+ All Categories
Home > Documents > Utility Installation Guide: Gas - Energetics...These are U6 size gas meter with a gas load ≤65kW...

Utility Installation Guide: Gas - Energetics...These are U6 size gas meter with a gas load ≤65kW...

Date post: 31-Jan-2021
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
27
Utility Installation Guide: Gas www.energetics-uk.com Practical Guidance and Contractual Requirements
Transcript
  • Utility Installation Guide:Gas

    www.energetics-uk.com

    Practical Guidance and Contractual Requirements

  • Gas

  • 3

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    Copyright © 2019 an unpublished work by Energetics. All rights reserved.

    Copyright Copyright © 2019 Energetics. All rights reserved. No part of this publication may be reproduced, transcribed, transmitted, stored in a retrieval system or translated into any language, in any form or by any means mechanical, manual, electronic, magnetic, chemical, optical, including photocopying or otherwise without the prior written permission of Energetics.

    Confidentiality This document is the property of Energetics, and is provided on the understanding that its use will be confined to the officers of your company and that no part of its contents will be disclosed to third parties without the prior written consent of Energetics.

    Version History

    Document version Date Description / reason for modifications

    Version 1.0 November 2019 First release of guide

    Printing Control This document is uncontrolled when printed. The electronic version of this document is the approved and most current. Any printed version is uncontrolled and may not be current. Please ensure you are referring to the latest version.

    Acknowledgements Energetics respectfully acknowledges all trademarks, trade names and other unique identification symbols, whether implied or explicit, used within this document.

    Energetics Fenick House Lister Way Hamilton International Technology Park Glasgow G72 0FT

    Tel: 03300 587 400 Web: www.energetics-uk.com

  • GasUtility Installation Guide

    4

    It contains the following sections:

    • Gas Emergencies, gives instructions on what to do in the event of a gas emergency. The emergency number is given and general advice provided.

    • Energetics Responsibilities, explains the role and responsibilities of Energetics during gas utility installations.

    • Open Trench Gas Mains, explains what the Site Developer must do to prepare these, their depths, fine filling and marking them.

    • Gas Mains Ducting, describes the Site Developer’s responsibilities for the depth at which ducts should be positioned, ducting sizes and ducting layouts.

    • Gas Services Ducting, details the responsibilities of the Site Developer for the depths of gas services and the duct diameters.

    • Flatted Properties – External Meter Boxes, gives details of how Site Developers must position and build external meter boxes.

    • Flatted Properties – Meter Banks and Compartments, describes the Site Developer’s responsibilities and describes the ventilation requirements for meter rooms.

    Gas

    This document deals with the installation of gas services.

    • Flatted Properties – External Steel and PE Risers, explains the Site Developer’s tasks for external gas risers in flatted properties.

    • Flatted Properties – Internal Risers, describes how Site Developers must construct internal gas risers and the safety precautions that are needed.

    • Flatted Property – External Pipeline Isolation Valve, explains how this type of isolation valve should be fitted in flatted properties.

    • Gas Meters, describes the steps Site Developers must take when installing gas meters. This includes the dimensions of the meter cupboard, their labelling and steps to take to avoid damaging meters.

    • Pressure Regulating Installations (PRIs) – Above Ground, describes how a PRI must be constructed above ground level, its dimensions and location.

    • Pressure Regulating Installations (PRIs) – Below Ground, explains PRI construction under ground level, steps that should be taken and Site Developer’s responsibilities.

  • 5

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    Your call will be taken by a call centre who will ask for more information. This will include:

    • Your name and phone number.

    • The address and location of the suspected gas escape or gas emergency.

    • Where the smell is most noticeable.

    • How long the smell has been noticeable.

    • Whether any other properties are affected.

    Gas Emergencies

    If you smell gas or are concerned about gas safety on site, phone the 24 Hour National Gas Emergency Number on 0800 111 999 immediately.

    Here is some general advice on what you should do if you suspect a gas escape or gas emergency (but always follow instructions from NGES):

    • If the suspected gas emergency is indoors, open doors and windows to ventilate the property.

    • Unless the smell of gas and the gas meter are located in a cellar or basement, turn off the gas supply at the meter. Do not enter the cellar or basement if the smell of gas is in there.

    • Extinguish all naked flames. If possible remove any sources of ignition and do not smoke.

    General Advice on Gas Emergencies

    • Any special circumstances or access information.

    • If the smell of gas is in or near to a highly populated building.

    Your answers to these questions enable the National Gas Emergency Service (NGES) to send an engineer to the right address. The NGES can now provide you with the right safety advice in the shortest possible time.

    • Do not turn off or turn on any power or light switches.

    • Do not operate any electrical equipment.

    • If the smell of gas is near or in an open excavation, do not enter the excavation.

    • As far as reasonably possible, keep all personnel and members of the public clear from any area where there is a suspected gas escape.

  • GasUtility Installation Guide

    6

    These are detailed below:

    • To lay all gas pipes in trenches pre-excavated or ducted (unless specified otherwise in the contract) by the Site Developer. This will only be done when it is confirmed that these trenches follow the correct route, are to the correct depth and the correct bedding has been provided.

    • Install, test, connect, and commission gas services in ducts previously installed by the Site Developer.

    Energetics Responsibilities

    • Provide recessed meter boxes or universal meter boxes (Uni-box) for installation by the Site Developer. These are U6 size gas meter with a gas load ≤65kW only.

    • Provide a marked up copy of a site drawing showing which gas mains and services are live on site during the construction phase.

    NOTE: Energetics staff will not undertake any work beneath scaffolding.

    Unless specified otherwise in their contract, the Site Developer is responsible for:

    • Excavating and backfilling trenches to provide the required depth.

    • Providing the required depth of cover to the top of the pipe and adequate fine bedding and main surround.

    • Fully surrounding and covering the gas main with a minimum of 150mm of fine fill material above the crown of the main and 75mm below the main.

    • Excavating of service jointing bays.

    Energetics will lay gas mains in position in the pre-excavated trenches in accordance with the SWUK guidelines as shown in the following diagram:

    Open Trench Gas Mains

    NOTE: Gas mains laid in the roadway must be installed at a depth of 750mm of cover to the finished surface level.

    © Energetics 2018 20

    Part 2: Gas

    Open Trench Gas Mains

    Unless specified otherwise in their contracts, the Site Developer is responsible for:

    • Excavating and backfilling trenches to provide the required depth.

    • Providing the required depth of cover to the top of the pipe and adequate fine bedding and main surround.

