TO: Honorable Carlos A. Gimenez
Mayor Honorable Esteban L. Bovo, Jr., Chairman and Members, Board of County Commissioners Joe Arriola, Chairman
and Members, Public Health Trust Board of Trustees FROM: José Luis Gómez, PE, Chairman Jackson Bond Citizens’ Advisory Committee DATE: April 26, 2016 RE: Jackson Bond Citizens’ Advisory Committee Quarterly Report
Pursuant to Section 2-2130(e) of the Code of Miami-Dade County, as created by the Board of County Commissioners via Ordinance No. 14-44, it is my pleasure to present the quarterly report from the Jackson Health System General Obligation Bond Citizens’ Advisory Committee, covering the period from January to March of 2017. The report was approved on April 25, 2017.
The Committee met once during the reporting period, and individual members have also participated in both public events and private briefings related to their duties. I can confidently report that our members are upholding the words and spirit of the legislation, and that we are receiving appropriate support from Jackson Health System staff.
If you have any questions, please feel free to contact me.
Attachment
c: Carlos A. Migoya, President & Chief Executive Officer Geraldine Lazarre, Vice Chairwoman and Members, Jackson Bond Citizens’ Advisory Committee
TO: Jose Luis Gomez, PE, Chairman, and Members, Jackson Bond Citizens’ Advisory Committee FROM: Carlos A. Migoya President & Chief Executive Officer DATE: April 25, 2017 RE: Jackson Miracle-Building Bond Quarterly Report – January to March 2017
During the second quarter of FY 2017, the Jackson Bond Citizens’ Advisory Committee met once to review two projects presented by staff. Both were recommended favorably and subsequently approved by the Public Health Trust Board of Trustees. Those projects, along with equipment and technology purchases under the bond, represent approximately $11.5 million of Miracle-Building Bond proceeds.
All the non-equipment dollars during this quarter were associated with infrastructure and renovation projects at the Jackson Memorial Medical Center, totaling $291,280.
Substantial technology and equipment purchases this quarter included $3.12 million for continuing upgrades to the system’s electronic health record software; $1.74 million for anesthesia equipment and $1.63 million for ventilator equipment at Jackson Memorial Hospital; $275,000 for surgical equipment and $175,000 for ultrasonic equipment at Jackson South Community Hospital; and $330,538 for incubators in the newborn intensive care unit at Holtz Children’s Hospital.
Jackson Bond Quarterly Report – January to March 2017 Page 2 of 18
Bond Dashboard
* The categories used in these graphics and throughout this report are administrative in nature and do not necessarily align with line-item purchase within a project. For example, a job may be categorized as an infrastructure project for reporting purposes even if that project includes the purchase of equipment. The above categories are consistent with the way in which funds are reviewed by the Citizens’ Advisory Committee and approved by the Public Health Trust Board of Trustees. Due to a scrivener’s error in an earlier report, funds approved for the Campus Wide Elevator Modernization Project ($8.95 million) were not accounted for in previous summaries. The totals have been retroactively updated in this report.
†Funds for Jackson West were approved without line-item designations. In this reporting period, $1,321,677 of previously unallocated funds was allocated for construction.
New Facilities
$0
of$150 million
Infrastructure
$1.36million
of$177 million
Hospital Upgrades
$0
of$150 million
Technology & Equipment
$10.14million
of$353 million
Approved Funds - Category: This Quarter*
New Facilities
$136.64million
of$150 million
Infrastructure
$39.58million
of$177 million
Hospital Upgrades
$231.68million
of$150 million
Technology & Equipment
$158.3million
of$353 million
Approved Funds - Category: Total*
Design
$0
Construction
$264,800
FFE & Technology
$11.21 million
Contingency
$26,480
Unallocated†
$0
Approved Funds – Line Item: This Quarter
Design
$76.09 million
Construction
$230.48 million
FFE & Technology
$236.73 million
Contingency
$22.90 million
Unallocated†
$0
Approved Funds – Line Item: Total
Jackson Bond Quarterly Report – January to March 2017 Page 3 of 18
Financial Update
Reimbursements received during the report timeframe totaled $14,748,876, bringing to $134,212,717 the total reimbursement received since the bond program began.
