+ All Categories
Home > Documents > TCS-Q-113-01-R0

TCS-Q-113-01-R0

Date post: 04-Jun-2018
Category:
Upload: tori-small
View: 220 times
Download: 2 times
Share this document with a friend

of 40

Transcript
  • 8/13/2019 TCS-Q-113-01-R0

    1/40

  • 8/13/2019 TCS-Q-113-01-R0

    2/40

    PAGE NO. 2OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    TABLE OF CONTENTS1.0 SCOPE

    2.0 CONFLICTS AND DEVIATIONS

    3.0 REFERENCE STANDARDS

    3.1 Company Standards

    3.2 Industry Standards

    3.3 ASTM Specifications and Test Methods

    3.4 AASHTO Standards and Test Methods

    4.0 GENERAL REQUIREMENTS

    4.1 On-Site Requirements

    4.2 Material Requirements

    4.3 Safety Requirements

    5.0 DESIGN REQUIREMENTS

    5.1 Specific Requirements

    5.2 Operational Requirements

    5.3 Miscellaneous/Minor Works

    6.0 EARTHWORKS

    6.1 Clearing and Preliminary Works

    6.2 Sub-grade

    6.3 Sub-base and Base Course Materials

    6.4 Construction

    7.0 PRIME AND TACK COAT REQUIREMENTS

    7.1 Prime Coat

    7.2 Tack Coat

    7.3 Precautions and Maintenance of Bituminous Coating

  • 8/13/2019 TCS-Q-113-01-R0

    3/40

    PAGE NO. 3OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    8.0 ASPHALT CONCRETE AND PAVING

    8.1 Materials

    8.2 Asphalt Concrete Mix Design

    8.3 Equipment

    8.4 Preparation of Asphalt Concrete

    8.5 Placement of Asphalt Concrete Mixture

    8.6 Tolerances

    8.7 Quality Control

    8.8 Miscellaneous Works

    9.0 FINAL CLEANUP

    10.0 APPENDIX

  • 8/13/2019 TCS-Q-113-01-R0

    4/40

    PAGE NO. 4OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    1.0 SCOPE

    This Standard covers the minimum mandatory requirements for the construction of Asphalt

    concrete pavement for the Saudi Electricity COMPANY works and includes, but not limited

    to, sub-grade preparation, installation of sub-base, base course and asphalt concrete paving,

    sampling, testing and inspection of materials, and equipment.

    2.0 CONFLICTS AND DEVIATIONS

    2.1 Any conflicts between this Standard and other applicable Saudi Electricity

    COMPANY (SEC) Standards, Industry Standards, Codes, and forms shall be

    resolved in writing by the COMPANY Representative.

    2.2 Any request to deviate from this Standard shall be directed to the Manager,

    Transmission Standards and SpecificationsDepartment.

    3.0 REFERENCE STANDARDS

    The latest revisions of the following Codes and Standards shall be applicable for the

    equipment/material covered in this TCS. In case of conflict, the vendor/ manufacturer may

    propose equipment/material conforming to one group of Industry Codes and Standards

    quoted hereunder without jeopardizing the requirements of this TCS.

    3.1 COMPANY Standards

    3.1.1 TCS-Q-113.02 Construction Standard for Earthworks

    3.1.2 No. 6.483 Special Manual for Industrial Security (Construction Safety

    Manual)

    3.2 Industry Standards

    3.2.1 AASHTO Guide for Design of Pavement Structures.

    American Association of State Highway and Transportation Officials, 1993

    3.2.2 The Asphalt Institute, Manual Series

    1. MS-1 Thickness Design -Asphalt Pavements for Highways and Streets

    2. MS-2 Mix design methods for asphalt concrete and other hot mix types

    3. MS-8 Asphalt Paving Manual

    4. MS-16 Asphalt in paving Maintenance

    5. MS-17 Asphalt overlays for Highways and Street Rehabilitation

  • 8/13/2019 TCS-Q-113-01-R0

    5/40

    PAGE NO. 5OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    3.2.3 Ministry of Communication (MOC):-General Specification for Road and

    Bridge Construction

    3.2.4 General Specifications For Building Construction in Kingdom of Saudi

    Arabia- Latest Edition

    3.3 ASTM Specifications and Test Methods

    3.3.1 Soil Materials

    1. ASTM D 1556 Test Method for Density and Unit Weight of Soil in

    place by the Sand Cone Method

    2. ASTM D 1557 Test Method for Laboratory Compaction Characteristic

    of soil using modified effort 56000 ft-lbs/ft3(2700 kN-

    m/m3)

    3. ASTM D 1883 Test Method for CBR (California Bearing Ratio) of

    laboratory-compacted soils

    4. ASTM D 2419 Test Method for Sand Equivalent Value of Soils and

    Fine Aggregate

    5. ASTM D 2922 Test Method for Density of Soil and Soil Aggregate inplace by the Nuclear Method (Shallow Depth)

    6. ASTM D 4253 Test Method for Maximum Index Density and Unit

    Weight of Soil using a Vibratory Table

    7. ASTM D 4254 Test Method for Minimum Index Density and Unit

    Weight of Soils and Calculation of Relative Density

    8. ASTM D 4318 Test Method for liquid limit, Plastic limit, and

    Plasticity Index of Soil.

    3.3.2 Aggregate Materials

    1. ASTM C 88 Test Method for Soundness of Aggregates by Use of

    Sodium Sulfate or Magnesium Sulfate

    2. ASTM C 117 Test Method for Materials finer than 75-m (No. 200)

    Sieve in Mineral Aggregates by washing

    3. ASTM C 131 Test Method for Resistance to Degradation of SmallSize Coarse Aggregate by Abrasion and Impact in the

    Los Angles Machine

  • 8/13/2019 TCS-Q-113-01-R0

    6/40

    PAGE NO. 6OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    4. ASTM C 136 Method for Sieve Analysis of Fine and Coarse

    Aggregates

    5. ASTM D 692 Specification for Coarse Aggregate for Bituminous

    Paving Mixtures

    6. ASTM D 1073 Specification for Fine Aggregate for Bituminous

    Paving Mixtures

    7. ASTM D 4791 Test Method for flat particles, elongated particles, or

    flat particles and elongated particles in coarse

    Aggregate

    3.4. AASHTO Standards and Test Methods

    3.4.1. Bituminous Materials

    1. AASHTO M-20 Specification for Penetration-Graded Asphalt Cement

    (for use in Pavement Construction)

    2. AASHTO M-81 Specification for Cut-back Asphalt (Rapid-Curing Type)

    3. AASHTO M-82 Specification for Cut-back Asphalt (Medium-Curing

    Type)

    4. AASHTO M-156 Specification for Mixing Plants for Hot Mixed, Hot

    laid Bituminous paving mixtures

    5. AASHTO M-320 Standard Specification for Performance Grade Asphalt

    Binder.

    3.4.2. Test Procedures

    1. AASHTO T-37 Specification for Mineral Filler for Bituminous Paving

    Mixtures

    2. AASHTO T-49 Test Method for Penetration of Bituminous Materials

    3. AASHTO T-99 The Moisture Density Relations of Soils Using a 5.5

    lb. Rammer and 12-Inch Drop

    4. AASHTO T-180 The moisture-Density Relations of Soils Using a 10-lb.

    Rammer and 18-inch Drop

    5. AASHTO T-209 Test Method for Theoretical Maximum Specific

    Gravity and Density of Bituminous Paving Mixtures

    6. AASHTO T-275 Test Method for Bulk Specific Gravity and Density of

    Non absorptive Compacted Bituminous Mixtures

  • 8/13/2019 TCS-Q-113-01-R0

    7/40

    PAGE NO. 7OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    4.0 GENERAL REQUIREMENTS

    4.1 On-Site Requirements

    4.1.1 All works performed and all materials furnished shall be in conformity with

    the lines, grades, cross-sections, dimensions, and material requirements,

    including tolerances, shown on the SEC approved plans/ drawings or

    indicated in the SEC specifications.

