of construction,
arrangement of traffic shall be done as per Clause 112.
508.1.7. Measurements for payment: Each coat of surface dressing shall be
measured as finished work in square metres.
508.1.8. Rates: The contract unit rate for each coat of surface dressing shall be
payment in full for carrying out the required operations including full compensation for
all components listed in Clause 504.8 (i) to (vi).
508.2. Two-Coat Surface Dressing Using Cationic Bitumen Emulsion
508.2.1. Scope
508.2.1.1. This work shall consist of two-coat surface dressing, each coat
consisting of a layer of cationic bitumen emulsion binder sprayed on a base preparedpreviously, followed by a cover of stone aggregate, properly rolled to form a wearing
course to the requirements of these Specifications.
508.2.1.2. It shall, however, not be applicable to a single coat surface dressing
using cationic bitumen emulsion.
508.2.2. Material
508.2.2.1. Binder: The binder shall be a Cationic type bitumen emulsion ofRapid Setting (RS) grade complying with IS : 8887 and having bitumen content 60 per
cent minimum by weight.
508.2.2.2. Aggregates
(A) General Requirements: Clause 508.1.2.2. shall apply
except the size requirement which shall be as given in Table 500-14. Wetaggregates can be used for surface dressing with Cationic bitumen
emulsions and when aggregates are dusty, they should be cleaned by
washing or by sprinkling water copiously. If the road surface is dry, a light
sprinkling with water shall be done.
(B) Size: The aggregates shall conform to the size given in Table 500-14.
TABLE 500-14. REQUIREMENTS OF STONE CHIPPINGS FOR SURFACE
DRESSING USING BITUMEN EMULSION
- 33 -
7/28/2019 Sec 500 (Most Version)
34/70
Base and Surface Courses (Bituminous) Section
500
1. For first coat-13.2 mm size Passing 22.4 mm sieve and retained on 11.2 mm
sieve.
2. For second coat-6.7 mm size Passing 9.5 mm sieve and retained on 2.36 mm sieve.
(C) Quantities of materials: The quantities of materials used for thiswork shall be as given in Table 500-15.
TABLE 500-15. REQUIREMENTS OF MATERIALS USING BITUMEN
EMULSION
Material For 10 sq.m. area For First Coat For Second Coat
Cationic Bitumen Emulsion 12 to 14 kg 16 to 18 kg
Aggregates 0.10 to 0.12 cu. m. 0.06 to 0.08 cu. m.
508.2.3. Construction operations
508.2.3.1. Weather limitations: Cationic bitumen emulsions should not
normally be stored below 0oC. However, surface dressing with Cationic bitumen
emulsion should be carried out only when the atmospheric temperature is above 10 oC.The work can be carried out when the base is damp. All standing water in depressions
shall, however, be removed.
508.2.3.2. Preparation of base: The existing base on which surface dressing isto be laid shall be prepared, shaped and corrected to a uniform grade and camber in
accordance with Clause 501.
The surface shall be cleaned to remove all loose particles, dust and foreign matter.
It is preferable to spray water on the surface to settle the loose dust and also to expose
clean surface of aggregates in the case of granular base courses.
508.2.3.3. Preparation of binder: Before opening, the Cationic bitumen
emulsion drums should be rolled at slow speed, to and fro, for a distance of about 10
metres, 5 to 6 times to mix the contents properly.
508.2.3.4. First Coat
- 34 -
7/28/2019 Sec 500 (Most Version)
35/70
Base and Surface Courses (Bituminous) Section
500
(A) Application of Binder: :Cationic bitumen emulsion binder can be applied
on wet road surface. If the road surface is dry, light sprinkling with watershall be done. Cationic bitumen emulsion shall be sprayed uniformly on the
prepared base by mechanical sprayers. In exceptional cases spraying from a
spraying can may be resorted to as directed by the Engineer. The spraying
can should have 6mm diameter holes spaced 30 mm apart to preventclogging. An emulsion tank of 30 litres capacity pressurized by compressed
air from a hand pump and a 12 mm flexible pipe with a spray nozzle is a
simple and efficient arrangement for spraying.
(B) Application of aggregate: Immediately after spraying of
Cationic emulsion, aggregate of 13.2 mm size shall be spread uniformly andevenly by mechanical means to cover the surface completely and evenly.
Any oversize aggregate, if seen, shall be removed.
(C ) Rolling: Immediately after the application of cover
material, the surface shall be rolled with 80-100 kN roller preferably bysmooth wheeled tandem type. The rolling shall begin at the edge and
proceed towards the centre, parallel to the centre line except insuperelevated and unidirectional cambered portions where it shall proceed
from the lower edge to the higher edge. While rolling, aggregates shall be
added or removed so as to ensure a uniformly covered surface. Each-pass ofroller shall uniformly overlap not less than one third of the track made in the
preceding pass. Rolling shall continue for just enough time to embed the
aggregates in the binder and present a uniform closed surface. Excessiverolling, resulting in crushing of aggregates shall be avoided.
