+ All Categories
Home > Documents > VES soundings Kajiado Town - SamSamWater...VES soundings Kajiado Town Technical Interpretation and...

VES soundings Kajiado Town - SamSamWater...VES soundings Kajiado Town Technical Interpretation and...

Date post: 04-Feb-2021
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
74
Pagina | 1 VES soundings Kajiado Town Technical Interpretation and inversion results of all available VES soundings in and near Kajiado Town up to date April 2017 by Harry Rolf , SamSamWater Foundation, Netherlands November, 2017 SamSamWater Foundation http://www.samsamwater.com/index.php
Transcript
  • P a g i n a | 1

    VES soundings Kajiado Town Technical Interpretation and inversion results of all available VES soundings in and near Kajiado Town up to

    date April 2017

    by Harry Rolf , SamSamWater Foundation, Netherlands

    November, 2017

    SamSamWater Foundation http://www.samsamwater.com/index.php

  • P a g i n a | 2

    Introduction This document comprises the technical interpretations (inversions) of all VES soundings -as far as available up to date - in and

    around Kajiado town.

    It includes:

    • 22 VES soundings from fieldwork for ISGEAG and Sponge city projects February 2017 and April 2017.

    • Re-interpretation of VES Soundings as found in existing survey reports .

    Unfortunately only a very limited number of seven (7) survey reports could be made available of which 3 are lacking

    measured field data. There must have been many more geophysical surveys, but the availability reports often

    appears to be a major organisational challenge in Kenya.

    Each interpretation includes all relevant administrative data (location, reference to report, etc.), the field measurements and the

    interpretation (inversion) results using SchlumBG software1. In case of the existing survey reports it concerns a re-interpretation

    of the data and a comparison to the interpretation as given in the report.

    The inversion, layer-model results are given with their 90% uncertainty range as calculated in the SchlumBG software. Some of

    the existing survey reports do not comprise the measured data; in those cases the measurements are generated by forward

    modelling but the re-interpretation is questionable.

    Reading guide First, the locations of all VES soundings are presented on a map (next page Figure 1) and the inversion (layer model) results are

    summarised in Tables 1,2 and 3.

    Next, for each VES sounding a short (2-3 pages) interpretation report is included. These reports are presented in three blocks:

    1) all soundings of the 2017 Sponge City/ ISGEAG surveys (up to page 53)

    2) the re-interpretations of soundings as found in existing survey reports that include the measured data and

    3) the soundings from reports that lack the measured data.

    Interpretation report content Each VES interpretation report contains 6 sections:

    General:

    • giving the aim, date and location (map) and reference to the survey report2

    VES information:

    • WGS84 coordinates, line direction, electrode reach, VES array, land elevation and estimated depth to groundwater

    Measured data:

    • Table and graph of measurements and data remarks

    VES interpretation:

    • giving the equivalent inversion model(s) having the best fit with the minimum nr. of layers

    Results:

    • giving the interpreted layer model parameters (depth of the top of the layer and layer resistivity) including their 90%

    confidence range

    • note: the layer depth gives the depth of the top (!) of the layer

    • ‘basement’ is defined when layers have resistivity > 1000 Ωm

    Major conclusion

    1 SchlumBG for Windows, C.J. Hemker and V.E.A.Post, http://www.microfem.com 2 For the Sponge City soundings the reader is referred to ‘Geophysical surveys for Sponge City project Kajiado, Kenya;

    SamSamWater, Harry Rolf, November 2017’

    For the ISGEAG soundings in Kajiado a research report is being prepared by Acacia Water (probably available in February 2018)

  • P a g i n a | 3

    Figure 1 VES locations in and around Kajiado Town. The ‘existing survey report’ locations are given by name, the

    ISGEAG/Sponge city VES locations are numbered.

  • P a g i n a | 4

    TABLE 1 summarized results of Sponge City/ ISGEAG VES soundings

    Sponge City/ ISGEAG soundings February and April 2017

    coordinates (WGS84) Electr RMS REMARKSname/ VES LAT LONG Elev sp. error TOP Rho confidence TOP confidence Rho confidence TOP confidence Rho confidence TOP confidence Rho

    location nr. (S) (East) (mas) AB/2 (m) x10-2 (m) (Ωm) (m) (Ωm) (m) (Ωm) (m) (Ωm)

    Gulley C VES1 1 01°49'39.5'' 36°46'31.2'' 1690 320 3.6 0 26 (23 - 29) 2 (1 - 4) 50 (40 - 80) 15 (12 - 30) >>>1000 discontinuities in meas.

    Gulley C VES3 3 01°49'26.8'' 36°46'27.8'' 1710 320 3.5 0 90 (80 - 120) 1.7 (1,5 - 2) 30 (23 - 40) 50 (40 - 60) discontinuities in meas.

    Gulley C VES4 4 01°49'34.7'' 36°46'22.9' 1685 320 9.2 0 2 (1 - 5) 2.5 (2-8_ 50 (30 - 1000) 4 < 8 >>1000 discontinuities in meas.

    Gulley C VES7 7 01°49'33.0'' 36°46'24.3' 1690 400 1.2 0 30 (25 - 60) 2.5 (2 - 3) 300 (290 - 320) 90 (80 - 100)

    Gulley C VES13 13 01°49'34.4'' 36°46'23.4' 1682 63 5 0 10 (6 - 12) 4.5 (4 - 5) >>1000 on gulley river bed

    Gulley C VES16 16 01°49'31.9'' 36°46'25.2'' 1687 500 3 0.1 250 (220 -280) 11 (9 - 15) 57 l(arge) 15 (large) 500 (250-1000) 76 (40-160) (1000-1500) some discontinuity

    VES2 (road) 2 01°49'55.1'' 36°46'22.0'' 1720 320 unreliable sounding unreliable (reason ?)

    Gulley B VES9 9 01°50'17.3'' 36°46'17.2'' 1710 500 1.2 0 290 (250 - 300) 1 (1 - 2) 145 (130 - 150) 9 (8 - 13) 90 (85 - 110) 55 (50 - 70) (700 - 900)

    Town VES5 5 01°50'21.7'' 36°46'59.1'' 1720 130 1.7 0 170 (150 - 200) 0.5 (0 - 1) 65 (60 - 70) 9 (8 - 12) 190 (150 - 300) ? >40 short AB line

    Town VES6 6 01°50'24.1'' 36°47'28.8'' 1735 130 1.6 0 5 (1 - 12) 3 (2 - 4) 43 (40 - 55) 45 (20 - 90) short AB line large disc.

    Town VES8 8 01°50'27.8'' 36°47'25.3'' 1732 63 1.8 0 53 (52 - 56) 11 (9 - 13) 100 (90 - 110) ? >75 short AB line large disc.

    Kajiado River:

    Kaj. R VES10,12 10,12 01°48'50.9'' 36°46'02.3'' 1680 500 2 0 35 (35 - 50) 1 (1 - 2) 48 (44 - 70) 12 (10 - 15) 400 (300 - 500) 130 (120 - 200) >>>1000 two perpendicual VES's

    Kajiado R VES11 11 01°49'46.3'' 36°45'50.6'' 1670 500 1.5 0 320 (150 - 500) 0.7 (0- 1) 4 (large) 0.8 (large) 130 (100 - 200) 35 (25 - 43) (>3000)

    VES11 layer4: 27 (large) 25 ( 1000

    Kajiado Ri VES15 15 01°49'03.5'' 36°45'59.8'' 1692 500 1.5 0 480 (340 - 700) 7 (2 - 12) 200 (185 - 210) 80 (65 - 95) >800 large discontinuity

    Kajiado R VES17 17 01°49'11.0'' 36°46'03.8'' 1675 250 4 0 60 (large) 0.3 (0 - 3) 20 (12 - 40) 13 (11 - 15) >>>1000

    Kajiado R VES18 18 01°49'11.1'' 36°46'03.5'' 1675 160 2.3 0 600 (300 - 1500) 1.2 (1 - 3) 3 (1 - 10) 1.7 (large) 240 (50 - 600) 80 >30 discontinuity

    Kajiado R VES19 19 01°49'06.2'' 36°46'11.6'' 1675 500 1.9 0 1200 (large) 0.7 (0 - 5) 80 (30 - 150) 9 (3 - 30) 500 (300 - 800) 33 (>25, uncertain) major disconinuity

    Kajiado R VES20 20 01°49'03.7'' 36°46'04.3'' 1680 200 1.7 0 800 (250 - 2600) 1.2 (1 - 4) 5 (large) 2.4 (large) 300 (140 - 700) 90 (>45, uncertain) short AB reach

    Interpreted geo-electric resistivity model

    surface layer Layer 2 Layer 3 Basement (Rho≈≥1000

  • P a g i n a | 5

    TABLE 2 summarized results re-interpreted VES soundings from existing survey reports

    TABLE 3 summarized results VES soundings from existing survey reports, lacking measured data

    re-interpreted from existing survey reports

    coordinates (WGS84) Electrode RMS remarks

    name/ VES nr. LAT LONG Elev spacing error TOP Rho confidence TOP confidence Rho confidence TOP confidence Rho confidence TOP confidence Rho

    location (S) (East) (mas) AB/2 (m) x10-2 (m) (Ωm) (m) (Ωm) (m) (Ωm) (m) (Ωm)

    MTTI VES1 MTTI 01°51'16.0'' 36°46'55.3'' 1720 200 1.87 0 350 (300-400) 1.5 (1 - 2) 100 (20 - 500) 25 (10 - 40) 200 (100 - 300) ?? > 80 detail coordinates missing

    MTTI VES2 MTTI 01°51'16.0'' 36°46'55.3'' 1720 160 0.95 0 10 (8 - 12) 1.5 (1 - 2) 75 (70 - 80) 25 (20 - 30) 340 (220 - 460 ?? > 80

    MTTI VES3 MTTI 01°51'16.0'' 36°46'55.3'' 1720 200 1.88 0 15 (10 - 20) 3 (1 - 5) 85 (70 - 100) 10 (8 - 14) 210 (190 - 240) ?? >130

    MTTI VES4 MTTI 01°51'16.0'' 36°46'55.3'' 1720 200 1.72 0 120 (90 - 160) 1.5 (1 - 2) 35 (28 - 40) 9 (5 - 10) 200 (130 - 230) ?? >50 or deep correctness of last 3 points ?

