“Railway Electrification Works Between
RANI (Excl) - SWARUPGANJ (Excl) ”
Volume - II
(PREAMBLE, EXPLANATORY NOTES, BOQ FOR PACKAGE – 1)
“ DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 25 KV,50HZ, SINGLE PHASE, TRACTION HIGH RISE OVER-HEAD EQUIPMENT,SWITCHING STATIONS, TRACTION SUB-STATIONS, SCADA, GENERALELECTRICAL SERVICES WORKS ALONG WITH CIVIL ENGINEERINGWORK ie. SERVICE BUILDINGS, QUARTERS AND OTHER ASSOCIATEDWORKS AND ALSO SIGNALING & TELECOMMUNICATION WORKSBETWEEN RANI (Excl.) –SWARUPGANJ (Excl.) 86 RKM / 198 TKM SECTIONIN AJMER DIVISION OF NORTH WESTERN RAILWAY IN THE STATE OFRAJASTHAN , INDIA
Volume II – Price Proposal
Execution of
Package- 1 - “ DESIGN, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 25 KV, 50HZ,
SINGLE PHASE, HIGH RISE TRACTION OVER-HEAD EQUIPMENT, SWITCHING STATIONS,
TRACTION SUB-STATIONS, SCADA, GENERAL ELECTRICAL SERVICES WORKS ALONG WITH CIVIL
ENGINEERING WORK ie. SERVICE BUILDINGS, QUARTERS AND OTHER ASSOCIATED WORKS
AND SIGNALING & TELECOMMUNICATION WORKS BETWEEN RANI (Excl.) TO SWARUPGANJ
(Excl.) SECTION OF 86 RKM/198 TKM IN AJMER DIVISION OF NORTH WESTERN RAILWAY IN
THE STATE OF RAJASTHAN, INDIA.”
FEB 2015
Corporate Office:
RAIL VIKAS NIGAM LIMITED First floor, August Kranti Bhavan,
Bhikaji Cama Place, New Delhi – 110 066
Tele : + 91-11-26738191 , Fax : + 91-11-26182957, web : www.rvnl.org
Table of Content
Bill of Quantities
Preamble
Summary sheet of bill of quantities
Bill of quantities(Electrical Engineering)
Bill of quantities(Civil Engineering)
Bill of quantities (Signal & Telecom Engineering )
Explanatory Note( Signal & Telecom Engineering)
Explanatory Notes (Electrical Engineering )
Volume – II
Bill Of Quantities
Package-1
Preamble
RVNL/RANI-SRPJ/RE
Page 1 of 16
Bill of Quantities PREAMBLE
PREAMBLE(Civil Engineering)
1. The Bill of Quantities shall be read in conjunction with the Instructions to Bidders,
General Conditions, Particular Conditions of Contract, Works Requirement (Technical Specifications, and Drawings).
2. The quantities given in the Bill of Quantities are estimated and provisional, and are given to provide a common basis for bidding. The basis of payment will be the actual quantities of work ordered and carried out, as measured by the Contractor and verified by the Engineer and valued at the rates and prices tendered in the priced Bill of Quantities, where applicable, and otherwise at such rates and prices as the Engineer may fix within the terms of the Contract.
3. In the Bill of Quantities, quantity and unit rates and thereby the amount against each
item have been indicated. From this, the estimated price of each bill has been worked out and indicated in the summary sheet in BOQ. The Bidder shall quote rates as percentage above/below/at par for each schedule in the summary sheet. If no percentage as above, below or par is indicated for any particular bill, the same will be considered as percentage at par.
4. The rates for each bill shall be written in indelible ink or type written in the summary sheet against each bill in words and figures as percentage above /below/at par with RVNL’s cost. Thereby, quoted price for each bill shall be calculated and written against each bill. The total price, as sum of quoted price for all the bills shall be shown at the bottom of the summary sheet. The total price shall also be written in words and figures.
5. General directions and descriptions of work and materials are not necessarily repeated
or detailed in the Bill of Quantities. References to the relevant specifications and sections of the contract documentation should be made before quoting rates in the Bill of Quantities.
6. The rates and prices Bid in the priced Bill of Quantities shall, except as otherwise
provided under the Contract, include all construction equipment, plant, labour, supervision, materials, erection, maintenance, insurance, profit, royalty, octroi, taxes and duties, together with all general risks, liabilities and obligations set out or implied in the Contract.
7. The rates are deemed to be inclusive of all lead (except as otherwise specifically
provided in the description of the particular item), lifts, ascend, descend, handling, re-handling crossing of nallah/streams/tracks any other obstructions.
RVNL/RANI-SRPJ/RE
Page 2 of 16
8. All enabling works for executing the work e.g. approach road to site, launching arrangements, procuring right of way, arrangement of water and electricity etc is to be arranged by the contractor at his own cost and deemed to be included in the quoted rates.
9. Storage of Material: All the material at site will have to be properly stacked & stored so
as to facilitate inspection. The material should be properly protected from the detrimental effects of nature and fire, theft etc. The contractor shall be responsible for watch & ward and any loss or deterioration on account of above shall lead to rejection of material and contractor has to replace the same at his own cost.
10. The method of measurement of completed work for payment shall be in accordance
with provisions in Works Requirements (Specifications) except as otherwise specifically provided in the description of item or particular bill of quantities or explanatory notes to the particular bill of quantities.
11. (a) In items of Bill No. 6: (Building and related items) and Bill No.9: (Site facilities), the
rates are inclusive of cost of all materials including cement, steel, etc. required to deliver the final product.
(b) In items of bill No.2: (Bridges), Bill No.5: (track linking), and Bill No.7: (Platforms,
passenger amenities and Misc works) where ever cement, reinforcement steel and HTS wire (strands) are required to be consumed in the item, the rates are exclusive of cost of these materials and the same shall be paid separately under relevant items for supply of these materials.
(c) In items of Bill No.4: (P. Way supply) the rates are inclusive of all materials including cement, steel and HTS wire (strands). Rails required for manufacture of item under Bill No.4 shall be issued free of cost by RVNL.
12. NOTES SPECIFIC TO EACH BILL OF QUANTITIES. 12.1. BILL NO.1 FOR EARTH WORK IN FORMATION 12.1.1 The earth work in formation and blanketing has to be executed as per latest RDSO
guidelines for earthwork in railway projects with up to date correction slips. If naturally available material in the project area is not suitable for using as blanketing material directly then the blanketing material conforming to RDSO specification has to be produced by blending various naturally available materials in required proportion in a pug mill.
12.1.2 Obtaining prior permission for felling of trees including payment of royalty and taxes etc
shall be contractor’s responsibility and deemed to be included in the rates.
RVNL/RANI-SRPJ/RE
Page 3 of 16
12.1.3 Joining of new formation with existing embankment has to be done with benching of 30 cm (V), 60 cm (H) in the existing bank slope. The rate of earthwork includes the cost of benching.
12.1.4 Locations where blasting is warranted, prior permission of the employer must be
obtained to ascertain whether blasting is permitted or prohibited. Rate of rock cutting includes the cost of all precautionary measures necessary for safety during blasting of rock.
