+ All Categories
Home > Documents > The Capital Grid Project - storage.googleapis.com · multiple pathways of power supply to ......

The Capital Grid Project - storage.googleapis.com · multiple pathways of power supply to ......

Date post: 09-Sep-2018
Category:
Upload: dotuyen
View: 214 times
Download: 0 times
Share this document with a friend
31
The Capital Grid Project: Building Tomorrow’s Energy Grid Today October 2, 2017 Lamond- Riggs Citizens Association
Transcript

The Capital Grid Project:

Building Tomorrow’s Energy Grid Today

October 2, 2017

Lamond- Riggs Citizens Association

2

Agenda

Welcome

How Safe, Clean, and Affordable Energy is Delivered

Our Current System

The Need: Enhancing Reliability and Resiliency

The Capital Grid Project Overview

• Building a Networked System

• Constructing a New Substation

• Upgrading and Replacing Aging Infrastructure

Capital Grid Project Benefits

Next Steps

3

How Energy is Delivered to You

4

The Current System

Since retiring generation facilities in

the District, we rely on the

transmission system to deliver

energy produced outside of the city

All of the energy supplied to the

District is imported from outside of

the city via radial or point-to-point

transmission lines

Four corridors of transmission lines

are supplying energy to the Capital

area, including Prince George’s and

Montgomery Counties

Entire areas of the Capital area are

currently fed by single pathways of

electric supply, which can lead to

outages if a pathway is temporarily

lost

The loss of any one of these

corridors could take several days to

several weeks to restore

This map animation is for illustration purposes only and does not reflect exact corridor locations or service area.

The Current System

The loss of any one of these four corridors could result in a significant loss of load, and could take as much as several days or even several weeks to repair, depending on the nature of the damage

6

The Need: Enhancing Reliability and Resiliency

Reliability and resiliency of the electric system are essential to:

• Prevent service disruptions through infrastructure and equipment

upgrades, underground transmission lines and state-of-the-art substation

designs

• Respond quickly to disruptions when they occur by rerouting power

through integrated, alternate pathways

Disruptions to a power path usually happen due to:

• A storm or other weather-related event

• A failure due to aging infrastructure or underground equipment

• An event related to increased demand from new commercial and mixed-

use development

• Intentional or unintentional physical damage to overhead facilities, such

as vandalism or a vehicle accident

7

The Solution: A Forward-Looking Plan

The Capital Grid project will solve a number of current needs with

one integrated solution by:

• Building a networked system of substations by installing approximately

10 miles of new underground transmission cable

• Constructing a new substation to meet increasing demand in

neighborhoods experiencing rapid growth

• Upgrading and replacing aging infrastructure and equipment to

enhance reliability

Building a

Networked

System

9

Building a Networked System:

Improving Reliability and Resiliency

The Capital Grid project will create

multiple pathways of power supply to

connect multiple substations in the

Capital area with higher electrical load

capacity

The project proposes a “networked

system” to deliver electricity faster to

areas experiencing an outage and

lessen the impact from severe weather

or other unexpected events

Networking the Capital area electric

system will create a more reliable and

resilient grid to provide capacity

expansion to support demand

10

The Capital Grid Project: 10-Mile

Transmission Route

CHAMPLAIN SUBSTATION *

HARVARD SUBSTATION *

MT. VERNON SUBSTATION *

WATERFRONT SUBSTATION *

TAKOMA SUBSTATION *

T STREET NW

4TH

STR

EET

NW

11

Ward 4 - Overview

* TAKOMA SUBSTATION

HARVARD SUBSTATION *

Ward 4 – Zoomed In

Ward 4 – Zoomed In (Cont’d)

Ward 4 – Zoomed In (Cont’d)

Ward 4 – Zoomed In (Cont’d)

