+ All Categories
Home > Documents > Statement of Work: Drilling, Sampling & Monitoring Well ...

Statement of Work: Drilling, Sampling & Monitoring Well ...

Date post: 03-Oct-2021
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
97
EXHIBIT 1 STATEMENT OF WORK DRILLING, SAMPLING, AND MONITORING WELL INSTALLATION at the LEMARS COAL GAS SITE LEMARS, IOWA TDD#: S07-0007-002 X. PAN #: 15 L LMTZXX Project Manager: Bill Mehnert Prepared by: Ecology and Environment, Inc. Superfund Technical Assessment and Response Team (START) 6405 Metcalf Avenue, Cloverleaf Building 3, Suite 404 _ Overland Park, Kansas 66202 { I 30324448 llllllllllllllllllllllll Superfund
Transcript
Page 1: Statement of Work: Drilling, Sampling & Monitoring Well ...

EXHIBIT 1

STATEMENT OF WORK

DRILLING, SAMPLING, AND MONITORING WELL INSTALLATION

at the

LEMARS COAL GAS SITE

LEMARS, IOWA

TDD#: S07-0007-002

X.

PAN #: 15L

LMTZXX

Project Manager: Bill Mehnert

Prepared by:

Ecology and Environment, Inc.Superfund Technical Assessment and Response Team (START)

6405 Metcalf Avenue, Cloverleaf Building 3, Suite 404 _Overland Park, Kansas 66202 {

I

30324448

llllllllllllllllllllllllSuperfund

Page 2: Statement of Work: Drilling, Sampling & Monitoring Well ...

TABLE OF CONTENTS

Section

1.0 GENERAL

Page

v............................................. 1-1

2.0 INFORMATION TO BIDDERS 2-1

3.0 GEOLOGY AND HYDROGEOLOGY................................................. ......................... .. . 3-1

3.1 SOILS ........................................................................................................................... 3_1

3.2 GEOLOGY/HYDROGEOLOGY ....................... ............................................. 3-1

4.0 SCOPE OF WORK.......................................................................... ..................................4-1

4.1 MONITORING WELL DRILLING PROCEDURES ................................................ 4-1

4.1.1 Shallow Monitoring Wells ............... 4-1

4.1.2 Intermediate Monitoring Wells.................................... 4-2

4.1.3 Deep Monitoring Wells ....................................................................................4-2

4.2 MONITORING WELL CONSTRUCTION AND INSTALLATION .................... .4-3

4.2.1 Casing and Screen.............................................................................................. 4-4

4.2.2 Centralizers.................................................................................... 4-3

4.3 BACKFILLING...................................... 4-4

4.3.1 Filter Pack ................................ 4-4

4.3.2 Seal and Grout.................................................................. 4-4

4.4 SURFACE PROTECTION............................................................................................4-4

4.5 DEDICATED PUMP INSTALLATION ..................................................................... 4-5

4.6 WELL DEVELOPMENT.................. 4-5

4.7 WELL REGISTRATION................. 4-6

4.8 DECONTAMINATION ......................................... 4-6

5.0 WASTE DISPOSAL OF CONTAMINATED SOIL AND WASH WATER.................. .5-1

6.0 SITE SAFETY.......................................................................................................................... 6-1

7.0 CONTRACT PARTICULARS......................... 7-1

8.0 BID PARTICULARS ......................... 8-1

BLM/JG/LKS— 1583LMTZXX/0007002/exhibitl/F

Page 3: Statement of Work: Drilling, Sampling & Monitoring Well ...

TABLE OF CONTENTS—(Continued)

Section

APPENDICES:

Page

A. Figures........................................................................................................................................ A

Figure 1 Site Location Map ................................ .............................................................. A-l

Figure 2 Site Area with Proposed Well Locations ............................................ ........... A-2

Figure 3 Representative Geologic/Hydrogeologic Column.............................................. A-3

Figure 4 Proposed PVC Monitoring Well-Construction Diagrams.................................. A-4

B. Levels of Protection Guidelines ............................................................................................ B

C. Statement of Medical Fitness........................................... C

D. Statement of Health and Safety Training........................................................... D

E. Representation and Certification Regarding Subcontractor Status.............................................E

LIST OF TABLES

Table Page

4-1 Well Construction Summary—Proposed Monitoring Wells 4-3

>

BLM/JG/LKS__ u 1583LMTZXX/0007002/exhibitl/F

Page 4: Statement of Work: Drilling, Sampling & Monitoring Well ...

(1.0 INTRODUCTION

Ecology and Environment, Inc. (E & E), with a business office at 6405 Metcalf, Cloverleaf Building

#3, Suite 404, Overland Park, Kansas 66202, has entered into an EPA Region 7 Superfund Technical

Assessment and Response Team Contract (START) (Contract No. 68-W6-0012) to furnish technical

assistance at uncontrolled hazardous substance facilities.

E & E is in the process of conducting a site investigation in Le Mars, Iowa, at the Le Mars Coal Gas

site. As part of this investigation it is necessary to install a monitoring well network of nested wells in

order to document the apparent source of contamination, and attribute potential municipal well

contamination to that apparent source. The installation of monitoring wells will facilitate the investigation’s

objectives.

The Le Mars Coal Gas site is located in Le Mars, Plymouth County, Nebraska (Appendix A: Figure

1: Site Location Map) within section 9, Township 92 North, Range 45 West. The site consists of a

contaminated ground water plume located beneath a mixture of commercial and residential properties in

the north-central to northwest portion of the city (Appendix A: Figure 2: Site Area Map with Proposed

Monitoring Well Locations). The primary contaminants are petroleum-related chemicals including BTEX

(benzene, toluene, ethyl benzene, and xylene) compounds and polynuclear aromatic hydrocarbons (PAHs).

Geoprobe™ borehole sampling of the shallow ground water (30-40 feet below ground surface [bgs])

has characterized a contamination plume migrating from the intersection of 4,h Avenue NE and 1st Street

NE to the west-northwest toward Central Avenue. Extensive subsurface soil sampling has shown that the

former manufactured gas plant (FMGP), located on the northwest corner of 4th Avenue and Is1 Street,

appears to be the source of this contamination. The subsurface soil contamination extends to the north of

an east-west railroad line (formerly the Illinois Central RR) and to the west of a north-south drainage ditch.

Previous investigations have identified ground water contamination in three shallow monitoring wells

installed at the site. Water samples collected from these wells have levels of benzene up to 160 parts per

million (ppm), toluene up to 46 ppm, naphthalene up to 18 ppm, phenol up to 34 ppm, and benzo(a) pyrene

up to 220 parts per billion (ppb). (Note: None of the proposed monitoring wells will be installed directly

beneath the source area.) Subsurface soils on the source property are contaminated with benzene and

naphthalene at concentrations in excess of 300 and 2,600 ppm, respectively.

BLM/JG/LKS„ 1-1 1583LMTZXX/0007002/exhibitl/F

Page 5: Statement of Work: Drilling, Sampling & Monitoring Well ...

The primary objectives of the monitoring well installation and sampling are to:

• Document the extent of shallow ground water contamination, previously delineated with Geoprobe™ temporary monitoring wells, with permanent shallow monitoring wells.

• Determine the vertical extent of ground water contamination northwest of the site with nested permanent monitoring wells established at three depths

• Characterize site geology based on logging of retrieved samples.

• Characterize site hydrogeology based on sample logging during well installation and on water levels andfslugitestssfollowing well installation.

• Determine the potential for contamination migrating from the site to the two municipal wells located less than Vi mile northwest of the site.

BLM/JG/LKS... 1-2 1583LMTZXX/0007002/exhibitl/F

Page 6: Statement of Work: Drilling, Sampling & Monitoring Well ...

2.0 INFORMATION TO BIDDERS

Questions regarding specific aspects of the work to be performed should be directed to the attention

of the E & E Project Manager (PM) Bill Mehnert or Program Manager Bob Overfelt at (913) 432-9961.

Questions concerning contract procedures should be addressed to the E & E Subcontracts Manager Ed

Pfeiffer at (716) 684-8060 or the E & E Project Manager Bill Mehnert at (913) 432-9961.

Eleven monitoring wells will be installed at the site. All installed wells will be located northwest of

the site other than the upgradient background well (see Figure 2 in Appendix A). Proposed locations are

approximate and may be changed by the PM based on utility clearance and drilling rig access. The 11

monitoring wells will be installed at five locations throughout the site. At 3 of the 5 locations a shallow

(approximately 25-30 feet below ground surface [bgs]) monitoring well will be installed across the water

table. At all five locations an intermediate aquifer (approximately 50-70 feet bgs) monitoring well will be

installed above the most surficial and substantial fine-grained aquitard unit (i.e., base of the glacial/alluvial

aquifer). At 3 of the 5 locations (not necessarily the same as the shallow well locations), a deep (140-160

feet bgs) monitoring well will be installed within buried channel deposits composed of sand and gravel.

Those buried channel deposits may be an important future source of drinking water for the city of Le Mars.

Final depths of all monitoring wells will be determined by E & E on-site personnel based on information

obtained from logging retrieved lithologic samples.

All monitoring wells will be installed using a rotosonic drilling rig. A single rig, with a minimum of

three subcontractor personnel, will be required for the project. In addition, and at a minimum, an equal

volume of water must be retrieved from the well during development as was lost to the formation

during well drilling and installation.

Before the commencement of drilling work, E & E will conduct a site orientation session with E & E

and subcontractor personnel. The session will cover a general site description, site safety, investigation-

derived waste handling, and decontamination procedures. It is the subcontractor’s responsibility to have

enough personnel present at the orientation meeting to adequately cover any unanticipated crew member

changes. Coordination and scheduling of such training will be with the E & E PM. For each day of on­

site work, all subcontractor personnel will also be required to attend a brief daily health and safety meeting

prior to commencement of work.

Currently, E & E anticipates to start drilling activities on-August 7, 2000 and continue to August 17,

2000. Subcontractor personnel will be required to provide adequate notification to E & E of any

BLM/JG/LKS.,- 2-1 1583LMTZXX/0007002/exhibitl/F

Page 7: Statement of Work: Drilling, Sampling & Monitoring Well ...

scheduling conflicts that would prevent work from being conducted in an expeditious manner. Once

project work has started subcontractor personnel and equipment must be committed to the project until

completion of the work or until released by E & E. Due to the nature of the work, the average work day

is anticipated to exceed eight hours. The subcontractor will be required to submit daily summaries of

the work completed and associated costs in writing to the E & E PM at the end of each day during

well construction, including an estimation of the amount of water lost to the formation for each

boring/well.

BLM/JG/LKS. 2-2 1583LMTZXX/0007002/exhibitl/F

Page 8: Statement of Work: Drilling, Sampling & Monitoring Well ...

3.0 GEOLOGY AND HYDROGEOLOGY

The following information is being provided to the subcontractor so a determination regarding the

applicability of the Rotosonic drilling method to site geologic conditions can be made. Receipt of a signed

bid by E & E from the subcontractor represents acceptance of the proposed drilling method.

3.1 SOILS

The general classification of soil in the Le Mars, Iowa area is silty soils of the Ida-Galva Association.

This association consists mainly of gently sloping to very steep silty soils that are well drained. One soil

type, the Galva silty clay loam is present at the Le Mars Coal Gas site. This soil develops on stream

benches that are about 5 to 15 feet above the flood plain and have moderate permeability and slope ranges

from 0 to 2 percent.

3.2 GEOLOGY/HYDROGEOLOGY

The upland surface of Plymouth County, in northwest Iowa, consists of a gently undulating prairie

topography which descends gradually toward the southwest and is trenched by a number of valleys that

trend south-westward. The Le Mars area is within the Dissected Till Plains Section of the Central

Lowlands Physiographic Province. The following discussion on the area geology and hydrogeology is

illustrated in Appenix A: Figure 3: General Geologic/Hydrogeologic Column.

Water in the Le Mars area is derived from two distinct aquifers, a surficial aquifer and the Dakota

sandstone aquifer. The surficial aquifer consists of unconsolidated recent alluvium, outwash sand and

gravel and glacial drift deposits and sand and gravel deposits in buried channels. The recent alluvium,

which is confined to the principal river valleys, and buried channels beneath the north and west portions

of Le Mars constitute a valuable source of water. The entire sequence of unconsolidated material is

considered an aquifer because sand and gravel of various ages are likely interconnected.

The Cretaceous-aged bedrock material consists of the Graneros Shale and the Dakota Formation which

is divided into the Woodbury and Nishnabotna members. The Graneros Shale is the youngest bedrock

encountered within the Le Mars area; however, it is unlikely this unit exists beneath the site although it is

found to cap the bedrock high about 1 V2 miles northeast of the site. The Woodbury Member of the Dakota

Formation is composed of interbedded shale, sandstone and lignite. The maximum thickness of the

BLM/JG/LKS 3-1 1583LMTZXX/0007002/exhibit 1/F

Page 9: Statement of Work: Drilling, Sampling & Monitoring Well ...

Woodbury Member is approximately 170 feet with post-Cretaceous erosion reducing this to approximately

70 feet beneath the buried channel. The Nishnabotna Member is composed of sandstones with some

interbedded shales and is approximately 250 feet in thickness. It is the Nishnabotna Member that comprise

the Dakota Aquifer in the area.

The Dakota Formation unconformably overlies the Ordovician Galena, Decorah, Platteville and

Glenwood Formations, which predominantly consist of shales and dolomites and constitute an aquitard

between the underlying St. Peter Sandstone and the Dakota Formation. In turn, these Ordovician units

unconformably overlie undifferentiated Cambrian and Pre-Cambrian rocks.

Regionally, the Dakota aquifer can be confined by the Woodbury Member shales, and younger

Cretaceous marine shales and limestones. Available city well logs indicate the Woodbury shales would

be a confining unit in the Le Mars area. The thickness of these Cretaceous units is highly variable because

of erosional dissection and complex facies relationships in the Dakota (Woodbury Member) shales and

sandstones. The glacial drift can also act as a confining unit of the Dakota aquifer in Plymouth County,

although the lack of lateral homogeneity is more likely to create perched ground water zones.

The nearest drinking water wells to the site are the Le Mars Municipal Well Nos. 4 and 8 (Figure 2),

located about one-half mile northwest of the site. The well depths of Municipal Well Nos. 4 and 8 are 313

feet and 371 feet, respectively. The two wells are located downgradient from the site relative to surficial

ground water flow and are both screened in the Dakota Formation (Nishnabotna Member). A

potentiometric surface map for the Dakota Aquifer indicates a southwest ground water flow.

It was discovered during the installation of the three Geotek monitoring wells that shallow ground water

flow appears to be in a north-northwest direction toward Willow Creek and the Floyd River. However,

during the E & E/START site inspection (SI) in February 1997, static water level measurements were

obtained from the three Geotek monitoring wells. These measurements indicated that shallow ground water

flow was trending in a more westerly direction toward the onsite buried drainageway with depths to

groundwater ranging from 12.6 feet bgs in MW-3 to 15.2 feet bgs in MW-1. In addition, a water table

map for the Surficial Aquifer along the entire Floyd River Basin indicates a west-southwest flow.

BLM/JG/LKS-,.. 3-2 1583LMTZXX/0007002/exhibit 1/F

Page 10: Statement of Work: Drilling, Sampling & Monitoring Well ...

4.0 SCOPE OF WORK

The subcontractor is to furnish all materials, equipment, and labor necessary for the drilling, sampling,

construction, and installation of 3 shallow, 5 intermediate, and 3 deep monitoring wells to total depths of

approximately 30, 70, and 160 feet bgs, respectively. The 11 monitoring wells will be installed at 5'locations throughout the site using a rotosonic drilling rig. In addition, the subcontractor Will provide

flush-mount surface protection and dedicated bladder pumps for each installed monitoring well.

Only clean, potable water may be used as wash or cooling water when drilling or flushing wells. It

is the subcontractor's responsibility to locate a source of clean water for all drilling and well

installation procedures. If drilling water is obtained from the city of Le Mars, the subcontractor must

ensureWeontaminatidnf E & E will not reimburse expenses incurred in the maintenance of an adequate water

supply.

4.1 MONITORING WELL DRILLING PROCEDURES

All 11 proposed monitoring wells will be installed using a rotosonic drilling rig with an accompanying

support vehicle(s). Proposed locations are shown in Figure 2 (Appendix A). The monitoring wells will

be installed in a highly developed residential and commercial area. Therefore, the physical arrangement

of the rotosonic drilling rig relative to its support vehicle(s) may vary depending on access.

Because of the granular nature of the sediment and the relatively shallow water table, the

subcontracted drilling team should be prepared to encounter and remedy the problem of heaving sands.

The subcontractor will inform the on-site E & E geologist of the quantity of water introduced to the

subsurface.

In general, all drilling and sampling operations shall conform to applicable standards specified by the

American Society for Testing and Materials (ASTM) and State of Iowa regulations..

4.1.1 Shallow Monitoring Wells

Three shallow monitoring wells will be installed at three separate locations. These wells will be

screened across the water table, which lies approximately 15 feet BGS. For costing purposes the

completion depth is considered to be approximately 30 feet bgs.

BLM/JG/LKS. 4-1 1583LMTZXX/0007002/exhibitl/F

Page 11: Statement of Work: Drilling, Sampling & Monitoring Well ...

All shallow monitoring wells will be drilled/sampled using a dual line of drill pipe. The inner 4-inch

(nominal) core barrel and rod will be advanced ahead of the outer 6-inch (nominal) casing. The outer

casing will then be advanced to the sampled depth and the inner rod and core barrel (with sample) will be

retrieved. As the continuous samples are retrieved from the borings, they shall be delivered to E & E field

personnel in plastic sleeves for sample extraction and geologic logging. The subcontractor will provide

a tray or table on which the soil cores can be examined and sampled. Continuous sample collection will

proceed in this manner to the final|depM^p|f^Riffi^Sn@ufilessIotheiiSVisgpe®5nilSd?l^lK|El^S

4.1.2 Intermediate Monitoring Wells

Five intermediate monitoring wells will be installed at each of the five locations. These wells will be

screened at the base of the shallow glacial/alluvial aquifer, which for costing purposes is considered to be

approximately 70 feet bgs. With the exception of the termination depth, the method of sample retrieval

and drilling is anticipated to be identical to that used for the installation of the shallow monitoring wells;

however, the subcontractor will be prepared to utilize 8-inch (nominal) and 9-inch (nominal) outer casing

in order to isolate anyjsuBstontlallclavglaversiabove the base of the shallow unconfined glacial/alluvial

aquifer.

