+ All Categories
Home > Documents > US Route 4 Traffic and Pedestrian Improvement Project

US Route 4 Traffic and Pedestrian Improvement Project

Date post: 16-Oct-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
34
Welcome to the public meeting for US Route 4 Traffic and Pedestrian Improvement Project June 5, 2018
Transcript
Page 1: US Route 4 Traffic and Pedestrian Improvement Project

Welcome to the public meeting for

US Route 4 Traffic and Pedestrian Improvement

ProjectJune 5, 2018

Page 2: US Route 4 Traffic and Pedestrian Improvement Project

Introduction

• Project Team• Town of North Greenbush,

• Tony Germano, Town Comptroller• Lou Desso, Town Supervisor

• Creighton Manning Engineering• Don Adams P.E., Greg Gibbons P.E., Josh Wilsey P.E., Matt Reluzco

• Laberge Group• Rich Laberge P.E.

• Rensselaer County• Wayne Bonesteel P.E.

• NYSDOT

Page 3: US Route 4 Traffic and Pedestrian Improvement Project

Background• Planning Studies

• 2007 – Route 4 and I‐90 Connector Study

• 2016 – Town of North Greenbush Route 4 Design Guidelines

• Funding • Locally Administered Federal 

Aid (LAFA) Project• Total Funding ‐ $9.83M; 

Construction Funding – $8.26M• 80% Federal/20% Local Match

US Route 4

Page 4: US Route 4 Traffic and Pedestrian Improvement Project

Agenda

• Project Objectives• Existing Conditions• Public Input• Possible Improvements• Project Schedule• Public Input

Page 5: US Route 4 Traffic and Pedestrian Improvement Project

Project Objectives

Reduce TrafficCongestion and

Improve Capacity

Minimize Impacts

Meet the Project Schedule and

Budget

Improve Safety and Mobility

Page 6: US Route 4 Traffic and Pedestrian Improvement Project

Project Process

Project InitiationProject Initiation

DataCollection

DataCollection

Develop Feasible

Improvements

Develop Feasible

ImprovementsPublic ReviewPublic Review

Assemble DraftDesign ApprovalDocuments

Assemble DraftDesign ApprovalDocuments

ReviewReviewAssess

Agency/PublicComments

AssessAgency/PublicComments

Recommend PreferredAlternative

Recommend PreferredAlternative

Final DesignApprovalDocument

Final DesignApprovalDocument

DesignApprovalDesignApproval

Detailed Design/ROW AcquisitionDetailed Design/ROW Acquisition ConstructionConstruction

Page 7: US Route 4 Traffic and Pedestrian Improvement Project

NEPA/SEQRA Process

• Project Identification, Needs and Objectives

• Preliminary Alternatives - Engineering

• Geometrics, Safety, Utilities, Landscaping, Pedestrians and Bicyclists, Cost Estimates

• Environmental, Social and Economic Considerations

• Environmental – Historical resources, Endangered Species

Page 8: US Route 4 Traffic and Pedestrian Improvement Project

Progress to Date

• Ground Survey and Highway Boundary

• Environmental Screenings (ESA, SHPO, NYSDEC)

• Crash Data - Collected/Analyzed

• Traffic Data• Recorded Existing• Developed Future Volumes (Year 2039)• Recorded Existing Vehicle Speeds

Page 9: US Route 4 Traffic and Pedestrian Improvement Project

Project Limits

…to City of Troy BorderFrom NY Route 43…. 2.8 miles

Page 10: US Route 4 Traffic and Pedestrian Improvement Project

Existing Conditions US 4: Bloomingrove Drive to Valley View Blvd

US Route 4

Partridge Hill Apartments

Oak Hill Apartments

Van Rensselaer Shopping

Center

1

2

34

Page 11: US Route 4 Traffic and Pedestrian Improvement Project

Existing ConditionsBloomingrove to Valley View

• US 4 facing South, Existing parking for businesses

• Valley View Intersection facing North

• Bloomingrove Drive Intersection facing West• US 4 and Bloomingrove facing Northeast

Page 12: US Route 4 Traffic and Pedestrian Improvement Project

Existing Conditions US Route 4 and Winter Street Ext.

US Route 4

Alexis Diner

1

2

3

Page 13: US Route 4 Traffic and Pedestrian Improvement Project

Existing ConditionsWinter Street Ext.

• Winter Street Ext. facing East

• Ravine adjacent to US 4

• US 4 & Winter Street Ext. facing North

Page 14: US Route 4 Traffic and Pedestrian Improvement Project

Existing ConditionsUS Route 4 and Williams/Glenmore Road

WS Auto Sales

StewartsShop

La Salle Institute

1

2

3

Page 15: US Route 4 Traffic and Pedestrian Improvement Project

Existing ConditionsWilliams/Glenmore Road

• US 4 facing North, Existing Sidewalk Limits

• Bloomingrove Drive and Williams Road

• Williams & US 4 Intersection facing East

Page 16: US Route 4 Traffic and Pedestrian Improvement Project

Public Comments – Existing Conditions

• What are your existing concerns?

• What did we miss?

Page 17: US Route 4 Traffic and Pedestrian Improvement Project

Proposed Improvements

How are improvements developed?

