Date post: | 05-Apr-2018 |
Category: |
Documents |
Upload: | nabeela-aman |
View: | 234 times |
Download: | 0 times |
of 27
7/31/2019 Tender Assigment
1/27
TENDER ESTIMATION
Page 1
ACKNOWLEDGEMENT
First of all I wish to express my sincere gratitude to Almighty God for giving me the courageand determination to complete this assignment.
Also I would like to express my utmost gratitude to my lecturerMR.N.T.K.LOKULIYANA he
gave me excellent guideline to complete this assignment and assess my all performance with
his busy schedule
Finally I like to thank to my class friends to give me a good corporation to complete this
assignment
7/31/2019 Tender Assigment
2/27
TENDER ESTIMATION
Page 2
CONTENTS
ACKNOWLEDGEMENT....01
CONTENTS.02
TASK -01
1.1... .........................03-07
1.2....08 -09
1.310
TASK -02
2.1.11
2.2 . ...12
2.3C/A :01-C/A:03
TASK -03
3.1....13 -14
3.2 C/A:04-C/A:17
TASK -04
4.1. 15
4.2. 16
4.317 -18
TASK -05
5.1 ....19-22
5.224 -25
5.3 C/A:18-C/A:22
CONCLUSION27
REFERENCES.28
7/31/2019 Tender Assigment
3/27
TENDER ESTIMATION
Page 3
TASK -01
DEMONSTRATE KNOWLEDGE AND UNDERSTANDING OF THE PRINCIPLES OF TENDER
PRICING
1.1. STATE AND DESCRIBE THE STEPS OF TENDER PRICING PROCESS
1. DECISION TO TENDER:
The tender documents arrive and the estimator records all relevant information such as:
The time allowed for preparing the tender Drawings available The approximate value and extent of the project The client, Architect, Q.S and other consultant Value of main contractors own work Project Details e.g. phased work, conditions of contract, access to site, working conditions. Firm price or fluctuating price tender required Current workload and timetable for project
After reviewing the above information, management must decide whether to tender for the project ordecline the invitation. If it is decided not to submit a price, the tender documents should be returnedimmediately to the architect/supervising officer. If it is decided that a tender should be submitted, thecontractor move to the next stage
2. INSPECTION OF TENDER DOCUMENTS
The arrival of the tender documents within a contractors office invariably causes a stir; everyone is
eager to have a look. The documents should be passed directly to the estimating department. The
Code of Estimating Practice (COEP) states that they should be inspected by the person who will be
responsible for preparing the estimate. This should be the head of department the individual who
takes the responsibility for the estimate not the estimator who will later be appointed to deal with the
task. It is most important that the early inspection is carried out by a person experienced in current
procedures and documentation, and capable in decision making and effective in communicating with
others.
The documents should first be checked that they accord with those listed in the letter of invitation,
normally:
1. Two copies of the bills of quantities.
2. Two copies of the general arrangement drawings.
3. Two copies of the form of tender.4. Addressed envelope for the return of tender (and priced bills if applicable).
If the documentation is not complete the fact should be reported immediately by telephone. If reference
is made in the letter that certain sections of the bills will follow shortly and the tendering time is as
stated in the preliminary invitation, an appeal should be made for a revision of time to comply with the
CPSSST.
This clearly states that the time for tendering should be calculated from the date of issue of the last
section.
7/31/2019 Tender Assigment
4/27
TENDER ESTIMATION
Page 4
3. COLLECTION OF INFORMATION
The time allowed for preparing a tender is always limited; the estimator must plan the program very
carefully. The work which has to be undertaken in a typical 4 week tender period comprises:
Dispatching enquires
Visit consultants offices
Visit the site
Receipt of quotations and examinations
The mechanical process of pricing the tender documentation
Meetings with plant manager, contracts manager etc to determine a preliminary program,
construction methods and likely plant requirements
4. ESTIMATE TIMETABLE
The estimator is responsible for preparing the estimating timetable showing the key dates for
him and the other members of the estimating team.
For most tenders there is an absolute requirement to meet the submission date.
The estimator must program the activities needed to produce a tender to show how the
deadline can be met and explain to other members of the team their part in the plan.
Each project is different, and some dates such as those for the return of quotations require firm
action to maintain the program dates.
Time allowed for tendering is usually limited by the clients need to start a project quickly.
If the design stage has been delayed it is often the tender stage that is shortened.
Flexibility is needed to concentrate on the critical parts on the estimate preparation.
The estimator can press on to complete his work with a day or so to spare for reconciling and
checking the estimate.
Much of the early part of the tender period is given over to the dispatch of enquiries to suppliers
and sub-contractors and setting up job files when a computer system is used.