4.1.3 Deep Monitoring Wells

Deep monitoring wells will be installed at three of the five monitoring well locations. The deep

monitoring wells will be screened within the buried channel aquifer previously described. Completion

depths of the deep monitoring wells are anticipated to be approximately 160 feet bgs. Because of the

possibility of transferring contaminated ground water from the glacial/alluvial to the buried channel aquifer,

override casing will be required. If no override casing is required to reach the bottom of the

glacial/alluvial aquifer, then 8-inch (nominal) override casing will be used to isolate the glacial/alluvial

aquifer from the buried channel aquifer. In the event that 8-inch override casing is needed in the

unconfined aquifer, 9-inch override casing will be driven over the 8-inch casing to the clay layer in the

unconfined aquifer and the 8-inch override casing will then be driven to the confining layer between the

shallow unconfined aquifer and the semi-confined buried channel aquifer. In the case that another

intervening fine-grained unit was encountered, 10-inch overide casing will be incorporated into the override

casing/drilling scheme. The annular space of all override casings must be seated with bentonite before

sampling/drilling proceeds.

BLM/JG/LKS... 4-2 1583LMTZXX/0007002/exhibitl/F

Page 12: Statement of Work: Drilling, Sampling & Monitoring Well ...

4.2 MONITORING WELL CONSTRUCTION AND INSTALLATION

The shallow, intermediate, and deep monitoring wells shall be installed to approximate depths of 30,

70, and 160 feet bgs. The final depth of completion at each monitoring well location shall be determined

by the E & E PM. This decision will be based on the depth to ground water and field observations for the

shallow wells and on lithology and field observations for the intermediate and deep wells.

Table 4-1

WELL CONSTRUCTION SUMMARY—PROPOSED MONITORING WELLSLeMars Coal Gas site—LeMars, Iowa

Well Construction Snecifications Shallow Monitorine Wells Intermediate Monitorine Wells DeeD Monitorine WellsApproximate Number 3 5 3Approximate Depth 30 feet BGS. 70 feet bgs 160 feet bgs

approximate length 15 feet 60 feet 150 feetCasing diameter 2-inch nominal

material Schedule 40 PVC Schedule 40 PVC Schedule 40 PVClength 15 feet 10 feet

Screendiameter 2-inch nominalmaterial Type 304 continuous wrap Ss

slot size 0.015 inchSand Pack 20-30 mesh 20-30 mesh 20-30 mesh

Seal 3 feet of bentonite chips

Grout Bentonite chips (hydrated) High-solids bentonite slurry

Surface Finish \11 wells completed with securable flush mount well protector set in 3-foot diameter conical concrete pa

PumDS All wells will be eauiDDed with dedicated OED bladder DumDKEY: PVC = Polyvinyl chloride Ss = stainless steel bgs = below ground surface

All casing, screen, bailers, and pumps must be certified clean by the manufacturer and received

in protective plastic wrap or containers. All well construction materials shall be provided by the

subcontractor. Specific construction requirements are described below and summarized in Table 4-1.

Figure 4 (Appendix A) provides a representative well-construction diagram for the proposed monitoring

wells.

4.2.1 Casing and Screen

All monitoring wells will be constmcted of 2-inch (nominal) schedule 40 PVC casing and continuous

wrap 0.015-inch slot Type 304 Ss screen. All shallow monitoring wells will require 15-foot screens;

intermediate and deeps wells will be constructed with 10-foot screens. All casing and screen sections will

have threaded flush joints (to be equal to or exceed schedule 40 ASTM standards) and all joints must have

the appropriate o-rings in place before well installation begins. No joining compounds will be used.

BLM/JG/LKS. 4-3 1583LMTZXX/0007002/exhibitl/F

Page 13: Statement of Work: Drilling, Sampling & Monitoring Well ...

4.2.2 Centralizers

Stainless steel centralizers will be used to ensure proper placement of the casing and screen in the

borehole. T^JfiK^^^aliz^^iUl^^l^Ili^meS^^^^^^^SCTeen^aliilglinteFf^ce. Additional

centralizers will be attached to the casing at 20-foot intervals, unless otherwise indicated by the E & E

project manager.

4.3 BACKFILLING

The annular space between the borehole wall and the casing and screen shall have a minimum thickness

of 2.0 inches and shall be backfilled in a manner that prevents bridging of annular materials.

4.3.1 Filter Pack

All monitoring wells will be constructed with filter packs consisting of clean 20-30 mesh silica sand.

top of the filter pack will be tagged

continuously during installation. The filter pack will extend 2 feet above the casing-screen interface for

the shallow monitoring wells and 5 feet above the casing-screen interface for the intermediate and deep

wells.

4.3.2 Seal and Grout

A 3-foot seal will be installed immediately above the filter pack of each monitoring well. Bentonite

chips introduced to the annular space of the shallow monitoring wells must be hydrated with clean water

where they extend above the water table. Hydration shall occur following the installation of every bag of

bentonite chips. Above the seal, the annular space of all the intermediate and deep monitoring wells will

be filled with a high-solids bentonite slurry. The grout slurry will be pumped into the annulus using tremie

pipe, the bottom of which will remain at least 2 feet below the level of grout during pumping. All grout

materials will be installed to within 3 feet of ground surface.

4.4 SURFACE PROTECTION

All monitoring wells will be constructed with a flush-mount surface finish. The flush-mount well

protector equipped with a water-tight securable lid will be installed in a concrete pad. The pad will be 3

feet in diameter and will extend from the top of the previously installed grout column (3 feet bgs) to

BLM/JG/LKS. 4-4 1583LMTZXX/0007002/exhibitl/F

Page 14: Statement of Work: Drilling, Sampling & Monitoring Well ...

approximately 1 inch above grade. The top of the concrete well pad will be circular and slope away from

the center to prevent pooling of surface water. The bottom of the pad will be conical in shape (point down)

in order to alleviate damage from frost heave.

Any excess casing stickup will be cut horizontally level to provide a clearance of approximately 6

inches between the top of casing and the bottom of the well protector lid. The well openings at the top of

the casing will require a temporary water-tight locking cap until such time as the dedicated bladder pumps

have been installed. All hardware, including the hardened steel locks (keyed alike), shall be provided

by the subcontractor.

4.5 DEDICATED PUMP INSTALLATION

The subcontractor will provide and install dedicated, QED Environmental Systems, Inc., stainless steel

bladder pumps with teflon tubing in each of the 11 wells. Each of the dedicated pumps shall have a water­

tight locking well cap (see Section 9, Item 20 for details). The dedicated pumps will be set at a level that

positions the inlet screen of the pump within the screened interval and approximately 3 feet above the

bottom of the well.

4.6 WELL DEVELOPMENT

A newly completed ground water monitoring well will not be developed for at least 24 hours after well

completion. The new ground water monitoring well will be developed by surging and pumping until the

water inside the well is visibly free of sediment and the pH, temperature, and specific conductance have

stabilized. E & E will provide instruments for monitoring these indicator parameters. All well

development pumping will be performed using either a submersible or drill-rig mounted pump

capable of extracting at least 5 gallons per minute (gpm), and a surge block no smaller than 1.75

inches in diameter. The subcontractor will supply all well development equipment, including bailers,

surge blocks, and pumps. The that the material that

has been agitated and loosened by the surging action is removed. The cycle of surging and pumping will

be repeated until satisfactory development and stabilization is attained. The E & E project manager will

determine when development on a particular well is complete. Stabilization will be considered to be

achieved when the difference between consecutive indicator parameter readings is less than or equal to 10

percent. If conditions do not allow the use of a pump, the monitoring well will be developed with a bailer

BLM/JG/LKS..- 4-5 1583LMTZXX/0007002/exhibitl/F

Page 15: Statement of Work: Drilling, Sampling & Monitoring Well ...

by the driller. All reusable well development materials; including surge blocks, pumps, pump tubing, and

bailers, must be thoroughly decontaminated between monitoring wells.

Acids, dispersing agents, and explosives will not be used to enhance well development. During

development, no water or other liquid will be introduced into the well.

All development water will be collected in a 500-gallon polyethylene tank and/or 55-gallon drums.

The driller will be required to provide the polyethylene tank and 55-gallon drums. Disposal of the

development water will be in accordance with procedures outlined in Section 5.

4.7 WELL REGISTRATION

The driller shall register all monitoring wells with the appropriate state regulatory agency and provide

copies of the registration to the E & E PM.

4.8 DECONTAMINATION

Prior to the mobilization of the drill rig to the site and following project completion, the rig and all

associated equipment (including sampling devices) shall be thoroughly cleaned to remove all oil, grease,

mud, tar, etc. This cleaning process shall consist of the following:

1) A high-pressure hot water cleaning with a low sudsing-detergent (i.e., Alconox).

2) A tap water rinse.

3) A final high-pressure hot water cleaning.

E & E personnel will inspect all equipment to insure sufficient cleaning. The subcontractor must provide

all equipment necessary for this cleaning process.

Before drilling each boring, all drilling equipment (i.e., cutting bits and drilling rods) shall be cleaned

with pressurized hot water and rinsed with clean water. All equipment that comes into contact with

subsurface samples (i.e., core barrel) shall be cleaned with hot water and alconox and a water rinse before

collection of each sample. Petroleum-based lubricants shall not be used to prevent binding.

The subcontractor will be responsible for providing a means for collecting wash water and related

materials in a decontamination pad. The decontamination pad will be constructed with walls on three sides

a minimum of 3 feet high to prevent overspray. It will be lined with a water proof tarp and sloped to allow

BLM/JG/LKS-. 4-6 1583LMTZXX/0007002/exhibitl/F

Page 16: Statement of Work: Drilling, Sampling & Monitoring Well ...

water to drain and collect at one corner. It will be wide enough to allow the drill rig to back into it for

decontamination purposes. The decontamination pad will be constructed by the subcontractor in an area

on site designated by the E & E project manager. The subcontractor will not begin decontamination of

equipment until the E & E PM has inspected and approved the decontamination pad according to the

aforementioned construction criteria.

BLM/JG/LKS™ 4-7 1583LMTZXX/0007002/exhibitl/F

Page 17: Statement of Work: Drilling, Sampling & Monitoring Well ...

5.0 WASTE DISPOSAL OF CONTAMINATED SOIL AND WASH WATER

Any drilling spoils or development water that remain after each monitoring well installation will be

considered hazardous material until determined by E & E to be otherwise. Wash water and solutions

remaining after decontamination, of drilling equipment will also be considered a hazardous material until

determined by E & E to be otherwise. Decontamination fluids will be pumped from the pad and

temporarily contained in 55-gallon drums. Development water will be temporarily containerized in 55-

gallon drums. The subcontractor will be required to provide the drums. Water in the drums will be

pumped through a carbon filtration drum/system on site. The carbon filtration drum/system will be

provided by the subcontractor, who will provide the E & E project manager with the capabilities and

specifications of the system prior to mobilization. The subcontractor will be responsible for pumping the

decontamination/development water from the drums through the carbon filtration drum/system. Water

filtered through the carbon filtration drum/system will be discharged on the ground. After completion of

the project, the drums used to temporarily store decontamination/development water will be

decontaminated and retained by the subcontractor.

Drilling spoils or cuttings will be staged on plastic sheeting adjacent to each well location. The driller

is responsible for providing the plastic sheeting. If the drilling spoils or cuttings are determined to be

potentially hazardous material by E & E, the driller will be responsible for containerizing these materials

in 55-gallon drums as per 40 CFR Part 173 specifications. If deemed necessary, the subcontractor will

remove the waste to a designated area. E & E will determine which materials must be stored in 55-gallon

drums. The subcontractor is required to provide the 55-gallon drums and plastic liners as necessary

to containerize any hazardous material. The subcontractor does not have to assume the role of

hazardous waste generator in order to containerize the wastes and move them to the designated on-site

area(s).

BLM/JG/LKS. 5-1 1583LMTZXX/0007002/exhibitl/F

Page 18: Statement of Work: Drilling, Sampling & Monitoring Well ...

6.0 SITE SAFETY

Because of the hazardous nature of the materials that may have been used, stored, or disposed of on

site, all personnel employed or retained for services by the subcontractor may be required to wear personal

protective clothing and respiratory protective equipment while engaged in site-related activities.

Prospective bidders are cautioned that the requirement to wear protective equipment may result in some

discomfort and added physical stress to subcontractor personnel. Accordingly, bidders should assure that

its employees' physical condition will allow them to successfully perform their duties without physical harm

or adverse health effects while wearing the protective equipment, per OSHA regulations contained in 29

CFR 1910.134 (b) 10. Appendix C contains U.S. EPA and E & E level of protection guidelines pertaining

to personal protective clothing and respiratory equipment. Site conditions or E & E guidelines may at

times call for minor modifications within each level of protection. Upon mobilization, the subcontractor

Shall be prepared to perform work at protection levels up to and including Level C. The subcontractor

is required to provide his employees with the appropriate respiratory protective equipment and the

necessary training in the use of the equipment. The required level of protection during operations will be

dictated by waste characteristics, type of activity, site characteristics, and meteorological conditions. In

addition, the potential for the need to upgrade protection levels exists at any site where hazardous waste

may be found. In the event of a need to further upgrade the level of protection to Level B, the

subcontractor will be requested to resume work with a minimal delay following notification of the level of

protection upgrade.

Determination of the type and need for respiratory protection will be made by E & E personnel on a

location-to-location basis at the site. It is anticipated that the operations to be performed will require the

use of Level D personal protective equipment.

Other personal protective equipment (PPE) which will be required for this task includes chemical-

resistant coveralls, neoprene rubber steel-toed boots or steel-toed safety boots, hard-hats, rubber gloves,

and safety goggles, all of which will be furnished by the subcontractor.

Questions regarding levels of protection and related equipment should be addressed to the E & E

project manager prior to preparation of the bid proposal. Carefully review Article 15, Health and Safety,

of the sample subcontract agreement. Additional safety-related requirements are defined therein (Parts A

through H).

BLM/JG/LKS. 6-1 1583LMTZXX/0007002/exhibitl/F

Page 19: Statement of Work: Drilling, Sampling & Monitoring Well ...

The successful bidder selected for subcontract award must prepare its own Health and Safety

Plan (HASP) for the specific operations to be performed. The HASP must be reviewed and approved

by the E & E site manager before operations can begin. E & E will provide site fact sheets to the

subcontractor to assist in the drafting of the HASP.

E & E will require documentation, in advance of field work, stating .that the assigned subcontractor

field personnel have been approved, from a health standpoint, for the use of respiratory and other

protective equipment, and that these individuals have been trained in compliance with all OSHA regulations

regarding work on hazardous waste sites. As confirmation of this, the subcontractor is required to

complete the enclosed statement of Medical Fitness (attachment to subcontract) and the statement of Health

and Safety Training (attachment to subcontract). The subcontractor must present the signed forms to E & E

prior to commencement of the project.

BLM/JG/LKS. 6-2 1583LMTZXX/0007002/exhibitl/F

Page 20: Statement of Work: Drilling, Sampling & Monitoring Well ...

7.0 CONTRACT PARTICULARS

The subcontractor shall, on its own time and at its own expense, procure all permits, licenses, and

certificates that may be required of him by law for the execution of the work hereunder. The subcontractor

will comply with all federal, state and local laws, ordinances, rules, and regulations relating to the

performance of the work hereunder.

E & E will be responsible for contacting utility companies and verifying in the field all existing

underground cables, gas mains or other utilities. The location of drilling will be altered, if necessary, to

avoid any damage to existing utilities. During the progress of the work, the subcontractor shall cooperate

with the owners of utilities and permit their representatives access (subject to E & E approval) to the work

area to determine if their utilities are being endangered in any way.

Upon the completion of field operations, it will be the responsibility of the subcontractor to

restore the site as nearly as possible, to its original condition (i.e., grade down ruts, spread out

cuttings remaining on site, remove excess well installation/backfilling materials). The E & E project

manager will determine whether the restoration is satisfactory.

Should boulders or other obstructions be encountered, the subcontractor will attempt to redrill, after

approval from E & E personnel, at distances not greater than 10 feet away from the first boring in an

attempt to penetrate the soil to a reasonable depth. Where a reasonable depth is not obtained due to

boulders or other obstructions, the subcontractor will be paid for the depth reached for all drilling attempts.

If it is necessary to move a drilling location to a new site, the new location will be designated by a new

boring number, and the boring location will be marked in the field by E & E personnel.

The contract bid items will include all services, labor, equipment, transportation, material, and supplies

needed to complete the work. Payment for these items will be provided in the compensation for drilling,

sampling and well installation, and will also include drilling in areas of difficult access; recording and

submitting data incidental to each item; and waste containerization costs. Any down time incurred by the

subcontractor other than delay at the request of E & E will not be a payment item.

No other payments for any specified or indicated work, nor for any work implied therefore, will be

made. No payment will be made for drilled holes abandoned without authorization by E & E, for drilling

jholes for which satisfactory samples and data are not submitted, or for non-functioning monitoring wells.

BLM/JG/LKS__ 7-1 1583LMTZXX/0007002/exhibit 1 /F

Page 21: Statement of Work: Drilling, Sampling & Monitoring Well ...

Prior to the start of field operations, the subcontractor shall designate a foreman or representative who

will be the only individual authorized to discuss work schedules and related matters with E & E personnel.

BLM/JG/LKS- — 7-2 1583LMTZXX/0007002/exhibitl/F

Page 22: Statement of Work: Drilling, Sampling & Monitoring Well ...

8.0 BID PARTICULARS

The quantities and items stated on the attached bid sheet are E & E's best approximation of the scope

of work and are for the specific purpose of comparing bids. E & E does not guarantee that the bid

quantities are correct or that stated tasks will be performed. E & E reserves the right to vary the quantities

or delete items in their entirety, and the subcontractor will not be entitled to any extra payment, over the

rates bid, due to such amended quantities or deleted items. It must be stated, however, that at this time

every item discussed in the work plan is expected to be performed under this contract.