508.2.3.5. Second coat
(A) Time interval: The second coat of surface dressing shall
be applied on the same day as the first coat but at least not earlier than one
hour after finishing the rolling of the first coat.
(B) Application of emulsion: Traffic shall not be allowed on the first
coat before the application of second coat. If the aggregates of the first coatappear to be loose and unbounded in few spots, the same shall not be
disturbed.
The Cationic bitumen emulsion for second coat shall be sprayed bymechanical sprayer or in exceptional cases by using pouring can with the
approval of the Engineer, taking care not to disturb the first layer while
walking over it.
(C ) Application of aggregate: Immediately after the
application of emulsion, 6.7 mm size aggregates shall be spread uniformlyby mechanical means to cover the whole surface evenly.
- 35 -
7/28/2019 Sec 500 (Most Version)
36/70
Base and Surface Courses (Bituminous) Section
500
(D) Rolling: Rolling shall start soon after spreading theaggregates and all operations carried out as per Clause 508.2.3.4 (C) to
achieve a uniform closed surface.
(E) Finishing: After one pass of the roller, depressions shall be filled with 6.7mm size aggregate. If excess of aggregate is found in isolated spots, the
bigger size aggregates shall be removed to give a uniform surface. Finish
rolling on the next day helps to give a firm surface.
508.2.4. Opening to traffic: The road may be opened to traffic 4 hours after
completing rolling of the second coat, but preferably the next day after 24 hours.
Where the road width is single lane, traffic can be allowed at slow speed of not
more than 10 km per hour making sure to add aggregates and emulsion wherever thesurface has been picked up by traffic.
508.2.5. Surface finish and quality control of work: The surface finish of
construction shall conform to the requirements of Clause 902.
Control on the quality of materials and works shall be exercised by the Engineer
in accordance with Section 900.
508.2.6. Arrangement for traffic: During the period of construction,
arrangement of traffic shall be done to Clause 112.
508.2.7. Measurements for payment: Two coats of surface dressing shall be
measured as a finished work in square metres.
508.2.8. Rate: The contract unit rate for two coats of surface dressing shall be
payment in full for carrying out the required operations including full compensation for
all components listed in Clause 504.8 (i) to (vi).
508.3. Surface Dressing with Precoated Aggregate using Bitumen
508.3.1. Scope
508.3.1.1. The work shall consist of application of either a single coat or two
coats of surface dressing over a previously prepared base, each coat consisting ofapplication of bituminous binder sprayed on a base previously prepared followed by a
cover of precoated materials properly rolled to form a wearing course to the requirements
of these Specifications.
508.3.1.2. This Specification may be adopted in lieu of the conventional surface
dressing to Clause 508.1, in situations where better adhesion is required between theaggregates and binder during construction and later in service. The technique is basically
- 36 -
7/28/2019 Sec 500 (Most Version)
37/70
Base and Surface Courses (Bituminous) Section
500
the same as conventional surface dressing except that a small quantity of binder is used
for precoating the aggregates. However, it is quite different from premix construction.
508.3.2. Materials
508.3.2.1. Binder: The binder shall be straight run bitumen of a suitable gradeappropriate to the region, traffic and other environmental conditions and as directed by
the Engineer and conforming to IS : 73.
508.3.2.2. Aggregates: The aggregates shall conform to Clause 504.2.2. They
shall conform to the quality requirements of Table 500-3 except that the water absorption
shall be restricted to maximum of 1 per cent. The Stone Polishing Value as measured byBS : 812 (Part-114) shall not be less than 55.
The size of the aggregates shall be in accordance with Table 500-12.
508.3.2.3. Quantities of materials: The quantities of materials used for thiswork shall be as specified in Table 500-12 and 500-13.
508.3.2.4. Precoating: The aggregates shall be precoated with 0.75 to 1.00 per
cent of their weight with binder and shall not be precoated simultaneously with the
surface dressing operation. The precoated aggregates shall be allowed to cure for at leastone week so that they become non-sticky to facilitate easy spreading like normal
uncoated aggregates. The aggregates, free of dust or fine particles shall be preheated to
160oC for precoating and then mixed with bitumen binder (0.75 to 1.00 per cent byweight of aggregate) heated to its application temperature. The aggregates and binder
shall be thoroughly mixed in a mixer of approved type till the aggregates are uniformly
coated.
508.3.3. Construction operations
508.3.3.1. Weather and seasonal Limitations: Clause 504.3.1 shall apply.
508.3.3.2. Preparation of base: Clause 508.1.3.2 shall apply.
508.3.3.3. Application of binder: After deducting the binder quantity consumed
in precoating aggregates for first coat in terms of para 508.3.2.4. from the quantities
specified in Table 500-13, remaining binder of first coat shall be heated to 1500 C165 0C
and sprayed on the clean and dry surface in a uniform manner prefe