Small-Business Enterprise Contracting
During this reporting period, 26 contracts were awarded totaling $11,057,693. Four of those projects, or 15.4 percent, were awarded to prime contractors who are certified small business enterprises (SBEs). Those four contracts had a total value of $362,714, or 3.3 percent of the combined value of all bond-funded contracts awarded in this period. It is important to note that some subcontractors on those projects are not registered SBEs. Another $875,697 flowed to SBE sub-contractors through non-SBE prime contractors, representing an additional 7.9 percent of total contract value this quarter.
The names and demographics of the prime and sub-contractors for all 26 contracts are detailed below.
These totals do not include bond-funded expenditures on non-construction items such as equipment and technology. The totals also do not include projects approved by the Trust Board that have not yet completed the procurement process. This list only represents contracts awarded during the reporting period – some projects include additional contracts detailed in prior reports or still pending award.
Six SBE outreach events were held during the reporting period:
January 10, 2017, at Jackson Memorial Hospital
January 12, 2017, at the Minority Business Development Agency Center in partnership with Turner Construction
January 31, 2017, at the Little Haiti Cultural Center in partnership with the Florida State Minority Supplier Development Council
February 14, 2017, at Jackson Memorial Hospital
February 15, 2017, at Jackson Memorial Hospital in partnership with Skanska
March 16, 2017, at the Miami Dade College North Campus, in partnership with Turner Construction
Two future SBE outreach events are currently scheduled, and others may be added:
May 16, 2017, at Jackson Memorial Hospital
June 15, 2017, at Jackson Memorial Hospital
Following are the four contracts awarded to SBE prime contractors:
Award Date & Method
Project Vendor Vendor
Demographic Contract
Value Vendor Share
02/15/17 Constr: JOC
Direct
Shoppes at Arch Creek Urgent Care Center
(UCC)
Harbour Construction,
Inc
White Male SBE
$240,025 60.84%
All Points
Design Corp
Hispanic Female
SBE 2.92%
Jackson Bond Quarterly Report – January to March 2017 Page 4 of 18
Comfort Tech Air
Conditioning, Inc
Hispanic Female
SBE 32.91%
High Power Electric, LLC
Hispanic Male SBE
3.33%
01/19/17 City of Miami
Beach Contract ITB 9-
11/12
Campus Wide Fire Door
Replacement
AAA Automated Door Repair Inc
Hispanic / White Male/Female
SBE $21,971 100.00%
01/27/17 City of Miami
Beach Contract ITB 9-
11/12
Campus Wide Fire Doors
Replacement
AAA Automated Door Repair Inc
Hispanic / White Male/Female
SBE $13,393 100.00%
02/21/17 JOC Direct
Institute & Institute Annex
Relocation
LEE Construction Group, Inc.
Hispanic Male SBE
$87,325 64.25%
Drywall and Framing
Investment Group, Inc
Hispanic Male
Non-SBE 28.63%
Kelly Glass &
Mirror Corporation
Hispanic Male
Non-SBE 7.13%
Following are the 22 projects awarded to non-SBE prime contractors:
Award Date & Method
Project Vendor Vendor
Demographic Contract
Value Vendor Share
01/06/17 Constr: RFP
East Tower 3A Post-Partum
Unit – Maternity
Skanska USA Buildiing, Inc.
Shareholder Owned
Shareholder Owned
Non-SBE
$4,616,718 TBD
SBE Trade
Partners TBD TBD
TBD 32.77% SBE-C 0.25%
SBE-G/S
03/02/17 National Joint
Powers Alliance (NJPA) Contract
100614-CDW
JNMC - Nuclear Medicine
Camera Suite Renovation &
Equipment
CDW Government,
Inc.
Shareholder Owned
Shareholder Owned
Non-SBE
$11,251 100.00%
Jackson Bond Quarterly Report – January to March 2017 Page 5 of 18
03/01/17 Goods & Serv:
RFP
Shoppes at Arch Creek Urgent Care Center
(UCC)
Pro Signs & Lighting, Inc.
Hispanic Woman Non-SBE
$5,295 100.00%
03/01/17 Goods & Serv:
RFP
Country Walk Urgent Care Center (UCC)
Pro Signs & Lighting, Inc.
Hispanic Woman Non-SBE
$1,160 100.00%
03/27/17 JOC Direct
JMH – Linear Accelerator
Equipment & Suite
Renovation - DTC 1st Floor
Johnson-Laux Construction,
LLC
White Female
Non-SBE $761,907 43.15%
Cutting Edge
Sales & Installation, Inc.
