+ All Categories
Home > Documents > Transmission Userguide

Transmission Userguide

Date post: 04-Jun-2018
Category:
Upload: vx800bike
View: 220 times
Download: 0 times
Share this document with a friend

of 14

Transcript
  • 8/13/2019 Transmission Userguide

    1/14

    ACCESS TO WESTERN POWERS TRANSMISSION

    NETWORKS

    A USERS GUIDE

    Transmission Division

    363 Wellington Street

    PERTH WA 6000

    GPO Box L921PERTH WA 6842

    Telephone: (08) 9326 6687

    Facsimile: (08) 9326 6550

    Version 1 - April 1998

  • 8/13/2019 Transmission Userguide

    2/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    \Z\19098PC.DOC

    TABLE OF CONTENTS

    1. SUMMARY................................................................................................................................. 1

    2. INTRODUCTION....................................................................................................................... 1

    3. MARKET ARRANGEMENTS IN WESTERN AUSTRALIA.................................................. 1

    4. ACCESS RULES......................................................................................................................... 2

    5. TECHNICAL CODE .................................................................................................................. 2

    6. APPLICATION PROCEDURE.................................................................................................. 3

    7. ACCESS ENQUIRIES ................................................................................................................ 3

    8. TREATMENT OF LOSSES & BALANCING........................................................................... 4

    8.1 LOSSES ........................................................................................................................................ 4

    8.2 BALANCING ................................................................................................................................. 4

    9. DESCRIPTION OF NETWORK ASSETS ................................................................................ 4

    10. TRANSMISSION NETWORK PRICING ............................................................................... 5

    11. NETWORK CHARGES ........................................................................................................... 5

    11.1 CHARGES TO A LOAD USER......................................................................................................... 5

    11.2 CHARGES TO A GENERATOR........................................................................................................ 5

    11.3 CHARGES TO A GENERATOR WITH ON-SITE LOADS ...................................................................... 6

    11.4 CHARGES TO A USER WITH STANDBY USAGE............................................................................... 6

    11.5 CATEGORIES OF CHARGES........................................................................................................... 6

    12. ANCILLARY SERVICES......................................................................................................... 7

    13. CAPITAL CONTRIBUTIONS................................................................................................. 7

    14. FURTHER INFORMATION..................................................................................................... 8

    BIBLIOGRAPHY............................................................................................................................ 8

    FIGURE 1 - WESTERN POWERS TRANSMISSION NETWORKS.......................................... 9

    FIGURE 2 - ACCESS APPLICATION PROCEDURE FLOW CHART..................................... 10

    FIGURE 3 - TRANSMISSION NETWORK - ASSET DESCRIPTION ...................................... 11

    APPENDIX 1 - ENERGY BALANCING EXAMPLE.................................................................. 12

  • 8/13/2019 Transmission Userguide

    3/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    1

    1. Summary

    The Western Power transmission networks becameavailable for open access on 1 January 1997. This has

    provided an opportunity for independent power

    producers to compete with Western Power and other

    generators in the supply of electrical energy using the

    Western Power transmission networks. Access to the

    Western Power transmission networks is managed by

    the Transmission Division in the South West and

    Pilbara Power Division in the North West, both of

    which operate as ring-fenced business units. The

    market arrangement currently supported is for

    bilateral contract trading between generators and

    loads. This is in contrast to the proposal for theNational Electricity Market (NEM) in Eastern

    Australia where all electricity will be traded through a

    pool. In the WA arrangement, independent

    generators seeking access must do so in conjunction

    with contracted associated loads.

    The access regime has been developed through

    extensive consultation with the Office of Energy and

    industry representatives. The terms and conditions of

    network access are defined by the Electricity

    Transmission Regulations 1996 (Regulations), the

    Electricity Transmission Access Technical Code

    (Technical Code) and the Electricity TransmissionAccess Pricing and Charges paper (Pricing and

    Charges Paper).

    Both the technical requirements for access and the

    transmission network pricing follow where practical

    the proposals for the National Electricity Market. In

    particular, the transmission Use of System prices vary

    according to location to promote economic efficiency.

    Ancillary services necessary for secure network

    operation are provided by generators and the

    transmission network operator and are charged for

    according to usage by generators and loads.

