BearWorks BearWorks
MSU Graduate Theses
Summer 2020
Stream Bank and Bar Erosion Contributions and Land Use Stream Bank and Bar Erosion Contributions and Land Use
Influence on Suspended Sediment Loads in Two Ozark Influence on Suspended Sediment Loads in Two Ozark
Watersheds, Southeast Missouri Watersheds, Southeast Missouri
Kayla Ann Coonen Missouri State University, [email protected]
As with any intellectual project, the content and views expressed in this thesis may be
considered objectionable by some readers. However, this student-scholar’s work has been
judged to have academic value by the student’s thesis committee members trained in the
discipline. The content and views expressed in this thesis are those of the student-scholar and
are not endorsed by Missouri State University, its Graduate College, or its employees.
Follow this and additional works at: https://bearworks.missouristate.edu/theses
Part of the Geomorphology Commons
Recommended Citation Recommended Citation Coonen, Kayla Ann, "Stream Bank and Bar Erosion Contributions and Land Use Influence on Suspended Sediment Loads in Two Ozark Watersheds, Southeast Missouri" (2020). MSU Graduate Theses. 3548. https://bearworks.missouristate.edu/theses/3548
This article or document was made available through BearWorks, the institutional repository of Missouri State University. The work contained in it may be protected by copyright and require permission of the copyright holder for reuse or redistribution. For more information, please contact [email protected].
STREAM BANK AND BAR EROSION CONTRIBUTIONS AND LAND USE
INFLUENCE ON SUSPENDED SEDIMENT LOADS IN TWO OZARK WATERSHEDS,
SOUTHEAST MISSOURI
A Master’s Thesis
Presented to
The Graduate College of
Missouri State University
TEMPLATE
In Partial Fulfillment
Of the Requirements for the Degree
Master of Science, Geospatial Sciences in Geography
By
Kayla Ann Coonen
August 2020
ii
Copyright 2020 by Kayla Ann Coonen
iii
STREAM BANK AND BAR EROSION CONTRIBUTIONS AND LAND USE
INFLUENCE ON SUSPENDED SEDIMENT LOADS IN TWO OZARK WATERSHEDS,
SOUTHEAST MISSOURI
Department of Geography, Geology and Planning
Missouri State University, August 2020
Master of Science
Kayla Coonen
ABSTRACT
In-channel sources and storages of fine-sediment such as in banks and bars can influence
sediment loads and overall geomorphic activity in stream systems. However, in-channel
processes and effects on sediment load are rarely quantified in geomorphic or water quality
studies. This study uses a sediment budget approach to assess the influence of bank erosion and
bar deposition on fine sediment loads in Mineral Fork (491 km2) and Mill Creek (133 km2)
watersheds located in the Ozark Highlands in Washington County, Missouri. These watersheds
were disturbed by historical lead and barite mining which included the construction of large
tailings dams across headwater valleys. USEPA’s Spreadsheet Tool for Estimating Pollutant
Loads (STEPL) was used to quantify suspended sediment delivery from upland areas and assess
land use-load relationships. Aerial photographs from 1995 and 2015 were used to identify spatial
patterns of erosion and deposition in bank and bar forms. LiDAR was used to characterize the
channel network and determine bank and bar heights. Field measurements were used to ground-
truth bank and bar heights and fine-sediment composition of alluvial deposits. Historical tailings
dams capture runoff from 27% of Mineral Fork and 28% of Mill Creek drainage areas, trapping
38% and 26% of the suspended sediment load annually, respectively. The total annual sediment
yield for Mineral Fork watershed was 92 Mg/km2/yr with 55% released by bank erosion and
<1% reduced by bar storage. The sediment yield for Mill Creek was 99 Mg/km2/yr with 33%
released by bank erosion and 24% reduced by bar storage. These results indicate that in-channel
processes are important contributors to sediment yields in these watersheds.
KEYWORDS: Bank Erosion, Mining, Sediment Budgets, STEPL, Nonpoint Source Pollution,
Ozark Highlands, Missouri
iv
STREAM BANK AND BAR EROSION CONTRIBUTIONS AND LAND USE
INFLUENCE ON SUSPENDED SEDIMENT LOADS IN TWO OZARK WATERSHEDS,
SOUTHEAST MISSOURI
By
Kayla Ann Coonen
A Master’s Thesis
Submitted to the Graduate College
Of Missouri State University
In Partial Fulfillment of the Requirements
For the Degree of Master of Science, Geospatial Sciences in Geography
August 2020
Approved:
Robert T. Pavlowsky, Ph.D., Thesis Committee Chair
Toby J. Dogwiler, Ph.D., Committee Member
Marc R. Owen, MS, Committee Member
Julie Masterson, Ph.D., Dean of the Graduate College
In the interest of academic freedom and the principle of free speech, approval of this thesis
indicates the format is acceptable and meets the academic criteria for the discipline as
determined by the faculty that constitute the thesis committee. The content and views expressed
in this thesis are those of the student-scholar and are not endorsed by Missouri State University,
its Graduate College, or its employees.
v
ACKNOWLEDGEMENTS
I thank my advisor Dr. Robert Pavlowsky for his expertise, advising, and providing me
with so many great opportunities during my time at Missouri State University. Throughout the
course of this research and my graduate studies. Thank my committee member Marc Owen for
his continued mentoring, knowledge, and support throughout the course of my graduate
assistantship. I also thank my committee member Dr. Toby Dogwiler for his support, editorial
assistance, and technological knowledge as I switched to complete my thesis online.
I thank all of the Ozarks Environmental and Water Resources Institute (OEWRI) staff
(Tyler Pursley, Triston Rice, Josh Hess, Michael Ferguson, Max Hillermann, Jean Fehr, Hannah
Eades, Sarah LeTarte, Hannah Adams, Katy Reminga, and Kelly Rose) for helping me make this
research possible with field and laboratory work, and for all the support during my graduate
studies. I also want to thank the OEWRI staff for the amazing memories at MSU, from the
unproductive lunch hour to the 2:30 coffee breaks. And a special thanks to Sierra Casagrand for
the help in the field, hours of helping me sieve samples, and most importantly the constant edits
and emotional support you provided towards the end of my studies.
I am tremendously grateful to my parents (Julie Wild and Chris Coonen) and step-parents
(Larry Wild and Teresa Coonen) who have given me endless support through all of my years of
schooling. I appreciated the care packages, all the phones calls that ended in “I’m Proud of You,”
and continued assistance for special trips home. Additionally, I thank my brother, Matthew
Coonen, for helping me, even when I was hours away. I could not have gotten to this point in my
academic career without all of you keeping my spirits high while I was away from home.
Lastly, I thank the OEWRI for my graduate assistantship, partial funding for this research
through funding by USEPA Cooperative agreement number V97751001 Big River Riffle-Basin
Monitoring Project for the Big River Superfund Site, and funding for my graduate assistantship
through the USDA-NRCS Missouri Agricultural Watersheds Assessment Project award number
R186424XXXXC030.
vi
TABLE OF CONTENTS
Introduction Page 1
Channel geomorphology influence on sediment loads Page 2 Bank erosion assessments Page 5 Channel sediment concerns in the Ozark Highlands Page 7 Purpose and objectives Page 8
Benefits of this study Page 10
Study Area Page 15
Location Page 15
Geology and soils Page 16
Climate and hydrology Page 17 Settlement and land use history Page 18
Methods Page 28
Channel bank and bar assessments Page 28 Spatial datasets Page 32 Geomorphic spatial analysis at the reach-scale Page 36 Sediment budget development Page 37
Results & Discussion Page 51
Channel delineation and network analysis Page 51
Bank and bar deposit assessment Page 52
Cell-level channel characteristics and trends Page 56 Sediment budget Page 65
Conclusions Page 99
References Page 103
Appendices Page 114 Appendix A. Drainage area and discharge relationships for 32
USGS gaging stations near the study watershed. Page 114
Appendix B. Field assessments. Page 116 Appendix C. Sediment sample information. Page 119 Appendix D. Cell location information in Mineral Fork. Page 120 Appendix E. Cell location information in Mill Creek. Page 128 Appendix F. STEPL inputs. Page 130 Appendix G. USLE inputs for STEPL. Page 131 Appendix H. Large dams in Mineral Fork and Mill Creek
watersheds. Page 132
vii
LIST OF TABLES
Table 1. Floodplain deposition rates in the Ozark Highlands and
Midwest Driftless Area.
Page 11
Table 2. Bank erosion contributions to suspended sediment loads from
watersheds in the U.S. Page 12
Table 3. Sediment yields from selected watersheds in the U.S. Page 13
Table 4. 12-Digit HUC watersheds within Mineral Fork and Mill
Creek. Page 22
Table 5. Descriptions of bedrock geology in Mineral Fork and Mill
Creek watersheds. Page 23
Table 6. Alluvial soils within Mineral Fork and Mill Creek watersheds. Page 23 Table 7. Change in land cover from 2010 to 2017 without mined land. Page 24
Table 8. Aerial photograph characteristics. Page 42 Table 9. Definition of variables for deposit volume and mass
calculations. Page 42
Table 10. Description of sediment budget terms. Page 43 Table 11. Total length of stream network by stream order delineation in
Mineral Fork. Page 73
Table 12. Total length of stream network by stream order delineation in
Mill Creek. Page 73
Table 13. Comparison of antecedent flood Conditions five years prior
to aerial photograph dates. Page 74
Table 14. Active channel width reach assessment. Page 74
Table 15. Height distribution per HUC-12 per stream order for bank
erosion. Page 75
Table 16. Height distribution per HUC-12 per stream order for bank
deposition. Page 76
viii
Table 17. Height distribution per HUC-12 per stream order for bar
erosion. Page 77
Table 18. Height distribution per HUC-12 per stream order for bar
deposition. Page 78
Table 19. Average cell mass for bank erosion. Page 79 Table 20. Average cell mass for bank deposition. Page 80 Table 21. In-channel sediment budget. Page 81
Table 22. Average cell mass for bar erosion. Page 82 Table 23. Average cell mass for bar deposition. Page 83 Table 24. Average cell mass for net in-channel supply. Page 84 Table 25. Sediment load with above dam contributions. Page 85 Table 26. Sediment load below dams. Page 85 Table 27. Sediment budget for below dam area. Page 86 Table 28. Suspended sediment loads below dams from upland erosion
by land use. Page 87
ix
LIST OF FIGURES
Figure 1. Model of sediment storage and remobilization within the
channel.
Page 14
Figure 2. Mineral Fork and Mill Creek watersheds within the Big River
in relation to the Old Lead Belt and the Barite Mining District.
Page 25
Figure 3. Geology of Mineral Fork and Mill Creek. Page 26
Figure 4. Major mined areas in Mineral Fork and Mill Creek
watersheds.
Page 26
Figure 5. Land Use classification from USDA-NASS 2017 for Mineral
Fork and Mill Creek watersheds.
Page 27
Figure 6. Location of field assessment sites. Page 44
Figure 7. Coarse unit thickness in bank deposits. Page 45
Figure 8. Texture of bank deposits. Page 45
Figure 9. Application of error to active channel features. Page 46
Figure 10. Digitized and delineated stream network. Page 47
Figure 11. Comparison of LiDAR bank height to field bank height. Page 47
Figure 12. Cell distribution below dams by stream order. Page 48
Figure 13. Deposit volume to fine sediment mass conversion by cell. Page 49
Figure 14. Mining areas classified as forest from the 2015 DOQQ
aerial photo.
Page 50
Figure 15. Number of cells in each subwatershed by stream order
below dams.
Page 87
Figure 16. Planform analysis for Mineral Fork with bar and bank
erosion and polygons.
Page 88
Figure 17. Planform analysis for Mill Creek with bar and bank erosion
and polygons.
Page 89
Figure 18. Annual peak flood record (1950-2019, 70 years). Page 90
x
Figure 19. Active channel width reach assessment. Page 90
Figure 20. Average bank and bar heights. Page 91
Figure 21. Average active channel width in 2015 and 1995. Page 91
Figure 22. Active channel width change from 1995 to 2015. Page 92
Figure 23. Average bar width in 2015 and 1995. Page 93
Figure 24. Percent bar width change from 1995 to 2015. Page 93
Figure 25. Mass of fine sediment from in-channel contributions. Page 94
Figure 26. Cells highlighting no erosion, erosion, and high erosion cells
that make up 25% of the bank erosion mass.
Page 94
Figure 27. Cells highlighting no erosion, erosion, and high erosion cells
that make up 25% of the bar erosion mass.
Page 95
Figure 28. Cells highlighting deposition, erosion, and high erosion cells
that make up 25% of the erosion mass.
Page 95
Figure 29. Alternating pattern of erosion and deposition upstream to
downstream in the Mill Creek watershed.
Page 96
Figure 30. Mass sediment budget for Mineral Fork watershed (Mg/yr). Page 96
Figure 31. Mass sediment budget for Mill Creek watershed (Mg/yr). Page 97
Figure 32. In-channel contributions to sediment loads. (A) Bank
erosion compared to upland erosion loads; (B) Bar erosion
compared to upland erosion loads; and (C) In-channel load
contribution to total load.
Page 98
1
INTRODUCTION
Eroding stream banks can be significant sources of fine sediment to streams that increase
water quality concerns, typically supplying 20% to 80% of the total suspended sediment load at
the watershed outlet (Harden et al., 2009; De Rose and Basher, 2011; Kessler et al., 2013;
Spiekermann et al., 2017). Bank erosion can occur gradually as the channel migrates back and
forth across the valley floor over relatively long periods of time (Figure 1) (Trimble, 1983;
Kondolf, 1997; De Rose and Basher, 2011). In many streams, it is a natural process for point bar
and floodplain deposition to be on the opposite side of cut-bank erosion in order to maintain a
constant channel width and shape (Kondolf, 1997). However, watershed-scale disturbances can
increase flood discharge, bank failures, or sediment loads, which can accelerate bank erosion
rates greater than 2 m/yr in smaller streams (Harden et al., 2009; Rhoades et al., 2009; De Rose
and Basher, 2011; Martin and Pavlowsky, 2011; Kessler et al., 2013; Janes et al., 2017;
Spiekermann et al., 2017).
Once eroded sediment is in transport, it is usually deposited relatively soon on channel
beds, bars, and floodplains. Bank and floodplain sediment can remain in storage for a year to
centuries before being remobilized again (Meade, 1982). Bank erosion can also exacerbate
channel instability by causing channel instability through channel widening, flow turbulence
along bends, and release of coarse sediment (Ferguson et al., 2003; Michalkova et al., 2011). The
additional coarse sediment load can accelerate bar deposition and create flow deflection and
more erosive currents in the channel (Jacobson and Primm, 1997; Blanckaert, 2011; Martin and
Pavlowsky, 2011). Therefore, bank erosion processes can be both a cause and effect of the
geomorphic and sediment characteristics of a stream channel.
2
The flood regime of a stream system will tend to control its shape and erosional potential
(Rosgen, 1994). High rates of bank erosion are commonly caused by high-magnitude, low-
frequency floods. However, flood effects on sand and gravel bars in rivers are not as well
understood (Hagstrom et al., 2018). Nevertheless, assessments of bank erosion rates and their
causal factors have been described in the literature (e.g., De Rose and Basher, 2011; Kessler et
al., 2013; Janes et al., 2017; and Spiekermann et al., 2017). Many studies of bank and bar
behavior have been completed for individual stream reaches. However, there have been fewer
attempts to quantify the spatial distribution of bank erosion inputs from different locations within
the channel network in relation to bank deposition and other in-channel sediment storages such
as bench and bar deposits (Panfil and Jacobson, 2001; Martin and Pavlowsky, 2011; Owen et al.,
2011).
Channel geomorphology influence on sediment loads
Sediment is recognized as the number one nonpoint source pollutant in the United States,
with 70% of fine sediment in impaired streams coming from past and present human activities
(Brown and Froemke, 2012; USEPA, 2018a). However, the important role of stream
geomorphology as a natural control on suspended loads, such as adjustments in channel form and
sediment storage, is commonly overlooked in nonpoint source (NPS) pollution models that
assess water quality trends in watersheds (Nejadhashemi et al., 2011; Fox et al., 2016; Beck et
al., 2018). Geomorphic processes involving the formation and adjustments of fluvial landforms
by sediment erosion and deposition can significantly change stream sediment loads at timescales
from years to decades (Jacobson and Gran, 1999; Knighton, 1998; Hession et al., 2003).
Increased runoff and bed instability can cause channel enlargement and the release of sediment
3
to the watershed, while impoundments and floodplain deposition can trap sediments (Ward and
Elliot, 1995; Knighton, 1998; James, 2013). Additionally, floodplains can be a major sink for
fine sediment with annual sedimentation rates typically ranging from 0.1 to 15 cm/yr (Table 1).
In some watersheds, the sediment delivery rates to streams have decreased significantly since the
period of highest land use disturbances that occurred almost a century ago due to improved land
management practices, bank stability structures, and the regrowth of vegetation (Trimble,
1983,1999; Troeh et al., 2004). Conversely, bank erosion inputs and channel deposition can
increase after a period of channel recovery or the implementation of stabilization practices in
some cases (Trimble, 1999; Schenk and Hupp, 2009; Gillespie et al., 2018). Sediment budgets
measure the amount of sediment eroded and stored in different sections of a watershed (i.e.
uplands, headwaters, floodplains, and in-channel processes) (Trimble, 1999; Lauer et al., 2017).
Sediment budgets are important assessment tools used to evaluate sediment fluxes and storage in
a watershed by quantifying the amounts of sediment being stored in and eroded from different
landform components (Phillips, 1991; Beach, 1994; Trimble, 2009).
An important contribution to a sediment budget can be the release of excess sediment
previously deposited on floodplains. Historical land use practices associated with widespread
agricultural settlement including the clearing of forests, soil disturbance by cultivation, and
construction of road networks released large volumes of fine sediment from hillslopes for
deposition on floodplains in the Midwest USA (Knox, 1972; Trimble, 1983). These “legacy”
sediment deposits were stored in floodplains and other valley floor locations at depths up to
several meters (Knox, 1972; Lecce, 1997; Wilkinson and McElroy B.J, 2007; Owen et al., 2011;
James, 2013; Donovan et al., 2015; Pavlowsky et al., 2017). Flow obstructions, such as mill
dams, increased the rate of legacy sediment deposition in some regions (Trimble and Lund,
4
1982; Walter and Merritts, 2008; Schenk and Hupp, 2009). In tributaries, the higher banks
formed by legacy deposits produced deeper flows that were able to generate higher stream
powers and increase bank erosion rates for more than 50 years (Knox, 1987; Lecce, 1997; Ward
et al., 2016). In mining districts, where relatively large volumes of tailings were introduced to
nearby rivers, legacy floodplain deposits were able to store metal-contaminated sediment from
100 to 1,000 years until remobilized by bank erosion (Marron, 1992; Rhoades et al., 2009; Lecce
and Pavlowsky, 2014). Even after conservation practices were implemented to reduce soil
erosion, legacy sediment stored in valleys was still being remobilized by bank erosion (Trimble,
1999; Troeh et al., 2004).
Typically, hydrologic watershed models are used to determine suspended sediment loads
from predicted upland soil erosion yields with the relative contribution to stream loads that are
decreasing with downstream distance (Brierley et al., 2006; Baartman et al., 2013; James, 2013).
In general, suspended sediment loads tend to increase with rainfall amount, intensity, and land
use characteristics that increase storm water routing, runoff rates and erosion (Lawler, 1993;
Brown and Froemke, 2010, 2012; Emili and Greene, 2013; USEPA, 2018b). Trimble (1983)
assessed sediment contributions to the Coon Creek watershed, Wisconsin from upland erosion,
main valleys, and tributaries. The sheet and rill erosion of uplands in Coon Creek were estimated
using the universal soil loss equation (USLE) in the form: A = RKLSCP, where A is equal to the
amount of soil loss in tons per acre per year, R is the rainfall factor, Kf is the soil erodibility
factor, L is the slope-length factor, S is the slope-gradient factor (S), C is the land use and land
management factor, and P is the erosion control practice factor (Trimble and Lund, 1982; Troeh
et al., 2004). Today, models like the Spreadsheet Tool for Estimating Pollutant Loads (STEPL)
incorporate the USLE into calculations of sediment load outputs from watersheds with variable
5
land uses and soil cover (Nejadhashemi et al., 2011; Park et al., 2014; WiDNR, 2014; Liu et al.,
2017). However, stream bed and bank erosion inputs are rarely evaluated directly in watershed
models and are only used to balance variations in modeled tributary inputs and assumed channel
conditions (Trimble, 1999; Bracken et al., 2015). The literature reported that streambank erosion
and other in-channel contributions such as bed material accounted for 7-92% of the annual
suspended sediment load in a watershed (Table 2) (Fox et al., 2016).
Bank erosion assessments
Over the past several decades, the methods for measuring bank erosion rates have
advanced from field work to GIS methods (Lawler, 1993). Field methods have long been
employed to study bank erosion (Leopold, 1973). Cross-sectional surveys can be used to
measure active channel widths and areas (Xia et al., 2014). Additionally, repeat cross-sectional
surveys over time can be used to assess bank erosion rates between floods (Julian and Torres,
2006). Erosion pins are deployed to estimate bank erosion rates where rebar pins are inserted into
the bank, leaving a known length exposed to provide a ‘benchmark’ against which bank erosion
can be measured as they become more exposed (Couper et al., 2002; Harden et al., 2009;
Foucher et al., 2017; Beck et al., 2018). Problems can arise with the use of erosion pins to
evaluate short-term (months to years) bank erosion rates since negative values can result from
the deposition of sediment during high flows, upper bank failures covering lower bank pins, and
human interference (Couper et al., 2002). More frequent observations can reduce erosion pin
error, but also add more cost and effort for the project (Couper et al., 2002; Xia et al., 2014).
Historical aerial photography is more commonly used now to track bank locations over
time to determine streambank erosion rates (Rhoades et al., 2009; Martin and Pavlowsky, 2011).
6
Typically, bank line locations are digitized and compared between two dates of aerial
photographs (Mount and Louis, 2005; De Rose and Basher, 2011; Spiekermann et al., 2017).
However, digitizing needs to be completed at a relatively large and consistent scale of 1:1,000 or
1:600 to reduce worker and photograph errors during manual digitizing (Rhoades et al., 2009;
Spiekermann et al., 2017). When planform surveys for different years are combined to identify
areas of erosion and deposition in the channel, tiny polygon “slivers” may occur and these are
likely insignificant for use as a survey result. Those areas can be identified by spatial error
analysis and ignored for use in erosion inventories (De Rose and Basher, 2011). In general, while
digitizing errors do occur, they are assumed to be random and cancel one another out (Mount and
Louis, 2005; De Rose and Basher, 2011; Spiekermann et al., 2017). However, during
georeferencing the root-mean-square error (RMSE) is calculated for distances between ground-
points compared between two photographs to evaluate spatial errors for feature measurements
(Mount and Louis, 2005; Janes et al., 2017). The typical range for RMSE errors in these studies
was two to five meters for the georeferenced aerial photographs.
The use of aerial photographs limits assessment of the channel migration process to a
two-dimensional result. By incorporating a high resolution light detection and ranging (LiDAR)
derived digital elevation model (DEM), bank heights can be estimated and used to calculate a
volume for the eroded banks (Rhoades et al., 2009; Kessler et al., 2013). The main problem
associated with incorporating LiDAR to the aerial photography is having data sets from the same
time periods. The collection data for the photographs and LiDAR are usually months or years
apart, potentially altering the actual geomorphic characteristics of the period being measured to
some degree (Kessler et al., 2012; Spiekermann et al., 2017). LiDAR also has errors depending
on how the dataset was mosaiced from different flight series and the degree to which water
7
surface reflections can give false heights on streambanks. Water reflection can be corrected in
streams by using an assumed channel geometry or field data to correct the bank heights (Kessler
et al., 2012; Podhoranyi and Fedorcak, 2014).
Channel sediment concerns in the Ozark Highlands
Historical farm and logging land clearing by European settlers caused increased soil
erosion on uplands and in tributary valleys increasing fine and coarse sediment loads in streams
of the Ozark Highlands of Missouri (Jacobson, 1995; Jacobson and Gran, 1999; Panfil and
Jacobson, 2001; Owen et al., 2011; Reminga, 2019). These disturbances were magnified by
prevailing topographic conditions including rolling hills with steep slopes, narrow valleys, and
streams with gravel bed loads (Nigh and Schroeder, 2002). Over several meters of silty sediment
were deposited on floodplains along some rivers that drained agricultural areas in the Ozark
Highlands (Owen et al., 2011; Pavlowsky et al., 2017). However, these land use changes also
increased the deposition rate and supply of coarser sand and gravel main channels and their
tributaries (Jacobson and Primm, 1997; Jacobson and Gran, 1999; Martin and Pavlowsky, 2011).
The coarse sediment deposits were located in the channel within persistent disturbance zones that
were reactivated by large floods (Panfil and Jacobson, 2001; Lauer et al., 2017). Present-day
gravel storages in the channel relate more to the influence of historical disturbances rather than
recent land use impacts (Panfil and Jacobson, 2001). Nevertheless, both legacy sediment and
recent gravel bars can increase channel instability in disturbance zones. These geomorphic
conditions can increase bank erosion rates or the storage rate of fine sediment on bars or benches
along the river channel (Martin and Pavlowsky, 2011; Lauer et al., 2017). Therefore, fine-
8
grained sediment storage and remobilization rates should be included to calculate accurate
sediment loads and sediment budgets in Ozark watersheds.
In the Ozark Highlands, there are no published studies that attempt to link the sediment
being stored and transported through a stream network to stream loads. One related example
would be the role that mining sediment storage plays in controlling sediment contamination
trends in the Big River, southeast Missouri which was contaminated by large-scale lead mining
from 1895 to 1972 (Pavlowsky et al., 2010, 2017). Another related example used the floodplain
core records to understand how legacy sediment deposition rates related to historical land use
changes along the James River, southwest Missouri (Owen et al., 2011). While there are several
studies that provide some information about suspended sediment yields from Missouri
watersheds, none describe how sediment is being routed through the channel system (Table 3). In
addition, there is a gap in knowledge in our understanding of how channel processes, sediment
storage, and land use factors control suspended sediment loads and associated pollutants.
Further, watershed managers in southeast Missouri are concerned about channel instability, bank
erosion, and sediment contamination by lead from mining operations since the 1700s in rural
watersheds with a long history of soil disturbance (MDNR, 2006, 2008, 2014; Mugel, 2017)
Purpose and objectives
The purpose of this study is to assess and evaluate the contributions of bank and bar
erosion to annual sediment loads of Mineral Fork (491 km2) and Mill Creek (133 km2)
watersheds in the Ozark Highlands, Missouri. Since there are no published studies available for
the Ozarks, this study will fill this gap and offer a methodology for assessing the watershed
trends in channel erosion where management efforts are needed to reduce bank erosion inputs.
9
Bank erosion rates were determined using historical aerial photography and LiDAR data to
evaluate to sediment loads derived from a simple NPS watershed model, the Spreadsheet Tool
for Estimating Pollutant Loads (STEPL) (Tetra Tech, 2018; USEPA, 2019). These watersheds
have been experiencing a decrease in water quality due to runoff and soil disturbances from
historical land-clearing and lead and barite mining, and cattle grazing agriculture (Jacobson and
Primm, 1997; Mugel, 2017; Schumacher and Smith, 2018; USEPA, 2018a). Environmental
managers are concerned about excess sedimentation in Ozark streams from bank, sheet, and rill
erosion (Adamski et al., 1995; MDNR, 2014, 2016, 2018).
The study watersheds are representative of landscape characteristics and stream network
conditions of the Salem Plateau, the largest sub-region of the Ozark Highlands (Nigh and
Schroeder, 2002; USDA-NRCS, 2006). They are affected by rural conditions including low
income, failure of septic systems, and grazing agriculture on slopes and within riparian corridors
(Jacobson and Primm, 1997; MDNR, 2014; USDA, 2017). Large barite tailings ponds and dams
built between 1935-1991 to trap mine tailings and eroding soil are distributed throughout the
middle and lower portions of these watersheds (Mugel, 2017; MSDIS, 2019). Over 27% of
Mineral Fork and 28% of Mill Creek watersheds are composed of obstructed drainage areas by
tailings dams up to 31 m high (MSDIS, 2019). Given that these dams trap 100% of the sediment
and water from above drainage areas, they may affect sediment loads downstream. Moreover,
mining disturbed lands can cause stream channel instability with excessive erosion and
sedimentation (Mugel, 2017).
Like most of the Ozark Highlands, Mineral Fork and Mill Creek transport a bedload of
sand and gravel that form bar complexes associated with local channel aggradation and high
rates of bank erosion and channel widening (Martin and Pavlowsky, 2011). These geomorphic
10
characteristics suggest that bank erosion and bar sedimentation may play an important role in
fine sediment supply in these watersheds. The specific objectives of this study are:
1) Assess geomorphic characteristics of Ozark streams using LiDAR, aerial
photography, and some ground-truthing involved bank measurements in the field;
2) Determine the spatial distribution and mass of fine sediment of channel erosion and
deposition within watersheds; and
3) Develop a sediment budget for each watershed that accounts for the contributions of
channel processes including bank and bar erosion and sedimentation to sediment
loads.
Benefits of this study
Sediment transport and storage can have long-term implications for geomorphic activity
and water quality in streams. This study will contribute to a better understanding of sediment
sources and loads in southeastern Missouri watersheds and aid in evaluating the effects of
historical mining disturbances on channel stability, bank erosion, and sediment loads in Barite
Mining District. Channel processes are often excluded from sediment loads in NPS assessments.
