Document/Plan Regulation/Plan No
Doc number
Date Submitted to
PINS
APPLICATION DOCUMENTS
1. Application Form Etc.
Application Form
Reg 5(1) 1.1 29 August 2014
Letter to accompany application
1.2 29 August 2014
Newspaper Notices (s48)
1.3 29 August 2014
Applicant’s s.55 Checklist
1.4 29 August 2014
NSIP Plans
Reg 5(2)(o) 1.5 29 August 2014
Highway NSIP Component Plans
Reg 5(2)(o) 1.5A 10 November 2014
Document List
1.6 29 August 2014
Document List – 10.11.14
1.6A 10 November 2014
Document List – 19.12.14
1.6B 19 December 2014
Document List – 06.03.15
1.6C 06 March 2015
Document List – 19.06.15 1.6D
19 June 2015
2. Plans /Drawings/Sections
Land Plans
Key Plan Sheet 1 Sheet 2 Sheet 3 Sheet 4 Sheet 5 Sheet 6
Reg 5(2)(i) BWB/NTH/209/142-01 P5 BWB/NTH/209/142-02 P13 BWB/NTH/209/142-03 P14 BWB/NTH/209/142-04 P8 BWB/NTH/209/142-05 P9 BWB/NTH/209/142-06 P10 BWB/NTH/209/142-07 P9
2.1 2.1A 2.1B 2.1C 2.1D 2.1E 2.1F
29 August 2014 19 December 2014 19 December 2014 29 August 2014 29 August 2014 19 December 2014 19 December 2014
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
2
Works Plans
Key Plan Sheet 1 Sheet 2 Sheet 3 Sheet 4 Sheet 5 Sheet 6
Reg 5(2)(j) BWB/NTH/209/140-01 P9
BWB/NTH/209/140-02 P11 BWB/NTH/209/140-03 P11 BWB/NTH/209/140-04 P11 BWB/NTH/209/140-05 P11 BWB/NTH/209/140-06 P11 BWB/NTH/209/140-07 P11
2.2 2.2A 2.2B 2.2C 2.2D 2.2E 2.2F
29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014
Access and Rights of Way Plans
Key Plan Sheet 1 Sheet 2 Sheet 3 Sheet 4 Sheet 5 Sheet 6
Reg 5(2)(k) BWB/NTH/209/144-01 P2 BWB/NTH/209/144-02 P5 BWB/NTH/209/144-03 P4 BWB/NTH/209/144-04 P4 BWB/NTH/209/144-05 P3 BWB/NTH/209/144-06 P4 BWB/NTH/209/144-07 P6
2.3 2.3A 2.3B 2.3C 2.3D 2.3E 2.3F
29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014
Reg 6 (2) Plans and Drawings Key Plan General Arrangement - Sheet 1 General Arrangement – Sheet 2 General Arrangement – Sheet 3 General Arrangement – Sheet 4 Longitudinal Sections - Sheet 1 Longitudinal Sections – Sheet 2 Longitudinal Sections – Sheet 3 Cross Sections – Sheet 1 Cross Sections – Sheet 2
Reg 5 (2) (p) and Reg 6(2) BWB/NTH/209/100-00 P3 BWB/NTH/209/100-01 P5 BWB/NTH/209/100-02 P4 BWB/NTH/209/100-03 P7 BWB/NTH/209/100-04 P4 BWB/NTH/209/101-01 P3 BWB/NTH/209/101-03 P4 BWB/NTH/209/101-04 P3 BWB/NTH/209/102-01 P3 BWB/NTH/209/102-02 P3
2.4 2.4A 2.4B 2.4C 2.4D 2.4E 2.4F 2.4G 2.4H 2.4J
29 August 2014 19 December 2014 29 August 2014 06 March 2015 29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
3
Cross Sections – Sheet 3 Cross Sections – Sheet 4 Cross Sections – Sheet 5 Drainage outfall details
BWB/NTH/209/102-03 P3 BWB/NTH/209/102-04 P3 BWB/NTH/209/102-05 P3 BWB/NTH/209/103 P2
2.4K 2.4L 2.4M 2.4N
29 August 2014 29 August 2014 29 August 2014 29 August 2014
Highway Classifications Plans
Key Plan Sheet 1 Sheet 2
Reg 5(2)(o) BWB/NTH/209/141-01 P4 BWB/NTH/209/141-02 P8 BWB/NTH/209/141-03 P6
2.5 2.5A 2.5B
29 August 2014 29 August 2014 29 August 2014
