+ All Categories
Home > Documents > Tender Assigment

Tender Assigment

Date post: 05-Apr-2018
Category:
Upload: nabeela-aman
View: 234 times
Download: 0 times
Share this document with a friend

of 27

Transcript
  • 7/31/2019 Tender Assigment

    1/27

    TENDER ESTIMATION

    Page 1

    ACKNOWLEDGEMENT

    First of all I wish to express my sincere gratitude to Almighty God for giving me the courageand determination to complete this assignment.

    Also I would like to express my utmost gratitude to my lecturerMR.N.T.K.LOKULIYANA he

    gave me excellent guideline to complete this assignment and assess my all performance with

    his busy schedule

    Finally I like to thank to my class friends to give me a good corporation to complete this

    assignment

  • 7/31/2019 Tender Assigment

    2/27

    TENDER ESTIMATION

    Page 2

    CONTENTS

    ACKNOWLEDGEMENT....01

    CONTENTS.02

    TASK -01

    1.1... .........................03-07

    1.2....08 -09

    1.310

    TASK -02

    2.1.11

    2.2 . ...12

    2.3C/A :01-C/A:03

    TASK -03

    3.1....13 -14

    3.2 C/A:04-C/A:17

    TASK -04

    4.1. 15

    4.2. 16

    4.317 -18

    TASK -05

    5.1 ....19-22

    5.224 -25

    5.3 C/A:18-C/A:22

    CONCLUSION27

    REFERENCES.28

  • 7/31/2019 Tender Assigment

    3/27

    TENDER ESTIMATION

    Page 3

    TASK -01

    DEMONSTRATE KNOWLEDGE AND UNDERSTANDING OF THE PRINCIPLES OF TENDER

    PRICING

    1.1. STATE AND DESCRIBE THE STEPS OF TENDER PRICING PROCESS

    1. DECISION TO TENDER:

    The tender documents arrive and the estimator records all relevant information such as:

    The time allowed for preparing the tender Drawings available The approximate value and extent of the project The client, Architect, Q.S and other consultant Value of main contractors own work Project Details e.g. phased work, conditions of contract, access to site, working conditions. Firm price or fluctuating price tender required Current workload and timetable for project

    After reviewing the above information, management must decide whether to tender for the project ordecline the invitation. If it is decided not to submit a price, the tender documents should be returnedimmediately to the architect/supervising officer. If it is decided that a tender should be submitted, thecontractor move to the next stage

    2. INSPECTION OF TENDER DOCUMENTS

    The arrival of the tender documents within a contractors office invariably causes a stir; everyone is

    eager to have a look. The documents should be passed directly to the estimating department. The

    Code of Estimating Practice (COEP) states that they should be inspected by the person who will be

    responsible for preparing the estimate. This should be the head of department the individual who

    takes the responsibility for the estimate not the estimator who will later be appointed to deal with the

    task. It is most important that the early inspection is carried out by a person experienced in current

    procedures and documentation, and capable in decision making and effective in communicating with

    others.

    The documents should first be checked that they accord with those listed in the letter of invitation,

    normally:

    1. Two copies of the bills of quantities.

    2. Two copies of the general arrangement drawings.

    3. Two copies of the form of tender.4. Addressed envelope for the return of tender (and priced bills if applicable).

    If the documentation is not complete the fact should be reported immediately by telephone. If reference

    is made in the letter that certain sections of the bills will follow shortly and the tendering time is as

    stated in the preliminary invitation, an appeal should be made for a revision of time to comply with the

    CPSSST.

    This clearly states that the time for tendering should be calculated from the date of issue of the last

    section.

  • 7/31/2019 Tender Assigment

    4/27

    TENDER ESTIMATION

    Page 4

    3. COLLECTION OF INFORMATION

    The time allowed for preparing a tender is always limited; the estimator must plan the program very

    carefully. The work which has to be undertaken in a typical 4 week tender period comprises:

    Dispatching enquires

    Visit consultants offices

    Visit the site

    Receipt of quotations and examinations

    The mechanical process of pricing the tender documentation

    Meetings with plant manager, contracts manager etc to determine a preliminary program,

    construction methods and likely plant requirements

    4. ESTIMATE TIMETABLE

    The estimator is responsible for preparing the estimating timetable showing the key dates for

    him and the other members of the estimating team.

    For most tenders there is an absolute requirement to meet the submission date.

    The estimator must program the activities needed to produce a tender to show how the

    deadline can be met and explain to other members of the team their part in the plan.

    Each project is different, and some dates such as those for the return of quotations require firm

    action to maintain the program dates.

    Time allowed for tendering is usually limited by the clients need to start a project quickly.

    If the design stage has been delayed it is often the tender stage that is shortened.

    Flexibility is needed to concentrate on the critical parts on the estimate preparation.

    The estimator can press on to complete his work with a day or so to spare for reconciling and

    checking the estimate.

    Much of the early part of the tender period is given over to the dispatch of enquiries to suppliers

    and sub-contractors and setting up job files when a computer system is used.