    Masai Stores Masai St 01°50'52.9'' 36°47'24.7'' 1730 200 1.28 0 75 (70 - 80) 1.5 (1- 2) 52 (50 - 55) 20 (15 - 25) 175 (100 - 400) 80 (50 - 130) >>1000 survey report model gives BAD FIT

    Osman town Osman 01°50'45.0'' 36°47'25.0'' 1730 250 1.31 0 14 (8 - 27) 0.7 (0- 3) 22 (21 - 23) 10 (10 - 11) 105 (93 - 130) ? >90

    Osman Kaj River Osman 01°49'26.0'' 36°45'54.5'' 1670 250 1.9 0 4 (3 - 5) 5 (4 - 6) 40 (15 - 50) 30 (15 - 40) >>1000 inconsistent interpretation in report

    Interpreted geo-electric resistivity model

    surface layer Layer 2 Layer 3 Basement (Rho≈≥1000

    Interpreted geo-electric resistivity model

    coordinates (WGS84) Electrode remarks

    Name/ VES nr. LAT LONG Elev

    spacing RMS

    error TOP Rho TOP Rho TOP Rho TOP Rho TOP Rho TOP Rho

    Location (S) (East) (mas) AB/2 (m) x10-2 (m bgs) (Ωm) (m bgs) (Ωm) (m bgs) (Ωm) (m bgs) (Ωm) (m bgs) (Ωm) (m bgs) (Ωm)

    Itinyika 01°50'40.0'' 36°45'40.0'' 1660 ? ? 0 70 2 30 8 100 16 200 50 80 100 700 field data missing

    Empeut VES1 01°50'3.54'' 36°47'42.0'' 1720 ? ? 0 79 0.8 17 1.4 53 19 1150 36 81 100 1000 field data missing

    Empeut VES2 01°50'0.97'' 36°47'40.4'' 1720 ? ? 0 16 1 30 11 93 42 1000 field data missing

    Parmet 01°49'05.0'' 36°45'40.0'' 1685 ? ? 0 90 2 15 7 100 40 250 80 125 125 1200 field data missing

    Layer 4surface layerLayer 2 Layer 3 Layer 5 Basement ≥1000 Ωm

  • P a g i n a | 6

    Content

    Interpretation report index

    Page nr.

    Sponge City and ISGEAG soundings:

    VES 1 --------------------------------------------------------------- 7

    VES 2 --------------------------------------------------------------- 9

    VES 3 --------------------------------------------------------------- 11

    VES 4 --------------------------------------------------------------- 13

    VES 5 --------------------------------------------------------------- 15

    VES 6 --------------------------------------------------------------- 17

    VES 7 --------------------------------------------------------------- 19

    VES 8 --------------------------------------------------------------- 21

    VES 9 --------------------------------------------------------------- 23

    VES 10/12 --------------------------------------------------------------- 25

    VES 11 --------------------------------------------------------------- 28

    VES 13 --------------------------------------------------------------- 31

    VES 14 --------------------------------------------------------------- 33

    VES 15 --------------------------------------------------------------- 35

    VES 16 --------------------------------------------------------------- 37

    VES 17/18 --------------------------------------------------------------- 39

    VES 19 --------------------------------------------------------------- 44

    VES 20 --------------------------------------------------------------- 47

    VES 21 --------------------------------------------------------------- 50

    mini VES --------------------------------------------------------------- 52

    From existing survey reports:

    MTTI --------------------------------------------------------------- 55

    Masai Stores --------------------------------------------------------------- 60

    Mr. Osman (Town) --------------------------------------------------------------- 63

    Mr. Osman (Kajiado River)--------------------------------------------------------------- 65

    ---------------------------------------------------------------

    Existing reports lacking field data:

    Itinyika --------------------------------------------------------------- 68

    Empeut --------------------------------------------------------------- 70

    Mr. Parmet --------------------------------------------------------------- 73

  • P a g i n a | 7

    Kajiado VES sounding nr.1 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 17/02/2017

    Client : Acacia Water

    General

    VES sounding for Sponge City project

    Aim: finding locations for infiltration (highly weathered or fractured rock)

    Location name: South bank of Gully C. This is one of the VES’s and HEP lines conducted close to this gully, see report Rolf 2017,

    Geophysical surveys for Sponge City project Kajiado, Kenya.

    Sounding Date : 15/02/2017

    Location

    VES sounding information

    Location: (WGS82): 360 46’31.2” E and Latitude 010 49’39.5” S

    Direction of sounding: 110 gr SE (the VES line has crossed the gully which may have caused anomaly in the measurements)

    AB reach: 320 m

    Array: Schlumberger

    Elevation: 1690 mas

    Estimated depth to Water: 30 m

    Measured data

    Remarks: There obviously was a lateral change, which in this case may be caused by the gully (geology change) that was crossed

    at the South east part of the line (at 65 m from the centerpoint)

    DATA table VES 1

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 27 27

    2 27 27

    2.5 28 28

    3.2 32 32

    4 31 31

    5 32 32

    6.3 38 38

    8 43 43

    10 46 46

    0.5 13 52 52

    5 13 58

    16 63 56

    20 63 59

    25 69 61.7

    5 32 95 85

    10 32 71

    40 97 114

    50 126 150

    10 63 163 193

    25 63 126

    80 182 280

    100 220 335

    25 130 268 407

    50 130 194

    160 230 483

    200 226 475

    250 225 472

    50 320 190 399

    100 320

    400

    500

    VES measurements

    10

    100

    1000

    1 10 100 1000AB/2 (m)

    Rho (ohm

    m)

    Rho

    Rho shifted

  • P a g i n a | 8

    VES interpretation Inversion results (SchlumBG modelling)

    Possible model concepts

    3 layers shifted data (leaving out the last bending down measurements) very high resistivity basement

    Results including 90% confidence levels

    Depth (m) Rho (Ωm )

    topsoil ------ 23 - 29

    Overburden 1 -4 40 – 80

    Shallow aquifer ------- ---------

    Basement (ρ>1000) 12 - 30 >>>1000 (high resistivity)

    Conclusion

    • Overburden on top of fresh basement rock at 12 – 30m depth

    The bending of the measurements beyond AB/2 = 100 is not (yet) explained.

    The VES line crossed a major anomaly, probably when crossing the gully.

    1 10 100 L/2

    10

    1e+2

    1e+3

    1e+4

    1e+5

    1e+6

    Rho

  • P a g i n a | 9

    Kajiado VES sounding nr.2 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 17/02/2017

    Client : Acacia Water

    General

    VES sounding for Sponge City project.

    Aim: finding locations for infiltration (highly weathered or fractured rock)

    Location name: along the road down to the Kajado River (in between gulley C and gulley B, at the beginning of HEP1 and HEP2

    profiles)

    Sounding date : 13/02/2017

    Location

    VES sounding information

    Location: (WGS82): 360 46’ 22.0” E and Latitude 010 49’ 55.1” S

    Direction of sounding: SE -N W along the road

    AB reach: 640 m

    Array: Schlumberger

    Altitude: 1718 mas

    Depth to groundwater

    (if any) estimated at: 70 mbgl

    Measured data

    Remarks: The measurements are discontinuous. The difference between the shifted and unshifted measurements is

    considerable. There are some clear outliers e.g. at AB/2 =30 m. The cause of these varying measurement quality is not clear. It

    may be caused by crossed powerlines and fences along the road.

    DATA table VES 2

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 276 276

    2 270 270

    2.5 264 264

    3.2 274 274

    4 274 274

    5 277 277

    6.3 284 284

    8 257 257

    10 228 228

    0.5 13 191 191

    5 13 225

    16 192 164

    20 185 157

    25 209 178

    5 32 221 187

    10 32 220

    40 282 240

    50 243 207

    10 63 257 220

    25 63 219

    80 252 252

    100 281 282

    25 130 318 319

    50 130 292

    160 326 299

    200 364 333

    250 404 370

    50 320 404 371

    100 320

    400

    500

    VES measurements

    100

    1000

    1 10 100 1000AB/2 (m)

    Rho (ohm

    m)

    Rho

    Rho shifted

  • P a g i n a | 10

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    3 or 5 layer model with shifted or unshifted data

    Basement layer (taken at ρ>1000 ohmm) is uncertain

    \

    5 layer unshifted

    3 layer unshifted

    4 layer shifted data

    Results including 90% confidence levels

    Depth (m) **) Rho (ohmm)

    topsoil (1000) >40 (actually unknown)

    *)Please note the topsoil Rho can be just a phony representing electrode contacts, electric leakings

    **) the top of the layer

    Conclusion

    • High uncertainty, actually the sounding is unreliable

    • The (dry) overburden layers are in the order of 160 - 250ohmm.

    • At the level of in between 25 – 75 m there is a change to a somewhat higher resistivity (380 – 500 ohmm)

    • No basement rock within 40 m depth

    1 10 100 L/2

    1e+2

    1e+3

    1 10 100 L/2

    1e+2

    1e+3

    1 10 100 L/2

    10

    1e+2

    1e+3

  • P a g i n a | 11

    Kajiado VES sounding nr.3 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 01/03/2017

    Client : Acacia Water

    General

    VES sounding for Sponge City project.

    Aim: finding locations for infiltration (highly weathered or fractured rock)

    Location name: on the Gully bed (Northern runoff gulley C) close to a solar borehole (Mr. Rehoba)

    Sounding Date : 16/02/2017

    Location

    VES sounding information

    Location: (WGS82): 36046’27.8” E and Latitude 01049’26.8” S

    Direction of sounding: NE at the north end of HEP line 1 (in the HEP line direction!)

