Date post: | 27-Oct-2014 |
Category: |
Documents |
Upload: | mohan-ekambaram |
View: | 80 times |
Download: | 4 times |
CERCCapital Cost Benchmarking
Formatting of Headers / Dividers
Sheet Header 1 CERC SheetHeader1
Sheet Header 2 Capital Cost Benchmarking SheetHeader2Sheet Header 3 SheetHeader3
Header 1 Header 1 Header1Header 2 Header 2 Header2Header 3 Header 3 Header3
Inputs Divider Operational Assumptions Inputs_Divider
Table Heading 2 Table Heading 2 Table_Heading2Table Heading 3 Table Heading 3Table Heading 4 Table Heading 4
Individual Cell Assumptions
Standard Assumption 100 Assumptions
Offsheet Reference 100 Offsheet
Flex Cell 100 Assumption_Flex
Name Inputs Cost Type Technical_Input
Technical Input 1,000.00 Input
Empy Cell Empty_Cell
Background for Flag 0 Flag
Infrastructure
Sub-Total Sub-Total Sub-Total
Line Total 100.00 Line_Summary
Units USD Unit
Operation Line (Non-Addition) 100 Line_Operation
Operation (Addition / Total) 100 Line_Total
Closing Balance 100 Line_ClosingBal
Key Line 100 Line_Key
Development Styles
WIP W WIP
Central Electricity Regulatory Commission
Capital Cost Benchmarking for Transmission Sub-Station 400/220 kV
CERCCapital Cost Benchmarking
S.No. Description
1
2
Number of Line Bays 400 kV220 kV
Number of ICT Bays 400 kV220 kV
Number of ICTs -Capacity in MVA 315500
Number of Reactors Shunt ReactorBus Reactor
3
4
5 The benchmark cost shall get computed in the cell C54 of "Computation_Sheet"
6 The month and the year of escalation can be chosen from drop down list provided in cell D5
7
The model for Transmission sub-station is meant to provide benchmark cost for selected configuration in terms of number of ICTs, reactors, bays etc.
There are 20 standard configurations (called alternates here) provided in the model. The cost has been computed for each of the alternates.For example alternate-1 has configuration given below:-
The user has to select the alternate that matches the configuration as given by petitioner using drop down list given in cell C10 of Computation_sheet
In case none of the alternates matches the configuration given by petitioner, user has to select the closest alternate that matches the configuration. The user may then add/substract components as given in cells C46 to C51 of "Computation_Sheet" to match the required configuration.
The model can be updated by entering the value of indices in sheet named "Indices" for corresponding month and year. The user to refer to IEEMA publications for the same.
Description
46222000
The benchmark cost shall get computed in the cell C54 of "Computation_Sheet"
The month and the year of escalation can be chosen from drop down list provided in cell D5
The model for Transmission sub-station is meant to provide benchmark cost for selected configuration in terms of
There are 20 standard configurations (called alternates here) provided in the model. The cost has been computed for
The user has to select the alternate that matches the configuration as given by petitioner using drop down list given in
In case none of the alternates matches the configuration given by petitioner, user has to select the closest alternate that matches the configuration. The user may then add/substract components as given in cells C46 to C51 of
The model can be updated by entering the value of indices in sheet named "Indices" for corresponding month and year.
CERCCapital Cost Benchmarking
Choose Month and Year of Escalation Jan-09
Choose Desired Configuration (from Alternates shown below)
Choose Sub-Station Configuration Alt - 1
Descripction Alt - 1 Alt - 2 Alt - 3 Alt - 4 Alt - 5 Alt - 6 Alt - 7 Alt - 8 Alt - 9 Alt - 10 Alt - 11 Alt - 12 Alt - 13 Alt - 14 Alt - 15 Alt - 16 Alt - 17 Alt - 18 Alt - 19 Alt - 20
Number of Line Bays 400 kV 4 4 4 4 2 2 6 4 11 6 2 2 2 6 4 2 2 12 7 4 220 kV 6 6 6 4 4 4 6 11 12 6 4 4 4 6 6 4 4 5 - -
Number of ICT Bays 400 kV 2 2 2 2 2 1 2 1 2 2 2 2 1 2 3 2 2 2 - - 220 kV 2 2 2 2 2 1 2 1 2 2 2 2 1 2 3 2 2 2 - -
Number of ICTs -Capacity in MVA 315 2 2 2 2 2 1 2 0 0 2 2 2 1 0 3 2 2 2 - - 500 0 0 0 0 0 0 0 1 2 0 0 0 0 2 0 0 0 0 - -
Number of Reactors Shunt Reactor 0 2 4 2 2 2 2 3 5 2 1 0 1 2 2 0 2 4 2 2 Bus Reactor 0 0 0 0 0 0 0 0 0 2 0 1 1 2 1 0 1 2 1 1
Description Alt - 1
Number of Line Bays 400 kV 4220 kV 6
Number of ICT Bays 400 kV 2220 kV 2
Number of ICTs -Capacity in MVA 315 2500 0
Number of Reactors Shunt Reactor 0Bus Reactor 0
Combination Name Configuration
Combination-1 400 kV Line Bay with Shunt Reactor
Combination-2 400kV Line Bay Combination-3 220KV Line Bay Combination-4 1 x 315 MVA ICT with 400 kV & 220 kV Bays Combination-5 Addition of Shunt Reactor to 400KV Line Bay Combination-6 400 kV Bus Reactor Bay
Component Add/ Subtract? 1Choose Combination to be added/ subtracted None Add 1Choose Combination to be added/ subtracted None Add 1Choose Combination to be added/ subtracted None Add 1 None Alt - 1 Alt - 2 Alt - 3 Alt - 4 Alt - 5 Alt - 6 Alt - 7 Alt - 8 Alt - 9 Alt - 10 Alt - 11 Alt - 12 Alt - 13 Alt - 14 Alt - 15 Alt - 16 Alt - 17 Alt - 18 Alt - 19 Alt - 20Choose Combination to be added/ subtracted None Add 1Choose Combination to be added/ subtracted None Add 1Choose Combination to be added/ subtracted None Add
NoneCombination-1
66.19 Combination-2
Combination-3Combination-4Combination-5Combination-6
For Modification in above configuration please choose from drop down list
Total Hard cost of the Configuration chosen (INR Crores)
Jan-06 Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07 Apr-07 May-07 Jun-07 Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14
CERCCapital Cost Benchmarking
S.No. Particulars Units Jan-06 Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07 Apr-07 May-07 Jun-07 Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09
1 Power Transformera) Copper INR/ MT 234,065.00 257,714.00 259,846.00 321,694.00 401541.00 367411.00 396727.00 396250.00 388127.00 377445.00 349767.00 331319.00 321137.00 266730.00 268199.00 300799.00 341326.00 331023.00 343064.00 310398.00 327855.00 350128.00 340897.00 291788.00 271169.00 298979.00 384365.00 356028.00 374688.00 378574.00 378065.00 379097.00 342410.00 349353.00 254789.00 201489.00 166808.00 175396.00 207578.00 232254.00 240138.00 258090.00 271982.00 314505.00 308032.00b) Electrical Lamination Steel INR/ MT 200,074.00 195,894.00 194,855.00 221,331.00 204827.00 203822.00 212009.00 210100.00 209593.00 200334.00 203675.00 198712.00 200218.00 195011.00 196183.00 191168.00 182565.00 185109.00 219073.00 198404.00 209701.00 191920.00 192092.00 195575.00 188296.00 194326.00 231172.00 195118.00 203869.00 212968.00 215227.00 225373.00 229721.00 243082.00 238764.00 230946.00 226040.00 213066.00 214251.00 204758.00 202337.00 184752.00 178393.00 177277.00 170233.00c) Contructing Steel Index No 257.90 256.90 233.40 243.30 226.20 243.30 243.90 243.40 250.80 253.50 254.90 258.90 259.30 259.20 259.90 260.10 261.20 266.20 268.30 276.70 276.70 217.22 276.70 277.30 277.90 280.10 280.60 280.00 287.40 357.10 354.60 357.90 353.67 348.92 341.61 338.67 330.60 322.70 319.10 286.10 289.00 286.00 286.20 286.70 286.40d) Insulating Material INR/ Kg 286.83 288.92 300.68 309.05 308.45 307,52 306.86 303.78 302.10 290.46 287.38 286.94 286.94 286.94 286.94 282.48 282.48 282.48 331.53 275.40 305.11 281.76 281.17 286.55 302.69 311.55 365.31 365.00 373.71 374.56 389.66 411.88 406.98 399.71 392.28 390.17 387.81 363.11 359.59 384.24 373.24 381.53 392.25 407.77 408.76e) Oil INR/ KL 34,017.00 34,017.00 36,127.00 38,018.00 38018.00 40350.00 40655.00 42602.00 42241.00 43946.00 41113.00 38995.00 38779.00 38562.00 38661.00 38183.00 36487.00 35573.00 35269.00 32484.00 36007.00 49950.00 35827.00 35827.00 36319.00 38599.00 39304.00 39304.00 40182.00 45215.00 49358.00 56272.00 59080.00 56642.00 54287.00 53145.00 52986.00 49375.00 46625.00 46250.00 45500.00 44125.00 45300.00 47250.00 58950.00f) Labour Index No. 130.07 129.12 129.60 130.77 130.77 130.77 131.71 133.83 135.00 135.00 136.18 138.30 138.30 138.30 138.30 139.39 138.30 139.39 132.01 133.01 133.01 144.88 144.83 145.92 145.92 145.92 138.01 147.00 149.19 150.28 151.37 152.46 147.25 149.31 150.34 150.34 147.01 147.00 148.00 148.00 148.00 150.64 160.00 162.00 162.00
2 LT Transformer a) Copper INR/ MT 234,065.00 257,714.00 259,846.00 321,694.00 401541.00 367411.00 396727.00 396250.00 388127.00 377445.00 349767.00 331319.00 321137.00 266730.00 268199.00 300799.00 341326.00 331023.00 343064.00 310398.00 327855.00 350128.00 340897.00 291788.00 271169.00 298979.00 384365.00 356028.00 374688.00 378574.00 378065.00 379097.00 342410.00 349353.00 254789.00 201489.00 166808.00 175396.00 207578.00 232254.00 240138.00 258090.00 271982.00 314505.00 308032.00b) Electrical Lamination Steel INR/ MT 200,074.00 195,894.00 194,855.00 221,331.00 204827.00 203822.00 212009.00 210100.00 209593.00 200334.00 203675.00 198712.00 200218.00 195011.00 196183.00 191168.00 182565.00 185109.00 219073.00 198404.00 209701.00 215120.00 192092.00 195575.00 188296.00 194326.00 231172.00 195118.00 203689.00 212968.00 215227.00 225373.00 229721.00 243082.00 238764.00 230946.00 226040.00 213066.00 214251.00 204758.00 202337.00 184752.00 178393.00 177277.00 170233.00c) Contructing Steel Index No 257.90 256.90 233.40 243.30 226.20 243.30 243.90 243.40 250.80 253.50 254.90 258.90 259.30 259.20 259.90 260.10 261.20 266.20 268.30 276.70 276.70 217.22 276.70 277.30 277.90 280.10 280.60 280.00 387.40 357.10 354.60 357.90 353.67 348.92 341.61 338.67 330.60 322.70 319.10 286.10 289.00 286.00 286.20 286.70 286.40d) Insulating Material INR/ Kg 286.83 288.92 300.68 309.05 308.45 307.52 306.86 303.78 302.10 290.46 287.38 286.94 286.94 286.94 286.94 282.48 282.48 282.48 331.53 275.40 305.11 281.76 281.17 286.55 302.69 311.55 375.31 365.00 373.31 374.56 389.66 411.88 406.98 399.71 392.28 390.17 387.81 363.11 359.59 384.24 373.24 381.53 392.25 407.77 408.76e) Oil INR/ KL 34,017.00 34,017.00 36,127.00 38,018.00 38018.00 40350.00 40655.00 42602.00 42241.00 43946.00 41113.00 38995.00 38779.00 38562.00 38661.00 38183.00 36487.00 35573.00 35704.00 35269.00 37131.00 49950.00 35827.00 35827.00 36319.00 38599.00 39304.00 39304.00 40182.00 45215.00 49538.00 56272.00 59080.00 56642.00 54287.00 53145.00 52986.00 47221.00 32138.00 32681.00 28067.00 26595.00 45300.00 47250.00 58950.00f) Labour Index No. 130.07 129.12 129.60 130.77 130.77 130.77 131.71 133.83 135.00 135.00 136.18 138.30 138.30 138.30 138.30 139.39 138.30 139.39 132.01 133.01 133.01 144.88 144.83 145.92 145.92 145.92 138.01 147.00 149.19 150.28 151.37 152.46 147.25 149.31 150.34 150.34 147.01 147.00 148.00 148.00 148.00 150.64 160.00 162.00 162.00
3 Circuit Breaker a) Contructing Steel Index No. 257.90 256.90 233.40 243.30 226.20 243.30 243.90 243.40 250.80 253.50 254.90 258.90 259.30 259.20 259.90 260.10 261.20 266.20 267.20 268.70 268.30 217.22 276.70 277.30 277.90 280.13 280.60 280.60 287.40 357.10 354.60 357.00 353.67 348.92 341.61 338.67 330.60 322.70 319.10 286.10 289.00 286.00 286.20 286.70 286.40b) Copper INR/ MT 245,956.00 257,714.00 259,846.00 326,199.00 401541.00 367411.00 396727.00 396250.00 388127.00 377445.00 349767.00 331319.00 321137.00 266730.00 268199.00 300799.00 341326.00 331023.00 327276.00 343064.00 328486.00 350128.00 299451.00 283695.00 302578.00 340650.00 384365.00 3,56,028 374688.00 378574.00 378065.00 379097.00 342410.00 349353.00 254789.00 201489.00 155954.00 166808.00 175396.00 207578.00 232254.00 240138.00 258090.00 271982.00 314505.00c) Aluminium INR/ MT 140,300.00 146,300.00 147,800.00 148,800.00 161800.00 161800.00 153300.00 153800.00 155300.00 154800.00 166300.00 162300.00 166300.00 162900.00 162900.00 160400.00 159400.00 155900.00 152900.00 155900.00 148900.00 145900.00 147400.00 144900.00 141400.00 143400.00 141317.00 1,63,400 167400.00 175400.00 174400.00 178400.00 167410.00 159465.00 151836.00 14398.00 131900.00 128400.00 128400.00 128400.00 131400.00 126900.00 132400.00 144650.00 150650.00d) Epoxy Resin INR/ Kg 168.00 168.00 168.00 168.00 168.00 168.00 180.00 180.00 180.00 180.00 180.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 188.00 188.00 188.00 188.00 188.00 188.00 188.00e) Labour Index No. 130.07 129.12 129.60 130.77 130.77 130.77 131.71 133.83 135.00 135.00 136.18 138.30 138.30 138.30 138.30 139.39 138.30 139.39 132.01 133.01 133.01 144.88 144.83 145.92 145.92 145.92 138.01 147.00 149.19 150.28 151.37 152.46 147.25 149.31 150.34 150.34 147.01 147.00 148.00 148.00 148.00 150.64 160.00 162.00 162.00
4 Current Transformer and Voltage Transformer a) Index INSLR Index No 136.69 136.24 134.10 133.93 134.42 137.60 138.99 139.25 141.91 142.76 143.83 144.08 143.74 142.89 144.33 143.95 143.74 144.43 144.78 144.88 144.72 144.79 145.71 146.40 148.13 148.18 148.21 148.21 150.71 159.36 160.11 167.71 170.33 171.24 168.45 164.89 161.94 157.02 159.87 150.87 150.64 150.70 153.18 153.63 156.06b) Contructing Steel Index No 257.90 256.90 233.40 243.30 226.20 243.30 243.90 243.40 250.80 253.50 254.90 258.90 259.30 259.20 259.90 260.10 261.20 266.20 267.20 268.70 268.30 217.22 276.70 277.30 277.90 280.13 280.60 280.60 287.40 357.10 354.60 357.90 353.67 348.92 341.61 338.67 330.60 322.70 319.10 286.10 289.00 286.00 286.20 286.70 286.40c) Oil INR/ KL 34,017.00 34,017.00 36,127.00 38,018.00 38018.00 40350.00 40655.00 42602.00 42241.00 43946.00 41113.00 38995.00 38779.00 38562.00 38661.00 38183.00 36487.00 35573.00 35704.00 35269.00 37131.00 49950.00 35827.00 35827.00 36319.00 38599.00 39304.00 39304.00 40182.00 45215.00 49538.00 56272.00 59080.00 56642.00 54287.00 53145.00 52986.00 47221.00 32138.00 32681.00 28067.00 26595.00 27178.00 30436.00 36277.00d) Index No.for Insulator Index No 136.69 136.24 134.10 133.93 134.42 137.60 138.99 139.25 141.91 142.76 143.83 144.08 143.74 142.89 144.33 143.95 143.74 144.43 144.78 144.88 144.72 144.79 145.71 146.40 148.13 148.18 148.21 148.21 150.71 159.36 160.11 167.71 170.33 171.24 168.45 164.89 161.94 157.02 159.87 150.87 150.64 150.70 153.18 153.63 156.06e) Electrical Steel Sheets INR/ MT 200,074.00 195,894.00 194,855.00 198,351.00 204827.00 203822.00 212009.00 210100.00 209593.00 200334.00 203675.00 198712.00 200218.00 195011.00 196183.00 191168.00 182565.00 185109.00 195331.00 190181.00 190143.00 215120.00 192092.00 195575.00 188296.00 194326.00 231172.00 1,95,118. 2,03,869 212968.00 215227.00 225373.00 229721.00 243082.00 248367.00 249862.00 250205.00 228507.00 237253.00 222515.00 219799.00 186754.00 187491.00 182536.00 170393.00f) Copper INR/ MT 245,956.00 257,714.00 259,846.00 326,199.00 401541.00 367411.00 396727.00 396250.00 388127.00 377445.00 349767.00 331319.00 321137.00 266730.00 268199.00 300799.00 341326.00 331023.00 327276.00 343064.00 328486.00 343215.00 299451.00 283695.00 302578.00 340650.00 384365.00 3,56,028 374688.00 378574.00 378065.00 3,79,097 342410.00 349353.00 254789.00 201489.00 155954.00 166808.00 175396.00 207578.00 232254.00 240138.00 258090.00 271982.00 314505.00g) Aluminium INR/ MT 140,300.00 146,300.00 147,800.00 148,800.00 161800.00 161800.00 153300.00 153800.00 155300.00 154800.00 166300.00 162300.00 166300.00 162900.00 162900.00 160400.00 159400.00 155900.00 152900.00 155900.00 148900.00 145900.00 147400.00 144900.00 141400.00 143400.00 141317.00 1,63,400 1,67,400 175400.00 174400.00 1,78,400 167410.00 159465.00 151836.00 14398.00 131900.00 128400.00 128400.00 128400.00 131400.00 126900.00 132400.00 144650.00 150650.00h) Epoxy Resin INR/ Kg 168.00 168.00 168.00 168.00 168.00 168.00 180.00 180.00 180.00 180.00 180.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 188.00 188.00 188.00 188.00 188.00 188.00 188.00i) Labour Index No 130.07 129.12 129.60 130.77 130.77 130.77 131.71 133.83 135.00 135.00 136.18 138.30 138.30 138.30 138.30 139.39 138.30 139.39 132.01 133.01 133.01 144.88 144.83 145.92 145.92 145.92 138.01 147.00 149.19 150.28 151.37 152.46 147.25 149.31 150.34 150.34 147.01 147.00 148.00 148.00 148.00 150.64 160.00 162.00 162.00
5 Isolator a) Contructing Steel Index No 257.90 256.90 233.40 243.30 226.20 243.30 243.90 243.40 250.80 253.50 254.90 258.90 259.30 259.20 259.90 260.10 261.20 266.20 267.20 268.70 268.30 217.22 276.70 277.30 277.90 280.13 280.60 280.60 287.40 357.10 354.60 357.90 353.67 348.92 341.61 338.67 330.60 322.70 319.10 286.10 289.00 286.00 286.20 286.70 286.40b) Copper INR/ MT 245,956.00 257,714.00 259,846.00 326,199.00 401541.00 367411.00 396727.00 396250.00 388127.00 377445.00 349767.00 331319.00 321137.00 266730.00 268199.00 300799.00 341326.00 331023.00 327276.00 343064.00 328486.00 350128.00 299451.00 283695.00 302578.00 340650.00 384365.00 3,56,028 374688.00 378574.00 3,78,065 3,79,097 342410.00 349353.00 254789.00 201489.00 155954.00 166808.00 175396.00 207578.00 232254.00 240138.00 258090.00 271982.00 314505.00c) Alluminium INR/ MT 140,300.00 146,300.00 147,800.00 148,800.00 161800.00 161800.00 153300.00 153800.00 155300.00 154800.00 166300.00 162300.00 166300.00 162900.00 162900.00 160400.00 159400.00 155900.00 152900.00 155900.00 148900.00 145900.00 147400.00 144900.00 141400.00 143400.00 141317.00 1,63,400 1,67,400 175400.00 1,74,400 1,78,400 167400.00 159465.00 151836.00 14398.00 131900.00 128400.00 128400.00 128400.00 131400.00 126900.00 132400.00 144650.00 150650.00d) Epoxy Resin INR/ Kg 168.00 168.00 168.00 168.00 168.00 168.00 180.00 180.00 180.00 180.00 180.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 198.00 188.00 188.00 188.00 188.00 188.00 188.00 188.00e) Labour Index No. 130.07 129.12 129.60 130.77 130.77 130.77 131.71 133.83 135.00 135.00 136.18 138.30 138.30 138.30 138.30 139.39 138.30 139.39 132.01 133.01 133.01 144.88 144.83 145.92 145.92 145.92 138.01 147.00 149.19 150.28 151.37 152.46 147.25 149.31 150.34 150.34 147.01 147.00 148.00 148.00 148.00 150.64 160.00 162.00 162.00
6 Surge Arrester a) Zinc INR/ MT 107,100.00 124,500.00 121,500.00 140,200.00 171900.00 197900.00 166200.00 175300.00 181600.00 180500.00 212300.00 228800.00 221500.00 176500.00 178000.00 160400.00 174000.00 166300.00 157800.00 163500.00 144500.00 136700.00 131100.00 111100.00 109800.00 104200.00 107300.00 107300.00 98000.00 97700.00 90300.00 88700.00 83657.00 76145.00 72134.00 68926.00 63400.00 68900.00 67900.00 80700.00 88400.00 88200.00 91000.00 98900.00 106900.00b) Cobalt INR/ Kg 1,756.49 1,566.66 1,436.71 1,545.07 1716.50 1794.76 1698.04 1655.52 1985.91 2203.03 1996.81 2024.60 2889.92 2725.73 2762.56 3064.45 2954.22 2806.47 2665.83 2550.15 2443.39 2662.27 2764.57 3038.87 3632.43 4203.70 4570.15 4784.31 4726.05 4772.21 4495.37 4035.76 3827.61 33143.28 2892.46 22637.34 1677.63 2003.71 1748.72 1602.87 1850.25 1721.26 1642.20 2023.92 2210.95c) Alluminium INR/ MT 140,300.00 146,300.00 147,800.00 148,800.00 161800.00 161800.00 153300.00 153800.00 155300.00 154800.00 166300.00 162300.00 166300.00 162900.00 162900.00 160400.00 159400.00 155900.00 152900.00 155900.00 148900.00 145900.00 147400.00 144900.00 141400.00 143400.00 141317.00 1,63,400 1,67,400 175400.00 1,74,400 1,78,400 1,67,400 159465.00 151836.00 14398.00 131900.00 92267.00 96267.00 96250.00 96250.00 96433.00 98100.00 105600.00 115433.00d) Ball clay INR/ MT 1,575.00 1,575.00 1,575.00 1,575.00 1575.00 1675.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1725.00 1846.00 1893.00 1975.00 1975.00 1975.00 2025.00 2025.00 2025.00 2275.00 2275.00 2275.00e) Bismath INR/ Kg 550.99 538.49 535.53 465.31 516.54 517.64 505.75 511.61 526.80 555.84 649.34 690.01 792.79 916.72 978.70 1108.54 1402.73 1671.45 1723.64 1658.22 1664.86 1469.70 1315.72 1272.41 1236.55 1103.05 1158.03 1416.12 1525.07 1433.90 1287.77 1158.03 1148.83 1182.67 1136.94 1185.26 1066.29 1073.42 1114.50 1086.91 972.94 873.21 798.12 763.51 780.47f) Fuels/power Index No 312.40 310.70 311.00 313.50 314.70 316.80 319.70 320.10 326.50 328.90 331.40 329.60 326.70 322.40 322.30 320.70 319.60 320.30 322.00 321.90 321.80 322.40 321.70 323.70 326.50 334.40 334.20 334.20 334.20 334.20 334.20 334.20 334.20 334.20 334.20 334.20 350.20 331.80 329.50 323.50 321.00 322.60 325.20 327.10 338.40g) Labour Index No 130.07 129.12 129.60 130.77 130.77 130.77 131.71 133.83 135.00 135.00 136.18 138.30 138.30 138.30 138.30 139.39 138.30 139.39 132.01 133.01 133.01 144.88 144.83 145.92 145.92 145.92 138.01 147.00 149.19 150.28 151.37 152.46 147.25 149.31 150.34 150.34 147.01 147.00 148.00 148.00 148.00 150.64 160.00 162.00 162.00