    4.1.2 All existing underground utilities which may be exposed/ uncovered or

    otherwise be affected by the excavation work shall be properly protected, by

    shoring, bracing, and supporting, etc., as needed.

    4.1.3 Care shall be taken to protect aerial, surface or underground utilities around

    the site.

    4.1.4 Adequate dewatering equipment to remove and dispose all surface and ground

    water entering the excavations and other parts of the work, shall be provided

    at site and maintained properly.

    4.1.5 Sub-grades or bottom of excavation for structures shall be firm, dense and

    thoroughly compacted as specified under Construction Requirements. It shall

    be free from mud and muck, and sufficiently stable to remain firm and intact

    under the feet of the workmen.

    4.2 Material Requirements

    4.2.1 All materials shall meet or exceed the appropriate AASHTO, ASTM, or other

    Standards and specifications as required by the SEC approved plans/ drawings

    or as indicated in the SEC specifications, but in no case shall be less than the

    requirements of this Standard.

    4.2.2 No material, regardless of its source, shall be incorporated in the Work until

    representative samples taken and tested and have been reviewed and approvedby the COMPANY Representative.

    4.2.3 Field and laboratory tests required to determine compliance with the

    requirements of this Standard before and during the work shall be done by an

    Independent Agency approved by the COMPANY.

  • 8/13/2019 TCS-Q-113-01-R0

    8/40

    PAGE NO. 8OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    4.3 Safety Requirements

    4.3.1 All the required safety provisions of Construction Safety Manual shall be

    strictly followed.

    4.3.2 Excavation by the use of explosives shall be with prior written approval from

    the COMPANY.

    4.3.3 The stability of adjacent structures or facilities including public safety shall

    not be impaired or endangered by excavation work.

  • 8/13/2019 TCS-Q-113-01-R0

    9/40

    PAGE NO. 9OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    5.0 DESIGN REQUIREMENTS

    Design shall be as per AASHTO Guidelines for Design of Pavement Structure, along with

    the requirements and guideline as given in the following sections.

    The thickness of Asphalt Concrete Pavement shall be dependent upon operational

    requirement as determined by COMPANY Design Engineer. The design shall be submitted

    to the COMPANY for checking and approval. The parameters for the calculation of the

    thickness of pavement shall be as given in the following sections.

    5.1 Specific Requirements:

    5.1.1 The traffic analysis period shall be twenty (20) years.

    5.1.2 Axle loads shall be based on a load meter survey, truck and equipment

    manufacturer's technical data or the maximum axle loads allowed by the

    Ministry of Communications, Kingdom of Saudi Arabia. See Table I for

    maximum legal Saudi Arabia truck loads.

    Table I: Wheel Loads

    Maximum Legal Saudi Arabia Truck Loads (per MOC)

    Steerable axle 6000 kg

    Single axle 13,000 kg

    Tandem axle 20,000 kg

    5.1.3 A Terminal Serviceability Index of 2.5 shall be used for all COMPANY

    designated access (pavement) roads and 2.0 for parking and storage lots.

  • 8/13/2019 TCS-Q-113-01-R0

    10/40

    PAGE NO. 10OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    5.1.4 The Structural Layer Coefficient for each pavement component shall be per

    Table II below:

    Table II Structural Layer Coefficients

    PAVEMENT COMPONENT Coefficient per cm.

    Hot mix Asphalt (High

    Stability) 0.16

    Base Course 0.06

    Sub-base Course 0.04

    5.1.5 Traffic Equivalence Factor shall be based on a structural number (SN) of 5.

    5.1.6 The equivalent 18000 lb. (EAL) loads shall be determined from Table III if a

    traffic count cannot be made.

    Table III: EAL Loads

    EQUIVALENT PAVEMENT

    CATEGORIES

    TRAFFIC AND LOAD 18000 lb

    (EAL) Loads

    Access Roadways Sedans to Truck up to 20

    Tons/Axle 1X 105

    Designated Roadways inside

    S/S yards

    Sedans to Truck up to 20

    Tons/Axle IX 105

    Undesignated areas inside S/S

    yards

    Sedans to Truck up to 20

    Tons/Axle I X 104

    Parking and Storage Lots Sedans and small trucks I X 105

    Parking and Storage Lots Heavy Traffic (Truck Material

    Yard)

    I X 106

    Plant Areas Occasional Heavy Loads I X 106

  • 8/13/2019 TCS-Q-113-01-R0

    11/40

    PAGE NO. 11OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    5.2 Operational Requirements

    If the designed pavement thicknesses as per Section 5.1 are lesser than the values per

    Table-IV, then, the values as shown in the Table IV shall be adopted.

    Table IV Thickness of Pavement Components

    Minimum Thickness of

    Base Course (mm) (1)

    Minimum Thickness of Combined

    Binder and Wearing Courses (mm) (2)

    PAVEMENT CATEGORIES CLASS A & B CLASS A CLASS B & C

    Access Roadways 150 80 100

    Designated Roadways inside

    Substation 150 80 100

    Undesignated pavement inside

    Substation 150 65 80

    Parking & Storage lots for

    Sedans and small trucks 150 80 100

    Substations with provision for

    Mobile units 300 - 100

    Parking and Storage Lots for

    Heavy Traffic (Material Yard) 230 120 140

    Power Plants Areas

    Occasional Heavy Loads 230 120 140

    Note: (1). Base Course Classes A & B as per TCS-Q-113.02

    (2). Asphalt Binder Course Classes A & B and Wearing Course Classes

    A, B & C as per Table VI

    5.3 Miscellaneous/Minor/Reinstatement Works

    If the area to be asphalted is small, such as for utility trenches, and non-traffic areas,

    the minimum base course and pavement thickness shall be as shown in Table IV

    with grading limits shown in Table VI.

    For all these works, the finish shall be better or at least same as before the start of

    work. Also, protection and treinstatement shall be done for all markings, affected

    structures and shoulders to the satisfaction of COMPANY and MOC Representative.

  • 8/13/2019 TCS-Q-113-01-R0

    12/40

    PAGE NO. 12OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    6.0 EARTHWORKS

    6.1 Clearing and Preliminary Works

    6.1.1 Clearing site and rough grading shall be per relevant clauses of TCS-Q-

    113.02. Scarification shall be done if required as per COMPANY

    Representative instructions.

    6.1.2 Protection of bench marks, existing structures, roads, sidewalks, pavings and

    kerbs shall be done against damage from vehicular traffic or personnel at the

    existing utilities during cleaning / compaction of sub-grade.

    6.1.3 Designated temporary roads, walkways and detours, for vehicles, pedestriansand working personnel shall be maintained properly.

    6.2 Sub-grade

    6.2.1 The rough grading for sub-grade shall be completed prior to construction of

    the surfacing. The sub-base/ base course material shal not be placed on loose,

    soft and undesirable materials under any circumstances. All soft and yielding

    spots shall be removed till hard and sound strata are available.

    When the top soil consists of loose, soft (sand or clay) or otherwise

    undesirable materials and if there is any inter bedded soil layer of loose, soft(sand or clay), where disclosed underlying the firm/dense layer of soil, then

    such material shall be completely removed until firm soils are encountered

    and replaced with select fill material per TCS-Q-113.02.