12.2 BILL NO.2: BRIDGES AND BILL NO.7: PLATFORM, PASSENGER AMENITIES AND
MISCELLANEOUS WORK FOR CC, RCC AND PSC ITEMS. 12.2.1 All material, equipment, labour, casting beds, stress frames, from work staging,
scaffolding, etc is to be arranged by the contractor within the quoted rates. 12.2.2 1:4:8, 1:3:6 and 1:2:4 indicates concrete prepared using volumetric mix in proportion of
cement: coarse sand: stone aggregate of specified size, respectively. 12.2.3 All design mix concrete shall be machine batched with automatic weigh batcher,
machine mixed and machine vibrated or Ready Mix Concrete prepared in depot and transported by transit mixer to the site of work.
12.2.4 Prior to demolishing of any structure measurements have to be taken, scheme of
dismantling has to be got approved from the Engineer. 12.3 BILL NO.4: (PERMANENT WAY SUPPLY) 12.3.1 All P. Way materials shall be procured only from suppliers included in part I list of RDSO
approved suppliers for the particular item. Where, such a list is not maintained by RDSO,
prior approval of source of supply shall be obtained from the employer.
12.3.2 All P. Way materials shall be inspected by the inspecting authority as prevalent over
zonal railway for the particular material. However, employer reserves the right to
nominate any authority or its own representative to inspect the material.
12.3.3 The price quoted also includes RITES/RDSO inspection and testing charges unless
otherwise specified in the bill of qty or technical specification. The prices quoted also include RITES/RDSO inspection and testing charges unless otherwise specified in the bill of quantities or Technical Specification. In case of change of inspection from RDSO/RITES to RVNL/consignee, 1% of cost of material to be deducted by RVNL, as inspection charges.
RVNL/RANI-SRPJ/RE
Page 4 of 16
12.3.4 If the rails required for manufacture of the finished material are to be issued free of cost by the Employer, as specified in the description of item, the employer shall issue such rails either in project area or from Bhilai . The quoted rates include cost of handling and transportation of rails to the manufacturer’s workshop and finished materials from the manufacturer’s workshop to the site of work.
12.3.5 All P. Way material shall be neatly stacked and stored in the project area and protected
against loss/ deterioration by proper watch and ward staff, insurance, etc, the cost of
which is deemed to be included in the rates.
12.4 BILL NO.5: (PERMANENT WAY LINKING) 12.4.1 Painting of rails for loops & platform lines shall be done before fixing in position and
touching to be done after laying in position. 12.4.2 Rates include day as well as night working and lighting arrangement as per requirement
and to the satisfaction of the engineer. 12.4.3 The welds found defective in USFD, shall have to be replaced by the contractor at his
own cost. 12.4.4 During the maintenance of track after commissioning, all arrangement for
transportation of labour , T&P etc will have to be done by contractor at his own cost. Necessary T&P for track maintenance will be procured by the contractor including consumables. The rate includes all such requirements.
12.4.5 The payment of rail cuts and drilling holes will be done as per final layout of
mainline/loop line/sidings and turnouts etc. Rail cuts/hole drilling required for temporary working will not be paid.
12.5 Bill No.8: (Supply of Cement): Payment for supply shall only be made after the quantity
is consumed in the related item of work. The consumption of cement shall be worked out based on cement consumption coefficients as given below or the actual consumption whichever is less.
COEFFICIENTS FOR CEMENT CONSUMPTION
S. No
Item Unit Cement consumption coefficients per unit in
Kg. (Maximum)
Cement Concrete
1. 1:3:6 (1 Cement 3 coarse sand, 6 graded stone aggregate)
Cum 220
RVNL/RANI-SRPJ/RE
Page 5 of 16
S. No
Item Unit Cement consumption coefficients per unit in
Kg. (Maximum)
2. 1:2:4 (1 cement, 2 coarse sand, 4 graded stone aggregate)
Cum 320
3. M20 Cum 400
4. M25 Cum 410
5. M30 Cum 420
6. M35 Cum 428
7. M40 Cum 435
8. M45 Cum 480
9. M50 Cum 500
Cement Mortar
1. Cement Mortar 1:2 (1 Cement: 2 Sand) Cum 680
2. Cement Mortar 1:3 (1 Cement: 3 Sand) Cum 510
3. Cement Mortar 1:4 (1 Cement: 4 Sand) Cum 380
4. Cement Mortar 1:5 (1 Cement: 5 Sand) Cum 310
5. Cement Mortar 1:6 (1 Cement: 6 Sand) Cum 250
Brick Work
1. Cement Mortar 1:4 (1 cement: 4 coarse sand)
Cum 95
2. Cement Mortar 1:6 (1 cement: 6 coarse sand)
Cum 62.5
3. Cement Mortar 1:3 (1 cement: 3 coarse sand) half brick
SqM 14.28
4. Cement Mortar 1:4 (1 cement: 4 coarse sand) half brick
SqM 10.64
Note: Cement consumption for any item if not mentioned above is to be worked out as per
CPWD DSR 2012.
12.6 Bill No.10: (NWR SOR Works) Specification and mode of measurements will be as per NWR specification
RVNL/RANI-SRPJ/RE
Page 6 of 16
Preamble to SBOQ for Railway Electrification and General Electrical Works
A. General Instructions
1. The bill of quantities (BOQ) shall be read in conjunction with the Instruction to bidders, General Conditions of Contract, Particular Conditions of Contract, Works requirements, Technical specifications & Drawings, Explanatory notes detailed after BOQs of RE & General Electrical works seperately, Payment conditions, pre-bid clarifications and Addenda and Corrigenda if any.
2. The summary of schedules is as under:
SN Schedule No. Description
1 16000 RE-General
2 17000 Switching Post Building
4 19000 OHE - Ferrous other than steel
structures and SPS
5 20000 OHE - Non Ferrous ’A’
6 21000 OHE - Non Ferrous ’B’
7 24000 TSS
8 27000 TSS-Spares
9 28000 Tools & Plants
10 29000 SCADA
11 30000 Common Items for OHE/TSS
12 33000 General Electrical Works
3. The quantities given in the Bill of Quantities are estimated and provisional, and are given
to provide a common basis for bidding. The basis of payment will be the actual quantities of work ordered and carried out, as measured by the Contractor and verified by the Engineer and valued at the rates and prices tendered in the priced Bill of Quantities, where applicable, and otherwise at such rates and prices as the Engineer may fix within the terms of the Contract. The Surplus quantities, if any after execution & not required by Railway, as determined by the engineer during the progress of the work or at the completion of the work, shall be taken back by the contractor and the recovery of such material will be adjusted from the pending claims.
RVNL/RANI-SRPJ/RE
Page 7 of 16
4. In the Bill of Quantities, quantity and unit rates and thereby the amount against each item have been indicated. From this, the estimated price of each bill has been worked out and indicated in the summary sheet in BOQ. The Bidder shall quote rates as percentage above/below/at par for each schedule in the summary sheet. If no percentage as above, below or at par is indicated for any particular bill, the same will be considered as percentage at par.
5. The rates for each bill shall be written in indelible ink or type written in the summary
sheet against each bill, in both words and figures, while clearly indicating whether the percentage quoted is above/below/at par over the estimated rate in the respective columns. The price for each bill shall accordingly be calculated and written against each bill in both words and figures. The total price, as the sum of prices of all bills shall be shown at the bottom of the summary sheet. The total price shall also be written in both words and figures.
6. General directions and descriptions of work and materials are not necessarily repeated
or detailed in the Bill of Quantities. References to the relevant specifications and sections of the contract documentation should be referred to before quoting rates in the Bill of Quantities.
