    INSPECTION AND REFURBISHIINGINSTRUCTIONS FOR CESSNA AIRCRAFT

    SURFACE SEAL* COATING SYSTEM

    DOCUMENT / PART NUMBER DSS 1001-300, REVISION H

    MAINTENANCE, ASSESSMENT, APPLICATION PROCEDURESFOR AIRCRAFT AND SPECIALTY GLASS-FACED WINDSHIELDS

    October 2006

    *Surface Seal and the logo are registered United States trademarks of PPG Industries Ohio,Inc.

  • 7/22/2019 SURFACE SEAL

    2/30

    This page intentionally left blank.

  • 7/22/2019 SURFACE SEAL

    3/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long asand to the extent that such information and data remain unpublished.

    iii

    Revisions

    Revision Date Page(s)Af fec ted

    By Approval Description Of Change

    H 10/18/06 All JWM DAB Complete update.

  • 7/22/2019 SURFACE SEAL

    4/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long asand to the extent that such information and data remain unpublished.

    iv

    Table of Contents

    Section Page

    1 Surface Seal Coated Glass...............................................................................................12 Maintenance, Measurement, and Refurbishment .............................................................13 The Coating-Efficiency Measurement Process .................................................................24 Measurement Kit Contents................................................................................................25 Health & Safety .................................................................................................................36 Coating-Efficiency Measurement Procedure.....................................................................37 The Re-Application Process..............................................................................................78 Master Kit Contents...........................................................................................................89 Curing Kit Contents ...........................................................................................................910 Health & Safety .................................................................................................................911 Re-Application Procedure ...............................................................................................10REORDER FORMS....................................................................................................................17

  • 7/22/2019 SURFACE SEAL

    5/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    1

    1 SURFACE SEAL COATED GLASS

    Developed to enhance pilot vision during rain conditions, Surface Seal coated glass from PPG

    Industries incorporates a transparent, water-repellent coating for efficient, cost-effective rain

    removal.

    2 MAINTENANCE, MEASUREMENT, AND REFURBISHMENT

    Although Surface Seal coated glass is easily maintained and protected by routine cleaning

    practices, the coating may not last the entire service life of some windshields. Periodic

    measurement of coating efficiency can be timed to coincide with regularly scheduled aircraft

    maintenance. And if refurbishment becomes necessary, a straight forward re-application will

    provide a like-new coated glass surface.

    To assist in that process, PPG offers the Surface Seal coating system, which includes three

    customized kits for coating-efficiency measurement and refurbishing. The measurement Kit

    contains the equipment and supplies needed to periodically measure the efficiency of the

    coating. It's available as a "stand-alone" kit; and it's also included in the Master Kit, which

    contains materials needed for re-application of the coating. The Curing Kit, containing

    protective films and customized heating blankets, completes the package.

    Safety glasses, a tape measure and pen or pencil are also required to complete the entiremeasurement and re-application process. These are not included in any kit and must be

    supplied by you.

    In planning the project, allow about 30-45 minutes for coating-efficiency measurement; about

    60-to-75 minutes for coating re-application; and 15-to-30 minutes for cleanup after heat curing,

    which takes a full eight hours(after proper installation of the heat blanket).

  • 7/22/2019 SURFACE SEAL

    6/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    2

    3 THE COATING-EFFICIENCY MEASUREMENT PROCESS

    In preparation for contact-angle measurement, first watch the PPG Video, titled "Coating

    Efficiency Measurement", which provides overall direction, and step-by-step guidelines. This

    video is contained in both the Measurement Kit and Master Kit.

    These written instruc tions are designed to supplement that video and should not be

    used without fir st watching the video program.

    Inspect the contents of the Measurement Kit carefully, and read all identification labels.

    Except for the safety glasses, tape measure, and pen or pencil, all supplies and equipment

    needed for contact-angle measurement are included in the Measurement Kit. Use only these

    materials throughout the process, and make no substi tutions.

    4 MEASUREMENT KIT CONTENTS

    Part Number Description

    DSS 1001 Instruction BookletDSS 1003 Video: "Coating-Efficiency Measurement"DSS 1009 MacroscopeDSS 1010 Illuminator/PenlightDSS 1011 Batteries (2), AADSS 1013 Eppendorf, Repeater

    DSS 1019 Deionized Water - 500 mL BottleDSS 1029 Spray NozzleDSS 3003 Kit C, Measurement Refill

    (Includes the following)Packing List/Reorder FormGloves (50)Pipetter Tips (10)Cleaning Cloths (1 box)Deionized Water (500 mL bottle)

    Post-ItNote Pad (3"x3")Disposal Bags (25)

    DSS 3004 Container Case for Measurement Kit

    To protect materials during transit, all liquids have been closed-capped for shipment. Retain

    original cap for use in future shipment.

  • 7/22/2019 SURFACE SEAL

    7/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    3

    5 HEALTH & SAFETY

    Disposable gloves and safety glasses should be worn at all times throughout the coating

    efficiency measurement process, unless otherwise noted in the instructions below.

    6 COATING-EFFICIENCY MEASUREMENT PROCEDURE

    Before beginning, remove one disposal bag from the kit and place it in a convenient, nearby

    location so that used materials can easily and safely be discarded throughout the process.