The methodology and results presented in this study will advance our understanding for using
sediment budget analysis to improve NPS assessments in small- to medium-sized watersheds in
the Ozarks. Moreover, it will use fluvial geomorphology concepts to link land use changes to
channel behavior and sediment sources throughout the drainage network. This will provide a
better understanding of the long-term recovery of stream channels from past land disturbances
and anthropogenic sediment inputs.
11
Table 1. Floodplain deposition rates in the Ozark Highlands and Midwest Driftless Area.
Stream Drainage Area
(km2)
Overbank Deposition
Rates (cm/yr) Reference
SW Ozark Highlands
Honey Creek, MO 174 0.6-0.8 Carlson, 1999 James River, MO 637 0.5 Owen et al., 2011
SE Ozark Highlands
Big River, MO 2,500 0.7-1.0 Pavlowsky, 2013
Big River, MO 2,500 0.2-3.4 Keppel et al., 2015
Big River, MO 2,500 0.1-1.0 Pavlowsky and Owen, 2015 Big River, MO 626-2,500 1.3-3.0 Pavlowsky et al., 2017 Big River, MO 2,500 0.8 Jordan, 2019
Big Barren Creek, MO 191 0.2-0.6 Reminga, 2019 Midwest Driftless Area
Kickapoo Valley, WI 1,989 1.52 Happ, 1944 Coon Creek, WI 350 1.5-15.0 Trimble and Lund, 1982
Galena River, WI, IL 340-400 0.8-1.9 Magilligan, 1985 Shullsburg Branch, WI, IL 26 0.3-1.3 Knox, 1987
Galena River, WI, IL 700-170,000 0.5-3.4 Knox, 2006
12
Table 2. Bank erosion contributions to suspended sediment loads from watersheds in the U.S.
Watershed Drainage
Area
(km2)
Suspended
sediment
load from
streambanks
(%)
Reference
Delaware Estuary, PA 35,066 39 Meade, 1982 Sacramento River, CA 7,100 59 USACE, 1983
Obion Forked Deer River, TN 2,000 81 Simon and Hupp, 1986 East Nishnabotna River, IA 2,300 30-40 Odgaard, 1987
Des Moines River, IA 41,000 30-40 Odgaard, 1987 Blue Earth River, MN 1,550 31-44 Sekely et al., 2002
James River, MS 74 78 Simon et al., 2002 Yalobusha River, MS 4,000 90 Simon and Thomas, 2002
Shades Creek, AL 190 71-82 Simon et al., 2004 Blue Earth River, MN 1,550 23-56 Thoma et al., 2005 Le Sueur River, MN 2,880 11-14 Gran et al., 2009
Lower Hinkson Creek, MO 231 67 Huang, 2012 Walnut Creek, IA 52 23-53 Palmer et al., 2014
Piedmont Streams, Baltimore County, MD 155 70 Donovan et al., 2015
13
Table 3. Suspended sediment yields from selected watersheds in the U.S.
Stream Drainage
Area (km2) Sediment Yield
(Mg/km2/yr) Floodplain
Storage (%) Reference
Waterfall Creek, TN 2 13 N/A Hart and Schurger, 2005 Terry Creek, TN 3 8 N/A Hart and Schurger, 2005 Upper Pigeon Roost Creek, TN 9 111 N/A Hart and Schurger, 2005 Wilson's Creek, MO 46 30 N/A Hutchison, 2010 Pearson Creek, MO 54 18 N/A Hutchison, 2010 Upper James River, MO 637 39 N/A Hutchison, 2010 Finley Creek, MO 676 9 N/A Hutchison, 2010 Middle James River, MO 1,197 87 N/A Hutchison, 2010 Le Suer River, MN 2,880 47 N/A Day et al., 2013 Lower Mississippi River, LA 276,460 218 N/A Turner and Rabalais, 2004 Missouri River 1,300,000 48 N/A Turner and Rabalais, 2004 Indian Creek, MN 17 118 65 Beach, 1994 Hay Creek, MN 127 258 87 Beach, 1994 Beaver Creek, MN 144 365 64 Beach, 1994 Coon Creek, WI 360 103 37 Trimble, 1999 Upper Tar, Piedmont, NC 1,119 48 92 Phillips, 1991 Upper Neuse, Piedmont, NC 1,997 64 84 Phillips, 1991 Deep River, Piedmont, NC 3,748 60 91 Phillips, 1991 Haw River, Piedmont, NC 4,217 46 93 Phillips, 1991 Minnesota River, MN 45,000 17 25-50 Lauer et al., 2017
14
Figure 1. Model of sediment storage and remobilization within the channel (Kondolf, 1997).
15
STUDY AREA
Location
The Mineral Fork Watershed (HUC-10# 0714010402) and Mill Creek Watershed (HUC-
12# 071401040301) are located in Washington County, Missouri within the Big River basin
(HUC-8# 07140104) (Figure 2) (USGS, 2018a). In addition to the Mill Creek watershed, Mineral
Fork contains six 12-Digit Hydrologic Unit Code (HUC) watersheds within its boundaries (Table
4). All together these two watersheds contain seven 12-Digit HUC subwatersheds in the study
area as follows: Mineral Fork (MF), Clear Creek-Mineral Fork (CCMF), Old Mines Creek
(OMC), Mine a Breton Creek (MBC), Fourche a Renault (FR), Sunnen Lake-Fourche a Renault
(SLFR), and Mill Creek (MC). The whole Mineral Fork watershed has a drainage area of 491
km2, total channel length of 433 km, and drainage density of 0.88 km/km2. The Mill Creek
watershed has a drainage area of 133 km2, total channel length of 198 km, and drainage density
of 1.49 km/km2. These watersheds drain in the Meramec River Hills Subsection of the of the
Salem Plateau Division of the Ozark Highland Province (Nigh and Schroeder, 2002). Maximum
elevation of headwaters is about 430 masl with base-level elevations near 150 masl at the
confluence of Big River. The local relief in the study area is typically greater than 45 m and rises
to more than 76 m along the major valleys of Mineral Fork (Nigh and Schroeder, 2002). Streams
within this region have incised through horizontally-bedded sedimentary strata, mainly
composed of dolomite and limestone with some shale and sandstone (Panfil and Jacobson, 2001;
Schumacher and Smith, 2018). In general, main channels and major tributaries of both
watersheds flow in deep and narrow valleys, with relatively high gradients, and in bedrock-
16
influenced riffle-pool streams with gravelly beds (Jacobson, 1995; Jacobson and Primm, 1997;
Skaer and Cook, 2005).
Geology and soils
Both watersheds drain in the Salem Plateau of the Ozark Highlands, which contain
Cambrian and Ordovician sedimentary rocks composed primarily of dolomites, chert, and
sandstones (Figure 3) (Adamski et al., 1995; USDA-NRCS, 2006). The Cambrian Eminence and
Potosi dolomites make up 74% of the surficial bedrock in Mineral Fork and Mill Creek
watersheds (Table 5). This formation was mineralized by hydrothermal fluid interaction along
orogenic belts during the Cambrian period and has been mined for shallow deposits of galena,
smithsonite (zinc carbonate ore), and barite (barium sulfate ore) since at least the early 1800s in
the Southeast Missouri Barite District in Washington County (Gregg and Shelton, 1989; Mugel,
2017).
Upland soils in Washington County, Missouri are generally formed in parent materials
consisting of a thin layer of silty Pleistocene loess over cherty clay residuum formed from the
weathering of the dolomites and limestones in the region (Skaer and Cook, 2005). The residuum
in the Ozarks is about 3 to 12 m thick, although locally it can be greater than 60 m (Seeger,
2006). Most of the uplands soils occur on gently-sloping to moderately-steep slopes with a
fragipan and gently-sloping to very-steep slopes containing chert fragments (Nigh and
Schroeder, 2002). In total, these watersheds contain 50.1 km2 of floodplain and alluvial terrace
soils with the Cedargap series occupying 70% of the floodplain soil area (Table 6). The
Haymond and Kaintuck series occur on larger floodplains, where the Cedargap and Bloomsdale
soils are commonly found on the valley floor of the narrow upstream reaches (Skaer and Cook,
17
2005). Upper stream bank deposits were formed by overbank deposition and are composed of
silt loam to fine sandy loam with >90% <2 mm sediment particles (Skaer and Cook, 2005).
Lower bank units were typically formed by bar and bench deposition (now stratigraphically
buried by overbank floodplain deposits) that are composed of coarser materials with loam to
sandy loam textures with <80% <2 mm including gravel- and cobble-sized fragments (Skaer and
Cook, 2005).
Climate and hydrology
Southeastern Missouri has a moist continental climate region (Peel et al., 2007; Skaer and
Cook, 2005). From 1990-2019, the mean monthly rainfall in Southeast Missouri ranged from
6.5- 13.7 cm with an average of 9.7 cm per month. The highest monthly rainfall totals (>10 cm)
occur in May, with typically less monthly precipitation (<9 cm) during the winter in December,
January, and February (MRCC, 2018). Snowfall occurs from November to March with totals
depths from 1.8 to 8.1 cm per month, with an average of 5.1 cm/month during the winter.
Between 1990 and 2019, the average annual temperature ranged from 12-15°C with an average
of 13°C. Over that period, average monthly temperatures range from -0.6°C in January to 25°C
in July (MRCC, 2018). Over the last 30 years, overall precipitation and temperature trends show
consistent, slightly increasing temperatures and overall rainfall since 1990 (MRCC, 2018).
Streamflow typically peaks in spring and rapidly declines through the summer. There are
no USGS gages located in the two watersheds. The mean annual discharge is 5.7 m3/s for
Mineral Fork and 1.6 m3/s for Mill Creek based on regional drainage area-discharge regression
equations developed from available USGS gaging data (Appendix A). The estimated maximum
annual discharge is 488 m3/s for Mineral Fork and 137 m3/s for Mill Creek. The uplands contain
18
karst features, and most low order stream channels are ephemeral or perennial “losing” streams
(USDA-NRCS, 2006). There are no natural lakes or ponds in the study area, however many
ponds have been constructed to trap mine tailings, support recreation, or supply water for
livestock purposes (Nigh and Schroeder, 2002).
Settlement and land use history
Historical land use. Oak-woodlands was the primary vegetation cover type in the pre-
settlement period in the study area with denser deciduous and pine forests occupying steep valley
slopes and bottoms (Nigh and Schroeder, 2002). These forests were logged and cleared to
varying extent across the Ozarks to support the settlement and economic growth of the region.
The second-growth forest was denser and with different composition compared to pre-settlement
conditions and was first harvested in the 1950s (Jacobson and Primm, 1997; Nigh and Schroeder,
2002).
The first phase of European settlement in the study area was by French miners in the
early to middle 1700s who worked shallow lead pits for galena around the towns of Potosi and
Old Lead Mines located in the Mineral Fork watershed (Mugel, 2017). The French mining
operations were abandoned after several years leaving only relatively small farming villages. The
second phase of European settlers began clearing the flatter uplands and valley floors for pasture
or row-crop agriculture around the 1840s (Jacobson and Primm, 1997). However, when the Civil
War ended and railroads extended lines into the region, farming activity increased after 1865
including more farm acreage, clearing and cultivation of hillslopes, and stripping the land for
mining purposes (Nigh and Schroeder, 2002). The resulting vegetation and soil disturbances
increased runoff and soil erosion rates significantly in many Ozark watersheds causing soil loss
19
and fertility problems, headwater stream incision, and accelerated delivery of gravel sediment to
main channels (Jacobson, 1995; Jacobson and Gran, 1999).
Many farmers would work or lease out shallow pit mines on their land during the winter
for galena and barite (locally known as “tiff”) in the 1800s. Then, more modern mining
operations moved into the district beginning in the early 1930s (Mugel, 2017). Surface soils
contained barite as residual deposits which were separated from the clayey host material by
processing in grinding and washer plants near Mineral Point (on Mill Creek) and northeast of
Potosi (along tributaries of Mineral Fork) (Mugel, 2017). The mining wastes were diverted into
tailings ponds within Mineral Fork and Mill Creek watersheds (Smith and Schumacher, 1993).
There are over 60 abandoned tailings ponds in the Barite District today storing a total of 39
million tons of tailings wastes (Mugel, 2017). Large tailings ponds and dams built between 1935-
1991 to trap mine tailings and eroding soil are distributed throughout the middle and lower
portions of these watersheds (Figure 4) (Mugel, 2017; MSDIS, 2019). There are 5.2 km2 of
ponds and a combination of 40 active wet and dry dams between the two watersheds. These
tailings dams range from 4 m to 31 m high with drainage areas ranging from 0.1 to 68.8 km2
(MSDIS, 2019). One of the largest ponds with a dam in the study area is Sunnen Lake in Mineral
Fork watershed which was developed for recreation and traps about one-half of the inflowing
sediment load (USGS, 2018a). Over 27% of the combined drainage area of the study watersheds
is located behind large tailings dams that are assumed to retain most of the runoff and trap all the
sediment flowing to them. Historically, there were probably more operating dams, but many
have filled in with sediment or were breached in recent time (MSDIS, 2019). Overall, about 12%
(80 km2) of the land area for these two watersheds was disturbed by surface barite mining
including pits, ponds and tailings dams (Schumacher and Smith, 2018). Approximately 1.8
20
million tons of barite were produced in the district until the last mine closed in 1998
(Schumacher and Smith, 2018).
Legacy over-bank deposits most likely occur along the floodplains of Mineral Fork and
Mill Creek below areas disturbed by cultivation, mining, and roadways. Field observations made
during this study indicate that buried A-horizons can be found up to one meter deep in the cut-
bank profiles suggesting that eroded soil was deposited on older floodplains since settlement
(Pavlowsky et al., 2017; Jordan, 2019). Tailings dams can create flow obstructions which can
trap sediment and increase the rate of legacy sediment deposition along streams (Trimble and
Lund, 1982; Walter and Merritts, 2008; Schenk and Hupp, 2009). For streams in smaller
watersheds, the higher banks formed by legacy deposits may produce deeper flows that can
generate higher stream powers and increase bank erosion rates (i.e. Knox, 1987; Lecce, 1997;
Ward et al., 2016).
Land use and land cover. Forestland is the major land use within these watersheds
based on the 2010-2017 National Agricultural Statistics Service (NASS) Crop Database (Table
7). Deciduous forest covered 79.3% of the watershed in 2017 (Figure 5). Today, wider valley
bottoms are usually cleared for agriculture (Nigh and Schroeder, 2002). Agricultural land
occupies 9.3% of the land area in the study, with pastureland covering 9% and 0.3% as cropland.
Cattle and poultry are the main types of livestock produced in Washington County (USDA,
2017). Cropland which includes row crops, double crops, small grains, and fallow ground only
covers about 0.1% of the area and alfalfa and other hay crops about 0.2% of the watershed
(USDA-NASS, 2018). The remainder of the watershed area is developed land (5.4%) or in
wetlands and open water (0.6%). Most of the urban area is formed in Potosi, Missouri
(population of 2,626 in 2017) which drain into both Mineral Fork and Mill Creek watersheds and
21
Mineral Point, Missouri (population of 354 in 2017) located east of Potosi, which drain into Mill
Creek (Figure 5) (US Census Bureau, 2017).
22
Tab
le 4
. 1
2-D
igit
HU
C w
ater
shed
s w
ith
in M
iner
al F
ork
an
d M
ill
Cre
ek.
*A
d =
dra
inag
e ar
ea
Wat
ersh
edA
d*
Ad B
elow
% A
d b
ehin
d
Wat
ersh
eds
Abbre
viat
ions
Typ
e(k
m2)
Dam
s (k
m2)
Dam
sU
rban
Agr
icul
ture
Fore
stM
ined
Mill
Cre
ekM
C12-D
igit
HU
C132.6
96.2
28
76
72
15
Min
eral
Fork
MF
12-D
igit
HU
C51.5
42.3
18
33
90
4
Cle
ar C
reek
-Min
eral
Fork
CC
MF
12-D
igit
HU
C98.8
75.6
24
34
92
2
Old
Min
es C
reek
OM
C12-D
igit
HU
C48.1
39.4
17
76
75
11
Min
e a
Bre
ton
Cre
ekM
BC
12-D
igit
HU
C123.6
105.4
15
815
73
4
Four
che
a R
enau
ltF
R12-D
igit
HU
C100.7
96.8
44
17
80
0
Sun
nen
Lak
e-F
our
che
a R
enau
ltS
LF
R12-D
igit
HU
C68.8
68.8
100
47
88
0
Min
eral
Fork
(W
hole
)M
F-W
hole
10-D
igit
HU
C490.5
428.6
27
510
82
3
Lan
d u
se (
%)
23
Table 5. Descriptions of bedrock geology in Mineral Fork and Mill Creek watersheds.
Unit Name Symbol Geologic Age Primary Rock
Type Secondary Rock
Type %
Area Eminence and Potosi dolomite Cep Cambrian Dolomite Chert 74 Gasconade dolomite Og Ordovician Dolomite Sandstone 21 Roubidoux sandstone and dolomite Or Ordovician Sandstone Chert, Dolomite 4 Elvins Bonne Terre Dolomite Ceb Cambrian Dolomite Conglomerate 1
Table 6. Alluvial soils within Mineral Fork and Mill Creek watersheds.
Soil Series Texture Landform Flood
Frequency Soil Order
Area
(km2) % of
Area Cedargap gravelly silt loam Floodplain
Frequently
Flooded Mollisols 34.83 69.7
Racket loam Floodplain Frequently
Flooded Mollisols 4.28 8.6
Razort silt loam Floodplain Occasionally
Flooded Alfisols 3.82 7.6
Bloomsdale silt loam Floodplain Frequently
Flooded Alfisols 2.88 5.8
Haymond silt loam Floodplain Frequently
Flooded Inceptisols 1.77 3.5
Higdon silt loam Stream terrace Occasionally
Flooded Alfisols 0.64 1.3
Sturkie silt loam Floodplain Occasionally
Flooded Mollisols 0.61 1.2
Kaintuck-Relfe
complex sandy loam Floodplain
Frequently
Flooded Entisols 0.62 1.2
Horsecreek silt loam Stream terrace Occasionally
Flooded Alfisols 0.26 0.5
Racoon-Freeburg
complex silt loam Stream terrace
Occasionally
Flooded Alfisols 0.21 0.4
Deible silt loam Stream terrace Rarely
Flooded Alfisols 0.09 0.2
24
Table 7. Change in land cover from 2010 to 2017 without mined land.
% of Land Cover 2010 2017 % Change
Forest 84.1 84.7 0.0
Pastureland 10.3 9.0 -12.3
Urban 5.0 5.4 4.3
Cropland 0.0 0.3 29.7
Water/Wetlands 0.7 0.6 -9.3
*(USDA-NASS, 2018)
25
Figure 2. Mineral Fork and Mill Creek watersheds within the Big River in relation to the Old
Lead Belt and the Barite Mining District.
26
Figure 3. Geology of Mineral Fork and Mill Creek.
Figure 4. Major mined areas in Mineral Fork and Mill Creek watersheds.
27
Figure 5. Land Use classification from USDA-NASS 2017 for Mineral Fork and Mill Creek
watersheds.
28
METHODS
This study assessed the volumetric changes of bank and bar landforms between 1995 and
2015 and then converted the volumes into masses of eroded and deposited fine sediment. The
masses of in-channel fine sediment erosion and storage were then compared with sediment
supplied by upland erosion and stream loads derived from STEPL modeling to develop a
sediment budget for the Mineral Fork and Mill Creek watersheds. The sediment budget was used
to assess the importance of bank and bar sediment processes and fine sediment load contributions
compared to total sediment transport for the watershed. The methods of the study are described
below including channel bank and bar assessment, spatial data sets and analysis, geomorphic
spatial analysis, STEPL sediment load modeling, and sediment budget framework.
Channel bank and bar assessment
Ozark streambanks are typically formed in floodplain deposits composed of two
sedimentary units, a finer-grained silty unit overlying a coarser-grained loamy unit containing
gravel (Panfil and Jacobson, 2001; Skaer and Cook, 2005; Owen et al., 2011). The upper unit
was formed by overbank flood deposition of suspended sediment composed of silt and clay with
lesser amounts of sand. The lower unit was formed by the deposition of bed-load along the
channel bed with finer sediments filling pore spaces (Panfil and Jacobson, 2001; Owen et al.,
2011). Profile descriptions of floodplain parent materials with varying texture in the study area
include Cedargap (gravelly), Kaintuck (sandy), and Haymond (silty) soil series (Skaer and Cook,
2005). In contrast, bar deposits are coarser than adjacent bank deposits and are generally
composed of sand and gravel (2-64 mm) with some cobble-sized clasts (64-256 mm) and finer
29
materials (<63 um) (Panfil and Jacobson, 2001; Pavlowsky et al., 2017). Bar forms are deposited
on the channel bed in zones of flow separation (e.g., point and delta bars) or where sediment
transport capacity is low relatively to sediment supply (e.g., center and side bars) (Rosgen,
1994). The profile characteristics of the Relfe soils generally describe the sedimentology of bar
features in the study area (Skaer and Cook, 2005).
As defined here, fine sediment is the material fraction of a bank or bar deposit less than
two millimeter in diameter including sand, silt, and clay particles. This fraction includes
sediment transported both in suspension (suspended load) and saltation or traction (bed-load).
Suspended sediment particles are assumed to be composed mostly of silt and clay particles (<63
µm) with some finer sand particles (<250 µm) (Rosgen, 1994). For example, sand percentages
(63-2,000 µm) in suspended sediment loads averaged from 6 to 39% in five southeastern
Minnesota rivers (Groten et al., 2016) and from 2 to 25% in Big River which receives flow from
both Mineral Fork and Mill Creek (Barr, 2016). In comparison, the sand content in floodplain
deposits in the study area varies from less than 20% in upper units to 10 to 40% in lower/coarser
units (Skaer and Cook, 2005). Thus, the fine sediment fraction evaluated for this study is
assumed to be similar in texture to that expected in the suspended load of these streams. The
percent fines were calculated by subtracting the % of coarse sediment (>2 mm) from 100%.
Channel and sediment assessment procedures. Field surveys of bank and bar location,
height, and stratigraphy were completed at 20 sites to provide data needed to verify bank height
measurements using LiDAR and estimate bank unit thickness based on local influences of stream
order and bank height (Appendix B). Sampling sites were distributed throughout the study
watersheds along tributaries and main channel at accessible locations not affected by road
crossings or local disturbances (Figure 6). GPS location and several photographs were collected
30
at each site. A stadia rod or folding ruler was used to measure bank height from the bank top
(i.e., near bank-full stage) to the bank toe. The bank toe was typically below the waterline at the
break in slope and texture, which was where the base of the floodplain bank meets the flatter
channel bed. Water depths were measured at the bank toe and channel thalweg (deepest point).
The cut-bank was scraped clean to identify stratigraphy including unit boundaries, sand or gravel
lenses, and buried soils.
Fourteen sediment samples were collected from upper bank (7) and lower bank (7)
sedimentary units at seven sites in Mineral Fork watershed to quantify the percentage of fine
sediment in the deposits (Figure 6; Appendix C). Composite samples from 0.2 to 0.5 m thick
were collected from cut-bank exposures by vertical scraping at a uniform depth. All sediment
samples were bagged and labeled in the field and returned to the laboratory at Missouri State
University for size analysis. The field samples were dried at 60°C in an oven, disaggregated with
a mortar and pestle, and passed through a 2 mm sieve. The fine sediment fraction reported as the
<2 mm mass divided by the total sample mass. The total field sample sometimes included
coarser clasts up to 64 mm in diameter.
Bank deposit and unit characteristics. Estimates of the thickness and fine sediment
content of upper and lower bank units were needed to apportion fine sediment fractions for
budget calculations. Analysis of stratigraphic measurements indicated that coarse unit thickness
averages about 55% of total bank height (as measured from the thalweg) across the range of
different bank heights evaluated for this study (Figure 7).
Field data and published information were used to develop relationships to predict the
fine sediment content of bank deposits. No trend in texture of the upper bank unit was indicated
for either bank height or stream order. Therefore, a constant value of a 90% fine sediment
31
fraction by volume (and 10% >2 mm) was assumed for all upper banks mapped as the Cedargap
soil series which included 70% of the floodplain soils in the study area (Skaer and Cook, 2005;
Figure 8; Appendix C). Floodplain banks associated with other soil series tend to have finer
upper units and were assumed to contain 100% fine sediment (Skaer and Cook, 2005). Sediment
samples from five of the seven sites plot along the 10% >2 mm line (90% fine sediment).
Further, this value also approximates the average composition of the upper A and B horizons of
the Cedargap soil series which represents the majority of sampled floodplains and previously
mapped soils along these streams (Skaer and Cook, 2005; Appendix B).
In contrast to the upper unit, the lower bank unit tends to become finer with increasing
bank height (Figure 8). Again, no trend was found with stream order, however, the sample size
was small. In the study area, banks with lower heights tend to be formed in geomorphic settings
associated with coarser sediment: (i) gravelly bench deposits where fine sediment is beginning to
bury coarse bar deposits to form young floodplains as shown by the Relfe soil series; and (ii)
gravelly floodplain deposits located along smaller and steeper channels where coarse sediment
transport and deposition is more frequent as shown by the Cedargap and Bloomsdale soils series
(Skaer and Cook, 2005). In contrast, higher banks tend occur in geomorphic settings associated
with finer-grained deposits: (i) floodplains along larger streams with lower slopes and wider
valley floors that deposit more silt and sand as shown by the Kaintuck and Haymond soil series;
and (ii) higher terraces along smaller streams as shown by the Higdon soil series (Skaer and
Cook, 2005). A linear regression equation was not appropriate for predicting textural
characteristics of lower bank units since deposits with similar textures were clustered according
to geomorphic features with discrete characteristics, not those grading into one another. Thus, a
step-function was used to classify lower unit texture according natural breaks with bank height as
32
follows: 40% fine sediment for <1.1 m height; 60% fine sediment for 1.1 m to 1.4 m height; and
70% fine sediment for >1.4 m height (Figure 8).
Bar Deposit Characteristics. No bar sediment samples were evaluated for this study.
Published values indicate that total pore or void space in gravel deposits generally averages
about 40%, thus comparing well with samples from the lower bank units composed of older
buried bar deposits (i.e., <40% fines by volume for low banks, Figure 8). However, fine
sediment does not typically fill in all the open spaces in recent or well-sorted gravel deposits.
Therefore, fine sediment content is typically less than the total open space might allow in bar
deposits ranging from 20 to 25% for silt and clay and up to 35% for sand (StormTech, 2012;
Dunning, 2017). Moreover, textural analyses of subsurface samples from the profile of the Relfe
soil series which occurs on larger bench and bar surfaces along Mineral Fork contains 20 to 30%
fine sediment (Skaer and Cook, 2005). Based on the evaluation above, it was assumed that all
bar deposits contained 25% fine sediment by volume for this study.
Bulk Density. Assumed bulk density values were used to convert volumetric
measurements into mass units for the sediment budget. For bank deposits, a bulk density of 1.4
Mg/m3 was used for fine sediment and 2.2 Mg/m3 for coarse material >2 mm (Bunte and Abt,
2001; Skaer and Cook, 2005). For bar deposits, a bulk density of 1.9 Mg/m3 was used for fine
sediment and 2.2 Mg/m3 for coarse sediment (Manger, 1963; Bunte and Abt, 2001; Pavlowsky et
al., 2017).
Spatial Datasets
Aerial photograph analysis. Historical aerial photographs from 1995 and 2015 were
used to assess channel width, bank location, and bar area to evaluate changes over a 20-year
33
period (Table 8). Pre-georeferenced USGS Digital Orthophoto Quarter Quads (DOQQ) were
retrieved from the Missouri Spatial Data Information Service for 1995 and 2015 (MSDIS, 2017).
The 1995 aerial photos have a spatial resolution of 1 m and were flown between March 1, 1995
and April 6, 1995. The 2015 aerial photos have a 0.15 m spatial resolution and were flown
between March 15, 2015 and April 17, 2015.
To account for rectification differences between the two sets of aerial photos, a mean
point-to-point error was calculated (Hughes et al., 2006). The point-to-point error is the
measured distance between known points on the two sets of photographs (Table 8). For this
study, 30 hard points were chosen in the study area, typically at building corners, and the 2015
color leaf-off was used as the reference photo (Table 8). Other studies have used between six and
30 points depending on the size of the watershed (Mount and Louis, 2005; Hughes et al., 2006;
Martin and Pavlowsky, 2011). UTM coordinates were assigned to each of the 1995 and 2015
points in ESRI’s ArcMap 10.7 and the distance between each set of points was calculated using
the distance formula. The distance between each set of points ranged from 0.98 m to 7.69 m with
a mean point-to-point distance of 2.76 m (n=30). This mean point-to-point error was later
incorporated into the next step of assessing erosion and deposition polygons to eliminate the area
inside the detection limit of error.
Erosion and deposition polygons. Both the wetted channel bank lines and bar features
were digitized from the 1995 and 2015 aerial photograph sets at a 1:1,000 scale in ArcGIS
(Figure 9a, b) (De Rose and Basher, 2011; Spiekermann et al., 2017). The aerial photographs
were used to digitize the active channel with the protocol to identify the stream banks until they
were not visible. Bar features were distinguished using the wetted channel boundaries as a guide
34
and an active channel layer was created by combining the two sets of features. These features
were converted to polygons and classified as either wetted channel or a bar in the attribute table.
Areas of bank erosion and deposition were identified by overlay analysis of the 1995 and
2015 active channel polygon layers. Bank erosion areas were identified by areas of the 2015
active channel beyond the 1995 active channel polygon using the erase tool in ArcGIS.
Deposition areas were identified as areas of the 1995 active channel outside of the 2015 active
channel polygon using the same tool. The same procedure was used to identify areas of erosion
and deposition of bar areas. Finally, the areas of all erosion and deposition polygons were
calculated in ArcGIS. In all, there were a four different polygon features produced from this
analysis: 1) bank erosion; 2) bank deposition; 3) bar erosion; and 4) bar deposition.
