Utility Installation Guide:Gas
www.energetics-uk.com
Practical Guidance and Contractual Requirements
Gas
3
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
Copyright © 2019 an unpublished work by Energetics. All rights reserved.
Copyright Copyright © 2019 Energetics. All rights reserved. No part of this publication may be reproduced, transcribed, transmitted, stored in a retrieval system or translated into any language, in any form or by any means mechanical, manual, electronic, magnetic, chemical, optical, including photocopying or otherwise without the prior written permission of Energetics.
Confidentiality This document is the property of Energetics, and is provided on the understanding that its use will be confined to the officers of your company and that no part of its contents will be disclosed to third parties without the prior written consent of Energetics.
Version History
Document version Date Description / reason for modifications
Version 1.0 November 2019 First release of guide
Printing Control This document is uncontrolled when printed. The electronic version of this document is the approved and most current. Any printed version is uncontrolled and may not be current. Please ensure you are referring to the latest version.
Acknowledgements Energetics respectfully acknowledges all trademarks, trade names and other unique identification symbols, whether implied or explicit, used within this document.
Energetics Fenick House Lister Way Hamilton International Technology Park Glasgow G72 0FT
Tel: 03300 587 400 Web: www.energetics-uk.com
GasUtility Installation Guide
4
It contains the following sections:
• Gas Emergencies, gives instructions on what to do in the event of a gas emergency. The emergency number is given and general advice provided.
• Energetics Responsibilities, explains the role and responsibilities of Energetics during gas utility installations.
• Open Trench Gas Mains, explains what the Site Developer must do to prepare these, their depths, fine filling and marking them.
• Gas Mains Ducting, describes the Site Developer’s responsibilities for the depth at which ducts should be positioned, ducting sizes and ducting layouts.
• Gas Services Ducting, details the responsibilities of the Site Developer for the depths of gas services and the duct diameters.
• Flatted Properties – External Meter Boxes, gives details of how Site Developers must position and build external meter boxes.
• Flatted Properties – Meter Banks and Compartments, describes the Site Developer’s responsibilities and describes the ventilation requirements for meter rooms.
Gas
This document deals with the installation of gas services.
• Flatted Properties – External Steel and PE Risers, explains the Site Developer’s tasks for external gas risers in flatted properties.
• Flatted Properties – Internal Risers, describes how Site Developers must construct internal gas risers and the safety precautions that are needed.
• Flatted Property – External Pipeline Isolation Valve, explains how this type of isolation valve should be fitted in flatted properties.
• Gas Meters, describes the steps Site Developers must take when installing gas meters. This includes the dimensions of the meter cupboard, their labelling and steps to take to avoid damaging meters.
• Pressure Regulating Installations (PRIs) – Above Ground, describes how a PRI must be constructed above ground level, its dimensions and location.
• Pressure Regulating Installations (PRIs) – Below Ground, explains PRI construction under ground level, steps that should be taken and Site Developer’s responsibilities.
5
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
Your call will be taken by a call centre who will ask for more information. This will include:
• Your name and phone number.
• The address and location of the suspected gas escape or gas emergency.
• Where the smell is most noticeable.
• How long the smell has been noticeable.
• Whether any other properties are affected.
Gas Emergencies
If you smell gas or are concerned about gas safety on site, phone the 24 Hour National Gas Emergency Number on 0800 111 999 immediately.
Here is some general advice on what you should do if you suspect a gas escape or gas emergency (but always follow instructions from NGES):
• If the suspected gas emergency is indoors, open doors and windows to ventilate the property.
• Unless the smell of gas and the gas meter are located in a cellar or basement, turn off the gas supply at the meter. Do not enter the cellar or basement if the smell of gas is in there.
• Extinguish all naked flames. If possible remove any sources of ignition and do not smoke.
General Advice on Gas Emergencies
• Any special circumstances or access information.
• If the smell of gas is in or near to a highly populated building.
Your answers to these questions enable the National Gas Emergency Service (NGES) to send an engineer to the right address. The NGES can now provide you with the right safety advice in the shortest possible time.
• Do not turn off or turn on any power or light switches.
• Do not operate any electrical equipment.
• If the smell of gas is near or in an open excavation, do not enter the excavation.
• As far as reasonably possible, keep all personnel and members of the public clear from any area where there is a suspected gas escape.
GasUtility Installation Guide
6
These are detailed below:
• To lay all gas pipes in trenches pre-excavated or ducted (unless specified otherwise in the contract) by the Site Developer. This will only be done when it is confirmed that these trenches follow the correct route, are to the correct depth and the correct bedding has been provided.
• Install, test, connect, and commission gas services in ducts previously installed by the Site Developer.
Energetics Responsibilities
• Provide recessed meter boxes or universal meter boxes (Uni-box) for installation by the Site Developer. These are U6 size gas meter with a gas load ≤65kW only.
• Provide a marked up copy of a site drawing showing which gas mains and services are live on site during the construction phase.
NOTE: Energetics staff will not undertake any work beneath scaffolding.
Unless specified otherwise in their contract, the Site Developer is responsible for:
• Excavating and backfilling trenches to provide the required depth.
• Providing the required depth of cover to the top of the pipe and adequate fine bedding and main surround.
• Fully surrounding and covering the gas main with a minimum of 150mm of fine fill material above the crown of the main and 75mm below the main.
• Excavating of service jointing bays.
Energetics will lay gas mains in position in the pre-excavated trenches in accordance with the SWUK guidelines as shown in the following diagram:
Open Trench Gas Mains
NOTE: Gas mains laid in the roadway must be installed at a depth of 750mm of cover to the finished surface level.
© Energetics 2018 20
Part 2: Gas
Open Trench Gas Mains
Unless specified otherwise in their contracts, the Site Developer is responsible for:
• Excavating and backfilling trenches to provide the required depth.
• Providing the required depth of cover to the top of the pipe and adequate fine bedding and main surround.
• Fully surrounding and covering the gas main with a minimum of 150mm of fine fill material above the crown of the main.
