UKCS Decommissioning Benchmarking Report 2020
1
1. Executive summary
Official government forecasts suggest that oil and gas will remain an important and critical part of the UK energy mix for the foreseeable future, as we transition to net zero. Managing the basin’s declining production to maximise value from the UKCS is still vital to meet our energy demands as long as they exist, as well as reducing reliance on imports and their associated carbon footprint. Ensuring that decommissioning is carried out safely, and in a timely, cost effective manner not only helps value extraction from the UKCS, but also demonstrates industry’s commitment to responsibly manage the UK’s hydrocarbon legacy.
This report provides comparison data which benchmarks a wide range of UKCS decommissioning activities. It follows the publication of the UKCS Decommissioning Cost Estimate 2020 in August. The reported cost/benchmark information is derived from the perspective of the customer (i.e. does not necessarily reflect the costs incurred by the service provider) and, with a very small number of defined exceptions (see appendix), is based on recently incurred, ‘actual’, expenditure.
The intent is that the benchmarking graphs will communicate the key insights without the need for detailed text. The second section of this report provides guidance on their interpretation. Supporting text will therefore only be present by exception, should there be an important element of the graphs that needs explanation.
Contents
1. Executive summary 1
2. Benchmark representation of cost performance and uncertainty 2
3. Benchmarks 4
Project Management 4Post-CoP Running Costs 8Well Decommissioning 14FPSO Removal 30
4. Appendix: Data screening rule-set 32
All costs are in £2019 unless otherwise stated
2 3
2. Benchmark representation of cost performance and uncertainty
2. Benchmark representation of cost performance and uncertaintyUKCS Decommissioning Benchmarking Report 2020
Cost information is collected from all UK decommissioning operators. Comparable data, such as costs of decommissioning platform wells in the Southern North Sea, is screened against a data quality rule-set (see Appendix), sorted from large to small, and then graphed as in Figure 1 to characterise the cost variances experienced for that parameter.
Figure 1 illustrates the definition of several key benchmarking terms used. In the generic example:
• the highest 25% of activity unit costs were executed for between £20 - £45. Unit costs in this range are referred to as being in the Fourth Quartile
• the second highest 25% of activity unit costs were executed for between £15 - £20. Unit costs in this range are referred to as being in the Third Quartile
• the second lowest 25% of activity unit costs were executed for between £11 - £15. Unit costs in this range are referred to as being in the Second Quartile
• the lowest 25% of activity unit costs were executed for between £5 - £11. Unit costs in this range are referred to as being in the First (or ‘Top’) Quartile
Other graph types utilised in this report to illustrate the cost performance data are:
Cost trend graphs (see Figure 2 exemplar): The graphic illustrates cost and cost uncertainty trends, and includes examples of the types of insights which can be derived.
Figure 1: Example ‘s-curve’ to illustrate definitions of quartiles and P-values
Figure 2: Example of unit cost trend graphic Figure 3: Example of cost performance quartiles
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £5 £10 £15 £20 £25 £30 £35 £40 £45 £50 Fra
ctio
n o
f co
st o
utco
mes
bel
ow
the
x-a
sis
valu
e
Cost of completed activity
Generic s-curve
Third Quartile: £15 - £20
Fourth Quartile: £20 - £45
Second Quartile: £11 - £15
First Quartile = £5 - £11
P25
P50
P75
P100
P0
£0
£2
£4
£6
£8
£10
£12
£14
2017 Pre 2017 2018 2019 2020 2021 2022
Co
st p
er w
ell (
MM
)
P25 P50 P75
Interpretation: The 2017 data has greater cost differences between the first quartile (P25) and the fourth quartile (P75), than is the case in 2018 and 2019. Cost performance is therefore more consistent in 2018/2019
Interpretation: Costs reduced from 2017 to 2018, and then remained unchanged through to 2019
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £5 £10 £15 £20 £25 £30 £35 £40 £45 £50 Fra
ctio
n o
f co
st o
utco
mes
bel
ow
the
x-a
sis
valu
e
Cost of completed activity
Generic s-curve
Third Quartile: £15 - £20
Fourth Quartile: £20 - £45
Second Quartile: £11 - £15
First Quartile = £5 - £11
P25
P50
P75
P100
P0
£0
£2
£4
£6
£8
£10
£12
£14
2017 Pre 2017 2018 2019 2020 2021 2022
Co
st p
er w
ell (
MM
)
P25 P50 P75
Interpretation: The 2017 data has greater cost differences between the first quartile (P25) and the fourth quartile (P75), than is the case in 2018 and 2019. Cost performance is therefore more consistent in 2018/2019
Interpretation: Costs reduced from 2017 to 2018, and then remained unchanged through to 2019
Representation of cost performance quartiles (see Figure 3 exemplar): The graphic contains most of the same information as s-curves (Figure 1), but more clearly illustrates the unit cost quartiles. In this example, the first cost performance quartile is £2.3MM - £4.8MM per well (i.e. the cheapest 25% of wells have costs in this range), the second quartile cost performance is £4.8MM - £5.3MM per well, etc.
