The World Bank Assessment and Analysis of the Demand and Supply Gap in Indian Road Construction Industry/Development Programme A Presentation Consulting Engineering Services (India) Pvt. Ltd.
Transcript
Page 1: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

The World Bank

Assessment and Analysis of the

Demand and Supply Gap in

Indian Road Construction Industry/Development Programme

A Presentation

Consulting Engineering Services (India) Pvt. Ltd.

Page 2: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

INTRODUCTIONINTRODUCTION

GENESIS OF STUDYGENESIS OF STUDY

CONCEPT OF STUDYCONCEPT OF STUDY

LEVEL OF STUDYLEVEL OF STUDY

National National

StateState

RuralRuralMAJOR STAKEHOLDERS :HIGHWAY CONSTRUCTION

INDUSTRY

MAJOR STAKEHOLDERS :HIGHWAY CONSTRUCTION

INDUSTRY

IMPLEMENTING AGENCIES

IMPLEMENTING AGENCIES CONTRACTORSCONTRACTORS CONSULTANTSCONSULTANTS

OTHER STAKEHOLDERS:HIGHWAY CONSTRUCTION

INDUSTRY

OTHER STAKEHOLDERS:HIGHWAY CONSTRUCTION

INDUSTRY

INDUSTRY REPRESENTATIVES

INDUSTRY REPRESENTATIVES

FINANCING ORGANIZATIONS

FINANCING ORGANIZATIONS

CONCESSIONAIRES (BOT PROJECTS)

CONCESSIONAIRES (BOT PROJECTS)

EQUIPMENT

LEASING

EQUIPMENT

LEASINGMATERIAL

MANUFACTURERSMATERIAL

MANUFACTURERSEQUIPMENT

MANUFACTURERSEQUIPMENT

MANUFACTURERS

IntroductionIntroduction

Page 3: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Scope of The StudyScope of The Study

Study past development trends of highway construction industry

Assessment of resources requirement for implementing the road development programme

Identifying the ways to increase the capacity for implementing the said programme.

Page 4: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Data Collection

Assessment of Demand and Gap AnalysisOver Medium Terms(10 Years)

Recommendations

Identification of critical issues

Assessment of Industry Response to past Demand (5 years)

(2000-2001 to 2004-2005)

MethodologyMethodology

Page 5: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

APPROACH

DATA COLLECTION

Following Data was collected from all stakeholders through a questionnaire

• Monetary value (Turnover)

• Distribution of contract size

• Time and cost overrun of contracts

• Capacity and Resource (HR and Equipment) base of the Contractors

• Constraints faced by the industry

• Performance of Contracts at all levels

• Views from all stakeholders about past performance of road construction industry(2000-2001 to 2004-2005)

CASE STUDY• Actual executed performance of

projects of various scales.

INTERACTION• Interactive discussions with various

stakeholders involved in HighwayConstruction.

SECONDARY DATA

Data Source :▪ MoSRTH

▪ Planning Commission▪ Rural Roads

(MORD/ PMGSY/NABARD)

▪ BRO(NH) ▪ Road Development Vision Document-2021 ▪ Rural Roads Vision Document-2025

.Others

Page 6: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Data Sources/Sample SizeData Sources/Sample Size

S# DepartmentData

Collection (Nos.)

A Government

1 NHAI 1

2 MoRT&H 1

3 State Road Authorities 15

4 Rural Roads (PMGSY), MORD & NABARD 1

5 Planning Commission 1

B Contractors

1Large Domestic > Rs 125 Crores(>USD 27.77 million) 7

2Medium Domestic Rs 40 to 125 Crores(USD 8.88 - 27.77 million) 4

3Small Domestic Rs 5 to 40 Crores(USD 1.11 - 8.88 million) 7

4Very Small Domestic less than Rs 5 Crores(<USD1.11 million) 4

5 Domestic (not entered in Road Sector) 2

6 Foreign 4

S# DepartmentData

Collection (Nos.)