• Excavating of service jointing bays.
Energetics will lay gas mains in position in the pre-excavated trenches in accordance with the NJUG guidelines as shown in the diagram below:
Note: Gas mains laid in the roadway must be installed at a depth of 750mm of cover to the finished surface level.
7
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
The Site Developer must:
• Ensure that where large diameter pipes and cables are laid, and/or where the footway or services corridor is less than 2m wide, then cross sectional spatial proposals must be agreed between Energetics and the Site Developer prior to construction starting.
• Maintain a minimum distance from to other plant of 250mm.
• Install the outside kerb log/brace and define the inner kerb line before Energetics start work on site.
As 3BE098
EG
G
E
E
G
270
3
272
276
The
31
268270A
266A
4
1
29
Sutton Mill
Artill
ery
Hous
e
Works
5
3
Arsenal
48
13
GUN
CO L
ANE
1
54
Cromet House
2
SNOW HILL
82
LANE
21
7
24
Wor
ks
13
27
3
43
6
8
11
BYRON'S
36
88
2
SLAC
K ST
MEE S
TREE
T
26
15
54
9450
52
55
63
65
64
E G
E
G
E
G
E
G
E
GAS
E
G
E
G
E
G
E G
E G
E G
E G
E
G
E
G
E
G
E
G
E
G
E
E
G
1 2 3
45
76
89
10
11 12
13 14
16
02
71 18 19
35
23
34
31
36
33
43
44
45
46
47
48
51
53
57
16
26
66
67
68
70
69
17
2773
7476
75
77
78
7908
81
2883
8485
86
E G
EG
E
G
E G
E G
E G
3BE098
3BE0
98
3RU0813R
U081
3PI078
3RU081
3BE098
4OA115
3RU0
813R
U081
3CH0
73
3RU081
3RU0813RU081
3RU0813RU081
3PI0
78
3CH0
73
3LA094
3BE098
4OA115
3RU081
3RU0
813R
U081
4OA115
As
As
AsOpp
Opp
As
As
As
As
As
As
Opp
As
AsOpp
AsOpp
As
Opp
Opp
As
As
AsO
pp
Opp
E
G
Opp4OA115
E
G
3WE1
03Op
p
E
G
Opp4OA
115
E
G
Opp4OA115
E
G
3LA094 Op
p
E
G
Opp4OA115
EG
3WE103
As
EG
3WE103
Opp
E
G
E
G
3WE1
03O
pp
Opp
E G
E G
AsO
ppE G
E G
3RU0
813R
U081
3BE0
98 A
LT3B
E098
ALT
As3BE098
E
G
E
G
3RU0813RU081
As
Opp
E
G
22
27
2425
2326
21
2829
30
E
G
E
3RU081Opp
3PI078
As
E
G
E
G
3LA094 Op
p
E
G
4OA115Opp
56
58
5960
87
E
G
3WE103
Opp
G
E
3WE103 As
As4OA1
15
38
39
41
42
E
G
E
G
EG
E
G
EG
EG
EG
EG
EG
EG
As4OA115
E
G
E
G
3RU0813RU081 As
G
E
G
E
4FU126
Opp
3FA116
As
G
E
G
E
4FU126As
3FA116Opp
G
E
4FU1
26
AsGE
E G
Opp3BE0
98
E G E
G
3RU081Opp
E
G
3WE103Opp
3WE103
As
As3BE0
98 A
LT
E
G
E
G
E
G
3WE103
As3LA094
Opp3LA094
As
AsO
pp
E
G
E
G
3RU081As 3RU081Opp
37
40
3FA1
16Op
p
As
G
E
3FA1
16
4FU1
26
Opp
3RU081
E
G
As
88
3RU081Opp
Sub Station
E
G
E
G
EG
EG
EG
EG
4BO140
4BO140
Opp
As4BO
140O
pp
4BO140
As
4BO1404BO140
OppAs
4BO140
4BO140
4BO140
As
4BO140
4BO140
AsO
pp
4BO140
4BO140
Opp
As4BO
1404BO
140
4BO140
Opp
AsO
pp
AsO
pp
E
G
Exist
ing
NG 1
80m
m P
E m
ain
Exist
ing
NG 1
80m
m P
E m
ain
CSEP LOCATION:125mm MDPE LP off existing180mm PE NG main.Branch saddle connection.