Error analysis. To account for the error associated with georeferencing, the mean point-
to-point error was incorporated into the erosion and deposition polygon analysis. A buffer using
half of the mean point-to-point error distance (1.38 m) was placed around the erosion and
deposition polygons (Figure 9c, d) (Mount and Louis, 2005; Hughes et al., 2006; Owen et al.,
2011). Areas from the bank erosion and deposition that overlapped the error buffer were
removed from the original polygons, creating erosion and deposition areas that were beyond the
error buffer accounting for rectification differences between the photo years (Figure 9c, d)
(Rhoades et al., 2009; Martin and Pavlowsky, 2011).
LiDAR analysis. A LiDAR derived DEM with one-meter horizontal and 0.185 m
vertical resolution was used to assign bank and bar heights to polygons and create a stream
network. The LiDAR derived DEM was obtained from MSDIS for Washington County and parts
of St. Francois County was flown June 30, 2011 (Table 8) (MSDIS, 2017). The LiDAR DEM
was used to delineate a stream network using the Strahler Stream Order method within each
35
watershed using the hydrology toolbox in ArcGIS (Strahler, 1957). The DEM was used to create
a flow accumulation and flow direction raster to establish a stream network with the stream link
tool. A threshold of 100,000 pixels (0.1 km2) was used for stream order classification. There was
a total of six stream orders created from using the Strahler method (Figure 10). The first and
second stream orders were not easy to identify because of low visibility in these heavily forested
watersheds. Therefore, only 3% of the first order and 24% of the second order streams were
digitized and later were not considered as part of the erosion and deposition analysis. However,
77% of third order streams were fully digitized. Third order streams remained in the cell
analysis, but the 23% unassessed stream length was addressed separately to determine the mass.
The LiDAR DEM was also used to assign landform heights to each polygon classified as
erosion or deposition for both the bars and banks (Notebaert et al., 2009; Rhoades et al., 2009;
De Rose and Basher, 2011; Kessler et al., 2012; Spiekermann et al., 2017). Because the aerial
photographs dates were different than the LiDAR flight date, banks and bars heights were
sampled using the LiDAR where both erosion and deposition occurred. Heights were only
sampled on erosion and deposition polygons below dams and on the third, fourth, fifth, and sixth
order streams. Polygons in third and fourth order streams were sampled every two kilometers,
and fifth and sixth order streams were sampled every 1 km because the stream length is smaller.
Of the 152 sites sampled, 10 (7%) had depositional bank heights larger than erosional bank
height. It was assumed that the cut-bank side of the channel should occur in the older part of the
floodplain which is higher due to a longer period of deposition. Therefore, the depositional bank
heights for these sites were corrected to equal those of the erosional bank heights. Of the 157
sites sampled, 21 (13%) had depositional bar heights larger than erosional bar heights.
36
To account for the elevation inaccuracies from water reflection in the LiDAR, the
assigned bank and bar heights were corrected to include water depths using field-based channel
topographic surveys. Bank height and water depth measurements were collected during rapid
field assessments that were completed throughout the watershed (Appendix B). The relationship
between bank heights recorded in the field and LiDAR banks heights shows an R2 value of
0.904, with the trend plotting just below the 1:1 as expected (Figure 11). This equation was used
to correct LiDAR height to actual field measured heights. In general, water depth added 0.07 to
0.14 m to LiDAR DEM derived bank heights. Average bank and bar heights were calculated for
each stream order in each 12-Digit HUC watershed.
Geomorphic spatial analysis at the reach-scale
Grid cell analysis. A longitudinal series of grid cells were overlain on digitized channel
centerlines to create a uniform reach scale for landform change analysis. Reach-scale studies of
stream geomorphology typically assess stream channel lengths that are 20-100 widths long
(Rosgen, 1994). For this study, active channel widths typically ranged from 10 m to 45 m.
Therefore, a cell length of 500 m was chosen for this study that is in the range of other studies of
Ozarks streams (Jacobson and Gran, 1999; Panfil and Jacobson, 2001; Pavlowsky et al., 2017).
These cells were created by placing a 100-meter buffer around the centerline derived from the
digitized stream network below dams that were then cut every 500 meters to create a total of 430
cells each 500 m long for the two study watersheds (Figure 12).
Cell analysis. The bank and bar erosion and deposition polygons were analyzed by the
cell unit as part of the reach-scale analysis in the third, fourth, fifth, and sixth order streams. In
ArcGIS, the “Intersect” tool is used to assign bank erosion, bank deposition, bar erosion, and bar
37
deposition polygons to each 500 m channel cell and the area of each was recalculated. If a
polygon was overlapping two cells, it would be divided into two polygons, one in each cell.
Finally, the average bank and bar heights for each of the cells were attributed by values from
each 12-Digit HUC watershed to each stream order. The bank and bar heights were multiplied by
the area to calculate the overall volume of sediment for each of the four different features. These
sediment volumes will ultimately be used in the sediment budget. (Table 9; Figure 13; Appendix
D-E). Results of cell locations and analyses are stored on the Ozarks Environmental and Water
Resources Institute (OEWRI) server. Lastly, unmeasured lengths, mainly in the third order
streams, were added to the masses from the cell analysis to the determine the volume of the
missing stream length in subwatershed. The volume of erosion/deposition for bank/bars in the
unassessed stream length was determined by taking the average volume of third order cells in per
12-Digit HUC subwatershed. The average cell volume (mass/0.5 km) was multiplied by the
length of unassessed stream order length below the dams to get the complete in-channel sediment
budget. The calculation and analysis of these values will be presented later in the results chapter.
Sediment budget development
The sediment budget approach applied in this study generally followed Trimble (1983)
and Trimble and Lund (1982). Sediment budgets measure the amount of sediment eroded and
stored in different landform units of a watershed (i.e. uplands, headwaters, floodplains, and in-
channel processes) over a period of time (Phillips, 1991; Beach, 1994; Trimble, 1999). To create
detailed sediment budgets, both sediment storage zones and active erosion zones need to be
added together to determine the output of sediment within a watershed (Davis, 2009). For
example, storage can occur in uplands at the base of slopes, on floodplains, in gravel bars, or in
38
impoundments (i.e. reservoirs, dams, lakes, ponds) (Trimble and Lund, 1982; Renwick et al.,
2005; Joyce et al., 2018). Additionally, sediment can be lost through sheet and rill erosion in the
uplands, re-mobilization of stored in-channel sediment (bars), or bank erosion (Trimble, 1999;
Davis, 2009; Lauer et al., 2017). Each of these factors will be incorporated into a sediment
budget using in-channel masses from this study, predicted sheet and rill erosion from uplands
and sediment loads from streams by STEPL modeling, and floodplain deposition rates based on
previous studies (Table 10).
STEPL Modeling. By using algorithms, Spreadsheet Tool for Estimating Pollutant
Loads (STEPL) calculates the nonpoint source loads, including fine sediment, nutrients, and
runoff, from the uplands of a watershed for predefined land use categories (urban, cropland,
pastureland, forest, and user-defined) (Tetra Tech, 2018). STEPL is a downloadable Microsoft
Excel spreadsheet that includes default parameters and options for users to customize and modify
inputs (WiDNR, 2014). The inputs for STEPL include: (1) land use area, (2) precipitation, (3)
agricultural animal numbers, (4) Universal Soil Loss Equation (USLE) output based on variable
Kf- and LS-factors, and (5) hydrologic soil group (Appendix F-G) (Tetra Tech, 2018). Much of
this data was obtained from the Soil Survey Geographic Database (SSURGO) and land-use data
from USDA-NASS (USDA-NRCS, 2017; USDA-NASS, 2018).
The User-Defined land use category was manipulated to represent areas within the
watershed that were mined. The 2017 land use data often classified the areas influenced by lead
or barite surface mining as forested (Figure 14). Forested lands typically have lower runoff and
sediment loads than agricultural land. Also, the mined lands within the watershed were more
representative of old construction sites that typically do not have as much vegetative cover and
bare ground is subject to increased runoff and soil erosion. Mined lands include features such as
39
surface mining pits and tailings piles, ponds/dams, and areas of soil disturbance that are
becoming forest covered. The area of mined land was mapped using the 2015 aerial photos and
2011 LiDAR dataset and used to reclassify the land use in Mineral Fork and Mill Creek (Figure
4, 14). The area of the watershed classified as mined lands was included in the User-Defined
category in STEPL.
The suspended sediment load in STEPL is computed based on the USLE and the
sediment delivery ratio (Park et al., 2014; 2015). STEPL is not a spatial model and it calculates
sediment loading for the watershed using default or generalized variables. Therefore, for this
study, STEPL was manipulated into being more spatially weighted by using specific soil series
data to derive area weighted K-, LS-, and C-Factors for each of the different land uses (Appendix
G) (USDA-NRCS, 2017). Finally, the total suspended sediment load is calculated by multiplying
soil erosion by the sediment delivery ratio, which is a rough estimate of sediment deposition and
storage within the watershed (Tetra Tech, 2018). The sediment delivery ratio (SDR) is calculated
based on the watershed area where a lower percentage of eroded soil is exported out of the
watershed as the drainage area increases (NRCS, 1983; James, 2013). Therefore, the sediment
load from STEPL represents the total mass of sediment leaving the watershed from sheet and rill
erosion annually after the SDR is applied to the upland erosion mass.
Tailings dam influences. Mineral Fork and Mill Creek watersheds contain 40 large
tailings dams and recreational lake dams along tributary and headwater streams according to the
records in the Missouri 2019 Dams shapefile (MSDIS, 2019) (Appendix H). The largest dams
that were capable of trapping 100% of the fine sediment loads were identified from published
locations and dam heights (MSDIS, 2019) and observations of disconnected drainage systems
from LiDAR (collected 2011) and aerial photography (collected 2015). A secondary “below
40
dam” drainage divide was delineated through the location points of most downstream large dams
along the tributary network to delineate the effective sediment-contributing drainage area for
each watershed. The following “below dam” drainage area was reduced by 27% for Mineral
Fork and 28% for Mill Creek (Figure 12). It was assumed for sediment load modeling purposes
that all the tailings dams trapped 100% of the sediment. However, based on trap-efficiency
equations, the Sunnen Lake dam passes about 50% of the suspended sediment load it receives
annually (St. Louis District Corps of Engineers, 1970; Ward et al., 2016).
STEPL was used to calculate the percent of the sediment load that was reduced due to
runoff retention and sediment deposition in the old tailing’s ponds and Sunnen Lake. First,
STEPL was used to estimate the upland erosion and stream loads for the entire watershed area
including the drainage areas behind the dams. Next, STEPL was applied only to the land areas
below the most downstream dam on a tributary, not including land areas above the dam. The
total load and below dam load were compared to determine the percent reduction in the overall
sediment load from the effects of dams. The drainage area above Sunnen Lake dam was assessed
separately to estimate suspended sediment load at the dam and then reduce by a best
management practice (BMP) efficiency setting of 50%. The reduced stream load from the
Sunnen Lake outlet was added to the upland erosion load for the “below dam” drainage area for
sediment budget calculations for the whole Mineral Fork watershed.
Overbank floodplain deposition. Overbank sedimentation storage was estimated using
deposition rates from research near Mineral Fork and Mill Creek and a review of published
results (Table 1). Based on the soil maps, Mineral Fork has 25.1 km2 of frequently flooded soils
and 3.9 km2 of occasionally flooded soils. Mill Creek has a total area of 5.4 km2 of frequently
flooded soils and 0.7 km2 of occasionally flooded soils mapped in the watershed (Skaer and
41
Cook, 2005). A review of floodplain sedimentation rates derived from Big River floodplain core
profiles using Cs-137 to identify the 1963 bomb testing peak showed that while higher
deposition rates >10 mm/yr occur on lower “in-channel” floodplain and bench surfaces, more
moderate rates from 6 and 10 mm/yr occur on floodplain surfaces at/near bank-full stage.
However, lower rates from 1-3 mm/yr occur on higher floodplains in wider valleys in stable
riparian zones (Pavlowsky, 2013; Keppel et al., 2015; Pavlowsky and Owen, 2015; Jordan,
2019). In a review of the literature, streams with drainage areas and soil conditions similar to the
study area tend to have lower floodplain sedimentation rates (1-10 mm/yr) (Owen et al., 2011;
Keppel et al., 2015; Pavlowsky and Owen, 2015). From the review and field observations, it was
assumed that soils frequently flooded had a deposition rate of 3 mm/yr and occasionally flooded
soils had a rate of 0.5 mm/yr In order to calculate mass, the total deposition volume (area times
deposition rate) was multiplied by 1.4 Mg/m3 (Manger, 1963; Pavlowsky et al., 2017).
42
Table 8. Aerial photograph characteristics.
Year Source Flight Date Type Resolution
(m)
Point to
Point Range
(m)
Mean Point
to Point
Error (m)
Buffer
(m)
2015 MSDIS 3/15/2015 True color leaf-off
DOQQ 0.15 Reference Image
1995 MSDIS 4/6/1995 Black and White
DOQQ 1 0.98 - 7.69 2.76 1.38
2011 MSDIS 6/30/2011 LiDAR DEM 1 N/A N/A N/A
Table 9. Definition of variables for deposit volume and mass calculations.
Variable Equation Bank Erosion and Deposition Cells Average Width (m) *Area (m2) / *Length (m) Lateral Change Rate (m/yr) Average Width (m) / 20 (yr) Total Volume (m3) *Area (m2) * *Bank Height (m) Lower Unit Volume (m3) (Total Volume * 0.55) * Fraction of Fines (0.4 - 0.7) Upper Unit Volume (m3) (Total Volume * 0.45) * Fraction of Fines (0.9 -1.0) Total Volume of Fines (m3) Lower Unit Volume (m3) + Upper Unit Volume (m3) Mass (Mg) Total Volume of Fines (m3) * bulk density (1.4 Mg/m3)
Bar Erosion and Deposition Cells Average Width (m) *Area (m2) / *Length (m) Total Volume (m3) *Area (m2) * *Bar Height (m) Total Volume of Fines (m3) Total Volume (m3) * Fraction of Fines (0.25) Mass (Mg) Total Volume of Fines (m3) * bulk density (1.9 Mg/m3) *Values from sampled LiDAR heights by subwatershed/stream order
43
Table 10. Description of sediment budget terms.
Component*# Description
Upland Erosion Overall soil erosion rates predicted by STEPL using variables in
appendix (Tetra Tech, 2018).
Floodplain Storage Estimated mass of sediment deposited into long-term storage on
frequently (3 mm/yr) and occasionally (0.5 mm/yr) flooded soil series
(Skaer and Cook, 2005). Annual deposition rates were based on
assumptions from literature review and limited regional data (Table 1).
Other Storage Upland Erosion rate (#1) minus floodplain (#2), bank, and bar
depositional storage rate and export load.
Bank Erosion (net) Sum of annual bank erosion and bank deposition rates (Figure 25).
Positive value indicates a net supply or release to the channel and
negative value indicates a net sink or storage from channel transport. Part
of the in-channel derived load (Table 25).
Bar Erosion (net) Sum of annual bar erosion and bar deposition rates (Figure 25). Positive
value indicates a net supply or release to the channel and negative value
indicates a net sink or storage from channel transport. Part of the in-
channel derived load (Table 25).
Upland Load Output of stream sediment from the watershed predicted by STEPL from
upland erosion (#1) after application of sediment delivery ratio (Tetra
Tech, 2018).
In-channel load Output of stream sediment from the watershed calculated by this study by
assessment of annual erosion and deposition rates of bank and bar
deposits (Table 25).
Export Load Total sediment load exported from the watershed outlet as the sum of
both upland (#6) and in-channel (#7) loads. The export load from the
Mineral Fork and Mill Creek watersheds would be assumed to enter Big
River (Table 27).
Sediment Yield Export load reported as a per unit area (km2) rate that indicates the
intensity of sediment production from the watershed (Table 27). *all units in Mg/yr except for sediment yield which is Mg/km2/yr #Positive (+) mass values denote erosion or the release of sediment to the channel, while negative
(-) values denote deposition or storage of sediment in colluvial or alluvial deposit
44
Figure 6. Location of field assessment sites.
45
Figure 7. Coarse unit thickness in bank deposits.
Figure 8. Texture of bank deposits.
46
Figure 9. Application of error to active channel features. (A) 2015 digitized active channel
compared to the (B) 1995 digitized active channel from the aerial photographs. (C) Areas of
erosion where parts of the active channel that do not overlap the 1995 active channel buffer (1.4
m). (D) Areas of deposition where parts of the active channel that do not overlap the 2015 active
channel buffer (1.4 m).
2015 1995
1995 Buffer 2015 Buffer
Erosion Deposition
47
Figure 10. Digitized and delineated stream network
.
Figure 11. Comparison of LiDAR bank height to field bank height.
48
Figure 12. Cell distribution below dams by stream order.
49
Figure 13. Deposit volume to fine sediment mass conversion by cell.
Bank Volume
Total Cell Volume
Lower Unit
55%
Volume of Fines
40% L, 60% M, 70% H
Bulk Density
1.4 Mg/m3
Mass (Mg)
Lower Unit
Bank Mass (Mg)
Lower + Upper Unit
Channel Mass (Mg)
Bank + Bar
Upper Unit
45%
Volume of Fines
Cedargap 90%, Other 100%
Bulk Density
1.4 Mg/m3
Mass (Mg)
Upper Unit
Bar Volume
Total Cell Volume
Volume of Fines
25%
Bulk Density
1.9 Mg/m3
Mass (Mg)
Bar Mass of Fines
50
Figure 14. Mining areas classified as forest from the 2015 DOQQ aerial photo.
51
RESULTS AND DISCUSSION
Channel delineation and network analysis
Stream network and orders. The stream networks were delineated for each watershed
from the LiDAR data using the Strahler Order method. The total channel length by stream order
for Mineral Fork was as follows: 486 km, first; 224 km, second; 104 km, third; 51 km, fourth; 25
km, fifth; and 28 km, sixth (Table 11). Not all segments of the channel network could be
digitized into channel and bar features on the aerial photographs due to the resolution errors and
obstruction by trees and shadows. Only 4% of the first order and 29% of the second order
streams were digitized in the Mineral Fork watershed. Therefore, only the third, fourth, fifth, and
sixth stream orders were evaluated in this study. In Mineral Fork, 100% of the fourth, fifth, and
sixth order and 78% of the third order delineated streams were digitized (Table 11). Of the total
assessed stream length (188 km), 16% of the network length was above dams as follows: 18%,
third; 21%, fourth; 13%, fifth; and 0%, sixth. Since it was assumed that 100% of sediment load
was trapped behind the large tailing’s dams, the stream lengths above dams were not included in
the channel assessment, with the exception of Sunnen Lake dam with its 50% trap efficiency for
sediment. Therefore, the total assessed length by stream order in Mineral Fork was as follows: 86
km, third; 40 km, fourth; 22 km, fifth; and 28 km, sixth (Table 11).
The total channel length by stream order for Mill Creek was as follows: 139 km, first; 70
km, second; 31 km, third; 24 km, fourth; and 5 km, fifth (Table 12). The first order streams were
not visible and only 4% of the second order streams were digitized. Therefore, similar to Mineral
Fork, the in-channel analysis only included third, fourth, and fifth order streams in the Mill
Creek watershed. The digitized stream network included 100% of the fourth and fifth order and
73% of the third order stream lengths in the Mill Creek watershed. Dams were only located on
52
third order streams, leaving 20% of the stream length above dams. Therefore, the total assessed
length by stream order in Mill Creek was as follows: 25 km, third; 24 km, fourth; 5 km, fifth
(Table 12).
Cell distribution. The channel morphology in each watershed below dams was
compared between the two aerial photograph years to support the analysis of in-channel
contributions to sediment budgets. The digitized stream network was divided into 500-m long
channel cells to quantify the spatial patterns of bank and bar erosion and deposition areas in
stream order segments (Jacobson and Gran, 1999; Panfil and Jacobson, 2001). Mineral Fork had
344 cells within its watershed below dams. The cells in Mineral Fork were grouped by stream
order as follows: 44%, third; 28%, fourth; 13%, fifth; and 16%, sixth (Figure 15). Mill Creek had
86 cells. The cells in Mill Creek were distributed by order as follows: 38%, third; 50%, fourth;
and 12%, fifth (Figure 15). The 430 cells were used as the unit of assessment to sum net erosion
or deposition in the channel erosion and deposition areas and were multiplied by average
landform height values for each stream order in each 12-Digit HUC subwatersheds. Volume of
bank and bar landform changes were then summed to assess sediment erosion and deposition of
both the cell and stream order scales.
Bank and bar deposit assessment
The total gravel bar area was digitized in the 1995 and 2015 aerial photographs, while the
active channel was used to determine if the active channel was widening or laterally moving in a
cut-bank point to bar formation (Kondolf, 1997). Examples of the spatial distribution of erosion
and deposition using polygons are shown in Figures 16 and 17. Typically, both erosion and
deposition for banks and bars were observed in spatially similar locations (Joyce et al., 2018).
53
More specifically, where bank erosion occurred deposition impacts were adjacent to it. Figures
16 and 17 also showed a detailed map of multiple cells/reaches where there were erosion zones
that contributed the most to the sediment load. Similarly, gravel bars were present in all of the
reaches (cells) in the figures for 1995 and 2015 (Figures 16, 17). Additionally, the reaches were
used to determine if there was movement of the gravel bars downstream (Panfil and Jacobson,
2001).
After identifying all of the erosion and deposition polygons, it was determined how much
of the stream length was disturbed. The total length of bank erosion (i.e. cut-banks) in Mineral
Fork was 87.0 km in the third through sixth order streams, or 21% of the digitized stream length.
The total length of polygons defined as bank deposition in Mineral Fork was 78.6 km, or 19% of
the active channel length evaluated for this study. Similarly, in Mill Creek, the total length of
cut-banks was 23.6 km, or 24% of the digitized stream length. The total length of bank
deposition was 9.7 km or 10% of the digitized stream length. The frequencies of eroding channel
lengths observed in Mineral Fork and Mill Creek are similar to other Ozark streams where 20 to
40% of channel lengths are in disturbed active zones along the main channel segments (Martin
and Pavlowsky, 2011; Owen et al., 2011).
Variable discharge effects on planform analysis. Studies have shown that there are
errors associated with using aerial photographs to determine channel morphology (Mount and
Louis, 2005; De Rose and Basher, 2011). One of the disadvantages are rectification procedures
and the ability to consistently locate bank features between dates of photography such as cases
where the resolution of the image is low or the study area is in a dense woody riparian cover (De
Rose and Basher, 2011; Spiekermann et al., 2017). However, mean point-to-point errors and
other polynomial transformations from georeferencing can reduce inaccuracies by applying
54
buffers to remove areas that are inside of the limit of error (2 m to 5 m) (Mount and Louis, 2005;
Hughes et al., 2006; De Rose and Basher, 2011). This study used a mean point-to-point error of
2.8 m, and applied half of the error on each side of the stream creating a buffer of 1.4 m.
Another problem with using the aerial photographs was the need to check if the discharge
during the photograph dates were similar thus allowing channel morphology, and not water
depth, to describe wetted width dimensions. This is usually addressed by finding the flow
measurements from historical USGS gage records among photograph dates (Barr, 2016).
However, these small watersheds do not contain gaging stations. Further, the photographs used
from MSDIS did not have exact flight dates of when the photographs were taken, only a range of
dates. The closest gages to Mineral Fork and Mill Creek were south (upstream) of the watersheds
on the Big River at Richwoods (#7018100) and north (downstream) of the watersheds on the
Meramec River near Sullivan (#7014500) (USGS, 2018b). The antecedent flooding was
compared by assessing the peak annual flood discharge in the 5-year period before each aerial
photograph year (Figure 18). The period from 1990 to 1994 had higher annual floods compared
to 2010-2014 (Table 13). The average of the annual flood peak record was the mean annual flood
with a recurrence interval of 2.33 years. The average flood peak in the five years before aerial
photographs were collected was 1.5-1.7 times larger in 1995 compared to 2015. Therefore, the
flood power could have had an influence on the wider channel in 1995 and photograph series
taken after the period of more floods might yield sharper and wider banks and brighter and easier
to delineate bars.
Water surface width on the day of the aerial photographs were taken varied with baseflow
or recent runoff. In order to detect if there was an impact of channel flooding and water levels on
the active channel width, 14 different 500 m reaches in the third through sixth stream orders
55
were compared to determine if there was a significant difference in the active channel width
between the photograph years (Table 14). Based on a 1:1 line for the 1995 active channel widths
to the 2015 widths, there was an R2 value of 0.84 (Figure 19). Trends showed that when the
active channel width increased, 1995 had a wider channel than 2015. Alternatively, when the
active channel width decreased, 2015 had a wider channel than 1995 (Figure 19). Therefore, the
1:1 showed that there was not a significant difference between the different years. The average
difference in channel width (1.1 m) was less than half of the mean point-to-point error (2.8 m).
Further, there was relatively little scatter among the site pairs suggesting that the discharge and
depth/width relation was similar for both years and that bank and bar lines would not vary
significantly due to water depth errors.
Bank and bar heights as a factor for volume. Because the aerial photos dates were
different than the LiDAR flight date, a subsample of bank (n = 152) and bar (n=157) heights
were collected in stream orders (3rd – 6th) below the dams. The water reflection from the LiDAR
was corrected on these heights to include water depths using field-based channel topographic
surveys. Of the 152 bank sites sampled, 10 (7%) had depositional bank heights larger than
erosional bank height. It was assumed that the cut-bank side of the channel should typically
erode into the older formation of floodplain deposits (i.e. low terrace or historical floodplain),
which are assumed to be higher due to a longer period of deposition. Therefore, the depositional
bank heights for these sites were corrected to equal those of the erosional bank height. Similarly,
of the 157 bar sites sampled, only 21 (13%) had depositional bar heights larger than erosional bar
heights. An average height was calculated for each stream order for bank and bar erosion and
deposition for each 12-Digit HUC watershed (Table 15-18). The average bank and bar heights
were assigned to each cell based on stream order location and subwatershed. Lastly, unmeasured
56
lengths of the third order streams were added in the analysis to estimate the volumes of the
missing stream length for each subwatershed. The volumes of erosion/deposition for bank/bars
was determined by taking the average volume in third order cells in each subwatershed and
multiplied that number by the length of unassessed stream order length below the dams.
Mass of bank and bar erosion and deposition of fine sediment
Geomorphic trends. As expected, average bank and bar heights increase from third to
sixth order streams by 1.6 to 1.9 times for banks and 1.4 to 1.6 times for bars (Tables 15-18;
Figure 20). Third order banks averaged from 1.6 to 2.0 m high and sixth order banks from 2.7 to
2.8 m (Table 15). Average depositional bank heights were about one-third lower than eroding
banks (Table 6; Figure 20). Erosional and depositional bar heights tended to be within 10% of
one another with eroding bars usually higher, ranging overall from 1 to 1.4 m in third order
channels to 1.7 to 1.8 m in sixth order channels (Table 17-18; Figure 20). Except for sixth order
streams, average bar heights tended to be slightly higher than depositional banks (Figure 20).
While this trend may reflect variations in bank and bar heights downstream, and not within the
same reach, it does suggest that in this study the depositional banks are forming on lower bar
surfaces as young benches or shelves (Owen et al. 2011). Further, bar features in the Ozarks can
accrete to relatively high elevations near bank-full stage in disturbance reaches (Panfil and
Jacobson, 2001; Martin and Pavlowsky, 2011). Specifically, for the subwatersheds, both
erosional and depositional bank heights, and bar heights to a lesser degree, tended to be higher in
MC and MF subwatersheds which drained directly into the Big River (Figure 12). This trend is
expected since longitudinal bank lines and channel beds would grade to meet those of the larger
57
river with local base-level control and decreasing slopes increasing floodplain and channel
deposition rates.
As expected, active channel width (including the wetted channel bed and gravel bars)
increased downstream from about 8 to 10 m in third order streams to 40 to 55 m in sixth order
streams (Figure 21). Average channel widths both increased and decreased among stream orders
and subwatersheds over the 20-year study period (Figure 21). The largest increase by almost
40% occurred in third order streams in OMC subwatershed. This geomorphic response may have
been caused by recent land disturbances that increase runoff rates into relatively unstable
channels due to the presence of mobile gravel deposits possibly linked to the effects of
settlement pressure and lead and barite mining since the mid-1700s (Adamski et al., 1995;
Jacobson and Primm, 1997; Jacobson and Gran, 1999; Olson, 2017).
The largest decreases in width from 24 to 37% occurred in the SLFR subwatershed for
third to fifth order streams (no sixth order streams were mapped in SLFR) (Figure 22a). It is
possible that the drainage network was affected by the relatively larger floods prior to 1995 or
that more conservation practices for riparian buffers were implemented there since 1995
compared to the other watersheds (Jacobson and Pugh, 1997; Zaimes and Schultz, 2015). Higher
antecedent flood magnitudes preceding the collection of the 1995 photographs would suggest
that channel widths would at least be temporarily wider than average width in 1995 since bank
scour and vegetation removal would be expected to occur during larger floods (Table 13)
(Hagstrom et al., 2018). If this was the case, then channels would be expected to recover and be
less scoured during 2015. Thus, a tendency for decreased channel widths in 2015 might be
assumed given no other changes in land use or flood climatology. However, average width
differences were less than 10-20% with nine subwatershed-order classes indicating increases in
58
width and ten classes showing decreases in width over the 20-year period (Figure 22a). The
average annual erosion rate for the all the subwatersheds combined was 0.15 m/yr. This 50:50
distribution of width change suggests the higher antecedent flood frequency and magnitude did
not influence the results of the present study to a significant degree.