    The following soil parameter values shall be considered as soft/loose and

    hence undesirable:

    Table V: Parameters for Unsuitable Soils

    Granular Soils Standard penetrationresistance (SPT) N values Less than 10

    Standard penetration

    resistance (SPT) N values Less than 4Cohesive

    Soils The unconfined

    compression strength, (Cu) Less than 1.0 kg/cm2

    Other portions of the sub-grade, which will not compact easily, when rolled

    or tamped, shall be removed, and all loose rock or boulders, embedded rocks,

    abandoned concrete etc., found in the excavation shall be removed or broken

    off to a depth of not less than 150 mm below the surface of the sub-grade.

  • 8/13/2019 TCS-Q-113-01-R0

    13/40

    PAGE NO. 13OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    6.2.2 All holes, ruts, soft places, and other defects shall be corrected. Irregularities

    or depressions that develop during the compaction should be corrected to thespecified grade by loosening the material at these places and adding,

    removing, or replacing the material.

    Where sub-grade is soil, levelling shall be achieved by using select fill

    materials. In case of rock, the levelling shall be done by concrete of same

    strength as the rock or 5500 psi, as directed by the COMPANY

    Representative. The soft and loose spots shall be removed and filled woth

    selet fill material/concrete as applicable.

    Compaction is then done until the surface is smooth, and uniform. In no case,

    shall the sub-base or base course be placed on soft or unstable material, orover areas that are not properly drained. If the sub-grade is dusty or muddy,

    operations shall be delayed until it is in a condition satisfactory to the

    COMPANY Representative.

    The compaction requirements for sub-grade shall be as follows:

    a. For Substations, the entire sub-grade in the yard shall be compacted to

    95% of the maximum density.

    b. Unpaved and other vacant areas in Substations shall be compacted to

    90% of the maximum density.

    6.2.3 The sub-grade shall be formed so that after compaction it will conform to the

    alignment, grade, and cross-section shown on the drawings, and as required

    by the COMPANY Representative.

    6.2.4 Where rolling of the sub-grade is required, any areas which are inaccessible

    to a roller shall be compacted either by a mechanical or hand tamper meeting

    the approval of the COMPANY Representative.

    6.2.5 Equipment of such weight, used in such a way, as to cause a rut in thefinished sub-grade of 50 mm or more in depth, shall be removed from the

    WORK, or the rutting otherwise prevented.

    6.2.6 The sub-grade shall be kept drained during placing and compaction of the

    sub-base, base course, binder and/or surface course. If berms of earth are

    deposited along the area upon which the succeeding course is being placed,

    provision shall be made for surface drainage by cutting lateral ditches

    through the berm of earth.

    6.2.7 The finished sub-grade shall be maintained in a smooth and compacted

    condition until the sub-base, base course, binder and/or surface course isplaced.

  • 8/13/2019 TCS-Q-113-01-R0

    14/40

    PAGE NO. 14OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    Where existing sub-grade materials are of poor quality, with California

    Bearing Ratioo (CBR) value less than 5 after 4-day soaking., sub-grademodification shall be accomplished to improve the CBR to a minimum value

    of 15. Prior approval of the COMPANY shall be obtained for any

    modification.

    In case CBR test values are not available, test shall be conducted from the top

    0.5 m of soil.

    Sub-grade modification shall be done by one or more of the following

    methods:

    a. Addition of aggregate such as crushed stone or coarse screenings

    b. Replacement of the sub-grade soil with sub-base material with

    minimum CBR of 15 and shall be minimum thickness of 200 mm.

    c. Chemical stabilization/treatment with lime or cement

    d. Asphalt stabilization

    e. Use of geotextiles and/or geogrids

    The minimum compacted thickness of the improved layer shall be 200 mm.CBR tests shall be conducted after the modification to verify the minimum

    requirements.

    6.2.8 Developing of Sabkhah area shall be in accordance with the applicable

    Sections of TCS-Q-113.02.

    6.2.9 At locations where grounding grid is to be installed below the asphalt level,

    following requirements shall be satisfied:

    a. The backfill materials

    shall have a maximum thermal resistivity lessthan 1.2 K-m/W.

    b. The Thermal Resistivity of the backfill materialsshall be lesser than

    that of the existing soil.

    6.3 Sub-base and Base Course Materials

    Minimum thickness of combined binder and wearing courses depends upon the type

    of sub-base. Hence, sub-base / base course materials shall be well-graded of the class

    or classes shown on the approved drawings or specifications. In addition, the

    following requirements are to be satisfied;

  • 8/13/2019 TCS-Q-113-01-R0

    15/40

    PAGE NO. 15OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    6.3.1 All materials shall be free from organic matter, shale or other deleterious

    matter and shall be of such quality that it will bind readily to form a firmstable base for placement of flexible pavement.

    6.3.2 Gradation and physical properties for base and sub-base materials shall

    conform to the requirements of TCS-Q-113.02.

    6.3.3. Class C materialsshall not be used for base course for COMPANY Utilities.

    6.3.4. Class C and Class D materialsfor Sub-base shall be as per TCS-Q-113.02.

    6.4 Construction

    6.4.1 General Requirements

    Prior to placement of the sub-base or the next layer of fill, the sub-grade or

    sub-base shall be inspected and approved by the COMPANY Representative

    for conformity to lines, grades, and typical sectionsshown on the approved

    construction drawings.

    6.4.2 CBR values for each class of fill materialsshall be as per TCS-Q-113.02.

    6.4.3 Placing / Spreading

    Base or sub-base materials shall be spread on the approved sub-grade in

    layers not exceeding 150 mm in compacted thickness. Spreading shall be

    done by means of approved mechanical spreader, distributing the materialsto

    the required loose thickness. Where the required base or sub-base thickness is

    greater than 150 mm, the materials shall be placed in layers of equal

    thickness. In no case shall a layer be less than 75 mm thick. Under no

    circumstances shall any soil materials be dumped in a pile on the sub-grade.

    When base or sub-base course is constructed more than one layer, the

    previously compacted layer shall be cleaned of loose and foreign matter.

    The materials shall be handled so as to avoid segregation. Segregated

    materials shall be remixed until uniformity is attained. Suitable precautions

    shall be taken to prevent rutting of the sub-base or sub-grade during the

    spreading of fill materials. No hauling or placement of materials will be

    permitted when in the judgment of the COMPANY Representative, the

    weather or road conditions are such that the hauling operations will cause

    cutting or rutting of the sub-base or sub-grade or cause contamination of the

    fill materials. The water content of the fill material shall be maintained at the

    optimum moisture content ( 2%) as determined by ASTM D 1557 or

    AASHTO T-180, as obtained from soil investigation reports.

  • 8/13/2019 TCS-Q-113-01-R0

    16/40

    PAGE NO. 16OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    6.4.4 Compaction

    a. The sub-base or base materials shall be compacted, keeping the

    moisture content between ( 2%) of optimum moisture content, with

    equipment capable of obtaining the desired density to the full depth of

    the respective layer.

    The rolling shall continue until the sub-base or base are compacted to

    not less than 95% of the maximum laboratory density as determined

    by ASTM D 1557 or AASHTO T-180 Method for soils containing

    more than 15% materials passing the 75 micron (# 200) sieve or

    compacted to 85% of relative density as determined by ASTM D

    4253 and ASTM D 4254 for free draining soils containing less than15% non-plastic materials passing the 75 Microns (#200) sieve unless

    otherwise specified asper other approved methods.

    b. Base and sub-base materials shall be compacted by means of

    approved compaction equipment, progressing gradually from the

    outside towards the center with each succeeding pass uniformly

    overlapping the previous pass. Rolling shall continue until the entire

    thickness of each layer is thoroughly and uniformly compacted to the

    specified density. Rolling shall be accompanied by sufficient blading

    in a manner approved by the COMPANY Representative, to insure a

    smooth surface free from ruts or ridges and having the proper sectionline and grade.

    c. All areas inaccessible to normal compaction equipment shall be

    compacted by means of mechanical tampers until satisfactory

    compaction is obtained.

    d. Each layer of base/sub-base material must be completely compacted,

    tested and approved by the COMPANY Representative prior to

    delivery of materials for a succeeding layer. Frequency of testing

    shall be in accordance with TCS-Q-113.02.