Hispanic Female
SBE 3.58%
GAMMA Air
Systems
Hispanic Male SBE
12.04%
Haber & Sons
Plumbing
Hispanic Male SBE
2.64%
The O.J. Painting &
Waterproofing Company
Black Male SBE
1.28%
Solares Electrical
Services
Hispanic Male SBE
26.59%
ASE Telecom and Data Inc.
Hispanic Female
Non-SBE 0.89%
Cardel Fire Protection
Hispanic Male / Female
Non-SBE 0.79%
Glenco
Industries
Hispanic Male
Non-SBE 3.53%
Ideacom Healthcare
Communications of Florida
White Male
Non-SBE 2.29%
AVI Integrators
dba Security 101
Hispanic Male/Female
Non-SBE 1.79%
Simplex Grinnell Shareholder
Owned 1.43%
Jackson Bond Quarterly Report – January to March 2017 Page 6 of 18
Shareholder Owned
Non-SBE
03/10/17 National Joint
Powers Alliance (NJPA) Contract
031913-SGL
JMH - Center Campus Fire
Alarm Upgrade: Voice
Messageing and Indoor Mass Notification
System
Simplex Grinnell
Shareholder Owned
Shareholder Owned
Non-SBE
$1,059,994 100.00%
01/26/17 Constr: JOC
Direct
JMH - Central Building Roof Replacement
Florida Roofing Solutions
Hispanic Male
Non-SBE $44,311 100.00%
01/19/17 Design: EDP
South Beach Urgent Care
Center MGE Architects
Hispanic Male
Non-SBE $27,850 14.04%
G & G
Engineering Group, Inc.
Hispanic Male SBE
31.38%
David Plummer
& Associates
White Male
Non-SBE 50.27%
G.D. Klieger,
Inc.
White Male
Non-SBE 4.31%
03/01/17 Goods & Serv:
RFP
Clock Tower Plaza Urgent Care Center
(UCC)
Pro Signs & Lighting, Inc.
Hispanic Woman Non-SBE
$5,295 100.00%
01/19/17 Exempt from Procurement
Regulation
Clock Tower Plaza Urgent Care Center
(UCC)
Art Resource, Inc
White Female
Non-SBE $13,230 100.00%
01/27/17 Constr: Bid
Waiver
Jackson South Community
Hospital Master Plan Projects –
Pre-Construction
and Construction Management
Services
Turner Construction
Company
Shareholder owned
Shareholder owned
Non-SBE
$51,100 100.00%
02/01/17 Constr: Bid
Waiver
Jackson West – Pre-
construction &
W.G. Yates & Sons
White Male
Non-SBE $60,000 100.00%
Jackson Bond Quarterly Report – January to March 2017 Page 7 of 18
Construction Management
Services
Construction Company
03/07/17 Constr: RFP
Jackson West – Pre-
construction & Construction Management
Services
W. G. Yates & Sons
Construction Company
White Male
Non-SBE $1,432,832 87.38%
Lunacon
Engineering Group, Corp.
Hispanic Female
SBE 6.31%
Lego
Construction Company
Hispanic Male SBE
6.31%
03/24/17 Constr: JOC
Direct
Jackson Memorial Hospital –
Interventional Radiology Neuro
Bi-plane Angiographic Equipment – West Wing Room #19
Johnson-Laux Construction,
LLC
White Female
Non-SBE $667,047 32.38%
Centerline
Plumbing, Inc.
White Male SBE
5.67%
Comfort Tech
Air Conditioning, Inc
Hispanic Female
SBE 16.20%
Cutting Edge
Sales & Installation, Inc.
Hispanic Female
SBE 2.95%
The O.J. Painting &
Waterproofing Company
Black Male SBE
2.88%
Solares Electrical
Services
Hispanic Male SBE
30.26%
ASE Telecom and Data Inc.
