+ All Categories
Home > Documents > Tarbela Reservoir

Tarbela Reservoir

Date post: 03-Apr-2018
Category:
Upload: suleman-bacha
View: 227 times
Download: 0 times
Share this document with a friend

of 35

Transcript
  • 7/28/2019 Tarbela Reservoir

    1/35

    1

    A presentation by

    Muhammad Suleman Bahca

  • 7/28/2019 Tarbela Reservoir

    2/35

    The current study focuses the siltation problem in

    Tarbela reservoir.

    Siltation is caused by the gradual deposition of

    the silt transported by the river upstream.

    Tarbela reservoir is a major source of Pakistan in

    terms of Electricity production and irrigation

    supplies.

    Tarbela dam was constructed in 1974 but now theSiltation has reached a stage where major

    problems have occurred which have to be dealt

    early.

    2

    Introduction

  • 7/28/2019 Tarbela Reservoir

    3/35

    To study the current prevailing situation of

    Siltation in Tarbela reservoir.

    To study the annual deposition rate of

    sedimentation in Tarbela reservoir.

    To study various impacts of Siltation on the

    reservoir.

    To check out the possible remedial measures to

    minimize the effects of Siltation in Tarbelareservoir.

    Objectives

    3

  • 7/28/2019 Tarbela Reservoir

    4/35

    Tarbela Reservoir

    Tarbela is one of the worlds greatest water

    resources development project built on the river

    Indus

    It is located about 100 km North West ofIslamabad

    The construction work on Tarbela Dam was

    started in 1968 and all the civil works were

    completed in 1974. Salient features of the Project are given in Table

    in the following slides.

    4

  • 7/28/2019 Tarbela Reservoir

    5/35

    5

    Characteristics Values

    Location Distt. Haripur, River Indus

    Completion year 1968

    Length of the main dam 2744m

    Reservoir length 97km

    Reservoir area 260km2

    Maximum depth 137m

    Dam height 148m

    Gross storage 14.34 BCM

    Live storage 11.95 BCM

    Dead storage 2.39 BCM

    Mean Annual inflow 79 BCM

  • 7/28/2019 Tarbela Reservoir

    6/35

    Maximum gross capacity level 472m

    Actual minimum operating level 396m

    Minimum reservoir level in 2006 417

    Capacity below min. reservoir level 1.55 x 109 m3

    Hydro power capacity 3478MW

    Electrical energy generation 14.8 GWh yr-1

    Number of tunnels for electricity 3

    Number of tunnels for irrigation 2

    Tunnels diameter (constant) 13.7m

    6

  • 7/28/2019 Tarbela Reservoir

    7/35

    7

  • 7/28/2019 Tarbela Reservoir

    8/35

    8

  • 7/28/2019 Tarbela Reservoir

    9/35

    9

  • 7/28/2019 Tarbela Reservoir

    10/35

    10

  • 7/28/2019 Tarbela Reservoir

    11/35

    To provide an 11.5 billion cubic metres (bcm) storage dam

    on River Indus in order to partly replace the water of

    eastern rivers ceded to India, and provide additional

    supplies during the low flow period to facilitate further

    development of irrigated agriculture.

    To increase food production to achieve self sufficiency,

    especially in wheat.

    To generate cheap hydropower through staged development

    of 2100 MW capacity.

    Purpose of Tarbela Reservoir

    11

  • 7/28/2019 Tarbela Reservoir

    12/35

    12

  • 7/28/2019 Tarbela Reservoir

    13/35

    Siltation or sedimentation is a process of gradual deposition

    or accumulation of silt in the water bodies i.e. Streams,

    Reservoirs (Dams).

    Indus River is one of the largest sediment producing rivers in

    the world.

    The main source of sediment is from the glacial landscape

    and erosion from steep sided barren slopes.

    The predicted rate of sediment inflow was 0.294 bcm per

    year meaning that the dam would silt up to 90% capacity in 50

    years

    Siltation

    13

  • 7/28/2019 Tarbela Reservoir

    14/35

    In practice, the actual sediment inflow rate has been

    significantly lower than predicted, with an average rate of

    0.106 bcm, i.e. 36% of the predicted inflow rate.

    The useful life of the dam is now considered to be 85 years.

    Average annual sediment deposit 0.134 x 109 m3

    Sediment volume up to 2006 4.23 x 109 m3

    14

    Siltation contn

  • 7/28/2019 Tarbela Reservoir

    15/35

    The drainage area of Indus at Tarbela Dam is 169,600km2out of which 10,400 km2lies immediately above TarbelaDam, falls in the active monsoon zone with annualprecipitation range of 800-1500 mm.

    Additional 7700 km2 located further northward is alsoexposed to the receding effects ofmonsoon rains annuallyaveraging 600 to 1200 mm.

