McNeil Generating Station Slow Living Conference June 3, 2011 John M. Irving, P.E. Burlington Electric Department
Transcript
Page 1: Sls 2011 irving

McNeil Generating Station

Slow Living ConferenceJune 3, 2011John M. Irving, P.E. Burlington Electric Department

Page 2: Sls 2011 irving
Page 3: Sls 2011 irving
Page 4: Sls 2011 irving
Page 5: Sls 2011 irving
Page 6: Sls 2011 irving
Page 7: Sls 2011 irving

Economic Benefits• Since startup in 1984, McNeil Station has contributed the following to

Vermont through August 2010:• Payroll $ 52,540,000• Property Taxes $ 24,880,000• Sales Taxes $ 930,000• Rail Transportation $ 34,420,000• Local Contractors $ 6,489,000• Wood Fuel Purchases $155,092,000• Total $ 274,351,000

• This does not include the $67,000,000 to build the McNeil Station much of which was spent locally

• McNeil has provided 5,079,359 MWH of power since construction. The majority of this power would have been produced from fossil fuels. This energy would require 400 million gallons of fuel oil to produce

Page 8: Sls 2011 irving

Employment Benefits

• Powerplant Jobs 36• Home Office Support Jobs 4• Forest Management Jobs 4• Harvesting Processing and Transport 77• Support Services 11• Train Transportation 5

Total 130

Page 9: Sls 2011 irving

Wastewood Disposal Benefits

• Local Residents bring 2,000-3,000 tons/year of yard trimmings

• Local Businesses bring 3,000-4,000 tons/year of clean shipping pallets

• Clean energy usage eliminates $85/ton land-filling costs and creates power for 5,000 homes

Page 10: Sls 2011 irving

Electrical Reliability Benefits

• Burlington lights stayed on in Great Northeast Blackout!

• Burlington lights stayed on in 1998 Ice Storm!

• Vermont unaffected with loss of 250 MW transmission line from New York in 2000!

• Provides power price stability in spite of fluctuating market costs!

Page 11: Sls 2011 irving

New Technology

• Biomass Gasification allows more efficient energy from biomass

• Expanded Fuel Potential• Still in development stage• Used as basis of technical

requirements for Massachusetts RPS for biomass

Page 12: Sls 2011 irving

NOx Removal System

• Reduces NOx emissions by 50%+

• Allows McNeil to qualify for RECs

• 1.5 year payback

• 93% voter favorability in bond vote!

Page 13: Sls 2011 irving

Waste Heat Utilization

Page 14: Sls 2011 irving

District Heating

Page 15: Sls 2011 irving

District Heating in Burlington

Page 16: Sls 2011 irving

Challenges at McNeil• Competing with other wood fueled plants that

have enjoyed generous PURPA rates while McNeil pays 25% more for fuel because of harvesting notification and rail requirements

• Matching widely variable fuel demand with supply

• Lack of Consistency with energy and REC pricing • Irrational and unattainable RPS eligibility

requirements (60% efficiency for biomass plants in Massachusetts)