    • Fully surrounding and covering the gas main with a minimum of 150mm of fine fill material above the crown of the main.

    • Excavating of service jointing bays.

    Energetics will lay gas mains in position in the pre-excavated trenches in accordance with the NJUG guidelines as shown in the diagram below:

    Note: Gas mains laid in the roadway must be installed at a depth of 750mm of cover to the finished surface level.

  • 7

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    The Site Developer must:

    • Ensure that where large diameter pipes and cables are laid, and/or where the footway or services corridor is less than 2m wide, then cross sectional spatial proposals must be agreed between Energetics and the Site Developer prior to construction starting.

    • Maintain a minimum distance from to other plant of 250mm.

    • Install the outside kerb log/brace and define the inner kerb line before Energetics start work on site.

    As 3BE098

    EG

    G

    E

    E

    G

    270

    3

    272

    276

    The

    31

    268270A

    266A

    4

    1

    29

    Sutton Mill

    Artill

    ery

    Hous

    e

    Works

    5

    3

    Arsenal

    48

    13

    GUN

    CO L

    ANE

    1

    54

    Cromet House

    2

    SNOW HILL

    82

    LANE

    21

    7

    24

    Wor

    ks

    13

    27

    3

    43

    6

    8

    11

    BYRON'S

    36

    88

    2

    SLAC

    K ST

    MEE S

    TREE

    T

    26

    15

    54

    9450

    52

    55

    63

    65

    64

    E G

    E

    G

    E

    G

    E

    G

    E

    GAS

    E

    G

    E

    G

    E

    G

    E G

    E G

    E G

    E G

    E

    G

    E

    G

    E

    G

    E

    G

    E

    G

    E

    E

    G

    1 2 3

    45

    76

    89

    10

    11 12

    13 14

    16

    02

    71 18 19

    35

    23

    34

    31

    36

    33

    43

    44

    45

    46

    47

    48

    51

    53

    57

    16

    26

    66

    67

    68

    70

    69

    17

    2773

    7476

    75

    77

    78

    7908

    81

    2883

    8485

    86

    E G

    EG

    E

    G

    E G

    E G

    E G

    3BE098

    3BE0

    98

    3RU0813R

    U081

    3PI078

    3RU081

    3BE098

    4OA115

    3RU0

    813R

    U081

    3CH0

    73

    3RU081

    3RU0813RU081

    3RU0813RU081

    3PI0

    78

    3CH0

    73

    3LA094

    3BE098

    4OA115

    3RU081

    3RU0

    813R

    U081

    4OA115

    As

    As

    AsOpp

    Opp

    As

    As

    As

    As

    As

    As

    Opp

    As

    AsOpp

    AsOpp

    As

    Opp

    Opp

    As

    As

    AsO

    pp

    Opp

    E

    G

    Opp4OA115

    E

    G

    3WE1

    03Op

    p

    E

    G

    Opp4OA

    115

    E

    G

    Opp4OA115

    E

    G

    3LA094 Op

    p

    E

    G

    Opp4OA115

    EG

    3WE103

    As

    EG

    3WE103

    Opp

    E

    G

    E

    G

    3WE1

    03O

    pp

    Opp

    E G

    E G

    AsO

    ppE G

    E G

    3RU0

    813R

    U081

    3BE0

    98 A

    LT3B

    E098

    ALT

    As3BE098

    E

    G

    E

    G

    3RU0813RU081

    As

    Opp

    E

    G

    22

    27

    2425

    2326

    21

    2829

    30

    E

    G

    E

    3RU081Opp

    3PI078

    As

    E

    G

    E

    G

    3LA094 Op

    p

    E

    G

    4OA115Opp

    56

    58

    5960

    87

    E

    G

    3WE103

    Opp

    G

    E

    3WE103 As

    As4OA1

    15

    38

    39

    41

    42

    E

    G

    E

    G

    EG

    E

    G

    EG

    EG

    EG

    EG

    EG

    EG

    As4OA115

    E

    G

    E

    G

    3RU0813RU081 As

    G

    E

    G

    E

    4FU126

    Opp

    3FA116

    As

    G

    E

    G

    E

    4FU126As

    3FA116Opp

    G

    E

    4FU1

    26

    AsGE

    E G

    Opp3BE0

    98

    E G E

    G

    3RU081Opp

    E

    G

    3WE103Opp

    3WE103

    As

    As3BE0

    98 A

    LT

    E

    G

    E

    G

    E

    G

    3WE103

    As3LA094

    Opp3LA094

    As

    AsO

    pp

    E

    G

    E

    G

    3RU081As 3RU081Opp

    37

    40

    3FA1

    16Op

    p

    As

    G

    E

    3FA1

    16

    4FU1

    26

    Opp

    3RU081

    E

    G

    As

    88

    3RU081Opp

    Sub Station

    E

    G

    E

    G

    EG

    EG

    EG

    EG

    4BO140

    4BO140

    Opp

    As4BO

    140O

    pp

    4BO140

    As

    4BO1404BO140

    OppAs

    4BO140

    4BO140

    4BO140

    As

    4BO140

    4BO140

    AsO

    pp

    4BO140

    4BO140

    Opp

    As4BO

    1404BO

    140

    4BO140

    Opp

    AsO

    pp

    AsO

    pp

    E

    G

    Exist

    ing

    NG 1

    80m

    m P

    E m

    ain

    Exist

    ing

    NG 1

    80m

    m P

    E m

    ain

    CSEP LOCATION:125mm MDPE LP off existing180mm PE NG main.Branch saddle connection.

    125mmMDPE LP

    125mm MDPE LP

    125m

    m M

    DPE

    LP

    125m

    m M

    DPE

    LP12

    5mm

    MDP

    E LP

    90m

    mM

    DPE

    LP

    90mm MDPE LP

    90m

    m M

    DPE

    LP

    90mm MDPE LP

    63m

    m M

    DPE

    LP

    63mm MDPE LP

    63mm MDPE LP

    63m

    m M

    DPE

    LP

    63m

    m M

    DPE

    LP

    100m

    m

    100m

    m

    100mm2x

    100mm

    100mm

    100mm

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    100mm

    100mm

    100mm

    100mm

    100mm100mm

    100mm

    100mm

    100mm

    100m

    m

    100m

    m

    100m

    m

    100m

    m2x

    Exist

    ing N

    G 18

    0mm

    PE m

    ain

    63mm MDPE LP

    63m

    m M

    DPE

    LP

    100mm

    7

    6

    5

    4

    3

    2

    E FDCBA

    E FDCBA

    8

    7

    6

    5

    4

    3

    2

    1

    8

    1

    Dimensions in mm

    Carriageway

    295

    MAINS IN A 2M FOOTPATHRECOMMENDED ARRANGEMENT OF

    Elec

    lv A

    lt po

    s'n

    Elec

    hv

    280 170

    Elec

    lv450

    600

    standard

    Boun

    dary

    Lamp

    295 270

    GasC

    able

    TV

    250

    600

    Wat

    er

    Tele

    com

    ms

    430260

    900

    350

    1255

    2000

    15501720

    430

    960690

    Out

    side

    sto

    p va

    lve

    International HouseStanley BoulevardHamilton International Technology ParkHigh Blantyre G72 0BNTel:01698 404949Fax:01698 404940Email: [email protected]

