+ All Categories
Home > Documents > 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR...

'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR...

Date post: 31-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
68
TURKEY'OINT 3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point Unit 3 steam generators was .conducted in October,. 1980. The following items were accomplished: 1. ,gauging, of steam generator hot legs and cold legs - all steam generators 2. measurements of 81 tube support plate flow slots in all steam generators 3. eddy current inspection of small radius U-bends in steam generator A 4; Regulatory Guide 1.83 eddy current. measurements in the hot legs and cold legs of all steam generators 5. ,preventive plugging Table 1 is a summary of the approximate number of steam generator tubes inspected in each category and in each steam generator. eovoaso BD2
Transcript
Page 1: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

TURKEY'OINT 3 STEAM GENERATOR

INSPECTION PROGRAM

I. Introduction

An extensive inspection program for the Turkey Point Unit 3 steam

generators was .conducted in October,. 1980. The following items were

accomplished:

1. ,gauging, of steam generator hot legs and cold legs - all steam

generators

2. measurements of 81 tube support plate flow slots in all steam

generators

3. eddy current inspection of small radius U-bends in steam generator A

4; Regulatory Guide 1.83 eddy current. measurements in the hot legs and

cold legs of all steam generators

5. ,preventive plugging

Table 1 is a summary of the approximate number of steam generator tubes

inspected in each category and in each steam generator.

eovoasoBD2

Page 2: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

S

'l)

~

4l Ol

~ . IP

'fl

Page 3: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

"Page 2.I

Table 1: Summary of Total Steam Generator Tubes Inspected

~AL ~ALA L ~II L ~CIA .L ~CH I C I ~

Gauging

U-Bend Rows

2-5

1170 )44 1342 210 1273 231

R.G- 155 428 199 260 150

This report summarizes the inspections conducted, the results of these

inspections and preventive plugging, programs accomplished .

II. Inspection Programs

A. Gauging Progr am

The tube gauging program in the tubelane area is based on previously

defined regions where significant tube deformation has occurred.

These regions were formerly determined using finite element analysis

techniques which yield tube hoop strain contours as a function of

plate deformation. The boundary in the peripheral'ubelane areas

near the three and nine o'lock ~iedge locations is modified to take

into account the greater extent of deformation in this region of the

plate determined by previous experience. After four reinspections

since the first gauging inspection at Turkey Point 3, it became

apparent that the finite element model no longer gave reasonable

Page 4: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~I~@rN tci

P

QT

Page 5: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

'P age 3

expectations as to the position of a strain boundary which might be

linked to location of the most severly restricted tubes. The 17.51

strain contour utilized in the 12/79 inspection would encompass most

of the hot leg tube bundle at 24 effective full power months beyond

closure of the support plate flow slots, which is regarded as having

occurred as of the 12/77 inspection. (The tube hoop strain at 24

effective full power months beyond full closure is given forreference purposes in Figure 1). Therefore, the gauging program,

based on the program used in 12/79, has been adjusted to reflect

prior experience at the Surry and Turkey Point plants. Additional

i nspection programs were defined for the periphery, wedge, and patch

plate regions. These programs were based on previous tube leakage

histories at the Turkey Point and Surry plant sites, as well as

previous gauging results at the Surry and Turkey Point sites, as

deemed apropriate. Due to the current awareness of the potential fortube deformation on the cold leg side, inspections of all three steam

generator cold legs were performed.

The inspection boundary for the December 1979 inspection (Figure 2)

is included for reference. The gauging inspection boundaries for the

October 1980 inspection are indicated in Figure 3 (typical hot leg)

and Figure 4 (typical cold leg).

Page 6: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

r'

Qil

I

.5 t ~

~P'

Page 7: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

' " Page 4

The following, conservatisms. were utilized in determining the Turkey Point 3

inspection boundary:

l. If a restricted tube was found close to the inspection boundary, the

inspection was expanded in that area.

2. In addition to the specific gauging inspection program, it should be .noted

that tubes in the central portion of the tube bundles from Row 13 upward

were tested with 700 mil probes, providing early indications on arp new

deformation which might exist away from the regions usually regarded as

active, i.e. the tubelane, patch plate, wedges, and periphery-

3. Tubes restricted in previous inspections, but not adjacent to the areas of

predominant activity were incorporated into the gauging program laid out

generally for the three steam generators.

B. Flow Slot Measurements

Photographs were taken in each steam generator through the secondary

handholes. These photographs were then utilized to measure the openings

in the 81 tube support plate flow slots. Results are discussed in Section

III. .FLow slot measurements are utilized in the finite element analysis

work and are an indicator of the present status of denting in the steam

generators.

Page 8: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

I '1

I ~

r

Page 9: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~ a' ''rage 5

tl t II 1 d~iThe U-bends of unplugged tubes in Rows 3 thru 5 in steam generator A,were

examined with 100, KHz. These inspections are performed to confirm the

integrity of the small raidius U-bends in low number rows.

In the January 1979 inspection, annulus measurements, were taken in steam

generator.B. These measurements provide a qualitative indicator of the

upper pl'ate expansion trends in the most affected steam generator. That

had been the second such measurement of this type .for steam generator B.7

No obvious trends had been noted in this unit or in three such

measurements in Turkey Point'Unit 4.. Therefore, this measurement was not

made at this inspection and is not planned for future inspections.

D. ~Re ul atony. Guide 1.83 R.G. 1.83 Ins ection

The types and extent of inspections required in this area are specified in

R.G. 1.83. Typical inspection, plans are included (Figures 5 and 6).

During the inspections, expansions of the program in steam generators A

and C'ere accomplished as required by R.G. 1.83. Results of the

inspection are discussed later in. this report.

Page 10: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

0\, ~I ~

t

Page 11: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

'r'a ge 6

III- Inspection Results

1

A. Gauging Program

Results of the gauging inspections are indicated in Figures 7, 8, 9,.

10, 11 and 12 and are summarized in Table 2. It shouTd be noted thatthe tubes inspected included tubes R22 C13 (S/G3A) and R12 C80

(S/G3B)- These tubes were previously reported to have been

inadvertently omitted from the last inspection program and were

committed to be inspected during this outage (letter L-80-26, January

18, 1980). The inspection results confirmed that neither tube

required plugging nor were they located in areas of generalized

denting.

Page 12: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Il i~ ~ I ~

~ 4

k

Page 13: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~ ' '8 "ge 7

TABLE '2: Tube Restriction Summary

Number of Tubes Restricting Passage of Gauge

S/G Gauge

Diameter Hot Le

Tubel ane

Cold Le

Periphery and Wedge Patch Plate

'G

A

.650" 22

. 610" 4

. 540" 9

0 22

0 0

SG B

.650" 14

. 610" 1

. 540" 0 :0

,0

0

SG'

. 650" 25 0' 0

. 610"

.'540"

4 0'

'0

Page 14: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~ I

I' ~

Page 15: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~ ~' ~"f age 8t

Summary comments resulting from the review of this and other data are as

follows:

1. In steam generators A, B, and C, restricted tubes generally developed

adjacent to previous activity or clustered together with other new

activity. This was particulary true of tubes that restricted the 0-610"

and 0.540" probes. Areas of activity were consistent with past

historical data for this and other plants.

2- Tube restrictions were noted in some of the inspected wedge areas (in the

hot legs) of all steam generators and this activity appears consistent

with previous experience at this and other units.

3. In this inspection of the cold leg areas, only one tube restriction was

noted in the tubelane regions (SGB). No activity was noted in four of

the six cold leg wedge areas inspected- Slight activity was noted

adjacent to one of the inspected wedge areas in each of SG/A and SG/C.

The level of activity is consistent with that noted in previous Turkey

Point inspections. The overall level of activity continues to indicate a

very low growth r ate as compared to the hot leg.

4. During the last approximately 8.5 EFPH of operations, no shutdowns due to

leakage events occurred-

Page 16: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

'1

'l~ 'I ~I

Page 17: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Page 9I

.'Review of the gauging results for this period shown that 82 tubes were

reported restricted in the tubelane region; this compares with 75

observed in December, 1979 after 6 EFPM and 214 in 1/79 a'fter 9.5 EFPM-

A restricted tube is defined as a tube not passing a 650 mil probe. The

apparent limitation in the number of restrictions reflects the fact that

plugging in December, 1979 was performed for a 10 month period, but less

than 8.5 months operation actually ensued.

