+ All Categories
Home > Documents > Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies...

Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies...

Date post: 26-Dec-2015
Category:
Upload: marcia-ward
View: 214 times
Download: 1 times
Share this document with a friend
Popular Tags:
38
Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington
Transcript
Page 1: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Security of Supply Issues:Technical & Economic Aspects

Chen-Ching Liu

Advanced Power Technologies Center

University of Washington

Page 2: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Outline

Blackout and cascaded events Shortage of transmission enhancement

Defense system technology Flexible grid configuration

Future areas - Transmission economics and Microgrids

Page 3: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

U.S. Blackout (Aug. 14, 2003)

High temperature in Midwest. FE 870 MW nuclear power plant was down for maintenance.

MISO SE is ineffective from 12:15 to 16:04.

A sequence of lines outages westward and northward across Ohio and into Michigan, and then eastward, splitting New York from Pennsylvania and New Jersey.

Eastlake unit 5 in northern Ohio tripped due to an exciter failure @ 13:31.

A series of 138-kV lines tripped in the vicinity of Akron @ 15:39.

345-kV line (Stuart – Atlanta) tripped @ 14:02.

Voltages in the Akron area fell below low limits.

Loss of the FE Control Center function shortly after 14:14.

345-kV line (Sammis – Star) tripped @ 16:05

Star-South Canton tie line between FE and AEP tripped and reclosed @ 14:27.

Transient instability began after 16:10, and large power swings occurred.

The system becomes unstableThe system become vulnerable Total blackout

Page 4: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Some NERC Recommendations

• Strengthen the NERC compliance enforcement program.• Evaluate vegetation management procedures and results.• Evaluate reactive power and voltage control practices.• Improve system protection to slow or limit the spread of future

cascading outages.• Install additional time-synchronized recording devices as

needed. • Re-evaluate system design, planning, and operating criteria.

Page 5: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Load Shedding

According to the Final NERC Report on August 14, 2003, Blackout, at least 1,500 to 2,500 MW of load in Cleveland-Akron area has had to be shed to prevent the blackout.

Page 6: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Planned Generation Capacity & Transmission Enhancement in U.S.

Actual data (1999~2000)

Planned Capacity ( 25% increase )

Projected Demand ( 18% increase )

Planned Transmission ( 3.5% increase )

Estimated Capacity Margin

(5% increase )

Source: “Reliability Assessment 2001-2010 Report” by NERC, 2001.Information Administration Website: “http://www.eia.doe.gov/cneaf/electricity/page/fact_sheets/transmission.html”

Page 7: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Defense Plans

Coordination of a number of special protection schemes for the entire system

Modification is required (e.g., BPA needs to update the SPSs regularly)

Build a defense system that performs self-healing control actions in an adaptive manner

Page 8: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Strategic Power Infrastructure Defense (SPID)

– Design self-healing strategies and adaptive reconfiguration schemes

To achieve autonomous, adaptive, and preventive remedial control actions

To provide adaptive/intelligent protection To minimize the impact of power system vulnerability

Research consortium with UW, Iowa State, Arizona State and Virginia Tech, sponsored by EPRI, U.S. DoD and 4 institutions, $ 3M total, 1998-2001

Page 9: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Vulnerability Assessment

Vulnerability Regions

AB

CBA CBB

Protection

Voltage Stability

Oscillatory Stability

Transient Stability

Pi

Dynamics and Control

Communication

Page 10: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Intelligent System Models for the Complex Networks

•Physics•Model-based reasoning•Rule-based system•Evolutionary algorithm

•ANN•Generic tasks

•Agent•Multi-agent System

•Decision-making •Forecasting•Learning•Self-healing

•Adaptation•Team work•Coordination•Negotiation

Page 11: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Multi-Agent System for SPID

RE

AC

TIV

E L

AY

ER CO

OR

DIN

AT

ION

LA

YE

R

DE

LIB

ER

AT

IVE

LA

YE

RKnowledge/Decision

exchange

Protection Agents

GenerationAgents

Fault Isolation Agents

FrequencyStabilityAgents

ModelUpdate Agents

CommandInterpretation

Agents

Planning Agent

Restoration Agents

HiddenFailure

Monitoring Agents Reconfiguration Agents

VulnerabilityAssessment

Agents

Power System

Controls

Inhibition Signal

Controls

Plans/Decisions

EventIdentification

Agents

Triggering Events

Event/AlarmFiltering Agents

Events/Alarms

Inputs

Update Model CheckConsistency

Comm.Agent

Page 12: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Adaptive Self-healing:Load Shedding Agent

