+ All Categories
Home > Documents > SUMMARY OF FINDINGS FM 973 WMA/RAP/RAS TEST SECTION · SUMMARY OF FINDINGS FM 973 WMA/RAP/RAS TEST...

SUMMARY OF FINDINGS FM 973 WMA/RAP/RAS TEST SECTION · SUMMARY OF FINDINGS FM 973 WMA/RAP/RAS TEST...

Date post: 06-Jun-2018
Category:
Upload: doquynh
View: 218 times
Download: 0 times
Share this document with a friend
34
SUMMARY OF FINDINGS FM 973 WMA/RAP/RAS TEST SECTION Mike Arellano, P.E, Austin District 2013 TxDOT Transportation Short Course October 15, 2013
Transcript

SUMMARY OF FINDINGS FM 973 WMA/RAP/RAS TEST SECTION Mike Arellano, P.E, Austin District 2013 TxDOT Transportation Short Course October 15, 2013

Table of Contents

2

Background

Development & Construction of FM 973 Test Sections

Lab Findings

Field Findings

Economics

Conclusions

Q&A

1

2

3

4

5

6

7

Background – Big Picture Issue

With limited funds for pavement preservation want to use new technology

Savings from using RAP/RAS

Performance with RAP/RAS

4

Background – Construction Issues with Recycle Asphalt Mixes

Compaction Issues – High

Air Voids

Tearing During

Compaction

Raveling/ Segregation

Background – Performance Issues with Recycled Asphalt Mixes

5

Longitudinal Cracking & Raveling

Fatigue Cracking

Top-Down Cracking

Background – Long-Term Performance Issues

FM 1460 – New Construction – Longitudinal, Block, and

Transverse Cracking for both RAS & RAP sections

– Raveling at the joints and transitions

– Economics • ~$158k in cost savings from grade

bumping • ~$50k in crack seal scheduled after

2 years of service • Unrealized future costs – future

routine maint. costs, unscheduled mill & inlay, reduced life cycle, etc…

6

DEVELOPMENT & CONSTRUCTION OF FM 973 TEST SECTIONS

7

Background – Goals for the Test Section

Goals of FM 973 –Acceptable amount of

RAS/RAP –Benefits of WMA and soft

binder –Evaluate Lab tests to

predict field performance –Field performance

8

Development – Partnership in Innovation

FM 973 at a Glance

FM 973 Accelerated Pavement Test Section – From FM 969 to SH 71 – Existing Section: 8” HMA/ 11” FLBS – Soft silty/sandy clays – marginal subgrade – ADT = 10,700 – % Truck = 9.1% (ADT-975) – Heavy Trucks – Ready Mix Plant, Sand & Gravel Pit,

ABIA Freight, and other Industrial traffic

– Schedule Inlay: 2” Mill, Seal & Inlay – TY C PG 70-22 SAC B

Research Studies

Study Title PI(s) Organization

TxDOT 0-6614 Use of Recycled Asphalt Shingles in HMA Fujie Zhou TTI

TxDOT 0-6092 Performance Evaluation & Mix Design for High RAP Mixtures Fujie Zhou TTI

TxDOT 0-6613 Evaluate Binder & Mixture Aging for Warm Mix Asphalts Charles Glover TTI

NCHRP 9-49 Performance of WMA Technologies: Stage I--Moisture Susceptibility

Amy Epps Martin, Cindy

Estakhri TTI

NCHRP 9-49A Performance of WMA Technologies: Stage II--Long-Term Field Performance

Shihui Shen Washington State University

Section No. Type Binder RAP RAS

1 HMA 70-22 0 0

7 WMA Foaming 70-22 0 0

8 WMA Additive 70-22 0 0

9 WMA Additive 64-22 15 3

3 HMA 64-22 15 3

4 HMA 64-22 0 5

2 HMA 64-22 30 0

5 HMA 58-28 30 0

6 HMA 58-28 15 3

FM 973 Between FM 969 and HWY 71

• Type C mix • Limestone C, D, F, Mfg.