    The purpose of this brochure is to outline the open

    access regime that has been set in place and provide

    details on how to make an access application.

    2. Introduction

    Western Power has two separate transmission

    networks: the South West Transmission Network and

    the North West Transmission Network (refer to figure

    1). A brief outline of each is given below. Reference

    should be made to the Western Power publication

    Transmission Networks for geographics and a more

    detailed description of the transmission networks.

    The South West Transmission Network extendsfrom Geraldton to Albany and across to the

    Eastern Goldfields. It contains 140 substations,

    some of which are privately owned, and over6000km of transmission/subtransmission lines

    owned by Western Power. Other lines are

    privately owned. The North West Transmission Network extends

    from Dampier/Karratha to Roebourne/Cape

    Lambert and across to Port Hedland. It contains

    over 27 substations, some of which are privately

    owned, and over 400km of

    transmission/subtransmission lines owned by

    Western Power. There is over 500km of privately

    owned transmission lines.

    The programme of implementation of access to

    Western Powers transmission and distribution

    networks, as determined by the Western Australian

    State Government, is as follows:

    Access to the transmission networks has beenavailable to all users regardless of load size since 1

    January 1997. Access to the distribution networks has been

    available to users with an average load of 10MWor above since 1 July 1997. Load levels for distribution network access will be

    progressively reduced. The State Governments

    current timetable for further deregulation is:

    1 July 1998 - Average load of 5MW orabove;

    1 January 2000 - Average load of 1MW orabove.

    3. Market Arrangements in Western

    Australia

    The Western Australian transmission access regime is

    currently based on physical bilateral contracts

    between generators and loads. This is in contrast to

    the proposed National Electricity Market which,

    being much larger, will operate as a pool of

    generators bidding into the market.

    As a consequence of the (physical) bilateral contract

    arrangements, users are required to ensure that the

    energy imported at their load points is balanced with

    the energy exported at their generation points

  • 8/13/2019 Transmission Userguide

    4/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    2

    (network losses are also taken into consideration).

    Refer to section 8.2 of this brochure for more details.

    Users must comply with the technical requirements

    set out in the Technical Code to ensure that thereliability and integrity of the networks are

    maintained.

    Prices for access to the networks and related services

    are set out in the Pricing and Charges Paper which is

    published annually by Western Power.

    A user is required to enter into an access agreement

    with Western Power for the provision of access

    services.

    4. Access Rules

    The requirements and regulations which form the

    open access regime for the transmission networks in

    Western Australia are set out in the following

    documents:

    Electricity Corporation Act 1994; Electricity Transmission Regulations 1996 (as

    amended); Electricity Transmission Access - Pricing andCharges (published each financial year); Electricity Transmission Access - Technical Code

    (Technical Code); and Electricity Referee and Dispute Resolution

    Regulations 1997.

    The Electricity Corporation Act 1994 requires

    Western Power to provide access to its transmission

    and distribution networks; the manner and timing

    being prescribed by ministerial order. Section 100 ofthe Act provides for the Governor to make any

    regulations necessary to give effect to the open access

    regime, in accordance with the principles and

    requirements set out in the Act.

    The Electricity Transmission Regulations 1996 (as

    amended) provide the framework for access to

    Western Powers transmission networks. They set

    out, among other things:

    the application and access procedure; confidentiality requirements;

    demand and energy balancing requirements; technical regulation provisions (contained in

    the Technical Code); terms and conditions of an access agreement;

    and transitional provisions.

    Persons requiring access to Western Powers South

    West network must submit an access application to

    the Transmission Division of Western Power.

    Persons requiring access to Western Powers North

    West network must submit an access application to

    the Pilbara Power Division of Western Power. Refer

    to Section 6 of this brochure for more details.

    The Pricing and Charges Paper sets out the prices tobe charged for access services (including ancillary

    services). These charges are covered in more detail in

    sections 11 and 12 of this brochure.

    The Technical Code sets out the technical

    requirements applying to the transmission networks

    and users facilities, and the network planning criteria

    to be used when planning reinforcements or

    enhancements to the transmission networks. Further

    detail is provided in Section 5 of this brochure.

    The Electricity Referee and Dispute ResolutionRegulations 1997 establish the office of the Electricity

    Referee for resolving disputes regarding transmission

    and distribution access.

