Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Research Approach: how integrative synthesis supports decision briefing and analysis
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmanted, sequential, inflexible
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Generalize
• The integration of heterogeneous options/ alternatives with heterogeneous information to support AEC decision-making tasks (DEEP)
• Such heterogeneous options/alternatives may be product (belt/bridge), process (OT/no OT), or organization (additional welding/original team)
• Such heterogeneous information are decision factors, which may include: functional requirements, cost, duration, precedence relationships, etc.
Contribution
• An extensible schema/relationship structure, which integrates options with decision factors.
• An interactive decision network, which represents and interlinks multiple types of information to support AEC decision-making tasks (e.g., to query decision factors, manipulate options, and select alternatives). – A CPM Gantt chart represents 1 information type for 1
option– A project curve represents 2 information types for 1 option– A 4D model represents 2 information types for 1 option– A decision network has the potential to embody multiple
information types (e.g., time, cost, organization, linkage to 3D objects, etc.) for multiple options
Evidence
• Degree of integration (in briefings—descriptions and explanations)a higher degree of integration would allow decision makers to describe and explain integrated decision factors more quickly and comprehensively.
• Degree of flexibility and extensibility (in evaluations)a higher degree of flexibility and extensibility would allow decision makers to evaluate more decision alternatives informatively with appropriate foci.
• Degree of repeatability (in predictions/re-evaluations)a higher degree of repeatability and responsiveness in handling new decision criterions would allow decision makers to quickly incorporate performance predictions, evaluate new decision criterions, and iteratively unlock/lock options.
Decision PlanAnalysisBriefingSynthesisPlanning
What-if?
What are the appropriate duration, unit rates, network logic, supervisor?
AEC Decision-Making Process in Selecting Project Alternativesiterative, multilateral, alternatives, creativity while influence level is relatively high
How to generate a PPO proposal? Based on the best available knowledge and criteria at the time
How to effectively present the alternative proposals to the decision makers?
Does the alternative meet the functional requirements? Decision criteria?
What if we relax the functional requirements, refine the decision criteria? Can the project team generate other creative alternatives?
Laydown and
Access
Background Case—Product, Process, Organization, Cost, and the Issues
Steel Sub
WelderErector
GC
Concrete Sub
Rebar Carpenter
lower level parking $ 733k
retail steel $ 657k
Total $ 13,069k (-0.2%)
Risk Issues
• Low coordination risk in baseline schedule, on time and on budget
3/11/02
Unforeseen Site Condition—Contaminated Soil, Native Indian Remains
Laydown and
Access
2-Month Delay and its Impact
Steel Sub
WelderErector
GC
Concrete Sub
Rebar Carpenter
Risk Issues
• The project would miss the turnover deadlines and the retail business window
• The owner requested the GC to come up with acceleration proposals for an OAC meeting
Owner
lower level parking $ 733k
retail steel $ 657k
Total $ 13,171k (+0.5%)
5/13/02
+54D
+56D
Laydown and
Access
Planning—How to accelerate?
Steel Sub
Welding Team 1, 2, 3Erector OT
GC
Concrete Sub
Rebar OT Carpenter OT
Risk issues/Uncertainty associated with the alternative
• High risk—concerns about production by the fabricator
• High risk—the impact of overtime work on productivity and rework
Owner
lower level parking $ ???k(+??%)
retail steel $ ???k(+??%)
Total $ ??,???k (+??%)
Additional Soffit Forming Material
How much can we accelerate by overtime and multiple welding team?
How much can we accelerate by additional formwork and overtime work?
Welding Sup
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : fragmanted options with intra-disciplinary predictions
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Group Responsible: Intra-disciplinary professionals, knowledgeable about their niche ** steel/concrete sub, scheduler, estimator**
Product Option: Acquiring additional soffit forming material** 3D models in ADT and CPT-4D**
Process Option: Shortening task duration with overtime workin steel erection, concrete reinforcement, etc.** MSP **
Organization Option: Bringing additional teams and supervisors for welding and coordination ** SV **
These intra-disciplinary applications do not incorporate P/P/O options.
The model either represent one option or the other option.
The testing of different combinations of intra-disciplinary options requires the generation of different models, which are discrete and unrelated with one another
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : Fragmanted options with intra-disciplinary predictions
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Laydown and
Access
In order to brief (describe and explain) the proposal to the decision makers…
Steel Sub
Welding Team 1, 2, 3Erector OT
GC
Concrete Sub
Rebar OT Carpenter OT
Risk Issues
• what is the impact to the steel erection supply chain?
• how will overtime work affect coordination? productivity? and rework?