    Make sure you wear disposable gloves throughout the cleaning process to keep oil from your

    skin off the glass. We recommend wearing two pair of gloves and changing only the outer

    pair, when called for in these instructions. By keeping one pair of gloves on your hands, you'll

    find putting on and removing the second pair much easier.

    Step 1 - Windshield Preparation

    Obtain a Cessna approved glass cleaner.

    NOTE. PPG furnished glass cleaner (Solution No. 1) has been deleted from kits effective with

    this Rev. 2 of the Inspection & RefurbishinqInstructions.

    With disposable towels from the kit, clean the windshield thoroughly. Deposit soiled towels in

    the disposal bag.

    Check your aircraft maintenance manual to locate the critical vision area on the glass.

    NOTE: It may be useful to locate the four corners of the critical vision area by marking them

    with a "Post-It" note sheet on the inside surface of the windshield. The central area enclosed

    by the note sheets is the critical vision area - the area of primary importance in this

    measurement

    To ensure cleanliness within the critical vision area, re-apply the glass cleaner at least twice,

    wiping thoroughly with disposable towels after each application.

  • 7/22/2019 SURFACE SEAL

    8/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    4

    Step 2 - Measurement Procedure

    Obtain the 500 ML bottle of deionized water and the spray nozzle from the kit. Replace the

    closed cap on the bottle with the spray nozzle. With the nozzle pointing away, turn the nozzle

    adjustment counterclockwise until no adjustment remains. The nozzle is now set to deliver a

    fine mist.

    If the disposable gloves have been removed after windshield cleaning, replace them with

    another pair. Avoiding possible contamination of the glass surface from skin oil is important in

    this assessment.

    Starting at the bottom of the windshield and with the nozzle at a distance of approximately

    12" from the glass, pump the spray nozzle to fully wet the windshield with mist from one side to

    the other. Progressively work up

    the windshield until the surface is fully misted. Starting at one side along the top edge,

    continue spraying the windshield until water droplets roll freely down the windshield. Continue

    across the windshield along the top edge until water droplets have rolled freely to the bottom of

    the windshield completely across the windshield. Smaller droplets that "crawl" through an area

    should be ignored.

    NOTE: Once droplets are rolling freely down the windshield, do not continue to spray the same

    area. "Doubled-up" tracks may provide confusing results.

    Examine the appearance of the remaining water on the windshield and the droplet tracks.

    Compare within the critical vision area to the photographs and photograph explanation

    contained in the aircraft maintenance manual.

    If the coating assessment is judged to be "like new" or "acceptable", no further action is

    required.

    If the coating assessment is judged to be "conditional", coating refurbishment should be

    scheduled, or the alternate measurement procedure (Steps 3 through 6) should be performed.

    If the coating assessment is judged to be "unacceptable" coating refurbishment must be

    accomplished. Proceed to Step 6 - Follow-up.

  • 7/22/2019 SURFACE SEAL

    9/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    5

    Once the water misting assessment has been completed, remove the spray nozzle from the

    water bottle and pump all water out of nozzle. Recap the water bottle, and return it and the

    nozzle to the kit.

    Step 3 - Alternate Measurement Procedure Via Contact Angle Measurement

    If the windshield is wet from the misted water procedure, dry it thoroughly using disposable

    towels from the kit.

    If the windshield coating efficiency has not been assessed using the misted water procedure,

    the windshield should be prepared using, Step 1 - Windshield Preparation, before proceeding

    further.

    Remove the macroscope from the instrument case. Focus the reticle with the upper knurled

    ring, and set it aside.(Note: a battery-powered illuminator is supplied for use in reduced-lighting

    conditions.)

    Remove the pipetter from the instrument case. Attach a 500 microliter tip; fill it with

    Deionized Water (Solution No. 2), and set the pipetter dial to "one."

    Because the pipetter can dispense an incorrect amount of water the first time, release one

    ten-microliter drop onto a non-test area of the windshield and wipe it away.

    Move to the first specified test location and gently push out one ten-microliter drop of

    Deionized Water from the pipetter and touch the drop to the windshield. Slowly withdraw thepipetter, leaving the drop on the glass surface undisturbed. (The "Coating-Efficiency

    Measurement" video demonstrates this procedure in detail.)

    Step 4 - Measurement

    Since evaporation will affect accuracy, drop-length dimension must be measured and recorded

    within one minute of drop placement.

    Place the macroscope on the glass surface, centered over the water droplet. (Removal of

    safety glasses will reduce awkwardness and widen your field of vision.)

    Adjust the image focus along the longest dimension of the drop, using the lower knurled ring.

    Adjust the macroscope position relative to the drop until the image is in focus and one end of

    the drop lines up with the zero mark, as shown.

  • 7/22/2019 SURFACE SEAL

    10/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    6

    With one edge of the water droplet lined up with the zero mark, estimate the drop length to

    0.05 millimeter accuracy (minimum scale division is 0.1 millimeter). Use only the upper scale of

    the reticle, which is 0 to 5 millimeters. (in the view shown, the drop length is 4.00 millimeters.)