125mmMDPE LP
125mm MDPE LP
125m
m M
DPE
LP
125m
m M
DPE
LP12
5mm
MDP
E LP
90m
mM
DPE
LP
90mm MDPE LP
90m
m M
DPE
LP
90mm MDPE LP
63m
m M
DPE
LP
63mm MDPE LP
63mm MDPE LP
63m
m M
DPE
LP
63m
m M
DPE
LP
100m
m
100m
m
100mm2x
100mm
100mm
100mm
100m
m
100m
m
100m
m
100m
m
100mm
100mm
100mm
100mm
100mm100mm
100mm
100mm
100mm
100m
m
100m
m
100m
m
100m
m2x
Exist
ing N
G 18
0mm
PE m
ain
63mm MDPE LP
63m
m M
DPE
LP
100mm
7
6
5
4
3
2
E FDCBA
E FDCBA
8
7
6
5
4
3
2
1
8
1
Dimensions in mm
Carriageway
295
MAINS IN A 2M FOOTPATHRECOMMENDED ARRANGEMENT OF
Elec
lv A
lt po
s'n
Elec
hv
280 170
Elec
lv450
600
standard
Boun
dary
Lamp
295 270
GasC
able
TV
250
600
Wat
er
Tele
com
ms
430260
900
350
1255
2000
15501720
430
960690
Out
side
sto
p va
lve
International HouseStanley BoulevardHamilton International Technology ParkHigh Blantyre G72 0BNTel:01698 404949Fax:01698 404940Email: [email protected]
Network:
Revision: B
Checked by:
Date Checked:
Sheet Size:Scale:
Date Drawn:
Drawn by: R. Adamson
30.03.17
DrawingNumber:
Client:
OS GridReference:
DrawingTitle: GAS LAYOUT
Gas Material Specifications.Materials will be in accordance with industry standards and relateddocuments including: IGE/TD/3 - Distribution Mains. IGE/TD/4 - Gas ServicesPipe and associated fitting will be sourced only from approved supplierswhich comply with the QC procedures and aid material traceability.Polyethylene systems will be manufactured to meet national andinternational specifications, as listed below:Note- PE fittings to operate at 7bar shall be Class C, PE100. Forapplications at or below 2bar, fittings will be Class B, PE80
Polyethylene Pipe GIS/PL2-2 Pipes for use at pressures up to 5.5bar GIS/PL2-8 Pipes for use at pressure up to 7barPolyethylene Fittings GIS/PL2-3 Self anchoring mechanical fittings for polyethylene
pipe for natural gas GIS/PL2-4 Fusion fitting with integral heating elements GIS/PL2-6 Spigot end fittings for elector fusion and / or butt
fusion purposesMains Valves GIS/V7-1 Distribution valves - Metal bodied line valves for use
at pressures up to 16bar and construction valves for use at pressures up to 7bar
GIS/V7-2 Distribution valves - plastic bodied line valves of sizes up to and including 180mm MDPE suitable for operation at pressures not exceeding 5.5bar
Service Valves GIS/V4 Service isolation valves up to 50mm diameter for use
up to 7bar maximum working pressureExcess Flow Valves GIS/EFV1 Specification for flow limiters for Polyethylene services
operating at a pressure above 75mbar and not exceeding 2bar and for gas flow not exceeding 6m3/hr
Emergency Control Valves (Meter Control Valves) GIS/V7-3 Brass Valves and associated fittings for pressures not
exceeding 5barDomestic Gas Meters & Associated Fitting BS 746 Specification for gas meter unions and adaptors BS EN 1359:1999 Gas meters diaphragm meters BS EN 10380 Pipework - corrugated metal hoses and hoseassemblies
N
Location of existing National Grid Gas Mains as shown is indicative only. Pleaserefer to NG Maps for guidance on exact location of mains or contact National GridPlant Protection Team (Tel: 01604 815 361 / 0800 688588) or e-mail at'[email protected]' prior to the commencement of any excavationworks. Hand dig only in the immediate vicinity of the National Grid Gas Mainusing safe digging practices, in accordance with HS (G) 47 Guidelines.
All single domestic services to be 32mm MDPE.
All unibox gas meter boxes to be located in an accessible area. The installation areamust be such that the meter boxes do not cause a trip hazard, are not susceptible todamage or covered by vegetation.
Where meter boxes are installed in groups such as for flatted properties then eachmeter box must be clearly and permanently marked with the address which it serves.
Dumb meters to be installed by Energetics.
125 & 180mm 225mm
315mm250mm
450mm350mm
GAS PIPE EXT. DIAMETER
32mm & less
90mm63mm
100mm
150mm100mm
DUCT MIN. INT. DIAMETER
All ducting used on site to facilitate gas mainroad crossings and gas services must conform toBritish Standard BS 4962, be of yellow perforatedconstruction, be surrounded by 75mm ofsand/fine-fill, and have “Gas” marker tape laid100mm directly above it. Polyethylene (PE) gas,water or cable pipe must not be used as a duct.A draw cord should always be inserted.
PROPOSED LP MAINS
PROPOSED MP MAINS
CAP END
DIAMETER CHANGE
PROPOSED IP MAINS
VALVE
GAS METERBOX / KIOSK
PRESSURE REDUCTIONINSTALLATION (P.R.I)
GAS RISER
GAS METER
GAS KEY
90mm 63mm
M
EXISTING/AS LAID LP MAINS
EXISTING/AS LAID MP MAINS
EXISTING/AS LAID IP MAINS
PIPE TO BE DECOMMISSIONED
PROPOSED LP SERVICE
PROPOSED MP SERVICE
DECOMMISSIONED PIPE X X X X
EXISTING/AS LAID LP SERVICE
EXISTING/AS LAID MP SERVICE
CPCATHODIC PROTECTION
MEDIUM PRESSURE SERVICEEXCESS FLOW VALVE
PPRESSURE PROTECTIONPRIDER PURGE POINT
PLOTS WITH CONNECTIONSOFF OTHER GT/ EXISTING GASNETWORKS
EXISTING HP MAINS
Rev Revision Details By Date
A Preliminary design 07.03.17GM/RA
B
C
D
E
F
G
H
G. McCaig
1:500 A1
30.03.17
10355_300_Gunco Lane, Macclesfield_1 of 1
10355_Gunco Lane, Macclesfield
392181 / 372602
Bellway Homes (Manchester)
Main added at side ofplot 10
30.03.17GM/RA
DESIGN
Date - 00.00.00
APPROVED BY
• Ensure ground levels are within + 150mm or – 150mm of the finished levels before Energetics start work.
• Place gas warning marker tapes 150mm to 250 mm directly above the main at the time of backfilling.
• Complete backfilling of the trench before any pressure testing or commissioning of the gas mains takes place.
The diagram below shows an example of a design approved gas drawing:
DESIGN
Date - 00.00.00
APPROVED BY DESIGN NOTAPPROVED
DESIGN
Date - 00.00.00
APPROVED BY DESIGN NOTAPPROVED
Open Trench Gas Mains
GasUtility Installation Guide
8
• That the gas main ducts are laid at the appropriate depths.
The following diagram shows a typical main’s crossing layout. It gives the depths at which the different utility ducts must be laid.
The Site Developer must ensure that for all road crossings:
• That an approved type of utility ducting is provided for gas mains (BS 4962).
• That ducting for gas mains road crossings is of the correct colour, material and laid at the correct depth and location.
Gas Mains Ducting
All ducts must have fine fill material 75mm above and below.
It is the Site Developer’s responsibility to ensure that the depths shown above are maintained.
