+ All Categories
Home > Documents > Transcript 9.28.10 Dipple Marsden

Transcript 9.28.10 Dipple Marsden

Date post: 05-Apr-2018
Category:
Upload: mariner12
View: 226 times
Download: 0 times
Share this document with a friend

of 69

Transcript
  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    1/69

    SUPERIOR COURT OF NEW JERSEYLAW DIVISIONCIVIL PARTUNION COUNTY, NEW JERSEYDOCKET NO.: UNN-L-140-08

    A.D. NO.: ____________

    CRANFORD DEVELOPMENT )ASSOCIATES )

    )Plaintiff ) TRANSCRIPT

    )vs. ) OF

    )TOWNSHIP OF CRANFORD ) TRIAL

    )Defendant )

    Place: Union County CourthouseTwo Broad StreetElizabeth, New Jersey 07207

    Date: September 28, 2010A.M. Session

    BEFORE:

    THE HONORABLE LISA F. CHRYSTAL, J.S.C.

    TRANSCRIPT ORDERED BY:

    CARL R. WOODWARD, ESQ.(Carella, Byrne, Bain,Gilfillan, Cecchi, Stewart & Olstein)

    APPEARANCES:

    STEPHEN M. EISDORFER, ESQ. (Hill, Wallack, LLP)Attorney for the Plaintiff

    CARL R. WOODWARD, ESQ. (Carella, Byrne, Bain,Attorney for the Defendant Gilfillan, Cecchi,

    Stewart & Olstein)

    REGINA CALDWELL

    UTOMATED TRANSCRIPTION SERVICESP.O. Box 1582

    Laurel Springs, New Jersey 08081(856) 784-4276

    SOUND RECORDEDOperator: Smishkewych

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    2/69

    2

    I N D E X

    September 28, 2010 - A.M. Session

    DIRECT CROSS REDIRECT RECROSS

    PLAINTIFFS WITNESS:

    Mr. Dipple 3 24 30

    DEFENSE WITNESS:

    Mr. Marsden 32 50 66 67(Eisdorfer) (Eisdorfer)

    63(McKenzie)

    EXHIBITS IDENTIFIED EVIDENCE

    D-159 Control Point Survey 18

    D-162 3/31/10 Plans 14

    D-180 Mr. Marsdens Report - 9/16/10 33

    D-184 Mr. Dipples Letter - 9/2/10 15

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    3/69

    Mr. Dipple - Cross 3

    THE COURT: Welcome back, everyone.1

    MR. WOODWARD: Good morning, Your Honor.2

    THE COURT: You can resume the stand and3

    youre still under oath. Were on the record?4

    COURT PERSONNEL: Yes, Your Honor.5

    THE COURT: Okay.6

    MR. WOODWARD: Thank you, Your Honor.7

    MICHAEL DIPPLE, PLAINTIFFS WITNESS, PREVIOUSLY SWORN8

    CROSS-EXAMINATION BY MR. WOODWARD:9

    Q. Mr. Dipple, Im going to show you P-63A,10

    which is your site analysis dated July 30, 2010.11

    Youve seen that before, correct?12

    A. I have, yes.13

    Q. All right. I just want to revisit the issue14

    of fire trucks for a minute. If a fire truck, during a15

    flooded stay -- during a flood, has to come into this16

    property, would it come in on the easterly side17

    driveway and circle through? If Birchwood Avenue was18

    flooded, based on your knowledge of Birchwood Avenue?19

    A. Yes. I suppose if the flood was extreme enough to20

    pass the -- at the same time there was a fire, the21

    flood was high enough to surpass the western most22

    driveway, then yeah, they would enter the eastern23

    driveway.24

    Q. Now, is there any ability for a fire truck,25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    4/69

    Mr. Dipple - Cross 4

    assuming you couldnt get out the westerly driveway, if1

    it came in the easterly driveway, to turn around, based2

    on this plan?3

    A. No, I dont think it could -- well, it may be able4

    to back up underneath Building A, potentially. But,5

    again, the floodwaters are only for a period of hours.6

    So, in some cases the extreme floods may only be there7

    for a period of hours, so.8

    Q. So, a fire truck could be stuck there for a9

    period of hours?10

    A. If --11

    Q. Without being able to get out or turn around?12

    A. If a fire coincided with a hundred year flood13

    event, I suppose that he would have to wait a couple14

    hours to turn his truck around.15

    Q. Well, one other thing. I mean if a fire16

    truck had to come on to this site during a major flood17

    event, and came in on the easterly sideline and is up18

    here in the -- fighting a fire in Building A or19

    Building B, and Birchwood Avenue is flooded, how would20

    the other people, the residents, get out? Could the21

    people from Building A get out?22

    A. Well, Im --23

    Q. Drive their cars out, I mean.24

    A. From Building A?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    5/69

    Mr. Dipple - Cross 5

    Q. Yeah.1

    A. If the fire truck was blocking the exit, would2

    they remove their cars, I dont know. I dont know3

    where the truck would be. The road is 24 feet wide and4

    thats passable by two vehicles in either direction.5

    So, if the truck was on the access road, yes, they6

    could drive right past it. A standard truck is nine,7

    ten feet wide and I believe we have minimum, per8

    Cranford standards, of 24 feet wide aisles, so.9

    Q. Now, with respect to the photo you were shown10

    yesterday, D-172, --11

    A. Yes.12

    Q. -- which is a photograph of the parking lot13

    taken by Mr. Marsden.14

    A. Yes.15

    Q. Do you recall that?16

    A. I do.17

    Q. Okay. Now, what was the height above the18

    parking lot that that photograph was taken?19

    A. What was the height above the parking --20

    Q. Yeah. I mean it was taken at eyelevel,21

    correct?22

    A. Okay, yeah. Yeah. Sorry.23

    Q. About five feet?24

    A. I would say, yeah, about five feet, Id say.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    6/69

    Mr. Dipple - Cross 6

    Q. Yes. And the distance to the back of the1

    parking lot is about four or 500 feet, isnt it?2

    A. Potentially, yeah.3

    Q. So, we have a very shallow angle trying to4

    determine whether theres any water in the back?5

    A. Yeah. It looks like theres not. Thats what Im6

    saying.7

    Q. But you really cant tell, can you, from that8

    angle?9

    A. Thats the -- the summary we made, from looking at10

    that photograph, was that theres flooding in the front11

    and not in the back.12

    Q. You werent there at the site when this13

    photograph was taken, were you, sir?14

    A. No.15

    Q. In fact, youve never been on the site with a16

    major -- with a significant rainfall like this, have17

    you?18

    A. I dont know how significant that rainfall is, but19

    I have been on the site on rainfall events, yes.20

    Q. Well, where this parking lot was this21

    flooded?22

    A. Mr. Woodward, the pipe was clogged --23

    Q. Can you answer my question, sir? Yes or no?24

    A. I dont know. I asked -- I answered your25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    7/69

    Mr. Dipple - Cross 7

    question.1

    Q. Now, you testified yesterday, as I recollect,2

    that the storm water system design that you were coming3

    up with -- Im showing you P-91 for identification.4

    A. Yes.5

    Q. Now, this kind of storm water design and the6

    analysis that went into that was typical of what you do7

    for clients during your due diligence, correct?8

    A. Yes, something like that.9

    Q. Well, did you say that or didnt you?10

    A. I did say that. That is what we -- this kind of11

    analysis is what we do for due diligence. In fact, Im12

    doing it right now on another project.13

    Q. All right. You did your due diligence in14

    this -- on this project back in 2008, didnt you?15

    A. The original site investigation report was done in16

    2008, yes.17

    Q. Well, that was -- there was a design put18

    together at that point, wasnt there?19

    A. No. There was a sketch, there was a site sketch20

    by Lasar (phonetic), the architect. But the due21

    diligence report doesnt typically include a storm22

    water management design.23

    Q. So, what you did was not due diligence back24

    in 2008?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    8/69

    Mr. Dipple - Cross 8

    A. You can call it -- I dont know what term youre1

    using. Its called site investigation report and its2

    -- it -- the scope of the site investigation report was3

    given to my client and he signed off on it. And whats4

    included in the report is what he asked me to do.5

    Q. But you used the term yesterday due6

    diligence. Did you consider that to be due diligence7

    by a poten -- by a prospective buyer of a piece of8

    property?9

    A. It is a form of due diligence, I would agree. You10

    know, I dont have the Websters definition of due11

    diligence in front of me, but its a -- the report -- I12

    may have said that, but the report is site13

    investigation report. That is what we prepared.14

    Q. So, what you did in 2008 wasnt due15

    diligence?16

    A. Sir, I dont agree with that, no. I dont agree17

    with that assessment. We use the term due diligence as18

    a means of investigation into issues and we highlight19

    them. If you want to call it due diligence, you can.20

    If you dont, if you want to show me that I have the21

    definition wrong, please do so.22

    Q. Well, you, in that site investigation report,23

    didnt do any flood hazard analysis, did you?24

    A. No, we did not.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    9/69

    Mr. Dipple - Cross 9

    Q. You didnt do any storm water analysis, did1

    you?2

    A. No, I believe we commented on storm water, though.3

    There is some -- I would say no. I dont have the4

    report in front of me. Could I be provided with that5

    report?6

    Q. Well, what do you remember?7

    A. I would like to see the report, if I can answer8

    questions in an exhibit correct.9

    Q. Well, okay. Well take a minute and get your10

    report. Hold on.11

    A. Okay.12

    Q. Im going to show you whats been marked for13

    identification as a report dated D -- or document D-43,14

    Site Investigation Report, dated May 21, 2008. Im15

    going to show it to you. Have you ever seen that16

    before?17

    A. I have, yes.18

    Q. Is this the report you prepared?19

    A. Yes.20

    Q. Okay. You said you wanted to review it.21

    Please take your time and review it.22

    A. Yes, theres a section, Section 6, called Storm23

    Water Management, where we discuss the storm water24

    management rule and how it would apply to this project,25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    10/69

