1 TRADE EXHIBITION PROJECT Project Plan Attending the National trade exhibition of Maldives Author: Zihuna Faiz (13185) Creation Date:09/23/2010
Transcript
Page 1: Trade Exhibition Project Management

1

TRADE EXHIBITION PROJECT

Project Plan

Attending the National trade

exhibition of Maldives

Author: Zihuna Faiz (13185)

Creation Date:09/23/2010

Page 2: Trade Exhibition Project Management

2

INTRODUCTION

The company that I have chosen for this assignment is a distributor of Resort-ware, XYZ Resort

Suppliers Maldives, is one of the distributor of Resort-ware in the Maldives. Established in

2002, it is a privately held company, employing more than 50 staffs. It is the distributor and

importer of high-end resort-ware, kitchen ware and electrical items in the Maldives. The

company is a supplier of cost effective and quality resort ware. The company covers a huge

range and variety of products and offer quality and efficient service. The company provides

premium brands, after-sales support, quality spare parts and excellent technical service for the

machines and equipment.

Keeping in line with the well-known brands of “Illy” Coffee, Food Service Range of “Paderno”

kitchen utensils, “SIRMAN” food service equipment, “NuovaSimonelli” Coffee Machines,

“Candola” refill lamps, “SIRMAN” kitchen machinery XYZ company provides high-quality

solutions coupled with consultation for the tourism industry.

We put a great effort to provide and deliver tailored solutions for our customers in the hospitality

industry in which the quality and brand of the products, equipments and machinery are

concerned. We have always valued the relationships with our current and future clients through

our

However, the company has been facing difficulty in reaching the main segment of the target

market. Particularly, there has been a serious gap in the awareness of the services provided

by the company.

Purpose of Plan

Since, it is a key initiative of the company to grow our customer base and promote our services;

the company has decided to participate in a trade exhibition held in Maldives. Trade fair is an

important tool, as it involves face-to-face communication. It is a means of displaying products to

persuade and remind prospective buyers about the enterprise. Participation at exhibition’s events

is an excellent opportunity to present the company to the targeted audience.

Page 3: Trade Exhibition Project Management

3

This is a project plan prepared for participation in the Maldives Hotel & Trade Exhibition which

will be held at Dharubaaruge, the premier convention and conference facility in the to be held in

6 months time.

The Project Plan defines the following:

Plan purpose

Scope definition

Project deliverables

Project Milestones

Technical Requirements

Limitations and exclusions

Work Breakdown Structure of the project

Network Diagram

Reflective summary

Page 4: Trade Exhibition Project Management

4

The scope definition

To deliver a trade exhibition project plan in order to gain the attention of the target

customers (business and resorts) of the company and expand the customers base.

Deliverables

The Project will

Demonstration of sample products.

Well-trained staffs.

Presentation of products demo using video clips.

Printed materials (brochures, banners, order forms, business cards)

Show give-away

Exhibition stand prepared.

A lead review will be prepared

Milestones

The following represent key project milestones, with estimated completion dates:

Milestone Estimated Completion Date

Budget prepared 01/08/2010

Budget Approved 18/08/2010

Page 5: Trade Exhibition Project Management

5

Project plan prepared 28/08/2010

Confirmation of stall 01/09/2010

Stall layout sketched 20/09/2010

Staff selected 25/09/2010

Staff trained 01/10/2010

Promotional plan prepared 15/10/2010

Promotional materials prepared 25/10/2010

Printed materials 10/11/2010

Stand assembled 03/10/2010

Conducting promotion 03/10/2010

Launching the exhibition 01/02/2011

Packing up Stall 04/02/2011

Lead review 10/02/2011

E-mail to visitors 12/02/2010

Technical requirements

The demo presentation requires visuals and graphics with use of projector and pc.

All displaying banners and posters should meet the criteria set in the designing stage

Negotiation with the trade fair organizers for one of the busiest sites when confirming the

stand.

While training staff members have to be thoroughly briefed on issues like: the objectives

of the fair; their duties; the products to be exhibited; rules of the trade fair.

The furnishing and decorations of the stand have to be suitable and adequate; creating

good flows of traffic and displaying the products and materials appropriately

Promotional activities should include E-mailing customers & key prospects and sending

passes to best customers

Printed materials should include brochures, price lists, order forms, and business cards.