8. Flow Slot Measurements

The results of the flow slot measurements are indicated in Figure 16.

Only the lower support plates are clearly visible in each S/G- The

results are consistent with previous behavior.

C. Other Dentin Related Ins ections

The U-bends of unplugged tubes in rows 3 thru 5,in steam generator A were

examined at 100 kHz- No .indications were noted in these small r adious U-

bends.'.

Re~ulato~r Guide 1;83 Ins ection Results and Evaiuation

The results of the Regulatory Guide 1.83 Inspection are summarized in

Table 3. As a result of this inspection, a total of fourteen tubes will

be plugged for indications equal to or greater than 40Ã wall

penetration. An additional tube (R4-C46) in steam generator A is

pluggable on this basis, but is also pluggable due to a .540 inch

Page 18: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

0'I

Page 19: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

I

Page 10

restriction- The pluggable tubes are generally located in rows 5 to 8,

inclusive, with only a .few in higher rows, as shown in Figures 13 and 15.

Evaluation of the results suggests probable thinning in the region of the

sludge pile in the cold leg.

Comparison of the eddy current signals from the affected tubes wi th

corresponding signals from previous inspections indicates that no major

change in depth of penetration has occur red. Therefore, it is'oncluded

that the rate of thinning has not increased substantially.

TABLE 3

Re ulator Guide 1.83

~ Ins ection Results

Si ze of Indication

/Wall Penetration)

SG A

Inlet Outl et

SG B

Inlet Outlet

SG C

Inlet Outlet

<20

20-29

30-39

)40

140

74

29

14

32

20

5 45

3 88

1 24

1 0

Page 20: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

! ~, ~

Page 21: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

IV. ~Pie gin Criteria

A- Gauging Program

Although experience has shown that advance of the predicated strain

contours from the finite element model no longer is an appropriate

basis for tube plugging, the plugging criteria which were developed

using the model have been retained, since'their application has

generally been conservative and effective in reducing the frequency

of tube leakage events resulting from denting. As in the tray, 1980

inspection of Turkey Point 4, a program which incorporates allpreviously observed activity with several rows margin beyond is

considered appropriate; again a sampling of central area tubes

provided by the Reg. Guide 1.83 inspection permits detection of new

areas of activity (should any occur).

The criterion established for plugging tubes in the region of the

patch-plate differs from that used for other regions of the bundle.

All leaks in the patchplate region have occurred at the perimeter of

the plate or near to the patchplate boundary, where plug welds

connect the patchplate to the main body of the tube support plate-

All observed data indicate that the phenomenon at the patchplate is

local in nature and is not consistent with the general strained state

of the plate, nor can the phenomenon be represented by the finiteelement model. Due to these factors, the region of the patchplate is

inspected and a specific set of plugging criteria applied- Because

Page 22: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

qfft ~ I t:IIl

Page 23: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~ ': Page 12

of the fact that leakers in this region have not always restricted0.540 inch probes, leakers and tubes that restrict the 0.540 i'nch

probe should be treated'like, and the surrounding tubes about both

should be plugged. In addition, tubes that restrict the 0.610 inch

probe 'should be plugged and tubes on either side of the patchplate

boundary (plate perimeter on one side the plug welds on the other

three sides) that restrict the 0.650 inch probe should be plugged-

Due to the local plate cracking that is believed to occur at the

periphery and near wedge locations, tube leaks may occur here at

lower levels of tube restriction than in the tubelane. Thus, the

wedge areas should have their own inspection program and plugging

criteria. The plugging criteria at hot leg wedge locations calls fortreating leakers and tubes that restrict the 0.540 inch probe in a

similar manner. In addition, tubes that restrict the 0-610 inch

probe and peripheral tubes that restrict the 0.650 inch probe should

be plugged. Cold leg plugging will be based on the degree of

activity noted and rates of progression observed from gauging-

The plugging criteria which support at least six months of operation

are:

1 ~ All tubes which do not pass the 0.540 inch probe will be plugged-

2. Additionally, two (2) tubes beyond (i.e , higher row numbers) any

tube in columns 1-92 which did not pass the 0.540 inch probe in

the tubelane region will be plugged.

Page 24: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

kt 0g ~ ~

Page 25: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

,. P «ge 13

3. All tubes .which do not pass the 0.610 inch probe will be plugged.

'4. The tubes in any column for which plugging under criter.ia (1),

(2), or (3) above is implemented in the tubelane region will also

be plugged in the lower row numbered tubes back to the tubelane

if not already plugged.

5. As a conservative measure, tubes completely sur rounding arp known

leaking tubes including the diagonally next tube will be plugged

if not already covered by the foregoing criteria. Since no

leaking tubes were discovered, application of this criterion is

not requried.

6. In any given column which is surrounded by columns containing

tubes with significant tube restrictions or prior plugging,

(thereby creating a "plugging valley" in the pattern) engineering

judgement will be used to.fill the bottom of thevalley.'.

Additional preventive plugging will be implemented at the hot leg

wedge locations. This plugging will include all tubes that:

a. restrict the 0.540 inch probe

b. restrict the 0.610 inch probe

c. restrict the 0.650 inch probe at the periphery

Page 26: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

r

/l

I

Page 27: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Page 14l ~

d. surround leakers and tubes that restrict the 0-540 inch probe

including the diagonally next tube

8. Application of the criteria specified in 'I.,above, will be made

on the basis of engineering judgement for cold leg wedge

locations.

9. Additional preventive plugging will be implemented in the

patchplate region- This plugging will include all tubes that:

a. restrict the 0.540 inch probe

b. restrict the 0.610 inch probe

c. surround leakers and tubes that restrict the 0-540 inch probe

including the diagonally next tube

d. lie on either sides of the patchplate boundary (plate

perimeter on one side, the plug welds on the other three) and

restrict the 0.650 inch probe.

The six month operati ng period was also evaluated relative to a postulated

main steam line break acci'dent (HSLB). In doing this, it was conservatively

assumed that each unplugged tube in the two rows beyond the present tubelane

Page 28: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

1

I llI r ~ i

4

7,

III

Page 29: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

'~ 'age 15

~ ~

.plugging boundary would leak at a rate of 0.05 gpm/tube during a postulated

main steam line break. Using the fact that there are 92,tubes in a row, the

total number of unplugged tubes in the tubelane region lying adjacent to the

current plugging boundary, at the end of the next six months is less than:

2 x 92 tubes per row = 184 tubes

The total resulting leakage from these tubes would be:

184 tubes x 0.05 GPM = 9.2'PM

tube

This added to the 0.3 GPM leakage assumed to be present at the start of a

postulated main steam line break (which would increase to approximately 0.7GPM

due to MSLB differential pressures) yield a total leakage less than 10 GPM,

which has been determined in previous submittals to be an acceptable level of

leakage during a postulated MSLB.

B. Re ulatory Guide 1.83

The criteria for plugging tubes in this area are established in the

regulatory guide-

C. Preventive Plu in Accom lished

The preventive plugging programs that were implemented are indicated in

Figures 13,, 14 and 15. Both gauging and Regulatory Guide 1.83 program

plugging are indicated. Table 4 summarizes this plugging.

Page 30: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

l~ V

Page 31: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~< ~

Page 16

TABLE 4 Summary of Tubes P1ugged

Gauqain R.G 183

SG A

SG B

SG C

57

.7

22

0

TOTAL 86

Page 32: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Ib II'

~ r

~ r

Page 33: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~ ~ 4

!f Jl.?'.; ii

) ~ A

') 1 7 4 I

rpc~r" )q C~q~

FIGURE l - T0BE HOOP STP>l!> AT

24 EFPH's BEYOND FULL CLOSURE

Page 34: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

I! 4lII

,a~

C

I,

Page 35: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

(0 V (VJ~S Q,I

M L7 9) t')j<(I II

IJt~l~j

GI~l Ni 7 bJ

II

03CO'S44

/pI ~ t ~ ~ ~ ~

cQ oo f.D»XCCQOQCOCrs' 3 PaC5

I I, wr ~ ssp» IQ«»»CaD

jj C Cz: iaooc.I CZC

I ~

I I«IK j ~cc

I Ml

, at

I ~ I ~

I I ~ ~ I C f--ic" Wq!

