+ All Categories

Shekhar

Date post: 06-Sep-2015
Category:
Upload: jai-bakliya
View: 216 times
Download: 2 times
Share this document with a friend
Description:
shekhr
Popular Tags:
76
Urban Infrastructure: Issues in structuring bankable projects ASCI-World Bank Programme on Strengthening Urban Management (SUM) January 23, 2003
Transcript
  • Urban Infrastructure: Issues in structuring bankable projectsASCI-World Bank Programme on Strengthening Urban Management (SUM) January 23, 2003

  • Often heard at seminars Small is beautifulGet your act togetherFirm up YOUR objectives first but recognize that others have their objectives too Experiment but be willing to correct yourselfStand by your commitments Do not ignore the ultimate customer/userBeware of smart/over-confident developersSounds like preaching? Read on ...

  • Structure of the Presentation

    Select illustrations of PSP in infrastructure Urban Infrastructure projectsPort sector projectsRoad sector projects

    Lessons from experience so far

    Objectives & Concerns of various stakeholders

  • Illustrations with wide coverageSectors CoveredUrban InfrastructurePortsRoadsStates CoveredPower/Telecom omitted141012Projects from 10 statesKerala, Karnataka, Tamil Nadu, Andhra PradeshMaharashtra, Goa, Gujarat, Madhya Pradesh, ChhattisgarhWest Bengal, OrissaRajasthan, U.P., BiharWell, there are lots of cases and a few good lessons!

  • Ahmedabad Municipal CorporationAMC became the countrys first municipality to raise bonds from capital markets Bond raising preceded by an internal restructuring and revenue enhancement measuresBond proceeds used for water supply schemes Bonds secured by a charge on octroi revenues of AMCUtilisation of bond proceeds have been slow as project implementation has been delayed

    Lesson: Careful planning & timing is necessary for sustainable project implementation processes

  • Bangalore Water Supply Project Private participation was sought for 500 MLD BOOT project by BWSSBBidding preceded by technical and demand studiesAfter pre-qualification, three consortia submitted final proposalsThe project was nearly awarded to a consortium led by Biwater International but the bidding process has been questioned and resulted in delays

    Lesson: Clear bidding parameters required to be stipulated & process transparency to be ensured

  • Chhattisgarh - Borai Water Supply Project Borai Bulk Water Supply Project is set up on BOOT basis as an industrial bulk water supply for Borai Industrial Growth Centre (BIGC) in Durg district, Chattisgarh under concession from CIDC It is a Project 30 MLD project with a cost of Rs. 420 mn. (including existing assets valued at Rs. 160 mn.)Radius Water Ltd. promoted by Kailash Engineering is the concessionaireThe first phase (12 MLD) of this project is already operational but there are some hiccups as to drawal rights and further expansion

    Lesson: Risk taking ability of the promoter helped this project go quickly through the initial stages.

  • Chennai Desalination Project Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB) mooted a project for implementing the tertiary treatment / Reverse Osmosis plant of 50 MLD capacity at Kodungaiyur, Chennai on a Design, Build, Own and Operate basisThe submission dates were postponed a number of times as CMWSSB was not sure of attractiveness to investors Ultimately it bid out both EPC & DBOO as alternate optionsResult: There were only two bids both on an EPC basis (L&T and BHEL). Meanwhile VA Tech Wabag another party chose to bid for a limited size project on captive basis for CPCL one of the major clients of CMWSSB

    Lesson: There is no harm in experimenting but first get your objectives right

  • Cochin Industrial Water SupplyMooted by KSIDC, which invited IFC to assistBasic project preparation was carried out including detailed technical studies as well as demand estimatesAlternate project structures were evaluatedMeanwhile KWA signed an agreement with Cochin Refineries, a major user allowing an off-take of waterLesson: Co-ordination among government agencies required for project development

  • Goa Salaulim Water SupplyGoa PWD had invited proposals for water supply project on a BOOT basis (with an option to bid in an alternative innovative format)BOOT bids were found very costly and then the GoG thought of alternative concession routeThe bidder questioned GoG's demand forecastAt present due to successive changes in the Government the process has been temporarily suspended

    Lesson: Inadequate homework by the state authorities

  • Haldia Industrial Water Supply SchemeHDA has sought private participation and received over 25 Expressions of Interest Despite adequate demand many technical issues (salinity, mix of ground water and river water, etc.) remain unresolved HDA decided against technical study, no project parameters have been set up & may instead go directly for BOT or EPC/O&M contracts (but may not have funds)Potential investors/bidders are unhappy as there is no progress

    Lesson: Project has not been thought through clearly

  • Nagpur Municipal BondsNMC proposed a Rs. 1.17 bn. capital expenditure programme under Pench-III Stage-I project of the Corporation, which envisages capacity creation in the water supply servicesNagpur Municipal Corporation proposed to raise Rs. 0.90 bn. from issue of Bonds to partially meet its requirement, the balance coming from from internal accruals and grants from State Government With a AA-(SO) rating by CRISIL SBI Capital Markets as arranger could raise only ~ Rs. 0.30 bn. even after extending dates several times.NMC however carried through with its tariff reforms (water & property taxes) & postponed the implementation till it could generate adequate internal accruals

    Lesson: Bhagwan ke pas der hai lekin Andher nahi.

  • Pune Water Supply Project Water Supply Project conceived with structuring assistance from USAIDProject conceived as EPC+O&M with funding from funds raised by PMCAlso a separate contract for management of billing & limited collectionsProject generated considerable investor interest as careful planning had gone into the project preparationBidding Process was terminated prematurelyPMC is now implementing the project on its own

    Lesson: Political risk (the power of lobbying groups) in the project was underestimated

  • Tiruppur Water Supply Project Project was conceived by IL&FS with support from GoTN, TACID and IndustryProposed as a BOOT project for sourcing, treatment and supply water mainly to industry with some social coverageTiruppur industry comprises of garment exports and willingness to pay is higherHowever, the project has taken considerable time to develop resulting in cost escalationThe cost of water for the commercial users has more than doubled during this periodReached financial closure 8 years after conceiving!