    Record the measurement onto the "Post-it" sheet. If the length is more than five millimeters,

    record the drop length as >5 millimeters.

    Repeat the procedure until five readings have been recorded at the first location. If one

    measurement is significantly different than the others, do not use it. Instead, repeat the

    measurement.

    Once five measurements have been made at all specified locations, calculate the average

    for each location, and write it on the "Post-it" sheet.

    Step 5 - Correlating Drop Dimension w ith Contact Angle

    To correlate the drop dimension with contact angle, compare each of the average drop-

    length measurements with the appropriate chart in your aircraft maintenance manual.

    Compare the lowest contact angle with the maintenance manual specifications to determine

    whether refurbishment is required.

    Step 6 - Follow-Up

    If refurbishment is indicated, make all necessary scheduling arrangements for reapplication.Note that it may be preferable and more convenient to refurbish both transparencies at the

    same time, even if only one is required.

    Schedule the next coating-efficiency measurement, as per your aircraft maintenance manual

    instructions.

    Complete all paperwork; return all equipment and reusables to their proper place; discard

    disposal bag in accordance with national, regional and local regulations.

    Take an immediate inventory of all contents of the Measurement Kit. If supplies must be

    reordered, make a photocopy of the Kit C reorder form contained in this instruction booklet.

    Complete the form, and mail or fax it, as per reorder form directions.

  • 7/22/2019 SURFACE SEAL

    11/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    7

    7 THE RE-APPLICATION PROCESS

    If the results of the coating efficiency measurement indicate that refurbishment is required,

    prepare for re-application of the coating by first watching the PPG video, titled 'Re-Application

    Procedure.' Contained in the Master Kit, this video proves step-by-step guidelines and overall

    direction.

    These written instructions are designed to supplement the video, and should not be used

    without first watching the video program.

    Materials needed for re-application of the coating are contained in the Master Kit and Curing

    Kit. Throughout this process, use only PPG-approved chemical materials, as provided, and do

    not make any substitutions.

    Inspect the contents of the Master Kit and Curing Kit carefully, reading all identification labels

    and noting any health and safety information.

  • 7/22/2019 SURFACE SEAL

    12/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    8

    8 MASTER KIT CONTENTS

    Part Number DescriptionDSS 1001 Instruction BookletDSS 1002 Video: 'Re-Application Procedure"

    DSS 1003 Video: "Coating-Efficiency Measurement"DSS 1004 Material Safety Data Sheets

    (MSDS) Sheets for Kit A and Kit B

    DSS 1005 Orbital Sander, with 1 1 5V ChargerDSS 1006 Orbital Sander (for export only)DSS 1007 Charger for Sander, 220V (for export only)

    DSS 1009 MacroscopeDSS 1010 Illuminator/PenlightDSS 1011 Batteries (2), AADSS 1013 Eppendorf, Repeater

    DSS 1014 Bottle, 15 mL (for Deionized Water)

    DSS 1015 Kit A (2), Application(each Kit A for one window only)

    Packing List/Reorder FormMSDS Sheets(Surface Prep, Next Generation Coating Solution)Felt Pad in Plastic Bag (1 Ea)Surface Prep (2), 20 mL AmpulesNext Generation Coating Solution (1), 20 mL Ampule

    Applicators (10) in Plastic BagDSS 1016 Kit B, Master Refill

    Packing List/Reorder FormMSDS Sheets(Cleaning Solvent, Polishing Slurry)Gloves (1 00)Pipetter Tips (25)Cleaning Cloths (2 boxes)Tape, 1/4" (1 roll)Tape, 2" (3 rolls)Cleaning Solvent (500 mL bottle)Polishing Slurry (250 mL bottle)Gauze Pads (100)Flip-Top Caps (4) for Reusable BottlesPost-it Note Pad (3"x3")

    Disposal Bags (25) (13 x 18)DSS 1017 Container Case for Master KitDSS 1018 ScissorsDSS 1019 Deionized Water - 500 mL BottleDSS 1029 Spray Nozzle

  • 7/22/2019 SURFACE SEAL

    13/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    9

    To protect materials during transit, all liquids have been closed-capped for shipment. With the

    exception of the15 ml container for Demonized Water (Solution No. 2), replace closed caps

    with flip-top caps, packed inside the zippered pouch. Screw caps on tightly and make certain

    that each cap is fully closed after each use. Retain original caps for use in future shipment.

    9 CURING KIT CONTENTS

    Part Number Description

    DSS 2007 Heater, 115V (9914380-1)DSS 2008 Heater, 220V (9914380-1) - For ExportDSS 2009 Heater, 115V (9914380-2)DSS 2010 Heater, 220V (9914380-2) - For ExportDSS 2011 Heater, 115V (9914379-1)DSS 2012 Heater, 220V (9914379-1) - For ExportDSS 2013 Heater, 115V (9914379-2)DSS 2014 Heater, 220V (9914379-2) - For ExportDSS 2015 Protective Films, 10 each (9914380)DSS 2016 Protective Films, 10 each (9914379)DSS 2017 Container Case for Curing Kit(9914379 & 80)

    10 HEALTH & SAFETY

    Disposable gloves, as included in the Master Kit, should be worn at all times during cleaning,

    chemical application and clean-up.

