Update on the FutureGen ProjectPathway Towards Zero Emissions
Michael J. MuddChief Executive Officer, FutureGen Industrial
Alliance
Gasification Technology Annual ConferenceOctober, 2006
• Commercial-scale 275-MWe Plant • Minimum 1-million (up to 2.5-million)
tons/year CO2 captured and sequestered
• Co-production of H2 and electricity• “Living laboratory” to test and validate
cutting-edge technologies• Public-private partnership• Stakeholder involvement• International participation• On-line 2012
FutureGenProject Features
FutureGen Alliance, Inc.
• Non-profit, 501(c)3 formed to manage the project
• Secured funding
• DOE Cooperative Agreement Signed Dec. 2, 2005
• 10 Members and still growing
Source : UK Department of Trade & Industry, A Strategy For Developing Carbon Abatement Technologies for Fossil Fuel Use
FutureGen
CO2 capture& storage
Ultra super criticalIGCC “capture ready”
Zero emissions
Increased efficiency
Pathway towards zero emissions
FutureGenPush the Technology Envelope
• Establish the technical, economic, and environmental viability of “zero-emission” coal plants by 2015; thus, creating the option for multiple commercial deployments by 2020
• Industry to validate DOE suggested goals:– Sequester >90% CO2 with potential for ~100%– >99% sulfur removal– <0.05 lb/MMBtu NOx– <0.005 lb/MMBtu PM– >90% Hg removal– With potential for a Nth plant commercial cost no more than 10%
greater than that of a conventional power plant
FutureGenIndustry’s View of the Facility
Air
Advanced Electricity
Generation
Research “User Facility”
Advanced Gas Clean-Up
SyngasSyngas CO2 H2
Advanced CO2 separation
O2 SyngasSyngas H2CO2Coal
Air
Slag
AirSeparation
UnitGasification Gas Clean-Up**
CO2Separation**
ElectricityGeneration**
Transportation and
other H2 uses
CO2Sequestration &
Monitoring
Electricity/Hydrogen Generation “Backbone” with CO2 Sequestration/Monitoring System
Advanced Oxygen
Separation
**Candidate for Multiple Technology Upgrades over FutureGen’s Lifetime.
Other Technologies
Electricity,H2, or
other Products
Advanced Coal
Conversion
Full-Scale Gasification
ResearchPlatform
Sequestration
Sub-scaleResearch
User Facility
POWERH2
POWER
FutureGenCurrent Activities
• Site Selection– “Final Four” announced July 25– NEPA process underway– Final site announced summer 2007
• Conceptual Plant Design– Reviews with major technology suppliers– Three alternative facility configurations– Conceptual design and cost estimate underway
• Conceptual Sequestration Design– Reservoir modeling for each site
FutureGenSiting Process Flow
Request for Proposals
Preferred Site
Notice of Intent
Record of Decision
Environmental ImpactStatement
US Government
Environmental Review Process
Qualifying CriteriaEliminated Sites
Scoring & Best Value Criteria
Eliminated Sites
Candidate Site List
Site Characterization &Environmental Information
Sites For Evaluation
Acceptable Site List
Final Decision Criteria
July 2006
July 2007
We Are Here
Proposed SitesMay 2006
March 2006
FutureGenSite RFP Criteria• Qualifying Criteria
– Each proposal evaluated against certain qualifying criteria (Y/N)
• Scoring Criteria– Each proposal scored on each criteria against a
predetermined scale – Weighting system used to roll-up criteria scores
• Best Value Criteria– Each proposal qualitatively evaluated against these
criteriaA report that details the process can be obtained from the
FutureGen web site www.FutureGenAlliance.org
FutureGenQualifying Criteria
17 Surface Criteria 18 Subsurface Criteria
FutureGenSite RFP Scoring Criteria
3.0 Power Plant
SiteCharacteristics
Construction &Operations
3.1 PhysicalCharacterisitcs
3.3 Proximity toSensitive Areas
3.4 Exposure toNatural Hazards
3.2 Other SiteCharacteristics
3.1.1Size
3.6 Water(Cooling)
3.7Transmission
3.8 Materialand FuelDelivery