I iCC«+,~S ~ I I3S

333 0C~

27

~ I, ~ I If i I

I r»« I al ~

~ I

I ~ I I~ ~ II I I ~ I~ ~

I s I I I ~ ~ ~

I ~ . I ~~ -II j ~ ~

~ .'Srl ' a I ~ I~ ~ I

II - ' ~ I I

. $ l;I s I

c"Q .~ ~II

IlI

II, ~ ~' 29

I I ~ I ~ I

Ij s I

t ~ f I t * t ' II I I . /ICC I-.~ '- I

s ~ .I'~ty''

I ~ I s ~' '

~',''i"j>-too'';

23 2II8c=','7j 6 IS

sj

I I I I ~ I+-I-I ~ ~ I I ~ I ~

I

i I I- ~

i i

~ I ~ ~, I ~ ~ . I

I

!I

I~ aI ~CC~ I, ~

~ ~

I

~ ~ .'

I s ~ l 's

~ Lf«aar I

C

a» arC C2«Ã« ~~ ~««L&~

I I i ~

~ I ~

I ~ ~ ~ II

~ '

I I I ~ I~ Q»«

~ I I ?

RQMS

~ aa

~a rrr r

~t

I ~ I Is I ~ II I I I I

~ r» ' ~ yaw» «rap ~a I aa e aa a» «a a»»

«I

aLX'.'j t a.as 5»»

r»%4V» a

+p p I r«»r~ »a»»&D««»«'I JPL»5"»r

HANG!AY

. CD~V) 07 0) NRR —CDt~U) 6) QNU) F) —QI~Ifi N —CD>U)R CDNU) 0) —CDI~U) NCD (0 C) C) W i~ i~ i~ P (0 Q Q (0 (0 U) U) ID W U) V < V V < (0 8 R B 8 R S R R R - - - - —0) > N N

t OLUHixS6 tjtl u g Nijib

FIGURE 2 A

'TYPICAL GAUGING INSPECTIONBOUNNRY - HOT LEG

DEC™iYIBER 1979 INSPECTION

Test Unshaded Region

~ a«r

Page 36: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

IpJ' ~

k

V

Cp 4I

N'I ~ 4

h

1Wl

I

Page 37: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

c

Fr L-A .

J- e je-.lA Ul tA S < < 0 <

t I

Il aaDCCDCaddor.

g/

COO

1

CD N lO N —0) W IQ R —0) N L) N —S N lD N —S > Lo (') —0) > lJ> (0 0) N R N S t lQ 8CO I 0) 6) 6) W WN N W (0 (0 Q Q S l0 lO lO 0) S V V % '0 < B 6 <0 6 0) OJ(UNNR "- 0) NlD (0

COLUN 'JS

SN tS'QSDttt 0+9D

V

~ ''.-FI I I

TT

43

35» 0

32 333129

~ tttJXDSDVXQDX

SQLSSSQDOOLSSQOCC

OCTADOOC

C»C , cCS» +SarCC I I, t

)crd

~ i I I ~ I~ ~CC

OC

cCC

I ~ I~ ~ I ~ ~ I I

~ ! I ~ I ~ ~ Ii ~

~ ~ I . I II ~

~ ~D»CS I-» 0»

00

Ca

0Qci 0t f~crtt DD

OOCC

I~ I~ ~ 272 w232II9I7

Ici »CCI

~ I ~

I I ~ II ~

I ~ I I ~ f~ I I

I ~000 S Stt

Q Sl S VL L

r ~ DtxItS"

I

~ ~

CD I ~C ,',~ I 8Ctt15tf ~ ~: »I ~

~ I I f~l ~I, . I II I'

~

ChI

I~ I i~ I ~ I I I

~ I ~I g

S C~ f~ I II I .'I I

~ I cc .0 ti

0-0 Ne

I-'~

L~ I .I

I ~

sI~ ~ I ~I ~ I ~ ~

. ~» I I ~»~C» r»

I I ~I I ~I ~~ % f

'I 53» ~

~ » ~ »» a ~I A

~ ~0LM~

+ RCWS

~ ~ ~~ o- » ~

' ', » ~ .AN»'»w ~"t"WDD

HANMAYFIGURE:.;2 8

TYPICAL GAUGING INSPECTIONBOUNDARY.- COLD LEG

DECENBER 1979 INSPECTION

Test BIocked" In Region

NOZZLE ---+

Page 38: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~ r ~ ~ ~

Page 39: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

FIGURE 3

GAUGItlG PROGRN< (TYPICAL) INLET

GAUGE ALL TUBES OUTSIDE BDUNDED AREA, OCTOBER, ISED '

p gg ~ ~ g - g> r U> g - S r IN - 0) r $ (0 - S t U> C)-

~~@~~~~~t ~~<g<g<geegu>eu)u) v<<<<078(0(ORblbl(VRbl-----+tCOLUMNS

CCQ QoneOQCoac

a

QuoDSQQQ

ORSQS

n coonnx ~ Qabaxaa0 ~ aD

00000

000

QO00

QOR

QRQRsRRQanacanoolnuha

og ahaao aaaOan

ooa00000

Rnxa h na«aaaa«ua Q u«ha

Ranhnah anxna nahnnn nannaDharmaDnaana

MANWAY

QanacamnxnunnascnancauaaaaaQQRSAQDQQQDDQQQQQQ«QQRQQQRQ

+

nacR

nod

DDQa au

nnanaaxxxnananhnnahbahsahnnxnnu

annaucauaaax

oauhaxunchanan"nanna

uhucnu<nahooRnabcalanc«DOxnxacara«auubx

«0on

SoOR

00OOR

0000

0000

0nOC

OO00

000

0da

oaRQ

hnnacscanna

aaak

CRQnoQho

aa 00

Q 0abaca onanna xahbaRnaRanRnaaaaa

xaaaa

Qna0C0

aa

acnun «hn

RRRQ ~ khaccnucuxxccza

nnaannnahuunrxan Rnxnha hanahnh RQ

nncaannurnhancxannaaanx"naacaannnhuaahuannuaaauuaaaQQSuxauaanxakhn

aaaxxahaxxnRhaasahxhan

+

. 4544'34248Se 39

373634323e 3'9

Z6 ~2422 2328 2t

19f7)5

~2

9I I

8642 3

ROWS

Page 40: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

I1 Cli ~ '

,I

I

Page 41: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

FIGURE 4

GAUGING PROGRAM (TYPICAL) OUTLET

GAUGE ALL TUBES 4IITHIN BOUNDED AREAOCTOBER, 1980

SERIES

-Q&lo(0-0)NU)(0 0)&$ 07-$ >lo(0-0)NMYJ .0)>lO(0 0)NU)C) 0)&lO(0QM 6) QRRN>W>WQ(OSQSSLOSSM <'f < < <RNRRF) RRRNN= — SNS(9-

CO LUMNSOCHER

Cuoc»cucQuu

ucauu05555

000ca 5»auc u

OCHER00000

050

505

55555555RurckuOOIukkuogkrauC . 555cuuca 5

krrare555555kaakuaa ccuzu

r«kbxxc5555xakccr

MANWAY

5555555555555R5555kaakuukkukruckAurauaaarkskkaukrksaaskacacakcur

oouuouuuueuaa

u 55

555uccsrarazaaauucuauulunsocuucrcalccaaccbcrtb kccuuckaau

00 SC

Ok00

0000 5

000

0

OC

0000

000

005

OR

555cu

555

uua5a Ruaiu 5Aalauuccu

kl »Jrabbkrabacauuaarssu

ck tuus ~e ~ R

raaa5555

cuaau ccaaha

cuRac550

55 00

555 5 0;Sr 5 55'a ukrrr

5 555 5AR 55555 AuKaurau 5555555 RRkakkaaueaaaaaaakacuAkakuarukkauakkkbku

+haxauukkascscacxccruacuaukkaraacaarkkaxakaauu55sasuukkusukuuauaakaaaurkaakuaauak