    Because a change of gloves is called for several times during the re-application procedure, it is

    suggested that two pair be worn at the same time. Changing only the outer pair eases and

    facilitates the glove-changing process.

    Safety glasses, although not included in the kit, should also be worn from start to finish.

    All steps in the process should be performed in a well ventilated area.

    For additional health and safety information, read the MSDS sheets stored in the Master Kit.

    Study this material thoroughly before beginning the project.

  • 7/22/2019 SURFACE SEAL

    14/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    10

    11 RE-APPLICATION PROCEDURE

    Before re-application can begin, two preliminary steps must be taken. First, make certain that

    the rechargeable orbital sander is fully charged. If not, follow the instructions found inside the

    box for proper preparation, making careful note of all safety precautions. Allow about one hour

    for a complete charge.

    Next, remove one disposal bag from the Master Kit and place it in a convenient, nearby

    location so that used materials can easily and safely be discarded throughout the process.

    Put on your disposable gloves and begin.

    Step 1 - Initial Cleaning

    If the windshield is not already clean from the Coating-Efficiency Measurement Process,obtain a Cessna approved glass cleaner.

    NOTE. PPG furnished glass cleaner (Solut ion No. 1) has been deleted from ki ts effective

    with Rev. 2 of these inspection and refurbishing instruct ions. With disposable towels

    from the Master Kit, thoroughly c lean the windshield, removing all foreign materials.

    Deposit soiled towels into the disposal bag.

    Using quarter-inch tape from the Master Kit, mask the glass periphery of the windshield, right

    up to the moisture seal, avoiding the bleed-air shroud. Trim as necessary, using the scissorsfrom the Master Kit.

    NOTE: You may remove your disposable gloves here, if you find the taping process

    easier to do bare-handed.

    Remove a roll of two-inch tape from the Master Kit, and apply it to the windshield, partly

    overlapping the quarter-inch tape, spanning the moisture sealant, and terminating on the

    windshield metal retainer. Although quarter-inch tape is not applied along the bleed-air shroud,

    apply two-inch tape from the glass up onto the shroud. This will prevent any possible

    contamination behind the shroud. (The 'Re-Application Procedure' video demonstrates this

    step in detail.)

  • 7/22/2019 SURFACE SEAL

    15/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    11

    Return the tape and scissors to the Master Kit, and if gloves have been removed or torn

    during the taping process, replace them before proceeding. (Gloves are extremely important in

    subsequent steps because elimination of skin-oil contamination is critical.)

    Remove the felt pad from the plastic bag inside the box labeled Kit A, and attach it to the

    fully charged orbital sander. (The PPG-supplied sander is the only one approved for this

    process. Make no substitution. Use of other equipment can result in contamination of the glass

    surface.)

    Remove the bottle of Polishing Slurry (Solution No. 3). Shake it well, and liberally apply the

    fluid to the felt pad. Be certain that no extraneous dirt or grit of any kind contacts the felt pad,

    and make certain it is thoroughly moistened with slurry prior to contact with the pre-cleaned

    glass surface.

    Lightly set the felt pad onto the glass surface and activate the sander. Using overlapping

    strokes, cover the entire glass surface evenly. Add additional slurry as needed to keep the felt

    pad well moistened throughout the process. A thin, cloudy film of slurry will be left on the glass

    surface, but if it "breaks up," that is, if the water in the Polishing Slurry does not remain in a

    thin film, repeat polishing operation.

    NOTE: Af ter two polishings on anti-static coated wind-shields there may st ill be areas

    that break up . This is the nature of anti-static coatings. Do not polish any further.

    After the slurry has been thoroughly applied, set the sander aside temporarily, placing it

    onto a clean, disposable towel. Remove your soiled gloves and place them in the disposal bag.

    NOTE. Remove soiled gloves carefully by pul ling the cuff down over your hand so that

    the glove is removed inside out. This prevents any possible contamination by contact

    with the glove as it is deposited into the disposal bag.

    Put on new gloves, and remove the 500 ML container of Deionized Water (Solution No. 2)

    and several disposable towels from the kit. Wash and dry the windshield thoroughly to remove

    all traces of Polishing Slurry and continue wiping until the glass is completely dry.

    Don't let thick water films evaporate, as this causes contamination of the surface; and don't

    use any other chemicals to remove the Polishing Slurry residue.

  • 7/22/2019 SURFACE SEAL

    16/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    12

    Remove your soiled gloves and deposit them in the disposal bag.

    The windshield glass surface is now extremely clean, and ready for the next step. But, before

    moving on, review all safety and health information for Surface Prep (Solution No. 4) and

    Coating Solution (Solution No. 5), provided on the container labels and MSDS sheets.

    Step 2 - Surface Preparation

    Put on a clean pair of disposable gloves, and remove one Surface Prep ampule and two

    applicators from Kit A in the Master Kit.

    The Surface Prep ampule is surrounded by sealed plastic tubing above the foam. To open it,

    use scissors to cut off a corner of the plastic tubing at the top. Do not cut into the foam.