    6.4.5 Finishing

    The surface of the compacted materialsshall be finished by blading or with

    automated equipment especially designed for this purpose and rolled with a

    steel-wheeled roller. In no case shall thin layers of fine materials be added to

    the top layer of the base course in order to meet the required elevation. The

    surface of the completed base course shall not show any deviation in excess

    of 4 mm when tested with a 4 meter straightedge. The completed thickness of

    the base shall be within 5 mm of the thickness indicated, and the average

    thickness shall not be less than the design thickness.

  • 8/13/2019 TCS-Q-113-01-R0

    17/40

    PAGE NO. 17OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    7.0 PRIME AND TACK COAT REQUIREMENTS

    Asphalt work including primer application and placing of asphalt concrete mixtures shall be

    done only when the atmospheric temperature is 4C or above and when the weather is not

    foggy or rainy and when the existing surface is free from moisture.

    7.1 Prime Coat

    7.1.1 Materials

    The prime coat shall be of medium-curing type cutback asphalt consisting of

    asphaltic base fluxed with suitable petroleum distillates. The product shall be

    free of water, show no separation prior to use, shall not foam when heated toapplication temperature and shall conform to the requirements of Grade MC-

    70 or MC-250 of ASTM D 2027.

    Emulsified asphalt MS-1 or SS-1 conforming to ASTM D 977 may also be

    used after getting approval from the COMPANY.

    7.1.2 Surface Preparation

    The surface shall be cleaned of all loose dirt and other objectionable

    materials by means of approved mechanical sweepersor blowers and or hand

    broomsprior to the application of the prime coat.

    7.1.3 Application

    Prime coat shall be applied uniformly to the base course using a pressure

    distributor at a rate between 1.0 to 1.75 liters per square meter. Excess

    application of primer shall be blotted by using clean and natural sand. The

    application temperature shall be within the ranges of 50C to 80C for MC-

    70 between 65C to 105C for MC-250. The primer shall be applied to a

    width of at least 300 mm greater on each side of the specified width of the

    finished surface. Surfaces in contact with the asphalt are to be primed up tothe asphalt thickness. The surfaces of manholes, catch basins, etc., which

    need to remain free of asphalt, shall be protected with oil to prevent asphalt

    adhesion.

    Prime coat shall be applied only when the surface to be treated is dry and

    when the weather is not foggy or rainy.

    7.1.4 Curing

    The prime coat shall be cured until the penetration into underlying surface

    has been approved by the COMPANY Representative. It shall be fully setand cured for not less than 24 hours before placing an asphalt concrete

    mixture on the base.

  • 8/13/2019 TCS-Q-113-01-R0

    18/40

    PAGE NO. 18OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    7.2 Tack Coat

    7.2.1 Materials

    Tack coat shall be of rapid-curing type cutback asphalt consisting of asphalt

    base fluxed with suitable petroleum distillates. The product shall be free of

    water, show no separation prior to use, shall not foam when heated to

    application temperature and shall conform to the requirements of Grade RC-

    800 of ASTM D 2028.

    Emulsified asphalt RS-1 conforming to ASTM D 977 or CRS-1 conforming

    to ASTM D 2397 may also be used after getting approval from the

    COMPANY.

    7.2.2 Application

    Tack Coat shall be applied on top of the binder course and damaged surfaces

    that are being overlaid by means of bitumen distributor from 0.5 to 1.0 liters

    per square meter or as directed by COMPANY Representative. This shall be

    uniformly applied over the entire surface of the area to be covered. The

    temperature shall be between 95C to 120C.

    Tack coat shall not be placed during rainy weather, sand storm or stormy

    weather, or when the moisture on the surface to be paved would preventproper bond. If application of the surface course is delayed by more than

    three days, dirt or sand and other impurities have contaminated the tack coat,

    then a new tack coat shall be applied thinly after the original one has been

    swept clean.

    7.3 Precautions and Maintenance of Bituminous Coating

    7.3.1 Protection of adjacent structures

    When primers are being applied, the surfaces of all structures, guard rails,curbs and gutters, and other roadway appurtenances shall be protected in a

    manner approved by the COMPANY Representative, to prevent them from

    being splattered with primer or marred by equipment operation.

    7.3.2 Maintenance of Bituminous Coating

    Prime and tack coatsshall be maintained intact until they are covered by the

    succeeding course. Any area where prime coat or previous course has been

    damaged by traffic or by equipment or personnel shall be cleaned of all loose

    materials, the defective surfaces are to be repaired to the satisfaction of

    COMPANY Representative and the prime coat or tack coat shall be re-applied. In case of rain after the application of the primer, the surface shall be

    scraped and allowed to dry to the condition prior to the application before re-

    applying the primer.

  • 8/13/2019 TCS-Q-113-01-R0

    19/40

    PAGE NO. 19OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    8.0 ASPHALT CONCRETE AND PAVING

    8.1 Materials

    8.1.1 Asphalt Cement shall be homogenous, Performance Grade 60-70, 85-100 or

    150-200, free of water, shall not foam when heated to 177C, and conforming

    to the requirements of ASTM D 946.

    8.1.2 Mineral aggregates shall consist of coarse aggregates, fine aggregates, and

    filler material all complying with the following requirements:

    a. When tested according to ASTM C 117 and ASTM C 136, the

    combined mineral aggregates shall conform to the gradation, shownon Table VI below.

    Table VI: Gradation for Combined Aggregates

    Sieve Size

    Asphalt Binder

    Course

    Asphalt Wearing Course

    mm/micron(US) Class A Class B Class A Class B Class C

    38.0 100 - - -

    25 100 80-100 - - -

    19.0 80-100 70-90 100 100

    12.5 ------ ------ 80-95 80-100 100

    9.5 60-80 55-75 ------ ------ 80-100

    4.75 (No. 4) 45-65 44-62 48-62 50-70 55-75

    2.0 (No. 10) 30-50 33-48 32-45 32-47 32-47

    425 micron (No. 40) 15-32 16-27 16-26 16-26 16-26

    212 micron (No. 80) - - 8-18 10-18 10-18

    75 micron (No. 200) 3-10 3-10 4-8 4-10 4-10

    The job mix formula grading may be varied within the specified limits on

    the basis of Marshall tests to obtain optimum stability, percent air voids,

    and voids in mineral aggregates of the compacted bituminous pavingmixture.

  • 8/13/2019 TCS-Q-113-01-R0

    20/40

  • 8/13/2019 TCS-Q-113-01-R0

    21/40

    PAGE NO. 21OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    8.2 Asphalt Concrete Mix Design

    8.2.1 Mix Design Methods

    Asphalt concrete mix shall be designed by satisfying any one of the following

    methods.

    8.2.1.1 Marshall Test Method

    This method is used in this document as guideline for the mix design.

    8.2.1.2 SHRP (Superpave) System

    This method of design has been explained in Appendix. The

    parameters to be obtained and other details are also included.

    8.2.1.3 HVEEM Test Method

    This method can be adopted for design of asphalt pavement for the

    SEC system upon approval by the COMPANY Design Engineer.

    8.2.2 The asphalt concrete mix design shall be submitted for review and approval

    by the COMPANY at least thirty (30) days prior to start production of plant

    mix. The design shall be a combination of mineral aggregates and asphaltcement in such proportion as to produce a mixture conforming to the

    composition limits by weight per Table VIII.