Only bids for the entire scope of work will be accepted.

Bid prices as submitted will remain valid for a period of 6 months from the date of bid opening in the

event there is a delay in awarding the contract.

Receipt of any contract additions sent to the bidder must be acknowledged by letter prior to the time

of bid opening or by attaching the required documents to the bid at time of submittal.

The following documentation must accompany the complete bid sheets:

1. A letter addressing the following items:

a. An estimate of the number of days required to complete the drilling and sampling of the borings and the construction of the wells.

b. The earliest date the subcontractor can mobilize after award of the bid.

c. The names of at least three references which E & E may contact; in particular, those for which the subcontractor has had experience drilling at potential hazardous waste/chemical spill sites.

d. The type and make of drilling equipment to be used.

2. Proof of minimum insurance coverage (see Exhibit 3 of subcontract agreement).

3. The completed Representations and Certifications Regarding Subcontractor status form.

4. Signed copies of the attached statement of Health and Safety Training and the attached statementof Medical Fitness.

Bids for the soil boring/sampling and well installation must be received by E & E, 6405 Metcalf,

Cloverleaf Building 3, Suite 404, Overland Park, Kansas, 66202, no later than 5:00 p.m., on July 21,

2000. The bid package will be enclosed in an envelope that will have the following marking in the lower

BLM/JG/LKS,. 8-1 1583LMTZXX/0007002/exhibit 1 /F

Page 23: Statement of Work: Drilling, Sampling & Monitoring Well ...

left-hand corner: Bid for: Lemars Coal Gas site, TDD: S07-0007-002, PAN: 1583LMTZXX, ATTN.:

Bill Mehnert.

The authorization for the selected bidder to proceed with the work will be under a subcontract issued

by E & E. A unit-price, time and materials type contract, with provision for designated lump sum items,

will be used.

The bid must be reviewed and approved by E & E and the EPA. E & E and the EPA reserve the right

to accept the bid most advantageous to the completion of the work or to reject any or all bids, as they may

determine in their sole and absolute discretion, and to proceed no further in this matter.

BLM/IG/LKS-— 8-2 1583LMTZXX/0007002/exhibitl/F

Page 24: Statement of Work: Drilling, Sampling & Monitoring Well ...

BID ITEMS

Item 1. Mobilization and Demobilization

This item will carry all charges incidental to equipment set-up and removal, in order that the charges

need not be distributed among the more variable items of the contract. This item will finchifliimMall

Mbli^^lffi^^eQ'ntaminationiS^S^^iii^S^^^S^lffiM The item will be paid at the contract lump

sum price for mobilization and demobilization and will include the furnishing of personnel, machinery,

tools, and all other equipment necessary to carry on and complete the work properly. All materials or

equipment furnished under this item will remain the property of the subcontractor and will be maintained,

cared for, and disposed of by the subcontractor. This item shall also include any costs incurred by the

subcontractor for decontamination equipment and supplies, personal safety and supplies, preparation of a

site-specific health and safety plan, and for moving containers of non-IDW hazardous material on site.

Item 2. Rotosonic Drilling/Sampling

This item will include all charges for equipment and labor necessary to complete the drilling and

sampling of the 11 monitoring well boreholes. Drilling/sampling will be accomplished using a 4-inch core

barrel inside of a 6-inch override casing. It is anticipated that 920 linear feet of rotosonic drilling/sampling

will be necessary to install the monitoring wells. Payment will be made for this item at the per linear foot

rate as bid.

Item 3. Override Casing 8-inch

This item will include all charges for equipment and labor necessary to install temporary 8-inch

diameter override casing around the aforementioned rotosonic drilling/sampling device. This item will be

necessary for the installation of the deep monitoring wells and possibly for the installation of some of the

intermediate monitoring wells, should substantial clays be encountered in the glacial/alluvial aquifer. It

is estimated that 426 linear feet of 8-inch override casing may be required for the installation of all

monitoring wells. Payment will be made at the per linear foot rate as bid.

Item 4. Override Casing 9-inch

This item will include all charges for equipment and labor necessary to install temporary 9-inch

diameter override casing around the aforementioned 8-inch override casing. The item may not be

necessary should no substantial clays be encountered in the glacial/alluvial aquifer. For bid purposes, it

BLM/JG/LKS... 1 1583LMTZXX/0007002/exhibitl/F

Page 25: Statement of Work: Drilling, Sampling & Monitoring Well ...

is estimated that 406 linear feet of 9-inch override casing may be necessary to install the intermediate and

deep monitoring wells. If required, payment will be made at the per linear foot rate as bid.

Item 5. Override Casing 10-inch

This item will include all charges for equipment and labor necessary to install temporary 10-inch

diameter override casing around the aforementioned 9-inch override casing to allow the 8-inch override

casing to be seated into the aquitard between the glacial/alluvial and buried channel aquifers. The item

may not be necessary should no, or a single, substantial clay be encountered in the glacial/alluvial aquifer.

For bid purposes, it is estimated that 141 linear feet of 10-inch override casing may be necessary to install

the deep monitoring wells. If required, payment will be made at the per linear foot rate as bid.

Item 6. PVC Casing

This item shall include the cost and installation of 2-inch Schedule 40 PVC casing with flush-threaded

joints used in the installation of selected monitoring wells. It is anticipated that 795 linear feet of PVC

casing will be necessary to install the monitoring wells. This item includes the cost and installation of all

required centralizers. Payment will be made for this item at the per linear foot rate as bid. If casing is

required to be cut at the surface, payment will be made for the in-hole portion of casing only. In order to

avoid unnecessary waste of materials, the subcontractor should have both 5 and 10-foot sections of casing

available.

Item 7. Stainless Steel Screen

This item shall include the cost of three 15-foot and eight 10-foot sections of 0.015-inch slot Type 304

stainless steel screens with stainless steel bottom caps to be used in the installation all monitoring wells.

A total of 125 feet of Ss screen will be required to install the monitoring wells. Payment will be made for

this item at the per linear foot rate as bid.

Item 8. Filter Pack

This item shall include the cost materials and installation of filter packs for all monitoring wells. The

filter pack will consist of 20-30 mesh clean silica sand. The filter pack will be installed via tremie pipe into

the annulus between the borehole wall and the outside of the well. Given this annular space, it is

anticipated that 171 feet of sand pack will be required. Payment will be made for this item at the per linear

foot rate as bid.

BLM/JG/LKS- 2 1583LMTZXX/0007002/exhibitl/F

Page 26: Statement of Work: Drilling, Sampling & Monitoring Well ...

Item 9. Buffer Sand

This item shall include the cost, materials and installation of 100 mesh fine silica sand to act as a buffer

between the filter pack and bentonite seal. The fine sand will be installed via tremie pipe into the annulus

between the borehole wall and the outside of the well. For the given annular space, it is anticipated that

11 feet of fine sand will be required. Payment will be made for this item at the per linear foot rate as bid.

Item 10. Bentonite Chip Seal

This item shall include the cost of materials and installation of a bentonite seal in all shallow monitoring

wells. The seal will consist of hydrated bentonite chips and will extend 3 feet above the top of the filter

pack. For the given annular space, it is anticipated that 60 feet of seal will be required. Payment will be

made for this item at the per linear foot rate as bid.

Item 11. High-solids Bentonite Slurry Grout

This item shall include the cost of materials and installation of a high solids (20-30) percent bentonite

by weight) bentonite slurry grout in the annular space of the intermediate and deep monitoring wells. It

is anticipated that 662 feet of annular space will be grouted using a high solids bentonite slurry grout.

Payment will be made for this item at the per linear foot rate as bid.

Item 12. Surface Protection

This item will include all costs for time and materials necessary to fabricate and install the required

well protection specified in the scope of work. This protection will consist of 11 water-tight flush-mount

protective covers installed in a 3-foot diameter circular concrete pad. The concrete pad will be conical in

shape (pointing downward) and extend to the top of the annular grout (3-foot bgs). The pad will extend

1 inch above surface grade and slope gradually away from the center to avoid pooling of surface water.

The top of all monitoring well casings will left approximately 6 inches below the well protector cover and

covered with a temporary water-tight locking cap. The flush-mount protectors will be securable and the

monitoring well caps will have identically keyed locks. Payment will be made at the per well rate as bid.

BLM/JG/LKS- 3 1583LMTZXX/0007002/exhibit 1 /F

Page 27: Statement of Work: Drilling, Sampling & Monitoring Well ...

Item 13. Well Development

This item will include all time and equipment necessary to properly develop each monitoring well.

Wells will be developed until deemed acceptable by E & E based on the criteria described in section 4.6.

Payment will be made for the development at the per well rate as bid.

Item 14. Decontamination Time

This item will include all charges for time and equipment (including rented equipment) necessary to

decontaminate drilling equipment after drilling die first boring, and on each occasion when drilling equip­

ment is moved to a new boring location. Decontamination procedures are specified in section 4.8.

Payment will be made at the hourly rate as bid.

Item 15. IDW Collection/Containerization

This item includes all time and materials required to collect and containerize all those materials

developed in connection with the work described in the specifications and deemed by E & E to be

suspected/known hazardous materials. This item also includes the cost of a 500-gallon or more poly tank.

The drilling subcontractor will retain possession of the tank at the end of the project. The materials not

deemed hazardous by E & E do not have to be collected or disposed of off site. Potentially hazardous

wastes will be segregated according to liquid/sludge or solid phases. It is anticipated that drilling spoils

associated with the drilling and installation of the 11 monitoring wells will be collected temporarily in

disposable plastic sleeves and presented to the on-site E & E geologist for logging and sampling.

Following logging, the sleeves will be emptied into a 55-gallon drum. The poly tank will be required for

containerization of development water.

The subcontractor shall provide drums meeting the requirements of 49 CFR Part 173. The

subcontractor must provide an estimate of the number 55-gallon steel drums required. The subcontractor

may be required to provide additional 55-gallon drums as needed. Payment will be made at the per drum

rate as bid.

\Item 16. Carbon Filtration Drum/System

This item includes the cost of a carbon filtration drum/system to be provided by the subcontractor. The

subcontractor will be responsible for pumping all containerized drilling, decontamination, and development

BLM/JG/LKS. 4 1583LMTZXX/0007002/exhibit 1 /F

Page 28: Statement of Work: Drilling, Sampling & Monitoring Well ...

water from the drums through the carbon filtration drum. Additional containerization requirements, if any,

shall be determined by the E & E field project manager.

Item 17. IDW Handling

This item includes all costs, equipment, and time to move IDW drums from the well locations to a

designated on-site area(s) and to pump IDW water through the carbon filtration drum/system. Payment

will be at the hourly rate as bid.

Item 18. Delay Time

If work by the subcontractor is delayed for more than 30 minutes as a result of action by E & E, the

subcontractor will be entitled to reimbursement for each delay ^^^^S^^^BuMtes. Both the subcontr­

actor and E & E will jointly record and verify any such instances and the time involved in excess of 30

minutes. At the project completion, the subcontractor will be paid for the accumulated totals of these

delays. Payment will be at the hourly rate as bid. This payment does not include time for difficult moving.

Item 19. Difficult Moving Time

This item will include only charges for time iiffillllt'-of'■3'0^nu©s§equired to move equipment on

and off specific boring locations where access is judged to be more difficult than normally encountered.

Such instances must also be jointly recorded by the subcontractor and E & E. Payment will be at the

hourly rate as bid.

Item 20. Dedicated Bladder Pumps

This item will include all time and materials necessary for providing and installing 11 dedicated, QED

Environmental Systems, Inc., stainless steel bladder pumps with stainless steel inlet screen, and associated

equipment. This equipment includes the necessary length of bonded Teflon-lined polyethylene tube (%-

inch discharge tube, 14-inch air supply tub) and 2-inch sealing well cap with sample discharge adaptor.

BLM/JG/LKS™ 5 1583LMTZXX/0007002/exhibit 1/F

Page 29: Statement of Work: Drilling, Sampling & Monitoring Well ...

ECOLOGY & ENVIRONMENT, INC.Cloverleaf Building 3, 6405 Metcalf Avenue, Overland Park, KS 66202

Phone: 913.432.9961; Fax: 913.432.0670

TELEPHONE CONVERSATION RECORD

DATE OF CALL:TIME OF CALL: COMPANY:PERSON CONTACTED TITLE:SUBJECT OF CALL: TELEPHONE #:

August 1,2000 14:45Boart Longyear Mark Prueher Operations Manager Dedicated Bailers (320) 632-6552

FAX#:CONVERSATION NOTES:

Larry Baer had requested, earlier in the day, that a bid item for dedicated (non­disposable) Teflon bailers be determined in case they were needed. The bailers would replace QED pumps if the formation materials were such that the wells would yield low amounts of ground water to the extent that micro-purging would be impossible. Prueher quoted a price of $327.50 per bailer.

SIGNATURE: DATE: S — ^W:\SHARE\0007\0007-002\TCR_01.WPD

Z+ooa

Page 30: Statement of Work: Drilling, Sampling & Monitoring Well ...

t BID SHEET

FOR DRILLING, SAMPLING, AND INSTALLATION OF MONITORING WELLSLemars Coal Gas Site—Lemars, Iowa

TDD: S07-9906-013 PAN: 1277TSTZXX

BidItem

DescriptionUnit Price

($)EstimatedQuantities

Totals ($)

1 Mobilization & Demobilization 15,950 Lump Sum 15,950

2 Rotosonic Drilling / Sampling (4-inch x 6-inch) 3QL.F. 920 L.F. 27,600

3 Override casing (8-inch) 15L.F. 426 L.F. 6,390

4 Override casing (9-inch) 21/L.F. 406 L.F. 8,526

5 Override casing (10-inch) 29/l.f. 141 L.F. 4,089

6 PVC casing 6/L.F. 795 L.F. 4,770

7 Stainless steel screen 34/L.F. 125 L.F. 4,250

8 Filter pack 8/L* F. 171 L.F. 1,368

' 9 Buffer Sand 8/L.F. 11 L.F. 88

10 Bentonite chip seal 20/L.F. 60 L.F. 1,200

11 High-solids bentonite slurry grout 6/L.F. 662 L.F. 3,972

12 Surface protection 200 /well 11 wells 2,200

13 Well Development 250/well 11 wells 2,750

14 Decontamination time 100 /Hr. 40 Hrs. 4,000

15 Waste Collection/Containerization* 40 /55-gal. drum 35 drums 1,400

16 Carbon filtration drum/system 850 /drum 1 drum 850

17 1DW handling 100 yHr. 30 Hrs. 3,000

18 Delay time 400 /Hr. 8 Hrs. 3,200

19 Difficult moving time 400 /Hr. 4 Hrs. 1,600

20 Dedicated bladder pumps (29) 1,700PumP 11 pumps 18,700

Total Bid Add Items 1 through 20 -------------------------------- -— Cl 1 l.cim

State Water Well Installers License Number: 40018

COMPANY:

Boart LongyearP.O. Box 355Little Falls, MN 56345

TELEPHONE NUMBER:

320-632-6552

SIGNATURE/TITLE OF AUTHORUS^D CO^RANY REPRESENTATIVE:

------- -Mark Prudher, Operations Manager

DATE:

7-20-00

BLM/JG/LKS- 9-6 125 lLMSRXX/9905004/driUing/drillsub/F

Page 31: Statement of Work: Drilling, Sampling & Monitoring Well ...

APPENDIX A

Figures 1-4

BLM/JG/LKS— A 1583LMTZXX/0007002/exhibitl/F

Page 32: Statement of Work: Drilling, Sampling & Monitoring Well ...

2000 2000 4000 Feet

PlymouthCounty

Him.. , miii i n u-h

KEY TO COUNTIES

LeMars Coal Gas Site LeMars, Iowa

TDD: S07-9905-004 PAN: 1251LMSRXX

Prepared by B. Barron July 2000

ecology and environment, inc.

OvEWAt® PMK. KAh&ASSource: USGS 7 5' Tooo

LeMars. (A. 1985.

LEMARS,APRFigure 1: Site Location Map

Page 33: Statement of Work: Drilling, Sampling & Monitoring Well ...

Le Mars Coal Gas Site TDD: S07-9905-004Le Mars, Iowa PAN: 1251LMSRXX

ecology and environment, inc. Prepared by STM L.J.BaerJune 2000

hydro.cdr Sdurce: Munter. 1983; Wahl. 1982.

Figure 3: GENERAL GEOLOGIC/HYDROGEOLOGIC COLUMN

Page 34: Statement of Work: Drilling, Sampling & Monitoring Well ...

SHALLOWWELL

INTERMEDIATEWELL

DEEPWELL

Ground Surface

High-Solids Bentonite Grout

2" Sch. 40.PVC Casing

Bentonite Chip Seal

Filter Pack(2' Above Screen) K*®'

■y

V

•'•'v

• » 0 .

\ C •'

' »>.

C i'^’• 1 ✓

» > , '

S'..-.!15'Type 304 Continuous

Wrap Ss Screen

Threaded Bottom Cap

High-Solids__Bentonite Grout

2" Sch. 40

High-Solids Bentonite Grout1; :'.vT

3-feet Bentonite Chip Seal

Unconfined Sand and Gravel Aquifer

* • \ * »1

Threaded Bottom Cap

Confining Layer ' '

Confined Sand and Gravel Aquifer

Not To Scale

3-feet Bentonite 'J

Chip Seal

Filter Pack (5'Above Screen) j^g’

Iff Type 304. Continuous

Wrap Ss Screen

Threaded Bottom Cap

LeMars Coal Gas Site LeMars, Iowa

ecology and environment, inc.

TDD: S07-9905-004 PAN: 1251LMSRXX

Prepared by B. Barron July 2000

MW-PVC.CDRFigure 4: PROPOSED PVC MONITORING WELL CONSTRUCTION DIAGRAMS

Page 35: Statement of Work: Drilling, Sampling & Monitoring Well ...

APPENDIX B

Levels of Protection Guidelines

\

APPENDIX B LEVELS OF PROTECTION GUIDELINES

BLM/JG/LKS— B 1583LMTZXX/0007002/exhibitl/F

Page 36: Statement of Work: Drilling, Sampling & Monitoring Well ...