• does the change order meet schedule and budget criteria?
Owner
lower level parking $ 748k(+2.0%)
retail steel $ 715k(+8.8%)
Total $ 13,649k (+4.2%)
Additional Soffit Forming Material
Welding Sup
Steel acceleration reduces duration from 68D to 51D in retail area
Concrete acceleration reduce duration from 116D to 103D in lower parking area
+8D
+7D
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : The coupling stage based on best available decision criteria
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Group Responsible: Inter-disciplinary professionals ** project executive **
Integration: generate a coherent inter-disciplinary package for the selected combination of options** Excel, 4D, MSP, SV, ADT **
Decision Criteria: ** Aiming for on-time completion **
In preparation for the OAC review meeting, the project executive filtered the many options into an alternative based on the best available decision criteria
“change the dials once at a time” “ paired comparison” “7+/-2” There is a limit of the simultaneous Information-handling capacity of the decision makers
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : The coupling stage based on best available decision criteria
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Group Responsible: decision makers** owner’s representatives **decision facilitators** project executive **
Descriptive questions:
Where is the laydown area?
What is the predecessor of retail steel work?
What is the cost implication of the acceleration alternative?
How much time can it buy back?
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : Descriptive tasks: What …? When …? Who …? How much …?
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : Descriptive tasks: What …? When …? Who …? How much …?
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : Descriptive tasks: What …? When …? Who …? How much …?
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Group Responsible: decision makers** owner’s representatives **decision facilitators** project executive **
Explanative questions:
How does overtime work impact the change order cost?
Why is there an idle time between the completion of retail slab-on-grade and retail steel erection?
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : Explanative tasks: Why …? How …?
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : High-level evaluation of alternatives with fixed options
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
pre-set combination of options
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : High-level evaluation of alternatives with fixed options
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Activity Milestone Baseline DelayConcrete
ExpeditionSteel
ExpeditionHybrid
Expedition
Overall Project 11/1/2002 10/30/2002 1/8/2003 12/18/2002 12/11/2002 11/19/20022 -68 -47 -40 -18
Parking Turnover 8/1/2002 7/23/2002 9/24/2002 8/22/2002 9/24/2002 8/22/20029 -54 -21 -54 -21
Bookstore Turnover 10/1/2002 9/19/2002 11/25/2002 11/5/2002 10/29/2002 10/9/200212 -55 -35 -28 -8
Retail Turnover 10/15/2002 10/2/2002 12/10/2002 11/18/2002 11/11/2002 10/22/200213 -56 -34 -27 -7
Cinema Turnover 10/15/2002 10/10/2002 12/11/2002 11/12/2002 11/20/2002 10/24/20025 -57 -28 -36 -9
Time
on-time? on budget? acceptable risk level? satisfactory performance level?
Laydown and
Access
Upon decision evaluation, the owners refined their functional requirements
Steel Sub
Welding Team 1, 2, 3Erector OT
GC
Concrete Sub
Rebar OT Carpenter OT
Risk Issues
• what is the impact to the steel erection supply chain?
• how will overtime work affect coordination? productivity? and rework?
• does the change order meet schedule and budget criteria?
Owner
lower level parking $ 748k(+2.0%)
retail steel $ 715k(+8.8%)
Total $ 13,649k (+4.2%)
Additional Soffit Forming Material
Welding Sup
Relax Parking Turnover Constraint
+8D
+7D
Predictions—What if steel erection has a concurrent relationship with lower parking?
Steel Sub
Welding Team 1, 2, 3Erector OT
GC
Concrete Sub
Rebar OT Carpenter OT
Risk Issues
• what is the impact to the steel erection supply chain? how will overtime work affect coordination? productivity? and rework?
• how to provide access to the parking area?
Owner
lower level parking $ 748k(+2.0%)
retail steel $ 715k(+8.8%)
coordination $ ??k (extra)
Total $ ??,???k (+4.5%)
Additional Soffit Forming Material
Welding Sup
How much float will be available
Concurrent coordination means, cost, and time
+??D
+??D
Connector Bridge?
Concrete Belt?
+??D
Synthesis
Process
Acceleration Alternative
Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Cost Resource
Process Product Org.
Brainstorm for PPO options
Test options with intra-disciplinary applications:
Planning
Cost Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
OT conc.
OT steel
Finish-Start
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
What if:
one changes the precedence relationship? From FS to SS?
there is no overtime work?
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : Available alternative is coupled; what-if requires re-integration
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan : New combinations of options generated anew, re-integrate, re-DEEP
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan
Test options with intra-disciplinary applications:
Predictions—What if steel erection has a concurrent relationship with lower parking?