    Network:

    Revision: B

    Checked by:

    Date Checked:

    Sheet Size:Scale:

    Date Drawn:

    Drawn by: R. Adamson

    30.03.17

    DrawingNumber:

    Client:

    OS GridReference:

    DrawingTitle: GAS LAYOUT

    Gas Material Specifications.Materials will be in accordance with industry standards and relateddocuments including: IGE/TD/3 - Distribution Mains. IGE/TD/4 - Gas ServicesPipe and associated fitting will be sourced only from approved supplierswhich comply with the QC procedures and aid material traceability.Polyethylene systems will be manufactured to meet national andinternational specifications, as listed below:Note- PE fittings to operate at 7bar shall be Class C, PE100. Forapplications at or below 2bar, fittings will be Class B, PE80

    Polyethylene Pipe GIS/PL2-2 Pipes for use at pressures up to 5.5bar GIS/PL2-8 Pipes for use at pressure up to 7barPolyethylene Fittings GIS/PL2-3 Self anchoring mechanical fittings for polyethylene

    pipe for natural gas GIS/PL2-4 Fusion fitting with integral heating elements GIS/PL2-6 Spigot end fittings for elector fusion and / or butt

    fusion purposesMains Valves GIS/V7-1 Distribution valves - Metal bodied line valves for use

    at pressures up to 16bar and construction valves for use at pressures up to 7bar

    GIS/V7-2 Distribution valves - plastic bodied line valves of sizes up to and including 180mm MDPE suitable for operation at pressures not exceeding 5.5bar

    Service Valves GIS/V4 Service isolation valves up to 50mm diameter for use

    up to 7bar maximum working pressureExcess Flow Valves GIS/EFV1 Specification for flow limiters for Polyethylene services

    operating at a pressure above 75mbar and not exceeding 2bar and for gas flow not exceeding 6m3/hr

    Emergency Control Valves (Meter Control Valves) GIS/V7-3 Brass Valves and associated fittings for pressures not

    exceeding 5barDomestic Gas Meters & Associated Fitting BS 746 Specification for gas meter unions and adaptors BS EN 1359:1999 Gas meters diaphragm meters BS EN 10380 Pipework - corrugated metal hoses and hoseassemblies

    N

    Location of existing National Grid Gas Mains as shown is indicative only. Pleaserefer to NG Maps for guidance on exact location of mains or contact National GridPlant Protection Team (Tel: 01604 815 361 / 0800 688588) or e-mail at'[email protected]' prior to the commencement of any excavationworks. Hand dig only in the immediate vicinity of the National Grid Gas Mainusing safe digging practices, in accordance with HS (G) 47 Guidelines.

    All single domestic services to be 32mm MDPE.

    All unibox gas meter boxes to be located in an accessible area. The installation areamust be such that the meter boxes do not cause a trip hazard, are not susceptible todamage or covered by vegetation.

    Where meter boxes are installed in groups such as for flatted properties then eachmeter box must be clearly and permanently marked with the address which it serves.

    Dumb meters to be installed by Energetics.

    125 & 180mm 225mm

    315mm250mm

    450mm350mm

    GAS PIPE EXT. DIAMETER

    32mm & less

    90mm63mm

    100mm

    150mm100mm

    DUCT MIN. INT. DIAMETER

    All ducting used on site to facilitate gas mainroad crossings and gas services must conform toBritish Standard BS 4962, be of yellow perforatedconstruction, be surrounded by 75mm ofsand/fine-fill, and have “Gas” marker tape laid100mm directly above it. Polyethylene (PE) gas,water or cable pipe must not be used as a duct.A draw cord should always be inserted.

    PROPOSED LP MAINS

    PROPOSED MP MAINS

    CAP END

    DIAMETER CHANGE

    PROPOSED IP MAINS

    VALVE

    GAS METERBOX / KIOSK

    PRESSURE REDUCTIONINSTALLATION (P.R.I)

    GAS RISER

    GAS METER

    GAS KEY

    90mm 63mm

    M

    EXISTING/AS LAID LP MAINS

    EXISTING/AS LAID MP MAINS

    EXISTING/AS LAID IP MAINS

    PIPE TO BE DECOMMISSIONED

    PROPOSED LP SERVICE

    PROPOSED MP SERVICE

    DECOMMISSIONED PIPE X X X X

    EXISTING/AS LAID LP SERVICE

    EXISTING/AS LAID MP SERVICE

    CPCATHODIC PROTECTION

    MEDIUM PRESSURE SERVICEEXCESS FLOW VALVE

    PPRESSURE PROTECTIONPRIDER PURGE POINT

    PLOTS WITH CONNECTIONSOFF OTHER GT/ EXISTING GASNETWORKS

    EXISTING HP MAINS

    Rev Revision Details By Date

    A Preliminary design 07.03.17GM/RA

    B

    C

    D

    E

    F

    G

    H

    G. McCaig

    1:500 A1

    30.03.17

    10355_300_Gunco Lane, Macclesfield_1 of 1

    10355_Gunco Lane, Macclesfield

    392181 / 372602

    Bellway Homes (Manchester)

    Main added at side ofplot 10

    30.03.17GM/RA

    DESIGN

    Date - 00.00.00

    APPROVED BY

    • Ensure ground levels are within + 150mm or – 150mm of the finished levels before Energetics start work.

    • Place gas warning marker tapes 150mm to 250 mm directly above the main at the time of backfilling.

    • Complete backfilling of the trench before any pressure testing or commissioning of the gas mains takes place.

    The diagram below shows an example of a design approved gas drawing:

    DESIGN

    Date - 00.00.00

    APPROVED BY DESIGN NOTAPPROVED

    DESIGN

    Date - 00.00.00

    APPROVED BY DESIGN NOTAPPROVED

    Open Trench Gas Mains

  • GasUtility Installation Guide

    8

    • That the gas main ducts are laid at the appropriate depths.

