Date post: | 22-Jan-2018 |
Category: |
Documents |
Upload: | damien-brennan |
View: | 331 times |
Download: | 1 times |
St James’s Market Service Tunnel
Damien Brennan Design Engineer Barhale plc
GE Basements and Underground Structures Conference
Presentation overview
Developing a Temporary Works solution to construct and support a permanent service
tunnel between basements
Presentation Content • Clients Brief
• Design Considerations
• Selection of Temporary Works Solution
• Design change
• Outline of design
• Design loading
• Technical Features
• Installation Sequence
• Construction Obstacles
• Installation Progression
• Construction Benefits
Clients Brief
• Provide an underground service corridor between two eight-
storey retail and commercial blocks basements between 1 St
James’s Market (1 SJM) and 2 St James’s Market (2 SJM).
• Corridor to consist of underground reinforced concrete finish,
8m deep
• Temporary corridor/tunnel support system that is:
• Cost-effective,
• Fully designed,
• Adaptable solution that could be delivered and
• Installed safely
Clients Brief
Clients Brief
Design Considerations
• Ground conditions: Stiff London CLAY
formation beneath 3m of soft slightly gravelly
CLAY
• Ground water was recorded below proposed
invert level of construction.
Design Considerations • Site access and compound size
restrictions due to the on-going
redevelopment works for the
adjoining building on each side of
corridor.
• Ground level above tunnel profile to
be used as a storage area
Design Considerations
• Design to be adaptable to change during
construction if any obstacle/unknown objects
or adverse ground conditions are encountered.
• Design to be constructible in terms of
components that can be man-handable,
delivery of installation sequence and access to
works areas
Two options considered for Temporary Works Solution tunnel construction:
• Pipe Roof Method
• Timber Heading construction
Selection of Temporary Works Solution
Typical Pipe Roof Method Typical Timber Heading
Pipe Roof Method • Generally shaft sunk on each end (from each basement)
• Microtunnel from centre top, proceeding in both direction if required
• Pipes to be braced/supported during excavation of soil
• Pipes fill with concrete
• Internal lined with concrete lining
• Lifting required for TBM and pipes
• Launch/reception frame required on each side for each Microtunnel launch
Timber Heading Construction • Drive length up to 25m
• Timber side & head boards
• Steel or timber head & side Trees
• Head boards driven and cell hand excavated and support by each setting
• Each cell connected on all sides
• Working platform required on each side on each level
• Drive direction can be changed
Heading Option Selected
Key Reasons
• Drive direction can change if unknown obstacles
are encountered
• Conditions can be monitored and design changed
during construction
• No plant required all hand dig
• All structural elements fabricated off-site
• All structural elements are man-handable
• No constraints in terms of tunnel dimensional
change
Design Change
Design Outline
Design Outline
Design Outline
Design Outline
Design Loading
Technical Features • Corridor/Tunnel 8m deep to invert level
• Total drive length 7.5m
• Internal Tunnel opening at 6.7m wide x 3.2m high & 2.2m high
• Main steel Headtrees, Sidetrees and Cills 152x23UC
• Maximum spacing of primary supports (Headtrees) 1.45m
• Internal heading dimensions 1.4m x 1.45m
• Total number of heading set per row 8
• Circa 350 Tonnes of hand dig soil removed during construction
• Thickness of permanent reinforced concrete skin wall of tunnel lining
350mm thick
Installation Sequence
Installation Sequence
Installation Sequence
Construction Obstacles
Construction Obstacles
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Installation Progression
Construction Benefits
• Adaptable to change –drive direction change
• Conditions can be monitored and design changed
during construction
• No plant required all hand dig
• All structural elements fabricated off-site
• All structural elements are man-handable
• No constraints in terms of tunnel dimensional
change
Questions?