    SAMPLE ESTIMATE TIMETABLE

  • 7/31/2019 Tender Assigment

    5/27

    TENDER ESTIMATION

    Page 5

    5. ENQUIRIES AND QUOTATIONS

    SUPPLIERS

    Enquires should state:

    The specification of the material

    The quantity required

    The anticipated delivery dates The terms upon which the price is required

    The date by which the quotation is required

    The address of the site and access details

    Period for which the quotation is open for acceptance

    SUB-CONTRACTORS

    Photo copies of the relevant parts of the bill of quantities, specifications and if possible copies

    of drawings should be sent out to perspective sub-contractors. Enquires should state clearly:

    The items to be priced The terms of the main contract

    The period for which the quotation is open for acceptance

    The plant, materials, attendance etc to be provided by the main contractor

    Anticipated commencement and completion dates

    The form of contract and details from the appendix

    The terms of payment

    Date by which the quotation is to be submitted

    Address and details of the site

  • 7/31/2019 Tender Assigment

    6/27

    TENDER ESTIMATION

    Page 6

    6. VISITS TO SITE

    The visit to site can be made after all enquires have been dispatched and before prices begin to come

    back. The visit to the site will enable the estimator to produce a report giving the following information:

    The position of the site in relation to roads etc

    Names of local and statutory authorities

    Details of site/ground conditions, spot items etc

    Site access, egress and possible site layouts Facilities for disposal of surplus excavated materials etc

    7. VISITS TO CONSULTANTS OFFICES

    It may be that only drawings showing plans and elevations will be sent out with the tender documentsand that further details and working drawings can be examined at the consultants offices e.g. theestimator may require further details of manufactured joinery, steelwork joinery fittings etc, beforethese sections can be priced accurately

    8. RECEIPT OF QUOTATIONS

    Prices received from sub-contractors and suppliers are examined for sufficiency, terms etc

    9. PLANNING AND MID TENDER REVIEW

    The project is discussed with other managers to determine a preliminary program, construction

    methods, sequence of work, site layouts and what other plant, services, labour and site staff are

    required. It must be decided whether:

    All labour can be obtained locally or will it be necessary to recruit for the project.

    Sufficient plant is already owned or is it necessary to purchase/hire additional items.

    It would be desirable to sub-let any further work. The preliminary program should also be

    prepared containing the following information:

    Contract starting and completion dates

    Any work to be done in stages

    Work to be sub-let by main contractor

    Work to be done by nominated sub-contractors (if JCT 98 forms)

  • 7/31/2019 Tender Assigment

    7/27

    TENDER ESTIMATION

    Page 7

    10. PREPARATION OF THE ESTIMATE

    It can be divided into 4 stages:

    1. The establishment of all-in rates for key items i.e. labour, gang costs, plant costs etc.

    2. The selection of domestic sub-contractors and suppliers

    3. The use of these all-in rates together with costs per unit for materials to calculate unit rates for each

    item in the bill4. The pricing of the preliminaries and project overheads

    TENDER ADJUDICATION

    Tender adjudication takes place after the bills of quantities are priced and usually involves the senior

    management of the contracting organization who will, among other matters, decide the level of profit

    required, sometimes referred to as the margin. This figure, together with a percentage to cover

    overheads, will be added to the rates calculated by the estimator. The level of profit is kept a closely

    guarded secret

    Having taken the decision to submit a tender the contractor will take delivery of the tender documentsand proceed to prepare the bid; this will involve:

    Carefully examining the drawings and bills of quantities for accuracy and then preparing a timetablefor the preparation of the bid

    Visiting the site, particularly appropriate for alteration work, or where the site has restricted access orworking

    Preparing any method statements; method statements are an analysis and description of how thecontractor proposes to carry out particularly complicated parts of the works.

    11. FINAL REVIEWThe consideration of the estimate to produce a tender is the responsibility of management .The

    estimator and other senior staff will prepare reports for consideration by management who will consider

    the following items before determining the tender figure;

    Project reports

    Conditions of contract

    Contractual and construction risks

    Terms of the quotations from sub-contractors

    Capital required for the project

    Technical and management staff required

    Current workload Market Conditions

    Competition

    Reputations of client, consultants and area

    Following evaluation of the alternatives, risk and scope for profitability the mark up is determined andthe actual tender figures calculated. The decision being made within the Frame work of company policy

    .A record of all tenders should be kept together will the results (if known) for future reference

  • 7/31/2019 Tender Assigment

    8/27

    TENDER ESTIMATION

    Page 8

    1.2. LIST THE FACTORS TO BE CONSIDERED IN PRICING A TENDER

    Market Condition:The volumes of work in progress in the area at a given point in time affect constructioncost. When the market is burying with many project, tender price list are generally high.Most consultants are busy and competition is not keen. However during ausle times when

    there are few projects, contractors are anxious to out bid themselves so as to stay inbusiness, so construction cost tends to be lower.

    Availability of Materials:When required materials are readily available in an area where a project is to be executed,materials will be cheaper than where they are not so available. Generally, materials arecheaper where they are produced e.g. if you can buy cement directly from Colombo, theprice will be a lot cheaper than in Jaffna because of transportation and profit margins ofmiddlemen and so on. Imported materials for similar reasons are more expensive thanlocally produced materials.