3.2.1Road
Access
3.2.2Proximityto Target.Forma-tion(s)
3.3.2 TES& CriticalHabitat
3.3.3Cultural
Resources
3.3.4PublicAccessAreas
3.3.5 Non-Attainment
/ Maint.Areas
3.3.1Class I
VisibilityAreas
3.6.1Distance
3.6.2Adequacy
3.7.1 GridProximity
3.7.2Voltage
3.8.3Access toNatural
Gas
3.8.2DeliveryMode
Flexibility
3.8.1 Rail/BargeAccess
3.5.1SEPA
3.1.3Ele-
vation
3.7.3Rights-of-way
3.9Availability of
Workforce
3.9.3Construc-tion Cost
3.9.2Opera-tionalLaor
3.9.1Construc-tion Labor
FutureGen Siting Scoring Criteria
3.1.2Topo-graphy
3.2.5Existing
Land Use
3.2.3Dis-
persion
3.2.4 AirQuality
3.4.1Hurricane
3.4.2Tornado
3.1.4Flood-plain
3.5 Regulatory& Permitting
3.1.5Wetlands
4.0 Geologic Storage
Security
4.1 FormationProperties
4.1.2Orien-tation
4.1.4Capacity
4.2.1Faults
4.2.2Capillary
EntryPressure
4.2.4Injection
WellPenetra-
tions
4.2.5Other
Penetra-tions
4.2.3FractureGradient
4.3.1PhysicalAccess
4.1.1TargetForma-tion(s)
GeologicCharacteristics
4.1.5Size
4.1.3 Per-meability
4.2 Seals4.3 Monitoring,Measurement &
Verification
4.2.6Secondary
Seals
4.3.3Subsurface
Access
4.3.2Legal
Access29 Surface Criteria 14 Subsurface Criteria
FutureGenSite RFP Best Value Criteria• Land Cost• Availability / Quality of
Existing Plant and Target Formation Characterization Data
• Land Ownership• Residences or Sensitive
Receptors above Target Formation
• Waste Recycling and Disposal
• Clean Air Act Compliance• Expedited Permitting• Transmission
Interconnection• Background CO2 Data• Power Sales• Market for H2
• CO2 Title and Indemnification
• Other Considerations
FutureGen Site Selection Underway
12 Sites in 7 States Proposed
Candidate Sites
4 Sites in 2 States on Candidate List
Design and Cost EstimateFacility Goals
Key Goals– Generate 1 to 2.5 million tons per year CO2; (target
90% CO2 capture)– Design for all U.S. coals (primarily bituminous and
sub-bituminous). • Maybe other coals.
– Push the technology (“prototype plant of the future”)– Commercial-scale (275-MW nominal rating)
12,94113,00013,980HHV (Dry Basis), Btu/lb
17.27.875.51Oxygen
0.53.52.49Sulfur
0.010.190.1Chlorine
0.91.51.47Nitrogen
4.94.95.14Hydrogen
70.371.677.67Carbon
6.710.47.62Ash
DRY BASIS (wt%)
6.710.47.62Ash
48.940.338.94Volatile Matter
44.449.353.44Fixed Carbon
DRY BASIS (wt%)
27.67.82Equilibrium Moisture
2911.57Total Moisture
AS-RECEIVED (wt%)
PRBIllinois BasinNorthern Appalachian
Mean Property Values
COAL SPECIFICATIONS
Design and Cost EstimatePlant Design for Fuel Flexibility
Design and Cost EstimateScreening Criteria
• Economic Criteria– Capex Overrun Potential– COE Reduction Potential
• Technical Criteria– Coal Flexibility– Step-Outs– Schedule Risk– Mission Risk– Technical Risk
• Programmatic Criteria– Vendor Alignment– DOE-Developed Backbone Technologies
Design and Cost EstimateConceptual Design Decision Process
List of PossibleConfigurations
Conceptual Designs and Cost Estimates Based on Detailed Heat & Mass Balances and PrelimEngineering
CommonDesignBasis
High LevelFlow Sheets forConfigurations
Single Train(s)
Dual Train(s)
“Hybrid” Train(s)
DownselectBased onQualitativeScreeningCriteria
Alliance w/ EPRI, TEG, Battelle, Internal Support A/E Firm
“Factored”Cost
Estimates
LeadingCandidateCases
Meeting(s) withDOE-NETL
DownselectBased onFactored Costs & Technical Review + “Constraints”
VendorPresentations
~30 cases 13 cases 3 cases
We Are Here
Design and Cost Estimate
Design Cases
• Two Single Trains:– Slurry feed water quench– Dry feed water quench
• One Multiple Stream Hybrid:– 100% full slurry quench– 30% transport gasifier with ITM air separation
• Three coal types:– Northern Appalachian– Illinois Basin– PRB
These are design configurations for the conceptual design and cost estimate, not the final designs. The actual designs
will be established through competitive bids in 2007.