The Site Developer must also position Gas Marker Warning Tape between 150mm to a maximum of 250mm directly above the gas main ducts.
900m
m
750m
m
700m
m
600m
m
Water
250mm 250mm 250mm
GasElecHV
ElecLV
Blue Duct
YellowDuct
Duct Marked ‘Electricity’
Typical Mains Crossings LayoutAll ducts to have �ne �ll material
75mm above and below
Ground Level
9
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
The following table provides details of the internal diameters required for the ducting for each size of gas pipe:
Minimum Mains Ducting Sizes
As 3BE098
EG
G
E
E
G
270
3
272
276
The
31
268270A
266A
4
1
29
Sutton Mill
Artil
lery
Hou
se
Works
5
3
Arsenal
48
13
GU
NC
O L
ANE
1
54
Cromet House
2
SNOW HILL
82
LANE
21
7
24
Wor
ks
13
27
3
43
6
8
11
BYRON'S
36
88
2
SLAC
K ST
MEE S
TREE
T
26
51
45
4950
52
55
63
65
64
E G
E
G
E
G
E
G
E
GAS
E
G
E
G
E
G
E G
E G
E G
E G
E
G
E
G
E
G
E
G
E
G
E
E
G
1 2 3
45
76
89
10
11 12
31 14
16
20
17 81
19
35
32
34
13
36
33
34
44
54
64
47
48
51
53
75
61
62
66
67
86
70
69
71
7273
7476
75
77
78
7980
81
8283
8458
86
E G
EG
E
G
E G
E G
E G
3BE098
3BE0
98
3RU0813R
U081
3PI078
3RU081
3BE098
4OA115
3RU
0813
RU08
1
3CH
073
3RU081
3RU0813RU081
3RU0813RU081
3PI0
78
3CH
073
3LA094
3BE098
4OA115
3RU081
3RU
081
3RU
081
4OA115
As
As
AsOpp
Opp
As
As
As
As
As
As
Opp
As
AsOpp
AsOpp
AsOpp
Opp
As
As
AsO
pp
Opp
E
G
Opp4OA115
E
G
3WE1
03O
pp
E
G
Opp4OA
115
E
G
Opp4OA115
E
G
3LA094 Op
p
E
G
Opp4OA115
EG
3WE103
As
EG
3WE103
Opp
E
G
E
G
3WE1
03O
pp
Opp
E G
E G
AsO
ppE G
E G
3RU
0813
RU08
13B
E098
ALT
3BE0
98 A
LT
As3BE098
E
G
E
G
3RU0813RU081
As
Opp
E
G
22
72
2425
2362
12
2829
30
E
G
E
3RU081O
pp
3PI078
As
E
G
E
G
3LA094 Op
p
E
G
4OA115Opp
56
58
5960
87
E
G
3WE103
Opp
G
E
3WE103 As
As4OA
115
83
93
41
42
E
G
E
G
EG
E
G
EG
E
G
EG
E
G
EG
E
G
As4OA115
E
G
E
G
3RU0813RU081 As
G
E
G
E
4FU126
Opp
3FA116
As
G
E
G
E
4FU126As
3FA116Opp
G
E
4FU1
26
AsGE
E G
Opp3BE0
98
E G E
G
3RU081Opp
E
G
3WE103Opp
3WE103
As
As3BE
098
ALT
E
G
E
G
E
G
3WE103
As3LA094
Opp
3LA094As
AsO
pp
E
G
E
G
3RU081As 3RU081Opp
37
40
3FA1
16O
pp
As
G
E
3FA1
16
4FU1
26
Opp
3RU081
E
G
As
88
3RU081O
pp
Sub Station
E
G
E
G
EG
EG
EG
E
G
4BO140
4BO140
Opp
As4BO
140O
pp
4BO140
As
4BO140
4BO140
Opp
As
4BO140
4BO140
4BO140
As
4BO140
4BO140
AsO
pp
4BO140
4BO140
Opp
As4BO
1404BO
140
4BO140
Opp
AsO
pp
AsO
pp
E
G
3x150mm
100m
m
100m
m
100m
m
100mm
100mm
100mm
100mm
100mm
100mm
100m
m
100m
m
100m
m
100m
m
100mm
100mm
100mm
100mm
100mm
100mm
100m
m
100m
m
100mm
100mm
100mm
100mm
100m
m
100m
m
100mm
100mm
100mm
100mm
100mm
100mm
100mm
100m
m
100mm
100mm
100mm
100mm
100mm
100mm
100m
m
100m
m
100m
m
100mm
100mm
100mm
100mm
100mm
100mm
100mm
100mm 1
00m
m10
0mm
100m
m
100m
m
100m
m
100m
m
100m
m
2x150mm
100mm
100mm
100m
m10
0mm
100m
m10
0mm
100mm100mm
100mm
100m
m
100m
m
100m
m
100m
m
100m
m
100m
m
100m
m
100m
m
100m
m
100mm
7
6
5
4
3
2
E FDCBA
E FDCBA
8
7
6
5
4
3
2
1
8
1
GAS DUCT
WATER DUCT
MU / DUCT KEYELECTRIC LV DUCT
ELECTRIC HV DUCT
MU ROUTE
TELECOMMS DUCT
CABLE DUCT
900m
m
750m
m
700m
m
600m
m
WATER
250mm 250mm 250mm
GASELEC
HV
ELECLV
BLUEDUCT
YELLOWDUCT
DUCT MARKED 'ELECTRICITY'
600m
m
600m
m
GAS ELEC
250mm750
mm
250mm
WATER100mmBLUEDUCT
100mmYELLOW
DUCT
100mm DUCTMARKED 'ELECTRICITY'
Ground Level
Ground Level
125 & 180mm 225mm
315mm250mm
450mm350mm
GAS PIPE EXT. DIAMETER
32mm & less
90mm63mm
100mm
150mm100mm
DUCT MIN. INT. DIAMETER
International HouseStanley BoulevardHamilton International Technology ParkHigh Blantyre G72 0BNTel:01698 404949Fax:01698 404940Email: [email protected]
Network:
Revision: B
Approved by:
Date Approved:
Sheet Size:Scale:
Date Drawn:
Drawn by: R. Adamson
30.03.17
DrawingNumber:
Client:
OS GridReference:
DrawingTitle: MU ROUTE AND DUCT LAYOUT
N
Gas Notes
1. Only one service is permitted with in a gasservice duct.
2. All Gas ducts to be perforated.
Gas & water ducts to comply with BS4692:1989Electric ducts to comply with ESISPECIFICATION 12-24
Recommended supplier for ducts-
Scotland NorthWestFusion Provida Fusion ProvidaDeans Ind Est Unit 9Livingstone Fishwicks Ind EstEH54 8AH Kilbuck Lane
St Helens Merseyside WA11 9SZ
G. McCaig
1:500 A1
30.03.17
10355_600_Gunco Lane, Macclesfield_1 of 1
10355_Gunco Lane, Macclesfield
392181 / 372602
Bellway Homes (Manchester)
Rev Revision Details By Date
A Preliminary design 09.03.17GM/RA
B
C
D
E
F
G
H
Plot 10 - Gas: Mains routerevised and duct added 30.03.17GM/RA
Typical Mains Crossings LayoutAll ducts to have �ne �ll material
75mm above and below
Typical Mains Crossings LayoutAll ducts to have �ne �ll material
75mm above and below
Ducting layouts may be shown on a specific gas layout drawing. In the case of multi-utility projects, a combined layout drawing may be provided by the Site Developer. An example of a multi-utility duct layout drawing is shown below:
Ducting Layouts
External diameter Internal diameter of gas main of ducting
63mm 100mm
90mm 150mm
125mm 200mm
180mm and 250mm 225mm and 300mm
315mm 400mm
Gas Mains Ducting
90mm 63mm
M
X X X X
CP
P
P
Pressure ReductionInstallation (P.R.I)
Gas Key
Medium Pressure ServiceExcess Flow Valve
Pressure Protection
Rider Purge Point
Plots With ConnectionsOff Other GT/ Existing Gas Networks
Proposed MP Mains
Proposed LP Mains
Cap End
Diameter Change
Proposed LP Mains
Valve
Gas Meterbox / Kiosk
Gas Riser
Gas Meter
Existing/as Laid LP Mains
Existing/as Laid MP Mains
Existing/as Laid LP Mains
Pipe to be Decommissioned
Proposed LP Service
Proposed MP Service
Decommissioned Pipe
Existing/as Laid MP Service
Existing/as Laid LP Service
Cathodic Protection
Existing HP Mains
GasUtility Installation Guide
10
It is the Site Developer’s responsibility to ensure:
• That an approved type of utility ducting is provided for gas services (BS 4962). The duct must be yellow and perforated along its entire length.
• That the line and depth of the gas service ducts are installed perpendicular to the property and to the main as per the approved design drawing and the latest version of IGEM/TD/4. The gas service ducts must be 250mm away from other utility services.
The following points are also important:
• In private ground the duct shall be laid to a finished depth of cover of 450mm. This applies over the length of the service, increasing to a minimum of 500mm of cover for the final 2m length at the meter box end. It is the Site Developer’s responsibility to ensure that these are maintained.
• Gas Marker Warning Tape must be positioned by the Site Developer 100mm directly above all gas service ducting.
Gas Services Ducting
Note: Only one service is permitted within a gas service duct.
7072
7366
7168
6774
69
103
104
105
106
107
108
109
110
111
G E
G E
EG
EG
E G
E G
G E
GE
GE
GE
GE
G E
G E
G E
GE
GE
100mm
100mm
100mm
100mm
100mm
100mm
100mm
100mm
125m
m M
DPE
The drawing below shows a typical duct drawing for gas services:
11
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
All ducts to have fine filling material 75mm above and below them.
Where the external diameter of the service pipe is 32mm, the internal diameter of the duct carrying must be 100mm.
Minimum Services Ducting Diameter
Different utilities are required to be laid at different depths as set out below. It is the Site Developer’s responsibility to ensure these are maintained. The following diagram summarises these depths:
Depth of Services
When installing external meter boxes to flat properties, the Site Developer must:
• Install gas meter boxes no closer than 150mm from cavity wall air bricks.
• Fit lids to the meter boxes when they are installed.
• Clearly identify flatted properties at the meter box before they are installed.
Flatted Properties - External Meter Boxes
Examples of ground level external meter boxes are shown below:
Gas Services Ducting
900m
m
750m
m
700m
m
600m
m
Water
250mm 250mm 250mm
GasElecHV
ElecLV
Blue Duct
YellowDuct
Duct Marked ‘Electricity’
Typical Mains Crossings LayoutAll ducts to have �ne �ll material
75mm above and below
Ground Level
GasUtility Installation Guide
12
Note: Energetics will not fit meters until the internal pipework is completed, the construction of the meter compartment finished, the required ventilation
provided and an appropriate lockable door has been installed.
Flatted Properties - Meter Banks and Compartments
Flatted properties often have meter banks located in meter rooms. An example of this is shown below:
For flatted properties, it is the Site Developer’s responsibility to:
• Ensure that the residents have 24/7 access to the meter room. This includes the provision of keys and access codes where applicable.
• Ensure that all pipework from the meter to the individual property is installed and labelled to identify the flat number prior to meters being fitted and commissioned.
• Provide a statement confirming the integrity of the building should there be a fire or explosion at or within the meter room.
• Provide adequate ventilation for the meter rooms.
13
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
No of external walls
Minimum area of free ventilation required as a % of the compartment floor area
Type of natural ventilation required to the outside
Position of low level vents
Position of high level vents
1 3%Louvered door or high and low level indicators
150mm above the floor
2 2%High and low level ventilators
150mm above the floor
3 2%High and low level ventilators
150mm above the floor
4 2%High and low level ventilators
150mm above the floor
As close as possible below, but no more than 10% of the total compartment height below, the roof or ceiling level
It is the Site Developer’s responsibility to ensure that ventilation is provided for the meter rooms. They must:
• Completely seal the meter room from any other part of the building.