C Consultants

1 Domestic 4

2 Foreign 5

D Equipment Supplier

1 Domestic Supplier 7

2 Domestic Hiring & Leasing Company 2

3 Foreign Supplier 4

E Material Supplier

1 Domestic Supplier 3

F Industry Representative 5

G BOT Concessionaire 4

H Finance Institution 4

Page 7: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

• Roads carry 85% of passengers & 61% of freight traffic• NH constitute 2% length of road network but carry 40% of traffic• SH & MDR carries about 25% traffic

Growth in Road NetworkGrowth in Road Network

CATEGORIES 1951( km)

Dec., 2004(km) % Growth Percentage

(%) of total length

- -

2%

4%

94%

194%

129%

963%

796%

Expressways Nil 200

National Highways 22,255 65,569

State Highways 60,000 137,711

Other roads including Major District Roads, Other District Roads

& Village Roads

318,000 3,383,344

400,255 3,586,824

Page 8: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Allocation and Expenditure Scenario in Road Sector Allocation and Expenditure Scenario in Road Sector ( Past 5 Years )( Past 5 Years )

(Rs. In crores)

0

5000

10000

15000

20000

25000

Year

Rs.

in C

rore

s

Total Allocation(Rs In Crores) Total Expenditure(Rs in Crores)

Total Allocation(Rs In Crores) 15743 16920 18440 20424 21826Total Expenditure(Rs in Crores) 14377 15203 16188 16774 19007

2000-2001 2001-2002 2002-2003 2003-2004 2004-2005

Page 9: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Road Construction Industry Response to Past Demand Road Construction Industry Response to Past Demand (Last 5 Years)(Last 5 Years)

Parameters Considered Increase ranges (%)

Monetary Value - 6 to 45

Human Resources - 8 to 40

Construction Equipments - 7 to 32

Cost Overrun normally - 10 to 50

Time overrun Normally - 25 to 75

Constrained faced by the industry in implementing planned

programme

Page 10: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Constraints Perceived by the IndustryConstraints Perceived by the Industry

Constraints perceived by Contractors (combined) to meet planned programme

15%

Cash flow : 12%

Delay in payment : 10%

Delay in decision/ approval by Eng./ Employer : 12%

Inadequate design and drawing : 12% Delay in handing over of site :

Deficiency in procurement of critical materials : 9%

Inadequacy of modern plant / equipment : 9%

Migration of experienced personnel : 10%

Inadequacy of experiencedmanpower : 11%

- Pre construction activities attributable to Employer 27%- Other constraints attributable to the Employer/Engineer 22%- Constraints attributable to the Contractors 51%

Page 11: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

- Pre construction activities attributable to Employer 55%- Other constraints attributable to the Employer/Engineer 12%- Constraints attributable to the contractors 33%

Constraints perceived by State agencies to meet planned programme

by Eng./ Employer : 12%

Non availability of qualified contractors: 12%

Rehab. & Resettlement : 8%

Environmental clearance : 11%

Inadequate allocation of fund : 11%

Delay in decision/ approval Inadequate design and drawing : 8%

Delay in handing over of site : 17%

Inadequacy of modern plant / equip.: 10%

Inadequacy of experienced manpower : 11%

Constraints Perceived by the IndustryConstraints Perceived by the Industry

Page 12: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Grouping of Constraints Perceived by State Agencies /Contractors

Resource Related (% Impact) Business Environment Related (% Impact)

Factors StatesAgencies

Contractors Factors StateAgencies

Contractors

Contract ManagementInadequate Allocation of fundsNon-Availability of funds in timeInadequacy of Staff for Management for managing programme/contract

Contracting IndustryNon-Availability of Qualified ContractorsNon-Availability of Suitable Construction EquipmentsInadequate availability of critical materialInadequacy of design/drawings

11%

-

11%

12%

10%

-

8%

12%

10%

11%

9%

9%

-

12%

Working EnvironmentDelay in land acquisition, Rehabilitation and Resettlement of Project affected personsDelay in utility relocationFrequent migration of experienced StaffOther inter-departmental clearances e.g. delay in decision/approval by engineer/employerEnvironmental Clearance

25%

-

-

12%

11%

15%

-

-

12%

10%

Total 52% 63% Total 48% 37%

Critical Deficiencies Constraining Road Construction Industry CaCritical Deficiencies Constraining Road Construction Industry Capacity pacity and Performance and Performance

Page 13: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Select past trend line with suitable calibration for assessment of

projected expenditure demand

Project the demand level for study horizon period of 10 years

upto 2015 with different growth scenarios

Possible growthdeclared

by Authorities and assumptions-

Scenario-2

Quantify the demand inmonetary

terms for the industry.