7 Substation Structures including bolts and Nuts a) Published Price Index of Structurel Steel Index No 22,310.00 23,269.00 24,214.00 25,444.00 24541.00 24068.00 23595.00 24257.00 25203.00 25783.00 25783.00 26729.00 26729.00 27188.00 27925.00 28680.00 28881.00 28126.00 28611.00 29237.00 29334.00 35286.00 35900.00 36245.00 37567.00 38889.00 46434.00 46434.00 46675.00 48117.00 49269.00 49632.00 49582.00 49696.00 49874.00 49963.00 50867.00 49471.00 49894.00 49766.00 49806.00 46805.00 47030.00 47030.00 47360.00b) Published Price Index of Electrolytic Zinc INR / MT 107,100.00 124,500.00 121,500.00 140,200.00 171900.00 197900.00 166200.00 175300.00 181600.00 180500.00 212300.00 228800.00 221500.00 176500.00 178000.00 160400.00 174000.00 166300.00 157800.00 163500.00 144500.00 136700.00 131100.00 111100.00 109800.00 104200.00 107300.00 107300.00 98000.00 97700.00 90300.00 88700.00 86400.00 82600.00 75800.00 72500.00 63400.00 68900.00 67900.00 80700.00 88400.00 88200.00 91000.00 98900.00 106900.00c) Labour Index No 130.07 129.12 129.60 130.77 130.77 130.77 131.71 133.83 135.00 135.00 136.18 138.30 138.30 138.30 138.30 139.39 138.30 139.39 132.01 133.01 133.01 144.88 144.83 145.92 145.92 145.92 138.01 147.00 149.19 150.28 151.37 152.46 147.25 149.31 150.34 150.34 147.01 147.00 148.00 148.00 148.00 150.64 160.00 162.00 162.00
8 Index INSLR 136.69 136.24 134.10 133.93 134.42 137.60 138.99 139.25 141.91 142.76 143.83 144.08 143.74 142.89 144.33 143.95 143.74 144.43 144.78 144.88 144.72 144.79 145.71 146.40 148.13 148.18 148.21 148.21 150.71 159.36 160.11 167.71 170.33 171.24 168.45 164.89 161.94 161.94 157.02 150.87 150.64 150.70 153.18 153.63 156.06a) Oil INR/ KL 34,017.00 34,017.00 36,127.00 38,018.00 38018.00 40350.00 40655.00 42602.00 42241.00 43946.00 41113.00 38995.00 38779.00 38562.00 38661.00 38183.00 36487.00 35573.00 35704.00 35269.00 37131.00 49950.00 35827.00 35827.00 36319.00 38599.00 39304.00 39304.00 40182.00 45215.00 49538.00 56272.00 59080.00 56642.00 54287.00 53145.00 52986.00 47221.00 32138.00 32681.00 28067.00 26595.00 45300.00 47250.00 58950.00b) Labour Index No 130.07 129.12 129.60 130.77 130.77 130.77 131.71 133.83 135.00 135.00 136.18 138.30 138.30 138.30 138.30 139.39 138.30 139.39 132.01 133.01 133.01 144.88 144.83 145.92 145.92 145.92 138.01 147.00 149.19 150.28 151.37 152.46 147.25 149.31 150.34 150.34 147.01 147.00 148.00 148.00 148.00 150.64 160.00 162.00 162.00
9 PVC/XLPE Insulated power and control cables a) PVC Compound INR / MT 77,250.00 77,250.00 77,250.00 77,250.00 73500.00 73500.00 74750.00 80750.00 84000.00 84000.00 82000.00 82750.00 83750.00 84000.00 84000.00 82650.00 83650.00 83650.00 83650.00 86000.00 89000.00 87000.00 87000.00 87500.00 87500.00 88000.00 89000.00 89000.00 91000.00 92000.00 97000.00 97000.00 97000.00 95000.00 92650.00 85280.00 80250.00 83000.00 84000.00 84500.00 84500.00 84500.00 87600.00 88000.00 91500.00b) Metal INR / MT - - - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 58000.00 70200.00 63900.00 78600.00 89100.00 86100.00 96200.00 102100.00 114800.00c) Aluminium INR / MT 123,200.00 131,133.00 128,567.00 132,733.00 161800.00 161800.00 153300.00 153800.00 155300.00 154800.00 166300.00 162300.00 147900.00 144500.00 144500.00 142167.00 137167.00 133000.00 130000.00 131667.00 125333.00 112467.00 147400.00 144900.00 141400.00 143400.00 141317.00 1,63,400 1,67,400 1,75,400 1,74,400 1,78,400 1,67,400 159465.00 151836.00 14398.00 131900.00 104150.00 104150.00 104150.00 104150.00 104267.00 105933.00 113433.00 123267.00d) Copper INR / MT 253,217.00 265,322.00 267,517.00 335,829.00 409628.00 374811.00 404717.00 404230.00 395943.00 385046.00 356811.00 337991.00 287323.00 279653.00 315666.00 361752.00 346886.00 337667.00 356255.00 340050.00 341598.00 350128.00 299451.00 283695.00 302578.00 340650.00 384365.00 3,56,028 3,74,688 3,78,574 3,78,065 3,79,097 3,42,410 3,49,353 254789.00 201489.00 185521.00 192169.00 222863.00 254794.00 255759.00 274252.00 276648.00 335659.00 337892.00e) weight in MT of metal KM(Size wise) - - - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
f) - - - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 451.10 452.20 452.20 452.20 452.20 481.40 481.40 481.40
g) Index No
130.07 129.12 129.60 130.77 130.77 130.77 131.71 133.83 135.00 135.00 136.18 138.30 138.30 138.30 138.30 139.39 138.30 139.39 132.01 133.01 133.01 144.88 144.83 145.92 145.92 145.92 138.01 147.00 149.19 150.28 151.37 152.46 147.25 149.31 150.34 150.34 147.01 147.00 148.00 148.00 148.00 150.64 160.00 162.00 162.00
h) Index No 169.90 256.90 233.40 191.00 226.20 243.30 243.90 243.40 250.80 253.50 254.90 258.90 259.30 259.20 259.90 260.10 261.20 266.20 267.20 268.70 268.30 217.22 276.70 277.30 277.90 280.13 280.60 280.60 287.40 357.10 354.60 357.90 342.50 337.90 335.20 346.10 330.60 322.70 319.10 286.10 289.00 286.00 286.20 286.70 286.40
i) Index No
186.20 188.88 190.60 191.20 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 190.60 211.70 211.70 213.50 214.30 216.80 219.40 219.40 219.40 219.40 220.16 220.24 220.78 220.86 223.10 223.10 223.10 224.00 224.00 224.00 224.00 224.00 227.20 227.20 227.20
j) Cement Index No 191.20 191.20 191.20 191.20 191.20 191.20 191.20 191.20 191.20 191.20 220.20 220.20 220.20 220.20 220.20 220.20 220.20 220.20 220.20 220.20 220.20 220.20 220.20 220.30 220.50 220.60 220.80 220.80 220.80 220.80 220.80 220.80 220.80 220.80 220.80 221.40 221.40 222.70 224.50 227.70 227.70 227.70 230.90 230.50 228.10k) Diesel Index No 418.00 418.00 418.00 418.00 418.00 418.00 418.00 418.00 418.00 418.00 418.00 418.00 418.00 418.00 418.00 418.00 449.50 449.50 449.50 449.50 449.50 449.50 449.50 451.50 451.50 451.50 465.80 465.80 465.80 465.80 465.80 478.90 478.90 478.90 478.90 478.90 482.30 451.10 452.20 452.20 452.20 452.20 481.40 481.40 481.40
Labour Correction Factor
Month and Year of Escalation
Month and Year of Escalation Jan-09
S.No. Particulars Units
1 Power Transformera) Copper INR/ MT b) Electrical Lamination Steel INR/ MT c) Contructing Steel Index No d) Insulating Material INR/ Kg e) Oil INR/ KL f) Labour Index No.
2 LT Transformera) Copper INR/ MT
b) Electrical Lamination Steel INR/ MT
c) Contructing Steel Index No
d) Insulating Material INR/ Kg
e) Oil INR/ KL
f) Labour Index No.
3 Circuit Breakera) Contructing Steel Index No. b) Copper INR/ MT c) Alluminium INR/ MT d) Epoxy Resin INR/ Kg e) Labour Index No.
4 Current Transformer and Voltage Transformera) Index INSLR Index No b) Contructing Steel Index No c) Oil INR/ KL d) Index No.for Insulator Index No e) Electrical Steel Sheets INR/ MT f) Copper INR/ MT g) Alluminium INR/ MT h) Epoxy Resin INR/ Kg i) Labour Index No
5 Isolatora) Contructing Steel Index No b) Copper INR/ MT c) Alluminium INR/ MT d) Epoxy Resin INR/ Kg e) Labour Index No.
6 Surge Arrestera) Zinc INR/ MT b) Cobalt INR/ Kg c) Alluminium INR/ MT d) Ball clay INR/ MT e) Bismath INR/ Kg f) Fuels/power Index No g) Labour Index No
7 Substation Structures including bolts and Nutsa) Published Price Index of Structurel Steel Index No b) Published Price Index of Electrolytic Zinc INR / MT c) Labour Index No
8 Index INSLR a) Oil INR/ KL b) Labour Index No
9 PVC/XLPE Insulated Power and Control Cablesa) PVC Compound INR / MT b) Metal INR / MT c) Alliminium INR / MT d) Copper INR / MT e) Weight in MT of metal KM (Size wise)
f)
g) Index No
h) Index No
i) Index No j) Cement Index No k) Diesel Index No
IOC _HST basic ceiling selling price ex -refinery issued by IOC Northern region New Delhi
All india average consuer prize index for industrial worker(base 1982=100)as published by labour bureau ,Govt of india and circulated by emo.
Index No.of whole sell price in india for iron and steel as published by reserve bank of india bulletein
Index No.of whole sell price in india for non metalic mineral products(Structural Clay Product) as published by RBI.
IOC _HST basic ceiling selling price ex -refinery issued by IOC Northen region New Delhi
All india average consuer prize index for industrial worker(base 1982=100)as published by labour bureau, Govt of india and circulated by emo.
Index No.of whole sell price in india for iron and steel as published by reserve bank of india bulltein
Index No.of whole sell price in india for non metalic mineral products(Structurel clay product) as published by RBI.
Labour Correction Factor
LT Transformer
P1 = Po x { 0.15 x (A1/Ao) + 0.26 x (B1/Bo) + 0.08x (C1/Co) + 0.05 x (D1/Do) + 0.11 x (E1/Eo) + 0.12 x (L1/Lo)} – Po
Auto Transformer
P1 = Po x { 0.15 + 0.23 x (A1/Ao) + 0.26 x (B1/Bo) + 0.07 x (C1/Co) + 0.05 x (D1/Do) + 0.15 x (E1/Eo) + 0.12 x (L1/Lo)} – Po
Circuit Breakers
P1 = Po x { 0.15 + 0.15 x (C1/Co) + 0.23 x (A1/Ao) + 0.22 x (Al1/Alo) + 0.15 x (D1/Do) + 0.20 x (L1-Lo)/Lo)} – Po
Current Transformer & Capacity Voltage Transformer
P1 = Po x { 0.15 + 0.13 x (A1/Ao) + 0.12 x (B1/Bo) + 0.11 x (C1/Co) + 0.23 x (D1/Do) + 0.06 x (E1/Eo) +0.20 x (L1-Lo)/Lo)} – Po
Isolators
P1 = Po x { 0.15 + 0.17 x (C1/Co) + 0.18 x (A1/Ao) + 0.25 x (Al1/Alo) + 0.05 x (D1/Do)+ 0.20 x (L1-Lo)/Lo)} – Po
Surge Arrestor
P1 = Po x { 0.15 + 0.20 x (Zn1/Zno) + 0.20 x (CO1/COo) + 0.15 x (Bi1Bio) + 0.10 x(Ba1/Bao)+ 0.20 x (L1-Lo)/Lo)} – Po
11 kV XLPE/PVC Insulated Power and Control Cables
P1 = Po x { 0.85 + 0.15 x (PVC1/PVCo) } – Po + (M1- Mo)
Sub-station Structures {Lattice Steel structures& Pipe Structures (Including Bolts and Nuts, washers & Foundation Bolts)
P1 = Po x { 0.15 + 0.58 x (Sa1/Sao) + 0.16 x (Zn1/Zno) + 0.11 x (L1)/Lo)} – Po
For Indian Rupee portion of Erection Price
ER1 = ERo x (0.20 + 0.80 x (L1/Lo)
Switchyard Fencing
P1= Po x { (0.30 + 0.50 x (C1/Co) + 0.20 x (L1/Lo) }
Bus-Bar Materials
P1= Po x { (0.15 + 0.60 x (Al1/Alo) + 0.15 x (D1/Do) + 0.10 x (L1/Lo) }
P1 = Price Adjustment amount, expressed in currency of bid Po =Ex-work price of main equipment in currency of Bid
A = Copper Prices as published by IEEMAB = CRGO Electrical SheetsC= Iron and SteelD= Insulating MaterialE= Transformer Oil Base StockI = InsulatorCO= CobaltBi = BismuthBa= Ball ClayAl = AluminumM= Weight in MT per km of Cable x Published Index of metal converted into currency (For Power Cable: Aluminum, For Control Cable : Copper)Zn = ZincINS= Index INSTRSa = Steel AngleL = Labour Index
Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14
CERCCapital Cost Benchmarking
Project Costs (Actual)
Name of the Utility
Name of sub-station
Reference P.O. No.
Month and Year of Commissioning
S.No. Name of the Component Unit
1 Power Transformer
a) INR Lakhs
b) INR Lakhs
c) INR Lakhs
d)
2 Shunt Reactor
a) 420KV, 125 MVAR, 3-Phase Shunt Reactor INR Lakhs
b) 420KV, 80 MVAR, 3-Phase Shunt Reactor INR Lakhs
c) 420KV, 63/50 MVAR, 3-Phase Shunt Reactor INR Lakhs
d) NGR with oil, for above 400 kV Shunt Reactor INR Lakhs
e) Surge Arrestors 120 kV for NGR INR Lakhs
f) Spares for NGR &120KV SA INR Lakhs
3 Bus Reactor a) 125 MVAR 400 kV INR Lakhs b) 80 MVAR 400 kV INR Lakhs
c) 63 / 50 MVAR 400 kV INR Lakhs
d) 50 MVAR INR Lakhs
e) Oil for shunt Reactor INR Lakhs
f) Spares for Bus Reactor INR Lakhs
4 420 kV Equipments
ICT 400/√3/220 √3/ 33KV,167 MVA, single phase autotransformer including Insulating Oil Frieght & Insurance
I.C.T 315 MVA, 3 Phase, 400/220/33 KV including including Insulating Oil Frieght & Insurance
ICT 400/√3/220 √3/ 33KV,105 MVA, single phase autotransformer including Insulating Oil Frieght & Insurance
I.C.T 250 MVA, 3 Phase, 400/220/33 KV including including Insulating Oil Frieght & Insurance
a) 420 kV Breakers with CR INR Lakhs
b) 420 kVBreakers without CR INR Lakhs
c) 420 kV CTs 2000A, 40KA, 5-Core, INR Lakhs
d) 420 kv CVT 4400 PF INR Lakhs
e) 420 kv CVT 8800 PF INR Lakhs
f) INR Lakhs
g) 420 KV,2000A,40 kA Isolators 3-Phase with two E/S with insulators INR Lakhs
h) 420 KV,2000A,40 kA Isolators one Phase with one E/S INR Lakhs
j) Surge Arrestors 390 kV INR Lakhs
5 400 kV Control and Protection Panel
a) Circuit Breaker panel with Auto Reclose INR Lakhs
b) Circuit Breaker panel without Auto Reclose INR Lakhs
c) Line protection panel INR Lakhs
d) Transformer protection panel(both HV and MV) INR Lakhs
e) Reactor protection panel INR Lakhs
f) Bus Bar Protection Panel INR Lakhs
6 245 kV Equipment a) Circuit Breakers 245 kV
1600 A, 40 kA INR Lakhs
2500 A, 40 kA INR Lakhs
b) Current Transformers 245 kV
1600 A, 40 kA , 5 core, with 120% extended current INR Lakhs
1600 A, 40 kA, 5 core, with 150% extended current INR Lakhs
c) Capacitive Voltage Transformer 245 kV
8800 pf, S- Ph, with 3 secondaries INR Lakhs
4400 pf, S- Ph with 3 secondaries INR Lakhs
d) Isolators 245 kV
1600A, 40 kA, DB Type with two E/S INR Lakhs
1600A, 40 kA, DB Type with one E/S INR Lakhs
1600A, 40 kA, DB, Tandem Type without E/S INR Lakhs2500A, 40 KA, DB Type with Two E/S INR Lakhs
1600A, 40 kA with one E/S S-phase INR Lakhs
1600A, 40 kA without E/S S phase INR Lakhs
e) 216 kV Surge Arrestors
f) 220 kV Control & Potection Panel
Circuit Breaker panel with Auto Reclose INR Lakhs
Circuit Breaker panel without Auto Reclose INR Lakhs
Line protection panel INR Lakhs
Bus Bar Protection panel INR Lakhs
7 Foundations a) ICT -315 MVA INR Lakhs
420 KV,2000 A,40 kA Isolators 3-Phase with one E/S (3 Phase) with insulators
b) ICT -S-ph 167 MVA INR Lakhs
c) Reactors INR Lakhs
d) 400 kV equipments
420 KV Circuit breakers INR Lakhs
420KV Isolators INR Lakhs
420 KV Current Transformers INR Lakhs
420KV CVT INR Lakhs
390KV surge Arrestors INR Lakhs
Towers , Lattice Type INR Lakhs
Lightning cum Lighting Masts INR Lakhs
B.P.I. INR Lakhs
Line( Wave) Traps both for 400 & 220 kV INR Lakhs
e) 220 kV equipments
245 KV Circuit breakers INR Lakhs
245 KV Isolators INR Lakhs
245 KV Current Transformers INR Lakhs
245 KV CVT INR Lakhs
216 KV surge Arrestors INR Lakhs
Towers , Lattice Type INR Lakhs
BPI INR Lakhs
f) L.T Transformers INR Lakhs
8 Firewalls for Single Phase ICT & Reactors INR Lakhs
9 Common Equipments a) Control & Relay panel.
INR Lakhs
b) LT Switchgear
800KVA 33/.400 KV Distribution Transformer INR Lakhs
630KVA, 11/400VKV Distribution Transformer INR Lakhs
72.5 kV Isolator with insulators INR Lakhs
72.5KV , 1250A, 25KA Circuit Breaker INR Lakhs
72.5KV, 25KA, 3 Core Current Transformer 3 Nos INR Lakhs
72.5KV, 2 Core, 33kV /√3 / 110 V/√3 CVT / PT INR Lakhs
Relay panel for 800 kVA Transformer on 72.5 kV side INR Lakhs
11KV Horn gap Fuse INR Lakhs
11KV Isolator without ES INR Lakhs
11KV Surge Arrestor. INR Lakhs
415V Main Switch Board INR Lakhs
415V ACDB INR Lakhs
415V MLDB INR Lakhs
415V Emergency LDB INR Lakhs
220V DCDB INR Lakhs
Complete Substation automation system for 400/230kV S/S including hardware and software for remote control station alongthwith associated equipments and Kiosks for the following bays ( bays) as defined in the teechnical specification, Sec-Substaion Automation
50V DCDB INR Lakhs
b) 220V Battery INR Lakhs
c) 50V Battery INR Lakhs
d) Battery Charger for 220V Battery INR Lakhs
e) Battery Charger for 50V Battery INR Lakhs
f) DG Set-250KVA with control panel INR Lakhs
g) High Wall Type Split AC unit of 2TR Capacity INR Lakhs
h) Illumination(Indoor and Outdoor) INR Lakhs
10 PLCC equipments on 400 kV side (Both for 400 & 220 kV) INR Lakhs
11 Mandatory Spares INR Lakhs
12 Steel Structures - Unit MT a) Lattice Type INR Lakhs
b) Tubular support structures INR Lakhs
13 Earth mat- 40 mm rods - Per kM INR Lakhs
14 Bus Bar Materials
a) 400 kV Switchyard INR Lakhs
A
Moose ACSR
Twin disc Ins. string with Tension Hardware fr Twin Moose
Twin disc Ins. string with Suspension Hardware fr Twin Moose
400KV BPI
Tee Clamp for Twin Moose to 4" IPS Al. Tube
Tee Clamp for Twin Moose to Twin Moose ACSR
PG Clamps
Spacer to Twin Moose ACSR
Ground wire and accessories
b) 220 kV Switchyard INR Lakhs
Quad disc Ins. string with Tension Hardware fr Quad Moose
Twin disc Ins. string with Suspension Hardware fr Quad Moose
Twin disc Ins. string with Tension Hardware fr Twin Moose
Twin disc Ins. string with Suspension Hardware fr Twin Moose
220KV BPI
4" IPS Al. Tube
Moose ACSR
Tee Clamp for Quad Moose to Twin Moose ACSR
Tee Clamp for Twin Moose to Twin Moose ACSR
Tee Clamp for Twin Moose to 4" IPS Al. Tube
Spacer to Quad Moose ACSR
Spacer to Twin Moose ACSR
PG Clamps
Ground wire and accessories
15 Fire fighting Equipment including one 315 MVA Transformer. INR Lakhs
16 Power Cables -- Cost per kM INR Lakhs
17 Control cables --- Cost per kM INR Lakhs
18 Land devolopment & Civil engineering works a) Soil Investigation (lump Sum) INR Lakhs
b) INR Lakhs
c) Ant weed treatment & Site Surfing Cost per Meter INR Lakhs
d) Road work (Cost per Meter) INR Lakhs
e) Storm water drain, Road culverts drain crossing, cable trench crossing INR Lakhs
f) Switch yard fencing INR Lakhs
g) DG room & Fire fighting Room (FFPH) INR Lakhs
h) Control room with cable vaults INR Lakhs
j) Cable ducts INR Lakhs
j) INR Lakhs
k) Parking sheds,Rain water Harvesting systems & land scaping etc. INR Lakhs
19 Erection charges a) Common equipments
INR Lakhs
Station D.C Batteries 220 V, 500 AH INR Lakhs
Station D.C Batteries 50 V, 500 AH INR Lakhs
Battery Charger System 220 V, 70A / 50 A Float cum Boost INR Lakhs
Battery Charger System 50 V, 70 A / 50 A Float cum Boost INR Lakhs
Common equipment pertaining to C&R system.( Automation) INR Lakhs
Power cables INR Lakhs
Control cables INR Lakhs
Earth mat 40 mm Rods ( Main Earth Mat) INR Lakhs
Diesel Generator set with AMF panel 250 kVA INR Lakhs
Air Conditioning and Ventilation INR Lakhs
Fire Fighting System INR Lakhs
Lightning & lightnening masts INR Lakhs
Illumination System - Indoor & outdoor INR Lakhs
b) ICTs ( Power Transformers)
I.C.T 315 MVA, 3Phase, 400/220/33 KV class INR Lakhs
I.C.T 167 MVA, S-Phase, 400/220 kV ( Single Phase 167 MVA Units) INR Lakhs
Intial Civil Engineering Works like Levelling,Retaining walls, Appoach Road, Peripheral Fencing etc. (lump Sum)
Providing water supply including drinking water & water for fire fighting system and sewage system
Auxiliary Transformers,LT Switchgear, AC & DC Panels.72.5 kV ,33kV & 11 kV equipments etc.