    Lesson: Complex projects are difficult to implement and subject to diverse risks

  • Consider this the city of AhmedabadGIDB has proposed an Integrated Public Transit System for Ahmedabad (IPTS) and appointed a consultant for the studiesAMC became the countrys first municipality to raise bonds from capital markets for various projects (primarily water)Sabarmati Riverfront Development Corporation (SRFDC) an organisation set up by AMC is proposing a massive area development project with the help of a local not-for-profit organisation (EPC)

    Lesson: Lack of integrated project development for the same city (and now watch out Mumbais integrated development)

  • Mumbai: non-toll bridge within cityProject conceived as self-financing bridge1.5 kms long flyover bypassing three junctions at Andheri on Western Express Highway.To be financed by selling commercial property under the bridge.Underground car park, two storeys of commercial property with a six lane carriageway on top.Project delayed initially due to delay in approvals and later due to litigation over alleged environmental issues; now real estate prices not at high levels.

    Lessons: Lack of coordinated efforts, insensitivity to local and environmental issues and non-transparent procedures.

  • 50 flyovers in Mumbai50 flyovers to be financed initially through bond issue and recovery through an entry toll (Rs. 20/-)Tolling commenced sometime back but was met with stiff resistance from Transporters Associations and court has put a stay on tollingMSRDC is fast running out of funds (on account of the flyovers as well as the Express way) but revenues not as per expectationsNow MSRDC would be reimbursed through a fuel cess on all Mumbai Petrol Pumps

    Lesson: Realistic assessment of willingness to pay (also, pay for use principle flouted)

  • Kolkata Car Park (Rowden Street)Kolkata Municipal Corporation (CMC) awarded multi-level automated car park project to Simplex Projects Project details:Location: Rowden Street (in the vicinity of Park Street) Project Cost: Rs. 90 mn. (CMC interest free advance Rs. 30 mn.)Car Parking: 216 cars at Ground+ 2 levelsTechnology: Machinefabriek Aarding BV of NetherlandsRevenues from Car Parking & AdvertisementsPerformance: Revised estimate for first full year of operations are at 55% of projected as the no parking zone has not been fully enforced resulting in lower car parking revenue

    Lesson: The corporation needs to stand by its commitments

  • Mumbai - Car Park at Breech CandyMunicipal Corporation of Greater Mumbai (MCGM) has bid out Car Park cum Commercial Development Project near Breech Candy Hospital on a BOOT basisBidding Parameters:Upfront payment of premium to MCGMNo. of cars & two wheelers that can be parkedBids received are a veritable mix of combinations of no. of car parks promised and upfront premium payment assuredCurrent Status: Bidders have been asked to make presentations on their project proposals showcasing the technologies used (capital cost, operating cost & access time)

    Lesson: Lack of adequate project preparation to ensure clear & transparent bidding process

  • Bidding Results (Mumbai Car Park)

  • Structure of the Presentation

    Select experience of PSP in infrastructure Urban Infrastructure projectsPort sector projectsRoad sector projects

    Lessons from experience so far

    Objectives & Concerns of various stakeholders

  • Container terminals at Chennai & Kandla & JNPTIn the mid-90s a number of projects were bid out in major ports for private sector Privatisation of container terminals was awarded to P&O a large international Ports & Shipping group at Kandla, JNPT, Cochin & ChennaiDespite some initial hiccups the JNPT project went through to financial closure. The Chennai Container Terminal took some further time (in years!) while Kandla became a major controversy leading to a showdown between the Port Trust & MoST. Cochin was not pursued by P&O as some comforts were not forthcoming.

    Lesson: The Government was unable to resolve key issues and/or read the real issues in competitive behaviour

  • Container terminal at JNPTBOT Project with a world class facility at a cost of Rs. 7.50 bn.Promoted by one of the worlds leading maritime business group.JNPT did not allow first charge on project assets to the lenders and other amendments to the concession agreement.

    So project financing was not available and ultimately the project was financed with the support of sponsor guarantee.

    Lesson: Despite hurdles, strong promoters can make project happen.

  • Container Terminals current statusAs everyone is aware, JNPT (P&O) is a major success storyBut despite this, and an aggressive lobbying effort by P&O, the new (revised) bidding conditions for the proposed new container terminal at JNPT explicitly disallows bidding or investment by P&O in any formCochin Container Terminal now comes as a package of phased development (handing over of existing terminal followed by development of Vallarpadam) Kandla Container Terminal finally did not proceedAdani sponsored Mundhra Port is now developing a Container Terminal which may be divested in favour of P&O

    Lesson: At times it is difficult for the Government to understand the machinations of the private sector

  • Dharma port project in OrissaProposed green-field port for dry bulk cargo at an estimated cost of Rs. 15 bn.To be developed on BOOST framework.Promoted by a JV of an Indian engineering company and two foreign companies.Significant delays in finalization of changes in concession suggested by lenders.Meanwhile both foreign sponsors have walked out of the deal while one firm ran into financial difficulties the other had lost interest due to delays and disagreement with respect to its potential role in O&M for the project

    Lesson: Lack of application and push by all parties.

  • Chemical terminal at Dahej, GujaratGreenfield liquid chemical handling facility at an estimated cost of Rs. 8 bn.Developed on a BOOT framework.Promoted by a JV of GMB, GIIC and four Indian petrochemical and fertiliser PSUs.Project physically complete and operational without the concession being signed and without financial closure.Multiplicity of promoters and speed of response is a key issue.

    Lesson: Too many cooks spoil the broth.

  • Enron, Dabhol & OWMSLOcean Sparkle Ltd. based in Hyderabad formed a JV with Weismueller of Netherlands to bid for and win a mandate for providing port services to the LNG Terminal at DabholProject: Comprising of state of the art 4 tugs costing Rs. 800 mn. To be built to the specifications of The DPCs O&M operator (a subsidiary of Enron) and operate for 20 yearsProject reached financial closure despite on-going problems at DPC and the tug-of-war with MSEBBy the time the plant closed down, the tugs were ready for delivery but no Enron to certify! Weismueller agreed to buy the tugs for redeployment and settled loans

    Lesson: In large projects, the smaller parties fall by the wayside but are saved only if they have some back-up.