    5. Technical Code

    Regulations 26 and 27 of the Electricity Transmission

    Regulations 1996 require Western Power to publish a

    Technical Code and network planning criteria,

    respectively. The Technical Code was first published

    on 31 March 1997. It sets out, among other things:

    transmission network performance criteria,including network planning criteria;

    technical requirements of users facilities; inspection, testing, commissioning, disconnection

    and reconnection requirements; power system security requirements; metering requirements; and schedules of technical details required to support

    an application for connection.

  • 8/13/2019 Transmission Userguide

    5/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    3

    The Electricity Transmission Regulations 1996

    require Western Power and all users to use all

    reasonable endeavours to comply with the Technical

    Code.

    The requirements of the Technical Code are similar tothose set out in the National Electricity Code,

    particularly those in Chapter 4 (Power System

    Security) and Chapter 5 (Network Connection).

    6. Application Procedure

    Part 2, Access, of the Electricity Transmission

    Regulations 1996 sets out the application procedure

    for a person requiring access to Western Powers

    transmission networks. Figure 2 shows the

    application procedure (simplified) in flow chart form.

    Application forms are available from, and should be

    submitted to, the following contacts within Western

    Power:

    For access to the South West Network:

    Manager Planning & Contracts

    Transmission Division

    Western Power Corporation

    363 Wellington Street

    PERTH WA 6000

    GPO Box L921PERTH WA 6842

    Telephone: (08) 9326 6687

    For access to the North West Network:

    Manager Pilbara Power

    Pilbara Power Division

    Western Power Corporation

    18 Anderson Street

    PORT HEDLAND WA 6721

    PO Box 314

    PORT HEDLAND WA 6721

    Telephone: (08) 9173 8222

    Following the receipt of an application, Western

    Power must provide the applicant with an initial

    response within 20 business days of receiving the

    application. The initial response will set out

    information such as:

    whether it is likely that there is sufficient sparecapacity to provide access to the network or

    whether the network will have to be augmented; whether it is likely that any connection will have

    to be installed or upgraded;

    whether a capital contribution will be required of

    the user;

    the period within which Western Power is able tomake a preliminary assessment; and

    whether Western Power is able to make an accessoffer within 65 business days of receiving the

    application, and, if not, an alternative period.

    Following the initial response, Western Power

    proceeds to performing a preliminary assessment of

    the application and/or making an access offer.

    A preliminary assessment is only performed ifrequested by the applicant. A preliminary assessment

    is intended to provide an applicant with a good

    assessment of their proposal in situations where the

    making of an access offer may not be appropriate.

    For instance, a number of generators may be

    tendering to provide generation for a project. Not all

    the generators will want Western Power to go as far

    as making an access offer but will want to know the

    feasibility of their proposal in terms of connecting to

    the network.

    Following an access offer being made by Western

    Power, an applicant has 20 business days within

    which to accept the offer. A longer period may be

    given with Western Powers agreement.

    Western Power charges for the assessment of an

    access application. Details of the estimated charges

    are provided to applicants in the initial response

    provided by Western Power.

    7. Access Enquiries

    In the feasibility stage of a project, a person may notwish to make an application but would still like to

    ascertain the likely feasibility of their project in terms

    of being able to connect to the transmission network.

    In this case, an access enquiry may be made.

    Information regarding the proposal to be assessed

    should be forwarded to the contacts mentioned in

    Section 6. To assist people in providing relevant

    information, it is often helpful if the information

    requested in an application form is completed as far

    as possible, however, it should be made clear that an

    access enquiry is being made.

  • 8/13/2019 Transmission Userguide

    6/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    4

    Western Power charges for the assessment of an

    access enquiry. Details of the estimated charges are

    provided following the receipt of an access enquiry.

    8. Treatment of Losses & Balancing

    8.1 Losses

    The calculation of system losses incurred in bilateral

    access arrangements is based on network connection

    point loss factors. Loss factors are used to determine

    the half hourly energy to be sent out from generators

    to meet the half hourly energy usages at the associated

    load points plus system losses. Loss factors are

    calculated in a similar way to that proposed for theNational Electricity Market (NEM). In the NEM, loss

    factors are applied to pool prices. In WA, loss factors

    are applied to quantities of power and energy.