    AB reach: 640 m

    Array: Schlumberger

    Elevation: 1710 mas

    Depth to groundwater (if any)

    Estimated at: 50 m

    Measured data

    Remarks: Major lateral changes and outliers. The sounding direction was across the direction of geology changes

    Data shifted acc. to Earth Water Consultant’s methodology.

    DATA table VES 3

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 62 62

    2 73 73

    2.5 85 85

    3.2 89 89

    4 90 90

    5 77 77

    6.3 78 78

    8 68 68

    10 61 61

    0.5 13 49 49

    5 13 76

    16 57 37

    20 48 31

    25

    5 32 48 31

    10 32 58

    40 64 34

    50 70 37

    10 63 53 28

    25 63 74

    80 104 36.64

    100 123 47.2

    25 130 177 67.6

    50 130 134

    160 152 76.5

    200 189 95.1

    250 202 101.5

    50 320 275 138

    100 320

    400

    500

    VES measurements

    10

    100

    1000

    1 10 100 1000AB/2 (m)

    Rho (ohm

    m)

    Rho

    Rho shifted

  • P a g i n a | 12

    Interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 layer model with shifted data

    4 layer unshifted data

    Results including 90% confidence levels

    Depth (m) **) Rho (Ωm )

    topsoil (1000) 40 - 60 >1000

    *) the topsoil Rho can be phony representing electrode contacts, electric leakings

    **) the top of the layer

    Conclusion

    • Overburden relatively low resistivity 23 - 40

    • Basement at 40 – 60 m

    Strong lateral changes indicating geology changes in NE direction

    1 10 100 L/2

    10

    1e+2

    1e+3

    1 10 100 L/2

    10

    1e+2

    1e+3

  • P a g i n a | 13

    Kajiado VES sounding nr.4 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 17/02/2017

    General

    VES sounding for Sponge City project.

    Aim: finding locations for infiltration (highly weathered or fractured rock)

    Location name: across Gulley C at HEPline1 (in the direction of HEP line!!)

    Sounding Date : 15/02/2017

    Location

    VES sounding information

    Location: (WGS82): 36°46'22.90"E and Latitude 1°49'34.70"S

    Direction of sounding: NNE (across the structure, centre is just South the gulley bed)

    AB reach: 320 m

    Array: Schlumberger

    Elevation 1685 mas

    Groundwater (if any)

    Depth estimated at: 20m

    Measured data

    Remarks: There obviously are large lateral changes, both from structural changes in geology, but also because the VES

    centerpoint was stationed close to the bed of the gulley, having clay and loamy sand deposits (explaining the low resistivity at

    small AB/2 range. The shifted curve is remarkable due the method of shifting. Therefore , the shifted line was only used to up to

    AB/2 = 20m in the inversion.

    DATA table VES4

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 18 18

    2 18 18

    2.5 17 17

    3.2 15 15

    4 13 13

    5 12 12

    6.3 12 12

    8 13 13

    10 14 14

    0.5 13 20 20

    5 13 29

    16 37 26

    20 49 34

    25 65 44

    5 32 82

    10 32 57

    40 95 63

    50 89 59

    10 63 91 60

    25 63 131

    80 131 63

    100 145 69

    25 130 151

    50 130 374 69.21429

    160 385 71

    200 380 70

    250 464 86

    50 320 584 108

    100 320

    400

    500

    VES measurements

    10

    100

    1000

    1 10 100 1000AB/2

    Rho

    Rho

    Rho shifted

  • P a g i n a | 14

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 layer model with shifted (up to 20 m) data

    The model fit is not good (RMSE 9.28E-02) due to the many lateral changes

    4 layer model , unshifted data

    Results including 90% confidence levels

    Depth (m) Rho (ohmm)

    topsoil (1000)

  • P a g i n a | 15

    Kajiado VES sounding nr.5 Technical report

    Harry Rolf for SamSamWater Foundation 16/02/2017

    Client : Acacia Water

    General

    VES sounding for Sponge City project.

    Aim: finding locations for infiltration (highly weathered or fractured rock)

    Location name: street in Kajiado town (originally suggested for HEP line3)

    Sounding Date : 15/02/2017

    Location

    VES sounding information

    Location: (WGS82): 36046’59.1” E and Latitude 01050’21.7” S

    Direction of sounding: 2620 West-SouthWest

    AB reach: 260m (short due to buildings and risky power lines)

    Array: Schlumberger

    Elevation: 1720 mas

    Groundwater depth (if any)

    Estimated at: 55 mbgl

    Measured data

    Remarks: Shifting is reasonable (K3= 1.177) , minor lateral changes within this (short) reach

    DATA table VES5

    MN/2 AB/2 Rho SHIFTED

    0.5 1.6 122

    2 102

    2.5 93

    3.2 79

    4 72

    5 68

    6.3 72

    8 70

    10 72

    0.5 13 75

    5 13 72

    16 77 81

    20 100 104

    25 111 116

    5 32 122

    10 32 125 127

    40 133 135

    50 148 150

    10 63 170 167

    25 63 142

    80 185 219

    100 199 234

    25 130 237 279

    50 130

    160

    200

    250

    50 320

    100 320

    400

    500

    VES measurements

    10

    100

    1000

    1 10 100 1000AB/2

    Rho

    Rho

    SHIFTED

  • P a g i n a | 16

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    3 or 4 layer model with shifted data

    Basement layer (assuming ρ>1000 ohmm) very uncertain

    3 layer model

    4 layer model

    Results including 90% confidence levels

    Depth (m) Rho (Ωm)

    (top)

    topsoil (1000) >40

    *)Please note the topsoil Rho can be just a phony layer, representing electrode contacts, electric leaking

    Conclusion

    • Overburden is like 65 (60 – 70) Ωm.

    • Less weathered/fractured rock starts at ≈10 m

    • Fresh basement rock unknown, but at least deeper than 40m

    • No indications for substantial structural changes within the (short) AB reach

    1 10 100 L/2

    10

    1e+2

    1e+3

    1 10 100 L/2

    10

    1e+2

    1e+3

  • P a g i n a | 17

    Kajiado VES sounding nr.6 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 24/02/2017

    Client : Acacia Water

    General

    VES sounding for Sponge City project.

    Aim: finding locations for infiltration (highly weathered or fractured rock)

    Location name: at the location in Kajiado Town, close to a Sponge City test infiltration pit along roadwater runoff gully

    Sounding Date : 15/02/2017

    Location

    VES sounding information

    Location: (WGS84): 36047’28.8” E and Latitude 01050’24.1” S

    Direction of sounding: East-Northeast

    AB reach: 160 m (short due to buildings/powerlines)

    Array: Schlumberger

    Elevation: 1735 mas

    Estimated depth to groundwater (if any): 75 mbgl

    Measured data

    Remarks: Short AB electrode reach due to building restrictions. Measurements show large discontinuity at potential change at

    13m. The inversion of the unshifted data is too inaccurate. Inversion only done on the shifted data. This however is tricky

    because over the large shift in the data. The shift may be caused by serious fracturing, or….. ??

    DATA table VES 6

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 10.2 10.2

    2 9.8 9.8

    2.5 9.9 9.9

    3.2 10.3 10.3

    4 11 11

    5 12.4 12.4

    6.3 15 15

    8 15.5 15.5

    10 19.6 19.6

    0.5 13 20.8 20.8

    5 13 36.7

    16 43.5 25

    20 53.3 30

    25 58.3 33

    5 32 54.7 35

    10 32

    40 72.2 41

    50 84 48

    10 63 87

    25 63 94 53

    80 123 70

    100

    25 130

    50 130

    160

    200

    250

    50 320

    100 320

    400

    500

    VES measurements

    10

    100

    1000

    1 10 100AB/2 (m)

    Rho (ohm

    m)

    Rho

    Rho shifted

  • P a g i n a | 18

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    3 or 4 layer model with shifted data only

    3 layer model

    4 layer model

    Results including 90% confidence levels

    Depth (m) Rho (Ωm )

    (top)

    topsoil ------ 9 - 12 *)

    topsoil2 0.5 – 4 1 - 10

    Overburden 2 - 4 38 - 54

    Basement 20 – 90 >> 1000

    *)Please note the topsoil Rho can be just a phony representing electrode contacts, electric leaking

    Conclusion

    • Overburden is like 45 (38 - 54) Ωm, top starting at 2 – 4 m

    • Fresh basement rock below 20 m, not deeper than 90 m

    • VES is rather uncertain due to large shifts in the measured data

    • Considerable shift in the measurements may indicate fracture zone??

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    1e+4

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 19

    Kajiado VES sounding nr.7 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 01/03/2017

    Client : Acacia Water

    General

    VES sounding for Sponge City project.

    Aim: finding locations for infiltration (highly weathered or fractured rock)

    Location name: parallel to the Gully C (North bank) on HEPline1

    Sounding Date : 15/02/2017

    Location

    VES sounding information

    Location: (WGS82): 360 46’ 24.3” E and Latitude 010 49’ 33.0” S

    Direction of sounding: 300gr SEast

    AB reach: 800 m

    Array: Schlumberger

    Elevation 1690 mas

    Groundwater (if any)

    Depth estimated at: 25m

    Measured data

    Remarks: only minor lateral changes

    DATA table VES 7

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 96 96

    2 82 82

    2.5 76 76

    3.2 80 80

    4 87 87

    5 95 95

    6.3 111 111

    8 138 138

    10 146 146

    0.5 13 170 170

    5 13 195

    16 224 196

    20 238 208

    25 251 219

    5 32 269

    10 32 273 236

    40 278 274

    50 277 273

    10 63 289 285

    25 63 276

    80 299 308

    100 309 318

    25 130 370 381

    50 130 344

    160 410 455

    200 458 508

    250 497 552

    50 320 623 691

    100 320 548

    400 613 772

    500

    VES measurements

    10

    100

    1000

    1 10 100 1000AB/2 (m)

    Rho (ohm

    m)

    Rho

    Rho shifted

  • P a g i n a | 20

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 layer model with both shifted and unshifted data

    4 layer model, shifted data

    4 layer model, unshifted data

    Results including 90% confidence levels

    Depth (m) Rho (ohmm)

    topsoil (1000) 80 – 100 1300 – 1800

    *)Please note the topsoil Rho can be a phony layer representing electrode contacts, electric resistance

    Conclusion

    • Basement at 90 m (80 – 100) overlain by overburden 300 Ωm (290 -320)

    • No structural changes in 300 gr SE direction

    1 10 100 L/2

    10

    1e+2

    1e+3

    1 10 100 L/2

    10

    1e+2

    1e+3 VES7

    north of the gully

    (parrallel )

  • P a g i n a | 21

    Kajiado VES sounding nr.8 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 16/02/2017

    Client : Acacia Water

    General

    VES sounding for Sponge City project.

