+ All Categories
Home > Documents > TFC-ENG-SB-C-01, Safety Basis Issuance and Maintenance · 2019. 1. 18. · ENGINEERING SAFETY BASIS...

TFC-ENG-SB-C-01, Safety Basis Issuance and Maintenance · 2019. 1. 18. · ENGINEERING SAFETY BASIS...

Date post: 15-Feb-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
21
RPP-27195 SAFETY BASIS ISSUANCE AND MAINTENANCE Manual Document Page Issue Date Engineering TFC-ENG-SB-C-01, REV F-1 1 of 21 May 24, 2017 Ownership matrix TABLE OF CONTENTS 1.0 PURPOSE AND SCOPE ................................................................................................................ 2 2.0 IMPLEMENTATION ..................................................................................................................... 2 3.0 RESPONSIBILITIES...................................................................................................................... 2 4.0 PROCEDURE ................................................................................................................................. 3 Safety Basis Change Development ..................................................................................... 3 Safety Basis Change Review and Submittal ....................................................................... 5 Incorporation of Documented Safety Analyses Page Changes ........................................... 7 Safety Basis Annual Update ............................................................................................... 8 Limited Duration Safety Basis Changes (Addenda, ESSs, and JCOs) ............................. 11 4.6 Safety Basis Implementation and Closeout ...................................................................... 14 5.0 DEFINITIONS .............................................................................................................................. 15 6.0 RECORDS .................................................................................................................................... 15 7.0 SOURCES ..................................................................................................................................... 16 Requirements .................................................................................................................... 16 References......................................................................................................................... 16 TABLE OF ATTACHMENTS ATTACHMENT A GUIDANCE FOR LIMITED DURATION CHANGES......................................... 18
Transcript
  • RPP-27195

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Manual

    Document

    Page

    Issue Date

    Engineering

    TFC-ENG-SB-C-01, REV F-1

    1 of 21

    May 24, 2017

    Ownership matrix

    TABLE OF CONTENTS

    1.0 PURPOSE AND SCOPE ................................................................................................................ 2 2.0 IMPLEMENTATION ..................................................................................................................... 2 3.0 RESPONSIBILITIES ...................................................................................................................... 2 4.0 PROCEDURE ................................................................................................................................. 3

    Safety Basis Change Development ..................................................................................... 3 Safety Basis Change Review and Submittal ....................................................................... 5 Incorporation of Documented Safety Analyses Page Changes ........................................... 7 Safety Basis Annual Update ............................................................................................... 8 Limited Duration Safety Basis Changes (Addenda, ESSs, and JCOs) ............................. 11

    4.6 Safety Basis Implementation and Closeout ...................................................................... 14 5.0 DEFINITIONS .............................................................................................................................. 15 6.0 RECORDS .................................................................................................................................... 15 7.0 SOURCES ..................................................................................................................................... 16

    Requirements .................................................................................................................... 16 References ......................................................................................................................... 16

    TABLE OF ATTACHMENTS

    ATTACHMENT A – GUIDANCE FOR LIMITED DURATION CHANGES ......................................... 18

    http://toc.wrps.rl.gov/rapidweb/PRO/index.cfm?pageNum=232

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    2 of 21

    May 24, 2017

    1.0 PURPOSE AND SCOPE (7.1.1, 7.1.2, 7.1.3)

    This procedure describes the safety basis document issuance and maintenance process, including

    amendments, annual updates, addenda, Evaluations of the Safety of the Situation (ESS), and

    Justifications for Continued Operation (JCO). This process applies to the three documented

    safety analyses (DSA) and technical safety requirements (TSR) for the Tank Farms, 242-A

    Evaporator, and 222-S Laboratory.

    Development of preliminary DSAs and new DSAs for new nuclear facilities or major

    modifications to existing nuclear facilities is within the scope of TFC-ENG-SB-C-06.

    The safety basis document issuance and maintenance process consists of the following functions:

    Updating or amending the safety basis to keep it current (i.e., to reflect changes in the facility, the work, and the hazards as they are analyzed in the DSAs);

    Annually submitting to the U.S. Department of Energy (DOE), Office of River Protection (ORP) either updated DSAs for approval or letters stating that there have been no changes

    in the DSAs since the prior submission;

    Incorporating page changes into the DSAs associated with negative unreviewed safety question (USQ) determinations and changes resulting from review of Chapter 1 and

    Chapters 6 through 17 of the DSA (included in the annual update);

    Updating or amending the safety basis for limited duration changes; and

    Incorporating directed changes and conditions of approval from the ORP.

    This procedure applies to Washington River Protection Solutions, LLC (WRPS) personnel and its

    subcontractors.

    2.0 IMPLEMENTATION

    This procedure is effective on the date shown in the header.

    3.0 RESPONSIBILITIES

    Nuclear Safety Manager – Responsible for written approval of exceptions to requirements in this

    procedure.

