Upgrade of SM18 Infrastructure on behalf of BE/RF-KCA section

Date post: 15-Jan-2016
Category:
Upload: khoi
View: 23 times
Download: 0 times
Share this document with a friend
Description:
Upgrade of SM18 Infrastructure on behalf of BE/RF-KCA section. Contents. Cryogenics Vertical test stand V3 Horizontal bunker M7 Klystron Wave guides Status and timescale. Cryogenics. Vertical test stand V3. Yesterday. Warm up bath for pumping. Old separated lines. Tomorrow. - PowerPoint PPT Presentation
Popular Tags:
17
Upgrade of SM18 Infrastructure on behalf of BE/RF-KCA section
Transcript
Page 1: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Upgrade of SM18 Infrastructure

on behalf of BE/RF-KCA section

Page 2: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Contents

• Cryogenics– Vertical test stand V3– Horizontal bunker M7

• Klystron• Wave guides

• Status and timescale

Page 3: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Cryogenics– Vertical test stand V3

Yesterday

Page 4: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Old separated lines

Warm up bath for pumping

Page 5: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Tomorrow

Welded connection

Common insulation vacuum

Integrated pumping

New cryostat with active screening and earth magnetic field compensation

Page 6: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Internal tubing with exchanger and valves

Surrounded by superinsulation

Page 7: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

4 Cryo service modules in workshop oct.12

Internal section of the distribution line.Cold He return make screening of the liquid He delivery

Page 8: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section
Page 9: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

V3,4,5,6 Cryo service modules welded in SM18

Page 10: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Cryogenics– Horizontal bunker M7

CCDTL

Dismantling old lines

Page 11: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section
Page 12: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Klystron• Operating frequency f0 : 704.4 MHz • Peak output power at saturation and load VSWR ≤ 1.05 ≥ 1.5 MW • Average output power at saturation and load VSWR ≤ 1.05 ≥ 150

kW • Operating point, below klystron saturation ≤ -1.5 dB • Saturated gain ≥ 40dB • Drive power max 200 Watts • Peak cathode voltage (Ub) at rated output power ≤ 115 kV • Peak cathode current (Ib) at rated output power ≤ 25 A • HV pulse duration 2 ms • HV rise & fall time (each) 80 - 150 μs • RF pulse duration (plateau) 1.7 ms 300 μs(LLRF)+1400 μs(Beam)• Repetition rate 50 Hz

Page 13: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Wave Guides• Integration in M7 well advanced (BE/RF, EN/MME (drawing office))

• Power distribution• Cryomodule (incl. slope)• New standard 2 kelvin service module

• Still to be done:• Detailed integration of cryomodule repair scenarios

• (i.e. how to lift the top cover of the CM?)

• Cabling (RF and Cryo)• SPL valve box to build

Page 14: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

• Adaptation of Wave guides to module change of tilt

• Tests at 0% and 2 (4?) % slope:• Will require WG distribution modifications (1-2 hours)• CM lifting device to be defined

Page 15: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Status & timescale (1)• Procurement of equipment:

• Klystron (1x): 1.5 MWp ordered, delivery end Summer ‘13

• Circulator (1x): ordered, delivery Summer ’14 (on purpose, for budget reasons)

• RF loads (3x): 1.5MWp ordered, delivery January ’13

• Waveguides: special pieces (magic tees, bends, bellows) ordered at Mega Industries (USA) (≈50 k$) all straight parts from Spain (≈50 kEuros)

• Modulator: delivery expected by Fall’13 (tbc by D. Nisbet)

• Electrical power: 3*400V 300A reserved with 400A upgrade on ERD2/M18

Page 16: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Status & timescale (2)

• Key dates:

• Now -> March ‘13: SM18 Cryo distribution replacement • March -> End Summer ‘13: CCDTL tests (Linac 4) • September -> December ’13: SPL HPRF system installation

• Providing the L4 RF tests are moved in Bld150 (3 MeV test stand)? (tbc by F. Gehrig)

• Controls:

• HPRF controls: re-use the PLC system developed and installed for L4 test stand• Cryomodule:

• RF controls expected to be ready by 2014 ( L. Arnaudon )• Cryo controls to be defined ( TE/CRG ) Attention LS1 !

• Low level ?

Page 17: Upgrade of SM18  Infrastructure on behalf of  BE/RF-KCA section

Thanks for your attention

• Live visit of SM18 site this afternoon