+ All Categories
Home > Documents > Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed...

Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed...

Date post: 18-Jan-2016
Category:
Upload: corey-potter
View: 219 times
Download: 0 times
Share this document with a friend
Popular Tags:
39
Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling
Transcript
Page 1: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

Status and Prospects for the AD and ELENA

Lars V. Jorgensen / CERN / BE-OP

With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling

Page 2: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 2

Outline

• AD start-up and status 2015• AD consolidation program• ELENA overview and status

I was reading a book on anti-gravity the other night- I couldn’t put it down!!

Page 3: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 3

AD start-up status 2015

• AD Physics Run 2015 started July 6th.• One month into the run we have so far had good up-time and good, relatively

high ejected numbers.

• What is new? Why might the AD work better/worse than last year??• Shutdown work 2014/15 - Some examples:

• Start of major target area renovation• Continued stochastic cooling renovation• Kicker pulse generator re-location• Magnet renovation• Cabling clean-up• Cryogenic Current Comparator (CCC)

Page 4: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 4

Injection/ejection kicker pulse generators for AD and ELENA

…have been removed to make place for ELENA

Situation at end of run 2014

Situation in early July 2015

Page 5: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 5

Pulse generators re-located to B393 including renewal of electronics/interlocks/controls interface etc.

Kicker platforms in the new building 393

Kicker platform replacement

Page 6: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 6

BHZ23 & BHZ24 renovated, 21 more of these will be done over the next years…..

Main dipole magnet refurbishment

Page 7: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 7

- Cryogenic Current Comparator installed in section 15.

- first results encouraging but due to cryo problems it will have to come out again next shutdown

Cryogenic current comparator

Page 8: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 8

CCC results and Schottky comparison

Page 9: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 9

Other items changed since last year

• Stochastic cooling consolidation: notch filter control, SW for pickup movement

• 3 new BCT:s in injection line, replaces obsolete units• Target area: extensive consolidation program underway. New targets

& design, New horns, refurbishment of buildings etc. etc.

Page 10: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 10

Good deceleration efficiency, transverse emittances and bunch length, but still room for improvement

The year so far?

Page 11: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

AD consolidationAn old machine gets a make over!

Page 12: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015

AD consolidation

• Most of AD dates from ~1980 => Main components are 30-35 years old….,

• Due to other important CERN programs (LHC), only urgent issues were addressed for the first ~10 years of AD operation

• For many years AD was always below the budget cut-off line since it’s not part of the LHC program

• A small consolidation program (~2.3 MCHF), separated from the LHC program, started in 2009 in view of running AD until 2016 or so

• After approval of the ELENA project, the scope of the consolidation increased and is aimed at continued operation of AD for at least 10-15 years after ELENA physics has started which means 2030 - 2035

• Concerned items are: Target area, magnets, power converters, vacuum system, beam cooling, instrumentation, RF, control system, Infrastructure etc.

• AD is at the moment in the middle of a major consolidation program with a budget plan of 23.8 MCHF allocated for the period 2014 – 2020

12

Page 13: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

Target Area

• During p program (1980 – 1996) a full team was looking after design, operation and maintenance

• Since the AD start-up only limited follow-up was done• Most of control equipment was conceived as prototypes

• Few problems occurred during 15 years of AD operation• Repetition rate is now ~ 100s, the target area was designed for 2,4 s• Very reduced maintenance over the year – loss of expertise

• Major consolidation activity has started in 2011/12 & LS1 and will continue through LS2 => Activities related to major items need to be started ASAP to be ready for LS2 installation

• Significant impact on AD physics in case of failure between LS2 and LS3• Know weak points (target, horn, magnets…)• Very long physics stops (≥ year)

• Increase contamination levels and associated radiological risks• Horn assembly failure discovered in LS1 is an indication that urgent consolidation is

needed for the whole area

WAG, London, August 7, 2015 13

Page 14: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

14WAG, London, August 7, 2015

Dump

Magnets dog-leg

PSAIF irradiation pit

Mobile shielding

BHZ6024/25 transformer

Page 15: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

Magnets, ring and transfer lines

• Main bendings (24):• Renovation and re-shimming: Regular coil movement measurements on remaining

units will determine which one(s) next.• 3 units will be renovated so far. 21 to go.