FutureGen
Phases of Sequestration
Preliminary Site Characterization
& Modeling
Detailed Site Characterization
Injection SystemDesign, Permitting,
& Construction
Operations &Monitoring
Post-injectionMonitoring
Closure
We are Here.2006
2018
CO2 Storage
Variety of Reservoir Types
Courtesy of Peter Cook, CO2CRC
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
CarbonContained in Global CoalResource
PotentialGeologic Storage
ReservoirCapacity
CarbonStorage
Demanded in 450
Stabilization
CarbonStorage
Demanded in 550
Stabilization
CarbonStorage
Demandedin 650
Stabilization
Gig
aton
s of
Car
bon
• Published estimates of potential storage capacity are approximately 3,000 GtC (11,000 GtCO2).
• In total this capacity exceeds the global need in ALL CO2 management regimes commonly discussed.
Potential Capacity
Potential Need
Sequestration Capacity: Is there enough?
Global Capacity Exceeds the Need
• 1,185 electric power plants • 447 natural gas processing
facilities• 154 petroleum refineries • 53 iron & steel foundries• 124 cement kilns
• 43 ethylene plants• 9 oil sands production areas• 40 hydrogen production • 25 ammonia refineries• 47 ethanol production plants• 8 ethylene oxide plants
2,082 Large Sources (100+ ktCO2/yr) with Total Annual Emissions = 3.8 GtCO2/yr
• 3,730 GtCO2 in deep saline formations (DSF)• 65 GtCO2 in deep unmineable coal seams with potential
for enhanced coalbed methane (ECBM) recovery• 40 GtCO2 in depleted gas fields• 13 GtCO2 in depleted oil fields with potential for
enhanced oil recovery (EOR)
3,800+ GtCO2 Capacity within 330 US and Canadian Candidate Geologic CO2 Storage Reservoirs
Sequestration Capacity: In Right Places?
Adequate Capacity in U.S.
~ 100 Years
FutureGenSchedule
EstablishLegal Entity
Limited Scope Cooperative Agreement
Negotiations
CooperativeAgreementNegotiations
Project Structuring & Conceptual
Design
Preliminary Design
Initial Full Scale Plant Operations
Site Monitoring Post Initial Operations
Alliance Proposal ---> BP0 BP1 BP4 BP5
DOE RAFA ---> BP2 BP3
BP2 BP3
DOE Projection
Final Design
BP0 BP1
FutureGen Summary Plan
Plant Start-Up and Testing
Facilities Construction
Full Scale Plant Operation Continues
Siting, NEPA, and Permitting
DOE/Alliance Sign
Cooperative Agreement
Critical Decision-1Approved
(Preliminary Baseline Range)
Critical Decision-2Approved
(Performance Baseline)
Critical Decision-3Approved
(Construction Start)
Critical Decision-4Approved
(Operations Start)
Oct 1, 2005 Jan 31, 2007 December 2007 July 2009 July 2016 July 2018
DOE/Alliance Sign Limited
Scope Cooperative Agreement
July 2012
v
ROD July 2007
Final Site Selected & Long-lead Procurements Sept 2007
PlantOnline2012
FutureGenFinancial Requirements
• DOE to provide $700M– $620M from Federal Appropriations
– $80M from Foreign Governments• India and South Korea are on International Steering Committee
• Industry to provide $250M– Expect to share between 10 to 14 full members
Summary
• FutureGen is real and moving forward fast
• FutureGen creates significant value– Supports a technology-based climate change strategy, which mitigates the
financial risk of climate change while protecting the environment– Validates the cost and performance of an integrated “zero-emission” coal-
fueled power plant– Creates the technical basis to retain coal in global energy mix with a long-
term goal of zero emissions.
• FutureGen is an opportunity to share the cost and risk of “zero emissions”technology development
Contact Information:
Michael J. MuddChief Executive OfficerFutureGen [email protected](614) 716-1585
Ken HumphreysTechnical Support, ManagerFutureGen [email protected](509) 521-7784
www.FutureGenAlliance.org