TECHNICAL WORKSHOP 4 – KWADUKUZA MUNICIPALITY
1. BACKGROUND
The KwaDukuza Municipality is one of four local municipalities that fall under the iLembe
District Municipality jurisdiction. The KwaDukuza area covers approximately ±750km²
between the uThongathi and uThukela rivers in Northern Kwa-Zulu Natal. It is located
between Africa’s two largest harbours, the Durban Harbour and Richards Bay harbours.
The boundary extends from:
the uThukela River and the Mandeni Local Municipality in the north,
the eThekwini Metropolitan Municipality and the uThongathi River in the south
the Maphumulo Local Municipality and Ndwedwe Local Municipality boundaries in
the west to
the coastline in the east.
The municipality borders a coastline that spans approximately 50km incorporating a range of
sensitive coastal environments and excellent tourism opportunities. The KwaDukuza region
consists of a number of development nodes with varying degrees of development. All main
towns but three are found along the coast, namely:
Ballito
Shakas Rock
Salt Rock
Tinley Manor
Zinkwazi
KwaDukuza (formally known as Stanger)
Groutville
Shakaskraal
The KwaDukuza Municipality has one of the fastest growing populations in the province, it is
characterised by a fairly young population. The growing population has subsequently
increased the demand for housing, social facilities, infrastructure and economic opportunities
to absorb the labour market. As per the STATS SA 2011 Census data it has experienced a
growth rate of approximately 3.2% between 2001 and 2011.
Figure 1: Current Population – Source: Statistics South Africa
POPULATION
231189
POPULATION GROUP
Black 182284
Coloured 2213
Indian 32532
White 12884
Other 1272
Figure 2: Population Distribution – Source: Statistics South Africa
AGE (YEARS)
< 9 47440
10 - 19 40652
20 - 29 52681
30 - 39 36855
40 - 49 23270
50 - 59 14650
60 - 69 9445
> 70 6195
1.1. Spatial Planning and Growth
The KwaDukuza Spatial Development Framework provides strategic guidance for the future,
physical/spatial development of the KwaDukuza municipal area. It ensures that the
envisaged physical space economy reflects the social, economic and environmental
development issues identified in the IDP. The adopted package of plans provides guidance
for the existing and future physical / spatial development of the municipality. It facilitates
integration, i.e. ensuring appropriate vertical and horizontal linkage of policies, intentions and
development which are given credibility by national, provincial and local policies. A key piece
of information that reflects the growth of KwaDukuza Municipality is that as depicted in the
Statistics South Africa report “Selected building statistics of the private sector as reported by
local government institutions, 2015” where eThekwini Metropolitan Municipality recorded the
0 50 100 150 200
Black
Coloured
Indian
White
Other
Thousands
0
500
1000
1500
2000
2500
< 9
10
- 1
9
20
- 2
9
30
- 3
9
40
- 4
9
50
- 5
9
60
- 6
9
> 7
0
Tho
usa
nd
s
highest value of building plans passed, contributing 68,5% or R11 445,9 million to the total of
R16 706,8 million reported for KwaZulu-Natal during 2015, followed by KwaDukuza
Municipality (13,4% or R2 238,1 million), Msunduzi Municipality (4,7% or R784,0 million),
Newcastle Municipality (3,2% or R540,6 million) and City of uMhlatuze (2,7% or R446,5
million).
The above indicates that the municipality is experiencing rapid growth since it is considered
to being a secondary city.
2. LOCATION MAP
3. DESCRIPTION OF THE TECHNICAL WORKSHOPS
The purpose of the technical workshops is to provide delegates with a diverse experience of
the planning and development atmosphere that currently exists in the Municipality. It will
expose the delegates to a number of the conference themes and further highlight the key
challenges that affect a diverse growing municipality that consists of rural, urban and coastal
regions.