• Provide meter rooms with a minimum ventilation of 2% of the nominal floor area when the ventilation is on two or more walls. If the ventilation is only on one wall, this increases to 3% of the nominal floor area.
Ventilation of Meter Room
• The ventilation shall be natural to the outside air and be evenly distributed at high and low levels.
See the table below for meter compartment ventilation requirements:
Flatted Properties - External Steel and PE Risers
GasUtility Installation Guide
14
Flatted Properties - External Steel and PE Risers
The photographs below show examples of an external PE Riser System for flatted properties:
The cross-section diagram below shows an example of an external steel or PR riser installation to a conventional build:
LATERAL ISOLATION VALVEOPTIONAL ISOLATION VALVE
OR BUILDING ENTRY TEE WITHINTEGRAL VALVE
VIEW A
FLAT
FLAT
FLAT
ECV
ECV
ECV
VIEW A
INSOLATION JOINT
GROUND LEVEL
ACCESS CHAMBER PIV
15
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
It is the Site Developer’s responsibility to:
• Provide a suitable safe access platform for the installation of all external gas riser works.
• Provide suitable sleeved core drillings for the installation of the lateral entries to the individual properties. The diagrams below show fire stopping and sleeving lateral gas pipes passing between walls or fire compartments.
• Risers supplying timber frame flatted properties must terminate immediately on the inside of the timber frame wall. They should not extend vertically or horizontally in the building. Site Developers must ensure meter location caters for this requirement.
• Ensure that pipes supplying timber frame flatted properties do not pierce through any other fitment or fitting within the timber frame structure. This includes items such as meter boards, kitchen units, fitted cupboards, etc.
Single Skin Walls
10mm
10mm10mm
Conventional Cavity Walls
10mm
10mm10mm
• Ensure that site staff do not fix risers, laterals and gas pipes supplying timber frame flatted properties to the timber frame under any circumstances.
• Prevent other utilities being attached to any part of the gas network.
The diagram below shows the fire stopping and sleeving lateral gas pipes passing between walls in a timber framed property. Note the need to make adequate allowance for internal movement due to shrinkage of the timber frame wall:
Flatted Properties - External Steel and PE Risers
View AView A
Anticipated PositionAfter Movement
Original Position ofPipe Entry
Make Adequate Allowance For InternalMovement Due To Shrinkage Of The Timber
Frame Wall Cover Plate To Be Provided
Part 2: Gas
© Energetics 2018 31
The photo below shows a gator installed on the inside of the lateral entry:
The photo below shows a gator installed on the inside of the lateral entry:
The diagram below shows the fire stopping and sleeving lateral gas pipes passing between walls in a timber framed property. Note the need to make adequate allowance for internal movement due to shrinkage of the timber frame wall:
GasUtility Installation Guide
16
Cross Sectional Area of Duct (m2) Equivalent Duct Dimensions
Minimum Free Area of Each Opening (m2) Equivalent Opening Diameter
≤0.01 ≤100mm x 100mm 0.002 50mm
>0.01 >100mm x 100mm≤0.375 ≤600mm x 600mm
0.0075 100mm
>0.375 >600mm x 600mm≤7.5 ≤2.7m x 2.7m
0.05 250mm
>7.5 >2.7m x 2.7m 1/150th of Cross Sectional Area of the Duct Dependent on the Cross Sectional Area of the Duct
For flatted properties, for internal gas risers, the Site Developer must:
• Provide half-hour fire resistant ducts/shafts. These must be constructed to BS 8313 standards.
• Ensure ducts have sufficient dimensions to accommodate initial construction and provide suitable access for ongoing maintenance.
• Ensure that all ducts are fitted with removable/replaceable access panels, which gives maintenance access to the riser.
Flatted Properties - Internal Risers
Services in ducts are specified in BS 8313:1997
The table below shows the minimum duct ventilation requirements for a full height internal gas riser:
Note: Energetics will make inspections of the ducting prior to installing any gas riser and on completion of the duct installation. This is to ensure
that the ducting and ventilation meets the standards required.
Duct Detail Ventilation Opening Details
The Site Developer must comply with:
• IGEM/G/5.
• Last Mile Asset Management policy for Multi-Occupancy buildings.
General Statement
• With the requirements of Last Mile Gas Ltd Gas In Flats procedures GIF1,2,3.
• Use a suitable material for the access panels such as ‘Superlux’. A suitable material helps the access panels to be removed and replaced without affecting the quality of the ventilation.
• Ensure that the riser ducts are permanently ventilated directly to the atmosphere. This must be done either:
- at the top and bottom
-or-
- at the top and bottom of each floor where fire stopped.
17
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
The following diagram shows an example of an external wall vent:
If the duct is not continuous, it must be ventilated at the top and bottom of each section. Between floors, the ends must be sealed so that the fire resistance of the property is not impaired.
External Wall Vent
The following diagrams show fire stopping and sleeving gas risers passing between floors or fire compartments:
Gas Risers Passing Between Floors or Fire Compartments
Fixing Screws
Ventilator
Spacer
Position of ductin external wallventilating directto outside air
NOTE:The overall dimensions of the ventilation are typically much larger thanthe ventilation duct and therefore will require spacers to be fitted toensure the full area of ventilation is used as demonstrated by thefollowing diagram.
Section of duct cut �ushwith wall
Fixing Screws
Ventilator
Spacer
Position of ductin external wallventilating directto outside air
NOTE:The overall dimensions of the ventilation are typically much larger thanthe ventilation duct and therefore will require spacers to be fitted toensure the full area of ventilation is used as demonstrated by thefollowing diagram.
Section of duct cut �ushwith wall
Flatted Properties - Internal Risers
GasUtility Installation Guide
18
Flatted Property - Internal Pipeline Isolation Valve
The Site Developer must ensure that Isolation Valves located within the building have unrestricted access for Emergency Services to isolate the gas supply.