WAG, London, August 7, 2015 15

BHN 05

BHN 06

BHW 08

BHW 09

BHN 11

BHN 12

BHN 17

BHN 18

BHW 20

BHW 21

BHN 23

BHN 24

BHN 33

BHN 34

BHW 36

BHW 37

BHN 39

BHN 40

BHN 45

BHN 46

BHW 48

BHW 49

BHN 51

BHS 52

0.000

0.500

1.000

1.500

2.000

2.500

3.000

Downstream, 2012 (mm) Upstream, 2012 (mm) Upstream, 2009 (mm) After shimming, 2009 (mm)

Page 16: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

Magnets, ring and transfer lines

• H/V correctors near e-cooler replaced during LS1.

• Ejection line quadrupoles (2) replaced during LS1.

• Spare inventory almost complete.• Target area magnets:

• Quadrupoles upstream of target (9050 & 9052). Area is very hot,1 spare exists but lack of knowledge about state, manipulation & connections. Alternative designs are being considered including permanent magnets.

• 2015 – 2017• Remaining Bendings and quads: renovation of spare units

• Ejection line magnets (except DEM-line) will be replaced by e-static units for ELENA ~2017

WAG, London, August 7, 2015 16

Page 17: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

Power converters

• Most urgent items consolidation finished during LS1.• General consolidation program for 2015 – 2020 approved; renewal

& standardization• Replacement of orbit corrector units with standard Cancun supplies

in 2015• 2/4 kV pulsed injection line converters to be replaced by new

Megadiscap in 2016 – 2018. 4 units are already in operation with good results.

• Replacement of thyristor converters by commercial units during LS2.

WAG, London, August 7, 2015 17

Page 18: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

Stochastic cooling

• Controls, electronics, delay/attenuator platform installation, individual u-wave amplifier power supplies and p/u & kicker movement motors/electronics all renovated or replaced during LS1.

• Notch filters: Replacement of large cable-box with optical filter system. 2015

• 0.8 – 1.6 GHz power amplifiers (48): Obsolete semi-conductors, increased failure rate. Prototyping for new design if old amplifiers become unrepairable or too unreliable. 2015/16.

• Vacuum tanks: Life expectancy and mechanical integrity of pickup and kicker vacuum tanks & s-cooling equipment inside. Possible consolidation not yet addressed.

WAG, London, August 7, 2015 18

Page 19: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 1919

• Renewal of electron cooler:– Build a new state-of-the-art cooler– 2015 – 2018. Aim for installation in

LS2.– Existing cooler:

• Is >35 years old• We have no spare magnets;

very long down time if failure, significant cost for new spares

• Performance issues• e- bpm:s not operational

Momentum pbar 300 MeV/c 100 MeV/c

Electron energy 35 keV 2.8 keV

Electron current 2.5 A 100 mA

Cooling length 1.5 mDrift magnet field 590 Gauss

Electron beam radius

25 mm

Cooling time 16 s 15 sεx / εy 3 / 3 (π × mm ×

mrad)0.8 / 0.5 (π

× mm × mrad)

dp/p 10-4 < 7 × 10-5

Electron cooling consolidation

Page 20: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

Instrumentation

• BIPM H and V systems merged into one vacuum tank.

• Orbit system: solution with individual ADC:s in 2015, similar to ELENA system. Will permit measurements during ramps. 2015 – 2017

• BBQ-tune measurement: Using existing pickup, commissioned but not yet in regular operation. 2015

• CCC (Cryogenic Current Comparator): Intensity measurements of low-intensity beams. To be used in ELENA as well. 2015 – 2016

• Schottky analysis (longitudinal): integrate ageing DSP equipment into new C02 LL beam control system + new system for visual monitoring. 2016 - 2018

WAG, London, August 7, 2015 20

Page 21: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

RF

• C02 HV & tuning power supplies. Interlock system. Required to make space for ELENA.