    Table VIII

    Mineral Aggregate Percent

    Total Mineral 93-96

    Asphalt cement 4-7

  • 8/13/2019 TCS-Q-113-01-R0

    22/40

    PAGE NO. 22OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    When tested according to the Marshall Method, the Asphalt Concrete mixture

    shall conform to the requirements of Table IX:

    Table IX

    Binder Course Wearing Course

    Flow (mm) 2.4-5.0 2.0-4.0

    Stability (kg) 820 min. 820 min.

    Loss of Marshall stability by

    submerging (ASTM D1559). (see note) 25% max. 20% max.

    Voids in total mix (%) 3.0-7.0 3.0-5.0

    Voids filled with Bitumen (%) 60-75 70-80

    Class A- 13 % Class A- 14 %

    ClassB - 12 % Class B- 15 %

    Voids in mineral aggregate (VMA)

    ASTM D2041

    (Minimum) Class C -16 %

    Note: Loss of Marshall Stability is measured by submerging specimens in water at

    60C for 24 hours as compared to stability measured after submersion in

    water at 60C for 20 minutes. (ASTM D 1559)

    A compaction effort of 75 blows per ASTM D 1559 shall be used for the mix

    design of all asphalt mixtures for SEC works.

    8.2.3 After receiving the COMPANY approved asphalt mix design, the

    proportioning of the individual aggregates, mineral filler and asphalt cement

    shall be done so as to produce a final mix that, when compared to the asphalt

    mix design, shall be within the tolerance limits of Table X.

    Table X Mix Design Tolerances

    Materials Tolerance

    Aggregate sieve size 4.76 mm (No.4) and larger 5.0

    Aggregate sieve size 2.0 mm (No.10) and retained

    on sieve size 75 microns (No.200) 5.0

    Aggregate sieve size 75 microns (No.200) and

    smaller 1.5

    Asphalt content 0.3

  • 8/13/2019 TCS-Q-113-01-R0

    23/40

    PAGE NO. 23OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    The Asphalt concrete mix shall be tested periodically for conformity to the

    approved asphalt mix design. If, during production, the grading of theaggregates alters, the mixture shall be redesigned and the plant to be

    readjusted.

    8.3 Equipment

    8.3.1 All the construction and asphalt batching plant equipment shall conform to

    the requirements of Ministry of Communication (MOC), General

    Specification for Road and Bridge Construction.

    8.3.2 In addition to the above requirements, trucks used for hauling Asphalt

    Concrete Mixture shall have tight, clean, smooth metal beds which have beenthinly coated with a minimum amount of paraffin oil, lime solution (1:3 with

    water), or other approved material to prevent the mixture from adhering to

    the beds. Each vehicle shall be equipped with a canvass, tarpaulin cover, or

    other suitable material of such size to protect the mixture from the weather.

    No petroleum derivatives shall be used to coat the truck beds.

    8.3.3 Rolling equipment shall be self-propelled. The wheels on the rollers shall be

    equipped with adjustable scrapers and the rollers shall have water tanks and

    sprinkling apparatus which shall be used to keep the wheels wet and prevent

    the surface material from sticking.

    Weights of two-axle tandem steel rollers, three-axle tandem steel rollers,

    three-wheel steel rollers and self propelled pneumatic tired rollers shall be as

    specified in MOC General Specification for Road and Bridge Construction.

    The total weight of the pneumatic tired roller shall be varied to prevent

    displacement of the asphalt concrete mixture.

    8.4 Preparation of Asphalt Concrete

    8.4.1 Asphalt cement shall be heated within a temperature range of 135C to

    163C at the time of mixing. All materials

    reheated more than 42C abovethe maximum shall be considered overheated and shall be rejected until the

    materialscan be re-sampled and tested. The reacceptance or rejection shall be

    made on the same requirements as established for the original materials.

    Asphalt cement received from the refinery at temperatures in excess of

    163C, but not exceeding 191C, may be used.

    Note: If polymers are used, these may require higher mixing temperatures.

    Mixing temperature range should be determined to be the temperature at

    which the asphalt binder has viscosity of 0.170 0.020 pa-s while

    compaction temperature range should be determined to be the temperature at

    which the asphalt binder has viscosity of 0.280 0.030 pa-s. The limits canbe determined from temperature-viscosity plot as developed by Rotational

    Viscometer.

  • 8/13/2019 TCS-Q-113-01-R0

    24/40

    PAGE NO. 24OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    8.4.2 Each aggregate ingredient shall be heated and dried at such temperatures that

    the temperature recorded in the hot fines bin after screening shall not exceed163C. If the aggregates contain sufficient moisture to cause foaming in the

    mixture, or if their temperature is in excess of 163C, they shall be removed

    from the bins and returned to their respective stockpiles.

    Immediately after heating, the aggregates shall be screened into at least three

    (3) sizes and conveyed into separate bins ready for batching and mixing with

    asphalt cement. When the aggregates furnished are of such size and grading

    that separating into three (3) bins is impractical, the number of required

    separations may be reduced to two (2) with the approval of the Engineer. The

    efficiency of the screening operations shall be sufficient to produce, at plant

    operating capacity, gradations in each of the sizes of heated and driedaggregates, which are reasonably uniform and result in the production of a

    mixture complying with the limits specified for the asphalt concrete mixture.

    8.4.3 Dried aggregatesas specified for asphalt concrete pavement construction and

    prepared as prescribed above shall be combined in the plant in the

    proportionate amounts as approved. Asphalt cement shall be introduced into

    the mixture in the proportionate amount all according to the COMPANY

    approved asphalt concrete mix design.

    The temperature of the asphalt, except for temporary fluctuations, shall not

    be lower than 14C below the temperature of the aggregate at the time thetwo materials enter the mixer or pug mill.

    During drying operations of aggregates for batch and continuous mixing

    plants to produce central plant hot-mixtures, the moisture content of mineral

    aggregates shall not exceed 0.25 percent.

    8.5 Placement of Asphalt Concrete Mixture

    8.5.1 Placing/Spreading

    a. The Asphalt Concrete Mixture shall be placed without delay on

    completion of 24 hours after priming the base course.

    b. All asphalt concrete mixtures shall be delivered to the site covered

    with tarpaulin prior to loading on the pavers at a temperature between

    1390C to 1630C. Mixtures delivered at other than these temperatures

    shall be rejected. No placement of asphalt concrete shall be permitted

    if the atmospheric temperature is below 4o C, when the weather is

    foggy or rainy, and when the existing surface is not free from

    moisture.

    If polymers are used which may require higher mixing temperatures,

    (see note in clause 7.4.1), mixing and laying temperature range should

    be determined and used.

  • 8/13/2019 TCS-Q-113-01-R0

    25/40

    PAGE NO. 25OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    c. The Asphalt Concrete Mixture shall be spread and finished true to

    line and grade by automatically controlled bituminous paver. Themaximum lift for any layer shall be 75 mm. Asphalt Concrete

    mixtures may be spread and finished by hand methods only where

    machine methods are impractical as determined by the COMPANY

    Representative.

    d. Asphalt concrete binder course shall be spread in a placement

    thickness so that after rolling, the nominal thickness after compaction

    will not exceed 75 mm or less than 50 mm per layer.

    e. The automatically controlled paver shall spread the Asphalt Concrete

    mixture without tearing the surface and shall strike a finish that issmooth, true to cross section, uniform density and texture and free

    from hollows, transverse corrugations and other irregularities. The

    joints made during the work shall be vertical, straight, clean, and free

    of broken or loose materials. All vertical joints are shall be primed to

    ensure proper bond.

    f. The paver shall be operated at a speed which will give the best result

    and which coordinates satisfactorily with the rate of delivery of the

    mixture to the paver so as to provide a uniform rate of placement

    without intermittent stoppages.

    g. Asphalt concrete wearing course shall be made flush with rain gutters,

    if any, adjacent to the pavement.