SAMPLE ESTIMATE TIMETABLE
7/31/2019 Tender Assigment
5/27
TENDER ESTIMATION
Page 5
5. ENQUIRIES AND QUOTATIONS
SUPPLIERS
Enquires should state:
The specification of the material
The quantity required
The anticipated delivery dates The terms upon which the price is required
The date by which the quotation is required
The address of the site and access details
Period for which the quotation is open for acceptance
SUB-CONTRACTORS
Photo copies of the relevant parts of the bill of quantities, specifications and if possible copies
of drawings should be sent out to perspective sub-contractors. Enquires should state clearly:
The items to be priced The terms of the main contract
The period for which the quotation is open for acceptance
The plant, materials, attendance etc to be provided by the main contractor
Anticipated commencement and completion dates
The form of contract and details from the appendix
The terms of payment
Date by which the quotation is to be submitted
Address and details of the site
7/31/2019 Tender Assigment
6/27
TENDER ESTIMATION
Page 6
6. VISITS TO SITE
The visit to site can be made after all enquires have been dispatched and before prices begin to come
back. The visit to the site will enable the estimator to produce a report giving the following information:
The position of the site in relation to roads etc
Names of local and statutory authorities
Details of site/ground conditions, spot items etc
Site access, egress and possible site layouts Facilities for disposal of surplus excavated materials etc
7. VISITS TO CONSULTANTS OFFICES
It may be that only drawings showing plans and elevations will be sent out with the tender documentsand that further details and working drawings can be examined at the consultants offices e.g. theestimator may require further details of manufactured joinery, steelwork joinery fittings etc, beforethese sections can be priced accurately
8. RECEIPT OF QUOTATIONS
Prices received from sub-contractors and suppliers are examined for sufficiency, terms etc
9. PLANNING AND MID TENDER REVIEW
The project is discussed with other managers to determine a preliminary program, construction
methods, sequence of work, site layouts and what other plant, services, labour and site staff are
required. It must be decided whether:
All labour can be obtained locally or will it be necessary to recruit for the project.
Sufficient plant is already owned or is it necessary to purchase/hire additional items.
It would be desirable to sub-let any further work. The preliminary program should also be
prepared containing the following information:
Contract starting and completion dates
Any work to be done in stages
Work to be sub-let by main contractor
Work to be done by nominated sub-contractors (if JCT 98 forms)
7/31/2019 Tender Assigment
7/27
TENDER ESTIMATION
Page 7
10. PREPARATION OF THE ESTIMATE
It can be divided into 4 stages:
1. The establishment of all-in rates for key items i.e. labour, gang costs, plant costs etc.
2. The selection of domestic sub-contractors and suppliers
3. The use of these all-in rates together with costs per unit for materials to calculate unit rates for each
item in the bill4. The pricing of the preliminaries and project overheads
TENDER ADJUDICATION
Tender adjudication takes place after the bills of quantities are priced and usually involves the senior
management of the contracting organization who will, among other matters, decide the level of profit
required, sometimes referred to as the margin. This figure, together with a percentage to cover
overheads, will be added to the rates calculated by the estimator. The level of profit is kept a closely
guarded secret
Having taken the decision to submit a tender the contractor will take delivery of the tender documentsand proceed to prepare the bid; this will involve:
Carefully examining the drawings and bills of quantities for accuracy and then preparing a timetablefor the preparation of the bid
Visiting the site, particularly appropriate for alteration work, or where the site has restricted access orworking
Preparing any method statements; method statements are an analysis and description of how thecontractor proposes to carry out particularly complicated parts of the works.
11. FINAL REVIEWThe consideration of the estimate to produce a tender is the responsibility of management .The
estimator and other senior staff will prepare reports for consideration by management who will consider
the following items before determining the tender figure;
Project reports
Conditions of contract
Contractual and construction risks
Terms of the quotations from sub-contractors
Capital required for the project
Technical and management staff required
Current workload Market Conditions
Competition
Reputations of client, consultants and area
Following evaluation of the alternatives, risk and scope for profitability the mark up is determined andthe actual tender figures calculated. The decision being made within the Frame work of company policy
.A record of all tenders should be kept together will the results (if known) for future reference
7/31/2019 Tender Assigment
8/27
TENDER ESTIMATION
Page 8
1.2. LIST THE FACTORS TO BE CONSIDERED IN PRICING A TENDER
Market Condition:The volumes of work in progress in the area at a given point in time affect constructioncost. When the market is burying with many project, tender price list are generally high.Most consultants are busy and competition is not keen. However during ausle times when
there are few projects, contractors are anxious to out bid themselves so as to stay inbusiness, so construction cost tends to be lower.
Availability of Materials:When required materials are readily available in an area where a project is to be executed,materials will be cheaper than where they are not so available. Generally, materials arecheaper where they are produced e.g. if you can buy cement directly from Colombo, theprice will be a lot cheaper than in Jaffna because of transportation and profit margins ofmiddlemen and so on. Imported materials for similar reasons are more expensive thanlocally produced materials.