Normal growth(Extension of

Past trend.)-Scenario-1

Accelerated growth(Govt. announcement)

Scenario-3

Assessment of Future Demand: Monetary ValueAssessment of Future Demand: Monetary Value

Page 14: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Assessment of Demand for Next Ten Years Assessment of Demand for Next Ten Years

Assessment of demand and Gap Analysis for the next 10 years has been carried out for the following attributes :

Monetary Value (Turnover)Contract SizesHuman ResourcesEquipmentMaterials

Human Resources/Equipments/Contract Size

Page 15: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Assessment of Demand for Next Ten Years Assessment of Demand for Next Ten Years

Mathematical Modeling have been used to develop demand equations with following structure:

HR/Equipment-Dependent Variable (y)= f (Turnover (x))

Scenario 1 - The past expenditure regressed over the time has been considered. Normalized expenditure at 2004-05 prices has been considered and future expenditure has been generated.

Scenario 2 – The projections by various authorities associated with road development and vision documents published/being published by Govt. of India setting a mid-term goal.

Scenario 3 – The Scenario-3 incorporates the massive investment in the National Highways sector announced by Govt. of India to achieve accelerated growth during 11th plan period by 2012. The announced expenditure of Rs. 48000 crores on Rural Roads under “Bharat Nirman Scheme” has also been incorporated for the period 2005-2009.

Mathematical Modeling and Three Scenario

Page 16: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

GapPeriod Grand Scenario-1 Grand Scenario-2 Grand Scenario-3

GS2-GS1 GS3-GS1

2005-2006 19105 21902 21902 2797 2797

2006-2007 19542 26335 36331 6793 16789

2007-2008 19979 28530 51360 8551 31381

2008-2009 20416 30348 66721 9932 46305

2009-2010 20853 31031 57750 10178 36897

2010-2011 21290 33062 68075 11772 46785

2011-2012 21727 36237 79033 14510 57306

2012-2013 22164 39564 17400

2013-2014 22601 42962 20361

2014-2015 23038 46542 23504

Overall National Scenario (Monetary Value)

Assessment of Demand for Next Ten Years: Monetary Value (Assessment of Demand for Next Ten Years: Monetary Value (RsRs. . CroresCrores))

Page 17: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

0

10000

20000

30000

40000

50000

60000

70000

80000

0 1 2 3 4 5 6 7 8 9 10 11Year

Rs.

in C

rore

s

Grand Scenario 3

Grand Scenario 2

Grand Scenario 1

year 1:2005-06

Grand Scenario Monetary Value

Assessment of Demand for Next Ten Years: Monetary Value (Assessment of Demand for Next Ten Years: Monetary Value (RsRs. . CroresCrores))

Page 18: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Maintenance Expenditure at all levels (i.e. NH/SH/RR)

All figures in Rs. Crores

Note :- Assumed 60% of maintenance expenditure as Contract based

-

-

-- RR figures are computed from vision document 2025 (draft)

State Roads figures upto 2009-10 are obtained from 12th Finance Commission Report

Assumed 5% increase in yearly expenditure beyond 2009-10 for State Roads since 12th Finance Commission figures are available only upto 2009-10 Assumed 10% increase in yearly expenditure for NH beyond 2006-07, since figures are available only for 2005-06 and 2006-07

Period Total Contract Based Maintenance-Expenditure-60% of Total

2005-2006 7264 4358

2006-2007 11281 6768

2007-2008 11697 7018

2008-2009 12138 7283

2009-2010 12605 7563

2010-2011 13287 7972

2011-2012 14010 8406

2012-2013 14775 8865

2013-2014 15584 9350

2014-2015 16440 9864

Assessment of Demand for Next Ten Years: Monetary ValueAssessment of Demand for Next Ten Years: Monetary Value