    Availability of Labor:

    Where a certain type of labor is not readily available in the area where a project is to be

    constructed, it may be necessary to import from an area where such labour is available. Some

    inducement may have to be offered before such labour will move from its base such as

    transportation, accommodation, inconveniences allowances etc. these add to the cost of

    construction.

    Transportation:

    The farther a site is from town, the more expensive will be the construction cost

    Location:

    The standard of living in an area affects the cost of construction. People are willing to payhigher prices for construction in places

    Location of Site: -

    The particular location of the site can have significant effect on cost. Remote site may require

    additional cost for the provision or access roads and temporary services or the provision of

    additional security measures. Also, a site in a congested or restricted area also gives rise to

    major problems such as delivery & storage of materials and components, protection of

    adjoining buildings and the public, restriction on the use of mechanical plants and so on, all

    these will increase the cost of construction.

    Time Consideration: -

    For certain reasons, a project may need to be completed in a very short time; this tends to push

    up construction cost. Laborers may be required to work overtime and overtime rates are usually

    higher than normal rates. Incentives scheme may have to be introduced to increase labor

    productivity. Closure supervision is necessary as mistake must be avoided, there may be

    time to apply remedial action

  • 7/31/2019 Tender Assigment

    9/27

    TENDER ESTIMATION

    Page 9

    Site Condition:

    May affect the construction cost of a particular building. The nature of ground may necessitate

    more complex form of foundation. The ground water level when close to surface will involve

    costly water pumping operation. A wet site may involve rising temporary sheds and offices

    above ground level and they involve more costly temporary roads. Steeply sloping site may

    involve major cost in cutting and filling requirements, existence of buried pipes and cables may

    involve major cost to re-root such.

    Total Height of Building:

    The higher a building is, the longer it takes and more difficult it is to get the point of execution of

    works. It is also more difficult to work at such height. Labor charges for 30working at great

    height are higher than normal height; there is also the cost of providing additional safety

    measures and insurance. Also, the need for special scaffolding, hoist, tower crane, elevators

    etc. will tend to increase the cost of very tall building over the cost of building requiring

    the same quantities at ground level.

    Class of Contractors:There are various types of contractors in the market. These gives rise to differentclassification.

    Small contractors comprises of one man board of directors. They usually carry littlegeneral overhead and keep very few permanent staff

    Medium contractors usually have a board of at least two but not more than fivedirectors they employ a few more permanent staff, have a reasonable office andpossess some equipment and official cars.

    Large contractors have a lot of times publicly owned with many share holders havingat least six members on their board of directors, fleet of cars and equipments, largeoffice space and a lot of staffs of various discipline. Generally, the larger the firm,the higher their cost. Also, the level of profit expected by the share holder of largerfirms is a lot more than that required by the smaller contractors. The rates for thesmall contractors therefore tends to be much lower than for large contractors

    Types of Consultants: Architect: - Some architects are very difficult to work with, their initial designs are not

    detailed and they rely a lot on instructions on site. Many variations occur and delaysare frequent. These will add to the cost of construction. The same applies toEngineers and other designers. Contractors are therefore known to increase theirprices by a certain percentage when it is known that they would be working withparticular consultant.

    Types of Tendering:Open tendering generally brings lower prices than selective tendering, and this in turnresult in lower price than negotiated tendering which brings the highest price of fall.

    REFERENCE: UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATION

    REVITALISATION PROJECT-PHASE IINATIONAL DIPLOMA IN QUANTITY SURVEYING

    TENDERING AND ESTIMATING II

    COURSE CODE: QUS 210

  • 7/31/2019 Tender Assigment

    10/27

    TENDER ESTIMATION

    Page 10

    1.3. LIST THE SOURCES AND NATURE OF INFORMATION REQUIRED FOR COST ESTIMATING

    1. Drawings :

    dimensions (length, width ,height )

    shape of component of the building

    elevations

    2. Specifications :

    quality of workmanship

    Way of construction

    Additional works related with work item

    3. Preambles :

    quality of material

    way of handling materials

    4. BOQ :

    Description of work

    Unit of work item

    Quantity of work item

    5. Suppliers quotation :

    Prices of materials

    Quality of materials

    Discounts

    6. Sub-contractor quotation :

    Prices of work item

    Discount

    7. Site visit :

    Condition of site

    Nature of soil

    Shape of land

    8. Previous experience :

    Labor cost

    9. Previous document:

    Additional related work

    10. BSR

    Standard prices for work items

  • 7/31/2019 Tender Assigment

    11/27

    TENDER ESTIMATION

    Page 11

    Task: 02

    PREPARE STANDARD RATES FOR LABOUR, CONSTRUCTION PLANT AND MATERIALS

    2.1. LIST THE FACTORS TO BE CONSIDERED WHEN CALCULATE ALL IN RATES FOR LABOR,

    PLANTS AND MATERIAL.

    Construction cost is a broad phrase or term and can be interpreted to mean cost of any sort toanyone associated with construction work. It depends on the point of view let us say you are a

    contractor, your costs are your expenditure on labour, materials and plant. The clients cost of land,

    consultant fees and so on.

