SESEI STEERING COMMITTEE MEETING #2June, 12th (08:30-12:00)
Presented by ETSI for SESEI SC#2
© ETSI 2013. All rights reserved
SESEI Project Management – Status
Status Liaison OfficeEBTC lease agreementCaliber manpower agreementBudget• Status• Discussion on Financial estimate proposal
2 © ETSI 2013. All rights reserved
Project Management Admin. I(Bernardo)
Legal Set-up: Liaison Office (LO)• LO application entering in its 4 month (estimative was 3-6 months for
conclusion) period• Reserve Bank of India has asked the Government of India for their
clearance (possibly clearance from Ministry of Finance as ETSI is a not-for-profit Organization).
• Good news: No further documentation asked• Outcome is foreseen anytime now, possibly during June• Once established, next step is to open the so-called QA22C account
with the bank which shall operate the LO (paper work already being analyzed)
© ETSI 2013 All rights reserved3
Project Management Admin. II
Rental lease agreement between EBTC-ETSI LO• A Business and Facilities Agreement finalized but in force only when
LO established and EBTC has authorization of the Indian Ministry of Home affairs to transfer running costs from Brussels to Delhi
• Intermediary solution (Gentlemen’s Agreement) agreed with EUROCHAMBERS as follows:
• Once the LO is in place, ETSI shall be invoiced retroactively for the due lease months a that point in time.
• A 6 months lease period (equivalent to 42 k Euros) has been set as limit for ETSI and EUROCHAMBERS to reconvene again and decide way forward
“Caliber” manpower agreement• Service provider Limited Agreement to be signed and effective as of
the start of the LO• Intermediary solution:
• Identical contract, with same provisions, signed between Dinesh’s company AeON and Caliber valid until the ETSI LO is in place.
© ETSI 2013. All rights reserved4
2. Project Management Admin. III Budgetary issues to be sorted out today
© ETSI 2013. All rights reserved5
2013 2014 2015 Total
legal costs for LO set up and closure
7000 € 0 5000 € 12 000 €
Legal annual services 4000 € 4000 € 4000 € 12000 €
Total Legal 11 000 € 4000 € 9000 € 24 000 €
Chartered Accountant Services
7 000 € 7 000 € 7 000 € 21 000 €
Grand TOTAL: 18 000 € 11 000 € 16 000 € 45 000 €
ESO Total
CEN 15 000 €
CENELEC 15 000 €
ETSI 15 000 €
Total: 45 000 €
An estimation of 45.000 € is foreseen to cover the costs listed in doc. 4 and broken down per item and year as follows:
Proposal: ESOs to share the costs for covering the above identified needs over the three years of the Project as follows
6. AOB & closure of meeting
6
Thank you!