Date post: | 02-Jan-2016 |
Category: |
Documents |
Upload: | edward-omowa |
View: | 214 times |
Download: | 1 times |
THE FOUNDATION DESIGN OF CBSS 6M RADIO TELESCOPE.
ONUIGBO, KEN and OMOWA E.
ICT DIVISION
BY
OCTOBER, 2015.
ABSTRACTFoundation of structures are salient but very important as it determines the life of the
structure. Our 6m Radio Telescope therefore requires a stable foundation so as to
achieve its optimum life span. In this work, the foundation design of CBSS 6m Radio
Telescope was carried out. The bearing capacity of the sub-soil in Nsukka area, which is
one of the basic considerations in foundation design, was used to calculate the required
size of the foundation trench. The sizes and distribution of steel reinforcements were
also computed using the Civil Engineering Design Code BS 8110. Based on the above,
the Bill of Engineering Measurements and Evaluations (BEME) were prepared to serve
as a guide to the Management of CBSS in the successful execution of the project.
Keywords: 6m Radio Telescope, Bearing Capacity, Steel Reinforcements, Design
Code , BEME.
Introduction. Purpose of the study. Determinants of the type of a foundation Load analysis. Design of the foundation trench. Design of the reinforcements. The bill of Engineering measurement and Evaluation. Conclusion.
OUTLINE:
INTRODUCTION
The foundation is the lowest part of a structure that transfers the load of the super structure to the soil on which it rests.
This part of the structure is somewhat unseen hence often neglected despite the fact that it is the most important part of the structure.
A properly designed foundation is that which transfers the structural load through out the soil without over stressing of the soil.
INTRODUCTION CONTD.
Such stress could result in excessive settlement or shear failure, both of which can damage the structure.
Our 6m radio telescope is never completed until it is mounted on a solid foundation, designed and constructed to counter the forces that will be acting on the it through out its entire life.
Such foundation must be designed and constructed based on a sound engineering economy.
PURPOSE OF THE STUDY
To provide a real time working drawings and
specifications for the completion of the 6m radio
telescope, putting cost into consideration.
To provide a consultancy service to CBSS on the civil
engineering aspect of the foundation to the 6m radio
telescope.
DETERMINANTS OF THE FOUNDATION OF A STRUCTURE.
Functions of the intending structure.
Its structural load.
The geological type of soil.
The bearing capacity of the sub soil.
The settlement criteria of the soil.
The cost available for the project.
Dia.30cmCounter balance
weight (Mc/2)Kg
Motor Assem
bly
Dish (400Kg)
U-Channel
Web Support
Cylindrical pipe
12
cm
50
cm
4m
12mm
ASSEMBLY DRAWING
Concrete core
LOAD ANALYSIS
No of sectors in the dish 6 No of ribs in a sector 11 Weight of a rib 4Kg Weight of 11 ribs in 1 sector 44Kg Trusses 5Kg Bolds and Nuts 1Kg Sub-total 50Kg
Weight of 6 sectors 300Kg Top ring plate 15Kg Bottom plate 20Kg Sheet 50Kg Miscellaneous 15Kg
Approx. Total weight of Antenna 400Kg
COUNTER WEIGHT: CALCULATEDRecall,
Mc = 400*x/y ……………… (1)
Where x = 12cm, y = 50cm
Therefore,
Mc = 400*12/50
Mc = 4800/50 = 96Kg
But, M’c = Mc/2
M’c= 96/2 = 48Kg.
Hence the total weight of dish is 400+96Kg.
=496Kg
Mc(Kg) 400Kg
o
12cm50cm
DESIGN OF THE FOUNDATION TRENCH DESIGN CODE BS 8110
P = N/A …………………………………….. (2)
Where
N = Axial load
A = Base Area of footing
P = Bearing capacity of the soil.