    The base cost of construction therefore comprises of expenditure on materials, labour and plant, the

    quantities of materials, labour and plant required for a job are determined &attaching prices to these

    defines the basic construction cost, but to these are also a variety of factors that affect this basic cost: -

    In our industry most estimators will calculate costs based on net rates these will then be enhancedlater to include overheads and profit. Gross rates are sometimes referred to as all-in rates

    ALL IN RATE FOR LABOR

    Minimum guaranteed overtime.

    Non productive time

    ETF & EPF

    Insurance

    Medical facilities

    Non productive time

    Tool money

    Inclement of bed weather

    Minimum guaranteed bonus

    ALL IN RATE FOR MATERIAL

    Prime cost of the material

    Transportation costs

    Unloading and Stacking costs

    Materials movement on site

    Extra Materials to compensate for

    Wastage Allowance for materials being measured net in BOQ

    Loss in consolidation, shrinkage etc

    ALL IN RATE FOR PLANT

    Depreciation of plant

    Repair and maintenance cost of plant

    License and Insurances cost

    Fuel and Lubricant

    Operator cost

  • 7/31/2019 Tender Assigment

    12/27

    TENDER ESTIMATION

    Page 12

    2.2. ANALYZE THE FACTORS LISTED IN 2.1 AND EXPLAIN HOW EACH ONE CONTRIBUTES TO

    THE TOPIC (LABOR COST, MATERIAL COST AND PLANT COST)

    The Resources which compromise a unit rate are labour, materials and plant

    LABOR

    In the construction industry labour is often employed in two main ways, these are

    :1.Direct Often referred to as cards in, the employer pays all the costs of employment including

    for example national insurance and sick pay amongst others

    .2.In-DirectThese workers are self employed or referred to in industry as on the lump

    These are often labour only sub-contractors without the normal costs of employment along with the

    other legal protections such as redundancy, sick pay and minimum notice periods.

    Labour may be paid for on an hourly, daily, weekly or piecework basis. Directly employed operatives

    are usually paid in accordance with a working rule agreement which will specify the rates

    and allowances to be paid. However, some contractors are trying to move away from the national wage

    bargaining and introduce local wage rates. Ultimately the actual rates paid for labour will dependon market forces

    MATERIALS

    Several factors affect the cost contractors pay for materials. In the material element of a unit rate, in

    addition to the actual cost of the material the estimator must also consider above factors because

    Where prices of materials are described by suppliers as exworks this means the price at the factory

    and delivery costs will have to be added.

    PLANT

    Plant may be divided into two main categories, the costs of which can be allocated to contracts indiffering ways.

    Non-Mechanical Plant

    Basic items of plant including barrows, hosepipes, spades, trestles, scaffolding, small powered hand

    tools etc

    With the exception of scaffolding and one or two other items it is virtually impossible to allocate the cost

    of non-mechanical plant items to a contract, let alone to a specific unit rate e.g. a wheelbarrow may be

    used on several contracts in its life time.

    The cost may be included in overhead charges as a percentage, as a lump sum in the preliminaries bill

    or, more accurately, on longer contracts a list of non-mechanical plant items is prepared, coasted andincluded in the contract sum

    Mechanical Plant

    This include all mechanical plant not allocated to unit rate such as cranes, lift, dumpers, hoist, tractor,

    generating set, drills, forklift etc. the contractor is expected to allow for this items whether they are

    purchased specifically for the project or they are already owned by the firm or they are to be hired for

    the period they are required on the project. The usual thing is to allow for

    (a) Cost of transporting plant to site

    (b)Hire rate for the period plant is on site

    (c)Cost of maintenance on site

    (d)Profit and overhead

  • 7/31/2019 Tender Assigment

    13/27

    TENDER ESTIMATION

    Page 13

    Task: 03

    BUILD UP UNIT RATES FOR TRADES WORK ITEM

    3.1. STATE THE FACTOR WHICH EFFECT THE CALCULATION OF UNIT RATES FOR

    FOLLOWING WORK ITEM

    01. EXCAVATION

    The following factors may affect unit rates for ground works

    Type of excavation e.g. trenches, pits, basements

    Ground conditions e.g. clay, sand, soil, rock

    Depth of excavation

    Ground water

    Time of year when excavating

    Mechanical or hand excavation

    Distance and availability of tips

    Estimated bulking of materials

    02. CONCRETE

    The following factors may affect unit rates for concrete work;

    Whether ready mixed or site mixed concrete is used

    Whether concrete is reinforced

    Surcharges for part loads Location of mixing plant on site

    Type and size of mixing plant

    Method of transporting, hoisting, placing and compacting mixed concrete

    Cost of protecting and curing

    Unset concrete Operatives working with concrete receive additional payments for skill and

    responsibility.

    Items of plant should be priced separately.