    Mr. Dipple - Cross 10

    and we provide a summary of that and some1

    recommendations.2

    Q. And your recommendation at this point was3

    just to limit it to the impervious surface to that4

    which currently exists, correct?5

    A. Thats correct.6

    Q. So, you didnt take into account the parking7

    lot behind the building at 215 Birchwood, did you?8

    A. No. I dont believe we had a survey of the9

    parking lot at this point. So, I dont think I10

    couldve done that.11

    Q. Now, you said yesterday, as I recollect, that12

    your August 19th report -- withdraw the question. Now,13

    I think you have up there P-87, which is your report of14

    August 19. Here we go, P-87.15

    A. Yes.16

    Q. Now, I think you said that this is what17

    constituted the type of due diligence you do nowadays,18

    correct?19

    A. I -- its a conceptual storm water management20

    analysis. If I used the term due diligence, then so be21

    it. I -- this is what it is. Its a conceptual storm22

    water analysis.23

    Q. But you were told by Mr. Marsden about the24

    storm drainage issue with respect to that parking lot25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    11/69

    Mr. Dipple - Cross 11

    back in 2009, werent you? When you met with him?1

    A. Mr. Marsden pointed out depressions throughout the2

    site, which we incorporated into the design. The3

    conceptual storm water management analysis, I should4

    say, not the design. And he pointed out the valves and5

    rendered an opinion on the valves at that point, yes.6

    Q. And the valves were part of a storm water7

    detention system that involved that parking lot, isnt8

    that what he told you?9

    A. Thats what he told me.10

    Q. So, in 2009, I think you said July of 2009,11

    you knew at least that the township engineer was12

    telling you this was an area that needed to be studied.13

    But you didnt study that until August of 2010, did14

    you?15

    A. I was not asked to study it, no.16

    Q. Now, Mr. Creelman submitted a report, back in17

    October of 2009, in which he told you that there was a18

    flood hazard problem on this site, didnt he?19

    MR. EISDORFER: Your Honor, this question has20

    been asked and answered previously.21

    THE COURT: Its cross-examination, so Ill22

    allow it.23

    CONTINUED BY MR. WOODWARD:24

    Q. Did you hear the question, sir?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    12/69

    Mr. Dipple - Cross 12

    A. Can you just repeat it? Im sorry, I --1

    Q. Sure. Mr. Creelman submitted a report, in2

    October of 2009, in which he said that there was a3

    flood hazard area problem on this site, correct?4

    A. I dont have the report in front of me, but the5

    issue is what methodology needs to be used in order to6

    determine the flood hazard area elevation. Where we7

    held the position that number -- that method three8

    could be used, he told us that method six needed to be9

    used. In the end it was method six, by the DEP10

    criteria, that was needed to determine the flood hazard11

    area elevation. So, it was a question of methodology.12

    Q. Well, didnt you, in your October 29, 200913

    report, P-37, state, and I quote, Therefore, it is our14

    professional opinion that a flood hazard area permit15

    does not apply to the proposed development?16

    A. Yes.17

    Q. That was your statement on October --18

    A. Yes.19

    Q. -- 29, 2009, correct?20

    A. Thats correct. Because I was using method three21

    and if you can use method three, you do not need a22

    flood hazard area permit. Thats what I thought at the23

    time.24

    Q. And you were mistaken, werent you?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    13/69

    Mr. Dipple - Cross 13

    A. I was mistaken and method six was the correct1

    method.2

    Q. In fact, in February of 2010, you wrote a3

    letter concurring with Mr. Creelmans analysis that4

    method six had to be used, correct?5

    A. I believe I testified to this. Yes, Mr. -- weve6

    agreed that, in written form and in testimony, that Mr.7

    Creelmans assessment of method six being the correct8

    method is correct, yes.9

    Q. And in that you also said however, that10

    wouldnt change the site design, isnt that correct?11

    A. Wouldnt change the site design?12

    Q. Yeah.13

    A. I dont know. Is that in my report? I dont have14

    the report in front of me. Did I say it wouldnt15

    change the site design, I dont recall that.16

    Q. In March 31, 2010, March 31, you submitted a17

    new plan, correct?18

    A. Yes, there was new plans prepared by Lasar Group,19

    you know, with our input, thats correct.20

    Q. And that plan recognized that there was a21

    major change in the site design, correct?22

    A. The Building A was reoriented to stay out of the23

    floodway, thats correct.24

    Q. And showing you whats been marked as D-16225

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    14/69

    Mr. Dipple - Cross 14

    for identification -- here, you can take a look at it1

    up close -- thats the March 31 plan that was2

    submitted, correct?3

    A. Thats correct.4

    THE COURT: D, what is it?5

    MR. WOODWARD: D-162, Your Honor.6

    THE COURT: Thank you.7

    CONTINUED BY MR. WOODWARD:8

    Q. And in July 30, its been marked as P-63A,9

    still another plan was submitted, correct?10

    A. I believe another -- I guess another plan was11

    submitted. I think it was a correction to the parking.12

    I dont recall, but that looks the same. But perhaps I13

    could see the two together and I could --14

    Q. Well, I mean the driveways were changed,15

    werent they?16

    A. Yes, some of the parking. As I just mentioned, it17

    was the parking that was changed. This doesnt include18

    parking under Building A, this one does. So, when you19

    take the parking out you need less surface stalls. I20

    believe this one was in error and this one is correct.21

    Q. So, the one, P-1 -- D-162, the March 31,22

    2010, was in error, correct?23

    A. Yes. I believe the Lasar Group forgot to add the24

    parking under the podium -- the podium parking, excuse25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    15/69

    Mr. Dipple - Cross 15

    me, in Building A.1

    Q. And by the way, the reason that Building A2

    was moved, in your March 31 plan, was because after you3

    had done the flood hazard study using method six, you4

    found out that almost the entire building was in the5

    floodway, correct?6

    A. Thats correct, yes.7

    Q. Im going to show you what was marked as D-8

    25C in evidence, ask you if youve seen this picture9

    before?10

    A. I have, yes. I believe so, yes.11

    Q. And that picture is of Birchwood Avenue in a12

    flooded condition, correct?13

    A. Thats correct, yes.14

    Q. Look at the right-hand side, isnt there a15

    fire truck in the parking lot of the building across16

    the street?17

    A. Yes, there is.18

    Q. And you dont see the fire truck driving down19

    the center of Birchwood when its flooded, do you?20

    A. No.21

    Q. Thank you. Im going to show you whats been22

    marked as D-184 for identification. Its a letter23

    dated September 2, 2010.24

    A. Yes.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    16/69

    Mr. Dipple - Cross 16

    THE COURT: I dont have it.1

    MR. WOODWARD: I think you should.2

    THE COURT: D-184?3

    MR. WOODWARD: Yeah. Its September 2, 2010.4

    If you want, Ill give you this extra copy.5

    THE COURT: Okay, maybe I dont. Did you6

    hand it to me?7

    MR. WOODWARD: I think I --8

    THE COURT: Because its not in the binder.9

    UNIDENTIFIED SPEAKER: Yeah, it was handed10

    out yesterday, Your Honor.11

    MR. WOODWARD: I think I handed them out12

    yesterday.13

    THE COURT: Oh.14

    MR. WOODWARD: It was late. Its that late15

    report.16

    THE COURT: Okay.17

    CONTINUED BY MR. WOODWARD:18

    Q. Now, this is a documentation or a letter that19

    you wrote on September 2nd, 2010 to Mr. Eisdorfer,20

    correct?21

    A. Yes.22

    Q. And this was provided in response to a letter23

    from me, dated August 26th, with -- regarding24

    supporting data for your report of August 19th,25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    17/69

    Mr. Dipple - Cross 17

    correct?1

    A. Yes.2

    Q. Okay. Now, lets just take a look at the3

    items that youve listed there. Item number one, you4

    made certain assumptions about drainage areas, existing5

    drainage area three and drainage area two, correct?6

    A. Yes.7

    Q. And you did that because you didnt have8

    sufficient time to work it all out, correct?9

    A. Yeah. I think, you know, wed probably break that10

    area up as I testified yesterday and yeah, the time11

    constraint, and I also think its pointless, but yes.12

    Q. Now, next, on item three, you say youve not13

    prepared a full comparison of time versus flow for14

    storm water runoff from the property. Do you see that?15

    A. Yes, I do.16

    Q. And you didnt think that was appropriate at17

    this time so that we would know what the time versus18

    flow analysis would be?19

    A. Yeah, I think theres a lot more that goes into it20

    than a conceptual design to make that determination.21

    Theres real pipes, theres real grades, theres real22

    channels, potentially, and yeah, thats a pretty big23

    analysis. And I -- right, I didnt -- I showed the24

    reductions and I felt that was sufficient.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    18/69