    A request for an exception to a requirement in this procedure must be provided to the Nuclear

    Safety Manager in writing providing:

    The procedure requirement (i.e., the specific procedure section) for which the exception is being requested;

    The safety basis document to which the requested exception is applicable; and

    The basis for the exception.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    3 of 21

    May 24, 2017

    Detailed responsibilities are described in Section 4.0.

    4.0 PROCEDURE

    Safety Basis Change Development

    This section describes the process for developing safety basis updates and amendments (see

    Section 4.5 for discussions on limited duration changes). Safety basis changes include updates

    and amendments resulting from the change control processes for facility or document changes.

    Line Management 1. Identify the need for a facility or document change.

    a. For DSA development for new nuclear facilities or major modifications to existing nuclear facilities, refer to

    TFC-ENG-SB-C-06.

    b. For controls needed for an operation with a known end point, identify the conditions under which it will no longer be

    necessary.

    2. Request Production Operations; Single-Shell Tank Retrievals; Waste

    Treatment Plant Support; Tank Farm Projects; Chief Engineer;

    Environmental, Safety, Health, and Quality; and Project Integration

    Management review the proposed change for organizational impacts,

    as applicable.

    Impacted

    Organization

    Representatives

    3. Assist Line Management in the development of the change by

    completing the following sub-steps.

    a. Perform required analyses, evaluations, and calculations.

    b. Modify impacted documents (including drawings, operating and administrative procedures, Functions and Requirements

    Evaluation Documents, Safety Requirement Evaluation

    Document, etc.).

    c. Identify potential training and qualification impacts.

    Line Management 4. Forward a description of the change to the Nuclear Safety Manager for

    processing.

    Nuclear Safety

    Manager

    5. Designate a Nuclear Safety Engineer or USQ Evaluator to coordinate

    development and process the change.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    4 of 21

    May 24, 2017

    Nuclear Safety

    Engineer/USQ

    Evaluator

    6. Review existing amendments, JCOs, ESSs, and addenda to determine

    if they are impacted by the proposed change. If they are impacted:

    a. Coordinate resolution of impacts and include within the scope of the change.

    b. Consider interim configurations during installation of new equipment and removal of old equipment for operating

    facilities.

    7. Develop an update to the DSA hazard analysis (e.g., RPP-15188,

    “Hazard Analysis Database Report”), as applicable.

    8. If a Process Hazard Analysis is required to evaluate the hazards or if a

    new hazard entry is required to be made to the DSA hazard analysis,

    process in accordance with TFC-ENG-DESIGN-C-35 and TFC-ENG-

    DESIGN-C-47.

    9. Develop the draft safety basis change package (including DSA and

    TSR redline/strikeout on the current released version of the DSA and

    TSR) in accordance with the following:

    Code of Federal Regulations (CFR) 10 CFR 830, “Nuclear Safety Management,” Subpart B, “Safety Basis

    Requirements,” Section 830.202, “Safety basis”; (7.1.1)

    DOE G 421.1-2, “Implementation Guide for Use in Developing Documented Safety Analyses to Meet Subpart B

    of 10 CFR 830”; (7.1.2)

    DOE G 423.1-1, “Implementation Guide for Use in Developing Technical Safety Requirements”; (7.1.3)

    DOE-STD-3009-94, “DOE Standard – Preparation Guide for U.S. Department of Energy Nonreactor Nuclear Facility

    Documented Safety Analyses”; (7.1.7)

    DOE-STD-1186-2004, “DOE Standard – Specific Administrative Controls”; (7.1.5) and

    DOE-STD-1189-2008, “DOE Standard – Integration of Safety into the Design Process,” as appropriate. (7.1.6)

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    5 of 21

    May 24, 2017

    10. Verify that existing documents added to a DSA as references in a

    safety basis change are not listed in RPP-27195, “Tank Operations

    Contractor Unreviewed Safety Question Process Out of Scope

    Documents and Facilities.”

    a. If the document is listed in RPP-27195, revise RPP-27195 to remove the document prior to implementation of the safety

    basis change.

    11. If, upon application of the USQ process as outlined in TFC-ENG-SB-

    C-03, it is determined that the change does not require ORP approval,

    attach the safety basis page changes to the USQ and exit this

    procedure.

    Safety Basis Change Review and Submittal

    NOTE: The following steps apply to DSA changes that require ORP approval

    prior to implementation (i.e., either the USQ determination performed in accordance with

    TFC-ENG-SB-C-03 shows a “positive” result, or the USQ was not conducted because the

    change is defined as requiring ORP approval, such as a TSR change).

    NOTE: Documents should be through the review process of the providing

    organization so that the DSA changes are based on accurate information.

    Nuclear Safety

    Engineer

    1. Obtain documents used to develop the safety basis amendment.

    2. Obtain peer review of safety basis amendment package by WRPS Nuclear Safety Engineer(s) who shall complete the following sub-

    steps:

    a. Review the change and complete the “Peer Review Checklist for Existing Safety Basis Documents” (DSA, TSRs,

    Addendum, JCO, ESS) form (A-6007-121).