Inc5 Subsea well P&A (SNS) Blank 0 0.0
Blank 2.3 2.3 First Quar�le 4.8 2.5 Second Quart 5.4 0.6 Third Quar�le 7.0 1.6 Fourth Quart 11.7 4.7
First Quartile
Second Quartile
Third Quartile
Fourth Quartile
£0
£2
£4
£6
£8
£10
£12
Cos
t /
wel
l (M
M)
The terms P25, P50 and P75 refer to the unit cost values below which 25%, 50% and 75% of these activities are executed. The simple relation between these values and the quartiles are illustrated in the figure.
4 5
3. Benchmarks
3. BenchmarksUKCS Decommissioning Benchmarking Report 2020
Decommissioning Project Management (Projects < £150MM)
New benchmark. This benchmark was not previously calculated as the number of completed projects on which to base an analysis was too low. Filtering of the dataset now available suggests that Project Management levels and uncertainty are functions of the project size, with £150MM being the approximate interface between the smaller and larger project populations.
Percentage
P25 7%
P50 10%
P75 16%
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
2017 Pre 2017 2018 2019 2020 2021 2022Pro
ject
Man
agem
ent
% o
f Tot
al D
ecom
Cos
t (%
)
P25 P50 P75
First Quartile
Second Quartile
Third Quartile
Fourth Quartile
0%
5%
10%
15%
20%
25%
Pro
ject
Man
agem
ent
% o
f Tot
al D
ecom
Cos
t (%
)
Figure 4A: Project Management (Total project: <£150MM) Figure 4B Figure 4C
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 5% 10% 15% 20% 25% 30%
1- P
roba
bilit
y of
Exc
eeda
nce
Fourth Quartile
Third Quartile
Second Quartile
First Quartile
% of Total Decom Spend
The information in this section summarises the cost performance of key cost drivers, based on actual cost experience i.e. not including cost estimates/forecasts (the few exceptions are listed in the Appendix). The terms quartiles, P25, P50 and P75, referenced in the graphs, are explained in the previous section.
Sample Size (Latest data) : 41-50 datapoints
6 73. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
0%
2%
4%
6%
8%
10%
12%
2017 Pre 2017 2018 2019 2020 2021 2022Pro
ject
Man
agem
ent
% o
f Tot
al D
ecom
Cos
t (%
)
P25 P50 P75
First QuartileSecond Quartile
Third Quartile
Fourth Quartile
0%
5%
10%
15%
20%
25%
Pro
ject
Man
agem
ent
% o
f Tot
al D
ecom
Cos
t (%
)
Figure 5A: Project Management (Total project: >£150MM) Figure 5B Figure 5C
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 5% 10% 15% 20% 25% 30%
-1 -
Pro
babi
lity
of E
xcee
danc
e
% of Total Decom Spend
Third Quartile
Second Quartile
First Quartile
Fourth Quartile
Percentage
P25 8%
P50 9%
P75 10%
Decommissioning Project Management (Projects > £150MM)
New Benchmark. This benchmark was not previously calculated as the number of completed projects on which to base an analysis was too low. Filtering of the dataset now available suggests that Project Management levels and uncertainty are functions of the project size, with £150MM being the approximate interface between the smaller and larger project populations.