    The following diagram shows a typical main’s crossing layout. It gives the depths at which the different utility ducts must be laid.

    The Site Developer must ensure that for all road crossings:

    • That an approved type of utility ducting is provided for gas mains (BS 4962).

    • That ducting for gas mains road crossings is of the correct colour, material and laid at the correct depth and location.

    Gas Mains Ducting

    All ducts must have fine fill material 75mm above and below.

    It is the Site Developer’s responsibility to ensure that the depths shown above are maintained.

    The Site Developer must also position Gas Marker Warning Tape between 150mm to a maximum of 250mm directly above the gas main ducts.

    900m

    m

    750m

    m

    700m

    m

    600m

    m

    Water

    250mm 250mm 250mm

    GasElecHV

    ElecLV

    Blue Duct

    YellowDuct

    Duct Marked ‘Electricity’

    Typical Mains Crossings LayoutAll ducts to have �ne �ll material

    75mm above and below

    Ground Level

  • 9

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    The following table provides details of the internal diameters required for the ducting for each size of gas pipe:

    Minimum Mains Ducting Sizes

    As 3BE098

    EG

    G

    E

    E

    G

    270

    3

    272

    276

    The

    31

    268270A

    266A

    4

    1

    29

    Sutton Mill

    Artil

    lery

    Hou

    se

    Works

    5

    3

    Arsenal

    48

    13

    GU

    NC

    O L

    ANE

    1

    54

    Cromet House

    2

    SNOW HILL

    82

    LANE

    21

    7

    24

    Wor

    ks

    13

    27

    3

    43

    6

    8

    11

    BYRON'S

    36

    88

    2

    SLAC

    K ST

    MEE S

    TREE

    T

    26

    51

    45

    4950

    52

    55

    63

    65

    64

    E G

    E

    G

    E

    G

    E

    G

    E

    GAS

    E

    G

    E

    G

    E

    G

    E G

    E G

    E G

    E G

    E

    G

    E

    G

    E

    G

    E

    G

    E

    G

    E

    E

    G

    1 2 3

    45

    76

    89

    10

    11 12

    31 14

    16

    20

    17 81

    19

    35

    32

    34

    13

    36

    33

    34

    44

    54

    64

    47

    48

    51

    53

    75

    61

    62

    66

    67

    86

    70

    69

    71

    7273

    7476

    75

    77

    78

    7980

    81

    8283

    8458

    86

    E G

    EG

    E

    G

    E G

    E G

    E G

    3BE098

    3BE0

    98

    3RU0813R

    U081

    3PI078

    3RU081

    3BE098

    4OA115

    3RU

    0813

    RU08

    1

    3CH

    073

    3RU081

    3RU0813RU081

    3RU0813RU081

    3PI0

    78

    3CH

    073

    3LA094

    3BE098

    4OA115

    3RU081

    3RU

    081

    3RU

    081

    4OA115

    As

    As

    AsOpp

    Opp

    As

    As

    As

    As

    As

    As

    Opp

    As

    AsOpp

    AsOpp

    AsOpp

    Opp

    As

    As

    AsO

    pp

    Opp

    E

    G

    Opp4OA115

    E

    G

    3WE1

    03O

    pp

    E

    G

    Opp4OA

    115

    E

    G

    Opp4OA115

    E

    G

    3LA094 Op

    p

    E

    G

    Opp4OA115

    EG

    3WE103

    As

    EG

    3WE103

    Opp

    E

    G

    E

    G

    3WE1

    03O

    pp

    Opp

    E G

    E G

    AsO

    ppE G

    E G

    3RU

    0813

    RU08

    13B

    E098

    ALT

    3BE0

    98 A

    LT

    As3BE098

    E

    G

    E

    G

    3RU0813RU081

    As

    Opp

    E

    G

    22

    72

    2425

    2362

    12

    2829

    30

    E

    G

    E

    3RU081O

    pp

    3PI078

    As

    E

    G

    E

    G

    3LA094 Op

    p

    E

    G

    4OA115Opp

    56

    58

    5960

    87

    E

    G

    3WE103

    Opp

    G

    E

    3WE103 As

    As4OA

    115

    83

    93

    41

    42

    E

    G

    E

    G

    EG

    E

    G

    EG

    E

    G

    EG

    E

    G

    EG

    E

    G

    As4OA115

    E

    G

    E

    G

    3RU0813RU081 As

    G

    E

    G

    E

    4FU126

    Opp

    3FA116

    As

    G

    E

    G

    E

    4FU126As

    3FA116Opp

    G

    E

    4FU1

    26

    AsGE

    E G

    Opp3BE0

    98

    E G E

    G

    3RU081Opp

    E

    G

    3WE103Opp

    3WE103

    As

    As3BE

    098

    ALT

    E

    G

    E

    G

    E

    G

    3WE103

    As3LA094

    Opp

    3LA094As

    AsO

    pp

    E

    G

    E

    G

    3RU081As 3RU081Opp

    37

    40

    3FA1

    16O

    pp

    As

    G

    E

    3FA1

    16

    4FU1

    26

    Opp

    3RU081

    E

    G

    As

    88

    3RU081O

    pp

    Sub Station

    E

    G

    E

    G

    EG

    EG

    EG

    E

    G

    4BO140

    4BO140

    Opp

    As4BO

    140O

    pp

    4BO140

    As

    4BO140

    4BO140

    Opp

    As

    4BO140

    4BO140

    4BO140

    As

    4BO140

    4BO140

    AsO

    pp

    4BO140

    4BO140

    Opp

    As4BO

    1404BO

    140

    4BO140

    Opp

    AsO

    pp

    AsO

    pp

    E

    G

    3x150mm

    100m

    m

    100m

    m

    100m

    m

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    100m

    m

    100m

    m

    100mm

    100mm

    100mm

    100mm

    100m

    m

    100m

    m

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    100m

    m

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    100m

    m

    100m

    m

    100m

    m

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm 1

    00m

    m10

    0mm

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    2x150mm

    100mm

    100mm

    100m

    m10

    0mm

    100m

    m10

    0mm

    100mm100mm

    100mm

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    100m

    m

    100mm

    7

    6

    5

    4

    3

    2

    E FDCBA

    E FDCBA

    8

    7

    6

    5

    4

    3

    2

    1

    8

    1

    GAS DUCT

    WATER DUCT

    MU / DUCT KEYELECTRIC LV DUCT

    ELECTRIC HV DUCT

    MU ROUTE

    TELECOMMS DUCT

    CABLE DUCT

    900m

    m

    750m

    m

    700m

    m

    600m

    m

    WATER

    250mm 250mm 250mm

    GASELEC

    HV

    ELECLV

    BLUEDUCT

    YELLOWDUCT

    DUCT MARKED 'ELECTRICITY'