Hispanic Female
Non-SBE 2.31%
Cardel Fire Protection
Hispanic Male / Female
Non-SBE 1.28%
Jackson Bond Quarterly Report – January to March 2017 Page 8 of 18
Glenco
Industries
Hispanic Male
Non-SBE 1.00%
Ideacom Healthcare
Communications of Florida
White Male
Non-SBE 0.84%
AVI Integrators
dba Security 101
Hispanic Male/Female
Non-SBE 2.31%
Simplex Grinnell
Shareholder Owned
Shareholder Owned
Non-SBE
1.92%
01/31/17 State of Florida
Contract 425-001-12-1
Institute & Institute Annex
Relocation Workscapes, Inc
White Female
Non-SBE $65,433 100.00%
02/24/17 MedAssets
Contract MS02613
Institute & Institute Annex
Relocation
CDW Government, Inc
Shareholder owned
Shareholder owned
Non-SBE
$27,561 100.00%
03/03/17 Constr: RFP
Jackson North Medical Center New Expansion & Backfill Phase
2
OHL-Arellano Construction Management
Services
Shareholder Owned
Shareholder Owned
Non-SBE
$301,318 TBD
SBE Trade
Partners TBD TBD
TBD 32.77% SBE-C 0.25%
SBE-G/S
03/03/17 Constr: RFP
Jackson North Medical Center New Expansion & Backfill Phase
2
OHL-Arellano Construction Management
Services
Shareholder Owned
Shareholder Owned
Non-SBE
$361,323 TBD
SBE Trade
Partners TBD TBD
TBD 32.77% SBE-C 0.25%
SBE-G/S
03/24/17 Constr: RFP
JMH - Refurbishment
Memios Environmental
Hispanic Male
Non-SBE $530,387 100.00%
Jackson Bond Quarterly Report – January to March 2017 Page 9 of 18
of Linen Chute System
Technologies, LLC
03/24/17 JOC Direct
JMH – CT Scanner Suite Renovation &
Equipment Replacement (West Wing – Rooms 214 &
216)
Johnson-Laux Construction,
LLC
White Female
Non-SBE $532,523 40.25%
AAA Automated Door Repair, Inc.
Hispanic / White Male / Female
SBE 7.23%
Centerline
Plumbing, Inc.
White Male SBE
2.90%
Comfort Tech
Air Conditioning, Inc
Hispanic Female
SBE 9.70%
Cutting Edge
Sales & Installation, Inc.
Hispanic Female
SBE 3.47%
The O.J. Painting &
Waterproofing Company
Black Male SBE
3.07%
Solares Electrical
Services
Hispanic Male SBE
21.49%
ASE Telecom and Data Inc.
Hispanic Female
Non-SBE 1.46%
Cardel Fire Protection
Hispanic Male / Female
Non-SBE 1.06%
Glenco
Industries
Hispanic Male
Non-SBE 2.64%
Ideacom Healthcare
Communications of Florida
White Male
Non-SBE 1.83%
AVI Integrators
dba Security 101
Hispanic Male/Female
Non-SBE 2.68%
Simplex Grinnell Shareholder
Owned 2.22%
Jackson Bond Quarterly Report – January to March 2017 Page 10 of 18
Shareholder Owned
Non-SBE
03/24/17 Design:
RFQualification
Jackson Memorial
Hospital – GI Suite
Renovations, South Wing 2nd
floor
Perkins + Will Architects, Inc.
Shareholder Owned
Shareholder Owned
Non-SBE
$67,000 51.24%
ESI Consulting Engineers, Inc.
Hispanic Male SBE
22.89%
Bard, Rao & Athanas
Consulting Engineers, LLC
White Male
Non-SBE 25.87%
03/28/17 Constr:
Emergency
Condensate Piping
Replacement UM Group, Inc.
Hispanic Male
Non-SBE $51,444 100.00%
Jackson Bond Quarterly Report – January to March 2017 Page 11 of 18
Status of Major Projects
Rehabilitation Center
The rehabilitation center is planned as a state-of-the-art facility to unite the clinical work now done at Jackson Rehabilitation Hospital with the research performed by the University of Miami and the development resources of The Miami Project to Cure Paralysis.
The schematic design phase is complete, and pricing for that phase has been verified to be within budget. The first package of plans, which includes enabling work such as demolition and utility work, is complete and will be permitting in April. Work on this phase is expected to begin over the summer and will include the demolition of the Institute and Institute Annex buildings, and the installation of temporary mechanical, electrical, and plumbing connections to the existing Jackson Rehabilitation Hospital.