A control action might fail Reinforcement Learning

– Autonomous learning method based on interactions with the agent’s environment

– If an action is followed by a satisfactory state, the tendency to produce the action is strengthened

Page 13: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Adaptive Self-healing:Load Shedding Agent

The 179 bus system resembling the western U.S. system

ETMSP simulation Remote load shedding scheme based on

frequency decline + frequency decline rate Temporal Difference (TD) method is used for

adaptation: Need to find the learning factor for convergence

Page 14: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Adaptive Self-healing:Load Shedding Agent

179 bus system

Page 15: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Adaptive Self-healing:Load Shedding Agent

0 50 100 150 200 25058.6

58.8

59

59.2

59.4

59.6

59.8

60

frequency with 20 % load shedding

10% load shedding frequ

ency

Time (multiples of 0.02 sec)

Page 16: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Adaptive Self-healing:Load Shedding Agent

0 20 40 60 80 100 120 140 160 1800

0.5

1

1.5

2

2.5

a=0.55

a=0.75

Number of trials

Norm

aliz

ed f

requency Expected normalized system

frequency that makes the system stable

“The load shedding agent is able to find the proper control action in an adaptive manner based on responses from the real power system”

“The load shedding agent is able to find the proper control action in an adaptive manner based on responses from the real power system”

Page 17: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Flexible Grid Configuration to Enhance Robustness

Flexible grid configuration can play a significant role in defense against catastrophic events

Power infrastructure must be more intelligent and flexible

– To allow coordinated operation and control measures to absorb the shock and minimize potential damages caused

by radical events

Page 18: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Area-Partitioning Algorithm

To develop a k-way partitioning algorithm, which uses the information available in network matrices and divides the power grid into k disjoint areas while minimizing load-generation imbalance for each area

Page 19: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Area-Partitioning Algorithm

5

2 1

6 4

3 1

0.1 0.1 0.1

2

1 1

Page 20: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Flexible Grid Configuration by Partitioning

Risk Management of Power Infrastructure

Self-sufficient Sub-networks

Flexible Grid Configuration by Partitioning

Normal Configuration (Wide Area Grid)

High Risk Alert

Lower the Risk Level

Alert is Over

Page 21: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Cascaded Events - Simulation

Compute Power Flows after Tripping– Six lines are found with limit violations – Trip these lines, Bus170 and 171 become isolated buses

Identify New Network Configuration and Solve Power Flows Again

– Fifteen lines are found with limit violations – Trip these lines, seven buses become isolated buses

Continue This Simulation Procedure– Finally the system collapses: most transmission lines are

tripped and most loads are lost

Page 22: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Flexible Grid Configuration to Absorb the Shock

Split the System into Two Areas– Seeds=[Bus 83, Bus 47]– Area One: 92 buses, 117 branches– Area Two: 87 buses, 140 branches

Page 23: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

WECC 179-bus System Example

33 32

31 30

35

80

78

74

79 66

75

77

76 72

82

81

86 83

84

85 156 157 161 162

167 165

158

159 155 44

45 160

166

163

5 11

6

8

9

18 17

4

3

7

14

12 13

138 139

147

15

19

16

114

115

118 119

103

107

108

110 102

104

109

142

37 64 63

153 145 151 152

136 49 48

146 154

149

143

43

230 kV 345 kV 500 kV

34

65

71

69

70

87 88

99 36

73

89 90

124 125

168 169 171

170 172 173

111

120

121 122

123

91 - 94 95 - 98

132 133

135 134 104

174, 176, 178 175, 177, 179

48 38

57 58

54 51

52 53 42

55 41 62 56

40

39

150

137

61

148 22

23 25

24

20 21

29 28

2

10

164

113 100

101

105 106

117

50

42

47

46

59 60(3)

116

27 26

68

67

112

141 140

144

180

48

48

48

Page 24: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Split System into Two Areas

33 32

31 3 0

35

80

78

74

79 66

75

77

76 72

82

81

86 83

84

85

114

115

118 119

103

107

108

110 102

104

109

230 kV 345 kV 500 kV

34

65

71

69

70

87 88

99 36

73

89 90

124 125

169 171

170 172 173

111

120

121 122

123

91 - 94 95 - 98

13 2 133

135 134 104

174, 176, 178

113 100

101

105 106

117 116

68

67

112

180

156 157 161 162 168

167 165

158

159 155 44

45 160

166

163

5 11

6

8

9

18 17

4

3

7

14

12 13

138 139

147

15

19

16

142

37 64 63

153 145 151 152

136 49 48

146 154

149

143

43

175, 177, 179

48 38

57 58

54 51

52 53 42

55 41 62 56

40

39

150

137

61

148 22

23 25

24

20 21

29 28

2

10

164

50

42

47

46

59 60(3)