3.1 Study Area 1: Greater Compensation Area Conceptual and Development
Framework Plan
Study area one consists of the southern region of KwaDukuza Municipality. It is located
within an “Aerotropolis” or “Airport city” which has the Dube TradePort and the King Shaka
International Airport as its nucleus. It is also located within the eThekwini-uMhlathuze
corridor which is the primary provincial corridor in terms of the provincial growth and
development plan.
The study area for this framework plan forms part of the southern region of KwaDukuza
Municipality and borders eThekwini Metropolitan Municipality and Ndwedwe Local
Municipality, and it falls within the iLembe District Municipal area. There are challenges
relating to cross border planning involving the different municipalities, bulk infrastructure
availability, and legislation relating to the Subdivision of Agricultural land, 1970 (Act No. 70 of
1970).
Figure 4: Compensation Locality Plan
The role of the study area is detailed below:
Roles Social Economic Environmental
National History and cultural heritage associated with
King Shaka
Economic support role to N2 corridor linking
eThekwini to Richard’s Bay
Sibudu Cave archaeological site
Vegetation and species of national significance
Provincial/
Regional
Mix of suburban, rural/ traditional and
agrarian settlements at the interface between
the northern corridor and inland region for
settlement, landscape, culture
Economic support role to N2 corridor and KSIA/DTP
Expansion of industrial/logistics development along
primary provincial corridor
Regional catchment role for water resources
Regional biodiversity role for KDM/NLM/IDM
interface
Regional landscape role at interface between
developed corridor, rural and natural landscapes
Municipal
Residential area alternative to coastal corridor
Potential social hub for community services
provision
Rural services networks
Consolidation of the urban edge and
protection of the accessibility of the coastal
corridor
Industrial and logistics expansion area and hub
Regional town centre expansion from Ballito
Agriculture and tourism
Employment opportunities and investment location
Protection of water resources and downstream
tourism assets
Rates income for the municipality
Biodiversity and environmental services role for
municipality, including protection of water
resources and downstream assets, UDL, etc.
Visual gateway to the metro and coastal areas
Local /
GCA
Residential settlement area
Social networks and community structures
Community facilities and institutions
Local cultural heritage and tradition
Local economic activities and employment
opportunities
Local retail and commercial services hub
Local environmental services and natural
resources
Local recreation
Landscape and local sense of place
Scenario planning for the Greater Compensation Area:
Growth Scenario 1: Low Growth
1% pa growth rate for KwaDukuza (based on KwaDukuza SDF growth projections) 8% share
of growth allocated to GCA (based on continuation of current share)
Growth Scenario 2: Medium Growth
3% pa growth rate for KwaDukuza (based on continuation of historic growth rate) 10% share
of growth allocated to GCA (based on increasing share given strategic potential of GCA)
Growth Scenario 3: High Growth
5% pa growth rate for KwaDukuza (based on contribution likely to be required from KDM to
achieve 3% pa growth of iLembe District in iLembe RSDP) 12% share of growth allocated to
GCA (based on a significantly increased share given strategic potential of GCA)
Estimated Land Demands
Should Growth Scenario 2 be taken into consideration, it is estimated that approx. 2 350 new
households will need to be accommodated in the GCA by 2020.
LAND USE AREA BASIS
Residential 80ha KDM pop growth of 3% and GCA absorbs 10% of KDM pop increase
Average occupancy ratio of 3 per/du
Average density of 30du/ha
Industrial 60ha KDM absorbs 50% of IDM growth and GCA absorbs 50% of KDM growth
Commercial/Business 20ha Estimated at 25% of residential land demand
Social Facilities 20ha Estimated at 25% of residential land demand
Sports, Recreation and Cultural Open Spaces
20ha Estimated at 25% of residential land demand
Total 188ha –
Figure 5: Compensation Aerial Image
3.1.1 Challenges
Fragmented land use pattern
Identifying new linkages to support existing road networks
Cross border alignment
Provision of Infrastructure
Release of land from the Subdivision of Land Act, 1970 (Act No. 70 of 1970)
Table 4: Drivers of Change in GCA
NO. SOCIAL IMPLICATIONS FOR STUDY AREA
1 Population Growth Medium to high population in KDM and GCA will generate increased demand for housing, facilities, jobs, infrastructure, services, public spaces, etc
2 Demographic Profile
Mixed income, education and skills levels with significant issues in relation to poverty, low skills and education, increasing younger population, etc. impacts in affordability, demand for facilities, skills available in the economy, etc.