Architectural Contract
Completed Feburary 2015
Program & Design
Construction Ribbon-Cutting
Rehabilitation Center Timeline
Timeline
Rehabilitation Center
Total Project Bond Fund Sources
New Facilities
$80million
of$150 million
Infrastructure
Hospital Upgrades
Technology & Equipment
Rehabilitation Center
Bond Fund Sources Approved This Quarter
New Facilities Infrastructure
Hospital Upgrades
Technology & Equipment
Rehabilitation Center Funding Progress
Timeline
Jackson Bond Quarterly Report – January to March 2017 Page 12 of 18
Jackson West
Schematic designs for Jackson West were completed during the prior reporting period, and the pricing was completed and verified to be within budget during the reporting period. Site preparation work is scheduled to begin in late spring or early summer, followed be demolition of existing structures in late summer or early fall. Based upon an administrative hearing examiner’s recommendation, construction on the inpatient-hospital portion of Jackson West may advance on a different schedule than the other elements of the campus: the emergency room, diagnostic center, physician clinics (including pediatric outpatient specialty facilities), and the parking garage. The inpatient unit – which was not contemplated during the 2013 bond campaign and is not being funded with those dollars – is planned as three floors above the emergency room and diagnostic center. This allows construction of the rest of the campus to proceed timely.
Land Purchase
Completed June 2015
ArchitectContracted February
2016
Program & Design
ConstructionRibbon-Cutting
Jackson West Timeline
Jackson West
Total Bond Fund Sources
New Facilities
$44.5million
of$150 million
Infrastructure
Hospital Upgrades
Technology & Equipment
$10million
of$353 million
Jackson West
Bond Fund Sources Approved This Quarter
New Facilities Infrastructure
Hospital Upgrades
Technology & Equipment
Jackson Bond Quarterly Report – January to March 2017 Page 13 of 18
Urgent Care Centers
Lease ExecutionCompleted Sept. 2015
ArchitectProgram & Design
ConstructionRibbon-Cutting
Lease ExecutionCompleted June 2015
ArchitectProgram & Design
ConstructionRibbon-Cutting
Urgent Care Centers
Total Bond Fund Sources
New Facilities
$11.51million
of$150 million
Infrastructure
Hospital Upgrades
Technology & Equipment
Urgent Care Centers Bond Fund Sources Approved This Quarter
New Facilities Infrastructure
Hospital Upgrades
Technology & Equipment
Keystone Point Timeline
Lease ExecutionCompleted June 2015
ArchitectProgram & Design
ConstructionRibbon-Cutting
Country Walk Timeline
South Beach Timeline
Lease ExecutionCompleted Sept. 2015
ArchitectProgram & Design
ConstructionRibbon-Cutting
Cutler Bay Timeline
Lease ExecutionCompleted Sept. 2015
ArchitectProgram & Design
ConstructionRibbon-Cutting
North Dade Timeline
Jackson Bond Quarterly Report – January to March 2017 Page 14 of 18
Operations at the two new centers are meeting or exceeding expectations, with Country Walk averaging 18 patients per day and Keystone Point averaging 14 per day.
The Cutler Bay is under construction, with a ribbon cutting and grand opening schedule for summer 2017.
The South Beach location remains in the permitting phase as we work through unexpected regulatory issues related to City of Miami Beach building codes.
The North Dade Health Center site is in the permitting phase and tentatively scheduled to open in late 2017.
The Doral location, which is not funded with bond proceeds, is tentatively scheduled to open in early 2018.
Jackson Bond Quarterly Report – January to March 2017 Page 15 of 18
Equipment and Technology Purchases
Bond proceeds were used this quarter to fund $6,565,053 in miscellaneous medical equipment and technology, including $5,493,111 from the Technology & Equipment area and $1,071,942 from Infrastructure. Those funds are being used at the following Jackson sites:
Systemwide Jackson
Memorial Jackson North
Jackson
South
Holtz
Children’s Other Sites
$0 $4,773,442 $50,518 $995,841 $525,793 $219,459
A line-item list of the purchases is attached to this report.
Bond proceeds were also used this quarter to fund $4,642,662 in information system purchases, which were drawn from the Technology & Equipment area to be used toward the fourth phase of Jackson’s electronic health record system upgrade, IT hardware, and IT licenses.
Additional Project Updates
Construction continues on the major renovations to units 6B and 3A in East Tower. Unit 6B is a pediatric inpatient unit, and 3A is a maternity unit that will mirror the M.B. Fernandez Family Little Miracles Maternity Suites in unit 3B. Both are expected to be completed in late summer 2017.
A new parking lot at Jackson North Medical Center began construction in March, with completion scheduled for April.