    The bulk of Indus drainage area, 94% of total catchmentarea, lies outside the monsoon belt.

    The northern areas generally receive scanty winter rains andprecipitation largely in the form of snow.

    The moving glaciers crush rocks on their way and leavebehind a lot of sediments when they melt which is carriedby the river due to steep gradient.

    15

    Sedimentation Process

  • 7/28/2019 Tarbela Reservoir

    16/35

    The velocity of the inflows containing the sedimentdecreases upon entering Tarbela reservoir, which reducesthe sediment carrying capacity of the river water.

    The coarse sediment tends to deposit in the upper reaches

    of the reservoir, while the finer particles travel downstreamtowards the dam and settle in the reservoir.

    Young geological formations of erodible nature in the Induscatchment are also responsible for higher sediment yield.

    Sediment carried by Indus is deposited in the reservoir at an

    annual rate of about 200 million tons, corresponding toabout 98 % of the sediment inflow.

    More than up to 80% of the sediment load is transported inthe reservoir during the months of July and August.

    16

    S.Proess contin

  • 7/28/2019 Tarbela Reservoir

    17/35

    The average composition of the deposits determined from

    samples collected from Tarbela reservoir is

    28% of sand

    55% of silt

    and

    17% of clay

    Composition of the Deposits

    17

  • 7/28/2019 Tarbela Reservoir

    18/35

    The predicted rate of sediment inflow was 0.294 billion m3annually.

    but the actual sediment inflow rate has been significantlylower with an average rate of 0.106 billion m3 which is 36%

    of the predicted rate. one aspect of the sediment deposition which was however

    not expected so early is the rapid advancement of thesediment delta front which is 10.6 km from the dam in2006.

    This endangers all the low level outlets including the powerstation which could be blocked by the liquefaction of thesediment under the severe earthquake.

    The minimum reservoir drawdown level was raised frominitial 396 m to 417 m until 2006.

    Current status

    18

  • 7/28/2019 Tarbela Reservoir

    19/35

    The capacity of reservoir is decreasing due to this heavy

    sediment load.

    The remaining storage capacity calculated from

    hydrographic survey 2005 is given in the table below

    19

    ReservoirCapacity

    Initial(1974) BCM

    Year 2005BCM

    Reduction %

    Gross

    Storage

    14.344 10.295 28.23

    Live Storage 11.948 8.695 27.22

    Dead Storage 2.395 1.598 33.30

  • 7/28/2019 Tarbela Reservoir

    20/35

    A loss oflive storage, which is causing gradual reduction inthe regulated yield of reservoir. This in turn would result inreduction in water availability for the agriculture indownstream mainly Punjab and Sindh.

    The physical effect of sediment, which includes the risk ofclogging of low level tunnel outlet particularly in a seismicactivity, the erosive action of sediment-laden water onoutlet concrete structures and Power turbines will result inexorbitant maintenance costs.

    Due to low storage available in the reservoir, chances offlood situation also increase.

    Sedimentation can also affect the aquatic fauna, mainlyfisheries.

    Problems Encountered due to Siltationof Tarbela Reservoir

    20

  • 7/28/2019 Tarbela Reservoir

    21/35

    21

  • 7/28/2019 Tarbela Reservoir

    22/35

    The most desirable method for controlling reservoir

    sedimentation is probably by reducing soil loss and erosion

    from the reservoir watershed.

    Can be achieved by

    reducing sediment inflow through soil conservation,

    watershed management,

    Gully control,

    vegetative screens building check dams.

    Problem of having difficult to implement

    Preserving Reservoir Capacity

    22

  • 7/28/2019 Tarbela Reservoir

    23/35

    Poor or improper land use and management are

    the major contributing factors to reservoir

    sedimentation.

    The need for watershed management to reducesediment input into the reservoirs is suggested

    widely.

    Measures like strip cropping, forestation, crop

    rotation, terracing, and gully control cansignificantly reduce the soil loss.

    Watershed Management

    23

  • 7/28/2019 Tarbela Reservoir

    24/35

    Building debris dams or check dams (or trap dams)

    as another way of reducing sediment inflow into

    the reservoirs

    It can control the flow of coarse sediments intothe reservoir.

    These deposits can be flushed or bypassed via

    diversion tunnels or pipes downstream of the

    main reservoir dam during high flows, orperiodically cleaned during low flows when the

    deposits are exposed.

    Check Dams

    24

  • 7/28/2019 Tarbela Reservoir

    25/35

    Reduction of sediment influx either by watershed

    management or by construction of check dams in the upper

    catchment is impractical as about 90% of total runoff isdominated by snow / glacier melt.

    Nothing can be done at this attitude on the steep

    mountains.

    Most of the catchment area is out of the monsoon zone.