LEVEL A

1. MSA 401 self-contained breathing apparatus

2. East Wind CP2000 encapsulating suit

3. White cotton coveralls

4. Cotton underwear

5. Surgical gloves

6. Neoprene boots with steel toe and shank

7. Butyl rubber or PVC booties

8. Disposable gloves* (additional pair)

9. Disposable booties* (additional pair)

10. Hard hat*

11. Cool pack*

LEVEL B

1. MSA 401 self-contained breathing apparatus

2. Butyl rubber apron, ankle length with sleeves

3. Butyl rubber of neoprene gloves

4. Surgical gloves

5. Neoprene boots with steel toe and shank

6. Butyl rubber booties

7. Chemical-resistant coveralls

8. Cotton underwear

9. Disposable booties* (additional pair)

10. Disposable gloves* (additional pair)

11. Hard hat with face shield*

BLM/JG/LKS-. B-l 1583LMTZXX/0007002/exhibitl/F

Page 37: Statement of Work: Drilling, Sampling & Monitoring Well ...

LEVEL C

1. MSA Ultra-Twin cartridge respirator

2. Robertshaw escape mask

3. Butyl rubber gloves

4. Butyl rubber apron, ankle length with sleeves

5. Surgical gloves

6. Neoprene boots with steel toe and shank

7. Butyl rubber booties

8. Chemical-resistant coveralls

9. Cotton underwear

10. Disposable booties* (additional pair)

11. Disposable gloves* (additional pair)

12. Hard hat with face shield*

LEVEL D

1. Cotton coveralls

2. Cotton underwear

3. Safety boots/shoes

4. Safety glasses

5. Hard hat with optional face shield

6. Ultra-Twin cartridge respirator (readily available)

7. Robertshaw escape mask (readily available)

8. Work gloves

NOTE: E & E guidelines may at times exhibit minor modifications to U.S. EPA criteria. * Optional

BLM/JG/LKS,. B-2 1583LMTZXX/0007002/exhibitl/F

Page 38: Statement of Work: Drilling, Sampling & Monitoring Well ...

1. MSA Ultra-Twin cartridge respirator

2. Robertshaw escape mask

3. Butyl rubber gloves

4. Butyl rubber apron, ankle length with sleeves

5. Surgical gloves

6. Neoprene boots with steel toe and shank

7. Butyl rubber booties

8. Chemical-resistant coveralls

9. Cotton underwear

10. Disposable booties* (additional pair)

11. Disposable gloves* (additional pair)

12. Hard hat with face shield*

LEVEL D

1. Cotton coveralls

2. Cotton underwear

3. Safety boots/shoes

4. Safety glasses

5. Hard hat with optional face shield

6. Ultra-Twin cartridge respirator (readily available)

7. Robertshaw escape mask (readily available)

8. Work gloves

NOTE: E & E guidelines may at times exhibit minor modifications to U.S. EPA criteria.

LEVEL C

* Optional

BLM/JG/LKS... B-2 1583LMTZXX/0007002/exhibitl/F

Page 39: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS /

Rotosonic Drilling Daily 'LEMARS COAL GAS SITE-LEMARS, IOWA T»JLA&AajaX

1 TDD: S07-0007-002/PAN: 1583LMTZXX * f

1 Date: ^ ^ O

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum 1j

' 2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. 9 In L F

3 Override casing (8-inch) $ 15 /L.F. 'z.Li lf. SCO-

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F. "

8 Filter pack sand $8 /L.F. L.F-.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

1. 15 Waste Collection/Containerization ^ p \ $ 40 /55-gal. drum drums 3*0

Carbon Filtration Drum/System $850 /drum f drums

17 IDW Handling $ 100/per hr . hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals: 12,1^

Totals to Date: ix,29r

§ of gallons of water used for each well:

Comments7m |ow<f 4yoiQr>

Page 40: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

- LEMARS COAL GAS SITE-LEMARS, IOWA1 TDD: S07-0007-002/PAN: 1583LMTZXX '

Date: £> " ? ~ 2. <5 OO

Bid Item | Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. G>Z. ^l.f. WSjx>-

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. 13C? l.f.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. ZC> L.F. CZK-

8 Filter pack sand $8 /L.F. ZAtS L-F.

9 Buffer sand $8 /L.F. | L.F.

10 Bentonite chip seal $20 /L.F. A.S L F-

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection ^ $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

L 15 Waste Collection/Containerization $ 40 /55-gal. drum f drums qo

|hr- Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals: 3 £<1- !

Totals to Date:is'Vh-

>------------

ft of gallons of water used for each well

• j t^foO cjjb {To 4ftu'<fer)

rig *iOiiit, (£3DRILLER: GEOLOGIST:

Comments:.

Page 41: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

. LEMARS COAL GAS SITE-LEMARS, IOWA Ttu^rzJU^1 TDD: S07-0007-002/PAN: 1583LMTZXX ' \

| Date: 8~l0~ZC><=>O

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. ST/ L.F.

_____3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. / / L.F. a

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. 15~ L.F. 5io

8 Filter pack sand $8 /L.F. 13 LF- "D1?

9 Buffer sand 1 $8 /L.F. ( L.F.

10 Bentonite chip seal $20 /L.F. Zfc L.F. )4&

11 High-solids bentonite slurry grout $ 6 /L.F. m lf

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. _2J hrs. 3 on

1, 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr.. Z. 5“hrs-

18 Delay Time $ 400 /per hr. f hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

ft of gallons of water used for each well:30 vats To MaJ-ZS

Page 42: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWA n.1 TDD: S07-0007-002/PAN: 1583LMTZXX ^

| Date: 8 ~( ( ~ 2.0 0 O

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) . $ 30 /L.F. / Z sr l.f. 3 QTo-

3 Override casing (8-inch) $ 15 /L.F. 5rsr l.f.

4 Override casing (9-inch) - ' $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

h 15 Waste Collection/Containerization $ 40 /55-gal. drum drums 220

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals: ^ ?ST—-4----- ,----------

Totals to Date:

§ of gallons of water used for each well:

Page 43: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

k LEMARS COAL GAS SITE-LEMARS, IOWAB TDD: S07-0007-002/PAN: 1583LMTZXX

| Date: & ~ ."&&& &Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $21/L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. loo L.F.loo—

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. ZO L.F- G&o-8 Filter pack sand $8 /L.F. Z. L.F.

T-

9 Buffer sand $8 /L.F. / L.F. ?~

10 Bentonite chip seal $20 /L.F. 3 L.F.

11 High-solids bentonite slurry grout $6 /L.F. 9O L-F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. /. -to- (To

It 15 Waste Collection/Containerization $ 40 /55-gal. drum drums Hohr-Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. ) ^ hrs. Tot?

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals: <2 90 (r

Totals to Date:

«

tt of gallons of water used for each well:_

7GO (^2 Yb ^0 f afeep

„,r.. KfiiGEOLOGIST:

'V

1

Page 44: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWA <,1 TDD: S07-0007-002/PAN: 1583LMTZXX

d*8-/J“Iooo

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. /6 £ l.f.

3 Override casing (8-inch) $ 15 /L.F. T 7 L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. 75 L.F. 4 it-7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. IO L.F.

8 Filter pack sand $8 /L.F. /£> L F 12 f-

9 Buffer sand $8 /L.F. Z. L.F. 16'10 Bentonite chip seal $20 /L.F. 2,0 L.F. Mod-

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development M. uJ> - 1 D $ 250 /per well [ wells <25o

14 Decontamination Time $ 100 /per hr. • ■S’ hrs. To

k 15 Waste Collection/Containerization $ 40 /55-gal. drum 2. drums ?6

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. 3. ^ hrs-3S"C>

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date: 33.

# of gallons of water used for each well: C? & & ^ 3 t ( (It O Cj MttJ

(lou>er AnoS-fer } ._____ ____________

RIG Sot'i ^>6 DRILLER:- GEOLOGIST:,OLfl-/v

Comments:

Page 45: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

. LEMARS COAL GAS SITE—LEMARS, IOWA .i TDD: S07-0007-002/PAN: 1583LMTZXX

| Date: (4 - 2-© O O

Bid Item Description Unit Price CostQuantities | Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-irich by 6-inch) 9 $ 30 /L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing 'f'f ( 5T $ 6 /L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen | Q $ 34 /L.F. /O LF. 340—

8 Filter pack sand }A - A? $8 /L.F. L F. 1

9 Buffer sand / . $8 /L.F. / L.F.

_________10 Bentonite chip seal 5 $20 /L.F. S LF- joo-

11 High-solids bentonite slurry grout (ob(c>b') +■ 3-5 C^JAj $6 /L.F. 99 LF

12 Surface Protection $ 200 /per well wells

13 Monitoring well development fA (AJ i C £, iO A- $ 250 /per well '2* wells

14 Decontamination Time $ 100 /per hr. 3, & hrs.

1, 15 Waste Collection/Containerization 3- $ 40 /55-gal. drum drums ?o-H-

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

ft of gallons of water used for each well:_ ggs oa.L rf.O QSeef d»\(('nc^ tfttf-Z.JT.

Rir. 1 f, lDRILLER: GEOLOGIST:.

Comments:.

Page 46: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWA To-^StJU^1 TDD: S07-0007-002/PAN: 1583LMTZXX '

Date O OBid Item Description

Unit Price Cost | Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) 4 4 , +" ?- 0? $ 30 /L.F. 7-2. L F-

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing 3 <L + e> f , c fc. u p $ 6 /L.F. 3Z. L.F. m—7 2-inch, 15-slot, Type 304 stainless steel screen / 0 $ 34 /L.F. lO L.F. 3 Ho—

8 Filter pack sand / 3 $8 /L.F. 13 L.F. It 4-

9 Buffer sand 1 $8 /L.F. / L.F. g-

10 Bentonite chip seal / . 5” f- 3.5> $20 /L.F.S’ L.F.

loo-

11 High-solids bentonite slurry grout cL. Q> $6 /L.F. L.F.

12 Surface Protection ^ p +" f b f- l S +• 5*4^“ $ 200 /per well wells 700—

13 Monitoring well development $ 250 /per well J wells j2To-

14 Decontamination Time $ 100 /per hr. “2, hrs- 3.6D—

lit 15 Waste Collection/Containerization $ 40 /55-gal. drum drums ■fra-

1 16 Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. S’ hm.

18 Delay Time $ 400 /per hr. / < ^ hrs. ^<50 —

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals: 5

Totals to Date: ,1 :—

§’

# of gallons of water used for each well

3oo c^^/s used - Z-X.

RIG: 9>GEOLOGIST:

Comments:

Page 47: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

. LEMARS COAL GAS SITE-LEMARS, IOWAm TDD: S07-0007-002/PAN: 1583LMTZXX 1

Datt: 8-/6-2000

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $" c. t 2- $ 30 /L.F. LF

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F. 1

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing ^Oo ~f if $ 6 /L.F. L.F. YX'h-

7 2-inch, 15-slot, Type 304 stainless steel screen 2.-5? $ 34 /L.F. Z S' L.F. TO& —

8 Filter pack sand / j- / 0> _ y 4- ! -T j $8 /L.F. 34 L.F.

9 Buffer sand 2- $8 /L.F. Z L F- ^t>-

10 Bentonite chip seal / k < S f" 2- $20 /L.F. /^^l.f. 3<=TO-

11 High-solids bentonite slurry grout 3 2- $6 /L.F. 3Z L.F.

12 Surface Protection MlO • ^*0 /^l(0 ^ $ 200 /per well 3 wells

13 Monitoring well development /'/l (A-) 1 ^ $ 250 /per well | wells 2^

14 Decontamination Time $ 100 /per hr. 7 hrs.

k 15 Waste Collection/Containerization Z- $ 40 /55-gal. drum drums ?6~

f Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. 7- hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals: ST?^-

Totals to Date:

# of gallons of water used for each well:_ „»/c -M* 0 os A ~f'<> fac^^(s for AtO-4JI________________________________

3 :J>RIG:. Ofuo

&

iZo 8 drille; GEOLOGIST:

Comments:

Page 48: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE—LEMARS, IOWA | TDD: S07-0007-002/PAN: 1583LMTZXX

1 Date: ^ & °

Bid Item DescriptionUnit Price Cost | Quantities

Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F. 1,

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. 3 'O L.F. | ?o

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. \ 5" l.f. 5*10

8 Filter pack sand $8 /L.F. ~2_| L.F. 16?9 Buffer sand $8 /L.F. _J_10 Bentonite chip seal $20 /L.F.

| o l.f.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. I.S^ hrs- I'dO

II 15 Waste Collection/Containerization $ 40 /55-gal. drum | drums MoH-

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700/pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

§ of gallons of water used for each well:___2^ ---- 4a——(o J> v_

RIG:SxQ/Ut' ) 5~

DRILLER: GEOLOGIST:

Comments:.

G T ^CiMirv^ * 1 ) \jLtar, "Op f ? <j Vf o ^ ^T-SLvId^S

5^1-Pf U-lorfo

Page 49: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWA1 TDD: S07-0007-002/PAN: 1583LMTZXX

Date: Q 00

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. OH. S’ L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. ZS L.F. T*ro-

8 Filter pack sand $8 /L.F. 3.\r l.f. Zi*

9 Buffer sand $8 /L.F. L.F. 1C

10 Bentonite chip seal $20 /L.F. Z. j L.F. 42 o

11 High-solids bentonite slurry grout $ 6 /L.F. 57 L.F. 3\T-

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. \ .5 hrs- 1*°

u 15 Waste Collection/Containerization $ 40 /55-gal. drum 3 drums \2 op-

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. | hrs. io-o

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

«

ft of gallons of water used for each well:_

RIG: Vo/lid- f*r

CrrotJ'i- fy\^&>£- (^Vcl-Ioa cXilj I. •** 5 \t> c >/***Comments:

Page 50: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWA l TDD: S07-0007-002/PAN: 1583LMTZXX

Date: OO

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. ins' lf-

3 Override casing (8-inch) $ 15 /L.F. £>4 l.f. W

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. I L F. <7 TO-

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. (2_0 L.F. (CK>-

8 Filter pack sand $8 /L.F. "2. S L F-

9 Buffer sand $8 /L.F. | L.F.

10 Bentonite chip seal $20 /L.F. ^5 L.F. |0D-

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well ^ wells

14 Decontamination Time $ 100 /per hr. Z.T hrs.

L 15 Waste Collection/Containerization ^ c $ 40 /55-gal. drum drumshr-

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. 3 hrs- 3<3t>

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals: a?-

Totals to Date:

t

# of gallons of water used for each well:"7 QQ

RIG: %-ant.L. 1DRILLER u

GEOLOGIST^^^-d^V

Comments

t

• brt\\ Sa-i- v^il\ -V>> &U.1 S^ *, £k\/3 Vo cWi*.<^ Uos-^^ g^-t/uA -t>^ r\f^

Acovi _________________________::

Page 51: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWA1 TDD: S07-0007-002/PAN: 1583LMTZXX

Date: Y-W-OO

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. C

8 Filter pack sand $8 /L.F. 1 l.f. ?9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. II4

12 Surface Protection $ 200 /per well wells 1200-

13 Monitoring well development $ 250 /per well ^ wells

14 Decontamination Time $ 100 /per hr.~~gj

k 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

r 16 Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. jO hrs ^60 -

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date: ’ll o'tz-

# of gallons of water used for each well: i

RIG • /S'DRILLER -s///4. GEOLOGIST:

Comments. fj\ wj~~~J<y<?<A- j C>Ac.

t

Page 52: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWA1 TDD: S07-0007-002/PAN: 1583LMTZXX

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization ^ J fO "frwx $ 15,950 Lump sum t}o2^

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6/L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well 1 wells l*o-

14 Decontamination Time $ 100 /per hr. <0'S frs- so-

L 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. Z hrs- j.at>

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump !~L- pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals: 29 <\z*

Totals to Date: (r i oo, on

-t3 <J JZ0_

it of gallons of water used for each well:_

100 1.3*7

RIG: /*?&!)DRILLER

Comments:. &

GEOLOGIST

Page 53: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE—LEMARS, IOWA1 TDD: S07-0007-002/PAN: 1583LMTZXX

Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $34 /L.F. L.F.

8 Filter pack sand $ 8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

r 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

y i6 Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

t

§ of gallons of water used for each well:.

RIG: DRILLER: GEOLOGIST:

Comments:

Page 54: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWATDD: S07-0007-002/PAN: 1583LMTZXX

Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) - $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $29/L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

> 15 Waste Collection/Containerization $ 40 /55-gal. drum drums1 16

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

# of gallons of water used for each well:

RIG: DRILLER: GEOLOGIST:

Comments:

Page 55: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

k LEMARS COAL GAS SITE-LEMARS, IOWAB TDD: S07-0007-002/PAN: 1583LMTZXX

Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $ 8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

u 15 Waste Collection/Containerization $ 40 /55-gal. drum drumshr-

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

§ of gallons of water used for each well:

RIG:_____________________ DRILLER: GEOLOGIST:

Comments:

Page 56: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE—LEMARS, IOWA TDD: S07-0007-002/PAN: 1583LMTZXX

Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

15 Waste Collection/Containerization $ 40755-gal. drum drums

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

# of gallons of water used for each well:

RIG: DRILLER: GEOLOGIST:

Comments:

Page 57: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

. . LEMARS COAL GAS SITE-LEMARS, IOWAi TDD: S07-0007-002/PAN: 1583LMTZXX

Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

t 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

# of gallons of water used for each well:

PTC: DRTT.T.F.R: GEOLOGIST:

Comments:

r

i •

Page 58: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Dailyk LEMARS COAL GAS SITE—LEMARS, IOWA■ TDD: S07-0007-002/PAN: 1583LMTZXX

1 Date:

Bid Item |Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) . ( $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

It 13 Waste Collection/Containerization $ 40 /55-gal. drum drums

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

I

it of gallons of water used for each well:

RTfi* TYRTT TER- GEOLOGIST:

>i:

Page 59: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWA1 TDD: S07-0007-002/PAN: 1583LMTZXX

1 Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. l.f:

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

1 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

p“Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to.Date:

§ of gallons of water used for each well:

RIG: DRILLER: GEOLOGIST:

Comments:

Page 60: Statement of Work: Drilling, Sampling & Monitoring Well ...

IfDAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

\

Rotosonic Drilling Daily

LEMARS COAL GAS SITE-LEMARS, IOWATDD: S07-0007-002/PAN: 1583LMTZXX

Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

k 15 Waste Collection/Containerization $ 40 /55-gal. drum drumshr-

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

# of gallons of water used for each well:

RIG: DRILLER: GEOLOGIST:

Comments:

Page 61: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

k LEMARS COAL GAS SITE—LEMARS, IOWAB TDD; S07-0007-002/PAN: 1583LMTZXX

| Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

Ilk 15 Waste Collection/Containerization $ 40 /55-gal. drum drumspr-

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

# of gallons of water used for each well:

RIG: DRILLER: GEOLOGIST:

Comments:

Page 62: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

k LEMARS COAL GAS SITE-LEMARS, IOWAB TDD: S07-0007-002/PAN: 1583LMTZXX

1 Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 . 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

k 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

hr- Carbon Filtration Drum/System $850 /drum ' drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700/pump pumps .

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

I

# of gallons of water used for each well:.

RIG: DRILLER: GEOLOGIST:

Comments:

Page 63: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

^ LEMARS COAL GAS SITE-LEMARS, IOWAM TDD: S07-0007-002/PAN: 1583LMTZXX

Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8. Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

, 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

it of gallons of water used for each well:

RIG: DRILLER: GEOLOGIST:

Comments:

Page 64: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

k LEMARS COAL GAS SITE-LEMARS, IOWA» TDD: S07-0007-002/PAN: 1583LMTZXX

[ Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /L.F. L.F.

3 Override casing (8-inch) $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

It 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

Carbon Filtration Drum/System $850 /drum drums

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

# of gallons.of water used for each well:.

RIG::' DRILLER: GEOLOGIST:

Comments:

Page 65: Statement of Work: Drilling, Sampling & Monitoring Well ...

DAILY PROGRESS SHEET FOR INSTALLATION OF MONITORING WELLS

Rotosonic Drilling Daily

. LEMARS COAL GAS SITE-LEMARS, IOWAM TDD: S07-0007-002/PAN: 1583LMTZXX

| Date:

Bid Item Description Unit Price Cost Quantities Total $

1 Mobilization/Demobilization $ 15,950 Lump sum

2 Rotosonic Drilling/Sampling (4-inch by 6-inch) $ 30 /l.f; L.F.

3 Override casing (8-inch) - r $ 15 /L.F. L.F.

4 Override casing (9-inch) $ 21 /L.F. L.F.

5 Override casing (10-inch) $ 29 /L.F. L.F.

6 2-inch ID Schedule 40 PVC casing $ 6 /L.F. L.F.

7 2-inch, 15-slot, Type 304 stainless steel screen $ 34 /L.F. L.F.

8 Filter pack sand $ 8 /L.F. L.F.

9 Buffer sand $8 /L.F. L.F.

10 Bentonite chip seal $20 /L.F. L.F.

11 High-solids bentonite slurry grout $6 /L.F. L.F.

12 Surface Protection $ 200 /per well wells

13 Monitoring well development $ 250 /per well wells

14 Decontamination Time $ 100 /per hr. hrs.

^ 15 Waste Collection/Containerization $ 40 /55-gal. drum drums

Carbon Filtration Drum/System $850 /drum drums •

17 IDW Handling $ 100 /per hr. hrs.

18 Delay Time $ 400 /per hr. hrs.

19 Difficult Moving Time $ 400 /per hr. hrs.

20 Dedicated QED Bladder Pumps $ 1,700 /pump pumps

21 Dedicated Teflon Bailer $ 327.50 /bailer bailers

Daily Totals:

Totals to Date:

§ of gallons of water used for each well:

RIG: DRILLER:! GEOLOGIST:

Comments:

t

Page 66: Statement of Work: Drilling, Sampling & Monitoring Well ...

14950 Iris Rd.P.O. Box 355Little Falls, Minnesota 56345 USA Telephone: 320-632-6552 Fax:320-632-2915

Boart Longyear Company Environmental Drilling Division

BOART LONGYEAR CONTRACTING SERVICES GROUP

01/22/01

Ecology & Environment 6405 Metcalf Cloverleaf Building #3 Overland Park, KS 66202

Attn: JeffGadt

Please find the completed well registration forms for the state of Iowa. If you have any

questions please call me at 320-632-6552.

Scott Thalacker Drilling Manager

Page 67: Statement of Work: Drilling, Sampling & Monitoring Well ...

iowa Department of Natural Resources Geological Survey Bureau109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

dd

Site identificationfpertyOwner C.3\/ o £ Ly fti4/S

tddress n C * L

Tenant _ _ _ _ _ _ _ _ _ _ _

Well Number / S

^ ar ■j}>\

Well Depth_ 3 b ft Date completed fi / / 0 / DC)

Location Countv 'f*! \r/ridu4~H

mi. N and s

mi.E of intersection of w

and

1/4 of the S^ 1/4 of the_^£_i/4 of Sec_2_TWp9^_RNG

Show exact location of well in section grid with a dot (•). Sketch map of well location on property.

N

&

1

-4--1

—“--t-_i_

_ J_. _1_

i -j--

E E(A A~P

200 ft

□ upland □ hillside □ valley Elevation (if known).

Formation logFrom To Color Hardness Formation description

5 /

use additional sheets as needed

Remarks (including depth of lost drilling fluids, materials, or tools)

ell use□ Domestic□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial I*) Monitoring□ Other____

(explain)

Drill method □ rotary □ auger Dcable other Go /) . C_

Hole size hole size continued

4,35inch from 0 ft lodb ft _ _ _ _ inch from____ ft to_ _ _ _ ft

_ _ _ _ inch from_ _ _ _ ft to_ _ _ _ ft _ _ _ _ inch from____ ft to_ _ _ _ ft

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

CasingSize^fOD)

Drive

Type / Wt

shoe (yesFraT^; Pitless adapter (yes fjroj)

fVcDepth top

0Depth bottom

1LAmount (length)

±L

Perforated or slotted casing? cyesgftpPerforated / slotted fromft

Perforated / slotted from

to.

to

Casing grouted? (fyeg/no) Placement method ~TVX in ,

Type Depth Top Depth bottom Amount (vol/wt)

6>OyvV. CJk«p* I' t'

Well screen? (yes) no)Slot size Depth Top Depth BottomDiameter

9 //0 a 3b'

Length

IS'Material

ss

Bottom capped no)

Seals / Packers (yes/(rio)

with

kind depth ■ ft

Gravel packed (fye)/ no) from to 3. b fttype ys/ss amount

Well developed? ^j/no^ExDlain ts. w f-'i f ,/)

(pumped, airlifted, bailed) tor-- - - - - ?- - - - - - - - - - - - - - - - - - -

hrs at GPM.

Pump installed? (yes (nop

Installer’s name_ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date

Type of pump Depth to intake _

Pump diameter _ Rated capacity _ GPM

Water information Aquifer: □ sand /gravel □ limestone □ sandstone

Main water-supply zone fromft toft □ seepage well

Static water level / 7. 3S ft above) GL; £cl tape □ airline □ E-line □ estimate

ft below GL;Pumping water level_ _ _

At yield of j.GPM; □ orifice □ volumetric □ estimate

Measurements taken at:(AM / PM) "Date

□ tape □ airline □ E-line □ estimate

Water quality test? (yes (no)

Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested

Contractor j’Sc&.f 4~ n w ^ y -e njf

Address f7C). {So/ C, ftW

Driller V K leu AT ^ f Certification no. 9tj Of

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 68: Statement of Work: Drilling, Sampling & Monitoring Well ...

? _! '

' .,A,,.Towa Department of Natural Resources Geological Survey Bureau $V?T09 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

Site identificationjoperty Owner/5// y <?C Lv Well Number I Q

taress Ai o ( Z t 6 Aut iS-fi u/*- I ^ Y Iv t \>•f-V\

Tenant_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Well Depth / 5<D tt Date completed 9' / 10/ A O

Location County_ "V lyirustsiS

mi. and s

mi.b of intersection of and1/4 of the 6 T- 1/4 of the 56 1/4 of Sec twp9^rngVS e

(w)Show exact location ot well in section grid with a dot (•). Sketch map of well location on property.

N

--h-i -4

--I

I

I_ J. _ __I__

E E<7 C n

200 ft

□ upland □ hillside □ valley Elevation (if known).

Formation logFrom To Color Hardness Formation description

Drill method □ rotary □ auger □ cable other C_

Hole sizeig. Clinch from 0 ft

inch from

to 15^ ft

to ft

hole size continued

inch from

inch from

to.

to

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

CasingSize^iiijfoD)

Drive shoe (yes/no) Pitless adapter (yes / no)

4?Type / Wtfi/e-

Depth top

0Depth bottom

-h&tr/lo l 30Amount (length)

Perforated or slotted casing? (yes<0Perforated / slotted fromft

Perforated / slotted from

to.

to

Casing grouted?Type

4 5o/i

ej/no)

Depth Top

Placement method *T f

A.

Depth bottom

SoAmount (vol/wt)

Well screen? (yes/no)

Diameter

2‘

Slot size

0.0/ SDepth Top

l5o

Depth Bottom

/

Length

So

Material

5 5

Bottom capped £ye^/ no) with

Seals / Packers (yes/fioft kind depthGravel packed ^e|/ no) from ! 5*0 ft to i

type W</55 amount

jtft

Well developed? ([yesy rExplain 5ru_<A

(pumped, airlifted, bailed) for. hrs at GPM.

Pump installed? (yes^njij) Date

Installer's name

Type of pump. Depth to intake.

Pump diameter. Rated capacity. GPM

Water information Aquifer: □ sand /gravel □ limestone □ sandstone

Main water-supply zone from ft toft □ seepage well

Static water level Lb ■C} ftiffieto^ above) GL: j^ltape □ airline □ E-line □ estimate

Pumping water level _

At yield of_ _ _ _ _ _ _

ft below GL; □ tape □ airline □ E-line □estimate

use additional sheets as needed

_ _ _ _ GPM; □orifice □ volumetric □ estimate

Measurements taken at:(AM / PM ) Date.

Remarks (including depth of lost drilling fluids, materials, or tools)Water quality test? (yes/fnoj)

Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested

•ell useD Domest □ Livestoi

Domestic□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial ,B Monitoring□ Other____

(explain)

Contractor r\Address fj$. Sex Driller (AeU k

L-.Hl* PJu n/J 545V<1? \ vh ,XL,1 ftU, 'AyC Certification no.Sid'd!

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 69: Statement of Work: Drilling, Sampling & Monitoring Well ...

. ,i.towa Department of Natural Resources Geological Survey BureauX*' 109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

Site identification

iKldress o C g?ojAd4 ^ 34

ppertyOwner C , Ey n-C 3 Well Number QJ

Tenant

Well Depth_ BA Date completed & / ji / rOQ

Location County_ Z V ff) a u (~K

mi. N and s

mi.E of intersection of - w

and

1/4 of the 6UJ_i/4 of the^E 1/4 of Sec *9 TWP RNG V S j.

Show exact location of well in section grid with a dot (•). Sketch map of well location on property.

N

W

1--h-

1

- A-__ 1__1

_ J_. 1

1

-\-~

__L

_ E E

5*«

i- 200 ft

□ upland □ hillside □ valley Elevation (if known),

Formation log

From To Color Hardness Formation description

use additional sheets as needed

Remarks (including depth of lost drilling fluids, materials, or tools)

*

Hole size

4.3finch from 0 ft toS tSft

inch from to ft

Drill method □ rotary □ auger □ cable other A 1 C

hole size continued

_ _ _ _ inch from _

inch from

_ft to.

ft to

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

CasingSize^DD)

Drive shoe (yes(no)) Pitless adapter (yes /no

■3.01/7Type / WtPUc

Depth top

0Depth bottom

33?Amount (length)

33

Perforated or slotted casing? (yes/<@

Perforated / slotted fromft

Perforated / slotted from

t°_

to

Casing grouted? (yes)/no) Placement method "T/'Ol if

Type Depth Top Depth bottom Amount (vol/wt)

<26. 3

Well screen? (j^/no)

Diameter Slot size Depth Top Depth Bottom

oDIB 35 V3?Length Material

ss

Bottom capped TVe? / no)

Seals / Packers (yes /(no)

Gravel packed (fye~sy no)

with

kind depth ft

from ft to <~l3 ft

type amount

Well developed? <fyes)no^

Explain (~>f < J i-AvU. P(pumped, airlifted, bailed) for hrs at GPM.

Pump installed? (yes Date_ _ _ _ /__ _ _/_ _ _ _

Installer's name

Type of pump Depth to intake ft

Pump diameter. Rated capacity _ GPM

Water information Aquifer: □ sand /gravel □ limestone □ sandstone

Main water-supply zone from _.ft toft □ seepage well

Static water level ^ tt (Treto^ above) GL: IJ^tape □ airline □ E-line □ estimate

Pumping water leveltt below GL: Dtape □ airline □ E-line □ estimate

At yield ofGPM; □ orifice □ volumetric □ estimate

Measurements taken at:(AM / PM) Date / /

Water quality test? (yes^^o})

Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested /. /

fell use

□ Domestic□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial PfMonitoring□ Other_ _ _ _ _

Contractor AyA.oy-p.gL/'

(explain)

Address ,Driller_ R'<

70* T \jQ V _______________________________________

. ISsk L , Hi* b*.jW A1K7 S4>Sl/5~

5 v. / ,. Certification no.34* ~4?/\■a./ iHa

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 70: Statement of Work: Drilling, Sampling & Monitoring Well ...

Iowa Department ot Natural Resources Geological Survey Bureau•<s^’ 109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

Site identification•

operty Owner (f - 14 v C C-p S Well Number 3S

Idress AlU v </- W** fv-vt-r <*3 ,

TenantWell Depth 3 7 ft Date completed ^ /<£3/

County ^ (y AA/i(yVV\ ~

Hole sizeinch from 0 ft to_ _ _ _ ft

inch from .TvV-frf to_ _ _ _ ft

Location

mi. N and s

1/4 of the $ ^ 1/4 of the

mi.E of intersection of w

and^>UJ 1/4 of Sec TWP'7g? RNG S' ^ l

<w)Show exact location ol well in section grid with a dot (•). Sketch map of well location on property.

N

1--h-_i_

--h-_i_

1

--I-1 i 1

E E

h 200 ft

□ upland □ hillside □ valley Elevation (if known).

Formation logFrom To Color Hardness Formation description

*S> ■e.-f

Drill method □ rotary □ auger □ cable other

hole size continued

_ _ _ _ inch from_ __ ft to_ __ ft

_ _ _ _ inch from ft to ft

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

Casing Drive shoe (yes/no) Pitless adapter (yes/no)

Size (iDfoD) | \ Depth top Depth bottom Amount (length)

3.01/1 Wc b 6>H

Perforated or slotted casing? (yes (m)Perforated / slotted fromft

Perforated / slotted from ft

to.

to

Casing grouted? <(yes>o)

Type Depth Top

&e<\V Ck\f <, Ll

Placement method TN-bii ■€_ _ _ _ _ _

Depth bottom Amount (vol/wt)

IfL

Well screen? (ye^no)Diameter Slot size Depth Top Depth Bottom Length Material

3" o.OL 5 an 37 /5' S50:___

Bottom capped rfyes-Ano) with

Seals/Packers (yes/no) kind depth

Gravel packed (yes / no) from ft to ft

type amount

Well developed? jfyes^no) pExplain l7 Cg) <T / IKK^ P

(pumped, airlifted, bailed) for _ hrs at GPM.

Pump installed? <yes(noj)

Installer's name

Date

Type of pump _ Depth to intake _

use additional sheets as needed

Remarks (including depth of lost drilling fluids, materials, or tools)

Pump diameter _ Rated capacity _ GPM

Water information Aquifer: □ sand /gravel □ limestone □ sandstone -

Main water-supply zone fromft toft □ seepage well Static water level -'*?■£ft ((tfejo^)/ above ) GL; □ tape □ airline □ E-line □ estimate

Pumping water levelft below GL; . Dtape □ airline □ E-line □ estimate

At yield ofGPM; □ orifice □ volumetric □ estimate

Measurements taken at:(AM / PM) Date ./. /

Water quality test?Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested / /

fell use□ Domestic□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial ^Monitoring□ Other_ _ _ _ _

Contractor

Address

(_t?Y\T7T~&,

(explain)Driller k • ■e.T"

<?x fU}Ij. 1)5QVi

Certification no. <3L- ft!

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 71: Statement of Work: Drilling, Sampling & Monitoring Well ...

■ •_ ; ;

.^Y Iowa Department of Natural Resources Geological Survey Bureau 109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

Site identification^Property Owner CL- ;4-y <o-C oj s Well Number 31

Address Arli-ev C■*- ibfWeov.

Tenant

Well Depth 50 . K ft

Location County_

Date completed ^ /g?/9 I &C>P lym^t/4- K.

mi. and s

_mi.E of intersection of w

and

1/4 of the 5e_ 1/4 of the ~$UJl/4 of Sec *7 TWP*^?? RNG H £ E

&Show exact location ot well in section grid with a dot (•). Sketch map of well location on property.

N

Drill method □ rotary □ auger □ cable other , c_

Hole sizeb •'dS inch from 0 ft to So A

inch from ft to

hole size continued

_ _ _ _ inch from_

_ _ _ _ inch from

_ft to _

ft to

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

Casing 0 Drive shoe (yes/no) Pitless adapter (yes/no)

Siz^ODfoD)Type / Wt | ■ Depth top Depth bottom Amount (length)

1

-4-- 1...

~r~--t--

1

--I-i

1

-j--

E E5^ /hcay3

h 200 ft

□ upland □ hillside □ valley Elevation (if known)

Formation logFrom To Color Hardness Formation description

5-e P

o Ho. 6 jo* 5

Perforated or slotted casing? (yes^fjoj).

Perforated / slotted from

Perforated / slotted from ft to ft

/Casing grouted? (yesjno). Placement method f /«.* .V

Type Depth Top Depth bottom Amount (vol/wt)/kJkS ef( 6 Vi

Well screen? ^yis)no )Diameter Slot size Depth Top Depth Bottom Length Material

0.Q1S Id -5 So ■€ JO' 350.__

Bottom capped /yfeV no) with • i’UUSeals / Packers (yes /rntj) kind depth

Gravel packed t-fyes/)no) from 56. s ft to

type amount

Well developed? <fyesJ) no) A 'Explain O » u. 0- Vo < lU- fi(pumped, airlifted, bailed) for hrs at GPM.