    NOTE: Comments may be submitted via SmartPlant®1

    Foundation (SPF), electronic file (with redlines and

    strikeouts), hard copy (mark-up), or e-mail.

    b. Provide review comments to Nuclear Safety Engineer responsible for safety basis amendment package, if applicable.

    3. Provide the safety basis amendment to the Safety Basis Change Review Board (SBCRB) administrator and request SBCRB review.

    4. Present safety basis amendment package to SBRCB and resolve comments.

    1 SmartPlant is a registered trademark of Intergraph Corporation d/b/a Hexagon Safety & Infrastructure,

    Madison, Alabama.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    6 of 21

    May 24, 2017

    5. Present safety basis amendment package briefing to Plant Review Committee (PRC) and resolve comments.

    NOTE: DSA changes resulting from negative USQ determinations shall not

    be submitted with Safety Basis amendments (i.e., e-mail drafts and official

    submittals) without prior ORP concurrence. DSA page changes with negative

    USQ determinations can either be incorporated into the DSA via separate

    release documents, or may be added to the release documents for DSA

    amendments approved by ORP, and put the ORP reviewers on distribution for

    the release.

    6. Forward e-mail draft of safety basis amendment package to the ORP.

    a. Arrange face-to-face discussions with the ORP technical staff for complex safety basis amendments, when required.

    7. Address ORP comments from the e-mail draft package, if applicable, by completing the following sub-steps:

    a. Coordinate resolution of ORP comments with impacted organization representatives.

    b. Revise amendment, if necessary.

    c. If amendment has been revised and requires an additional review, coordinate a review with the impacted organization

    representatives.

    d. Revise and finalize amendment, as appropriate.

    e. Repeat Section 4.1, Step 10, if necessary.

    f. Receive e-mail documentation from the ORP that all comments have been closed satisfactorily.

    Impacted

    Organization

    Representatives

    8. Revise documents used to develop safety basis amendment, as applicable, and obtain approval.

    9. If changes to the document results in a positive USQ, issue the document as part of the safety basis amendment implementation.

    Nuclear Safety

    Engineer

    10. Ensure that the official submittal package (with the amendment attached) is prepared in accordance with TFC-BSM-AD-C-03.

    WRPS Project

    Manager

    11. Approve and submit amendment to the ORP for approval.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    7 of 21

    May 24, 2017

    Nuclear Safety

    Engineer and

    Impacted

    Organization

    Representatives

    12. Upon receipt from the ORP, review safety evaluation report and approval letter with consideration for the following:

    Any directed changes or conditions of approval

    Safety evaluation report implementation date is consistent with date requested.

    WRPS Project

    Manager

    13. Notify the ORP if directed changes or conditions of approval cannot be implemented as specified in the safety evaluation report, or cannot

    be implemented in a timely manner.

    Nuclear Safety

    Engineer

    14. Coordinate resolution of ORP directed changes or conditions of approval, if applicable.

    15. Proceed to Section 4.6 for safety basis amendment implementation and closeout.

    Incorporation of Documented Safety Analyses Page Changes

    NOTE: DSA page changes processed per this section must be submitted to ORP in

    redline/strikeout format with the annual update processed per Section 4.4.

    This section describes the process for incorporating DSA page changes for which negative USQs

    have been determined.

    Nuclear Safety

    Engineer

    1. Consolidate outstanding update changes (e.g., DSA page changes associated with negative USQs) into individual safety bases sections

    and incorporate the changes into a redline/strikeout format.

    2. Verify that existing documents added to a DSA as references during incorporation of a negative USQ determination are not listed in

    RPP-27195.

    a. If the document is listed in RPP-27195, revise RPP-27195 to remove the document prior to incorporation of the DSA page

    change.

    3. IF the wording being incorporated is different from the wording attached to the negative USQ determination:

    a. IF the change is not an inconsequential change per TFC-ENG-SB-C-03, revise the USQ determination in

    accordance with TFC-ENG-SB-C-03 by attaching the actual

    incorporated page change to the USQ determination prior to

    incorporating the change.

    b. IF the change is an inconsequential change per TFC-ENG-SB-C-03, revise the DSA page change and

    document that GCX-2 was applied for the change (e.g., on the

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    8 of 21

    May 24, 2017

    document release form for the revised DSA) per

    TFC-ENG-SB-C-03 (Section 4.4, Step 1).

    4. Obtain peer review of safety basis update package by WRPS Nuclear Safety Engineer(s) who shall complete the following substeps:

    a. Review the change and complete the “Peer Review Checklist for Existing Safety Basis Documents” (DSA, TSRs,

    Addendum, JCO) form (A-6007-121).

    b. Provide review comments to Nuclear Safety Engineer responsible for safety basis update package, if applicable.

    Comments may be submitted via SPF, electronic file (with

    redlines and strikeouts), hard copy (mark-up), or e-mail.

