+ All Categories
Home > Documents > Target Value Design Simulation - ENVR

Target Value Design Simulation - ENVR

Date post: 19-Oct-2021
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
58
Target Value Design Simulation Zofia K. Rybkowski, PhD Associate Professor Department of Construction Science College of Architecture Texas A&M University
Transcript
Page 1: Target Value Design Simulation - ENVR

Target Value Design Simulation

Zofia K. Rybkowski, PhDAssociate ProfessorDepartment of Construction ScienceCollege of ArchitectureTexas A&M University

Page 2: Target Value Design Simulation - ENVR

Learning Objectives Understand and apply the basic elements of Target Value Design

Page 3: Target Value Design Simulation - ENVR

How can we make BETTER QUALITY buildings FINANCIALLY FEASIBLE?

Page 4: Target Value Design Simulation - ENVR

Target Value Design

Page 5: Target Value Design Simulation - ENVR

Target Value Design

Reduce waste and add value to your projects

Rybkowski, Z. K., Munankami, M., Shepley, M. M., and Fernández-Solis, J. L. (2016). “Development and testing of a lean

simulation to illustrate key principles of Target Value Design: A first run study.” In: Proc. 24th Ann. Conf. of the Int’l. Group for

Lean Construction, Boston, MA, USA,sect.4 pp. 133–142.

Page 6: Target Value Design Simulation - ENVR

Materials required for simulation (Munakami 2012)

Page 7: Target Value Design Simulation - ENVR

Simulation built on Marshmallow Challenge by Peter Skillman…

Round One:• Each team makes a tower that is 2 ft. tall with a

marshmallow on top.• No more than 2 in. out of plumb• Freestanding (not attached to the table)

Page 8: Target Value Design Simulation - ENVR

How much did each team’s tower cost ? Teams report their quantities to facilitator in charge of overall spreadsheet.

Page 9: Target Value Design Simulation - ENVR

Market Cost: Into a spreadsheet, facilitator inputs the cost of each tower, and adds 10% profit. The average is the Market Cost.

Allowable Cost: Facilitator takes the Market Cost and reduces it by 20%. This is the MUST HAVE cost that must be met in order for the

project to proceed. Otherwise it will be cancelled.

Target Cost: Each team declares a Target Cost “stretch goal.” This is the NICE TO HAVE cost. It is nice to have though not critical for

the project to proceed.

Page 10: Target Value Design Simulation - ENVR

Round Two:• Teams make a tower that is 2 ft. tall with a marshmallow on

top.• No more than 2 in. out of plumb• Freestanding (not attached to the table)• Teams MUST meet Allowable Cost but should also aim

for the Target Cost, if possible.

Page 11: Target Value Design Simulation - ENVR

Which team met all the criteria at the lowest cost?

Page 12: Target Value Design Simulation - ENVR

Some examples of past results

Page 13: Target Value Design Simulation - ENVR

Spreadsheet for tabulation of tower costs after Rounds I and II.

Page 14: Target Value Design Simulation - ENVR

Round Two: Once target cost was established, teams co-located and worked collaboratively to re-design the tower to meet target cost (Munankami 2012).

Page 15: Target Value Design Simulation - ENVR

An Owner wants to design and build a tower that is 2’-0” tall which is capable of holding a marshmallow at the top and that is no more than 2” out-of-plumb. The tower must be constructed with supplied materials and must be free-standing (i.e. cannot be taped to a table). Participants have 20 minutes to construct a tower without concern for cost (Round 1), and 20 minutes to construct another tower that is 20% less than the average of first tower costs (Round 2).

2 FT

2 FT

$ 118 $ 27

Page 16: Target Value Design Simulation - ENVR

Target Value Design

“Under the Hood”Rybkowski, Z. K., Munankami, M., Shepley, M. M., and Fernández-

Solis, J. L. (2016). “Development and testing of a lean simulation to illustrate key principles of Target Value Design: A first run study.” In: Proc. 24th Ann. Conf. of the Int’l. Group for

Lean Construction, Boston, MA, USA,sect.4 pp. 133–142.

Page 17: Target Value Design Simulation - ENVR

Concepts associated withTarget Value Design:

• Big Room meetings• Market cost• Allowable cost• Target Cost• Co-location• A3s• Set-based Design• Uniformat estimating• Choosing by Advantages (CBA) system of decision-making• Optimization of the whole over the parts• Relational and Risk-sharing contracts

(IFOA, Consensus Docs, etc.)• Systems Optimization over sub-optimization

Page 18: Target Value Design Simulation - ENVR

Impact

Comparison of two similar projects using different project delivery systems.

From Ballard, G., and Reiser, P. (2004). "The St. Olaf College Fieldhouse Project: a Case Study in Designing to Target Cost." 12th Annual Conference of the International Group for Lean Construction, Elsinor, Denmark, 234-249.

Page 19: Target Value Design Simulation - ENVR

Adapted from Ballard, G. (2008). “The Lean Project Delivery System: An Update.” Lean Construction Journal, 1-19.