The next diagram shows fire stopping and sleeving lateral gas pipes as they pass between walls or fire compartments.
Both Single Skin Walls and Cavity Walls are demonstrated:
Single Skin Walls
10mm
10mm10mm
Conventional Cavity Walls
10mm
10mm10mm
Single Skin Walls Cavity Wall
A gas service pipe that supplies an internal or external gas riser must have an external Pipeline Isolation Valve (PIV) fitted. The following points are important:
• These should be fitted 5-10 metres from the building.
• The Site Developer must ensure PIV are located in the footway, not within an area that may be planted with shrubbery or where vehicles are likely to park.
Part 2: Gas
© Energetics 2018 35
Flatted Property – External Pipeline Isolation Valve
A gas service pipe that supplies an internal or external gas riser must have an external Pipeline Isolation Valve (PIV) fitted. The following points are important:
• These are normally fitted 5-10 metres from the building.
• The Site Developer must ensure these are located in the footway, not within an area that may be planted with shrubbery or where vehicles are likely to park.
• The Site Developer must ensure a gas surface box is installed to permit future access to the valve. This box must be installed as part of the permanent reinstatement. Clear access to the top of the valve must be maintained and be clear of all debris.
The diagrams below show the requirements for the gas surface box fitted during the permanent reinstatement.
600m
m C
ove
r Fo
otp
ath/
45
0mm
Co
ver
Pri
vate
Gas Valve Box Cover marked with ‘G’ or GAS to be fitted as part of permanent reinstatement
Access box/pit to be supplied by Developer prior to permanent reinstatement
• The Site Developer must ensure a gas surface box is installed to permit future access to the valve. This box must be installed as part of the permanent reinstatement. Clear access to the top of the valve must be maintained and be clear of all debris.
The diagram below show the requirements for the gas surface box fitted during the permanent reinstatement.
External Pipeline Isolation Valve
19
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
Gas Meters
Where a gas meter is to be installed within an internal cupboard, the Site Developer must ensure:
• That a minimum installation area of 500mm (H) x 500mm (W) x 300mm (D) is maintained.
• That the gas meter is not located below or within 40mm of the electrical distribution board.
• That the gas meters and associated fittings are installed with a minimum separation distance of 150mm from any electrical meters and 25mm from any electrical cable.
Meter Point Reference Number
Information required for flatted properties where meter is installed in a meter bank
Service Information Label
The Site Developer must ensure that meters or their labels are not removed, damaged or exchanged to another property once they have been installed.
Each meter supply point has a Service Information Label attached at the Emergency Control Valve. The label contains a Meter Point Reference Number (MPRN) which is a unique number allocated to each plot. Energetics supply and install these labels.
If the meter is located in a communal meter bank, the Site Developer must ensure that the flat number which the meter supplies is clearly identified and marked at the meter position for the plot. This is recorded on the Service Information Label when the label is installed.
Shown here is an example of a Service Information Label:
Energetics will not fit meters until the associated installation pipe work has been completed and it is clearly and permanently labelled by the developer to identify the property that it supplies.
• Where internal cupboards containing gas meters, open onto a means of escape from the property, the cupboards must have a minimum ½ hour fire rating with a self-closing door.
GasUtility Installation Guide
20
Damage to Meter Installations
Part 2: Gas
© Energetics 2018 37
Damage to Meter Installations
The flexible connection pipe connecting the outlet of the Emergency Control Valve to the meter installation is made out of corrugated stainless steel.
Some solder fluxes, used on copper joints, are particularly corrosive to stainless steel. They can quickly cause corrosion in the form of pin holes.
The Site Developer must ensure that any flux spillage on the flexible stainless steel meter connectors and other parts of the meter installation is immediately cleaned and rinsed off to avoid potential corrosion and the risk of leaking gas.
The image below shows damage to a flexible connection pipe:
The following points are also important to prevent damage to the meter connections:
• Commercially available washing up liquids also contain substances that are potentially corrosive. Washing up liquid or similar soap solutions should not be used as a Leak Detection Fluid (LDF).
• The Site Developer must ensure that any LDF is completely wiped off after the tightness testing of the installation pipework has been completed.
• The Site Developer must also ensure that when their Gas Engineer tests and commissions the gas installation pipework, they do not over-tighten the meter test nipple as this will permanently damage the gas meter. The image below shows damage to a meter test nipple.
Part 2: Gas
© Energetics 2018 37
Damage to Meter Installations
The flexible connection pipe connecting the outlet of the Emergency Control Valve to the meter installation is made out of corrugated stainless steel.
Some solder fluxes, used on copper joints, are particularly corrosive to stainless steel. They can quickly cause corrosion in the form of pin holes.
The Site Developer must ensure that any flux spillage on the flexible stainless steel meter connectors and other parts of the meter installation is immediately cleaned and rinsed off to avoid potential corrosion and the risk of leaking gas.
The image below shows damage to a flexible connection pipe:
The following points are also important to prevent damage to the meter connections:
• Commercially available washing up liquids also contain substances that are potentially corrosive. Washing up liquid or similar soap solutions should not be used as a Leak Detection Fluid (LDF).
• The Site Developer must ensure that any LDF is completely wiped off after the tightness testing of the installation pipework has been completed.
• The Site Developer must also ensure that when their Gas Engineer tests and commissions the gas installation pipework, they do not over-tighten the meter test nipple as this will permanently damage the gas meter. The image below shows damage to a meter test nipple.
If you smell gas or are concerned about gas safety on site, phone the 24 hours National Gas Emergency Number on 0800 111 999.
The Site Developer must ensure that any flux spillage on the flexible stainless steel meter connectors and other parts of the meter installation is immediately cleaned
and rinsed off to avoid potential corrosion and the risk of leaking gas.
The flexible connection pipe connecting the outlet of the Emergency Control Valve to the meter installation is made out of corrugated stainless steel.