    5. Proceed to Section 4.6 for safety basis update implementation and closeout.

    6. Include the safety basis update package within the annual update package as part of Section 4.4.

    Safety Basis Annual Update

    This section describes the process for developing the annual safety basis update. The annual

    safety basis update includes the following types of changes:

    Changes attached to negative USQ determinations;

    Editorial changes; and

    Changes to Chapter 1 and Chapters 6 through 17 of the DSA, as applicable.

    Nuclear Safety

    Manager

    1. Determine the need for the preparation of one of the following

    documents annually:

    Updated DSA for ORP approval or

    A letter to the ORP stating that there have been no changes in the DSA since the date of the previous annual safety basis

    update or letter. (7.1.1, 7.1.2)

    2. Designate a Nuclear Safety Engineer to coordinate the annual update

    or to develop the letter.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    9 of 21

    May 24, 2017

    Nuclear Safety

    Engineer

    3. Complete the following sub-steps if a “no changes” letter is being

    developed; otherwise proceed to Step 4.

    a. Prepare the letter.

    b. Ensure the letter for ORP submittal is processed in accordance with TFC-BSM-AD-C-03.

    c. Exit this procedure; no additional actions are required.

    NOTE: The annual safety basis update and annual USQ determination

    summary report developed per TFC-ENG-SB-C-03 require separate transmittal

    letters to ORP.

    4. Consolidate outstanding update changes (e.g., DSA page changes

    associated with negative USQs) into individual safety bases sections

    and incorporate the changes into a redline/strikeout format.

    5. IF the wording being incorporated is different from the wording

    attached to the negative USQ determination:

    a. IF the change is not an inconsequential change per TFC-ENG-SB-C-03, revise the USQ determination in accordance with

    TF-ENG-SB-C-03, or distinguish the change within the safety

    basis update package and submit the change to ORP for their

    approval if agreed to by ORP.

    b. IF the change is an inconsequential change per TFC-ENG-SB-C-03, revise the DSA page change and document that GCX-2

    was applied for the change (on the document release form for

    the revised DSA) per TFC-ENG-SB-C-03 (Section 4.4, Step

    1).

    6. Identify and include in the annual update any changes already

    implemented into the safety basis per Section 0.

    7. Review Chapter 1 and Chapters 6 through 17 of the DSA, to determine

    whether updates are required.

    a. If DSA changes are required, include in a USQ determination with DSA page changes or the safety basis annual update

    package if agreed to by ORP.

    8. Develop the safety basis update, including a summary of changes.

    9. Develop and include a list of negative USQ determinations with DSA

    page changes issued by March 31 (to meet the July 31 transmittal date)

    with the annual safety basis update package, and include safety basis

    change incorporation information (e.g., whether the page changes are

    incorporated, and the reasoning if not incorporated).

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    10 of 21

    May 24, 2017

    10. Obtain peer review of safety basis update package from WRPS

    Nuclear Safety Engineer(s) who shall complete the following sub-

    steps:

    a. Review the change and complete the “Peer Review Checklist for Existing Safety Basis Documents” (DSA, TSRs,

    Addendum, JCO) form (A-6007-121).

    b. Provide review comments to Nuclear Safety Engineer responsible for safety basis update package, if applicable.

    Comments may be submitted via SPF, electronic file (with

    redlines and strikeouts), hard copy (mark-up), or e-mail.

    Nuclear Safety

    Manager

    11. Determine if PRC review is required:

    a. If PRC review is not required, proceed to step 12.

    Nuclear Safety

    Engineer

    12. Present safety basis update package briefing to the PRC and resolve

    comments.

    13. Forward an e-mail draft of the safety basis update package to the ORP

    (e.g., by June 30 to meet the July 31 transmittal date).

    a. Arrange face-to-face discussions with the ORP technical staff for complex safety basis updates (or complex USQ

    determinations), when required.

    14. Resolve any comments received from the e-mail draft submittal.

    15. Receive e-mail documentation from the ORP that all comments have

    been closed satisfactorily.

    16. Ensure that the official submittal (with the annual safety basis update

    and summary attached) is prepared in accordance with

    TFC-BSM-AD-C-03.

    WRPS Project

    Manager

    17. Approve and submit the safety basis update to the ORP for approval

    by July 31 of each year.

    Nuclear Safety

    Engineer

    18. Upon receipt from the ORP, review the safety evaluation report and

    approval letter with consideration of any identified directed changes or

    conditions of approval.

    WRPS Project

    Manager

    19. Notify the ORP if directed changes or conditions of approval cannot

    be implemented as specified in the safety evaluation report, or cannot

    be implemented in a timely manner.

    Nuclear Safety

    Engineer

    20. Coordinate resolution of the ORP directed changes or conditions of

    approval, if applicable.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    11 of 21

    May 24, 2017

    21. Proceed to Section 4.6 for safety basis update implementation and

    closeout.