    600m

    m

    600m

    m

    GAS ELEC

    250mm750

    mm

    250mm

    WATER100mmBLUEDUCT

    100mmYELLOW

    DUCT

    100mm DUCTMARKED 'ELECTRICITY'

    Ground Level

    Ground Level

    125 & 180mm 225mm

    315mm250mm

    450mm350mm

    GAS PIPE EXT. DIAMETER

    32mm & less

    90mm63mm

    100mm

    150mm100mm

    DUCT MIN. INT. DIAMETER

    International HouseStanley BoulevardHamilton International Technology ParkHigh Blantyre G72 0BNTel:01698 404949Fax:01698 404940Email: [email protected]

    Network:

    Revision: B

    Approved by:

    Date Approved:

    Sheet Size:Scale:

    Date Drawn:

    Drawn by: R. Adamson

    30.03.17

    DrawingNumber:

    Client:

    OS GridReference:

    DrawingTitle: MU ROUTE AND DUCT LAYOUT

    N

    Gas Notes

    1. Only one service is permitted with in a gasservice duct.

    2. All Gas ducts to be perforated.

    Gas & water ducts to comply with BS4692:1989Electric ducts to comply with ESISPECIFICATION 12-24

    Recommended supplier for ducts-

    Scotland NorthWestFusion Provida Fusion ProvidaDeans Ind Est Unit 9Livingstone Fishwicks Ind EstEH54 8AH Kilbuck Lane

    St Helens Merseyside WA11 9SZ

    G. McCaig

    1:500 A1

    30.03.17

    10355_600_Gunco Lane, Macclesfield_1 of 1

    10355_Gunco Lane, Macclesfield

    392181 / 372602

    Bellway Homes (Manchester)

    Rev Revision Details By Date

    A Preliminary design 09.03.17GM/RA

    B

    C

    D

    E

    F

    G

    H

    Plot 10 - Gas: Mains routerevised and duct added 30.03.17GM/RA

    Typical Mains Crossings LayoutAll ducts to have �ne �ll material

    75mm above and below

    Typical Mains Crossings LayoutAll ducts to have �ne �ll material

    75mm above and below

    Ducting layouts may be shown on a specific gas layout drawing. In the case of multi-utility projects, a combined layout drawing may be provided by the Site Developer. An example of a multi-utility duct layout drawing is shown below:

    Ducting Layouts

    External diameter Internal diameter of gas main of ducting

    63mm 100mm

    90mm 150mm

    125mm 200mm

    180mm and 250mm 225mm and 300mm

    315mm 400mm

    Gas Mains Ducting

    90mm 63mm

    M

    X X X X

    CP

    P

    P

    Pressure ReductionInstallation (P.R.I)

    Gas Key

    Medium Pressure ServiceExcess Flow Valve

    Pressure Protection

    Rider Purge Point

    Plots With ConnectionsOff Other GT/ Existing Gas Networks

    Proposed MP Mains

    Proposed LP Mains

    Cap End

    Diameter Change

    Proposed LP Mains

    Valve

    Gas Meterbox / Kiosk

    Gas Riser

    Gas Meter

    Existing/as Laid LP Mains

    Existing/as Laid MP Mains

    Existing/as Laid LP Mains

    Pipe to be Decommissioned

    Proposed LP Service

    Proposed MP Service

    Decommissioned Pipe

    Existing/as Laid MP Service

    Existing/as Laid LP Service

    Cathodic Protection

    Existing HP Mains

  • GasUtility Installation Guide

    10

    It is the Site Developer’s responsibility to ensure:

    • That an approved type of utility ducting is provided for gas services (BS 4962). The duct must be yellow and perforated along its entire length.

    • That the line and depth of the gas service ducts are installed perpendicular to the property and to the main as per the approved design drawing and the latest version of IGEM/TD/4. The gas service ducts must be 250mm away from other utility services.

    The following points are also important:

    • In private ground the duct shall be laid to a finished depth of cover of 450mm. This applies over the length of the service, increasing to a minimum of 500mm of cover for the final 2m length at the meter box end. It is the Site Developer’s responsibility to ensure that these are maintained.

    • Gas Marker Warning Tape must be positioned by the Site Developer 100mm directly above all gas service ducting.

    Gas Services Ducting

    Note: Only one service is permitted within a gas service duct.

    7072

    7366

    7168

    6774

    69

    103

    104

    105

    106

    107

    108

    109

    110

    111

    G E

    G E

    EG

    EG

    E G

    E G

    G E

    GE

    GE

    GE

    GE

    G E

    G E

    G E

    GE

    GE

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    100mm

    125m

    m M

    DPE

    The drawing below shows a typical duct drawing for gas services:

  • 11

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    All ducts to have fine filling material 75mm above and below them.

    Where the external diameter of the service pipe is 32mm, the internal diameter of the duct carrying must be 100mm.

    Minimum Services Ducting Diameter

    Different utilities are required to be laid at different depths as set out below. It is the Site Developer’s responsibility to ensure these are maintained. The following diagram summarises these depths:

    Depth of Services

    When installing external meter boxes to flat properties, the Site Developer must:

    • Install gas meter boxes no closer than 150mm from cavity wall air bricks.

    • Fit lids to the meter boxes when they are installed.

    • Clearly identify flatted properties at the meter box before they are installed.

    Flatted Properties - External Meter Boxes

    Examples of ground level external meter boxes are shown below:

    Gas Services Ducting

    900m

    m

    750m

    m

    700m

    m

    600m

    m

    Water

    250mm 250mm 250mm

    GasElecHV

    ElecLV

    Blue Duct

    YellowDuct

    Duct Marked ‘Electricity’

    Typical Mains Crossings LayoutAll ducts to have �ne �ll material

    75mm above and below

    Ground Level

  • GasUtility Installation Guide

    12

    Note: Energetics will not fit meters until the internal pipework is completed, the construction of the meter compartment finished, the required ventilation

    provided and an appropriate lockable door has been installed.

    Flatted Properties - Meter Banks and Compartments

    Flatted properties often have meter banks located in meter rooms. An example of this is shown below:

    For flatted properties, it is the Site Developer’s responsibility to:

    • Ensure that the residents have 24/7 access to the meter room. This includes the provision of keys and access codes where applicable.