    Hold the ampule assembly with the cut tubing pointing upward. Break the seal by bending the

    ampule above the cylindrical reservoir.

    Hold the ampule so you can clearly see the fluid level between the edges of the label. Pour a

    liberal amount of the fluid onto one of the applicator pads. Do not saturate the applicator to the

    extent that any fluid drips off.

    Apply the Surface Prep to the windshield, using slightly overlapping strokes. Work at a

    moderate speed, covering approximately two feet per second.

    A thin film of solution will trail from the applicator and quickly evaporate from the glass surface.Do not allow thick films of liquid to accumulate on the glass surface.

    After the entire windshield has been covered, repeat the application process, using a new

    applicator. Again, be sure not to over-saturate the pad.

    Visually inspect the outside surface of the windshield making certain that there is no

    streaking or remaining haze. If any appears, buff the windshield with dry gauze pads from the

    Master Kit until the windshield is perfectly clear. Then place the used applicators, used gauze

    pads, disposable gloves, and used Surface Prep ampule into the disposal bag.

    If streaking or haze persists, it may be caused by a residue of Surface Prep solution remaining

    on areas where too much was applied, and a thick film was allowed to evaporate.

  • 7/22/2019 SURFACE SEAL

    17/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    13

    However, before attempting any removal of the streaking or haze, first make certain the

    problem is not actually due to contamination on the interior surface of the windshield.

    If the streaking or haze is localized, you should be able to remove the extra Surface Prep

    thickness by reworking just that one area. Apply some Polishing Slurry to the felt pad, and use

    the orbital sander to lightly polish the problem area. Clean the area with Deionized Water and

    dry it with a clean disposable towel. Examine the area to see if the problem persists. If it

    does, repeat this sequence of light polishing, washing and drying until the streaking or haze is

    eliminated.

    If the problem is wide-spread across the windshield, you will need to repeat all previous steps,

    using the sander and Polishing Slurry on the entire glass surface.

    After the haze or streaking has been eliminated, remove your soiled gloves and put on a cleanpair. Thoroughly wash and dry the entire windshield surface using Deionized Water and clean

    disposable towels.

    If you do need to re-apply the Surface Prep, an additional ampule and applicators are included

    in Kit A.

    If re-application is not required, retain the extra Surface Prep ampule for possible future use.

    Keep it, along with the proper health and safety instructions, inside the Master Kit.

    Remove the felt pad from the orbital sander and place it in the disposal bag. Wipe off the

    sander with towels, and return it to the storage box in the kit. Remove your soiled gloves and

    deposit them into the disposal bag.

    Step 3 - Coating Procedure

    Put on clean, disposable gloves, and remove the Coating Solution ampule and another

    applicator from Kit A. Repeat the previously explained technique for opening the ampule; cut

    off the top corner of the plastic tubing surrounding the ampule above the foam; hold the

    ampule assembly with the cut tubing pointing upward; break the seal by bending the ampule

    above the cylindrical reservoir.

  • 7/22/2019 SURFACE SEAL

    18/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    14

    Pour a liberal amount of the solution onto the applicator, and wipe the Coating Solution onto

    the glass surface, using quick, circular motions. Begin in the critical vision areas and work

    toward the outer edges of the windshield.

    As the applicator becomes dry, add more solution, and continue the process until the ampule

    is empty. A haze will form over the entire glass surface.

    Place the used applicator, empty ampule, and soiled gloves into the disposal bag. Dispose of

    these materials in full accordance with national, regional, and local regulations.

    Step 4 - Heat Cure

    To accomplish this procedure, the Curing Kit is required.

    First, remove the two-inch tape from the bottom of the windshield and shroud to allow room

    for the protective film and specially designed heating blankets, as contained in the Curing Kit.

    Carefully place the correct sheet of protective film over the windshield, making sure to line up

    all edges. Then secure the film to the surface at each corner, with short strips of quarter-inch

    tape.

    Apply the heating blanket to the windshield's surface and anchor it securely in place, using

    two-inch tape. Then, plug the blanket into the proper power source.

    The blanket temperature has been pre-set to maintain150 degrees Fahrenheit for the heat

    curing process, which can continue for up to eight hours.

    NOTE: See Cessna aircraft maintenance manual regarding heat cure and duration of

    heat cure options.

    CAUTION:

    Al though heat blankets do not transfer heat qu ickly, the temperature o f the exposed

    surface will be high, so avoid any direct contact during the heat cure period.

    You may want to use this time to recharge your orbital sander battery so that it's ready and

    waiting for the next application. In any case, your work is temporarily completed. Close your

  • 7/22/2019 SURFACE SEAL

    19/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    15

    disposal bag and dispose of it in full accordance with all national, regional and local

    regulations. The empty Kit A box can be placed in any convenient trash bin.

    After up to eight hours have elapsed, unplug the blanket and allow it to cool down to near-

    ambient room temperature. This should require no more than five or ten minutes.

    After checking carefully to make certain that the blanket is not too hot to handle, remove the

    tape, blanket, and protective film. Return the blanket to its proper place in the Curing Kit.

    Remove all two-inch and quarter-inch tape still attached to the windshield and dispose if it,

    along with the protective film, in any convenient trash bin.

