+ All Categories
Home > Documents > Updates on Pakistan Kidney Centre (PKC)

Updates on Pakistan Kidney Centre (PKC)

Date post: 24-Feb-2016
Category:
Upload: freira
View: 58 times
Download: 0 times
Share this document with a friend
Description:
Updates on Pakistan Kidney Centre (PKC). PKC Introductory Function July 2012. Donation Database . PKC Site Location. Inauguration Ceremony . Foundation laid by Dr. Abdul Qadir Khan On December 02, 2012. Key Operational Dates. Out Patient Dept. (OPD): March 2014. - PowerPoint PPT Presentation
Popular Tags:
20
Updates on Pakistan Kidney Centre (PKC)
Transcript
Page 1: Updates on  Pakistan Kidney Centre (PKC)

Updates on Pakistan Kidney Centre (PKC)

Page 2: Updates on  Pakistan Kidney Centre (PKC)

PKC Introductory FunctionJuly 2012

Page 3: Updates on  Pakistan Kidney Centre (PKC)

Donation Database

Donor Information Database

Bank Transfer Details

Cost Schedule

Page 4: Updates on  Pakistan Kidney Centre (PKC)

PKC Site Location

Page 5: Updates on  Pakistan Kidney Centre (PKC)

Inauguration Ceremony

• Foundation laid by Dr. Abdul Qadir Khan On December 02, 2012

Page 6: Updates on  Pakistan Kidney Centre (PKC)

Key Operational Dates

Fully Functional: December 2014

Out Patient Dept. (OPD):March 2014

Mobile Field Hospital: March 2014

Page 7: Updates on  Pakistan Kidney Centre (PKC)

Architectural and Structural Design: Designmen Ltd, Islamabad

Construction Contractors:Capital Construction Ltd, Islamabad

Page 8: Updates on  Pakistan Kidney Centre (PKC)
Page 9: Updates on  Pakistan Kidney Centre (PKC)
Page 10: Updates on  Pakistan Kidney Centre (PKC)
Page 11: Updates on  Pakistan Kidney Centre (PKC)
Page 12: Updates on  Pakistan Kidney Centre (PKC)
Page 13: Updates on  Pakistan Kidney Centre (PKC)

Expenditure Details

Item Expenditure

(PKR)

Steel 7,170,500

Cement 986,000

Other Construction Material 758,843

Labour 335,672

Misc. (all exp other than above 4 Heads)271,617

Contractor Fee (15% of till date expense) -

Total 9,522,632

Page 14: Updates on  Pakistan Kidney Centre (PKC)

Target - A (up to 03 August)

ItemExpected Expenditure

(PKR)

Cement 500,000

Other Material 350,000

Form Work 800,000

Conducting 50,000

Labour 350,000Total Target - A 2,050,000

Page 15: Updates on  Pakistan Kidney Centre (PKC)

Target -B (03 August to September)

ItemExpected Expenditure

(PKR)

Bricks 2,600,000

Cement 1,200,000

Millenniums Material 500,000

Door Frames & Windows Frame 600,000

Labour 900,000

Total Target -B 5,800,000

Page 16: Updates on  Pakistan Kidney Centre (PKC)

Project Execution Plan

Page 17: Updates on  Pakistan Kidney Centre (PKC)

www.pkc.com.pk

Page 18: Updates on  Pakistan Kidney Centre (PKC)

www.pkc.com.pk

Page 19: Updates on  Pakistan Kidney Centre (PKC)

www.pkc.com.pk

Page 20: Updates on  Pakistan Kidney Centre (PKC)

Our Final Goal, insha’ Allah

“…if anyone saved a life, it would be as if he saved the life of the whole people” Quran (5, 32).


Recommended