Traffic Regulation Plans
Key Plan Sheet 1 Sheet 2 Sheet 3 Sheet 4
Reg 5(2)(o) BWB/NTH/209/145-08 P3 BWB/NTH/209/145-04 P4 BWB/NTH/209/145-05 P5 BWB/NTH/209/145-06 P4 BWB/NTH/209/145-07 P4
2.6 2.6A 2.6B 2.6C 2.6D
29 August 2014 29 August 2014 06 March 2015 29 August 2014 29 August 2014
Speed Limits Plans
Key Plan Sheet 1 Sheet 2
Reg 5(2)(o) BWB/NTH/209/145-01 P4 BWB/NTH/209/145-02 P5 BWB/NTH/209/145-03 P4
2.7 2.7A 2.7B
29 August 2014 29 August 2014 29 August 2014
Crown Land Plans Highways England Manorial Rights Plan Highways England Land subject to Manorial Rights Key Plan Sheet 1 Sheet 2 Sheet 3
Reg 5 (2)(in) BWB/NTH/209/143-01 P4 BWB/NTH/209/143-01 P3 BWB/NTH/209/143-02 P8 BWB/NTH/209/143-03 P2 BWB/NTH/209/143-04 P3
2.8 2.8 2.8A 2.8B 2.8C
19 June 2015 29 August 2014 19 December 2014 29 August 2014 29 August 2014
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
4
Location Plan
Reg 5(2)(o) BWB/NTH/209/104 P3
2.9
29 August 2014
Parameters Plan
Key Layout Sheet 1 Sheet 2 Sheet 3
Reg 5(2)(o) 3899-038 P32 3899-038 P32 3899-038 P32 3899-038 P32
2.10 2.10A 2.10B 2.10C
10 November 2014 10 November 2014 10 November 2014 10 November 2014
Illustrative Masterplan
Sheet 1 Sheet 2 Sheet 3
Reg 5(2)(o) 3252-L-03 G 3252-L-16 3252-L-17 3252-L-18
2.11 2.11a 2.11b 2.11c
29 August 2014 29 August 2014 29 August 2014 29 August 2014
Illustrative Rail Interchange Drawings
Layout Plan Container Distribution Flow Intermodal Layout
Reg 5(2)(o) 3899-053 P7 3899-052 P7 3899-051 P7
2.12A 2.12B 2.12C
29 August 2014 29 August 2014 29 August 2014
Highways Works Components Plans Key Plan
Sheet 1 Sheet 2 Sheet 3
Reg 5(2)(o) BWB/NTH/209/146–01 P4 BWB/NTH/209/146–02 P4 BWB/NTH/209/146–03 P4 BWB/NTH/209/146–04 P4
2.13 2.13a 2.13b 2.13c
29 August 2014 29 August 2014 29 August 2014 29 August 2014
Ecology and Landscape Plans
Reg 5(2)(l)
In Chapters 5 and 6 of the ES
29 August 2014
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
5
Heritage Plans and Assessment
Reg 5(2)(m)
In Chapter 11 of the ES
29 August 2014
Ease of reference A3 plan bundle
Reg 5(2)(o)
2.14
29 August 2014
3. Draft Development Order
Draft Development Consent Order (including requirements)
Reg 5(2)(b)
3.1
29 August 2014
Draft Development Consent Order (including requirements) (Tracked and Clean)
Reg 5(2)(b)
3.1A
19 December 2014
Draft Development Consent Order (including requirements) (Tracked and Clean)
Reg 5 (2)(b) 3.1B 06 March 2015
Draft Development Consent Order (including requirements) (Tracked and Clean)
Reg 5 (2)(b)
3.1C
19 June 2015
Explanatory Memorandum
Reg 5(2)(c)
3.2
29 August 2014
Revised Explanatory Memorandum
Reg 5(2)(c)
3.2A
06 March 2015
Revised Explanatory Memorandum
Reg 5(2)(c)
3.2B
19 June 2015
Draft Development Consent Order Tracker
Reg 5(2)(b)
3.3
19 December 2014
4. Compulsory Acquisition Information
Statement of Reasons
Reg 5(2)(h)
4.1
29 August 2014
Funding Statement
Reg 5(2)(h)
4.2
29 August 2014
Book of Reference