c) Shunt & Bus Reactors 400 kV INR Lakhs
d) 400 kV equipments
420 KV Circuit breakers INR Lakhs
420KV Isolators INR Lakhs
420 KV Current Transformers INR Lakhs
420KV CVT INR Lakhs
390KV surge Arrestors INR Lakhs
Towers , Beams Lattice Type INR Lakhs
Tubular type pipe structures INR Lakhs
Bus Bars formation etc. INR Lakhs
e) Control & Protection panels
400KV CB relay Panel INR Lakhs
400KV Line Protection Panel INR Lakhs
400-220/33KV Transformer Protection Panel INR Lakhs
400KV Reactor Protection Panel INR Lakhs
Duplicate Bus Bar Protection Panel - 400KV INR Lakhs
INR Lakhs
f) 220 kV Equipments INR Lakhs
245 KV Circuit breakers INR Lakhs
245 KV Isolators INR Lakhs
245 KV Current Transformers INR Lakhs
245 KV CVT INR Lakhs
216 KV surge Arrestors INR Lakhs
h) 220 kV Towers & beams INR Lakhs
i) 220 tubular pipe structures INR Lakhs
j) 220 kV Bus Bars formation etc INR Lakhs
k) Control & Protection panels
Circuit breaker relay panel With Auto reclosure INR Lakhs
Line protection panel INR Lakhs
Single Bus Bar protection panel INR Lakhs
PLCC Equipments (Both for 400 kV & 220 kV)
1 2 3 4 5
PGCIL PGCIL PGCIL PGCIL PGCIL
Aug-05 Apr-06 Aug-05 Jan-06 Aug-05
- - - - -
585.90 - 730.44 - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
400/220 kV S/S, ARASUR(New)
400/220 kV S/S AT,ROORKEE
400/220 kV S/S,
PUGALUR(New)
400/220 kV S/S, DAMOH (New)
400/220 kV S/S,
KARAIKUDI(New)
Ref:- LOA-55803-S119A-7/LOA-
1/1986 &1987 Dated 10-03-2006
Ref-C-13901-S919A-3/LOA-I/2198 & 2199 DATED 01/11/2006
Ref:- LOA C-55802-S119A-7/LOA-1/1966 &1967(Proj-1) Dated
24/02/06
Ref:- LOA C-56204-S919A-3/LOA-I/2025 & 2026 DATED:20/04/06
Ref:- LOA C-56301-S919A-3/LOA-II/2128&2129 dated 23-08-2006
- - - 34.83 - 32.70 37.11 30.52 27.44 27.01 5.36 7.85 4.64 5.17 5.09 3.12 6.01 3.01 3.11 3.22 - - - - - 5.93 5.58 6.20 8.15 4.91 6.86 6.78 7.15 9.35 7.51 - - - - - 0.88 1.10 1.65 1.48 0.98
7.59 - 6.46 6.44 5.36 6.28 - 5.23 6.44 5.61 35.67 - 27.21 13.58 13.30 19.71 - 17.01 18.76 17.19 - - - 13.63 12.54 107.73 - 181.78 159.75 96.37
12.02 15.97 14.49 13.19 12.99 12.02 16.80 14.49 13.19 12.99
- -
2.73 3.34 2.30 2.64 2.60
2.84 3.34 2.43 2.69 2.65 - -
- - - - -
2.38 3.56 2.09 2.22 2.18 - -
2.90 3.45 2.85 3.88 2.28
2.46 2.91 2.51 3.29 1.62 2.07 2.39 2.22 3.79 2.52 3.02 3.63 2.99 4.09 2.02 - - - - -
- - - - - 0.38 0.53 0.59 0.55 0.63
- - 6.28 - 5.23 6.44 5.61 6.28 - 5.23 6.44 5.36 24.86 - 18.52 13.58 13.30 65.70 - 111.98 50.22 45.50
15.00
15.00 10.00 - 1.25 0.50 0.10 0.10 0.05 3.00 4.00 0.05 0.50 - 0.50 0.40 0.10 0.10 0.40 2.50 0.40 0.20
1.00
- - - - -
5.28 18.94 7.52 12.21 13.17 4.46 18.11 5.01 10.12 12.74 1.58 - 0.74 0.97 1.08 6.14 - 6.28 5.38 5.40 2.73 - 2.52 2.43 0.90 2.88 - 1.53 2.43 0.90 4.37 - 4.06 6.44 - 0.10 - 0.16 0.13 0.18 0.13 - 0.35 0.54 0.52 0.18 - 0.07 0.11 0.04 9.40 13.05 8.79 11.29 12.85 9.75 6.73 5.78 10.96 12.96 3.08 2.93 2.73 2.76 4.75 1.23 0.79 1.16 0.79 0.86 2.05 1.49 0.97 3.16 2.25
1.52 1.34 0.91 3.16 2.16 6.39 6.17 5.70 4.57 5.11 1.94 1.69 1.41 1.21 1.45 1.50 2.93 3.56 2.35 2.85 1.06 2.26 2.66 1.79 1.83 13.39 17.63 19.62 22.21 24.75 0.36 0.44 0.30 0.32 0.37 - - - - -
- - - - -
- - - - -
0.60 - - - -
0.80 - - - -
6.00 - - - -
160.00 - - - -
180.00 - - - -
180.00 - - - -
75.00 - - - -
1.20 - - - -
1.00 - - - -
2.00 - - - -
70.00 - - - -
0.00 - - - - 0.02 - - - - 0.02 - - - - 0.00 - - - - 56.00 - - - - 100.00 - - - - 90.00 - - - -
5.00 - - - -
30.00 - - - -
2.00 - - - -
0.25 - - - -
0.10 - - - -
0.20 - - - -
0.15 - - - -
7.00 - - - - 4.00 - - - - 6.00 - - - - 15.00 - - - - 0.60 - - - - 0.90 - - - - 8.00 - - - - 0.90 - - - - 10.00 - - - -
6.00 - - - - 6.00 - - - -
4.00 - - - -
0.30 - - - - 0.20 - - - - 0.06 - - - - 0.06 - - - - 0.03 - - - - 6.30 - - - - 2.00 - - - - 15.00 - - - -
0.30 - - - - 0.90 - - - - 0.55 - - - - 0.10 - - - - 1.60 - - - - 1.25 - - - -
0.20 - - - - 0.15 - - - - 0.05 - - - - 0.05 - - - - 0.03 - - - - 6.00 - - - - 3.00 - - - - 16.00 - - - -
0.25 - - - - 0.66 - - - - 2.00 - - - -
6 7 8 9 10
PGCIL PGCIL PGCIL PGCIL PGCIL
Kankroli Kaithal Tirunelveli Shubashgram
Aug-05 May-05 Jun-02 May-05 Sep-03
- - - - -
723.28 - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
400/220 kV S/S AT, WARANGAL
Ref-C-55807-S119A-7/LOA-I-
2020 & 2021 DATED 31/03/2006
C-13502-S919A-3/LOA-I/1905 & 2021
DT: 16/01/2006
C-1128-S948-3/LOA-I/1064 DT: 28/03/2003
C-52705-S919A-3/LOA-II/1842 DT:
02/11/2005
C-42406-S919A-3/LOA-I/1237 & 1238
DT: 30/01/2004
- 40.17 - 31.36 29.44 31.12 46.08 29.73 27.93 27.41 7.12 7.22 3.27 5.14 5.08 4.84 5.21 2.30 4.31 4.07 - - - - - 5.75 7.99 5.91 6.59 7.51 6.83 9.45 7.01 7.72 8.76 - - - - - 0.99 1.44 1.47 1.32 1.50
9.79 10.84 1.44 10.45 2.59 8.17 9.04 1.13 9.73 5.26 18.28 15.03 10.60 17.99 16.90 11.61 12.83 5.21 27.66 9.80 - 13.12 - 13.67 - 68.28 133.64 5.16 210.46 29.66
12.74 12.46 10.92 12.08 12.02 12.74 12.46 10.92 12.08 12.76 - - - -
3.44 3.79 1.81 2.50 2.34
3.51 3.85 1.91 2.50 2.44 - - - - - - - - -
2.53 2.81 1.79 2.50 2.44 - - - -
2.72 3.72 2.88 3.22 3.42
2.33 3.18 2.43 2.80 2.91 1.98 3.40 2.01 2.43 2.42 2.81 3.91 2.93 3.38 3.51 - - - - -
- - - - - 0.52 0.75 0.62 0.60 0.59 - - - - - 9.79 10.84 1.44 10.45 5.26 8.17 9.04 1.14 9.73 2.59 18.28 15.03 9.82 17.99 13.34 47.84 61.22 - 73.68 18.46
- - - - -
- 10.36 7.42 5.60 6.89 3.97 6.21 5.70 3.04 4.95 2.79 0.64 0.85 - 0.70 0.94 5.68 - - - - 0.63 - - - - 0.57 - - - - - - - - - 0.27 0.17 - 0.21 0.09 0.31 - - 0.32 0.57 0.10 - - 0.14 - 11.71 15.76 8.73 13.93 12.75 5.19 6.98 4.23 6.32 6.33 3.46 4.65 1.11 3.37 3.79 1.18 1.58 0.34 0.76 1.25 1.30 4.34 3.07 1.38 1.44
1.06 1.74 1.86 1.25 1.37 5.47 6.38 5.22 5.58 4.57 1.66 1.93 1.22 1.76 1.66 1.20 1.64 1.78 2.46 1.56 1.10 1.50 1.13 1.59 1.10 15.05 19.35 10.81 23.57 12.09 0.41 0.49 - 0.29 - - - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - -
- - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - -
11 12 13 14 15
PGCIL PGCIL PGCIL PGCIL PGCIL
Raigarh Amritsar Fatehabad
Mar-04 Sep-03 Nov-04 Oct-04 Oct-04
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
Kolar,Munirabad & Somanahalli extn
works
Ludhiyana, Extn of Jalandhar &
Malerakotla
C-32306-S919A-3/LOA-I/1424 DT:
11/10/2004
C-21501-S919A-3/LOA-I/1349 & 1350
LTCD/EIC/PGCIL/56004/ONLN /2005/101
C-21702-S919A-3/LOA-I/1759
C-21703-S919A-3/LOA-I/1718
30.67 - - - - 28.10 29.29 33.55 33.91 26.76 4.77 5.50 5.85 6.05 4.73 3.82 4.25 - 5.03 2.88 - - - - - 7.17 9.20 6.10 7.73 8.67 8.27 10.15 - 9.03 10.11 - - 2.03 - - 1.30 1.30 1.36 1.51 1.48
3.50 2.22 - 21.48 8.29 1.94 1.50 - 15.82 8.14 15.68 23.54 - 24.54 20.38 8.56 6.02 - 19.82 20.78 6.42 - - 14.82 13.45 89.02 16.94 - 244.09 107.45
12.19 12.10 14.21 14.72 12.35 12.24 12.10 14.21 14.72 12.35 - - - - -
2.36 2.05 2.96 2.84 2.37
2.40 2.07 - 2.84 2.44 - - - - - - - - - -
2.23 2.32 2.96 2.65 1.90 - - - - -
3.70 3.28 2.89 3.57 3.58
3.15 2.82 2.38 3.07 4.31 2.60 2.53 - 2.94 3.03 3.81 3.77 - 3.65 4.28 - - 1.27 - -
- - 0.86 - - 0.62 0.45 0.69 0.63 0.59 - - - - - 4.23 2.22 - 21.48 8.29 2.33 1.50 - 15.82 8.14 18.44 23.54 - 24.54 20.38 56.00 16.94 - 86.27 55.58
- - - - -
4.59 5.11 - 5.27 6.81 3.71 2.54 - 4.40 4.90 0.61 - - - - - - - - - - - - - - - - - - - - - - - - 0.12 - - - - 0.57 - - - - 0.16 - - - - 14.94 5.62 - 8.78 9.12 6.79 4.35 - 6.34 10.24 3.62 2.11 - 2.27 3.46 0.82 0.55 - 0.51 0.62 1.48 1.23 - 1.89 3.18
1.34 1.16 - 1.52 2.80 6.34 5.22 - 6.59 7.71 1.87 1.19 - 1.79 1.71 1.52 2.08 - 1.77 2.95 1.29 1.18 - 1.52 1.74 13.46 13.00 - 18.78 18.71 0.25 0.30 - - - - - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
16 17 18 19 20
PGCIL PGCIL PGCIL PGCIL PGCIL
Gwalior Patna Narendra Melakottaiyur
Oct-04 Aug-04 Sep-03 Sep-03 May-05
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
Muzaffarpur & Biharsheriff
.C-324054-S919-3/LOA-I/1549 DT: 14-
03-05
:C-45907-S919A-3/L0A-I/1708
C-42407-S919A-3/LOA-I/1294
DT: 29/03/2004
C-55102-S919A-3/LOA-1/1208 dt:
31/12/2003:
C-56103-S919A-3/LOA-I/1921
dated 31/01/2006
38.66 39.87 - - - 32.76 29.13 43.36 24.71 39.67 5.84 5.76 5.04 4.55 6.96 4.87 3.74 5.81 2.79 5.05 4.99 - - - - 7.46 8.36 9.01 8.75 8.82 8.68 9.55 - 10.02 10.22 - - - - - 1.46 1.67 2.70 1.78 1.39
20.78 4.26 - 2.67 11.19 15.29 3.22 - 1.94 9.64 23.68 30.32 - 16.37 18.75 19.11 19.17 - 9.38 11.78 14.37 13.52 - - 8.59 234.94 181.96 - 6.18 123.29
14.31 12.62 - 11.79 16.49 14.31 12.62 - 11.79 16.49 - - - - -
2.74 2.83 - 2.05 3.57
2.74 2.99 - 2.47 3.63 - - - - - - - - - -
2.55 2.58 - 1.74 2.76 - - - - -
3.46 3.68 - 3.75 3.88
2.97 3.16 - 3.12 3.36 2.49 2.63 - 2.58 2.87 3.54 3.78 - 3.68 4.06 - - - - -
- - - - - 0.61 0.57 - 0.66 0.72 - - - - - 20.78 4.19 - 2.67 11.19 15.29 3.16 - 1.94 9.64 23.68 29.83 - 15.95 18.75 82.91 90.63 - - 48.51
- - - - -
5.07 4.01 - 7.28 7.28 4.45 3.45 - 7.28 6.34 0.76 1.03 - 3.62 3.98 - - - 0.86 0.82 - - - - - - - - - - - - - - - 0.12 0.57 - - - 0.52 0.56 - 0.27 0.51 0.39 0.31 - 0.40 0.39 8.48 10.68 - 0.12 0.18 6.12 8.32 - 9.88 15.14 2.20 3.55 - 6.79 6.71 0.49 1.28 - 2.70 4.47 1.84 1.96 - 0.60 1.52
1.47 1.86 - 2.36 1.68 6.36 9.85 - 1.70 1.37 1.65 2.99 - 5.37 5.48 1.71 1.75 - 1.53 1.63 1.47 1.30 - 2.15 1.52 18.33 14.68 - 1.50 1.32 0.48 0.31 - 20.06 18.62 - - - 0.38 0.39
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
21 22 23 24 25 26
RVPN APTRANSCO MSETCL MSETCL MSETCL
Oct-07 Mar-08 Jan-09 Oct-07 Oct-07 Aug-05
- - 414.69 - - -
- 790.61 - - - 691.81
- - - 392.75 391.50 -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
NSPCL -Sail power company
for Bilai steel plantJaisalmer -
Rajasthan State
Malkaram -
A.P.TRANSCO
Koradi- Maharastra
Khaparkheda - MSETCL-
Maharastra
Chakan- MSETCL-
Maharastra
NSPCL -Sail power company
for Bilai steel plantRVPN:400 kV
Design/Xtn(Tr)/TN-231/Supply/PO274/D.1236. Jaipur
Dt:22-04-08
OM - 0332 CE/Const./400KV/
SE.PM-II/D2-A1/MLKM/Supply/D. No. 604/2008
Dated - 20/09/2008 -
Supply of Equipments and
Material
REF: TBMS/08/E1036/
PD Rev 01 DT 12.5.09
REF: No.MSETCL/CO/
Tr. Proj./TKP/2007-08/23 DT: 30-11-
07
REF: No.MSETCL/CO/
Tr. Proj./TKP/2007-
08/23 DT: 30-11-07
LOA No.C&M-101-231-080-9-
FC-NOA-6 dated 15.12.2005
- - - 38.21 35.76 37.51 26.61 32.91 24.77 38.21 35.76 33.93 5.15 7.14 5.46 7.26 6.80 6.34 3.60 4.39 3.26 4.65 4.35 5.07 - - - - - - 8.59 6.70 4.59 4.08 - 4.07 9.67 7.92 5.28 5.03 - 4.64 - - 1.53 2.05 - - 1.02 1.30 1.01 1.49 1.39 0.99
13.71 6.70 10.54 - - - - 4.54 - - - - 16.07 14.74 22.18 20.36 16.94 - 16.39 17.87 25.19 26.10 - - 11.10 - - - - - 109.30 44.16 133.58 37.90 35.69 -
11.61 13.98 11.24 16.05 15.02 14.04 - 13.98 - - - 14.05 - - - - - -
- 3.69 3.48 - - -
- - 3.92 4.14 3.87 4.53 - - - - - - - - - - - -
2.50 3.20 - - - 3.40 - - - - - -
4.72 3.67 - - - 3.09
3.80 3.23 3.20 1.67 - 2.53 - - 2.86 1.14 - 2.09 - - - - - 3.14 - - - - - -
- - - - - - 0.32 0.55 0.38 0.51 0.48 0.37 - - - - - - - - - - - - - 4.34 - - - - 13.71 12.97 17.14 - - - 71.14 74.16 85.51 - - -
- - - - - -
13.12 7.97 - - - 5.11 10.44 6.99 10.09 10.09 - 2.54 2.24 0.56 - - - - - - - - - - - 0.84 - - - - - 0.84 - - - - - - - - - - - 0.42 - - - - - - - - - - - 0.48 0.33 0.33 - - 16.65 12.09 - - - 5.62 14.52 11.48 13.26 13.26 - 4.35 4.34 5.02 7.56 7.56 - 2.11 1.11 - 0.65 0.65 - 0.55 3.59 2.80 5.10 5.10 - 1.23
3.45 3.19 3.19 3.19 - 1.16 17.43 10.41 7.50 7.50 - 5.22 3.80 7.92 2.82 2.82 - 1.19 3.70 10.38 3.67 3.67 - 2.08 1.79 3.54 2.86 2.86 - 1.18 17.61 21.18 - - - 13.00 - - - - - 0.30 - - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
27 28 29 30 31 32
PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL
GIS New Delhi Gwalior
Dec-07 Dec-06 Jul-07 Jul-07 Aug-04 Aug-04
- - - - - -
800.83 896.00 837.75 870.00 533.32 530.36
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
Shulajpur(New), Dehgam & VAPI
(Extn Works)
Mandola,Malerakotla
Biharsherief, Hyderabad &
Durgapaur
(Extn Works),
GWALIOR, WARDHA,
PUNE, RAIPUR
Pirana,Gwaliar & Bina
55701-S116-3/LOA-1/2582
&2583 Dated 14-07-2008
C-00703 -S-916-3/LOA-
1/2340: DT:18-04-2007
33501-S116-3/LOA-I/2534 DT:
02-05-2008 :
C-33501-S116-3/LOA-1/2534 & 2535 Dt:02-05-
2008
C-41414-S919 A-I/1553 DT:29-03-2005 :
C-32404-S116-3I/1LOA/1582 DT:
24-03-2005 :
- - - - - - - - -
- - - - - -
- - -
-
- - -
- -
-
- - - -
- - - - - - -
-
- - - - - - - - - - - - - - -
- - - - - - - -
-
-
-
-
-
- - - - - -
-
-
-
-
-
-
-
- - - - - - -
-
-
-
-
-
-
-
- - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
33 34 35 36 37 38
PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL
Batapara Amritsar Navi Mumbai Kota Kankroli Ludhiyana
Aug-04 Sep-05 Nov-07 Sep-04 Sep-04 Jul-04
- - - - - -
534.69 708.39 1,023.72 522.40 522.97 544.81
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
C-32404-S116-3I/1LOA/1582
DT: 24-03-2005 :
C-22101-S916-3/LOA/1980 DT:
02-03-2006
C-33402-S119A-3/LOA-II/2472
DT:20/03/2008:
C-13501-S917-3/LOA/1730
C-13501-S917-3/LOA/1730
C-21702-S916-3/LOA/1535 DT:
07-03-2005 :
- - - - - -
39 40 41 42 43 44
PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL
Fathebad Moga Sonepat Khandwa Dehgan
Jul-04 Sep-05 Sep-07 Aug-07 Aug-07 Apr-08
- - - - - -
544.81 - 841.35 - - -
- - - - - -
- 642.70 - - - -
- - - 408.00 412.00 323.25
- - - - - -
- - - - - -
- - - - - 23.72
- - - - - 0.95
- - - - - -
765 kV & 400 kV pooling station- Bihar
sherief (Balia,Phathepur, Agra, Lucknow)
C-21702-S916-3/LOA/1535 DT:
07-03-2005 :
C-22101-S916-3/LOA/1980 DT:
02-03-2006 :
C-14404-S-116-3/C-156/LOA-12462 DT;20-
03-08
C-33601-S117-7/LOA-I/2458 & LOA -II / 2459 DT:05-03-
2008 :
C-33601-S117-7/LOA-I/2458 & LOA -II /
2459 DT:05-03-2008 :
C-14803-S117-3/LOA-1/2708: DT:22-10-2008
:
- - - - - -
45
PGCIL
Ludhiyana
Jul-04
-
-
-
-
-
-
258.00
-
-
-
C-21702-S917-3/LOA/1664 DT: 04-05-
2005 :
-
46 47 48 49 50
PGCIL PGCIL PGCIL PGCIL PGCIL
Udamalpet & Trichi Fathebad Patna Ranchi
Sep-07 Sep-07 Jul-04 Mar-04 Mar-04
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - 228.00 217.25 228.00
354.50 350.90 217.00 205.00 -
- - - 16.60 -
- - - 1.30 -
- - - - -
Trivandrum, & Madurai
C -56401 - S117 - 3 / LOA - 1 / 2478 DT: 25
- 03 - 2008 :
C -56401 - S117 - 3 / LOA - 1 / 2478 DT: 25 -
03 - 2008 :
C-21702-S917-3/LOA/1664 DT: 04-
05-2005
C-45906-S917-3/LOA/1438 DT: 20-10-2004 :
C-45906-S917-3/LOA/1438 DT:
20-10-2004
- - - - -
51 52 53 54 55 56
PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL
Bihar Sharif Shujalpur Kankroli Kota
Mar-04 Dec-07 Jan-05 Sep-04 Apr-08 Apr-08
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - 409.35 408.50
237.25 - - 256.30 - -
- 333.90 234.50 - 320.90 322.25
- 23.30 17.60 - 23.60 23.65
- 0.95 1.60 - 0.95 0.95
- - - - - -
Bihar Sharif,Sasaram &
Ranchi
Gaya, DVC & Maithon
C-45906-S917-3/LOA/1438 DT: 20-10-2004 :
C -33701 - S117 - 3 / P-165/LOA-1/2584 & 2585
DT: 14 - 07 - 2008 :
C-13501-S917-3/LOA/1730 Dt:18-
10-04
C-13501-S917-3/LOA/1730 Dt:18-
10-04
C -47208 - S117 - 3 / LOA - 1 / 2706
DT: 22 -10 - 2008
C -47208 - S117 - 3 / LOA - 1 / 2706
DT: 22 -10 - 2008
- - - - - -
57 58 59 60 61
PGCIL PGCIL PGCIL PGCIL PGCIL
Lucknow Agra Fatepur Balia Allahabad
Apr-08 Apr-08 Apr-08 Apr-08 Dec-06
- - - - -
- - - - -
- - - - -
- - - - -
405.30 404.15 404.15 408.15 -
- - 347.65 - -
- 319.05 - - 312.50
- 23.45 23.45 - -
- 0.95 0.95 - -
- - - - -
C -47208 - S117 - 3 / LOA - 1 / 2706 DT: 22 -10 - 2008
C -47208 - S117 - 3 / LOA - 1 / 2706 DT: 22 -10 - 2008
C -14803 - S117 - 3 / LOA - 1 / 2708
& 2709 DT:22 - 10 - 2008 :
C -14803 - S117 - 3 / LOA - 1 / 2708
& 2709 DT:22 - 10 - 2008 :
C -00704 - S917 - 3 / LOA - 1 / 2365
& 2366 DT: 25 - 06 - 2007
- - - - -
62 63 64 65
PGCIL PGCIL PGCIL PGCIL
Itarsi Vijayawada Rourkela Tiruvanneli
Dec-06 Dec-06 Dec-06 May-05
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
307.00 312.00 316.00 274.85
- - - 16.75
- - - 2.25
- - - -
C -00704 - S917 - 3 / LOA - 1 / 2365