Pump installed? (yes Date ____/_ /Installer's name

Type of pump Depth to intake tt

Pump diameter Rated capacity GPM

Water information Aquifer: □ sand / gravel □ limestone □ sandstone

Main water-supply zone from ft to ft □ seepage well

s additional sheets as needed

Remarks (including depth of lost drilling fluids, materials, or tools)

Static water level 5? 3 ft fbeio^/ above) GL: Mtape □ airline □ E-line □ estimate

Pumping water level ft below GL: Otape □ airline □ E-line □ estimate

At yield ofGPM; □ orifice □ volumetric □ estimate

Measurements taken at:(AM/PM) Date / /

Water quality test? (yes41^Tested by _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested / /

'ell useDomestic

□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial 0. Monitoring□ Other_ _ _ _ _

Contractor 4~ {L.^-rvVyy C&u(Address_ to. B>*x 355 £1U mDriller t'r\+x k )<&C * ....... "

(explain) Certification no

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 72: Statement of Work: Drilling, Sampling & Monitoring Well ...

> Iowa Department of Natural Resources Geological Survey Bureau109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

Site identificationProperty Owner CL ,• K, „ C k... „ „ a Li. j

^ ¥\m <> Well Number VI[ddress tVlKfy i fa*3"* SeW* <

54-tenant____________ _

Well Depth QL • S' ft Date completed

Location County P l\j{v\A,J 4k.

mi. N and s

1/4 of the f\JUJ_mi.E of intersection of

wand

Drill method □ rotary □ auger □ cable other ‘San ■ C.Hole size

inch from 0 ft to 31 ft

_ _ _ _ inch from ft' to ft

hole size continued

_ _ _ _ inch from

_ _ _ _ inch from

.1/4 of the fr € 1/4 of Sec TWP*?^ RNG *75"

Show exact location of well in section grid with a dot (•). Sketch map ol well location on property.

N

W ~r-

-1--

i -4-

__L

_

i i -4-

__I__

E e

200 ft

□ upland □ hillside □ valley Elevation (if known)

Formation logFrom To Color Hardness Formation description

use additional sheets as needed

Remarks (including depth of lost drilling fluids, materials, or tools)

<&>

CasingSize

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

Pitless adapter (yes / no)

Depth bottomI¥T

Drive shoe (yes/no)

P.dClType / WtToe

Depth top

_6_Amount (length)

io-5

Perforated or slotted casing? (yes<n?|>

Perforated/slotted fromft to

Perforated / slotted fromft to

Casing grouted?/fyej>nType Depth Top

o

Well screen? (^/no)

Placement method _

Depth bottom

/ Cun A.

Amount (vol/wt)

33

Diameter

aSlot size

o .asDepth Top

HOSDepth Bottom

66Length

10 'Material

S5>

Bottom capped ^fy?s> no) with ruUSeals / Packers (yes jfnol) kind depth ftGravel packed £yeSy no) from a ft to ft

type H/ss amount

Well developed? (tjeExplain (rj ( ex r\ H,

S^/no)

___L _P(pumped, airlifted, bailed) for hrs at GPM.

Pump installed? (yes

Installer’s name

(noj) Date / /-

Type of pump Depth to intake ft

Pump diameter Rated capacity GPM

Aquifer: □ sand / gravel □ limestone □ sandstone

ft to _ft □ seepage well

^el[ell useDomestic Livestock Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial fff Monitoring

u Other

Water informationMain water-supply zone from

Static water level gsL ftdljejo^ / above) GL; ^0 tape □ airline □ E-line □ estimate

Pumping water levelft below GL; Dtape □ airline □ E-line □ estimate

At yield of_ _ _ _ _ _ GPM; □ orifice □ volumetric □ estimate

Measurements taken at :(AM / PM) Date / /

Water quality test? (yes//™Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested / J

(explain)

Contractor y _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _Address 7? 0 ■ 8zx ^66 L)UL 6*IL.COOLDriller fYWk K,Ls<«L

Certification no

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 73: Statement of Work: Drilling, Sampling & Monitoring Well ...

' Iowa Department of Natural Resources Geological Survey Bureau-109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

Site identificationoperty Owner c;+V g-C L< 5 Well tyumber_

Ho

,ddressi^iWvo^ /9 ho? ^

TenantWell Depth //7.

Location County_

Date completed ^ / 00

’ ly in

Drill method □ rotary □ auger □ cable other

Hole sizeL> OS inch from 0 ft

mi. N and s

1/4 of the AWmi.E of intersection of

' w1/4 of the

and

St 1/4 of Sec TWP RNG H6 l

Show exact location ol well in section grid with a dot (•). Sketch map of well location on property.

N

<3>

w

--h-i

-,-h-__i__1

i

i 1

E e 5 e-e i

h 200 ft□ upland □ hillside □ valley Elevation (if known)

Formation logFrom To Color Hardness Formation description

6q-e Lo^<>

use additional sheets as needed

Remarks (including depth of lost drilling fluids, materials, or tools)

inch from

hole size continued

_ _ _ _ inch from _

inch from

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

CasingSize(@>D)

Drive shoe (yes/no) Pitless adapter (yes / no)

3.onType/Wt1

Depth top

6Depth bottom

77. *8Amount (length)

7 7. <8

Perforated or slotted casing? (yes£noj)

Perforated / slotted fromft . to _

Perforated / slotted from_ _ _ _ _ _ _ _ _ _ ft to _

Casing grouted? <ye§>no)Type Depth Top

Placement method ~TFf ^

/•f K ODepth bottom

3LAmount (vol/wt)

Well screen? no)Diameter Slot size Depth Top Depth Bottom

Op 1 77<fLength

SSOMaterial

55

Bottom capped (£ye£y no) with /°kW

kind depth ftfrom J 30 ft ,o <7/ fttype HS/SS amount

Well developed? no lExplain 6>Pu v, C„<>__fu <v\ P

(pumped, airlifted, bailed) for _ hrs at GPM.

Pump installed? (yes^noj)

Installer's name

Date

Type of pump _ Depth to intake

Pump diameter _ Rated capacity _ GPM

Water information Aquifer: □ sand /gravel □ limestone □ sandstone

Main water-supply zone fromft to __ _ _ _ _ _ _ ft □ seepage wellStatic water level 4U£. ft (lieiovT) above) GL: Si tape □ airline □ E-line □ estimate

Pumping water levelft below GL; Dtape □ airline □ E-line □ estimate

At yield ofGPM; □ orifice □ volumetric □ estimate

Measurements taken at:(AM / PM) Date//

Water quality test? (yes/noj)

Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested /

ell use□ Domestic□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial ■0 Monitoring'□ Other____

(explain)

Contractor 4~ l-rViA& y*#*Address Pd .B>tK 365 . PlO ODriller k A-U W _____ Certification no. -6f

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 74: Statement of Work: Drilling, Sampling & Monitoring Well ...

# ’

. ;>■ Iowa Department of Natural Resources Geological Survey Bureau109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575 ,

WELL RECORD Permit No.

Site identification*"

d

pertv Owner G',4-y ^ (_<- ____ WellfMumber

dress Mify A-Uy 3 4 if v

HS Hole sizeinch from 0 ft to 3 j ft

Tenant

Well Depth ?> L ■ *7 ft

Location County_

Date completed It / /L> / rOO

-^1v -/n

mi.E of intersection of ~ w

1/4 of the iOuJ 1/4 of the 5 £ 1/4 of Sec_

mi. N and s

’ arid

TWP %. RNG HS

Show exact location ot well in section grid with a dot (•). Sketch map of well location on property.

N

~r~--t--

i i1_ j__

i

1- -L _ __1__

E

200 ft

□ upland □ hillside □ valley Elevation (if known)

Formation logFrom To Color Hardness Formation description

use additional sheets as needed

Remarks (including depth of lost drilling fluids, materials, or tools)

<£>

Drill method vD retary □ auger □ cable other O i C.

inch from ft to

hole size continued

___ inch from _

inch from

_ft to_ _ _ _ ft

ft to_ _ _ _ ft

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

Size <Td70D)

i

Drive shoe

Type / Wt(yes^noj)

PUcDepth topJl

s adapter (yes

Depth bottom

a\.nAmount (length)

5U, 7

Perforated or slotted casing? (yes^

Perforated / slotted \ fromft

Perforated / slotted from ft

to.

to

Casing grouted?rfy%no) Placement method / / ■e m«<1Type Depth Top

o

Depth bottom

n,6Amount (vol/wt)

Well screen?(fyepno)

Diameter Slot size Depth Top Depth Bottom Length Material

o.OhS 91*) /S' <<

0.____

Bottom capped (fyeijnq) Seals / Packers (yes/fncTjl

Gravel packed ^y?sy no)

with

kind depth ftfrom / "7,5 ft to 3 7 ft

tvoe amount

Well developed? d^nao ^Explain I it, wx j-J

(pumped, airlifted, bailed) for _ hrs at GPM.

Pump installed? ( yesijm)Installer's name

Date

Type of pump _ Depth to intake _

Pump diameter _ Rated capacity _ GPM

Water information Aquifer: □ sand /gravel □ limestone □ sandstone

Main water-supply zone fromft toft □ seepage well

Static water level ft((beiow/)above) GL; ^Stape □ airline □ E-line □ estimate

Pumping water level ft below GL: Dtape □airline □ E-line □ estimate

At yield of-GPM; □ orifice □volumetric □estimate

Measurements taken at:(AM / PM) Date _ _ _ _ //

Water quality test? (yes(mT>

Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested _/_ _/_

ell use□ Domestic□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial Monitoring

□ Other _ _ _ _

Contractor,

Address

4~ y aX.0. K* m hLl'-K

(explain)Driller, 6 l i Certification no. ~0 f

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 75: Statement of Work: Drilling, Sampling & Monitoring Well ...

*r•Iowa Department ot Natural Resources Geological Survey Bureau109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

Site identificationOwner CL- »TV r?Vi t cm —■ wen ivurriuer noAlUv J 1^9" 6~f.

;operty Owner CL- 8.4 y Ci ^ Well Number tn

Idress

Tenant

Well Depth_ Q6 5 »

Location

Date completed /c?P /

County P ^ V fi'XoU i^y ~

Hole sizeinch from 0 tt tofe.

___ inch trom .. . It;, to____ tt

mi. N and s

mi.E of intersection of w

and1/4 of the iOtU 1/4 of the 6£_1/4 of Sec*? TWP 7t3 RNG H £1

CyShow exact location ot well in section grid with a dot (•). Sketch map ot well location on property.

N

1

~r~--t-

i1

1

1_ j. _ __ i__

E E

<,t£" MP

200 tt□ upland □ hillside □ valley Elevation (if known)

Formation logFrom To Color Hardness Formation description

6 e g u^<i

Drill method □ rotary □ auger □ cable other >chole size continued

_ _ _ _ inch from____ ft to ft

inch from ft to ft

Record,all depth measurements from ground level (GL). Use (+) for above GL measurements.

Casing Drive shoe (yes / no) Pitless adapter (yes / no)

Size Type/Wt Depth top Depth bottom Amount (length)

O' ■60 72c 6 54-5

Perforated or slotted casing? (yes^

Perforated / slotted fromft to_

Perforated / slotted from

Casing grouted? ^fyeg)' no) Placement method ■ -C.

Type t Depth Top Depth bottom Amount (vol/wt)Mck S A IT

Well screen? (yes / no)

Diameter Slot size Depth Top

cJ0.

36-5Depth Bottom Length

/iTMaterial

55

Bottom capped rfyes)' no) withSeals / Packers (yes(^))

Gravel packed km) no)kind depth ft

from to £ S ft

type te/r* amount

Well developed? <@/no^Explain G> < Q-v\ Cs I p

(pumped, airlifted, bailed) for_ hrs at GPM.

Pump installed? r ves/fto)

Installer's name

Type of pump _

Date ./ /

Depth to intake _

Pump diameter _ Rated capacity _ GPM

use additional sheets as needed

Water information Aquifer: □ sand /gravel □ limestone □ sandstone

Main water-supply zone fromft toft □ seepage well

Static water level 3a-7 ft gfieiow)' above) GL; ^tape □ airline □ E-line □ estimate

Pumping water levelft below GL; Dtape □ airline IDE-line □ estimate

At yield ofGPM; □ orifice □ volumetric n estimate

_ _ _ _ _ _ (AM/PM)Measurements taken at Date ./. ./.

Remarks (including depth of lost drilling fluids, materials, or tools)Water quality test? (ye^fnoj)Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested

fkII useDomestic

□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial 'gf- Monitoring□ Other_ _ _ _ _

(explain)

Contractor V CrU\o* y 'Qa/' to. ho% 5JU f\\)££3tfS

AddressDriller 'CLsU k rtS A "&L Certification no.

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 76: Statement of Work: Drilling, Sampling & Monitoring Well ...

r Iowa Department of Natural Resources Geological Survey BureauK?,' 109 Trowbridge Hall, Iowa City. IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

Site identificationoperty Owner Q.~fy . L <t fr 5 Well ,Number_ £p-

Idress fMWv J V 'A^> fi’-f 1

Tenant

Well Depth_5 5 ft Date completed 55 /V /

Location Countyl_ \j K

mi. N and s

mi.E of intersection of w

and

1/4 of the it) E 1/4 of the_S_UJi/4 of Sec 5 TWP%* RNG S5 E

Show exact location ot well in section grid with a dot (•). Sketch map of well location on property.

N

W

-4--

1.-

1--t-_ _ 1_ _

\

--I-1 1 -5-

1

E E

b200 ft

□ upland □ hillside □ valley Elevation (if known)

Drill method □ rotary □ auger □ cable other 5^n. C

Hole size(4^5 inch from 0 ft .oii«

_ _ _ _ inch from ft to __ ft

hole size.continued

_ _ _ _ inch from____ ft to_ _ _ _ ft

inch from ft to ft

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

Casing Drive shoe (yes/no) Pitless adapter (yes / no)

Size (ID/OD) | Type / Wt | Depth top Depth bottom | Amount (length)

9.0Ln Juc7 U it / &

Perforated or slotted casing? (yes/no^

Perforated / slotted from ■ft to

Perforated / slotted from

Casing grouted?(fyes)no)Type' Depth Top

^ uOrVv SoVl_____ 0

Placement method _ _ _ _ _ _

Depth bottom Amount (vol/wt)

Formation logFrom To Color Hardness Formation description T

kn

5 (~c^ Well screen? <jyes)no)

Diameter Slot size Depth Top Depth Bottom Length MaterialP" o.61 5 If

Bottom capped ('fes)' no)

Seals / Packers (yes/^oj)

Gravel packed (^yes/jio)

with_

kind

4*' /o 55

55depth_

from_

type ^~>/SSft to OP

amount

Well developed? fe^>no) *Explain Qg S / LX-.rvv. yd5?

(pumped, airlifted, bailed) for hrs at GPM.

Pump installed? (yes/^j)Installer's name_ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Type of pump_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date

Depth to intake _

Pump diameter _ Rated capacity _ GPM

use additional sheets as needed

Water information Aquifer: □ sand /gravel □ limestone □ sandstone

Main water-supply zone fromft toft □ seepage well

Static water level ft (ffeiow)' above) GL; ^ tape □ airline □ E-line □ estimate

Pumping water levelft below GL; Dtape □airline □ E-line □ estimate

At yield ofGPM; □ orifice □volumetric □estimate

DateMeasurements taken at . (AM / PM ) / /Remarks (including depth of lost drilling fluids, materials, or tools)

Water quality test? (yes^no)Tested by _ _ _ _ _ _ _ _ _

Date tested /

fell use□ Domestic□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial fiL Monitoring D Other____

Contractor A~~ L^oYXC/^J 4 0^>f.O. L;(4b fidk/WsAVf

A f\ t •» \(explain)

Address

Driller ftV: s k ?55-r M.& Xa/~ Certification no. cOkrtiwhite copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 77: Statement of Work: Drilling, Sampling & Monitoring Well ...

^ Iowa Department of Natural Resources Geological Survey Bureautef 109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

fsit

#Site identification

jperty Ownerd ■ 4- y a C L-e Z*'! S Well Number ^ 1

[dress MUa g?'-A ' 5 3 * 5~F

Tenant_______________________ • ' -'Well Depth 5Li, (t Date completed *7? !} H / OO

Location County h 6U \K__________

Hole size(inch from 0 ft

mi. N and - s

_ _ _ _ _ mi.E of intersection of and;

1/4 of the /O £ 1/4 of the .*$ iy/1/4 of Sec. C? VNP^cH RNG Jn

Show exact location of well in section grid with a dot (•). Sketch map of well location on property.

N---11 - --L-

i

1

-A-

__

1_ 1__L_

1

Drill method □ rotary □ auger □ cable other t C.

inch from:

to £5 ft

ft to •___ ft

hole size continued

_ _ _ _ inch from.

inch from

_ft to_ _ _ Jt

ft to____ ft

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

CasingSize^CD)

Drive shoe (yes/no) Pitless adapter (yes/ no)

3. Dbl

E . E£ ^P

h 200 ft

□ upland □ hillside □ valley Elevation (if known)

Formation logFrom To Color Hardness Formation description

Lx>

3 additional sheets as needed

Remarks (including depth of lost drilling fluids, materials, or tools)

jtell use□ Domestic□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial 0 Monitoring□ Other ___

(explain)

Type / WtJOc

Depth top

6Depth bottom

VV.5Amount (length)

yy.

Perforated or slotted casing? (yes/^o}

Perforated / slotted fromft

_ _ _ _ _ ftPerforated / slotted from

to.

to

Casing grouted? <£ye§>no) Placement method

Type

tlDepth Top

oDepth bottom

3VAmount (vol/wt)

Well screen? (yesjho)Diameter Slot size

i.tf t 5Depth Top

TH5Depth Bottom

Si. 6Length

idMaterial

55

depth_

Bottom capped ^e^/ no) with__

Seals / Packers (yes <55 kind_ _Gravel packed /'f^es / no) from ‘C'V. 5_ _ _ _ _ ft to_ 3f

iS/SS

_tttt

type_ amount

Well developed? ((^no)^Explain P U-w __ /L-cn^P_

(pumped, aidifted, bailed) for_ hrs at GPM.