    Loss factors are based on marginal losses on the

    system. They depend on the system operating

    conditions and will vary with the load and generation

    patterns. They are to be re-calculated annually and

    based on past system operating conditions.

    Loss factors are defined by the following equations:

    For a lossless network with n nodes,i = n

    Pi = o

    i = 1

    i.e. energy injected equals energy taken.

    For actual networks where a proportion ofenergy is consumed (lost) in lines and

    transformers, the energy balance is given by:

    i = n

    Li*Pi = o

    i = 1

    where Li is the loss factor for node i at which

    incremental energy Pi is injected or taken.

    8.2 Balancing

    The principles of energy and demand balancing are

    given in Part 4 of the Electricity Transmission

    Regulations 1996. The prices and charges, including

    practical examples, are provided in the Pricing andCharges Paper.

    As stated earlier, the energy market arrangement

    currently operating in the Western Australian

    transmission open access regime is not based on a

    generator pool system, but relies on bilateral contracts

    between generators and loads.

    Therefore, network users must use reasonable

    endeavours to ensure that the energy imported at their

    load (exit) points is balanced, after considering losses,

    with the energy exported at their generation (entry)

    points. It is likely that some form of load following

    governor control would need to be installed to achieve

    this.

    Energy imbalances which occur within a permitted

    tolerance of 3% of half the Contract Maximum

    Demand, ie small load following errors, may be

    settled on an energy basis. Where imbalances exceedthis tolerance, settlement will be on a financial basis

    at published half hourly seasonal energy rates. An

    energy balancing example is provided in Appendix 1

    of this brochure.

    However, to assure reliability of supply during periods

    of generator maintenance or unplanned outages, users

    are encouraged to contract for the provision of

    standby power. This standby power, or standby

    generation reservation, may be contracted from

    Western Power or from any independent generator

    user.

    Where a users import power demand exceeds its

    export power supply by more than its standby

    generation reservation it will incur an excess standby

    generation capacity charge for each kW in excess.

    This charge can only be applied once in every seven

    day excess demand period to the maximum demand

    imbalance occurring during that period.

    Unlike energy imbalances, there is no permitted

    tolerance for demand imbalances. This provides users

    with a significant incentive to contract for the

    provision of standby power.

    To assist Western Power in the management of

    transmission capacity, users are also given an

    incentive to match their export supply and import

    demand power to the generator declared sent out

    capacity (DSOC) and load contract maximum

    demand (CMD), respectively. Users which exceed

    their DSOC or CMD will incur an excess network

    usage charge.

    9. Description of Network Assets

  • 8/13/2019 Transmission Userguide

    7/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    5

    The principal elements of the transmission networks

    include transmission substations and zone substations,

    interconnected by transmission and subtransmission

    lines. The transmission networks enable the

    transportation of electricity from power stations to

    zone substations and high voltage customer loads.

    The zone substations provide the interface betweenthe transmission networks and distribution networks.

    For the purpose of transmission open access, the

    transmission networks assets comprise Connection

    assets, Shared Network assets and Ancillary Services

    assets. These are described as follows:

    Connection Assets: those assets at the point ofphysical interconnection with the transmission

    networks which are dedicated to a user - that is, at

    substations including transformers and

    switchgear, but excluding the incoming lineswitchgear. Connection assets for generators are

    referred to as entry assets and for loads they are

    called exit assets.

    Shared Network Assets: all other transmissionassets in the networks not dedicated to any

    particular customer, but shared to some extent by

    network users.

    Ancillary Services Assets: network assetsperforming an Ancillary Services function

    comprise:

    Those providing a Control System Serviceeg system control centres, supervisory

    control and communications facilities.

    Those providing a Voltage Control servicein the networks eg a proportion of the costs

    of capacitor and reactor banks in

    substations.

    Figure 3 shows in simplified form the principal

    elements of the transmission networks and the

    categorisation of the assets as described above.

    10. Transmission Network Pricing

    Transmission pricing for the Western Power

    transmission network has been developed along

    similar lines to other Australian states and as

    proposed for the National Electricity Market. There

    are two main aspects to determining prices: (i)

    determination of the aggregate annual revenue

    requirement (AARR), and (ii) the cost reflective

    allocation of the revenue requirement to network

    connection points. The methodology for the latter is

    known as the cost reflective network pricing (CRNP)

    method.