    Aim: finding locations for infiltration (highly weathered or fractured rock)

    Location name: in Kajiado town, behind the Mosque at school premises

    Sounding Date : 15/02/2017

    Location

    VES sounding information

    Location: (WGS82): 36047’25.3” E and Latitude 01050’27.8” S

    Direction of sounding: 2900 Northwest

    AB reach: 126 m (short due to school buildings)

    Array: Schlumberger

    Elevation: 1732mas

    Depth to groundwater (if any)

    Estimated at: ??

    Measured data

    Remarks: Discontinuity at AB/2 32m is considerable, maybe caused by e.g close-by buildings?

    DATA table VES 8

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 34 34

    2 29 29

    2.5 33 33

    3.2 37 37

    4 41 41

    5 43 43

    6.3 49 49

    8 50 50

    10 51 51

    0.5 13 52 52

    5 13 53

    16 56 56

    20 62 62

    25 66 66

    5 32 71

    10 32 83 71

    40 85 73

    50 94 80

    10 63 93 80

    25 63

    80

    100

    25 130

    50 130

    160

    200

    250

    50 320

    100 320

    400

    500

    VES measurements

    10

    100

    1 10 100AB/2 (m)

    Rh

    o (

    oh

    mm

    )

    Rho

    Rho shifted

  • P a g i n a | 22

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    3 layer model with shifted or unshifted data

    Basement layer (assuming ρ>1000 ohmm) beyond Depth of Investigation

    3 layer model, unshifted data

    3 layer model, shifted data

    Results including 90% confidence levels

    Depth (m) Rho (Ωm )

    topsoil (1000) >75

    *)Please note the topsoil Rho can be just a phony layer representing electrode contacts, electric leakings

    Conclusion

    • Overburden is like 54 (52-56) Ωm.

    • Weathered/Fractured rock (≈ 100 Ωm) starts at 10 (9-13) m.

    • Fresh basement rock unknown, but at least deeper than 75m

    • VES is too short to see any evidence of fracturing/structural lateral changes, though the measured shift at AB/2=32m may

    indicate a geological anomaly.

    1 10 100 L/2

    1

    10

    1e+2

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    Rho

  • P a g i n a | 23

    Kajiado VES sounding nr.9 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 01/03/2017

    Client : Acacia Water

    General

    VES sounding for Sponge City project.

    Aim: finding locations for infiltration (highly wheathered or fractured rock)

    Location name: end of HEP line2, SW of the Gully B orthogonal to HEPline

    Sounding Date : 15/02/2017

    Location

    VES sounding information

    Location: (WGS82): 360 46’ 17.2” E and Latitude 010 50’ 17.3” S

    Direction of sounding: SEast- NW

    AB reach: 1000 m

    Array: Schlumberger

    Elevation 1710 mas

    Groundwater (if any)

    Depth estimated at: 50m

    Measured data

    Remarks: The shifting is wrong due to an error outlier measurement at AB/2 = 63. Beyond that point (63) , the unshifted data

    were used in the inversion.

    DATA table VES 9

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 231 231

    2 228 228

    2.5 201 201

    3.2 176 176

    4 169 169

    5 151 151

    6.3 153 153

    8 144 144

    10 141 141

    0.5 13 130 130

    5 13 153

    16 143 121

    20 135 116

    25 123 105

    5 32 125

    10 32 131 107

    40 132 107

    50 135 110

    10 63 83 67

    25 63 126

    80 151 81

    100 171 92

    25 130 210 112

    50 130 189

    160 244 145

    200 274 162

    250 317 187

    50 320 377 223

    100 320 357

    400 430 268

    500 466 291

    VES measurements

    10

    100

    1000

    1 10 100 1000AB/2 (m)

    Rho (ohm

    m)

    Rho

    Rho shifted

  • P a g i n a | 24

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 layer model with shifted or unshifted data

    4 layer shifted data

    4 layer model, unshifted data

    Results including 90% confidence levels

    Depth (m) Rho (ohmm)

    topsoil ------ 250 - 300 *)

    overburden 1 - 2 130 - 150

    Shallow aquifer 8 - 15 85 - 110

    Basement 50 - 70 700 – 900 (just below 1000)

    *)Please note the topsoil Rho can be phony layer representing electrode contacts, electric leaking

    Conclusion

    • Basement at ≈60 m (50 – 70) overlain by shallow aquifer and overburden

    • Basement resistivity is relatively low (just below 1000 Ωm).

    • Minor/ no structural changes in SE direction

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    1e+2

    1e+3

  • P a g i n a | 25

    Kajiado VES sounding nr.10 and 12 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 26/02/2017

    Client : Acacia Water

    General

    Two perpendicular VES soundings ISGEAG geophysical project .

    Aim: reconnaissance to find interesting locations to test contemporary geophysical methods

    Location name: NW of Kajiado town Two perpendicular VES soundings in between 2 branches of Kajiado river (Kajiado river

    branch and Imutatin river branch in the West)

    Sounding Date : 17/02/2017

    Location

    VES sounding information

    Location: (WGS82): 360 46’ 02.3” E and Latitude 01048’ 50.9” S

    Direction of sounding: North - South (Ves10) and East West (Ves 12) ,

    AB reach: 1000 m

    Array: Schlumberger

    Elevation: 1680 mas

    Depth to groundwater (if any)

    Estimated at: 15 - 20 m

  • P a g i n a | 26

    Measured data VES10

    Measured data VES12

    Remarks: Apart from the (unexplained) discontinuity in VES12 (at AB/2=13 m) there is no big difference in lateral changes

    between the two soundings.

    It is not clear whether the discontinuity in VES12 actually due to a change in geology or a measurement error

    DATA table VES 10

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 42.8 42.8

    2 38.7 38.7

    2.5 43.2 43.2

    3.2 44.4 44.4

    4 51.2 51.2

    5 45.9 45.9

    6.3 49.5 49.5

    8 50.9 50.9

    10 51.1 51.1

    0.5 13 49.1 49.1

    5 13 45.5

    16 51.2 55.3

    20 59.8 64.6

    25 72.7 78.6

    5 32 91.6

    10 32 84.1 99

    40 103.9 122.3

    50 127.5 150.2

    10 63 164 193

    25 63 131

    80 157 231

    100 192 283

    25 130 247 364

    50 130 256

    160 307 436

    200 378 537

    250 445 632

    50 320 513 728

    100 320 553

    400 654 861

    500 928 958

    VES measurements

    10

    100

    1000

    10000

    1 10 100 1000AB/2 (m)

    Rh

    o (

    oh

    mm

    )

    Rho

    Rho shifted

    DATA table VES 12

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 64 64

    2 60 60

    2.5 64 64

    3.2 69 69

    4 75 75

    5 75 75

    6.3 82 82

    8 84 84

    10 87 87

    0.5 13 98 98

    5 13 56

    16 60 104

    20 70 122

    25 82 144

    5 32 101

    10 32 93 177

    40 113 215

    50 143 272

    10 63 179 341

    25 63 173

    80 198 391

    100 218 430

    25 130 227 448

    50 130 230

    160 279 544

    200 344 671

    250 381 743

    50 320 497 969

    100 320 485

    400 628 1254

    500 765 1528

    VES measurements

    10

    100

    1000

    10000

    1 10 100 1000AB/2 (m)

    Rh

    o (

    oh

    mm

    )

    Rho

    Rho shifted

  • P a g i n a | 27

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    5 layer model with shifted or unshifted data

    VES10 Unshifted 5 layer

    VES12 5layer model , first measurements shifted down

    Results including 90% confidence levels

    Depth (m) Rho (Ωm )

    topsoil (1000) 120 - 200 >>>>1000 Ωm

    Conclusion

    • Overburden layer accurately 44 – 70 Ωm

    • Shallow 300 – 500 Ωm aquifer and

    • deep, high resistive basement > 120m (like 150m)

    • Apart from the unexplained shift in (the first - shallow - part of VES12) there are no indications for large structural changes

    in both directions.

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    10

    1e+2

    1e+3

    1e+4

    1e+5

    1e+6

    Rho

  • P a g i n a | 28

    Kajiado VES sounding nr.11 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 26/02/2017

    Client : Acacia Water

    General

    VES sounding for VIA Water ISGEAG project.