Ward 4 – Spring/Summer 2018

Spring/Summer 2018 - 1 location

0.45 miles of civil construction

Civil Construction

• Temporary Traffic Control

• Closure of 2 lanes

• Trenching

• Temporary Steel Plates

• Installation of ductbank

• Installation of manholes

• Backfilling

• Temporary Restoration

• Permanent Restoration

* TAKOMA SUBSTATION

HARVARD SUBSTATION *

Ward 4 – Fall 2018/Winter 2019

Fall 2018/Winter 2019 - 2 locations

0.9 miles of civil construction

Civil Construction

• Temporary Traffic Control

• Closure of 2 lanes

• Trenching

• Temporary Steel Plates

• Installation of ductbank

• Installation of manholes

• Backfilling

• Temporary Restoration

• Permanent Restoration

* TAKOMA SUBSTATION

HARVARD SUBSTATION *

Ward 4 – Spring/Summer 2019

Spring/Summer 2019 - 1 location

0.45 miles of civil construction

Civil Construction

• Temporary Traffic Control

• Closure of 2 lanes

• Trenching

• Temporary Steel Plates

• Installation of ductbank

• Installation of manholes

• Backfilling

• Temporary Restoration

• Permanent Restoration

Electrical Construction • Work occurs at manhole locations throughout route

• Temporary Traffic Control at manhole locations

• Pulling and Installation of Cable

• Splicing of Cable

* TAKOMA SUBSTATION

HARVARD SUBSTATION *

Ward 4 – Fall 2019/Winter 2020

Fall 2019/Winter 2020 - 1 location

0.45 miles of civil construction

Civil Construction

• Temporary Traffic Control

• Closure of 2 lanes

• Trenching

• Temporary Steel Plates

• Installation of ductbank

• Installation of manholes

• Backfilling

• Temporary Restoration

• Permanent Restoration

Electrical Construction • Work occurs at manhole locations throughout route

• Temporary Traffic Control at manhole locations

• Pulling and Installation of Cable

• Splicing of Cable

* TAKOMA SUBSTATION

HARVARD SUBSTATION *

Ward 4 – Spring/ Summer 2020

Spring/Summer 2020 - 1 location

0.45 miles of civil construction

Civil Construction

• Temporary Traffic Control

• Closure of 2 lanes

• Trenching

• Temporary Steel Plates

• Installation of ductbank

• Installation of manholes

• Backfilling

• Temporary Restoration

• Permanent Restoration

Electrical Construction • Work occurs at manhole locations throughout route

• Temporary Traffic Control at manhole locations

• Pulling and Installation of Cable

• Splicing of Cable

* TAKOMA SUBSTATION

HARVARD SUBSTATION *

Ward 4 – Completed Construction – Spring 2021

• 2018 - 2 Crews1

• 0.9 miles of construction

• 2019 - 1 Crew1

• 1.1 miles of construction

• 2020 – 1 Crew1

• 0.7 miles of construction

Assumptions: 20 Linear feet per day Two crews mobilized at different

locations along route Sometimes only 1 crew in Ward 4 3-5 members per crew

1 - Assumptions based on preliminary design and previous projects. Actual durations and number of crews subject to change upon award of contract to contractor

* TAKOMA SUBSTATION

HARVARD SUBSTATION *

Upgrading Aging

Infrastructure

23

Upgrading Aging Infrastructure

Upgraded equipment and infrastructure will include higher capacity transformers and feeders to relieve other substations, which are expected to reach their maximum capacity within the next few years

Takoma Substation Harvard Substation Champlain Substation

Built in 1932

Planned Work:

Upgrade existing

substation

Built in 1930

Planned Work:

Rebuild and upgrade

existing substation

Built in 1907

Planned Work:

Rebuild and upgrade

on existing

substation site

Addressing

Capacity Needs

25

Constructing a New Substation:

Mount Vernon Substation

Mount Vernon Triangle,

Northwest One, Shaw, NoMa and

surrounding areas are

experiencing residential and

commercial growth:

• More than 22,700 residential

units and over 16.6 million

square feet of retail and

office space is completed or

in progress

This growth places increasingly

heavier demands on the electric

grid

Meeting this demand requires

new infrastructure, like the

proposed Mount Vernon

Substation

Project Benefits

The Capital Grid project is supporting the

District of Columbia Renewable Portfolio

Standard Expansion Amendment Act of

2016, which strives to increase the District’s

renewable portfolio by 50% by 2032

The Capital Grid project supports this

initiative by modernizing the system so that

it can accommodate more solar

connections to the grid, ultimately we will

accommodate more customers who want to

sell power back into the grid

By increasing transmission and substation

capacity, the Capital Grid project will

increase the electric system hosting

capacity for accommodating more

customer-generated power by up to 150

MW (about 30,000 home rooftop

installations)

The Capital Grid Project:

Renewable Energy Benefits

10

28

The Capital Grid Project:

Economic Benefits

The proposed Capital Grid project will

support the local economy by:

• Expanding and increasing procurement

opportunities for local minority, women, veteran,

and disabled contractors as well as *CBE

subcontractors for good-paying technical jobs and

contracts

• Supporting economic development and new

residential and business growth by establishing a

strong, dynamic grid

*Certified Business Enterprises in the District

Timeline &

Next Steps

The Review Process

As a regulated company, our proposal must be

reviewed and approved before construction may

begin

The Public Service Commission of the District of

Columbia (DC PSC) will examine our proposed

plan in the form of two formal filings

The DC PSC will provide opportunity for

community feedback and evaluate the safety,

need and reasonableness of our proposal before

making a decision

The District of Columbia Board of Zoning

Adjustment (BZA) will also review the proposed

Capital Grid Project plan

31

Stakeholder Outreach

We are committed to:

Creating awareness among our local and federal partners

Maintaining a close working relationship with residents and businesses

through all project phases

Receiving input from affected neighbors through charrettes, community

meetings and presentations

Providing project information and updates regarding the regulatory review

process and construction locations and hours

Sharing information via project website, listservs, etc.

• Online: www.pepco.com/CapitalGrid

• Email: [email protected]

• Social Media: Use #CapGrid on Twitter and Facebook

• Community meetings


Recommended