7. The rates and prices Bid in the priced Bill of Quantities shall, except as otherwise
provided under the Contract, include all construction equipment, plant, labour, supervision, materials, erection, maintenance, insurance, profit, royalty, octroi, taxes and duties, together with all general risks, liabilities and obligations set out or implied in the Contract.
8. The rates are deemed to be inclusive of all lead (except as otherwise specifically
provided in the description of the particular item), lifts, ascend, descend, handling, rehandling crossing of nallah/streams/tracks any other obstructions.
9. All enabling works for executing the work e.g. approach road to site, launching arrangements, procuring right of way, arrangement of water and electricity etc is to be arranged by the contractor at his own cost and deemed to be included in the quoted rates. Where a temporary tube well or any other water source are constructed by the contractor in the railway land for the purpose of taking power /water for construction purposes, no charge would be recovered from the contractor but written permission will however, be obtained by the contractor from the Engineer who may, at his discretion, refuse such permission for such construction of temporary arrangement. The contractor shall also be required to restore the site to its proper condition as directed by the Engineer.
10. Storage of Material: All the material at site will have to be properly stacked & stored so as to facilitate inspection. The material should be properly protected from the detrimental effects of nature and fire, theft etc. The contractor shall be responsible for watch & ward and any loss or deterioration on account of above shall lead to rejection of material and contractor has to replace the same at his own cost. All the disposable material should be disposed off outside the railway boundary at a designated place as directed by the Engineer.
RVNL/RANI-SRPJ/RE
Page 8 of 16
11. The method of measurement of completed work for payment shall be in accordance with provisions in Works Requirements (Specifications) except as otherwise specifically provided in the description of item or particular bill of quantities or explanatory notes to the particular bill of quantities.
12. Trees falling in the alignment or any other site of the works which belongs to the railways will be trimmed and stacked at a nominated place at his /their own cost as directed by Engineer and the same will be Railway/Employer’s property. Trees of the forest department will be trimmed and deposited in the nearest forest depot. No separate payment on this account shall be made to the contractor.
B. Instructions for quoting by the bidders
1. The prices for supply of materials and erection are in accordance with the technical
specifications, approved drawings and designs. The contractor should note that no item
of materials, equipment, fittings and components shall be supplied by the Employer.
2. UNIT PRICE:
i) The unit price indicated under “Supply” in the bills is the all inclusive price of
materials and all incidental charges for transport, loading/unloading and handling etc.
ii) The price also include taxes, duties, levies (including octroi) applicable on Works
contracts, insurance/bank guarantee/indemnity bond charges etc.
iii) The prices also include provision for losses and wastages in transit and erection.
iv) The price quoted also include RITES/RDSO representative inspection and testing
charges unless otherwise specified in the bill of quantities or Technical
Specification. In case of change of inspection from RDSO/RITES to
RVNL/CONSIGNEE, 1% of the cost of material will be deducted by RVNL as
inspection charges.
(v) The unit price indicated under “Erection” in the bills should be inclusive of the cost
of erection and testing and also include all cost of administration of the contract,
insurance premia, banker’s charges, cost of stamps/storage/loading/unloading and
handling of materials and also include the cost of transportation which the
contractor may incur for carriage of material to the site of works. The unit prices
should also include cost of works and adjustment that may become necessary
during or after the tests for commissioning.
3. The whole cost of complying with the provisions of the contract shall be included in the
items/bills provided in the BOQ and, where no items/bills are provided, the cost shall
be deemed to be distributed among the rates and amount entered for related Items of
Works.
RVNL/RANI-SRPJ/RE
Page 9 of 16
C. NOTES SPECIFIC TO PAYMENT: INVOICING PROCEDURE
1. All invoices shall be submitted with original supporting documents or certified
true copies of supporting documents wherever these are acceptable to the
Engineer as per contract. Where copies of original documents are required in
support of several invoices, true certified copies of the original documents may
be forwarded to the Engineer, with his consent.
2. Invoices shall be submitted only on the basis of provisions in Contract
Agreement and prices. The quantities and measurement of works completed
should be approved by the Engineer prior to the submission of invoices. For this
purpose, the schedule of quantities and measurement submitted by the
contractor for approval of the Engineer may be only up to the extent of work
completed except in the case of payments on Provisional Acceptance.
D. PAYMENT PROCEDURE
1. ON ACCOUNT PAYMENT AGAINST SUPPLY OF MATERIAL
On Account Payment will be made as described below:
(i) “On Account Payment” shall be made for the items specified in detailed
terms of payment of each schedule under clause No. 4.0 of this
preamble.
(ii) „On Account Payment‟ shall be made to the extent of 85% of the
accepted supply rate, after receipt, acceptance, accountal, proper storage and protection against loss, damage or deterioration on the items mentioned in each schedule.
(iii) „On Account Payment‟ made to the contractor will subsequently be
adjusted against progress payments and against payment due on
provisional acceptance.
(iv) All invoices shall be accompanied with the following, for the purpose of
arranging „On Account Payment‟ against the contract:
a. Supplier’s Delivery Challans.
b. Inspection certificate granted by the authorized approved
agency/Purchaser’s representative as per contract agreement.
c. Certificate of receipt of material at Contractor’s depot/work sites duly
accepted by the Engineer.
d. Comprehensive Insurance Policy for supply and safe custody of
material.
e. Bank Guarantee issued by a Scheduled Bank of the equivalent
amount for which On Account Payment is claimed. Such Bank
Guarantee shall be released after erection of the material and on
certification by the Engineer.
f. Quality assurance documents.
RVNL/RANI-SRPJ/RE
Page 10 of 16
2. PROGRESS PAYMENT AGAINST SUPPLY AND ERECTION OF MATERIAL:
On completion of each item of BOQ, the contractor shall receive payment to the
extent of 95% of the supply and erection costs after making any recoveries and
adjusting of On Account Payment, which may be due.
3. REMAINING 5% PAYMENT: The balance 5% of each item of the BOQ shall be
paid to the contractor after commissioning of the portion of the work or handing
over of the installation/material to the employers/Railways representative. This is
applicable for all schedules.
4.0 PROCEDURE OF SCHEDULE WISE PAYMENTS 4.1 Schedule 16000:
(i) Schedule No. 16001 (Design & Drawing)
The payment shall be made as under:
(a) 50% of Scheduled rates shall be paid after “in principle approval
of design/drawings by RVNL”.
(b) 45% of Scheduled rates shall be paid after the submission &
acceptance of as erected/ completion drawings by RVNL.
(ii) All other items except item No. 16001:
(a) On Account Payment shall be made only for item Nos. 16009 &
16010 and as per terms and conditions given in clause No. D (1) under “Payment Procedure”.
(b) The Progress Payment to the extent of 95% of all the items in the
schedule shall be paid for the supply and erection prices after
adjustment of “On Account payment” & other recoveries, if any,
wherever applicable.
4.2 Schedule 17000:
i) 50% of the Schedule rate shall be paid on Casting of the Roof of the Switching Station Building.
ii) 45% of the Schedule rate shall be paid on completion of the building in all respects and certification by the Engineer.
4.3 Schedule 19000:
(i) On Account Payment will be made only for item No. 19004 and as per
terms and conditions given in clause No. D (1) under “Payment Procedure”.
