+ All Categories
Home > Documents > The Changing Electricity Sector - MILE

The Changing Electricity Sector - MILE

Date post: 23-Mar-2022
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
10
The Changing Electricity Sector CONTENTS Introduction Potential for Distributed Generation Impacts of Distributed Generation Potential for Residential Roof Top Solar PV Payback Period Calculation Derived for Roof Top PV Case Study of Bisasar Road Landfill gas to electricity project Conclusion Sanjeeth Sewchurran. Pr Eng (eThekwini Electricity, UKZN)
Transcript

The Changing Electricity Sector

CONTENTS

Introduction

Potential for Distributed Generation

Impacts of Distributed Generation

Potential for Residential Roof Top

Solar PV

Payback Period Calculation

Derived for Roof Top PV

Case Study of Bisasar Road

Landfill gas to electricity project

Conclusion

Sanjeeth Sewchurran. Pr Eng (eThekwini Electricity, UKZN)

Under – frequency load shedding, rising electricity tariffs, changing environment regulations and delays in constructing new power stations have plunged South Africa into one of its greatest challenges ever in the electricity sector.

This has lead consumers and producers alike to start

exploring various local renewable energy generation options namely distributed generation.

eThekwini Electricity is however faced with various

concerns with understanding the impact of distributed generation on the existing distribution networks.

Electricity Shortage

Residential electricity tariffs have increased by an average of 14.5% over the past 7 years

Solar Photo Voltaic (PV) (residential, commercial, industrial, solar farms)

Landfill gas to electricity (DSW, private landfills) Hydro Electricity (inlet to water reservoirs, aqueduct

pipelines) Waste Water treatment works (extract bio gas and

use for generation of electricity) Co – generation from existing processes (utilize excess

steam to generate electricity - Tongaat Hullets, NCP Alcohols)

SA is blessed with good climatic conditions

Bi – directional power flow Impact of network power quality Impact on network planning Impact on network losses Impact on network protection Metering Fault Levels Efficiency Reduce emission and pollutant Increase or reduce network congestion Network voltage profiles Power flow and control Impact Municipal revenue

Two Feasibility Scenarios With no payment for exported energy With avoided cost payment for exported energy

Three Usage Scenarios

50% generated electricity usage 75% generated electricity usage 100% generated electricity usage

Payback Period – With/Without Feed in Tariff

Tariff Increase Scenario 50% Usage 75% Usage 100 % Usage

Low (8%) >10 years –

10 years

9 years –

9 years

8 years

unchanged

Medium (11.5%) >10 Years –

9 years

9 years –

8 years

7 years

unchanged

High (14.5%) 10 years –

8 years

8 years –

7 years

7 years

unchanged

Three Electricity Tariff Increase Scenarios Low (8%) (MYPD 3 – Eskom) Medium (11.5%) High (14.5%) (Past 7 Year average)

Description Symbol

Total Capital Cost of Installation TCOI

Export Tariff ET

Total kWh generated from system over a period of one year TKWG

Average Annual Percentage increase in tariff PI

Percentage electricity utilised by the consumer from the PV system PU

Number of years N

Percentage interest rate of loan obtained for installation M

Total number of years i

Annual percentage degradation in output PD

Factor for different orientation and inclination rooftop PV installations K

Import Tariff IT

Annual Maintenance and Repair Costs AMARC

Subsidy Value SV

The equation can be easily simplified as follows:

Term B = 0, if the utility does not offer any compensation

scheme for electricity exported to the grid such as a

generation export tariff or REFIT.

Term C can be simplified to C = TCOI, if no loan was

taken for the purchase and installation of the PV system.

Term D = 0, if there is no incentive or subsidy scheme

offered by the utility or country.

Term E = 0, if there is no maintenance costs or costs

incurred to replace damaged panels and inverters.

From (1), it can be seen that there are a number of

factors that can influence the payback period of rooftop

PV.

Savings from electricity

not purchased from the

grid

Revenue from electricity

exported to the grid

Total cost of installation

including interest paid

on loan

Connaught Major 33/11 kV

Substation

Landfill

Generation

Plant

Quarry/Kennedy

Pumps DSS

Alpine &

Quarry DSS

6 MVA

6 MVA

8 MVA

Electricity

Department

DSS

1/5 Intersite

Avenue DSS

Rise in single and

three phase fault

levels

Impact of

voltage with

varying in

Power Factor

Off Peak Voltage

Rise

Cable loading

exceeding

thermal

capacity of

cable

The electricity sector is changing. There is large potential in eThekwini and South Africa for the

implementation of distributed generation projects. The feasibility of roof top PV is expected to increase drastically

when the payback period reduces to 5 years and below. The current residential electricity tariffs need to be revised to

accommodate a fixed charge for network usage to ensure that Municipal revenue is not lost with the increase in roof top PV uptake.

The case study carried out indicates that there is potential

negative impacts to the local distribution networks if proper studies and not carried out prior to the implementation of these projects.

The End

Thank You

Comments & Questions???


Recommended