    Mr. Dipple - Cross 18

    Q. You felt that was sufficient, but if1

    someones going to analyze it, they dont have the2

    ability to analyze it thoroughly the way if -- as if it3

    would be if it had been properly prepared, correct?4

    A. In order to prepare that analysis you would need5

    full site plan design and that -- theres no time for6

    that.7

    Q. Now, item four, pipe invert and size8

    information for the predevelopment conditions were9

    taken from the survey by Control Point. Just so I want10

    to make sure that we have everything tied together, the11

    survey by Control Point is this document, D-159,12

    correct?13

    A. Yes.14

    Q. Thats the survey that you based this15

    analysis on?16

    A. That is.17

    Q. And then you also took some documentation18

    prepared by Mr. Marsden of certain elevations and19

    compared them and certain sizes and compared them to20

    what was on that survey, correct?21

    A. Thats correct, yeah.22

    Q. And if there was a dispute, if there was a23

    disagreement in the numbers, you accepted Mr. Marsdens24

    numbers, correct?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    19/69

    Mr. Dipple - Cross 19

    A. I believe so, yes. Yes. Yeah, and I go on to say1

    we confirmed it.2

    Q. Now, you also say, in item five, you talk3

    about pond reports, but at the very end you include a4

    statement, the storm sewer system shown in the5

    information provided is conceptual. Therefore, no6

    storm sewer calculations were made. Correct?7

    A. Yes, yes.8

    Q. So, we dont know whether numerically these9

    -- the system works properly, do we?10

    A. The storm sewer system?11

    Q. Yeah.12

    A. No, I wasnt asked to do a storm sewer design. I13

    mean its -- it was a detention basin conceptual -- a14

    detention basin analysis. The storm sewers just showed15

    the direction which they would discharge toward the16

    ditch. There was no --17

    Q. Okay. Now -- oh, that reminds me. One other18

    thing, with respect to your comments regarding the plan19

    of July 30, 2010, I think you were testifying about20

    this. This is P-63A. You were talking about how --21

    maybe this is the wrong one. Excuse me. Withdrawn.22

    P-90.23

    A. Yes.24

    Q. P-90 you testified about yesterday as showing25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    20/69

    Mr. Dipple - Cross 20

    the proposed existing -- excuse me, proposed drainage1

    area map, correct?2

    A. Yes. Yes, correct.3

    Q. All right. And you were asked about, by Mr.4

    Eisdorfer, about the areas that are within these5

    indentations in Building B. Do you see that?6

    A. Yeah, I do.7

    Q. Okay. Now, you said that a way of getting8

    this water out of here --9

    A. Yes.10

    Q. -- would be to pipe it under the road,11

    correct?12

    A. If it were to be designed that way. That wasnt13

    part of the detention system, yes. But this is a14

    conceptual --15

    Q. And -- but if you were to do that, those16

    pipes would have to run underneath the road and out17

    into the wetlands area, correct?18

    A. Yeah, they would probably discharge at the base of19

    the wall, yes.20

    Q. Yeah. And youd need a DEP permit for that?21

    A. For a discharge to the wetlands, I think within22

    the transition area you may, yeah.23

    Q. Oh. The -- this is -- Im showing you P-9124

    again, the storm detention system.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    21/69

    Mr. Dipple - Cross 21

    A. Yes.1

    Q. What is the size of them again?2

    A. I believe, --3

    Q. I think you said --4

    A. -- if my memory serves me right, its 35,000 cubic5

    feet in total. So, divide that roughly by three, so6

    theyre maybe 12,000 each. I think one of thems shown7

    a little smaller, but, you know, roughly.8

    Q. And dimension wise the -- theyre pretty9

    shallow, like maybe 30 inches high I think you said?10

    A. I think so. Just thats what we used as an11

    initial conceptual takeout, it was, you know, 3012

    inches.13

    Q. Two and a half feet?14

    A. Yes.15

    Q. All right, and their dimension?16

    A. Oh. I think I said 140, maybe, by 40 on one of17

    them. The one on the right I think was the one I gave18

    the dimensions. I mean I have a scale here, I could19

    check, but --20

    Q. What would be the elevation at which would be21

    the bottom of these tanks?22

    A. Id have to look at my analysis. One second.23

    Q. Could I know what youre looking at?24

    A. Im looking at P-88, which is the --25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    22/69

    Mr. Dipple - Cross 22

    Q. Got it.1

    A. -- conceptual hydrologic and hydraulic analysis.2

    Q. Thank you.3

    A. And I have them at 75.85, 75.85.4

    Q. The bottom would be -- the elevation would be5

    75.8 --6

    A. 75.85, yeah. Thats what my analysis shows.7

    THE COURT: What page are we on?8

    THE WITNESS: Im sorry. I -- that same --9

    about ten pages in, that same pond report. And it10

    looks like that.11

    MR. WOODWARD: So I can see.12

    THE WITNESS: Keep going. I think its13

    coming up. Its -- heres 75.85.14

    MR. WOODWARD: This is what I think --15

    THE WITNESS: Well, its -- I think its --16

    its this one. Oh, no, Im sorry. Im looking at the17

    wrong page. I apologize, theres no page numbers. My18

    output doesnt give me page numbers. Im going to19

    amend that. Its 76. Its not that much different.20

    And Im looking at this page. The elevations 76.21

    THE COURT: Which page?22

    THE WITNESS: Now it looks like that. Its23

    kind of a -- Im going to say its not quite halfway24

    through the report.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    23/69

    Mr. Dipple - Cross 23

    THE COURT: The pond report?1

    THE WITNESS: Yeah, but thats not the right2

    one. Just keep going a little bit further.3

    THE COURT: Maybe we should take a break and4

    number the pages.5

    THE WITNESS: Thats it. Thats it. And if6

    you look right here, I have elevation on the bottom,7

    76, under state storage takeout.8

    THE COURT: Thank you.9

    CONTINUED BY MR. WOODWARD:10

    Q. Now, you designed that so that it was11

    slightly above the invert elevation of the discharge12

    pipe at the ditch, correct?13

    A. Thats correct.14

    Q. So, if theres a flood and theres no flood15

    restriction, tail water can back up into that, correct?16

    A. Thats correct, yeah. On -- in that analysis,17

    right, yeah.18

    Q. Wouldnt you -- wouldnt it be better to --19

    withdraw the question. So, your design does not take20

    into account the impact of tail water?21

    A. No. I testified to that. Nor does it take it22

    into consideration on existing conditions, so.23

    MR. WOODWARD: No further questions, Your24

    Honor.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    24/69

    Mr. Dipple - Redirect 24

    THE COURT: Any redirect?1

    MR. EISDORFER: Just --2

    REDIRECT EXAMINATION BY MR. EISDORFER:3

    Q. Mr. Dipple, are you familiar with Residential4

    Site Improvement Standards?5

    A. I am.6

    THE COURT: I didnt hear your question.7

    MR. EISDORFER: Im sorry.8

    CONTINUED BY MR. EISDORFER:9

    Q. Mr. Dipple, are you familiar with Residential10

    Site Improvement Standards?11

    A. I am, yes.12

    Q. Can you tell us what they are?13

    A. It was standards, I believe --14

    MR. WOODWARD: Objection, Your Honor. This15

    goes beyond the scope of direct.16

    MR. EISDORFER: No, it does not. You asked17

    that driveway. So, Im going to ask some questions of18

    that driveway.19

    THE COURT: Okay.20

    MR. WOODWARD: Excuse me, Your Honor.21

    Driveways were asked in direct. Specifically, there22

    was a discussion of driveways on direct. I cross-23

    examined him on it.24

    MR. EISDORFER: Yes, and Im going to follow25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    25/69

    Mr. Dipple - Redirect 25

    up that cross-examination.1

    THE COURT: Let me just hear where this is2

    going, okay?3

    MR. WOODWARD: All right.4

    CONTINUED BY MR. EISDORFER:5

    Q. Can you tell us what the Residential Site6

    Improvement Standards are?7

    A. In brief, they govern -- I believe its a document8

    that is -- was prepared and is governed -- or is part9

    of the Department of Community Affairs, which regulates10

    residential construction throughout the State of New11

    Jersey. I believe it was an attempt to standardize12

    residential construction, you know, throughout the13

    state.14

    Q. And does that have standards governing15

    driveways, in terms of circulation?16

    A. Yes, it does.17

    Q. And do those standards reflect safety18

    considerations?19

    A. Yes, I believe they do.20

    Q. Is this compliant with the RSIS standards?21

    MR. WOODWARD: Your Honor, Im going to22

    object because there was no testimony on direct about23

    whether this complies with RSIS or not.24

    MR. EISDORFER: Your Honor, the -- he was25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    26/69