Page 20: Target Value Design Simulation - ENVR

“Target Value Design is a management practice that drives design to deliver customer value,

and develops design within project constraints.”.

Ballard, G. (2011). “Target Value Design: Current benchmark (1.0).” Lean Construction Journal, 79-84.

Denerolle, S. (2011). Technical report: The application of target value design to 3 hospital projects. Project Production Systems Laboratory, University of California, Berkeley.

Page 21: Target Value Design Simulation - ENVR

Metrics of success

time

cost

quality

safety

Photo source: http://c12solutions.com/blog1/sustainability-green-business-models-fdu/

Page 22: Target Value Design Simulation - ENVR

TIME

market time

target time

Page 23: Target Value Design Simulation - ENVR

COST

Pro

ject

cos

t ($)

time

allowable cost

target cost

market cost

Page 24: Target Value Design Simulation - ENVR

targ

et n

eeds

QUALITY

Page 25: Target Value Design Simulation - ENVR

Target Value design finds its historical foundation in

Target Costing

Page 26: Target Value Design Simulation - ENVR

What is Target Costing?

Target Price

Target Cost

Proposed Price

Cost

P = C + M

Margin

Target Costing: TC = TP - TM

Target Margin

Adapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 27: Target Value Design Simulation - ENVR

Time

Cos

t

Allowable CostTarget Cost

Market Cost

Costing terms associated with TVDAdapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 28: Target Value Design Simulation - ENVR

Predesign Schematic Design Construction Agency Permit/ Construction Design Development Documents Bidding

Conceptualization Criteria Detailed Implementation Agency Coord/ Construction

Design Design Documents Final Buyout

1

2

43

Time / ScheduleD

esig

n Ef

fort

/ Effe

ct

1

2

4

3

Ability to impact cost and function

Cost of design changes

Traditional Design-Bid-Build process

Integrated Project Delivery Process

TRADITIONAL DESIGN-BID BUILD

INTEGRATED DESIGN DELIVERY

Integrated Project Delivery

The MacLeamy Curve

Adapted from: http://ohainc.com/news_detail.php?news_id=00031 (accessed on October 17, 2012)

Page 29: Target Value Design Simulation - ENVR

OWNER

ARCHITECT

ENGINEER

CONTRACTOR

SUBCONSTRACTORS

w w w w w w w

OWNER

ARCHITECT

ENGINEER

CONTRACTOR

SUBCONSTRACTORS

w=waste

Travel path of an RFI in traditional (left) versus Lean (right) project deliveryAdapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 30: Target Value Design Simulation - ENVR

100

90

80

70

60

50

40

30

20

10

0

From Clifton et al, Target Costing: Market-Driven Product Design, figure 5.2, p. 73

Market Cost

Subsystem 1Current Cost

Subsystem 1 Allowable Cost

Cost Reduction Objective

Subsystem Cost Reduction Objective

Subsystem 6

Subsystem 5

Subsystem 4

Subsystem 3

Subsystem 2

Subsystem 1

The role of cost sharing

Perce

nt of

total

proje

ct co

st

Costs after TVD

Allowable Cost

Adapted from: Clifton, M. B., Bird, H. M. B., Albano, R. E., and Townsend, W. P. (2004). Target Costing: Market-driven Product Design, Marcel Dekker, Inc., New York

Page 31: Target Value Design Simulation - ENVR

100

90

80

70

60

50

40

30

20

10

0

Market Cost

Allowable Cost

Cost Reduction Objective

Subsystem 6

Subsystem 5

Subsystem 4

Subsystem 3

Subsystem 2

Subsystem 1

Market Cost

Allowable Cost

Cost Reduction Objective

Subsystem 6

Subsystem 5

Subsystem 4

Subsystem 3Subsystem 2Subsystem 1

The importance of flexible cost boundaries

Adapted rom Clifton et al, Target Costing: Market-Driven Product Design, figure 5.2, p. 73

Costs after TVD Costs after TVD

Adapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley

Adapted from: Clifton, M. B., Bird, H. M. B., Albano, R. E., and Townsend, W. P. (2004). Target Costing: Market-driven Product Design, Marcel Dekker, Inc., New York

Page 32: Target Value Design Simulation - ENVR

Cost

of pr

oject

($)

TVD Early experimental results: Sutter Fairfield (CA)Adapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 33: Target Value Design Simulation - ENVR

• Patient-focused care• Private patient rooms• Accessibility and ease of way-finding• Comfortable and varied environments• Healing environments with natural light• Visitor hospitality lounges on each floor• Private medical consulting rooms• Pleasant dining areas• Awareness of diversity of cultures• Parking convenience• Efficient intercampus transfer and mobility• One stop registration for all OP [operations]• Easy access to emergency services• A design that focuses on the patient• Physician and staff friendly• Sustainable• Cost efficient and constructible

TVD Case Study: Sutter Health’s Cathedral Hill Hospital

Sutter Health: California Pacific Medical Center (850,000 SF; 550 beds)Cathedral Hill Hospital (San Francisco, CA)

California Pacific Medical Center is committed to a vision of healthcare for our community that will encompass a new state of the art facility and programs that will fulfill our mission of clinical excellence, education, and research. The patient and family experience comes first.

Adapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 34: Target Value Design Simulation - ENVR

HVAC/Plumbing Electrical Structural

BIM Champions Administration Interiors Sustainability

ExteriorEnclosure

TechnicalArchitects

Planning

Integrated Project Delivery : Co-locationAdapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 35: Target Value Design Simulation - ENVR

Week 1

Week 2

Week 3

Week 4

PS

PS

PS

PP

PP

PP

PSPP

M T W Th F

Pull Scheduling:Last Planner(“Big Room”) meeting

Design Engine:Subcommittee meeting

Pull Pricing:Target Value Design(“Big Room”) meeting

Design Engine: Cluster Group meeting

PSPP

Meetings at Cathedral HillAdapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 36: Target Value Design Simulation - ENVR

Lean-IPD contractual motivators

Pain sharing:Incentive plan to meetAllowable Cost

Gain sharing:Incentive plan to reach below Allowable Cost

Allowable Cost

Time

Proje

ct Co

st

Target Cost

Allowable Cost

Adapted from: Rybkowski, Z. K. (2009).

Market Cost

Page 37: Target Value Design Simulation - ENVR

Pain SharingAdapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 38: Target Value Design Simulation - ENVR

Gain SharingAdapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 39: Target Value Design Simulation - ENVR

Scope changeAdapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 40: Target Value Design Simulation - ENVR

Target Value Design

Applied to an actual projectRybkowski, Z. K., Munankami, M., Shepley, M. M., and Fernández-

Solis, J. L. (2016). “Development and testing of a lean simulation to illustrate key principles of Target Value Design: A first run study.” In: Proc. 24th Ann. Conf. of the Int’l. Group for

Lean Construction, Boston, MA, USA,sect.4 pp. 133–142.

Page 41: Target Value Design Simulation - ENVR

Target Value Design

Page 42: Target Value Design Simulation - ENVR

Target Value Design

Page 43: Target Value Design Simulation - ENVR

Target Value Design

Page 44: Target Value Design Simulation - ENVR

Target Value Design

Page 45: Target Value Design Simulation - ENVR

Target Value Design

Page 46: Target Value Design Simulation - ENVR

Target Value Design

Page 47: Target Value Design Simulation - ENVR

Target Value Design

Page 48: Target Value Design Simulation - ENVR

Target Value Design

Page 49: Target Value Design Simulation - ENVR

Target Value Design

Page 50: Target Value Design Simulation - ENVR

Target Value Design

Page 51: Target Value Design Simulation - ENVR

Target Value Design

Page 52: Target Value Design Simulation - ENVR

Target Value Design (Sutter Health)

Full-scale cardboard mock-up and testing week during TVD: Akron Children’s Hospital.

(Image source: Bernita Beikman, HKS, with permission, 2013)

Target Value Design

Page 53: Target Value Design Simulation - ENVR

Target Value Design of Sutter Health’s Cathedral HillAdapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 54: Target Value Design Simulation - ENVR

Tesmer Diagram

SD DD CD CA

Design-Bid-Build

Target Costing

Overcoming initial skepticismAdapted from: Rybkowski, Z. K. (2009). “The Application of Root Cause Analysis and Target Value Design to Evidence-Based Design in the Capital Planning of Healthcare Facilities,” Doctoral Dissertation, University of California, Berkeley, CA

Page 55: Target Value Design Simulation - ENVR

Cost performance on some typical construction projects

Cost performance on construction projects using TVD

Cost performance comparing traditional versus TVD case studiesAdapted from: Forbes, L. H., and Ahmed, S. M. (2011). Modern Construction: Lean Project Delivery and Integrated Practices, CRC Press, Boca Raton. . Adapted from: Ballard, G. (personal communication, 2012)

Page 56: Target Value Design Simulation - ENVR

Costs as percentage of starting budget; required to meet specified level of LEED.

Matthiessen, L. F. and Morris, P. (2004) Costing Green: A Comprehensive Cost Database and Budgeting Methodology, Davis Langdon.

How might TVD help reduce the first cost premium of green?

Page 57: Target Value Design Simulation - ENVR

Must green design cost more? Even before TVD was developed, it appears that green

projects designed in an integrated fashion, with early involvement of stakeholders , did

not necessarily cost more.

Now imagine what TVD can do!

Matthiessen, L. F. and Morris, P. (2004) Costing Green: A Comprehensive Cost Database and Budgeting Methodology, Davis Langdon.

Overcoming the cost premium of green buildings

Page 58: Target Value Design Simulation - ENVR

Zofia K. Rybkowski, PhD

Associate ProfessorDepartment of Construction Science

College of ArchitectureTexas A&M UniversityCollege Station, TX

[email protected]


Recommended