Bank erosion rates can be used to evaluate channel activity since relatively high rates
indicate unstable planform conditions with poorly organized bar forms in Ozark streams
(Jacobson, 1995; Jacobson and Primm, 1997; Martin and Pavlowsky, 2011). Bank erosion rates
>1-2 m/yr in smaller streams like those in this study were considered excessive (Harden et al.,
2009; Rhoades et al., 2009; De Rose and Basher, 2011; Kessler et al., 2013; Janes et al., 2017;
Spiekermann et al., 2017). In this study, average bank erosion rates and their range among the
subwatersheds increased with stream order as follows: third, 0.09 m/yr (0.04-0.10 m/yr); fourth,
0.13 m/yr (0.04-0.18 m/yr); fifth, 0.18 m/yr (0.05-0.28 m/yr); and sixth, 0.18 m/yr (0.27-0.43
m/yr). Average annual bank erosion rates as a percent of active channel width ranged from 0.2 to
1.2% from 1995 to 2015 for the seven subwatersheds evaluated for this study (Figure 22b).
There was a tendency for relatively higher rates in third and fourth order streams (>0.9%) and
lower rates in fifth and sixth order streams (<0.7%). Locally, one sixth order stream cell in MF
had an average bank erosion rate of 0.43 m/yr which was 8% of the active channel width. Bank
erosion rates for Mineral Fork and Mill Creek compare well with those reported for 40 stream
segments draining the Mid-Atlantic Piedmont with average rates from 0.4-0.19 m/yr and relative
rates averaging 2.5%, with a range of 0.9-4.4%, of the active channel width (Donovan et al.
2015).
Gravel bars are common in Ozarks streams and tend to cluster in disturbance zones
separated by relatively stable segments (Jacobson and Primm, 1997; Martin and Pavlowsky,
59
2011; Olson, 2017). In the Mineral Fork watershed, 1.39 km2 of bars were mapped in 1995 and
1.37 km2 in 2015 (1.4% decrease). On average, gravel bars in third and fourth order streams in
the Mineral Fork watershed covered 17 to 36% of the active channel area in 1995 and 31 to 43%
in 2015. Bar area in fifth and sixth order streams covered 29% of the active channel during both
1995 and 2015. In the Mill Creek watershed, 0.25 km2 of bars were mapped in 1995 and 0.27
km2 in 2015 (8% increase). The Mill Creek watershed had relatively higher bar areas in the
active channel compared to Mineral Fork overall with 29% in 1995 and 43% in 2015. Like the
active width, average bar width also tends to increase downstream from less than 5 m in third
order channels to 10-15 m in sixth order streams (Figure 23).
All stream order classes contained at least two subwatersheds where bar area in the active
channel increased by > 40% from 1995 to 2015 (Figure 24). The greatest increases in bar area
occurred in fifth order streams (up to 65% in FR). It is possible that some of the gravel sediment
previously released by historical or more recent land use disturbances and channel incision was
first deposited in in upstream reaches and then migrated downstream into higher order channels
in a wave-like process (Jacobson and Primm, 1997; Jacobson and Gran, 1999). Bar areas
decreased by 10-30% in third and fourth order channels in some subwatersheds perhaps as the
result of erosion and downstream transport of gravel (Figure 24). Surprisingly, bar areas in sixth
order streams of the lower Mineral Fork watershed did not change much between the two
photograph years (<10% increase) (Figure 24). Valley confinement by higher bluffs and lower
rates of lateral channel migration along the lower segments may have limited available bar
accommodation space along the lower Mineral Fork Creek (Lecce, 1997; De Rose and Basher,
2011; Janes et al., 2017).
60
Patterns of bank and bar storage and erosion masses. The cell-level channel
characteristics and sediment samples collected in the field were used to estimate the total mass of
fines for bank and bar erosion and deposition. The alternation of depositing and eroding cells has
persisted in many Ozark streams since at least since the early 1900s (Jacobson, 1995). This can
also be an indication of a dynamic equilibrium condition among discharge, sediment supply, and
topography (Martin and Pavlowsky, 2011). Therefore, patterns of the bank and bar storage and
erosion were identified by subwatershed and stream order to determine the overall mass of
storage and erosion per cell to make sure to include these reach-scale sediment variations.
Sediment masses by cell were also used to determine areas where most of the bank erosion, bar
erosion, and net erosion load were located to identify which cells combined to make up 25% of
the overall load contribution of fine sediment.
Bank erosion. Of the 430, 500 m long cells assessed for this study, 98% produced bank
erosion and 93% bank deposition. As expected, average eroded masses increased from third to
sixth order streams by 11.8 to 15.5 times (Tables 19-20). Third order bank erosion masses per
cell averaged from 24 to 55 Mg/yr and sixth order from 357 to 821 Mg/yr (Table 19). Average
depositional bank masses were lower than eroding banks with rates from 11 to 40 Mg/yr in third
order and 198 to 328 Mg/yr in sixth order (Table 20).
The Mill Creek watershed had a total of 8,334 Mg/yr of sediment from bank erosion and
2,114 Mg/yr from bank deposition with a net supply of sediment to the channel system by bank
erosion of 6,190 Mg/yr (Table 21; Figure 25). Therefore, eroding banks were releasing nearly
four times as much fine sediment as they were depositing during the formation of new bench and
floodplain landforms. Only one of the 86 cells in Mill Creek did not contain bank erosion (Figure
26). Specifically, the locations in Mill Creek with the highest erosion (i.e. supplying 25% of the
61
total bank erosion load, not including deposition) were in four cells along the main stem of Mill
Creek with inputs ranging from 353 to 739 Mg/yr in the per cell (Figure 26).
The Mineral Fork watershed had a total of 48,382 Mg/yr of bank erosion and 26,593
Mg/yr from bank deposition yielding a net sediment output from bank erosion of 21,789 Mg/yr
(Table 21). The subwatersheds within Mineral Fork indicated that MF and CCMF have the
highest contributions of sediment from bank erosion and deposition (Figure 25). These
watersheds contain the highest banks along main stem of Mineral Fork Creek which flows
directly into Big River. Moreover, MF supplies 46% of the overall bank erosion load and 34% of
the annual bank storage and CCMF contributes to 26% of bank erosion and 26% to bank
deposition to the Mineral Fork watershed. OMC and SLFR (which had 50% sediment trap from
Sunnen Lake) contain the smallest contributions to bank erosion and deposition loads. There was
no bank erosion measured in only seven cells in the following watersheds: OMC (1 cell), MBC
(3 cells), FR (2 cells), and SLFR (2 cells). Of the 344 cells in the whole Mineral Fork watershed,
the largest contributors of bank eroded sediment include five cells in MF and two in CCMF
(Figure 26). Ultimately, cells with the highest bank erosion rates were downstream from the
barite mined areas (Schumacher and Smith, 2018). The cells that accounted for 25% of the bank
erosion load ranged from 1,314 to 3,015 Mg/yr in the Mineral Fork watershed.
Bar erosion. Of the 430 cells, 90% included bar erosion and 91% bar deposition. Similar
to banks, average bar masses increase from third to sixth order streams by about 9.5 to 19.4 times
(Tables 22-23). Third order bar erosion masses per cell averaged from 11 to 82 Mg/yr and sixth
order from 401 to 440 Mg/yr (Table 22). Average depositional bar sediment rates were lower
than measured in eroding bars from 17 to 30 Mg/yr in third order streams but were higher than
bar erosion rates in the sixth order streams ranging from 391 to 593 Mg/yr (Table 23).
62
The streams in Mill Creek and Mineral Fork watersheds flow through alluvial soils with
gravelly silt loam and channels with coarse beds. As expected, bars had a significant influence
on the fine sediment storage within each watershed. The Mill Creek watershed had a total of
5,546 Mg/yr of fine sediment released by bar erosion and 9,985 Mg/yr of storage by bar
deposition (Table 21). This demonstrated that the bar storage was 1.8 times the load of fine
sediment released by bar erosion. Even though bank erosion and deposition were a common
process in the Mill Creek watershed, gravel bars had higher rates of both erosion and storage
compared to banks (Figure 25). If bar erosion is the only factor being assessed (without bar
storage), Mill Creek had two cells that make up the highest erosion and 13 cells with no
measured bar erosion. The two cells that included 25% of the bar erosion load contributed 575
and 858 Mg/yr. The stream reaches affected by high erosion were again located on the main stem
of Mill Creek, compared to the cells indicating no erosion that were located in the lower-order
tributaries (Figure 27).
The Mineral Fork watershed had a total of 48,777 Mg/yr of bar erosion and 48,818 Mg/yr
from bar deposition (Table 21). Bars in Mineral Fork stored nearly equal amounts of fine
sediment by bar deposition as released by bar erosion (-41 Mg/yr of net storage). Recall that bar
area only decreased by -1.4% since 1995. Of the subwatersheds in Mineral Fork, the largest
influence of bar storage and bar erosion was in MF, CCMF, and MBC, with OMC and SLFR
having the lowest contribution of bar sediment (Table 21). MF and FR were the only two
subwatersheds that had more sediment put into bar storage than released by bar erosion (Figure
25). Subwatersheds CCMF, OMC, MBC, and SLFR had the highest annual bar erosion masses.
With bar deposition was not considered, the highest sediment masses released to the channel
from bar erosion were also located in MF (3 cells), CCMF (3 cells), and MBC (4 cells) (Figure
63
27). The cells that contributed to 25% of the bar erosion load ranged from 572 to 1,574 Mg/yr.
Again, deposition cells were located near reaches with high bar erosion rates and occurred
downstream from the barite mined areas (Figure 27). Of the 344 cells in the whole Mineral Fork
watershed, there were only a few without measured bar erosion cells in all of the subwatersheds:
MF (5 cells), CCMF (13 cells), OMC (4 cells), MBC (3 cells), FR (8 cells), and SLFR (2 cells).
Net Mass. When all factors were being included (bank and bar erosion and deposition),
Mill Creek had a net in-channel load of 1,751 Mg/yr (Table 21). Mill Creek had 59% of its cells
with a net erosion and 41% indicating either no erosion, in balance, or with a net storage.
Therefore, if stabilization practices were being considered for the Mill Creek watershed, they
would be most effective within the two high erosion cells near Fountain Farm Branch and in the
mining disturbed areas (Figure 28). The two cells that contributed to 25% of the overall net
erosion output yielded 519 and 841 Mg/yr of fine sediment. In Mill Creek there were more cells
releasing fine sediment than there were cells storing fine sediment (Figure 28, 29). However,
there was higher rates of net deposition occurred in the downstream segment of Mill Creek
(Figure 29).
Bank and bar erosion and deposition in Mineral Fork yielded a net in-channel sediment
load of 21,748 Mg/yr (Table 21). Moreover, 94% of the cells indicated net erosion, with 6%
having no erosion or net storage. On average the net sediment masses released per cell increase
from third to sixth order streams by about 19.1 times (Table 24). Third order net masses per cell
averaged from 22 to 119 Mg/yr and sixth order masses from 957 to 1,526 Mg/yr (Table 24).
Since bar erosion and bar deposition were balanced with similar masses, the bank erosion rates
had a greater influence on the net sediment load in the Mineral Fork watershed. The fifth order
streams in Mill Creek were the only places in the channel network that had a net storage of
64
sediment. Bank erosion, bar erosion, and bar deposition all had similar annual masses in the
overall in-channel sediment budget and were almost two times higher than the bank deposition
mass (Figure 25). If bank stabilization practices were being considered for the whole Mineral
Fork watershed, they would be most effective along the lower segment (sixth order stream) of
Mineral Fork Creek within MF and CCMF (Figure 28). MF contained ten cells and CCMF had
two cells that combine to make up 25% of the overall load contribution of fine sediment. More
importantly, MF contributed 44% of the overall in-channel sediment load to Mineral Fork (Table
21). The cells that contributed to 25% of the overall net erosion output ranged from 1,819 to
5,659 Mg/yr of fine sediment from in-channel processes.
Ultimately, bar storage was a key factor in understanding the spatial variability of
sediment storages and sinks within the two watersheds. The channel reaches where bar
deposition was greater than bank erosion tended to be adjacent to land disturbed by historical
mining activities which can cause channel instability (Gillespie et al., 2018). However, there
were still more cells eroding than depositing in both watersheds. Cells with high erosion masses
tended to be in the larger stream orders where banks were higher. This was also where there was
much more gravel bar activity. The alternation of depositing and eroding cells, especially in Mill
Creek, was consistent with channel responses and patterns of many Ozark streams (Figure 29)
(Jacobson, 1995; Martin and Pavlowsky, 2011). Altogether, the collective length of all actively
eroding and depositing reaches accounted for 34% of the stream length in Mill Creek and 40% in
Mineral Fork.
In Mill Creek, the spacing or wavelength of erosion and deposition cycles was about 2
km in 3rd and upper 4th order channels and 2.5 to 4 km in lower 4th and 5th order channels which
scales to 100 to 200 channel widths (Figure 29). The concept of alternating reaches is still being
65
studied and could be similar to the concept of hierarchical patch dynamics from landscape
ecology. At coarse spatial scales, this concept contains a longitudinal series of alternating stream
segments with different geomorphological structures (Poole, 2002). Geomorphic variables that
might be important in controlling the amounts of bank and bar erosion and deposition could be
controlled by the locations and stability of the higher banks in the larger order streams and the
width of the valley flood as confirmed by slopes and bluffs. Active reaches may also be
controlled by low order tributary inputs or valley confinement trends (Jacobson and Gran, 1999;
Martin and Pavlowsky, 2011). Jacobson and Gran (1999) reported that gravel bar accumulations
along the Current River, Missouri were controlled by lagged sediment transport in wave-like
patterns from the low-order tributaries to the main stems in a watershed. Geomorphic factors
driving in-channel sediment cycling could also be linked to historical mining disturbances or
legacy effects from the conversion of forest to agricultural land (Jacobson and Primm, 1997;
Pavlowsky et al., 2017).
Sediment load contributions
Sediment budgets measure the amount of sediment eroded and stored in all sections of a
watershed which include uplands, floodplains, and in-channel processes (Phillips, 1991; Beach,
1994; Trimble, 1999). Therefore, in order to create detailed sediment budgets for Mill Creek and
Mineral Fork, sediment storage and erosion components were combined to determine the overall
amount of sediment that makes it out of the basin (Table 10) (Davis, 2009). The sediment budget
in this study specifically evaluated erosion in the uplands, over-bank floodplain deposition, bank
erosion and deposition, gravel bar storage and erosion, and the influences of tailings dams on
66
trapping sediment (Trimble and Lund, 1982; Trimble, 1999; Renwick et al., 2005; Davis, 2009;
Schenk and Hupp, 2009; Lauer et al., 2017; Gillespie et al., 2018; Joyce et al., 2018).
STEPL. Before dams were considered as sediment traps that reduce the overall sediment
load, the entire Mineral Fork watershed produced an upland sediment load of 24,132 Mg/yr from
upland sources. STEPL estimated that upland erosion was about 292,522 Mg/yr before a
sediment delivery ratio of 0.08 was applied to calculated the upland loads at the watershed outlet
(Table 25). The entire Mill Creek watershed produced a sediment load of 12,554 Mg/yr, with the
estimated upland erosion calculated by STEPL at 115,157 Mg/yr (Table 25). Because Mill Creek
watershed had a smaller drainage area than the Mineral Fork watershed, the sediment delivery
ratio was higher at 0.11.
Mineral Fork has 27% of its drainage areas above tailings dams and Mill Creek has 28%.
The tailings dams were assumed to trap 100% of the sediment that entered the impoundment,
except for Sunnen Lake that only trapped 50% of the sediment due to its size (Renwick et al.,
2005; Trimble and Lund, 1982; Ward et al., 2016). The upland erosion load below dams in
STEPL was 17,785 Mg/yr in Mineral Fork. Therefore, the total upland load was reduced by 26%
with 6,348 Mg/yr of sediment behind the dams (Table 26). The Mill Creek watershed had an
upland erosion load of 7,741 Mg/yr for the watershed area below the dams. The amount of
sediment being stored above the tailings dams was 4,813 Mg/yr, which lead to a 38% reduction
in the overall sediment load (Table 26).
Overbank floodplain storage. Historical floodplain sedimentation could have followed
the introduction of mining and agricultural settlement as described by other studies around the
Ozarks and the Midwest (Knox, 1972, 1987, 2006; Owen et al., 2011; Pavlowsky et al., 2017;
Reminga, 2019). The floodplains soils within the cells were predominantly classified as
67
frequently flooded (84%), with a few cells that that had soils that were identified as occasionally
flooded (16%). The annual mass of overbank floodplain deposition was assumed using mapped
alluvial soils from the Soil Survey and deposition rates calculated from other studies surrounding
the study area (Skaer and Cook, 2005; USDA-NRCS, 2017). The soils that were frequently
flooded had a deposition rate of 3 mm/yr applied to the area and occasionally flooded soils had a
rate of 0.5 mm/yr (Table 1) (Pavlowsky and Owen, 2015). Therefore, Mineral Fork had an
annual mass of 108,263 Mg/yr of sediment that was depositing on the floodplains, which
provided 40% of the fine-sediment storage in Mineral Fork. Approximately, 23,269 Mg/yr of
sediment contributed to the overbank floodplain storage in Mill Creek, providing 33% of the
sediment storage was from overbank deposition. More specifically, other research has suggested
that soil disturbance on hillslopes by mining activities might have been a major source of
overbank floodplain sedimentation (Knox, 1987; Pavlowsky et al., 2017; Jordan, 2019).
Sediment budget evaluation. Sediment budgets are important for determining where
sediment is coming from and going to within a watershed. However, it is important to assess the
effects of specific land uses such as mining disturbed land cover to understand how they may
increase or decrease the sediment yields from the uplands bank erosion (Xiao and Ji, 2007;
James and Lecce, 2013). The upland loads below dams and in-channel sediment inputs were
combined to complete a sediment budget for the Mineral Fork and Mill Creek watersheds.
Sediment budget for Mineral Fork and Mill Creek watersheds. With the land uses,
floodplain deposition, and in-channel processes, Mineral Fork had a sediment yield of 92.2
Mg/km2/yr and Mill Creek had a yield of 98.6 Mg/km2/yr for the drainage area below dams
(Table 27). The mass of sediment that was exported out of the basin from the upland sources was
derived from the sediment delivery ratio and how much sediment was being stored in tailings
68
dams. Only 7% of the total upland erosion in Mineral Fork was estimated to make it out of the
basin. Sheet and rill erosion from the uplands contribute to 45% of the total load with 17,785
Mg/yr. With the different land uses in the uplands, bank erosion, and bar storage, Mineral Fork
was exporting 39,533 Mg/yr of sediment into Big River (Figure 30). About 8% of the soil eroded
from the uplands in Mill Creek left the watershed. Upland erosion of 7,741 Mg/yr contributed to
42% of the total load. Ultimately, Mill Creek had a sediment export of 9,492 Mg/yr to Big River
(Figure 31).
Significance of in-channel sediment processes. In addition to the upland erosion, bank
erosion and deposition were also major contributors to the sediment budgets. Based on the
differences between bank erosion and bank deposition in each cell, Mineral Fork had a net
sediment load export of 21,789 Mg/yr (Table 27). The net load of bank erosion contributed to
55% of the load that made it to the outlet of the watershed. Mill Creek had a net sediment load of
6,190 Mg/yr from bank erosion (Table 27). The net bank erosion load contributed to 34% of the
sediment load leaving the watershed. Bank erosion as a ratio of the upland load estimated in
STEPL was 2.7 in Mineral Fork and 1.1 in Mill Creek (Figure 32a). Net bank erosion as a
percent of the upland load was 1.2 in Mineral Fork and 0.8 in Mill Creek (Figure 32a).
Therefore, overall bank erosion contributions, even after bank deposition was incorporated, were
relatively higher compared to annual loads, especially in Mineral Fork.
Ozark streams have been known to have a large presence of gravel bars. After taking the
difference in bars from 1995 to 2015, the Mineral Fork watershed was in balance. Specifically,
there was only net load -41 Mg/yr of fine-grained sediment being deposited on the bars (Table
27). Ultimately, the net deposition in bars accounted for only 0.1% of the reduction of sediment
to the watershed outlet. Comparatively, Mill Creek had a net storage of -4,439 Mg/yr along the
69
bars in the watershed (Table 27). The bars had a pronounced influence on the sediment storage
within each watershed. Mill Creek had a net deposition in bars accounted for 24% of the load
reduction of sediment to the watershed outlet. Even when bar erosion was compared to the
upland load estimated in STEPL, bar erosion had a ratio of 2.7 in Mineral Fork and 0.7 in Mill
Creek (Figure 32b). Again, bar erosion contributions were relatively high compared when
compared to annual loads. However, net bar erosion as a percent of the upland load was 0 in
Mineral Fork and -0.6 in Mill Creek (Figure 32b). In the case of the Mineral Fork watershed the
zero indicates that the bar erosion and deposition loads are in balance. The negative percent
indicated that there was a net bar storage in Mill Creek. However, bar storage was important for
Mill Creek by having a significant reduction in the overall export of sediment out of the
watershed basin.
When combining the annual bank and bar erosion and deposition loads, the in-channel
contributions released more sediment than it was storing in both watersheds. The in-channel load
as a percent of the total load was 55% in Mineral Fork and 19% in Mill Creek (Figure 32c).
Mineral Fork and Mill Creek had their sediment loads more influenced by in-channel processes
than sediment eroding from the uplands. Generally, in-channel storage is not studied. Based on
the in-channel contributions of Mineral Fork and Mill Creek watersheds, deposition process and
bar forms should be included more often in bank erosion studies. In Mineral Fork, bank erosion
loads as a percent of the upland load was reduced by half after bank deposition loads were
incorporated. Similarly, sediment from bars was storing more than it was releasing in Mill Creek.
Therefore, studies that have not incorporated storage factors in their bank erosion studies could
be overestimating the amount of sediment being exported from a watershed.
70
Land use contributions. Each of the land use categories specified in STEPL were used to
determine which land use had the largest sediment load contribution to Mineral Fork and Mill
Creek. Even though mines in the study area have been closed since 1998, the land use category
did not accurately represent the land use/land cover of the mining disturbed landscape.
Therefore, for this study, STEPL was manipulated to have mined areas as a land use type in the
user-defined category (Tetra Tech, 2018). The mined land was mapped based on location found
on the landscape of the LiDAR derived DEM. Mineral Fork was a predominantly forested
watershed with this land use covering 82% of the watershed. However, the main sources to
sediment load in the uplands came from mining areas (31%), pastureland (27%), and forest
(26%) (Table 28). Mining and pasture land covered 2% and 11%, respectively, of the drainage
area in Mineral Fork. However, they represented the largest contributors to the upland erosion
loads because mined land and pastureland had less cover and higher rates of erosion than
forested land (Troeh et al., 2004; Park et al., 2014). The land use in Mill Creek was forest (78%),
mines (8%), and pasture (7%). The largest sediment contributors were mining areas (58%) and
forest (28%) (Table 28). The parameters from USLE and the increase in the percent of mined
land caused Mill Creek to have more of its upland sediment load to be coming from mined land
than Mineral Fork (Troeh et al., 2004; Renwick et al., 2005).
Future work. Additional studies are needed to improve this research. For example, more
field data can be collected on fine sediment variability for in-channel and overbank floodplain
deposits. Presently, it is not clear to what degree the texture of channel and floodplain deposits
varies spatially downstream and among different landforms. Additionally, more studies on
floodplain sedimentation rates are needed such as similar to those completed for other Ozark
rivers including Big River (Owen and Pavlowsky, 2015; Pavlowsky et al., 2017; Jordan, 2019).
71
According to the sediment budget from 1995 to 2015, floodplain deposition was estimated to
provide 33 to 40% of the annual upland storage contributions in the two watersheds. A more
precise analysis can try to validate the stream loads derived from this sediment budget by
monitoring or modeling discharge and suspended loads. Further, Cs-137 can be used to date
floodplain soil cores and quantify recent sedimentation rates (Owen et al., 2011; Reminga,
2019).
Because these are mining disturbed watersheds, the sediment budget can also be applied
to sediment contamination questions by adding a component of metal contributions to the overall
suspended sediment load. More sampling can be completed to determine the geochemical
analysis of Pb, Zn, or Ba concentrations in the Southeastern Missouri Barite District (Barr, 2016;
Pavlowsky et al., 2010, 2017; Schumacher and Smith, 2018). A wider range of analyses would
need to be completed on more sediment samples from uplands, floodplains, and in channel
locations including banks, gravel bars, benches, and bed samples in disturbed and undisturbed
mining locations. Using geochemical analysis, the spatial distribution of metal concentrations
could also be determined at different locations in the channel network.
Additional studies could be completed using LiDAR exclusively to model flows and
sediment transport and loads. More geomorphic studies are being completed to using LiDAR to
support geomorphic fieldwork (Roering et al., 2013). Remote sensing with LiDAR can be used
to study channel reaches in detail or watersheds to detect changes over time (Betts et al., 2003;
De Rose and Basher, 2011). The LiDAR for this study was collected in 2011, future work may
include repeat LiDAR collection over this area to detect changes in the DEM through hillslope
erosion or channel morphology over 10 plus years (De Rose and Basher, 2011; Roering et al.,
72
2013). In theory, Sequential LiDAR data could also be used to calculate vertical sedimentation
rates (Notebaert et al., 2009; Höfle and Rutzinger, 2011).
Understanding Ozark streams. Based the range of other sediment yields determined in
SW Missouri (9-87 Mg/km2/yr), sediment yields for Mineral Fork and Mill Creek were slightly
higher than the range of sediment yields for watersheds of similar sizes (Table 3). However, the
other studies may not have included in-channel sources. Since there are few published studies on
sediment budgets and channel erosion available for the Ozarks, this study filled the gaps in our
understanding of the watershed trends in channel erosion and where management efforts are
needed to reduce erosion inputs. Recently, Ozark watersheds have been experiencing a decrease
in water quality due to runoff and soil disturbances from historical land-clearing, lead and barite
mining, and cattle grazing agriculture (Jacobson and Primm, 1997; Mugel, 2017; Schumacher
and Smith, 2018; USEPA, 2018a). There are on-going concerns about excess sedimentation in
Ozark streams from bank, sheet, and rill erosion (MDNR, 2014, 2016, 2018). Eroding stream
banks can be significant sources of fine sediment to streams supplying up to 80% of the total
suspended sediment load at the watershed outlet (Harden et al., 2009; De Rose and Basher, 2011;
Kessler et al., 2013; Fox et al., 2016; Spiekermann et al., 2017). Other studies have assessed
disturbance in different reaches across watersheds. The findings of this study indicate the in-
channel sediment sources including bank and bar erosion can supply 19-55% of the annual
suspended sediment load to Ozark watersheds.
73
Table 11. Total length of stream network by stream order assessed in Mineral Fork.
Mineral Fork Stream Order
1 2 3 4 5 6 Total Total Watershed Area (490.5 km2)
Delineated stream length (km) 486.0 224.0 104.1 50.7 25.4 28.4 918.6 Delineated distribution (% by order) 53 24 11 6 3 3 100 Digitized stream length (km) 18.2 65.6 82.1 50.7 25.4 28.4 270.5 Digitized coverage (% of delineated) 4 29 79 100 100 100 29
Below Dam Area (428.3 km2)
Delineated stream length (km) 346.6 158.7 85.5 40.2 22.1 28.4 681.5 Delineated distribution (% by order) 51 23 13 6 3 4 100 Digitized stream length (km) 11.4 43.0 66.5 40.2 22.1 28.4 211.6 Digitized coverage (% of delineated) 3 27 78 100 100 100 31
Table 12. Total length of stream network by stream order assessed in Mill Creek.
Mill Creek Stream Order
1 2 3 4 5 Total Total Watershed Area (132.6 km2)
Delineated stream length (km) 138.5 70.1 30.9 23.5 5.4 268.4 Delineated distribution (% by order) 52 26 12 9 2 100 Digitized stream length (km) 0 3.8 22.5 23.5 5.4 55.2 Digitized coverage (% of delineated) 0 5 73 100 100 21
Below Dam Area (96.5 km2)
Delineated stream length (km) 104.1 45.9 24.6 23.5 5.4 203.4 Delineated distribution (% by order) 51 23 12 12 3 100 Digitized stream length (km) 0 2.4 18.3 23.5 5.4 49.6 Digitized coverage (% of delineated) 0 5 75 100 99 24
74
Table 13. Comparison of antecedent flood Conditions five years prior to aerial photograph dates.
WY Big River at Richwoods (#7018100) Meramec River near Sullivan (#7014500) Q
2.33 = 625.3 m3/s (70-year record) Q
2.33 = 718.1 m3/s (70-year record)
Date Qpk (m3/s) Qpk/Q
2.33 Date Qpk (m
3/s) Qpk/Q
2.33
Aerial photography collected during March-April 1995
1990 May 26, 1990 863 1.38 May 04, 1990 557.5 0.78 1991 Dec. 30, 1990 515 0.82 Dec. 30, 1990 653.7 0.91 1992 Apr. 20, 1992 388 0.62 Apr. 21, 1992 778.3 1.08 1993 Sep. 23, 1993 1692 2.71 Sep. 26, 1993 967.9 1.35 1994 Apr. 11, 1994 1429 2.29 Apr. 12, 1994 1596.1 2.22 Mean 977 1.56 911 1.27
Aerial photography collected during March-April 2015
2010 Oct. 30, 2009 889 1.42 Oct. 31, 2009 852 1.19 2011 Apr. 28, 2011 753 1.20 Apr. 28, 2011 722 1.00 2012 Mar. 17, 2012 149 0.24 Mar. 16, 2012 447 0.62 2013 Apr. 19, 2013 914 1.46 Mar. 18, 2013 801 1.12 2014 Apr. 03, 2014 201 0.32 Apr. 03, 2014 196 0.27
Mean= 581 0.93 603 0.84
Table 14. Active channel width reach assessment.