    Concrete is usually measured in m3Site Mixed Concrete

    03. BRICK WALL

    The following factors may affect unit rates for brick work;

    Quality of finished works

    Type of work (i.e. straight walls, curved walls, foundations etc)

    Working overhand, at height

    Type of pointing

  • 7/31/2019 Tender Assigment

    14/27

    TENDER ESTIMATION

    Page 14

    04. FORMWORK

    Formwork measures the actual faces of work covered or to be supplied. The following must be taken

    into consideration in determining the size of the formwork

    The amount of material required

    The kind of finishes required i.e. sawn faced or smooth finish, ground finish, biscuit etc. This determines the

    types of materials to be used as formwork and the surface from finish required is removed.

    The height to be supported. This determines the height of props and types of props.

    Normal labour for fabricating, erecting and striking of formwork.

    The number of uses required of the formwork this is usually a matter of experience. In small

    contract it may be possible to reuse the same formwork twice depending on the repetitive

    nature of the work

    REFERENCE: UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATION

    REVITALISATION PROJECT-PHASE IINATIONAL DIPLOMA IN QUANTITY SURVEYING

    TENDERING AND ESTIMATING II

    COURSE CODE: QUS 210

  • 7/31/2019 Tender Assigment

    15/27

    TENDER ESTIMATION

    Page 15

    TASK: 04

    DEMONSTRATE ABILITY TO COSTING OF PRELIMINARIES / OVERHEAD COST OF THE

    CONTRACTOR

    4.1. EXPLAIN PRELIMINARIES AND OVERHEAD COSTS IN BILL OF QUANTITIES

    WHAT ARE PRELIMINARY ITEMS?

    Preliminary items are items of cost which do not relate to any particular work section and usually listed

    in the first bill of quantities. Many estimators prefers to inserts a lump sum for all the preliminaries

    usually worked out as a percentage of the total of the measured works. It is good practice however to

    put a price to each of the item. The price quoted should read at after careful consideration of each item

    as it applies to the particular job at hand e.g water for the works. It will be pipe bone water readily

    available on site or water has to be transported to site on trucks.

    PRELIMINARY BILL

    The preliminaries bill gives the contractors the opportunity to price overheads which is described in the

    Code of Estimating Practice as the cost of administering a project and providing general plant, site

    staff, facilities and site based services and other items not included in bill rates.

    Preliminaries costs vary from contract to contract depending on complexity of work, size of

    contract, specialist plant and equipment required, conditions imposed by the employer etc.

    On relatively simple contracts preliminary costs may be in the order of 10 15% of the contract

    sum whereas on complex contracts this figure could be much higher.

    A contractor must calculate the cost of the preliminary items separately for each contract; no

    two contracts are the same.

    SMM7 recommends that fixed and time-related charges should be identified separately in a bill

    of quantities.

    A fixed charge is defined as the cost of work which can be considered as being independent ofduration

    A time-related charge is defined as the cost of work which is to be considered as dependant on

    duration.

    OVERHEADSOverheads may be defined as the cost of maintaining (running) the contractors organization.

    There are two types of overheads:

    (1) Head Office

    Annual cost of staff salaries, expenses, rents, rates, gas, water, electricity, telephones, officeequipment, postage, insurance, maintenance of buildings and equipment etc. The cost of these itemsis expressed as a percentage of a companys turnover and included in the tender.

    (2) Project or SiteProject site costs including non productive (manual) site staff, site office costs, storage facilities andother preliminary / site organization costs. Items are priced as individual items and may be fixed or timerelated costs or a mix of fixed and time related costs. The costs of these items are included in thetender.

  • 7/31/2019 Tender Assigment

    16/27

    TENDER ESTIMATION

    Page 16

    4.2. JUSTIFY THE GIVEN SCENARIO IN RELATION TO THE ABOVE TWO EXAMPLES,

    HOW/WHY DIFFERENT COSTS INVOLVED FOR THE SAME PRELIMINARY ITEMS IN

    DIFFERENT PROJECTS.

    The preliminaries are most important part in a BOQ also it is very difficult to calculate because it

    usually will differ project to project because of following reasons

    Will identify the two work item how it differ project to project

    Transportation of machineries

    The different distance of transporting plant to site

    The different machineries needed for the different project

    The different project scope (large or small)

    Site office for consultant representative

    The different number of staff for each project

    The different maintain period because of the different duration of project

    The accommodation required for the project it will defer each project The cost will differ according to place weather on site or off site

    For the above mentioned reasons the cost of preliminary will differ each project so as an estimator he

    will gain this knowledge through the past experience. Most of the times the preliminary item will be

    calculate separately even same project scope

  • 7/31/2019 Tender Assigment

    17/27

    TENDER ESTIMATION

    Page 17

    4.3. CALCULATE THE COST OF ABOVE TWO ITEMS WITH YOUR OWN ASSUMPTION

    PRELIMINARY ITEM-01: SITE OFFICE FOR CONSULTANTS REPRESENTATIVE

    The contractor is usually expected to provide and maintain temporary site accommodation for Supervising consultant on site

    Site agent and site staff Hut for workmen Storage, shed for materials, tools etc.

    Pricing for these must cover the cost of:

    Initial construction of accommodation

    Removal on completion and making good ground disturbed

    Maintenance of accommodation throughout duration of the project

    Furniture including ventilation and air conditioning

    Overhead and profit from this estimator must remove the resale value of items are still

    useable at the end of the projects

    SITE OFFICE

    The contractor shall provide suitable accommodation for the clerk of works, with a minimum floor area

    of 20 m2 including desk, four chairs, filing cabinet and all necessary heating, lighting and cleaning.