Steel Sub
Welding Team 1, 2, 3Erector OT
GC
Concrete Sub
Rebar OT Carpenter OT
Risk Issues
• what is the impact to the steel erection supply chain? how will overtime work affect coordination? productivity? and rework?
• how to provide access to the parking area?
Owner
lower level parking $ 748k(+2.0%)
retail steel $ 715k(+8.8%)
coordination $ 50k (extra)
Total $ 13,700k (+4.5%)
Additional Soffit Forming Material
Welding Sup
Float Available
Concurrent coordination means, cost, and time
+36D
+20D
Connector Bridge?
Concrete Belt?
+20D
Predictions—What if steel erection has a concurrent relationship with lower parking?
Steel Sub
Welding Team 1, 2, 3Erector OT
GC
Concrete Sub
Rebar OT Carpenter OT
Risk Issues
• what is the impact to the steel erection supply chain? how will overtime work affect coordination? productivity? and rework?
• how to provide access to the parking area?
Owner
lower level parking $ 748k(+2.0%)
retail steel $ 715k(+8.8%)
coordination $ 50k (extra)
Total $ 13,700k (+4.5%)
Additional Soffit Forming Material
Welding Sup
How to minimize cost and coordination risk?
+36D
+20D
Connector Bridge?
Concrete Belt?
+20D
How to minimize parking delay?
Steel Sub
WelderErector
What-if predictions and re-evaluation
GC
Concrete Sub
Rebar OT Carpenter OT
Risk Issues
• bear lower risks for steel erection supply chain, overtime work, coordination, productivity, and rework
• float allow connector bridge to accelerate at a lower cost
Owner
lower level parking $ 748k(+2.0%)
retail steel $ 657k
coordination $ 20k (lower)
Total $ 13,612k (+3.9%)
Additional Soffit Forming Material
Connector Bridge
How to minimize parking delay?
Utilize the float for bridge construction
+22D
17 additional days with no overtime or extra welding teams
Acceptable !
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Test options with intra-disciplinary applications:
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan include decision options (both high and detail levels)
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmented, sequential, inflexible
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Test options with intra-disciplinary applications:
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan include decision options (both high and detail levels)
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmented, sequential, inflexible
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Test options with intra-disciplinary applications:
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmented, sequential, inflexible
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan XML schema—hierarchically integrate heterogeneous project data
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Test options with intra-disciplinary applications:
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmented, sequential, inflexible
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Generate an interactive decision network based on the inputs
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Test options with intra-disciplinary applications:
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmented, sequential, inflexible
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Interactive output allows one to describe with iRoom apps
iRoom event
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Test options with intra-disciplinary applications:
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmented, sequential, inflexible
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Interactive output allows one to explain/record rationales
Explicitly register the concerns
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Test options with intra-disciplinary applications:
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmented, sequential, inflexible
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Evaluation of performance metrics at different decision nodes
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Test options with intra-disciplinary applications:
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmented, sequential, inflexible
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Decision focus for decoupling or manipulating options
Directly add/edit/delete relationships, de/activate options, or change attributes in the decision network
Synthesis
Acceleration Alternative
Product Org.
Test options with intra-disciplinary applications:
Lock-up a set of options into an alternative:
Resource
Product Org.
Test options with intra-disciplinary applications:
Planning
Resource
Baseline Alternative
Lock-up a set of options into an alternative:
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
Process
OT conc.
OT steel
Concurrent
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Cost Resource
Planning
Process
OT conc.
OT steel
Finish-Start
Product
Belt
Bridge
Add Soffit
Org.
welding sup
3+weld crew
add safety
Brainstorm for PPO options
Planning
Cost Resource
Briefing
iRoom highlight
Describe and explain:
explain
Analysis
Functional require.
Evaluate and predict:
What-if?
PPO Option data,
functional requirements
Macro Production Plan Query
Test new criteria
ResourcesResources
MethodsMethods
Decision Network
Alternatives Courses
Concurrent Alternative
Lock-up a set of options into an alternative:
• XML data files
• CIFE applications
• iRoom infrastructure
• Hierarchical PPO object concept
• XML schema for AEC alternatives
hierarchically represent,
centrally integrate, and
automatically propagate
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Belt
Bridge
Add Soffit
welding sup
3+weld crew
add safety
Test options with intra-disciplinary applications:
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Implication: a coherent macro network helps production planning
Planning | Synthesis | Briefing | Analysis | Decision or Re-plan Current Process: fragmented, sequential, inflexible