  • Haldia Berth 4A for coking coalHaldia Port bid out development of Berth 4A for handling coking coal imports required by steel plantsISPL was awarded the contract and they simultaneously approached project financiers and Steel Authority (a likely major off-taker)Despite considerable delays, ISPL was able to reach a 20 year contract with SAIL for using their facility for importing coking coal, an important ingredient in Steel ProductionProject lenders unsuccessfully sought a number of amendments to the Concession Agreement (essentially in line with the Model Agreement drafted by IDFC for MoS)

    Lesson: Small project, long off-take contract, viability beyond doubt; a formula for success

  • Structure of the Presentation

    Select experience of PSP in infrastructure Urban Infrastructure projectsPort sector projectsRoad sector projects

    Lessons from experience so far

    Objectives & Concerns of various stakeholders

  • Noida Toll BridgeProject comprises a 6-lane bridge over Yamuna river and approach roads costing Rs. 4.00 billion.Flyover at Ashram road junction required for smooth traffic flow from the project delayed.Traffic significantly lower than appraisal estimates.Average daily collection is Rs. 0.27 million(Debt service liability about Rs. 1.70 million/day)

    Lesson: Co-ordinated development of linkages and accurate traffic estimation key for project success.

  • Coimbatore By-passBy-pass on NH-47 developed by L&T on BOT basisToll-free alternative available to local trafficSubsequent to the award of the project, scope enlarged to include strengthening of Attupalam bridge before the by-passToll-free alternative no longer availableHence local opposition to toll collectionEarlier, willingness to pay did not capture such an event

    Lesson: Project structure should be sensitive to local traffic

  • Durg by-passBy-pass on NH-6 developed by Sancheti group on BOT basisToll-free alternative available to local traffic.Project scope includes a river bridge and ROB.NHAI provided sub-debt and limited shortfall guarantee.Project completed almost as per schedule.No local opposition to toll collection.Project in operation for two years.

    Lesson: Being first project, project reached closure with help of financial support from NHAI.

  • Delhi-Gurgaon Expressway ProjectOriginally conceived in mid 1990s, CIDB, Malaysia was to be mandated in 2000 to complete this project as part of govt-to-govt initiative, but the proposal sought a grant of Rs. 1.20 bn. from NHAI, and was thus rejected.This year the project bid out by NHAI for Capital Subsidy (Grant) received a number of bids promising premium instead and was awarded to Jaiprakash Industries-D.S.Construction consortium which offered the highest Rs. 615 mn. PremiumThe project is adversely affected by recent Court order on ban of polluting vehicles (non-CNG trucks/busesa) entering New Delhi

    Lesson: Classic case of the nature of risks in infrastructure projects. Who is right CIDB or Jaiprakash?

  • Mattancherry Bridge at CochinFirst BOT bridge project in Kerala State; GCDA acted as the sponsor authorityOther agencies involved - KSIDC, CPT, Cochin Corporation and PWD Project was offered on a BOT basis and bid for concession period. At bidding stage Traffic studies, technical studies & draft concession agreement was given to biddersProject has been awarded to Gammon IndiaLesson: Initial investment on project preparation yields high returns

  • PPP in NHDP The NHDP has been partially successful in attracting private sector investment.

  • PPP or not to P(rivatise)Construction ContractRs. 280 mn. Per Km. This is an item rate contract (not FTFC EPC)Add a further Rs. 80 mn. (Pre-op, IDC, Fees, etc.)At Rs. 360 mn. per km. this is still far lower than ..Annuity Project CostRs. 500 mn. per km.A typical BOT project (either annuity or toll based)

    Rs. 500 mn. per km.

    Now add Rs. 140 mn. for escalation due to extra work to get Rs. 500 mn. Add now for 15-20 years of repairs & maintenance No further addition, Project cost still Rs. 500 mn. per km. Project cost still Rs. 500 mn. per km.

    Mumbai Pune Expressway cost was Rs. 16 bn. (as per contractors bids) and now on completion it is Rs. 22 bn. Reliance had quoted Rs. 30 bn. including 1000 hectares of land acquisition

  • PPP in roads are maturingToll-based BOTAnnuity SchemeGrant/Capital Subsidy

    Reverse Grant/PremiumO&M/Tolling Contracts

    Real-estate linked project

    Many state level projects6 projects awardedJaipur-Kishengarh (NHAI)Many projects in M.P.Delhi-Gurgaon4-lane NHDP stretchesMumbai-Pune Exp. WayMahakali Flyover, MumbaiVivekanand Flyover, KolkataBangalore-Mysore Infrastructure Corridor

  • Comparison of Expressways dev.

  • Structure of the Presentation

    Select experience of PSP in infrastructure Urban Infrastructure projectsPort sector projectsRoad sector projects

    Lessons from experience so far

    Objectives & Concerns of various stakeholders

  • Some case studies ..1East Coast Road vs. Tiruppur & Noida Toll BridgeDurg Bypass vs. Jaipur-Kishengarh Bhiwandi Bypass vs. Mumbai-Pune ExpresswayDhamra vs. Haldia berth 4A & Kakinada

    Small is beautiful

  • Some case studies ..2Coimbatore Bypass (sensitivity to local traffic)Mumbai Entry Point Tolls (user pay principle challenged)Noida Toll Bridge (international class but low turnout)

    Do not ignore the ultimate customer/user

  • Some case studies 3AMC Bonds (Utilisation of proceeds)City of Ahemedabad (GIDB vs. SRFDC)Cochin Industrial Water Supply (KSIDC vs. KWA)Haldia Development Authoritys Water Supply Project

    Get your act together

  • Some case studies 4Goa Salaulim Water Project (BOOT or Concession)CMWSSBs Chennai Desalination Project (EPC or BOT)Mumbai Car Park (upfront payment or no. of cars)

    Firm up YOUR objectives first

  • Some case studies 5Mattancherry Bridge (insisted on upfront payment but later relented)NHAIs Palasit Panagarh (rebid after initial high bids)Durg Bypass (selected weak promoter but later extended guarantee & sub-debt support)MMRDAs Convention Centre (bidding failed twice)Experiment but be willing to correct yourself

  • Some case studies 6Jaipur-Kotputli Toll Collection OperationsMahakali Flyover (PIL & subsequent developments)NOIDAs Dadri Bridge (UPSBC upstages Simplex)Bidding for Container Terminals in the country

    Beware of smart/over-confident developers

  • Some case studies 7Kolkata Car Park (enforcement of no-parking zone)BOT Roads in general (timely toll notification)Road Bypasses (enforcement of ban on through traffic)Tax benefits under 10-23 (g) (delays/denial of Certificate) Enron !!!!!