    ASSUMPTION

    Contract period: 144 weeks

    Transport to and from site: Rs.22500 per trip

    Hire of hut: Rs.8500.00 per week

    Hire of furniture and heaters, etc.: Rs.2500.00 per week

    FIXED CHARGES

    Transport to and from site 2 trips Rs.22500 45000.00

    Erection 10 hours

    Dismantle 5 hours

    15 hours laborer @ Rs.300.00 4500.00

    Total of fixed charges 49,500.00

    TIME RELATED CHARGES

    Hire of hut 144 weeks @ Rs.8, 500.00 per week 1,224,000.00

    Furniture and heaters 144 weeks @ Rs.2500.00 per week 360,000.00

    Energy costs for heating and lighting:

    144 weeks @ Rs.640.00 per week 92.160.00

    Cleaning 2 hours per week 144 weeks =

    288 hours @ Rs.1980.00 285,120.00

    Total of time related charges 1,961,280.00

    Rate per week = Rs.13, 620.00

    Total (fixed and time related charges) 49,500.00 + 1,961,280.00 = 2,010,780.00

  • 7/31/2019 Tender Assigment

    18/27

    TENDER ESTIMATION

    Page 18

    PRELIMINARY ITEM-02: TRANSPORTATION OF MACHINERIES

    This include all mechanical plant not allocated to unit rate such as cranes, lift, dumpers, hoist, tractor,

    generating set, drills, forklift etc. the contractor is expected to allow for this items whether they are

    purchased specifically for the project or they are already owned by the firm or they are to be hired for

    the period they are required on the project. The usual thing is to allow for

    (a) Cost of transporting plant to site

    (b) Hire rate for the period plant is on site

    (c) Cost of maintenance on site

    (d) Profit and overhead

    TRANSPORTATION OF MACHINERIES

    Cost of plant 3,000,000.00

    Less scrap value 450,000.00

    2,550,000.00

    Assume a life of 4 years therefore annual cost 2,550,000.00

    4

    = 637,500.00

    Assume a usage of 1500 hours per year:

    Cost per hour 637,500.00

    1500

    = 425.00

    Assume 25% for repair and maintenance = 106.25

    Assume 10% for license and insurance = 42.50

    Total cost of plant 573.75

    Assume 1 liter of fuel per hour @ Rs.135.00 Per liter = 135.00Assume 0.5 liter of lubricant oil per hour @ Rs.720.00 per liter = 360.00

    Assume Rs.175.00 for the operator per hour = 175.00

    Net unit rate 1,243.75

    Overhead & profit 25% =310.93

    Gross unit rate 1554.68

  • 7/31/2019 Tender Assigment

    19/27

    TENDER ESTIMATION

    Page 19

    TASK: 5 DESCRIBE THE PROCEDURE FOLLOWED IN PREPARATION OF A QUOTATION

    5.1. DESIGN TWO SAMPLES INQUIRY LETTERS TO SUBCONTRACTOR AND SUPPLIER IN

    ORDER TO COLLECT THEIR QUOTATION.

    ENQUIRY LETTER TO SUPPLIERS

    12/07/2012

    DELTA MAGACONSTRUCTION (PVT) LTD,

    NO: 39, DANIEL ROAD,

    COLOMBO: 03

    TO: SALES MANAGERORANGE ELECRIC PVT LTD,

    165, GALLE ROAD,

    DEHIWALA,

    SRI LANKA.

    Dear Sir,

    CONSTRUCTION OF A PROPOSED SHOPPING COMPLEX

    WE INVITE YOU TO QUOTE YOUR BEST PROPOSAL FOR SUPPLY OF BELOW MENTIONED

    MATERIAL FOR OUR PROPOSED SHOPPING PROJECT AT

    ITEM NO DESCRIPTION QUANTITY

    01 ORANGE SPIRAL SHAPE ENERGY SAVING LAMP

    TRI-PHOSPHOR POWDER

    FLAME RETARDANT CAP

    TUBE DIAMETER: 12MM

    WATTAGE: 20W VOLTAGE: 110V

    1000

    YOUR QUOTATION MUST BE DELIVERED TO THIS ADDRESS

    DELTA MAGACONSTRUCTION (PVT) LTD,

    NO: Z39,

    DANIEL ROAD,

    COLOMBO: 03

  • 7/31/2019 Tender Assigment

    20/27

    TENDER ESTIMATION

    Page 20

    TERMS AND CONDITIONS

    Payment terms : 1 week after delivery

    Advance payment : 25% of total

    Payment type & term : Please mention your payment type & term

    Discounts : Please notify your discount

    Transportation : By the Suppliers with safe with protection.

    Traffic condition or restrictions : During week days from 8.00 am to 05.30 pm

    vehicles can park at the site area.