RVNL/RANI-SRPJ/RE
Page 11 of 16
(ii) Schedule No. 19003: On completion of erection of bracket assemblies,
the contractor shall receive payment to the extent of 85% of prices for supply and erection of bracket assemblies. After final adjustment of OHE and SED checking, contractor shall receive another 10% payment”.
(iii) The Progress Payment to the extent of 95% of all the items in the
schedule shall be paid for the supply and erection prices after adjustment
of “On Account payment” & other recoveries, if any, wherever
applicable.
4.4 Schedule 20000:
(i) On Account Payment will be made only for item Nos. 20002 & 20003
and as per terms and conditions given in clause No. D (1) under “Payment Procedure”.
(ii) Item No. 20001: On completion of erection of the items the contractor shall receive payment to the extent of 85% of the prices for supply and erection.
(iii) The Progress Payment to the extent of 95% of all the items in the
schedule shall be paid for the supply and erection prices after final
adjustment of OHE and SED checking and after adjustment of “On
Account payment” & other recoveries, if any, wherever applicable.
4.5 Schedule 21000:
(i) On Account Payment will be made only for item Nos. 21003, 21004, 21005 & 21014 and as per terms and conditions given in clause No. D(1) under “Payment Procedure”.
(ii) The Progress Payment to the extent of 95% of all the items in the
schedule shall be paid for the supply and erection prices after adjustment
of “On Account payment” & other recoveries, if any, wherever
applicable.
4.6 Schedule 24000:
(i) Item No. 24001 (Design & Drawing of TSS)
(a) 50% of Scheduled rates shall be paid after the “in principle
approval of design/drawings by RVNL”.
(b) 45% of Scheduled rates shall be paid after the submission &
acceptance of as erected/ completion drawings by RVNL.
RVNL/RANI-SRPJ/RE
Page 12 of 16
(ii) On Account Payment will be made only for item Nos. 24004 to 24014,
24032 to 24036 and as per terms and conditions given in clause No. D(1) under “Payment Procedure”.
(iii) The Progress Payment to the extent of 95% of all the items in the
schedule shall be paid for the supply and erection prices after adjustment of “On Account payment” & other recoveries if any
wherever applicable except item No. 24001 which will be paid as per (i) above.
4.7 Schedule 27000 & 28000:
95% of the accepted price shall be paid on receipt & accountal of material at site or required destination after inspection and production of documents as listed below:
(i) Supplier’s Delivery Challans.
(ii) Inspection certificate granted by the authorized approved
agency/Purchaser’s representative as per contract.
(iii) Certificate of receipt of material at Contractor’s depot/work sites duly
accepted by the Engineer.
(iv) Quality Assurance Documents including Guarantee/Warrantee, if any.
4.8 Schedule 29000:
(i) Item No. 29001 (Design & Drawing of SCADA)
(a) 50% of Scheduled rates shall be paid after the “in principle
approval of design/drawings by RVNL”.
(b) 45% of Scheduled rates shall be paid after successful completion
of the work and handing over of the soft & hard copies of as
erected/completion drawings & software to RVNL.
(ii) On Account Payment shall be made only for item Nos. 29002 to 29005 &
29007 and as per terms and conditions given in clause No. D(1) under “Payment Procedure”.
(iii) The Progress Payment to the extent of 95% of all the items in the schedule shall be paid for the supply and erection prices after adjustment of “On Account payment” & other recoveries if any wherever applicable
except item No. 29001 which will be paid as per clause (i) above.
4.9 Schedule 30000:
(i) (a) On Account Payment shall be made only for item Nos. 30001 to
30003 and 30005 and as per terms and conditions given in clause No. D(1) under “Payment Procedure”.
RVNL/RANI-SRPJ/RE
Page 13 of 16
(b) The progress payment of the above items to the extent of 95% of
the supply and erection prices shall be paid after adjusting of “On
Account payment” & other recoveries.
(ii) Item Nos. 30006, 30007: On completion of foundation work, the
Contractor shall receive payment to the extent of 75% of the prices (for
supply and erection taken together) of foundation and another 20%
after mast erection, muffing, backfilling etc.
(iii) Item No. 30008: On completion of work, Contractor shall receive
progress payment to the extent of 95% of the prices.
(iv) Item No. 30009: On completion of erection of structures, the
Contractor shall receive payment to the extent of 85% of the prices for supply and erection of structures and another 10% after erection of respective bracket assemblies/equipment.
4.10 SCHEDULE No. 33000 (General Electrical Works):
(i) 85% of the accepted supply rate shall be paid on receipt of material at site, after inspection & against submission of an indemnity bond.
(ii) Further payment of supply & erection cost to cover 95% of the total item
cost shall be paid on completion of the work and on certification by the
Engineer after adjusting already paid amount & other recoveries if any.
5. FINAL SETTLEMENT
On expiry of the defect liability period and issue of the taking over certificate of the entire installation, the Bank Guarantee for Performance security shall be released to the contractor after adjustment of any dues payable by the contractor.
6. RECOVERIES FROM THE CONTRACTOR
All the recoveries for materials supplied and services rendered by the Purchaser to
the Contractor and other refunds due from the Contractor shall be made by
deductions from payments due to the Contractor covering the value of supply and
erection in the progress payment and from payments due on provisional
Acceptance.
7. TAXES AND DUTIES
(i) All taxes, duties and levies (including octroi, works contract tax, service tax) arising
out of the transactions between the contractor and his sub-contractor/Suppliers for
this work will be deemed to be included in the accepted rates, unless otherwise
specified in the BOQ or technical specification.
RVNL/RANI-SRPJ/RE
Page 14 of 16
(ii) Where the law makes it statutory for the Purchaser to deduct any amount towards
sales tax or any other taxes on works contract, the same shall be deducted and
remitted to the concerned authority.
8. PRICE VARIATION
Coefficients governing the adjustment of changes in cost to be read with clause
13.8 of GCC applicable to various schedules are also included.
RVNL/RANI-SRPJ/RE
Page 15 of 16
Signal & Telecommunication Works
1 Bill No.11: (Signal & Telecommunication Works)
2 The bill of quantities (BOQ) shall be read in conjunction with the instruction to Bidders, General Conditions of contract, Particular Conditions of Contract, Works requirements, Technical Specifications, Explanatory Notes, Payment conditions, pre-bid clarifications and Addenda and Corrigenda if any.
BOQ has been divided in four groups‟ i.e.
GROUP C Items starting with Series
38,40 & NS
Contains SUPPLY items on which PVC to be
paid as per RBI indices
GROUP D Items starting with Series
39,40 & NS
Contains EXECUTION items on which PVC
to be paid as per RBI indices
Arrangement for water supply for execution of different items of works will be made by the contractor at his / their own cost.
3 The unit prices for “Supply items” in the bills is the all inclusive price of materials and all incidental charges for transport, loading/unloading
and handling. The prices also include taxes, duties, levies (including octroi) applicable on works contract, insurance / bank guarantee / indemnity bond charges etc. The prices also include provision for losses and wastages in transit and erection. The prices also include RITES/RDSO or other agencies inspection and testing charges unless otherwise specified in the bill of quantities or Technical Specification. In case of change of inspection from RDSO/RITES to RVNL/consignee, 1% of cost of material to be deducted by RVNL, as inspection charges.