.4S43

48 Sg3736

34 333138 2g282524

22 2328 19

1716 1S13

18 11

8642 3

1

ROWS

Page 42: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

'pl I ~

0

L

Page 43: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

'F IGURE 5

Regulatory Guide 1.83 Inspection

Program (Typical) - Inlet Leg

7<ccc c<cccoc«<[ 7<< c<(cc< 7«@ I« I '77<Bc< (cc cc ~ '~cc <7««< c«

7«.7'«<<cc

or<co<� '~ < c" c~cc~"<~"< +~ceo< +"~ 4c" c~ I4'I ~c C cl~ ~<a W.--«c<7cc«SERXES 44(~~ Lw~cm gIIec7s ~$ cpy~ +bc s by e¹cTb~v E~y- (~~P q.~ Iy)

Tol 77<«f<o <'< << 7! c<<( l C<«<<<«T 7z< ~ 7<'<. II<<I«<l« I ~ c<«<'«o 1'<<««~(<<«<wc<7«)o << col<A/ 4 CC<<<, C P gVjlft<4 THE S T<IISc IS Ibfotrca'cub A« BelcSclc R~~c<cTCD Tu CSo g c bc7<C +cc'f abc ccS by doc~ 14'<Ijc<c~ e< QbcIS ~~ Ic>< S<c~»+ul~abc<4 pccbc. Aocy ~ c'csI ~M ~T h~c-l~ f+gD(~co <~) as ~as ~Tccb(. ba~ z4sc Tcc~ ccu ~ ccrc 60<<«cg Pr ccia~ ~~ ~c As&<c4 IvsqTy ~adjcc<'.c t Nt+s cL<.c p Q g/LpogiA; rw a +4~w+4c JA'z Ej™gael br<<< CnSTWCyC<C +gi~l) CIC PC~ aC IT'S PA FCT,eSSW rO A'rG~C,—0)>lAN $ &lAO)-0)>lAN $ &lA $ >lAYJ-$>lAN Qr lAN-$>lAN (D&lAN

O)MC)mmr t r I t (0$ (0(OQlAlAlAlAlA~~~~~RNNO)NRNNNN-----COLUMNS

lA

Qraas05555

055

OQ00

OOS R0

QQQQOQOQOOaQRQaaa 5

NRQQQL INQQOOQQQNRRIAQQNQ 00

50Os a

SSSSQS5QQQK5 QNNR ac

OR00

OOQ

00

QOOCQaa c-<-c 5QSQQQQo< a

OO00

000 0000

0000

OO0

00005

OO0

505I'QQRaaaa

QNNNQQOOI SCRQcgaasa0 QNR

Oca00000

55aa

aaaa555255

as'RQQQQC55555 ASQ+ Q

X; X ~

~5

I QQ,RcQ

NRNCQRasaa

000Ca

CR5QsaRQ

05RBOSQC

QaQNaalQR

Qa F00QRCc S 0NCRQRQ R

Q 0Qas

000

sasaxl ra

RasaQSQRaaKQSRCSQQaaa

alasaSQ

5552QNN ~ 5 Q

DRRQRRS

Na, 5555SXCNNQL¹1

CQRQ<5SX

I ADIIN 'Nabs

QRDNNCc 5 ANSQ

DRCQL QQSDSQ ~

Raaasaasa+

Qf a DNR 5caazaI'QQCSXQ QNQQ Scar'Ncs Rssaassaaaaasassaaaaaaasasaaaaaasaabbrsassabb¹ARQRQQQQQQQQRLNRQRQQCRQRRQRQ

ROW I TU8E-ENDS REesOVKD DURXNG CLAD RKPAXR

4S4442 4f38 3S36 3S323e 3'S

26 2S22 23

2)18 1S—17

is14

S86

2. 3

ROWSg. Azevloccsp Fccl~cb T¹c<s+--- NANWAY NOZZLE ---+

Page 44: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

ci

f

I

'!

p I

Page 45: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

o-

t~ I~ tt Ot i~ I~ l ~ ~ ~ ~

0 I~ ) > 0 lt ~ ~ 0 tt t ~ 0 I~ ~ ~ 0 I~ ~ > 0 It t > 0 lt t > 0 it ) ~ 0 lt ~ ~

t 0 it lt I't It ~ ~ ~ t ~ ~ 'I 4 '

...... .. Rlaa~RNS tkkR S RE%ERR% RRENNSNEREERS

1 RkkRRS ...,. ... N~EEEERRNEXREERNXEAEXRAERNRNR, . SSEEXHERRE ... , ,, ~ ~ RA%kg%ESSE%ERAS%ERA%EAR%ERE

~ . SESS , PEER%ERR%EN,. .. , ,, ~ ~ XE5XXAARNAAXEXENEXRENEEEAXENVNRSE PiSESEXEXXS,......, ~ VSANXSERRRNEENESAASNEN

RAENNAEASAS NENNNAAANAE . 1,, NEAAANNANA'ENNEA%ANN%AA%AREAR%RE%X RARRCV RNNA SE . , RENNES ~ ~ ESSE%EAR%ARSE%RARE

XRXEEEEREERNEX RASXSVEREV ENSE RE%ERASES ', EXREREEREARNEEEERRAEXEERREREARRBRX EAA %REER%ENSE%RE%AX%EASE%REER EhNXEEEEARNERENRAARE%EARN%RAN%RES ESRREEXAXRSAgEEEEEEESARNRRNEEE ESSE%EASE%A%ERE

EARS%%%%EAR%V%X '., RVXRXESkRRSXAk XSEEAEEAERRNANEEEA %PREEN%A%SEANVVRRSRSRR'ASSES gL5EXRRRNPEEEENERRREERENRREEN RES%A%EVER%A

RXARXEEREREANSRRXARNE MMRVARE RE%ARMS%SEERS%ERASE%% EARS%AX%%NESEERR%EX%%%) RXRESN Nkkkkkk XEXIRRERREREEXASMIAEAEEREEEESEARS SENEX%EN%%ERE. a%EN%AX% EXAXANAANENASNANEXNRAENENAANENNEA%SESS%RENE%EN . NaaaaNNAAE

NNAANNAEERARNAXAARXNPgNANNEXERR%NASA%RA%SEE%ASSNNSENANNNAANA ~ NARNQEENNEEEXAARSERRRERXRREXA RENNNNNEREgkRESRRNSENRSEEAEERREPAEENEVRR . ARNARAEXESRRNXERNMER111RREERR%SEE%ESSEX% RRkkkESSRESEENAVRRSRAASAN%ERNE RE%ASAR

~'SNERNERNRERERRRRNEANEESNNXEERRNHXNERRNAXAEllgkkg~ENERRNNREERNEEEEER ~ SAEAER ~

ENXRERREXNXEEREXERRAWKWRAEXXERR%RA%RENE %SEE Ek NRAXENEEAEREEEESRAE ' REAREREESRRAXSEXESIXRRERAEPOMMNEXR%ERE%EX%SASS E ASSESS%ERR%RESS%RE%ERA%RARE RL'A%RE

XRAEESERRRREAAXXRREENES4%ERA%RA%EN%SENSE NVRVRRARNXAERRSRRNVRERXXEHSS SEES%XRRERNRRXEXXRNEVMREESRgEXXEXAE .. NAR .. ASAR%A%SEA NAEEEAENNERRNENREA ENNEA

~ %RE%ERE%REX%NEER%%%%1%%%% ANR ..., %%1%%1% ENS'ERE%%1%%1%NEER %1%1

~SARSEN%EX%SAR%EX%ENSE%RE%XX, A .;,, REV, SE, EN%ERE%RA%%EVANS ~ %%%~

E%%ERA%%RAN%%AX%RE%ERE%EARRXSXRS RE%%%X . 1%%%, EAR%RE%RES%RA%ASAR KLlSRXRIlERXRXEAXXXXEESNEXVmtENERXANRXENRRAXARRRE'R .. R ', RRRESEXRAERARENAEENEA EAAEXNIIXNRSRXXERXRRESMXRRMEEE5%%XRRR%%i4%%%%%XRERARR ., EEXRRQA%5XRENRXXRNSRER . RNARXIlRARSXEERRXRNERNEXNSP%P%%+HRXNENEXRSXAARERNER RRXR RRREEAEEAHARXRRRAREEAER .: SL