    Submission of quotation : Two weeks

    Suppliers will be required to deliver the material according to the schedule. If you need to make any

    inquires you may visit the site after contacting the site manager of the project. We would appreciate if

    you could provide us with the relevant discounts since we are one of your frequent customers. If your

    company is out of stock then please notify us when you will be able to receive these materials. And if

    there are any clarifications about the tender please contact Mr.Aslam the estimator of the project.

    We would appreciate if you would send the acknowledge receipt of this enquiry and submit the

    quotation in accordance with the given instructions.

    Yours Faithfully,

    ......

    Aslam

    (Quantity Surveyor)

  • 7/31/2019 Tender Assigment

    21/27

    TENDER ESTIMATION

    Page 21

    ENQUIRY LETTER TO SUBCONTRACTOR

    __/__/2012

    DELTA MAGA CONSTRUCTION (PVT) LTD,

    NO: 39, DANIEL ROAD,

    COLOMBO: 03

    TO: MANAGER

    JUDI CONTRACTORS (PVT) LTD,

    GALLE ROAD,

    BARUWALA,

    SRI LANKA.

    DEAR SIR,

    CONSTRUCTION OF A PROPOSED GYMNASIUM

    WE INVITE YOU TO QUOTE YOUR BEST PROPOSAL FOR DOING OF BELOW MENTIONED WORK

    FOR OUR PROPOSED GYMNASIUM PROJECT AT PANAGODA.

    ITEM NO DESCRIPTION QUANTITY

    01PLASTERING FOR EXTERNAL BRICK WALL WITH1:3

    CEMENT: SAND MORTAR750m

    2

    YOUR QUOTATION MUST BE DELIVERED TO THIS ADDRESS

    DELTA MAGA CONSTRUCTION (PVT) LTD,

    NO: 39, DANIEL ROAD,

    COLOMBO-03

    TO ARRIVE NO LATER THAN 02.00 P.M. ON OR BEFORE __ OF ___ 2012

  • 7/31/2019 Tender Assigment

    22/27

    TENDER ESTIMATION

    Page 22

    TERMS AND CONDITIONS

    Payment terms : 2 weeks after work started

    Advance payment : 20% of total

    Payment type & term : Please mention your payment type & term

    Traffic condition or restrictions : During week days from 8.00 am to 05.30 pm vehicles can park

    at the site area.

    Submission of quotation : Two weeks

    Subcontractor will be required to deliver the material according to the schedule. If you need to make

    any inquires you may visit the site after contacting the site manager of the project. We would

    appreciate if you could provide us with the relevant discounts since we are one of your frequent

    contractors. If your company is out of stock then please notify us when you will be able to receive these

    materials. And if there are any clarifications about the tender please contact Mr. Aslam the estimator of

    the project.

    We would appreciate if you would send the acknowledge receipt of this enquiry and submit the

    quotation in accordance with the given instructions.

    Yours Faithfully

    ..........................

    Aslam

    (Quantity Surveyor)

  • 7/31/2019 Tender Assigment

    23/27

    TENDER ESTIMATION

    Page 23

    5.2. DESCRIBE THE FACTORS THAT WILL BE CONSIDERED BY THE ESTIMATOR

    WHEN EVALUATING THE QUOTATION RECEIVED FROM SUBCONTRACTORS AND

    SUPPLIERS

    Choosing the right suppliers involves much more than scanning price lists. Your choice will depend on

    a wide range of factors such as value for money, quality, reliability and service. How you weigh up the

    importance of these different factors will depend on your business priorities and strategy.

    the criteria for evaluating and awarding a contract is required to be stated in the tender documents

    these would normally be the most economically advantageous taking account of such factors as: PURCHASE PRICE:

    Lowest Price Technically Acceptable This approach is appropriate when best value is expected to

    result from selection of the technically acceptable offer with the lowest evaluated price. Price is

    important, but it shouldn't be the only reason you choose a supplier. Lower prices may reflect

    poorer quality goods and services which, in the long run, may not be the most cost-effective option.

    Be confident that your supplier can make a sufficient margin at the price quoted for the business to

    be commercially viable.

    OTHER WHOLE LIFE COSTS :

    It will involve Running costs, obsolescence, resale value or disposal cost, after sales service and

    technical assistance from supplier or sub-contractor

    DELIVERY:

    The requesting activity may provide instructions via the Purchase Request that delivery is a critical

    factor in choosing the prospective supplier or sub-contractor

    QUALITY :The estimator should have to check the quality requirement according to the specification prepared

    for the particular work

    DISCOUNT RATE :

    This is the important feather among the supplier or subcontractor because he can improve his profit

    through this discount and he can reduce his tender value so he can win a job through this

    CONTRACT TERMS :

    The main estimator responsibility is to consider the contract terms to continue the contract deal with

    a supplier in a fair manner

    PAST PERFORMANCE :

    The ability of well performance is a main reason in selecting subcontractor so the estimator should

    have to take attention in past performance of subcontractor with the same project

    BUSINESS PRACTICES :

    The estimator will look at his business deal with other contractor and check his practices in his

    business it will be useful to continue the deal for long period

    The above mentioned factors should have to consider by the estimator in evaluating quotation fromsupplier and subcontractor because it will be very helpful to win a job.