    Mr. Dipple - Redirect 26

    questioned on whether the driveway is adequate for fire1

    equipment. RSIS is a uniform state standard that2

    reflects all those and the testimonys going to be if3

    this was compliant with the RSIS.4

    THE COURT: I mean, you know, I assume it5

    complies. Thats not the point. I mean -- to that6

    extent Im going to allow it.7

    BY THE WITNESS:8

    A. I believe that -- I believe the width of the9

    driveway complies with the RSIS standards. Again, this10

    is not a developed site plan, a designed site plan.11

    So, yeah, there may have to be some engineering that12

    goes into this for full compliance, yes.13

    Q. Now, you were asked questions about different14

    soil characteristics.15

    A. Yes.16

    Q. Do you recall that?17

    A. Yes.18

    Q. Now, can -- and you indicated that some of19

    the soils were Class C --20

    A. Yes.21

    Q. -- and Class D.22

    A. Thats correct.23

    Q. Can you come and point out to us --24

    A. Yes.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    27/69

    Mr. Dipple - Redirect 27

    Q. -- where the Class C and Class D soils are?1

    A. Yes.2

    Q. Im asking you to point it out in connection3

    with your existing drainage area maps, which is P-89, I4

    guess.5

    A. Right. I -- okay. So, the soil on this side of6

    the site is the Haledon type and the soil thats over7

    here on this side of the site is the Passaic type. And8

    based upon the soil map that was provided as part of9

    Exhibit D-184, Im just going to trace with my finger10

    about where the soil line is. Its right about here11

    and then it goes this way. And then it looks like it12

    comes out this way and then makes its way down to13

    Wildhorse Terrace. It kind of bows out right in here14

    somewhere.15

    Q. Now, which is Class C and which is Class --16

    A. This is C on this side and that is hydrologic soil17

    group D. Its -- thats the official term, hydrologic18

    soil group.19

    Q. So, now in drainage area -- where would the20

    -- well, for which of these drainage areas would the21

    soil type have an impact on your analysis?22

    A. Drainage area three, proposed -- are you speaking23

    of proposed?24

    Q. Yeah. No, --25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    28/69

    Mr. Dipple - Redirect 28

    A. Youre looking at the proposed drainage area. No,1

    Im sorry, youre looking at existing.2

    Q. Existing. Existing.3

    A. I apologize. Existing drainage area three.4

    Q. Okay. And based on what youve just shown us5

    is drainage area three entirely in Class C?6

    A. No. No, theres a significant part of drainage7

    area three that is Class -- or hydrologic soil group C8

    and theres a significant area in hydrologic soil group9

    D.10

    Q. In practical terms, would it have made any11

    practical difference in the outcome if you had treated12

    that as partially in C and partially in D?13

    A. No. Basically, youre going to get a little more14

    runoff in the Class D soil. So, if you take half of15

    that, lets say its half. I dont know what the split16

    is. Say half of its C, half of its D. Its just17

    going to bump up incrementally. So, your existing18

    conditions runoff rate is going to go up a little bit19

    and your proposed conditions runoff rate is going to20

    go up a little bit. So, were only comparising --21

    comparing the difference between the two. So, its22

    kind of a sliding scale. If they go up a little bit,23

    were only looking at the difference. And we actually24

    ran all of drainage area three with D and it made no25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    29/69

    Mr. Dipple - Redirect 29

    difference in the change between the two flow rates.1

    MR. WOODWARD: Objection, Your Honor.2

    Theres nothing in his testimony which he just gave in3

    any of his reports.4

    MR. EISDORFER: Your Honor, the door was5

    opened. He was cross-examined on this.6

    THE COURT: Do you have anything else on7

    this?8

    MR. EISDORFER: No, I dont.9

    THE COURT: Okay, then move on.10

    CONTINUED BY MR. EISDORFER:11

    Q. You were shown a New Jersey Department of12

    Transit manual.13

    A. Department of Transportation, yes.14

    Q. Department of Transportation, sorry, --15

    A. Yes.16

    Q. -- manual concerning the calculation of storm17

    water and you testified that that was not the18

    appropriate manual. Do you know what the appropriate19

    manual is?20

    A. Yes. Its the Best Management Practices manual,21

    which is referenced in the storm water management rule.22

    The storm water management rule references back and23

    puts some of the engineering standards into the Best24

    Management Practices manual.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    30/69

    Mr. Dipple - Redirect 30

    Q. Does that have the same standard for1

    sheeploads as the DOT manual?2

    A. No, it doesnt. Its different than the DOT3

    manual.4

    Q. And what is that standard? What is the5

    standard in the DEP manual?6

    A. The standard in the DEP manual, the Best7

    Management Practices manual, its actually called the8

    New Jersey Storm Water Best Management Practices9

    manual. Its in chapter five and it states the maximum10

    sheepload length recommended by the NRCS is 150 feet.11

    According to the NRCS, longer lengths may be used only12

    in special cases, such as smooth, uniformly graded13

    parking lots.14

    MR. EISDORFER: I have no further questions.15

    THE COURT: Anything else, Mr. Woodward?16

    RECROSS-EXAMINATION BY MR. WOODWARD:17

    Q. Mr. Dipple, when you did -- when you were18

    just asked those questions by Mr. Eisdorfer, you were19

    referring to a -- you said you could use it for a20

    parking lot, but the proposal here is not to build a21

    parking lot, is it? Its to build a building with22

    driveways, correct?23

    A. But Im analyzing the existing -- the common24

    concentration issue revolves around existing conditions25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    31/69

    Mr. Dipple - Recross 31

    of drainage area one and that is a parking lot.1

    Q. Now, with respect to the Passaic soils that2

    you mentioned, at least half the site is that class3

    type D soils, correct?4

    A. Im going to say yes, about half.5

    Q. And isnt there a procedure under the TR-556

    that you have to use a worksheet and put the numbers7

    down, do an analysis, do an averaging? Did you do8

    that?9

    A. Its a weighted average.10

    Q. Did you do that?11

    A. I didnt include the type D, no. I was12

    simplifying the analysis.13

    MR. WOODWARD: Okay. No further questions,14

    Your Honor.15

    THE COURT: Anything else?16

    MR. EISDORFER: Not from me. I dont know --17

    THE COURT: Okay, you can step down. Thank18

    you. Oh, wait a minute. Ms. McKenzie?19

    MR. EISDORFER: I dont know if Ms. McKenzie20

    has questions.21

    MS. MC KENZIE: I dont think I have any22

    questions.23

    THE COURT: No?24

    MS. MC KENZIE: No, Your Honor. Thank you.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    32/69

    Mr. Marsden - Direct 32

    THE COURT: Okay, you could step down.1

    THE WITNESS: Thank you.2

    THE COURT: Mr. Eisdorfer, anything further?3

    MR. EISDORFER: I have no further witnesses.4

    THE COURT: Okay. So, the Plaintiff rests5

    subject to the admission of the evidence.6

    MR. EISDORFER: Thats correct.7

    THE COURT: Okay. So, why dont we take ten8

    minutes and your witness?9

    (Off record. Back on record.)10

    THE COURT: All right. Mr. Woodward?11

    MR. WOODWARD: Thank you, Your Honor. Id12

    call Richard Marsden to the stand.13

    RICHARD A. MARSDEN, JR., DEFENSE WITNESS, SWORN14

    COURT PERSONNEL: Please state your name for15

    the record.16

    THE WITNESS: Richard Arnold Marsden, Jr.17

    MR. WOODWARD: Thank you.18

    DIRECT EXAMINATION BY MR. WOODWARD:19

    Q. Mr. Marsden, youre the township engineer for20

    Cranford?21

    A. Yes.22

    Q. And you previously testified in this case,23

    correct?24

    A. Correct.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    33/69

    Mr. Marsden - Direct 33

    Q. Subsequent to your testimony there were a1

    couple reports produced by Mr. Dipple and Im going to2

    show them to you. One is dated August 19th, 2010, and3

    bears exhibit number P-87D, and with it is a conceptual4

    hydrologic and hydraulic analysis of P-88, plus a5

    series of drawings, including one thats labeled P-92,6

    P-89, P-86, P-91 and P-90. And Im going to ask you if7

    youve ever seen those documents before?8

    A. I have.9

    Q. And in addition, there was a document dated10

    September 2, 2010, which has been marked for11

    identification as D-184. And have you ever seen that12

    before?13

    A. Yes.14

    Q. Have you reviewed those documents?15

    A. I have.16

    Q. And as a result of your review, did you17

    prepare a report?18

    A. Yes, I did.19

    Q. And Im going to show you whats been marked20

    as D-180 for identification. And its dated September21

    16, 2010. Take a moment to look at it, D-180. Is this22

    a copy of your report?23

    A. Yes, it is.24

    Q. Now, could you tell us what documents you25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    34/69

    Mr. Marsden - Direct 34

    reviewed in preparing this report?1

    A. Well, as it states in the report, I reviewed the2

    L2A letter, dated September 2nd; the August report,3

    dated August 19th; the conceptual hydraulic and4

    hydrologic analyses, dated August 19th; their maps5

    entitled Proposed Drainage Area Map, dated August6

    19th; the existing drainage area map, dated August 19th;7

    the parking lot, storage exhibit map, dated August8

    19th, and the conceptual basin location plan, dated9

    August 19th.10

    Q. Now, based upon your review of those11

    documents and your analysis as a professional engineer,12

    could you tell us whether you reached any conclusions13

    regarding the content of the report and the letter and14

    the various documents you reviewed?15

    A. Yes, I did.16

    Q. Could you tell us what your -- in summary,17

    what your conclusions were?18

    A. Well, in summary, my conclusions were that there19

    were two assumptions that were made that were not20

    correct. One is that the gate valves were assumed21

    completely open and the second one is the assumption22

    that the proposed design that regulated the outflow23

    elevation would be higher than the flood elevation.24

    Q. All right. Well, lets talk about the first25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    35/69

    Mr. Marsden - Direct 35

    one, gate valves assumed to be completely open in the1

    analysis. Could you tell me, or tell us what the2

    significance of that is?3

    A. Well, the assumption that the gate valves were4

    completely open also assumes that, quite fra -- leads5

    to the question of why are they there in the first6

    place. If the gate valves were there, they would have7

    a function. Trying to analyze what the functions would8

    be, I can only come to the conclusion that it was a9

    regulated outflow function, meaning that the gate valve10

    was closed at some point to regulate the storm water11

    system for detention on that parking lot.12

    Q. Can you tell us what are the factors that13

    lead to your conclusion that the parking lot was14

    designed as a storm water detention facility?15

    A. Well, the initial overriding factor, before any of16

    these reports came into play, were when we looked at17

    the parking lot and we saw the outflow chamber that led18

    to the outflow of the storm water piping system through19

    a gate valve. There are pipes that were entering this20

    chamber that were larger than the pipe that left the21

    chamber. And in that pipe that left the chamber there22

    were gate valves. I tried to assume that well, what23

    would those gate valves have as a function. Its not24

    used for maintenance for backwater. Because if there25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    36/69

