Date post: | 03-Apr-2018 |
Category: |
Documents |
Upload: | suleman-bacha |
View: | 227 times |
Download: | 0 times |
of 35
7/28/2019 Tarbela Reservoir
1/35
1
A presentation by
Muhammad Suleman Bahca
7/28/2019 Tarbela Reservoir
2/35
The current study focuses the siltation problem in
Tarbela reservoir.
Siltation is caused by the gradual deposition of
the silt transported by the river upstream.
Tarbela reservoir is a major source of Pakistan in
terms of Electricity production and irrigation
supplies.
Tarbela dam was constructed in 1974 but now theSiltation has reached a stage where major
problems have occurred which have to be dealt
early.
2
Introduction
7/28/2019 Tarbela Reservoir
3/35
To study the current prevailing situation of
Siltation in Tarbela reservoir.
To study the annual deposition rate of
sedimentation in Tarbela reservoir.
To study various impacts of Siltation on the
reservoir.
To check out the possible remedial measures to
minimize the effects of Siltation in Tarbelareservoir.
Objectives
3
7/28/2019 Tarbela Reservoir
4/35
Tarbela Reservoir
Tarbela is one of the worlds greatest water
resources development project built on the river
Indus
It is located about 100 km North West ofIslamabad
The construction work on Tarbela Dam was
started in 1968 and all the civil works were
completed in 1974. Salient features of the Project are given in Table
in the following slides.
4
7/28/2019 Tarbela Reservoir
5/35
5
Characteristics Values
Location Distt. Haripur, River Indus
Completion year 1968
Length of the main dam 2744m
Reservoir length 97km
Reservoir area 260km2
Maximum depth 137m
Dam height 148m
Gross storage 14.34 BCM
Live storage 11.95 BCM
Dead storage 2.39 BCM
Mean Annual inflow 79 BCM
7/28/2019 Tarbela Reservoir
6/35
Maximum gross capacity level 472m
Actual minimum operating level 396m
Minimum reservoir level in 2006 417
Capacity below min. reservoir level 1.55 x 109 m3
Hydro power capacity 3478MW
Electrical energy generation 14.8 GWh yr-1
Number of tunnels for electricity 3
Number of tunnels for irrigation 2
Tunnels diameter (constant) 13.7m
6
7/28/2019 Tarbela Reservoir
7/35
7
7/28/2019 Tarbela Reservoir
8/35
8
7/28/2019 Tarbela Reservoir
9/35
9
7/28/2019 Tarbela Reservoir
10/35
10
7/28/2019 Tarbela Reservoir
11/35
To provide an 11.5 billion cubic metres (bcm) storage dam
on River Indus in order to partly replace the water of
eastern rivers ceded to India, and provide additional
supplies during the low flow period to facilitate further
development of irrigated agriculture.
To increase food production to achieve self sufficiency,
especially in wheat.
To generate cheap hydropower through staged development
of 2100 MW capacity.
Purpose of Tarbela Reservoir
11
7/28/2019 Tarbela Reservoir
12/35
12
7/28/2019 Tarbela Reservoir
13/35
Siltation or sedimentation is a process of gradual deposition
or accumulation of silt in the water bodies i.e. Streams,
Reservoirs (Dams).
Indus River is one of the largest sediment producing rivers in
the world.
The main source of sediment is from the glacial landscape
and erosion from steep sided barren slopes.
The predicted rate of sediment inflow was 0.294 bcm per
year meaning that the dam would silt up to 90% capacity in 50
years
Siltation
13
7/28/2019 Tarbela Reservoir
14/35
In practice, the actual sediment inflow rate has been
significantly lower than predicted, with an average rate of
0.106 bcm, i.e. 36% of the predicted inflow rate.
The useful life of the dam is now considered to be 85 years.
Average annual sediment deposit 0.134 x 109 m3
Sediment volume up to 2006 4.23 x 109 m3
14
Siltation contn
7/28/2019 Tarbela Reservoir
15/35
The drainage area of Indus at Tarbela Dam is 169,600km2out of which 10,400 km2lies immediately above TarbelaDam, falls in the active monsoon zone with annualprecipitation range of 800-1500 mm.
Additional 7700 km2 located further northward is alsoexposed to the receding effects ofmonsoon rains annuallyaveraging 600 to 1200 mm.
The bulk of Indus drainage area, 94% of total catchmentarea, lies outside the monsoon belt.