    Stand by your commitments

  • Summary: Some practical lessonsSmall is beautifulDo not ignore the ultimate customer/userGet your act togetherFirm up YOUR objectives first but recognize that others have their objectives too Experiment but be willing to correct yourselfBeware of smart/over-confident developersStand by your commitments Still sounds like preaching?

  • Some practical approachesInstitutionalize your approach through a vehiclePIDB, GIDB, I-Deck, I-Kin, I-Win, APIIF, MPIDB, CIDCFind a champion & give him a long tenureFirst develop small & medium projects to demonstrate success then replicateGive importance to good project preparation and not just to announcing good sounding projectsKeep the bidding simple & evaluate on just one key parameterHire advisors to help!

  • Need for PSPPrivate Sector Participation is sought to essentially bring in:

    Private capitalPrivate managementNew & better technology

    The modality of PSP critically depends on exact objectives sought to be achieved

  • Why private sector participation?Economic/Political ReasonsPolicy of privatisationFostering competitionCommercial principles Pay-for-use culturePolitical bottlenecks in tariff restructuring or reduction in subsidies

    Management Reasons Better management of all resources & operational efficiencyImproved level of service and responsiveness to usersFinancial ReasonsBudgetary priorities and constraintsAdditionality of fundsBetter utilisation of financial resources

    Other reasonsNew and better technology Involvement of users and other stake holdersEnvironmental requirements

  • Different modes of PSP can be explored

  • Lessons from past experienceReasons for failure attributable to one or more of the following:

    Inadequate framework for PSPInsufficient project preparation & developmentFailure to address concerns of all stakeholders

  • Framework for PSPClarity in objectives of PSP Institutional restructuring to coincide with PSP initiativesRegulatory framework to be put in placeManaging political risk and willingness to pay issues

  • Project preparation & developmentCo-ordination issues: Identification of nodal agency and defining roles of other agenciesEstablishing independent commercial viability of the project: demand, revenues & costsIdentification of risks, allocation & mitigationProject structuring & role of private sectorComprehensive information memorandum covering studies & draft contract agreementsDesigning transparent competitive bidding processTransparent & fair procurement process

  • Stakeholder concernsCapacity building of government / public agenciesInterest and capacity among private sector operatorsBuilding awareness for pay for use principle among consumers and communities within societyAddressing financing issues of lenders and investorsEnsuring adequacy of services at affordable rates to the urban poor

  • Structure of the Presentation

    Select experience of PSP in infrastructure Urban Infrastructure projectsPort sector projectsRoad sector projects

    Lessons from experience so far

    Objectives & Concerns of various stakeholders

  • Government/Local Authority Sustained improvement in provision of InfrastructureConserving scarce public resourcesCreation of facilities and provision of efficient servicesTransparency and fair processProtection of Social/Developmental commitments

  • Developer/InvestorCommercial viability of projectFreedom & flexibility in conduct of businessAvoidance of risks beyond controlFairness in transactionDelays in approvals

  • Project Financiers/LendersFinancial viability of projectAcceptable concession frameworkFreedom to exercise step-in-and-cure-rightsProtection against defaults by Government and developer

  • Consumers/UsersAvailability of facilities & servicesAcceptable levels of tariffs/taxes/tollsAppropriate grievance redress system

  • Thank You

  • Feedback Ventures Ltd.e-mail: [email protected]: http://www.feedbackventures.com Delhi Feedback House 7, Local Shopping Centre Panchsheel Park New Delhi 110017 India Tel: (011) 2649 5766-68Fax: (011) 2649 5762/65Mumbai Bengal Chemicals Bhavan, 3rd Floor, 502, Veer Savarkar Marg, Prabhadevi Mumbai 400025

    Tel: (022) 5661 3632Fax: (022) 5661 3631Hyderabad 7, Amruta Business Complex, 2nd FloorAmeerpetHyderabad 500 016India

    Tel: (040) 2375 6481Fax: (040) 2375 6482

  • What is project finance

    Project Finance is a technique of non-recourse or limited recourse financing in which the project lender principally look to the cash flow of a single project as security for their long-term loans.

    In India the term Project Finance was generally applied to long term loans given by Term Lending institutions (Fis) to new (or modernisation/ upgradation) industrial projects as compared to working capital facility extended by commercial banks.

  • Extent of sponsor recourseFull-recourseAkin to corporate finance

    Non-recourse financeExtremely rare

    Limited recourse financeCompletion guaranteesUndertakings to cover cost overruns

  • Limited recourse financing...Insulates sponsors from project debt and risk of project failure

    Enables them to share some risks in a large project with other participants

    Overcome the inability to borrow through a corporate loan as balance sheet cannot support the project debt

  • Project finance is cash flow basedCash flow based financing for infrastructure projectsSignificant value of the project is derived from intangibles and not from the assets createdEstimation of debt requirement of the project depends on the future cash flows of the project as against the capital expenditure incurred in conventional projectsTelecom/ Ports : based on peak cash negative Power/Roads : cash requirement till project completionFuture cash flows from the project are the primary source of debt repayment

  • Project finance needs strong security structureSecurity structure needs to be more stringent than a normal project assistance and typically includes -Legal mortgage of all assets, including receivables (as opposed to the normal equitable mortgage)Pledge of promoter shareholdings in the project companyEscrow mechanism for cash flows of the companyAssignment in favour of lenders of all the project contracts

  • Project finance vs. corporate finance

  • Lenders approach to financingFocus on economically strong projects

    Back strong sponsors with successful track record in implementing large projects

    Comprehensive due diligence on all counterparties (incl. EPC contractor, O&M contractor, Licensor, etc)