. RE%II%NEAR%AXE%EX%%%%%%%95% 5%% S %ERE%EVEN%RE%%ENSE REX%ARE%ERR%ERE%AS%RARIIHRRXENREXEXAERRXRXRWX ...%XXVX%%ERAS~EXEREEAXRAERXREXSRRRSEEEXEEERASER

IlRXEAXNXRXXXR k RXQ5..... EX%!NEXEEAEEAEAEAggEXRXRENEESREAEX%ASSESS% . AA

~ .. RNARPSNXRNASXA SERA% . fi %%MISS%RASA%%EN% EASE%RAP%SEA%ERAS%RENE .. R'AAEASXNRNAREEN REVE% . %55%ENXENRSXRENEESNAESNEE)REERRNAgNAEEEVEENX .. a

~ ..'VRXENEXNLEXEXREXXQX, Q5i+EXEXXEXLAEENEXESAXR EXE %EXES ARAXXANQRAASAXNANSXXRNEA%%%%%%%% StKrMRONXNNSANAA NEAR%%ANN%AN%, NEXANNEAENNNA ~ l

~A, IISXNSEERXERESg Ekkkkkkk HEX RE%%PCS AX%RE ERA%%@%5, SEHERSSEXV! .';kSE, CESS%RE%SR REX%,, %REX... IINANEXNEE ., %)~..... AREXRRRSER .. AR

: EXES, , ERE%a%, EE ;. ERR%REX%SR . .. a%RES nk .' ARES E ',' EQ, RARQERX '.. Eu

ESX ..', ESSE , RS . XESSRER ~ XRK XEE .. . , AER, EA . A%ERNE . .., EE~ ...X...,S,,...,,,,Rk...,...,...,.E... ~

r .. ~

0 ~ ~

0 ~

Page 46: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

I

if 0

I

aD

Page 47: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Turkey Point Unit 3

Steam Gererator A - InletGauging Results - OctoCer, 1980

Restrictions

O = .650".610"

X = .540"

No. ofTubes

695

12

SERIES 44I

FPL-A0) NU) 0) —0) NU)(0 0) &SF> $ %$ (0™~0)&LOS —0) >lA(0 QNS(0 —0)NU) 8

0> Q I 6) R IN N N N N (0 S Q S S lA LO lO g S 'l W V 0 'f (9 (0 (0 (0 (0 N Q (V N 8 ~ ~ ~ 0) N U) 8 ~COLUMNS

QAOuuu

oou 5QO0ou0

OACusa

DuuuaorQ QQ ~

QuR5ji

OCQQsu ~ 5DrxuusDo. a

00 ~ 900 Q000

00D

00

ji09

QSQDuuusQQARDD

COIQRRROQ QQRRo xuuouu

OCQ0000

Qrr5 5 5

DXQSo . Qaaassa DRD25 QXQSDDuuuuusaaaa uauuuxxauuuuuua X 2Qaauauaaaaauaauuuauuuaaauu2

+

5 jl55Duaaa5 5 a llQ

5 sSuuR

uxuQRRQu

a

5 5 R slJl 5 554I a25552DSADusluuuuuuuuuAXRXQDRSARQ

A DR~ii ilu 5 iuuaxu

i1 buu

uaubuuuaaauuuus5Duxbuutu5500uuuxxaluuuuuoo

QoCD

0CQ

00005

0000

00000

0u00

oo00

000Oa

OS

QXax

CDSSOQDO

aa oouuaaa40Qsxas Q usaua Q 0

auabuxaaaa

Rux jixaDuu 055u 0SXXX 0xusss aa

XXQQQDQ SaRuraauaxaaaajlassaasass+

uauuRxua

Dubuuuuuuuauuuuuuuu Quxua auuuuu xauu5!Xuuurullujluxxajluuxa AuaucuuuaRuauauraaRDuasauuuaauaxaauaaau

4S43

393736

32 333)38

2826 2S2422 23

2i<s18

16f4i2'~ s86

2 31

ROWS+-'-- HANWAY NOZZLE ---+

Page 48: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Ib 4I~ lt II

ting

L'e„t

4

!

I

D

'I

IJ

C

e

~ gW

Page 49: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Turkey. Point Unit 3

Steam Generator A - Gut'letGauging Results - October, 1980

'b v h L. G

'""~; "Restrict":oiis,

e= .650"<= .610"

X '== .540"

No. ofTubes

01

0

FPL-A', 0)%$ (0-0)&S(0 0)>'SR 0)>SR 0)>SR-.%&SR-'0)&SR 0)&SRexecerrrrr SSQSSSSSSSVVve<RRRRF)(URRNC4-----0)l SR-

COLUNNS

SI ~

$ <NSRSeRRRRNNB

ooraCQC

Qaaaododdodaaxaaaa'aaaradra

avardalxaao»XXDNBRlaaaRDODQQDDDaxaaa

0cad

QC0

00OCIaaxaa

CQIKQ

QOC aRa ~ QRNBDNQI

OO'000

CC

Nd

0Q

NCINQ IaRNNRRaaraaOclaxaa

C +5 IIIc QaONQ

OCQ00000

XIIIIaxaaxxxaaadaRNDRDBNBNaxaxxxaIQRIPRIIQIDaaxaa

+

axaPaa

RR

I 'rpaIaIXQQQLJraara IXaaaaxax

xaarQC PXRNNRNKraaxaxxarxxaaadarzxaaraxxr.xaaxararIaraaxxxaaaaapaaaaaraaaaxxarNXXNpraraNavar

NrxxrdXRNNQ

Id ad5555

a ax a ~ INa

DB 555aa 5xaax axddI xxxaaaxaaax BIN RN arxaaxIIII5 5 5 5 I c rIII a a a RB I Q Na

QRBQDQIPNNNQQRQRRRDNIR5

COOC

00OO 0»

0 ttaoo

000

CO0CR

CRQBINRR

CQRNCaao

Qa 00III~ IQDNQRRRQQ I CQQR aaaDxaIQR 0axxa cxaaxa II

INNQRRR laNxpaaxaaxxxaRRRIQNRRRDIQ

+

IQraaaarardxxaax aaIIQNQRQQ

.4S43

'38 S3?36 3~34

32 333)38

28

z~ "222a 19

i7l6-- i2. '3

$ 886

2 3

ROWS+--- HANWAY NOZZLE ---+

Page 50: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Ik ~IpJ ~ ~

C

1 1

'II

II

Page 51: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Turkey Point Unit 3Steam Generator 8 - InletGauging Results - October, 1980

I.iGuRERes trict ion s

e = .650"k,~ .610"X = .540"

No.of'ubes

242

0

SERZES

EP —B

SNlDN 0)NRN 0)&lAF) SNSY) —$ >N(0 0)NU)N 0)NMN SNNN SNU>YJ.0) 0000MINNNNN(0Q Q(067NNNN S < < < v <07NN(0(0NAINNAl~~

COLUMNMSVNSR{OVNSONNNNF)blRANN—

afaQaaRrl

CQ00

QOSSRS

SQSQQcaaaasCSQRQSRR

OCa QCOC

CQCCS00

00SQOIOsuauc QsCOOOOORSI uaar

RQRIQIQRaff IQQIasar 00000

CQQCQQ

SQILSQOO

OQQSO

00000

00OC

000

000

QOaaaaQ5

DCR0

CSCSCRIQR

001 Qr IOf IQI0 QRRSRfaf plclara g I Q

CRSRQ~ IRRCR p QjffruCQ a<afarOQ Q Irsura Iaal ~ RIL5aafu IQaalrrlf RlfJrfauaallaaaaluua

+

rlsIaf IurfraIfLrrarrrcrsl

ra% I Suu Jf QAQJCQXAIADIXSQQQ1iaaf ra 5llfQQXX

0000

QOQ ~ ISall

RaaSC

0OC

0Qaa, QCRf IQ1CSar R OCI ~ IR e 0QlfIlacQRIIÃafISSIIRRI fIfr

LXI RfraIRAQ IIAI Q

CIuaxaQXQJ

IaIaRAIIxfr

I Iaaf I Iaf IRAQSf

ara�bic

Rtaffa ~ C5 far af I,e I KQI Q

AfI I -'4=Quar Irrfaal f I rrrrr rr {gt Qxxxsrraaafxaaal-zsrfaaarau ILAILDI arfaxr laffaaaaa afaua LLQQRIAI OALLIRQILLraflf5QIIARIJISRIRIQIRIRRRR

+Icr Qara Jxf af IIrRrrr IQurrxrr Xs IJururf XSAQQQI JfIllrafIRR JI Jraaarllaaalr AARXJrf Xrara JQIIIRAQSA

4S03

4838 3936 37

3532 33

313828

2426

22 21

18 1

1716

12 13

1886

2 3.