  • 7/31/2019 Tender Assigment

    24/27

    TENDER ESTIMATION

    Page 24

    5.3 DESCRIBE THE DIFFERENT FORM DISCOUNT OFFERED IN THE CONSTRUCTION

    INDUSTRY AND EXPLAIN HOW YOU INCORPORATE THEM IN PRICING.

    DISCOUNTS

    Discounts are the quoted amount or stated cost which will deduct from the payments to the suppliers

    and subcontractors, depend on fulfillment of the conditions which are specified in the contract for

    acquiring discounts.

    Followings are two types of discounts accepted by the subcontractors and suppliers.

    Trade discounts

    Cash discounts

    TRADE DISCOUNTS

    Trade discounts apply particularly when there are standard price lists prepared by manufacturers orsuppliers and when items may be sold direct to the public. The discount is varied to allow forfluctuations in prices to avoid frequent revision of such lists. Some suppliers allow large discounts for

    regular customers who purchase large quantities.

    Ex: -

    Builders and plumbers may get, say, a 20% discount on the supply of sanitary fittings when

    compared with the retail price to the general public.

    Let us consider a supplier of Bricks. The supplier might allow trade discounts as given below.

    Quantity Discounts

    5000 - 10000 Bricks 15%

    10000 - 15000 Bricks 18%

    15000 - 20000 Bricks 20%

    If the buyer purchases more than 5000 Bricks then the buyer is entitled for a discount of 15 % from the

    marked price. Similarly if the buyer purchases more than 10,000 Bricks s, he could get a discount of

    18%. Similarly if the buyer purchases more than 20,000 Bricks which are considered to be a large

    quantity, he could get a 20% discount rate. While the price of Bricks raised by 2%. Then the supplier

    could alter the discount rate without making any changes to the actual prices. In this case reducing the

    discount up to 3% for 1000-5000 Bricks would be satisfactory.

  • 7/31/2019 Tender Assigment

    25/27

    TENDER ESTIMATION

    Page 25

    CASH DISCOUNTS

    A cash discount is often given by suppliers and subcontractors to encourage early settlement of

    accounts.

    If the contractor settle the accounts to the suppliers and subcontractors before the original date than

    the contractor will get some percentage of discounts

    Ex: -

    Let us consider that the electrical installation was carried out by a sub-contractor. The invoiced value of

    work done by the sub-contractor is Rs. 400,000 for a particular month. Usually the sub-contractors

    payment is done through the main contractor. If the main contractor settles the amount Rs. 400,000

    within the specific period, the main contractor is entitled for a discount which is normally 5 % of the

    invoice value. So the contractor has to pay only Rs. 180000. But if the main contractor fails to make

    the payment within the specified time, then the main contractor has to pay the entire Rs. 400,000 Such

    discounts given by sub-contractors will motivate the contractors to make the payments earlier. Thus itwill ensure the smooth function of the construction project. Likewise the suppliers also give such cash

    discounts to encourage the contractor to settle the payments quickly.

    Explanation of how to incorporate them into the tender

    The main contractor is always expecting about the discount to use it in pricing the tender. If the main

    contractor knows the amount of the discounts from the subcontractors or suppliers

    Contractor can reduce the rate of the work in that tender. So the tender price may be reduced.

    This might be increased the chance to win the tender.

    That is why the estimator or being consultancy Quantity Surveyors should have a thorough knowledge

    about the discounts and should apply the discounts while he is pricing the tender.

  • 7/31/2019 Tender Assigment

    26/27

    TENDER ESTIMATION

    Page 26

    CONCLUSION

    As a quantity surveyor we have some responsibility construction industry out of them tender

    stage is a most important one. Because each and every constructions except some unique

    construction going to hand over to one of a best contractor only by calling tender.

    Here we are supposed to refer and suppose to understand something clearly about the

    knowledge of tender. And we have to have enough knowledge about the project that has been

    invited, client of the proposed project and about the consultant as well. Cause those are the

    important thing that we are going to have a relationship.

    So that we want to understand this all thing as a QS and we are the peoples who are going to

    handle with this kind of meter

    In this way I collected some useful information according to the lecturer requirement so I think

    it will be very useful document which explain basic knowledge of tender

  • 7/31/2019 Tender Assigment

    27/27

    TENDER ESTIMATION

    REFERENCES

    UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATIONREVITALISATION PROJECT-PHASE II

    NATIONAL DIPLOMA IN QUANTITY SURVEYING

    TENDERING AND ESTIMATING II

    COURSE CODE: QUS 210

    QUANTITY SURVEYORS POCKET BOOK

    FIRST EDITION2009DUNCAN CARTLIDGE FRICS

    PUBLISHED BY ELSEVIER LTD

    ESTIMATING AND TENDERING FOR CONSTRUCTION WORK

    THIRD EDITION 2004

    MARTIN BROOK BENG (TECH) FCIOB

    PUBLISHED BY ELSEVIER LTD

    WWW.GOOGLE.LK

    WWW.WIKIPIDIA.COM

    http://www.google.lk/http://www.google.lk/http://www.wikipidia.com/http://www.wikipidia.com/http://www.wikipidia.com/http://www.google.lk/

Recommended