& 2366 DT: 25 - 06 - 2007
C -00704 - S917 - 3 / LOA - 1 / 2365
& 2366 DT: 25 - 06 - 2007
C -00704 - S917 - 3 / LOA - 1 / 2365 & 2366
DT: 25 - 06 - 2007
C-45906-S917-3/L0A/1438
DT:13-06-2005:
- - - -
CERCCapital Cost Benchmarking
Month and Year of Escalation Jan-09
Project Costs (Escalated)1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64
Name of the Utility PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL RVPN APTRANSCO MSETCL MSETCL MSETCL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL PGCIL
Name of sub-station Kankroli Kaithal Tirunelveli Shubashgram Raigarh Amritsar Fatehabad Gwalior Patna Narendra Melakottaiyur Koradi- Maharastra Pirana,Gwaliar & Bina GIS New Delhi Gwalior Batapara Amritsar Navi Mumbai Kota Kankroli Ludhiyana Fathebad Moga Sonepat Khandwa Dehgan Ludhiyana Udamalpet & Trichi Fathebad Patna Ranchi Bihar Sharif Shujalpur Kankroli Kota Gaya, DVC & Maithon Lucknow Agra Fatepur Balia Allahabad Itarsi Vijayawada Rourkela
Month and Year of Commissioning Aug-05 Apr-06 Aug-05 Jan-06 Aug-05 Aug-05 May-05 Jun-02 May-05 Sep-03 Mar-04 Sep-03 Nov-04 Oct-04 Oct-04 Oct-04 Aug-04 Sep-03 Sep-03 May-05 Oct-07 Mar-08 Jan-09 Oct-07 Oct-07 Aug-05 Dec-07 Dec-06 Jul-07 Jul-07 Aug-04 Aug-04 Aug-04 Sep-05 Nov-07 Sep-04 Sep-04 Jul-04 Jul-04 Sep-05 Sep-07 Aug-07 Aug-07 Apr-08 Jul-04 Sep-07 Sep-07 Jul-04 Mar-04 Mar-04 Mar-04 Dec-07 Jan-05 Sep-04 Apr-08 Apr-08 Apr-08 Apr-08 Apr-08 Apr-08 Dec-06 Dec-06 Dec-06 Dec-06
S.No. Name of the Component Unit
1 Power Transformer
a) INR Lakhs - - - - - - - - - - - - - - - - - - - - - - 414.69 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
b) INR Lakhs 692.45 - 863.27 - - 854.81 - - - - - - - - - - - - - - - 712.14 - - - 817.62 797.02 877.07 799.23 829.99 874.30 869.46 876.55 771.40 779.29 780.14 838.52 838.52 - 815.75 - - - - - - - - - - - - - - - - - - - - - - -
c) INR Lakhs - - - - - - - - - - - - - - - - - - - - - - - 382.21 381.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
d) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 699.87 - - - - - - - - - - - - - - - - - - - - - - - -
2 Shunt Reactor a) 420KV, 125 MVAR, 3-Phase Shunt Reactor INR Lakhs 411.75 415.79 307.22 - - - - - - - - - - 389.05 388.24 385.20 384.11 384.11 387.91 - - - - b) 420KV, 80 MVAR, 3-Phase Shunt Reactor INR Lakhs - - - - - - 350.92 357.68 375.38 390.61 - - 382.33 - - - - 330.41 - - - - - c) 420KV, 63/50 MVAR, 3-Phase Shunt Reactor INR Lakhs - - - 397.09 343.71 340.22 333.99 337.51 - - 332.31 345.14 - 304.99 306.27 - 303.23 - - 305.90 300.51 305.41 309.32
d) NGR with oil, for above 400 kV Shunt Reactor INR Lakhs - - 22.54 - - - - 27.33 - - 23.19 25.90 - 22.43 22.48 - 22.29 22.29 - - - - -
e) Surge Arrestors 120 kV for NGR INR Lakhs - - 0.90 - - - - 1.36 - - 0.99 2.35 - 0.99 0.99 - 0.99 0.99 - - - - - f) Spares for NGR &120KV SA INR Lakhs - - - - - - - - - - - - - - - - - - - - - - -
3 Bus Reactor a) 125 MVAR 400 kV INR Lakhs
b) 80 MVAR 400 kV INR Lakhs
c) 63 / 50 MVAR 400 kV INR Lakhs
d) 50 MVAR INR Lakhs
e) Oil for shunt Reactor INR Lakhs
f) Spares for Bus Reactor INR Lakhs
4 420 kV Equipments a) 420 kV Breakers with CR INR Lakhs - - - 35.05 - - 43.78 - 34.18 38.77 35.83 - - - - 43.26 44.65 - - - - - - 36.04 33.73 40.15 b) 420 kVBreakers without CR INR Lakhs 35.01 36.17 32.67 27.61 28.91 33.32 50.22 41.80 30.44 36.10 32.83 38.57 37.49 37.94 29.94 36.66 32.63 57.10 32.54 43.24 25.10 29.48 24.77 36.04 33.73 36.32 c) 420 kV CTs 2000A, 40KA, 5-Core, INR Lakhs 5.74 7.65 4.97 5.20 5.45 7.62 7.87 4.59 5.61 6.69 5.57 7.24 6.54 6.77 5.30 6.53 6.45 6.64 6.00 7.59 4.86 6.40 5.46 6.85 6.41 6.79 d) 420 kv CVT 4400 PF INR Lakhs 3.34 5.86 3.22 3.13 3.45 5.18 5.68 3.23 4.70 5.35 4.46 5.60 - 5.63 3.22 5.45 4.19 7.65 3.68 5.50 3.40 3.93 3.26 4.39 4.10 5.43 e) 420 kv CVT 8800 PF INR Lakhs - - - - - - - - - - - - - - - 5.58 - - - - - - - - - -
f) INR Lakhs 6.35 5.44 6.64 8.20 5.26 6.16 8.71 8.31 7.18 9.89 8.38 12.11 6.82 8.65 9.70 8.35 9.36 11.86 11.52 9.61 8.10 6.00 4.59 3.85 - 4.36
g) INR Lakhs 7.34 6.61 7.65 9.41 8.04 7.31 10.30 9.86 8.41 11.53 9.66 13.37 - 10.10 11.31 9.71 10.69 - 13.19 11.14 9.12 7.09 5.28 4.74 - 4.97
h) 420 KV,2000A,40 kA Isolators one Phase with one E/S INR Lakhs - - - - - - - - - - - - 2.27 - - - - - - - - - 1.53 1.93 - - j) Surge Arrestors 390 kV INR Lakhs 0.94 1.07 1.77 1.49 1.05 1.06 1.57 2.07 1.44 1.97 1.52 1.71 1.52 1.69 1.66 1.63 1.87 3.56 2.34 1.51 0.96 1.16 1.01 1.41 1.31 1.06
5 400 kV Control and Protection Panel
a) Circuit Breaker panel with Auto Reclose INR Lakhs 7.59 - 6.46 6.44 5.36 9.79 10.84 1.44 10.45 2.59 3.50 2.22 - 21.48 8.29 20.78 4.26 - 2.67 11.19 13.71 6.70 10.54 - - - b) Circuit Breaker panel without Auto Reclose INR Lakhs 6.28 - 5.23 6.44 5.61 8.17 9.04 1.13 9.73 5.26 1.94 1.50 - 15.82 8.14 15.29 3.22 - 1.94 9.64 - 4.54 - - - - c) Line protection panel INR Lakhs 35.67 - 27.21 13.58 13.30 18.28 15.03 10.60 17.99 16.90 15.68 23.54 - 24.54 20.38 23.68 30.32 - 16.37 18.75 16.07 14.74 22.18 20.36 16.94 - d) Transformer protection panel(both HV and MV) INR Lakhs 19.71 - 17.01 18.76 17.19 11.61 12.83 5.21 27.66 9.80 8.56 6.02 - 19.82 20.78 19.11 19.17 - 9.38 11.78 16.39 17.87 25.19 26.10 - - e) Reactor protection panel INR Lakhs - - - 13.63 12.54 - 13.12 - 13.67 - 6.42 - - 14.82 13.45 14.37 13.52 - - 8.59 11.10 - - - - - f) Bus Bar Protection Panel INR Lakhs 107.73 - 181.78 159.75 96.37 68.28 133.64 5.16 210.46 29.66 89.02 16.94 - 244.09 107.45 234.94 181.96 - 6.18 123.29 109.30 44.16 133.58 37.90 35.69 -
6 245 kV Equipment a) Circuit Breakers 245 kV
1600 A, 40 kA INR Lakhs 12.87 15.57 15.51 13.28 12.66 13.64 13.58 15.35 13.16 15.83 14.24 15.93 15.88 16.47 13.82 14.40 14.14 - 15.52 17.97 10.95 12.52 11.24 15.14 14.17 15.03 2500 A, 40 kA INR Lakhs 12.87 16.37 15.51 13.28 11.06 13.64 13.58 15.35 13.16 16.80 14.30 15.93 15.88 16.47 13.82 14.40 14.14 - 15.52 17.97 - 12.52 - - - 15.04
b) Current Transformers 245 kV - - - - - - - - - - - - - - - - - - - - - - - -
1600 A, 40 kA , 5 core, with 120% extended current INR Lakhs 2.92 3.26 2.46 2.66 2.21 3.69 4.13 2.55 2.72 3.08 2.76 2.70 3.31 3.18 2.65 2.76 3.17 - 2.70 3.89 - 3.31 3.48 - - - 1600 A, 40 kA, 5 core, with 150% extended current INR Lakhs 3.04 3.26 2.60 2.71 2.26 3.75 4.20 2.68 2.72 3.21 2.80 2.73 - 3.18 2.73 2.76 3.35 - 3.25 3.95 - - 3.92 3.90 3.65 4.85
c) Capacitive Voltage Transformer 245 kV - - - - - - - - - - - - - - - - - - - - - - - - 8800 pf, S- Ph, with 3 secondaries INR Lakhs - - - - - - - - - - - - - - - - - - - - - - - - - - 4400 pf, S- Ph with 3 secondaries INR Lakhs 2.55 3.47 2.24 2.23 1.86 2.71 3.06 2.52 2.72 3.21 2.60 3.05 3.31 2.97 2.13 2.57 2.89 - 2.29 3.01 2.36 2.87 - - - 3.64
d) Isolators 245 kV
1600A, 40 kA, DB Type with two E/S INR Lakhs 3.15 3.40 3.10 3.95 2.25 2.95 4.05 4.05 3.51 4.50 4.32 4.32 3.23 3.99 4.01 3.48 4.12 - 4.94 4.23 4.45 3.29 - - - 3.36 1600A, 40 kA, DB Type with one E/S INR Lakhs 2.67 2.86 2.73 3.35 1.60 2.53 3.47 3.42 3.05 3.83 3.68 3.71 2.66 3.44 4.82 2.99 3.54 - 4.11 3.66 3.58 2.89 3.20 1.58 - 2.75 1600A, 40 kA, DB, Tandem Type without E/S INR Lakhs 2.25 2.35 2.41 3.86 2.48 2.15 3.71 2.83 2.65 3.19 3.04 3.33 - 3.29 3.39 2.51 2.95 - 3.40 3.13 - - 2.86 1.08 - 2.27 2500A, 40 KA, DB Type with Two E/S INR Lakhs 3.28 3.57 3.25 4.17 1.99 3.05 4.26 4.12 3.68 4.62 4.45 4.96 - 4.08 4.79 3.56 4.23 - 4.85 4.43 - - - - - 3.41 1600A, 40 kA with one E/S S-phase INR Lakhs - - - - - - - - - - - - 1.42 - - - - - - - - - - - - - 1600A, 40 kA without E/S S phase INR Lakhs - - - - - - - - - - - - 0.96 - - - - - - - - - - - - -
e) 216 kV Surge Arrestors INR Lakhs 0.41 0.52 0.64 0.56 0.62 0.56 0.82 0.87 0.65 0.77 0.72 0.59 0.77 0.70 0.66 0.61 0.64 - 0.87 0.78 0.30 0.49 0.38 0.48 0.45 0.40 f) 220 kV Control & Potection Panel
Circuit Breaker panel with Auto Reclose INR Lakhs 6.28 - 5.23 6.44 5.61 9.79 10.84 1.44 10.45 5.26 4.23 2.22 - 21.48 8.29 20.78 4.19 - 2.67 11.19 - - - - - - Circuit Breaker panel without Auto Reclose INR Lakhs 6.28 - 5.23 6.44 5.36 8.17 9.04 1.14 9.73 2.59 2.33 1.50 - 15.82 8.14 15.29 3.16 - 1.94 9.64 - 4.34 - - - - Line protection panel INR Lakhs 24.86 - 18.52 13.58 13.30 18.28 15.03 9.82 17.99 13.34 18.44 23.54 - 24.54 20.38 23.68 29.83 - 15.95 18.75 13.71 12.97 17.14 - - - Bus Bar Protection panel INR Lakhs 65.70 - 111.98 50.22 45.50 47.84 61.22 - 73.68 18.46 56.00 16.94 - 86.27 55.58 82.91 90.63 - - 48.51 71.14 74.16 85.51 - - -
7 Foundations a) ICT -315 MVA INR Lakhs 15.00 b) ICT -S-ph 167 MVA INR Lakhs 15.00 c) Reactors INR Lakhs 10.00 d) 400 kV equipments -
420 KV Circuit breakers INR Lakhs 1.25 420KV Isolators INR Lakhs 0.50 420 KV Current Transformers INR Lakhs 0.10 420KV CVT INR Lakhs 0.10 390KV surge Arrestors INR Lakhs 0.05 Towers , Lattice Type INR Lakhs 3.00 Lightning cum Lighting Masts INR Lakhs 4.00 B.P.I. INR Lakhs 0.05 Line( Wave) Traps both for 400 & 220 kV INR Lakhs 0.50
e) 220 kV equipments - 245 KV Circuit breakers INR Lakhs 0.50 245 KV Isolators INR Lakhs 0.40 245 KV Current Transformers INR Lakhs 0.10 245 KV CVT INR Lakhs 0.10 216 KV surge Arrestors INR Lakhs 0.40 Towers , Lattice Type INR Lakhs 2.50 BPI INR Lakhs 0.40
f) L.T Transformers INR Lakhs 0.20
8 Firewalls for Single Phase ICT & Reactors INR Lakhs 1.00
9 Common Equipments a) Control & Relay panel.
INR Lakhs - - - - - - - - - - - - - - - - - - - - - - - - - -
b) LT Switchgear
800KVA 33/.400 KV Distribution Transformer INR Lakhs 6.21 17.98 8.84 12.71 15.48 12.18 9.30 8.57 8.63 7.01 7.33 9.03 - 8.28 10.70 5.28 6.38 - 12.86 9.12 13.12 7.05 - - - 6.01 630KVA, 11/400VKV Distribution Transformer INR Lakhs 5.24 17.19 5.89 10.53 14.98 7.30 7.14 4.66 6.21 4.92 5.92 4.49 - 6.91 7.70 4.64 5.49 - 12.86 7.95 10.10 6.18 10.09 9.77 - 2.99 72.5 kV Isolator with insulators INR Lakhs 1.86 - 0.87 1.01 1.27 0.75 1.07 - 0.88 1.66 0.97 - - - - 0.79 1.64 - 6.39 4.99 2.17 0.50 - - - - 72.5KV , 1250A, 25KA Circuit Breaker INR Lakhs 7.22 - 7.38 5.60 6.35 6.68 - - - - - - - - - - - - 1.52 1.03 - - - - - - 72.5KV, 25KA, 3 Core Current Transformer 3 Nos INR Lakhs 3.64 - 2.96 2.53 0.85 0.74 21.39 - - - - 72.5KV, 2 Core, 33kV /√3 / 110 V/√3 CVT / PT INR Lakhs 3.39 - 1.80 2.53 0.85 0.67 20.31 - - - - Relay panel for 800 kVA Transformer on 72.5 kV side 4.37 - 4.06 6.44 - - - - - - - - - - - - - - - - - - - - - - 11KV Horn gap Fuse INR Lakhs 0.10 - 0.16 0.13 0.18 0.27 0.17 - 0.21 0.09 0.12 - - - - 0.12 0.57 - - - - 0.42 - - - - 11KV Isolator without ES INR Lakhs 0.15 - 0.41 0.63 0.62 0.36 - - 0.38 0.67 0.67 - - - - 0.61 0.66 - 0.32 0.60 - - - - - - 11KV Surge Arrestor. INR Lakhs 0.18 - 0.07 0.11 0.04 0.10 - - 0.14 - 0.16 - - - - 0.39 0.31 - 0.40 0.39 - 0.48 0.33 0.33 - - 415V Main Switch Board INR Lakhs 9.40 13.05 8.79 11.29 12.85 11.71 15.76 8.73 13.93 12.75 14.94 5.62 - 8.78 9.12 8.48 10.68 - 0.12 0.18 16.65 12.09 - - - 5.62 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 415V ACDB INR Lakhs 9.75 6.73 5.78 10.96 12.96 5.19 6.98 4.23 6.32 6.33 6.79 4.35 - 6.34 10.24 6.12 8.32 - 9.88 15.14 14.52 11.48 13.26 13.26 - 4.35 415V MLDB INR Lakhs 3.08 2.93 2.73 2.76 4.75 3.46 4.65 1.11 3.37 3.79 3.62 2.11 - 2.27 3.46 2.20 3.55 - 6.79 6.71 4.34 5.02 7.56 7.56 - 2.11 415V Emergency LDB INR Lakhs 1.23 0.79 1.16 0.79 0.86 1.18 1.58 0.34 0.76 1.25 0.82 0.55 - 0.51 0.62 0.49 1.28 - 2.70 4.47 1.11 - 0.65 0.65 - 0.55 220V DCDB INR Lakhs 2.05 1.49 0.97 3.16 2.25 1.30 4.34 3.07 1.38 1.44 1.48 1.23 - 1.89 3.18 1.84 1.96 - 0.60 1.52 3.59 2.80 5.10 5.10 - 1.23 50V DCDB INR Lakhs 1.52 1.34 0.91 3.16 2.16 1.06 1.74 1.86 1.25 1.37 1.34 1.16 - 1.52 2.80 1.47 1.86 - 2.36 1.68 3.45 3.19 3.19 3.19 - 1.16
b) 220V Battery INR Lakhs 6.39 6.17 5.70 4.57 5.11 5.47 6.38 5.22 5.58 4.57 6.34 5.22 - 6.59 7.71 6.36 9.85 - 1.70 1.37 17.43 10.41 7.50 7.50 - 5.22 c) 50V Battery INR Lakhs 1.94 1.69 1.41 1.21 1.45 1.66 1.93 1.22 1.76 1.66 1.87 1.19 - 1.79 1.71 1.65 2.99 - 5.37 5.48 3.80 7.92 2.82 2.82 - 1.19 d) Battery Charger for 220V Battery INR Lakhs 1.50 2.93 3.56 2.35 2.85 1.20 1.64 1.78 2.46 1.56 1.52 2.08 - 1.77 2.95 1.71 1.75 - 1.53 1.63 3.70 10.38 3.67 3.67 - 2.08 e) Battery Charger for 50V Battery INR Lakhs 1.06 2.26 2.66 1.79 1.83 1.10 1.50 1.13 1.59 1.10 1.29 1.18 - 1.52 1.74 1.47 1.30 - 2.15 1.52 1.79 3.54 2.86 2.86 - 1.18 f) DG Set-250KVA with control panel INR Lakhs 13.39 17.63 19.62 22.21 24.75 15.05 19.35 10.81 23.57 12.09 13.46 13.00 - 18.78 18.71 18.33 14.68 - 1.50 1.32 17.61 21.18 - - - 13.00
g) High Wall Type Split AC unit of 2TR Capacity INR Lakhs 0.36 0.44 0.30 0.32 0.37 0.41 0.49 - 0.29 - 0.25 0.30 - - - 0.48 0.31 - 20.06 18.62 - - - - - 0.30
h) Illumination(Indoor and Outdoor) INR Lakhs - - - - - - - - - - - - - - - - - - 0.38 0.39 - - - - - -
10 INR Lakhs - - - - - - - - - - - - - - - - - - - - - - - - - -
11 Mandatory Spares INR Lakhs - - - - - - - - - - - - - - - - - - - - - - - - - -
12 Steel Structures - Unit MT a) Lattice Type INR Lakhs 0.60 b) Tubular support structures INR Lakhs 0.80
13 Earth mat- 40 mm rods - Per kM INR Lakhs 6.00
14 Bus Bar Materials a) 400 kV Switchyard INR Lakhs 160.00
Moose ACSR
Twin disc Ins. string with Tension Hardware fr Twin Moose
Twin disc Ins. string with Suspension Hardware fr Twin Moose
400KV BPI
Tee Clamp for Twin Moose to 4" IPS Al. Tube
Tee Clamp for Twin Moose to Twin Moose ACSR
PG Clamps
Spacer to Twin Moose ACSR
Ground wire and accessories
b) 220 kV Switchyard INR Lakhs 180.00
15 INR Lakhs 75.00
16 Power Cables -- Cost per kM INR Lakhs 1.20
17 Control cables --- Cost per kM INR Lakhs 0.98
18 Land devolopment & Civil engineering works
a) Soil Investigation (lump Sum) INR Lakhs 2.00
b) INR Lakhs 70.00
c) Ant weed treatment & Site Surfing Cost per Meter INR Lakhs 0.00 d) Road work (Cost per Meter) INR Lakhs 0.02
e) INR Lakhs 0.02
f) Switch yard fencing INR Lakhs 0.00 g) DG room & Fire fighting Room (FFPH) INR Lakhs 56.00 h) Control room with cable vaults INR Lakhs 100.00 j) Cable ducts INR Lakhs 90.00
j) INR Lakhs 5.00
k) INR Lakhs 30.00
NSPCL -Sail power company for Bilai
steel plant
400/220 kV S/S, ARASUR(New)
400/220 kV S/S AT,ROORKEE
400/220 kV S/S,
PUGALUR(New)
400/220 kV S/S, DAMOH (New)
400/220 kV S/S,
KARAIKUDI(New)
400/220 kV S/S AT, WARANGAL
Kolar,Munirabad & Somanahalli extn
works
Ludhiyana, Extn of Jalandhar &
Malerakotla
Muzaffarpur & Biharsheriff
Jaisalmer -Rajasthan State
Malkaram -
A.P.TRANSCO
Khaparkheda - MSETCL- Maharastra
Chakan- MSETCL- Maharastra
NSPCL -Sail power company for Bilai
steel plant
Shulajpur(New), Dehgam & VAPI
(Extn Works)
Mandola,Malerakotla
Biharsherief, Hyderabad &
Durgapaur
(Extn Works), GWALIOR, WARDHA,
PUNE, RAIPUR
765 kV & 400 kV pooling station- Bihar
sherief (Balia,Phathepur, Agra,
Lucknow)
Trivandrum, & Madurai
Bihar Sharif,Sasaram & Ranchi
ICT 400/√3/220 √3/ 33KV,167 MVA, single phase autotransformer including Insulating Oil Frieght & Insurance
I.C.T 315 MVA, 3 Phase, 400/220/33 KV including including Insulating Oil Frieght & Insurance
ICT 400/√3/220 √3/ 33KV,105 MVA, single phase autotransformer including Insulating Oil Frieght & Insurance
I.C.T 250 MVA, 3 Phase, 400/220/33 KV including including Insulating Oil Frieght & Insurance
420 KV,2000 A,40 kA Isolators 3-Phase with one E/S (3 Phase) with insulators
420 KV,2000A,40 kA Isolators 3-Phase with two E/S with insulators
Complete Substation automation system for 400/230kV S/S including hardware and software for remote control station alongthwith associated equipments and Kiosks for the following bays ( bays) as defined in the teechnical specification, Sec-Substaion Automation
PLCC equipments on 400 kV side (Both for 400 & 220 kV)
Fire fighting Equipment including one 315 MVA Transformer.