    Limited Duration Safety Basis Changes (Addenda, ESSs, and JCOs)

    This section describes the process for developing limited duration safety basis changes. Limited

    duration safety basis changes result from the design change process for non-permanent facility or

    document changes (i.e., for a short duration or “one-time” activity in the nuclear facility, allowing

    for an expedient removal of the change at the completion of the activity) (i.e., addenda), or from a

    discovery as a result of a positive USQ issue (i.e., JCO or ESS).

    NOTE: Per TFC-ENG-SB-C-03, an ESS providing a final evaluation of the problem and

    specifics of how the facility has been/will be within the DSA may be submitted in lieu of a JCO

    for positive USQs that can be promptly resolved (< 1 month), or the facility is in a TSR safe

    mode, and no controls other than operational restrictions are required.

    Line Management 1. Identify the need for a limited duration facility or document change.

    2. Request Production Operations; Single-Shell Tank Retrievals; Waste

    Treatment Plant Support; Tank Farm Projects; Chief Engineer;

    Environmental, Safety, Health, and Quality; and Project Integration

    Management review the proposed change for organizational impacts, as

    applicable.

    Impacted

    Organization

    Representatives

    3. Assist Line Management in the development of the change by

    completing the following sub-steps:

    a. Perform required analyses, evaluations, and calculations.

    b. Modify impacted documents (drawings, operating and administrative procedures, Functions and Requirements

    Evaluation Documents, Safety Requirement Evaluation

    Document, etc.).

    c. Identify potential training and qualification impacts.

    Line Management 4. Forward a description of the change to the Nuclear Safety Manager for

    processing.

    Nuclear Safety

    Manager

    5. Designate a Nuclear Safety Engineer or USQ Evaluator to coordinate

    development and process the change.

    Nuclear Safety

    Engineer/USQ

    Evaluator

    6. Review existing amendments, JCOs, ESSs, and addenda to determine if

    they are impacted by the proposed change. IF they are impacted,

    coordinate resolution of impacts and include within the scope of the

    change.

    7. Develop revision to DSA hazard analysis (e.g., RPP-15188), as

    applicable.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    12 of 21

    May 24, 2017

    8. IF a Process Hazard Analysis is required to evaluate the hazards or IF a

    new hazard entry is required to be made to the DSA hazard analysis,

    process in accordance with TFC-ENG-DESIGN-C-35 and

    TFC-ENG-DESIGN-C-47.

    9. Develop draft safety basis change package in accordance with

    Attachment A.

    10. IF upon application of the USQ process as outlined in

    TFC-ENG-SB-C-03, it is determined that the change does not require

    ORP approval, attach the safety basis change pages to the negative

    USQ and exit this procedure.

    NOTE: The following steps apply to DSA changes that require ORP approval

    prior to implementation (i.e., either the USQ determination performed in

    accordance with TFC-ENG-SB-C-03 shows a “positive” result, or the USQ

    was not conducted because the change is defined as requiring ORP approval,

    such as a TSR change).

    11. If the positive USQ from a PISA can be promptly resolved (

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    13 of 21

    May 24, 2017

    Impacted

    Organization

    Representatives

    15. Review the change by completing the following sub-steps:

    a. Review the change.

    b. Provide review comments, if applicable. Comments may be submitted by an electronic file (with redlines and strikeouts), a

    hard copy (mark-up), or via e-mail.

    16. Obtain peer review of documents used to support development of the

    safety basis addendum/JCO/ESS.

    Nuclear Safety

    Engineer

    17. Present safety basis addendum/JCO/ESS briefing to SBCRB and

    resolve comments.

    18. Present the safety basis addendum/JCO/ESS briefing to the PRC and

    resolve comments.

    19. Forward e-mail draft of safety basis addendum/JCO/ESS to the ORP.

    a. Arrange face-to-face discussions with the ORP technical staff for complex safety basis amendments, when required.

    20. Address ORP comments from the e-mail draft, if applicable, by

    completing the following sub-steps:

    a. Coordinate resolution of ORP comments with impacted organization representatives.

    b. Revise safety basis addendum/JCO/ESS, if necessary.

    c. If safety basis addendum/JCO/ESS has been revised and requires an additional review, coordinate a review with the

    impacted organization representatives.

    d. Revise and finalize safety basis addendum/JCO/ESS, as appropriate.

    e. Receive e-mail documentation from the ORP that all comments have been closed satisfactorily.

    Impacted

    Organization

    Representatives

    21. Revise documents used to develop safety basis addendum/JCO/ESS, as

    applicable, and obtain approval.

    22. If a change to the document results in a positive USQ, issue the

    document as part of the safety basis implementation.

    Nuclear Safety

    Engineer

    23. Ensure that the official submittal package (with the safety basis

    addendum/JCO/ESS attached) is prepared in accordance with

    TFC-BSM-AD-C-03.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    14 of 21

    May 24, 2017

    WRPS Project

    Manager

    24. Approve and submit safety basis addendum/JCO/ESS to the ORP for

    approval.

