TW@ESI12TH MARCH 2017
Hello to all , hope you all had a good weekend.
The following is a record of what was done during the last working week and a forecast of the Next week.....
Initial Points
Projects and Deadlines
Design
Installation Panel Build
Mater Dei Hospital PPM
Business Development
New employee - Miltiadis Charalampidis (AKA Miltos) – Please join us on Linkedin
Some Points Before Starting
Shridar will be on long leave from 17 Feb 2017 to 20th March
Dennis Smith has resigned from his post as Projects Co Ordinator will
work till 17th March 2017 - We will struggle to fill in Dennis’ shoes and I will need everyone’s help until we
find his replacement- I would like to thank Dennis for the service he gave ESI and wish him luck on his
future
A New employee - Francisco Rupérez Herrera (Spanish
Nationaliity) will be joining us as of 16th March 2017- he will
be working as a technician with SSA and CFH
We have a new intern Redis Ziu (Italian Nationaility) who is
working with SSA/CFH
Projects and Deadlines
16_025_DeLaRue_OFX
50% of the machines have been commissioned by CFH
14_069_OTM Additions
Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017
Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs
16_007_LeMeridien
We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-
We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here
16_066_Sterling_DCS_Line2
We have started some preliminary engineering here.... We will now proceed to detailed engineering
16_040_Playmobil_Factory
We have started design and engineering here on MCC1 and 2 and I have started placing major orders
Projects and Deadlines
16_023_GGY
We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform
15_011- Sliema apartments
We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017
15_023_FM panels
D20 ASRD being built by sub contractor and scheduled for 9th March 2017
15_023 Q012 [D10 Endicare 230V] - Beginning april 2017
Q004_013_D5M ASRD 110 PPA is scheduled for 30th April – we also have another scheduled for 30th Sept
16_041_RSM_Security
We need to close off here – the sooner the better
SAI needs to give a date by when ESI will be completed from all works (works pending from others excluded)
16_058_Methode
Another fast tack project Jace Based AHU control system here
We have done some giant steps on Testing and commissioning – still an amount to do after other finish their works
Projects and Deadlines
12_043_LSP
There are some points on the tenant billing application which we are tackling
13_031_CCA
We have a number of snags here , which are to be put to bed once and for all!!
The snags are centred around the AC controls and the NUOO CCTV system
14_08_Siggiewi School-
We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –
14_083_Interconti
We have commissioned the system with snags - we will return to site when snags are done by others-
We also have to deliver the pool panel
15_038_new_HA_Ovt and 15_026_Apap
Residence
These two home automation projects are now urgent- we need to complete all installation
We also need to start working of the software development- they are urgent and we have to perform
Projects and Deadlines
12_025_SCM PH2
The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
13_070- SCM Lagoona Plant room
We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue
13_075_Bosch_ProWatch_Genetec_Interface
The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
01 02 03 04
DesignFor the Past week we have been working on the following
OTM – Continued Q020 Netherlocks remaining Design )OTM – Started SSA’s Q021 docs revision request
Playmobil HF80 – completed Panel Design of MCC1 & MCC2released MCC2 to for DraughtingPlaymobil HF80 – started draughting of MCC1
Design
Started & completed new FM Env. Sent to CFH to submit
01 02 03 04
DesignAnd next week… we will work on
Playmobil HF80 – continue complete draughting of MCC1Playmobil HF80 – Dimensions & labels for MCC1 – Continue Draughting of MCC2
Design
This is what the Installation team have been working on last week
Completed power and bms install at Methode
Completed panel terminations on Level 1,2 and 3 at Graham
Installation
Installation of water meters at Graham
Completed most of the commissioning at Methode
Continued with panel terminations at OVT
….. And this is what is planned for next week
Continue with commissioning at Intercontinental
Testing of louvers at Siggiewi primary
Tackle snags at Methode
Installation
Updating of panel drawings at OTM
Sterling PPM cleaning
Next week we will • FM Env D10_Endicare_230– This will be built by a sub
contractor
Panel Build
Panel Build
Week 11PPMYearly Field devices checks, IR images & coordinated tests Mar-- E01-CC1, E02-CC1, EP1-CC1, E01-CC2, E01-CC3 Quarterly panel checks Mar -- H01-CC1, HP1-CC1, P04-CC1, P02-CC1, P03-CC1, T01-CC1, T02-CC1 E01-CC1, E02-CC1, EP1-CC1, F01-CC1, F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1 Weekly update of antivirus on all BMS stations
Mater Dei Maintenance
ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberQxxx_NewCPRalarmsWO-000117205926_ModifyC01-AHU1
Mater Dei Maintenance
Crane Currency BMS and ELV Proposals
Actavis Solvent area Process quote
De La Rue BMS
These are the quotes the business development
team have been working on
Business Development
\
HAPPY BIRTHDAYCLIFTON CAMENZULI – 16TH MARCH
I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
I urge you all to follow this blog and keep up to
date with what is happening at ESI
Lets all work to get the work done on time, on
budget and to the required quality
We need to communicate, pull the rope in the
same direction to make our projects a success
and profitable
Some Last Thoughts
I wish you all a good and productive
week