+ All Categories
Home > Documents > Spectrum Health East Beltline Integrated Care Center

Spectrum Health East Beltline Integrated Care Center

Date post: 31-Mar-2016
Category:
Upload: elzinga-volkers
View: 218 times
Download: 0 times
Share this document with a friend
Description:
The Cornerstone - Issue 25
Popular Tags:
3
Project Update Design and construcƟon progress conƟnues on the ICC Beltline. The design team has been working closely with Spectrum Health on the review of our Design Development drawings. We had a meeƟng with the faciliƟes departments within Spectrum and took note of the revisions they would like to have done to the documents proceeding forward into the ConstrucƟon Document phase. IA has noted all of the changes and will proceed forward with these notes. With Design Development drawings there is sƟll some mechanical and electrical drawings being developed. In order to conrm that the project remains on track it was determined that there be a 50% CD review meeƟng in early June. In addiƟon to the documents proceeding into CD, Elzinga & Volkers and Concord have been working together to review the overall project budget to be sure that we conƟnue to stay within our approved budget and look for cost savings anywhere we can while we sƟll have the interior bid packages to bid out. On the construcƟon side of the project we conƟnue to proceed forward. Kent companies and Dykema have been working closely together on the foundaƟons and have been doing a great job, even with all of the wet weather we have been experiencing. The building foundaƟons have made their way down the west elevaƟon and will be making the turn to the south elevaƟon next week. While concrete foundaƟons press forward, TL Masonry has joined the team onsite and has started laying block on the north stairwell and double elevator pit. Each one of these tasks is extremely criƟcal because Builders Iron will be onsite to start steel erecƟon next week. While the building is starƟng to take shape, the site is already well on its way. Dykema and Kent have been able to get the enƟre west parking lot ready for asphalt paving. Once the subgrade was ready for the paving, EV contacted Michigan Paving and had a site walk through inspecƟon of all the curb and gravel to make sure there were not any soŌ spots or high/low spots in the gravel. All quality aspects checked out and we were “blacked out” within a few days. The progress has not proceeded without its share of challenges. With the phase drawings we are asking quick answers to quesƟons on interior bearing embed locaƟons, placement of elevator sumps and uƟlity locaƟons within the building. All of these have direct relaƟon with the interior packages that are sƟll under design, but EV, IA, JDH, NEDERVELD and all of the trade contractors have been working closely to make sure we maintain our overall schedule. We truly have a great design build team on this project. e Cornerstone Volume 1, Issue 25 May 24, 2013 Created By: DusƟn Kuzee, Project Manager dkuzee@elzingavolkers.com Contractor of the Week In this issue Elzinga & Volkers would like to acknowledge the eort that Michigan Paving put forth to get the asphalt installed. As menƟoned in the project update, EV conducted a quality inspecƟon and scheduled the paving with Michigan Paving. At this meeƟng we determined that the paving of the west parking lots would take two days. The two days that this work would be performed on would be Friday and Monday but the one thing that neither one could predict is that on Friday the heavens would let loose and it would rain all day. It was then determined that the schedule would have to be pushed back to Monday and Tuesday of the following week. Michigan Paving arrived onsite Monday morning at 7:00am and did not leave the jobsite unƟl the enƟre lot and entry drive was paved. They were onsite unƟl 10:00pm that night compleƟng the base asphalt. This was a great accomplishment and speaks to the quality of contractor Michigan Paving is, they took the Ɵme to meet their original schedule even when the reason they were behind had nothing to do with their acƟon. Thank you for the hard work and we look forward to the rest of the parking lot being paved out soon!
Transcript
Page 1: Spectrum Health East Beltline Integrated Care Center

Project Update Design and construc on progress con nues on the ICC Beltline. The design

team has been working closely with Spectrum Health on the review of our

Design Development drawings. We had a mee ng with the facili es

departments within Spectrum and took note of the revisions they would like to

have done to the documents proceeding forward into the Construc on

Document phase. IA has noted all of the changes and will proceed forward with

these notes. With Design Development drawings there is s ll some mechanical

and electrical drawings being developed. In order to confirm that the project

remains on track it was determined that there be a 50% CD review mee ng in

early June. In addi on to the documents proceeding into CD, Elzinga & Volkers

and Concord have been working together to review the overall project budget

to be sure that we con nue to stay within our approved budget and look for

cost savings anywhere we can while we s ll have the interior bid packages to

bid out.