    Insist on complete financial closure before commitment of any funds

    Arranging project finance requires substantial time and cost

  • Basis for lenders risk aversionLenders have the maximum money on a project rated at BBB and the minimum returns

    whereasThe developers put a small money as equity and aspire for supernormal profitsThe Users get a facility for which they can pay if they so wish (or protest/use alternatives, etc.)The Government puts no money but has the right to intervene, take over if it is dissatisfiedyetthe lenders lenders are not so easy on them and besides expecting a AAA rating also face stringent RBI/SEBI regulations

  • Risks over the 3 project phasesLenders identify three separate phase of risk over the life of the project Engineering &Construction PhaseStart-up PhaseOperationPhaseCODPhysical Completion

  • Project finance lifecycleDisbursementsArranger Mandate

  • FIMMDA Annualised Spreads Source: http://www.fimmda.org

    Gilts

    zero coupon ratesannualized ytmsPV-zcyccum-pv-zcycZero-coupon ratesMtyPar ytm (semi-annual)

    15.86%15.86%0.945.86%5.86%15.78%

    25.91%25.91%0.890.945.91%5.91%25.82%

    36.02%36.01%0.841.846.02%6.01%35.92%

    46.21%46.19%0.792.686.21%6.19%46.09%

    56.40%56.35%0.733.466.40%6.35%56.26%

    66.58%66.51%0.684.196.58%6.67%76.57%

    76.77%76.67%0.634.886.77%6.88%86.77%

    87.03%86.88%0.585.517.03%7.09%96.97%

    97.30%97.09%0.536.097.30%7.13%107.01%

    107.34%1.001.11.21.31.41.51.61.71.81.922.12.22.32.42.52.62.72.82.933.13.23.33.43.53.63.73.83.944.14.24.34.44.54.64.74.84.955.15.25.35.45.55.65.75.85.966.16.26.36.46.56.66.76.86.977.588.599.51011121314151617181920107.13%0.496.627.34%7.44%157.30%

    117.41%5.86%5.86%5.87%5.87%5.88%5.88%5.89%5.89%5.90%5.90%5.91%5.92%5.93%5.94%5.95%5.96%5.97%5.98%6.00%6.01%6.02%6.04%6.06%6.07%6.09%6.11%6.13%6.15%6.17%6.19%6.21%6.23%6.25%6.27%6.28%6.30%6.32%6.34%6.36%6.38%6.40%6.41%6.43%6.45%6.47%6.49%6.51%6.52%6.54%6.56%6.58%6.58%6.58%6.58%6.58%6.58%6.58%6.58%6.58%6.58%6.58%6.67%6.77%6.90%7.03%7.16%7.30%13.10%10.38%11.81%12.13%12.50%13.86%10.90%10.90%10.90%10.90%117.20%0.467.117.41%7.65%207.51%

    127.49%127.26%0.427.577.49%

    137.57%137.32%0.397.997.57%

    147.66%147.38%0.368.387.66%

    157.75%157.44%0.338.737.75%

    167.82%167.48%0.309.067.82%

    177.88%177.52%0.289.367.88%

    187.96%187.57%0.259.637.96%

    198.03%197.61%0.239.898.03%

    208.12%207.65%0.2110.128.12%

    CONFIRM

    Spread input

    Annualised spreads12345678910

    AAA60626965616058636872

    AA+858696939088869196101

    AA122124134131129127125131136142

    AA-167168180178176175173178184189

    A+238242261264268267265271277283

    A293308334343352352353358364370

    A-360383419429437438439445451456

    BBB+457460482479475480485495506517

    BBB479510556570583585586592598604

    BBB-647651674672669675682693704715

    I-Sec

    Annualised spreads12345678910

    AAA57595961625956565656

    AA+77797983878481818181

    AA102104104108112109106106106106

    AA-132134139146152149146146146146

    A+217224239258277274271271271271

    A267294324353382379376376376376

    A-332379434463492489486486486486

    BBB+

    BBB402464539573607604601601601601

    BBB-

    Crisil

    Annualised spreads12345678910

    AAA60757865525048597081

    AA+92100111988581768798109

    AA142150161148135131126137148159

    AA-202210221208195191186197208219

    A+267275286273260256251262273284

    A332340351341330328326337348359

    A-407415426416405403401412423434

    BBB+497505516506495493491502513524

    BBB587595606596585583581592603614

    BBB-707715726716705703701712723734

    Credence

    Annualised spreads12345678910

    AAA64537070707171747780

    AA+8778989898100101105109113

    AA123117136138140142144149155160

    AA-167159181181181184186192197203

    A+231227257262266270274280287293

    A281291328336343350356362368374

    A-340356398407415423430436443449

    BBB+416414448451454466478488499509

    BBB449471522540557567577584590597

    BBB-587587622627632647662673685696

    CONFIRM

    CorpoBonds

    Spreads over Gilt curve in bpsUpdated on 31st Oct 2002

    Annualised spreads12345678910

    AAA60626965616058636872

    AA+858696939088869196101

    AA122124134131129127125131136142

    AA-167168180178176175173178184189

    A+238242261264268267265271277283

    A293308334343352352353358364370

    A-360383419429437438439445451456

    BBB+457460482479475480485495506517

    BBB479510556570583585586592598604

    BBB-647651674672669675682693704715

    Zero coupon spreads12345678910

    AAA60627065616058657379

    AA+8586979490888694102109

    AA122124135132130128126135144153

    AA-167168181179177177175183194202

    A+238242263267272272270281293303

    A293309337348360360363373387396

    A-360384424436446449452464479487

    BBB+457460485482479487497517541561

    BBB479512564580598601605619636647

    BBB-647651678677675686700725754775

    11.11.21.31.41.51.61.71.81.922.12.22.32.42.52.62.72.82.933.13.23.33.43.53.63.73.83.944.14.24.34.44.54.64.74.84.955.15.25.35.45.55.65.75.85.966.16.26.36.46.56.66.76.86.977.588.599.510

    AAA26060.260.460.660.86161.261.461.661.86262.863.664.465.26666.867.668.469.27069.56968.56867.56766.56665.56564.664.263.863.46362.662.261.861.46160.960.860.760.660.560.460.360.260.16059.859.659.459.25958.858.658.458.25861.56569737679

