+ All Categories
Home > Documents > SESEI STEERING COMMITTEE MEETING #2 June, 12 th (08:30-12:00) Presented by ETSI for SESEI SC#2 ©...

SESEI STEERING COMMITTEE MEETING #2 June, 12 th (08:30-12:00) Presented by ETSI for SESEI SC#2 ©...

Date post: 17-Jan-2018
Category:
Upload: tiffany-wilkinson
View: 218 times
Download: 0 times
Share this document with a friend
Description:
Project Management Admin. I (Bernardo) Legal Set-up: Liaison Office (LO) LO application entering in its 4 month (estimative was 3-6 months for conclusion) period Reserve Bank of India has asked the Government of India for their clearance (possibly clearance from Ministry of Finance as ETSI is a not- for-profit Organization). Good news: No further documentation asked Outcome is foreseen anytime now, possibly during June Once established, next step is to open the so-called QA22C account with the bank which shall operate the LO (paper work already being analyzed) © ETSI 2013 All rights reserved 3
6
SESEI STEERING COMMITTEE MEETING #2 June, 12 th (08:30-12:00) Presented by ETSI for SESEI SC#2 © ETSI 2013. All rights reserved
Transcript
Page 1: SESEI STEERING COMMITTEE MEETING #2 June, 12 th (08:30-12:00) Presented by ETSI for SESEI SC#2 © ETSI 2013. All rights reserved.

SESEI STEERING COMMITTEE MEETING #2June, 12th (08:30-12:00)

Presented by ETSI for SESEI SC#2

© ETSI 2013. All rights reserved

Page 2: SESEI STEERING COMMITTEE MEETING #2 June, 12 th (08:30-12:00) Presented by ETSI for SESEI SC#2 © ETSI 2013. All rights reserved.

SESEI Project Management – Status

Status Liaison OfficeEBTC lease agreementCaliber manpower agreementBudget• Status• Discussion on Financial estimate proposal

2 © ETSI 2013. All rights reserved

Page 3: SESEI STEERING COMMITTEE MEETING #2 June, 12 th (08:30-12:00) Presented by ETSI for SESEI SC#2 © ETSI 2013. All rights reserved.

Project Management Admin. I(Bernardo)

Legal Set-up: Liaison Office (LO)• LO application entering in its 4 month (estimative was 3-6 months for

conclusion) period• Reserve Bank of India has asked the Government of India for their

clearance (possibly clearance from Ministry of Finance as ETSI is a not-for-profit Organization).

• Good news: No further documentation asked• Outcome is foreseen anytime now, possibly during June• Once established, next step is to open the so-called QA22C account

with the bank which shall operate the LO (paper work already being analyzed)

© ETSI 2013 All rights reserved3

Page 4: SESEI STEERING COMMITTEE MEETING #2 June, 12 th (08:30-12:00) Presented by ETSI for SESEI SC#2 © ETSI 2013. All rights reserved.

Project Management Admin. II

Rental lease agreement between EBTC-ETSI LO• A Business and Facilities Agreement finalized but in force only when

LO established and EBTC has authorization of the Indian Ministry of Home affairs to transfer running costs from Brussels to Delhi

• Intermediary solution (Gentlemen’s Agreement) agreed with EUROCHAMBERS as follows:

• Once the LO is in place, ETSI shall be invoiced retroactively for the due lease months a that point in time.

• A 6 months lease period (equivalent to 42 k Euros) has been set as limit for ETSI and EUROCHAMBERS to reconvene again and decide way forward

“Caliber” manpower agreement• Service provider Limited Agreement to be signed and effective as of

the start of the LO• Intermediary solution:

• Identical contract, with same provisions, signed between Dinesh’s company AeON and Caliber valid until the ETSI LO is in place.

© ETSI 2013. All rights reserved4

Page 5: SESEI STEERING COMMITTEE MEETING #2 June, 12 th (08:30-12:00) Presented by ETSI for SESEI SC#2 © ETSI 2013. All rights reserved.

2. Project Management Admin. III Budgetary issues to be sorted out today

© ETSI 2013. All rights reserved5

2013 2014 2015 Total

legal costs for LO set up and closure

7000 € 0 5000 € 12 000 €

Legal annual services 4000 € 4000 € 4000 € 12000 €

Total Legal 11 000 € 4000 € 9000 € 24 000 €

Chartered Accountant Services

7 000 € 7 000 € 7 000 € 21 000 €

Grand TOTAL: 18 000 € 11 000 € 16 000 € 45 000 €

ESO Total

CEN 15 000 €

CENELEC 15 000 €

ETSI 15 000 €

Total: 45 000 €

An estimation of 45.000 € is foreseen to cover the costs listed in doc. 4 and broken down per item and year as follows:

Proposal: ESOs to share the costs for covering the above identified needs over the three years of the Project as follows

Page 6: SESEI STEERING COMMITTEE MEETING #2 June, 12 th (08:30-12:00) Presented by ETSI for SESEI SC#2 © ETSI 2013. All rights reserved.

6. AOB & closure of meeting

6

Thank you!

© ETSI 2013. All rights reserved


Recommended