    Aim: finding locations , fracture zones for the ISGEAG geophysical methods project

    Location name: on the Kajiado river bed South of Haraf Borehole

    Date : 17/02/2017

    Location

    VES sounding information

    Location: (WGS82): 360 45’ 50.6” E and Latitude 010 49’ 46.3” S

    Direction of sounding: SSWest on the river bed ,

    AB reach: 1000 m

    Array: Schlumberger

    Elevation: 1670 mas

    Depth to groundwater (if any)

    Estimated at: 20 m

    VES interpretation

    Measured data

    Remarks: just minor discontinuity (lateral changes)

    DATA table VES 11

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 110.95 110.95

    2 80.9 80.9

    2.5 73.6 73.6

    3.2 69.8 69.8

    4 72.5 72.5

    5 78 78

    6.3 89.8 89.8

    8 96.3 96.3

    10 101.3 101.3

    0.5 13 111 111

    5 13 109

    16 112 114

    20 118 120

    25 116 118

    5 32 116 117

    10 32 118

    40 121 120

    50 125 125

    10 63 139 139

    25 63 134

    80 162 168

    100 197 204

    25 130 291 301

    50 130 268

    160 319 358

    200 400 448

    250 490 550

    50 320 606 680

    100 320 565

    400 705 850

    500 794 957

    VES measurements

    10

    100

    1000

    10000

    1 10 100 1000AB/2 (m)

    Rh

    o (

    oh

    mm

    )

    Rho

    Rho shifted

  • P a g i n a | 29

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 or 5 layer model with shifted or unshifted data

    4 layer model , unshifted data

    5 layer model with shifted data

    Results including 90% confidence levels

    Depth (m) Rho (Ωm )

    topsoil (1000) 35 (25-43)*) 5000 ((>3000)

    *) see sensitivity analysis below

    Conclusion

    • The 5 layer model concept (basement overlain by a less resistive layer) has a significantly better fit, but the parameters are

    uncertain

    • Accepting the 5 layer concept, sensitivity analysis indicates basement depth in between 25 a 43 m

    • No indications of fracturing (in this SSW direction)

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    1e+4

    Rho

  • P a g i n a | 30

    Sensitivity analysis

    Sensitivity analysis on the 5 layer model (shifted data) shows the following:

    The optimal RMSE fit is 1.51*10-2. Any solution within a 10% less good fit (RMSE < 1.66 *10-2) is acceptable

    Minimizing (and fixing) the basement depth shows a (still mathematically acceptable) solution as:

    Minimized basement depth (at 16m, RMSE = 1.56*10-2) mathematically possible, but it is most unlikely that the sounding can

    ‘see’ such a thin low resistivity layer.

    And maximizing basement depth gives a (maximal) solution as follows:

    Maximum basement depth solution (basement at 43m RMSE = 1.65*10-2)

    From this we conclude that basement depth is somewhere in between ≈25m and 43m

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    1e+4

    Rho

    RMSE = 1.56

    1 10 100 L/2

    10

    1e+2

    1e+3

    1e+4

    Rho

    RMSE = 1.65

  • P a g i n a | 31

    Kajiado VES sounding nr.13 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 26/02/2017

    Client : Acacia Water

    General

    VES sounding for Sponge City project.

    Aim: finding locations for infiltration (highly weathered or fractured rock)

    Location name: on the Gully bed (Northern runoff-gully c) in the centre of HEP profile 1

    Sounding Date : 16/02/2017

    Location

    VES sounding information

    Location: (WGS82): 360 46’ 23.4” E and Latitude 010549’ 34.4” S

    Direction of sounding: SEast on top of the gulley bed ,

    AB reach: 126 m

    Array: Schlumberger

    Elevation: 1682 mas

    Depth to groundwater (if any)

    Estimated at: 20 m

    Measured data

    Remarks: Only minor discontinuities (at AB/2=32m)

    DATA table VES 13

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 34 34

    2 15.3 15.3

    2.5 14 14

    3.2 14.2 14.2

    4 14.1 14.1

    5 15.2 15.2

    6.3 17.3 17.3

    8 21.9 21.9

    10 26.2 26.2

    0.5 13 35.5 35.5

    5 13 32.9

    16 40.5 43.7

    20 52.5 56.7

    25 76.6 82.7

    5 32 106.1

    10 32 95.1 114.6

    40 126.9 154.1

    50 171 206

    10 63 229.5 276.6

    25 63

    80

    100

    25 130

    50 130

    160

    200

    250

    50 320

    100 320

    400

    500

    VES measurements

    10

    100

    1000

    10000

    1 10 100AB/2 (m)

    Rho (ohm

    m)

    Rho

    Rho shifted

  • P a g i n a | 32

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    3 or 4 layer model with shifted or unshifted data

    3 layer Unshifted data

    4 layer Shifted data

    Results including 90% confidence levels

    Depth (m) Rho (Ωm )

    topsoil (1000) 4 – 5 >>>1000

    Conclusion

    • Topsoil is representing the clayey sand deposits on the gully bed

    • Thickness of these deposits is 3 – 4 m

    • Right below the gully bed there is high resistive fresh basement rock at ≈ 4 m depth

    • No signs of lateral changes is this direction , no indications of fracturing (in this direction)

    Remark:

    Other experiments (visual and logger data) prove that water infiltrates at this location from the gully into the subsoil. There

    must be major permeable fractures right to the North or South gulley bank allowing this vertical infiltration

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    1e+4

    1e+5

    Rho

  • P a g i n a | 33

    Kajiado VES sounding nr.14 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 18/04/2017

    Client : Acacia Water

    General

    VES sounding for VIA Water ISGEAG project.

    Aim: underground at West side of HEP8 line (having a constant resistivity of ≈60 ohmm)

    Location name: Kajiado River, close to Osiligi farm at the West end of ISGEAG HEP profile 8

    Date : 18/04/2017

    Location

    VES sounding information

    Location: (WGS84): 360 45’ 53.4” E and Latitude 010 49’ 03.4” S

    Direction of sounding: N-South

    AB reach: 400 m

    Array: Schlumberger

    Elevation: 1675 mas

    Depth to groundwater (if any)

    Estimated at: 20 m

    Measured data

    Remarks: Only minor discontinuity at AB/2=130m

    DATA table VES14

    # MN/2 AB/2 Rho Rho shifted

    0.5 1.6 18.6

    2 20.4

    2.5 20

    3.2 18.1

    4 15.3

    5 12.6

    6.3 10.4

    8 8.4

    10 7.5

    0.5 13 8.5

    5 13 8

    16 9.7

    20 12

    25 13.9

    5 32 18.2

    10 32 17.1

    40 23.1

    50 30.9

    10 63 43.2

    25 63 46.6

    80 65

    100 85.4

    25 130 116.6

    50 130 100.8

    160 128.5

    200 174.3

    250

    50 320

    100 320

    400

    500

    VES measurements

    1

    10

    100

    1000

    1 10 100 1000AB/2 (m)

    Rho (ohm

    m)

    Rho

    Rho shifted

  • P a g i n a | 34

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 or 5 layer model unshifted data

    4 layer model , clay right on top of very high resistive basement

    5 layer model, having an ‘in between’ layer below the clay overlaying basement

    Results including 90% confidence levels (

    Depth (m) Rho (Ωm)

    (top of the layer)

    topsoil (>>1000

    Conclusion

    • Clay layer on top of shallow very high resistive rock (hardcap?)

    1 10 100 L/2

    0.1

    1

    10

    1e+2

    1e+3

    1e+4

    1e+5

    1e+6

    Rho

  • P a g i n a | 35

    Kajiado VES sounding nr.15 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 21/04/2017

    Client : Acacia Water

    General

    VES sounding for VIA Water ISGEAG project.

    Aim: to confirm ERT2 results at Kajiado River

    Location name: 65 m East of the ERT profile centre

    Date : 21/04/2017

    Location

    VES sounding information

    Location: (WGS84): 360 45’ 59.8” E 010 49’ 03.5” S

    Direction of sounding: 195 azimuth S-N

    AB reach: 1000 m

    Array: Schlumberger

    Elevation: 1692 mas

    Depth to groundwater (if any)

    Estimated at: 30 m

    Measured data

    Remarks: major discontinuities. The south line was close to powerline at AB/2=250 m (or even passed the river bed?)

    DATA table VES15

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 308 355.432

    2 331 381.974

    2.5 367 423.518

    3.2 394 454.676

    4 380 438.52

    5 389 448.906

    6.3 384 443.136

    8 382 440.828

    10 352 406.208

    0.5 13 337 388.898

    5 13 389

    16 348 348

    20 334 334

    25 278 278

    5 32 249 249

    10 32 258 257

    40 248 248

    50 227 227

    10 63 237 237

    25 63 222 222

    80 242 242

    100 265 265

    25 130 303 303

    50 130 293 293

    160 325 325

    200 389 389

    250 384

    50 320 404

    100 320 441 539.784

    400 532 651.168

    500 591 723.384

    VES measurements

    100

    1000

    1 10 100 1000AB/2 (m)

    Rh

    o (

    oh

    mm

    )

    Rho

    Rho shifted

  • P a g i n a | 36

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 layer unshifted or shifted

    4 layer model unshifted data

    4 layer model shifted data

    Results including 90% confidence levels (

    Depth (m) Rho (Ωm)

    (top of the layer)

    topsoil 0 (340 – 700)

    Overburden 7 (2 – 12) ( 185 – 210)

    Basement (ρ>1000) 80 (65 – 95) >800

    Conclusion

    • Shallow aquifer

    • Basement (not very high resistive) at 80m

    Discontinuities may be caused by anomalies or by passing powerline or river bed

    1 10 100 L/2

    1e+2

    1e+3

    1 10 100 L/2

    10

    1e+2

    1e+3

  • P a g i n a | 37

    Kajiado VES sounding nr.16 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 23/04/2017

    Client : Acacia Water

    General

    VES sounding for VIA Water ISGEAG project.

    Aim: to confirm ERT1 anomaly results at Gully C

    Location name: , Kajiado Osiligi , Northern run-off Gully C about 130 m North East of the Gulley bed, on HEPline/ERT line 1

    Date : 23/04/2017

    Location map

    VES sounding information

    Location: (WGS84): 360 46’ 25.2” E 010 49’ 31.9” S

    Direction of sounding: 295 GR azimuth SE-NW

    AB reach: 1000 m

    Array: Schlumberger

    Elevation: 1687 mas

    Depth to groundwater (if any)

    Estimated at: 25 m

    Measured data

    DATA table VES16

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6 37 37

    2 42.4 42.4

    2.5 49.2 49.2

    3.2 58.9 58.9

    4 73.5 73.5

    5 88.9 88.9

    6.3 104 104

    8 116 116

    10 131 131

    0.5 13 147

    5 13 129 147

    16 153 174.35

    20 161 183.47

    25 161.4 183.92

    5 32 174

    10 32 203 198.28

    40 215 210

    50 239 233.44

    10 63 277

    25 63 279 270.56

    80 315 305.47

    100 353 342.32

    25 130 422

    50 130 349 409.23

    160 389 456.13

    200 421 493.66

    250 494 579.26

    50 320 606

    100 320 527 710.59

    400 584 787.44

    500 599 807.67

    VES measurements

    10

    100

    1000

    1 10 100 1000AB/2 (m)

    Rh

    o (

    oh

    mm

    )

    Rho

    Rho shifted

  • P a g i n a | 38

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 or 5 layer model shifted data

    (the unshifted data have too many discontinuity)

    4 layer model shifted data

    5 layer model , shifted data

    There is reason to believe, and to accept the 5 layer model (it corresponds with the findings in the ERT tomography), the

    uncertainty though is high.