The northern areas generally receive scanty winter rains andprecipitation largely in the form of snow.
The moving glaciers crush rocks on their way and leavebehind a lot of sediments when they melt which is carriedby the river due to steep gradient.
15
Sedimentation Process
7/28/2019 Tarbela Reservoir
16/35
The velocity of the inflows containing the sedimentdecreases upon entering Tarbela reservoir, which reducesthe sediment carrying capacity of the river water.
The coarse sediment tends to deposit in the upper reaches
of the reservoir, while the finer particles travel downstreamtowards the dam and settle in the reservoir.
Young geological formations of erodible nature in the Induscatchment are also responsible for higher sediment yield.
Sediment carried by Indus is deposited in the reservoir at an
annual rate of about 200 million tons, corresponding toabout 98 % of the sediment inflow.
More than up to 80% of the sediment load is transported inthe reservoir during the months of July and August.
16
S.Proess contin
7/28/2019 Tarbela Reservoir
17/35
The average composition of the deposits determined from
samples collected from Tarbela reservoir is
28% of sand
55% of silt
and
17% of clay
Composition of the Deposits
17
7/28/2019 Tarbela Reservoir
18/35
The predicted rate of sediment inflow was 0.294 billion m3annually.
but the actual sediment inflow rate has been significantlylower with an average rate of 0.106 billion m3 which is 36%
of the predicted rate. one aspect of the sediment deposition which was however
not expected so early is the rapid advancement of thesediment delta front which is 10.6 km from the dam in2006.
This endangers all the low level outlets including the powerstation which could be blocked by the liquefaction of thesediment under the severe earthquake.
The minimum reservoir drawdown level was raised frominitial 396 m to 417 m until 2006.
Current status
18
7/28/2019 Tarbela Reservoir
19/35
The capacity of reservoir is decreasing due to this heavy
sediment load.
The remaining storage capacity calculated from
hydrographic survey 2005 is given in the table below
19
ReservoirCapacity
Initial(1974) BCM
Year 2005BCM
Reduction %
Gross
Storage
14.344 10.295 28.23
Live Storage 11.948 8.695 27.22
Dead Storage 2.395 1.598 33.30
7/28/2019 Tarbela Reservoir
20/35
A loss oflive storage, which is causing gradual reduction inthe regulated yield of reservoir. This in turn would result inreduction in water availability for the agriculture indownstream mainly Punjab and Sindh.
The physical effect of sediment, which includes the risk ofclogging of low level tunnel outlet particularly in a seismicactivity, the erosive action of sediment-laden water onoutlet concrete structures and Power turbines will result inexorbitant maintenance costs.
Due to low storage available in the reservoir, chances offlood situation also increase.
Sedimentation can also affect the aquatic fauna, mainlyfisheries.
Problems Encountered due to Siltationof Tarbela Reservoir
20
7/28/2019 Tarbela Reservoir
21/35
21
7/28/2019 Tarbela Reservoir
22/35
The most desirable method for controlling reservoir
sedimentation is probably by reducing soil loss and erosion
from the reservoir watershed.
Can be achieved by
reducing sediment inflow through soil conservation,
watershed management,
Gully control,
vegetative screens building check dams.
Problem of having difficult to implement
Preserving Reservoir Capacity
22
7/28/2019 Tarbela Reservoir
23/35
Poor or improper land use and management are
the major contributing factors to reservoir
sedimentation.
The need for watershed management to reducesediment input into the reservoirs is suggested
widely.
Measures like strip cropping, forestation, crop
rotation, terracing, and gully control cansignificantly reduce the soil loss.
Watershed Management
23
7/28/2019 Tarbela Reservoir
24/35
Building debris dams or check dams (or trap dams)
as another way of reducing sediment inflow into
the reservoirs
It can control the flow of coarse sediments intothe reservoir.
These deposits can be flushed or bypassed via
diversion tunnels or pipes downstream of the
main reservoir dam during high flows, orperiodically cleaned during low flows when the
deposits are exposed.
Check Dams
24
7/28/2019 Tarbela Reservoir
25/35
Reduction of sediment influx either by watershed
management or by construction of check dams in the upper
catchment is impractical as about 90% of total runoff isdominated by snow / glacier melt.
Nothing can be done at this attitude on the steep
mountains.
Most of the catchment area is out of the monsoon zone.
Water shed Management is being implemented by the NWFPForest Department up to Besham and it has very little
effect.