2015 1995 Difference Reach Stream Order
Area
(m2) Length
(m) Width
(m) Area
(m2) Length
(m) Width
(m) (m) %
1 MF 6 16,544 499 33 17,463 499 35 -1.8 -5.3 2 MF 6 33,272 482 69 30,540 482 63 5.7 8.9 3 MC 5 10,193 489 21 10,766 489 22 -1.2 -5.3 4 MC 5 19,497 490 40 17,716 490 36 3.6 10.1 5 FR 5 22,744 496 46 14,062 496 28 17.5 61.7 6 MBC 5 17,572 487 36 22,967 487 47 -11.1 -23.5 7 SB 4 11,107 487 23 5,297 487 11 11.9 109.7 8 MC 4 14,461 496 29 17,072 496 34 -5.3 -15.3 9 OMC 4 5,553 500 11 6,636 500 13 -2.2 -16.3 10 MBC 4 8,785 500 18 8,797 500 18 0.0 -0.1 11 FFB 3 5,472 494 11 4,886 494 10 1.2 12.0 12 PC 3 4,944 473 10 3,447 473 7 3.2 43.4 13 NFFR 3 3,170 494 6 6,085 494 12 -5.9 -47.9 14 CC 3 2,684 508 5 2,977 508 6 -0.6 -9.9
Mean 12, 571 492 26 12,051 492 25 1 9
75
Table 15. Height distribution per HUC-12 by stream order for bank erosion.
Avg. Bank Erosion Height 3 4 5 6
MC# 1.96 2.45 2.59 N/A Cv%* 37.3 24.0 25.6
n 10 11 5
MF 2.04 N/A N/A 2.85 Cv% 51.8 27.3
n 5 13
CCMF 1.58 1.85 N/A 2.66 Cv% 23.4 9.6 39.6
n 12 3 14
OMC 1.13 2.14 N/A N/A Cv% 26.8
n 1 7
MBC 1.80 1.96 2.02 N/A Cv% 23.7 40.6 24.0
n 10 10 5
FR 1.63 1.85 2.04 N/A Cv% 41.3 22.3 28.2
n 10 4 13
SLFR 1.62 1.61 1.90 N/A Cv% 40.1 29.6
n 10 7 1
All 1.68 1.90 2.03 2.75 Cv% 35.5 31.7 25.8 33.4
n 58 42 24 27 # 12-Digit HUC subwatershed descriptions in Table 4 * Coefficent of Variation (%) = 100 x ( Standard Deviation ÷ Mean)
76
Table 16. Height distribution per HUC-12 by stream order for bank deposition.
Avg. Bank Deposition Height 3 4 5 6
MC# 1.27 1.63 1.66 N/A Cv%* 27.9 32.1 29.3
n 10 11 5
MF 1.23 N/A N/A 2.06 Cv% 61.5 29.5
n 5 13
CCMF 1.08 1.24 N/A 2.05 Cv% 34.9 4.2 36.8
n 12 3 14
OMC 0.88 1.18 N/A N/A Cv% 32.1
n 1 7
MBC 1.16 1.31 1.55 N/A Cv% 38.8 40.5 17.4
n 10 10 5
FR 0.99 1.17 1.31 N/A Cv% 37.6 42.5 34.0
n 10 4 13
SLFR 1.03 1.22 1.39 N/A Cv% 30.1 33.0
n 10 7 1
All 1.08 1.24 1.38 2.06 Cv% 38.6 34.0 29.1 32.8
n 58 42 24 27 # 12-Digit HUC subwatershed descriptions in Table 4 * Coefficent of Variation (%) = 100 x ( Standard Deviation ÷ Mean)
77
Table 17. Height distribution per HUC-12 by stream order for bar erosion.
Avg. Bar Erosion Height 3 4 5 6
MC# 1.29 1.62 1.80 N/A Cv%* 30.4 39.8 34.9
n 10 14 5
MF 1.42 N/A N/A 1.73 Cv% 54.2 41.4
n 3 14
CCMF 1.41 1.62 N/A 1.74 Cv% 46.8 5.5 31.5
n 13 4 12
OMC N/A 1.66 N/A N/A Cv% 21.4
n 6
MBC 1.32 1.31 2.07 N/A Cv% 26.3 44.7 22.0
n 11 12 6
FR 0.95 1.25 1.26 N/A Cv% 26.3 35.0 40.0
n 13 5 13
SLFR 1.27 1.44 1.16 N/A Cv% 24.1 13.5 28.2
n 7 7 2
All 1.24 1.43 1.48 1.73 Cv% 38.7 30.5 40.3 36.4
n 57 48 26 26 # 12-Digit HUC subwatershed descriptions in Table 4 * Coefficent of Variation (%) = 100 x ( Standard Deviation ÷ Mean)
78
Table 18. Height distribution per HUC-12 by stream order for bar deposition.
Avg. Bar Deposition Height 3 4 5 6
MC# 1.43 1.48 1.69 N/A Cv%* 37.2 36.5 45.5
n 10 14 5
MF 1.42 N/A N/A 1.82 Cv% 54.2 36.6
n 3 14
CCMF 1.31 1.38 N/A 1.73 Cv% 57.5 14.9 32.3
n 13 4 12
OMC N/A 1.32 N/A N/A Cv% 40.3
n 6
MBC 0.97 1.22 1.83 N/A Cv% 40.9 46.8 34.7
n 11 12 6
FR 0.95 1.05 1.37 N/A Cv% 26.3 28.7 37.1
n 13 5 13
SLFR 1.09 1.25 0.87 N/A Cv% 22.6 29.1 4.0
n 7 7 2
All 1.11 1.24 1.46 1.78 Cv% 46.3 36.1 39.3 34.2
n 57 48 26 26 # 12-Digit HUC subwatershed descriptions in Table 4 * Coefficent of Variation (%) = 100 x ( Standard Deviation ÷ Mean)
79
Table 19. Average cell mass for bank erosion.
Mass by stream order (Mg/yr) HUC 3 4 5 6 MC 53 122 107 N/A
n 32 43 10
MF 55 N/A N/A 821 n 14 26
CCMF 40 91 N/A 357 n 28 43 29
OMC 34 47 N/A N/A n 1 21
MBC 30 96 236 N/A n 27 30 11
FR 31 51 97 N/A n 22 43 10
SLFR 24 58 10 N/A n 24 21 2
All 37 87 124 576 n 179 134 53 55
80
Table 20. Average cell mass for bank deposition.
Mass by stream order (Mg/yr) HUC 3 4 5 6 MC -14 -32 -52 N/A
n 28 36 10
MF -30 N/A N/A -328 n 13 26
CCMF -21 -83 N/A -198 n 34 9 28
OMC -12 -52 N/A N/A n 1 21
MBC -40 -60 -151 N/A n 29 31 10
FR -19 -28 -80 N/A n 41 10 28
SLFR -11 -83 -117 N/A n 19 23 1
All -22 -54 -90 -261 n 165 130 49 54
81
Tab
le 2
1.
In-C
han
nel
sed
imen
t budget
.
*R
atio
bet
wee
n E
rosi
on a
nd D
eposi
tion r
ates
for
ban
ks
and b
ars,
res
pec
tivel
y
Bel
ow
Ban
kB
ank
E/D
Bar
Bar
E/D
In-C
hann
elS
edim
ent
Dam
Ad
Ero
sio
nD
eposi
tion
Rat
io*
Ero
sio
nD
eposi
tion
Rat
io*
Lo
ad (
Net
)Y
ield
12-D
igit
HU
C W
ater
shed
s(k
m2)
(Mg/
yr)
(Mg/
km
2/y
r)
Mill
Cre
ek9
6.2
8,3
34
2,1
44
3.9
5,5
46
9,9
85
0.6
1,7
51
18.2
Min
eral
Fo
rk4
2.3
22,2
19
8,9
93
2.5
11,9
85
15,6
61
0.8
9,5
50
225
.6
Cle
ar C
reek
-Min
eral
Fo
rk7
5.6
12,5
73
7,0
11
1.8
14,0
54
12,9
85
1.1
6,6
30
87.8
Old
Min
es C
reek
39.4
1,1
97
1,1
67
1.0
1,8
75
651
2.9
1,2
54
31.8
Min
e a
Bre
ton
Cre
ek1
05
.46
,604
4,9
71
1.3
10,8
33
9,5
53
1.1
2,9
13
27.6
Fo
urch
e a
Ren
ault
96.8
4,8
45
3,3
19
1.5
6,5
20
8,1
55
0.8
-110
-1.1
Sun
nen
Lak
e-F
our
che
a R
enau
lt6
8.8
944
1,1
32
0.8
3,5
11
1,8
13
1.9
1,5
10
21.9
Min
eral
Fo
rk (
Who
le)
428
.64
8,3
82
26,5
93
1.8
48,7
77
48,8
18
1.0
21,7
48
50.7
(Mg/
yr)
(Mg/
yr)
82
Table 22. Average cell mass for bar erosion.
Mass by stream order (Mg/yr) 3 4 5 6
MC 11 102 111 N/A n 27 40 10
MF 48 N/A N/A 440 n 9 26
CCMF 33 207 N/A 401 n 23 8 29
OMC N/A 88 N/A N/A n 19
MBC 66 103 473 N/A n 25 32 11
FR 35 64 148 N/A n 39 11 30
SLFR 82 206 192 N/A n 23 21 3
All 44 120 210 420 n 146 131 54 55
83
Table 23. Average cell mass for bar deposition.
Mass by stream order (Mg/yr) HUC 3 4 5 6 MC -30 -180 -219 N/A
n 27 40 9
MF -26 N/A N/A -593 n 9 26
CCMF -17 -123 N/A -391 n 23 8 29
OMC N/A -34 N/A N/A n 19
MBC -26 -103 -487 N/A n 25 32 11
FR -26 -47 -219 N/A n 39 11 30
SLFR -30 -125 -68 N/A n 23 21 3
All -25 -118 -266 -486 n 156 128 53 55
84
Table 24. Average cell mass for net in-channel supply.
Mass by stream order (Mg/yr) HUC 3 4 5 6 MC 22 28 -32 N/A
n 33 43 10
MF 71 N/A N/A 1,526 n 14 26
CCMF 57 315 N/A 957 n 35 9 29
OMC 22 96 N/A N/A n 1 22
MBC 69 237 1,058 N/A n 184 32 11
FR 65 132 389 N/A n 47 11 30
SLFR 119 299 227 N/A n 25 21 3
All 64 156 439 1,226 n 183 138 54 55
85
Tab
le 2
5. S
edim
ent
load
wit
h a
bove
dam
contr
ibu
tions.
Ad
Upla
ndF
loodpla
inO
ther
Upla
ndS
edim
ent
(km
2)
Ero
sion
Sto
rage
Sto
rage
Load
Yie
ld
12-D
igit
HU
C W
ater
shed
s(M
g/km
2/y
r)
Mill
Cre
ek132.6
115,1
57
-25,0
00
-77,6
03
12,5
54
94.7
Min
eral
Fork
51.5
21,2
30
-17,8
79
-2,2
76
5,6
27
109.3
Cle
ar C
reek
-Min
eral
Fork
98.8
30,6
72
-27,4
64
-856
4,0
64
41.1
Old
Min
es C
reek
48.1
27,5
21
-7,9
39
-15,1
68
4,4
13
91.8
Min
e a
Bre
ton
Cre
ek123.6
116,4
66
-24,4
82
-77,4
57
14,5
28
117.5
Four
che
a R
enau
lt100.7
71,6
19
-31,7
77
-30,5
16
9,3
26
92.6
Sun
nen
Lak
e-F
our
che
a R
enau
lt68.8
14,5
03
-17,3
31
-4,9
88
2,1
60
31.4
Min
eral
Fork
(W
hole
)490.5
292,5
22
-122,6
82
-145,7
08
24,1
32
49.2
(Mg/
yr)
Tab
le 2
6.
Sed
imen
t lo
ad b
elo
w d
ams.
Ad
Up
land
Flo
od
pla
inO
ther
Up
land
Sed
imen
t%
Dam
(km
2)
Ero
sio
nS
tora
geS
tora
geL
oad
Yie
ldS
edim
ent
12-D
igit
HU
C W
ater
shed
s(M
g/k
m2/y
r)R
educ
tion
Mill
Cre
ek9
6.2
57,5
25
-23,2
69
-26,5
16
7,7
41
58.4
38.3
Min
eral
Fo
rk4
2.3
25,4
92
-16,0
27
-5,3
40
4,1
25
80.1
26.7
Cle
ar C
reek
-Min
eral
Fo
rk7
5.6
24,5
09
-19,8
03
-962
3,4
67
35.1
14.7
Old
Min
es C
reek
39.4
23,8
43
-6,9
48
-12,8
78
4,0
18
83.5
9.0
Min
e a
Bre
ton
Cre
ek1
05
.41
10
,394
-23,4
17
-72,6
46
14,3
31
115
.91
.4
Fo
urch
e a
Ren
ault
96.8
70,9
04
-31,3
40
-30,2
37
9,3
28
92.7
0.0
Sun
nen
Lak
e-F
our
che
a R
enau
lt6
8.8
7,2
51
-4,2
32
-2,3
84
635
9.2
70.6
Min
eral
Fo
rk (
Who
le)
428
.61
98
,538
-108
,263
-72,4
90
17,7
85
36.3
26.3
(Mg/
yr)
86
Tab
le 2
7. S
edim
ent
load
budget
for
bel
ow
dam
s.
Ad
Up
land
Up
land
Flo
od
pla
inO
ther
Net
Ban
kN
et B
arT
ota
lS
edim
ent
(km
2)
Ero
sio
nL
oad
Sto
rage
Sto
rage
Ero
sio
nE
rosi
on
Lo
adY
ield
12-D
igit
HU
C W
ater
shed
s(M
g/k
m2/y
r)
Mill
Cre
ek9
6.2
57,5
25
7,7
41
-23,2
69
-26,5
16
6,1
90
-4,4
39
9,4
92
98.6
Min
eral
Fo
rk4
2.3
25,4
92
4,1
25
-16,0
27
-5,3
40
13,2
27
-3,6
76
13,6
75
323
.0
Cle
ar C
reek
-Min
eral
Fo
rk7
5.6
24,5
09
3,4
67
-19,8
03
-962
5,5
61
1,0
69
10,0
98
133
.7
Old
Min
es C
reek
39.4
23,8
43
4,0
18
-6,9
48
-12,8
78
30
1,2
24
5,2
72
133
.7
Min
e a
Bre
ton
Cre
ek1
05
.41
10
,394
14,3
31
-23,4
17
-72,6
46
1,6
33
1,2
80
17,2
44
163
.6
Fo
urch
e a
Ren
ault
96.8
70,9
04
9,3
28
-31,3
40
-30,2
37
1,5
25
-1,6
35
9,2
18
95.2
Sun
nen
Lak
e-F
our
che
a R
enau
lt6
8.8
7,2
51
635
-4,2
32
-2,3
84
-188
1,6
98
2,1
46
31.2
Min
eral
Fo
rk (
Who
le)
428
.61
98
,538
17,7
85
-108
,263
-72,4
90
21,7
89
-41
39,5
33
92.2
(Mg/
yr)
87
Table 28. Suspended sediment loads below dams from upland erosion by land use.
Ad TSS (Mg/yr) Watershed (km
2) Urban Cropland Pastureland Forest Mined Total
Mineral Fork 490.5 916 1,872 4,856 4,705 5,436 17,785 % of Load 5 11 27 26 31 100
% of total Area 6 0.3 10 82 3 100
Mill Creek 132.6 304 191 1,045 1,687 4,513 7,741 % of Load 4 2 14 22 58 100
% of total Area 7 0.2 7 78 8 100
Figure 15. Number of cells in each subwatershed by stream order below dams.
0
10
20
30
40
50
60
70
80
90
100
MC MF CCMF OMC MBC FR SLFR
# o
f C
ells
Subwatersheds
3 4 5 6
88
89
Figure 17. Planform analysis for Mill Creek with bar and bank erosion and polygons.
90
Figure 18. Annual peak flood record (1950-2019, 70 years).
Figure 19. Active channel width reach assessment.
0
200
400
600
800
1000
1200
1950 1960 1970 1980 1990 2000 2010 2020
Un
it Q
pk
(l/s
/km
2)
Year
Big River Meramec River 4 per. Mov. Avg. (Big River) 4 per. Mov. Avg. (Meramec River)
y = 0.865x + 2.3826
R² = 0.838
0
10
20
30
40
50
60
70
0 10 20 30 40 50 60 70
20
15
Act
ive
Ch
an
nel
Wid
th (
m)
1995 Active Channel Width (m)
Channel Width 1:1 Width Linear (Channel Width)
1995
Photograph
Year
2015
Photograph
Year
91
Figure 20. Average bank and bar heights.
Figure 21. Average active channel width in 2015 (A) and 1995 (B).
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3 4 5 6
Av
g. H
eig
ht
(m)
Stream Order
Bank Erosion Bank Deposition
Bar Erosion Bar Deposition
0
10
20
30
40
50
60
3 4 5 6
20
15
Ch
an
nel
Wid
th (
m)
Stream Order
MC MF CCMF OMC MBC FR SLFR
0
10
20
30
40
50
60
3 4 5 6
19
95
Ch
an
nel
Wid
th (
m)
Stream Order
MC MF CCMF OMC MBC FR SLFR
A)
B)
92
Figure 22. Active channel width change from 1995 to 2015. A) percent change in active width;
and B) annual bank erosion rate as a percent of active channel width.
-50-40-30-20-10
01020
304050
3 4 5 6
Wid
th C
ha
ng
e (%
)
Stream Order
MC MF CCMF OMC MBC FR SLFR
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
3 4 5 6
Av
g. B
an
k E
rosi
on
Ra
te a
s %
of
Ch
an
nel
Wid
th
Stream Order
MC MF CCMF OMC MBC FR SLFR
A)
B)
93
Figure 23. Average bar width in 2015 (A) and 1995 (B).
Figure 24. Percent bar width change from 1995 to 2015.
0
5
10
15
20
3 4 5 6
20
15
Ba
r W
idth
(m
)
Stream Order
MC MF CCMF OMC MBC FR SLFR
0
5
10
15
20
3 4 5 6
19
95
Ba
r W
idth
(m
)
Stream Order
MC MF CCMF OMC MBC FR SLFR
-70
-50
-30
-10
10
30
50
70
3 4 5 6
Wid
th C
ha
ng
e (%
)
Stream Order
MC MF CCMF OMC MBC FR SLFR
A)
B)
94
Figure 25. Mass of fine sediment from in-channel contributions.
Figure 26. Cells highlighting no erosion, erosion, and high erosion cells that make up 25% of the
bank erosion mass.
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
MC MF CCMF OMC MBC FR SLFR MF-Whole
Ma
ss o
f F
ine
Sed
imen
t (M
g/y
r)
Bank Erosion Bank Deposition
Bar Erosion Bar Deposition
95
Figure 27. Cells highlighting no erosion, erosion, and high erosion cells that make up 25% of the
bar erosion mass.
Figure 28. Cells highlighting deposition, erosion, and high erosion cells that make up 25% of the
erosion mass.
96
Figure 29. Alternating pattern of erosion and deposition upstream (27 km) to downstream (0 km)
in the Mill Creek watershed.
Figure 30. Mass sediment budget for Mineral Fork watershed (Mg/yr).
97
Figure 31. Mass sediment budget for Mill Creek watershed (Mg/yr).
98
Figure 32. In-channel contributions to sediment loads. (A) Bank erosion compared to upland
erosion loads; (B) Bar erosion compared to upland erosion loads; and (C) In-channel load
contribution to total load.
-2
-1
0
1
2
3
4
5
6
MC MF CCMF OMC MBC FR SLFR MF-Whole
Ra
tio
to
Up
lan
d L
oa
dBank Erosion
Net Bank Erosion
-2
-1
0
1
2
3
4
5
6
MC MF CCMF OMC MBC FR SLFR MF-Whole
Ra
tio
to
Up
lan
d L
oa
d
Bar Erosion
Net Bar Erosion
-10
0
10
20
30
40
50
60
70
80
MC MF CCMF OMC MBC FR SLFR MF-Whole
% o
f T
ota
l L
oa
d
In-Channel Load
A)
B)
C)
99
CONCLUSIONS
The purpose of this study was to assess and evaluate the contributions of bank and bar
erosion to annual sediment loads of the Mineral Fork and Mill Creek watersheds in the Ozark
Highlands, Missouri. Since there were no published studies available for the Ozarks on this
topic, this study filled a research gap and presented a methodology for understanding the
watershed trends (i.e. by stream order and subwatersheds) in channel erosion which can be used
to inform management efforts to reduce bank erosion impacts on sediment loads. Historical
tailings dams were also assessed to evaluate the degree to which these legacy structures trapped
upland sediment loads. Sediment budgets were created using the EPA’s STEPL model to
calculate suspended sediment loads and from in-channel erosion and deposition rates derived
from this study. The land use and soil types were also assessed to understand their influence
suspended sediment loads. Fine sediment can be deposited on the channel banks, beds, and bars
and remain in storage for variable amounts of time before it is remobilized and transported
downstream (Jacobson and Gran, 1999; Davis, 2009; Donovan et al., 2015; Groten et al., 2016).
This is one of the first studies to directly assess the amounts and spatial distribution of bank and
bar erosion and deposition at the watershed-scale in the Ozark Highlands. The findings indicated
that channel processes are important controls on sediment yields in these watersheds and
validates the use of historical aerial photography to assess channel morphology and sediment
processes in a mining-disturbed watershed. The main conclusions of this study were:
1. Based the range of other sediment yields determined in Missouri, Mineral Fork and
Mill Creek are slightly above the range of sediment yields for watersheds of similar
size within the Ozark Highlands from 9 to 1,197 km2. After establishing a sediment
100
budget, Mineral Fork was contributing a sediment yield of 92 Mg/km2/yr to Big River
and Mill Creek was contributing a sediment yield of 99 Mg/km2/yr to Big River.
2. In-channel processes from bank and bar erosion and deposition contribute a
significant amount of sediment to the overall sediment budget. Bank erosion
contributes to 55% of the sediment load in Mineral Fork and 33% in Mill Creek.
Additionally, the bars influenced the load by <1% in Mineral Fork and 24% in Mill
Creek by reducing the overall sediment load to the outlet of the watershed. Eroding
stream banks can supply <1% to 63% of the total suspended sediment load at the
watershed outlet from the subwatersheds. Some subwatersheds had bar erosion
supply 7% to 67% to the of the load, while other reduced the load from 13 to 24%.
These results indicate that in-channel processes are important controls on sediment
yields in these disturbed watersheds.
3. Remaining barite tailings ponds and dams trap significant amounts of eroded soil and
stream sediment in these watersheds. These large dams retain 100% of the sediment
delivered to them and almost all the flow. Contributing land areas draining to large
tailings dams cover 27% of the land area in Mineral Fork and 28% in Mill Creek. A
USLE-modeling approach (STEPL) suggests that about 26% of the annual sediment
load is captured behind tailings dams in Mineral Fork and 38% in Mill Creek. This is
equivalent to reducing sediment yields by 12.9 and 36.3 Mg/km2/yr, respectively.
4. Upland soil erosion from mining disturbed lands and pastures provide the highest
contributions to suspended sediment loads to the study watersheds. This study used
LiDAR and aerial photography to develop an accurate delineation of lands disturbed
by historical mining. Mining disturbed lands cover about 3% of Mineral Fork and
101
15% of Mill Creek watershed but contribute 31% and 58% of the sediment load from
the uplands, respectively. Pastures cover about 10% of Mineral Fork and 6% of Mill
Creek watershed but contribute 27% and 14% of the sediment load, respectively.
More work is needed to further evaluate why mining areas were associated with high
channel erosion and sediment load rates in this study.
Fluvial erosion of channel banks and gravel bars can provide significant contributions of
fine sediment to stream loads in streams in the Ozark Highlands. This study found that in-
channel erosion can provide 19-55% of the predicted annual sediment load from Mineral Fork
and its subwatersheds and Mill Creek in Washington County, Missouri. Previous work has
focused attention on the spatial distribution and causes of mobile gravel bar formation as an
indicator of coarse sediment transport and storage in Ozark rivers. However, this study is the first
to evaluate the role of bar erosion and deposition in the storage and supply of fine sediment in
the channel. While bank erosion was a net source of fine sediment to the channel during the 1995
to 2015 study period, bar deposition involved relatively large masses of fine sediment indicating
the potential to be an important net sink or source in the channel system if environmental
conditions change. It is not clear about the long-term influence of bar storage on sediment loads
in these watersheds.
Land use may also have played a role in controlling in-channel sources of fine sediment.
Tailings ponds and dams left behind by historical barite mining activities presently trap about a
third of the stream sediment loads in these watersheds. Further, mining disturbed lands tend to be
associated with relatively high upland erosion rates and channel instability. This study provided
evidence that in-channel fine sediment may play an important role in regulating suspended
sediment loads, thus potentially linking geomorphic processes to NPS water quality conditions.
102
However, more research is needed to better understand fine-grained sediment storage and
suspended sediment transport in Ozark streams. Nevertheless, the present study provided a
framework to use the combination of stream channel and fine sediment assessments to better
understand how fluvial processes and sediment transport operate over decadal timescales in
watersheds.
103
REFERENCES
Adamski, J.C., Petersen, J.C., Freiwald, D.A., Davis, J. V, 1995. Environmental and hydrologic
setting of the Ozark Plateaus study unit, Arkansas, Kansas, Missouri, and Oklahoma, U.S.
Geological Survey Water-Resources Investigations Report.
Baartman, J.E.M., Masselink, R., Keesstra, S.D., Temme, A.J.A.M., 2013. Linking landscape
morphological complexity and sediment connectivity. Earth Surf. Process. Landforms 38,
1457–1471. https://doi.org/10.1002/esp.3434
Barr, M.N., 2016. Surface-Water Quality and Suspended-Sediment Quantity and Quality within
the Big River Basin, Southeastern Missouri, 2011–13. Scientific Investigations Report 2015
– 5171.
Beach, T., 1994. The Fate of Eroded Soil: Sediment Sinks and Sediment Budgets of Agrarian
Landscapes in Southern Minnesota, 1851-1988. Ann. Assoc. Am. Geogr. 84, 5–28.
https://doi.org/10.1111/j.1467-8306.1994.tb01726.x
Beck, W., Isenhart, T., Moore, P., Schilling, K., Schultz, R., Tomer, M., 2018. Streambank
alluvial unit contributions to suspended sediment and total phosphorus loads, walnut Creek,
Iowa, USA. Water (Switzerland) 10, 22. https://doi.org/10.3390/w10020111
Betts, H.D., Trustrum, N.A., De Rose, R.C., 2003. Geomorphic changes in a complex gully
system measured from sequential digital elevation models, and implications for
management. Earth Surf. Process. Landforms 28, 1043–1058.
Blanckaert, K., 2011. Hydrodynamic processes in sharp meander bends and their morphological
implications. J. Geophys. Res. Earth Surf. 116, 1–22. https://doi.org/10.1029/2010JF001806
Bracken, L.J., Turnbull, L., Wainwright, J., Bogaart, P., 2015. Sediment connectivity: A
framework for understanding sediment transfer at multiple scales. Earth Surf. Process.
Landforms 40, 177–188. https://doi.org/10.1002/esp.3635
Brierley, G., Fryirs, K., Jain, V., 2006. Landscape connectivity: The geographic basis of
geomorphic applications. R. Geogr. Soc. 38, 165–174. https://doi.org/10.1111/j.1475-
4762.2006.00671.x
Brown, T.C., Froemke, P., 2012. Nationwide Assessment of Nonpoint Source Threats to Water
Quality. Bioscience 62, 136–146. https://doi.org/10.1525/bio.2012.62.2.7
Brown, T.C., Froemke, P., 2010. Risk of impaired condition of watersheds containing National
Forest lands. Fort Collins, CO.
104
Bunte, K., Abt, S.R., 2001. Sampling Surface and Subsurface Particle-Size Distributions in
Wadable Gravel- and Cobble-Bed Streams for Analyses in Sediment Transport , Hydraulics
, and Streambed Monitoring, General Technical Report RMRS-GTR-74. Rocky Mountain
Research Station, Fort Collins, CO. https://doi.org/10.1017/CBO9781107415324.004
Carlson, J.L., 1999. Zinc mining contamination and sedimentation rates of historical overbank
deposits, Honey Creek Watershed, southwest Missouri. Missouri State University.
Couper, P., Stott, T., Maddock, I., 2002. Insights into river bank erosion processes derived from
analysis of negative erosion-pin recordings: Observations from three recent UK studies.
Earth Surf. Process. Landforms 27, 59–79. https://doi.org/10.1002/esp.285
Davis, L., 2009. Sediment Entrainment Potential in Modified Alluvial Streams: Implications for
Re-mobilization of Stored In-channel Sediment. Phys. Geogr. 30, 249–268.
De Rose, R.C., Basher, L.R., 2011. Geomorphology Measurement of river bank and cliff erosion
from sequential LIDAR and historical aerial photography. Geomorphology 126, 132–147.
https://doi.org/10.1016/j.geomorph.2010.10.037
Donovan, M., Miller, A., Baker, M., Gellis, A., 2015. Sediment contributions from floodplains
and legacy sediments to Piedmont streams of Baltimore County, Maryland. Geomorphology
235, 88–105. https://doi.org/10.1016/j.geomorph.2015.01.025
Dunning, D., 2017. Void Ratio for Common Gravel & Sand [WWW Document]. Sciencing.
URL https://sciencing.com/void-ratio-common-gravel-sand-7958152.html (accessed
4.2.20).