Availability of Labor:
Where a certain type of labor is not readily available in the area where a project is to be
constructed, it may be necessary to import from an area where such labour is available. Some
inducement may have to be offered before such labour will move from its base such as
transportation, accommodation, inconveniences allowances etc. these add to the cost of
construction.
Transportation:
The farther a site is from town, the more expensive will be the construction cost
Location:
The standard of living in an area affects the cost of construction. People are willing to payhigher prices for construction in places
Location of Site: -
The particular location of the site can have significant effect on cost. Remote site may require
additional cost for the provision or access roads and temporary services or the provision of
additional security measures. Also, a site in a congested or restricted area also gives rise to
major problems such as delivery & storage of materials and components, protection of
adjoining buildings and the public, restriction on the use of mechanical plants and so on, all
these will increase the cost of construction.
Time Consideration: -
For certain reasons, a project may need to be completed in a very short time; this tends to push
up construction cost. Laborers may be required to work overtime and overtime rates are usually
higher than normal rates. Incentives scheme may have to be introduced to increase labor
productivity. Closure supervision is necessary as mistake must be avoided, there may be
time to apply remedial action
7/31/2019 Tender Assigment
9/27
TENDER ESTIMATION
Page 9
Site Condition:
May affect the construction cost of a particular building. The nature of ground may necessitate
more complex form of foundation. The ground water level when close to surface will involve
costly water pumping operation. A wet site may involve rising temporary sheds and offices
above ground level and they involve more costly temporary roads. Steeply sloping site may
involve major cost in cutting and filling requirements, existence of buried pipes and cables may
involve major cost to re-root such.
Total Height of Building:
The higher a building is, the longer it takes and more difficult it is to get the point of execution of
works. It is also more difficult to work at such height. Labor charges for 30working at great
height are higher than normal height; there is also the cost of providing additional safety
measures and insurance. Also, the need for special scaffolding, hoist, tower crane, elevators
etc. will tend to increase the cost of very tall building over the cost of building requiring
the same quantities at ground level.
Class of Contractors:There are various types of contractors in the market. These gives rise to differentclassification.
Small contractors comprises of one man board of directors. They usually carry littlegeneral overhead and keep very few permanent staff
Medium contractors usually have a board of at least two but not more than fivedirectors they employ a few more permanent staff, have a reasonable office andpossess some equipment and official cars.
Large contractors have a lot of times publicly owned with many share holders havingat least six members on their board of directors, fleet of cars and equipments, largeoffice space and a lot of staffs of various discipline. Generally, the larger the firm,the higher their cost. Also, the level of profit expected by the share holder of largerfirms is a lot more than that required by the smaller contractors. The rates for thesmall contractors therefore tends to be much lower than for large contractors
Types of Consultants: Architect: - Some architects are very difficult to work with, their initial designs are not
detailed and they rely a lot on instructions on site. Many variations occur and delaysare frequent. These will add to the cost of construction. The same applies toEngineers and other designers. Contractors are therefore known to increase theirprices by a certain percentage when it is known that they would be working withparticular consultant.
Types of Tendering:Open tendering generally brings lower prices than selective tendering, and this in turnresult in lower price than negotiated tendering which brings the highest price of fall.
REFERENCE: UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATION
REVITALISATION PROJECT-PHASE IINATIONAL DIPLOMA IN QUANTITY SURVEYING
TENDERING AND ESTIMATING II
COURSE CODE: QUS 210
7/31/2019 Tender Assigment
10/27
TENDER ESTIMATION
Page 10
1.3. LIST THE SOURCES AND NATURE OF INFORMATION REQUIRED FOR COST ESTIMATING
1. Drawings :
dimensions (length, width ,height )
shape of component of the building
elevations
2. Specifications :
quality of workmanship
Way of construction
Additional works related with work item
3. Preambles :
quality of material
way of handling materials
4. BOQ :
Description of work
Unit of work item
Quantity of work item
5. Suppliers quotation :
Prices of materials
Quality of materials
Discounts
6. Sub-contractor quotation :
Prices of work item
Discount
7. Site visit :
Condition of site
Nature of soil
Shape of land
8. Previous experience :
Labor cost
9. Previous document:
Additional related work
10. BSR
Standard prices for work items
7/31/2019 Tender Assigment
11/27
TENDER ESTIMATION
Page 11
Task: 02
PREPARE STANDARD RATES FOR LABOUR, CONSTRUCTION PLANT AND MATERIALS
2.1. LIST THE FACTORS TO BE CONSIDERED WHEN CALCULATE ALL IN RATES FOR LABOR,
PLANTS AND MATERIAL.
Construction cost is a broad phrase or term and can be interpreted to mean cost of any sort toanyone associated with construction work. It depends on the point of view let us say you are a
contractor, your costs are your expenditure on labour, materials and plant. The clients cost of land,
consultant fees and so on.