Intial Civil Engineering Works like Levelling,Retaining walls, Appoach Road, Peripheral Fencing etc. (lump Sum)
Storm water drain, Road culverts drain crossing, cable trench crossing
Providing water supply including drinking water & water for fire fighting system and sewage system
Parking sheds,Rain water Harvesting systems & land scaping etc.
19 Erection charges
a) Common equipments
INR Lakhs 2.00
Station D.C Batteries 220 V, 500 AH INR Lakhs 0.25 Station D.C Batteries 50 V, 500 AH INR Lakhs 0.10
Battery Charger System 220 V, 70A / 50 A Float cum Boost INR Lakhs 0.20
Battery Charger System 50 V, 70 A / 50 A Float cum Boost INR Lakhs 0.15
Common equipment pertaining to C&R system.( Automation) INR Lakhs 7.00
Power cables INR Lakhs 4.00 Control cables INR Lakhs 6.00 Earth mat 40 mm Rods ( Main Earth Mat) INR Lakhs 15.00 Diesel Generator set with AMF panel 250 kVA INR Lakhs 0.60 Air Conditioning and Ventilation INR Lakhs 0.90 Fire Fighting System INR Lakhs 8.00 Lightning & lightnening masts INR Lakhs 0.90 Illumination System - Indoor & outdoor INR Lakhs 10.00
b) ICTs ( Power Transformers) - I.C.T 315 MVA, 3Phase, 400/220/33 KV class INR Lakhs 6.00
INR Lakhs 6.00
c) Shunt & Bus Reactors 400 kV INR Lakhs 4.00 d) 400 kV equipments -
420 KV Circuit breakers INR Lakhs 0.30 420KV Isolators INR Lakhs 0.20 420 KV Current Transformers INR Lakhs 0.06 420KV CVT INR Lakhs 0.06 390KV surge Arrestors INR Lakhs 0.03 Towers , Beams Lattice Type INR Lakhs 6.30 Tubular type pipe structures INR Lakhs 2.00 Bus Bars formation etc. INR Lakhs 15.00
e) Control & Protection panels - 400KV CB relay Panel INR Lakhs 0.30 400KV Line Protection Panel INR Lakhs 0.90 400-220/33KV Transformer Protection Panel INR Lakhs 0.55 400KV Reactor Protection Panel INR Lakhs 0.10 Duplicate Bus Bar Protection Panel - 400KV INR Lakhs 1.60 PLCC Equipments (Both for 400 kV & 220 kV) INR Lakhs 1.25
f) 220 kV Equipments - 245 KV Circuit breakers INR Lakhs 0.20 245 KV Isolators INR Lakhs 0.15 245 KV Current Transformers INR Lakhs 0.05 245 KV CVT INR Lakhs 0.05 216 KV surge Arrestors INR Lakhs 0.03
h) 220 kV Towers & beams INR Lakhs 6.00 i) 220 tubular pipe structures INR Lakhs 3.00 j) 220 kV Bus Bars formation etc INR Lakhs 16.00 k) Control & Protection panels -
Circuit breaker relay panel With Auto reclosure INR Lakhs 0.25 Line protection panel INR Lakhs 0.66 Single Bus Bar protection panel INR Lakhs 2.00
Auxiliary Transformers,LT Switchgear, AC & DC Panels.72.5 kV ,33kV & 11 kV equipments etc.
I.C.T 167 MVA, S-Phase, 400/220 kV ( Single Phase 167 MVA Units)
65
PGCIL
Tiruvanneli
May-05
-
-
-
-
- - 347.22
21.16
2.35 -
CERCCapital Cost Benchmarking
Average Rates
S.No. Name of the Component Unit Final Rates
1 Power Transformer
a) INR Lakhs 414.69
b) INR Lakhs 815.97
c) INR Lakhs 381.60
d) INR Lakhs 699.87
- 2 Shunt Reactor -
a) 420KV, 125 MVAR, 3-Phase Shunt Reactor INR Lakhs 383.71 b) 420KV, 80 MVAR, 3-Phase Shunt Reactor INR Lakhs 364.55 c) 420KV, 63/50 MVAR, 3-Phase Shunt Reactor INR Lakhs 327.52 d) NGR with oil, for above 400 kV Shunt Reactor INR Lakhs 23.29 e) Surge Arrestors 120 kV for NGR INR Lakhs 1.33 f) Spares for NGR &120KV SA INR Lakhs -
3 Bus Reactor a) 125 MVAR 400 kV INR Lakhs
b) 80 MVAR 400 kV INR Lakhs
c) 63 / 50 MVAR 400 kV INR Lakhs
d) 50 MVAR INR Lakhs
e) Oil for shunt Reactor INR Lakhs
f) Spares for Bus Reactor INR Lakhs
4 420 kV Equipments a) 420 kV Breakers with CR INR Lakhs 38.54 b) 420 kVBreakers without CR INR Lakhs 35.25 c) 420 kV CTs 2000A, 40KA, 5-Core, INR Lakhs 6.26 d) 420 kv CVT 4400 PF INR Lakhs 4.52 e) 420 kv CVT 8800 PF INR Lakhs 5.58
f) INR Lakhs 7.82
ICT 400/√3/220 √3/ 33KV,167 MVA, single phase autotransformer including Insulating Oil Frieght & Insurance
I.C.T 315 MVA, 3 Phase, 400/220/33 KV including including Insulating Oil Frieght & Insurance
ICT 400/√3/220 √3/ 33KV,105 MVA, single phase autotransformer including Insulating Oil Frieght & Insurance
I.C.T 250 MVA, 3 Phase, 400/220/33 KV including including Insulating Oil Frieght & Insurance
420 KV,2000 A,40 kA Isolators 3-Phase with one E/S (3 Phase) with insulators
g) INR Lakhs 8.99
h) 420 KV,2000A,40 kA Isolators one Phase with one E/S INR Lakhs 1.91 j) Surge Arrestors 390 kV INR Lakhs 1.55
5 400 kV Control and Protection Panel
a) Circuit Breaker panel with Auto Reclose INR Lakhs 8.32 b) Circuit Breaker panel without Auto Reclose INR Lakhs 6.61 c) Line protection panel INR Lakhs 19.64 d) Transformer protection panel(both HV and MV) INR Lakhs 16.19 e) Reactor protection panel INR Lakhs 12.29 f) Bus Bar Protection Panel INR Lakhs 107.15
6 245 kV Equipment a) Circuit Breakers 245 kV
1600 A, 40 kA INR Lakhs 14.35 2500 A, 40 kA INR Lakhs 14.65
b) Current Transformers 245 kV - 1600 A, 40 kA , 5 core, with 120% extended current INR Lakhs 3.03 1600 A, 40 kA, 5 core, with 150% extended current INR Lakhs 3.25
c) Capacitive Voltage Transformer 245 kV - 8800 pf, S- Ph, with 3 secondaries INR Lakhs 3.10 4400 pf, S- Ph with 3 secondaries INR Lakhs 2.74
d) Isolators 245 kV - 1600A, 40 kA, DB Type with two E/S INR Lakhs 3.76 1600A, 40 kA, DB Type with one E/S INR Lakhs 3.17 1600A, 40 kA, DB, Tandem Type without E/S INR Lakhs 2.81 2500A, 40 KA, DB Type with Two E/S INR Lakhs 3.94 1600A, 40 kA with one E/S S-phase INR Lakhs 1.42 1600A, 40 kA without E/S S phase INR Lakhs 0.96
e) 216 kV Surge Arrestors INR Lakhs 0.61 f) 220 kV Control & Potection Panel -
Circuit Breaker panel with Auto Reclose INR Lakhs 8.02 Circuit Breaker panel without Auto Reclose INR Lakhs 6.45 Line protection panel INR Lakhs 18.18 Bus Bar Protection panel INR Lakhs 63.46
- 7 Foundations -
a) ICT -315 MVA INR Lakhs 15.00 b) ICT -S-ph 167 MVA INR Lakhs 15.00 c) Reactors INR Lakhs 10.00 d) 400 kV equipments
420 KV Circuit breakers INR Lakhs 1.25 420KV Isolators INR Lakhs 0.50 420 KV Current Transformers INR Lakhs 0.10 420KV CVT INR Lakhs 0.10
420 KV,2000A,40 kA Isolators 3-Phase with two E/S with insulators
390KV surge Arrestors INR Lakhs 0.05 Towers , Lattice Type INR Lakhs 3.00 Lightning cum Lighting Masts INR Lakhs 4.00 B.P.I. INR Lakhs 0.05 Line( Wave) Traps both for 400 & 220 kV INR Lakhs 0.50
e) 220 kV equipments
245 KV Circuit breakers INR Lakhs 0.50 245 KV Isolators INR Lakhs 0.40 245 KV Current Transformers INR Lakhs 0.10 245 KV CVT INR Lakhs 0.10 216 KV surge Arrestors INR Lakhs 0.40 Towers , Lattice Type INR Lakhs 2.50 BPI INR Lakhs 0.40
f) L.T Transformers INR Lakhs 0.20
8 Firewalls for Single Phase ICT & Reactors INR Lakhs 1.00
-
9 Common Equipments -
a) Control & Relay panel. -
INR Lakhs 250.00
b) LT Switchgear INR Lakhs 66.21 800KVA 33/.400 KV Distribution Transformer INR Lakhs 9.62 630KVA, 11/400VKV Distribution Transformer INR Lakhs 7.79 72.5 kV Isolator with insulators INR Lakhs 1.79 72.5KV , 1250A, 25KA Circuit Breaker INR Lakhs 5.11 72.5KV, 25KA, 3 Core Current Transformer 3 Nos INR Lakhs 5.35 72.5KV, 2 Core, 33kV /√3 / 110 V/√3 CVT / PT INR Lakhs 4.92 Relay panel for 800 kVA Transformer on 72.5 kV side INR Lakhs 4.96 11KV Horn gap Fuse INR Lakhs 0.21 11KV Isolator without ES INR Lakhs 0.39 11KV Surge Arrestor. INR Lakhs 0.24 415V Main Switch Board INR Lakhs 10.03 415V ACDB INR Lakhs 8.66 415V MLDB INR Lakhs 3.80 415V Emergency LDB INR Lakhs 1.08 220V DCDB INR Lakhs 2.25 50V DCDB INR Lakhs 1.89
b) 220V Battery INR Lakhs 6.45 c) 50V Battery INR Lakhs 2.41 d) Battery Charger for 220V Battery INR Lakhs 2.62 e) Battery Charger for 50V Battery INR Lakhs 1.76 f) DG Set-250KVA with control panel INR Lakhs 20.23
Complete Substation automation system for 400/230kV S/S including hardware and software for remote control station alongthwith associated equipments and Kiosks for the following bays ( bays) as defined in the teechnical specification, Sec-Substaion Automation
g) High Wall Type Split AC unit of 2TR Capacity INR Lakhs 0.34 h) Illumination(Indoor and Outdoor) INR Lakhs 55.00
-
10 INR Lakhs 76.00
-
11 Mandatory Spares INR Lakhs 175.00
-
12 Steel Structures - Unit MT -
a) Lattice Type INR Lakhs 0.60 b) Tubular support structures INR Lakhs 0.80
-
13 Earth mat- 40 mm rods - Per kM INR Lakhs 6.00
-
14 Bus Bar Materials -
a) 400 kV Switchyard INR Lakhs 160.00 A - Moose ACSR - Twin disc Ins. string with Tension Hardware fr Twin Moose -
- 400KV BPI - Tee Clamp for Twin Moose to 4" IPS Al. Tube - Tee Clamp for Twin Moose to Twin Moose ACSR - PG Clamps - Spacer to Twin Moose ACSR - Ground wire and accessories -
b) 220 kV Switchyard INR Lakhs 180.00 Quad disc Ins. string with Tension Hardware fr Quad Moose -
-
Twin disc Ins. string with Tension Hardware fr Twin Moose - -
220KV BPI - 4" IPS Al. Tube - Moose ACSR - Tee Clamp for Quad Moose to Twin Moose ACSR - Tee Clamp for Twin Moose to Twin Moose ACSR - Tee Clamp for Twin Moose to 4" IPS Al. Tube - Spacer to Quad Moose ACSR - Spacer to Twin Moose ACSR - PG Clamps - Ground wire and accessories -
-
15 INR Lakhs 75.00
PLCC equipments on 400 kV side (Both for 400 & 220 kV)
Twin disc Ins. string with Suspension Hardware fr Twin Moose
Twin disc Ins. string with Suspension Hardware fr Quad Moose
Twin disc Ins. string with Suspension Hardware fr Twin Moose
Fire fighting Equipment including one 315 MVA Transformer.
-
16 Power Cables -- Cost per kM INR Lakhs 1.20
- 17 Control cables --- Cost per kM INR Lakhs 0.98
-
18 Land devolopment & Civil engineering works -
a) Soil Investigation (lump Sum) INR Lakhs 2.00
b) INR Lakhs 70.00
c) Ant weed treatment & Site Surfing Cost per Meter INR Lakhs 0.00 d) Road work (Cost per Meter) INR Lakhs 0.02
e) INR Lakhs 0.02
f) Switch yard fencing INR Lakhs 0.00 g) DG room & Fire fighting Room (FFPH) INR Lakhs 56.00 h) Control room with cable vaults INR Lakhs 100.00 j) Cable ducts INR Lakhs 90.00
j) INR Lakhs 5.00
k) INR Lakhs 30.00
- 19 Erection charges - a) Common equipments -
INR Lakhs 2.00
Station D.C Batteries 220 V, 500 AH INR Lakhs 0.25 Station D.C Batteries 50 V, 500 AH INR Lakhs 0.10 Battery Charger System 220 V, 70A / 50 A Float cum Boost INR Lakhs 0.20 Battery Charger System 50 V, 70 A / 50 A Float cum Boost INR Lakhs 0.15 Common equipment pertaining to C&R system.( Automation) INR Lakhs 7.00 Power cables INR Lakhs 4.00 Control cables INR Lakhs 6.00 Earth mat 40 mm Rods ( Main Earth Mat) INR Lakhs 15.00 Diesel Generator set with AMF panel 250 kVA INR Lakhs 0.60 Air Conditioning and Ventilation INR Lakhs 0.90 Fire Fighting System INR Lakhs 8.00 Lightning & lightnening masts INR Lakhs 0.90 Illumination System - Indoor & outdoor INR Lakhs 10.00
b) ICTs ( Power Transformers) - I.C.T 315 MVA, 3Phase, 400/220/33 KV class INR Lakhs 6.00
INR Lakhs 6.00
c) Shunt & Bus Reactors 400 kV INR Lakhs 4.00 d) 400 kV equipments -
420 KV Circuit breakers INR Lakhs 0.30 420KV Isolators INR Lakhs 0.20
Intial Civil Engineering Works like Levelling,Retaining walls, Appoach Road, Peripheral Fencing etc. (lump Sum)
Storm water drain, Road culverts drain crossing, cable trench crossing
Providing water supply including drinking water & water for fire fighting system and sewage system
Parking sheds,Rain water Harvesting systems & land scaping etc.
Auxiliary Transformers,LT Switchgear, AC & DC Panels.72.5 kV ,33kV & 11 kV equipments etc.
I.C.T 167 MVA, S-Phase, 400/220 kV ( Single Phase 167 MVA Units)
420 KV Current Transformers INR Lakhs 0.06 420KV CVT INR Lakhs 0.06 390KV surge Arrestors INR Lakhs 0.03 Towers , Beams Lattice Type INR Lakhs 6.30 Tubular type pipe structures INR Lakhs 2.00 Bus Bars formation etc. INR Lakhs 15.00
e) Control & Protection panels - 400KV CB relay Panel INR Lakhs 0.30 400KV Line Protection Panel INR Lakhs 0.90 400-220/33KV Transformer Protection Panel INR Lakhs 0.55 400KV Reactor Protection Panel INR Lakhs 0.10 Duplicate Bus Bar Protection Panel - 400KV INR Lakhs 1.60 PLCC Equipments (Both for 400 kV & 220 kV) INR Lakhs 1.25
f) 220 kV Equipments - 245 KV Circuit breakers INR Lakhs 0.20 245 KV Isolators INR Lakhs 0.15 245 KV Current Transformers INR Lakhs 0.05 245 KV CVT INR Lakhs 0.05 216 KV surge Arrestors INR Lakhs 0.03
h) 220 kV Towers & beams INR Lakhs 6.00 i) 220 tubular pipe structures INR Lakhs 3.00 j) 220 kV Bus Bars formation etc INR Lakhs 16.00 k) Control & Protection panels -
Circuit breaker relay panel With Auto reclosure INR Lakhs 0.25 Line protection panel INR Lakhs 0.66 Single Bus Bar protection panel INR Lakhs 2.00
414.69
815.97
381.60
699.87
383.71 364.55 327.52 23.29 1.33 -
38.54 35.25 6.26 4.52 5.58
7.82
Average Rate Excluding Taxes
and Duties
8.99
1.91 1.55
8.32 6.61 19.64 16.19 12.29 107.15
14.35 14.65
3.03 3.25
3.10 2.74
3.76 3.17 2.81 3.94 1.42 0.96 0.61
8.02 6.45 18.18 63.46
15.00 15.00 10.00
1.25 0.50 0.10 0.10
0.05 3.00 4.00 0.05 0.50
0.50 0.40 0.10 0.10 0.40 2.50 0.40 0.20
1.00
250.00
66.21 9.62 7.79 1.79 5.11 5.35 4.92 4.96 0.21 0.39 0.24 10.03 8.66 3.80 1.08 2.25 1.89 6.45 2.41 2.62 1.76 20.23
0.34 55.00
76.00
175.00
0.60 0.80
6.00
160.00
180.00
75.00
1.20
0.98
2.00
70.00
0.00 0.02
0.02
0.00 56.00 100.00 90.00
5.00
30.00
2.00
0.25 0.10 0.20 0.15 7.00 4.00 6.00 15.00 0.60 0.90 8.00 0.90 10.00
6.00
6.00
4.00 - 0.30 0.20
0.06 0.06 0.03 6.30 2.00 15.00 - 0.30 0.90 0.55 0.10 1.60 1.25 - 0.20 0.15 0.05 0.05 0.03 6.00 3.00 16.00 - 0.25 0.66 2.00
CERC Capital Cost Benchmarking
S.No Description Unit Rate ALT - 1 ALT - 2 ALT - 3 ALT - 4 ALT - 5 ALT - 6 ALT - 7 ALT - 8 ALT - 9 ALT - 10 ALT - 11 ALT - 12 ALT - 13 ALT - 14 ALT - 15 ALT - 16 ALT - 17 ALT - 18 ALT - 19 ALT - 20 400 kV Line Bay with Shunt Reactor 400kV Line Bay 220KV Line Bay 400 kV Bus Reactor Bay
1 Common General Works Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount Quantity Amount1-A Land devolopment & Civil engineering worksa) Soil Investigation (lump Sum) Lump Sum 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 - - - - - - - - - - - -
b) Lump Sum 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 1.00 70.00 - - - - - - - - - - - -
c) Ant weed treatment & Site Surfing Cost per Meter Sq mt 0.000502 130,600.00 65.55 130,600.00 65.55 109,000.00 54.70 125,200.00 62.84 103,600.00 51.99 103,600.00 51.99 153,000.00 76.79 176,400.00 88.53 238,800.00 119.85 173,800.00 87.23 125,200.00 62.84 114,400.00 57.42 114,400.00 57.42 173,800.00 87.23 130,600.00 65.55 103,600.00 51.99 114,200.00 57.31 238,800.00 119.85 100,980.00 50.68 100,980.00 50.68 - - - - - - - - - - - -
e) Road work (Cost per Meter) Metre 0.02 2,900.00 52.82 2,900.00 52.82 2,900.00 52.82 2,900.00 52.82 1,700.00 30.96 1,700.00 30.96 3,360.00 61.20 3,500.00 63.75 3,750.00 68.30 3,360.00 61.20 1,700.00 30.96 1,700.00 30.96 1,700.00 30.96 3,360.00 61.20 2,900.00 52.82 1,700.00 30.96 1,700.00 30.96 6,000.00 109.28 2,217.60 40.39 1,663.20 30.29 30.00 0.55 30.00 0.55 20.00 0.36 90.00 1.64 - - 30.00 0.55
d) Metre 0.02 2,120.00 33.07 2,120.00 33.07 2,120.00 33.07 2,120.00 33.07 2,000.00 31.20 2,000.00 31.20 2,520.00 39.31 2,720.00 42.43 4,487.45 70.00 2,520.00 39.31 2,000.00 31.20 2,000.00 31.20 2,000.00 31.20 2,520.00 39.31 2,120.00 33.07 2,000.00 31.20 2,000.00 31.20 7,000.00 109.19 1,663.20 25.94 1,247.40 19.46 30.00 0.47 30.00 0.47 20.00 0.31 90.00 1.40 - - 30.00 0.47