Page 6: Trade Exhibition Project Management

6

During the launch of the exhibition, staffs should create a professional image and all

times, one person should work directly with customers while the other should keep an

eye on the booth

When reviewing the leads, the contacts, sales goals, profit, new ideas, and information

gained should be considered

Work breakdown structure

The work breakdown structure of the project is map of the project to be done. It is used to assure

that all the work elements in the exhibition project are being identified. The WBS will also help

to integrate the project with the current organization and to establish a basis control.

The WBS includes the major area of work; concept development, promotion, training, HR

allocation, organizing materials, setting stall, launching the exhibition and post-show activities.at

the top of the charter is the project end item. Note that the different levels of the structure

represent information for different levels of work elements. The level one represents the total

objective of the project and level 2, 3,4, 5, 6,7 represents the tasks and subtasks to be performed

in order to achieve the objective of the project. It it’s divided in to subtasks and work packages.

The WBS us generated around the deliverables. An additional key attribute of the WBS is that it

is a hierarchical decomposition of the work. This decomposition (or subdivision) clearly and

comprehensively defines the scope of the project in terms of individual sub-deliverables that the

project participants can easily understand.

During the first stage of the project as represented in WBS involves concept development, which

requires planning and budgeting. In the planning stage, the nature of the enterprises and their

marketing problems should shape the specific objectives that the show. should try to achieve at

the trade fair. For trade exhibition careful planning is vital because trade fairs involve many

details. Detailed budget should be drawn up immediately after the decision to organize a trade

fair is made. Although it may be difficult to decide on the exact budget, it is necessary to have

Page 7: Trade Exhibition Project Management

7

detailed information and quotations regarding the overall accrued costs. Cost estimates should

therefore be obtained on time. These both activities are drawn in the same level as it.

The HR allocation of the project is of importance as coordination of the trade fair; stand

designing; registering; taking care of communications; controlling passes; cleaning; taking care

of security needs to be well managed by knowledgeable staffs. All staff members have to be

thoroughly briefed before the show starts on issues like:

The objectives of the fair; their duties; the products of the exhibitors; rules of the trade fair in the

training session ot be taken. Choosing an appropriate stand location is a major factor involved in

the trade exhibition planning setting stalls and confirmation is important.

Other sub tasks in the WBS are as follow:

Identifying Budget, Approve Budget, Produce plan ,Selecting staffs, Assigning task to staffs,

Conduct training, Sketch Layout, Prepare promo- plan, Design materials, Printing, Order give-

away, Prepare video,Stall setup ,E-mail customers & key Prospects, Send passes to best

customers, Package materials, Material transportation to location, Materials unpacking,

Arranging materials, Exhibition, Lead review, E-mail to show visitors.

Project integration management

The project integration Management knowledge area is concerned with coordinating all aspects

of the project plan and is highly interactive. It involves project planning, project execution, and

change control. All these processes occur through out the life of the project and are repeated

continuously while working on the project. Project planning, execution, and change control are

tightly linked. The processes that constitute Project Integration Management include the

following:

Page 8: Trade Exhibition Project Management

8

Develop project charter

Develop preliminary project scope

Develop project management plan

Direct and manage project execution

Monitor and control project work

Integrated change control

Close project

It is recommended that the Project Change Management and Project Change Planning documents

be referred to and used to address these concerns at a more detailed level in the management of

the trade exhibition project..

Projects almost always bring significant change to organizations and are therefore disruptive.

People inherently dislike change and are skeptical towards those things that bring about the

change. Those that aren’t directly involved with the project team are likely worried about their

role and what might happen to them as the changes take place in the organization. It’s up to the

project team to recognize this as a serious matter and plan the appropriate communications to

ensure correct expectations.

Integrated Project Management sets the path for companies large and small to meet their goals

faster, more efficiently and with higher-quality results - whether embarking on a major capital

project or developing a new product or critical initiative.

IPM can help to tighten timelines and reduce risk through laser-focused planning and disciplined

execution.

Integrate Project Plan (IPP). The specific parts of the IPP related to the inputs for Controlling

are: Some of the important areas in context with our organizations include:

Overall Change Management Plan. Defines how changes to the project’s

scope/requirements, costs, schedule, quality, and risks will be coordinated for

understanding and possible impact in all of the planned areas. Ensures the ongoing

integrity of the project’s Integrated Project Plan.

Page 9: Trade Exhibition Project Management

9

Quality Management Plan. Addresses how Quality Control will monitor the specific

project results to determine if they comply with relevant quality standards and identifies

ways to eliminate causes of unsatisfactory performance.

Risk Management Plan. Addresses how Risk Response Control (mitigation and

contingencies) will respond to changes in risk over the course of the project.