    Results including 90% confidence levels

    Depth (m) Rho (Ωm)

    (top of the layer)

    topsoil (1000) 76 (40 – 160) 1250 (1000 – 1500)

    *) large: meaning that uncertainty is high and not quantifiable

    Conclusion

    • Basement depth uncertain; shallow aquifer in the order of 500 ohmm possibly below a (57 ohmm) sub-layer

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 39

    Kajiado VES sounding nr.17 and 18 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 25/04/2017

    Client : Acacia Water

    General

    VES sounding for VIA Water ISGEAG project Kajiado.

    Aim: to confirm fracturing at HARAF Traders borehole at Kajiado River

    The HARAF borehole is probably the best yielding borehole in Kajiado. It is believed to abstract water from a major regional

    fracture zone close to Kajiado river. Unfortunately no documents (from the borehole survey, nor from borehole completion and

    drillers’ log, could be made available.

    Two VES soundings were conducted in two directions, close to the borehole, mainly to detect fracture structures. The positioning

    of the VES lines was restricted by local powerlines and river beds.

    The co-operation the owner Mr. Osman is highly appreciated

    Location name: , Kajiado (Olkuajado) river close to HARAF Traders borehole

    Souning date : 25/04/2017

    Location

    Location details. The center-points of the two VESs were 10 m apart, about 40 m NE of the HARAF traders borehole

  • P a g i n a | 40

    VES 17 and 18 sounding information

    Location: (WGS84): VES17: 360 46’ 03.8” E 010 49’ 11.0” S

    VES18: 360 46’ 03.5” E 010 49’ 11.1” S

    Direction of sounding: VES17: azimuth 360gr. S-N

    VES18: azimuth 67gr ENE

    AB reach: VES17: 500 m

    VES18: 320 m

    Array: Schlumberger

    Elevation: 1675 mas

    Depth to groundwater

    Estimated at: 15 m (SWL from data logger observations in the borehole)

    Measured data

    Remarks:

    Although the centerpoints were just 10 m apart, there is a striking difference in the field curves, both in the absolute level and

    the discontinuity (AB/2 = 63m) in VES18.

    VES17 was done parallel to the believed N-S fractured structure direction and VES18 was across the structure direction.

    VES17 has passed the river bed on the south side at AB/2 = 150 m.

    DATA table

    MN/2 AB/2 VES17 VES18

    0.5 1.6 18.3 139

    2 17 166

    2.5 16 191

    3.2 16 200

    4 17 189

    5 17.9 170

    6.3 19.2 141

    8 20.4 98

    10 21.9 84

    0.5 13 24.9 80

    5 13 26.7 73

    16 30.1 77

    20 35 91

    25 42.3 108

    5 32 52.1 122

    10 32 56.3 112

    40 64 134

    50 75.4 148

    10 63 93.6 179

    25 63 89 127

    80 125 171

    100 165 171

    25 130 236 214

    50 130 236 211

    160 282 249

    200 349

    250 558

    50 320

    100 320

    400

    500

    VES measurements

    10

    100

    1000

    1 10 100 1000AB/2 (m)

    Rh

    o (

    oh

    mm

    )

    VES17

    VES18

  • P a g i n a | 41

    VES interpretation VES17

    VES17 Inversion results (SchlumBG modelling)

    Possible model concepts

    3 or 4 layer model unshifted data

    3 layer unshifted

    4 layer unshifted

    VES17 Results including 90% confidence levels

    Depth (m) Rho (Ωm)

    (top of the layer)

    topsoil (1000) 12 (10 – 15) >>>1000

    Conclusion VES17

    • High resistive basement at ≈10 – 15 m depth

    • No indication of fracture zone (discontinuity)

    1 10 100 L/2

    10

    1e+2

    1e+3

    1e+4

    1e+5

    1e+6

    Rho

    1 10 100 L/2

    10

    1e+2

    1e+3

    1e+4

    1e+5

    1e+6

    Rho

  • P a g i n a | 42

    VES18 Inversion results (SchlumBG modelling)

    Possible model concepts

    5 layer model unshifted or shifted data

    5 layer unshifted

    5 layer unshifted leaving out last measurements

    5 layer with shifted data

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 43

    VES18 Results including 90% confidence levels

    Depth (m) Rho (Ωm)

    (top of the layer)

    topsoil (1000) 80 (>30)) >1000

    Conclusion VES18

    • Shallow clay layer

    • Basement at 80 m

    • Discontinuity at potential electrode change AB/2 = 63m

    Comparing VES17 and VES18

    Although the two soundings are just 10 m apart, there is a clear difference:.

    • Basement in VES18 is deeper and there is a shallow clay layer.

    • Basement resistivity in VES17 is higher.

    This indicates a significant difference in lithology within short range. Remaining question is: why doesn’t VES18 show

    discontinues measurements at the short range, and only at AB/2 = 63??

    VES17 VES18

    1 10 100 L/2

    10

    1e+2

    1e+3

    1e+4

    1e+5

    1e+6

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 44

    Kajiado VES /IP sounding nr.19 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 26/04/2017

    Client : Acacia Water

    General

    VES sounding for VIA Water ISGEAG project.

    Aim: to confirm TDEM sounding at the east end of ERT line2

    Location name: Kajiado on the East bank of Kajiado River (end of HEP line 8 and ERT line2)

    Date : 26/04/2017

    Location

    VES sounding information

    Location: (WGS84): 360 46’ 11.6” E 010 49’ 06.2” S

    Azimuth of sounding: 205 GR SSW

    AB reach: 1000 m

    Array: Schlumberger

    Elevation: 1675 mas

    Depth to groundwater (if any)

    estimated at: 15 m

  • P a g i n a | 45

    Measured data Resistivity (Ωm) and IP (mS)

    Remarks:

    When the measured line showed large discontinuity 2 additional points (in blue) were measured with a larger MN/2 of 100m

    instead of 50m (red points).

    obviously a major geological change was reached at ≈ AB/2 100 m (or even at 63 m).

    DATA table

    MN/2 AB/2 VES19 MN/2 100

    0.5 1.6 116

    2 135

    2.5 140

    3.2 159

    4 167

    5 154

    6.3 119

    8 132

    10 125

    0.5 13 130

    5 13 119

    16 127

    20 139

    25 156

    5 32 179

    10 32 173

    40 207

    50 233

    10 63 249

    25 63 239

    80 219

    100 207

    25 130 230

    50 130 216

    160 217

    200 199 262

    250 216 319

    50 320 242

    100 320 370

    400 471

    500 652

    DATA table IP

    MN/2 AB/2 VES19 MN/2 100

    0.5 1.6 0.21

    2 0.19

    2.5 0.2

    3.2 0.21

    4 0.24

    5 0.27

    6.3 0.24

    8 0.43

    10 0.67

    0.5 13 0.75

    5 13 0.75

    16 0.75

    20 0.75

    25 0.77

    5 32 0.9

    10 32 1.08

    40 1.12

    50 1.44

    10 63 2.1

    25 63 1.89

    80 1.97

    100 2.89

    25 130 1.94

    50 130 2.1

    160 2.09

    200 2.23 2.71

    250 2.49 3.68

    50 320 2.67

    100 320 2.33

    400 2.82

    500 4.96

    VES measurements

    100

    1000

    1 10 100 1000AB/2 (m)

    Rh

    o (

    oh

    mm

    )

    MN/2 100

    VES19

    IP measurements

    0

    1

    2

    3

    4

    5

    6

    1 10 100 1000AB/2 (m)

    IP (

    mS

    )

    MN/2 100

    VES19

  • P a g i n a | 46

    VES interpretation

    (IP interpretation is not discussed here)

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 layer only using the data up to AB/2 = 63 m

    Or

    6 layer using the full measurements and leaving out the 3 points with MN/2 50 at 200, 250 and 320 m

    4 layer using only data up to AB/2 = 63m

    6 layer model

    Overall results including 90% confidence levels (between brackets)

    Depth (m) Thickness (m) Rho (Ωm)

    (top of the layer)

    topsoil (10 500 (300 – 800)

    Basement (ρ>1000) > 25 >1000

    Alternative interpretation:

    Low resistive layer 24 (large) 9 13 (large)

    Basement 33 (large) >>> 1000

    Conclusion

    • Measurements show major discontinuity at AB/2 > 63 m indicating lateral lithological changes

    • Basement deeper than 25 m, may be at 33m (with large uncertainty) underlaying a low resistivity weathered zone between

    24 and 33 m.

    To better detect anomalies it makes sense to measure parallel with alternative MN potential electrode distances

    IP measurements show discontinuities at larger range as well. Shallow IP confirms that there are no shallow clay layers

    1 10 100 L/2

    10

    1e+2

    1e+3

    1 10 100 L/2

    10

    1e+2

    1e+3

    1e+4

  • P a g i n a | 47

    Kajiado VES nr.20 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 27/04/2017

    Client : Acacia Water

    General

    VES sounding for VIA Water ISGEAG project.