    • Ensure that all pipework from the meter to the individual property is installed and labelled to identify the flat number prior to meters being fitted and commissioned.

    • Provide a statement confirming the integrity of the building should there be a fire or explosion at or within the meter room.

    • Provide adequate ventilation for the meter rooms.

  • 13

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    No of external walls

    Minimum area of free ventilation required as a % of the compartment floor area

    Type of natural ventilation required to the outside

    Position of low level vents

    Position of high level vents

    1 3%Louvered door or high and low level indicators

    150mm above the floor

    2 2%High and low level ventilators

    150mm above the floor

    3 2%High and low level ventilators

    150mm above the floor

    4 2%High and low level ventilators

    150mm above the floor

    As close as possible below, but no more than 10% of the total compartment height below, the roof or ceiling level

    It is the Site Developer’s responsibility to ensure that ventilation is provided for the meter rooms. They must:

    • Completely seal the meter room from any other part of the building.

    • Provide meter rooms with a minimum ventilation of 2% of the nominal floor area when the ventilation is on two or more walls. If the ventilation is only on one wall, this increases to 3% of the nominal floor area.

    Ventilation of Meter Room

    • The ventilation shall be natural to the outside air and be evenly distributed at high and low levels.

    See the table below for meter compartment ventilation requirements:

    Flatted Properties - External Steel and PE Risers

  • GasUtility Installation Guide

    14

    Flatted Properties - External Steel and PE Risers

    The photographs below show examples of an external PE Riser System for flatted properties:

    The cross-section diagram below shows an example of an external steel or PR riser installation to a conventional build:

    LATERAL ISOLATION VALVEOPTIONAL ISOLATION VALVE

    OR BUILDING ENTRY TEE WITHINTEGRAL VALVE

    VIEW A

    FLAT

    FLAT

    FLAT

    ECV

    ECV

    ECV

    VIEW A

    INSOLATION JOINT

    GROUND LEVEL

    ACCESS CHAMBER PIV

  • 15

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    It is the Site Developer’s responsibility to:

    • Provide a suitable safe access platform for the installation of all external gas riser works.

    • Provide suitable sleeved core drillings for the installation of the lateral entries to the individual properties. The diagrams below show fire stopping and sleeving lateral gas pipes passing between walls or fire compartments.

    • Risers supplying timber frame flatted properties must terminate immediately on the inside of the timber frame wall. They should not extend vertically or horizontally in the building. Site Developers must ensure meter location caters for this requirement.

    • Ensure that pipes supplying timber frame flatted properties do not pierce through any other fitment or fitting within the timber frame structure. This includes items such as meter boards, kitchen units, fitted cupboards, etc.

    Single Skin Walls

    10mm

    10mm10mm

    Conventional Cavity Walls

    10mm

    10mm10mm

    • Ensure that site staff do not fix risers, laterals and gas pipes supplying timber frame flatted properties to the timber frame under any circumstances.

    • Prevent other utilities being attached to any part of the gas network.

    The diagram below shows the fire stopping and sleeving lateral gas pipes passing between walls in a timber framed property. Note the need to make adequate allowance for internal movement due to shrinkage of the timber frame wall:

    Flatted Properties - External Steel and PE Risers

    View AView A

    Anticipated PositionAfter Movement

    Original Position ofPipe Entry

    Make Adequate Allowance For InternalMovement Due To Shrinkage Of The Timber

    Frame Wall Cover Plate To Be Provided

    Part 2: Gas

    © Energetics 2018 31

    The photo below shows a gator installed on the inside of the lateral entry:

    The photo below shows a gator installed on the inside of the lateral entry:

    The diagram below shows the fire stopping and sleeving lateral gas pipes passing between walls in a timber framed property. Note the need to make adequate allowance for internal movement due to shrinkage of the timber frame wall:

  • GasUtility Installation Guide

    16

    Cross Sectional Area of Duct (m2) Equivalent Duct Dimensions

    Minimum Free Area of Each Opening (m2) Equivalent Opening Diameter

    ≤0.01 ≤100mm x 100mm 0.002 50mm

    >0.01 >100mm x 100mm≤0.375 ≤600mm x 600mm

    0.0075 100mm

    >0.375 >600mm x 600mm≤7.5 ≤2.7m x 2.7m

    0.05 250mm

    >7.5 >2.7m x 2.7m 1/150th of Cross Sectional Area of the Duct Dependent on the Cross Sectional Area of the Duct

    For flatted properties, for internal gas risers, the Site Developer must:

    • Provide half-hour fire resistant ducts/shafts. These must be constructed to BS 8313 standards.

    • Ensure ducts have sufficient dimensions to accommodate initial construction and provide suitable access for ongoing maintenance.

    • Ensure that all ducts are fitted with removable/replaceable access panels, which gives maintenance access to the riser.

    Flatted Properties - Internal Risers

    Services in ducts are specified in BS 8313:1997

    The table below shows the minimum duct ventilation requirements for a full height internal gas riser:

    Note: Energetics will make inspections of the ducting prior to installing any gas riser and on completion of the duct installation. This is to ensure

    that the ducting and ventilation meets the standards required.

    Duct Detail Ventilation Opening Details

    The Site Developer must comply with:

    • IGEM/G/5.

    • Last Mile Asset Management policy for Multi-Occupancy buildings.

    General Statement

    • With the requirements of Last Mile Gas Ltd Gas In Flats procedures GIF1,2,3.

    • Use a suitable material for the access panels such as ‘Superlux’. A suitable material helps the access panels to be removed and replaced without affecting the quality of the ventilation.

    • Ensure that the riser ducts are permanently ventilated directly to the atmosphere. This must be done either:

    - at the top and bottom

    -or-

    - at the top and bottom of each floor where fire stopped.

  • 17

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    The following diagram shows an example of an external wall vent:

    If the duct is not continuous, it must be ventilated at the top and bottom of each section. Between floors, the ends must be sealed so that the fire resistance of the property is not impaired.

    External Wall Vent

    The following diagrams show fire stopping and sleeving gas risers passing between floors or fire compartments:

    Gas Risers Passing Between Floors or Fire Compartments

    Fixing Screws

    Ventilator

    Spacer

    Position of ductin external wallventilating directto outside air

    NOTE:The overall dimensions of the ventilation are typically much larger thanthe ventilation duct and therefore will require spacers to be fitted toensure the full area of ventilation is used as demonstrated by thefollowing diagram.