Diamer Basha Dam shall have some positive impact as it
would enhance its life.
25
7/28/2019 Tarbela Reservoir
26/35
Density currents are caused by the difference in
density of the relatively cleaner reservoir water
and the sediment-laden incoming stream flow.
Density differences can be generated either bythe high concentrations of suspended sediment
particles in the incoming stream flow, or by the
temperature differences between the stream flow
and the reservoir waters.
Venting Density Currents
26
7/28/2019 Tarbela Reservoir
27/35
Frequent flushing of sediments is done during the
high-inflow season
The purpose of regulating the flows during the
flood season is to release as much sediment aspossible from the reservoir.
This takes advantage of the silt-carrying capacity
of floodwaters in the reservoir and in the
downstream reaches of the river. This operation greatly reduces sediment
entrapment in the reservoir.
Flood Flushing
27
7/28/2019 Tarbela Reservoir
28/35
Drawdown flushing is different from venting density
currents and flood flushing.
It is implemented to evacuate the sediments that
have already been deposited in the reservoir. Drawdown (or hydraulic) flushing involves the
release of water from a reservoir through a low-
level outlet, while reducing the pool to an
allowable minimum level.
Depends on the reservoir topography, outlet
capacity and elevation, characteristics of the
incoming sediment material, operation of the
reservoir, and duration of the flushing operation.
Drawdown Flushing
28
7/28/2019 Tarbela Reservoir
29/35
In the case of Tarbela reservoir Evacuation of 200 million
tons of yearly sediments by flushing through four low level
high capacity outlets from the left bank has been proposed
by the consultants.
This option would comprise four 12 m diameter tunnels
driven through the left abutment.
WAPDA considers the under water dyke and the four tunnelsan unprecedented option, the example of which does not
exist else where in the World. Moreover, this option would
in no time adversely affect the downstream hydropower
Project of Ghazi Barotha and Chashma and kill them much
earlier.
29
7/28/2019 Tarbela Reservoir
30/35
Dredging is an Excavation activity or operation usuallycarried out at least partly underwater, in shallow seas orfresh water areas with the purpose of gathering up bottomsediments and disposing of them at a different location.
One of the most popular methods in dealing with reservoirsedimentation
It is the most controversial issue in reservoir storagerehabilitation.
It has both environmental benefits and hazards.
One of the major environmental concerns is that dredging resuspends sediments which may release toxic substances.
If the removed sediments contain hazardous material,disposal of the dredged material may be a major problem.
Sediment Dredging
30
7/28/2019 Tarbela Reservoir
31/35
The dredging option in case of Tarbela reservoir is not only
prohibitive in cost but also is without any precedence and
impractical.
Any dredging proposal to be effective must provide for
removal and disposal of 550,000 tons of sediments every
day.
Realistically, the target is unattainable even if hundred of
dredgers and ancillary equipment are deployed over the
reservoir stretch of 50 Sq. Km. to work round the clock.
31
7/28/2019 Tarbela Reservoir
32/35
Heightening the dam can also be considered
but it will only increase in the live storage equal
to few years of sediment inflow.
There are some shortcomings attached to thismethod like:
The gates of the service and auxiliary spillways
would then also be modified.
The stability of the dam must also be studied
before taking out the process.
Heightening of the dam
32
7/28/2019 Tarbela Reservoir
33/35
It is the last option left when the production and
benefits from the dam will become less than the
management cost of the project.
But as our country is in a crucial financialposition, this option should be kept under the
pillow.
Replacement of existing dam byanother
33
7/28/2019 Tarbela Reservoir
34/35
Reservoir capacity at Tarbela is being lost at the rate of about 0.132
BCM per year.
The predicted rate of sediment inflow in the reservoir was 0.294
billion m3 annually which envisages that the sediment load will fill up
the capacity of Tarbela reservoir up to 90% in 50 years.
After that, the dam will continue to provide only about 1.2 billion m3of live storage.
The usable life of the dam is considered to be 85 years now but the
usable storage will gradually decline over this time.
Flushing of sediments at Tarbela through the existing tunnels during
low reservoir level is on the average 7% of total incoming sediment.
The remedial action in terms of dredging & excavation and disposal of
upstream deposits are not economical. Studies for sediment flushing
with the existing outlets should continue at Tarbela.
Conclusions
34
7/28/2019 Tarbela Reservoir
35/35