The base cost of construction therefore comprises of expenditure on materials, labour and plant, the
quantities of materials, labour and plant required for a job are determined &attaching prices to these
defines the basic construction cost, but to these are also a variety of factors that affect this basic cost: -
In our industry most estimators will calculate costs based on net rates these will then be enhancedlater to include overheads and profit. Gross rates are sometimes referred to as all-in rates
ALL IN RATE FOR LABOR
Minimum guaranteed overtime.
Non productive time
ETF & EPF
Insurance
Medical facilities
Non productive time
Tool money
Inclement of bed weather
Minimum guaranteed bonus
ALL IN RATE FOR MATERIAL
Prime cost of the material
Transportation costs
Unloading and Stacking costs
Materials movement on site
Extra Materials to compensate for
Wastage Allowance for materials being measured net in BOQ
Loss in consolidation, shrinkage etc
ALL IN RATE FOR PLANT
Depreciation of plant
Repair and maintenance cost of plant
License and Insurances cost
Fuel and Lubricant
Operator cost
7/31/2019 Tender Assigment
12/27
TENDER ESTIMATION
Page 12
2.2. ANALYZE THE FACTORS LISTED IN 2.1 AND EXPLAIN HOW EACH ONE CONTRIBUTES TO
THE TOPIC (LABOR COST, MATERIAL COST AND PLANT COST)
The Resources which compromise a unit rate are labour, materials and plant
LABOR
In the construction industry labour is often employed in two main ways, these are
:1.Direct Often referred to as cards in, the employer pays all the costs of employment including
for example national insurance and sick pay amongst others
.2.In-DirectThese workers are self employed or referred to in industry as on the lump
These are often labour only sub-contractors without the normal costs of employment along with the
other legal protections such as redundancy, sick pay and minimum notice periods.
Labour may be paid for on an hourly, daily, weekly or piecework basis. Directly employed operatives
are usually paid in accordance with a working rule agreement which will specify the rates
and allowances to be paid. However, some contractors are trying to move away from the national wage
bargaining and introduce local wage rates. Ultimately the actual rates paid for labour will dependon market forces
MATERIALS
Several factors affect the cost contractors pay for materials. In the material element of a unit rate, in
addition to the actual cost of the material the estimator must also consider above factors because
Where prices of materials are described by suppliers as exworks this means the price at the factory
and delivery costs will have to be added.
PLANT
Plant may be divided into two main categories, the costs of which can be allocated to contracts indiffering ways.
Non-Mechanical Plant
Basic items of plant including barrows, hosepipes, spades, trestles, scaffolding, small powered hand
tools etc
With the exception of scaffolding and one or two other items it is virtually impossible to allocate the cost
of non-mechanical plant items to a contract, let alone to a specific unit rate e.g. a wheelbarrow may be
used on several contracts in its life time.
The cost may be included in overhead charges as a percentage, as a lump sum in the preliminaries bill
or, more accurately, on longer contracts a list of non-mechanical plant items is prepared, coasted andincluded in the contract sum
Mechanical Plant
This include all mechanical plant not allocated to unit rate such as cranes, lift, dumpers, hoist, tractor,
generating set, drills, forklift etc. the contractor is expected to allow for this items whether they are
purchased specifically for the project or they are already owned by the firm or they are to be hired for
the period they are required on the project. The usual thing is to allow for
(a) Cost of transporting plant to site
(b)Hire rate for the period plant is on site
(c)Cost of maintenance on site
(d)Profit and overhead
7/31/2019 Tender Assigment
13/27
TENDER ESTIMATION
Page 13
Task: 03
BUILD UP UNIT RATES FOR TRADES WORK ITEM
3.1. STATE THE FACTOR WHICH EFFECT THE CALCULATION OF UNIT RATES FOR
FOLLOWING WORK ITEM
01. EXCAVATION
The following factors may affect unit rates for ground works
Type of excavation e.g. trenches, pits, basements
Ground conditions e.g. clay, sand, soil, rock
Depth of excavation
Ground water
Time of year when excavating
Mechanical or hand excavation
Distance and availability of tips
Estimated bulking of materials
02. CONCRETE
The following factors may affect unit rates for concrete work;
Whether ready mixed or site mixed concrete is used
Whether concrete is reinforced
Surcharges for part loads Location of mixing plant on site
Type and size of mixing plant
Method of transporting, hoisting, placing and compacting mixed concrete
Cost of protecting and curing
Unset concrete Operatives working with concrete receive additional payments for skill and
responsibility.
Items of plant should be priced separately.
Concrete is usually measured in m3Site Mixed Concrete
03. BRICK WALL
The following factors may affect unit rates for brick work;
Quality of finished works
Type of work (i.e. straight walls, curved walls, foundations etc)
Working overhand, at height
Type of pointing
7/31/2019 Tender Assigment
14/27
TENDER ESTIMATION
Page 14
04. FORMWORK
Formwork measures the actual faces of work covered or to be supplied. The following must be taken
into consideration in determining the size of the formwork
The amount of material required
The kind of finishes required i.e. sawn faced or smooth finish, ground finish, biscuit etc. This determines the
types of materials to be used as formwork and the surface from finish required is removed.