Pump installed? (yes

Installer's name_ _ _ _ _ _ _ _ _ _

Date

Type of pump. Depth to intake

Pump diameter _ Rated capacity _ GPM

Water information Aquifer: □ sand /gravel □ limestone □ sandstone

Main water-supply zone from_ _ _ _ _ _ _ _ft toft □ seepage well

Static water level 3b ■ ^ ft (beiovjl/ above) GL; tape □ airline □ E-line □ estimate

Pumping water leveltt below GL; □ tape □ airline □ E-line □ estimate

At yield otGPM; 000506 □ volumetric □ estimate

Date/Measurements taken at .(AM/PM) /

Water quality test? (yes/(n<j)

Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested /.

Contractor _______ ;________ ■

Address ?.£>. ibae KH fbs, i(i 5(33^5Driller k i /H a i ^7 (~ Certification no^?fe -€>/

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 78: Statement of Work: Drilling, Sampling & Monitoring Well ...

fowa Department of Natural Resources Geological Survey Bureau109 Trowbridge Hall, Iowa City, IA 52242-1319 PH (319) 335-1575

WELL RECORD Permit No.

Site identification)ertv Owner C.i7y <0^ Well Number 'lO

fU« r Ay 5 ,V.A J tR 'T/a c V$adress

Tenant PI \ m co V h CA. /'A./ Cf/by * cA______Well Depth ■ 5 ft Date completed % / <?H / O 0

~P\\i{v\cU'iP<\Location County_

mi. N and s

1/4 of the

mi.E of intersection of w

and

6 E 1/4 of the 1/4 of Sec7 TWPRNG *7 1

Show exact location ot well in section grid with a dot (•). Sketch map of well location on property.

N---1

- 4- - 1

—“

--t-__i__--I-1 i - j

- -

__i__

E E

Drill method □ rotary □ auger □ cable other 5^/1 <<

Hole sizeA 4? 5 inch from 0 ft

inch from ■ ft'

to !

to ft

hole size continued

___ inch from _

inch from

Record all depth measurements from ground level (GL). Use (+) for above GL measurements.

CasingSizefyD/OD)

Drive shoe (yes / no)

A-667

<5^ ff\&P

200 ft

Type / Wt

T>0 cDepth top

Pitless adapter (yes / no)

Depth bottom

o 5$ • 5Amount (length)196-6

Perforated or slotted casing? (yes^Q>

Perforated / slotted fromft

ftPerforated / slotted from

to.

to

Casing grouted? (fyer^no) Placement method

□ upland □ hillside □ valley Elevation (if known) Type Depth Top Depth bottom Amount (vol/wt)

Formation log iVv^iL o //5From To Color Hardness Formation description

A-e-e kck s Well screen? <ye|)/ no)j

Diameter Slot size Depth Top Depth Bottom Length Material

r?" o jQt_i /ViA 9of 5 5^ ■

o._ _ _, ....... PL V.ZP

donom cappea ^ yesy noj Seals / Packers (yes/5i£)>

Gravel packed ((yes) no)

wuii a wl » ^kind dep

to

th ftfrom / *7 5 ' 5 ft )\1. < ft

tvoe '"i£/S£ amount

Well developed? (yepnow

Explain C>( la. v\ \o ru <h i-< -r - - - - - - - - - - - - - - *£- - - - - - - =- - - f- - - -

(pumped, airlifted, bailed) for hrs at .GPM.Pump installed? (yes/(^ Date//Installer’s name

Tvoe of oumo Depth to intake ft

Pump diameter Rated capacity GPM

Water information Aquifer: □ sand /gravel □ limestone □ sandstone

Main water-suoDlv zone from ft to ft □ seepage wellStatic water level 53 • ^ ftrteioWi/ above) GL; 0tape □ airline □ E-line □ estimate

At vield of GPM □ orifice □volumetric □estimate

use additional sheets as needed Measurements taken at (AM/PM)' Date / _ _/_ _Remarks (including depth of lost drilling fluids, materials, or tools)

ell use□ Domestic□ Livestock□ Test well

□ Municipal□ Public supply□ Irrigation

□ Commercial )Zl Monitoring□ Other_ _ _ _

(explain)

Water quality test? (yes / no)

Tested by_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Date tested

^OaS 7“ JS±Contractor_ _ _ _ _ _ _ _ _ _ _

Address f-Q. fSox K 55 5, f/ U /~kilf$. A7lV) 5437^ Driller C^-duf V ]S t'-fe-/ ►b'ixa, .-e-V Certification noc?L~0}

white copy - Iowa DNR, Geological Survey Bureau blue copy - Well Contractor pink copy - Customer yellow copy - County Health Officer

Page 79: Statement of Work: Drilling, Sampling & Monitoring Well ...

ecology and environment, inc.

Tltto: SOP-HEALTH AND SAFETY ON DRILLING RIG OPERATIONS

Category: H & S, Training 2.7Revised: JANUARY 1990

Approved: H. Van Cleave

STANDARD OPERATING PROCEDURES

FORHEALTH AND SAFETY ON

DRILLING RIG OPERATIONS

REVISED^__J.ANUARY 1990

Prepared by

Ecology and Enviroramnt,^Inc. "‘368'PleasautvievDriye

-I4nca3ter» Nev.Ydrk 14086

*V-

fmtfii -irutiun wntnihmin, | A

'V*

Page 80: Statement of Work: Drilling, Sampling & Monitoring Well ...

1TOe: SOP-HEALTH AND SAFETY ON DRILLING RIG OPERATIONS

u Cateqcor: H & s. training 2.7________. R*v,8ed: JANUARY 1990

None of the information contained in this Ecology and Environment, Inc. (E & E), publication is to be construed as granting any right, by implication or otherwise, for the manufacture, sale, or use in connection with any method, apparatus, or product covered by letters patent, or as insuring anyone against liability for infringement of

letters patent.

Anyone wishing to use this E & E publication should first seek permission of the company. Every effort has been made by E & E to ensure the accuracy and reliability of the data contained in the document; however, the company makes no representation, warranty, or guarantee -in connection with this E & E publication and hereby expressly disclaims any liability or responsibility for loss or damage resulting from its use; for any violation of any Federal, State, or municipal regulation with which this E & E publication may conflict; or for the infringement of any patent resulting from the use of the E & E

publication.

Page 81: Statement of Work: Drilling, Sampling & Monitoring Well ...

CONTENTS

Page

1

2 OPERATION OF DRILL RIG BY E & E PERSONNEL ........... 1

2.1 RESPONSIBILITIES AND AUTHORITY OF SITE

SAFETY OFFICER ..... ............................ 12.2 RESPONSIBILITIES AND AUTHORITY OF E & E DRILLER ... 12.3 RESPONSIBILITIES AND AUTHORITY OF OTHER

E & E PERSONNEL....................................... 3

3 TRAINING REQUIREMENTS FOR SITE PERSONNEL........... 3

3.1 E & E SITE SAFETY OFFICER . ........................... 33.2 E & E DRILLER AND HELPER............................. 43.3 OTHER E & E DRILLING PERSONNEL...................... 43.4 SUBCONTRACT DRILLER AND OTHER SUBCONTRACT DRILLING

PERSONNEL ................................. . ......... 4

4 SUPERVISION OF SUBCONTRACT DRILLERS ...... ......... 5

4.1 RESPONSIBILITIES AND AUTHORITY OF SITESAFETY OFFICER ....................................... 5

4.2 RESPONSIBILITIES AND AUTHORITY OF OTHER

E & E PERSONNEL.......................... 7

5 GENERAL DRILLING SITE SAFETY CHECKLISTS ................. 8

5.1 SAFETY CHECKLISTS FOR SPECIFIC DRILLING ACTIVITIES 85.1.1 General Drilling Site Safety Checklist . ... 85.1.2 Rotary and Core Drilling................ 9

. 5.1.3 Cathead Usage ................................ 105.1.4 Continuous-Flight or Hollow-Stem Augers ... 125.1.5 Use of Vire Line Hoists, Vire Rope, and

Hoisting Equipment ............................ 13

6 REFERENCES..................... :.......... .. ........... 16

Section

1 INTRODUCTION .

iii

tcvciea oaoer INI

Page 82: Statement of Work: Drilling, Sampling & Monitoring Well ...

Title:_SQP-HF.AT.TH AND SAFETY ON DRILLING RIG OPERATIONS

Category;H A Sr TRATNTNC 7-7

Revised:JANUARY 1990

1 INTRODUCTION

This document is meant to be used in conjunction with E & E SOPs for field operations and hazardous waste site operations, and incorporates by reference all the safety precautions required therein. It specifically addresses the functions and responsibilities of

personnel working on or around drilling operations.

E & E personnel are frequently required to work in the field with drill rigs, taking soil and rock samples, installing piezometers, and monitoring wells. Two general situations discussed separately are the supervision of Subcontract Drillers by E & E, and the direct operation of E & E's own drill rig by our personnel.

2 OPERATION OF DRILLING EQUIPMENT BY E & E

2.1 RESPONSIBILITIES AND AUTHORITY OF SITE SAFETY OFFICER

The duties of the Site Safety Officer (SSO) on drilling sites are the same as in other types of operations with the exception of the increased emphasis on the hazards unique to drilling work. This section details specific drilling concerns of an SSO.

E & E personnel are restricted from the borehole area during active drilling. When E & E personnel are doing drilling, they will be restricted from the borehole area by means of a "super exclusion zone" delineated by placing a 4- by 8-foot sheet of plywood over the borehole.

2.2 RESPONSIBILITIES AND AUTHORITY OF E & E DRILLER

At the beginning of each work day, the E & E driller must inspect the rig to ensure the following components have been properly inspected, maintained, or replaced, or procedures have been performed:

o Kill switches tripped and operation verified;

o Chain guards in place; o Belt guards in place; o Belts set to proper tension (visual); o Loose belts;o Presence of any fluid leaks; o Any damaged hoses, cables, ropes, chains; o Control panel is clean; o Control lever functions labeled; o Pressure relief valves function; o Cathead free of rust and grease; o Cathead grooves less than 1/8 inch in depth; o All tools in proper working order; o Rig leveled and stabilized; o Check for weld cracks in mast; and o Safety hooks operational.

1

■ecyciaa saner vumm mm imimimii in

Page 83: Statement of Work: Drilling, Sampling & Monitoring Well ...

■TWe: SOP-HEALTH AND SAFETY ON DRILLING RIG OPERATIONS

Category: H & s> trah^ng 2.7 Revised: JANUARY 1990

The Driller will report items needing attention to the SSO; however, it is the Driller's responsibility to make sure that these items are corrected prior to drilling.

During the drilling operations, the following safety practices will be in effect:

o All wheels will be blocked.

o Rig will be leveled using jacks or stabilizers.

o Rig engine will be in neutral when not actively turning augers.

o Plywood (or suitable substitute material) "super exclusion zone" pad will be in place over borehole.

o Rig engine key will be properly labeled.

o Rig equipment will be kept in an orderly manner within drilling work zone.

o All equipment will be properly lubricated.

o Tools will be used only for their intended purpose.

o Safety glasses, hearing protection will be worn when hammers are operated.

o Jaws of all wrenches will be clean and free of mud to prevent slippage.

o All lift hooks will have jaw clasps.

o Fire extinguisher will be staged at rear of rig.

o Rig will not be moved when mast is in raised position.

o Cables and ropes will be tied back or secured on stabilizer

posts.

o All unattended drill holes will be covered.

o Check for overhead obstructions when raising rig mast, boom will not be raised within 25 feet of overhead utilities.

o No refueling will be permitted while equipment is running.

2

Page 84: Statement of Work: Drilling, Sampling & Monitoring Well ...

Title:S0P-HF.A1.TH AND SAFETY ON DRILLING RIG OPERATIONS

Category:H & S. TRAINING 2.7

Revised:JANUARY 1990

The Driller has authority to direct personnel vithin the area while drilling operations are in progress. Access to the hazardous area around the auger and borehole is restricted by the "super exclusion zone" delineated by the 4- by 8-foot sheet of plywood centered over the borehole before drilling. A large hole cut in the plywood allows

penetration of the augers. No personnel are allowed in this zone pad at any time while drilling is actively underway.

Housekeeping around the rig is the responsibility of the Driller, but all team members must participate in this effort as well.

2.3 RESPONSIBILITY AND AUTHORITY OF OTHER E & E PERSONNEL

E & E personnel working at a drilling site must act as support to the Drilling Team by providing any necessary support functions; however, it is important that personnel are careful not to interfere with the drilling process. Personnel are restricted from approaching the "super exclusion zone" while drilling is underway. If an E & E crew member recognizes an unsafe condition in the work area or on the rig, he should bring it to the attention of the SSO and Team Leader, if it is not resolved in a timely manner. If conditions are still deemed to be hazardous, team members have the option to contact their Regional Safety Coordinator (RSC) or Corporate Health and Safety in Buffalo.

It is the responsibility of all E & E personnel to carry their issued nondisposable gear, including hard hat, face shield, respirator, steel-toed boots, eyepiece inserts, safety glasses, and appropriate outerwear for the expected climate.

All personnel should be aware of emergency facilities, egress routes, and special medical conditions of their team members. As with all E & E field work, the buddy system is to be enforced.

3 TRAINING REQUIREMENTS FOR SITE PERSONNEL

3.1 E & E SITE SAFETY OFFICER

In addition to Basic Health and Safety Training and other OSHA mandated training, first aid, CPR, and necessary training in field monitoring of personnel, an SSO should have previously worked as a team member on field drilling projects in order to have a working knowledge of the drill rig and its inherently hazardous nature. Vhere monitoring instrumentation is to be used, the SSO must be properly trained prior to field work. The SSO must have an understanding of the hazards of heat and cold stress, their associated symptoms, and proper work modifications to protect field staff from potential injury.

recycled caper

3

'■roiotfv nmi ''mimmnriii onopia

Page 85: Statement of Work: Drilling, Sampling & Monitoring Well ...

TWe: SOP-HF.ALTH AND SAFETY ON DRILI„ING RIG OPERATIONS

■- « s. T„»TNTNn 7.. 1Revised: JANUARY 1990 .

3.2 E & E DRILLER AND HELPER

The E & E driller and helper shall have taken and passed the basic 40-hour Health and Safety Training as prescribed by E & E and mandated by OSHA. They shall also meet the other minimum requirements for field work including medical approvals and respirator fit test. Based on previous experience and training, the Driller will be critiqued by the E & E Drilling Team upon employment with E & E, by performing various types of drilling. This review will be the basis for determining whether additional training or apprenticeship will be required before allowing this employee to act as Driller. An existing E & E employee shall have a minimum of 1 year experience as a Driller's Helper on an assortment of field projects before he or she can be reviewed for advancement to the position of Driller. If a Driller is uninvolved in drilling efforts for 1 year or more, he or she will be required to act as a Driller's Helper on a project, as well as receive rig-specific training on the equipment, before being permitted to act as a Driller again. The Driller's Helper position requires prior attendance at a drilling training school program. Following successful completion of such a course, the Driller's Helper will be observed on sites for a period of approximately 6 months, during which time he or she will work on several drilling projects performing assorted types of drilling. The E & E Drilling Team will determine, based on these field observations, whether additional training is required for this individual.

3.3 OTHER E & E DRILLING PERSONNEL

All E & E personnel shall have taken the basic 40-hour Health and Safety Training course. Field personnel must meet medical and respiratory fit test requirements established by E & E and OSHA, as

well.

3.4 SUBCONTRACT DRILLER AND OTHER SUBCONTRACT DRILLING PERSONNEL

Subcontract Drillers and their support personnel must, at a minimum, have passed basic 40-hour Health and Safety Training as prescribed by OSHA 29 CFR1910.120. They shall be medically approved and trained to use the level(s) of respiratory protection required onsite. Certification of training by the Subcontractor shall be required as a deliverable included in E & E's contractual documentation. This training shall be verbally verified and logged onsite by the SSO or Team

Leader before starting work.

Page 86: Statement of Work: Drilling, Sampling & Monitoring Well ...

u

THIa*SOP-HEAT.TH AND SAFETY ON DRILLING RIG OPERATIONS

Cat8q0ry: HAS- TRAINING 2.7________ Revised: JANUARY 1990

4 SUPERVISION OF SUBCONTRACT DRILLERS

4.1 RESPONSIBILITIES AND AUTHORITY OF SITE SAFETY OFFICER

The responsibilities of the SSO at a drilling site where subcontracted drillers are used include the following: rig inspections,

personnel monitoring, and personnel protection.

A rig inspection starts with, but is not limited to, verifying each

item on the following checklist:

o The mast must be located at least 25 feet from any overhead or

underground utility lines.

o The location and operation of operational and unencumbered kill svitches must be reiterated to all site personnel.

o Outriggers, stabilizers, or jacks are in place, and the rig is

level.

o A geophysical survey (electromagnetic or ground-penetrating radar) or a reliable site history must be obtained to verify

absence of buried obstacles, tanks, or drums.

o A first aid kit and filled eyewash must be readily available.

A fire extinguisher should be charged to the proper pressure and

staged at rear of rig during drilling.

o The condition of ropes, chains, and cables must be checked.

o A lifeline or safety belt must be available if mast climbing is

necessary.

o The Site Safety Plan (SSP) must be posted with emergency phone

list and map of hospital route.

o A "super exclusion zone" must be established around theborehole, using a 4- by 8-foot sheet of plyvood. This defined area will be entered during active drilling only by the Driller,

except in emergency situations.

If any of these items need replacement or repair, the SSO must make necessary arrangements and later verify that repair or replacement is sufficient before actual drilling begins. Working together, the SSO and the driller should verify that the rig has been checked against the

Operator's checklist.

5

recycled oaper iiuu nmrnmunii ooanpys

Page 87: Statement of Work: Drilling, Sampling & Monitoring Well ...

