Date post: | 31-Mar-2016 |
Category: |
Documents |
Upload: | elzinga-volkers |
View: | 218 times |
Download: | 0 times |
Project Update Design and construc on progress con nues on the ICC Beltline. The design
team has been working closely with Spectrum Health on the review of our
Design Development drawings. We had a mee ng with the facili es
departments within Spectrum and took note of the revisions they would like to
have done to the documents proceeding forward into the Construc on
Document phase. IA has noted all of the changes and will proceed forward with
these notes. With Design Development drawings there is s ll some mechanical
and electrical drawings being developed. In order to confirm that the project
remains on track it was determined that there be a 50% CD review mee ng in
early June. In addi on to the documents proceeding into CD, Elzinga & Volkers
and Concord have been working together to review the overall project budget
to be sure that we con nue to stay within our approved budget and look for
cost savings anywhere we can while we s ll have the interior bid packages to
bid out.
On the construc on side of the project we con nue to proceed forward. Kent
companies and Dykema have been working closely together on the founda ons
and have been doing a great job, even with all of the wet weather we have been
experiencing. The building founda ons have made their way down the west
eleva on and will be making the turn to the south eleva on next week. While
concrete founda ons press forward, TL Masonry has joined the team on‐site
and has started laying block on the north stairwell and double elevator pit. Each
one of these tasks is extremely cri cal because Builders Iron will be on‐site to
start steel erec on next week.
While the building is star ng to take shape, the site is already well on its
way. Dykema and Kent have been able to get the en re west parking lot
ready for asphalt paving. Once the subgrade was ready for the paving, EV
contacted Michigan Paving and had a site walk through inspec on of all the curb
and gravel to make sure there were not any so spots or high/low spots in the
gravel. All quality aspects checked out and we were “blacked out” within a few
days. The progress has not proceeded without its share of challenges. With the
phase drawings we are asking quick answers to ques ons on interior bearing
embed loca ons, placement of elevator sumps and u lity loca ons within the
building. All of these have direct rela on with the interior packages that are s ll
under design, but EV, IA, JDH, NEDERVELD and all of the trade contractors have
been working closely to make sure we maintain our overall schedule. We truly
have a great design build team on this project.
The Cornerstone Volume 1, Issue 25
May 24, 2013
Created By:
Dus n Kuzee, Project Manager
dkuzee@elzinga‐volkers.com
Contractor of the Week In this issue Elzinga & Volkers would
like to acknowledge the effort that
Michigan Paving put forth to get the
asphalt installed. As men oned in the
project update, EV conducted a quality
inspec on and scheduled the paving
with Michigan Paving. At this mee ng
we determined that the paving of the
west parking lots would take two
days. The two days that this work
would be performed on would be
Friday and Monday but the one thing
that neither one could predict is that on
Friday the heavens would let loose and
it would rain all day. It was then
determined that the schedule would
have to be pushed back to Monday and
Tuesday of the following
week. Michigan Paving arrived on‐site
Monday morning at 7:00am and did not
leave the job‐site un l the en re lot
and entry drive was paved. They were
on‐site un l 10:00pm that night
comple ng the base asphalt. This was
a great accomplishment and speaks to
the quality of contractor Michigan
Paving is, they took the me to meet
their original schedule even when the
reason they were behind had nothing
to do with their ac on. Thank you for
the hard work and we look forward to
the rest of the parking lot being paved
out soon!
The Cornerstone Page 2
+
Project Photos
Kent didn’t waste any me se ng
up forms along the west founda on
wall
We are star ng to go ver cal with the
building. TL con nues with the north
stair well
Interior pads forms ge ng prepped
for concrete
Kent’s crane se ng up gang forms
for Phase 3 west founda on wall
Builders Iron started delivering steel
this week
TL Masonry has started laying block
on‐site
Dykema excava ng the west
founda on wall
Dykema backfilling the north wall
Forms being setup along the south wall
and interior pads being excavated
Project Forecast
The next few weeks of the project will be exci ng and require a large amount of coordina on on‐site. Next week, Builders Iron will have their steel erec on crews start standing steel. To help speed up the process, Elzinga & Volkers is going to have all the anchor bolts surveyed by a 3rd party. This will ensure that all of the anchor bolts are in the proper loca on and Builders Iron can start erec on of the steel as soon as they arrive. In addi on to the steel star ng, we will con nue with the founda ons in phase 2 and 3 and start working our way out of the building. To throw another twist in the coordina on, TL Masonry will be working on the double elevator sha while steel erec on is ongoing. This will take proper planning and coordina on with Builders and TL in order to ensure that everyone on‐site is working safely and does not have poten al hazards swinging over their head. Design of the building will be an internal task of IA’s in the next two weeks. They will be incorpora ng all of the comments heard at the DD mee ngs as well as developing the construc on documents further. We will also be moving into a cri cal phase of shop drawing review with exterior metal studs, exterior glazing, metal panels and masonry. These are going to be what everyone see’s once the building is finished and we need to make sure Spectrum is ge ng the greatest quality as possible.
The Cornerstone Page 3
Programming Basis of Design/SD Design Documents Construc on Documents
+
Track the Project’s Progress as the Forest Grows!