    Nuclear Safety

    Engineer and

    Impacted

    Organization

    Representatives

    25. Review safety evaluation report and approval letter, upon receipt from

    the ORP, with consideration for the following:

    Any directed changes or conditions of approval and

    Safety evaluation report implementation date is consistent with date requested.

    WRPS Project

    Manager

    26. Notify the ORP if directed changes or conditions of approval cannot be

    implemented as specified in the safety evaluation report, or cannot be

    implemented in a timely manner.

    Nuclear Safety

    Engineer

    27. Coordinate resolution of the ORP directed changes or conditions of

    approval, if applicable.

    28. Proceed to Section 4.6 for safety basis implementation and closeout.

    4.6 Safety Basis Implementation and Closeout

    This section describes the release, processing, and closeout of approved safety basis changes.

    Nuclear Safety

    Engineer

    1. Ensure ORP approved safety evaluation report is posted on the WRPS Safety Basis Website on the Hanford Intranet, if applicable.

    2. Develop a safety basis bulletin with consideration of any directed actions or conditions of approval in the safety evaluation report and

    approval letter and how they relate to the USQ process.

    3. Ensure the safety basis bulletin is posted on the WRPS Safety Basis Website on the Hanford Intranet.

    Safety Basis

    Compliance Officer

    4. Process change implementation in accordance with TFC-OPS-OPER-C-02, if applicable.

    5. Notify the Nuclear Safety Manager when ready to make DSA amendment effective.

    Technical

    Writer/Editor

    6. As part of safety basis implementation, incorporate the safety basis amendment, update pages, or addendum into the safety basis for

    release.

    NOTE: Technical reviews have previously been performed so the purpose of

    the final check in the following step is to verify that the safety basis

    amendment/addendum page changes are consistent with those approved by

    ORP or the safety basis update page changes are consistent with those in the

    associated negative USQ determinations and to verify that all the associated

    paperwork is in order.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    15 of 21

    May 24, 2017

    Nuclear Safety

    Engineers

    7. For safety basis amendments, safety basis updates, or addendums, complete the following sub-steps:

    a. Prepare release paperwork in accordance with TFC-ENG-DESIGN-C-25 and TFC-ENG-DESIGN-C-06.

    b. Check release paperwork per TFC-ENG-DESIGN-C-52 and TFC-ENG-DESIGN-P-54.

    Technical

    Writer/Editor and

    USQ Coordinator

    8. After implementation, complete the following sub-steps:

    a. Validate the distribution list for the safety basis revision and submit the approved document to a Document Service Center

    for controlled copy release on the first work day following the

    activity.

    b. Ensure safety basis record copies are updated and consistent with documentation requirements.

    c. Ensure the WRPS Safety Basis Website on the Hanford Intranet is updated with the new revision.

    Nuclear Safety

    Engineer

    9. For JCOs/ESSs, check the JCO/ESS to ensure text is consistent with that approved by ORP.

    Technical

    Writer/Editor or

    USQ Coordinator

    10. Ensure the JCO/ESS is posted on the appropriate WRPS Safety Basis Website on the Hanford Intranet.

    5.0 DEFINITIONS

    Safety Basis Amendment. A safety basis change that requires approval from the ORP prior to

    implementation. TSR changes are categorized as amendments.

    Safety Basis Update. A safety basis change that does not require approval from the ORP prior to

    implementation. Safety basis updates are submitted to the ORP on an annual basis for approval.

    6.0 RECORDS

    The following records are generated during the performance of the procedure:

    222-S Laboratory Documented Safety Analysis (HNF-12125)

    222-S Laboratory Technical Safety Requirements (HNF-14733)

    242-A Evaporator Documented Safety Analysis (HNF-14755)

    242-A Evaporator Technical Safety Requirements (HNF-15279)

    Tank Farms Documented Safety Analysis (RPP-13033), and

    Tank Farms Technical Safety Requirements (HNF-SD-WM-TSR-006).

    The records custodian identified in the Company Level Records Inventory and Disposition

    Schedule (RIDS) is responsible for record retention in accordance with TFC-BSM-IRM_DC-C-

    02, “Records Management.”

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    16 of 21

    May 24, 2017

    7.0 SOURCES

    Requirements

    1. 10 CFR 830, “Nuclear Safety Management,” Subpart B, “Safety Basis Requirements,” Section 830.202, “Safety basis.”

    2. DOE G 421.1-2, “Implementation Guide for Use in Developing Documented Safety Analyses to Meet Subpart B of 10 CFR 830.”

    3. DOE G 423.1-1, “Implementation Guide for Use in Developing Technical Safety Requirements.”

    4. DOE G 424.1-1B, Chg 1 (March 20, 2013), “Implementation Guide For Use In Addressing Unreviewed Safety Question Requirements.”