4 The unit price for “Erection items” in the bills are inclusive of the cost of erection and testing/commissioning and also include all cost of administration of the contract, insurance premium, banker’s charges, cost of stamps/storage /loading/ unloading and handling of materials and also include the cost of transportation which the contractor may incur for carriage of material to the site of works. The unit prices also
RVNL/RANI-SRPJ/RE
Page 16 of 16
include cost of works and adjustment that may become necessary during or after the commissioning test.
5 All invoices for S&T work shall be accompanied with the following, for the purpose of arranging payment against supply of item:
i. Supplier’s Delivery Challan ii. Inspection certification granted by the authorized approved agencies/Purchaser’s
representatives as per contract.
iii. Certificate of receipt of material at contractor’s depot’s duly accepted by the Engineer in good condition without damage.
iv. Comprehensive insurance policy for supply and safe custody of material.
v. Quality assurance document like Manufacture / Supplier warranty certificate.
6 80% of the accepted cost of material supplied for which installation is to be done by the contractor will be paid on receipt of the material duly inspected by the inspecting authority. Balance 10% of the accepted cost of materials for which installation is to be done by the contractor will be paid after the installation and testing of the work. Balance 10% of the accepted cost of material for which installation is to be done by the contractor will be paid after the commissioning of the work station/IBH/gate wise portion opened for traffic.
7 100% will be paid for spares, tool kits etc on receipt of equipment, duly inspected by inspecting agency and Engineer.
8 For the items of designing / installation / erection, 100% payment will be made after completion for the activity acceptable to the RVNL.
9 Before placing the supply order for STM/MUX counter specific approval of RVNL to be obtained.
The same is required to maintain uniformity in telecom in the section.
10 Released communication items will require shifting to other stations and installed.
******
Summary of Bill of Quantities
Percentage in Figures Percentage in Words Write whether Percentage
quoted in Col. 4 & 5 is
above/below/at par over
estimated rates
In Figures In Words
1 2 3 4 5 6 7 8
1 Earthwork in Formation 24,14,940
2ABridge work (Other than Steel
works)
17,58,350
2CBridge work (Supply of Steel items
)
12,17,930
3 Ballast Supply 8,44,500
4 AP.Way Supply (Other than steel
items)
7,18,424
4 B P.Way Supply (Steel Items) 5,46,973
5 APermanent Way Linking:
Installation Works
5,76,083
5 BPermanent Way Linking: Supply
and Installation Works
2,96,280
6 Buildings 317,24,528
7A
Platform, Passenger Amenities and
Miscellaneous Works : Other than
Steel items
33,08,568
7BPlatform, Passenger Amenities and
Miscellaneous Works : Steel items
144,71,760
8 Supply of Cement
28,08,000
9 Site Facility 152,91,100
10 SOR Items 6,30,172
Group C 227,03,363
Group D 151,03,972
Name of work - Railway Electrification works between RANI (Excl.) - SRPJ (Excl) Section 198 TKM of Ajmer Division of North Western Railway Summary
Sheet of Bill of Quantities Package-1
Sr. No. Description of Schedule Estimated Cost in Rs.
Rate quoted by Contractor as percentage above/ below/ at par over the
estimated rates Price in Rs.
11
Summary Sheet of bill of quantities
Signature of Contractor
Package-1 of RANI-PNU Electrification Project Page 1 of 2
16000 RE General 138,25,863
17000 Swithing Post Building 7,02,649
19000 OHE Ferrous 1000,62,133
20000 OHE Non -ferrous 2285,90,826
21000 OHE Insulators 200,57,517
24000 Traction Sub-station 448,41,680
27000 Maintenance Spares (TSS) 9,13,533
28000 Maintenance Tools & Plants (PSI) 8,58,748
29000 SCADA 94,31,550
30000Common items required for OHE &
TSS
2283,41,816
33000 General Eelctrical Works 189,79,066
Miscellaneous Miscellaneous items 31,94,698
Total Estimated cost 7842,15,022
Note:
(e) Bidder should ensure that the rates are filled with due care and caution so as not to lead to any omission or discrepancy or ambiguity.
Total Quoted Price =
(a) Please refer to ITB 14 and 32 while filling the rates in the summary sheet.
(b) Please mention the percentage rate, in both figures and words, for each schedule in columns 4 & 5 respectively. Please also mention in column 6 whether the percentage rate mentioned in columns 4 & 5
are above or below or at par over the estimated rates.
(c) The price for each bill shall be calculated and written against each bill, in both figures and words, in columns 7 & 8 respectively.
(d) The total price, as sum of the price of all the bills/ schedules shall be shown, in both figures and words under columns 7 & 8 respectively in the last row of the summary sheet.
Summary Sheet of bill of quantities
Signature of Contractor
Package-1 of RANI-PNU Electrification Project Page 2 of 2
Bill of Quantities
(Civil Engineering)
BOQ for Railway Elecrification works between RANI(Excl.)-SRPJ(Excl.)sectin 198 TKM of Ajmer Division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
1001 Earthwork in filling in Embankment Fill and Top Layer of formation including trolley refuges,
etc using contractor's earth of approved quality as per RDSO Guidelines and specifications for
Design of Formation For Heavy Axle Load, Nov 2009 for 25 T Axle Load (using SQ1/SQ2/SQ3
soil with CBR value of 3 or more in Lower Embankment Fill and using either SQ1 soil with CBR
value of 4 or more generally but not less than 3 in isolated cases in Top Layer of 1 meter
thickness or SQ2/SQ3 soil with CBR value of 6 or more generally but not less than 5 in
isolated cases in Top Layer of 0.5 meter thickness), procured from outside railway land
including site clearances, setting out and demarcation, benching, initial compaction of subsoil
after levelling the surface after site clearance, spreading loose earth in 30 CM layers using
grader up to extra width of 0.5 M beyond designed profile, compaction using vibratory
compactors, top and side dressing and removal of extra earth from sides to provide final
formation as per designed profile as per RDSO Guidelines. The rate shall include cutting of
trees with girth upto 30 CM, making good the pockets and depressions left in soil during
clearing and uprooting of jungle/trees at site and one round of heavy rolling of sub-soil
thereafter. The rate shall not include cutting of trees of girth beyond 30 CM and compaction
which shall be paid separately. The minimum Ev2 Criteria as mentioned in the guidelines is
not applicable. The rate shall also not include cost of CBR tests which will be paid vide
separate BOQ item.
Note: 1) Undrained shear strength, CU from Unconfined Compression (UCC) test or Vane Shear
Test and Penetration Number ( N- Value) from Standard Penetration Test of the subsoil will
also be carried out by the bidder before carrying out the work of Earthwork. The quoted rates
are deemed to include these tests.
Note:- 2) Pleasenote that shrinkage allowance shall be deducted as per provisions of para
7.1.1.5 of RVNL standard specifications.
4000 Cum 175.00 700000
BILL No.1 : EARTHWORK IN FORMATION
Page 1 of 20
BOQ for Railway Elecrification works between RANI(Excl.)-SRPJ(Excl.)sectin 198 TKM of Ajmer Division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
1002 Earthwork in excavation by mechanical means (Hydraulic excavator) in cutting, in
formation, trolley refuges, side drains, yard drains, catch water drains, etc. including
leading usable cut spoils up to 200 M and making formation in filling using the cut
spoils, site clearances, setting out and demarcation, disposing off surplus unusable cut
spoils as per directions of the engineer, and top and side dressing to provide final
formation as per designed profile. The rate shall not include cutting of trees with girth
above 30 CM and compaction, which shall be paid separately.