The Site Developer must ensure that any flux spillage on the flexible stainless steel meter connectors and other parts of the meter installation is immediately cleaned and rinsed off to avoid potential corrosion and the risk of leaking gas.
Some solder fluxes, used on copper joints, are particularly corrosive to stainless steel. They can quickly cause corrosion in the form of pin holes.
The following image shows damage to a flexible connection pipe:
The following points are also important to prevent damage to the meter connections:
• Commercially available washing up liquids also contain substances that are potentially corrosive. Washing up liquid or similar soap solutions must not be used as a Leak Detection Fluid (LDF).
• The Site Developer must ensure that any LDF is completely wiped off after the tightness testing of the installation pipework has been completed.
• The Site Developer must also ensure that when their Gas Engineer tests and commissions the gas installation pipework, they do not over-tighten the meter test nipple as this will permanently damage the gas meter. The image below shows damage to a meter test nipple.
Any costs associated with remedial works are passed directly on to the Site Developer.
Gas Meters
21
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
Inlet Outlet
Front
Parking Bay
Pressure Regulating Installations (PRIs) - Above Ground
The position of the PRI must be agreed with Energetics at the design stage and not subsequently altered without Energetics written agreement.
The Site Developer must ensure:
• That the PRI is sited at least 3 metres from any building or ignition source.
• That the PRI is located in a place where maintenance teams are able to access and egress from, and work in vicinity of, the PRI. This is particularly important in the event of emergency works.
Location
Note: The sizes are determined by the dimensions of the PRI.
• That a parking space is provided for the maintenance team vehicle where identified on the approved design drawing.
The diagram below shows an example layout for a PRI:
GasUtility Installation Guide
22
Front
Plan
Elevation
Side Elevation
Isometric View
Front
Plan
Elevation
Side Elevation
Isometric View
Front
Plan
Elevation
Side Elevation
Isometric View
The Site Developer must ensure:
• The concrete base for the PRI is adequately sized:
- The concrete base dimensions will be 300mm greater than the external dimensions of the kiosk, though this may be less for smaller sites with Energetics agreement.
- The base thickness will be a minimum of 200mm, with consideration for the installation of reinforcement. Energetics may specify a smaller base for smaller sites.
- That the base has a 45-degree chamfer around the perimeter of the base.
- That the base is installed on a compacted sub-base layer of MOT Type 1, to a minimum 200mm depth.
• That the minimum specification of concrete used is c30.
Construction
The sizes are determined by the dimensions of the PRI.
Prior to commissioning the PRI, Energetics and the Network Operator will conduct an inspection. The purpose of this is to ensure that all work required for the construction and operation of the
PRI is completed. Any outstanding work will result in the PRI not being commissioned.
• When the base has been constructed, it must be protected from the weather. It must be given a 3-day period before installation of the module / housing so that the concrete sets properly.
• That the base has a floated finish.
• When commissioning is finished, the slots must be backfilled with sand and a 50mm layer of C30 concrete to finish the base.
• All shuttering must be removed on completion of works.
• All legal completions must be in place before the PRI is commissioned.
The diagram below shows a typical drawing for a PRI base
Pressure Regulating Installations (PRIs) - Above Ground
23
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
The images below show typical arrangements for PRIs on completion:
Pressure Regulating Installations (PRIs) - Above Ground
GasUtility Installation Guide
24
Pressure Regulating Installations (PRIs) - Below Ground
Location
a vent stack is required forbelow ground installation
surface level
porousmaterial
customer to install adrainage to surface
water drainage system
Twin Stream Installation
Inlet and outlet valves to be installeda minimum of 2m from PRI
InletValve
OutletValve
The position of the PRI must be agreed with Energetics at the design stage and not subsequently altered without Energetics written agreement.
The Site Developer must ensure:
• That the PRI is sited at least 3 metres from any building or ignition source.
• That the PRI is located in a place where maintenance teams are access and egress from, and work in the vicinity of, the PRI. This is particularly important in the event of emergency works.
• That the installation is located away from any carriageway or parking area. For example, the installation could be located in a verge or footpath.
The sizes are determined by the dimensions of the PRI.
• That the PRI is not installed in areas where there is a risk of flooding.
• That the site (and equipment) is located to avoid damage from vandalism or road traffic.
• That the PRI is clear of overhead electricity cables and large trees.
• That there is a suitable location for terminating relief pipework in a 3m high vent stack.
• That a parking space is provided for the maintenance team vehicle where identified on the approved design drawing.
The diagrams below show an example layout for a PRI below ground:
25
GasUtility Installation Guide
© Energetics 2019. Utility Installation Guide: Gas v1.0
The Site Developer must ensure:
• That the concrete base for a PRI is sized adequately for the PRI module in accordance with Energetics’ specifications.
• That the minimum specification of concrete used is C30.
• That on completion of construction of the base, it must be protected from the weather. It must be given a 3-day period before installation of the module / housing so that the concrete sets properly.
• That the base has a floated finish.
Construction
Prior to commissioning the PRI, Energetics and the Network Operator will conduct an inspection. The purpose of this is to ensure that all work required for the construction and operation of the
PRI is completed. Any outstanding work will result in the PRI not being commissioned.
The sizes are determined by the dimensions of the PRI.
• When commissioning is finished, the slots must be backfilled with sand and a 50mm layer of C30 concrete to finish the base.
• All shuttering must be removed on completion of works.
• All legal completions must be in place before the PRI is commissioned.
The diagram below shows an example drawing for a PRI base:
A393 Mesh
Concrete Base
Compacted Type 1Granular Material
Plinth Elevation
Plinth PlanA393 Mesh
Concrete Base
Compacted Type 1Granular Material
Plinth Elevation
Plinth Plan
Pressure Regulating Installations (PRIs) - Below Ground
GasUtility Installation Guide
26
The image below shows a typical arrangement for a below ground PRI on completion:
Pressure Regulating Installations (PRIs) - Below Ground
Energetics Fenick House Lister Way Hamilton International Technology Park Glasgow G72 0FT
TEL: 03300 587 400 www.energetics-uk.com