Local Sustainable Transport Fund
Nottingham Urban Area partnership:• Key component = £5 million secured• Large scale bid = £11 million business case submitted
Key elements:– Smartcard integration– Community Travel Hubs– Active travel partnerships incl. Ucycle/GNTP/Community cycling
package incl. schools, events programme– Development of low carbon transport network (incl. cycling,
electric vehicle infrastructure, car club)
Nottingham Station Hub
• £70m partnership project • Interchange for train, tram, bus,
taxis, cycling• Multi-storey car park works due to
complete May 2012• Main station works to start summer
2012• Major signal and trackwork
upgrading summer 2013• All works complete November 2014
NET Phase 2
• Final Government approval in Dec 2012
• Tramlink Consortium to design, build and operate
• Site clearance and utility works have started
• System capacity to double to 20m passengers per year
• Further 2,500 P&R spaces• New lines to open in 2014
Quality Bus Network
Planned further investment:• £5m Better Bus Areas Bid to extend Statutory Bus Quality
Partnership Scheme along high frequency bus corridors• £1.7m Green Bus Fund Bid supporting £4.6m investment
in 19 hybrid diesel electric buses (third of Linkbus fleet)• 8 electric CentreLink buses to enter service in the spring• Bus stop infrastructure incl. real time information
Workplace Parking Levy• The Workplace Parking Levy (WPL) is a
charge on employers with more than 10 commuter parking spaces located within the City of Nottingham
• Local contributions to:- NET Phase 2- Station Hub- Link bus network
Milestones:1st October 2011 – Scheme in force and employers
legally obliged to hold a licence (no charge)
1st April 2012 – WPL charging to commence
• Business support- Travel planning advice and support- Car park management- Bespoke public transport information packages- Cycling promotion package
A453 widening M1 to Nottingham
Latest position:• £160m funding announced in
Autumn Statement• Awaiting statement from
Secretary of State on scheme orders and outcome of public inquiry
• Integration with NET Phase 2 through 1,000 space P&R
• Construction to start this year• Completion by 2015
Ring Road Major Scheme
Components:• Junction improvements• Selective widening• New crossings• Bus interchange facilities• Cycle route upgrade
Investment = £16m
Timescales:– Funding announced (Dec 2011)– Consultation (Spring 2012)– Final Approval (by end 2012)– Construction (2013 – 15) Derby Road
Hucknall Road
A610
Midland Mainline
• Ambition to achieve Nottingham to London in 90 minutes
• Line speed upgrades• Timetable improvements• Electrification
• Prerequisite to new High Speed Rail line
High Speed Rail
• Proposed Y network endorsed including stop serving the East Midlands with Line to Birmingham by 2024 and extensions by 2032
• Engagement on extensions from Autumn 2012
• Detailed consultation expected in 2014