    Put on a clean pair of disposable gloves, remove several disposable towels, and the

    Cleaning Solvent (Solution No. 6) from the Master Kit. Using Cleaning Solvent, remove all

    visible haze from the aircraft windshield, and any residue remaining from the tape.

    Because the haze tends to smear rather than clean off easily, this will require some effort. Any

    variety of wiping techniques can be used, but a two-step approach is recommended: make one

    pass with a wet disposable towel moistened with Cleaning Solvent; make a second pass using

    a dry one. Several sets of wipings will be necessary.

    After haze has been removed, wash the windshield with Deionized Water and dry it with

    disposable towels.

    Because the windshield surface is now extremely water-repellent, it may be easier to apply

    water to the towels rather than applying it directly to the glass.

    Discard your disposable gloves (pulling them off inside out) and place them in a disposal bag

    along with any used towels. Seal the top of the bag, and dispose of it in full accordance with

    national, regional, and local environmental regulations.

    At this point, refurbishment is complete. However, effectiveness of the treatment and efficiency

    of the coating must be measured.

    Coating-Efficiency Measurement

    Repeat the coating-efficiency measurement procedure explained in Step 2 of the Coating

    Efficiency Measurement Procedure in this booklet, and demonstrated on the video cassette,

  • 7/22/2019 SURFACE SEAL

    20/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    16

    titled 'Coating-Efficiency Measurement", found in the Master Kit. Or, use the Alternate

    Measurement Procedure - Step 3, via Direct Measurement of Contact Angle.

    For each measurement position, the contact angle corresponding to the average drop length

    should be at least 1 00 degrees. If the readings are not 100 degrees, repeat the haze removal

    process and re-inspect.

    Once the job is complete, take an immediate inventory of all Master Kit contents. Make certain

    that all equipment and re-usables have been returned to their proper places. As necessary,

    make photocopies of the order forms included in this booklet. Complete the form, and mail or

    fax it, as per order form instructions.

    .

  • 7/22/2019 SURFACE SEAL

    21/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    17

    REORDER FORMS

    List of Figures

    Figure I Master Kit...........................................................................................................................18Figure II Measurement Kit...............................................................................................................19Figure III Curing Kit .........................................................................................................................20Figure IV Kit A - Application ............................................................................................................21Figure V Kit B Master Refill..........................................................................................................22

    Figure VI Kit C Measurement Refill ..............................................................................................23Figure VII Shipping Information ......................................................................................................24Figure VIII Billing Information..........................................................................................................25

  • 7/22/2019 SURFACE SEAL

    22/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    18

    Surface Seal Coating System

    Master Kit

    Reor der Par tQuant i t y Number Descr i pt i on

    ________ DSS 1000 Mast er Ki t , Compl et e________ DSS 1OOOX Mast er Ki t , Compl et e ( f or expor t )

    ________ DSS 1001 I nst r uct i on Bookl et________ DSS 1002 Vi deo, Re- Appl i cat i on Pr ocedure________ DSS 1003 Vi deo, Coat i ng- Ef f i ci ency Measur ement________ DSS 1004 Mat er i al Saf et y Dat a Sheet s ( MSDS) f or Ki t A and Ki t B________ DSS 1005 Or bi t al Sander , wi t h 115V Charger________ DSS 1006 Or bi t al Sander ( f or export onl y)________ DSS 1007 Charger f or Sander , 220V ( f or export onl y)________ DSS 1009 Macr oscope________ DSS 1010 I l l umi nator / Penl i ght________ DSS 1011 Bat t er i es ( 2) , AA________ DSS 1013 Eppendor f , Repeat er________ DSS 1014 Bot t l e, 15 mL________ DSS 1015 Ki t A, Appl i cat i on ( f or one wi ndow onl y)

    ________ DSS 1016 Ki t B, Mast er Ref i l l________ DSS 1017 Case f or Mast er Ki t________ DSS 1018 Sci ssor s________ DSS 1019 Bot t l e, 500 mL, Dei oni zed Wat er________ DSS 1029 Spray Nozzl e

    Figure I Master Ki t

    To reorder kits or components, photocopy this form, write quantities above, and

    send to:

    Cessna Ai r cr af t CompanyAt t n: CPD Sal es Depar t mentP. O. Box 7706Wi chi t a, KS 67277- 7706 USA

    Or photocopy and FAX this reorder form to: ( 316) 517- 7711; At t n: Sal esDepar t mentBe sure to include a copy of the completed Billing and Shipping Information

    form.