Construction and equipping of three major diagnostic suites at Jackson Memorial Hospital are scheduled to begin in April: the biplane, linear accelerator, and CT scan suites. All are scheduled for completion in late 2017.
Three bond-funded projects were formally closed during the reporting period, meaning the contracts were completed and all payments fully reconciled. They include:
Jackson Memorial Hospital: West Wing 10 Renovation
Budget & Funding Sources
Source Original Approved Final Closeout Difference
Miracle Bonds $2,565,304 $2,636,700 $71,396
Capital Contribution $71,396 $97,989.86 $26,593.86
Other Sources $617,943.58 $617,943.58
TOTAL $2,636,700 $3,352,633.44 $715,933.44
Line-Item Allocations
Line Item Original Approved Final Closeout Difference
Design $192,000 $95,291.98 ($96,708.02)
Construction $1,955,000 $2,918,046.60 $963,046.60
FF&E $250,000 $339,294.86 $89,294.86
Contingency/Balance $239,700 $0 ($239,700)
TOTAL $2,636,700 $3,352,633.44 $715,933.44
Jackson Bond Quarterly Report – January to March 2017 Page 16 of 18
Jackson Memorial Hospital: Clark Diagnostic Treatment Center Air Handler Units
Budget & Funding Sources
Source Original Approved Final Closeout Difference
Miracle Bonds $227,000 $168,500 ($58,500)
TOTAL $227,000 $168,500 ($58,500)
Line-Item Allocations
Line Item Original Approved Final Closeout Difference
Design $ 7,000 ($7,000)
Construction $60,000 ($60,000)
FF&E $140,000 $168,500 $28,500
Contingency/Balance $ 20,000 ($20,000)
TOTAL $227,000 $168,500 ($58,500)
Perdue Medical Center Chiller Replacement
Budget & Funding Sources
Source Original Approved Final Closeout Difference
Miracle Bonds $550,000 $500,000 ($50,000)
TOTAL $550,000 $500,000 ($50,000)
Line-Item Allocations
Line Item Original Approved Final Closeout Difference
Design
Construction $500,000 $500,000 $0
FF&E
Contingency/Balance $ 50,000 ($50,000)
TOTAL $550,000 $500,000 ($50,000)
Further details of these projects are provided in the attached project closeout forms.
Jackson Bond Quarterly Report – January to March 2017 Page 17 of 18
Three additional bond-funded projects were functionally completed during the reporting period, meaning they are in service. They include:
Jackson North Medical Center: Nuclear Medicine Suite
Jackson North Medical Center: Fluoroscopy Suite
Jackson Bond Quarterly Report – January to March 2017 Page 18 of 18
Jackson South Community Hospital: CT Scanner
Our staff looks forward to continue working with the Citizens’ Advisory Committee to track the progress of the Jackson Miracle-Building Bond Program, ensuring the highest levels of transparency and seeking expert input.
If you have any questions, please feel free to call me.
Attachments
c: Joe Arriola, Chairman and Members, Public Health Trust Board of Trustees
Item # Location Funding Source County Bond Category Activity # Activity Description Total Allocated for Ac vity CAC/Quarterly Approval Date3600414 All Other Locations Miracle Bldg Bonds 2 ‐ Infrastructure Projects 160170001 JRSHC AIR HANDLER 36,850 03/31/173180438 Holtz Children's Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 110170059 ET PERINATAL CART 64,410 03/31/173180438 Holtz Children's Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 110170045 NIC INFANT INCUBATOR 190,538 03/31/173180437 Holtz Children's Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 110170045 NIC INFANT INCUBATOR 140,000 03/31/173180017 Holtz Children's Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 110170070 RADIOLOGY ANYWHERE SOFTWARE 112,320 03/31/173120429 Jackson Behavioral Health Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 110170081 OPERATION AHU 25,300 03/31/173160499 Jackson Memorial Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 110170077 ANESTHESIA ENDOSCOPE 108,908 03/31/173200667 Jackson South Community Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 120170017 JS SCANNER 102,818 03/31/173200667 Jackson South Community Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 120170007 JS ULTRASONIC UNIT 180,964 03/31/173200667 Jackson South Community Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 120170008 JS EEG EQUIPMENT 75,823 03/31/173200577 Jackson South Community Hospital Miracle Bldg Bonds 2 ‐ Infrastructure Projects 120170012 JS BRONCHOSCOPE 34,010 03/31/17
SUB‐TOTAL INFRASTRUCTURE PROJECTS 1,071,942
Item # Location Funding Source County Bond Category Activity # Activity Description Total Allocated for Ac vity CAC/Quarterly Approval Date3110405 All Other Locations Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170062 ENT CLINIC MEDICAL EQUIP 26,401 03/31/173110405 All Other Locations Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170065 ENT LARYNGOSCOPE 32,527 03/31/173110405 All Other Locations Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170058 SURGICAL CLINIC SCOPES 66,150 03/31/173110405 All Other Locations Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170064 ENT ENDOSCOPE 10,842 03/31/173110405 All Other Locations Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170063 ENT CLINIC LARYNGO FIBERS 21,389 03/31/173180567 Holtz Children's Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170052 