    Mr. Marsden - Direct 36

    was a backwater effect at the time of a large storm1

    event, there would be no real velocities, thered be no2

    real sediment depositing back into the piping system3

    that would be a concern because everything would fall4

    out. Because youre having a very large floodplain and5

    the perimeter, the outer limits of the floodplain the6

    velocities drop tremendously and in this ditch, thats7

    the furthest point. So, I wasnt concerned, as a8

    Public Works Director, that something like that would9

    deal -- would be a backup. It just didnt make sense.10

    Because it also leads to the first chamber, which also11

    adds to a wider opening and would, in turn, reduce the12

    velocities. Now, when I heard testimony that the pipes13

    were clear, I -- it just confirms that the piping14

    system flushes itself out for whatever little debris15

    may have backed up into it, because those gate valves16

    have been opened fully. So, it wasnt that. The only17

    conclusion I can come to is that these gate valves were18

    there to regulate the outflow. Why would an engineer19

    spend the money, or recommend spending the money, to20

    put a gate valve when you had a twelve inch pipe that21

    wouldve done the same thing.22

    Q. So, the function of a gate valve is to do23

    what?24

    A. The function of a gate valve --25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    37/69

    Mr. Marsden - Direct 37

    Q. In your view.1

    A. -- is to regulate the outflow. It would reduce2

    the outflow to some degree that would be comparable to3

    what the preexisting conditions were on that site. The4

    -- in reducing the gate valve opening, it would have5

    water backup, as has been testified from Mr. Dipple,6

    that would fill the parking lot. In looking at the map7

    of the parking lot, as it regulated its flow depth, it8

    almost looked uniform, meaning that the parking lot was9

    pretty much flat. If you --10

    Q. Now -- go ahead. Im sorry.11

    A. If you didnt need it there for storm water12

    detention, you wouldnt have graded it such a way,13

    because the terrain itself, on either end of that14

    portion of the site, goes from elevation 81 at one15

    point to 82. And at the drops where you can obviously16

    see the fill, which was testified by, it goes to 77,17

    78. So, theres a natural slope that was there. A18

    design engineer, if he wasnt being required to do19

    anything other than put a parking lot in, would pretty20

    much do what Site 235 did, just put it down close to21

    grade and pitch it so it drains towards the river.22

    Q. Now, you say Site 235, and Im -- right now23

    Im looking at --24

    A. Building number. I guess its --25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    38/69

    Mr. Marsden - Direct 38

    Q. 235 is --1

    A. Yeah.2

    Q. -- on the far western side of the property?3

    A. Thats correct.4

    Q. And that parking lot, can you describe that5

    parking lot?6

    A. Well, that parking lot basically drains close to7

    the grades. It appeared to be built close to the8

    grades that are flat along the river, Casino Brook that9

    is. And it drains from the parking lot down to the10

    back and then out the back. There are no real inlet11

    connections there that accommodate that. I think there12

    may be two, but theres not a series of storm water13

    detention systems and gate valves.14

    Q. Now, take a look at whats been marked as P-15

    92, which was an attachment to Mr. Dipples August 19th16

    report. Could you tell us what this document is?17

    A. Well, the --18

    Q. Or what you understand it to be, I guess.19

    A. Well, this document is -- it shows the storage of20

    runoff at different elevations. The one in the upper21

    left-hand corner has an elevation height, maximum22

    storage height of 90 -- 79.2, and as you go clockwise,23

    it goes 79.4, 79. -- oh, excuse me -- .6 and 79.8. It24

    shows almost uniformly, through the blue filled in25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    39/69

    Mr. Marsden - Direct 39

    areas, that it fills up equally, like a bathtub not1

    flushed or regularly. So, it was built, in my opinion,2

    to act as a storm water detaining facility.3

    Q. Now, I think when you testified earlier in4

    this trial, Mr. Marsden, you testified as having5

    designed systems somewhat like this during the 1970s?6

    A. I mean -- that is correct. We did parking lot7

    storage then. It was a cheap efficient way to detain8

    water without going through, you know, additional9

    costs, doing underground piping systems.10

    Q. And do you know when this -- approximately11

    when this building was constructed and that parking12

    lot?13

    A. Well, we believe it started around, I guess it was14

    maybe completely constructed around 1976 or 74. I15

    dont know specifically. I dont have that -- I dont16

    know if I had a map showing it after that. I know it17

    was after 1973.18

    Q. Now, if there was a reduction in the flow19

    through a gate valve, what impact, if any, would that20

    have on the detention ability of that parking lot?21

    A. Well, what would happen is, if there is -- if the22

    gate flow was set at a certain reduction, more water23

    would be stored in the parking lot. As you go from --24

    referring back to Exhibit, was that P-92D -- FD? Im25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    40/69

    Mr. Marsden - Direct 40

    sorry.1

    Q. I think its --2

    A. I cant read that.3

    Q. P-92 for identification.4

    A. Oh, sorry. P-92, it shows that when they got to5

    elevation 79.8 it really hadnt gone up to a large part6

    of the curb. So, as it fills up the area becomes7

    greater. Therefore, the volume becomes a lot larger8

    per change in height. So, thered be a lot more9

    storage capability in that parking lot. And in10

    previous testimony, and in these reports, it showed11

    that the weir or the spillway elevations were very12

    close, within a half an inch of all three that were13

    mentioned. It was, was it 81.13? No, 80.13 and 80.0714

    and another one like that, which its quite a15

    coincidence that they were all set close to the same16

    for spillover.17

    Q. Now, in terms of calculating what the flow18

    from this should -- by the way, what is the purpose of19

    detaining water on a site, such as this, through20

    structures, such as you have described here?21

    A. Well, the purpose is that engineers, the State22

    Department of Environmental Protection, weve, for a23

    long time, weve tried to regulate outflows from24

    developed sites. Because when we put impervious cover,25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    41/69

    Mr. Marsden - Direct 41

    parking lots, buildings, on a site, it increases the1

    rate of flow off the site and that rate of flow then2

    enters your bodies of water quicker, sooner. So, at3

    some point downstream theres now more water than there4

    used to be. So, we try to regulate the outflow from5

    the sites to what the existing or precondition was.6

    One way of doing that is to provide detention7

    structures, parking lot or in the ground structures,8

    that hold that water out and regulate the outflow that9

    would mimic the precondition.10

    Q. Now, in this particular situation you11

    indicated in your report that in order to determine how12

    much the gate valve should function, you had to look at13

    what the original site conditions were before14

    development.15

    A. Thats correct. And there is -- theres no16

    information out there showing us what the gate valve17

    regulation was. The only way you can do that is to18

    back-step into it, meaning that you come back with the19

    original concept of what the design criteria was, which20

    was a wooded, or an undeveloped site, to a developed21

    site with this impervious cover. Determine what the22

    undeveloped site outflow was, pretty much what they did23

    here except for they used the parking lot as the24

    control assuming the gate valve was fully open. You25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    42/69

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    43/69

    Mr. Marsden - Direct 43

    you disagree with. Could you go into that, talking1

    about outflow elevation?2

    A. Oh.3

    Q. And --4

    A. The other --5

    Q. -- the storage facility.6

    A. What that led to is, in reviewing the reports7

    prepared by Mr. Dipple, one of the things you try to do8

    is not to create a -- and I call it backwater for9

    simple terms, but its tail water, or headwater effect.10

    Tail water effect? Gosh, Im losing it. Anyway, its11

    -- it is the backing up of the water that tries to get12

    out of the system that cant get out because theres13

    already water in the downstream portion of the system14

    that it has to displace. The only way it is displaced15

    is the increase in height of the water in the upstream16

    system creating a head, which gives more weight to that17

    water, which, by gravity, pushes it down and is able to18

    push it out. That effect, if there is water already in19

    the downstream system, will reduce the outflow of that20

    pipe. It has the downstream ponding. Using the fact21

    that in order to design it properly, which we do and I22

    think Mr. Dipple stated, was that we have to build the23

    outflow pretty much at what the flood elevation would24

    be so there would be no backwater due to the -- upon25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    44/69