Reg 5(2)(d)
4.3
29 August 2014
Book of Reference (Tracked and Clean)
Reg 5(2)(d)
4.3A
19 December 2014
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
6
Book of Reference (Tracked and Clean)
Reg 5(2)(d)
4.3B
19 June 2015
Book of Reference Amendments Explained
Reg 5(2)(d)
4.4
19 December 2014
Book of Reference Amendments Explained
Reg 5(2)(d)
4.4A
19 June 2015
5. EIA
Scoping Opinion
Reg 5(2)(a)
5.1
Provided by PINS in December 2012
Environmental Statement
Reg 5(2)(a) FRA Reg 5(2)(e) Heritage Assessment Reg 5(2)(m) Nature Conservation Reg 5(2)(l)
5.2
29 August 2014
NTS
5.3
29 August 2014
Noise Errata Note
Reg 5(2)(a)
5.4
19 December 2014
6. Other Reports/Statements
Consultation Report
Section 37(3)(c) Planning Act 2008
6.1
29 August 2014
Section 79(1) of Environmental Protection Act 1990 Statement (re statutory nuisance)
Reg 5(2)(f)
6.2
29 August 2014
Report on European Sites (Reg 5(2)(g))
Reg5(2)(g)
6.3
29 August 2014
Supplemental Note on European Sites
Reg5(2)(g)
6.3A
10 November 2014
Draft Development Consent Obligations – Heads of Terms
Reg 5(2)(q)
6.4
29 August 2014
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
7
Draft Development Consent Obligation – Unilateral Undertaking: Nottinghamshire County Council
Reg 5(2)(q)
6.4A
19 December 2014
Draft Development Consent Obligation: North West Leicestershire District Council and Leicestershire County Council
Reg 5(2)(q)
6.4B
19 December 2014
Draft Development Consent Obligation: North West Leicestershire District Council and Leicestershire County Council
Reg 5(2)(q)
6.4C
06 March 2015
Development Consent Obligation – Unilateral Undertaking: Nottinghamshire County Council dated 19 June 2015
Reg 5(2)(q)
6.4D
19 June 2015
Development Consent Obligation: North West Leicestershire District Council and Leicestershire County Council dated 19 June 2015
Reg 5(2)(q)
6.4E
19 June 2015
“Short” Document
- Jan 2014 - May 2014
Reg 5(2)(q)
6.5A 6.5B
29 August 2014 29 August 2014
Planning Statement
Reg 5(2)(q)
6.6
29 August 2014
Rail Report Rail Report Plans
Reg 5(2)(q)
6.7 6.7A
29 August 2014 29 August 2014
Market Report
Reg 5(2)(q)
6.8
29 August 2014
Design and Access Statement
Reg 5(2)(q)
6.9
29 August 2014
Construction Management
Reg 5(2)(q)
6.10
19 June 2015
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
8
Framework Plan
Site Waste Management Framework Plan
Reg 5(2)(q)
6.11
29 August 2014
Strategy for the Safeguarding of EM Airport
Reg 5(2)(q)
6.12
29 August 2014
Sustainability Report
Reg 5(2)(q)
6.13
29 August 2014
Construction Management Strategy for Safeguarding the Derwent Valley Aqueduct
Reg 5(2)(q)
6.14
29 August 2014
Strategic Distribution Site Assessment Study for the Three Cities Sub-Area of the East Midlands – Aecom Final Report, May 2010
Reg 5(2)(q)
6.15
29 August 2014
Mitigation Tracker
Reg 5(2)(q)
6.16
29 August 2014
Existing Highways Orders
Reg 5(2)(q)
6.17
29 August 2014
Category 3 Note
6.18
10 November 2014