• C02 Low-Level: Migration to PSB/ELENA-like DSP based system (including Schottky analysis). 2016 – 2018.

• C10 Low-Level & High-Level renewal: • C10 final stage (obsolete TH116 valves): New power

amplifier/control/interlock systems to be developed: 4MCHF 2016-2018

WAG, London, August 7, 2015 21

Page 22: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

Controls/software

• Major LS1 renovation:• Front-end upgrade (ACCOR): ~complete (80-90%) renewal in LS1• Central Timing: re-design for de-coupling AD from the LHC injector complex • Cycle Generation: adaptation to comply with new timing system• New Beam Request Server• Similar CT, CG and BRS systems will be implemented in ELENA• FESA, Java migration, InCA: majority has been completed (standardization)• Some implications:

• All AP:s have been adapted (OP + Eq. groups)• Major debugging effort during 2014 start-up !

• => No major consolidation needs !

WAG, London, August 7, 2015 22

Page 23: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

Infrastructure

• Cryo-distribution line for AD experiments, large dewar outside building + distribution lines to experimental zones. 2015/16

• B193/B195 cooling/ventilation:• Requested for LS2 major upgrade

• B193 cranes: • Requested for LS2

WAG, London, August 7, 2015 23

Page 24: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

ELENAOverview and status

Page 25: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 25

ELENA Overview

Momentum range, MeV/c 100 - 13.7

Energy range, MeV 5.3 - 0.1

Circumference, m 30.4

Intensity of injected beam 3 × 107

Intensity of ejected beam 1.8 × 107

Number of extracted bunches 1 to 4

Emittances (h/v) at 100 KeV, π·mm·mrad, [95%] 4 / 4

∆p/p after cooling, [95%] 10−3

Bunch length at 100 keV, m / ns 1.3 / 300

Required (dynamic) vacuum, Torr 3 × 10−12

Page 26: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 26

ELENA Overview and Layout

• Deceleration of antiprotons from 5.3 MeV to 100 keV to improve efficiency of experiments

• Circumference 30.4 m (1/6 the size of the AD)• Fits in available space in AD hall and allows installing all equipment without particular efforts • Lowest average field (beam rigidity over average radius) Br/R = 94 G (smaller than for AD 115 G)

High sensitivity magneticpick-up for Schottky diagnostic (intensity) and LLRF

Extraction towards existing experiments(with fast electrostatic deflector)

Wideband RF cavity

Scraper to measureemittances(destructive)

Electron Cooler andcompensation solenoids

Extraction towards new exp. zone

Injection with magnetic septum (≈300 mrad)and kicker (84 mrad)

Quadrupoles

Line from H- and proton source for commissioning

Page 27: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 27

ELENA Overview and Layout

New annex building withkicker equipment

Towardsexistingexperiments

ELENAringNew area with

GBAR and AEgIS

AD Shielding

Page 28: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 28

ELENA Overview and Layout

Transfer line(magnetic)from AD

Electro-static line towardsexisting experimental area

Extraction towards new experimental area

External source for commissioning

Page 29: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 29

Selected Features and Challenges

• Energy Range• Machine operated at an unusually low energy for a synchrotron (down to 100 keV!)