  • 7/22/2019 SURFACE SEAL

    23/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    19

    Surface Seal Coating System

    Measurement Kit

    Reor der Par tQuant i t y Number Descr i pt i on

    ________ DSS 3000 Measur ement Ki t , Compl et e________ DSS 1001 I nst r uct i on Bookl et________ DSS 1003 Vi deo, Coat i ng - Ef f i ci ency Measur ement________ DSS 1009 Macr oscope________ DSS 1011 Bat t er i es ( 2) , AA________ DSS 1013 Eppendor f , Repeat er________ DSS 1019 Bot t l e, 500 mL, Dei oni zed Wat er________ DSS 1029 Spray Nozzl e________ DSS 3003 Ki t C, Measur ement Ref i l l________ DSS 3004 Case f or Measur ement Ki t

    Figure II Measurement Ki t

    To reorder kits or components, photocopy this form, write quantities above, and

    send to:

    Cessna Ai r cr af t CompanyAt t n: CPD Sal es Depar t mentP. O. Box 7706Wi chi t a, KS 67277- 7706 USA

    Or photocopy and FAX this reorder form to: ( 316) 517- 7711; At t n: Sal esDepar t ment

    Be sure to include a copy of the completed Billing and Shipping Information

    form.

  • 7/22/2019 SURFACE SEAL

    24/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    20

    Surface Seal Coating System

    Curing Kit

    Reorder Part

    Quantity Number Description

    ________ DSS 2000 Cur i ng Ki t , 115V ( 9914379 & 80)________ DSS 2001 Cur i ng Ki t , 220V ( 9914379 & 80)________ DSS 2002 Cur i ng Ki t , 115V ( 9914380)________ DSS 2003 Cur i ng Ki t , 220V ( 9914380)

    ________ DSS 2004 Cur i ng Ki t , 115V ( 9914379)________ DSS 2005 Cur i ng Ki t , 220V ( 9914379)

    ________ DSS 2007 Heater , 115V ( 9914380- 1)________ DSS 2008 Heater , 220V ( 9914380- 1)________ DSS 2009 Heater , 115V ( 9914380- 2)________ DSS 2010 Heater , 220V ( 9914380- 2)

    ________ DSS2011 Heat er , 115V ( 9914379- 1)________ DSS 2012 Heater , 220V ( 9914379- 1)________ DSS 2013 Heater , 115V ( 9914379- 2)________ DSS 2014 Heater , 220V ( 9914379- 2)

    ________ DSS 2015 Pr ot ect i ve Fi l ms, 30 Each ( 9914380)________ DSS 2016 Pr ot ect i ve Fi l ms, 30 Each ( 9914379)

    ________ DSS 2017 Case f or Cur i ng Ki t ( 9914379 & 80)

    Note f or Heat er s: "- 1" i ndi cat es Lef t wi ndow, "- 2" i ndi cat es Ri ght wi ndow

    Figure III Curing Kit

    To reorder kits or components, photocopy this form, write quantities above, and

    send to:

    Cessna Ai r cr af t CompanyAt t n: CPD Sal es Depar t mentRO. Box 7706Wi chi t a, KS 67277- 7706 USA

    Or photocopy and FAX this reorder form to: ( 316) 517- 7711; At t n: Sal esDepar t ment

    Be sure to include a copy of the completed Billing and Shipping Information

    form.

  • 7/22/2019 SURFACE SEAL

    25/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    21

    Sur f ace Seal Coat i ng Syst em

    Kit A Application

    Reorder Part

    Quantity Number Description

    ________ DSS 1015 Ki t A - Appl i cat i on ( f or one wi ndow onl y)

    Kit A Components

    Must be ordered as a kit - items are not available separately

    1. Packi ng Li st / Reor der For m2. Mater i al Saf ety Data Sheet s ( MSDS) ( Sur f ace Prep, Next Generat i on Coat i ng

    Sol ut i on)3. Fel t Pad i n Pl ast i c Bag4. Sur f ace Prep ( 2) , 20 ML Ampul es (4. 9- SSL- OPR- 000. 8/ 31/ 98)5. Next Generat i on Coat i ng Sol ut i on ( 1) , 20 ML Ampul e ( 4. 9- SSL- OPR- 000. 8/ 31/ 98)

    Figure IV Kit A - Application

    To reorder kits or components, photocopy this form, write quantities above, and

    send to:

    Cessna Ai r cr af t CompanyAt t n: CPD Sal es Depar t mentP. O. Box 7706Wi chi t a, KS 67277- 7706 USA

    Or photocopy and FAX this reorder form to: ( 316) 517- 7711; At t n: Sal esDepar t ment .

    Be sure to include a copy of the completed Billing and Shipping Information

    form.

  • 7/22/2019 SURFACE SEAL

    26/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    22

    Surface Seal Coating System

    Kit B - Master Refill

    Reorder Part

    Quantity Number Description

    _______ DSS 1016 Ki t B - Mast er Ref i l l

    Kit B ComponentsMust be ordered as a kit - items are not available separately

    1. Packi ng Li st / Reorder For m 2. Mat er i al Saf et y Dat a Sheet s ( MSDS) ( Cl eani ng Sol vent , Pol i shi ng Sl ur r y)3. Gl oves ( 100)4. Pi pet t er Ti ps ( 25)5. Cl eani ng Cl oths ( 2 boxes)6. Tape, 1/ 4"( 1 r ol l )7. Tape, 2" ( 3 r ol l s)8. Cl eani ng Sol vent ( 500 ML bott l e) ( 1)9. Pol i shi ng Sl ur r y ( 250 ML bot t l e) ( 1)

    10. Dei oni zed Water ( 2 - 500 ML bot t l es) DSS1019 ( 2)11. Gauze Pads ( 100)12. Fl i p Top Caps f or Reusabl e Bot t l es ( 4)

    13. Post ~l t Not e Pad ( 3" x 3" )14. Di sposal Bags ( 25) ( 18" x 13")

    Figure V Kit B Master Refill

    To reorder kits or components, photocopy this form, write quantities above, and

    send to:

    Cessna Ai r cr af t CompanyAt t n: CPD Sal es Depar t ment

    RO. Box 7706Wi chi t a, KS 67277- 7706 USA

    Or photocopy and FAX this reorder form to: ( 316) 517- 7711; At t n: Sal esDepar t mentBe sure to include a copy of the completed Billing and Shipping Information

    form.