    Aim: to confirm ERT/TDEM soundings in the centre of ERT line2

    Location name: ,Kajiado ,Ildamat, Osiligi , Kajiado River

    Sounding date : 27/04/2017

    Location

    VES sounding information

    Location: (WGS84): 360 46’ 04.3” E 010 49’ 03.7” S

    Azimuth of sounding: 7 degrees NS

    AB reach: 400 m

    Array: Schlumberger

    Elevation: 1680 mas

    Depth to groundwater (if any)

    estimated at: 15 m

    Measured apparent resistivity data (Ωm)

    Remarks:

    Discontinuity at AB/2 = 63m. The AB reach is short; the sounding had to be stopped due to planned TDEM measurements at the

    same location.

    DATA table

    VES20

    MN/2 AB/2 Rho Rho shfted

    0.5 1.6 86 86

    2 103 103

    2.5 116 116

    3.2 119 119

    4 125 125

    5 121 121

    6.3 112 112

    8 86 86

    10 79 79

    0.5 13 72 72

    5 13 74 74

    16 72 72

    20 71 71

    25 78 78

    5 32 102 102

    10 32 106 106

    40 127 127

    50 150 150

    10 63 179

    25 63 151 179

    80 174 206

    100 196 232

    25 130 246 292

    50 130 234 277

    160 289 343

    200 338 401

    250

    50 320

    100 320

    400

    500

    VES measurements

    10

    100

    1000

    1 10 100 1000AB/2 (m)

    Rho (ohm

    m)

    Rho shfted

    Rho

  • P a g i n a | 48

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    5 layer model with unshifted or shifted data

    5 layer model, basement can be anywhere deeper than 55 m

    5 layer model shifted data basement anywhere deeper than 45 m

    Overall results including 90% confidence levels (

    Depth (m) Thickness (m) Rho (Ωm)

    (top of the layer)

    topsoil (1000) 90 (> 45) 2500 (>1000)

    Conclusion

    • Clay layer

    • Basement depth uncertain but anywhere deeper than 45 m

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 49

    ERT comparison

    The ERT2 profile (ISGEAG research) shows a high resistive ‘hard cap’ at 25 m, overlying a less resistive (250 ohmm) zone and the

    actual basement somewhere at 100m.

    We forced the interpretation (by fixing layer parameters) to see if the VES data could correspond with such a solution.

    The answer is YES it could (see graphs below), but any solution of such reverted low resistivity under a high resistivity is possible.

    So this cannot be found without additional knowledge (the ERT info in our case).

    Reverted low resistivity below a ‘hard cap’ high resistivity (VES20 6 layers, unshifted data)

    Reverted low resistivity below a ‘hard cap’ high resistivity (VES20 6 layers, shifted data)

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 50

    Kajiado VES /IP sounding nr.21 Technical interpretation report

    Harry Rolf for SamSamWater Foundation 30/04/2017

    Client : Acacia Water

    General

    VES sounding for VIA Water ISGEAG project, to verify an existing VES sounding

    Aim: to confirm VES4 (clay on top of basement) from survey report (Kariuki for mr. Osman, HARAF

    Location name: Kajiado, Ildamat, Osiligi , at HARAF farm West of Kajiado River.

    Sounding date : 28/04/2017

    Location

    VES sounding information

    Location: (WGS84): 360 45’ 54.4” E 010 49’ 25.9” S

    Azimuth of sounding: 7 degr. NSouth

    AB reach: 160 m

    Array: Schlumberger

    Elevation: 1670 mas

    Depth to groundwater (if any)

    estimated at: 5 m

    Measured data Resistivity (Ωm) and IP (mS)

    Remarks:

    discontinuity in measurements at AB/2 40m. indicating fracture/lateral change. Measurements > 32 m left out in the inversion.

    DATA table VES21

    MN/2 AB/2 Rho IP (mS)

    0.5 1.6 23 0.23

    2 23 0.23

    2.5 21 0.2

    3.2 19 0.19

    4 16 0.23

    5 14 0.47

    6.3 13 0.46

    8 13 1.12

    10 14 0.94

    0.5 13 18 0.47

    5 13 19 0.46

    16 24 0.82

    20 29 0.85

    25 36 1.48

    5 32 56 1.1

    10 32 52 1

    40 56 1.73

    50 65 1.93

    10 63 82 2.04

    25 63 76 1.94

    80 99 2.48

    100

    25 130

    50 130

    160

    200

    250

    50 320

    100 320

    400

    500

    VES measurements

    0.1

    1

    10

    100

    1 10 100

    AB/2 (m)

    Rho (ohmm)

    Rho

    IP (mS)

  • P a g i n a | 51

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    3 layer Measurements > 32m left out

    Overall results including 90% confidence levels (

    Depth (m) Thickness (m) Rho (Ωm)

    (top of the layer)

    topsoil (1000) 3.4 >>>>1000

    Conclusion

    • This verification VES clearly shows a shallow clay layer on top of high resistive (basement) rock

    • Discontinue measurements (>40m) indicate anomaly (fractured?)

    The results of this VES can be compared with the VES4 results in the existing survey report, see

    borehole survey for Mr. Osman, HARAF farm near Kajiado River, page @

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 52

    Kajiado mini VES Technical interpretation report

    Harry Rolf for SamSamWater Foundation 27/09/2017

    Client : Acacia Water

    General

    Mini VES sounding for VIA Water ISGEAG project.

    Aim: short range VES to test the resistivity of the clay topsoil and training purposes

    Location name: ,Kajiado ,Ildamat, Kajiado River on West-East HEP/ERT profile

    Sounding date : 27/04/2017

    Location

    VES sounding information

    Location: (WGS84): 1°49'3.50"S 36°46'8.04"E

    Azimuth of sounding: Northeast - Southwest

    AB reach: 64 m

    Array: Schlumberger

    Elevation: 1676 mas

    Depth to groundwater (if any)

    estimated at: 15 m

    Measured apparent resistivity data (Ωm)

    Remarks:

    The mini VES sounding was conducted at a location where compact clays were found (and confirmed by shallow hand drillings).

    The electrode distances are very short, starting with potentials at only 5 cm and current electrodes at only 20 cm from the

    centre point (see photo). The electrode distances were increased in small steps, from 20cm, 40cm,… up to AB/2 of 32 m.

    The field curve shows apparent resistivity initially going down and consequently going up when the current starts passing the

    bottom of the clay layer.

    VES measurements

    1

    10

    100

    0.1 1 10 100AB/2 (m)

    Appare

    nt re

    sis

    tivity

    (ohm

    m)

    DATA table

    Mini VES

    MN/2 AB/2 Rho

    0.05 0.2 14

    0.4 9.8

    0.8 8.7

    1.6 7.8

    3 7.9

    6

    0.5 6 9.6

    12 15

    20 24

    32 38

    5 32 39

  • P a g i n a | 53

    Foto ISGEAG field team conducting mini VES (a ‘veeeeery small ves’)

    VES interpretation

    Inversion results (SchlumBG modelling)

    The SchlumBG software assumes the AB/2 distances are in meters. SchlumBG in this case appears to have difficulties with the

    data points within one meter. Since the inversion mathematics is linear with electrode distance, the distances are multiplied by

    factor 10 to avoid the software problem. The layer model depth results are therefore in dm (decimetres).

    Possible model concepts

    3layer model (note: electrode distance in decimetres!

    Overall results including 90% confidence levels (

    Depth (m) Thickness (m) Rho (Ωm)

    (top of the layer)

    topsoil (1000 ohmm basement)

    • According to the ‘rule of thumb’ the Depth of Investigation (1/6 of AB) in this case is like 10 m (AB = 64m)

    1 10 100 L/2

    1

    10

    1e+2

    Rho

    layer depth in dm!!

  • P a g i n a | 54

    Existing survey reports The following section contains the re-interpretation of VES soundings from existing survey reports in the area of Kajiado

    Town

  • P a g i n a | 55

    MTTI Masai Technical Training institute survey re-interpretation of VES soundings report

    Harry Rolf for SamSamWater Foundation 26/02/2017

    Client : Acacia Water

    General

    Existing survey report: Hydrogeological survey for Masai Technical Training Institute, Kajiado. Report nr. AWS/1572/2008;

    S.N.Njoroge. Aquawell Services Nairobi, February 2008

    Aim: verification/re-interpretation of existing VES sounding data

    Location

    VES sounding information

    Location: (WGS82): unknown (general location MTTI compound = 36°46'55.3"E 1°51'16.1"S)

    Direction of sounding: ?

    AB reach: 400 m

    Array: Schlumberger

    Elevation: 1715 - 1730mas

    Depth to groundwater (if any)

    Estimated at: ??

    MTTI VES Measured data (for numbers, see report)

    Remarks

    VES4 was advised for drilling, the data may have been shifted to get smooth curves

    VES Graphs MTTI (survey report)

    10

    100

    1000

    1 10 100 1000

    AB/2 (m)

    Resis

    tivity

    MTTI VES1MTTI VES3MTTI VES2MTTI VES4

    Dry boreholes issue The MTTI survey comprised 2 HEP lines and 4 VES soundings. Unfortunately the precise locations are not given in the report. (in the

    report the VES soundings all have the same coordinates)

    Striking fact is that two borehole were initially drilled at the MTTI parcel, both were found dry.

    According to a visit paid on 15 Feb 2017 (info Mr. Stephen Musyimi, (0725326932) the situation became more clear. The first dry

    borehole (1) (): 36°46'58.83"E 1°51'9.42"S) presumably was drilled at location of VES4 (as advised in the survey report). The second

    dry drilling, at 36°46'56.52"E 1°51'30.75"S most likely was at VES1 location. This drilling had a water strike at 70mbgl, but the water

    ‘disappeared’ when drilling continued to 90 mbgl)

    Later (unknown date) a third, good yielding borehole was drilled at 36°47'2.71"E 1°51'9.63"S, just 120 m East of the dry borehole

    (1). This borehole is presently known as the Masai Tech borehole. Unfortunately no technical borehole documents could be

    made available.