Emili, L.A., Greene, R.P., 2013. Modeling agricultural nonpoint source pollution using a
geographic information system approach. Environ. Manage. 51, 70–95.
https://doi.org/10.1007/s00267-012-9940-4
Ferguson, R.I., Parsons, D.R., Lane, S.N., Hardy, R.J., 2003. Flow in meander bends with
recirculation at the inner bank. Water Resour. Res. 39.
https://doi.org/10.1029/2003WR001965
Foucher, A., Salvador-Blanes, S., Vandromme, R., Cerdan, O., Desmet, M., 2017. Quantification
of bank erosion in a drained agricultural lowland catchment. Hydrol. Process. 31.
https://doi.org/10.1002/hyp.11117
Fox, G.A., Purvis, R.A., Penn, C.J., 2016. Streambanks: A net source of sediment and
phosphorus to streams and rivers. J. Environ. Manage. 181, 602–614.
https://doi.org/10.1016/j.jenvman.2016.06.071
Gillespie, J.L., Noe, G.B., Hupp, C.R., Gellis, A.C., Schenk, E.R., 2018. Floodplain trapping and
cycling compared to streambank erosion of sediment and nutrients in an agricultural
watershed. J. Am. Water Resour. Assoc. 54, 565–582.
105
Gran, K.B., Belmont, P., Day, S.S., Jennings, C., Johnson, A., Perg, L., Wilcock, P.R., 2009.
Geomorphic evolution of the Le Sueur River, Minnesota, USA, and implications for current
sediment loading. Spec. Pap. Geol. Soc. Am. 451, 119–130.
https://doi.org/https://doi.org/10.1130/2009.2451(08)
Gregg, J.M., Shelton, K.L., 1989. Minor- and trace-element distributions in the Bonneterre
Dolomite (Cambrian), southeast Missouri: Evidence for possible multiple-basin fluid
sources and pathways during lead-zinc mineralization. Bull. Geol. Soc. Am. 101, 221–230.
https://doi.org/10.1130/0016-7606(1989)101<0221:MATEDI>2.3.CO;2
Groten, J.T., Ellison, C.A., Hendrickson, J.S., 2016. Suspended-Sediment Concentrations,
Bedload, Particle Sizes, Surrogate Measurements, and Annual Sediment Loads for Selected
Sites in the Lower Minnesota River Basin, Water Years 2011 through 2016, U.S.
Geological Survey Scientific Investigations Report 2016-5174.
Hagstrom, C.A., Leckie, D.A., Smith, M.G., 2018. Point bar sedimentation and erosion produced
by an extreme flood in a sand and gravel-bed meandering river. Sediment. Geol. 377, 1–16.
Happ, S.C., 1944. Effect of sedimentation on floods in the Kickapoo Valley, Wisconsin. Geology
52, 53–68.
Harden, C.P., Foster, W., Morris, C., Chartrand, K.J., Henry, E., 2009. Rates and Processes of
Streambank Erosion in Tributaries of the Little River, Tennessee. Phys. Geogr. 30, 1–16.
https://doi.org/10.2747/0272-3646.30.1.1
Hart, E.A., Schurger, S.G., 2005. Sediment storage and yield in urbanized karst waters.
Geomorphology 70, 85–96.
Hession, W.C., Pizzuto, J.E., Johnson, T.E., Horwitz, R.J., 2003. Influence of bank vegetation on
channel morphology in rural and urban watersheds. Geol. Soc. Am. 31, 147–150.
Höfle, B., Rutzinger, M., 2011. Topographic airborne LiDAR in geomorphology: A
technological perspective. Zeitschrift fur Geomorphol. 55, 1–29.
https://doi.org/10.1127/0372-8854/2011/0055S2-0043
Huang, D., 2012. Quantifying Stream Bank Erosion and Deposition Rates in a Central U.S.
Urban Watershed. University of Missouri-Columbia.
Hughes, M.L., McDowell, P.F., Marcus, W.A., 2006. Accuracy assessment of georectified aerial
photographs: Implications for measuring lateral channel movement in a GIS.
Geomorphology 74, 1–16. https://doi.org/10.1016/j.geomorph.2005.07.001
Hutchison, E.C.D., 2010. Mass transport of suspended sediment, dissolved solids, nutrients, and
anions in the James River, SW Missouri. Missouri State University.
106
Jacobson, R.B., 1995. Spatial controls on patterns of land-use induced stream disturbance at the
drainage-basin scale—An example from gravel-bed streams of the Ozark Plateaus,
Missouri., AGU Geophy. ed. American Geophysical Union, Washington, DC.
Jacobson, R.B., Gran, K.B., 1999. Gravel sediment routing from widespread, low-intensity
landscape disturbance, Current River basin, Missouri. Earth Surf. Process. Landforms 24,
897–917. https://doi.org/10.1002/(SICI)1096-9837(199909)24:10<897::AID-
ESP18>3.0.CO;2-6
Jacobson, R.B., Primm, a T., 1997. Historical land-use changes and potential effects on stream
disturbance in the Ozark Plateaus, Missouri, U. S. Geological Survey Water-Supply Paper
2484.
Jacobson, R.B., Pugh, A.L., 1997. Riparian-vegetation controls on the spatial pattern of stream-
channel instability, Little Piney Creek, Missouri. Denver, CO.
James, L.A., 2013. Legacy sediment: Definitions and processes of episodically produced
anthropogenic sediment. Anthropocene 2, 16–26.
https://doi.org/10.1016/j.ancene.2013.04.001
Janes, V.J.J., Nicholas, A.P., Collins, A.L., Quine, T.A., 2017. Analysis of fundamental physical
factors influencing channel bank erosion: results for contrasting catchments in England and
Wales. Environ. Earth Sci. 76, 1–18. https://doi.org/10.1007/s12665-017-6593-x
Jordan, M.M., 2019. Historical Floodplain Sedimentation Rates Using Mining Contaminant
Profiles, Cesium-137, and Sediment Source Indicators along the Lower Big River, Jefferson
County, Missouri. Missouri State University.
Joyce, H.M., Hardy, R.J., Warburton, J., Large, A.R.G., 2018. Sediment continuity through the
upland sediment cascade: geomorphic response of an upland river to an extreme flood
event. Geomorphology 317, 45–61. https://doi.org/10.1016/j.geomorph.2018.05.002
Julian, J.P., Torres, R., 2006. Hydraulic erosion of cohesive riverbanks. Geomorphology 76,
193–206.
Keppel, A., Owen, M.R., Pavlowsky, R.T., 2015. Mining influence on lead profiles in historical
floodplain deposits along the Big River, in: 49th Annual Meeting of the South Central
Section of the Geological Society of America. Stillwater, OK, March 19-20.
Kessler, A.C., Gupta, S.C., Brown, M.K., 2013. Assessment of river bank erosion in Southern
Minnesota rivers post European settlement. Geomorphology 201, 312–322.
https://doi.org/10.1016/j.geomorph.2013.07.006
Kessler, A.C., Gupta, S.C., Dolliver, H.A.S., Thoma, D.P., 2012. Lidar Quantification of Bank
Erosion in Blue Earth County, Minnesota. J. Environ. Qual. 41, 197.
https://doi.org/10.2134/jeq2011.0181er
107
Knighton, D., 1998. Fluvial Forms & Processes: A New Perspective. Oxford University Press
Inc., New York.
Knox, J.C., 2006. Floodplain sedimentation in the Upper Mississippi Valley: Natural versus
human accelerated. Geomorphology 79, 286–244.
https://doi.org/10.1016/j.geomorph.2006.06.031
Knox, J.C., 1987. Historical Valley Flood Sedimentation in the Upper Mississippi Valley. Ann.
Assoc. Am. Geogr. 77, 224–244.
Knox, J.C., 1972. Valley alluviation in southwestern Wisconsin. Ann. Assoc. Am. Geogr. 62,
401–410.
Kondolf, G.M., 1997. Hungry water: Effects of dams and gravel mining on river channels.
Environ. Manage. 21, 533–551. https://doi.org/10.1007/s002679900048
Lauer, J.W., Echterling, C., Lenhart, C., Belmont, P., Rausch, R., 2017. Air-photo based change
in channel width in the Minnesota River basin: Modes of adjustment and implications for
sediment budget. Geomorphology 297, 170–184.
https://doi.org/10.1016/j.geomorph.2017.09.005
Lawler, D.M., 1993. The Measurement of River Bank Erosion and Lateral Channel Change: A
Review. Earth Process. Landforms 18, 777–821.
Lecce, S.A., 1997. Spatial patterns of historical overbank sedimentation and floodplain
evolution, Blue river, Wisconsin. Geomorphology 18, 265–277.
https://doi.org/10.1016/s0169-555x(96)00030-x
Lecce, S.A., Pavlowsky, R.T., 2014. Geomorphology Floodplain storage of sediment
contaminated by mercury and copper from historic gold mining at Gold Hill , North
Carolina , USA. Geomorphology 206, 122–132.
https://doi.org/10.1016/j.geomorph.2013.10.004
Leopold, L.B., 1973. River Channel Change with Time: An Example. Geol. Soc. Am. Bull. 84,
1845–1869.
Liu, Y., Li, S., Wallace, C.W., Chaubey, I., Flanagan, D.C., Theller, L.O., Engel, B.A., 2017.
Comparison of Computer Models for Estimating Hydrology and Water Quality in an
Agricultural Watershed. Water Resour. Manag. https://doi.org/10.1007/s11269-017-1691-9
Magilligan, F.J., 1985. Historical floodplain sedimentation in the Galena River Basin, Wisconsin
and Illinois. Ann. Assoc. Am. Geogr. 75, 583–594.
Manger, G.E., 1963. Porosity and Bulk Density of Sedimentary Rocks: Contributions to
Geochemistry. Washington, DC. https://doi.org/10.1111/nan.12452
108
Marron, D.C., 1992. Floodplain Strogae of Mine Tailings in the Belle Fourche River System: A
Sediment Budget Approach. Earth Surf. Process. Landforms 17, 675–685.
Martin, D.J., Pavlowsky, R.T., 2011. Spatial Patterns of Channel Instability Along an Ozark
River, Southwest Missouri. Phys. Geogr. 32, 445–468.
MDNR, 2018. 2018 Section 303(d) Listed Waters: TMDL Prioritization and Development
Schedule [WWW Document]. URL https://dnr.mo.gov/env/wpp/tmdl/documents/tmdl-
priorities-and-schedule-for-2018-303dlist.pdf (accessed 10.2.18).
MDNR, 2016. The State of Our Missouri Waters: Meramec River Watershed [WWW
Document].
MDNR, 2014. The State of Our Missouri Waters: Big River Watershed [WWW Document].
Missouri Dep. Nat. Resour. URL https://dnr.mo.gov/omw/docs/omw-big-summary.pdf
(accessed 10.3.18).
MDNR, 2008. Missouri Department of Natural Resources Water Protection Program Total
Maximum Daily Load ( TMDL ) for Tributary to Pond Creek Washington County,
Missouri.
MDNR, 2006. Biological Assessment Report Mill Creek Washington County , Missouri
September 2005- March 2006.
Meade, R.H., 1982. Sources, Sinks, and Storage of River Sediment in the Atlantic Drainage of
the United States. Geology 90, 235–252.
Michalkova, M., PieGay, H., Kondolf, G.M., Greco, S.E., 2011. Lateral erosion of the
Sacramento River, California (1942-1999), and responses of channel and floodplain lake to
human influences. Earth Surf. Process. Landforms 36, 257–272.
https://doi.org/10.1002/esp.2106
Mount, N., Louis, J., 2005. Estimation and propagation of error in measurements of river channel
movement from aerial imagery. Earth Surf. Process. Landforms 30, 635–643.
https://doi.org/10.1002/esp.1172
MRCC, 2018. State and Climate Division Data - Monthly by Year [WWW Document]. URL
https://mrcc.illinois.edu/CLIMATE/nClimDiv/STCD_monthly1.jsp (accessed 10.17.18).
MSDIS, 2019. MO 2019 Dams [WWW Document]. Missouri Spat. Data Inf. Serv.
MSDIS, 2017. Missouri County-Extent Digital Ortho Quarter Quads [WWW Document]. URL
http://www.msdis.missouri.edu/data/imagery/index.html (accessed 10.18.18).
Mugel, D.N., 2017. Geology and Mining History of the Southeast Missouri Barite District and
the Valles Mines, Washington, Jefferson, and St. Francois Counties, Missouri.
109
Nejadhashemi, A.P., Woznicki, S.A., Douglas-Mankin, K.R., 2011. Comparison of Four Models
(STEPL, PLOAD, L-THIA, and SWAT) in Simulating Sediment, Nitrogen, and Phosphorus
Loads and Pollutant Source Areas. Am. Soc. Agric. Biol. Eng. 54, 875–890.
Nigh, T.A., Schroeder, W.A., 2002. Atlas of Missouri Ecoregions.
Notebaert, B., Verstraeten, G., Govers, G., Poesen, J., 2009. Qualitative and quantitative
applications of LiDAR imagery in fluvial geomorphology. Earth Surf. Process. Landforms
34, 217–231. https://doi.org/10.1002/esp
NRCS, 1983. National Engineering Handbook:, Part 630 Hydrology.
Odgaard, A.J., 1987. Streambank erosion along two rivers in Iowa. Water Resour. Res. 23.
Olson, L.M., 2017. Channel Bar Morphology, Distribution, and Mining-Related Geochemistry in
the Big River, St. Francois County, Missouri: Implications for Geomorphic Recovery.
Missouri State University.
Owen, M.R., Pavlowsky, R.T., 2015. Nonpoint Source Bank Erosion and Load Reduction
Assessment for the Pearson Creek 319 Riparian Corridor Easement Site, 5377 E . Foxgrove
Lane Greene County, Missouri.
Owen, M.R., Pavlowsky, R.T., Womble, P.J., 2011. Historical disturbance and contemporary
floodplain development along an Ozark river, Southwest Missouri. Phys. Geogr. 32, 423–
444.
Palmer, J.A., Schilling, K.E., Isenhart, T.M., Schultz, R.C., Tomer, M.D., 2014. Streambank
erosion rates and loads within a single watershed: Bridging the gap between temporal and
spatial scales. Geomorphology 209, 66–78. https://doi.org/10.1016/j.geomorph.2013.11.027
Panfil, M.S., Jacobson, R.B., 2001. Relations Among Geology, Physiography, Land Use, and
Stream Habitat Conditions in the Buffalo and Current River Systems, Missouri and
Arkansas [WWW Document]. Biol. Sci. Rep. USGS/BRD/BSR--2001-0005. URL
https://www.cerc.usgs.gov/pubs/center/pdfdocs/BSR2001-0005.pdf (accessed 10.1.19).
Park, Y.S., Engel, B.A., Harbor, J., 2014. A web-based model to estimate the impact of best
management practices. Water (Switzerland) 6, 455–471. https://doi.org/10.3390/w6030455
Park, Y.S., Engel, B.A., Kim, J., Theller, L., Chaubey, I., Merwade, V., Lim, K.J., 2015. A web
tool for STORET/WQX water quality data retrieval and Best Management Practice scenario
suggestion. J. Environ. Manage. 150, 21–27. https://doi.org/10.1016/j.jenvman.2014.11.006
Pavlowsky, R.T., 2013. Source allocation for lead-contaminated sediment in the Big River from
two different mining sources in St. Francois and Washington Counties, Missouri.
110
Pavlowsky, R.T., Lecce, S.A., Owen, M.R., Martin, D.J., 2017. Legacy sediment, lead, and zinc
storage in channel and floodplain deposits of the Big River, Old Lead Belt Mining District,
Missouri, USA. Geomorphology 299, 54–75.
https://doi.org/10.1016/j.geomorph.2017.08.042
Pavlowsky, R.T., Owen, M.R., 2015. Floodplain Core Sampling and Lead Contamination at St .
Francois State Park and Washington State Park , Southeast Missouri.
Pavlowsky, R.T., Owen, M.R., Martin, D.J., OEWRI, 2010. Distribution, Geochemistry, and
Storage of Mining Sediment in Channel and Floodplain Deposits of the Big River System in
St . Francois, Washington, and Jefferson Counties, Missouri Field work completed Fall
2008 to Spring 2009.
Peel, M.C., Finlayson, B.L., McMahon, T.A., 2007. Updated world map of the Köppen-Geiger
climate classification. Hydrol. Earth Systm. Sci. Discuss. 4, 439–473.
Phillips, J.D., 1991. Fluvial sediment budgets in the North Carolina Piedmont. Geomorphology
4, 231–241. https://doi.org/10.1016/0169-555X(91)90006-V
Podhoranyi, M., Fedorcak, D., 2014. Inaccuracy introduced by LiDAR-generated cross sections
and its impact on 1D hydrodynamic simulations. Environ. Earth Sci. 73, 1–11.
https://doi.org/10.1007/s12665-014-3390-7
Poole, G.C., 2002. Fluvial landscape ecology: Addressing uniqueness within the river
discontinuum. Freshw. Biol. 47, 641–660. https://doi.org/https://doi.org/10.1046/j.1365-
2427.2002.00922.x
Reminga, K.N., 2019. Historical Land Use Influence on Fine-Grained Sedimentation in Channel
and Floodplain Deposits in a Forested Missouri Ozark Watershed. Missouri State
University.
Renwick, W.H., Smith, S. V., Bartley, J.D., Buddemeier, R.W., 2005. The role of impoundments
in the sediment budget of the conterminous United States. Geomorphology 71, 99–111.
https://doi.org/10.1016/j.geomorph.2004.01.010
Rhoades, E.L., O’Neal, M.A., Pizzuto, J.E., 2009. Quantifying bank erosion on the South River
from 1937 to 2005, and its importance in assessing Hg contamination. Appl. Geogr. 29,
125–134. https://doi.org/10.1016/j.apgeog.2008.08.005
Roering, J.J., Mackey, B.H., Marshall, J.A., Sweeney, K.E., Deligne, N.I., Booth, A.M.,
Handwerger, A.L., Cerovski-Darriau, C., 2013. “You are HERE”: Connecting the dots with
airborne lidar for geomorphic fieldwork. Geomorphology 200, 172–183.
https://doi.org/10.1016/j.geomorph.2013.04.009
Rosgen, D.L., 1994. A classification of natural rivers. Catena 22, 169–199.
https://doi.org/https://doi.org/10.1016/0341-8162(94)90001-9
111
Schenk, E.R., Hupp, C.R., 2009. Legacy effects of colonial millponds on floodplain
sedimentation, bank erosion, and channel morphology, Mid-Atlantic, USA. J. Am. Water
Resour. Assoc. 45, 596–606.
Schumacher, J.G., Smith, D.C., 2018. Distribution of Mining-Related Trace Elements in
Streambed and Flood-Plain Sediment along the Middle Big River and Tributaries in the
Southeast Missouri Barite District , 2012 – 15 Scientific Investigations Report 2018 – 5103.
Seeger, C., 2006. Old Mines Area Sample Area Mining History and Geology, Memorandum.
Sekely, A.C., Mulla, D.J., Bauer, D.W., 2002. Streambank slumping and its contributions to the
phosphous and suspended sediment loads of the Blue Earth River, Minnesota. J. Soil Water
Conserv. 57, 243–250.
Simon, A., Bingner, R.L., Langendoen, E.J., Alonso, C.V., 2002. Actual and reference sediment
yields for the James Creek Watershed, Mississippi, Technical Report No. 31.
Simon, A., Hupp, C.R., 1986. Channel evolution in modified Tennessee channels. Proc. Fourth
Interag. Sediment. Conf. 2, 71–82.
Simon, A., Langendoen, E.J., Bingner, R.L., Wells, R.R., Yuan, Y., Alonso, C.V., 2004.
Suspended-sediment Transport and Bed-material Characteristics of Shades Creek, Alabama
and Ecoregion 67: Developing Water-quality Criteria for Suspended and Bed-material
Sediment, Technical Report No. 43.
Simon, A., Thomas, R.E., 2002. Processes and forms of an ustable alluvial stream with resistant
cohesive streambeds. Earth Surf. Process. Landforms 27.
Skaer, D.M., Cook, M.A., 2005. Soil Survey of Washington County, Missouri.
Spiekermann, R., Betts, H., Dymond, J., Basher, L., 2017. Volumetric measurement of river
bank erosion from sequential historical aerial photography. Geomorphology 296, 193–208.
https://doi.org/10.1016/j.geomorph.2017.08.047
St. Louis District Corps of Engineers, 1970. Sunnen Lake Dam Inspection Report, US Army
Engineer District. https://doi.org/10.1017/CBO9781107415324.004
StormTech, 2012. Porosity of Structural Backfill. Rocky Hill, CT.
Tetra Tech, I., 2018. USER ’ S GUIDE: Spreadsheet Tool for the Estimation of Pollutant Load
(STEPL) Version 4.4. Fairfax, VA.
Thoma, D.P., Gupta, S.C., Bauer, M.E., Kirchoff, C.E., 2005. Airborne laser scanning for
riverbank erosion assessment. Remote Sens. Environ. 95, 493–501. https://doi.org/. http://
dx.doi.org/10.1016/j.rse.2005.01.012
112
Trimble, S.W., 2009. Geomorphology Fluvial processes , morphology and sediment budgets in
the Coon Creek Basin , WI ,. Geomorphology 108, 8–23.
https://doi.org/10.1016/j.geomorph.2006.11.015
Trimble, S.W., 1999. Decreased Rates of Alluvial Sediment Storage in the Coon Creek Basin,
Wisconsin, 1975-93. Am. Assoc. Adv. Sci. 285, 1244–1246.
https://doi.org/10.1126/science.285.5431.1244
Trimble, S.W., 1983. A sediment budget for Coon Creek Basin in the Driftless Area, Wisconsin.
Am. J. Sci. 283, 454–474.
Trimble, S.W., Lund, S.W., 1982. Soil Conservation and the Reduction of Erosion and
Sedimentation in the Coon Creek Basin, Wisconsin. Geol. Surv. Prof. Pap. 1234.
Troeh, F.R., Hobb, J.A., Donahue, R.L., 2004. Soil and Water Conservation for Productivity and
Environmental Protection, Fourth Edi. ed. Pearson Education Inc., Upper Saddle River,
New Jersey.
Turner, R.E., Rabalais, N.N., 2004. Suspended sediment, C, N, P, and Si yields from the
Mississippi River Basin. Hydrobologia 511, 79–89.
US Census Bureau, 2017. American Community Survey 5-Year Estimates: Potosi [WWW
Document]. US Census Bur. Am. FactFinder. URL
https://factfinder.census.gov/faces/nav/jsf/pages/searchresults.xhtml?refresh=t (accessed
10.18.18).
USACE, 1983. Sacramento River and Tributaries Bank Protection and Erosion Control
Investigation, California Sediment Transport Studies. Sacramento, CA.
USDA-NASS, 2018. CropScape and Cropland Data Layer [WWW Document]. URL
https://www.nass.usda.gov/Research_and_Science/Cropland/SARS1a.php (accessed
10.9.18).
USDA-NRCS, 2017. Web Soil Survey [WWW Document]. URL
https://websoilsurvey.sc.egov.usda.gov/App/WebSoilSurvey.aspx (accessed 10.26.18).
USDA-NRCS, 2006. Land Resource Regions and Major Land Resource Areas of the United
States, the Caribbean, and the Pacific Basin.
USDA, 2017. 2017 Census of Agriculture: County Profile. Washington County, Missouri.
USEPA, 2019. Spreadsheet Tool for Estimating Pollutant Loads (STEPL) [WWW Document].
Polluted Runoff Nonpoint Source Pollut. URL https://www.epa.gov/nps/spreadsheet-tool-
estimating-pollutant-loads-stepl#doc (accessed 1.31.19).
USEPA, 2018a. Land Reclamation Activities Improve Water Quality in the Upper. Missouri.
113
USEPA, 2018b. Basic Information about Nonpoint Source (NPS) Pollution [WWW Document].
United States Environ. Prot. Agency. URL https://www.epa.gov/nps/basic-information-
about-nonpoint-source-nps-pollution (accessed 11.7.18).
USGS, 2018a. National Hydrology Dataset [WWW Document]. URL https://nhd.usgs.gov
(accessed 9.6.18).
USGS, 2018b. USGS Current Water Data for Missouri [WWW Document]. URL
https://waterdata.usgs.gov/mo/nwis/rt (accessed 9.19.18).
Walter, R.C., Merritts, D.J., 2008. Natural streams and the legacy of water-powered mills.
Science (80-. ). 219, 299–304.
Ward, A.D., Elliot, W.J., 1995. Environmental Hydrology. Lewis Publishers, Inc, Boca Raton.
Ward, A.D., Trimble, S.W., Burckhard, S.R., Lyon, J.G., 2016. Environmental Hydrology, Third
Edit. ed. CRC Press, Taylor and Francis Group, Boca Raton.
WiDNR, 2014. The Spreadsheet Tool for Estimating Pollutant Loads (STEPL).
Wilkinson, B.H., McElroy B.J, 2007. The impact of humans on continental erosion and
sedimentation. Geol. Soc. Am. Bull. 119, 140–156.
Xia, J., Li, T., Li, X., Zhang, X., Zong, Q., 2014. Daily bank erosion rates in the lower yellow
river before and after dam construction. J. Am. Water Resour. Assoc. 50, 1325–1337.
https://doi.org/10.1111/jawr.12192
Zaimes, G.N., Schultz, R.C., 2015. Riparian land-use impacts on bank erosion and deposition of
an incised stream in north-central Iowa, USA. Catena 125.
https://doi.org/10.1016/j.catena.2014.09.013
114
APPENDICES
Appendix A. Drainage area and discharge relationships for 32 USGS gaging stations near
the study watershed.
Appendix A-1. Mean and max discharge and drainage area relationships for USGS gaging
stations near the study watershed.
115
Ap
pen
dix
A-2
. U
SG
S g
agin
g s
tati
on
s n
ear
the
wat
ersh
ed.
US
GS
Yea
rs o
f
Gag
e ID
Sta
tion
Nam
eS
trea
mS
tart
Yea
rR
eco
rdA
d (
km
2)
Ele
vatio
n (m
)90%
50%
10%
Max
Mea
n
06935755
Bo
nho
mm
e C
reek
nea
r E
llisv
ille,
MO
Bo
nho
mm
e C
reek
1997
21
11.4
996
173.3
0.0
00.0
20.1
316.8
20.1
0
07010090
Mac
Ken
zie
Cre
ek n
ear
Shr
ewsb
ury,
MO
Mac
Ken
zie
Cre
ek1997
21
9.0
391
129.4
0.0
00.0
20.1
95.6
60.1
0
07010094
Gra
mm
ond
Cre
ek n
ear
Wilb
ur P
ark
, M
OG
ram
mo
nd C
reek
1997
21
1.6
058
133.5
0.0
00.0
10.0
40.7
60.0
2
07010097
Riv
er D
es P
eres
at S
t. L
oui
s, M
OR
iver
Des
Per
es2002
16
220.6
68
119.0
0.0
50.2
03.6
0274.7
02.1
6
07010180
Gra
vois
Cre
ek n
ear
Meh
lvill
e, M
OG
ravo
is C
reek
1996
22
46.8
79
128.7
0.0
30.1
21.0
647.0
10.6
3
07010208
Mar
tigne
y C
reek
nea
r A
rno
ld,
MO
Mar
tigne
y C
reek
1997
21
6.8
376
124.2
0.0
10.0
30.1
76.0
30.1
0
07010350
Mer
amec
Riv
er a
t C
oo
k S
tatio
n, M
OM
eram
ec R
iver
1965
53
515.4
1263.6
0.4
81.1
96.5
7467.2
83.6
8
07013000
Mer
amec
Riv
er n
ear
Ste
elvi
lle,
MO
Mer
amec
Riv
er1922
96
2022.7
9207.8
3.7
97.6
531.1
51353.7
017.0
5
07014000
Huz
zah
Cre
ek n
ear
Ste
elvi
lle,
MO
Huz
zah
Cre
ek2007
11
670.8
1202.7
1.5
43.1
714.1
6597.5
57.8
7
07014500
Mer
amec
Riv
er n
ear
Sul
livan
, M
OM
eram
ec R
iver
1921
97
3820.2
5177.3
7.5
617.2
268.2
52350.5
635.6
5
07016500
Bo
urb
euse
Riv
er a
t U
nio
n, M
OB
our
beu
se R
iver
1921
97
2092.7
2148.9
1.1
94.9
637.9
51784.1
619.5
0
07017200
Big
Riv
er a
t Ir
ond
ale,
MO
Big
Riv
er1965
53
453.2
5229.6
0.2
81.5
510.3
9603.2
25.4
1
07017610
Big
Riv
er b
elo
w B
onn
e T
erre
, M
OB
ig R
iver
2011
71059.3
1191.4
1.3
23.8
222.6
81011.0
213.0
8
07018100
Big
Riv
er n
ear
Ric
hwo
ods,
MO
Big
Riv
er1949
69
1903.6
5159.4
2.9
28.1
637.6
71517.9
520.5
3
07018500
Big
Riv
er a
t B
yrne
svill
e, M
OB
ig R
iver
1922
96
2375.0
3132.2
3.3
79.6
048.1
41687.8
724.7
5
07019000
Mer
amec
Riv
er n
ear
Eur
eka,
MO
Mer
amec
Riv
er1903
115
9810.9
2123.2
15.2
640.5
0195.4
64502.8
893.7
8
07019072
Kie
fer
Cre
ek n
ear
Bal
lwin
, M
OK
iefe
r C
reek
1996
22
10.1
269
133.8
0.0
30.0
70.3
18.5
50.1
6
07019090
Will
iam
s C
reek
nea
r P
eerles
s P
ark
, M
OW
illia
ms
Cre
ek1997
21
19.7
358
126.6
0.0
20.0
70.3
813.4
50.1
8
07019120
Fis
hpo
t C
reek
at V
alle
y P
ark
, M
OF
ishp
ot C
reek
1996
22
24.8
122
128.6
0.0
00.0
00.1
523.1
40.1
9
07019150
Gra
nd G
laiz
e C
reek
nea
r M
anch
este
r, M
OG
rand
Gla
ize
Cre
ek1997
21
13.1
831
137.8
0.0
00.0
20.2
719.2
60.1
5
07019175
Sug
ar C
reek
at K
irk
wo
od,
MO
Sug
ar C
reek
1997
21
13.1
572
128.3
0.0
10.0
30.2
227.4
40.1
8
07019185
Gra
nd G
laiz
e C
reek
nea
r V
alle
y P
ark
, M
OG
rand
Gla
ize
Cre
ek1997
21
56.4
62
127.1
0.0
40.1
51.0
755.2
20.6
8
07019195
Yar
nell
Cre
ek a
t F
ento
n, M
OY
arne
ll C
reek
1997
21
7.0
189
123.3
0.0
10.0
20.1
613.9
10.1
0
07019220
Fen
ton
Cre
ek n
ear
Fen
ton,
MO
Fen
ton
Cre
ek1997
21
11.1
111
126.8
0.0
10.0
30.2
720.2
50.1
8
07019317
Mat
tese
Cre
ek n
ear
Mat
tese
, M
OM
atte
se C
reek
1996
22
20.4
092
128.6
0.0
00.0
40.4
820.4
80.2
8
07035000
Litt
le S
t. F
ranc
is R
iver
at F
red
eric
kto
wn,
MO
Litt
le S
t. F
ranc
is R
iver
1939
79
234.3
95
206.8
0.0
80.9
37.0
0390.8
23.4
4
07035800
St. F
ranc
is R
iver
nea
r M
ill C
reek
, M
OS
t. F
ranc
is R
iver
1987
31
1307.9
5169.6
0.4
24.9
032.5
72039.0
416.7
2
07036100
St. F
ranc
is R
iver
nea
r S
aco
, M
OS
t. F
ranc
is R
iver
1983
35
1719.7
6143.9
0.8
87.2
851.8
32509.1
525.9
1
07061270
Eas
t F
ork
Bla
ck R
iver
nea
r L
este
rvill
e, M
OE
ast F
ork
Bla
ck R
iver
2001
17
135.1
98
251.5
0.1
10.5
73.7
9197.1
12.2
5
07061290
Eas
t F
ork
Bla
ck R
iver
bel
ow
Lo
wer
Tau
m S
auk
Res
ervo
ir,
MO
Eas
t F
ork
Bla
ck R
iver
2008
10
226.1
07
221.0
0.1
61.0
17.8
4254.0
33.7
3
07061500
Bla
ck R
iver
nea
r A
nnap
olis
, M
OB
lack
Riv
er1939
79
1253.5
6173.7
3.4
87.9
332.5
71622.7
417.1
7
07061600
Bla
ck R
iver
bel
ow
Ann
apo
lis,
MO
Bla
ck R
iver
2006
12
1276.8
7169.3
4.8
19.4
937.1
01690.7
021.0
3
Flo
w E
xcee
den
ce (
m3/s
)
116
Appendix B. Field assessments.