    Mr. Marsden - Direct 44

    that youre at maximum flood of the Casino Brook. In1

    doing that youd have to raise that elevation to the2

    height of the storm event elevation, which I believe3

    was 78.6. Using that as just a very conceptual4

    starting point, and not assuming any slopes and any5

    pipes upstream, not assuming slopes to get the water to6

    the inlets that would have to collect this water for7

    the detention basin, we utilized what information was8

    in the report. The report stated that theres 309

    inches, the conceptual detention basin, or detention10

    structure, that would have a height of 30 inches, which11

    is two and a half feet, which is actually very good.12

    Its one of the more common ways we do it because its13

    more efficient. If you start going higher and deeper,14

    you get more troubles. Narrower and wider it becomes a15

    maintenance issue. So -- and its an acceptable16

    practice and I agree there. But when you add up what17

    elevations, 78.6, plus two and a half feet, that gives18

    you 80.1 -- 81. Let me look at my report. My math19

    skills as I get older.20

    Q. Please, go ahead.21

    A. 80 -- 78 outflow structure. Yeah, it gives you22

    elevation 81, you know, 81.1. On top of that, when you23

    put -- you have to have cover or thickness of your24

    detention structure. And again, typically youre going25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    45/69

    Mr. Marsden - Direct 45

    to try to stay pretty deep, because the structure1

    itself will have some type of limited integrity due to2

    depth under the ground. A minimum would be twelve3

    inches. So, wed assume twelve inches, another foot.4

    So that brings the top of your detention structure to5

    about elevation 72.1. Again, thats not assuming --6

    Q. Excuse me. 72.1?7

    A. 72.1. It was 71 --8

    Q. Or 82.1?9

    A. 82.1. 82.1. That would bring -- not even10

    counting the slope to get the water to that point,11

    which would even be higher. That would then tell me12

    that the minimum height that you have to have on the13

    site is 82.1. Going back through their profile14

    reports, which we have here, for example, its Exhibit15

    P-83, it shows conceptual elevations of those16

    buildings. Building B was at 80. Building A was at17

    79.6. That tells me at this point, in order to have a18

    system similar to what was in the report done, the19

    whole site pretty much has to be raised more than two20

    feet, which then now impacts the relative height of the21

    property with the surrounding area.22

    Q. And as a result of that do you have a23

    conclusion as to whether or not there is sufficient24

    data to make a determination as to whether or not this25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    46/69

    Mr. Marsden - Direct 46

    design would be approved by the DEP?1

    A. Well, what this shows is that theres not enough2

    data to accurately determine to say well, this is what3

    the height of the buildings going to be, or this is4

    what -- where the detention structure is going to be.5

    My feeling is DEP is going to look at this and if they6

    present it this way, theyre going to question what is7

    the outflow based upon the existing parking lot8

    condition, meaning the detention and the restricted9

    outflow. Because there is no real fact, other than my10

    opinion, going back to what the precondition design was11

    and theyre probably going to request that. Can it get12

    approved? I dont think it can get approved without13

    going through that analysis.14

    Q. Do you have an opinion as to whether or not15

    the -- by the way, attached to your report is an aerial16

    photograph. Do you see that?17

    A. Yes.18

    Q. Could you tell us what that is?19

    A. This is an aerial photograph. It came to my20

    attention -- it was in the construction departments21

    plat files. It wasnt in mine. Theyre plates that22

    were developed and taken by -- excuse me -- Aerial23

    Photographic Survey, on February 25th, 1973. And going24

    through them I found this plate. Its actually25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    47/69

    Mr. Marsden - Direct 47

    somewhere written in white above -- even in that plate,1

    it says 2/25-73, shows when it was flown. Next to it2

    is the actual series number they use when they do their3

    aerial flights. Its 068-73, its on the right-hand4

    top side. It looks like one and then 08. I pulled5

    this plate out because it shows our site, what it6

    looked like in 1973.7

    Q. Well, can you direct the court to where8

    Birchwood Avenue is, if you want to hold it up to show9

    the Judge?10

    A. Okay. Actually, if you look at it, as its been11

    stapled together, youll see a fan like structure12

    there, a fan like structure there. Thats the nursing13

    facility.14

    THE COURT: Cranford Conva --15

    BY THE WITNESS:16

    A. Cranford Con -- yeah. And just going up slightly17

    to the left is, you can almost see a tree line there,18

    darker objects that are going across there. That19

    represents trees that are along the edge of that20

    property. Above that is all open area, with a little21

    dark diagonal slot, which was probably an old tree row,22

    that farmers typically use when theyre cleaning their23

    fields and theyre putting rocks aside and -- you know,24

    so they can be able to farm it. That is approximately25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    48/69

    Mr. Marsden - Direct 48

    in the middle of this proposed site thats housing 235.1

    Q. 215?2

    A. 215. Im sorry. Now, above that you see a double3

    line, very faint. Thats the parking lot to the other4

    building. Thats the entranceway to the other5

    building. So, you can gauge that just downward of that6

    double line and above the fan building, that thats the7

    site that we are talking about.8

    Q. Was it developed at that point?9

    A. No, it wasnt.10

    Q. That is the 215 Birchwood site.11

    A. Thats correct.12

    Q. And this was in 1973?13

    A. That was 1973.14

    Q. February. Now -- by the way, with respect to15

    the proposed detention system that was in P-81, are any16

    of those located in the driveway?17

    A. The potential location of the underground storm18

    water storage systems, two of them. One is fully19

    located under a driveway. The one thats furthest20

    north is partially, a little less than half of it21

    appears to be located under a driveway. The third one22

    appears to be located in more of a court area.23

    Q. Now, with respect to the ones in the24

    driveway, is there any particular structural25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    49/69

    Mr. Marsden - Direct 49

    requirements so that vehicles and trucks and so on can1

    drive over them without problem?2

    A. Of course thered have to be -- theyd have to3

    have structures that would be able to support the loads4

    of those vehicles. I mean our typical storm water5

    inlets are designed to do that. There are systems out6

    there, like the arch, I think Mr. Dipple is alluding7

    to. A certain criteria has arch, corrugated arch8

    systems or concrete thatll also have the structural9

    integrity to support loads under a parking lot or a10

    driveway.11

    Q. Do you have a conclusion as to whether, based12

    on what youve seen from these reports, the impact that13

    it would have or whether it would create increased --14

    strike that. Do you have an opinion as to whether or15

    not the site, with this additional requirement, vis--16

    vis the drainage system, or the detention system, is17

    suitable for the size of the development as proposed?18

    A. Well, based on their reports and the fact that19

    they show theres detention going up to the elevation,20

    it was, I believe, going up to elevation 79.8 on those21

    maps, with the gate fully open, my opinion is I know22

    the gate wouldnt be there if it was fully open. So,23

    the gate had to be closed to some degree. Therefore,24

    there would be more storage in that parking lot. In25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    50/69

    Mr. Marsden - Cross 50

    addition, showing the calculations that were showing1

    outflow rates, there would be less existing outflow,2

    because the gates were partially closed. So, yes, it3

    would bring water into the system sooner if this cri --4

    if this concept, the design was held and it would5

    negatively impact downstream of us.6

    MR. WOODWARD: No further questions, Your7

    Honor.8

    THE COURT: Cross-examine.9

    CROSS-EXAMINATION BY MR. EISDORFER:10

    Q. Mr. Marsden, have you inspected the valve11

    youve been describing?12

    A. No.13

    Q. No. So, do you know what its current state14

    is?15

    A. Well, its current state is nonoperational.16

    Q. In what way is it nonoperational?17

    A. Through, I believe, probably snowplowing, it was18

    bent or knocked over. Both gates -- both gate shafts19

    were bent.20

    Q. How long have you been municipal engineer at21

    Cranford?22

    A. A little over six years.23

    Q. Has the gate ever been operational during the24

    period when youve been municipal engineer?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    51/69

    Mr. Marsden - Cross 51

    A. I couldnt tell you that. I wasnt there1

    initially in my first couple years.2

    Q. Im sorry, I dont un --3

    A. I was not at the site until later on. So, --4

    Q. When was the first time you were at the site?5

    A. When we had flooding. 2007.6

    Q. And was the gate operational then?7

    A. It appeared not to be.8

    Q. Have you actually seen the gate anything9

    other than fully open?10

    A. Well, you cant tell whether the gates fully open11

    or not, because you dont know what the height of the12

    steering wheel or the shaft was, regulations.13

    Q. Do you have any municipal records that14

    indicate that --15

    A. No, I dont.16

    Q. -- that it was anything other than fully17

    open?18

    A. No.19

    Q. So, any -- theres no actual evidence of it20

    being full -- of being anything other than fully open?21

    A. Well, theres no evidence in knowing how much or22

    how little it was open.23

    Q. But is there any evidence of it being -- do24

    you have any evidence of it being less than fully open?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    52/69