e) Switch yard fencing Metre 0.00 2,052.00 1.48 2,052.00 1.48 2,052.00 1.48 1,944.00 1.40 1,836.00 1.32 1,836.00 1.32 2,164.00 1.56 2,632.00 1.90 2,944.00 2.12 2,268.00 1.63 1,944.00 1.40 1,890.00 1.36 1,890.00 1.36 2,268.00 1.63 2,052.00 1.48 1,836.00 1.32 1,890.00 1.36 2,496.00 1.80 1,428.24 1.03 1,428.00 1.03 - - - - - - - - - - - -
f) DG room & Fire fighting Room (FFPH) No 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 1.00 56.00 - - - - - - - - - - - -
g) Control room with cable vaults No 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 1.00 100.00 - - - - - - - - - - - -
h) Cable ducts Lump Sum 90.00 0.90 81.00 1.05 94.50 1.00 90.00 1.00 90.00 0.85 76.50 0.85 76.50 1.20 108.00 1.25 112.50 1.50 135.00 1.20 108.00 0.78 70.20 0.78 70.20 0.85 76.50 1.30 117.00 1.23 110.70 0.85 76.50 0.85 76.50 1.50 135.00 0.60 54.00 0.50 45.00 - - - - - - - - - - - -
i) Lump Sum 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 1.00 5.00 - - - - - - - - - - - -
j) Lump Sum 30.00 1.00 30.00 1.00 30.00 1.00 30.00 1.00 30.00 1.00 30.00 1.00 30.00 1.10 33.00 1.10 33.00 1.10 33.00 1.10 33.00 1.00 30.00 1.00 30.00 1.00 30.00 1.10 33.00 1.00 30.00 1.00 30.00 1.00 30.00 1.00 30.00 1.00 30.00 1.00 30.00 - - - - - - - - - - - -
Sub-Total -1-A INR Lakhs 466.91 480.41 465.07 473.12 424.98 424.98 519.85 542.10 628.27 530.37 429.60 424.14 430.44 539.37 496.61 424.98 430.34 708.12 435.04 409.46 1.01 1.01 0.68 3.04 - 1.01
1-B Electrical worksa) A.C.Supply
i Set 66.21
1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 1.00 66.21 - - - - - - - - - - - -
ii LumpSum 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 1.00 0.20 - - - - - - - - - - - -
b) Station D.C Batteries 220 V, 500 AH Set 6.45 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 2.00 12.90 1.00 6.45 1.00 6.45 - - - - - - - - - - - -
c) Station D.C Batteries 50 V, 500 AH Set 2.41 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 2.00 4.83 1.00 2.41 1.00 2.41 - - - - - - - - - - - -
d) Set 2.62 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 2.00 5.24 1.00 2.62 1.00 2.62 - - - - - - - - - - - -
e) Set 1.76 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 2.00 3.51 1.00 1.76 1.00 1.76 - - - - - - - - - - - -
f) Set 250.00 1.364 341.00 1.516 379.00 1.668 417.00 1.38 345.00 1.15 288.00 1.08 269.00 1.74 436.00 1.72 430.00 2.76 690.00 1.97 493.00 1.08 269.00 1.15 288.00 1.00 250.00 1.97 493.00 1.81 453.00 1.00 250.00 1.15 288.00 2.816 704.00 1.00 250.00 1.00 250.00 0.15 38.00 0.15 38.00 0.08 19.00 0.23 57.00 0.08 19.00 0.15 38.00
g) Power Cables Km 1.20 44.50 53.40 44.50 53.40 48.60 58.32 40.10 48.12 34.00 40.80 30.60 36.72 51.18 61.42 72.00 86.40 121.50 145.80 61.40 73.68 30.60 36.72 30.60 36.72 30.60 36.72 86.00 103.20 56.14 67.37 34.00 40.80 34.00 40.80 121.50 145.80 25.59 30.71 19.19 23.03 4.00 4.80 2.50 3.00 2.00 2.40 4.50 5.40 2.50 3.00 4.00 4.80
h) Control Cables Km 0.98 90.00 87.94 90.00 87.94 106.00 103.57 76.50 74.75 61.00 59.60 51.85 50.66 108.00 105.53 143.00 139.73 238.50 233.04 140.40 137.19 55.00 53.74 55.00 53.74 51.85 50.66 200.00 195.42 115.00 112.37 61.00 59.60 61.00 59.60 238.50 233.04 54.00 52.76 40.50 39.57 8.00 7.82 5.00 4.89 4.00 3.91 9.00 8.79 8.00 7.82 8.00 7.82 J Earth mat - 40mm dia MS rods Km 6.00 27.70 166.20 27.70 166.20 27.70 166.20 26.59 159.54 22.00 132.00 22.00 132.00 32.50 195.00 37.50 225.00 60.70 364.20 37.86 227.16 26.59 159.54 24.30 145.80 24.29 145.74 36.90 221.40 27.70 166.20 22.00 132.00 24.29 145.74 50.80 304.80 21.44 128.66 16.08 96.50 1.50 9.00 1.50 9.00 0.40 2.40 2.70 16.20 1.70 10.20 1.70 10.20 k) Diesel Generator set along with AMF panel 250 kVA Set 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 1.00 20.23 - - - - - - - - - - - -
l) No. 0.34 12.00 4.02
12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 12.00 4.02 1.00 0.34 1.00 0.34 - - - - - - - - - - - -
m) Fire fighting system 1.00 75.00 1.00 75.00 1.13 84.75 1.27 95.25 1.13 84.75 1.13 84.75 1.00 75.00 1.13 84.75 1.47 110.25 2.00 150.00 1.25 93.75 1.07 80.25 1.06 79.50 1.00 75.00 1.93 144.75 1.33 99.75 1.00 75.00 1.20 90.00 1.40 105.00 1.00 75.00 1.00 75.00 0.07 5.25 - - - - 0.13 9.75 0.10 7.50 0.15 11.25
o) Illumination System - Indoor and Outdoor Lump Sum 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 1.00 55.00 0.66 36.30 0.66 36.30 - - - - - - - - - - - -
p) Mandatory spares Lump Sum 175.00 1.00 175.00 1.20 210.00 1.20 210.00 0.87 152.25 1.20 210.00 1.10 192.50 1.20 210.00 1.50 262.50 2.00 350.00 1.20 210.00 1.20 210.00 1.20 210.00 1.20 210.00 1.20 210.00 1.20 210.00 1.00 175.00 1.20 210.00 2.00 350.00 1.00 175.00 1.00 175.00 - - - - - - - - - - - - Sub Total -1-B INR Lakhs 1,070.69 1,153.44 1,222.49 1,036.56 987.30 928.03 1,264.84 1,426.02 2,105.19 1,406.92 981.40 985.91 940.27 1,539.92 1,280.83 904.55 1,006.29 2,014.79 848.65 795.62 64.87 54.89 27.71 97.14 47.52 72.07
1-C Erection charges
a) Set 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 - - - - - - - - - - - -
b) Station D.C Batteries 220 V, 500 AH Set 0.25 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 2.00 0.50 - - - - - - - - - - - -
c) Station D.C Batteries 50 V, 500 AH Set 0.10 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 2.00 0.21 - - - - - - - - - - - -
d) Set 0.20 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 2.00 0.40 - - - - - - - - - - - -
e) Set 0.15 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 2.00 0.30 - - - - - - - - - - - -
f) Set 7.00
1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 1.00 7.00 0.06 0.42 0.06 0.42 0.06 0.42 0.10 0.70 0.06 0.42 0.06 0.42
g) Power cables Set 4.00 1.00 4.00 1.00 4.00 1.10 4.40 0.90 3.60 0.75 3.00 0.69 2.76 1.15 4.60 1.62 6.48 2.70 10.80 1.38 5.52 0.69 2.76 0.69 2.76 0.69 2.76 1.93 7.72 1.26 5.04 0.75 3.00 0.75 3.00 2.70 10.80 0.58 2.30 0.43 1.73 0.09 0.36 0.06 0.22 0.05 0.18 0.10 0.40 0.09 0.36 0.09 0.36
h) Control cables Set 6.00 1.00 6.00 1.00 6.00 1.18 7.08 0.77 4.62 0.68 4.08 0.58 3.48 1.20 7.20 1.59 9.54 2.65 15.90 1.56 9.36 0.61 3.66 0.61 3.66 0.58 3.48 2.22 13.32 1.28 7.68 0.68 4.08 0.68 4.08 2.65 15.90 0.60 3.60 0.45 2.70 0.09 0.54 0.06 0.34 0.05 0.27 0.10 0.60 0.09 0.54 0.09 0.54
i) Earth mat formation Set 15.00 1.00 15.00 1.00 15.00 1.00 15.00 1.00 15.00 1.00 15.00 1.00 15.00 1.20 18.00 1.50 22.50 2.50 37.50 1.20 18.00 1.00 15.00 1.00 15.00 1.00 15.00 1.20 18.00 1.00 15.00 1.00 15.00 1.10 16.50 2.50 37.50 0.79 11.88 0.59 8.91 0.16 2.40 0.02 0.24 0.05 0.67 0.22 3.30 0.16 2.40 0.16 2.40
j) Diesel Generator set with AMF panel 250 kVA Set 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 1.00 0.60 - - - - - - - - - - - -
k) Air Conditioning and Ventilation Set 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 1.00 0.90 - - - - - - - - - - - -
l) Fire Fighting System Set 8.00 1.00 8.00 1.35 10.80 1.75 14.00 1.35 10.80 1.35 10.80 1.00 8.00 1.35 10.80 1.75 14.00 2.50 20.00 1.35 10.80 1.00 8.00 1.00 8.00 1.00 8.00 1.00 8.00 1.00 8.00 1.00 8.00 1.35 10.80 2.50 20.00 1.00 8.00 1.00 8.00 0.50 4.00 - - - - 0.50 4.00 0.50 4.00 0.50 4.00
n) Illumination System - Indoor & outdoor Set 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 1.00 10.00 0.66 6.60 0.66 6.60 - - - - - - - - - - - -
Sub Total -1-C INR Lakhs 54.91 57.71 62.39 55.93 54.79 51.15 62.51 74.43 106.11 65.59 51.33 51.33 51.15 68.95 57.63 51.99 56.29 106.11 44.29 39.84 7.72 1.22 1.55 9.00 7.72 7.72
Total -1 INR Lakhs 1,592.51 1,691.56 1,749.95 1,565.61 1,467.07 1,404.15 1,847.20 2,042.55 2,839.56 2,002.88 1,462.32 1,461.37 1.00 1,421.85 1.00 2,148.23 1,835.07 1,381.52 1,492.91 2,829.01 1,327.98 1,244.92 73.60 57.12 29.93 109.19 55.24 80.80
2 ICTs
a) I.C.T 315 MVA, 3Phase, 400/220/33 KV class No. 815.97 2.00 1,631.95 2.00 1,631.95 2.00 1,631.95 2.00 1,631.95 2.00 1,631.95 1.00 815.97 2.00 1,631.95 - - - - 2.00 1,631.95 2.00 1,631.95 2.00 1,631.95 1.00 815.97 - - 3.00 2,447.92 2.00 1,631.95 2.00 1,631.95 2.00 1,631.95 - - - - - - - - - - 1.00 815.97 - - - -
b) No. 414.69 - - - - - - - - - - - - - - 4.00 1,658.76 7.00 2,902.83 - - - - - - - - 7.00 2,902.83 - - - - - - - - - - - - - - - - - - - - - - - -
d) Erection Charges Nos 6.00 2.00 12.00 2.00 12.00 2.00 12.00 2.00 12.00 2.00 12.00 1.00 6.00 2.00 12.00 4.00 24.00 7.00 42.00 2.00 12.00 2.00 12.00 2.00 12.00 1.00 6.00 7.00 42.00 3.00 18.00 2.00 12.00 2.00 12.00 2.00 12.00 - - - - - - - - - - 1.00 6.00 - - - -
e) Foundations Nos 15.00 2.00 30.00 2.00 30.00 2.00 30.00 2.00 30.00 2.00 30.00 1.00 15.00 2.00 30.00 4.00 60.00 7.00 105.00 2.00 30.00 2.00 30.00 2.00 30.00 1.00 15.00 7.00 105.00 3.00 45.00 2.00 30.00 2.00 30.00 2.00 30.00 - - - - - - - - - - 1.00 15.00 - - - -
f) Fire wall between the Transformers Nos 1.00 - - - - - - - - - - - - - - 3.00 3.00 4.00 4.00 - - - - - - - - 4.00 4.00 1.00 1.00 - - - - - - - - - - - - - - - - - - - - - -
Total -2 INR Lakhs 1,673.95 1,673.95 1,673.95 1,673.95 1,673.95 836.97 1,673.95 1,745.76 3,053.83 1,673.95 1,673.95 1,673.95 836.97 3,053.83 2,511.92 1,673.95 1,673.95 1,673.95 - - - - - 836.97 - -
3 Shunt & Bus Reactors Reactors3-A Shunt Reactorsa) Shunt Reactor 420 kV 63/50 MVAR No. 327.52 - - 2.00 655.04 4.00 1,310.08 2.00 655.04 2.00 655.04 2.00 655.04 2.00 655.04 3.00 982.56 5.00 1,637.61 2.00 655.04 1.00 327.52 - - 1.00 327.52 2.00 655.04 2.00 655.04 - - 2.00 655.04 4.00 1,310.08 2.00 655.04 2.00 655.04 1.00 327.52 - - - - - - 1.00 327.52 - -
b) Shunt Reactor 420 kV 80 MVAR No. 364.55 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
c) Shunt Reactor 420 kV 125 MVAR No. 383.71 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
d) NGR,145KV No. 23.29 - - 2.00 46.58 4.00 93.16 2.00 46.58 2.00 46.58 2.00 46.58 2.00 46.58 3.00 69.87 5.00 116.45 2.00 46.58 1.00 23.29 - - 1.00 23.29 2.00 46.58 2.00 46.58 - - 2.00 46.58 4.00 93.16 2.00 46.58 2.00 46.58 1.00 23.29 - - - - - - 1.00 23.29 - -
e) Surge Arrestors 120 kV for NGR No. 1.33 - - 2.00 2.65 4.00 5.31 2.00 2.65 2.00 2.65 2.00 2.65 2.00 2.65 3.00 3.98 5.00 6.63 2.00 2.65 1.00 1.33 - - 1.00 1.33 2.00 2.65 2.00 2.65 - - 2.00 2.65 4.00 5.31 2.00 2.65 2.00 2.65 1.00 1.33 - - - - - - 1.00 1.33 - -
f) Errection Charges Set 4.00 - - 2.00 8.00 4.00 16.00 2.00 8.00 2.00 8.00 2.00 8.00 2.00 8.00 3.00 12.00 5.00 20.00 2.00 8.00 1.00 4.00 - - 1.00 4.00 2.00 8.00 2.00 8.00 - - 2.00 8.00 4.00 16.00 2.00 8.00 2.00 8.00 1.00 4.00 - - - - - - 1.00 4.00 - -
g) Foundation for 400 kV Shunt Reactors with NGR No. 10.00 - - 2.00 20.00 4.00 40.00 2.00 20.00 2.00 20.00 2.00 20.00 2.00 20.00 3.00 30.00 5.00 50.00 2.00 20.00 1.00 10.00 - - 1.00 10.00 2.00 20.00 2.00 20.00 - - 2.00 20.00 4.00 40.00 2.00 20.00 2.00 20.00 1.00 10.00 - - - - - - 1.00 10.00 - -
Sub-Total -3-A INR Lakhs - 732.27 1,464.55 732.27 732.27 732.27 732.27 1,098.41 1,830.69 732.27 366.14 - 366.14 732.27 732.27 - 732.27 1,464.55 732.27 732.27 366.14 - - - 366.14 -
3-B Bus Reactorsa) Bus Reactor, 420KV, 63 / 50 MVAR No. 327.52 - - - - - - - - - - - - - - - - - - 2.00 655.04 - - - 1.00 327.52 2.00 655.04 1.00 327.52 - - 1.00 327.52 2.00 655.04 - - - - - - - - - - - - - - 1.00 327.52
b) Bus Reactor, 420KV, 80 MVAR No. 364.55 - - - - - - - - - - - 1.00 364.55 - - - - - - 1.00 364.55 1.00 364.55 - - - - - -
c) Bus Reactor, 420KV, 125 MVAR No. 383.71 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
d) Errection Charges No. 4.00 - - - - - - - - - - - - - - - - - - 2.00 8.00 - - 1.00 4.00 1.00 4.00 2.00 8.00 1.00 4.00 - - 1.00 4.00 2.00 8.00 1.00 4.00 1.00 4.00 - - - - - - - - - - 1.00 4.00
e) Foundation for 400 kV Bus Reactors No. 10.00 - - - - - - - - - - - - - - - - - - 2.00 20.00 - - 1.00 10.00 1.00 10.00 2.00 20.00 1.00 10.00 - - 1.00 10.00 2.00 20.00 1.00 10.00 1.00 10.00 - - - - - - - - - - 1.00 10.00
Sub-Total -3-B INR Lakhs - - - - - - - - - 683.04 - 378.55 341.52 683.04 341.52 - 341.52 683.04 378.55 378.55 - - - - - 341.52
Total -3 INR Lakhs - 732.27 1,464.55 732.27 732.27 732.27 732.27 1,098.41 1,830.69 1,415.32 366.14 378.55 707.66 1,415.32 1,073.80 - 1,073.80 2,147.59 1,110.83 1,110.83 366.14 - - - 366.14 341.52
4 400 kV Bays & Equipments4-A 400 KV Equipments a) No. 38.54 - - - - - - - - - - - - - - 7.00 269.80 9.00 346.89 - - - - - - - - - - - - - - - - 20.00 770.87 11.00 423.98 6.00 231.26 - - - - - - - - - - - -
b) No. 35.25 9.00 317.29 11.00 387.80 13.00 458.31 11.00 387.80 8.00 282.03 7.00 246.78 14.00 493.56 4.00 141.02 13.00 458.31 17.00 599.32 7.00 246.78 8.00 282.03 7.00 246.78 17.00 599.32 14.00 493.56 6.00 211.53 8.00 282.03 9.00 317.29 1.00 35.25 2.00 70.51 1.50 52.88 1.50 52.88 - - 1.50 52.88 1.00 35.25 1.50 52.88
c) No. 6.26 30.00 187.81 30.00 187.81 30.00 187.81 30.00 187.81 18.00 112.69 15.00 93.91 42.00 262.94 27.00 169.03 60.00 375.63 51.00 319.28 18.00 112.69 24.00 150.25 12.00 75.13 48.00 300.50 39.00 244.16 18.00 112.69 24.00 150.25 87.00 544.66 45.00 281.72 30.00 187.81 4.50 28.17 4.50 28.17 - - 4.50 28.17 - - 6.00 37.56
d) CVT - -
i 420 kV CVT 4400 PF No. 4.52 12.00 54.26 12.00 54.26 12.00 54.26 12.00 54.26 6.00 27.13 6.00 27.13 18.00 81.39 12.00 54.26 27.00 122.08 18.00 81.39 6.00 27.13 6.00 27.13 6.00 27.13 18.00 81.39 12.00 54.26 6.00 27.13 6.00 27.13 6.00 27.13 6.00 27.13 6.00 27.13 3.00 13.56 3.00 13.56 - - - - 3.00 13.56 - -
ii 420 kV CVT 8800 PF No. 5.58 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 6.00 33.51 36.00 201.03 21.00 117.27 12.00 67.01 - - - - - - - - - - - -
e) Isolators No. - -
i No. 7.82 22.00 171.94 24.00 187.57 26.00 203.20 24.00 187.57 16.00 125.05 13.00 101.60 32.00 250.09 23.00 179.76 47.00 367.33 40.00 312.62 15.00 117.23 19.00 148.49 15.00 117.23 40.00 312.62 32.00 250.09 14.00 109.42 19.00 148.49 70.00 547.08 32.00 250.09 21.00 164.12 5.00 39.08 4.00 31.26 - - 4.00 31.26 1.00 7.82 5.00 39.08
ii 420 KV,2000A,40 kA Isolator one Phase with one E/S No. - - - - - - - - - - - - - - 8.00 - 14.00 - - - - - - - - - - - - - - - - - - - 2.00 - 2.00 - - - - - - - - - - - - -
iii No. 8.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 2.00 17.99 - - - - - - - - - - - - - - - -
f) Surge Arrestor 390 kV No. 1.55 18.00 27.94 24.00 37.25 30.00 46.56 24.00 37.25 18.00 27.94 18.00 27.94 30.00 46.56 24.00 37.25 48.00 74.50 36.00 55.88 15.00 23.28 15.00 23.28 15.00 23.28 36.00 55.88 30.00 46.56 12.00 18.63 21.00 32.60 60.00 93.13 30.00 46.56 21.00 32.60 6.00 9.31 3.00 4.66 - - 3.00 4.66 3.00 4.66 3.00 4.66
g) PLCC equipments on 400 kV side (Both for 400 & 220 kV) 1.00 76.00 1.71 129.96 1.71 129.96 1.71 129.96 1.42 107.92 1.00 76.00 1.00 76.00 2.13 161.88 2.45 186.20 4.83 367.08 2.13 161.88 1.42 107.92 1.00 76.00 1.00 76.00 2.13 161.88 1.71 129.96 1.00 76.00 1.00 76.00 3.25 247.00 1.41 106.84 1.14 86.64 0.25 19.00 0.25 19.00 - - - - - - - -
Sub Total - 4-A INR Lakhs 940.69 1,036.15 1,131.60 1,014.11 702.33 624.85 1,347.92 1,088.81 2,163.31 1,581.87 686.53 758.68 617.04 1,563.08 1,270.09 606.88 768.00 2,766.18 1,288.85 867.08 162.01 149.54 - 116.97 61.29 134.18