• Lattice and geometry• Many Constraints (Long straight Section with small Dispersion for Electron Cooling, Geometry in AD

hall, Beta Functions and resulting Beam Sizes, Working Point ...)• Hexagonal shape and optics with periodicity two (two long Straights without Quadrupole Magnets)

• Electron cooling• Applied at two plateaus to mitigate losses and generate dense bunches• Very low energy electrons at bottom plateau• Bunched Beam Cooling at 100 keV extraction Energy to generate dense Bunches for Experiments• Effect (perturbation) of magnetic field of cooler on circulating antiprotons: delicate study started,

continuation under discussion

• Expected main performance limitation: Intra Beam Scattering IBS• Determines beam parameters with cooling (equilibrium between the two processes)

• Vacuum System: fully baked with NEGs where possible to reach 3 10-12 Torr ➠ Interactions with rest gas (Blow-up, Losses) not the dominant limitation despite the low energy

• Beam Diagnostics with very low Intensities and at low Energy• E.g.: Beam currents down to well below 1 mA far beyond reach standard slow BCTs➠ Intensity of coasting beam measured with Schottky diagnostics

Page 30: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 30

The situation as of this Monday

Page 31: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 31

Main components production status

8 dipoles

Magnet Ready

Sector 2 18/02/2016

Sector 3 18/02/2016

Sector 4 16/03/2016

Sector 5 16/03/2016

Sector 6 13/04/2016

Sector 1 13/04/2016

16 quadrupoles 3 skew quadrupoles

1 2 3 4 5 6 7 8 90

5

10

15

20

Installation Ready

Installation monthNu

mbe

r of m

agne

tsOct. 2015 Apr. 2016

3 TL dipoles

Magnet Ready

3 magnets 1 available2 in October 15

Courtesy: D. Schoerling

Page 32: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 32

Main components production status (2)

1 2 3 4 5 6 702468

10121416

Installation Ready

Installation month

Num

ber o

f mag

nets

Oct. 2015 Apr. 2016

14 H/V correctors

5 sextupoles

Magnet Ready

Pre-series 10/2015

Series 12/2015

3 solenoids

Magnet Ready

2 magnets 01/2016

Courtesy: D. Schoerling

Page 33: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 33

• Electron cooler: • Critical for ELENA! Operate at very low electron energies (down to 55 eV). Operate at very low magnetic field to minimize disturbance to circulating low

energy antiprotons – we have chosen 100 Gauss in the cooler. Have extremely good vacuum. Adiabatic expansion to reduce transverse temperatures. Very good field quality – especially in the cooler solenoid (B˔/Bǁ < 5 × 10-4 ). Orbit correctors and solenoid compensators.• Magnetic system in production at TESLA, vacuum system designed and to be

produced at CERN,Delivery expected 15 March 2016

Main components production status (3)

Page 34: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 34

Main components production status (4)

• RF Finemet cavity

• Scraper

• BTV

• Tune measurements

• Longitudinal pick-ups

• Beam Position Monitors

• Septum

• Injection kicker magnet

• Electrostatic elements

• SEM grids

• Vacuum equipment

• Supports

Other components: All in production – on time (!)

Page 35: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 35

Replacing the magnetic lines from the AD by electrostatic lines from ELENA

LNE00 LNE01 LNE02

LNE06

LNE07

LNE05

LNE04

LNE03

Atrap 1

Atrap 2

Replacing the current magnetic ejection lines with the new electrostatic ejection lines will take about 9 months!! + commissioning ~ 6 weeks!

Page 36: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 36

Possible scenarios for 2017 and 2018 with LS2 starting around mid 2018

~10 weeks(week 41 to week 50)

~8 weeks(week 15 to week 22)

~33 weeks(week 18 to week 50)

preceded by ion run

Page 37: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 37

Possible scenarios for 2017 and 2018 with LS2 starting around end 2018

Detailed planning not yet available(dates guessed)

Page 38: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 38

Summary and Outlook

• AD off to a good start 2015• Major upgrade work underway at the AD• ELENA design finished – production underway• ELENA installation is progressing according to plan – so far!!!• 100 keV pbars coming to an experiment near you! – but when?

Thanks!

Page 39: Status and Prospects for the AD and ELENA Lars V. Jorgensen / CERN / BE-OP With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling.

WAG, London, August 7, 2015 39


Recommended