    8.5.2 Compaction of Mixtures

    a. After spreading and strike-off of asphalt mixture and as soon as

    possible, mixture shall be thoroughly and uniformly compacted.

    b. Rollers shall be of the steel/pneumatic tire type, shall be of good

    condition capable of reversing without backlash, and shall be operatedat speeds slow enough to prevent displacement of the mixture. The

    number and weight of rollers shall be sufficient to compact the

    mixture to the required density while it is still in a workable

    condition. Use of equipment, which results in excessive crushing of

    the aggregates shall not be permitted.

    c. Compaction shall be carried out in three passes sequence operations.

    Each pass of roller shall overlap the previous pass to ensure smooth

    surface free of roller marks. Rollers shall be operated by competent

    and experienced operators and shall be kept in operation

    continuously, if necessary, so that all parts of the pavement willreceive substantially equal compaction within the time desired.

  • 8/13/2019 TCS-Q-113-01-R0

    26/40

    PAGE NO. 26OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    d. The initial or breakdown rolling shall be done by means of a tandem

    power steel roller or three (3) wheeled power steel roller followed byrolling with a pneumatic-tired roller. Final compacting and finish

    rolling shall be done by means of pneumatic tired roller. The wheels

    of the rollers shall be kept properly moistened with water to prevent

    adhesion of the mixture to the rollers. Excessive water shall not be

    permitted. For other equipment, see section 8.3.

    e. Hand tamping or plate compactor may be used where the area is

    inaccessible to the rolling equipment.

    f. The surface of the compacted asphalt pavement shall be true to lines,

    grades and elevations indicated and shall be free from anydepressions. The paving machine shall be fitted with an automatic

    screed control operating from an independent grade line or with a

    long ski (traveling reference) for leveling the courses. The binder

    course shall be laid with utmost accuracy so that there are fewer

    chances of deformations in the wearing course.

    g. The compacted density of asphalt concrete pavement shall be equal or

    greater than 96% of the Marshall Density of each day's production.

    8.6 Tolerances

    8.6.1 Weighing Scales

    The accuracy of the weighing devices for mineral aggregates and bituminous

    materials shall be within 1.0% of the actual weight being measured per

    ASTM D 995.

    8.6.2 Thickness of Asphalt Concrete

    The total thickness of the asphalt concrete pavement shall be measured in a

    separate operation for each course. Measurement of any core sample shall notbe deficient by 5 mm or 7% of the designed thickness whichever is less.

    Core samples shall be taken from the binder course prior to placement of the

    wearing course. Core sampling for the wearing course shall be taken as near

    as possible to the location where the core sample for binder course was taken.

    The placement thickness of the wearing course shall be adjusted when the

    average thickness of the binder course is deficient by more than 5 mm.

    If the total thickness of asphalt is found deficient, additional cores at intervals

    of not more than 25 meters apart for parking/storage lots and at every 100

    linear meters for roadways taken parallel to the centerline in each direction todetermine the average thickness of the pavement. Deficiency in average

    thickness exceeding the specified tolerance shall be corrected without

    additional compensation from the COMPANY.

  • 8/13/2019 TCS-Q-113-01-R0

    27/40

    PAGE NO. 27OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    Correction shall be done by total removal of deficient materialsand replacing

    them with new materials. The deficient thickness area shall be removed bysaw cutting to the full depth of wearing and binder courses, forming parallel

    and perpendicular lines to the architectural features where practical. Same

    procedure will be done for all the areas to be repaired.

    Application of additional thin layers of fine materials to the top of wearing

    course shall be permitted in order to achieve the required thickness or

    specified tolerances.

    8.6.3 Surface Tolerance

    The asphalt concrete surface shall be tested either by the straightedge testmethod or by the water flooding test method as directed by COMPANY

    Representative at his option:

    a. Roadways

    i. The variation of the asphalt surface from the testing edge of

    the four {4) meter straightedge between any two (2) contacts

    with the surface shall at no point exceed 4.0 mm when placed

    on or parallel to the centerline of the roadway or 3.0 mm when

    placed perpendicular to the centerline of the roadway.

    ii. For water flooding test, the finished asphalt concrete surface

    shall not have evidence of water ponding greater than 5.0 mm.

    b. Large Areas

    Surface tolerances for large areas, such as substation yards, storage

    yards, parking areas, etc., are specified below;

    i. The variation of the asphalt surface from the testing edge of

    the four (4) meter straightedge between any two (2) contactswith the surface shall at no point exceed 4.0 mm when placed

    in any direction.

    ii. Water flooding of the asphalt concrete surface shall be done to

    check proper drainage and water ponding and the following

    conditions shall be adhered to:

    (a) The finished surface shall not show any water ponding.

    (b) The finished surface shall not have any depression.

    All humps and depressions exceeding the specified tolerancesshall be corrected by removing the defective work and

    replacing it with new material as directed by the COMPANY

    Representative conforming to Asphalt Manual MS-16.

  • 8/13/2019 TCS-Q-113-01-R0

    28/40

    PAGE NO. 28OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    8.7 Quality Control

    8.7.1 A Quality Control Program shall be prepared and submitted for review and

    approval by the COMPANY which shall include, but not limited to, material

    and equipment checks, construction, inspection and testing of finished

    asphalt concrete pavement.

    8.7.2. The asphalt concrete batching plant shall also maintain a Quality Control

    Program which includes the following material tests and frequencies:

    a. Materials

    Test Frequency

    Penetration of Asphalt Cement 1/week or 1/lot

    Gradation of Fine, Coarse

    Aggregates & Filler materials 1/week or 1/lot

    Specific Gravity of Aggregates l/week

    Resistance to Abrasion (LA) l/month

    Sulfate and Magnesium soundness l/month

    Sand equivalent l/month

    Plasticity Index l/month

    b. Uncompacted Asphalt Concrete

    Samples for extraction, gradation and Marshall Properties shall be

    taken daily at the following rates of production

    0 to 500 tons 1 per 100 tons500 to 800 tons 1 per 150 tons

    800 and above tons 1 per 200 tons

    c. Compacted Asphalt Concrete

    Cores for density and thickness shall be taken daily from previous

    day's work at the following rates of placement

    Less than 4000 m2 1 per 400 m2

    4,000 to 20,000 m2 1 per 900 m2

    20,000 and above m2

    1 per 1200 m2

    For minor Asphalt Works, the sampling for Marshall Properties and

    Cores shall be taken as directed by the COMPANY Representative.

  • 8/13/2019 TCS-Q-113-01-R0

    29/40

    PAGE NO. 29OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    8.7.3 The independent laboratory must provide upon request, valid calibration

    certificates of all testing equipment and the results of all Quality Control(QC) tests on materials and asphalt concrete mixtures to the COMPANY.

    Validity period for Calibration Certificates shall be 4 (four) months and the

    calibration shall be done by COMPANY approved laboratory.

    COMPANY Representative shall be given full access to the testing

    laboratory facilities, the asphalt concrete batch plant, and the job site for his

    inspection. All testing and production records shall be made available upon

    request.

    8.7.4 Protect the newly compacted section of asphalt concrete from traffic byproviding barricades or approved suitable method until it has hardened

    properly.

    8.8 Miscellaneous Works

    Suitable and appropriate methods as directed by the COMPANY Representative

    from Asphalt Institute Manuals MS-16 and MS-17 shall be adopted for the following

    works:

    Preventive maintenance, including Drainage maintenance, Fog Seal

    Routine Maintenance like crack sealing, Pot Holes and Patching, etc.