Note- Rock spoils such as stones, boulders, pebbles, gravels etc available from
excavation, if are found suitable for use in works as per required specifications even
after modifications etc., can be used free of cost but the legally payable royalty and
taxes are to be paid by the contractor to the concerned authorities.
1002 a Soil excluding rock. 1000 Cum 146.00 146000
1002 b Rock not requiring blasting. 75 Cum 227.00 17025
1002 c Hard Rock requiring blasting. 75 Cum 387.00 29025
1002 d Hard Rock requiring blasting, but blasting not permitted hence to be excavated by
chiselling.50 Cum 485.00 24250
Page 2 of 20
BOQ for Railway Elecrification works between RANI(Excl.)-SRPJ(Excl.)sectin 198 TKM of Ajmer Division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
1005 Providing and laying blanketing materials of specifications as per RDSO Guidelines and
Specifications for Design of Formation for Heavy Axle Load - Nov 2009 for 25 T Axle
Load in layers of 30 CM in loose state using graders and compaction using vibratory
compactors, top and side dressing to provide final formation as per designed profile.
The rate shall not include compaction, which shall be paid separately.
NOTE :
1) If naturally available materials do not meet the laid down specifications, blanket
material has to be produced by mechanical process using mechanical crushing or
mechanical blending method or combination of these two methods as given in the
Annexure C of RDSO Guidelines and Specifications for Design of Formation for Heavy
Axle Load -2009. The quoted rates are deemed to include the production of material
by mechanical process.
2) The filter criteria and minimum EV2 Criteria as mentioned in the guidelines is not
applicable.
3) The rate shall not include cost of CBR tests which will be paid vide separate BOQ
item.
1400 Cum 977.00 1367800
1006 Mechanical Compaction of Earth and Blanket materials in layers of about 30 CM (or
more or less) in loose state using vibratory compactor (of adequate capacity) so as to
achieve compaction as per RDSO Guidelines and Specification for Design of Formation
for Heavy Axle Load – Nov 2009. Minimum EV2 Criteria as mentioned in the
guidelines is not applicable
5400 Cum 13.94 75276
1009 Cutting down trees and uprooting of roots including transporting the wood to nearby
railway store or forest godown as per direction of the engineer.
Note:
(i) Cutting of trees with girth less than 30 cm and their clearance is covered under
item No. 1001 & 1002. Girth will be measured at a height of 1 M above ground level.
(ii) Contractor will arrange necessary forest clearance on behalf of RVNL before
cutting/felling trees.
1009 d Girth above 180 CM and up to 270 CM 1 Each 1339.00 1339
Page 3 of 20
BOQ for Railway Elecrification works between RANI(Excl.)-SRPJ(Excl.)sectin 198 TKM of Ajmer Division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
1015 Providing barricading with the help of fencing along the running track where the work
is to be done in close vicinity of the track. The fencing shall be minimum 1.5m high
with 2.2m wooden balli/bamboo posts, 25cm girth (min) placed every 2.0m apart,
embedded in cement concrete (1:2:4) blocks of size 0.23 x 0.23 x 0.23M and every
15th post (or nearer, if there is abrupt change of ground slope), last but one end post
and corner post shall be strutted on both sides and end post one side only and struts
embedded in cement concrete (1:2:4) block of size 0.23 x 0.23 x 0.23M, provided with
3 horizontal wooden/bamboo ballies fixed with G.I. staples/binding wire/nail driven
into the posts including 2 bands (red and white) 300 mm long shall be painted with
water bound paints on the ballies from top and two bands (100mm apart) of yellow
reflective tape of width 50mm shall be pasted on top white band. The rate includes
cost of all materials including cement. After execution of all works requiring safety
fencing in particular stretch, the fencing shall be removed with the approval of the
Engineer-in-charge and formation shall be repaired to its profile and released
materials will be contractor’s property.
225 meter 241.00 54225
Total for Bill No. 1 (Carried forward to Summary) 2414940.00
Page 4 of 20
BOQ for Railway Electrification works between RANi(Excl.)-SRPJ(Excl.)section 198 TKM of Ajmer Division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
2001 Earth work in excavation in foundation of bridges to desired profile including
backfilling, compaction of back fill, and disposal of surplus earth as per directions
of the Engineer.
2001 a Soil excluding rock. 40 Cum 233 9320
2001 b Rock not requiring blasting. 15 Cum 246 3690
2001 d Hard Rock requiring blasting, but blasting not permitted, hence to be excavated
by chiselling.10 Cum 492 4920
2004 Providing and laying design mix control concrete M20/M25 in piers, retaining
walls, wing walls, return walls, bottom/top plug of wells and protection work
etc. using well graded stone aggregate of 40 MM/20 MM nominal size.35 Cum 4183 146405
2005 Providing and laying Design mix control concrete M25/M30/M35/M40 in cast-in-
situ RCC works of raft, pile cap, pier, abutment, well steining, RCC well kerb,
well cap, pier cap, Jacketing, dirt wall, return wall, wing wall, fly wing wall,
retaining wall, approach slab, foot path slab, wearing course, ballast retainers,
RCC railing, inspection platform, pedestal, boxes and other miscellaneous works
using well graded stone aggregate of 20 MM nominal size.
300 Cum 5202 1560600
2042 Providing & laying non pressure NP-4 Class RCC pipe with collars, jointing with 1:2
Cement and ordinary sand mortar including testing of joints but excluding earth
work with all labour and material as a complete job. Cement for mortar will be
paid separately.
2042f 1200 mm dia 5 Meter 6683 33415
Total for Bill No.2A (Carried forward to Summary) 1758350
BILL No.2 : BRIDGES
Bill No. 2A: Bridge work (Other than Steel items)
Page 5 of 20
BOQ for Railway Electrification works between RANI(Excl.)- SRPJ(Excl.)section 198 TKM of Ajmer division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
2076 Supplying TMT Fe-500 reinforcement steel conforming to IS:1786-1985
including decoiling, straightening, cutting, bending, placing in position,
binding with 1MM dia GI binding wire.
Note : Reinforcement, shall be measured in length for different diameters
used in the works and then paid as per standard weights as per IS 1732.
Wastages, overlaps, coupling, welded joints, space bars, chairs and binding
wire shall not be measured and cost of these items shall be deemed to be
included in the rates.
17.5 MT 69596 1217930
Total for Bill No.2C (Carried forward to Summary) 1217930
BILL No.2 : BRIDGES
Bill No. 2C: Supply of Steel items
Page 6 of 20
BOQ for Railway Electrification works between RANI(Excl.) - SRPJ(Excl.) section 198 TKM of Ajmer divisionof North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in
Rs.
Amount in Rs.
3001 Supply of machine-crushed stone ballast on cess as per RDSO specifications for track
ballast: IRS-GE-1 of June, 2004 from outside railway limits stacked in specified quantities
alongside the proposed alignment on either side of track, in yards and at locations as per
site requirement as directed by the Engineer.
Note 1:
Payment will be made on actual stack measurement for gross quantities without any
deduction for voids in following stages: (i) 95% on receipt at site, acceptance,
measurement, account, proper storage and protection against loss, damage or
deterioration; and (ii) balance 5% after training out.