Location Major Stream Date Site # Easting Northing Watershed Order Assessed
1 697,486.96 4,218,825.81 Mineral Fork 5 6/20/2019 2 694,756.23 4,218,145.52 Mineral Fork 2 12/17/2018 3 693,524.85 4,217,365.72 Mineral Fork 3 12/17/2018 4 689,491.40 4,212,240.43 Mineral Fork 5 12/17/2018 5 698,326.50 4,216,875.00 Mineral Fork 1 6/20/2019 6 698,326.50 4,216,701.39 Mineral Fork 3 6/20/2019
7.1 696,905.74 4,211,905.84 Mineral Fork 3 6/20/2019 7.2 696,903.51 4,211,838.80 Mineral Fork 1 6/20/2019 8 696,655.55 4,209,189.72 Mineral Fork 2 6/20/2019 9 686,393.90 4,211,894.93 Mineral Fork 2 6/20/2019 10 683,497.01 4,210,422.94 Mineral Fork 1 6/20/2019 11 682,491.74 4,204,138.61 Mineral Fork 4 6/20/2019 12 685,772.92 4,198,062.38 Mineral Fork 3 6/20/2019 13 692,734.66 4,201,718.25 Mineral Fork 3 6/20/2019 14 692,287.55 4,210,532.79 Mineral Fork 2 11/6/2019 15 686,339.11 4,209,358.10 Mineral Fork 4 11/6/2019 16 688,132.67 4,207,244.61 Mineral Fork 2 11/6/2019 17 688,948.30 4,206,544.35 Mineral Fork 3 11/6/2019 18 693,665.41 4,201,932.80 Mineral Fork 2 11/6/2019 19 681,870.98 4,203,061.68 Mineral Fork 2 11/6/2019
20.1 682,993.53 4,198,052.15 Mineral Fork 2 11/6/2019 20.2 683,009.91 4,198,032.45 Mineral Fork 2 11/6/2019
1 705,661.09 4,210,520.83 Mill Creek 3 6/20/2019 2 706,207.39 4,210,219.38 Mill Creek 3 12/17/2018 3 705,337.67 4,207,763.60 Mill Creek 3 12/17/2018 4 705,031.98 4,206,075.55 Mill Creek 3 12/17/2018 5 699,590.48 4,205,176.99 Mill Creek 2 6/20/2019 6 703,742.55 4,203,250.33 Mill Creek 2 6/20/2019 7 699,928.02 4,202,673.17 Mill Creek 1 6/20/2019 8 700,191.36 4,202,047.74 Mill Creek 3 6/20/2019
117
Appendix B. Field assessments (Continued).
Major Bank Height (m) Coarse Unit Thickness
(CUT) (m) CUT (%
of bank Channel
Width Water
depth Site # Watershed Field LiDAR Upper Unit Lower Unit Height) (m) (m)
1 Mineral Fork 2.9 2.75 0.6 2.3 79 33 0.4 2 Mineral Fork 1.2 1.5 0.4 0.8 67 10 0.3 3 Mineral Fork 1.3 1.3 1 0.3 23 8 0.4 4 Mineral Fork 1.3 1.3 0.8 0.5 38 23 0.15 5 Mineral Fork 1.2 0.9 0.75 0.5 38 8 0.2 6 Mineral Fork 0.8 0.85 0.4 0.4 50 14 0.1
7.1 Mineral Fork 2.6 2.75 1.1 1.5 58 7 0.08 7.2 Mineral Fork 1.1 0.8 0.3 0.8 73 6 0.1 8 Mineral Fork 1.6 1.5 0.5 1.1 69 6 0.07 9 Mineral Fork 2.5 2.25 0.7 1.1 44 14 0.1 10 Mineral Fork 1.1 0.95 0.2 0.9 82 5 0.1 11 Mineral Fork 1.4 1.2 0.3 1.1 79 25 0.3 12 Mineral Fork 2 1.5 0.7 1.3 65 10 0.3 13 Mineral Fork 1.3 1.3 0.7 0.6 46 13 0.4 14 Mineral Fork 0.9 0.9 0.2 0.7 78 8.1 0.1 15 Mineral Fork 1.8 1.75 0.2 1.1 61 18.5 0.4 16 Mineral Fork 1.2 1 0.2 0.7 58 4.2 0.35 17 Mineral Fork 0.85 0.9 0.4 0.5 53 13.7 0.25 18 Mineral Fork 0.6 0.8 0.2 0.4 67 7.2 0.3 19 Mineral Fork 1 0.95 0.55 0.5 45 6.6 dry
20.1 Mineral Fork 1.5 1.3 0.2 0.6 40 10.7 0.4 20.2 Mineral Fork 1.9 1.5 1 0.9 47 10.7 0.4
1 Mill Creek 1.4 1.5 0.9 0.5 35.7 11 0.04 2 Mill Creek 2.9 2.75 2.3 0.4 13.8 9 0.22 3 Mill Creek 1.45 1.45 1.0 0.5 31.0 7 0.25 4 Mill Creek 2.1 1.6 0.4 1.7 81.0 22 0.5 5 Mill Creek 1.5 1.4 0.3 1.2 80.0 5 0.3 6 Mill Creek 0.8 0.8 0.5 0.3 34.3 4 0.1 7 Mill Creek 1.4 1.3 0.9 0.5 34.5 8 0.1 8 Mill Creek 0.9 1 0.2 0.7 77.8 6 0.3
118
Appendix B. Field assessments (Continued).
Major Stream Soil Characteristics (NRCS) Site # Watershed Order Series Texture-Upper Slope (%) Flood Frequency
1 Mineral Fork 5 Haymond silt loam 0-3 Frequently 2 Mineral Fork 2 Cedargap gravelly silt loam 0-2 Frequently 3 Mineral Fork 3 Cedargap gravelly silt loam 0-2 Frequently 4 Mineral Fork 5 Cedargap gravelly silt loam 0-2 Frequently 5 Mineral Fork 1 Cedargap gravelly silt loam 0-2 Frequently 6 Mineral Fork 3 Cedargap gravelly silt loam 0-2 Frequently
7.1 Mineral Fork 3 Cedargap gravelly silt loam 0-2 Frequently 7.2 Mineral Fork 1 Cedargap gravelly silt loam 0-2 Frequently 8 Mineral Fork 2 Cedargap gravelly silt loam 0-2 Frequently 9 Mineral Fork 2 Cedargap gravelly silt loam 1-3 Frequently 10 Mineral Fork 1 Cedargap gravelly silt loam 1-3 Frequently 11 Mineral Fork 4 Cedargap gravelly silt loam 0-2 Frequently 12 Mineral Fork 3 Cedargap gravelly silt loam 0-2 Frequently 13 Mineral Fork 3 Cedargap gravelly silt loam 0-2 Frequently 14 Mineral Fork 2 Cedargap gravelly silt loam 1-3 Frequently 15 Mineral Fork 4 Cedargap gravelly silt loam 0-2 Frequently 16 Mineral Fork 2 Cedargap gravelly silt loam 1-3 Frequently 17 Mineral Fork 3 Cedargap gravelly silt loam 0-2 Frequently 18 Mineral Fork 2 Cedargap gravelly silt loam 0-2 Frequently 19 Mineral Fork 2 Cedargap gravelly silt loam 0-2 Frequently
20.1 Mineral Fork 2 Cedargap gravelly silt loam 0-2 Frequently 20.2 Mineral Fork 2 Cedargap gravelly silt loam 0-2 Frequently
1 Mill Creek 3 Cedargap gravelly silt loam 0-2 Frequently 2 Mill Creek 3 Racket loam 0-3 Frequently 3 Mill Creek 3 Cedargap gravelly silt loam 0-2 Frequently 4 Mill Creek 3 Cedargap gravelly silt loam 0-2 Frequently 5 Mill Creek 2 Cedargap gravelly silt loam 1-3 Frequently 6 Mill Creek 2 Cedargap gravelly silt loam 1-3 Frequently 7 Mill Creek 1 Cedargap gravelly silt loam 1-3 Frequently 8 Mill Creek 3 Cedargap gravelly silt loam 0-2 Frequently
119
Appendix C. Sediment sample information.
Sample Lab Lab Sample Mass (Mg) Site # ID Name ID Watershed < 2mm to 250 µm Total % Fines
14 MF 14-1 KC 65 Mineral Fork 110 154 71.4 14 MF 14-2 KC 66 Mineral Fork 183 633 28.9 15 MF 15-1 KC 69 Mineral Fork 225 373 60.3 15 MF 15-2 KC 70 Mineral Fork 117 743 15.7 15 MF 15-3 KC 71 Mineral Fork 93 271 34.3 16 MF 16-1 KC 74 Mineral Fork 139 288 48.3 16 MF 16-2 KC 75 Mineral Fork 90 209 43.1 16 MF 16-3 KC 76 Mineral Fork 137 371 36.9 17 MF 17-1 KC 79 Mineral Fork 148 262 56.5 17 MF 17-2 KC 80 Mineral Fork 226 799 28.3 18 MF 18-1 KC 83 Mineral Fork 215 326 66.0 18 MF 18-2 KC 84 Mineral Fork 141 522 27.0 19 MF 19-1 KC 91 Mineral Fork 363 545 66.6 19 MF 19-2 KC 92 Mineral Fork 143 1,225 11.7 20 MF 20-1 KC 87 Mineral Fork 84 280 30.0 20 MF 20-2 KC 88 Mineral Fork 191 513 37.2
120
Appendix D. Cell location information in Mineral Fork.
Cell Stream Location 12-Digit HUC Cell
ID Order Easting Northing Watershed Land Use
66 6 694,922.58 4,217,711.55 Clear Creek-Mineral Fork Forest 69 6 694,752.87 4,217,254.00 Clear Creek-Mineral Fork Forest
73 6 694,478.82 4,216,899.30 Clear Creek-Mineral Fork Forest 77 6 694,091.88 4,216,761.71 Clear Creek-Mineral Fork Forest
81 6 693,688.40 4,216,619.50 Clear Creek-Mineral Fork Forest 85 6 693,425.75 4,216,236.31 Clear Creek-Mineral Fork Forest
89 6 693,176.31 4,215,827.90 Clear Creek-Mineral Fork Forest 94 6 692,794.38 4,215,677.15 Clear Creek-Mineral Fork Forest
98 6 692,497.63 4,215,356.56 Clear Creek-Mineral Fork Forest
102 6 692,421.56 4,214,902.78 Clear Creek-Mineral Fork Forest 106 6 692,393.09 4,214,435.52 Clear Creek-Mineral Fork Forest
111 6 692,059.81 4,214,225.10 Clear Creek-Mineral Fork Forest 116 6 691,744.89 4,214,509.87 Clear Creek-Mineral Fork Road Crossing
121 6 691,305.17 4,214,564.70 Clear Creek-Mineral Fork Forest 126 6 691,017.42 4,214,248.70 Clear Creek-Mineral Fork Forest
131 6 691,259.61 4,213,947.74 Clear Creek-Mineral Fork Forest 136 6 691,115.57 4,213,602.10 Clear Creek-Mineral Fork Forest
141 6 690,697.49 4,213,610.91 Clear Creek-Mineral Fork Forest 147 6 690,232.56 4,213,665.51 Clear Creek-Mineral Fork Forest
153 6 689,767.25 4,213,559.20 Clear Creek-Mineral Fork Forest 159 6 689,718.07 4,213,172.04 Clear Creek-Mineral Fork Forest
164 6 689,663.39 4,212,718.51 Clear Creek-Mineral Fork Forest 170 6 689,539.99 4,212,342.07 Clear Creek-Mineral Fork Road Crossing
174 6 689,226.84 4,212,326.56 Clear Creek-Mineral Fork Forest 181 6 688,491.69 4,212,046.29 Clear Creek-Mineral Fork Forest
185 6 688,712.93 4,211,763.74 Clear Creek-Mineral Fork Forest
188 6 688,853.08 4,211,436.65 Clear Creek-Mineral Fork Forest 191 6 688,465.50 4,211,368.50 Clear Creek-Mineral Fork Forest
177 6 688,819.94 4,212,339.58 Clear Creek-Mineral Fork Road Crossing 70 4 694,535.79 4,217,607.14 Clear Creek-Mineral Fork Forest
74 4 694,035.66 4,217,503.61 Clear Creek-Mineral Fork Forest 78 4 693,581.45 4,217,377.47 Clear Creek-Mineral Fork Road Crossing
82 4 693,148.75 4,217,384.08 Clear Creek-Mineral Fork Forest 86 4 692,667.53 4,217,510.40 Clear Creek-Mineral Fork Forest
90 4 692,208.08 4,217,761.83 Clear Creek-Mineral Fork Forest 95 4 691,855.12 4,218,022.31 Clear Creek-Mineral Fork Forest
99 4 691,467.32 4,218,268.13 Clear Creek-Mineral Fork Forest 103 4 691,035.72 4,218,426.74 Clear Creek-Mineral Fork Forest
162 3 687,060.52 4,219,254.77 Clear Creek-Mineral Fork Forest 107 3 690,912.47 4,218,846.02 Clear Creek-Mineral Fork Forest
112 3 690,743.93 4,219,296.43 Clear Creek-Mineral Fork Road Crossing
117 3 690,431.24 4,219,626.47 Clear Creek-Mineral Fork Forest 122 3 690,038.55 4,219,813.51 Clear Creek-Mineral Fork Forest
121
Appendix D. Cell location information in Mineral Fork (Continued).
Cell Stream Location 12-Digit HUC Cell
ID Order Easting Northing Watershed Land Use
127 3 689,650.22 4,220,012.88 Clear Creek-Mineral Fork Road Crossing 132 3 689,218.36 4,219,944.34 Clear Creek-Mineral Fork Forest
137 3 688,766.61 4,219,904.44 Clear Creek-Mineral Fork Forest 142 3 688,351.07 4,219,758.18 Clear Creek-Mineral Fork Forest
148 3 687,939.56 4,219,700.22 Clear Creek-Mineral Fork Forest 154 3 687,546.49 4,219,546.58 Clear Creek-Mineral Fork Forest
108 3 690,682.41 4,218,667.88 Clear Creek-Mineral Fork Forest 96 3 693,485.08 4,215,625.79 Clear Creek-Mineral Fork Forest
100 3 693,695.13 4,215,061.79 Clear Creek-Mineral Fork Forest
104 3 693,688.20 4,214,588.50 Clear Creek-Mineral Fork Forest 109 3 693,549.45 4,214,133.73 Clear Creek-Mineral Fork Forest
114 3 693,483.74 4,213,656.52 Clear Creek-Mineral Fork Forest 119 3 693,653.79 4,213,209.71 Clear Creek-Mineral Fork Forest
120 3 691,715.01 4,213,952.77 Clear Creek-Mineral Fork Forest 125 3 691,780.12 4,213,395.63 Clear Creek-Mineral Fork Forest
130 3 691,936.68 4,212,944.06 Clear Creek-Mineral Fork Forest 135 3 692,076.17 4,212,466.91 Clear Creek-Mineral Fork Forest
140 3 692,300.14 4,212,041.76 Clear Creek-Mineral Fork Forest 145 3 692,235.55 4,211,576.45 Clear Creek-Mineral Fork Road Crossing
151 3 692,288.60 4,211,122.85 Clear Creek-Mineral Fork Road Crossing 157 3 692,287.99 4,210,654.69 Clear Creek-Mineral Fork Road Crossing
161 3 692,319.39 4,210,178.04 Clear Creek-Mineral Fork Forest 166 3 692,512.85 4,209,758.40 Clear Creek-Mineral Fork Road Crossing
152 3 690,740.33 4,212,980.68 Clear Creek-Mineral Fork Forest 158 3 690,505.21 4,212,614.30 Clear Creek-Mineral Fork Forest
146 3 690,773.03 4,213,346.70 Clear Creek-Mineral Fork Forest
167 3 689,519.29 4,212,902.39 Clear Creek-Mineral Fork Forest 172 3 689,117.55 4,212,914.63 Clear Creek-Mineral Fork Road Crossing
175 3 688,696.56 4,213,128.79 Clear Creek-Mineral Fork Forest 178 3 688,394.48 4,213,404.61 Clear Creek-Mineral Fork Forest
194 5 688,152.01 4,211,095.02 Fourche a Renault Forest 199 5 687,745.64 4,210,931.76 Fourche a Renault Forest
204 5 687,331.54 4,210,789.08 Fourche a Renault Forest 210 5 687,045.24 4,210,431.95 Fourche a Renault Road Crossing
215 5 686,701.46 4,210,160.75 Fourche a Renault Road Crossing 220 5 686,668.88 4,209,710.98 Fourche a Renault Road Crossing
224 5 686,372.88 4,209,354.85 Fourche a Renault Road Crossing 229 5 686,111.18 4,209,007.30 Fourche a Renault Forest
234 5 685,984.55 4,208,568.48 Fourche a Renault Forest 239 5 685,680.58 4,208,236.55 Fourche a Renault Forest
249 5 684,900.88 4,207,780.83 Fourche a Renault Road Crossing
244 5 685,296.25 4,207,979.37 Fourche a Renault Road Crossing 254 5 684,793.57 4,207,433.46 Fourche a Renault Forest
122
Appendix D. Cell location information in Mineral Fork (Continued).
Cell Stream Location 12-Digit HUC Cell
ID Order Easting Northing Watershed Land Use
261 5 684,947.21 4,207,024.89 Fourche a Renault Forest 265 5 684,707.78 4,206,763.56 Fourche a Renault Road Crossing
269 5 684,344.68 4,206,553.10 Fourche a Renault Road Crossing 274 5 683,963.12 4,206,466.14 Fourche a Renault Forest
279 5 683,773.53 4,206,133.18 Fourche a Renault Road Crossing 284 5 684,062.47 4,205,901.90 Fourche a Renault Road Crossing
289 5 683,809.22 4,205,725.12 Fourche a Renault Forest 293 5 683,434.90 4,205,594.29 Fourche a Renault Road Crossing
296 5 683,257.72 4,205,194.01 Fourche a Renault Pasture
301 5 683,468.55 4,204,784.08 Fourche a Renault Pasture 306 5 683,301.58 4,204,423.43 Fourche a Renault Forest
311 5 682,876.96 4,204,551.56 Fourche a Renault Forest 316 5 682,531.25 4,204,317.30 Fourche a Renault Road Crossing
321 5 682,476.43 4,203,847.79 Fourche a Renault Pasture 326 5 682,229.61 4,203,458.19 Fourche a Renault Forest
330 5 682,071.78 4,203,042.73 Fourche a Renault Forest 335 5 681,864.51 4,202,652.09 Fourche a Renault Forest
196 4 687,983.62 4,211,239.64 Fourche a Renault Forest 201 4 687,572.52 4,211,284.95 Fourche a Renault Forest
207 4 687,143.58 4,211,155.18 Fourche a Renault Forest 213 4 686,734.73 4,210,980.89 Fourche a Renault Forest
218 4 686,280.00 4,211,073.91 Fourche a Renault Road Crossing 222 4 685,909.62 4,210,828.26 Fourche a Renault Forest
333 4 681,842.64 4,202,883.86 Fourche a Renault Road Crossing 338 4 681,532.68 4,202,795.49 Fourche a Renault Road Crossing
343 4 681,166.64 4,202,789.22 Fourche a Renault Forest
347 4 680,741.15 4,202,764.03 Fourche a Renault Pasture 352 4 680,290.20 4,202,692.31 Fourche a Renault Road Crossing
384 3 678,463.84 4,201,668.28 Fourche a Renault Forest 226 3 685,473.53 4,210,739.24 Fourche a Renault Road Crossing
231 3 685,030.07 4,210,604.05 Fourche a Renault Road Crossing 236 3 684,568.21 4,210,477.74 Fourche a Renault Road Crossing
358 3 679,876.96 4,202,457.12 Fourche a Renault Forest 365 3 679,481.13 4,202,344.33 Fourche a Renault Forest
371 3 679,103.80 4,202,154.54 Fourche a Renault Forest 377 3 678,791.00 4,201,869.22 Fourche a Renault Forest
206 3 687,200.68 4,211,468.74 Fourche a Renault Forest 212 3 686,802.20 4,211,600.62 Fourche a Renault Forest
217 3 686,409.03 4,211,873.43 Fourche a Renault Road Crossing 221 3 686,072.23 4,212,215.55 Fourche a Renault Forest
225 3 685,665.85 4,212,421.84 Fourche a Renault Road Crossing
230 3 685,233.46 4,212,507.23 Fourche a Renault Pasture 235 3 684,818.88 4,212,357.98 Fourche a Renault Pasture
123
Appendix D. Cell location information in Mineral Fork (Continued).
Cell Stream Location 12-Digit HUC Cell
ID Order Easting Northing Watershed Land Use
227 3 685,670.56 4,210,387.61 Fourche a Renault Forest 232 3 685,231.36 4,210,015.14 Fourche a Renault Road Crossing
237 3 684,899.48 4,209,685.61 Fourche a Renault Forest 242 3 684,549.09 4,209,354.11 Fourche a Renault Road Crossing
247 3 684,157.92 4,209,101.16 Fourche a Renault Road Crossing 257 3 685,105.40 4,207,401.48 Fourche a Renault Road Crossing
263 3 685,205.39 4,206,830.60 Fourche a Renault Road Crossing 267 3 685,026.20 4,206,416.68 Fourche a Renault Road Crossing
271 3 685,097.63 4,205,994.51 Fourche a Renault Forest
276 3 685,378.11 4,205,597.57 Fourche a Renault Forest 281 3 685,491.23 4,205,125.76 Fourche a Renault Road Crossing
286 3 685,500.80 4,204,651.43 Fourche a Renault Pasture 291 3 685,273.32 4,204,246.62 Fourche a Renault Pasture
294 3 685,056.99 4,203,857.95 Fourche a Renault Forest 297 3 685,081.08 4,203,428.43 Fourche a Renault Forest
303 3 685,217.85 4,203,014.92 Fourche a Renault Forest 334 3 681,743.13 4,203,126.93 Fourche a Renault Road Crossing
340 3 681,380.08 4,203,327.21 Fourche a Renault Forest 345 3 681,002.08 4,203,486.89 Fourche a Renault Forest
349 3 680,621.09 4,203,382.13 Fourche a Renault Forest 355 3 680,228.22 4,203,449.64 Fourche a Renault Pasture
361 3 679,784.53 4,203,468.26 Fourche a Renault Forest 368 3 679,339.07 4,203,422.01 Fourche a Renault Forest
374 3 678,967.30 4,203,564.22 Fourche a Renault Forest 380 3 678,562.82 4,203,537.24 Fourche a Renault Forest
387 3 678,123.94 4,203,478.68 Fourche a Renault Forest
394 3 677,710.69 4,203,474.83 Fourche a Renault Forest 350 3 680,437.67 4,202,506.73 Fourche a Renault Pasture
356 3 680,716.25 4,202,290.37 Fourche a Renault Forest 362 3 680,934.06 4,201,894.82 Fourche a Renault Forest
369 3 681,006.70 4,201,443.27 Fourche a Renault Forest 375 3 681,037.67 4,201,007.04 Fourche a Renault Forest
198 5 688,490.54 4,210,907.44 Mine a Breton Creek Forest 203 5 688,269.89 4,210,444.80 Mine a Breton Creek Forest
209 5 688,167.36 4,210,081.98 Mine a Breton Creek Forest 214 5 688,340.20 4,209,690.12 Mine a Breton Creek Forest
219 5 688,428.90 4,209,306.40 Mine a Breton Creek Forest 223 5 688,560.39 4,208,869.90 Mine a Breton Creek Forest
228 5 688,284.89 4,208,520.20 Mine a Breton Creek Road Crossing 233 5 688,277.72 4,208,241.11 Mine a Breton Creek Road Crossing
238 5 688,703.97 4,208,204.55 Mine a Breton Creek Forest
243 5 689,052.45 4,207,873.68 Mine a Breton Creek Forest 248 5 689,119.24 4,207,450.62 Mine a Breton Creek Forest
124
Appendix D. Cell location information in Mineral Fork (Continued).
Cell Stream Location 12-Digit HUC Cell
ID Order Easting Northing Watershed Land Use
253 4 689,407.57 4,207,259.36 Mine a Breton Creek Road Crossing 260 4 689,838.45 4,207,337.86 Mine a Breton Creek Forest
264 4 690,298.19 4,207,344.99 Mine a Breton Creek Forest 268 4 690,599.39 4,207,005.21 Mine a Breton Creek Forest
272 4 690,723.51 4,206,609.73 Mine a Breton Creek Forest 277 4 691,022.94 4,206,366.78 Mine a Breton Creek Forest
282 4 691,268.59 4,205,960.25 Mine a Breton Creek Forest 287 4 691,605.32 4,205,658.74 Mine a Breton Creek Forest
292 4 691,992.59 4,205,357.25 Mine a Breton Creek Forest
295 4 692,329.96 4,205,376.16 Mine a Breton Creek Forest 300 4 692,571.68 4,205,472.29 Mine a Breton Creek Forest
305 4 692,889.77 4,205,135.43 Mine a Breton Creek Forest 310 4 693,308.95 4,205,010.62 Mine a Breton Creek Road Crossing
315 4 693,395.51 4,204,560.02 Mine a Breton Creek Forest 320 4 693,365.64 4,204,074.28 Mine a Breton Creek Pasture
325 4 693,407.01 4,203,594.06 Mine a Breton Creek Forest 339 4 693,616.57 4,203,192.04 Mine a Breton Creek Forest
344 4 693,595.34 4,202,713.36 Mine a Breton Creek Forest 348 4 693,489.73 4,202,272.91 Mine a Breton Creek Road Crossing
256 4 689,149.06 4,206,860.17 Mine a Breton Creek Road Crossing 262 4 688,845.19 4,206,396.04 Mine a Breton Creek Road Crossing
266 4 688,681.13 4,205,934.68 Mine a Breton Creek Forest 270 4 688,523.31 4,205,492.79 Mine a Breton Creek Road Crossing
275 4 688,323.17 4,205,075.06 Mine a Breton Creek Pasture 280 4 688,262.80 4,204,600.37 Mine a Breton Creek Pasture
285 4 688,262.91 4,204,168.08 Mine a Breton Creek Road Crossing
354 4 693,109.22 4,202,190.99 Mine a Breton Creek Road Crossing 360 4 692,752.14 4,201,908.22 Mine a Breton Creek Road Crossing
367 4 692,577.08 4,201,507.43 Mine a Breton Creek Forest 373 4 692,215.68 4,201,199.83 Mine a Breton Creek Forest
379 4 691,863.78 4,200,927.34 Mine a Breton Creek Forest 386 4 691,508.02 4,200,682.32 Mine a Breton Creek Forest
353 3 693,669.93 4,201,903.95 Mine a Breton Creek Road Crossing 359 3 693,917.26 4,201,493.63 Mine a Breton Creek Road Crossing
366 3 694,175.65 4,201,108.91 Mine a Breton Creek Road Crossing 372 3 694,578.86 4,200,833.20 Mine a Breton Creek Road Crossing
378 3 694,974.99 4,200,546.29 Mine a Breton Creek Road Crossing 385 3 695,260.77 4,200,161.34 Mine a Breton Creek Road Crossing
392 3 695,505.41 4,199,774.57 Mine a Breton Creek Road Crossing 398 3 695,359.17 4,199,355.67 Mine a Breton Creek Road Crossing
404 3 695,155.74 4,198,920.00 Mine a Breton Creek Pasture
410 3 694,839.81 4,198,603.20 Mine a Breton Creek Road Crossing 290 3 687,989.73 4,203,815.64 Mine a Breton Creek Pasture
125
Appendix D. Cell location information in Mineral Fork (Continued).