    The AARR consists primarily of asset related charges

    and operating costs, the largest component of which

    is the asset charges reflecting the capital intensive

    nature of transmission. Transmission assets areindependently valued using the Optimised Deprival

    Value (ODV) methodology. The operating costs

    component of revenue reflects good operating practice

    and is scaled from year to year using an efficiency

    factor to reflect expected improvements in operating

    efficiency.

    The CRNP method basically performs the function of

    allocating network revenue requirements according to

    usage of network assets. In principle the further the

    load from generation sources, the higher will be the

    usage of network assets and the higher the charges.The proportion of network AARR allocated using this

    method (50%) is chosen to provide a pricing signal to

    loads approximating the long run incremental cost of

    network augmentation at each connection point. The

    decision to base pricing on long run rather than short

    run signals reflects the belief that most network users

    invest for the long run and that short run signals for

    the most part would not be effective.

    11. Network Charges

    11.1 Charges to a Load User

    A load user will be required to pay the following

    charges:

    connection; exit use of system; common services; capital contribution in relation to any system

    augmentation, connection assets or ancillary

    service; and

    excess standby generation capacity and excessnetwork usage charges.

    11.2 Charges to a Generator

    A generator will be required to pay the following

    charges:

    connection; entry use of system; ancillary service; capital contribution in relation to any system

    augmentation, connection assets or ancillary

    service; and

  • 8/13/2019 Transmission Userguide

    8/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    6

    excess standby generation capacity and excessnetwork usage charges.

    11.3 Charges to a Generator With On-site Loads

    A generator with on-site loads which exports and

    imports energy from the transmission network will be

    required to pay the following charges:

    connection; the higher of the entry use of system charge based

    on the declared sent out capacity or the total of the

    exit use of system and common services charges

    based on the contract maximum demand (CMD);

    ancillary service; capital contribution in relation to any system

    augmentation, connection assets or ancillary

    service; and

    excess standby generation capacity and excessnetwork usage charges.

    11.4 Charges to a User With Standby Usage

    A load user or a generator with on-site loads can

    apply for network standby usage and receive a

    discount on the common services charge if it satisfies

    the following:

    there is a feeder at the connection dedicated tostandby access or the total generation capacity of

    on-site generators is more than 10MW; and the load factor of actual standby energy usage

    during the standby terms is not more than 0.15.

    Reference should be made to the Pricing and Charges

    Paper for further details.

    11.5 Categories of Charges

    Connection charge: this charge is based on theconnection assets provided and includes the

    control system service (CSS) charge which is one

    of the ancillary services charges.

    Transmission Use of System (TUOS) charge: this

    charge provides locational signals to all network

    users to encourage efficient network expansion.

    There are exit TUOS charges and entry TUOS

    charges. The exit TUOS charge applies to a user

    who imports electricity from the transmission

    network (load user). 50% of the cost of the

    transmission shared network is allocated to the

    exit TUOS cost pool. This cost pool is allocated to

    individual load users using the Cost Reflective

    Network Pricing (CRNP) method. The exit TUOS

    prices are based on the CMDs.

    The entry TUOS cost pool represents 20% of the

    cost of the transmission shared network assets and

    is allocated to generators. This cost pool is

    allocated to individual generators using the CRNP

    method. The entry TUOS prices are based on the

    declared sent out capacities.

    Common service charge: the remaining 30% ofthe cost of the transmission share network plus

    two-thirds of the voltage control cost is postage

    stamped to all load users. Ancillary services charges: these are to recover the

    cost of providing the following services:

    voltage control control system services (CSS) spinning reservepost trip management energy balancingVoltage control charge: one third of the voltage

    control cost is allocated to the connection charge

    and the remaining is included in the common

    services charge.

    CSS charge: this is allocated to all connection

    points based on the equivalent number of remote

    terminal units (RTU) installed on site. This

    charge is included in the connection charge for

    simplicity.

    Spinning reserve charge: at present,

    approximately 20% of the spinning reserve cost is

    allocated to load users and the remaining to

    generators with a generation capacity of 10MW

    and higher. Refer to the Pricing and Charges

    Paper for details of the allocation.

    Post trip management charge: this is allocated to

    generators based on the number of times the unit

    is tripped and its MW losses. Refer to the Pricing

    and Charges Paper for details of the charge

    calculation.