Sand + Field Sand • Section length ~ 2,040 ft • Sections 1 & 7: 400 tons • Sections 2-6,8,9: 800 tons Austin Bergstrom Int. Airport

Construction

PAVE _IR

LABORATORY FINDINGS

Section No. Type Binder RAP RAS

1 HMA 70-22 0 0

7 WMA Foaming 70-22 0 0

8 WMA Additive 70-22 0 0

9 WMA Additive 64-22 15 3

3 HMA 64-22 15 3

4 HMA 64-22 0 5

2 HMA 64-22 30 0

5 HMA 58-28 30 0

6 HMA 58-28 15 3

FM 973 Between FM 969 and HWY 71

• Type C mix • Limestone C, D, F, Mfg.

Sand + Field Sand • Section length ~ 2,040 ft • Sections 1 & 7: 400 tons • Sections 2-6,8,9: 800 tons Austin Bergstrom Int. Airport

Sections highlighted in yellow being used in this project

Upper limit of binder replacement

16

Section Type Binder RAP RAS 1 HMA 70-22 0 0 2 HMA 64-22 30 0 3 HMA 64-22 15 3 4 HMA 64-22 0 5

01020304050607080

OT

Cycl

es

Overlay Test0

1

2

3

4

5

Rut D

epth

(mm

)

Hamburg Test@10000passes

Impact of Soft Binder

17

Section Type Binder RAP RAS 2 HMA 64-22 30 0 5 HMA 58-28 30 0

0

5

10

15

20

25

PG64-22/30%RAP PG58-28/30%RAP

OT

Cycl

es

Overlay Test0

1

2

3

4

5

6

7

8

9

10

PG64-22/30%RAP PG58-28/30%RAP

Rut D

epth

(mm

)

Hamburg Test@10000passes

Objectives: NCHRP 9-49

Select conditioning/curing protocol for WMA

Evaluate if/when WMA = HMA

Evaluate moisture susceptibility of WMA

18

Section No. Type Binder RAP RAS

1 HMA 70-22 0 0

7 WMA Foaming 70-22 0 0

8 WMA Additive 70-22 0 0

9 WMA Additive 64-22 15 3

3 HMA 64-22 15 3

4 HMA 64-22 0 5

2 HMA 64-22 30 0

5 HMA 58-28 30 0

6 HMA 58-28 15 3

FM 973 Between FM 969 and HWY 71

• Type C mix • Limestone C, D, F, Mfg.

Sand + Field Sand • Section length ~ 2,040 ft • Sections 1 & 7: 400 tons • Sections 2-6,8,9: 800 tons Austin Bergstrom Int. Airport

Sections highlighted in yellow being used in this project

Time Horizon: WMA = HMA

20

100

200

300

400

500

600

700

800

900

1000

0 1 2 3 4 5 6 7 8 9

Resi

lient

Mod

ulus

( R

oom

Tem

pera

ture

25C

)

Time (Weeks)

HMA

Evotherm

Foaming

HMA+RAP/RAS

Equivalent stiffness ≈ 3 weeks

Lab Mix-Lab Compacted (LMLC) Specimens

Moisture Susceptibility: HWTT @ 10,000

21

4.4

5.9

8.1

2.4

5.1 5.8

9.0

12.3

8.9

12.5+

0

2

4

6

8

10

12

14

HMA Evotherm FOAMING HMA+RAP/RAS Evotherm+RAP/RAS

Rut D

epth

(mm

)

Mixture Type

Off-Site PMLCPMFC

Off-Site Plant Mix-Lab Compacted (PMLC) Plant Mix Field Cores (PMFC)

Moisture Susceptibility: TSR, MR Ratio

22

Section MIX TYPE RAP, %

RAS, %

TSR, %

MR RATIO, %

3 HMA w/RAP/RAS 15 3 91 106

9 WMA Additive w/RAP/RAS 15 3 85 94

1 HMA 0 0 74 69

8 WMA Additive 0 0 73 74

7 WMA Foaming 0 0 65 63

Off-Site Reheated Plant Mix-Lab Compacted (PMLC) Specimens

FIELD FINDINGS

23

Transverse Cracking

Raveling

Fatigue & Longitudinal

Cracking

Examples of Distress on FM 973

FM 973 Performance (14 Months) – HMA Sections

Section Binder RAP RAS

Distress

Long WP (LF)

Fat. Crk.