    Mr. Marsden - Cross 52

    A. No.1

    Q. Now, have -- does the -- did the resolution2

    approving this project specify the existence of this3

    gate valve?4

    A. I dont know.5

    Q. Did it specify that it had to be maintained6

    at being less than fully open?7

    A. I dont know.8

    Q. At the time when this project was -- you9

    indicated that the project was constructed sometime in10

    the 1970s, after 1973, but you thought maybe by 1978,11

    is that right?12

    A. It could, yeah, it could be by then, later. 76,13

    its tough to --14

    Q. At that point there was no state regulation15

    of storm water, was there?16

    A. 76. 78, yes, we were doing storm water17

    regulation.18

    Q. But was it --19

    A. Flood hazard regulation.20

    Q. Yeah. The first state regulations didnt21

    come in until 1983, didnt -- did they?22

    A. No, I believe we were doing flood hazard23

    regulations. I know locally we were doing detention24

    basins and facilities.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    53/69

    Mr. Marsden - Cross 53

    Q. When you say locally, you dont mean in --1

    A. I mean in Union County.2

    Q. You dont mean in Cranford?3

    A. And -- well, part of Cranford did through Union4

    County. The Lenape Park detention basin, I think. We5

    have the Carpenter Street detention basin. We were all6

    aware of the increase in impervious cover issues.7

    Q. At -- well, was there state regulation at8

    that point, in the 19 -- at the time this was built?9

    A. I couldnt say directly --10

    Q. You dont know?11

    A. -- without looking it up.12

    Q. You dont know?13

    A. Not right now.14

    Q. Cranford didnt have an ordinance until 1983,15

    did it?16

    A. No.17

    Q. So, there was no local regulation?18

    A. There was no local regulation.19

    Q. So, you dont know what standards were20

    applied when this project was approved, do you?21

    A. That is correct.22

    Q. Any -- and it is merely inference on your23

    part that the standards were reproducing existing24

    conditions, isnt that right?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    54/69

    Mr. Marsden - Cross 54

    A. Its -- say -- can you try that again?1

    Q. I asked you if it is merely inference on your2

    part that the standards that would have been applied at3

    that point were reproducing existing conditions, is4

    that right?5

    A. Based upon -- yes. Base -- yes.6

    Q. In fact, its not inference, its7

    speculation, because you dont really know. You dont8

    have --9

    MR. WOODWARD: Objection, argumentative.10

    CONTINUED BY MR. EISDORFER:11

    Q. You havent seen the resolution, have you?12

    A. No.13

    Q. There was no ordinance.14

    A. Thats correct.15

    Q. There was no state regulation.16

    A. Dont know.17

    Q. So, you dont have any actual knowledge of18

    what standard was applied then.19

    A. Direct knowledge, no.20

    Q. Youre merely speculating as to what you21

    think might -- would, could or shouldve been applied.22

    A. My speculation is what we have applied in the mid-23

    70s, yes.24

    Q. Now, have you modeled, have you done the25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    55/69

    Mr. Marsden - Cross 55

    calculations as to what the affect of partially closing1

    the valve would be?2

    A. No. Thats -- well, my task was to review the3

    report. We have consultants, you know, who will look4

    into that if it ever came up to be a request.5

    Q. So, you cant tell us how much additional6

    flood -- how much additional water storage there would7

    be if it were fully closed, can you?8

    A. Well, could I now?9

    Q. Now.10

    A. No.11

    Q. No.12

    A. I couldnt --13

    Q. You havent done the calculations?14

    A. Well, --15

    MR. WOODWARD: Objection, Your Honor. Hes16

    interrupting the witness. The witness hadnt finished17

    his answer.18

    THE COURT: Lets let him finish his answer.19

    MR. EISDORFER: Okay.20

    BY THE WITNESS:21

    A. What I do know is, through my experience of these22

    type structure designs, by reducing the outflow you23

    will increase storage. You will reduce rate of24

    outflow.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    56/69

    Mr. Marsden - Cross 56

    Q. But you cant tell us how much?1

    A. I could not tell you exactly how much.2

    Q. So, you cant -- you cannot tell us what the3

    significance, in quantitative terms, would be of4

    closing the valve a little bit, a little more or a5

    little more than that, can you?6

    A. I can tell you that there is an increase in7

    outflow, if they stay -- if theyre opened more. I can8

    tell you that if they are closed it will be decreased9

    in outflow rate. The actual ratio and significance I10

    cant tell you. I did not do those calculations.11

    Q. Now, the curb on the existing parking lot is12

    six inches high, is that correct?13

    A. I dont know exactly. It may be a little less14

    because its been resurfaced or whatever. I dont -- I15

    cant tell you.16

    Q. Is that something you measured when you did17

    your survey?18

    A. They probably did. I didnt remember -- memorize19

    all top of curb and bottom of curb elevations.20

    Q. If the water gets above the curb what21

    happens?22

    A. Well, if it gets above the curb, it actually wont23

    get above the curb --24

    Q. Well, if it gets above the curb what happens?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    57/69

    Mr. Marsden - Cross 57

    A. It cant get above the curb in all but one1

    location.2

    Q. Well, what happens when the water gets high3

    enough to get above the curb?4

    A. Well, it then spills over.5

    Q. Spills over.6

    A. Thats what your consultant, Mr. Dipples design7

    showed that it would spill over the curb in the lower8

    left-hand side of that map youre working with.9

    Q. Now, that sets a limit on how much water can10

    be detained.11

    A. Thats correct.12

    Q. It cant -- it can never hold more than the13

    volume --14

    A. That volume of water.15

    Q. That volume of water.16

    A. Thats right.17

    Q. And so thats the maximum.18

    A. That would be the maximum.19

    Q. Now, so did you calculate what the effect of20

    that maximum would be?21

    A. As I said, I didnt do any calculations, in a22

    large degree. I do know theres three weirs there.23

    One -- the other two structures are the driveway24

    entrances and exits to the parking lot. And that lower25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    58/69

    Mr. Marsden - Cross 58

    left-hand corner acts as a weir, as Mr. Dipple1

    testified.2

    Q. Now, if -- youve testified that this manual3

    valve was set at some predetermined level. Do you know4

    what the predetermined level was?5

    A. No. I said that.6

    Q. Under what circumstances would people change7

    it, would someone go out there and change the level?8

    A. Well, they would change the level -- they would9

    open it up all the way to maintain it. Meaning that if10

    its opened and sediment developed in that last11

    chamber, its easy to flush a twelve inch pipe thats12

    completely open without having a restriction in the13

    middle of it than it is to have an orifice restriction.14

    I can give you an example that DEP and I discussed in15

    the 70s about restricted outflows. We have -- there16

    was a regulation of DEP in the 70s that required a17

    minimum orifice size of three inches. Through the18

    state, the developers, we had issues about that minimum19

    size because it was a maintenance problem. Outcomes of20

    that were options to be able to open up your outflow21

    structure with plates or possibly these type of gates.22

    The plates Im talking about would be in the chamber23

    itself before it leads out. It would be put in front24

    of the twelve inch pipe that had a restricted burned25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    59/69

    Mr. Marsden - Cross 59

    out circle that would say thats your outflow. When1

    its time to maintain it youd pull it out, youd flush2

    your pipe system. Public works departments had3

    equipment that would push water through it or sweep a4

    pipe to get this type of thing clean. You have to5

    maintain your outflow structures. That couldve been6

    one way of having your restriction and then being able7

    to open the valve up and then flush your pipe out8

    without hitting that restriction.9

    Q. So, do you imagine that that valve was only10

    used for maintenance?11

    A. I believe that valve was only used for12

    maintenance, tied into detention.13

    Q. So -- but the valve itself was just used for14

    maintenance?15

    A. The valve was set for detaining the water at a16

    certain reduced opening. It was decided to use a valve17

    possibly because of maintenance.18

    Q. Is that how you would design a system now?19

    A. Design a system now?20

    Q. Would you use a -- would you design a system21

    now with a manually operated valve?22

    A. No, Id probably use a plate in front of it.23

    Q. Would -- if -- as a municipal engineer, would24

    you approve a system now designed with a manually25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    60/69

