TW@ESI14th May 2016
The following is a record of what was done during the past week and a forecast of the next week.....
A General Note before we start- New premises
The new premises.... Most works have now been completed- well done to all for their efforts done. The following is to be done before we can ay we are really ready! a) Electrical door lock installation on new doorb) Office DAC and intruder are re commissionedc) Air Conditioning controls with JACEd) Re installation of fire alarm panele) Re installation of all wall mounted items in tech areaf) Patching of IP points in design and commissioning offices will
happen next Monday 16th May- we may have restricted access to internet / serer after 1500hrs- As soon as this is done- Design and commissioning offices may be shifted back to place
g) Snag list is pending which is with Dennis to implement
A General Note before we start- Some General Notes•It was great seeing you all last Friday for LVA/GME/CCA farewell•Welcome to our new employees Stefan and Andrew- Clifton and Claudio please get them on Linkedin and onto this group for them to follow us•Stefan and Clifton have started some Webex sessions on Intruder alarms with Honeywell they also had a session with a Honeywell expert in our offices last Wednesday•Myself and John will be in the US for next week.. I will return on 25th May... John will be visiting Microbiz in SF for the week after•Margaret will be on leave as of 21st May to 1st June – Happy Holidays Margaret.
Projects and deadlines• 15_044_Hilton_Restaurant_Kitchen_AHU and
15_034_Hilton_Calorifier_Monitoring. We have managed to commission basic closed loop controls ... Next would be the full commissioning of the project- My estimate is that this will be completed by end of May 2016- CVA can you confirm that this is achievable
• 15_033_Westin_7-AHU- Most of the T&C should by now be completed. Pending is documentation CCI I would like a target date on the completion here
• 15_008 - Aurobindo PH02 BMS- We have made progress on commissioning here- we are stuck on a lot of issues by the client – We must do all we can to close items which are our control
Projects and deadlines• 13_052 New offices- Now a target is – Complete all
installations and everyone to move back to their places – new target – Mid May 2016... Latest!!
• 12_027- Parliament installation of St James lift intercom and DAC system, this too , is a very urgent project and we have progressed well on the lift- Hopefully we finish next week guys!! Last Friday we had an emergency situation at Parliament which Clifton solved with help from Honeywell... And some people also know what it took to get hold of the software which was locked in the bonds
• The Vibrant Lighting control project will be due soon and I expect the commissioning of the project to happen in June or Latest July 2016
DesignLast week• Life Sciences - Concluded Panel Drawings printing,
distributed to Clifton, for site, my files, MPa O&M manual
• Siggiewi – Printed full set for MPa O&M manual• AAP Residence – Concluded Intelligent Ltg P&IDs,
submitted. (now awaiting final go-ahead from Martin) / Trashed all BMS related queries with TBR re: remaining systems, will start Points list & P&IDs as from Monday / released various requests for pending info from others
DesignNext Week:• Life Sciences – PDFs of all drawings for MPA O&M• Westin 7AHUs – get As Built feedback from DSH,
implement• AAP Residence – Points list & P&IDs of all remaining
systems, hopefully submit• Release query of Terminating details from all
accordingly, so I compile library for Terminating Matrix
• OTM –next week I can commence on Q015_MOV_PT_for_P12
InstallationPast week:– Changed cold room sensors and PD sensor at Hilton– Assisted Claudio at Fimbank on A/C testing– Started installation on parliament lift– Completed intruder new cabling at ESI offices
InstallationNext week:– Meet with DLI and discuss installation of OVT
Penthouse– Complete intruder termination at ESI offices– Start DAC at ESI – Complete parliament lift– Start University intruder installation
Panel BuildThere are no Panel Build activities at this point- we
need to have a plan for the following panel designsa) Hilton VSD for EF48b) OVT panelsc) APP panels
Mater DeiThe following are the tasks being worked on and planned for the next weeks• MCC Panel Checks/UPS in BMS Panel E01-CC1, E02-CC1, EP1-CC1, F01-CC1,
F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL D00-CC1, D01-CC1, DP1-CC1, D02-
CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D02-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3
• Field Device PPm D08-CC1, DP5-CC1 / D08-CC2, D08-CC3 / D09-CC1, D09-CC2• COORDINATED CHECKS OF ALARMS FROM 3RD PARTY DEVICES D08-CC1, DP5-
CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• Handling of reactive work orders• Quotation works new angiography project• Cont WinCC Upgrade HMIs- which are now all on line- well done all!!• To Add 2 new Alarms from volt free contacts of medical fridges in rooms
D113051 and D113052• New Medical gas alarm in B212005
Development and Commissioning• We have done large important steps on finishing off the Parliament
we need to get the documentation out of the way too to avoid us going time and time again on site- IT IS NOW A PRORITY AND WE NEED TO GET A COMPLETION- we have an urgent quote to implement on Parliament St James lift (intercom and DAC readers)
• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION
• 12_043_Life Sciences – Collecting the KWhr monthly data and finishing off what we can is a huge urgency!!
• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
• The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
Development and Commissioning• OTM urgent jobs and snags – P12/ Tank Field 3 and
quoting for the AS410 change over• Well done for changing CCA intruder - We now have some
internal snags on the panel to resolve- we also have to get to the bottom of the AC snags. CCI and DFA I need your feedback and way ahead
• Oncology 14_066- We have done most of the work here and are waiting from Panta on this
• Aurobindo we are proceeding with software development and we have done quite some progress – we are also now commissioning this project- we will need to come up with a plan here.
Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- is now
urgent and must meet our deadlines• 14_081_Siggiewi School- Lets move on
concluding issues related to Data acquisition and analysis.... We need data and good data to prove our systems
Data, data and more data• We have a lot of projects which are giving us a lot
of data and I would like to start telling “stories” by data
• Story no 1 – Plot all VSD speed of motors above 10KW for last 8 weeks and show how much energy has been saved by looking at the speed profiles – compare the speed profiles of Chilled and hot water compared to outside air temperature
Data, data and more data• Story 2 – Present data from the Siggiewi school
and show this data on some relationships. I have asked Clifton to provide data for classes, corridors, KW meters, PV generation as well as pool data and energy for last 2 months
• Story 3 – Data for SCM PH1 and PH2- I would like some ideas on what stories can be told through data from this project- Claudio can you have a short think and give me some pointers here!!!
Sales and Business Development• We have been working on a quote for Actavis, 2 other Home
automation projects and soon we will be quoting OTM for the change over of their PLC/Operating system and re writing of their core software.
• We are also working to close off a large project at Meridien and a larger than life home automation system
• Last week we had our regional sales manager from Italy – Flavio Romano who came with a Technical expert on CCTV who gave some pointers to Clifton and Stefan
• We have won a small DAC project at a very important and prestigious client – BMIT- this client has more work for us and this small (one door) DAC project has to be an opportunity for us to prove ourselves
Birthday wishes go to
Marita Fenech and Lyubomir Ivanov Atanasov
20th May
• More lessons to follow shortly
Team ESI• I urge you all to follow this blog and keep up to date with
what is happening at ESI • I await all your feedback on all the ESI discussions –
without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group
• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
Team ESI• Lets all work to get the work done on time, on budget
and to the required quality• We need to communicate, pull the rope in the same
direction to make our projects a success and profitable• I have been seeing a lot of encouraging actions
showing teamwork- people working and helping each other as a team – this needs to go on and we must work to achieve what we persist for- success!!!
• Have a good week