Communication Plan. Addresses the collecting and disseminating of performance

information. This may includes status reporting, progress measurement and forecasting.

Furthermore, it is important to understand that in some organizations, selections, and

management of projects often fail to support the strategic plan of the organization. So a the

integration of the project management system is one in which all of the parts in the project

are related. A change in any on of the parts will influence the whole. Every organization has

a customer it is seeking to satisfy. The customers set the raison d’etre for the organization. In

with

Some of the benefits that our company will gain with the use of IPM include the following:

Knowledge is transferred from project level to the organization

Improved planning through better understanding of process performance

Lower cost of process planning in projects as reuse is promoted

Improved coordination among people involved in a project

Commitment to the organization is improved as communication & sharing between teams

is facilitated

Institutionalizing key management practices

Reuse of knowledge

Integration of plans

Tracking dependencies & collaboration issues

“Post mortem” analysis

There are two dimensions in the IPM. The first is the technical side of the management process

which consists of the formal, disciplined, pure logic parts of the process. The technical side

relies on the formal information system available. This dimension include, planning,

scheduling, and controlling a project.

Page 10: Trade Exhibition Project Management

10

The second dimension is the socio-cultural side of the project management process. In contrast to

with the orderly world of the project planning, this dimension involves the much messier,

often contradictory and paradoxical world of implementation. It centers on creating a

temporary social system within a larger organizational environment that combines the talent

of a divergent set of professionals working to complete the project. I as a project manager

have considered this as crucial and have planned on giving training for the participating staffs

of the projects. Further it will be recommended if other staffs in the organization are made

aware of the effects of attending the exhibition. Their work load may increase due to increase

in customer basse, more sales needs to be generated, bigger transactions will take place.

Thus, they all need to be part of the project taking place directly or indirectly.

Network Diagram

A Network Diagram is a visual representation of a project’s schedule. Well known complements

to network diagrams include the PERT and Gantt charts. A network diagram in project

management is useful for planning and tracking the project from beginning to finish. It

represents a project’s critical path as well as the scope for the project.A good network

diagram will be a clear and concise graphic representation of a project.

The network diagram is a technique for illustrating how impacts are related and what the

consequences of impacts are. For example, it may be possible to fairly accurately predict the

impact of increased diversions or higher irrigation efficiencies on the low flow regime of a

river. However, there may be many and far reaching secondary or tertiary consequences of a

change in low flow. These consequences can be illustrated using network diagrams. For

example, reduced low flows are likely to reduce the production of fish which may or may not

be of importance depending on the value (either ecological or economic) of the fish. If fish

are an important component of diet or income, the reduction may lead to a local reduction in

the health status, impoverishment and possibly migration. Also, reduced low flow coupled

with increased pollution, perhaps as a result of increased agricultural industry, may further

damage the fish population as well as reduce access to safe water.

Page 11: Trade Exhibition Project Management

11

CPM Benefits

• Provides a graphical view of the project.

• Predicts the time required to complete the project.

• Shows which activities are critical to maintaining the schedule and which are not.

CPM Limitations

While CPM is easy to understand and use, it does not consider the time variations that can have a

great impact on the completion time of a complex project. CPM was developed for complex

but fairly routine projects with minimum uncertainty in the project completion times. For less

routine projects there is more uncertainty in the completion times, and this uncertainty limits

its usefulness.

Page 12: Trade Exhibition Project Management

12

Activity dependency table

Activity Description Dependency Activity Duration (Days)

A Identifying Budget 10

B Approve Budget A 7

C Produce plan B 10

D Selecting staffs C 4

E Assigning task to staffs D 3

F Conduct training E 7

G Sketch Layout C 20

H Prepare promo- plan C 8

I Design materials C,H 20

J Printing I 6

K Order give-away I 20

L Prepare video H 15

M Stall setup G 2

N E-mail customers & key Prospects H 1

O Send passes to best customers H 4

P Package materials k,L,J 10

Q Material transportation to location M,P 1

R Materials unpacking P,Q 2

S Arranging materials M,R 3

T Exhibition N,O,S 3

U Lead review T 7

V E-mail to show visitors T 7

Page 13: Trade Exhibition Project Management

13

Reflective summary

The project undertaken for the planning of the trade exhibition was a very knowledgeable experience. The

whole planning and budgeting helped to understand various aspects needed to be concerned in terms if financial and

handling resources. The scope development and deliverables identification and especially the development s of the

WBS was a great experience. Major difficulty was in making the network diagram and the WBS, effective planning

helped to overcome this.