    Energy balancing charge: this consists of the

    balancing service charge and the out of balancing

    and half hourly out of balancing charges. The

    balancing service charge depends on the number

    of connections involved in the access

    arrangement. The out of balancing and half

    hourly out of balancing charges depend on usage.

    Loss factors are used to determine the system

    losses. Refer to regulation 22 in the Electricity

    Transmission Regulations 1996 for details.

  • 8/13/2019 Transmission Userguide

    9/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    7

    Refer to section 12 of this brochure for further

    details on ancillary services, including definitions

    of the services listed above.

    Capital contribution charge: refer to Section 13,Capital Contributions, below.

    Excess standby generation charge: refer to section8.2 of this brochure for details.

    Excess network usage charge: refer to section 8.2of this brochure for details.

    12. Ancillary Services

    Western Power in its role of system operator is

    responsible for maintaining the quality of supply, and

    ensuring the safe, secure and reliable operation of the

    power system. To satisfy these responsibilities, a

    system operator must be able to monitor and correct

    where necessary the system frequency and voltage,

    transmission network loading, generation dispatch,

    communication and SCADA facilities.

    To this end, Western Power has defined a number of

    categories of ancillary services which are provided bygeneration, transmission, and system operations

    communication and control equipment.

    These categories are:

    Voltage Control; Spinning Reserve; Post Trip Management;

    Control System Services; and Energy Balancing.

    Voltage Control is required to maintain the system

    voltage within operational limits during steady state

    operation and in the aftermath of trips. It is achieved

    by regulating generator MVAr output and

    transmission voltage control equipment, such as

    capacitors, reactors and transformer on-line tap

    changers.

    Spinning Reserve is the additional generation

    capacity and interruptible load schemes necessary to

    maintain the system frequency during load

    fluctuations and generator tripping.

    Post Trip Management is the maintenance of system

    stability in the aftermath of generator trips. It is

    provided by spinning and standing reserves.

    Control System Services is the 24 hour monitoring

    and control of the power system, including data

    acquisition, switching and generator dispatch. It is

    provided by control centres and SCADA and

    communication assets.

    Energy Balancing refers to the marginal energy

    trades that will occur between Western Power and

    independent generation. The energy balancing

    ancillary service is required to monitor and record

    energy supply and usage in order to facilitate energy

    balancing and settlement.

    13. Capital Contributions

    A new user who requires Western Power to make a

    capital investment to provide the access services, the

    connection services or the ancillary service to it will

    be required to make a capital contribution to make the

    investment commercially viable to Western Power.

    The investment is commercially viable to Western

    Power if:

    Western Power can recover within a reasonabletime the costs, the capital investment and a

    reasonable rate of return without increasing the

    charges payable by the existing users to contribute

    to the new investment; and Western Power has sufficient allocated capital

    funds to undertake the augmentation.

    The reasonable time, which is limited to 15 years, is

    determined based on:

    the expected commercial life of the augmentation; the potential future use of the augmentation by

    existing and potential users; the financial viability of the applicant and the

    applicants business; and Western Powers performance targets.Reference should be made to the Electricity

    Transmission Regulations 1996 (as amended) for

    details.

  • 8/13/2019 Transmission Userguide

    10/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    8

    14. Further Information

    Further information on all aspects of access to

    Western Powers transmission networks (including

    obtaining various documents and application forms -

    see Bibliography below) may be obtained from thecontacts given in Section 6 of this brochure.

    Bibliography

    1. Electricity Corporation Act 1994.2. Electricity Transmission Regulations 1996 (as

    amended).3. Electricity Referee and Dispute Resolution

    Regulations 1997.4. Western Power Corporation, Electricity

    Transmission Access - Pricing and Charges - 1

    July 1997 to 30 June 1998.5. Western Power Corporation, Electricity

    Transmission Access - Technical Code.6. Western Power Corporation, Transmission

    Networks.

    Documents 1, 2 and 3 are available from:

    State Law Publisher10 William Street

    PERTH WA 6000

    Telephone: (08) 9321 7688

    Facsimile: (08) 9321 7536

    Documents 4, 5 and 6 are available from the Western

    Power contacts listed in Section 6 of this brochure.