ROQSNANWAY NOZZLE ---+

Page 52: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~l, ~ II y ~'l

I

I g ~ ~

P

I

J

Page 53: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

F IGURE l0

Tur'key Point Unit 3Steam Generator 8 - OutletGauging Results - October, 1980

Restrictions

g ss"0

~ Q(O

X =

Ho. ofTubes

'I

01

0

S.ERZ.ES

- FPL-B—SASH SASH) 0)NSN $ >SN $ >U)N —0>>S0) —(9>SO) —0>NSN —SNSN-Q 00 C) Q R N N N N N (0 (0 6 (0 (0 S S S S S V 'f < < < 0) P) N 0) P) R 0 R Cd N-

COLUNNS

00

CQOCRC

00

QSXXI55«5 5 5

CRX 5

IXC~ 5 lt 5Qgaa

OCQROOC

tt 5 05 0000 000000XXSCAIXQ

IIXXXXIQI ~ jaXQXO

OCOOC

CQQsaaa

05500

OC00

5OC

0000

5CX0

CQCRCXXXX

Octaaa0OtoaRaaa

Xt

aaaatagoa55555XXXXQX555554$ 55555

Oagt ICtl gas

QXQ ~ 5SltgoaQalta 4

+

tt 555xxQQ

555xaRXXSXgao

QXAXOxax

IXXAXQ5 XQQAxaa554555

itt 55555QXSXX

X XXQ5xaoxxg PxaaxxgxI xazxxxaoxaaxxn Qxxaxxottoggxoattoaaaax xoxatxa xaxaxa5555 ~ agxa

I ttaa

SXOaaaa

ac0OC

0SC50

SRIRlC5555100SaxaiCQOSOSX™

saaaagaaIRIQRIIIRxxaaaaxxaasasasxxa 0aaaaxaa cI ~ XIRRR 0

aaaan Qxxaaaaa cI 4 5 5 5 5 X ~ 4 5 I 4 I 4 II I 55 5 lta 5 IX g RR I5 AS 5 5 5 5,I 5 I I tt 4 4 I 5 4 4 4 5 4 5 5 I tt 5 I 5 I 5 4 4 4 o s I 4 I 4 4 4 4 5 k 5 5 5 4 4 tt 4 5 4 i 4 5 5 4 I4 4 5 5 o 4 st 4 5 5 5

g I 4 5 5 4 5 g 5 5 5 4 lt 5 Q tt 5 5 5 5 I5 4 I 5 5 Q 5 4 5 5 4 5 I tt 4 5 tt 5 tt 5 4 I 5 5 ti 4 4 I 5 5 5 5 5 5 tt 5 5 5 5 5 5 5

454341393736

32 "31+Q

2826 272 25

--22- 232e 2'S

17161412

111886

2 31

ROWS

MANWAY NOZZLE

Page 54: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Ik.1

I .'ll

n',

Page 55: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

Turkey Point Unit B

Steam Generator C - InletGa~ing Results - October, 1980

F I G li R E.„'=ll..V

Restrictions

e = ,650"a.= ,610"X = .548"

Ho. ofTubes

3852 SERIES 44

EPL-t-0)NSN-0)NRN G)&lOR G)&lDN-0)ALON $ &lON $ >lA(0 Q&l0(0 SNSN

0)(0C) C)%l r t t t SQQQQ) lALO10$ 1OV V Crt WRNNNÃ(UCIRAA-----COLUNNS

QaabOOSQ000 R000

OOOOQO

<(US%LOUR C

Ia Coo 00 0000 saaaaa

a»a ~ QRARaaa ~RRRO

a ~ QssaoQb SSS

aOSS

00

RCCO

QRA

oo a

.000

QQQR

QSQRXR1Q,aaaz 5',

QR5255,a s Raai

~Raaaab,Qaaaa ~

Qaaba ~iag+ —aa0 ~Q11oaaaasbbQAQQA551

RSaaa

R Qa

OXQJDASuaaaa

«555 ~~1»XaaaaaaRaaa

IauaazORQJAQ+Qaa»11 J)a f~J «Qua'DJ551

g»aaaa»

e5 5 4 a 5 'a

%">3SGQ'IDana ab:II Ergo'vKO

aRSRQ

RR

Qaaa

.0aa a

a QaaaQa aa. IQDA4

R iZ 5 j-I a 4 r. a

g «QB

Qaaaab015513C:IOVR i>G

AXQa 4» Q1 .«1 1«XASSBaa «Caua«CI AO R=P4 R

la a Jaaa Aaaaaaa JQ 51 a DRQ151baas:Q aROB I YUGO-K.'4OS

Qoa

0000

0000

0000

oa

RQQRRaRR

QaboSRSO

sabasbQbaaa ~ QOasatsasobga RSQ

Rasa ROO«Qaa»55 R 0

Rpaabaaa 0Qa Q ~ aaaaba 0

Na R 41 taab SQR" a.:xs AQ 5155 RSNJsaa1saabassaabsass

WS

4838363432 33

3138 292826

22 232I28 1S18

16

121118

86

2 3

ROWS+--- NANWAY NOZZLE ---+~ I

Page 56: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

v> ' ~ ',I

IItC

Page 57: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

F I GURE 12

Turkey Point Unit 3Stea"„. Generator C - OutletGauging Results - October, 1980

Restrictions

o = .650"h = .610"X = ,540"

I'eo. ofTubes

020

SERIES

FPL-C

~ s

~!~SN

e!e+ (D

el~(QI(D

!mls<'(0 N

I

(0 (D5 I<

N(0

NS(O(DANNA!Si(0

—8 N U> N —S N U) 0) - 0) > U) (ri 6 N lD N —S N U) (0 - 8 N I (rj —CO N S F) - 0) N U) (rj - S N S N—0) 0 I (0 tO N N W N N (D (D (D (D (D LO lO Io R LO < < '0 < 4 (0 (O N N P) R N 8 8 {U

COLUMNS

5S

RXSSan

XQSa e'aSQZS$ 4

S554Rxax00CxxaSSSR

CRRC

100 SAR,OCO

CCO0OC

0

RXRC a COO OCOII Iiaaasaw

000SSISSSRxxa ~axsCRI-Iaara000

xaa

SXS 0COO

Oax

anaazsx00san00

co a000

OO

R

5

RsxaSxa555,555,555,LS5,

aaRJ

XXXxaaxaasx

XSXa'T+

CXSr@5 I'%)15-4-Ii ..

r55,5$ns);xaa

IlaaSS)S~SL 5X

5~$ 45$ 1) +*~;-=a ~i cAX3SC

SRSXAQXSSRXSSSSIJS$ $ Iarsinaraanaaaa)IISZXurauaexr 'I:XISRRC'A 'I TUBE-EIePS REMOVED DI)R'I3 Ci *D

SX ri A)anXSW IQ ia I55)IQCZBRREI AXR

00 IIXCSa ~ cc

0CCOC

OC00

00000

ORCa

asaxaaa

RRSORRSCrasasa

XXSR'5 ~ RQsnx snaosea Raa

551 JC)5515

arsI 45545Rex-aran55 S$ ~ AX eSX

R 000

xxxna.sl nxaaas RXXXRXSQAA$5ssassaxaxs

45~2 ~3

38 393736 3534 3332 338

28.2624.22 23—21

191716

131118

86

2 3

ROWS+--- HANWAY

Page 58: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~I~..I '

~ ~ ~ -"'ll

~ *I ~

Page 59: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

F IGURE 13w4

AQ

TURKEY POINT Unit I::3

STEN GENEPATOR AOctober, 1980

RECOMlfENDED

PlUGGING PER:

0= Gauging ResultsX= Reg. Guide 1.83Q= Previous Plugging

NO. OF

TUBES

5713

SE:R1ES 44

EPL-AS > Lo (0 0) N M R 8 > I 0) —0) N R 8 8 > R 0) —0) > S R 8 > I (0 —0) > 'I N

CO Q Q IN N 0 N N (0 63 S S s LO lQ S U) U) v '0 < < < (0 8 <0 <0 8 N N 8 OJ 8 — 8 > 8 <0

COLUMNS

OQCaaa

OC0

55Ca

QXQI

akkCaar

QOCRa~ 5IXX'5 5550 ~ I

CQR

i. S

OG000

OC0

~ II

50CC

ICIRXCRkkcaRQIQXC

Odt IXXIogaxccCNXXXOCQ0000

akxRRQQ

XXXQQXXQIQXIC

~ -IISQXQIasarac LIC955

r XXQIicaaQX-" RQXQRQQ Xcccccr ~ II Qa IQa IIIIIIIIIRaacxaxcsx 95RIRRIIRRRQIII

+

+--- HANMAY

XXXXCXxcIIC

Xa

I AskQscasa

1 XX'XQX 55

«XXQQQXQXBXCXXRQXIQXQ

005 Cc RC

errIQQCXIIIX

acrQQQracQQXXQQ)XQQOCXIQCIQIRQQRQOakxakkaxaaa 0

0 0OaQQI

aaa00

00000

0000

XXQXSXXXIXR

IIkaaaces

QQSXXLSXX

XISQCkmIIRcars r95922 QII555 I'2 I5 Qk QCc xxIRQQQIxxaaax

RCiQIXR5525Izcx 5

.5 Xk 5QQAAIIIQ

QXX5QQscxcc»skkccaaxIkaakcaa

CI0&0 t%

0OC

0cc05Iaxaa

Oa550IQC

00$ 59RIXRQQQ I 0aaa aaaAaa CQRR 0RRXX 0

Xacca IaQaccx xa

RXXQRIQXQXXRcacaaaaaaaaa

+

«4s434 1

393736 3S34

32 3138 2926.24 2S22 23

21fe 1716

12.18 11

8642 3

ROWS

Page 60: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

!i

IIp.~ 4's

(~~

'

t ~

E

I

Page 61: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

F I GURE 14

TURKEY POINT UNIT I'..'3

STEm GENEV IOR 8October, l980

RECOINENOEDPLIJGGING PER:

O =Gauging ResulttsX=geg. Cuide 1.83@QPrevious Plugging

NO. OFTllBES

7

0 SERIES

FPL-8

COLUMNSVNSR S 0 (0

U)$ <rtI

I

sm(0S S LO

lI

OOOCRQQAQXIQ

R Q CQ OOCOCODRRQOl aa

QRS ~Q ~ RR g3

38 3937

t:IXXRQ4D ItXt QQCCXXIII

SCCa al„

SC

OOCIc

ca»Crr

,SACRIDAOc

RO QCCXQ

ac 353432 33

3i3~ 29

XIIItaR I I I tt~ IIXQ OO

C

,0»XIX

~ RXXR~ IXR»I , C»

,ROC

: XXXI.RaaaQct- aa

0»0

QCRSRR

IQ»C

«Q»RCR I RRI It

RaIR

OO;ICtQXISIS RPara

XXCIXXCQXICQI XIXII1 I XllXIXXCSCRXD

CSXRXCSSXX

RSS ~ IXSSIDSIR DX

+

~ IDDDxxarDD I I I

'

'a

Ia I I~I:'I

,RIQC

rD ~rsXD»XDQsrrDD«Qcr»QISQIjt X Q it

,','Rtr ~cr

R 'Xra" I—IQDrc r Drrr Rri DDXl'l»CCC" ~ DISA

Rf-QQ

RDQI ~

DrtiiCCV'rrxrctc

r r D I 5 II R DR I It I Q I I tt

QCQR~ ttracl ~ Ir 22«XDXDDsarxac

C I IJ R IrXDIQAQ

DQCAQC Iiah»r DD»iV ~ X a I ti » r I 4 5 tt rI I Q I Ii 5 Q tt 4 4 II R I

~-xrlrrrr x»ccD I D It I R X

III s II I I I Iirt D IIXQAJID IDCIQIRXA

28 272624

22 2328 )918

$ 6

1i(87S3

1

ROWS

OCOC

0I»Q ~ QSQQR

RlaRC

CCCC,Q»

Ra,QCIRIO'RARQtOC

RIXS AC«SXDCSQRSX Q5CA»,I DRQ I a 8

, CXXDDAXSAX,'xcxrr RIR ~ c 6CIQtrsa c

Q

IC,, XX

XQ, IXtCrt'SQI2Q

CCQrs» ~ I0 D 5 Q Q Q II 5 II A I »I S I II IIII H Q D I I X a I X IIII a

+

MANWAY NOZZLE

Page 62: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

0 0( «1"I

V

~'

dl

P

J

Page 63: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

F IGURE 15

rC~ I

~ «

TURKEY POINT UNIT N3STEAM GENERATOR B

October, 1980

RECOMMENDED

PLUGGING PER:

0 = Gauging ResultsX= Reg. Guide 1.83Ct= Previous Plugging

NO. OF

TUBES

221

SERIES 44

FPL-CG>NU)P) 0)&lA(0 0)NU)(0 0)NIDN 0)ALON Q>SR $ >$ (0 SASH SASH

SMI00m> >>w>(0QS Q) SU) U) NMS'0 < v'0 <0) NNp) F>RN8(UN--COLUNNS

ass IRraa55«

Ra aROCCa aRas

C.OQCQR

5Rk

L kkaakRSRR«aakiaaaR ~ aaRkkk

~ I

ka|XRR

aaI

«75k 5RCR5%Raska

R R~l

DD I—,\ ~«««C

a'kka

RaaRaak

OCQA

Ca

RRSRDDRocaaa

~ l

~ III I ~ I

4S42~e ~f

3936

- 3~ 3~32

~ ~p 329

26 27

OO QOO CsaDa«DXR

sascaC

R

OOO

aaa ~ RRRRkaa'asC~ R RRRDQRR Ram

5

OCRROO r.pQO

C4C Oakaa

OOO=R

DCR

QCQDQ

0OO

OQOC 25

23211917

OCCCR 22

ck,-„—. 2818

RRRkksQ ' gDRRQaskkak

Rasak ~ eQ

1S13

97

~ I '

R Rr«'R

~saa

gaf RaRXD I 555res raaTp

gL,~ «««

~ ka» ROQkk|S"55 a ~ Cl I ~ ~laaa 6

2 31 ~

ROWS

x kaa»R55 oR aches«$ 5 C

xs ~ kk=aa R"k sacak

L-,g«555Tj'RJ545A kkkkLRRRRRRRR

(iEPAZP.BC J'4 E 743 Eeia?8 Fc'10'/CO O'Jtl.iIiG C AD

~lail'P I:". s i-,O

HANWAY NOZZLE

Page 64: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

0 gl'

~ ~ (II~ II

'R

rl

"I

Page 65: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

s1t! I~ el

i) ilI:I:..C!l(llI ~ e

~ % '-'51

3,,}3,! e i

I

~ "Ijl~,

."i; 'rqj

I.

~ .'':.k,

tl~ l,}

3~

.13 ~

» l!..: .I!

'I;0

~ ~

.,ri '531: ~

> ~ ~ I> ~ I~ ~ ~ ~ >~ ~ I~ ~ ~

~ » ~

1("., ~ I I

e

C~f;

'.*3

: II.11,1

lI ~

If

I

I1

~

iii}!it?

