Date post: | 18-Jan-2016 |
Category: |
Documents |
Upload: | corey-potter |
View: | 219 times |
Download: | 0 times |
Status and Prospects for the AD and ELENA
Lars V. Jorgensen / CERN / BE-OP
With many slides borrowed from T. Eriksson, C. Carli, F. Butin, D. Schoerling
WAG, London, August 7, 2015 2
Outline
• AD start-up and status 2015• AD consolidation program• ELENA overview and status
I was reading a book on anti-gravity the other night- I couldn’t put it down!!
WAG, London, August 7, 2015 3
AD start-up status 2015
• AD Physics Run 2015 started July 6th.• One month into the run we have so far had good up-time and good, relatively
high ejected numbers.
• What is new? Why might the AD work better/worse than last year??• Shutdown work 2014/15 - Some examples:
• Start of major target area renovation• Continued stochastic cooling renovation• Kicker pulse generator re-location• Magnet renovation• Cabling clean-up• Cryogenic Current Comparator (CCC)
WAG, London, August 7, 2015 4
Injection/ejection kicker pulse generators for AD and ELENA
…have been removed to make place for ELENA
Situation at end of run 2014
Situation in early July 2015
WAG, London, August 7, 2015 5
Pulse generators re-located to B393 including renewal of electronics/interlocks/controls interface etc.
Kicker platforms in the new building 393
Kicker platform replacement
WAG, London, August 7, 2015 6
BHZ23 & BHZ24 renovated, 21 more of these will be done over the next years…..
Main dipole magnet refurbishment
WAG, London, August 7, 2015 7
- Cryogenic Current Comparator installed in section 15.
- first results encouraging but due to cryo problems it will have to come out again next shutdown
Cryogenic current comparator
WAG, London, August 7, 2015 8
CCC results and Schottky comparison
WAG, London, August 7, 2015 9
Other items changed since last year
• Stochastic cooling consolidation: notch filter control, SW for pickup movement
• 3 new BCT:s in injection line, replaces obsolete units• Target area: extensive consolidation program underway. New targets
& design, New horns, refurbishment of buildings etc. etc.
WAG, London, August 7, 2015 10
Good deceleration efficiency, transverse emittances and bunch length, but still room for improvement
The year so far?
AD consolidationAn old machine gets a make over!
WAG, London, August 7, 2015
AD consolidation
• Most of AD dates from ~1980 => Main components are 30-35 years old….,
• Due to other important CERN programs (LHC), only urgent issues were addressed for the first ~10 years of AD operation
• For many years AD was always below the budget cut-off line since it’s not part of the LHC program
• A small consolidation program (~2.3 MCHF), separated from the LHC program, started in 2009 in view of running AD until 2016 or so
• After approval of the ELENA project, the scope of the consolidation increased and is aimed at continued operation of AD for at least 10-15 years after ELENA physics has started which means 2030 - 2035
• Concerned items are: Target area, magnets, power converters, vacuum system, beam cooling, instrumentation, RF, control system, Infrastructure etc.
• AD is at the moment in the middle of a major consolidation program with a budget plan of 23.8 MCHF allocated for the period 2014 – 2020
12
Target Area
• During p program (1980 – 1996) a full team was looking after design, operation and maintenance
• Since the AD start-up only limited follow-up was done• Most of control equipment was conceived as prototypes
• Few problems occurred during 15 years of AD operation• Repetition rate is now ~ 100s, the target area was designed for 2,4 s• Very reduced maintenance over the year – loss of expertise
• Major consolidation activity has started in 2011/12 & LS1 and will continue through LS2 => Activities related to major items need to be started ASAP to be ready for LS2 installation
• Significant impact on AD physics in case of failure between LS2 and LS3• Know weak points (target, horn, magnets…)• Very long physics stops (≥ year)
• Increase contamination levels and associated radiological risks• Horn assembly failure discovered in LS1 is an indication that urgent consolidation is
needed for the whole area
WAG, London, August 7, 2015 13
14WAG, London, August 7, 2015
Dump
Magnets dog-leg
PSAIF irradiation pit
Mobile shielding
BHZ6024/25 transformer
Magnets, ring and transfer lines
• Main bendings (24):• Renovation and re-shimming: Regular coil movement measurements on remaining
units will determine which one(s) next.• 3 units will be renovated so far. 21 to go.