The height to be supported. This determines the height of props and types of props.
Normal labour for fabricating, erecting and striking of formwork.
The number of uses required of the formwork this is usually a matter of experience. In small
contract it may be possible to reuse the same formwork twice depending on the repetitive
nature of the work
REFERENCE: UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATION
REVITALISATION PROJECT-PHASE IINATIONAL DIPLOMA IN QUANTITY SURVEYING
TENDERING AND ESTIMATING II
COURSE CODE: QUS 210
7/31/2019 Tender Assigment
15/27
TENDER ESTIMATION
Page 15
TASK: 04
DEMONSTRATE ABILITY TO COSTING OF PRELIMINARIES / OVERHEAD COST OF THE
CONTRACTOR
4.1. EXPLAIN PRELIMINARIES AND OVERHEAD COSTS IN BILL OF QUANTITIES
WHAT ARE PRELIMINARY ITEMS?
Preliminary items are items of cost which do not relate to any particular work section and usually listed
in the first bill of quantities. Many estimators prefers to inserts a lump sum for all the preliminaries
usually worked out as a percentage of the total of the measured works. It is good practice however to
put a price to each of the item. The price quoted should read at after careful consideration of each item
as it applies to the particular job at hand e.g water for the works. It will be pipe bone water readily
available on site or water has to be transported to site on trucks.
PRELIMINARY BILL
The preliminaries bill gives the contractors the opportunity to price overheads which is described in the
Code of Estimating Practice as the cost of administering a project and providing general plant, site
staff, facilities and site based services and other items not included in bill rates.
Preliminaries costs vary from contract to contract depending on complexity of work, size of
contract, specialist plant and equipment required, conditions imposed by the employer etc.
On relatively simple contracts preliminary costs may be in the order of 10 15% of the contract
sum whereas on complex contracts this figure could be much higher.
A contractor must calculate the cost of the preliminary items separately for each contract; no
two contracts are the same.
SMM7 recommends that fixed and time-related charges should be identified separately in a bill
of quantities.
A fixed charge is defined as the cost of work which can be considered as being independent ofduration
A time-related charge is defined as the cost of work which is to be considered as dependant on
duration.
OVERHEADSOverheads may be defined as the cost of maintaining (running) the contractors organization.
There are two types of overheads:
(1) Head Office
Annual cost of staff salaries, expenses, rents, rates, gas, water, electricity, telephones, officeequipment, postage, insurance, maintenance of buildings and equipment etc. The cost of these itemsis expressed as a percentage of a companys turnover and included in the tender.
(2) Project or SiteProject site costs including non productive (manual) site staff, site office costs, storage facilities andother preliminary / site organization costs. Items are priced as individual items and may be fixed or timerelated costs or a mix of fixed and time related costs. The costs of these items are included in thetender.
7/31/2019 Tender Assigment
16/27
TENDER ESTIMATION
Page 16
4.2. JUSTIFY THE GIVEN SCENARIO IN RELATION TO THE ABOVE TWO EXAMPLES,
HOW/WHY DIFFERENT COSTS INVOLVED FOR THE SAME PRELIMINARY ITEMS IN
DIFFERENT PROJECTS.
The preliminaries are most important part in a BOQ also it is very difficult to calculate because it
usually will differ project to project because of following reasons
Will identify the two work item how it differ project to project
Transportation of machineries
The different distance of transporting plant to site
The different machineries needed for the different project
The different project scope (large or small)
Site office for consultant representative
The different number of staff for each project
The different maintain period because of the different duration of project
The accommodation required for the project it will defer each project The cost will differ according to place weather on site or off site
For the above mentioned reasons the cost of preliminary will differ each project so as an estimator he
will gain this knowledge through the past experience. Most of the times the preliminary item will be
calculate separately even same project scope
7/31/2019 Tender Assigment
17/27
TENDER ESTIMATION
Page 17
4.3. CALCULATE THE COST OF ABOVE TWO ITEMS WITH YOUR OWN ASSUMPTION
PRELIMINARY ITEM-01: SITE OFFICE FOR CONSULTANTS REPRESENTATIVE
The contractor is usually expected to provide and maintain temporary site accommodation for Supervising consultant on site
Site agent and site staff Hut for workmen Storage, shed for materials, tools etc.
Pricing for these must cover the cost of:
Initial construction of accommodation
Removal on completion and making good ground disturbed
Maintenance of accommodation throughout duration of the project
Furniture including ventilation and air conditioning
Overhead and profit from this estimator must remove the resale value of items are still
useable at the end of the projects
SITE OFFICE
The contractor shall provide suitable accommodation for the clerk of works, with a minimum floor area
of 20 m2 including desk, four chairs, filing cabinet and all necessary heating, lighting and cleaning.