    Mr. Marsden - Cross 60

    operated --1

    A. With a manually operating valve, no, because it2

    adds to a maintenance headache. Another point where3

    youd have to maintain the valve, where its a lot4

    easier to maintain or remove a steel plate and replace5

    it.6

    Q. So, but your assumption is that the municipal7

    engineer in 1970 had a different view than you do?8

    A. Well, an engineer that was responsible for the9

    site criteria, yes. I dont know whether it was a10

    municipal engineer or a county engineer at that time.11

    Q. But had a different opinion --12

    A. Had a different opinion.13

    Q. -- than you do.14

    A. And it was fresh in our design criteria detention15

    and the answer would be yes.16

    Q. And -- but you dont know what that opinion17

    was?18

    A. I have no idea.19

    MR. WOODWARD: Objection, Your Honor,20

    interruption.21

    MR. EISDORFER: Im sorry.22

    BY THE WITNESS:23

    A. I have no idea.24

    Q. You have no idea what that opinion was?25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    61/69

    Mr. Marsden - Cross 61

    A. No, what that opinion was. I was not -- I dont1

    even know who did the --2

    Q. Now, based on your analysis, do you have an3

    opinion whether its possible to design this site along4

    the lines of the concept plans that have been proposed,5

    that would comply with NJDEP regulations?6

    A. Well, as I stated earlier, in order to properly7

    determine the outflow you would have to use the pre-8

    assumption that the site was undeveloped. If they use9

    that criteria, I dont see how DEP would not approve.10

    Q. Assuming thats not the case, assuming that11

    the standard is the existing -- the comparison is the12

    existing conditions. Do you have an opinion as to13

    whether the -- that the site can -- that this can be14

    presented to DEP and it would -- let me take it back.15

    Assuming that we compare it to the existing conditions,16

    which is the valve is fully open, do you have an17

    opinion as to whether a storm water system can be18

    designed that would comply with the DEP regulations?19

    A. Im not sure I understand the question. With the20

    valve completely open can a storm water system be21

    designed --22

    Q. Assuming that the existing conditions were23

    comparing to that needed to be mimicked is the valve24

    was fully open.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    62/69

    Mr. Marsden - Cross 62

    A. Well, I guess maybe Im misunderstanding the1

    question. Because I can turn around, as I stated a2

    minute ago, a restrictive valve flow orifi -- a3

    restrictive plate in that one chamber before it gets to4

    the gate to make it comply.5

    Q. Now, my question is, is it infeasible to6

    comply with the DEP regulations on this site?7

    MR. WOODWARD: Objection as to specificity.8

    CONTINUED BY MR. EISDORFER:9

    Q. Assuming the site plan that was presented in10

    -- the July 30th site plan.11

    A. Not counting storm water, assuming that they can12

    do some form of detention that would make the site13

    developable. I mean --14

    Q. Well, thats my question. Is it impossible15

    to design a storm water system that would comply with16

    DEP regulations to that site?17

    A. Talking to an engineer, no. I mean you can -- we18

    can design whatever it takes, whatever the cost is, to19

    make it work. Its a very tight site. Its not going20

    to be an easy design. It would be more costly. It21

    wouldnt be a simple aboveground structure, as your --22

    Mr. Dipple testified. It would have to be some type of23

    underground system.24

    Q. But its your opinion that it could be25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    63/69

    Mr. Marsden - Cross 63

    designed?1

    A. Oh, sure.2

    MR. EISDORFER: I have no further questions.3

    MR. WOODWARD: No further questions, Your4

    Honor.5

    THE COURT: Okay, you can step down. Oh,6

    wait, wait, wait. Not yet. Sorry. Ms. McKenzie?7

    MS. MC KENZIE: Yes, I just have a couple of8

    quick questions.9

    THE COURT: Good, good.10

    THE WITNESS: Where is she?11

    CROSS-EXAMINATION BY MS. MC KENZIE:12

    Q. Not long. Ive got to find it. Okay, Mr.13

    Marsden, in your experience, what does -- when the14

    NJDEP looks at the existing hydraulic condition of the15

    site, what is it that theyre looking at normally?16

    When they -- if presented with a site such as this,17

    what would they consider to be the existing hydraulic18

    condition on the site?19

    A. Well, theyd look at what features are out there20

    presently; the existing structure, the existing21

    terrain, the existing soils and its permeability22

    aspects. The -- its vegetative state.23

    Q. Okay. So, in your opinion, how would the DEP24

    treat the drainage structures that are there, those25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    64/69

    Mr. Marsden - Cross 64

    existing drainage structures? Do you have an opinion1

    as to how they would respond to those?2

    A. Well, because they have the restricted ori -- have3

    the orif -- the gate valves in there, because the4

    parking lot is as flat as it is, and there is a5

    question to whether the existing site had detention on6

    it already. They would then, in my opinion, consider7

    -- make the request that the site should be considered8

    undeveloped when doing the design criteria for your new9

    system.10

    Q. And have you been involved in applications to11

    DEP where this kind of situation has arisen and that12

    has been their reaction?13

    A. I have not gotten to that point, because we have14

    had systems where farmers had facilities, have had15

    storage area, ponding, that we just assumed didnt16

    exist as a detention. And we went ahead with an17

    undeveloped condition and developed from there.18

    Q. I see. Okay. And you had indicated that you19

    main -- you had designed systems with these kinds of20

    gate valves in the past, in your experience.21

    A. Well, I know they were talked about. I have seen22

    designed system -- I have not done that myself.23

    Q. Okay. Because in the systems that youre24

    aware of were -- how was the management of the gate25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    65/69

    Mr. Marsden - Cross 65

    valve handled?1

    A. Well, the only management or the maintenance of2

    the gate valves that would be handled, and I cant tell3

    you specifically, because it was a long time ago, would4

    be basically a maintenance program, just like we do now5

    for detention structures. We have a maintenance6

    program that says after so many storms, or storms of7

    major extent, we need you to make sure you clean out8

    your detention system. That gate valve may possibly be9

    used at that time, open it up, to flush out the outflow10

    structure so it could be cleaned. Remember, when you11

    put a gate valve in its going to require a12

    restriction. Water, sediment, pebbles from gravel13

    driveways or stone driveways, leaves, would hit this14

    restriction and then drop down. So, then it would15

    start to build up. You have to occasionally get that16

    cleaned out. To clean it out you got to remove the17

    restriction and flush it.18

    Q. And who would normally do that?19

    A. That, in this case, wouldve been somebody thats,20

    because it was a private system, would be somebody in21

    the maintenance of that building.22

    Q. But there was no mechanism in place where23

    public works checked on whether that was undertaken?24

    A. At that time I dont know. I mean now we do. In25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    66/69

    Mr. Marsden - Cross / Redirect 66

    my term, six year plus term here, we do regulate and1

    keep an eye on those structures, because we have2

    reports that mandate maintenance.3

    Q. And -- but you indicated that since you have4

    been on the site youre not aware of any maintenance --5

    A. No.6

    Q. -- thats been undertaken?7

    A. Thats correct.8

    Q. Is there an easement on the property to get9

    to those --10

    A. No, there arent.11

    Q. For maintenance purposes to get to the12

    valves?13

    A. No. Its a private system.14

    MS. MC KENZIE: Okay, thank you very much.15

    MR. WOODWARD: Your Honor, just if I may.16

    REDIRECT EXAMINATION BY MR. WOODWARD:17

    Q. Mr. -- you were asked -- just the last18

    question that you were asked was whether there was any19

    easement to get to the system. But in fact, isnt20

    there a sewer easement on this property?21

    A. As a sanitary sewer, but not storm sewer related.22

    Q. And that runs across the back of this23

    property?24

    A. Thats correct.25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    67/69

    Mr. Marsden - Recross 67

    Q. Over to the Casino Brook area?1

    A. Correct.2

    MR. WOODWARD: No further questions, Your3

    Honor.4

    MR. EISDORFER: Just follow up on one of Ms.5

    McKenzies questions.6

    RECROSS-EXAMINATION BY MR. EISDORFER:7

    Q. Have you been involved in any DEP8

    applications in which there were existing drainage9

    structures where DEP said go back to the predevelopment10

    conditions in designing your new drainage?11

    A. Well, a system, I stated Im involved, and I12

    believe it was Society Hill at Burnage, there was a13

    swale and a pond design. We assumed that that, even14

    before going to DEP, we did not incorporate that.15

    Q. But that wasnt a DEP decision, that was the16

    developers --17

    A. That was our decision.18

    Q. The developers decision?19

    A. Thats correct.20

    Q. Are you aware of any instances in which there21

    are existing manmade drainage facilities where DEP has22

    said go back to the predevelopment conditions?23

    A. Well, Im aware that by regulation, as I stated24

    last time in testimony, which is in our new storm water25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    68/69

    Mr. Marsden - Recross 68

    management, that there is the option or the ability to1

    reanalyze the system, if there is signs that there is a2

    condition that shows what preconditions should be.3

    Q. Well, but that regulation says you look back4

    five years, doesnt it?5

    A. I dont know an exact answer for that one. I6

    dont have it memorized anymore.7

    MR. EISDORFER: I have no further questions.8

    THE WITNESS: Thank you.9

    THE COURT: Anything else, anyone?10

    MR. WOODWARD: No thanks, Your Honor.11

    MS. MC KENZIE: No.12

    THE COURT: Okay. You can step down.13

    THE WITNESS: Thank you.14

    THE COURT: So, I guess next is -- anything15

    further, Mr. Woodward?16

    MR. WOODWARD: Yes. I have Mr. Creelman17

    here.18

    THE COURT: Oh, okay. Should we break for19

    lunch and start --20

    MR. WOODWARD: I think it might be a good21

    idea. Hell be a while.22

    THE COURT: Okay. All right, good. So,23

    well see you at 1:30. Enjoy your lunch.24

    (End of the A.M. session of this proceeding)25

  • 7/31/2019 Transcript 9.28.10 Dipple Marsden

    69/69

    69

    * * * * * * * * * * * *1

    CERTIFICATION2

    I, Regina R. Caldwell, the assigned transcriber,3

    do hereby certify that the foregoing transcript of4

    proceedings in the matter of CRANFORD DEVELOPMENT5

    ASSOCIATES VS. TOWNSHIP OF CRANFORD, heard in the Union6

    County Superior Court, Law Division, Civil Part, on7

    September 28, 2010, Tape #236/10, Index #0890 to the8

    end, and Tape #237/10, Index #0001 to #1200, is9

    prepared in full compliance with the current Transcript10

    Format for Judicial Proceedings and is a true and11

    accurate non-compressed transcript of the proceedings12

    as recorded.13

    AUTOMATED TRANSCRIPTION SERVICES14

    15

    By: Regina Caldwell _357_____________16

    Regina Caldwell A.O.C. Number17

    Date: October 9, 201018

    19

    20

    21


Recommended