WAG, London, August 7, 2015 15
BHN 05
BHN 06
BHW 08
BHW 09
BHN 11
BHN 12
BHN 17
BHN 18
BHW 20
BHW 21
BHN 23
BHN 24
BHN 33
BHN 34
BHW 36
BHW 37
BHN 39
BHN 40
BHN 45
BHN 46
BHW 48
BHW 49
BHN 51
BHS 52
0.000
0.500
1.000
1.500
2.000
2.500
3.000
Downstream, 2012 (mm) Upstream, 2012 (mm) Upstream, 2009 (mm) After shimming, 2009 (mm)
Magnets, ring and transfer lines
• H/V correctors near e-cooler replaced during LS1.
• Ejection line quadrupoles (2) replaced during LS1.
• Spare inventory almost complete.• Target area magnets:
• Quadrupoles upstream of target (9050 & 9052). Area is very hot,1 spare exists but lack of knowledge about state, manipulation & connections. Alternative designs are being considered including permanent magnets.
• 2015 – 2017• Remaining Bendings and quads: renovation of spare units
• Ejection line magnets (except DEM-line) will be replaced by e-static units for ELENA ~2017
WAG, London, August 7, 2015 16
Power converters
• Most urgent items consolidation finished during LS1.• General consolidation program for 2015 – 2020 approved; renewal
& standardization• Replacement of orbit corrector units with standard Cancun supplies
in 2015• 2/4 kV pulsed injection line converters to be replaced by new
Megadiscap in 2016 – 2018. 4 units are already in operation with good results.
• Replacement of thyristor converters by commercial units during LS2.
WAG, London, August 7, 2015 17
Stochastic cooling
• Controls, electronics, delay/attenuator platform installation, individual u-wave amplifier power supplies and p/u & kicker movement motors/electronics all renovated or replaced during LS1.
• Notch filters: Replacement of large cable-box with optical filter system. 2015
• 0.8 – 1.6 GHz power amplifiers (48): Obsolete semi-conductors, increased failure rate. Prototyping for new design if old amplifiers become unrepairable or too unreliable. 2015/16.
• Vacuum tanks: Life expectancy and mechanical integrity of pickup and kicker vacuum tanks & s-cooling equipment inside. Possible consolidation not yet addressed.
WAG, London, August 7, 2015 18
WAG, London, August 7, 2015 1919
• Renewal of electron cooler:– Build a new state-of-the-art cooler– 2015 – 2018. Aim for installation in
LS2.– Existing cooler:
• Is >35 years old• We have no spare magnets;
very long down time if failure, significant cost for new spares
• Performance issues• e- bpm:s not operational
Momentum pbar 300 MeV/c 100 MeV/c
Electron energy 35 keV 2.8 keV
Electron current 2.5 A 100 mA
Cooling length 1.5 mDrift magnet field 590 Gauss
Electron beam radius
25 mm
Cooling time 16 s 15 sεx / εy 3 / 3 (π × mm ×
mrad)0.8 / 0.5 (π
× mm × mrad)
dp/p 10-4 < 7 × 10-5
Electron cooling consolidation
Instrumentation
• BIPM H and V systems merged into one vacuum tank.
• Orbit system: solution with individual ADC:s in 2015, similar to ELENA system. Will permit measurements during ramps. 2015 – 2017
• BBQ-tune measurement: Using existing pickup, commissioned but not yet in regular operation. 2015
• CCC (Cryogenic Current Comparator): Intensity measurements of low-intensity beams. To be used in ELENA as well. 2015 – 2016
• Schottky analysis (longitudinal): integrate ageing DSP equipment into new C02 LL beam control system + new system for visual monitoring. 2016 - 2018
WAG, London, August 7, 2015 20
RF
• C02 HV & tuning power supplies. Interlock system. Required to make space for ELENA.