Page 19: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Assessment Of Demand for Next Ten YearsAssessment Of Demand for Next Ten Years : Contracts Sizes: Contracts Sizes

GapPeriod Size of

Contracts Grand Scenario-1 Grand Scenario-2 Grand Scenario-3GS2-GS1 GS3-GS1

2005-2006 L 80 122 122 42 42

M 89 119 119 30 30

S 2380 2506 2506 126 126

VS 3341 4015 4015 674 674

2006-2007 L 81 176 260 95 179

M 91 170 242 79 151

S 2447 2725 4525 278 2078

VS 3440 4091 7690 651 4250

2007-2008 L 82 171 396 89 314

M 92 168 360 76 268

S 2515 3399 6689 884 4174

VS 3540 5284 11864 1744 8324

2008-2009 L 83 172 535 89 452

M 94 172 482 78 388

S 2582 3735 8687 1153 6105

VS 3640 5801 15704 2161 12064

2009-2010 L 84 156 674 72 590

M 95 160 602 65 507

S 2650 4098 913 1448

VS 3740 6370 2630

Overall National Scenario : Distribution of Contracts ( Size wise)

L - Large Contract M - Medium Contract S - Small Contract Vs - Very small Contract

Page 20: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Assessment Of Demand for Next Ten YearsAssessment Of Demand for Next Ten Years : Contracts Sizes: Contracts Sizes

Overall National Scenario : Distribution of Contracts ( Size wise)

L - Large Contract M - Medium Contract S - Small Contract Vs - Very small Contract

GapPeriod Size of

Contracts Grand Scenario-1 Grand Scenario-2 Grand Scenario-3GS2-GS1 GS3-GS1

2010-2011 L 85 158 812 73

M 96 164 722 68

S 1373 4489 992 3116

VS 5184 6997 1813

2011-2012 L 86 166 950 80

M 97 175 923 78

S 2784 4961 1118 2177

VS 3940 7685 3745

2012-2013 L 87 175 88

M 99 186 87

S 2852 5468 2616

VS 4039 8444 4405

2013-2014 L 88 183 95

M 100 198 98

S 2919 6013 3094

VS 4139 9277 5138

2014-2015 L 89 193 104

M 102 210 108

S 7226 16799 9573

VS 12717 30591 17874

Page 21: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

GapPeriod Grand Scenario-1 Grand Scenario-2 Grand Scenario-3

GS2-GS1 GS3-GS1

2005-2006 105354 113057 113057 7703 7703

2006-2007 109672 129180 166809 19508 57137

2007-2008 116443 140683 227860 24240 111417

2008-2009 123436 151874 288836 28438 165400

2009-2010 130417 159560 240799 29143 110382

2010-2011 137487 171199 282188 33712 144701

2011-2012 147885 190308 329262 42423 181377

2012-2013 158424 209720 51296

2013-2014 169144 229271 60127

2014-2015 179662 249202 69540

Overall National Scenario (Human Resources no.)

Assessment Of Demand for Next Ten Years :Assessment Of Demand for Next Ten Years :

Page 22: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

0

50000

100000

150000

200000

250000

300000

350000

0 1 2 3 4 5 6 7 8 9 10 11YEAR

OVE

RA

LL H

R:N

UM

BER

Grand Scenario 3

Grand Scenario 2

Grand Scenario 1

year 1:2005-06

OVERALL NATIONAL SCENARIO : HR

Assessment of Demand for Next Ten Years : Human Assessment of Demand for Next Ten Years : Human ResourcesResources

Page 23: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

GapPeriod Grand Scenario-1 Grand Scenario-2 Grand Scenario-3

GS2-GS1 GS3-GS1

2005-2006 105354 113057 113057 7703 7703

2006-2007 109672 129180 166809 19508 57137

2007-2008 116443 140683 227860 24240 111417

2008-2009 123436 151874 288836 28438 165400

2009-2010 130417 159560 240799 29143 110382

2010-2011 137487 171199 282188 33712 144701

2011-2012 147885 190308 329262 42423 181377

2012-2013 158424 209720 51296

2013-2014 169144 229271 60127

2014-2015 179662 249202 69540

OVER ALL NATIONAL SCENARIO : EQUIPMENT

Assessment Of Demand for Next Ten Years :Assessment Of Demand for Next Ten Years :