    AA+38585.185.285.385.485.585.685.785.885.98687.188.289.390.491.592.693.794.895.99796.796.496.195.895.595.294.994.694.39493.693.292.892.49291.691.290.890.49089.889.689.489.28988.888.688.488.28887.887.687.487.28786.886.686.486.286909498102105.5109

    AA4122122.2122.4122.6122.8123123.2123.4123.6123.8124125.1126.2127.3128.4129.5130.6131.7132.8133.9135134.7134.4134.1133.8133.5133.2132.9132.6132.3132131.8131.6131.4131.2131130.8130.6130.4130.2130129.8129.6129.4129.2129128.8128.6128.4128.2128127.8127.6127.4127.2127126.8126.6126.4126.2126130.5135139.5144148.5153

    AA-5167167.1167.2167.3167.4167.5167.6167.7167.8167.9168169.3170.6171.9173.2174.5175.8177.1178.4179.7181180.8180.6180.4180.2180179.8179.6179.4179.2179178.8178.6178.4178.2178177.8177.6177.4177.2177177177177177177177177177177177176.8176.6176.4176.2176175.8175.6175.4175.2175179183188.5194198202

    A+6238238.4238.8239.2239.6240240.4240.8241.2241.6242244.1246.2248.3250.4252.5254.6256.7258.8260.9263263.4263.8264.2264.6265265.4265.8266.2266.6267267.5268268.5269269.5270270.5271271.5272272272272272272272272272272272271.8271.6271.4271.2271270.8270.6270.4270.2270275.5281287293298303

    A7293294.6296.2297.8299.4301302.6304.2305.8307.4309311.8314.6317.4320.2323325.8328.6331.4334.2337338.1339.2340.3341.4342.5343.6344.7345.8346.9348349.2350.4351.6352.8354355.2356.4357.6358.8360360360360360360360360360360360360.3360.6360.9361.2361.5361.8362.1362.4362.7363368373380387391.5396

    A-8360362.4364.8367.2369.6372374.4376.8379.2381.6384388392396400404408412416420424425.2426.4427.6428.8430431.2432.4433.6434.8436437438439440441442443444445446446.3446.6446.9447.2447.5447.8448.1448.4448.7449449.3449.6449.9450.2450.5450.8451.1451.4451.7452458464471.5479483487

    BBB+9457457.3457.6457.9458.2458.5458.8459.1459.4459.7460462.5465467.5470472.5475477.5480482.5485484.7484.4484.1483.8483.5483.2482.9482.6482.3482481.7481.4481.1480.8480.5480.2479.9479.6479.3479479.8480.6481.4482.2483483.8484.6485.4486.2487488489490491492493494495496497507517529541551561

    BBB10479482.3485.6488.9492.2495.5498.8502.1505.4508.7512517.2522.4527.6532.8538543.2548.4553.6558.8564565.6567.2568.8570.4572573.6575.2576.8578.4580581.8583.6585.4587.2589590.8592.6594.4596.2598598.3598.6598.9599.2599.5599.8600.1600.4600.7601601.4601.8602.2602.6603603.4603.8604.2604.6605612619627.5636641.5647

    BBB-11647647.4647.8648.2648.6649649.4649.8650.2650.6651653.7656.4659.1661.8664.5667.2669.9672.6675.3678677.9677.8677.7677.6677.5677.4677.3677.2677.1677676.8676.6676.4676.2676675.8675.6675.4675.2675676.1677.2678.3679.4680.5681.6682.7683.8684.9686687.4688.8690.2691.6693694.4695.8697.2698.6700712.5725739.5754764.5775

    Annualised ytms5.86%5.91%6.01%6.19%6.35%6.51%6.67%6.88%7.09%7.13%

    Zero coupon5.86%5.91%6.02%6.21%6.40%6.58%6.77%7.03%7.30%7.34%

    Annualised ytms12345678910

    AAA6.46%6.53%6.70%6.84%6.96%7.11%7.25%7.51%7.77%7.85%

    AA+6.71%6.77%6.97%7.12%7.25%7.39%7.53%7.79%8.05%8.14%

    AA7.08%7.15%7.35%7.50%7.64%7.78%7.92%8.19%8.45%8.55%

    AA-7.53%7.59%7.81%7.97%8.11%8.26%8.40%8.66%8.93%9.02%

    A+8.24%8.33%8.62%8.83%9.03%9.18%9.32%9.59%9.86%9.96%

    A8.79%8.99%9.35%9.62%9.87%10.03%10.20%10.46%10.73%10.83%

    A-9.46%9.74%10.20%10.48%10.72%10.89%11.06%11.33%11.60%11.69%

    BBB+10.43%10.51%10.83%10.98%11.10%11.31%11.52%11.83%12.15%12.30%

    BBB10.65%11.01%11.57%11.89%12.18%12.36%12.53%12.80%13.07%13.17%

    BBB-12.33%12.42%12.75%12.91%13.04%13.26%13.49%13.81%14.13%14.28%

    Zero coupon rates12345678910

    AAA6.46%6.53%6.71%6.86%7.00%7.18%7.34%7.68%8.03%8.13%

    AA+6.71%6.77%6.99%7.15%7.30%7.46%7.63%7.96%8.32%8.43%

    AA7.08%7.15%7.37%7.53%7.69%7.86%8.03%8.38%8.74%8.87%

    AA-7.53%7.59%7.83%8.00%8.17%8.35%8.52%8.86%9.24%9.36%

    A+8.24%8.33%8.65%8.88%9.12%9.29%9.47%9.84%10.23%10.37%

    A8.79%8.99%9.39%9.69%9.99%10.18%10.40%10.76%11.17%11.30%

    A-9.46%9.75%10.26%10.57%10.86%11.06%11.28%11.67%12.09%12.21%

    BBB+10.43%10.51%10.87%11.03%11.18%11.45%11.73%12.19%12.71%12.95%

    BBB10.65%11.03%11.65%12.01%12.37%12.59%12.81%13.22%13.67%13.81%

    BBB-12.33%12.42%12.80%12.98%13.14%13.44%13.77%14.27%14.84%15.09%

    Bootstrapping

    PV-ZC

    AAA0.93932517830.8811979390.82289928460.76684537710.71287105060.65975397990.60889176120.55342660840.49905365770.457844786