4-B 400 kV Simplex type Panels a) Circuit breaker relay panel With Auto reclosure No. 8.32 7.00 58.21 7.00 58.21 7.00 58.21 7.00 58.21 4.00 33.26 4.00 33.26 10.00 83.15 7.00 58.21 16.00 133.04 10.00 83.15 4.00 33.26 4.00 33.26 4.00 33.26 11.00 91.47 7.00 58.21 4.00 33.26 4.00 33.26 20.00 166.30 11.00 91.47 6.00 49.89 1.50 12.47 1.50 12.47 - - 0.50 4.16 - - - -
b) Circuit breaker relay panel Without Auto reclosure No. 6.61 2.00 13.21 4.00 26.43 4.00 26.43 4.00 26.43 4.00 26.43 3.00 19.82 4.00 26.43 4.00 26.43 7.00 46.25 4.00 26.43 3.00 19.82 4.00 26.43 3.00 19.82 7.00 46.25 7.00 46.25 2.00 13.21 4.00 26.43 9.00 59.46 1.00 6.61 2.00 13.21 - - - - - - 1.00 6.61 1.00 6.61 1.50 9.91
c) Line protection panel No's 19.64 4.00 78.57 4.00 78.57 4.00 78.57 4.00 78.57 2.00 39.28 2.00 39.28 6.00 117.85 4.00 78.57 9.00 176.77 6.00 117.85 2.00 39.28 2.00 39.28 2.00 39.28 6.00 117.85 4.00 78.57 2.00 39.28 2.00 39.28 12.00 235.70 7.00 137.49 4.00 78.57 1.00 19.64 1.00 19.64 - - - - - - - -
d) Reactor protection panel Nos 12.29 - - 2.00 24.59 4.00 49.17 2.00 24.59 2.00 24.59 2.00 24.59 2.00 24.59 3.00 36.88 5.00 61.47 4.00 49.17 1.00 12.29 1.00 12.29 2.00 24.59 4.00 49.17 3.00 36.88 - - 3.00 36.88 6.00 73.76 3.00 36.88 3.00 36.88 1.00 12.29 - - - - - - 1.00 12.29 1.00 12.29
e) Transformer Protection panel for both HV and MV sides No. 16.19 2.00 32.38 2.00 32.38 2.00 32.38 2.00 32.38 2.00 32.38 2.00 32.38 2.00 32.38 1.00 16.19 2.00 32.38 2.00 32.38 2.00 32.38 2.00 32.38 2.00 32.38 2.00 32.38 3.00 48.56 2.00 32.38 2.00 32.38 2.00 32.38 - - - - - - - - - - 1.00 16.19 - - - -
f) Double Bus Bar protection panel No. 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 1.00 107.15 - - - - - - - - - - - - Sub Total - 4-B INR Lakhs 289.51 327.31 351.90 327.31 263.09 256.48 391.54 323.42 557.06 416.13 244.19 250.79 256.48 444.27 375.62 225.29 275.38 674.75 379.60 285.70 44.41 32.11 - 26.95 18.90 22.20
4-C a) Tower Type 4C1 - Number * Unit Weight MT 0.60 25.00 15.00 25.00 15.00 25.00 15.00 25.00 15.00 15.00 9.00 15.00 9.00 35.00 21.00 25.00 15.00 65.00 39.00 35.00 21.00 15.00 9.00 15.00 9.00 15.00 9.00 40.00 24.00 25.00 15.00 15.00 9.00 15.00 9.00 90.00 54.00 45.00 27.00 25.00 15.00 7.50 4.50 7.50 4.50 - - 10.00 6.00 - - - -
b) Tower Type 4C2 - Number * Unit Weight MT 0.60 38.00 22.80 38.00 22.80 38.00 22.80 38.00 22.80 28.50 17.10 19.00 11.40 38.00 22.80 38.00 22.80 36.00 21.60 38.00 22.80 28.50 17.10 28.50 17.10 19.00 11.40 36.00 21.60 45.00 27.00 28.50 17.10 28.50 17.10 28.50 17.10 - - - - - - - - - - 19.00 11.40 - - - -
c) Tower Type 4C3 - Number* Unit Weight MT 0.60 72.00 43.20 72.00 43.20 72.00 43.20 72.00 43.20 38.25 22.95 45.00 27.00 108.00 64.80 72.00 43.20 206.25 123.75 108.00 64.80 40.50 24.30 58.50 35.10 45.00 27.00 136.00 81.60 80.75 48.45 27.00 16.20 40.50 24.30 279.00 167.40 90.00 54.00 76.50 45.90 27.00 16.20 27.00 16.20 - - 21.00 12.60 - - 36.00 21.60
d) Beam Type 4B1 - Number * Unit Weight MT 0.60 16.00 9.60 16.00 9.60 16.00 9.60 16.00 9.60 8.00 4.80 8.00 4.80 24.00 14.40 16.00 9.60 25.00 15.00 24.00 14.40 8.00 4.80 8.00 4.80 8.00 4.80 15.00 9.00 10.00 6.00 8.00 4.80 8.00 4.80 64.00 38.40 28.00 16.80 16.00 9.60 4.00 2.40 4.00 2.40 - - 4.00 2.40 - - - -
e) Beam Type 4B2 - Number * Unit Weight MT 0.60 73.50 44.10 73.50 44.10 73.50 44.10 73.50 44.10 49.00 29.40 38.50 23.10 101.50 60.90 70.00 42.00 90.00 54.00 101.50 60.90 49.00 29.40 63.00 37.80 38.50 23.10 85.25 51.15 58.50 35.10 42.00 25.20 52.50 31.50 203.00 121.80 56.00 33.60 45.50 27.30 14.00 8.40 14.00 8.40 - - 24.50 14.70 - - 14.00 8.40
f) MT 0.60
45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 45.00 27.00 27.00 16.20 27.00 16.20 - - - - - - - - - - - -
g) Equipment Support Structure - Number * Unit Weight MT 0.60 28.20 16.92 28.20 16.92 30.00 18.00 28.20 16.92 16.80 10.08 15.00 9.00 43.20 25.92 28.20 16.92 63.00 37.80 48.60 29.16 16.80 10.08 20.40 12.24 13.20 7.92 48.60 29.16 35.40 21.24 16.80 10.08 20.40 12.24 88.20 52.92 48.00 28.80 30.00 18.00 6.60 3.96 6.60 3.96 - - 1.50 0.90 - - 3.60 2.16 Sub Total - 4-C INR Lakhs 178.62 178.62 179.70 178.62 120.33 111.30 236.82 176.52 318.15 240.06 121.68 143.04 110.22 243.51 179.79 109.38 125.94 478.62 176.40 132.00 35.46 35.46 - 48.00 - 32.16
4-D a) CVT - Number * Unit Weight No/MT18*0.5MT 0.80 10.80 8.64 10.80 8.64 10.80 8.64 10.80 8.64 7.20 5.76 7.20 5.76 14.40 11.52 10.80 8.64 4.50 3.60 14.40 11.52 7.20 5.76 7.20 5.76 7.20 5.76 12.00 9.60 9.00 7.20 7.20 5.76 7.20 5.76 25.20 20.16 16.20 12.96 10.80 8.64 1.80 1.44 1.80 1.44 - - - - - - - -
b) BPI - Number * Unit Weight No/MT63*0.5MT 0.80 37.80 30.24 37.80 30.24 37.80 30.24 37.80 30.24 18.00 14.40 16.80 13.44 59.40 47.52 59.40 47.52 78.00 62.40 59.40 47.52 18.00 14.40 21.60 17.28 18.00 14.40 49.50 39.60 34.50 27.60 18.00 14.40 25.20 20.16 64.80 51.84 54.00 43.20 27.00 21.60 7.20 5.76 7.20 5.76 - - 18.00 14.40 3.60 2.88 18.00 14.40
c) Isolators - Number * Unit Weight No/MT24*2.0MT 0.80 48.00 38.40 52.00 41.60 48.00 38.40 52.00 41.60 36.00 28.80 30.00 24.00 68.00 54.40 66.00 52.80 112.00 89.60 84.00 67.20 34.00 27.20 42.00 33.60 34.00 27.20 84.00 67.20 68.00 54.40 32.00 25.60 42.00 33.60 144.00 115.20 51.00 40.80 34.50 27.60 10.00 8.00 10.00 8.00 - - 10.00 8.00 2.00 1.60 10.00 8.00
d) SA - Number * Unit Weight No/MT18*0.5MT 0.80 10.80 8.64 14.40 11.52 18.00 14.40 14.40 11.52 10.80 8.64 9.00 7.20 18.00 14.40 14.40 11.52 24.00 19.20 21.60 17.28 9.00 7.20 9.00 7.20 9.00 7.20 18.00 14.40 15.00 12.00 7.20 5.76 12.60 10.08 36.00 28.80 18.00 14.40 12.60 10.08 3.60 2.88 1.80 1.44 - - 1.80 1.44 1.80 1.44 1.80 1.44 Sub Total - 4-D INR Lakhs 85.92 92.00 91.68 92.00 57.60 50.40 127.84 120.48 174.80 143.52 54.56 63.84 54.56 130.80 101.20 51.52 69.60 216.00 111.36 67.92 18.08 16.64 - 23.84 5.92 23.84
4-E Bus Bar & Hard ware materials for 400 kV a) 4" EH-IPS Alluminium Tube(OD- 114.2, ID-97.18)
L/S 160.00 1.80 288.00 1.80 288.00 1.80 288.00 1.80 288.00 1.00 160.00 1.00 160.00 2.60 416.00 2.60 416.00 3.80 608.00 2.50 400.00 1.80 288.00 1.35 216.00 1.35 216.00 3.30 528.00 2.15 344.00 1.00 160.00 1.35 216.00 4.90 784.00 2.34 374.40 1.46 234.00 0.30 48.00 0.30 48.00 - - 0.40 64.00 0.20 32.00 0.35 56.00
b) Moose ACSR
c)
d)
e) 400KV Bus post insulators
f)
g) Tee Clamps Twin Moose to Twin Moose - 400kV side
h) PG Clamps
i) Spacer Clamps for Twin Moose
j) Ground wire and accessories Sub Total - 4-E INR Lakhs 288.00 288.00 288.00 288.00 160.00 160.00 416.00 416.00 608.00 400.00 288.00 216.00 216.00 528.00 344.00 160.00 216.00 784.00 374.40 234.00 48.00 48.00 - 64.00 32.00 56.00
4-Fa) Towers - -
i Towers Type 4C1 No. 3.00 5.00 15.00 5.00 15.00 5.00 15.00 5.00 15.00 3.00 9.00 3.00 9.00 7.00 21.00 5.00 15.00 13.00 39.00 7.00 21.00 3.00 9.00 3.00 9.00 3.00 9.00 7.00 21.00 5.00 15.00 3.00 9.00 3.00 9.00 18.00 54.00 8.00 24.00 5.00 15.00 1.50 4.50 1.50 4.50 - - 2.00 6.00 - - - -
ii Towers Type 4C2 No. 3.00 8.00 24.00 8.00 24.00 8.00 24.00 8.00 24.00 6.00 18.00 4.00 12.00 8.00 24.00 8.00 24.00 8.00 24.00 8.00 24.00 6.00 18.00 6.00 18.00 4.00 12.00 8.00 24.00 10.00 30.00 6.00 18.00 6.00 18.00 6.00 18.00 - - - - - - - - - - 4.00 12.00 - - - -
iii Towers Type 4C3 No. 3.00 16.00 48.00 16.00 48.00 16.00 48.00 16.00 48.00 9.00 27.00 10.00 30.00 24.00 72.00 16.00 48.00 33.00 99.00 24.00 72.00 9.00 27.00 13.00 39.00 10.00 30.00 24.00 72.00 19.00 57.00 6.00 18.00 9.00 27.00 62.00 186.00 20.00 60.00 17.00 51.00 6.00 18.00 6.00 18.00 - - 6.00 18.00 - - 8.00 24.00
b) Equipment support structures - - - - - - - - -
i Circuit breaker No. 1.25 9.00 11.25 9.00 11.25 13.00 16.25 9.00 11.25 8.00 10.00 7.00 8.75 14.00 17.50 11.00 13.75 23.00 28.75 17.00 21.25 7.00 8.75 8.00 10.00 7.00 8.75 17.00 21.25 14.00 17.50 6.00 7.50 8.00 10.00 29.00 36.25 12.00 15.00 8.00 10.00 1.50 1.87 1.50 1.87 - - 1.50 1.87 1.00 1.25 2.50 3.12
ii Isolator No. 0.50 24.00 12.00 26.00 13.00 28.00 14.00 26.00 13.00 18.00 9.00 15.00 7.50 34.00 17.00 33.00 16.50 63.00 31.50 42.00 21.00 17.00 8.50 21.00 10.50 17.00 8.50 42.00 21.00 34.00 17.00 16.00 8.00 21.00 10.50 72.00 36.00 34.00 17.00 23.00 11.50 5.00 2.50 4.00 2.00 - - 4.00 2.00 1.00 0.50 5.00 2.50
iii CT No. 0.10 27.00 2.70 27.00 2.70 30.00 3.00 27.00 2.70 18.00 1.80 15.00 1.50 42.00 4.20 27.00 2.70 60.00 6.00 51.00 5.10 18.00 1.80 24.00 2.40 12.00 1.20 51.00 5.10 39.00 3.90 18.00 1.80 24.00 2.40 87.00 8.70 45.00 4.50 30.00 3.00 6.00 0.60 6.00 0.60 - - 4.50 0.45 - - 6.00 0.60 iv CVT No. 0.10 18.00 1.80 18.00 1.80 18.00 1.80 18.00 1.80 12.00 1.20 12.00 1.20 24.00 2.40 18.00 1.80 33.00 3.30 24.00 2.40 12.00 1.20 12.00 1.20 12.00 1.20 24.00 2.40 18.00 1.80 12.00 1.20 12.00 1.20 42.00 4.20 27.00 2.70 18.00 1.80 3.00 0.30 3.00 0.30 - - - - - - - - v SA No. 0.05 18.00 0.90 18.00 0.90 18.00 0.90 18.00 0.90 18.00 0.90 15.00 0.75 30.00 1.50 24.00 1.20 48.00 2.40 36.00 1.80 15.00 0.75 15.00 0.75 15.00 0.75 36.00 1.80 30.00 1.50 12.00 0.60 21.00 1.05 60.00 3.00 30.00 1.50 21.00 1.05 6.00 0.30 3.00 0.15 - - 3.00 0.15 3.00 0.15 3.00 0.15 vi Line Trap No. 0.50 8.00 4.00 8.00 4.00 8.00 4.00 8.00 4.00 4.00 2.00 4.00 2.00 12.00 6.00 8.00 4.00 18.00 9.00 12.00 6.00 4.00 2.00 4.00 2.00 4.00 2.00 12.00 6.00 8.00 4.00 4.00 2.00 4.00 2.00 24.00 12.00 14.00 7.00 8.00 4.00 2.00 1.00 2.00 1.00 - - - - - - - - vii BPI No. 0.05 63.00 3.15 63.00 3.15 63.00 3.15 63.00 3.15 30.00 1.50 28.00 1.40 99.00 4.95 99.00 4.95 156.00 7.80 99.00 4.95 30.00 1.50 36.00 1.80 30.00 1.50 99.00 4.95 69.00 3.45 30.00 1.50 42.00 2.10 108.00 5.40 90.00 4.50 45.00 2.25 12.00 0.60 12.00 0.60 - - 30.00 1.50 6.00 0.30 30.00 1.50
Sub Total - 4-F INR Lakhs 122.80 123.80 130.10 123.80 80.40 74.10 170.55 131.90 250.75 179.50 78.50 94.65 74.90 179.50 151.15 67.60 83.25 363.55 136.20 99.60 29.67 29.02 - 41.97 2.20 31.87
4-Ga) 420 KV Circuit breaker No. 0.30 9.00 2.70 11.00 3.30 13.00 3.90 11.00 3.30 8.00 2.40 7.00 2.10 14.00 4.20 11.00 3.30 23.00 6.90 17.00 5.10 7.00 2.10 8.00 2.40 7.00 2.10 17.00 5.10 14.00 4.20 6.00 1.80 8.00 2.40 29.00 8.70 12.00 3.60 8.00 2.40 1.50 0.45 1.50 0.45 - - 1.50 0.45 1.00 0.30 2.50 0.75
b) 420KV Isolator No. 0.20 24.00 4.80 26.00 5.20 28.00 5.60 26.00 5.20 18.00 3.60 15.00 3.00 34.00 6.80 33.00 6.60 63.00 12.60 42.00 8.40 17.00 3.40 21.00 4.20 17.00 3.40 42.00 8.40 34.00 6.80 16.00 3.20 21.00 4.20 72.00 14.40 34.00 6.80 23.00 4.60 5.00 1.00 4.00 0.80 - - 4.00 0.80 1.00 0.20 5.00 1.00
c) 420 KV Current Transformer No. 0.06 30.00 1.80 30.00 1.80 30.00 1.80 30.00 1.80 18.00 1.08 15.00 0.90 42.00 2.52 27.00 1.62 60.00 3.60 51.00 3.06 18.00 1.08 24.00 1.44 12.00 0.72 48.00 2.88 39.00 2.34 18.00 1.08 24.00 1.44 87.00 5.22 45.00 2.70 30.00 1.80 6.00 0.36 4.50 0.27 - - 4.50 0.27 - - 6.00 0.36
d) 420KV CVT No. 0.06 18.00 1.08 18.00 1.08 18.00 1.08 18.00 1.08 12.00 0.72 12.00 0.72 24.00 1.44 18.00 1.08 33.00 1.98 24.00 1.44 12.00 0.72 12.00 0.72 12.00 0.72 24.00 1.44 18.00 1.08 12.00 0.72 12.00 0.72 42.00 2.52 27.00 1.62 18.00 1.08 3.00 0.18 3.00 0.18 - - - - - - - -
e) 390KV surge Arrestor No. 0.03 18.00 0.54 24.00 0.72 30.00 0.90 24.00 0.72 18.00 0.54 15.00 0.45 30.00 0.90 24.00 0.72 48.00 1.44 36.00 1.08 15.00 0.45 15.00 0.45 15.00 0.45 36.00 1.08 30.00 0.90 12.00 0.36 21.00 0.63 60.00 1.80 30.00 0.90 21.00 0.63 6.00 0.18 3.00 0.09 - - 15.00 0.45 3.00 0.09 3.00 0.09
f) Towers & Beams - Lattice Type Set 6.30 1.00 6.30 1.00 6.30 1.00 6.30 1.00 6.30 0.67 4.23 0.62 2.64 1.31 3.46 0.98 3.40 2.03 6.90 1.33 9.18 0.67 6.17 0.78 4.84 0.62 2.98 1.55 4.63 1.15 5.31 0.67 3.57 0.77 2.74 2.05 5.61 1.31 7.35 0.82 6.02 0.30 1.68 0.25 0.42 - - 0.30 - 0.10 - 0.30 -
g) Support Structures - Pipe Type Set 2.00 1.00 2.00 1.00 2.00 1.00 2.00 1.00 2.00 0.67 1.34 0.62 1.25 1.31 2.62 0.98 1.97 2.03 4.06 1.33 2.66 0.67 1.34 0.78 1.57 0.62 1.23 1.55 3.11 1.15 2.29 0.67 1.34 0.77 1.54 2.05 4.10 1.31 2.62 0.82 1.64 0.30 0.60 0.25 0.50 - - 0.30 0.60 0.15 0.30 0.30 0.60
h) Bus Bars formation etc Set 15.00 1.00 15.00 1.00 15.00 1.00 15.00 1.00 15.00 0.67 10.08 0.62 9.35 1.31 19.65 0.98 14.76 2.03 30.45 1.33 19.95 0.67 10.08 0.78 11.76 0.62 9.24 1.55 23.29 1.15 17.21 0.67 10.08 0.77 11.52 2.05 30.75 1.31 19.65 0.82 12.28 0.30 4.50 0.25 3.75 - - 0.30 4.50 0.10 1.50 0.30 4.50
k) Control & Protection panels - -
i 400KV CB relay Panel No. 0.30 9.00 2.70 11.00 3.30 13.00 3.90 11.00 3.30 8.00 2.40 7.00 2.10 14.00 4.20 11.00 3.30 23.00 6.90 17.00 5.10 7.00 2.10 8.00 2.40 7.00 2.10 17.00 5.10 14.00 4.20 6.00 1.80 8.00 2.40 29.00 8.70 12.00 3.60 8.00 2.40 1.50 0.45 1.50 0.45 - - 0.50 0.15 1.00 0.30 2.50 0.75
ii 400KV Line Protection Panel No. 0.90 4.00 3.60 4.00 3.60 4.00 3.60 4.00 3.60 2.00 1.80 2.00 1.80 6.00 5.40 4.00 3.60 9.00 8.10 6.00 5.40 2.00 1.80 2.00 1.80 2.00 1.80 6.00 5.40 4.00 3.60 2.00 1.80 2.00 1.80 12.00 10.80 7.00 6.30 4.00 3.60 1.00 0.90 1.00 0.90 - - - - - - - -
iii 400/220/33KV Transformer Protection Panel No. 0.55 2.00 1.09 2.00 1.09 2.00 1.09 2.00 1.09 2.00 1.09 1.00 0.55 2.00 1.09 2.00 1.09 2.00 1.09 2.00 1.09 2.00 1.09 2.00 1.09 1.00 0.55 2.00 1.09 3.00 1.64 2.00 1.09 2.00 1.09 2.00 1.09 - - - - - - - - - - 1.00 0.55 - - - -
iv 400KV Reactor Protection Panel No. 0.10 - - 2.00 0.19 4.00 0.38 2.00 0.19 2.00 0.19 2.00 0.19 2.00 0.19 3.00 0.29 5.00 0.48 4.00 0.38 1.00 0.10 1.00 0.10 2.00 0.19 4.00 0.38 3.00 0.29 - - 3.00 0.29 6.00 0.57 3.00 0.29 3.00 0.29 1.00 0.10 - - - - - - 1.00 0.10 1.00 0.10
v Duplicate Bus Bar Protection Panel - 400KV No. 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 1.00 1.60 - - - - - - - - - - - -
l) PLCC Equipments (Both for 400 kV & 220 kV) Set 1.25 1.00 1.25 1.00 1.25 1.00 1.25 1.00 1.25 0.75 0.94 0.75 0.94 1.25 1.56 1.40 1.75 2.50 3.13 1.25 1.56 1.00 1.25 0.75 0.94 0.75 0.94 1.25 1.56 1.00 1.25 0.75 0.94 0.75 0.94 1.15 1.44 0.83 1.03 0.62 0.77 0.25 0.31 0.25 0.31 - - - - - - - - Sub Total - 4-G INR Lakhs 44.46 46.43 48.40 46.43 32.02 27.57 55.63 45.08 89.23 66.01 33.28 35.30 28.01 65.06 52.70 29.38 33.30 97.31 58.06 39.11 10.71 8.12 - 7.77 2.79 8.15
Total - 4 INR Lakhs 1,950.01 2,092.31 2,221.39 2,070.27 1,415.77 1,304.70 2,746.30 2,302.21 4,161.30 3,027.08 1,506.73 1,562.31 1,357.22 3,154.22 2,474.55 1,250.04 1,571.47 5,380.41 2,524.87 1,725.42 348.34 318.90 - 329.51 123.10 308.40
BOQ & Cost for 400 / 220 KV Sub Station of various combinations of Bays,ICTs,Shunt & Bus Reactors for new 400/220 kV Sub-Stations (Green field stations)
1X315 MVA ICT with 400KV & 220KV Bays
Addition of Shunt Reactor to 400KV Line Bay
Intial Civil Engineering Works like Levelling,Retaining walls,Appoch Road,Peripheral Fencing etc (lump Sum)
Storm water drain, Road culverts drain crossing, cable trench crossing
Providing water supply including drinking water & water for fire fighting system and sewage system
Parking sheds,Rain water Harvesting systems & land scaping etc.,
LT Switch Gear consisting of 415 V main switch board, ACDB, MLDB, Emergency LDB, A/C DB, 220 V DCDB, 50V DCDB, 1 trasformer each of rating 630KVA, 11kV/440V and 800KVA, 33KV/440V,72.5KV Isolator, CT, PT, CB/Fuse 33KV and 11KV Isolator, fuse, SA
Foundations for 1of 630KVA 33/0.415 kV and one of 800kVA 33/0.415kv LT transformer, BM Kiosk etc.