• C02 Low-Level: Migration to PSB/ELENA-like DSP based system (including Schottky analysis). 2016 – 2018.
• C10 Low-Level & High-Level renewal: • C10 final stage (obsolete TH116 valves): New power
amplifier/control/interlock systems to be developed: 4MCHF 2016-2018
WAG, London, August 7, 2015 21
Controls/software
• Major LS1 renovation:• Front-end upgrade (ACCOR): ~complete (80-90%) renewal in LS1• Central Timing: re-design for de-coupling AD from the LHC injector complex • Cycle Generation: adaptation to comply with new timing system• New Beam Request Server• Similar CT, CG and BRS systems will be implemented in ELENA• FESA, Java migration, InCA: majority has been completed (standardization)• Some implications:
• All AP:s have been adapted (OP + Eq. groups)• Major debugging effort during 2014 start-up !
• => No major consolidation needs !
WAG, London, August 7, 2015 22
Infrastructure
• Cryo-distribution line for AD experiments, large dewar outside building + distribution lines to experimental zones. 2015/16
• B193/B195 cooling/ventilation:• Requested for LS2 major upgrade
• B193 cranes: • Requested for LS2
WAG, London, August 7, 2015 23
ELENAOverview and status
WAG, London, August 7, 2015 25
ELENA Overview
Momentum range, MeV/c 100 - 13.7
Energy range, MeV 5.3 - 0.1
Circumference, m 30.4
Intensity of injected beam 3 × 107
Intensity of ejected beam 1.8 × 107
Number of extracted bunches 1 to 4
Emittances (h/v) at 100 KeV, π·mm·mrad, [95%] 4 / 4
∆p/p after cooling, [95%] 10−3
Bunch length at 100 keV, m / ns 1.3 / 300
Required (dynamic) vacuum, Torr 3 × 10−12
WAG, London, August 7, 2015 26
ELENA Overview and Layout
• Deceleration of antiprotons from 5.3 MeV to 100 keV to improve efficiency of experiments
• Circumference 30.4 m (1/6 the size of the AD)• Fits in available space in AD hall and allows installing all equipment without particular efforts • Lowest average field (beam rigidity over average radius) Br/R = 94 G (smaller than for AD 115 G)
High sensitivity magneticpick-up for Schottky diagnostic (intensity) and LLRF
Extraction towards existing experiments(with fast electrostatic deflector)
Wideband RF cavity
Scraper to measureemittances(destructive)
Electron Cooler andcompensation solenoids
Extraction towards new exp. zone
Injection with magnetic septum (≈300 mrad)and kicker (84 mrad)
Quadrupoles
Line from H- and proton source for commissioning
WAG, London, August 7, 2015 27
ELENA Overview and Layout
New annex building withkicker equipment
Towardsexistingexperiments
ELENAringNew area with
GBAR and AEgIS
AD Shielding
WAG, London, August 7, 2015 28
ELENA Overview and Layout
Transfer line(magnetic)from AD
Electro-static line towardsexisting experimental area
Extraction towards new experimental area
External source for commissioning
WAG, London, August 7, 2015 29
Selected Features and Challenges
• Energy Range• Machine operated at an unusually low energy for a synchrotron (down to 100 keV!)