    AA+0.93712451670.87724501720.8166280160.75875655320.70311002740.64936823680.5977011120.54173122820.48709087090.4450231491

    AA0.93388639570.87102617980.8079621910.74803769960.69032939830.63521499170.58249944730.52535971990.47041000910.4274865438

    AA-0.92997817290.86392007910.7976115050.73498353250.6753006860.61821142270.56432060230.50704315750.45124795160.4087448047

    A+0.92387794990.85213436340.77970543110.71159910140.64643754050.58668783110.53088964160.47213594640.41612014280.3729532782

    A0.91920715620.84176421740.76392992880.69075537520.62115882850.55893831010.50040652660.44159206120.38567469540.3427360535

    A-0.91358069780.83022785460.74604320730.66904714950.59720164240.53277765560.47314066590.41353330290.35792209750.3159182078

    BBB+0.90555590340.81883996870.73378680050.65794733030.58862931110.52181348420.45993689190.39838201780.34061040880.2959766004

    BBB0.9037554210.81125132890.71845623620.63522938380.55811540440.49089496020.43000080310.37040879750.31574987470.2743035481

    BBB-0.89023884360.79123329390.69678051160.61381814710.5393650260.46934406290.40543501570.34393408810.28794051380.2452755149

    Cum-PV-ZCYC

    AAA0.93932517831.82052311732.6434224023.41026777914.12313882974.78289280965.39178457085.94521117916.4442648369

    AA+0.93712451671.81436953382.63099754983.38975410314.09286413054.74223236735.33993347935.88166470756.3687555784

    AA0.93388639571.80491257552.61287476653.36091246614.05124186444.68645685625.26895630355.79431602346.2647260325

    AA-0.92997817291.79389825192.59150975693.32649328944.00179397544.62000539815.18432600045.69136915796.1426171095

    A+0.92387794991.77601231332.55571774453.26731684593.91375438644.50044221755.03133185915.50346780555.9195879483

    A0.91920715621.76097137362.52490130243.21565667763.83681550614.39575381624.89616034285.3377524045.7234270994

    A-0.91358069781.74380855242.48985175973.15889890923.75610055164.28887820714.76201887315.1755521765.5334742735

    BBB+0.90555590341.7243958722.45818267253.11613000283.70475931394.22657279814.686509695.08489170785.4255021167

    BBB0.9037554211.71500674992.43346298613.06869236983.62680777424.11770273444.54770353754.9181123355.2338622097

    BBB-0.89023884361.68147213752.37825264912.99207079623.53143582234.00077988514.40621490094.7501489895.0380895027

    Calculations

    AAA1.06527874941.06713108711.06861938731.07003455881.07177345591.07344546621.07675648361.08028711271.0812551095

    AA+1.06767615861.06985579051.07145611121.07298917781.07461152271.07629382351.07963515131.08320336651.0843306647

    AA1.07148080621.07366712111.07527395981.07693310221.07856554721.08026227971.08378442011.08740542171.0886988273

    AA-1.07587846841.07829153731.08001701561.08168438861.08345404621.08516630241.08860264251.09244179281.0935906172

    A+1.08329305881.08648352911.08878255121.09117570071.09294628931.09467476571.09835218071.1023234061.1036581053

    A1.08994546781.09391142541.09690478681.09991586821.10180825131.10396133271.10757295591.1116688291.1130226975

    A-1.09749196651.10258481371.10569620461.10860236651.11064602411.11283290951.11669915811.12093144971.1221283489

    BBB+1.10509721261.10868975631.1103303671.1118126811.11450182441.11734159091.12192166381.12712307961.1294688614

    BBB1.1102538541.11652013751.12012723081.12371246421.12590540611.12813619511.13217833051.13665465481.1380906554

    BBB-1.12421072271.12797983271.129770081.13141893741.13436141391.13765675381.14272202281.14835844731.1508920243

    ZCYC spreads12345678910

    AAA60627065616058657379

    AA+8586979490888694102109

    AA122124135132130128126135144153

    AA-167168181179177177175183194202

    A+238242263267272272270281293303

    A293309337348360360363373387396

    A-360384424436446449452464479487

    BBB+457460485482479487497517541561

    BBB479512564580598601605619636647

    BBB-647651678677675686700725754775

    Help

    Help for the Calculator

    ---->Only the cells shaded white are input cells. Make an input only to these cells

    ---->The other cells are all "no-input" cells. Please do not change any of their values or formulae

    Method for price calculation of Non-SLR securities

    ---->The Corporate Bonds are valued using the FIMMDA Goisec Curve by adding the spreads for various rating categories

    ---->The spreads are provided by ICICI Securities, CRISIL and Credence Ltd.

    ---->The spreads provided by them are averaged to arrive at the FIMMDA spreads

    ---->The spreads across the maturities are added to the respective Gilt rates to value the bonds

    ---->A detailed document on the methodology is downloadable from the website along with the calculator

    ---->Before using the calculator make sure that 'Analysis ToolPak' is installed in the Add Ins

    Inputs to the Calculator

    ---->The Inputs required for the calculator are:

    - rating of the bond- redemption schedule

    - face value of the bond- coupon of the bond

    - coupon frequency- day count convention

    - value date- maturity date

    - last coupon date- final redemption date

    In addition, we have provided two methods of valuation, the ZCYC method and the YTM method

    Output of the Calculator

    ---->The Output from the calculator are:

    - dirty price of the bond- clean price of the bond

    - accrued interest on the bond- residual maturity of the bond

    - the yield of the bond- the macaulay duration of the bond

    The outputs are given using the method of valuation chosen.