Engineering Design Standards

Previous Studies

Public Comment

Stakeholder Objectives

Page 18: US Route 4 Traffic and Pedestrian Improvement Project

Proposed Improvements

• Bloomingrove Drive and US Route 4 Intersection

• US Route 4 Widening

• Winter Street Ext. Traffic Signal

• US Route 4 and Williams/Glenmore Intersection• Alternative 1: Intersection widening, replace traffic signal• Alternative 2: Roundabout

• Additional Sidewalk Locations

Page 19: US Route 4 Traffic and Pedestrian Improvement Project

Proposed ImprovementsBloomingrove Drive

1. Realigned Intersection with New Traffic Signal

2. Widening for Turn Lane and curbed median on Bloomingrove

3. Widening for Turn Lanes on US 44. Proposed Sidewalks5. Western Leg for Commercial

Development

1

2

3

4

4

4

5

3

Page 20: US Route 4 Traffic and Pedestrian Improvement Project

Proposed ImprovementsWidening Bloomingrove to Valley View

1. Proposed Road Widening

2. Two-Stage Left-Turns

3. Multiple Parking Alternatives at Businesses

4. Proposed Sidewalk

1 1 123

3

44

Page 21: US Route 4 Traffic and Pedestrian Improvement Project

Proposed ImprovementsWinter Street Ext. Traffic Signal

1. Winter Street Ext. Realignment

2. Coordinate Signal with Jordan Road

3. Proposed Sidewalk

1233

Page 22: US Route 4 Traffic and Pedestrian Improvement Project

Proposed AlternativeWilliams Road Traffic Signal

1. Proposed Traffic Signal2. Widen for Turn Lanes3. Bloomingrove Realignment4. Sidewalks• ROW Impacts = 0.22 Ac

1

2

4

4

2 2

3

4

Page 23: US Route 4 Traffic and Pedestrian Improvement Project

Proposed AlternativeWilliams Road Roundabout

1. Roundabout

• 2 lanes SB and WB

• Traffic Calming

• Gateway to NG

2. Realign Bloomingrove

3. Driveway Access Control

4. Sidewalks

• ROW Impacts = 0.37 Ac

1

2

4

4

4

3

Page 24: US Route 4 Traffic and Pedestrian Improvement Project

Roundabouts – Why?

• FHWA Proven Safety Countermeasure

• 78-82% Reduction in Severe Crashes

• Improve safety for all users, including pedestrians

and bicycles

• Applicable for both urban and rural locations

• Traffic Calming (24/7/365)

Page 25: US Route 4 Traffic and Pedestrian Improvement Project

Roundabouts – Vehicle Safety

Source: FHWA Roundabout Guide, 2nd Edition, Exhibits 5-1, 5-2

Page 26: US Route 4 Traffic and Pedestrian Improvement Project

Proposed Alternative:Williams Road Traffic Signal

Page 27: US Route 4 Traffic and Pedestrian Improvement Project

Proposed Alternative:Williams Road Roundabout

Page 28: US Route 4 Traffic and Pedestrian Improvement Project

Alternative Analysis

Criteria Traffic Signal Roundabout

Safety Improvement Yes Yes++

Traffic Calming No Yes

Proposed Peak Hour Level of Service

LOS C 26 Sec. Delay

LOS C27 Sec. Delay

Estimated Property Impacts

3 Properties(.22 Acres)

3 Properties (.37 Acres)

Estimated Cost $1.5M $2.5M

Page 29: US Route 4 Traffic and Pedestrian Improvement Project

Sidewalk Alternatives

• In 2017, the project team created a Planning Document to prioritize sidewalk improvements in the Corridor

• Criteria Evaluated Included:• Known Pedestrian Generators• Existing Facilities• Logical Termini• Topography• Cost

Page 30: US Route 4 Traffic and Pedestrian Improvement Project

Proposed Improvements:Sidewalks – NY 43 to Valley View Drive

• Proposed Sidewalk• 2200’ along west side of Route 4 from NY

Route 43 to Valley View Drive• 350’ along south side of Bloomingrove Drive

to Van Rensselaer Shopping Plaza• Connects Ped. Generators and Destinations

Page 31: US Route 4 Traffic and Pedestrian Improvement Project

Proposed Improvements:Sidewalks – Jordan Road to Williams Road

• Proposed Sidewalk

• 5900’ along West side of Route 4 from Jordan Rd to Glenmore/Williams Rd Intersection (Stewarts)

• Minimal property impacts (Temporary Easement and/or grading release)

Page 32: US Route 4 Traffic and Pedestrian Improvement Project

Project Schedule

• Draft Design Document Summer 2018

• Preliminary Design Fall 2018

• Detailed Design/Property Acquisition Winter 2018/2019

• Project Out to Bid Fall 2019

• Construction Begins Fall 2019

Page 33: US Route 4 Traffic and Pedestrian Improvement Project

Public Comments/Questions

Town Procedure for comments:

• Oral Comments – Persons may make statements, and/or submit documents concerning the proposed project tonight.

• Written Comments – emailed to the Town’s Comptroller or Creighton Manning.

• Electronic Comments – submitted through project website, https://route4corridorng.com/contact/

• A copy of this presentation and display boards will be made available on the project website 

Page 34: US Route 4 Traffic and Pedestrian Improvement Project

We Appreciate Your Input!

www.route4corridor.com

Tony GermanoTown Comptroller(518)-283-3525

[email protected]

-Or-

Greg GibbonsCreighton Manning Engineering, LLP

(518) [email protected]

Please submit comments within the next 14 days (June 19th).

THANK YOU!!!!


Recommended