$1,000 $11,000 $21,000 $31,000 $41,000 $51,000 $61,000
DOIT SIRCITS
TRD Tapestry
HSD ASPEN SBM
HSD MMIS
CYFD EPICS
SLO LIMS
DOIT SWIRE
TRD ONGARD
HSD MMISR
HSD CSESR
EPMO Focus Portfolio Top Ten FY15 Q2 Est. Costs (000's) Spent Remaining
t Management Office (EPMO) Portfolio Projects Fiscal Year 2014 Q1
The Compliance and Project Management Program is the State's Enterprise Project Management Office (EPMO) and performs the following functions:
• Provide IT Management Lifecycle policies, methodologies and templates for information technology (IT) initiatives to promote quality and success and report
regularly to Executive, Legislative, and ITC on the status of the State's IT Project Portfolio
• Provide support, guidance and oversight on IT projects and procurements to promote improved outcomes
• Review executive agency IT plans for prudent allocation of IT resources and monitor compliance of projects with agency plan and the state IT strategic plan
• Review appropriation requests and legislation related to IT and make recommendations to the DFA, and LFC for formal approval by the Legislature and the
Governor, and
• Provide senior project management guidance for enterprise projects.
http://www.doit.state.nm.us/oversight.html
Enterprise Project Management Office (EPMO) Portfolio
Fiscal Year 2015 Q2
Total Estimate Cost $159,960
$0 $30,000 $60,000
All other agencies (35)
SLO
DPS (5)
CYFD (3)
DOT (15)
PED (7)
HSD (4)
TRD (2)
DOIT (8)
Project for FY15 Quarter Two Estimated Costs
(000's)
Total Estimate Cost $253,353
Agency Estimated Costs
(000's)
All other agencies (35) $39,779
SLO $6,800
DPS (5) $10,504
CYFD (3) $11,010
DOT (15) $14,404
PED (7) $16,849
HSD (4) $28,579
TRD (2) $49,823
DOIT (8) $75,607
Total # Projects 80 $253,353
Project
Stat
us
Spent Remaining Total cost Est Completion
Date
DOIT SIRCITS $48,783 $6,917 $55,700 9/30/2015
TRD Tapestry $9,315 $36,303 $45,618 9/5/2016
HSD ASPEN SBM $8,773 $6,329 $15,102 TBD
HSD MMIS $13,477 $0 $13,477 10/31/2014
CYFD EPICS $6,671 $3,836 $10,507 8/30/2017
SLO LIMS $2,317 $4,483 $6,800 6/30/2018
DOIT SWIRE $3,270 $1,730 $5,000 6/30/2015
TRD ONGARD $596 $3,609 $4,205 1/15/2019
HSD MMISR $0 $2,000 $2,000 11/30/2019
HSD CSESR $0 $1,551 $1,551 11/30/2019
$159,960
Enterprise Project Certifications
Certification Form
Project Charter
Certification Form
Project
Management Plan
IV & V Selected
And Contract
Negotiated
Certification Form
Updated Project
Management Plan
IV & V Reports
Submitted
Technical
Architecture
Approved
Certification Form
Final IV & V
Report
Project Closeout
Report
Lessons Learned
Initiation Phase Planning PhaseImplementation
PhaseCloseout Phase
Project
Closed
Initiation Phase
Certification*
Planning Phase
Certification*
Implementation
Phase
Certification*
Closeout Phase
Certification*
Project Closeout
Presentation
http://www.doit.state.nm.us/oversight.html
Enterprise Project Management Office (EPMO) Portfolio
Enterprise Project Certifications Fiscal Year 2015 Q2
2
Phase Value (000's) # of Projects
Initiation $302,965 2
Initiation/Planning $393,780 2
Initiation/Planning/Implementation $0 0
Planning $1,033,615 1
Implementation $838,630 1
Planning/Implementation $1,405,327 3
Close $9,087,228 8
Change $190,000 1
Status 1
Total: $13,251,545 19
Initiation $302,965
Initiation/ Planning $393,780
Planning $1,033,615
Implementation $838,630
Planning/ Implementation
$1,405,327
Close $9,087,228
Change $190,000
FY15 Q2 Total Certifications
Worth $13,251,545
Enterprise Project Management Office (EPMO) Portfolio
Closed Projects Fiscal Year 2015 Q2
FY15 Q2 Closed Projects
• Eight projects closed with a combined budget of $9,087,228
• 7 out of 8 projects successfully accomplished business objectives
• All 8 projects completed on or within budget
• 7 out of 8 projects completed on or within baseline schedule
http://www.doit.state.nm.us/oversight.html
7
1
FY15 Q2 Completed Schedule
On Schedule Schedule Delay *
* DOH National Background check Program - Project schedule delays were attributed to state resource availability.
Agency Project Name Amount
SOS Business Assessment & Infrastructure Improvements
$220,000
PED K-3 Formative Assessment $2,808,719
PED Direct Certification $221,197
DOH Billing and Electronic Health Record (BEHR) Upgrade
$288,881
DOH National Background Check Program $1,592,166
GSD Paperless Procurement $256,211
GCB Gaming Central Monitoring System Replacement
$2,500,000
DOT Document Imaging and Content Management Migration
$1,200,054
Total $9,087,228
7
1
FY15 Q2 Completed Successfully
Successfully metBusiness Objectives
Business Objectivesnot met *
* GSD Paperless Procurement decided to limit scope to Phase 1 and not pursue further Phases.
SOS Business Assessment & Infrastructure Improvements
PED K-3 Formative Assessment
PED Direct Certification
DOH Billing and Electronic Health
Record (BEHR) Upgrade
DOH National Background Check
Program
GSD Paperless Procurement GCB Gaming
Central Monitoring System
Replacement
DOT Document Imaging and
Content Management
Migration
FY15 Q2 Closed Projects
100%
FY15 Q2 within Budget
Under or on Budget Over Budget
EPMO Focus Portfolio (Top Ten) http://www.doit.state.nm.us/docs/pocd_portfolio
http://www.doit.state.nm.us/pcc/index.html
EPMO Top 10 Projects Quarterly Reports
http://www.doit.state.nm.us/docs/pocd_portfolio
Project Certifications
EPMO Home http://www.doit.state.nm.us/oversight.html
Enterprise Project Management Office (EPMO) Online
EPMO Project Portfolio http://www.doit.state.nm.us/docs/pocd_portfolio