    If the method chosen is "ZCYC method", computation is done by discounting all

    the cash flows at their respective zero-coupon rates

    If the method chosen is the "YTM method", computation is done using the annualised YTM

    for the maturity of the bond

    YTM method

    YTM Based Valuation

    Value Date31-Oct-02

    Maturity Date20-Apr-04

    Face Value100.00

    Coupon Rate11.67%

    RatingAA-

    Annualised Yield7.56%

    Coupons/yr4

    Price105.96

    * Applicable only to Bonds with non-amortizing principals

    Time to Maturity1.4916666667

    Roundup2

    Rounddown1

    Roundup Yield0.075857101

    Rounddown Yield0.0752940544

    Yield for maturity0.0755708857

    Calci

    S4yearly11

    Security DescMethod to be used1AAA5half-yearly22

    Rating2AA+quarterly34Zcyc method1

    Redemption SchedulePrice Output3AA3YTM method2Strike Price

    Dirty Price106.314AA-ChosenYTM method2Maturity

    Accrued Interest0.355A+Volatility

    Face ValueCoupon RateCoupons/YearConventionClean Price105.956Aactual / actual11Price

    10011.67%437A-actual / 36022

    8BBB+actual / 36533

    Value DateIssue DateLast Coupon DateFinal Redemption Date9BBB30 / 360 E44

    31-Oct-0220-Jul-0120-Apr-0420-Apr-0410BBB-30/360 US50

    3

    Residual MaturityAverage MaturityYieldMacualay DurationSame as coupon payment schedule1S

    1.471.389.655%1.37Different from coupon payment schedule2D

    1

    00.0002.01

    20-Apr-04

    Coupon Payment SchedulePrincipal Redemption SchedulePV using ytmpv using yield

    DateCash FlowsResidual TimePV Cash FlowsDateCash FlowResidual TimePV Cash FlowsPrincipal BalanceCoupon ZCYC RatePrincipal Redn ZCYC RateCoupon spreadsPrin Redn spreadsDiscounting rates103.524887317-2.78106.3038786828

    20-Jan-0320-Jul-01100100

    120-Jan-032.920.222.8720-Apr-041001.4789.84100020-Jul-011001005.86%5.88%0.0170.0177.53%7.56%2.858432775387.31920713742.870711828589.836248386

    120-Apr-032.920.472.820.000.000020-Jul-011001005.86%0.00%0.0170.0007.53%0.00%2.794204027202.81960448150

    220-Jul-032.920.722.770.000.000020-Jul-011001005.86%0.00%0.0170.0007.53%0.00%2.730728860902.76885429960

    320-Oct-032.920.972.720.000.000020-Jul-011001005.86%0.00%0.0170.0007.53%0.00%2.66802184602.71847492880

    420-Jan-042.921.222.670.000.000020-Jul-011001005.87%0.00%0.0170.0007.54%0.00%2.606754801902.66901221180

    520-Apr-042.921.472.620.000.000020-Apr-0410005.88%0.00%0.0170.0007.56%0.00%2.547537868202.62097254670

    631-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    731-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    831-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    931-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1031-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1131-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1231-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1331-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1431-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1531-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1631-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1731-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1831-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    1931-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2031-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2131-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2231-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2331-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2431-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2531-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2631-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2731-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2831-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    2931-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3031-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3131-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3231-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3331-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3431-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3531-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3631-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3731-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3831-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    3931-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    4031-Dec-990.000.000.000.000.000031-Dec-99000.00%0.00%0.0000.0000.00%0.00%0000

    4116.4789.8360601623

    42

    43

    44

    45

    46

    47

    48

    49

    50

    51Price105.95

    52Error0.0

    53Next Coupon date20-Jan-03

    54

    55

    56

    57

    58

    59

    60

    61

    62

    63

    64

    65

    66

    67

    68

    69

    70

    71

    72

    73

    74

    75

    76

    77

    78

    79

    80

    81

    82

    83

    84

    85

    86

    87

    88

    89

    90

    91

    92

    93

    94

    95

    96

    97

    98

    99

    100

    101

    1020.0

    1030.0

    1040.0

    1050.0

    1060.0

    1070.0

    1080.0

    1090.0

    1100.0

    1110.0

    1120.0

    0.00.000

    The Principal repayment dates have to be entered here. The 1st row should not be left blank.

    CALCULATE

    Please enter the reduced face value if some of the principal has already been repaid

    MBD00000044.unknown

    MBD000FB7E6.unknown

    MBD000F5360.unknown

  • Different modes of PSP can be exploredProject Financing required

  • Common Project Structures 1Build-Operate-Transfer (BOT)New Asset/facility against collection of user fee investor rights revert back to the public authority at the end of the concessionownership vests with the public authorityused for highways, utilities and ports

    Build-Own-Operate (BOO)similar to BOT but without the transfer of rightsmay also stipulate payment of some fee to the public authority for the right to operate the facilityused for telecom and power projects

  • Common Project Structures...2Built-Own-Lease-Transfer (BOLT)assured revenue through lease rentalsproposed for Indian Railways

    Built-Own-Operate-Share-Transfer (BOOST)revenue shared with the public authorityMinor ports proposed in some states

    Annuity structureConcessionaire responsible for construction and O&MConcessionaire receives fixed annuity over the concessionProposed for National Highways projectsLikely to replace Railways BOLT scheme

    Lack of clarity in objectives of PSP *PSP aimed at attracting capital & curtailing public sector employment rather than increasing efficeincy and effectiveness of service delivery*Undue emphasis on new source development rather than improving distribution systems and operational management

    Lack of city-wide scope *Scale efficiency on outsourcing can be achieved (in operational tasks like transportation of water & solid waste( through municipality-wide schemes rather than restricted to certain limited areas.

    Institutional restructuring *Despite 74th Constitutional Amendment Act which vests water supply & sanitation services with local / municipal authorities there is no clear link among investments, costs & revenues*Political intervention*Skewed tariff policies*promote corporatisation of water providing agencies as a step towards profit centre concept

    Regulatory frameworkTo specify service standards, quality & tariff issues, balance industry & consumer interestsImpact on poorImpact of different PPP approaches on employment conditions and on access to services for the poor

    Capacity of public agenciesMany local initiatives have failed due either to inadequate understanding and preparation or due to political reasons

    Interest and capacity among private sector operatorsThe number of operators is limited in this sector. Hence capacity building among these operators is required

    Capacity of consumers is important in influencing the initial design decision through articulation of local demand as well as monitoring operator performance


Recommended