ASSUMPTION
Contract period: 144 weeks
Transport to and from site: Rs.22500 per trip
Hire of hut: Rs.8500.00 per week
Hire of furniture and heaters, etc.: Rs.2500.00 per week
FIXED CHARGES
Transport to and from site 2 trips Rs.22500 45000.00
Erection 10 hours
Dismantle 5 hours
15 hours laborer @ Rs.300.00 4500.00
Total of fixed charges 49,500.00
TIME RELATED CHARGES
Hire of hut 144 weeks @ Rs.8, 500.00 per week 1,224,000.00
Furniture and heaters 144 weeks @ Rs.2500.00 per week 360,000.00
Energy costs for heating and lighting:
144 weeks @ Rs.640.00 per week 92.160.00
Cleaning 2 hours per week 144 weeks =
288 hours @ Rs.1980.00 285,120.00
Total of time related charges 1,961,280.00
Rate per week = Rs.13, 620.00
Total (fixed and time related charges) 49,500.00 + 1,961,280.00 = 2,010,780.00
7/31/2019 Tender Assigment
18/27
TENDER ESTIMATION
Page 18
PRELIMINARY ITEM-02: TRANSPORTATION OF MACHINERIES
This include all mechanical plant not allocated to unit rate such as cranes, lift, dumpers, hoist, tractor,
generating set, drills, forklift etc. the contractor is expected to allow for this items whether they are
purchased specifically for the project or they are already owned by the firm or they are to be hired for
the period they are required on the project. The usual thing is to allow for
(a) Cost of transporting plant to site
(b) Hire rate for the period plant is on site
(c) Cost of maintenance on site
(d) Profit and overhead
TRANSPORTATION OF MACHINERIES
Cost of plant 3,000,000.00
Less scrap value 450,000.00
2,550,000.00
Assume a life of 4 years therefore annual cost 2,550,000.00
4
= 637,500.00
Assume a usage of 1500 hours per year:
Cost per hour 637,500.00
1500
= 425.00
Assume 25% for repair and maintenance = 106.25
Assume 10% for license and insurance = 42.50
Total cost of plant 573.75
Assume 1 liter of fuel per hour @ Rs.135.00 Per liter = 135.00Assume 0.5 liter of lubricant oil per hour @ Rs.720.00 per liter = 360.00
Assume Rs.175.00 for the operator per hour = 175.00
Net unit rate 1,243.75
Overhead & profit 25% =310.93
Gross unit rate 1554.68
7/31/2019 Tender Assigment
19/27
TENDER ESTIMATION
Page 19
TASK: 5 DESCRIBE THE PROCEDURE FOLLOWED IN PREPARATION OF A QUOTATION
5.1. DESIGN TWO SAMPLES INQUIRY LETTERS TO SUBCONTRACTOR AND SUPPLIER IN
ORDER TO COLLECT THEIR QUOTATION.
ENQUIRY LETTER TO SUPPLIERS
12/07/2012
DELTA MAGACONSTRUCTION (PVT) LTD,
NO: 39, DANIEL ROAD,
COLOMBO: 03
TO: SALES MANAGERORANGE ELECRIC PVT LTD,
165, GALLE ROAD,
DEHIWALA,
SRI LANKA.
Dear Sir,
CONSTRUCTION OF A PROPOSED SHOPPING COMPLEX
WE INVITE YOU TO QUOTE YOUR BEST PROPOSAL FOR SUPPLY OF BELOW MENTIONED
MATERIAL FOR OUR PROPOSED SHOPPING PROJECT AT
ITEM NO DESCRIPTION QUANTITY
01 ORANGE SPIRAL SHAPE ENERGY SAVING LAMP
TRI-PHOSPHOR POWDER
FLAME RETARDANT CAP
TUBE DIAMETER: 12MM
WATTAGE: 20W VOLTAGE: 110V
1000
YOUR QUOTATION MUST BE DELIVERED TO THIS ADDRESS
DELTA MAGACONSTRUCTION (PVT) LTD,
NO: Z39,
DANIEL ROAD,
COLOMBO: 03
7/31/2019 Tender Assigment
20/27
TENDER ESTIMATION
Page 20
TERMS AND CONDITIONS
Payment terms : 1 week after delivery
Advance payment : 25% of total
Payment type & term : Please mention your payment type & term
Discounts : Please notify your discount
Transportation : By the Suppliers with safe with protection.
Traffic condition or restrictions : During week days from 8.00 am to 05.30 pm
vehicles can park at the site area.
Submission of quotation : Two weeks
Suppliers will be required to deliver the material according to the schedule. If you need to make any
inquires you may visit the site after contacting the site manager of the project. We would appreciate if
you could provide us with the relevant discounts since we are one of your frequent customers. If your
company is out of stock then please notify us when you will be able to receive these materials. And if
there are any clarifications about the tender please contact Mr.Aslam the estimator of the project.