    5. DOE-STD-1186-2004, “DOE Standard – Specific Administrative Controls.”

    6. DOE-STD-1189-2008, “DOE Standard – Integration of Safety into the Design Process.”

    7. DOE-STD-3009-94, Change Notice No. 3, “DOE Standard – Preparation Guide for U.S. Department of Energy Nonreactor Nuclear Facility Documented Safety Analyses.”

    References

    1. HNF-SD-WM-TSR-006, “Tank Farms Technical Safety Requirements.”

    2. RPP-13033, “Tank Farms Documented Safety Analysis.”

    3. RPP-15188, “Hazard Analysis Database Report.”

    4. RPP-27195, “Tank Operations Contractor Unreviewed Safety Question Process Out of Scope Documents and Facilities.”

    5. RPP-48900, “242-A Evaporator Hazard Evaluation Database Report.”

    4. TFC-BSM-AD-C-03, “Correspondence Preparation and Control.”

    5. TFC-BSM-IRM_DC-C-02, “Records Management.”

    6. TFC-ENG-DESIGN-C-06, “Engineering Change Control.”

    7. TFC-ENG-DESIGN-C-10, “Engineering Calculations.”

    8. TFC-ENG-DESIGN-C-25, “Technical Document Control.”

    9. TFC-ENG-DESIGN-C-35, “Process Hazard Analysis Determination and Technique Screening.”

    10. TFC-ENG-DESIGN-C-47, “Process Hazard Analysis.”

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    17 of 21

    May 24, 2017

    11. TFC-ENG-DESIGN-C-52, “Technical Reviews”

    12. TFC-ENG-DESIGN-P-54, “Checking of Engineering Documents.”

    13. TFC-ENG-SB-C-03, “Unreviewed Safety Question Process.”

    14. TFC-ENG-SB-C-06, “Safety Basis Development.”

    15. TFC-OPS-OPER-C-02, “Safety Basis Implementation Checklist Preparation, Review, and Approval.”

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    18 of 21

    May 24, 2017

    ATTACHMENT A – GUIDANCE FOR LIMITED DURATION CHANGES

    Limited duration safety basis changes may be processed as a Justification for Continued Operation (JCO)

    or an Evaluation of the Safety of the Situation (ESS), (if part of a discovery from the Unreviewed Safety

    Question [USQ] process), or as an addendum for a limited duration planned activity. (7.1.1, 7.1.2, 7.1.3, 7.1.4)

    The ESS for a positive or negative USQ should include the following information:

    Title

    Description of occurrence or discovery and any immediate compensatory actions taken (i.e., operational restrictions).

    Date PISA was discovered and ORPS report number.

    Results of immediate safety assessment (including discussion of probability and consequence risk factors) and of USQD (positive/negative). Reference relevant

    documents.

    Results of any subsequent safety analysis developed to further support conclusions as to safety of the facility with and/or without operational restrictions/compensatory measures.

    Path forward. Discuss if additional work is to be performed to resolve the issue, and anticipated completion date.

    The ESS for a positive USQ should include the following additional information:

    Current operational status of the facility.

    Clear identification of all operational restrictions needed to maintain the facility in a safe condition.

    Analysis that addresses the safety impact of the PISA with the operational restrictions removed (or with the operational restrictions in place if their removal is not proposed).

    Path forward for restoring the facility into compliance with the DSA (e.g., by revising the DSA or by correcting the discrepant condition).

    Summary of recommendations and conclusions.

    The limited JCO and addendum duration change should include the following information, or address

    why it is not necessary.

    1.0 PURPOSE

    The purpose of a JCO limited duration change is to document the bases for continuing to operate

    facilities on a limited duration basis before the resolution of a condition that is outside of the

    approved safety basis, or to permit resumption of activities that were suspended when the

    condition that is outside the approved safety basis was declared. Include a brief summary of the

    issue and the reason that the limited duration change is being written. Cite the ESS that transmits

    or precedes the JCO, as applicable. The summary should contain a history of the problem.

    Specify the condition and/or date of the JCO change closure. For example:

    The safety basis amendment to be approved by the U.S. Department of Energy (DOE) Office of River Protection (ORP).

    The condition that initiated the USQ or JCO change that must be resolved.

    The anticipated duration of the limited duration JCO change.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    19 of 21

    May 24, 2017

    ATTACHMENT A – GUIDANCE FOR LIMITED DURATION CHANGES (cont.)

    The purpose of a limited duration addendum change is to consolidate the hazard and accident

    analyses, and required additional controls (if any) for a temporary change to the nuclear facility

    (i.e., temporary equipment change or operational activity) and to facilitate the removal of the

    change when the equipment is restored to its original condition or the operational activity is

    completed.

    For the addendum, specify:

    The equipment modification and/or operational activity to be approved by the ORP and

    The anticipated duration of the limited duration addendum change.

    NOTE: Limited duration changes are temporary until the activity is completed and the addendum

    is canceled.

    2.0 SCOPE

    Define the bounds of applicability. Define the projects, facilities, and any specific areas or

    operations contained therein that are covered under the scope of the subject limited duration

    change.