3 Settlement Growth Existing settlements at Ballito, Umhlali, Shaka’s Head and Driefontein will attract growth and development and require supporting urban systems
4 Urbanisation and Sprawl
Increasingly urbanised population but tendency for development to occur in more suburban, peripheral and greenfield locations promotes sprawl, inefficient and wasteful resource use, etc.
5 Lifestyle Choices
Preferences for suburban and rural lifestyles impact on the type and location of housing demand Security issues precipitate an increase in cluster/gated developments
6 Social Inclusion
Need for social inclusion and social justice influences demands for greater social, economic and spatial integration, expectations around improved service delivery, requirements for basic needs provision, etc.
NO. ECONOMIC IMPLICATIONS FOR STUDY AREA
1 Agricultural Activities
Declining dominance of the agricultural sector with competing land demands for urban and industrial uses Increasing importance of food security and retention and improvement of food production activities
2 Industrial and Logistics Development
Increased demand for industrial and logistics development linked to N2/R102, airport and DTP Large scale, inward looking nature of development with potential impacts on built form, spatial integration, etc.
3 Commercial and Business Development
Flight of offices, retail and business developments to greenfield sites in suburban and peripheral locations Growing population generates demands for commercial services and employment opportunities
Proposed development in the Greater Driefontein Area:
3.2 eThembeni Precinct Plan/Township Establishment Project
Study area two is the eThembeni township establishment and lies west of the uMvoti Toll
Plaza on the N2 national road and south-east of Groutville, within the KwaDukuza Local
Municipality. The project area comprises 82 properties on approximately 230 hectares which
was set aside for a human settlement project called the Chief Albert Luthuli Rural Upgrade
Project (CALRUP). Previously, the area comprised rural small holdings. However, over the
past few years, the area has experienced rapid development, due mainly to the informal
subdivision and disposal of sites by the original owners. Numerous residential houses have
been and are being constructed on the plots, without formal subdivision or proper planning
layout and, in some cases, in waterlogged areas. As a consequence, there is a need to
formalise the area to control the ad hoc and illegal developments, with structures
appropriately located, with the provision of bulk services and with management of the
environmentally sensitive areas (primarily wetlands) on the site. Added to this situation, is
the fact that a large portion (+-73%) of this area is considered to be a wetland.
To this end, the KwaDukuza Local Municipality has appointed a professional services to co-
ordinate the eThafeni Planning and Development Framework which will guide formal
township establishment.
There are currently a number of interventions under way including:
1) Environmental Authorization,
2) Regularization of illegal development,
3) Providing a Planning framework,
4) Township establishment process, and 5) facilitating the transfer of land.
Figure 9: eThembeni Aerial Image
The key themes that are set out to be addressed are Urban Planning and Policy making in
times of uncertainty, fragility and insecurity, and Planning Activism and Social Justice.
3.2.1. Challenges:
Lack of service infrastructure;
Occupation of uncertified housing structures;
Sand mining operations within the catchment;
Inadequate sewage disposal system due to high water table;
Canalisation, drainage and farming of various units across the site;
Encroachment and direct loss of habitat through formal and ad hoc development
# Issue Description Items of Concern Recommendations Specialists and Key Role
Players Required
1 Wetlands Preliminary
findings indicate
that wetland
coverage could
range between 27
and 81 hectares
(12-35%) of the
total 230 hectare
site (this includes
areas already
under housing).