    Major Maintenance, including Surface Treatment, Distortions, Slurry Seals, Surface

    recycling, etc.,

    9.0 FINAL CLEANUP

    Upon completion of the work and before final acceptance, the project site including adjacent

    properties defaced, damaged or occupied by the equipment and personnel in connection withthe work shall be cleaned of all rubbish, excess materials, false work, temporary structures

    and equipment and the damages repaired to the satisfaction of the COMPANY

    Representative. The project site and all parts of the work shall be left in a neat and

    presentable condition.

    10.0 APPENDIX

    Superpave (SHRP) Method of design has been explained in th Appendix.

  • 8/13/2019 TCS-Q-113-01-R0

    30/40

    PAGE NO. 30OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    SUPERPAVE (SHRP) METHOD OF PAVEMENT DESIGN.

    1.0 SELECTION OF DESIGN LEVEL

    Superpave analysis and design method being more complex than those in current use, the

    extent of its use depends on the traffic level or functional classification of the pavement for

    which it is being used. Consequently, three levels of superpave mixture design and analysis

    are being used. Their extent of use and testing requirements are:

    Table-I

    Traffic, ESALs Design level Testing requirements*

    106 Mix Design Volumetric design

    106< ESALs 107 Intermediate mix design

    Volumetric design+

    Performance prediction tests

    ESALs>107 Complex mix analysis

    Volumetric design+ Enhanced

    performance prediction tests

    * In all cases, moisture susceptibility must be evaluated using AASHTO T-283.

    For SEC facilities, referring to Table III in TCS-Q-001, the design level is to be limited to

    option # 1 in the above table, corresponding to the traffic Level of up to ESALs 1X106.

    2.0 TERMS AND DEFINITIONS

    TERMS SYMBOL DEFINITIONS

    2.1 Air Voids Paor Va Total Volume of small air pockets between coated

    aggregates particles expressed as Percentage of the bulk

    volume of the compacted paving mixture

    2.2 Voids in

    Mineral

    Aggregates

    VMA The volume of inter granular void space between the

    aggregate particles of a compacted paving mixture that

    includes the air voids and effective asphalt content

    expressed as Percentage of the total volume of the

    compacted paving mixture

    2.3 Effective

    Asphalt

    content

    Pbe The total asphalt content of the paving mixture less the

    portion of asphalt binder that is absorbed by the aggregate

    particles expressed as Percentage of the total weight of the

    compacted paving mixture2.4 Voids filled

    with Asphalt

    Pfa or

    VFA

    The portion of the VMA that contains asphalt binder

    expressed as Percentage of the total volume of mix or

    VMA

  • 8/13/2019 TCS-Q-113-01-R0

    31/40

    PAGE NO. 31OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    TERMS SYMBOL DEFINITIONS

    2.5 Aggregate

    Bulk specific

    gravity

    Gsb The ratio of the mass in air of a unit volume of aggregate,

    including permeable and impermeable voids, to the mass of

    an equal volume of water, both at the same temperature

    2.6 Aggregate

    effective

    specific

    gravity

    Gse

    The ratio of the mass in air of a unit volume of aggregate,

    excluding voids permeable to asphalt, to the mass of an

    equal volume of water, both at the same temperature

    2.7 Asphalt

    binder

    specific

    gravity

    Gb The ratio of the mass in air of a given volume of asphalt

    binder, to the mass of an equal volume of water, both at the

    same temperature

    2.8 Mixture Bulk

    specific

    gravity

    Gmb

    The ratio of the mass in air of a given volume of compacted

    HMA to the mass of an equal volume of water, both at the

    same temperature

    2.9

    Theoretical

    maximum

    specific

    gravity of the

    mix

    Gmm

    The ratio of the mass of a given volume of HMA with no

    air voids to the mass of an equal volume of water, both at

    the same temperature

    2.10 Volume of

    absorbed

    asphalt

    Vba The volume of the asphalt binder that has been absorbed

    into the pores of the aggregate

  • 8/13/2019 TCS-Q-113-01-R0

    32/40

    PAGE NO. 32OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    3.0 VOLUMETRIC MIX DESIGN

    For design of the asphalt concrete mix, the following steps to be adopted:

    3.1 Selection of aggregates

    3.2 Selection of binders

    3.3 Selection of a design aggregate structure (Trial Blend Analysis)

    3.4 Selection of Design Asphalt Binder Content

    3.5 Moisture Sensitivity

    3.6 Performance Based tests

    3.1 Selection of Aggregates

    3.1.1 Properties of Aggregates

    Table-II gives the tests and the requirements for the aggregates for use in

    Superpave for SEC facilities.

  • 8/13/2019 TCS-Q-113-01-R0

    33/40

    PAGE NO. 33OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    Table-II

    All tests are for ESALs 0.3-1x106

    Tests ASTM AASHTO Requirements Remarks

    Coarse Aggregate

    angularity*

    75% top 100 mm

    50% lower than

    100 mm

    (At least one

    crushed faces)

    Fine Aggregate angularity* 40%

    Flat and elongated pieces,

    by weight (larger than 25

    mm, thickness less than 1/5

    length)

    D 4791 10% max

    Sand Equivalent D 2419 T 176 45% min

    Los Angeles Abrasion

    Limits T 96 45% max

    For Wearing &

    binder Courses

    Specific Gravity for Coarse

    Aggregates C 127

    Depends on

    local material

    Specific Gravity for Fine

    Aggregates C128

    Depends on

    local material

    Deleterious Materials T 112 Nil

    For Wearing &

    binder Courses

    12% max Fine

    aggregates

    Loss by Sodium Sulphate

    test. C88 T 104

    15% max Coarse

    Aggregates

    18% max Fine

    aggregates

    Loss by Magnesium Sulfate

    Soundness Test C88 T 104

    20% max

    Coarse

    Aggregates

    Moisture Content 0.25% Max.

    * For Surface Course depth 100 mm.

    3.1.2 Gradation And Restricted Zone

    a. The control points for the Superpave mixtures gradation are as

    follows:

  • 8/13/2019 TCS-Q-113-01-R0

    34/40

    PAGE NO. 34OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    Table-III

    Percentage Passing For Mixture TypesSieve Size

    (mm) SP375 SP250 SP190 SP125 SP95

    50 100

    37.5 90-100

    25.0 90-100 100

    19.0 90-100 100

    12.5 90 90-100 100

    9.5 90-100

    2.36 15-41 19-45 23-49 28-58 32-670.075 0-6 1-7 2-8 2-10 2-10

    b. Restricted Zones

    The combined aggregate gradation shall pass between control points

    and should not pass through the restricted zone as shown in the table

    IV and as plotted on a 0.45 power chart. Mixtures passing through this

    zone will be considered only if the mixture satisfies all other

    requirements.

    Table-IV

    Percent passing limits for Restricted ZoneSieve Size

    (mm) SP375 SP250 SP190 SP125 SP95

    4.75 34.7 39.5

    2.36 23.3-27.3 26.8-30.8 34.6 39.1 47.2

    1.18 15.5-21.5 18.1-24.1 22.3-28.3 25.6-31.6 31.6-37.6

    0.600 11.7-15.7 13.6-17.6 16.7-20.7 19.1-23.1 23.5-27.5

    0.300 10 11.4 13.7 15.5 18.7

    3.2 Selection of Binders

    Asphalt binder shall be selected based on AASHTO MP-1 specification

    Performance-Graded Asphalt Binder to meet Performance Grade (PG) of at least

    76-10. The selected Binder should meet the testing requirements shown in table V.