PEDI TEE PROBE MED EQUIP 18,525 03/31/173160500 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170077 ANESTHESIA ENDOSCOPE 1,735,676 03/31/173160500 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170048 RADIOLOGY MRI 111,750 03/31/173160500 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170049 MRR ICE MAKER 5,313 03/31/173160500 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170041 OR LIGHTSURGI 93,000 03/31/173160500 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170040 SIC VENTILATORS 1,629,369 03/31/173160500 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170050 OR FREEZER 8,504 03/31/173160500 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170051 MED SURG CERNER EQUIP 313,964 03/31/173160500 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170044 GI STATION PROCESSORS FOR GI 129,237 03/31/173160257 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170075 TRANS SVCS BLOOD REFRIGATOR 6,923 03/31/173160251 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170076 ANATOMIC MEDICAL EQUIP 96,600 03/31/173160251 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170066 READING TABLE 53,136 03/31/173160251 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170074 TRAN SVCS INCUBATOR 12,898 03/31/173160251 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170073 CORE LAB REFRIGERATOR 14,753 03/31/173160251 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170072 SIC CART 114,100 03/31/173160251 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170068 OR MEDICAL EQUIPMENT 38,192 03/31/173160251 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170067 OR COLPOSCOPE 13,003 03/31/173160251 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170069 Anesthesia ULTRA SOUND 90,580 03/31/173160059 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170060 ANESTHESIA VIDEO BRONCHOSCOPE 179,213 03/31/173160052 Jackson Memorial Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170057 OR CART WASHER CONTAINER RACK 18,324 03/31/173300411 Jackson North Medical Center Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 130170003 JNMC ICE MAKER 50,518 03/31/173200631 Jackson South Community Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 120170018 JS SURGERY MED EQUIP 45,756 03/31/173200588 Jackson South Community Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 120170009 JS TRAUMA MEDICAL EQUIP7 5,768 03/31/173200581 Jackson South Community Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 120170016 RESPIRATORY THERAPY VENTILATOR 38,890 03/31/173200573 Jackson South Community Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 120170007 JS ULTRASONIC UNIT 175,000 03/31/173200568 Jackson South Community Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 120170014 PATHOLOGY MEDQUIP7 9,445 03/31/173200567 Jackson South Community Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 120170015 PATHOLOGY MEDICAL RQUIP 43,727 03/31/173200566 Jackson South Community Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 120170010 JS BLOOD BANK FREEZER 8,639 03/31/173200539 Jackson South Community Hospital Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 120170018 JS SURGERY MED EQUIP 275,000 03/31/17
SUB‐TOTAL MEDICAL EQUIPMENT 5,493,111
Item # Location Funding Source County Bond Category Activity # Activity Description Total Allocated for Ac vity CAC/Quarterly Approval Date3141001 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170080 IT LICENSES 158,501 03/31/173141001 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 31022104 EHR Phase 4C‐ JATA / NUANCE 408,664 03/31/173141001 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 31019104 EHR Phase 4B‐ JATA / NUANCE 612,996 03/31/173141001 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 31017104 EHR Phase 4A‐ JATA / NUANCE 1,940,932 03/31/173141002 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 31017104 EHR Phase 4A‐ JATA / NUANCE ‐ 03/31/173141002 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170046 IT COMPUTER NETWORK 249,655 03/31/173141002 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170071 NETWORK SUPPORT SERVER 495,323 03/31/173141003 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170079 NETWORK SUPP ENDPOINTS 212,446 03/31/173141003 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 31017104 EHR Phase 4A‐ JATA / NUANCE 76,928 03/31/173141003 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 110170047 IT ENDPOINT COMP NETWORK 411,047 03/31/173141004 System‐Wide Miracle Bldg Bonds 3 ‐ Medical and Technology Equipment and Software 31017104 EHR Phase 4A‐ JATA / NUANCE 76,170 03/31/17
SUB‐TOTAL TECHNOLOGY EQUIPMENT SOFTWARE 4,642,662
Grand‐Total 11,207,714
Jackson Miracle-Building Bond Program Public Health Trust
Project Close Out Report
Bond Project Name: Perdue Medical Center Chiller Replacement
Activity # 58016010 Approval Date 01/27/16
Scope and description: Installation of a new chilled water system, including two new cooling towers, two new larger capacity chillers, piping, primary water pumps, condenser water pumps, electrical controls, insulation, and a new transformer.