  • 7/22/2019 SURFACE SEAL

    27/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    23

    Surface Seal Coating System

    Kit C - Measurement Refill

    Reorder Part

    Quantity Number Description

    ______ DSS 3003 Ki t C Measur ement Ref i l l

    Ki t C ComponentsMust be order ed as a ki t - i t ems ar e not avai l abl e separat el y

    1. Packi ng Li st / Reor der For m2. Gl oves ( 50)3. Pi pet t er Ti ps (10)4. Cl eani ng Cl oths ( 2 boxes)5. Dei oni zed Wat er ( 500 ML bot t l e) ( 1)

    6. Post~l t Note Pad ( 3" x 3") ( 1)

    7. Di sposal Bags ( 18" x 13" ) ( 25)

    Figure VI Kit C Measurement Refill

    To reorder kits or components, photocopy this form, write quantities above, and

    send to:

    Cessna Ai r cr af t CompanyAt t n: CPD Sal es Depar t mentRO. Box 7706

    Wi chi t a, KS 67277- 7706 USA

    Or photocopy and FAX this reorder form to: ( 316) 517- 7711; At t n: Sal esDepar t mentBe sure to include a copy of the completed Billing and Shipping Information

    form.

  • 7/22/2019 SURFACE SEAL

    28/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    24

    Shipping Information_________________________________________________________

    SHIP TO:

    _________________________________________________________

    _________________________________________________________Name Ti t l e/ Depar t ment_________________________________________________________

    Company_________________________________________________________

    Di vi si on_________________________________________________________

    Addr ess_________________________________________________________

    Ci t y St at e Zi p / Post al CodeCount r y

    _________________________________________________________Phone_________________________________________________________

    Figure VII Shipping Information

    When r eor der i ng ki t s or component s, i ncl ude t hi s Bi l l i ng and Shi ppi ngI nf or mat i on, and send to:

    Cessna Ai r cr af t CompanyAt t n: CPD Sal es Depar t mentP. O. Box 7706Wi chi t a, KS 67277- 7706 USA

    Or phot ocopy and FAX t hi s f orm t o: ( 316) 517- 7711; At t n: Sal es Depart ment

  • 7/22/2019 SURFACE SEAL

    29/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as andto the extent that such information and data remain unpublished.

    25

    Billing Information_________________________________________________________

    BILL TO:

    _________________________________________________________P. O. #_________________________________________________________

    Name_________________________________________________________Ti t l e/ Depar t ment_________________________________________________________

    Company_________________________________________________________

    Di vi si on

    _________________________________________________________Addr ess_________________________________________________________

    Ci t y St at e Zi p/ Post al Code Count r y_________________________________________________________

    Phone_________________________________________________________

    Aut hor i zed Si gnat ur e Dat e

    Figure VIII Billing Information

    When r eor der i ng ki t s or component s, i ncl ude t hi s Bi l l i ng and Shi ppi ngI nf or mat i on, and send to:

    Cessna Ai r cr af t CompanyAt t n: CPD Sal es Depar t mentP. O. Box 7706Wi chi t a, KS 67277- 7706 USA

    Or phot ocopy and FAX t hi s f orm t o: ( 316) 517- 7711; At t n: Sal es Depart ment

  • 7/22/2019 SURFACE SEAL

    30/30

    DSS 1001-300 Revision H

    CONFIDENTIAL: The technical information and design data disclosed herein constitute trade secrets ofPPG INDUSTRIES, INC. and are to be maintained in strict confidence by the recipient hereof so long as and

    PPG Aerospace

    PPG Industries, Inc. PPG Industries Glass SA

    PPG Aerospace 8, avenue Condorcet

    Sales and Marketing 69100 Villeurbanne

    P. O. Box 040004 France

    Huntsville, AL 35804 Phone: (33) 78 89 7437

    Phone: (256) 851-7001 FAX: (33) 78 94 9371

    FAX: (256) 851-8822

    PPG AmpaSpacePPG Industries, Inc. Via Montello 40

    PPG Aerospace Sales 26010 Casaletto Vaprio (CR)

    111 S. Whittier Italy

    Wichita, KS 67207 Phone: (39) 373 273538

    Phone: (316) 689-4243 FAX: (39) 373 274387

    FAX: (316) 689-4258

    PPG Industries, Inc.

    PPG Aerospace Sales

    14205 S. E. 36thSt.

    Suite 100

    Bellevue, WA 98006Phone: (425) 649-1123

    FAX: (425) 649-1136


Recommended