    The contractor should present testing certificate from an acceptable testing agency to

    certify that the selected asphalt meets the requirements of Table V. Polymer additive

    may be required to meet the PG 76-10 requirements.

  • 8/13/2019 TCS-Q-113-01-R0

    35/40

    PAGE NO. 35OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    Table V: Performance-Graded Asphalt Binder Specification

  • 8/13/2019 TCS-Q-113-01-R0

    36/40

    PAGE NO. 36OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    3.3 Selection of a Design Aggregate Structure (Trial Blend Analysis)

    3.3.1 Selection of Trial Blend

    For the selection of the trial blend, at least three sets of aggregate blends

    consisting of varying stockpile percentages of each aggregate size are taken.

    The sieve analysis is conducted for each of the blends. A plot of percentage

    passing and sieve size raised to power 0.45 is done. It is recommended that

    the plot passes below the restricted zone and must be within the control

    points.

    3.3.2 Estimation of Aggregate Blend Properties

    The aggregate blend properties shall be calculated mathematically from

    calculated values as follows with the limits as shown in Table II.

    3.3.3 Evaluation of trial blends

    Two specimens are made with each of the blends using Superpave Gyratory

    Compactor and volumetric properties are determined. The trial asphalt binder

    content is determined for each trial blend by estimating the effective specific

    gravity of the blend using the formula below:

    a. Bulk specific gravity

    Gse= Gsb+ Y (Gsa-Gsb)

    Where, Y= 0.7 to 0.8 depending on the absorption of the aggregate

    The Bulk specific gravity of the combined aggregate (Gsb)

    Gsb

    = (P1+ P

    2+P

    3)

    P1 P2 P3

    G1 G2 G3

    Where Pi =Percent by mass of each component aggregate in blend

    Note: (P1+ P2+P3) = 100

    Gi= Gsbof each component aggregate in blend

    b. Volume of asphalt binder (Vba)

    Calculate the volume of asphalt binder (Vba) absorbed into the

    aggregatesby using the following equation:

    ++

  • 8/13/2019 TCS-Q-113-01-R0

    37/40

    PAGE NO. 37OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    Vba= Psx (1-Va) x 1 1

    Pb Ps Gsb GscGb Gse

    Where, Vba= volume of absorbed binder, cm3/cm3of mix

    Ps = Percent of aggregates

    Va = volume of air voids

    Gb= specific gravity of binder

    Pb= Percent of binder

    c. Volume of effective binder (Vbe)

    Calculate the Volume of effective binder (Vbe) for the blend using the

    following formula:

    (Vbe) = 0.081 0.02931 x {In(Sn)} cm3/cm3of mix

    where Sn= The nominal maximum sieve size of the aggregate

    blend (in inches)

    d. Initial trial asphalt binder (Pbi)

    Calculate the initial trial asphalt binder (Pbi) using the following

    formula:

    Pbi= Gbx (Vbe+ Vba) x 100

    Gbx (Vbe+ Vba)

    Ws

    Where Pbi= Percent (by weight of mix) of binder

    Ws= weight of aggregate (grams)

    Where Ws= Psx (1 Va)

    Pb + Ps

    Gb Gse

    e. Maximum theoretical specific gravity of the mixture

    Two specimens are prepared for the determination of Maximum

    theoretical specific gravity of the mixture. Two other samples are

    made for each trial blend using Superpave Gyratory Compactor

    (SGC). AASHTO T-209 gives the minimum size of sample required

    for various mixtures.

    + -

  • 8/13/2019 TCS-Q-113-01-R0

    38/40

    PAGE NO. 38OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    The number of gyrations for initial compaction, design compaction

    and maximum compaction shall be determined from Table VIfollowing AASHTO MP-2 specification.

    Densification is done for the sample specimens and SGC data

    obtained. Plots are drawn for %Gmm versus the logarithm of the

    number of gyrations.

    Also, the percent of air voids and voids in the mineral aggregates

    (VMA) are determined from these tables, using the following

    equations:

    % Air Voids = 100 - % Gmm@ Ndesign

    % VMA = 100- (%Gmm@Ndesignx GmmxPs)

    Gsb

    Keeping 4% air voids at Ndesign, the asphalt binder is estimated for

    each trial blend using the empirical formula as given below:

    Pb,estimated= Pbi 0.4x (4- Va))

    Where, Pb,estimated = Estimated percent binder

    Pbi= Initial (trial) percent binder

    Va= percent air voids at Ndesign

    From all the three trial blends, the effective asphalt binder is

    determined as follows:

    Pbe,estimated= - (Psx Gb) x ( Gse-Gsb) + Pb,estimated

    Gsex Gsb

    Calculation of dust proportion is as follows:

    DP = P0.075

    Pbe,estimated

    The values of dust proportion shall be between 0.6 to 1.2.

    The trial blend satisfying the criteria shown in Table VI (AASHTO

    MP-2) shall be selected as the design aggregate structure.

  • 8/13/2019 TCS-Q-113-01-R0

    39/40

    PAGE NO. 39OF 40TCSQ11301R0/SZA

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Date of Approval: April 10, 2006

    Table VI: Superpave Volumetric Mixture Design Requirements

    (1) Design ESALs are anticipated project traffic level expected on the design lane over a

    20 years period. Regardless of the actual design life of the roadway, determine the

    design ESALs for 20 years and choose appropriate Ndesign level.

    (2) For 9.5 mm nominal maximum size mixtures the specified VFA range shall be 73%to 76% for design traffic levels > 3 million ESALs.

    (3) For 25.0 mm nominal maximum size mixtures the specified lower limit of the VFA

    shall be 66% for design traffic levels

  • 8/13/2019 TCS-Q-113-01-R0

    40/40

    TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.01, Rev. 0

    Minimum of two specimens are also prepared for determination of maximum

    theoretical Specific gravity at the estimated binder content. Specimens are prepared

    and tested in the same manner as the specimens from the section. 3.3. above.

    The test results are tabulated for each trial asphalt binder content. Densification

    curves for each trial asphalt binder content shall be plotted, the average densification

    curve taken from the two specimens for each asphalt content plotted on the same

    plot.

    Mixture properties are evaluated for the selected blend at the different asphalt binder

    contents, by using the densification data at Ninitial, Ndesign, and Nmaximum.

    The volumetric properties are calculated at the design number of gyrations (Ndesign)for each trial asphalt binder content. From these data points, graphs of air voids,

    VMA, and VFA versus asphalt binder content are generated.

    The design asphalt binder content is established at 4.0% air voids. The design

    asphalt binder content corresponding to 4.0% air voids at Ndesign is adopted as the

    design asphalt binder content. All other mixture properties are checked at the design

    asphalt binder content to verify that they meet criteria.

    3.5 Moisture Sensitivity

    The final step in the Superpave mixture design process is to evaluate the moisture

    sensitivity of the design mixture. This is accomplished by performing AASHTO T-

    283 testing on the design aggregate blend at the design asphalt binder content.

    Specimens are compacted to approximately 7% air voids. One subset of three

    specimens are considered control specimens. The other subset of three specimens is

    the conditioned subset. The conditioned subset is subjected to vacuum saturation

    followed by an optional freeze cycle, followed by a 24 hour thaw cycle at 600C. All

    specimens are tested to determine their indirect tensile strengths. The moisture

    sensitivity is determined as a ratio of the tensile strengths of the conditioned subset to

    the tensile strengths of the control subset.

    The minimum criterion for tensile strength ratio is 80%. The design blend, if it

    exceeds the minimum requirement, is the Superpave mixture.

    3.6 Performance Based tests:

    The Performance Based tests for Superpave mix design are optional, as the traffic

    level is 106 ESALs, where only volumetric mix design is considered sufficient.


Recommended