We would appreciate if you would send the acknowledge receipt of this enquiry and submit the
quotation in accordance with the given instructions.
Yours Faithfully,
......
Aslam
(Quantity Surveyor)
7/31/2019 Tender Assigment
21/27
TENDER ESTIMATION
Page 21
ENQUIRY LETTER TO SUBCONTRACTOR
__/__/2012
DELTA MAGA CONSTRUCTION (PVT) LTD,
NO: 39, DANIEL ROAD,
COLOMBO: 03
TO: MANAGER
JUDI CONTRACTORS (PVT) LTD,
GALLE ROAD,
BARUWALA,
SRI LANKA.
DEAR SIR,
CONSTRUCTION OF A PROPOSED GYMNASIUM
WE INVITE YOU TO QUOTE YOUR BEST PROPOSAL FOR DOING OF BELOW MENTIONED WORK
FOR OUR PROPOSED GYMNASIUM PROJECT AT PANAGODA.
ITEM NO DESCRIPTION QUANTITY
01PLASTERING FOR EXTERNAL BRICK WALL WITH1:3
CEMENT: SAND MORTAR750m
2
YOUR QUOTATION MUST BE DELIVERED TO THIS ADDRESS
DELTA MAGA CONSTRUCTION (PVT) LTD,
NO: 39, DANIEL ROAD,
COLOMBO-03
TO ARRIVE NO LATER THAN 02.00 P.M. ON OR BEFORE __ OF ___ 2012
7/31/2019 Tender Assigment
22/27
TENDER ESTIMATION
Page 22
TERMS AND CONDITIONS
Payment terms : 2 weeks after work started
Advance payment : 20% of total
Payment type & term : Please mention your payment type & term
Traffic condition or restrictions : During week days from 8.00 am to 05.30 pm vehicles can park
at the site area.
Submission of quotation : Two weeks
Subcontractor will be required to deliver the material according to the schedule. If you need to make
any inquires you may visit the site after contacting the site manager of the project. We would
appreciate if you could provide us with the relevant discounts since we are one of your frequent
contractors. If your company is out of stock then please notify us when you will be able to receive these
materials. And if there are any clarifications about the tender please contact Mr. Aslam the estimator of
the project.
We would appreciate if you would send the acknowledge receipt of this enquiry and submit the
quotation in accordance with the given instructions.
Yours Faithfully
..........................
Aslam
(Quantity Surveyor)
7/31/2019 Tender Assigment
23/27
TENDER ESTIMATION
Page 23
5.2. DESCRIBE THE FACTORS THAT WILL BE CONSIDERED BY THE ESTIMATOR
WHEN EVALUATING THE QUOTATION RECEIVED FROM SUBCONTRACTORS AND
SUPPLIERS
Choosing the right suppliers involves much more than scanning price lists. Your choice will depend on
a wide range of factors such as value for money, quality, reliability and service. How you weigh up the
importance of these different factors will depend on your business priorities and strategy.
the criteria for evaluating and awarding a contract is required to be stated in the tender documents
these would normally be the most economically advantageous taking account of such factors as: PURCHASE PRICE:
Lowest Price Technically Acceptable This approach is appropriate when best value is expected to
result from selection of the technically acceptable offer with the lowest evaluated price. Price is
important, but it shouldn't be the only reason you choose a supplier. Lower prices may reflect
poorer quality goods and services which, in the long run, may not be the most cost-effective option.
Be confident that your supplier can make a sufficient margin at the price quoted for the business to
be commercially viable.
OTHER WHOLE LIFE COSTS :
It will involve Running costs, obsolescence, resale value or disposal cost, after sales service and
technical assistance from supplier or sub-contractor
DELIVERY:
The requesting activity may provide instructions via the Purchase Request that delivery is a critical
factor in choosing the prospective supplier or sub-contractor
QUALITY :The estimator should have to check the quality requirement according to the specification prepared
for the particular work
DISCOUNT RATE :
This is the important feather among the supplier or subcontractor because he can improve his profit
through this discount and he can reduce his tender value so he can win a job through this
CONTRACT TERMS :
The main estimator responsibility is to consider the contract terms to continue the contract deal with
a supplier in a fair manner
PAST PERFORMANCE :
The ability of well performance is a main reason in selecting subcontractor so the estimator should
have to take attention in past performance of subcontractor with the same project
BUSINESS PRACTICES :
The estimator will look at his business deal with other contractor and check his practices in his
business it will be useful to continue the deal for long period
The above mentioned factors should have to consider by the estimator in evaluating quotation fromsupplier and subcontractor because it will be very helpful to win a job.