• Lattice and geometry• Many Constraints (Long straight Section with small Dispersion for Electron Cooling, Geometry in AD
hall, Beta Functions and resulting Beam Sizes, Working Point ...)• Hexagonal shape and optics with periodicity two (two long Straights without Quadrupole Magnets)
• Electron cooling• Applied at two plateaus to mitigate losses and generate dense bunches• Very low energy electrons at bottom plateau• Bunched Beam Cooling at 100 keV extraction Energy to generate dense Bunches for Experiments• Effect (perturbation) of magnetic field of cooler on circulating antiprotons: delicate study started,
continuation under discussion
• Expected main performance limitation: Intra Beam Scattering IBS• Determines beam parameters with cooling (equilibrium between the two processes)
• Vacuum System: fully baked with NEGs where possible to reach 3 10-12 Torr ➠ Interactions with rest gas (Blow-up, Losses) not the dominant limitation despite the low energy
• Beam Diagnostics with very low Intensities and at low Energy• E.g.: Beam currents down to well below 1 mA far beyond reach standard slow BCTs➠ Intensity of coasting beam measured with Schottky diagnostics
WAG, London, August 7, 2015 30
The situation as of this Monday
WAG, London, August 7, 2015 31
Main components production status
8 dipoles
Magnet Ready
Sector 2 18/02/2016
Sector 3 18/02/2016
Sector 4 16/03/2016
Sector 5 16/03/2016
Sector 6 13/04/2016
Sector 1 13/04/2016
16 quadrupoles 3 skew quadrupoles
1 2 3 4 5 6 7 8 90
5
10
15
20
Installation Ready
Installation monthNu
mbe
r of m
agne
tsOct. 2015 Apr. 2016
3 TL dipoles
Magnet Ready
3 magnets 1 available2 in October 15
Courtesy: D. Schoerling
WAG, London, August 7, 2015 32
Main components production status (2)
1 2 3 4 5 6 702468
10121416
Installation Ready
Installation month
Num
ber o
f mag
nets
Oct. 2015 Apr. 2016
14 H/V correctors
5 sextupoles
Magnet Ready
Pre-series 10/2015
Series 12/2015
3 solenoids
Magnet Ready
2 magnets 01/2016
Courtesy: D. Schoerling
WAG, London, August 7, 2015 33
• Electron cooler: • Critical for ELENA! Operate at very low electron energies (down to 55 eV). Operate at very low magnetic field to minimize disturbance to circulating low
energy antiprotons – we have chosen 100 Gauss in the cooler. Have extremely good vacuum. Adiabatic expansion to reduce transverse temperatures. Very good field quality – especially in the cooler solenoid (B˔/Bǁ < 5 × 10-4 ). Orbit correctors and solenoid compensators.• Magnetic system in production at TESLA, vacuum system designed and to be
produced at CERN,Delivery expected 15 March 2016
Main components production status (3)
WAG, London, August 7, 2015 34
Main components production status (4)
• RF Finemet cavity
• Scraper
• BTV
• Tune measurements
• Longitudinal pick-ups
• Beam Position Monitors
• Septum
• Injection kicker magnet
• Electrostatic elements
• SEM grids
• Vacuum equipment
• Supports
Other components: All in production – on time (!)
WAG, London, August 7, 2015 35
Replacing the magnetic lines from the AD by electrostatic lines from ELENA
LNE00 LNE01 LNE02
LNE06
LNE07
LNE05
LNE04
LNE03
Atrap 1
Atrap 2
Replacing the current magnetic ejection lines with the new electrostatic ejection lines will take about 9 months!! + commissioning ~ 6 weeks!
WAG, London, August 7, 2015 36
Possible scenarios for 2017 and 2018 with LS2 starting around mid 2018
~10 weeks(week 41 to week 50)
~8 weeks(week 15 to week 22)
~33 weeks(week 18 to week 50)
preceded by ion run
WAG, London, August 7, 2015 37
Possible scenarios for 2017 and 2018 with LS2 starting around end 2018
Detailed planning not yet available(dates guessed)
WAG, London, August 7, 2015 38
Summary and Outlook
• AD off to a good start 2015• Major upgrade work underway at the AD• ELENA design finished – production underway• ELENA installation is progressing according to plan – so far!!!• 100 keV pbars coming to an experiment near you! – but when?
Thanks!
WAG, London, August 7, 2015 39