TW@ESI19TH FEBRUARY 2017
Greetings from Koh Samui or as the Thais say sawatdee ka , well they actually say sawatdee kaaaaaaaaaa with an ever prolonged aaaaaaaaaa
The following is a record of what was done during the last working week and a forecast of the Next week.....
Initial Points
Projects and Deadlines
Design
Installation Panel Build
Mater Dei Hospital PPM
Business Development
Unfortunately I have to announce the resignation of
Karolina Jurczenia... Her last working day will be 28th Feb 2017.... I would like to thank Karolina for her service and wish her luck in her future
Some Points Before Starting
Also note that Shridar will be on long leave from 17 Feb 2017 to 20th
March
Two new full time employees will be starting
shortly... I will let MPA do the formal introductions
Projects and Deadlines
16_025_DeLaRue_OFX
Training by overseas specialists was delivered and we now await for the client to install hardware in machines so as for us to commission
14_069_OTM Additions
Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017
Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs
16_007_LeMeridien
We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-
We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here
16_066_Sterling_DCS_Line2
We have started some preliminary engineering here.... I will holding a kick off meeting shortly
16_040_Playmobil_Factory
We have started some preliminary engineering here.... I will holding a kick off meeting shortly
Projects and Deadlines
16_023_GGY
We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform
15_011- Sliema apartments
We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017
15_023_FM panels
D20 ASRD being built by sub contractor and scheduled for 9th March 2017
D05 M 110 – scheduled for 1st May 2017
D20 ASRD 690 is presently in quotation stage
16_041_RSM_Security
We need to close off here – the sooner the better
SAI has prepared a snag list of outstanding works and he now needs to give a date by when ESI will be completed from all works (works pending from others excluded)
16_058_Methode
Another fast tack project Jace Based AHU control system here
Prosit for all efforts to complete the panel!! It will be delivered next week
Dennis will now push our sub contractors to complete the required cable pulling and terminations
CCI/CVA are to proceed with programming
Projects and Deadlines
12_043_LSP
We have an important and urgent snag to be rectified ASAP – treating the rust on enclosures
There are some points on the tenant billing application which we are tackling
13_031_CCA
We have a number of snags here , which are to be put to bed once and for all!!
The snags are centred around the AC controls and the NUOO CCTV system
14_08_Siggiewi School-
We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers – We also have a major fault/snag which needs to be rectified
14_083_Interconti
We have commissioned the system with snags - we will return to site when snags are done by others-
we also have to deliver the pool panel
15_038_new_HA_Ovt and 15_026_Apap
Residence
These two home automation projects are now urgent- we need to complete all installation
We also need to start working of the software development- they are urgent and we have to perform
Projects and Deadlines
12_025_SCM PH2
The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
13_070- SCM Lagoona Plant room
We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue
13_075_Bosch_ProWatch_Genetec_Interface
The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
01 02 03 04
DesignFor the Past week we have been working on the following
OTM – Q020 Netherlocks – completed & submitted TF3_NVC_002OTM – Q020 Netherlocks – BH1_NVC_001 – 85%
Playmobil HF80 – compiled Points Lists including all Tag References for ALL project – Started P&ID for MCC1
Sterling DCS Line2 – Preliminary Panel Sizing with TBR, to release Rittal quote request
Design
01 02 03 04
DesignAnd next week… we will work on
FM Environmental – Update as per CFH feedback, re-send to CFH to re-submit
AAP – complete implementation of Additions
Design
OTM – Q020 Netherlocks – BH1_NVC_001 – OTM – Q020 Netherlocks – TF3_NVC_004 and NVC 022 revise as per Client feedback (minor changes) & re-submit
Playmobil HF80 – continue P&IDs for MCC1, start-off P&IDs for MCC2
This is what the Installation team have been working on last week
Continued with works at OVT- Completed Data terminations at OVT
Added DALI sensors at RSM
Connected some doors at RSM
Installation
Continued with some works at Mosta workshop
….. And this is what is planned for next week
commissioning at RSM
Start canalization and cable pulling at Methode
Installation
Change VSD at Medichem
Deliver panel to Methode
Next week we will • 16_058_Methode- I am aware that we still have some
more work on this panel- but it must be delivered next week
• FM Env D20-ASRD – This will be built by a sub contractor as soon as we get the parts
Panel Build
Panel Build
Week 07PPMYearly Field devices checks, IR images & coordinated tests Feb-- D11-CC2, D12-CC1, F02-CC1, F05-CC1, F05-CC4, F05-CC5
Quarterly panel checks Feb -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D05-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2,D12-CC1
Weekly update of antivirus on all BMS stations
Mater Dei Maintenance
ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberWO- 116184572 (Q131)To supply and replace existing control gear for F2-CHW1-P2 with a new simocode and sirus soft starter
Mater Dei Maintenance
BOV control panels and systems
lighting control systems in Qatar
Quote for Fire alarm
Building automation in a private clinic
MCC for an officeThese are the quotes the business development
team have been working on
Business Development
Some Last Thoughts
Re one of the last major projects we have won – Playmobil- I know a lot of people contributed to this success- people who gave ideas, thoughts, shorcomings on similar projects, opened doors to contacts, worked on quotes and re quotes- you know who you are- and I say a big Thank you!! It gives me great satisfaction to achieve something when a lot of people have pulled together to win a goal!
I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
I urge you all to follow this blog and keep up to
date with what is happening at ESI
Lets all work to get the work done on time, on
budget and to the required quality
We need to communicate, pull the rope in the
same direction to make our projects a success
and profitable
Some Last Thoughts
I wish you all a good and productive
week