Tltla*Sr>P-HF.AI.TH AND SAFETY ON

Cat"q0ry: H & £. TRAINING 2.7

DRILLING RIG OPERATIONS

Revised: JANUARY 1990

The SSO's monitoring duties include calibration and setup of the appropriate monitoring devices, as specified in the SSP. At a minimum, this generally includes an O^/explosimeter and realtime organic vapor monitoring capabilities (e.g., HNU, OVA). Noise monitoring, like heat stress monitoring, is employed where appropriate. If the SSO believes additional monitoring devices beyond the directive of the SSP should be employed (e.g., Rad Mini, Mini Ram), it is his or her responsibility to obtain this equipment with the cooperation of the RSC or the Corporate Health and Safety Group, from the nearest E & E office.

It is the responsibility of the SSO to ensure that all safety equipment is in good working order. Day-to-day operations, as well as calibration data, must be recorded in the equipment log or SSO log. Adequate supplies such as breathing air, drinking liquids, and

calibration gas must be maintained.

E & E personnel are forbidden from entering the "super exclusion zone" around the borehole while the rig is actively drilling. The SSO must not attempt to take air readings in or around the auger while in use, nor are cutting samples taken while the auger is in motion. An O./explosimeter should be set up if possible for unmanned (alarmed) operations at the rig using an extension hose to continuously draw samples from the borehole area during drilling operations.

The SSO has the ultimate authority over the Subcontractor with regard to whether work practices meet the requirements of the SSP. Shutdown of work or restriction of personnel are options available to the SSO. The SSO should hold informal site safety briefings at the start of both field work and daily work shifts throughout the course of the project. Although E & E contractually requires Subcontractors to provide properly' trained and outfitted staff, the SSO should verify verbally at the start-up meeting that the field staff has necessary respiratory approval and OSHA-mandated training, especially on hazardous waste sites. Site safety briefing topics, as well as attendees, will be

recorded in the site safety log.

If the SSO has reason to believe either E & E or Subcontractor personnel are under the influence of alcohol or drugs, or are otherwise ill before or during work onsite, he or she should consider restricting those team members from site work. Personnel arriving for work requiring level C protection who are not cleanly shaved may also be

restricted at the discretion of the SSO.

The following is a list of basic topics to be covered at site

safety meetings:

o Personnel responsibilities;o Planned investigation and presumed potential hazards;o Levels of protection, monitoring plan, and equipment;o Emergency scenario plans, including kill switch use;

6

Page 88: Statement of Work: Drilling, Sampling & Monitoring Well ...

TKto: SOP-HEALTH AND SAFETY ON DRILLING RIG OPERATIONS

Category: H & s> training 2.7 Revised: JANUARY 1990

o Location and operation of kill switches, fire extinguisher, and

first aid kit;o Heat and cold stress hazards;o "Super exclusion zone" around borehole; ando Warnings to Subcontractors about hazards of climbing the mast

vithout safety belt and other equipment.

Because heat stress is a constant threat during warm weather, the SSO is responsible for determining whether conditions are unsuitable for work. Where workers cannot work with the assistance of work modifications, cooling vests, and other cooling means, the SSO may decide that work should not continue. The need for worker monitoring through blood pressure and oral temperature checks will be determined by the SSO with assistance from the RSC and Buffalo Health and Safety

staff, if necessary.

The SSO will be responsible for shutdown of the drilling operation

if electrical storms are in the site area.

No refueling operations will be performed until rig engines are shut down. Hotor fuels should be stored and dispensed from spring-loaded, OSHA/FM-approved gas cans constructed of metal or

polyethylene.

The SSO should ensure and document that no boreholes are left open or unfilled after drilling equipment is moved. In instances where a hole must be left open and unattended, suitable barricades, or the equivalent, will be staged around the hole to prevent personnel and

equipment from falling in.

4.2 RESPONSIBILITIES AND AUTHORITY OF OTHER E & E PERSONNEL

All E & E personnel on site are required to follow the terms of the SSP and the direction of the SSO. Because the SSO cannot be in all places at all times, the crew should observe the subcontractors and condition of their equipment at all times, and report immediately to the Team Leader and SSO any safety-related issues that are unresolved. Included are such details as dressout, site functions, and decontamination. It is important that the SSO be involved so that

proper log entries can be made.

E & E, as policy, does not provide safety equipment or monitoring instrumentation to subcontractors. Some projects, however, may be set up so that E & E personnel and subcontractors share the same expendable

supplies.

E & E personnel are forbidden from approaching augers during drilling. Activities at the borehole, such as sampling, require that

equipment be stopped.

\

Page 89: Statement of Work: Drilling, Sampling & Monitoring Well ...

(f™®: SOP-HEALTH AND SAFETY ON DRILLING RIG OPERATIONS

Category: H & s_ TRAINing 2.7 JANUARY 1990

5 GENERAL DRILLING SITE SAFETY CHECKLISTS

5.1 SAFETY CHECKLISTS FOR SPECIFIC TYPES OF DRILLING ACTIVITIES

5.1.1 General Drilling Site Safety Checklist

o All E & E drilling personnel will have read and understood the

terms of the E & E drilling SOP.

o Obvious or questionable safety,conditions that arise duringdaily inspection of the rig and its components will be cause for

work interruption.

o Only approved Drillers will remain in proximity to the borehole

during drilling, and an approximate 4- by 8-£oot "super exclusion area" will be established around the moving auger at all times. No personnel, except the Driller and the Driller's Helper, will enter this zone during drilling. The SSO will issue warnings to those personnel who breach this zone.

o Continuous 0-/explosimeter monitoring at borehole using remote

sampling hose will exist at all times.

o All field team members will be briefed on planned drilling operations and possible problems before work begins on day 1.All will be shown the location and operation of "kill switches,

which will be operationally checked each morning.

o Fire extinguisher(s) will be staged next to the rig before

drilling and refueling operations.

o Welding and cutting activities will only be performed away from

ignition sources at a distance approved by the SSO or Team

Leader.

o Appropriate personnel protective equipment (based on hazards

associated with assumed well contaminants) will be worn as directed by the SSO and the SSP. At a minimum, steel-toed boots, hard hats, and face shields will be worn during any

active drilling.

o Outrigger stabilizers must be in place before drilling \

commences, and the rig must also be leveled.

o The drill rig mast must be horizontal during movement of rig and

should not be erected within 25 feet of overhead lines.

Page 90: Statement of Work: Drilling, Sampling & Monitoring Well ...

TW*: snP-HF.AT.TR AND SAFETY ON

Cateqt>fy: H fc'c TRAINING 2.7

DRILLING RIG

Revised:

OPERATIONS

JANUARY 1990

o Electrical storms within hearing range of the job site will signal work termination until the SSO and Team: Leader notify

personnel otherwise.

o The local utilities should be contacted prior to drilling so that their lines can be located and flagged. Situations of close proximity may involve isolating utility lines (i.e.,

shutdown and inerting of gas lines).

o When buried drums or other material are suspected, a full survey of the drilling zone is required using appropriate

instrumentation prior to ground breaking.

o Only trained, experienced staff who have studied proper drilling methods and served as a Helper under an experienced Driller will

operate the cathead.

o Only properly licensed staff will drive the drill rig. A daily safety check of the vehicle, following E & E protocol, will be

carried out by the driver.

o Climbing on the vertical mast is not permitted by E & E staff. Because the boom is not equipped with a ladder, it should be

lowered for repairs.

5.1.2 Rotary and Core Drilling

The following precautionary measures should be taken during rotary

and core drilling:

o Rotary drilling tools should be safety checked prior to

drilling:

- Rods and bit should be open and clear.

- Water swivels and hoisting plugs should be lubricated and

checked for "frozen” bearings before use.

- Drill rod chuck jaws should be checked periodically and

replaced when necessary.

- The capacities of hoists and sheaves should be checked against the anticipated weight of the drill rod string, in

addition to other expected hoisting loads.

- All hoses to and from the pump should be checked for properly installed couplings; couplings should be secured with locking

devices on "quick connect" fittings or wire on

"Chicago-Style" couplings.

9

onwn Pfcllrecycled paper

Page 91: Statement of Work: Drilling, Sampling & Monitoring Well ...

THla: i~np uvm.TH AND ^Fy;rY ON DRlUj^.—---------------- ( Revised:

Category: ^ l <^T TURNING 2^7

I\i>^ w ~ ;

iaNUAR'j 199Q_

ted daily for deterioration and

- Hoses should ^^'if needed.

leakage, and P £or safe rotary or core

Special Precaf i0"huckingf join^break, hoisting, and lowering

drilling involve chucking, J

of drill rods: brake or set a

. only the Operator of ‘chuck) will not occur

manual chuck so hatro the chuck.—r t I braked while being lowered into the

Drill rods should not be brak

hole vUh chuck, jews. ^ the hole with

. ' Drill cods should not be heldpipe wrenches. -ly or inadvertently

- 10%rah the .SIUUH

rods with hands or a ^ clrculation blockage,

Tn the event of a plugged bit °r °d hose between the pump an - the1 high Pt—onuldhhePlrPeliIvaeddor bled down before

td« »bS'The10£itrt “=ol1oint.

breaking the shoold be

- pit"0do°ri

members. The •*£,%£££ -hold drill rig fitted, cover panels strong

personnel. unsecured against

- r ir-

to beSe^o^Lo^s ^fety glas-^-^^/and respiratory

pso”ection*added asErequired

5-‘-3 SStheadJsSS frM o£ rust, oil. and grease. If it

Keep the cathead clean ylre brush,becomes rusty, clean wit

10

Page 92: Statement of Work: Drilling, Sampling & Monitoring Well ...

^*8: ^OP-HEALTH AND SAFETY ON DRILLING RIG OPERATIONS

Category: HRS. TRAINING 2. Revised: JANUARY 1990

o Check the cathead periodically, when the engine is not running, for rope wear grooves. If a rope groove forms- to a depth greater than 1/8 inch (3 mm), the cathead should be replaced.

o Always use a clean, dry, sound rope. A wet or oily rope may "grab" the cathead and cause drill tools or other items to be

rapidly hoisted to the top of the mast.

o Should the rope "grab" the cathead or otherwise become tangled in the drum, release the rope and sound an appropriate alarm for all personnel, including the Operator, to rapidly back away and stay clear. If the rope "grabs" the cathead and tools are hoisted to the sheaves at the top of the mast, the rope will often break, releasing the tools. If the rope does not break, stay clear of the drill rig until the Operator can turn off the drill rig engine and initiate other appropriate actions to release the tools. The Operator should carefully watch the suspended tools, quickly backing away after turning off the

engine.

o Chemicals can cause deterioration of the rope that may not be visibly detectable, thus the rope should always be protected

from any chemical contact.

o Never wrap the rope from the cathead (or any other rope, wire rope, or cable on the drill rig) around a hand, wrist, arm, foot, ankle, leg, or any other part of the body.

o Always maintain a minimum of 18 inches of clearance between the operating hand and the cathead drum when driving samplers, casing, or other tools with the cathead and rope method. Be aware that the rope advances toward the cathead with each hammer blow as the sampler or other drilling tool advances into the

ground.

o Do not use more rope wraps than are required to hoist a load.

o Do not leave a cathead unattended with the rope wrapped on the

drum.

o Position all other hoist lines to prevent contact with the

operating cathead rope.

o When using the cathead and rope for driving or back-driving,make sure that all threaded connections are tight, while staying as far away as possible from the hammer impact point.1

o The cathead Operator must be able to operate the catheadstanding on a level surface with sound, firm-footing conditions,

without distraction or disturbance.

11

recycieo paper rTuIItK^MM^mTPmiTnFtiH

Page 93: Statement of Work: Drilling, Sampling & Monitoring Well ...

1TWe: SOP-HEALTH AND SAFETY ON DRILI_ING RIG OPERATIONS

Category: H & s< training 2.7 Revised: JANUARY 1990

5.1.4 Continuous-Flight or Hollow-Stem Augers

o Prepare to start an auger boring with the drill rig level, the clutch or hydraulic rotation control disengaged, the transmission in low gear, and the engine running at low RPH.

o Apply an adequate amount of down pressure before rotation to seat the auger head below the ground surface.

o Check, auger flights for nicks or burrs that could catch clothing

during rotation, and file them down.

o Vatch the auger head while slowly engaging the clutch orrotation control, and start rotation. Stay clear of the auger.

o Slowly rotate the auger and auger head while continuing to apply down pressure. Keep one hand on the clutch or the rotation control at all times until the auger has penetrated about 1 foot

or more below ground surface.

o If the auger head slides out of alignment, disengage the clutch or hydraulic rotation control, and repeat the starting process.

o An auger guide should be considered to facilitate the starting

of a straight hole through hard ground or pavement.

o The Operator and tool handler should establish a system of responsibility for the various activities required for auger drilling, such as connecting and disconnecting auger sections and inserting and removing the auger fork. The Operator must ensure that the tool handler is well away from the auger column and that the auger fork is removed before starting rotation.

o Only use the manufacturer's recommended method of securing the auger to the power coupling. Do not touch the coupling or the auger with your hands, a wrench, or any other tool during

rotation.

o Whenever possible, use tool hoists to handle auger sections.

o Never place hands or fingers under the bottom of an auger section when hoisting the auger over the top of the auger section in the ground or other hard surfaces such as the drill

rig platform.

o Never allow feet to get under the auger section that is being

hoisted.

iii

Iiiii

i

\f

t

Page 94: Statement of Work: Drilling, Sampling & Monitoring Well ...

"™e: SOP-HEALTH AND SAFETY ON DRILLING RIG OPERATIONS

Category: TRAINING 2.7 R6yl8ed: JANUARY 1990

o When rotating augers, stay clear of the rotating auger and other rotating components of the drill rig. Never reach behind or

around a rotating auger.

o Use a long-handled shovel to move auger cuttings away from the auger. Never use your, hands or feet to move cuttings away from

the auger.

o Do not use hands to clean rotating augers when removing augers

from the ground.

o The use of wire line hoists, wire rope, and hoisting hardware should conform to stipulations developed by the American Iron and Steel Institute Wire Rope Users Manual.

5.1.5 Use of Wire Line Hoists, Wire Rope, and Hoisting Equipment

All wire ropes and fittings should be visually inspected during use and thoroughly inspected at least once a week for abrasion, broken wires, wear, reduction in rope diameter, reduction in wire diameter, fatigue, corrosion, damage from heat, improper weaving, jamming, crushing, bird caging, kinking, core protrusion, and damage to lifting hardware. All related equipment must conform to standards as established by the American Iron and Steel Institute Wire Rope Users Manual. Wire ropes should be replaced when inspection indicates excessive damage according to the Wire Rope Users Manual. All wire ropes which have not been used for a period of 1 month or more should be thoroughly inspected before being returned to service.

o End fittings and connections consist of spliced eyes and various manufactured devices. All manufactured end fittings and connections should be installed according to the manufacturer's instructions and loaded according to the manufacturer's

specifications.

o If a ball-bearing type hoisting swivel is used to hoist drill rods, swivel bearings should be inspected and lubricated daily to ensure that the swivel freely rotates under load.

}

I

I

I

o If a rod slipping device is used to hoist drill rods, do not drill through or rotate drill rods through the slipping device, and do not hoist the drill rod column higher than one-half the mast height above the top of the mast (derrick). Do not hoist a rod column with loose tool joints and do not make up, tighten, or loosen tool joints while the rod column is being supported by a rod slipping device. If drill rods should slip back into the borehole, do not attempt to brake the fall of the rods with hands or by tensioning the slipping device.

13

recvciea paper iiml •‘mirmttnriii

Page 95: Statement of Work: Drilling, Sampling & Monitoring Well ...

■ 1™®: SOP-HEALTH AND SAFETY ON DRILLING RIG OPERATIONS

Category: H & S- TRAINING 2.7 Revised: JANUARY 1990

o Host sheaves on exploration drill rigs are stationary with a single part line. The number of parts of line should never be increased without first consulting with the manufacturer of the

drill rig.

o Wire ropes must be properly matched with each sheave—if the rope is too large, the sheave will pinch the wire rope—if the rope is too small, it will groove the sheave. Once the sheave is grooved, it will severely pinch and damage larger wire ropes.

o Use tool handling hoists only for vertical lifting of tools (except when angle hole drilling). Do not use tool handling hoists to pull objects away.from the drill rig; however, drills may be moved using the main hoist if the wire rope is spooled through proper sheaves according to the manufacturer's

recommendations.

o When stuck tools or similar loads cannot be raised with a hoist, disconnect the hoist line and connect the stuck tools directly to the feed mechanism of the drill. Do not use hydraulic leveling jacks for added pull to the hoist line or the feed

mechanism of the drill.

o When attempting to free a mired vehicle or drill carrier, use only a winch on the front or rear of the vehicle, and stay as far as possible away from the wire rope. Do not attempt to use tool hoists to pull out a mired vehicle or drill rig carrier.

o Hinimize shock loading on a wire rope—apply loads smoothly and

steadily.

o Avoid sudden loading in cold weather.

o Never use frozen ropes.

o Protect wire rope from sharp corners or edges.

o Do not operate the rig with damaged or faulty guides, rollers, sheave bearings, or latches on safety hooks.

o Clutches and brakes on hoists should be periodically tested.

o Know and do not exceed the rated capacity of hooks, rings, links, swivels, shackles, and other lifting aids.

o Always wear gloves when handling wire rope.

o Following the installation of a new wire rope, first lift a light load to allow the wire rope to adjust.

Page 96: Statement of Work: Drilling, Sampling & Monitoring Well ...

TWe: SOP-HEALTH AND SAFETY ON DRILLING RIG OPERATIONS

Category: H & TRAINING 2.7 r Revteed: JANUARY 1990

Never carry out hoisting operations when weather conditions are such that hazards to personnel, the public, or property are

created.

o Never leave a load suspended in the air when the hoist is

unattended.

o Never hoist a load over the head, body, or feet of personnel.

o Never use a hoist line to "ride" up the mast (derrick) of a drill rig.

o Replacement of vire ropes should conform to the drill rig manufacturer's specifications.

15

recycled paper '•ruiutf* iimi mvinHimriii

Page 97: Statement of Work: Drilling, Sampling & Monitoring Well ...

suojieooi ||9AA 6uuoi!UO|/\| pasodojd ifl|M eajv aj|S Z ajn6y


Recommended