On the construc on side of the project we con nue to proceed forward. Kent

companies and Dykema have been working closely together on the founda ons

and have been doing a great job, even with all of the wet weather we have been

experiencing. The building founda ons have made their way down the west

eleva on and will be making the turn to the south eleva on next week. While

concrete founda ons press forward, TL Masonry has joined the team on‐site

and has started laying block on the north stairwell and double elevator pit. Each

one of these tasks is extremely cri cal because Builders Iron will be on‐site to

start steel erec on next week.

While the building is star ng to take shape, the site is already well on its

way. Dykema and Kent have been able to get the en re west parking lot

ready for asphalt paving. Once the subgrade was ready for the paving, EV

contacted Michigan Paving and had a site walk through inspec on of all the curb

and gravel to make sure there were not any so spots or high/low spots in the

gravel. All quality aspects checked out and we were “blacked out” within a few

days. The progress has not proceeded without its share of challenges. With the

phase drawings we are asking quick answers to ques ons on interior bearing

embed loca ons, placement of elevator sumps and u lity loca ons within the

building. All of these have direct rela on with the interior packages that are s ll

under design, but EV, IA, JDH, NEDERVELD and all of the trade contractors have

been working closely to make sure we maintain our overall schedule. We truly

have a great design build team on this project.

 

The Cornerstone Volume 1, Issue 25

May 24, 2013

Created By:

Dus n Kuzee, Project Manager

dkuzee@elzinga‐volkers.com

Contractor of the Week In this issue Elzinga & Volkers would

like to acknowledge the effort that

Michigan Paving put forth to get the

asphalt installed. As men oned in the

project update, EV conducted a quality

inspec on and scheduled the paving

with Michigan Paving. At this mee ng

we determined that the paving of the

west parking lots would take two

days. The two days that this work

would be performed on would be

Friday and Monday but the one thing

that neither one could predict is that on

Friday the heavens would let loose and

it would rain all day. It was then

determined that the schedule would

have to be pushed back to Monday and

Tuesday of the following

week. Michigan Paving arrived on‐site

Monday morning at 7:00am and did not

leave the job‐site un l the en re lot

and entry drive was paved. They were

on‐site un l 10:00pm that night

comple ng the base asphalt. This was

a great accomplishment and speaks to

the quality of contractor Michigan

Paving is, they took the me to meet

their original schedule even when the

reason they were behind had nothing

to do with their ac on. Thank you for

the hard work and we look forward to

the rest of the parking lot being paved

out soon!

Page 2: Spectrum Health East Beltline Integrated Care Center

The Cornerstone Page 2

Project Photos

Kent didn’t waste any me se ng

up forms along the west founda on

wall

We are star ng to go ver cal with the

building. TL con nues with the north

stair well

Interior pads forms ge ng prepped

for concrete

Kent’s crane se ng up gang forms

for Phase 3 west founda on wall

Builders Iron started delivering steel

this week

TL Masonry has started laying block

on‐site

Dykema excava ng the west

founda on wall

Dykema backfilling the north wall

Forms being setup along the south wall

and interior pads being excavated

Page 3: Spectrum Health East Beltline Integrated Care Center

Project Forecast

The next few weeks of the project will be exci ng and require a large amount of coordina on on‐site. Next week, Builders Iron will have their steel erec on crews start standing steel. To help speed up the process, Elzinga & Volkers is going to have all the anchor bolts surveyed by a 3rd party. This will ensure that all of the anchor bolts are in the proper loca on and Builders Iron can start erec on of the steel as soon as they arrive. In addi on to the steel star ng, we will con nue with the founda ons in phase 2 and 3 and start working our way out of the building. To throw another twist in the coordina on, TL Masonry will be working on the double elevator sha while steel erec on is ongoing. This will take proper planning and coordina on with Builders and TL in order to ensure that everyone on‐site is working safely and does not have poten al hazards swinging over their head. Design of the building will be an internal task of IA’s in the next two weeks. They will be incorpora ng all of the comments heard at the DD mee ngs as well as developing the construc on documents further. We will also be moving into a cri cal phase of shop drawing review with exterior metal studs, exterior glazing, metal panels and masonry. These are going to be what everyone see’s once the building is finished and we need to make sure Spectrum is ge ng the greatest quality as possible.

The Cornerstone Page 3

Programming Basis of Design/SD Design Documents Construc on Documents

Track the Project’s Progress as the Forest Grows!


Recommended