Long N-WP (LF)

Trans Crk.

Raveling Index

1 70-22 (Control) 0 0 10 0 25 0 3.0

2 64-22 30 0 35 0 25 0 3.5

5 58-28 30 0 40 4 25 0 3.5

3 64-22 15 3 150 2 260 7 3.5

6 58-28 15 3 20 0 100 1 4.5

4 64-22 0 5 430 8 130 18 3.5

FM 973 Performance (14 Months) – WMA Sections

Section Binder RAP RAS

Distress

Long WP (LF)

Fat. Crk.

Long N-WP (LF)

Trans. Crk

Raveling Index

1 70-22 (Control) 0 0 10 0 25 0 3.0

7 70-22 WMA

Foaming 0 0 25 0 20 0 3.5

8 70-22 WMA

Additive 0 0 30 0 25 0 4.0

9 64-22 WMA

Additive 15 3 20 0 30 1 4.5

3 64-22 15 3 150 2 260 7 3.5

ECONOMICS – COST/BENEFIT

27

Economics – Initial Cost Savings of FM 973

28

Initial Material Cost Savings from Grade Bumping AC

Section No. Type Binder RAP RAS Target

AC FRAP

AC RAS AC

AC Cost (No Recycled AC)

AC Cost (With

Recycled AC)

9 WMA Additive 64-22 15 3 5.3 5 20 $27,560 $20,540

3 HMA 64-22 15 3 5.3 5 20 $27,560 $20,540

4 HMA 64-22 0 5 5.4 0 20 $28,080 $22,880

2 HMA 64-22 30 0 5.2 5 0 $27,040 $19,240

5 HMA 58-28 30 0 5.2 5 0 $27,040 $19,240

6 HMA 58-28 15 3 5.3 5 20 $27,560 $20,540

Total Cost Savings $41,860

Percent Cost Savings 25%

Economics – Long-Term Maintenance Costs (Last 2 years)

29

Year Routine Maintenance RM Expenses Non-RM

Expenses Total

1 None - - -

2 Crack Seal $9390 $2348 -$11,738

Initial Construction Cost Savings $41,860

Cost Savings Remaining (after 2 years of RM costs) $30,122

% Reduction of Cost Savings within 2 year of Service -28%

SUMMARY OF CONCLUSIONS

Conclusions – Recycled Materials

31

Lab Field

RAP/RAS stiffen mix Control section (polymer modified) best

RAP stiffens more than RAS 5% RAS worst

RAP/RAS improves rutting, moisture susceptibility RAP sections better than RAS

RAP/RAS more cracking Soft virgin binders help

Soft virgin binders reduce stiffness

RAP/RAS sections require crack sealing

Conclusions – Recycled Materials

32

Lab Field

Standardized mixture conditioning

WMA & HMA with PG 70-22 about same performance

FMLC @ plant vs reheating WMA chemical additive & WMA Foam about same performance

WMA more susceptible to moisture in short term

WMA improved performance of RAP/RAS

WMA stiffness after few months equals initial HMA stiffness

WMA reduces aging in long term - inconclusive

Conclusions – Implementation – Austin District

97% target density Minimum HWTT of 4 mm Use WMA with RAP/RAS mixtures High RAP/RAS with pretreatment Contractor demonstrate RAP/RAS more

resistant to cracking – Extracted/recovered binder – Overlay test

33

WATER WATER

“Half Full” 95% Full


Recommended