No development may take
place in wetlands or
associated buffers. This
sterilises potentially 27-81
hectares of the site.
The ongoing protection of
wetlands as a no
development zone is
required in the township
plan. A wetland
rehabilitation plan is
recommended.
Water Use Licenses are
required if development
encroaches on wetlands or
their buffers.
Increase in the
development cost.
A comprehensive wetland
delineation (delineate the outer
edge of the temporary zone of
wetness) is required to
accurately determine wetland
boundaries and appropriate
buffers (generally 30m), so
that “no go” areas can be more
accurately determined.
The planning team is to
determine whether the extent
of “no go” areas affects the
feasibility of developing the
site, from a cost perspective.
Wetland Ecology Specialist
Town Planner
Project Co-ordinator
Specialist studies are
underway and appropriate
applications to the relevant
departments to be done.
2. Existing
Structures in
Wetlands
Subject to
confirmation via
detailed wetland
delineation which is
underway, it is
likely that a number
of houses have
been constructed
within wetlands.
Theoretically, these
structures should be
removed, the area
rehabilitated, the owners
compensated and
application made for Water
Use Licenses from DWA.
Another option is to create
drainage structures to dry
out the areas where the
houses are standing. The
destruction of wetlands and
their buffers would require
retrospective applications to
DWA (Water Use Licenses)
and DAEA (environmental
authorisation).
The project team will need to consider the options, consult with DWA and DAEA and Current and future building in wetlands needs to be stopped.
Wetland Ecology Specialist
Town Planner
Department of Water Affairs
(DWA)
Department of Agriculture
and Environmental Affairs
(DAEA)
3 Poor site
drainage/
site wetness
Regardless of
where true
wetlands are
situated, the site is
generally very wet
as high clay soils
retain moisture and
are poorly drained.
Founding conditions for
structures.
Effects of rising damp on
structures.
Ongoing damp damage to built structures.
Sewage disposal.
Stormwater drainage (to
prevent inundation of
buildings and gardens).
Increased cost of bulk
services.
Relevant specialists and
project team members to
advise on items of concern,
including how this affects costs
of construction, operation and
maintenance.
Soils and Geotechnical
Specialist
Hydrology Specialist
Structural Engineer and
Building Services Specialist
Wetland Ecology Specialist
3 Land use The current land
use is largely
residential,
however, there will
be a change of
land use from
agricultural to
housing via the
Land Use
Management
System
Arable land will be lost.
Vegetable gardens are an
important survival strategy
for poorer households.
The Department of
Agriculture will need to give
permission to develop the
land to a non-agricultural
use.
The town plan should make
provision for the incorporation
of individual or communal
vegetable gardens, some
wetlands may not be used for
this purpose.
Permission to release the land
from agriculture will require a
strong motivation as this goes
against Department of
Agriculture’s policy. This may
be favourable as the area is
already settled
Town Planner
Department of Agriculture
4 Soil and water
pollution
Drainage lines and
streams are
currently polluted
with litter and water
quality appears
poor, especially in
drainage lines
around stand
pipes. Illegal
dumping is taking
place in some
areas.
Waste disposal services
are required.
Ongoing anti litter and
dumping management
required.
Increased cost of service
provision (with a negative
effect on rates).
Project team will need to
consider the level and costs of
services required
(construction, operation and
maintenance).
Town Planner
KwaDukuza Local
Municipality
5 Illegal
subdivisions
and land
ownership
Individual owners
of original large
plots have sold off
small parcels to
numerous
individuals who
have built houses
without legal
subdivision or title
deeds.
Since the subdivisions are
illegal, while new house
owners have invested in
their properties, they are
unlikely to hold legal land
tenure.
The issue of land subdivisions
and land ownership will further
be investigated, confirmed and
resolved.
KwaDukuza Local
Municipality
Town Planner
Land Legal Services
6. Timing of
approvals
Time frames
associated with
various
applications to
obtain the
necessary
authorisations and
licenses are being
sought.