27 26

141 140

144

48

48

48

Page 25: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Flexible Grid Configuration to Absorb the Shock

Use “Power Redispatching & Load Shedding” in Area Two

– Totally, 188 + 64.4 + 60 = 312.4 MW load are shedBus

#Original Load

(MW)Load Shed

(MW)Load Supplied

(MW)

8 239 188 51

16 793.4 64.4 729

154 1066 60 1006

Page 26: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Alert is Over (Wide-Area Grid)

33 32

31 30

35

80

78

74

79 66

75

77

76 72

82

81

86 83

84

85 156 157 161 162

167 165

158

159 155 44

45 160

166

163

5 11

6

8

9

18 17

4

3

7

14

12 13

138 139

147

15

19

16

114

115

118 119

103

107

108

110 102

104

109

142

37 64 63

153 145 151 152

136 49 48

146 154

149

143

43

230 kV 345 kV 500 kV

34

65

71

69

70

87 88

99 36

73

89 90

124 125

168 169 171

170 172 173

111

120

121 122

123

91 - 94 95 - 98

132 133

135 134 104

174, 176, 178 175, 177, 179

48 38

57 58

54 51

52 53 42

55 41 62 56

40

39

150

137

61

148 22

23 25

24

20 21

29 28

2

10

164

113 100

101

105 106

117

50

42

47

46

59 60(3)

116

27 26

68

67

112

141 140

144

180

48

48

48

Page 27: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Investment & Return Analysis of Transmission Expansion

Economics of transmission expansion should be analyzed from an investment / return point of view. - Economic value of transmission capacity improvement- Economic incentives of transmission owners- Economic incentives of generators

Techniques for electricity price forecasting can be used for economic analysis of transmission

expansion.

Page 28: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Example: Investment & Return Analysis of Transmission Expansion

The expected present value of the discounted stream of revenues ($100) exceeds the investment cost ($84).

Invest now

0 1 2 ... T ... Period

Initial Investment

$15

$5

$15 $15

$5 $5

...

...

...

...

Revenueif Priceis high

Revenue

if Priceis low

50%

50%

Discount rate = 10%

Cost of investment = $84

Page 29: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Wait for One Period to Decide

If price is low, $50 < $ 84 Don’t invest Don’t invest

If price is high, $150 > $ 84 Invest Invest

Expected payoff (= 0.5*($150-$84)/1.1 = $30). Waiting for one period is better than investing now since $30 >

$16.

0 1 2 ... T ... Period

Initial Investment

$15

$5

$15 $15

$5 $5

...

...

...

...

Revenueif Priceis high

Revenue

if Priceis low

50%

50%Discount rate = 10%

Cost of investment = $84

Page 30: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Value of Investment Opportunity

An investment project whose revenue follows a geometric Brownian motion

Value of waiting

Overall value of the investment opportunity

Page 31: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Micro Grid Concept

Distant or remote locations

-Islands

-Regions with no pre-existing infrastructure Special power needs

-Chip fabrication plants

-Financial centers

Page 32: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Wind Generators

CADET Technical Brochure 68 “33.6 MW Wind Farm near Carno” EA, OECD, 1998

Page 33: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Example

Load BusGS-1

Load Bus GS-2 Load Bus GS-3 Load Bus GS-4

Load Bus GS-5

Page 34: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Frequency Response with no Control Agent

0 5 10 15 20 25 3059.92

59.94

59.96

59.98

60

60.02

60.04

Time (seconds)

Fre

quency (

hert

z)

GS-3GS-5

Page 35: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Inter-Machine Oscillations

With no control agent there are clear indications of inter-machine oscillation

Results:

•Unnecessary flow oscillations of power along tie lines

•Unnecessary stress on the machines

•Excessively large overshoots

•Excessively long settling times

Page 36: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Control Agent Scheme

Measure the load at each of the load buses. Measure the frequency at each of the load

buses. When a load change is sensed the control

agent generates control signals based on the current rotational energy of the rotors.

Page 37: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Frequency Response with a Control Agent

0 5 10 15 20 25 3059.96

59.965

59.97

59.975

59.98

59.985

59.99

59.995

60

60.005

60.01

Time (seconds)

Fre

quen

cy (

hert

z)

GS-3GS-5

Page 38: Security of Supply Issues: Technical & Economic Aspects Chen-Ching Liu Advanced Power Technologies Center University of Washington.

Grand Challenges

Prevention of Major Blackouts Energy Crisis in Western U.S. Evolution of Electricity Markets Alternative Energy and Distributed Generation

Engineering / Technology, Economics,

Public Policy


Recommended