Note 2:
i) Wherever sufficient railway land is not available, contractor will have to arrange
land for supply and stacking of ballast at his own cost for which extra payment as per
item no. 3001a will be admissible.
ii) The rate also includes levelling, dressing of ground for stacking of ballast.
1000 Cum 837.00 837000
3001 a Extra over item no. 3001 if ballast is to be stacked in private land in case sufficient
railway land is not available. 250 Cum 30.00 7500
844500
BILL No.3 : BALLAST SUPPLY
Total for Bill No. 3 (Carried forward to summary)
Page 7 of 20
BOQ for Railway Electrification works between RANI(Excl.) - SRPJ(Excl.) section 198 TKM of Ajmer Division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
4001 Supply of P.Way Components
4001 a GFN Liners to RDSO Drg. No. T-3706. 1240 Each 9.09 11271.6
4001 b Combination GFN liners to RDSO Drg. No.T-3707 and T-3708. 1240 Set 29.53 36617.2
4001 c GRSP to RDSO Drg. No.T-3711. 1240 Each 24.99 30987.6
4002 Supply of glued insulated rail joints G3 L 6.5 M long with 10 MM thick end post on PSC sleepers. Rails will be
issued free of cost by the Employer @ 6.5 M for each joint.
4002 a 60 KG Kg rail section as per RDSO Drg No. RDSO/T-5843 10 Each 10923 109230
4002 b 52 KG rail section as per RDSO Drg No. RDSO/T-5361 10 Each 9559 95590
4010 Supplying at site of work including leading, loading, unloading and stacking of Special PSC Monoblock
Sleepers (pre-tensioned type) for B.G. 1 in 8½ Derailing Switch as per RDSO Drg. No.-T-6068 to suite both
52/60 kg rails as per RDSO Design and IRS Specifications No. T-45-96 (2nd Edition) as amended from time to
time with contractor's labour, materials, tools & Plant, equipment and machinery, transport etc complete .1 Set 126917 126917
4012 Supplying at site of work including leading, loading, unloading and stacking PSC turnout sleepers and
approach sleepers for fanshaped layout of 60 kg 1 in 8.5 turnout for B.G 60 Kg. (UIC) rail/52 kg rails to RDSO
Drg. No. T-4865 Alt-5 (for general layout) and drawings thereof with latest alterations if any, complete set
with contractor's labour, materials, tools & Plant, equipment and machinery, transport etc complete .
1 Set 240121 240121
4017 Supply of Grooved Rubber Sole Plates for 1 in 8.5 turnouts for layout Drg no. T-4865 with latest alterations if
any, complete set for the turnout as per IRS specification for Grooved Rubber Sole Plate (6mm thick) for
placing beneath rails Sl. No. T-47-2006 with up to date corrigendum if any
1 Set 29272 29272
4018 Supply of Grooved Rubber Sole Plates for 1 in 12 turnouts for layout Drg no. T-4218 with latest alterations if
any, complete set for the turnout as per IRS specification for Grooved Rubber Sole Plate (6mm thick) for
placing beneath rails Sl. No. T-47-2006 with up to date corrigendum if any
1 Set 38418 38418
718424.4
Payment Conditions for items of this Bill:
d) Indemnity bond for entire cost of material supply.
(2) The remaining 10 % payment shall be made after commissioning of the portion of the work or handing over of the material to the employer's / Railway's
Representative, required for maintenance purposes.
Note: The transportation charges from sleeper manufacturing plant to supply point in the project area as directed by Engineer are inclusive in the rates of special
sleepers. Item No.5031 of Bill No. 5 is for the further movement of the sleeper in project area if required as per the site conditions.
c) Quality Assurance documents.
BILL No.4 : PERMANENT WAY SUPPLY
Bill No. 4 A: P.WAY SUPPLY (Other than Steel Items)
(1) 90% payment shall be made on receipt, acceptance, accountal and taking into custody of complete materials. The invoices shall be accompanied by the following :
a) Supplier's challan and manufacturer's challan.
b) Inspection certificate issued by Employer's/Engineer's nominated inspecting agency.
Total for Bill No. 4A (Carried forward to summary)
Page 8 of 20
BOQ for Railway Electrification works between RANI(Excl.)- SRPJ(Excl.) section 198 TKM of Ajmer Division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
4021 Supply of P.Way Components
4021 a ERC to RDSO Drg. No.T-3701 2480 Each 70 173600
4021 b ERC "J" to RDSO Drg. No.T-4158 25 Each 77 1925
4021 d Supply of rail screws to RDSO Drg. No.T-1035/10675 10 Each 31.74 317.4
4022 Supply of Fish plates
4022 a 60 KG as per Drawing No. T -1898 20 Each 1324 26480
4022 b 52 KG as per Drawing No. T- 090 (M) 20 Each 834 16680
4024 Supply of fish bolts with nuts for 60 KG, 52 KG rails as per RDSO Drawing No.T-1899, T-11501. 50 Each 62 3100
4025 Supply of joggled fish plates (2 No. per set) with 4 pair clamps, 4 No. Bolts & Nuts and 8 No. special
washers.
4025 a For 60 KG as per RDSO Drawing No. T -4016/T-5849 4 Set 3620 14480
4025 b For 52 KG as per RDSO Drawing No. EDO/T-620 or T-5848 2 Set 2837 5674
4026 Supply of Fish plates one meter long as per standard drawing of RDSO
4026 a 60 KG rail (As per RDSO Drg.No.T-5916/T-5851 ) 2 Each 1597 3194
4026 b 52 KG rail (As per RDSO Drg. No. T-5915/ T-5850 ) 2 Each 1280 2560
4029 Supply of 52 kg 1 in 8.5, 6400mm OR Switch confirming to RDSO Drg. No. T-4866 with latest
alteration, if any complete with all parts as listed in the drawing with check rails (excluding fish plates,
Fish bolts & nuts, GRSPs, Liners and ERCs).
1 Set 73312 73312
4031 Supply of 52 KG 1 in 8½ Derailing Switch conforming to RDSO Drg No. 5836 with latest alteration, if
any complete with all parts as listed in the drawing including GRSPs (excluding fish plates, fish bolts &
nuts, Liners and ERCs).Note: Rails will be issued free of cost by the employer.1 Set 45346 45346
4032 Supply of 52 kg CMS Crossing for 1 in 8½ PSC Layout conforming to Drg No. T-4867 with latest
alterations complete with all parts as listed in the drawing (excluding fish plates, fish bolts & nuts,
GRSPs, Liners and ERCs).
1 Nos 164805 164805
NS 4039 Supply of plate scews to RDSO Drawing No T-3912500 each 31 15500
546973
Payment Conditions for items of this Bill:
d) Indemnity bond for entire cost of material supply.
(2) The remaining 10 % payment shall be made after commissioning of the portion of the work or handing over of the material to the employer's / Railway's Representative, required for maintenance purposes.
BILL No.4 : PERMANENT WAY SUPPLY
Bill No. 4 B: P.WAY SUPPLY (Steel Items)
Total for Bill No. 4B (Carried forward)
(1) 90% payment shall be made on receipt, acceptance, accountal and taking into custody of complete materials. The invoices shall be accompanied by the following :
a) Supplier's challan and manufacturer's challan.
b) Inspection certificate issued by Employer's/Engineer's nominated inspecting agency.
c) Quality Assurance documents.