    Include for the JCO, as necessary, a brief discussion of the safety impact of the nonconforming or

    degraded condition (e.g., noncompliance with the Tank Farms Technical Safety Requirements

    [TSR] [HNF-SD-WM-TSR-006,]) or regulatory noncompliance, relative to the capability of the

    facility to be operated in accordance with the current safety basis.

    Include for the addendum, as necessary, a brief discussion of the mission impact of the temporary

    equipment modification and/or operational activity (e.g., necessity of new technology retrieval

    activity for tank waste conditions).

    3.0 PROPOSED COMPENSATORY MEASURES

    Define the allowed operating conditions and the limited duration restrictions and controls

    imposed as requirements of the limited duration change to ensure acceptable safety risk based on

    the best available information, analysis, and engineering judgment, including:

    For the JCO ‒

    A list of terminated operations and/or specific criteria for identifying terminated operations;

    Prohibitions against the performance of activities;

    Limitations on the uses of the JCO change to authorize additional work or activities;

    The scope of activities that will be allowed to continue under the control of the JCO change;

    The credited purpose for each compensatory measure;

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    20 of 21

    May 24, 2017

    ATTACHMENT A – GUIDANCE FOR LIMITED DURATION CHANGES (cont.)

    The method for implementing and controlling (tracking) compensatory measures; and

    Controls in the form of compensatory measures (i.e., administrative, physical, or procedural controls).

    NOTE: Compensatory measures should be written in accordance with the format of

    Code of Federal Regulations (CFR) 10 CFR 830, Subpart B, “Safety Basis

    Requirements,” Section 830.202, “Safety basis”; DOE G 421.1-2, “Implementation

    Guide for Use in Developing Documented Safety Analyses to Meet Subpart B of 10 CFR

    830”; DOE G 423.1-1, “Implementation Guide for Use in Developing Technical Safety

    Requirements”; DOE-STD-3009-94, “DOE Standard – Preparation Guide for

    U.S. Department of Energy Nonreactor Nuclear Facility Documented Safety Analyses”;

    DOE STD-1186-2004, “DOE Standard – Specific Administrative Controls”; and

    DOE-STD-1189-2008, “DOE Standard – Integration of Safety into the Design Process”

    as a Limiting Condition for Operation (LCO) or Administrative Control (AC), as

    appropriate. This should include a description of potential conditions, required actions,

    completion times, and surveillances, as necessary. The bases for the required actions

    should be provided. (7.1.1, 7.1.2, 7.1.3, 7.1.5, 7.1.6, 7.1.7)

    For the Addendum ‒

    A list of equipment modifications and/or operational activities to be authorized within the scope of the addendum;

    Prohibitions against the performance of activities, if applicable;

    Limitations on the uses of the addendum to authorize additional work or activities; and

    Any additional or modified controls required to conduct the activities outlined in the addendum.

    Compensatory measures should be written in accordance with the format of 10 CFR 830,

    Subpart B; DOE G 421.1-2; DOE G 423.1-1; DOE-STD-3009-94; DOE STD-1186-2004; and

    DOE-STD-1189-2008 as an LCO or AC, as appropriate. This should include a description of

    potential conditions, required actions, completion times, and surveillances, as necessary. The

    bases for the required actions should be provided. (7.1.1, 7.1.2, 7.1.3, 7.1.5, 7.1.6, 7.1.7)

    4.0 TECHNICAL JUSTIFICATION

    Provide the technical justification and basis for approval of the risk for the allowed operations

    and controls imposed by this limited duration change. That is:

    Discuss why approval of the limited duration change is necessary and

    Discuss why the risk of the limited duration change is acceptable.

  • ENGINEERING

    SAFETY BASIS ISSUANCE AND

    MAINTENANCE

    Document

    Page

    Issue Date

    TFC-ENG-SB-C-01, REV F-1

    21 of 21

    May 24, 2017

    ATTACHMENT A – GUIDANCE FOR LIMITED DURATION CHANGES (cont.)

    Risk discussions should be quantified using a method consistent with the current safety basis. As

    appropriate:

    Provide an estimate of the risk associated with continued normal operation after identification of the USQ (applicable to JCOs). (Reference the applicable hazard

    analysis.)

    Provide an estimate of the risk associated with the limited duration operation upon implementing the proposed limited duration controls. (Reference the applicable hazard

    analysis.)

    The justification should describe how the existing facility hazard controls/restrictions, in

    conjunction with additional limited duration controls/restrictions, would maintain safe conditions

    during the proposed continued operation.

    If a USQ determination is not associated with the limited duration change, provide supporting

    analysis to quantitatively or qualitatively identify the increase in risk that the ORP is requested to

    approve.

    The USQ determination questions should be used as guidance. Discussion should be provided for

    those questions that would be answered “Yes.”

    The justification should describe any special conditions or time constraints that pertain to the

    operation of the facility.


Recommended