Sample Size (Latest data) : 5-10 datapoints
8 93. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Platform Post-CoP Running Costs in the Northern North Sea (NNS) & Central North Sea (CNS)
These have reduced substantially, largely due to better optimisation of the late-life and warm/cold phases of decommissioning, with rapid reduction in running costs after cessation of production (CoP). Scheduling well decommissioning and Permanent Isolation/Cleaning activities so as to minimise the duration of the inspection/maintenance-intensive warm phase, and then de-manning, has typically proven very cost effective.
Due to the infrequent and multi-calendar-year nature of this metric, these datapoints include estimates for platforms still being decommissioned, where the relevant operator has a well defined plan and recent decommissioning experience with similar infrastructure.
£0
£20
£40
£60
£80
£100
£120
£140
£160
£180
£200
2017 Pre 2017 2018 2019 2020 2021 2022
Tota
l Pos
t CoP
Run
ning
Cos
t (M
M)
P25 P50 P75
First Quartile
Second Quartile
Third Quartile
Fourth Quartile
£0
£50
£100
£150
£200
£250
Tota
l Pos
t CoP
Run
ning
Cos
t (M
M)
Figure 6A: Large Platform Running Cost distribution: NNS & CNS Figure 6B Figure 6C
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £50 £100 £150 £200 £250
1 -
Pro
babi
lity
of E
xcee
danc
e
MM Total
Fourth Quartile
Third Quartile
Second Quartile
First Quartile
Units: MM
P25 £71
P50 £112
P75 £145Sample Size (Latest data) : 5-10 datapoints
10 113. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Units: MM
P25 £0.5
P50 £1.2
P75 £2.1
Platform (Normally Unattended Installation (NUI)) Post-CoP Running Costs in the Southern North Sea (SNS) & East Irish Sea (EIS)
While these costs are typically very low, at the high end they can be considerably impacted by poor commercial frameworks with host infrastructure or 3rd-party duty holders.
Figure 7A: Platform (Normally Unattended) Running Cost distribution: SNS & EIS Figure 7B Figure 7C
£0.0
£0.5
£1.0
£1.5
£2.0
£2.5
2017 Pre 2017 2018 2019 2020 2021 2022
Tota
l Pos
t C
oP R
unni
ng C
ost
(MM
P25 P50 P75
First QuartileSecond Quartile
Third Quartile
Fourth Quartile
£0
£5
£10
£15
£20
£25
Tota
l Pos
t C
oP R
unni
ng C
ost
(MM
)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £5 £10 £15 £20 £25
1- P
roba
bilit
y of
Exc
eeda
nce
Post CoP Running Costs Total
Fourth Quartile
Third Quartile
Second Quartile
First Quartile
Sample Size (Latest data) : 5-10 datapoints
12 133. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
FPSO Post-CoP Running Costs in the NNS & CNS
New benchmark. Other than a very small number of outliers, these costs are spread over a narrow range.
Units: MM
P25 £10.3
P50 £11.2
P75 £11.3
£6
£7
£8
£9
£10
£11
£12
2017 Pre 2017 2018 2019 2020 2021 2022
Tota
l FP
SO
Pos
t C
oP R
unni
ng C
osts
(MM
)
P25 P50 P75
Figure 8A: FPSO Post-CoP Running Cost distribution: NNS & CNS
First/Second/Third Quartile
Fourth Quartile
£0
£5
£10
£15
£20
Tota
l FP
SO
Pos
t CoP
Run
ning
Cos
ts (M
M)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £2 £4 £6 £8 £10 £12 £14 £16 £18 £20
1 -
Pro
babi
lity
of E
xcee
danc
e
MM Total
Fourth Quar�le
Fourth Quartile
Third Quartile
Second Quartile
First Quartile
Figure 8B Figure 8C
Sample Size (Latest data) : 5-10 datapoints
14 153. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Platform well decommissioning costs in the NNS & CNS
The 2017 reductions of 65% in unit NNS/CNS well decommissioning cost have not been sustained, largely due to reduced activity by lower cost Operators, and high impacts from platform-rig reactivation (included in this benchmark). Unit costs per well (P50) have returned to pre-2017 levels, and 4th quartile costs are even higher than experienced then. Significant variation in the well decommissioning costs delivered by different Operators is an issue identified previously, and still to be resolved.