While approvals are being
sought, problems on site (illegal
construction, illegal
subdivisions, inundation,
damage to wetlands, etc) will
continue, if not controlled.
Current and future building in
wetlands needs to be stopped.
The project team will need to
consider how these issues are
managed in the interim.
Town Planner
Legal Advisor
KwaDukuza Local
Municipality
3.3 Groutville Priority 1
Study area three focuses on Groutville which is located approximately 4 km south of the
KwaDukuza Town. This project entails an upgrading of an existing informal settlement which
has both formal and informal structures. There are housing structures that are located on
wetlands and environmentally sensitive areas. The project grapples with the challenge of
maintaining a balance between the provision of infrastructure and sustaining existing
location of houses.
Figure 11: Groutville Aerial Image
The key themes that are set out to be addressed are Transforming Human Settlements.
Urban Planning and Policy making in times of uncertainty, fragility, and insecurity, as well as
Planning activism and Social Justice.
3.3.1 Challenges:
Policy gaps and/or rigidity;
Illegal land transaction;
Illegal development;
Competing needs i.e. provision of social land recreation vs residential opportunities;
Number of proposed units not matching beneficiary needs;
Delays in town planning process of implications on the ground;
Implications to relocation of existing structures located within wetland zone, size of
structure vs low income unit
Images of Groutville Priority 1:
3.4 Rocky Park Integrated Housing Project
Study area four is called the Rocky Park Integrated Housing Project. It is located on the
western periphery of the KwaDukuza CBD. This is a mixed use development comprising of
community residential units, affordable units, and lower income units with associated service
infrastructure and social amenities. It is a ground breaking project as it integrates a range of
income levels and accommodates different forms of housing opportunities.
The project is an infill development and provides housing opportunities within close proximity
to areas of economic activity. The Rocky Park Integrated Residential Development has met
the key objectives of the KwaDukuza Municipality (which are derived form the National and
Provincial Strategies) which include the following:
ensure the development in well located areas that provide convenient access to
urban amenities, including places of employment.
create social cohesion.
servicing of stands for a variety of land uses including commercial, recreational, as
well as residential blocks for both low, middle and high income groups.
land use and income group mix are based on local planning and needs assessment.
As the project is an Integraed Residential Development, part of the criterion for it to be
classified as an Integrated Residential Development it takes into account the different strata
of income levels which determined the mix of income groups and these have been defined
below:
R 0.00 – R 3,500.00
R 800.00 – R10,000.00
R 3,500.00 – R 15,000.00
> R 15,000.00
Tenure types are as folows:
Sectional Title Ownership (Low income)
Low Income Rental
Middle Income Rental
As a synopsis, Breaking New Ground principles were used to inform the project outcomes
which are summarised below:
BNG – KEY PRIORITIES
Is it
applicable
to the
project?
Residents should live in a safe and secure environment, and have adequate access to
economic opportunities, a mix of safe and secure housing, and tenure types, reliable and
affordable basic services, educational, entertainment and cultural activities and health, welfare
and police services.
✔
Ensure the development of compact, mixed land use, diverse, life-enhancing environments
with maximum possibilities for pedestrian movement and transit via safe and efficient public
transport in cases where motorized means of movement is imperative.
✔
Ensure that low-income houses are provided in close proximity to areas of economic
opportunities. ✔
Integrate previously excluded groups into the city, and the benefits it offers, and to ensure the
development of more integrated, functional and environmentally sustainable human
settlements, towns and cities. The latter includes densification.
✔
Encourage social (Medium-density) Rental Housing – Social rental housing is generally
medium-density and this housing intervention may make a strong contribution in urban renewal
and integration.