Budget & Funding Sources
Source Original Approved Final Closeout Difference
Miracle Bonds $550,000 $500,000 ($50,000)
Capital Contribution
Philanthropic Donation
Other Sources
TOTAL $550,000 $500,000 ($50,000)
Line-Item Allocations
Line Item Original Approved Final Closeout Difference
Design
Construction $500,000 $500,000 $0
FF&E
Contingency/Balance $ 50,000 ($50,000)
TOTAL $550,000 $500,000 ($50,000)
Project Team
Architect/Engineer: N/A
Contractor: Johnson Controls
Closeout Notes:
The project was closed in September 2016.
Jackson Miracle-Building Bond Program Public Health Trust
Project Close Out Report
Bond Project Name: Jackson Memorial Medical Center – Air Handler Replacements, DTC
Activity # 51016018 Approval Date 3/23/16
Scope and description: Replacement of three air handler units (231, 232 and 233) on the roof of the Clark Diagnostic & Treatment Center, which support the interventional radiology department on the second floor. The scope included complete replacement of the units, ductwork, controls, piping, smoke detectors, permits, rentals, labor, equipment, and installation with five years of warranty from the original equipment manufacturer.
Budget & Funding Sources
Source Original Approved Final Closeout Difference
Miracle Bonds $227,000 $168,500 ($58,500)
Capital Contribution
Philanthropic Donation
Other Sources
TOTAL $227,000 $168,500 ($58,500)
Line-Item Allocations
Line Item Original Approved Final Closeout Difference
Design $ 7,000 ($7,000)
Construction $60,000 ($60,000)
FF&E $140,000 $168,500 $28,500
Contingency/Balance $ 20,000 ($20,000)
TOTAL $227,000 $168,500 ($58,500)
Project Team
Architect/Engineer: N/A
Contractor: Marvi Builders (SBE)
Closeout Notes:
The project was closed in February 2017.
Jackson Miracle-Building Bond Program Public Health Trust
Project Close Out Report
Bond Project Name: West Wing 10 Patient Floor Modernization
Activity # 51014013 Approval Date 03/30/15
Scope and description: Renovation and modernization of WW10 patient floor to include new finishes, new furniture, new equipment, new nurse call system, and three ADA- compliant bathrooms, as well as, upgrades to mechanical, electrical, and plumbing systems.
Budget & Funding Sources
Source Original Approved Final Closeout Difference
Miracle Bonds $2,565,304 $2,636,700 $71,396
Capital Contribution $71,396 $97,989.86 $26,593.86
Philanthropic Donation
Other Sources $617,943.58 $617,943.58
TOTAL $2,636,700 $3,352,633.44 $715,933.44
Line-Item Allocations
Line Item Original Approved Final Closeout Difference
Design $192,000 $95,291.98 ($96,708.02)
Construction $1,955,000 $2,918,046.60 $963,046.60
FF&E $250,000 $339,294.86 $89,294.86
Contingency/Balance $239,700 $0 ($239,700)
TOTAL $2,636,700 $3,352,633.44 $715,933.44
Project Team
Architect/Engineer: FDC In-house Architect, G&G Engineering (SBE) – Final Contract Amount $95,291.98
Contractor: Lego Construction (SBE) – Final Contract Amount $2,259,310.61
SBE’s Subcontractors: ComforTech Air Conditioning Inc, Haber & Sons Plumbing, Century Fire, Astro
Painting, Amion Enterprise, Stucco Drywall Contractors (SDC) Inc.
Closeout Notes:
The project was completed in June 2016, closed December 2016.