Axial load(N) = weight of the dish * acceleration due to gravity. ….(3)
= 496Kg*9.81m/s2
= 4865.76KN
Assume self weight of concrete footing to be 150KN.
Total design load = 1.0gk + 1.0qk
= 4865.76 +150.
= 5015.76KN.
Assuming the bearing capacity to be 200KN/m2, and substituting for N,
Base Area = 5015.76/200
= 25.079m2.
Hence, provide a base of 5m by 5m.`
DESIGN OF THE FOUNDATION TRENCH DESIGN CODE BS 8110 CONTD.
5.0m
SECTION A-A
5.0m
1.2m
A A
5.0m
FOUNDATION PLAN
DESIGN OF THE REINFORCEMENTS
Taking 50% and 35% factors of safety respectively for dead load (gk) and
live load( qk),
Axial load = 1.5gk+ 1.35qk
= 1.5*4868.761+1.35*150
= 7505.642KN/m
Earth pressure = Axial load/Area2
= 7505.642/(25.079)2
=11.934KN/m2
Assume a 600mm concrete footing with effective depth, K = 520mm
DESIGN OF THE REINFORCEMENTS CONTD.
2m 1m
5m
Bending moment as a result of axial load:
At the column face, moment is critical Hence, M = (11.934*5*2)2/2 =119.34KN/m2
Bending moment as a result of wind force:
Moment = area of dish*wind speed *height
Area of dish =πd2
= 3.142*6*6 =113.112m2
Assuming wind speed to be 48m/s at 5m height,
Moment = 113.112*48*5 = 27.15KN/m2
Total moment on the foundation= axial load moment+ wind speed moment.
=119.34+27.15 =146.49KN/m2
As=M/0.87fykz
Where As= Area of required steel fy= Characteristic strength of steel
k = effective depth z = lever arm(0.95) As= 146.49 *106/0.87*500*0.95*520 =681.70mmHence provide Y16@200mm c/cAlso provide 6nos of Y25 as bolted nuts.
Courtesy:R.C.D. Table A.3R.C.D. Table A.1
dd
dd
dd
900mm
90
0m
m C C
Column Plan
6 Nos. of Y25 as threaded bolts
900mm
1.9
mm
8 Nos. of Y10 @ 225mm as stirrups
Section C-C
BILL OF ENGINEERING MEASUREMENT AND EVALUATION (BEME)
S/N DESCRIPTION QUANTITY UNIT RATE(N) AMOUNT(N)
1Excavation of the foundation trench upto 1.2m depth 32.5 m3 950 35,635.00
2Preparation and casting of concrete mix of grade 1:2:4 16.73 m3 28000 468,400.00
325mm high yield steel reinforcement 12 m 300 3,600.00
416mm high yield steel rienforcement 345 m 250 86,250.00
510mm high yield steel rienforcement 38 m 100 3,800.00
6
Backfilling of foundation with dug out laterite materials and
compaction 21.64 m3 400 8,656.00
7carting away excess laterite materials away from site 15.86 m3 600 9,516.00
82 working days each for mason, carpenter and iron bender 6 # 4000 24,000.00
9 25mm marine plywood 1 sheet 3,500 3,500.00
10 Transportation, logistic and misc 50,000.00
TOTAL 693,347.00
Most projects are often times delayed, while some
are abandoned mid way due to poor planning.
Hence it is better not to start a fence until you
know what you are walling in and what you are
walling out. This study is a sort of a proactive
measure to executing the foundation of our 6m
Radio Telescope. In addition to the design, it offers
an Engineering over view of what to expect in
terms of materials and resources.
CONCLUSION
REFERENCES:
Reynolds and Steadman, (2001), Reinforced Concrete Designers Manual.
Bill Mosley, et al, (2007), Reinforced Concrete Design.
Anthony O. A. et al, (2011), Proctor Cone Penetrometer for In-situ Soil Strength Studies in Nigeria.
Chukwunyere K. E., 6m Radio Telescope Mount Design