BUILDING STRONG ® Bagram Airfield Waste Water Treatment Plant 01 OCT 2014 Who : U.S. Army Corps of Engineers, Transatlantic Afghanistan District What: The Wastewater Treatment Plant (WWTP) is one component of the $26.8M Eastside Utilities Infrastructure Project at Bagram Airfield. The new WWTP, located adjacent to the existing plant, increases the Where: Bagram Airfield, Afghanistan When: 01 October 2014 Why: To increase capacity of current wastewater treatment systems and disposal of waste water Way Ahead: WWTP is 90% complete and scheduled to finish at the end of CY14. Contractor is making significant progress on commissioning the process equipment and continues to complete civil works including site grading & area drainage. Commissioning of new Equalization Tank #1 Existing WWTP Aeration Tanks (foreground) and new WWTP (background) New Headworks structure, first stage of processing , exterior equipment designed to screen and direct effluent to either the new or Existing WWTP
Transcript
Page 1: story board -Eastside Utilities WWTP Project (2)

BUILDING STRONG®

Bagram Airfield Waste Water Treatment Plant

01 OCT 2014

Who: U.S. Army Corps of Engineers, Transatlantic Afghanistan District

What: The Wastewater Treatment Plant (WWTP) is one component of the $26.8M Eastside Utilities Infrastructure Project at Bagram Airfield. The new WWTP, located adjacent to the existing plant, increases the

Where: Bagram Airfield, Afghanistan

When: 01 October 2014

Why: To increase capacity of current wastewater treatment systems and disposal of waste water

Way Ahead: WWTP is 90% complete and scheduled to finish at the end of CY14. Contractor is making significant progress on commissioning the process equipment and continues to complete civil works including site grading & area drainage.

Commissioning of new Equalization Tank #1

Existing WWTP Aeration Tanks (foreground) and new WWTP (background)

New Headworks structure, first stage of processing , exterior equipment designed to screen and direct effluent to either the new or Existing WWTP