  • P a g i n a | 56

    MTTI VES1 interpretation

    Possible model concepts

    Survey report MODEL VES1

    (re-interpreted) 6 layer model

    There may as well (giving the same fit) be basement (1000ohmm) at 80 m:

    8 layer model with basement at 80m

    Results VES1 (90% confidence levels)

    Depth (m) Rho (Ωm )

    topsoil (1000) anywhere > 80m

    Conclusion

    • Due to the undulations in the field curve, many solutions are possible

    • Unknown to what extend the measured data are corrected and whether these undulations are realistic

    • Up to 20 m (‘overburden’) a variety of low and mediate resistivities

    • Basement may be anywhere below 80 m

  • P a g i n a | 57

    MTTI VES 2 interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    VES2 MODEL acc. to the Survey report

    5 layer model

    There may as well (the same fit) be basement (1000ohmm) at 80 m:

    6 layer model with basement at 80m

    Results MTT VES2 (90% confidence levels)

    Depth (m) Rho (Ωm )

    topsoil (1000) anywhere > 80m

    Conclusion

    • Below (low resistive) topsoil there is an overburden zone of 70 -80 ohmm

    • Resistivity of the shallow aquifer is depending on the actual depth of basement

    • Basement may be anywhere below 80 m

  • P a g i n a | 58

    MTTI VES 3 interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    Interpreted model from the SURVEY REPORT

    5 layer model THE LAST 4 measurements are shifted (indicating lateral change)

    There may as well (same fit) be basement (1000ohmm) at 130 m:

    6 layer model with basement at 130m

    (Even when the last measurements are corrected for the shifts, basement is deeper than 130m)

    Results (90% confidence levels)

    Depth (m) Rho (Ωm )

    topsoil (1000) anywhere > 130m

    Conclusion

    • Below (low resistive) topsoil there is an overburden zone of 70 -100 ohmm

    • Resistivity of the shallow aquifer is depending on the actual depth of basement

    • Basement may be anywhere below 130 m

    1 10 100 L/2

    10

    1e+2

    1e+3 acc to survey report

  • P a g i n a | 59

    MTTI VES 4 interpretation (location advised for drilling)

    Possible model concepts

    Survey report MODEL VES4

    4 layer model

    If the 3 (declining) last measurements were correct (!!), basement would be deep (as 200m or more)

    5 layer model leaving out last (3) measurements (basement could even be at 50m) giving the same, good fit

    Results (90% confidence levels)

    Depth (m) Rho (Ωm )

    topsoil (1000) can be deep but could as well be at 50m (depending on the last 3 measurements being y/n correct)

    Conclusion

    • Below topsoil there is an thin overburden zone of 30 ohmm

    • Resistivity of the shallow aquifer is depending on the actual depth of basement

    • Basement may be at 50m if the last declining measurements are false, if not basement is deep.

    VES4 was advised for drilling and turned to be a dry borehole (drilling showed “just dust”). I tend to believe that the last 3

    (declining) measurements were wrong.

    1 10 100 L/2

    10

    1e+2

    1e+3 SURVEY REPORT

    MODEL

    1 10 100 L/2

    10

    1e+2

    1e+3

  • P a g i n a | 60

    Kajiado Masai Stores survey Re-interpretation VES existing survey report

    Harry Rolf for SamSamWater Foundation 26/02/2017

    Client : Acacia Water

    General

    Existing survey report:

    Hydrogeological/Geophysical survey report for one production borehole in LR.NO; 9923/262 forMasai Store Ltd Kajiado. Report

    by E.Njaramba, NYIKA Associates Ltd Groundwater Consultants

    Aim: verification/re-interpretation of existing VES sounding data

    Location

    VES sounding information

    VES

    Location: (WGS82): 1°50'52.87"S 36°47'24.75"E

    Direction of sounding: ?

    AB reach: 400 m

    Array: Schlumberger

    Elevation: 1730 mas

    Depth to groundwater (if any)

    Estimated at: ??

    For measured data, see survey report

  • P a g i n a | 61

    VES interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    Model and measurements from the survey report and apparent resistivity acc. to SchlumBG

    REMARKABLE DIFFERENCES ON THE SAME DATA ???

    Above: Model (fixed parameters) and measurements according to the survey report, entered in SchlumBG software does not

    give a good fit.

    Below: In the report, the same model on the same data shows a good fit,

    WHAT COULD EXPLAIN THE GOOD FIT as given in the report (below)??? Can it be difference in the software used or…….??

    1 10 100 L/2

    10

    1e+2

    1e+3

    Model from SURVEY

    REPORT

  • P a g i n a | 62

    Re-interpretation:

    2 possible model concepts (comparable good fit)

    4 layer model and 5 layer model

    4 layer model

    5 layer model , having an in-between lower resistive layer

    Results (confidence levels unknown)

    Depth top (m) Rho (Ωm )

    topsoil (1000) 50 -130 >>> 1000

    Conclusion

    • Overburden in the order of 50 ohmm

    • Shallow aquifer resistivity uncertain

    • Top of Basement in between 50 and 130 m

    In the survey report the last layer (> 64m) is interpreted as 390 Ωm. According to the re-interpretation the resistivity is higher

    (> 1000 Ωm)

    What is the explanation for the bad fit we are getting in SchlumBG for the interpreted model of the survey report?

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 63

    Kajiado survey for Mr Osman in Town Re-interpretation existing VES

    Harry Rolf for SamSamWater Foundation 27/04/2017

    Client : Acacia Water

    General

    Survey report for Mr. Osman (HARAF):

    Hydrogeological report survey for Mr. Hamud Mohammed Osman, carried out along Great North Road. S.N.Njoroge, Aqua Well

    Services, Nairobi, report nr. AWS/2673A/2011, December 2011.

    Aim: to verify and re-interpret existing survey report soundings

    Location name: ,Kajiado Township block 1/229

    Date : December 2011

    Location

    VES sounding information

    Location: (WGS84): approximately 360 47’ 25” E 010 50’ 45” S (coordinates in report are probably in ARC1960, not in

    WGS84, coordinates estimated from map)

    Azimuth of sounding: N-S

    AB reach: 500 m

    Array: Schlumberger

    Elevation: 1733 mas

    Depth to groundwater (if any)

    estimated at: ? m

    VES interpretation

    Measured data Resistivity (Ωm) SEE SURVEY REPORT

    Remarks on the data:

    Remarkable 1 point anomaly at AB/2 = 32 and Only one potential change (at 32m) ??

    Inversion results (SchlumBG modelling)

    Model from the Survey Report 10 layers!! Basement (688 Ωm) at 200 m !

    1 10 100 L/2

    10

    1e+2

    1e+3

    SURVEY

    REPORT MODEL

  • P a g i n a | 64

    Possible model concepts: 4 layer model

    4.layer model basement at 134 m

    4.layer model basement at 100 m, having he same GOOD fit

    Overall results including 90% confidence levels (

    Depth (m) Thickness (m) Rho (Ωm)

    (top of the layer)

    topsoil ( 90 105 (93 – 130)

    Basement (ρ>1000) > 90

    Conclusion

    Instead of the 10 layer model in the survey report, a 4 layer model has the same good fit.

    Basement depth uncertain, but deeper than 90 m

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 65

    Borehole survey for Mr. Osman, HARAF farm near Kajiado River

    Re-interpretation of soundings form existing survey report

    Harry Rolf for SamSamWater Foundation 22/04/2017

    General

    Survey report:

    Geophysical and hydrogeological investigation J.W.KARIUKI, Groundwater Max Ltd, report nr. GML- 029/07, Feb 2007.

    Aim: re-interpretation of geophysical soundings, to understand high yielding HARAF Trades borehole., as part of ISGEAG

    geophysical methods research project near Kajiado (Kajiado River)

    Location name: Ildamat , Osiligi, 3 km NW of Kajiado Town

    Sounding Date : Feb 2007

    Location VES4 has been conducted close to ‘HARAF BH2’ close to the Kajiado River

    LOCATIONS ARE NOT CLEAR. The location of VES4 (advised for drilling) is estimated from the hand-drawn map in the survey

    report.

    Note: the coordinates for the selected site are given in the report as 1 49 15 – 36 46 08. These could be in ARC 1960 grid system,

    but, even when transferred to WGS84 (01 49’ 24.2” 36 46 10.9) the coordinates do not point at the location as given on the

    hand-drawn map.

    5 VES soundings were conducted in the survey, along 1 HEP profile line: VES4 was advised for drilling.

    The re-interpretation results of only VES4 is given below. The other soundings are not (yet) re-interpreted.

    VESnr.4 sounding information

    Location: (WGS84): not given in report presumably: 1°49'25.90"S 36°45'54.40"E

    Direction of sounding: not given

    AB reach: 500 m

    Array: Schlumberger

    Elevation: 1670 mas

    Depth to groundwater (if any)

    Estimated at: 5 m

  • P a g i n a | 66

    Measured data

    Remarks:

    the south end of the line must have been close to the powerline at AB/2=250 m

    The field curve already indicates a clay layer and shallow basement

    VES re-interpretation

    Inversion results (SchlumBG modelling)

    Possible model concepts

    4 or 5 layer model

    4 layer model , basement at 23 m

    5 layer model, basement at 21 m

    DATA table HARAF VES4

    MN/2 AB/2 Rho Rho shifted

    0.5 1.6

    2 10.6

    2.5 9.2

    3.2 7.4

    4 5.9

    5 5.7

    6.3 6.3

    8 7.2

    10 9.7

    0.5 13 12.2

    5 13

    16 12.8

    20 15.6

    25 20.3

    5 32 25.7

    10 32

    40 28

    50 36.2

    10 63 46.2

    25 63

    80 63

    100 73.6

    25 130 92.8

    50 130

    160 117.7

    200 155.6

    250

    50 320

    100 320

    400

    500

    VES measurements

    1

    10

    100

    1000

    1 10 100 1000AB/2 (m)

    Rho (ohm

    m)

    Rho

    Rho shifted

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

    1 10 100 L/2

    1

    10

    1e+2

    1e+3

    Rho

  • P a g i n a | 67

    Re-interpreted results

    Depth (m) Rho (Ωm)


Recommended