    Section of duct cut �ushwith wall

    Fixing Screws

    Ventilator

    Spacer

    Position of ductin external wallventilating directto outside air

    NOTE:The overall dimensions of the ventilation are typically much larger thanthe ventilation duct and therefore will require spacers to be fitted toensure the full area of ventilation is used as demonstrated by thefollowing diagram.

    Section of duct cut �ushwith wall

    Flatted Properties - Internal Risers

  • GasUtility Installation Guide

    18

    Flatted Property - Internal Pipeline Isolation Valve

    The Site Developer must ensure that Isolation Valves located within the building have unrestricted access for Emergency Services to isolate the gas supply.

    The next diagram shows fire stopping and sleeving lateral gas pipes as they pass between walls or fire compartments.

    Both Single Skin Walls and Cavity Walls are demonstrated:

    Single Skin Walls

    10mm

    10mm10mm

    Conventional Cavity Walls

    10mm

    10mm10mm

    Single Skin Walls Cavity Wall

    A gas service pipe that supplies an internal or external gas riser must have an external Pipeline Isolation Valve (PIV) fitted. The following points are important:

    • These should be fitted 5-10 metres from the building.

    • The Site Developer must ensure PIV are located in the footway, not within an area that may be planted with shrubbery or where vehicles are likely to park.

    Part 2: Gas

    © Energetics 2018 35

    Flatted Property – External Pipeline Isolation Valve

    A gas service pipe that supplies an internal or external gas riser must have an external Pipeline Isolation Valve (PIV) fitted. The following points are important:

    • These are normally fitted 5-10 metres from the building.

    • The Site Developer must ensure these are located in the footway, not within an area that may be planted with shrubbery or where vehicles are likely to park.

    • The Site Developer must ensure a gas surface box is installed to permit future access to the valve. This box must be installed as part of the permanent reinstatement. Clear access to the top of the valve must be maintained and be clear of all debris.

    The diagrams below show the requirements for the gas surface box fitted during the permanent reinstatement.

    600m

    m C

    ove

    r Fo

    otp

    ath/

    45

    0mm

    Co

    ver

    Pri

    vate

    Gas Valve Box Cover marked with ‘G’ or GAS to be fitted as part of permanent reinstatement

    Access box/pit to be supplied by Developer prior to permanent reinstatement

    • The Site Developer must ensure a gas surface box is installed to permit future access to the valve. This box must be installed as part of the permanent reinstatement. Clear access to the top of the valve must be maintained and be clear of all debris.

    The diagram below show the requirements for the gas surface box fitted during the permanent reinstatement.

    External Pipeline Isolation Valve

  • 19

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    Gas Meters

    Where a gas meter is to be installed within an internal cupboard, the Site Developer must ensure:

    • That a minimum installation area of 500mm (H) x 500mm (W) x 300mm (D) is maintained.

    • That the gas meter is not located below or within 40mm of the electrical distribution board.

    • That the gas meters and associated fittings are installed with a minimum separation distance of 150mm from any electrical meters and 25mm from any electrical cable.

    Meter Point Reference Number

    Information required for flatted properties where meter is installed in a meter bank

    Service Information Label

    The Site Developer must ensure that meters or their labels are not removed, damaged or exchanged to another property once they have been installed.

    Each meter supply point has a Service Information Label attached at the Emergency Control Valve. The label contains a Meter Point Reference Number (MPRN) which is a unique number allocated to each plot. Energetics supply and install these labels.

    If the meter is located in a communal meter bank, the Site Developer must ensure that the flat number which the meter supplies is clearly identified and marked at the meter position for the plot. This is recorded on the Service Information Label when the label is installed.

    Shown here is an example of a Service Information Label:

    Energetics will not fit meters until the associated installation pipe work has been completed and it is clearly and permanently labelled by the developer to identify the property that it supplies.

    • Where internal cupboards containing gas meters, open onto a means of escape from the property, the cupboards must have a minimum ½ hour fire rating with a self-closing door.

  • GasUtility Installation Guide

    20

    Damage to Meter Installations

    Part 2: Gas

    © Energetics 2018 37

    Damage to Meter Installations

    The flexible connection pipe connecting the outlet of the Emergency Control Valve to the meter installation is made out of corrugated stainless steel.

    Some solder fluxes, used on copper joints, are particularly corrosive to stainless steel. They can quickly cause corrosion in the form of pin holes.

    The Site Developer must ensure that any flux spillage on the flexible stainless steel meter connectors and other parts of the meter installation is immediately cleaned and rinsed off to avoid potential corrosion and the risk of leaking gas.

    The image below shows damage to a flexible connection pipe:

    The following points are also important to prevent damage to the meter connections:

    • Commercially available washing up liquids also contain substances that are potentially corrosive. Washing up liquid or similar soap solutions should not be used as a Leak Detection Fluid (LDF).

    • The Site Developer must ensure that any LDF is completely wiped off after the tightness testing of the installation pipework has been completed.

    • The Site Developer must also ensure that when their Gas Engineer tests and commissions the gas installation pipework, they do not over-tighten the meter test nipple as this will permanently damage the gas meter. The image below shows damage to a meter test nipple.

    Part 2: Gas

    © Energetics 2018 37

    Damage to Meter Installations

    The flexible connection pipe connecting the outlet of the Emergency Control Valve to the meter installation is made out of corrugated stainless steel.

    Some solder fluxes, used on copper joints, are particularly corrosive to stainless steel. They can quickly cause corrosion in the form of pin holes.

    The Site Developer must ensure that any flux spillage on the flexible stainless steel meter connectors and other parts of the meter installation is immediately cleaned and rinsed off to avoid potential corrosion and the risk of leaking gas.

    The image below shows damage to a flexible connection pipe:

    The following points are also important to prevent damage to the meter connections:

    • Commercially available washing up liquids also contain substances that are potentially corrosive. Washing up liquid or similar soap solutions should not be used as a Leak Detection Fluid (LDF).

    • The Site Developer must ensure that any LDF is completely wiped off after the tightness testing of the installation pipework has been completed.

    • The Site Developer must also ensure that when their Gas Engineer tests and commissions the gas installation pipework, they do not over-tighten the meter test nipple as this will permanently damage the gas meter. The image below shows damage to a meter test nipple.

    If you smell gas or are concerned about gas safety on site, phone the 24 hours National Gas Emergency Number on 0800 111 999.

    The Site Developer must ensure that any flux spillage on the flexible stainless steel meter connectors and other parts of the meter installation is immediately cleaned

    and rinsed off to avoid potential corrosion and the risk of leaking gas.