Units: MM
P25 £2.5
P50 £3.7
P75 £6.5
Figure 9A: Change in platform well decommissioning cost distribution: NNS & CNS
Figure 9B Figure 9C
£0
£1
£2
£3
£4
£5
£6
£7
2017 Pre 2017 2018 2019 2020 2021 2022
Cos
t pe
r w
ell (
MM
)
P25 P50 P75
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £2 £4 £6 £8 £10 £12 £14
1- P
roba
bilit
y of
Exc
eeda
nce
MM / Well
Fourth Quartile
Third Quartile
Second Quartile
First QuartileFirst Quartile
Second Quartile
Third Quartile
Fourth Quartile
£0
£2
£4
£6
£8
£10
£12
£14
Cos
t /
wel
l (M
M)
Sample Size (Latest data) : >50 datapoints
16 173. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Platform well decommissioning costs using jack-up rigs in the NNS & CNS
Certain platforms in the NNS and CNS do not have integrated rigs, and utilise jack-up rigs in either cantilever or tender mode when plugging and abandoning wells. Costs are largely unchanged from last year.
Units: MM
P25 £3.7
P50 £4.3
P75 £6.2
£0
£1
£2
£3
£4
£5
£6
£7
2017 Pre 2017 2018 2019 2020 2021 2022
Cos
t pe
r w
ell (
MM
)
P25 P50 P75
Figure 10A: Platform well decommissioning cost distribution using jack-up rigs: NNS & CNS
Figure 10B Figure 10C
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £10 £20 £30 £40 £50 £60 £70
1- P
rob
abili
ty o
f Exc
eed
ance
MM / Well
Fourth Quartile
Third Quartile
Second Quartile
First Quartile
First/ Second QuartileThird Quartile
Fourth Quartile
£0
£10
£20
£30
£40
£50
£60
£70
Cos
t /
wel
l (M
M)
Sample Size (Latest data) : 21-30 datapoints
18 193. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Platform rig reactivation costs: NNS & CNS
New Benchmark.
Units: MM
P25 £12.3
P50 £18.7
P75 £49.6
Figure 11A: Platform rig reactivation cost distribution NNS & CNS
First Quartile
Second Quartile
Third/Fourth Quartile
£0
£5
£10
£15
£20
£25
£30
£35
£40
£45
£50
Tota
l Rig
Rea
ctiv
atio
n C
ost
(MM
)
Figure 11B Figure 11C
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £10 £20 £30 £40 £50 £60
1- P
roba
bilit
y of
Exc
eeda
nce
MM Total
Fourth Quartile
Third Quartile
Second Quartile
First Quartile£0
£10
£20
£30
£40
£50
£60
2017 Pre 2017 2018 2019 2020 2021 2022
Tota
l Rig
Rea
ctiv
atio
n C
ost (
MM
)
P25 P50 P75
Sample Size (Latest data) : 5-10 datapoints
20 213. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Platform well decommissioning costs in the SNS
There has been a slight reduction in unit SNS well decommissioning costs. The variations in the cost performance of different operators has narrowed.
Units: MM
P25 £1.6
P50 £2.5
P75 £3.2
Figure 12A: Platform well decommissioning cost distribution: SNS Figure 12B Figure 12C
£0.0
£0.5
£1.0
£1.5
£2.0
£2.5
£3.0
£3.5
£4.0
2017 Pre 2017 2018 2019 2020 2021 2022
Cos
t per
wel
l (M
M)
P25 P50 P75
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £2 £4 £6 £8 £10
1 -
Pro
bab
ility
of E
xcee
dan
ce
MM / Well
Fourth Quartile
Third Quartile
Second Quartile
First Quartile
First Quartile
Second Quartile
Third Quartile
Fourth Quartile
£0
£1
£2
£3
£4
£5
£6
£7
£8
Cos
t / w
ell (
MM
)
Sample Size (Latest data) : >50 datapoints
22 233. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Subsea development well decommissioning costs in the NNS & CNS
Unit costs have halved since 2017, and cost uncertainty much reduced. This positive performance has been sustained.