IcI

:;,I'.:It

I''II

)i}-t

~ 1 .j;I

).c:e

( ~ ~ ~

jill

,:il

Ii'I

~ e

I>Pi}

1 ~'I ~ ~

~ ~

\

h

3)e~ ~

~ ~ ~

~ ~ I

~ oe

egl) )

~ ~

'I~ r

»i ~

3

::l «:t;

~ ~~ n'l~ ' ~

cs...,

~ > ~

~ ~ ~

'I ~

Io".. 3( '

}i~

~ ~ ~

iiI!

i:".II( ~

»

~5Hf(

~ ~ II

III!te

rl ~5

~ I

". I I.!!I

I:!';

'-'I

:jilis}i

I";:i!

lli~ IIill

j'I

ljit(

~f}l(5'"(ll}i (c(i

iljtIlil

i(fi

,( ri11! i(;31.1 L!}list

;; ~ (jlllc

ill}'l'I

' ~

s 3';

Ice

~ I>3 3

~ ~~ ~

'.3::.Qs 'if! .I.'3'f5

~ ~

~ Ilit)~ I~ ~ ~

~ ~ ~ ~ ~

~

I!~ »

1'::

~

I~

1

!.IiI

~ ~

~ 1

~ \1s jog ::.i 3(~ ~ \ ~

1}n.l5: :I

!'i'. !ii!!ii!3 ljii

t~ ~ I',!:

'

;t!1

ie1 ~ )

'"'(':i

I:ii"1 !!!

~ I ~ ~

33113~

1--~ I ~

I

e'I)':3

~ I

h O.C~ ~

slit

JijI

I

3'l

113

1~ % ~

1l'

1 I)3>le

~ I ~>II~ ~ I

~ ~ ~ e

li

i tel

i

: ~ 13

~ ~ ~

v:~'ow%f L)ws R 2470 (OC~ ee ~ ~

>,C4

) "I

~ 1I ~ rllee

I I(3I

'

1~

I ~

ljils r'll'

s. 1

i" ll~ ~ ll

l. i(

Ij~)i

'3(%

II~

1Pf1

':l':(j

1I

II

f

II~ 1

I~ ~I

I

I

5

~ Is

"TTT

III}ijiI

jfj}I;.1

) ~i)iIsr1}1

)f~

i!~

}

lI,

Iiis fi('i lt)I ~ I>ll.,ill

.'Iifi!I!!Ic.~ ~ I>iegere 'i

:filI~It

r.il

I!fe

lj

f3

i1

)

II

i'!3

1(l,

ll,:il

IIilI'I

jl

.I>«

)i)i ,.(efs ~ I

I1 ~l

~ sl

gP i ~1I'I ff':I'l3

,:1~ ii!fr. 3

1H ~!tii;".i!

t~ I3) te 153 )n) >3 %feil

le 5veri~ I ~

5 H;i itf1 R): .'",.!31,' I

~ft g tl)i '

~ ~ lit jI

) )jji)3 ICI)>e 3 ~ > ~ I:~ 'se

, 31I1

I ~

~415«3 32 e ~

V ~ ~

ici li" ilil tits

~ ti3 ~

".'!'I!!!; ~ ~C)3~ I)3 I ~ ~

it)i 3I> ~

1~ ~ ~I ~

~ ~ ~ I ~

f. lr;il"..

)tls "!.3!e ~

it ~ I-1 ~(

I1

~ ( 15; iisnI

3

~1

~ ~ I I~ 3

~ ~ V

('I\e ie'IJ

~ ~

1 li~

31 ~

ni'3:

Pf

is

':.f 6:l ~iit

i!Ii i:!! !.5\

3~

~ I.s~ ~ ~ ~ ~I ~

~ ~

et ~

el~ ~ ~ ~ ~

~ ~5)

is / 'ali!'OO ~ ~ee ')" "3 "4~ ~ ~ ~

~ fIIi)1st 153

::!tI'113~ ~ ~

:3!i'!3} I'I "I'Ie ~

lfee

5 pr

IJ ~

ill

ill

I'I

~ ~3(.l

ii)!IIl~

e ~ Is

i(l.' 'II ~ o«

Cf

.1%'~

e

)i!1~ e

if%i

~ ~

I ~

I(~

t rhq

e

~ ~

11 hail!Ic cc isis io ihc Cess) fcr ccrc

~1

,).I(

jj~!3-

ill}

ill'

I "!,)is 3

cjt

~(

I

~

II

5! IlI ~I ~ ~

~ I ~

:if3

)e

4 IIjl!I(fjjjit'

I!551:~ ~ 'I

1 ~ IlI~ i(ii

~ Il~

II

illjilij!1(

)ij

.Iil

I

'i!f

I

j

~ I ~ .I I ~

I~

il Ii) ~

If~ I

~ t

iijf%).s

Il~

!}lI ~

e lttii 11 i>3li,l

e ~ ~ tIifi )ti%eh ~ 3

~r I

g!Ie"5( t'I~ ~

I ~

i ~ ) I 3.1>'.

~ I ~

)~ ~ ~

~ of~ ~ ~

~ ~

s

lift~ ~

5}}3 I II ~ it~

)iie II:I I 4 ~13

8?o/ I ~ >

el)i

if ere.'ill:i:ii 33)

)l.ii'!Ei3

~

I 1 3

'il!nP

~ Iijl eie.t

)135

8'I i:3.3~ ~

I:~, I ~

~ >~'I

~ ~ ~ el}

~ j i}!I~ 113;::

I ~ I I~1

O.

Pi I

!III)e»j

~ ~ ~

.!il.'}53

t:

ve

~ 11%t'e

te

55 3

!I!Ine

~5

I ~ ~Ill

~ ~

~ ~I ~~ ~

~ 3*3

~n

P:3 rli i~ ~

~ ~ ~III 33'.

i.»

3 ~ ee~ ~

!iii iii'fif!~

s 1

('

-'1 lli ill~

VJf !if: I Jt

g ~

."i.:! ~4: s!f

lnt:eif: i:!I~ I ieli:Il"3% I:ll )lli

!;! !!!3 i!!I~ .

3:I

~ ~ I'Iite

~ ~ ~

ret ~

~333

it 1)1!::::en .I:.

":e ": '>':

~ ~

liij j'ii!!ii~ >

!lii nL!

sill

'jte

I3

~ ~

ills

I ~ ~ ~

3')f

45

3

I

li;.~ '

~

3311.c ~ >1

~ ~

:)el~ ~~ 3e 1-

esl

~ ~ ~

13

~ e

5 ~ (~

~ I

55:

~ ~

~ ~ee

e 15!

I ~

I'e ~

I ~ ~~ ~

31

3)!I

F5'~ \

5%.:

~1

I') '»

~ ~~ ~

131

3~

I ~ ~~ ~

~ ~

~3

~ ~ ~ ~

~ . e~re

:ifeile

~ ~

;1~ ~

~ I ~

:2, 3}'}ifn

~ ~ e~ ~

~ ~

::el

I ~

~ ~

~ ~ ~

~ ~ ~ ~ ~ ~ ~ ~ ~

~ ~

~ ~

I ~ ~e

IC,'I

~ ~ ~ ~ ~ ~ ~ ~ C

5!!I}iI I

~ ~

~ %t ~

»I

I ~ tt j ~

HP,! }."

~ ~ ~:::I

te ~

::3:ir .13!

~ %% ~ ~ '

r ~ ~

~ ~ ~

~ 3:

I~

r ~

~ ~ ~ ~

e ~ ~

5!5}3

r ~

~ ~ I

. ~ ~ I

~ ~

~ ~ ~ ~ ~ ~ ~ ~

> ~~ e

~ ~ ~ ~

Page 66: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

~ g m ~ lt

Page 67: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

STATE OF FLORIDA ))

COUNTY OF DADE )

ss

00 being first duly sworn, deposes and says:

Tha ne is Vice PresidentLight Company, the Licensee herein;

of Florida Power s

That he has executed the foregoing document; that the state-ments made in this said document are true and correct to thebest of his knowledge, information, and belief, and that he isauthorized to execute the document on behalf of said Licensee.

Hi el C. Cook

~ ] lf'IP

Subscribed and sworn to before me thisdR5t 0f 19 gQ

NOTARY PUBLIC, in and fo the County of Dade,State of Flori a

Notary Public, State of Florida at Large

Qn e Xpire S . My Comrnidon B<P ire s 0ctobs r 30, 1 983~ ly l \ I4

Page 68: 'Turkey Point 3 Steam Generator Insp Program.' · 2019. 3. 7. · TURKEY'OINT3 STEAM GENERATOR INSPECTION PROGRAM I. Introduction An extensive inspection program for the Turkey Point

/

~

QP""

~r

a,

C 4


Recommended