Battery Charger System 220 V, 70A / 50 A Float cum Boost
Battery Charger System 50 V, 70 A / 50 A Float cum Boost
Sub-Station Automation including Hardware, software, Remote Control Station, DMT scheme along with associated equipment and kiosks
A/C and ventilation - High Valve Type split AC unit of 2TR capacity
Auxiliary Transformers,LT Switchgear, AC & DC Panels.72.5 kV ,33kV, & 11 kV equipments Etc
Battery Charger System 220 V, 70A / 50 A Float cum Boost
Battery Charger System 50 V, 70 A / 50 A Float cum Boost
Sub-Station Automation including Hardware, software, Remote Control Station, DMT Scheme along with associated equipment and kiosks
I.C.T 167 MVA, S-Phase, 400/220/33 kV (Single Phase 167 MVA Units)
420 KV,2000A, 40KA CB without CR & with support structure
420 KV,2000A, 40KA CB without CR & with support structure
420 kV CT 2000A, 40KA, 5-Core with 120% extended current
420 KV,2000 A,40 kA Isolator, DB Type with one E/S (3phase)
420 KV,2000 A,40 kA Isolator, DB Type with two E/S (3phase)
400 kV Towers, Beams & support structures - Lattice Type
Lightning cum Lighting mast on both 400 & 220 kV switch Yard (6Nos *4.5 MT + 6Nos *3MT)
400 KV Tubular type (Pipe) Equipment Support Structures
Twin Disc Iinsulator string with Tension Hardware for Twin Moose on 400KV side
Single Disc Iinsulator string with suspension Hardware for Twin Moose on 400KV side
Tee Clamps Twin Moose to EH-IPS Al Tube 4" - 400kV side
Foundations for 400 kV Towers & Equipment Support structures
Erection, Testing & commisioning Charges for 400 kV Outdoor Equipments
5 220 kV Bays & Equipments5-A 245 kV equipment a) Circuit Breaker 245 kV
i 1600 A, 40 kA No. 14.35 9.00 129.19 9.00 129.19 9.00 129.19 7.00 100.48 7.00 100.48 7.00 100.48 9.00 129.19 12.00 172.25 15.00 215.31 9.00 129.19 7.00 100.48 7.00 100.48 6.00 86.13 9.00 129.19 10.00 143.54 7.00 100.48 7.00 100.48 8.00 114.83 - - - - - - - - 1.00 14.35 1.00 14.35 - - - -
ii 2500 A, 40 kA No. 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 1.00 14.65 - - - - - - - - - - - - - - - -
b) Current Transformer 245 kV - -
i 1600 A, 40 kA , 5 core, with 120% extended current No. 3.03 27.00 81.74 27.00 81.74 27.00 81.74 21.00 63.57 21.00 63.57 21.00 63.57 27.00 81.74 36.00 108.99 45.00 136.23 27.00 81.74 21.00 63.57 21.00 63.57 18.00 54.49 27.00 81.74 30.00 90.82 21.00 63.57 21.00 63.57 24.00 72.66 - - - - - - - - 3.00 9.08 3.00 9.08 - - - -
ii 1600 A, 40 kA, 5 core, with 150% extended current No. 3.25 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 3.00 9.75 - - - - - - - - - - - - - - - -
c) CVT 245 kV - -
i 8800 pf, S- Ph, with 3 secondaries No. 3.10 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 6.00 18.60 - - - - - - - - - - - - - - - -
ii 4400 pf, S- Ph with 3 secondaries No. 2.74 18.00 49.29 18.00 49.29 18.00 49.29 12.00 32.86 12.00 32.86 12.00 32.86 18.00 49.29 30.00 82.15 36.00 98.58 18.00 49.29 12.00 32.86 12.00 32.86 12.00 32.86 18.00 49.29 18.00 49.29 12.00 32.86 12.00 32.86 15.00 41.07 - - - - - - - - 3.00 8.21 - - - - - -
d) Isolator 245 kV No. - -
i 1600A, 40 kA, DB Type with two E/S No. 3.76 9.00 33.81 9.00 33.81 9.00 33.81 7.00 26.30 7.00 26.30 7.00 26.30 9.00 33.81 12.00 45.08 15.00 56.35 9.00 33.81 7.00 26.30 7.00 26.30 6.00 22.54 9.00 33.81 10.00 37.57 7.00 26.30 7.00 26.30 8.00 30.05 - - - - - - - - 1.00 3.76 1.00 3.76 - - - -
ii 1600A, 40 kA, DB Type with one E/S No. 3.17 9.00 28.54 9.00 28.54 9.00 28.54 7.00 22.20 7.00 22.20 7.00 22.20 9.00 28.54 11.00 34.89 13.00 41.23 9.00 28.54 7.00 22.20 7.00 22.20 6.00 19.03 9.00 28.54 10.00 31.72 7.00 22.20 7.00 22.20 8.00 25.37 - - - - - - - - 1.00 3.17 1.00 3.17 - - - -
iii 1600A, 40 kA, DB, Tandem Type without E/S No. 2.81 17.00 47.84 17.00 47.84 17.00 47.84 13.00 36.59 13.00 36.59 13.00 36.59 17.00 47.84 23.00 64.73 29.00 81.62 17.00 47.84 13.00 36.59 13.00 36.59 11.00 30.96 17.00 47.84 19.00 53.47 13.00 36.59 13.00 36.59 15.00 42.22 - - - - - - - - 2.00 5.63 2.00 5.63 - - - -
iv 2500A, 40 KA, DB Type with Two E/S No. 3.94 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 2.00 7.87 - - - - - - - - - - - - - - - -
v 1600A, 40kA with one E/S, S-phase No. 1.42 - - - - - - - - - - - - - - 8.00 11.35 14.00 19.87 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
vi 1600A, 40 kA without E/S, S phase 0.96 - -
e) 216 kV Surge Arrestors No. 0.61 24.00 14.69 24.00 14.69 24.00 14.69 18.00 11.02 18.00 11.02 18.00 11.02 24.00 14.69 34.00 20.81 49.00 29.99 24.00 14.69 18.00 11.02 18.00 11.02 15.00 9.18 24.00 14.69 27.00 16.52 18.00 11.02 18.00 11.02 21.00 12.85 - - - - - - - - 3.00 1.84 3.00 1.84 - - - - Sub Total - 5-A INR Lakhs 333.00 435.97 435.97 435.97 343.88 343.88 343.88 435.97 591.11 730.05 435.97 343.88 343.88 306.05 435.97 473.80 343.88 343.88 389.93 - - - - - - 46.04 37.83 - -
5-B 220 kV Simplex type Panels a) Circuit breaker relay panel With Auto reclosure No. 8.02 6.00 48.14 6.00 48.14 6.00 48.14 4.00 32.09 4.00 32.09 4.00 32.09 6.00 48.14 10.00 80.23 10.00 80.23 6.00 48.14 4.00 32.09 4.00 32.09 4.00 32.09 6.00 48.14 6.00 48.14 4.00 32.09 4.00 32.09 5.00 40.11 - - - - - - - - 1.00 8.02 - - - - - -
b) Circuit breaker relay panel Without Auto reclosure No. 6.45 4.00 25.81 4.00 25.81 4.00 25.81 4.00 25.81 4.00 25.81 4.00 25.81 4.00 25.81 3.00 19.36 4.00 25.81 4.00 25.81 4.00 25.81 4.00 25.81 3.00 19.36 4.00 25.81 5.00 32.26 4.00 25.81 4.00 25.81 4.00 25.81 - - - - - - - - - - 1.00 6.45 - - - -
c) Line protection panel No. 18.18 6.00 109.09 6.00 109.09 6.00 109.09 4.00 72.73 4.00 72.73 4.00 72.73 6.00 109.09 10.00 181.82 10.00 181.82 6.00 109.09 4.00 72.73 4.00 72.73 4.00 72.73 6.00 109.09 6.00 109.09 4.00 72.73 4.00 72.73 5.00 90.91 - - - - - - - - 1.00 18.18 - - - - - -
d) Single Bus Bar protection panel No. 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 1.00 63.46 - - - - - - - - - - - - - - - - Sub Total - 5-B INR Lakhs 246.50 246.50 246.50 194.09 194.09 194.09 246.50 344.87 351.32 246.50 194.09 194.09 187.64 246.50 252.95 194.09 194.09 220.29 - - 26.21 6.45 - -
5-C 220 kV Towers, Beams & Support structures a) Tower Type 2C1 - Number * Unit Weight MT 0.60 67.50 40.50 67.50 40.50 67.50 40.50 54.00 32.40 54.00 32.40 54.00 32.40 67.50 40.50 121.50 72.90 121.50 72.90 67.50 40.50 54.00 32.40 54.00 32.40 54.00 32.40 67.50 40.50 67.50 40.50 54.00 32.40 54.00 32.40 67.50 40.50 - - - - - - - - - - - - - - - -
b) Tower Type 2C2 - Number * Unit Weight MT 0.60 72.00 43.20 72.00 43.20 72.00 43.20 60.00 36.00 60.00 36.00 60.00 36.00 72.00 43.20 48.00 28.80 48.00 28.80 72.00 43.20 60.00 36.00 60.00 36.00 60.00 36.00 72.00 43.20 68.00 40.80 60.00 36.00 60.00 36.00 72.00 43.20 - - - - - - - - 8.00 4.80 6.00 3.60 - - - -
c) Tower Type 2C3 - Number * Unit Weight MT 0.60 14.00 8.40 14.00 8.40 14.00 8.40 10.50 6.30 10.50 6.30 10.50 6.30 14.00 8.40 56.00 33.60 63.00 37.80 14.00 8.40 10.50 6.30 10.50 6.30 10.50 6.30 14.00 8.40 14.00 8.40 10.50 6.30 10.50 6.30 10.50 6.30 - - - - - - - - - - 14.00 8.40 - - - -
d) Beam Type 2B1 - Number * Unit Weight MT 0.60 30.00 18.00 30.00 18.00 30.00 18.00 24.00 14.40 24.00 14.40 24.00 14.40 30.00 18.00 48.00 28.80 48.00 28.80 30.00 18.00 24.00 14.40 24.00 14.40 24.00 14.40 30.00 18.00 30.00 18.00 24.00 14.40 24.00 14.40 30.00 18.00 - - - - - - - - - - - - - - - -
e) Bea Type 2B2 - Number * Unit Weight MT 0.60 42.50 25.50 42.50 25.50 42.50 25.50 32.50 19.50 37.50 22.50 37.50 22.50 59.50 35.70 27.50 16.50 32.50 19.50 42.50 25.50 32.50 19.50 32.50 19.50 32.50 19.50 42.50 25.50 42.50 25.50 37.50 22.50 37.50 22.50 47.50 28.50 - - - - - - - - 2.50 1.50 5.00 3.00 - - - -
f) Beam Type 2B3 - Number * Unit Weight MT 0.60 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
g) Equipment Support Structure - Number * Unit Weight MT 0.60 33.00 19.80 33.00 19.80 33.00 19.80 24.00 14.40 24.00 14.40 24.00 14.40 33.00 19.80 49.50 29.70 51.00 30.60 27.00 16.20 24.00 14.40 24.00 14.40 22.50 13.50 33.00 19.80 34.50 20.70 24.00 14.40 24.00 14.40 31.50 18.90 - - - - - - - - 4.50 2.70 1.50 0.90 - - - - Sub Total - 5-C INR Lakhs 155.40 155.40 155.40 123.00 126.00 126.00 165.60 210.30 218.40 151.80 123.00 123.00 122.10 155.40 153.90 126.00 126.00 155.40 - - 9.00 15.90 - -
5-Da) CVT - Number * Unit Weight MT 0.80 12.00 9.60 12.00 9.60 12.00 9.60 9.00 7.20 9.00 7.20 9.00 7.20 12.00 9.60 18.00 14.40 16.50 13.20 12.00 9.60 9.00 7.20 9.00 7.20 9.00 7.20 12.00 9.60 12.00 9.60 9.00 7.20 9.00 7.20 10.50 8.40 - - - - - - - - 1.50 1.20 - - - - - -
b) BPI - Number * Unit Weight MT 0.80 34.00 27.20 34.00 27.20 34.00 27.20 24.00 19.20 24.00 24.00 22.50 18.00 34.00 27.20 42.00 33.60 45.00 36.00 34.00 27.20 24.00 19.20 24.00 19.20 21.00 16.80 34.00 27.20 30.00 24.00 24.00 19.20 24.00 19.20 27.00 21.60 - - - - - - - - 3.50 2.80 3.50 2.80 - - - -
c) Isolators - Number * Unit Weight MT 0.80 55.50 44.40 55.50 44.40 55.50 44.40 27.00 27.00 27.00 21.60 43.50 34.80 55.50 44.40 84.00 67.20 97.50 78.00 55.50 44.40 27.00 21.60 27.00 21.60 23.00 18.40 55.50 44.40 61.50 49.20 27.00 21.60 43.50 34.80 49.50 39.60 - - - - - - - - 6.00 4.80 6.00 4.80 - - - -
d) SA - Number * Unit Weight MT 0.80 12.00 9.60 12.00 9.60 12.00 9.60 9.00 7.20 9.00 7.20 9.00 7.20 12.00 9.60 18.00 14.40 18.00 14.40 12.00 9.60 9.00 7.20 9.00 7.20 7.50 6.00 12.00 9.60 13.50 10.80 9.00 7.20 9.00 7.20 10.50 8.40 - - - - - - - - 1.50 1.20 1.50 1.20 - - - - Sub Total - 5-D INR Lakhs 90.80 90.80 90.80 60.60 60.00 67.20 90.80 129.60 141.60 90.80 55.20 55.20 48.40 90.80 93.60 55.20 68.40 78.00 - - 10.00 8.80 - -
5-E Bus Bar & Hard ware materials for 220 kV
a) Set
180.00 1.50 270.00 1.50 270.00 1.50 270.00 1.00 180.00 1.00 180.00 1.00 180.00 1.50 270.00 3.25 585.00 3.50 630.00 1.50 270.00 1.00 180.00 1.00 180.00 1.00 180.00 1.50 270.00 1.50 270.00 1.00 180.00 1.00 180.00 1.25 225.00 - - - - - - - - 0.25 45.00 0.25 45.00 - - - -
b) Set
c) Set
d) Set
e) 220KV Bus post I nsulators No.
f) 4" EH-IPS Alluminium Tube(OD- 114.2, ID-97.18) Metre
g) Moose ACSR Metre
h) Tee Clamps Quad Moose to Twin Moose No.
i) Tee Clamps Twin Moose to Twin Moose - 220kv side No.
j) Tee Clamps Twin Moose to 4' IPS Al Tube - 220kv side No.
k) Spacer Clamps for Quad Moose ACSR No.
l) Spacer Clamps for Twin Moose ACSR No.
m) PG Clamps No.
n) Ground wire with Accessories Lump Sum
Sub Total - 5-E INR Lakhs 270.00 270.00 270.00 180.00 180.00 180.00 270.00 585.00 630.00 270.00 180.00 180.00 180.00 270.00 270.00 180.00 180.00 225.00 - - - 45.00 45.00 - -
5-Fa) Towers
i Towers Type 2C1 No. 2.50 15.00 37.50 15.00 37.50 15.00 37.50 12.00 30.00 12.00 30.00 12.00 30.00 15.00 37.50 27.00 67.50 27.00 67.50 15.00 37.50 12.00 30.00 12.00 30.00 12.00 30.00 15.00 37.50 15.00 37.50 12.00 30.00 12.00 30.00 15.00 37.50 - - - - - - - - - - - - - - - -
ii Towers Type 2C2 No. 2.50 18.00 45.00 18.00 45.00 18.00 45.00 15.00 37.50 15.00 37.50 15.00 37.50 18.00 45.00 12.00 30.00 12.00 30.00 18.00 45.00 15.00 37.50 15.00 37.50 15.00 37.50 18.00 45.00 17.00 42.50 15.00 37.50 15.00 37.50 18.00 45.00 - - - - - - - - 2.00 5.00 2.00 5.00 - - - -
iii Towers Type 2C3 No. 2.50 4.00 10.00 4.00 10.00 4.00 10.00 3.00 7.50 3.00 7.50 3.00 7.50 4.00 10.00 16.00 40.00 18.00 45.00 4.00 10.00 3.00 7.50 3.00 7.50 3.00 7.50 4.00 10.00 4.00 10.00 3.00 7.50 3.00 7.50 3.00 7.50 - - - - - - - - - - 2.00 5.00 - - - -
b) Equipment support structures - - - - - - - - - - - - - - - - -
i Circuit breakers No. 0.50 10.00 5.00 10.00 5.00 10.00 5.00 8.00 4.00 8.00 4.00 8.00 4.00 10.00 5.00 13.00 6.50 14.00 7.00 10.00 5.00 8.00 4.00 8.00 4.00 7.00 3.50 10.00 5.00 11.00 5.50 8.00 4.00 8.00 4.00 9.00 4.50 - - - - - - - - 1.00 0.50 1.00 0.50 - - - -
ii Isolators No. 0.40 37.00 14.80 37.00 14.80 37.00 14.80 29.00 11.60 29.00 11.60 29.00 11.60 37.00 14.80 56.00 22.40 65.00 26.00 37.00 14.80 29.00 11.60 29.00 11.60 25.00 10.00 37.00 14.80 41.00 16.40 29.00 11.60 29.00 11.60 33.00 13.20 - - - - - - - - 4.00 1.60 4.00 1.60 - - - -
iii C.Ts No. 0.10 30.00 3.00 30.00 3.00 30.00 3.00 24.00 2.40 24.00 2.40 24.00 2.40 30.00 3.00 39.00 3.90 42.00 4.20 30.00 3.00 24.00 2.40 24.00 2.40 21.00 2.10 30.00 3.00 33.00 3.30 24.00 2.40 24.00 2.40 27.00 2.70 - - - - - - - - 3.00 0.30 3.00 0.30 - - - - iv CVT No. 0.10 24.00 2.40 24.00 2.40 24.00 2.40 18.00 1.80 18.00 1.80 18.00 1.80 24.00 2.40 36.00 3.60 33.00 3.30 24.00 2.40 18.00 1.80 18.00 1.80 18.00 1.80 24.00 2.40 24.00 2.40 18.00 1.80 18.00 1.80 21.00 2.10 - - - - - - - - 3.00 0.30 - - - - - - v SA No. 0.40 24.00 9.60 24.00 9.60 24.00 9.60 18.00 7.20 18.00 7.20 18.00 7.20 24.00 9.60 36.00 14.40 36.00 14.40 24.00 9.60 18.00 7.20 18.00 7.20 15.00 6.00 24.00 9.60 27.00 10.80 18.00 7.20 18.00 7.20 21.00 8.40 - - - - - - - - 3.00 1.20 3.00 1.20 - - - - vi WT No. 0.50 12.00 6.00 12.00 6.00 12.00 6.00 8.00 4.00 8.00 4.00 8.00 4.00 12.00 6.00 20.00 10.00 20.00 10.00 12.00 6.00 8.00 4.00 8.00 4.00 8.00 4.00 12.00 6.00 12.00 6.00 8.00 4.00 8.00 4.00 10.00 5.00 - - - - - - - - 2.00 1.00 - - - - - - vii BPI No. 0.40 68.00 27.20 68.00 27.20 68.00 27.20 48.00 19.20 48.00 19.20 45.00 18.00 68.00 27.20 84.00 33.60 90.00 36.00 68.00 27.20 48.00 19.20 48.00 19.20 45.00 18.00 68.00 27.20 60.00 24.00 48.00 19.20 48.00 19.20 54.00 21.60 - - - - - - - - 7.00 2.80 7.00 2.80 - - - -
Sub Total - 5-F INR Lakhs 160.50 160.50 160.50 125.20 125.20 124.00 160.50 231.90 243.40 160.50 125.20 125.20 120.40 160.50 158.40 125.20 125.20 147.50 - - 12.70 16.40 - -
5-G Erection Testing & commissioning Charges 220 kV OUTDOOR EQUIPMENTS
a) 245 KV Circuit breakers No. 0.20 10.00 2.00 10.00 2.00 10.00 2.00 8.00 1.60 8.00 1.60 8.00 1.60 10.00 2.00 13.00 2.60 14.00 2.80 10.00 2.00 8.00 1.60 8.00 1.60 7.00 1.40 10.00 2.00 11.00 2.20 8.00 1.60 8.00 1.60 9.00 1.80 - - - - - - - - 1.00 0.20 1.00 0.20 - - - -
b) 245 KV Isolators No. 0.15 37.00 5.55 37.00 5.55 37.00 5.55 29.00 4.35 29.00 4.35 29.00 4.35 37.00 5.55 56.00 8.40 65.00 9.75 37.00 5.55 29.00 4.35 29.00 4.35 25.00 3.75 37.00 5.55 41.00 6.15 29.00 4.35 29.00 4.35 33.00 4.95 - - - - - - - - 4.00 0.60 4.00 0.60 - - - -
c) 245 KV Current Transformers No. 0.05 30.00 1.50 30.00 1.50 30.00 1.50 24.00 1.20 24.00 1.20 24.00 1.20 30.00 1.50 39.00 1.95 42.00 2.10 30.00 1.50 24.00 1.20 24.00 1.20 21.00 1.05 30.00 1.50 33.00 1.65 24.00 1.20 24.00 1.20 27.00 1.35 - - - - - - - - 3.00 0.15 3.00 0.15 - - - -
d) 245 KV CVT No. 0.05 24.00 1.20 24.00 1.20 24.00 1.20 18.00 0.90 18.00 0.90 18.00 0.90 24.00 1.20 36.00 1.80 36.00 1.80 24.00 1.20 18.00 0.90 18.00 0.90 18.00 0.90 24.00 1.20 24.00 1.20 18.00 0.90 18.00 0.90 21.00 1.05 - - - - - - - - 3.00 0.15 - - - - - -
e) 216 KV surge Arrestors No. 0.03 24.00 0.72 24.00 0.72 24.00 0.72 18.00 0.54 18.00 0.54 18.00 0.54 24.00 0.72 33.00 0.99 36.00 1.08 24.00 0.72 18.00 0.54 18.00 0.54 15.00 0.45 24.00 0.72 27.00 0.81 18.00 0.54 18.00 0.54 21.00 0.63 - - - - - - - - 3.00 0.09 3.00 0.09 - - - -
f) 220 kV Towers , Beams Set 6.00 1.00 6.00 1.00 6.00 1.00 6.00 0.80 4.80 0.80 4.80 0.80 4.80 1.00 6.00 1.32 7.92 1.41 8.46 1.00 6.00 0.80 4.80 0.80 4.80 0.80 4.80 1.00 6.00 1.00 6.00 0.80 4.80 0.80 4.80 1.00 6.00 - - - - - - - - 0.20 1.20 0.20 1.20 - - - -
g) 221 kV Tubular type Pipe Structures Set 3.00 1.00 3.00 1.00 3.00 1.00 3.00 0.80 2.40 0.80 2.40 0.80 2.40 1.00 3.00 1.32 3.96 1.41 4.23 1.00 3.00 0.80 2.40 0.80 2.40 0.80 2.40 1.00 3.00 1.00 3.00 0.80 2.40 0.80 2.40 1.00 3.00 - - - - - - - - 0.20 0.60 0.20 0.60 - - - -
h) 220 kV Bus Bars formation etc Set 16.00 1.00 16.00 1.00 16.00 1.00 16.00 0.80 12.80 0.80 12.80 0.80 12.80 1.00 16.00 1.32 21.12 1.41 22.56 1.00 16.00 0.80 12.80 0.80 12.80 0.80 12.80 1.00 16.00 1.00 16.00 0.80 12.80 0.80 12.80 1.00 16.00 - - - - - - - - 0.20 3.20 0.20 3.20 - - - -
j) Control & Protection panels 1.00 - -
i Circuit breaker relay panel No. 0.22 10.00 2.17 10.00 2.17 6.00 1.30 8.00 1.74 8.00 1.74 8.00 1.74 10.00 2.17 13.00 2.82 14.00 3.04 10.00 2.17 8.00 1.74 8.00 1.74 7.00 1.52 10.00 2.17 11.00 2.39 8.00 1.74 8.00 1.74 9.00 1.95 - - - - - - - - 1.00 0.22 - - - - - -
ii Line protection panel No. 0.57 6.00 3.44 6.00 3.44 6.00 3.44 4.00 2.29 4.00 2.29 4.00 2.29 6.00 3.44 10.00 5.73 10.00 5.73 6.00 3.44 4.00 2.29 4.00 2.29 4.00 2.29 6.00 3.44 6.00 3.44 4.00 2.29 4.00 2.29 5.00 2.86 - - - - - - - - 1.00 0.57 - - - - - -
iii Single Bus Bar protection panel No. 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 1.00 1.74 - - - - - - - - - - - - - - - - Sub Total - 5-G INR Lakhs 43.31 43.31 42.45 34.35 34.35 34.35 43.31 59.03 63.28 43.31 34.35 34.35 33.10 43.31 44.57 34.35 34.35 41.33 - - - 6.98 6.04 - -
Total - 5 INR Lakhs 1,402.49 1,402.49 1,401.62 1,061.13 1,063.53 1,069.53 1,412.69 2,151.81 2,378.05 1,398.89 1,055.73 1,055.73 997.69 1,402.49 1,447.22 1,058.73 1,071.93 1,257.46 - - - 155.93 136.42 - -
6 Hard cost ---- Grand total (1+2+3+4+5) INR Lakhs 6,618.95 7,592.58 8,511.45 7,103.23 6,352.58 5,347.63 8,412.41 9,340.74 14,263.43 9,518.11 6,064.86 6,131.91 5,321.39 11,174.09 9,342.56 5,364.23 6,884.05 13,288.42 - 4,963.68 - 4,081.16 788.08 376.02 185.86 1,412.09 544.47 730.73
Material and Equipment Cost Only 5,683.85 6,610.21 7,504.34 6,174.19 5,530.64 4,562.28 7,329.86 8,127.11 12,661.19 8,374.63 5,256.41 5,310.74 4,534.20 9,910.20 8,275.30 4,588.53 6,037.12 11,698.30 4,247.89 3,450.95 724.96 336.64 163.96 1,306.86 517.77 667.97
Taxes 12.51% 710.82 - 826.67 - 938.49 - 772.14 - 691.66 - 570.56 - 916.67 - 1,016.38 - 1,583.41 - 1,047.33 - 657.37 - 664.16 - 567.05 - 1,239.37 - 1,034.91 - 573.84 - 755.00 - 1,462.99 531.24 - 431.58 - 90.66 - 42.10 - 20.50 - 163.44 - 64.75 - 83.54
7 Total Cost Including Taxes 7,329.77 - 8,419.25 - 9,449.94 - 7,875.37 - 7,044.24 - 5,918.19 - 9,329.08 - 10,357.12 - 15,846.84 - 10,565.44 - 6,722.23 - 6,796.07 - 5,888.44 - 12,413.46 - 10,377.47 - 5,938.07 - 7,639.05 - 14,751.41 5,494.92 - 4,512.74 - 878.75 - 418.12 - 206.36 - 1,575.53 - 609.22 - 814.26
220 KVTubular type (Pipe) Equipment support / mounting Structures
Quad Disc Iinsulator string with Tension Hardware for Quad Moose (220KV Main Bus)
Twin Disc Iinsulator string with Suspension Hardware for Quad Moose(220KV Main Bus)
Twin Disc Iinsulator string with Tension Hardware for Twin Moose (220KV Transfer Bus and Jack Bus)
Twin Disc Iinsulator string with Suspension Hardware for Twin Moose(220KV Transfer and Jack Bus)
Foundations for 220 kV Towers & Equipment mounting structures