✔
There is a need to move away from a housing-only approach to a more holistic development of
human settlements, including the provision of social and economic infrastructure. ✔
More appropriate settlement designs and housing products, and more acceptable housing
quality. ✔
Enhancing settlements design by including professionals at planning and project design
stages, and developing design guidelines. ✔
There is a need to focus on changing the face of the stereotypical RDP houses, and
settlements, through the promotion of alternative technology and design. ✔
Social renting houses must be understood to accommodate a range of housing product
designs to meet spatial and affordability requirements. Social housing products may include: ✔
Multi-level flat, or apartment options, for middle income groups, incorporating beneficiary mixes
to support the principle of integration and cross-subsidisation; ✔
Co-operative group housing; and ✔
Communal housing with a combination of family and single-room accommodation ✔
Figure 12: Rocky Park Aerial Image
The key themes that are set out to be addressed are Transforming Human Settlements.
Planning Activism and Social Justice, and Planning for an interlinked and integrated rural-
urban development.
Challenges:
Flexibility of traditional town planning policies (i.e. town planning scheme);
Municipal policies on infrastructure provision not adequately catering for affordable
housing;
Funding availability for beneficiaries
4 EXPECTED OUTCOME
The main purpose of the workshop and selected sites is to expose the delegates to a
number of the conference themes. The workshops will further ensure that the delegates are
provided with a holistic view of key challenges that the municipality has overcome and still
has to overcome in order to achieve the concept of “cities we need”.
The municipality is also hoping to engage delegates in finding innovative and sustainable
solutions in order to solve existing problems as well as provide further guidance in
maximising on identified opportunities.
Images of Rocky Park IRD:
5 PROPOSED ITINERARY
Technical Workshop Item Description Time
1. Workshop delegates depart from Durban ICC
All participants and delegates depart from the Durban ICC
8:00
2. Arrival of delegates at KwaDukuza Municipal offices.
All participants and delegates will be
welcomed by Mr. Mava Ntanta and
Chimene Pereira
9:00
3. Presentation and Discussion - Greater Compensation Area Conceptual and Development Framework Plan.
The municipality will identify a suitable
venue where delegates and participants
will converge to receive briefing on the
Greater Compensation Area Conceptual
and Development Framework Plan
(Study area 1).
9:15
4. Drive around KwaDukuza Municipality
To give delegates a feel of the area 10:00
5. Departure for Rocky Park Integrated Housing project
The delegates will be transported to the
Rocky Park Integrated Housing project
(Study area 4)
11:15
6. Presentation and Discussion - for Rocky Park Integrated Housing project.
Delegates arrive at Rocky Park.
Presentation by Mr. Themba Dube 11:45
7. Departure for Chief Albert Luthuli Museum
The delegates will be transported to the
Groutville Priority 1 area (Study area 3) 12:30
8. Arrive at Chief Albert Luthuli Museum
Delegates arrive at Groutville Priority 1.
Presentation by Mr. Brian Xaba.
LUNCH and
13:00
9. Departure for eThembeni
The delegates will be transported to the
eThembeni area (Study area 2) 14:30
10. Arrive at eThembeni Delegates arrive at eThembeni.
Presentation by Mr. Mava Ntanta 14:45
11. Departure for Groutville Priority 1
The delegates will be transported to the Chief Albert Luthuli Museum
15:45
12. Presentation and Discussion - for Groutville Priority 1
Delegates arrive at Groutville Priority 1.
Presentation by Mrs. Nqobile Khawula 16:00
13. Discussion and debriefing
All to contribute 16:45
Technical Workshop Item Description Time
14. Workshop delegates depart from KwaDukuza Municipality for Durban ICC
All participants and delegates depart from the KwaDukuza Municipality for Durban ICC 17:00
6 TECHNICAL WORKSHOP LEADER(S)
Mr. Mava Ntanta – Director (EDP)
Mr. Chimene Pereira – Chief Town Planner (EDP)
Mr. Themba Dub – Director Human Settlements
Mrs. Nqobile Khawula – Senior Manager KDM Human Settlements