Units: MM
P25 £6.0
P50 £7.3
P75 £9.3
£0
£5
£10
£15
£20
£25
£30
£35
2017 Pre 2017 2018 2019 2020 2021 2022
Cos
t per
wel
l (M
M)
P25 P50 P75
Figure 13A: Subsea development well decommissioning cost distribution: NNS & CNS
Figure 13B Figure 13C
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £5 £10 £15 £20 £25
1- P
roba
bilit
y of
Exc
eeda
nce
MM / Well
Fourth Quartile
Third Quartile
Second Quartile
First QuartileFirst Quartile
Second QuartileThird Quartile
Fourth Quartile
£0
£5
£10
£15
£20
£25
Cos
t / w
ell (
MM
)
Sample Size (Latest data) : >50 datapoints
24 253. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Subsea development well decommissioning costs in the SNS
Unit costs and cost uncertainty have both reduced substantially since 2017.
Figure 14A: Subsea development well decommissioning cost distribution: SNS Figure 14B Figure 14C
Units: MM
P25 £4.8
P50 £5.4
P75 £7.0
£0
£2
£4
£6
£8
£10
£12
£14
2017 Pre 2017 2018 2019 2020 2021 2022
Cos
t per
wel
l (M
M)
P25 P50 P75
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £2 £4 £6 £8 £10 £12 £14 £16 £18
1- P
roba
bilit
y of
Exc
eeda
nce
MM / Well
Fourth Quartile
Third Quartile
Second Quartile
First Quartile
First Quartile
Second Quartile
Third Quartile
Fourth Quartile
£0
£2
£4
£6
£8
£10
£12
Cos
t /
wel
l (M
M)
Sample Size (Latest data) : 11-20 datapoints
26 273. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Subsea Exploration and Appraisal (E&A) well decommissioning costs in the NNS & CNS
New benchmark. Suspended E&A wells typically have lower decommissioning costs than subsea producers and injectors, due to the absence of completion tubing and/or a simplified casing scheme. Cost data for these wells are therefore analysed separately to development wells.
The costs reflected here represent the full abandonment of a well i.e. ‘Type 0’ wells which have negligible remaining scopes are not included.
Units: MM
P25 £2.2
P50 £2.7
P75 £7.8
Figure 15A: Subsea E&A well decommissioning cost distribution: NNS & CNS Figure 15B Figure 15C
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £2 £4 £6 £8 £10 £12 £14 £16 £18
MM / Well
1 -
Pro
babi
lity
of E
xcee
danc
e
Fourth Quartile
Third Quartile
Second Quartile
First Quartile£0
£1
£2
£3
£4
£5
£6
£7
£8
£9
2017 Pre 2017 2018 2019 2020 2021 2022
Cos
t /
Wel
l (M
M)
P25 P50 P75
First QuartileSecond Quartile
Third Quartile
Fourth Quartile
£0
£2
£4
£6
£8
£10
£12
£14
£16
Cos
t / w
ell (
MM
)
Sample Size (Latest data) : 5-10 datapoints
28 293. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Subsea E&A well decommissioning costs in the SNS & EIS
New benchmark. Suspended E&A wells typically have lower decommissioning costs than subsea producers and injectors, due to the absence of completion tubing and/or a simplified casing scheme. Cost data for these wells are therefore analysed separately to development wells.
The costs reflected here represent the full abandonment of a well i.e. ‘Type 0’ wells which have negligible remaining scopes are not included.
Units: MM
P25 £2.5
P50 £4.1
P75 £6.6
Figure 16A: Subsea E&A well decommissioning cost distribution: SNS & EIS
First Quartile
Second Quartile
Third Quartile
Fourth Quartile
£0
£1
£2
£3
£4
£5
£6
£7
£8
Cos
t /
wel
l (M
M)
Figure 16B Figure 16C
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £1 £2 £3 £4 £5 £6 £7 £8 £9 £10
1 -
Pro
bab
ility
of E
xcee
dan
ce
Fourth Quartile
Third Quartile
Second Quartile
First Quartile£0
£1
£2
£3
£4
£5
£6
£7
2017 Pre 2017 2018 2019 2020 2021 2022
Cos
t /
Wel
l (M
M)