7/31/2019 Tender Assigment
24/27
TENDER ESTIMATION
Page 24
5.3 DESCRIBE THE DIFFERENT FORM DISCOUNT OFFERED IN THE CONSTRUCTION
INDUSTRY AND EXPLAIN HOW YOU INCORPORATE THEM IN PRICING.
DISCOUNTS
Discounts are the quoted amount or stated cost which will deduct from the payments to the suppliers
and subcontractors, depend on fulfillment of the conditions which are specified in the contract for
acquiring discounts.
Followings are two types of discounts accepted by the subcontractors and suppliers.
Trade discounts
Cash discounts
TRADE DISCOUNTS
Trade discounts apply particularly when there are standard price lists prepared by manufacturers orsuppliers and when items may be sold direct to the public. The discount is varied to allow forfluctuations in prices to avoid frequent revision of such lists. Some suppliers allow large discounts for
regular customers who purchase large quantities.
Ex: -
Builders and plumbers may get, say, a 20% discount on the supply of sanitary fittings when
compared with the retail price to the general public.
Let us consider a supplier of Bricks. The supplier might allow trade discounts as given below.
Quantity Discounts
5000 - 10000 Bricks 15%
10000 - 15000 Bricks 18%
15000 - 20000 Bricks 20%
If the buyer purchases more than 5000 Bricks then the buyer is entitled for a discount of 15 % from the
marked price. Similarly if the buyer purchases more than 10,000 Bricks s, he could get a discount of
18%. Similarly if the buyer purchases more than 20,000 Bricks which are considered to be a large
quantity, he could get a 20% discount rate. While the price of Bricks raised by 2%. Then the supplier
could alter the discount rate without making any changes to the actual prices. In this case reducing the
discount up to 3% for 1000-5000 Bricks would be satisfactory.
7/31/2019 Tender Assigment
25/27
TENDER ESTIMATION
Page 25
CASH DISCOUNTS
A cash discount is often given by suppliers and subcontractors to encourage early settlement of
accounts.
If the contractor settle the accounts to the suppliers and subcontractors before the original date than
the contractor will get some percentage of discounts
Ex: -
Let us consider that the electrical installation was carried out by a sub-contractor. The invoiced value of
work done by the sub-contractor is Rs. 400,000 for a particular month. Usually the sub-contractors
payment is done through the main contractor. If the main contractor settles the amount Rs. 400,000
within the specific period, the main contractor is entitled for a discount which is normally 5 % of the
invoice value. So the contractor has to pay only Rs. 180000. But if the main contractor fails to make
the payment within the specified time, then the main contractor has to pay the entire Rs. 400,000 Such
discounts given by sub-contractors will motivate the contractors to make the payments earlier. Thus itwill ensure the smooth function of the construction project. Likewise the suppliers also give such cash
discounts to encourage the contractor to settle the payments quickly.
Explanation of how to incorporate them into the tender
The main contractor is always expecting about the discount to use it in pricing the tender. If the main
contractor knows the amount of the discounts from the subcontractors or suppliers
Contractor can reduce the rate of the work in that tender. So the tender price may be reduced.
This might be increased the chance to win the tender.
That is why the estimator or being consultancy Quantity Surveyors should have a thorough knowledge
about the discounts and should apply the discounts while he is pricing the tender.
7/31/2019 Tender Assigment
26/27
TENDER ESTIMATION
Page 26
CONCLUSION
As a quantity surveyor we have some responsibility construction industry out of them tender
stage is a most important one. Because each and every constructions except some unique
construction going to hand over to one of a best contractor only by calling tender.
Here we are supposed to refer and suppose to understand something clearly about the
knowledge of tender. And we have to have enough knowledge about the project that has been
invited, client of the proposed project and about the consultant as well. Cause those are the
important thing that we are going to have a relationship.
So that we want to understand this all thing as a QS and we are the peoples who are going to
handle with this kind of meter
In this way I collected some useful information according to the lecturer requirement so I think
it will be very useful document which explain basic knowledge of tender
7/31/2019 Tender Assigment
27/27
TENDER ESTIMATION
REFERENCES
UNESCO-NIGERIA TECHNICAL & VOCATIONAL EDUCATIONREVITALISATION PROJECT-PHASE II
NATIONAL DIPLOMA IN QUANTITY SURVEYING
TENDERING AND ESTIMATING II
COURSE CODE: QUS 210
QUANTITY SURVEYORS POCKET BOOK
FIRST EDITION2009DUNCAN CARTLIDGE FRICS
PUBLISHED BY ELSEVIER LTD
ESTIMATING AND TENDERING FOR CONSTRUCTION WORK
THIRD EDITION 2004
MARTIN BROOK BENG (TECH) FCIOB
PUBLISHED BY ELSEVIER LTD
WWW.GOOGLE.LK
WWW.WIKIPIDIA.COM
http://www.google.lk/http://www.google.lk/http://www.wikipidia.com/http://www.wikipidia.com/http://www.wikipidia.com/http://www.google.lk/