1
AREA DRAINAGE IMPROVEMENTS Municipality of Anchorage Project Management & Engineering Department Project Timeline We are here Pending funding * * Spring 2020 Dra� Design Study Report Public Mee�ng #2 Summer 2020 Design Study Report Spring 2021 Design Winter 2019 Data Collec�on Public Mee�ng #1 Summer 2021 Construc�on * TICIA CIRCLE / ASHLEY CIRCLE PM&E Project #19-10
Transcript
  • AREA DRAINAGE IMPROVEMENTS Municipality of Anchorage Project Management & Engineering Department

    Project Timeline

    We are here

    Pending funding*

    *

    Spring 2020• Dra� Design Study Report• Public Mee�ng #2

    Summer 2020• Design Study Report

    Spring 2021• Design

    Winter 2019• Data Collec�on

    Public Mee�ng #1

    Summer 2021•

    Construc�on *

    TICIA CIRCLE / ASHLEY CIRCLEPM&E Project #19-10