    Water shed Management is being implemented by the NWFPForest Department up to Besham and it has very little

    effect.

    Diamer Basha Dam shall have some positive impact as it

    would enhance its life.

    25

  • 7/28/2019 Tarbela Reservoir

    26/35

    Density currents are caused by the difference in

    density of the relatively cleaner reservoir water

    and the sediment-laden incoming stream flow.

    Density differences can be generated either bythe high concentrations of suspended sediment

    particles in the incoming stream flow, or by the

    temperature differences between the stream flow

    and the reservoir waters.

    Venting Density Currents

    26

  • 7/28/2019 Tarbela Reservoir

    27/35

    Frequent flushing of sediments is done during the

    high-inflow season

    The purpose of regulating the flows during the

    flood season is to release as much sediment aspossible from the reservoir.

    This takes advantage of the silt-carrying capacity

    of floodwaters in the reservoir and in the

    downstream reaches of the river. This operation greatly reduces sediment

    entrapment in the reservoir.

    Flood Flushing

    27

  • 7/28/2019 Tarbela Reservoir

    28/35

    Drawdown flushing is different from venting density

    currents and flood flushing.

    It is implemented to evacuate the sediments that

    have already been deposited in the reservoir. Drawdown (or hydraulic) flushing involves the

    release of water from a reservoir through a low-

    level outlet, while reducing the pool to an

    allowable minimum level.

    Depends on the reservoir topography, outlet

    capacity and elevation, characteristics of the

    incoming sediment material, operation of the

    reservoir, and duration of the flushing operation.

    Drawdown Flushing

    28

  • 7/28/2019 Tarbela Reservoir

    29/35

    In the case of Tarbela reservoir Evacuation of 200 million

    tons of yearly sediments by flushing through four low level

    high capacity outlets from the left bank has been proposed

    by the consultants.

    This option would comprise four 12 m diameter tunnels

    driven through the left abutment.

    WAPDA considers the under water dyke and the four tunnelsan unprecedented option, the example of which does not

    exist else where in the World. Moreover, this option would

    in no time adversely affect the downstream hydropower

    Project of Ghazi Barotha and Chashma and kill them much

    earlier.

    29

  • 7/28/2019 Tarbela Reservoir

    30/35

    Dredging is an Excavation activity or operation usuallycarried out at least partly underwater, in shallow seas orfresh water areas with the purpose of gathering up bottomsediments and disposing of them at a different location.

    One of the most popular methods in dealing with reservoirsedimentation

    It is the most controversial issue in reservoir storagerehabilitation.

    It has both environmental benefits and hazards.

    One of the major environmental concerns is that dredging resuspends sediments which may release toxic substances.

    If the removed sediments contain hazardous material,disposal of the dredged material may be a major problem.

    Sediment Dredging

    30

  • 7/28/2019 Tarbela Reservoir

    31/35

    The dredging option in case of Tarbela reservoir is not only

    prohibitive in cost but also is without any precedence and

    impractical.

    Any dredging proposal to be effective must provide for

    removal and disposal of 550,000 tons of sediments every

    day.

    Realistically, the target is unattainable even if hundred of

    dredgers and ancillary equipment are deployed over the

    reservoir stretch of 50 Sq. Km. to work round the clock.

    31

  • 7/28/2019 Tarbela Reservoir

    32/35

    Heightening the dam can also be considered

    but it will only increase in the live storage equal

    to few years of sediment inflow.

    There are some shortcomings attached to thismethod like:

    The gates of the service and auxiliary spillways

    would then also be modified.

    The stability of the dam must also be studied

    before taking out the process.

    Heightening of the dam

    32

  • 7/28/2019 Tarbela Reservoir

    33/35

    It is the last option left when the production and

    benefits from the dam will become less than the

    management cost of the project.

    But as our country is in a crucial financialposition, this option should be kept under the

    pillow.

    Replacement of existing dam byanother

    33

  • 7/28/2019 Tarbela Reservoir

    34/35

    Reservoir capacity at Tarbela is being lost at the rate of about 0.132

    BCM per year.

    The predicted rate of sediment inflow in the reservoir was 0.294

    billion m3 annually which envisages that the sediment load will fill up

    the capacity of Tarbela reservoir up to 90% in 50 years.

    After that, the dam will continue to provide only about 1.2 billion m3of live storage.

    The usable life of the dam is considered to be 85 years now but the

    usable storage will gradually decline over this time.

    Flushing of sediments at Tarbela through the existing tunnels during

    low reservoir level is on the average 7% of total incoming sediment.

    The remedial action in terms of dredging & excavation and disposal of

    upstream deposits are not economical. Studies for sediment flushing

    with the existing outlets should continue at Tarbela.

    Conclusions

    34

  • 7/28/2019 Tarbela Reservoir

    35/35


Recommended