Page 24: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

0

20000

40000

60000

80000

100000

120000

0 1 2 3 4 5 6 7 8 9 10 11

YEAR

OVE

R A

LL E

QU

PT: N

UM

BER

YEAR 1:2005-06

Grand Scenario 1

Grand Scenario 2

Grand Scenario 3

OVER ALL NATIONAL SCENARIO : EQUIPMENT

Assessment Of Demand for Next Ten YearsAssessment Of Demand for Next Ten Years : Equipment: Equipment

Page 25: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Supply of Materials (In Million Supply of Materials (In Million TonneTonne))

Bitumen Steel Cement Aggregate

Planned Annual Capacity

Demand over medium terms-Grand Scenario-3

6.37 88 255 Production to be adjusted to meet the demand

6.26 4.1 21 342

Page 26: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Recommendations and Action Plan Recommendations and Action Plan

Critical Issues

Recommendations Action Plan

Inadequacy of Staff for managing programme/contract

Develop targeted training and awareness programmeReview academic and experience criteria and make selected training programmeInternational exposure required for technical officers.Emphasis be given to the areas of project management, equipment maintenance and operation, dispute resolution, contract administration and quality assurance. Separate funds should be allocated for development of skills.Shortage of Civil Engineers is critical due to the student preference is in the declineCareer advancement needs to be linked to training.Skill development programme for road agencies to familiarize them with FIDIC/Standard Bidding Documents

Comprehensive Plan to be drawn up to increase capacity through high degree mechanized constructionSpecific guidelines, instruction and manuals should be developed covering:Supervision of civil works with emphasis on quality controlManaging the construction process in a time bound plan.Remuneration of Civil Engineers to be adequate to act as incentive

Non-Availability of Qualified Contractors

Dispute Resolution Mechanism Programme for Agencies/ContractorsJVs can be encouraged to bring in non-technical partners but good in financing and management Model Concession Agreement to make PPP attractivePromoting effective/meaningful Joint Venture between Foreign andIndian Construction Companies

For BOT/Annuity under PPP environment essential to have services of Financial Managers, Contract Specialist, Traffic and Transport Specialist and Legal Experts to minimize dispute and litigations in handling large financers.Encourage SBDs throughout the country to cut down contract negotiation timeModel Concession Agreement for National and State Highways Disputes to be resolved through fair arbitration

Page 27: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Recommendations and Action PlanRecommendations and Action Plan

Critical Issues

Recommendations Action Plan

Non-Availability of Suitable Construction Equipment

Establish a viable equipment hiring and leasing company as this would help in enhancing the capacity of the contractorsIdentify high-valued equipment items – motor graders, sensory paverfinishers and vibratory compactors – to be in the inventory of the rental agenciesEncourage hiring of surplus equipment of one contractor by another contractor to make best use of idle periodEnhance the list of equipment qualified for import without customs duty (e.g. Hydraulically operated self propelled piling rigs for drilling holes of 1.5m and 36m depth)Liberalize procedures for import of equipment (without duty) to fully mechanize road construction to gain speed and quality

Utmost emphasis should be given for developing Road Construction Equipment Bank in various regions of the country.

Inadequacy of designs/ drawings

Monitoring and review of design and drawing by Design and Corridor Development Team (DCDT) and any defect identified to be rectified before commencement of contractSystem of penalty to be introduced for deficiencies in Design and Drawings submitted by outsource agency (Consultant)

Review of Design and Drawing to be mandatory assignment of DCDT as major preconstruction activity

Page 28: The World Bank Assessment and Analysis of the …siteresources.worldbank.org/INTSARREGTOPTRANSPORT/3562298... · Assessment & Analysis of the Demand and supply Gap in Indian Road

Assessment & Analysis of the Demand and supply Gap in Indian Road Construction Industry/Development Programme

Thank You