  • 8/13/2019 Transmission Userguide

    11/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    9

    FIGURE 1 - WESTERN POWERS TRANSMISSION NETWORKS

  • 8/13/2019 Transmission Userguide

    12/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    10

    APPLICANT

    1. Formulate proposal.

    2. Submit access application with

    optional request for preliminary

    assessment.

    6. Accept access offer within 20

    business days or such longer

    period as is agreed.

    WESTERN POWER

    3. Prepare written response to access

    application within 20 business days

    (unless further information

    requested by Western Power).

    Response to include:

    . time for preliminary assessment;

    . time to make access offer.

    4. If a preliminary assessment isrequired, prepare report within

    time specified in response,

    otherwise prepare access offer

    within period specified in response

    (unless further information

    requested by Western Power).

    5. Prepare access offer within time

    specified in response (unlessfurther information requested by

    Western Power).

    7. Finalise access agreement.

    NOTE: The application procedure shown in this chart is in simplified form. The

    procedure and times for performing activities are subject to conditions

    and variations set out in Part 2 of the Electricity Transmission

    Regulations 1996.

    FIGURE 2 - ACCESS APPLICATION PROCEDURE FLOW CHART

  • 8/13/2019 Transmission Userguide

    13/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    11

    FIGURE 3 - TRANSMISSION NETWORK - ASSET DESCRIPTION

    Generator

    Transformer

    330,220 & 132 kV

    Lines

    132 & 66 kV

    Lines

    POWER

    STATION

    TRANSMISSION

    SUBSTATION

    TRANSMISSION

    NETWORK

    TRANSMISSION

    SUBSTATION

    SUBTRANSMISSION

    NETWORK

    ZONE/CUSTOMER

    SUBSTATION

    SHARED

    NETWORK

    ASSETS

    CONNECTION

    (ENTRY)

    ASSETS

    CONNECTION

    (EXIT)

    ASSETS

    TRANSMISSION

    NETWORK

  • 8/13/2019 Transmission Userguide

    14/14

    Access To Western Powers Transmission Networks - A Users Guide

    Version 1 - April 1998

    12

    Appendix 1 - Energy Balancing Example

    The following energy balancing example assumes a transmission access agreement consisting of two

    generators in the users group of entry connections and three loads in the users group of exit

    connections.

    The entry and exit point energy amounts are based on a single half hour energy reading.

    Gen 1 Gen 2 Load 1 Load 2 Load 3

    Entry Loss Factor (LFEntry) 1.025 1.020

    Entry Energy Reading, kWh ( ETEntry) 4763.5 3239.0

    Contract Max Demand, kW ( CMD) 11000 16000 8000

    Exit Loss Factor (LFExit) 1.040 1.030 1.035

    Exit Energy Reading, kWh (ETExit) 2705.5 3964.0 1989.5

    Energy Imbalance (EIMB) = Energy Entry Amount (EEA) - Energy Exit Amount (EEXA)

    EEA = (ETEntry * LFEntry)

    = (4763.5 * 1.025) + (3239.0 * 1.020)

    = 8186.37 kWh

    EEXA = (ETExit * LFExit)

    = (2705.5 * 1.04) + (3964.0 * 1.03) + (1989.5 * 1.035)

    = 8955.77 kWh

    EIMB = 8186.37 - 8955.77

    = -769.40 kWh

    Permitted Tolerance (TOL) = 3% * CMD/2

    = 0.03 * (11000 + 16000 + 8000)/2

    = +/-525 kWh

    Energy Settlement

    The energy imbalance amount to be settled on an energy basis by the end of the month, called the

    Adjusted Net Amount (ANA), is equal to the negative of the Permitted Tolerance = -525 kWh.

    The aggregate of this amount and all other ANAs for the month would be multiplied by the

    appropriate out of balance price to calculate the energy out of balance charge for the month.

    Financial Settlement

    The energy imbalance amount to be settled on a financial basis at half hourly seasonal energy rates,

    called the Revised Net Amount (RNA), is equal to the amount in excess of the Permitted Tolerance =

    -769.40 - (-525) = -244.40 kWh

    This amount would be multiplied by the applicable half hour seasonal energy price to calculate the

    energy imbalance charge.

    In both cases the energy imbalance is negative. The user would, therefore, be in debt to Western

    Power for the energy deficit.


Recommended