P25 P50 P75
Sample Size (Latest data) : 5-10 datapoints
30 313. Benchmarks (cont.)UKCS Decommissioning Benchmarking Report 2020
3. Benchmarks (cont.)
Units: MM
P25 £11.2
P50 £21.1
P75 £27.9
FPSO removal (incl. disconnection and tow) in the NNS & CNS
New Benchmark.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
£0 £5 £10 £15 £20 £25 £30 £35
1 -
Pro
babi
lity
of E
xcee
danc
e
MM Total
Third Quartile
Fourth Quartile
Second Quartile
First Quartile
First Quartile
Second Quartile
Third Quartile
Fourth Quartile
£0
£5
£10
£15
£20
£25
£30
£35
Tota
l FP
SO
Dis
conn
ectio
n &
Tow
(MM
)
Figure 17A: FPSO disconnection and tow Figure 17B Figure 17C
£0
£5
£10
£15
£20
£25
£30
2017 Pre 2017 2018 2019 2020 2021 2022
Tota
l FP
SO
Dis
conn
ectio
n &
Tow
(MM
)
P25 P50 P75
Sample Size (Latest data) : 5-10 datapoints
32 33
Appendix: Data screening rule-set
Appendix: Data screening rule-setUKCS Decommissioning Benchmarking Report 2020
A simple rule-set is utilised when selecting data for inclusion when calculating the benchmarking metrics. The main purposes of the rule-set are to ensure that:
1. data is sufficiently current to be relevant
2. there are sufficient datapoints to create a meaningful s-curve
3. high certainty is achieved for the few benchmark categories1 which are not completely based on historic-costs/actuals or fixed-price contracts
The rule-set evolves based on experience of where it results in misleading results. The rule-set as of Quarter 2 2020 is listed opposite:
Relevant S-curves S-curves are done by WBS, unless a subset of data from one WBS can be accurately tracked, e.g. subsea and platform well P&A within the ‘Well Abandonment’ WBS.
Data validity criteria (1) The S-curves should only include data points from the start of the previous year if there are 5 or more data points in this period, except for well P&A where the previous 2 years of data will be taken. (Reasoning: well P&A often done in batch mode which can take >1 year from P&A start to finish)
If there are <5 data points in this period then data can be taken from previous years to get the minimum 5 data points required. If there are not 5 data points available then there will be no benchmark calculated.
Data validity criteria (2) Data points can either be actuals where work has been fully executed by an operator and the actual cost is known, or costs where there is a high level of certainty e.g. fixed price contract in place or high percentage of work complete.
*For Running Costs, we class a high degree of certainty when either the PM spent is >80% or when the associated platform well P&A is underway and the amount of running cost spent is >30% of the total running costs expected to be spent.*For Project Management, we class a high degree of certainty as when either the PM spent is > 80% or the total decommissioning estimate is certain (i.e. complete, underway, contracts placed for majority of the activity) and > 50% spent. The actual PM is typically considered certain as the Operators core project team wont fluctuate significantly during a decommissioning project.*For Isolation & Cleaning, we class a high degree of certainty when >80% of the spend has occurred.Note: the data points that are not actuals should be shown on the S Curve in grey font and the actuals should be shown in black font.
Benchmark calculation Add the data into the data table within the appropriate WBS tab.Sort the data by the appropriate benchmark metric e.g. Cost highest value to lowest value.Percentiles and point numbers will calculate automatically and update the S Curve.The P10, P50 and P90 will calculate automatically and update the ‘Benchmark Table’ to which it is linked. Check the numbers are as expected.
1Project Management, Post-CoP Running Costs, Permanent Isolation and Cleaning
Copyright © Oil and Gas Authority 2018
www.ogauthority.co.uk
Contact us at:[email protected]
twitter.com/ogauthoritywww.linkedin.com/company/oil-and-gas-authority
OGA London Office 4th Floor 21 Bloomsbury Street London WC1B 3HF
OGA HeadquartersAB1 Building 48 Huntly Street Aberdeen AB10 1SH
Oil and Gas Authority is a limited company registered in England and Wales with registered number 09666504 and VAT registered number 249433979. Our registered office is at 21 Bloomsbury Street, London, United Kingdom, WC1B 3HF
www.ogauthority.co.uk
Copyright © Oil and Gas Authority 2020
Oil and Gas Authority is a limited company registered in England and Wales with registered number 09666504 and VAT registered number 249433979. Our registered office is at 21 Bloomsbury Street, London, United Kingdom, WC1B 3HF