Cell Stream Location 12-Digit HUC Cell
ID Order Easting Northing Watershed Land Use
393 3 691,335.18 4,200,277.46 Mine a Breton Creek Forest 399 3 691,194.47 4,199,861.88 Mine a Breton Creek Forest
405 3 690,993.26 4,199,431.43 Mine a Breton Creek Forest 411 3 690,984.36 4,198,973.75 Mine a Breton Creek Forest
417 3 691,195.10 4,198,566.45 Mine a Breton Creek Road Crossing 423 3 691,278.45 4,198,130.60 Mine a Breton Creek Forest
429 3 691,292.85 4,197,720.35 Mine a Breton Creek Road Crossing 434 3 691,498.51 4,197,328.35 Mine a Breton Creek Forest
439 3 691,461.84 4,196,891.28 Mine a Breton Creek Road Crossing
391 3 691,185.62 4,200,637.60 Mine a Breton Creek Forest 397 3 690,923.60 4,200,310.98 Mine a Breton Creek Forest
445 3 691,718.10 4,196,593.06 Mine a Breton Creek Road Crossing 451 3 691,889.56 4,196,251.06 Mine a Breton Creek Forest
457 3 692,103.99 4,195,889.32 Mine a Breton Creek Forest 462 3 692,297.85 4,195,505.68 Mine a Breton Creek Forest
466 3 692,335.20 4,195,047.68 Mine a Breton Creek Forest 470 3 692,233.84 4,194,618.28 Mine a Breton Creek Forest
1 6 703,227.27 4,219,464.35 Mineral Fork Forest 2 6 703,073.82 4,219,020.11 Mineral Fork Forest
3 6 702,721.92 4,219,013.83 Mineral Fork Forest 4 6 702,271.25 4,219,387.11 Mineral Fork Forest
5 6 701,810.44 4,219,463.65 Mineral Fork Forest 6 6 701,529.44 4,219,094.38 Mineral Fork Forest
7 6 701,098.16 4,218,992.83 Mineral Fork Forest 8 6 700,681.67 4,218,866.69 Mineral Fork Forest
9 6 700,443.29 4,218,552.06 Mineral Fork Forest
10 6 700,002.19 4,218,425.64 Mineral Fork Forest 11 6 699,587.71 4,218,414.68 Mineral Fork Forest
13 6 699,302.52 4,218,639.09 Mineral Fork Forest 16 6 699,066.48 4,218,825.25 Mineral Fork Forest
19 6 698,692.44 4,219,024.76 Mineral Fork Forest 22 6 698,222.00 4,219,135.33 Mineral Fork Forest
25 6 697,839.36 4,218,958.41 Mineral Fork Forest 29 6 697,475.89 4,218,784.08 Mineral Fork Road Crossing
33 6 697,428.46 4,218,336.16 Mineral Fork Road Crossing 38 6 697,128.17 4,218,033.40 Mineral Fork Forest
43 6 696,749.54 4,218,184.28 Mineral Fork Forest 48 6 696,652.67 4,218,494.33 Mineral Fork Forest
52 6 696,403.87 4,218,887.13 Mineral Fork Forest 55 6 696,052.32 4,218,873.81 Mineral Fork Forest
58 6 695,918.20 4,218,503.50 Mineral Fork Forest
61 6 695,517.76 4,218,286.53 Mineral Fork Forest 64 6 695,097.50 4,218,134.30 Mineral Fork Forest
126
Appendix D. Cell location information in Mineral Fork (Continued).
Cell Stream Location 12-Digit HUC Cell
ID Order Easting Northing Watershed Land Use
91 3 693,248.14 4,220,424.70 Mineral Fork Forest 12 3 699,691.44 4,218,084.67 Mineral Fork Forest
14 3 699,824.49 4,217,638.59 Mineral Fork Forest 17 3 700,077.06 4,217,245.02 Mineral Fork Forest
20 3 700,354.29 4,216,859.50 Mineral Fork Road Crossing 23 3 700,518.09 4,216,415.83 Mineral Fork Forest
26 3 700,790.53 4,216,030.88 Mineral Fork Forest 67 3 694,800.29 4,218,170.93 Mineral Fork Road Crossing
71 3 694,482.09 4,218,405.82 Mineral Fork Forest
75 3 694,242.94 4,218,795.23 Mineral Fork Forest 79 3 694,056.81 4,219,227.18 Mineral Fork Forest
83 3 693,817.16 4,219,653.63 Mineral Fork Forest 87 3 693,574.71 4,220,081.70 Mineral Fork Forest
93 3 692,838.11 4,220,544.81 Mineral Fork Forest 15 4 699,291.49 4,218,205.02 Old Mines Creek Forest
18 4 699,023.56 4,217,805.36 Old Mines Creek Forest 21 4 698,758.50 4,217,445.08 Old Mines Creek Forest
24 4 698,497.48 4,217,025.33 Old Mines Creek Forest 27 4 698,244.77 4,216,606.11 Old Mines Creek Road Crossing
35 4 697,681.25 4,215,835.76 Old Mines Creek Road Crossing 31 4 697,970.85 4,216,199.65 Old Mines Creek Road Crossing
40 4 697,458.59 4,215,448.38 Old Mines Creek Forest 45 4 697,139.10 4,215,111.71 Old Mines Creek Forest
50 4 696,793.46 4,214,776.64 Old Mines Creek Forest 53 4 696,662.42 4,214,318.60 Old Mines Creek Forest
56 4 696,741.96 4,213,838.39 Old Mines Creek Forest
59 4 696,796.70 4,213,366.31 Old Mines Creek Forest 63 4 696,752.40 4,212,885.57 Old Mines Creek Road Crossing
65 4 696,782.99 4,212,425.36 Old Mines Creek Road Crossing 68 4 696,869.58 4,211,982.22 Old Mines Creek Road Crossing
72 4 697,041.08 4,211,560.90 Old Mines Creek Road Crossing 76 4 697,127.13 4,211,083.49 Old Mines Creek Road Crossing
80 4 697,126.59 4,210,594.02 Old Mines Creek Forest 84 4 697,052.22 4,210,116.55 Old Mines Creek Road Crossing
88 4 696,976.87 4,209,630.49 Old Mines Creek Road Crossing 92 4 696,739.01 4,209,220.41 Old Mines Creek Road Crossing
97 3 696,512.69 4,208,813.29 Old Mines Creek Road Crossing 364 5 682,369.64 4,201,511.46 Sunnen Lake-Fourche a Renault Dam/Pond
370 5 683,100.48 4,200,398.82 Sunnen Lake-Fourche a Renault Road Crossing 376 5 683,085.04 4,199,956.51 Sunnen Lake-Fourche a Renault Forest
383 4 683,137.64 4,199,532.25 Sunnen Lake-Fourche a Renault Road Crossing
390 4 683,332.21 4,199,132.74 Sunnen Lake-Fourche a Renault Forest 396 4 683,628.30 4,198,902.23 Sunnen Lake-Fourche a Renault Forest
127
Appendix D. Cell location information in Mineral Fork (Continued).
Cell Stream Location 12-Digit HUC Cell
ID Order Easting Northing Watershed Land Use
402 4 683,977.52 4,198,770.07 Sunnen Lake-Fourche a Renault Pasture 408 4 684,315.86 4,198,524.13 Sunnen Lake-Fourche a Renault Road Crossing
414 4 684,682.49 4,198,350.35 Sunnen Lake-Fourche a Renault Road Crossing 420 4 685,081.33 4,198,284.46 Sunnen Lake-Fourche a Renault Pasture
426 4 685,500.41 4,198,189.81 Sunnen Lake-Fourche a Renault Road Crossing 381 4 682,923.22 4,199,707.72 Sunnen Lake-Fourche a Renault Forest
388 4 682,756.71 4,199,303.42 Sunnen Lake-Fourche a Renault Road Crossing 395 4 682,709.86 4,198,866.38 Sunnen Lake-Fourche a Renault Pasture
431 4 685,827.73 4,198,012.72 Sunnen Lake-Fourche a Renault Road Crossing
436 4 686,043.41 4,197,735.57 Sunnen Lake-Fourche a Renault Pasture 441 4 686,176.65 4,197,362.96 Sunnen Lake-Fourche a Renault Road Crossing
448 4 686,205.36 4,196,934.04 Sunnen Lake-Fourche a Renault Forest 454 4 686,208.10 4,196,534.41 Sunnen Lake-Fourche a Renault Forest
460 4 686,151.84 4,196,113.43 Sunnen Lake-Fourche a Renault Pasture 464 4 686,205.78 4,195,694.49 Sunnen Lake-Fourche a Renault Pasture
468 4 686,428.43 4,195,338.83 Sunnen Lake-Fourche a Renault Pasture 471 4 686,616.23 4,194,959.50 Sunnen Lake-Fourche a Renault Road Crossing
474 4 686,635.35 4,194,544.83 Sunnen Lake-Fourche a Renault Road Crossing 401 3 682,852.95 4,198,459.68 Sunnen Lake-Fourche a Renault Road Crossing
407 3 683,024.57 4,198,088.95 Sunnen Lake-Fourche a Renault Road Crossing 413 3 683,132.68 4,197,737.61 Sunnen Lake-Fourche a Renault Forest
419 3 683,030.32 4,197,322.09 Sunnen Lake-Fourche a Renault Forest 425 3 683,052.11 4,196,891.96 Sunnen Lake-Fourche a Renault Forest
430 3 683,126.65 4,196,446.13 Sunnen Lake-Fourche a Renault Road Crossing 435 3 683,200.82 4,196,027.51 Sunnen Lake-Fourche a Renault Road Crossing
440 3 683,347.14 4,195,592.59 Sunnen Lake-Fourche a Renault Forest
447 3 683,713.39 4,195,331.98 Sunnen Lake-Fourche a Renault Forest 477 3 686,805.01 4,194,112.41 Sunnen Lake-Fourche a Renault Forest
480 3 687,027.86 4,193,730.42 Sunnen Lake-Fourche a Renault Forest 432 3 685,949.86 4,198,201.53 Sunnen Lake-Fourche a Renault Road Crossing
437 3 686,340.28 4,198,297.23 Sunnen Lake-Fourche a Renault Road Crossing 442 3 686,739.60 4,198,377.28 Sunnen Lake-Fourche a Renault Road Crossing
449 3 687,147.91 4,198,303.94 Sunnen Lake-Fourche a Renault Forest 455 3 687,474.76 4,198,043.29 Sunnen Lake-Fourche a Renault Forest
461 3 687,768.96 4,197,814.48 Sunnen Lake-Fourche a Renault Road Crossing 465 3 687,996.60 4,197,523.19 Sunnen Lake-Fourche a Renault Forest
469 3 688,083.38 4,197,107.14 Sunnen Lake-Fourche a Renault Forest 472 3 688,089.18 4,196,702.83 Sunnen Lake-Fourche a Renault Forest
475 3 688,194.91 4,196,368.18 Sunnen Lake-Fourche a Renault Dam/Pond 478 3 688,415.49 4,195,986.49 Sunnen Lake-Fourche a Renault Road Crossing
481 3 688,605.60 4,195,624.03 Sunnen Lake-Fourche a Renault Pasture
483 3 688,712.67 4,195,255.80 Sunnen Lake-Fourche a Renault Forest 485 3 688,966.97 4,194,910.29 Sunnen Lake-Fourche a Renault Forest
128
Appendix E. Cell location information in Mill Creek.
Cell Stream Location 12-Digit HUC Cell ID Order Easting Northing Watershed Land Use 1 5 708,792.15 4,212,394.39 Mill Creek Forest 2 5 708,470.21 4,212,151.70 Mill Creek Forest 3 5 708,076.71 4,211,976.26 Mill Creek Forest 4 5 707,767.00 4,211,672.92 Mill Creek Forest 5 5 707,547.55 4,211,275.29 Mill Creek Forest 6 5 707,426.78 4,210,872.91 Mill Creek Forest 7 5 707,008.85 4,210,716.32 Mill Creek Forest 8 5 706,643.30 4,211,145.77 Mill Creek Forest 9 5 706,274.94 4,211,069.78 Mill Creek Forest 10 5 706,326.97 4,210,645.06 Mill Creek Forest 85 4 700,147.10 4,201,977.28 Mill Creek Road Crossing 11 4 706,242.52 4,210,160.37 Mill Creek Road Crossing 13 4 706,020.20 4,209,739.00 Mill Creek Forest 15 4 705,605.64 4,209,745.17 Mill Creek Forest 17 4 705,268.78 4,210,032.35 Mill Creek Forest 19 4 704,926.66 4,210,185.38 Mill Creek Forest 21 4 705,099.00 4,209,899.72 Mill Creek Forest 23 4 705,021.99 4,209,517.73 Mill Creek Forest 25 4 704,702.48 4,209,169.36 Mill Creek Forest 27 4 704,650.25 4,208,773.04 Mill Creek Forest 29 4 705,055.63 4,208,602.03 Mill Creek Forest 32 4 705,495.41 4,208,576.48 Mill Creek Forest 35 4 705,378.09 4,208,232.86 Mill Creek Forest 38 4 705,260.05 4,207,830.20 Mill Creek Road Crossing 41 4 705,636.71 4,207,660.03 Mill Creek Forest 43 4 705,858.07 4,207,275.24 Mill Creek Forest 44 4 705,748.02 4,206,860.03 Mill Creek Forest 45 4 705,573.17 4,206,443.24 Mill Creek Forest 46 4 705,408.37 4,206,095.92 Mill Creek Forest 47 4 704,970.34 4,206,073.51 Mill Creek Road Crossing 48 4 704,535.49 4,206,110.44 Mill Creek Forest 50 4 704,076.22 4,205,986.96 Mill Creek Forest 52 4 703,601.44 4,205,899.83 Mill Creek Forest 54 4 703,123.63 4,205,938.89 Mill Creek Forest 56 4 702,701.47 4,205,808.13 Mill Creek Forest 58 4 702,444.56 4,205,502.47 Mill Creek Forest 61 4 702,002.30 4,205,388.74 Mill Creek Forest 64 4 701,579.02 4,205,236.17 Mill Creek Forest 67 4 701,318.62 4,204,880.27 Mill Creek Road Crossing 70 4 701,036.34 4,204,484.59 Mill Creek Forest 73 4 700,757.29 4,204,090.92 Mill Creek Forest 76 4 700,427.76 4,203,745.40 Mill Creek Forest 80 4 700,220.59 4,203,302.41 Mill Creek Forest
129
Appendix E. Cell location information in Mill Creek (Continued).
Cell Stream Location 12-Digit HUC Cell ID Order Easting Northing Watershed Land Use
82 4 700,258.40 4,202,833.73 Mill Creek Forest
83 4 700,229.28 4,202,412.88 Mill Creek Forest 12 4 706,026.38 4,210,380.73 Mill Creek Road Crossing 14 4 705,692.25 4,210,430.76 Mill Creek Road Crossing 16 4 705,483.53 4,210,820.43 Mill Creek Road Crossing 18 4 705,087.70 4,210,693.38 Mill Creek Forest 20 4 704,701.02 4,210,511.85 Mill Creek Road Crossing 22 4 704,268.47 4,210,522.95 Mill Creek Road Crossing 24 4 703,912.92 4,210,197.82 Mill Creek Forest
89 4 699,807.25 4,201,676.31 Mill Creek Forest 88 3 698,347.43 4,204,243.03 Mill Creek Road Crossing
101 3 698,087.77 4,199,194.03 Mill Creek Road Crossing 26 3 703,571.58 4,209,929.94 Mill Creek Forest 31 3 704,567.06 4,208,421.51 Mill Creek Forest 34 3 704,241.92 4,208,159.82 Mill Creek Forest 37 3 703,899.65 4,207,849.34 Mill Creek Road Crossing 60 3 702,330.60 4,205,781.34 Mill Creek Forest 63 3 701,955.01 4,205,847.45 Mill Creek Forest
66 3 701,563.25 4,205,993.52 Mill Creek Road Crossing 69 3 701,142.64 4,205,863.00 Mill Creek Forest 72 3 700,694.01 4,205,688.32 Mill Creek Forest 75 3 700,308.58 4,205,414.54 Mill Creek Forest 78 3 699,898.74 4,205,220.88 Mill Creek Forest 81 3 699,488.00 4,205,118.43 Mill Creek Road Crossing 84 3 699,112.77 4,204,839.81 Mill Creek Forest 86 3 698,751.09 4,204,574.14 Mill Creek Forest
49 3 704,771.83 4,205,800.00 Mill Creek Forest 51 3 704,485.47 4,205,467.35 Mill Creek Forest 53 3 704,115.14 4,205,228.40 Mill Creek Forest 55 3 704,016.21 4,204,842.76 Mill Creek Forest 57 3 704,136.86 4,204,379.38 Mill Creek Forest 59 3 704,030.08 4,203,899.47 Mill Creek Forest 62 3 703,823.53 4,203,455.27 Mill Creek Road Crossing 87 3 699,955.01 4,201,498.08 Mill Creek Road Crossing 90 3 699,867.66 4,201,084.91 Mill Creek Road Crossing
92 3 699,930.06 4,200,678.54 Mill Creek Road Crossing 94 3 700,116.49 4,200,299.15 Mill Creek Forest 91 3 699,490.54 4,201,418.90 Mill Creek Road Crossing 93 3 699,340.97 4,200,970.53 Mill Creek Forest 95 3 699,157.60 4,200,542.37 Mill Creek Forest 97 3 698,779.83 4,200,262.37 Mill Creek Forest 99 3 698,498.93 4,199,935.82 Mill Creek Road Crossing
100 3 698,323.77 4,199,555.06 Mill Creek Forest
130
Ap
pen
dix
F.
ST
EP
L i
np
uts
.
Load
Ad
Wat
ersh
edT
ype
(km
2)
HS
GU
rban
Cro
pP
astu
reF
ore
stM
ined
Cat
tleC
hick
en#
of S
eptic
Po
p. per
Sys
tem
%
Mill
Cre
ekT
ota
l Load
132.6
D7.0
0.2
6.2
71.8
14.9
884
130
884
30.3
9
Mill
Cre
ekB
elow
Dam
s96.2
D7.1
0.2
6.5
78.4
7.9
615
130
884
30.3
9
Min
eral
Fork
Tota
l Load
51.5
D2.9
0.7
2.6
90.1
3.8
216
30
189
30.3
9
Min
eral
Fork
Bel
ow
Dam
s42.3
D2.5
0.7
2.1
92.5
2.2
87
30
189
30.3
9
Cle
ar C
reek
-Min
eral
Fork
Tota
l Load
98.8
D2.8
0.2
3.8
91.6
1.7
376
52
37
30.3
9
Cle
ar C
reek
-Min
eral
Fork
Bel
ow
Dam
s75.6
D2.6
0.2
4.4
91.5
1.3
324
52
37
30.3
9
Old
Min
es C
reek
Tota
l Load
48.1
D7.5
0.2
6.3
75.1
11.0
339
47
454
30.3
9
Old
Min
es C
reek
Bel
ow
Dam
s39.4
D8.6
0.2
7.4
73.7
10.2
286
47
454
30.3
9
Min
e a
Bre
ton
Cre
ekT
ota
l Load
124
D8.2
0.5
14.1
73.4
3.8
1,4
29
197
2,0
75
30.3
9
Min
e a
Bre
ton
Cre
ekB
elow
Dam
s105
D8.4
0.5
16.2
73.1
1.7
1,6
87
197
2,0
75
30.3
9
Four
che
a R
enau
ltT
ota
l Load
101
D3.7
0.1
16.4
79.6
0.2
1,3
14
181
106
30.3
9
Four
che
a R
enau
ltB
elow
Dam
s96.8
D3.8
0.1
17.0
79.1
0.1
1,6
18
181
106
30.3
9
Sun
nen
Lak
e-F
our
che
a R
enau
ltT
ota
l Load
68.8
C4.1
0.0
6.5
88.1
1.3
411
56
204
30.3
9
Sun
nen
Lak
e-F
our
che
a R
enau
ltB
elow
Dam
s68.6
C4.1
0.0
6.5
88.1
1.3
220
56
204
30.3
9
Min
eral
Fork
-Who
leT
ota
l Load
490.5
D5.0
0.3
9.5
82.2
3.0
4,7
01
563
3,0
65
30.3
9
Min
eral
Fork
-Who
leB
elow
Dam
s428.6
D5.2
0.3
10.9
81.5
2.1
4,2
28
563
3,0
65
30.3
9
# o
f A
nim
als
Sep
tic S
yste
ms
Lan
d u
se (
%)
131
Ap
pen
dix
G. U
SL
E i
np
uts
for
ST
EP
L.
Lo
adA
d
Wat
ersh
edT
ype
(km
2)
KL
SK
LS
KL
SK
LS
C
Mill
Cre
ekT
ota
l Lo
ad132.6
0.4
76
1.1
94
0.4
80
1.2
31
0.4
07
2.4
36
0.3
00
1.5
30
0.1
70
Mill
Cre
ekB
elo
w D
ams
96.2
0.4
88
1.1
45
0.4
90
1.1
84
0.3
99
2.5
76
0.3
09
1.4
93
0.1
78
Min
eral
Fo
rkT
ota
l Lo
ad51.5
0.4
53
1.0
45
0.4
09
3.3
04
0.2
85
4.3
01
0.2
76
3.3
44
0.2
15
Min
eral
Fo
rkB
elo
w D
ams
42.3
0.4
53
0.5
05
0.4
00
2.8
12
0.2
78
4.5
85
0.2
56
3.6
69
0.2
99
Cle
ar C
reek
-Min
eral
Fo
rkT
ota
l Lo
ad98.8
0.4
57
1.8
31
0.4
38
2.4
97
0.2
66
3.4
38
0.2
68
1.5
75
0.1
57
Cle
ar C
reek
-Min
eral
Fo
rkB
elo
w D
ams
75.6
0.4
61
1.8
56
0.4
44
2.2
62
0.2
69
3.4
49
0.2
71
1.6
94
0.1
94
Old
Min
es C
reek
To
tal L
oad
48.1
0.4
47
2.0
21
0.4
67
1.9
67
0.3
44
2.9
91
0.3
04
1.4
26
0.1
12
Old
Min
es C
reek
Bel
ow
Dam
s39.4
0.4
50
2.1
10
0.4
70
1.9
96
0.3
58
2.9
96
0.3
08
1.4
25
0.1
19
Min
e a
Bre
ton
Cre
ekT
ota
l Lo
ad124
0.4
83
6.1
49
0.4
58
4.2
31
0.3
10
3.3
85
0.3
05
2.2
45
0.0
33
Min
e a
Bre
ton
Cre
ekB
elo
w D
ams
105
0.4
84
6.1
46
0.4
61
4.2
57
0.3
16
3.3
98
0.2
94
1.9
27
0.0
45
Fo
urch
e a
Ren
ault
To
tal L
oad
101
0.4
15
1.7
32
0.4
36
3.5
45
0.2
99
3.3
57
0.3
45
2.3
35
0.0
32
Fo
urch
e a
Ren
ault
Bel
ow
Dam
s96.8
0.4
17
1.7
37
0.4
37
3.5
56
0.2
97
3.3
61
0.3
44
2.1
80
0.1
14
Sun
nen
Lak
e-F
our
che
a R
enau
ltT
ota
l Lo
ad68.8
0.2
62
1.5
24
0.3
12
1.4
55
0.2
58
3.7
71
0.3
11
2.8
19
0.0
00
Sun
nen
Lak
e-F
our
che
a R
enau
ltB
elo
w D
ams
68.6
0.2
62
1.5
24
0.3
12
1.4
55
0.2
58
3.7
71
0.3
11
2.8
19
0.0
00
Min
eral
Fo
rk-W
hole
To
tal L
oad
490.5
0.4
61
3.5
21
0.4
34
3.4
07
0.2
91
3.5
16
0.2
96
1.9
48
0.0
97
Min
eral
Fo
rk-W
hole
Bel
ow
Dam
s428.6
0.4
64
3.4
87
0.3
33
1.7
88
0.3
99
2.5
76
0.2
95
3.5
40
0.1
33
Cro
pP
astu
reF
ore
stM
ined
132
Appendix H. Large dams in Mineral Fork and Mill Creek watersheds.
Appendix H-1. Large dams characteristics identified in Mineral Fork and Mill Creek watersheds.
ID# Year
Completed Regulation HUC12 Stream
Dam
Height
(m)
Ad (m2)
MO31006 1965 Wet Clear Creek-Mineral Fork Sycamore Creek 6.1 6,291,875
MO31986 1991 Wet Mineral Fork Trib. Mineral Fork 6.1 1,121,645
MO30744 1947 Wet Old Mines Creek Trib. Old Mines Creek 6.4 1,015,205
MO30996 1965 Wet Mine a Breton Creek Mine a Breton Creek 4.9 1,948,590
MO30722 1972 Wet Clear Creek-Mineral Fork Simpson Branch 9.4 6,861,948
MO31123 1975 Wet Mill Creek Trib. Shibboleth Branch 9.4 2,470,149
MO30708 1959 Dry Mill Creek Trib. Mill Creek 30.2 220,254
MO30715 1978 Dry Mill Creek Trib. Mill Creek 29.6 277,201
MO31158 1963 Dry Mill Creek Trib. Mill Creek 27.1 143,573
MO30476 1962 Filled/Wet Mine a Breton Creek Trib. Mine a Breton Creek 25.9 3,286,917
MO30728 1967 Wet Mineral Fork Trib. Mineral Fork 25.9 1,755,412
MO31825 1980 Wet Mill Creek Pond Creek 24.4 9,131,134
MO31155 1973 Dry Old Mines Creek Trib. Old Mines Creek 24.1 355,241
MO30475 1953 Dry Old Mines Creek Trib. Old Mines Creek 23.8 91,681
MO30386 1979 Filled/Wet Mill Creek Fountain Farm Branch 23.5 836,326
MO30705 1968 Dry Mill Creek Trib. Mill Creek 21.9 1,129,036
MO31154 1943 Dry Mill Creek Trib. Mill Creek 21.3 1,067,055
MO30479 1971 Filled/Wet Mine a Breton Creek Trib. Mine a Breton Creek 20.7 668,043
MO30688 1965 Wet Mine a Breton Creek Trib. Bates Creek 20.7 2,498,095
MO30112 1971 Wet Fourche a Renault Ashly Branch 20.4 3,768,750
MO31124 1977 Filled/Wet Mill Creek Trib. Shibboleth Branch 18.9 740,778
MO30706 1980 Dry Old Mines Creek Mud Town Creek 18.6 1,754,851
MO31005 1957 Dry Old Mines Creek Trib. Old Mines Creek 17.1 399,823
MO30111 1948 Wet Sunnen Lake-Fourche a Renault Fourche a Renault 15.5 68,748,769
MO30101 1960 Wet Mine a Breton Creek Swan Branch 15.2 3,833,738
MO30903 1957 Wet Mill Creek Trib. Mill Creek 15.2 1,445,524
MO31118 1979 Dry Mill Creek Trib. Cadet Creek 14.6 480,594
MO30716 1970 Wet Clear Creek-Mineral Fork Trib. Arnault Branch 14.0 2,167,054
MO30731 1941 Wet Mineral Fork Trib. Mineral Fork 13.7 6,310,471
MO30124 1972 Dry Mill Creek Fountain Farm Branch 9.1 50,457
MO31117 1968 Dry Mill Creek Trib. Mill Creek 9.1 7,110,537
MO31122 Dry Old Mines Creek Salt Pine Creek 9.1 4,586,143
MO31949 1991 Wet Old Mines Creek Rubidoux Branch 9.1 1,301,740
MO30723 1967 Wet Clear Creek-Mineral Fork Trib. Mineral Fork 10.4 1,684,346
MO30480 1950 Wet Mine a Breton Creek Trib. Mine a Breton Creek 10.1 636,485
MO30746 1935 Wet Mine a Breton Creek Trib. Mine a Breton Creek 12.5 1,508,306
MO31147 1950 Dry Mill Creek Mill Creek 10.5 117,909
MO30749 1964 Wet Mill Creek Shibboleth Branch 8.5 11,635,162
MO30994 1968 Wet Mine a Breton Creek Trib. Bates Creek 8.5 3,034,165
MO30993 1952 Wet Mine a Breton Creek Trib. Mine a Breton Creek 3.7 834,759
MO30720 1974 Wet Clear Creek-Mineral Fork Rogue Creek 8.2 3,720,890
MO31396 1977 Wet Clear Creek-Mineral Fork Trib. Clear Creek 7.6 1,172,961
MO31397 1979 Filled/Wet Clear Creek-Mineral Fork Clear Creek 7.6 1,394,923
133
Appendix H-2. Topography and land use of historical mine tailings ponds and dams in Mill
Creek (A & B) and Mineral Fork (C & D) watersheds.
134
Appendix H-3. Ground view of A) and B), the Cadet Mine Tailings Dam (#MO30715) within
the Mill Creek watershed (Photo taken December 18, 2018).