    The flexible connection pipe connecting the outlet of the Emergency Control Valve to the meter installation is made out of corrugated stainless steel.

    The Site Developer must ensure that any flux spillage on the flexible stainless steel meter connectors and other parts of the meter installation is immediately cleaned and rinsed off to avoid potential corrosion and the risk of leaking gas.

    Some solder fluxes, used on copper joints, are particularly corrosive to stainless steel. They can quickly cause corrosion in the form of pin holes.

    The following image shows damage to a flexible connection pipe:

    The following points are also important to prevent damage to the meter connections:

    • Commercially available washing up liquids also contain substances that are potentially corrosive. Washing up liquid or similar soap solutions must not be used as a Leak Detection Fluid (LDF).

    • The Site Developer must ensure that any LDF is completely wiped off after the tightness testing of the installation pipework has been completed.

    • The Site Developer must also ensure that when their Gas Engineer tests and commissions the gas installation pipework, they do not over-tighten the meter test nipple as this will permanently damage the gas meter. The image below shows damage to a meter test nipple.

    Any costs associated with remedial works are passed directly on to the Site Developer.

    Gas Meters

  • 21

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    Inlet Outlet

    Front

    Parking Bay

    Pressure Regulating Installations (PRIs) - Above Ground

    The position of the PRI must be agreed with Energetics at the design stage and not subsequently altered without Energetics written agreement.

    The Site Developer must ensure:

    • That the PRI is sited at least 3 metres from any building or ignition source.

    • That the PRI is located in a place where maintenance teams are able to access and egress from, and work in vicinity of, the PRI. This is particularly important in the event of emergency works.

    Location

    Note: The sizes are determined by the dimensions of the PRI.

    • That a parking space is provided for the maintenance team vehicle where identified on the approved design drawing.

    The diagram below shows an example layout for a PRI:

  • GasUtility Installation Guide

    22

    Front

    Plan

    Elevation

    Side Elevation

    Isometric View

    Front

    Plan

    Elevation

    Side Elevation

    Isometric View

    Front

    Plan

    Elevation

    Side Elevation

    Isometric View

    The Site Developer must ensure:

    • The concrete base for the PRI is adequately sized:

    - The concrete base dimensions will be 300mm greater than the external dimensions of the kiosk, though this may be less for smaller sites with Energetics agreement.

    - The base thickness will be a minimum of 200mm, with consideration for the installation of reinforcement. Energetics may specify a smaller base for smaller sites.

    - That the base has a 45-degree chamfer around the perimeter of the base.

    - That the base is installed on a compacted sub-base layer of MOT Type 1, to a minimum 200mm depth.

    • That the minimum specification of concrete used is c30.

    Construction

    The sizes are determined by the dimensions of the PRI.

    Prior to commissioning the PRI, Energetics and the Network Operator will conduct an inspection. The purpose of this is to ensure that all work required for the construction and operation of the

    PRI is completed. Any outstanding work will result in the PRI not being commissioned.

    • When the base has been constructed, it must be protected from the weather. It must be given a 3-day period before installation of the module / housing so that the concrete sets properly.

    • That the base has a floated finish.

    • When commissioning is finished, the slots must be backfilled with sand and a 50mm layer of C30 concrete to finish the base.

    • All shuttering must be removed on completion of works.

    • All legal completions must be in place before the PRI is commissioned.

    The diagram below shows a typical drawing for a PRI base

    Pressure Regulating Installations (PRIs) - Above Ground

  • 23

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    The images below show typical arrangements for PRIs on completion:

    Pressure Regulating Installations (PRIs) - Above Ground

  • GasUtility Installation Guide

    24

    Pressure Regulating Installations (PRIs) - Below Ground

    Location

    a vent stack is required forbelow ground installation

    surface level

    porousmaterial

    customer to install adrainage to surface

    water drainage system

    Twin Stream Installation

    Inlet and outlet valves to be installeda minimum of 2m from PRI

    InletValve

    OutletValve

    The position of the PRI must be agreed with Energetics at the design stage and not subsequently altered without Energetics written agreement.

    The Site Developer must ensure:

    • That the PRI is sited at least 3 metres from any building or ignition source.

    • That the PRI is located in a place where maintenance teams are access and egress from, and work in the vicinity of, the PRI. This is particularly important in the event of emergency works.

    • That the installation is located away from any carriageway or parking area. For example, the installation could be located in a verge or footpath.

    The sizes are determined by the dimensions of the PRI.

    • That the PRI is not installed in areas where there is a risk of flooding.

    • That the site (and equipment) is located to avoid damage from vandalism or road traffic.

    • That the PRI is clear of overhead electricity cables and large trees.

    • That there is a suitable location for terminating relief pipework in a 3m high vent stack.

    • That a parking space is provided for the maintenance team vehicle where identified on the approved design drawing.

    The diagrams below show an example layout for a PRI below ground:

  • 25

    GasUtility Installation Guide

    © Energetics 2019. Utility Installation Guide: Gas v1.0

    The Site Developer must ensure:

    • That the concrete base for a PRI is sized adequately for the PRI module in accordance with Energetics’ specifications.

    • That the minimum specification of concrete used is C30.

    • That on completion of construction of the base, it must be protected from the weather. It must be given a 3-day period before installation of the module / housing so that the concrete sets properly.

    • That the base has a floated finish.

    Construction

    Prior to commissioning the PRI, Energetics and the Network Operator will conduct an inspection. The purpose of this is to ensure that all work required for the construction and operation of the

    PRI is completed. Any outstanding work will result in the PRI not being commissioned.

    The sizes are determined by the dimensions of the PRI.

    • When commissioning is finished, the slots must be backfilled with sand and a 50mm layer of C30 concrete to finish the base.

    • All shuttering must be removed on completion of works.

    • All legal completions must be in place before the PRI is commissioned.

    The diagram below shows an example drawing for a PRI base:

    A393 Mesh

    Concrete Base

    Compacted Type 1Granular Material

    Plinth Elevation

    Plinth PlanA393 Mesh

    Concrete Base

    Compacted Type 1Granular Material

    Plinth Elevation

    Plinth Plan

    Pressure Regulating Installations (PRIs) - Below Ground

  • GasUtility Installation Guide

    26

    The image below shows a typical arrangement for a below ground PRI on completion:

    Pressure Regulating Installations (PRIs) - Below Ground

  • Energetics Fenick House Lister Way Hamilton International Technology Park Glasgow G72 0FT

    TEL: 03300 587 400 www.energetics-uk.com


Recommended