Section 38 and 278 Agreement: Leicestershire County Council
6.19
19 December 2014
Section 278 Agreement: Secretary of State for Transport
6.20
19 December 2014
Explanatory Note - Amended Reg 6(2) Plan (Doc 2.4A)
6.21
19 December 2014
Draft CEMP
Reg 5(2)(q)
6.22
08 May 2015
Draft Earthworks Strategy
Reg 5(2)(q)
6.23
08 May 2015
Schedule of Archaeological Works
Reg 5(2)(q)
6.24
08 May 2015
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
9
Site Wide Travel Plan
Reg 5(2)(q)
6.25
19 June 2015
Drawing of Quarry Exit at J24
NTH/209/SK137/P2
6.26
19 June 2015
7. Statements of Common Ground
Planning
- NWLDC and LCC
Reg 5(2)(q)
7.1
29 August 2014
Transport
- Highways Agency - DCC - NCC - LCC - NCityC - DCityC
Reg 5(2)(q)
7.2 7.2A 7.2B 7.2C 7.2D 7.2E
29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014 29 August 2014
Rail
- Network Rail
Reg 5(2)(q)
7.3
29 August 2014
Flood Risk
- Environment Agency
Reg 5 (2)(q)
7.4
29 August 2014
Geology, Soils and Groundwater
- Environment Agency, NWLDC, LCC and Highways Agency
Reg 5 (2)(q)
7.5
29 August 2014
Utilities
- Severn Trent Water Limited
Reg 5 (2)(q)
7.6
29 August 2014
Heritage
- Leicestershire County Council
- English Heritage
Reg 5 (2)(q)
7.7 7.7A
29 August 2014 29 August 2014
Air Quality
- North West Leicestershire District Council
Reg 5 (2)(q)
7.8
29 August 2014
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
10
Ecology
- Natural England
- Leicestershire County Council
Reg 5 (2)(q)
7.9 7.9A
10 November 2014 19 December 2014
Noise
- North West Leicestershire District Council
Reg 5 (2)(q)
7.10
19 December 2014
Archaeology
- Leicestershire County Council
Reg 5 (2)(q)
7.11
19 December 2014
Transport Addendum - Highways Agency - DCC - NCC - LCC - NCityC - DCityC
Reg 5 (2)(q) 7.12 7.12A 7.12B 7.12C 7.12D 7.12E
06 March 2015
Agricultural Land - Natural England
Reg 5 (2)(q) 7.13 06 March 2015
Aviation - East Midlands Airport
Reg 5 (2)(q) 7.14 06 March 2015
Flood Risk Addendum - Environment Agency
Reg 5 (2)(q) 7.15 06 March 2015
Archaeology Addendum - Leicestershire County
Council and English Heritage
Reg 5 (2)(q) 7.16 06 March 2015
8.. Responses to Examining Authority
Responses to relevant representations
8.1 13 February 2015
Summaries of oral submissions of Applicant at 4 February 2015 Hearing
8.2 13 February 2015
Responses to Examining Authority’s First Questions
8.3 06 March 2015
Response Tracker re Actions from 4 Feb 2015 Hearing
8.4 06 March 2015
Applicant’s Comments for Deadline V
8.5 07 April 2015
The East Midlands Gateway Rail Freight Interchange and Highway Order 201X
Document List Document 1.6D
19 June 2015
11
Responses to Examining Authority’s Second Questions
8.6 08 May 2015
Schedule of Proposed changes to Draft DCO and DCOb
8.7 27 May 2015
Applicant’s Comments for Deadline VII
8.8 29 May 2015
Response Tracker from Hearings held on 2 and 3 June
8.9 19 June 2015
Summary of Applicant’s Oral Submissions made at the Hearings held on 2 and 3 June