Page 9 of 20
BOQ for Railway Electrification works between RANI(Excl.) - SRPJ(Excl.) section 198 TKM of Ajmer division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
5001 Leading upto 100m lead and putting in track/formation of ballast from measured stacks along
side track or on formation or unloaded ballast by contractor's own means and putting the same
into track uniformly to form profile as per IRPWM in following phases: (i) Laying of first layer to form
level bed for sleepers with top surface dressed including mechanical compaction; (ii) Filling ballast in
cribs and making up shoulders; and (iii) Recouping shortages after each packing and finally making
profile as per IRPWM.
1000 Cum 91 91000
5004 Cutting of 60 KG, 52 KG, 90 R rails with contractor’s Abrasive Disc Cutter complete including men,
material, fuel etc. true to square.300 Each 290 87000
5005 Drilling 26.5 MM, 32 MM diameter holes with Rail Drilling Machine in web of 60 KG, 52 KG, 90 R
rails in track or on cess at correct locations including chamfering. 100 Each 70 7000
5006 Transportation of rails, switches, crossings, etc. (supplied by RVNL) from point of issue to their final
location of laying in track
5006 a Average lead, from the place of issue upto the middle point of location of laying in each KM, upto 10
KM 70 MT 272 19040
5006 b Incremental rate for lead beyond 10 KM under item 5006 (a) above 2280 MT KM 5.53 12608.4
5007 Installation of BG track as per methodology specified in para 4.0 of Section 5: Specifications in the
Bidding Documents or any other methodology approved by the Employer in all locations e.g.
straight, curves, bridges, level crossings, yards, etc including installation of SEJ and glued joints
including installation and dismantling of auxiliary track. Note: 60% of the rate shall be paid after
placement of the sleepers, rails, fastening, initial squaring and correcting sleepers spacing
450 Track Meter 314 141300
5008 Installation of PSC fan shape turnouts, derailing switches 60 KG / 52 KG including lead rails as per
RDSO layout drawings including katcha packing with bars or off track tampers for 20 KMPH speed.
Activities of rail cutting, drilling of holes, welding of joints and transportation are not included in this
item and shall be paid separately under relevant items.
5008 b Turnouts 1 in 81/2 1 Each 42249 42249
5008 c Derailing switches 1 Each 10618 10618
5016 Provision of Buffer stop of 60 KG, 52 KG, 90 R rail section as per plan including painting with
luminous paint etc. as directed by the engineer.
Note: Rail required for this item will be issued free of cost by the Employer.
1 Each 31521 31521
5026 Dismantling of existing BG track, turnouts, derailing switches, dead ends, sand humps, etc. of any
rail section and any type of sleepers of any density and transporting all released material including
sleepers, rails, switches, crossings and fittings & fastenings to the nearest station or manned level
crossing or road loading point as directed by the Engineer.
5026 a Plain track including SEJ and Glued Joints and track at level crossing, bridge & bridge approaches and
sharp curves with check rails50 Track Meter 104 5200
5028 Scarifying, digging existing caked Ballast upto the depth as directed by the Engineer, removal and
screening of Ballast, removal and disposal of muck, dressing of formation to the required profile and
putting back the screen ballast in track.
50 Per Track meter 66 3300
5030 USFD testing of 60 KG, 52 KG rail welds (Flash Butt / SKV) as per RDSO Manuals and submitting
reports on proforma as directed by the Engineer. 90 Each 47.56 4280.4
BILL No.5 : PERMANENT WAY LINKING
Bill No. 5A : P.Way Linking (Installation Work)
Page 10 of 20
BOQ for Railway Electrification works between RANI(Excl.) - SRPJ(Excl.) section 198 TKM of Ajmer division of North Western Railway Package-1
5031 Transportation of PSC sleepers including special sleepers for SEJs, check rails, guard rails and turn
out sleepers from the place of issue (in case of sleepers issued free of cost by RVNL) and from
stacking place acceptable to Engineer at work site ( in case of supplied by the contractor ) to their
final location of laying.
Note:
1. For the purpose of payment each turnout sleeper will be considered as 1.5 No. of ordinary line
sleeper. All other special sleepers shall be considered on par with ordinary line sleeper.
(2) 100% payment shall be made on transportation to designated site as directed by
employer/engineer.
(3) The item is intended for transportation of sleepers issued free of cost by the employer or
supplied by the contractor in P.Way supply schedule in the project area. However, if the sleepers to
be issued free of cost by the employer are made available at the sleeper plant and loading of
sleepers is done by concrete sleeper plant even then the rate quoted in the item shall be applicable
subject to recovery @ Rs.10/- per track sleeper.
(4) Rate includes multiple handlings.
5031 a Average lead upto 2 KM (from place of issue to middle point of kilometer of laying in track) 693 Sleeper 49.77 34490.61
5031 b Incremental rate for lead beyond 2 KM for every km additional lead upto 30 kms over item (a)
above 19404 Sleeper KM 1.66 32210.64
5031 c Incremental rate for lead beyond 30 KM for every KM additional lead upto 60 KM over item (a) & (b)
above20790 Sleeper KM 0.63 13097.7
5031 d Incremental rate for lead beyond 60 KM for every KM additional lead upto 250 KM over item (a),
(b) & (c ) above110880 Sleeper KM 0.36 39916.8
5033 Painting of particulars of 1 in 16, 1 in 12 and 1 in 8 ½ turnouts and derailing switches including turn
in curves on the inside web of outer rail with stencils of specified height in black enamel paint on
surface of specified length painted with two coats of yellow enamel paint over a primer coat painted
after cleaning the surface free from dust and dirt.
1 Turn Out 774 774
5034 Fouling marks of size 150x250x225 MM in M20 grade cement concrete including engraving the
letters “FM”, white washing with two coats and painting the letters in black enamel paint indicating
the numbers of vehicles duly fixed at site.
1 Each 476 476
576082.55
NOTE:
4) Track laying -
a) For mechanized laying of track only service rails will be made available by RVNL. All other materials such as wooden blocks, fish plates, rail screw etc. will have to be arranged by contractor. The rails will be
b) Manual linking of track may be permitted by the Engineer where mechanical linking is not feasible due to constraints in working. Only 90% of the accepted rates shall be payable in case of Manual linking.
5) During the maintenance of track after commissioning, all arrangement for transportation of labour, T&P etc will have to be done by contractor at his own cost. Necessary T&P for track maintenance will be
produced by the contractor including consumables. The rate includes all such requirements.
6) The payment of rail cuts and drilling holes will be done as per final layout of mainline/loop line /sidings and turnouts etc. Rail cuts/ hole drilling required for temporary working will not be paid.
3) The welds found defective in USFD, shall have to be replaced by the contractor at his own cost.
Total for Bill No. 5A (Carried forward)
1) In case of work being executed under traffic block, extra payment will be made for the item of work over and above the accepted rate of the item @ 50% of the accepted rate of the item for day time working
under traffic block and @ 100% of the accepted rate of the item for night time working under traffic block for BOQ item no. 5007, 5008, 5010 & 5026. Rates include lighting arrangement as per requirement and to the
satisfaction of the Engineer
2) Rates for all the items of this bill except those mentioned in note 1) above include day as well as night working and lighting arrangement as per requirement and to the satisfaction of the Engineer.
Page 11 of 20
BOQ for Railway Electrification works between RANI(Excl.) -SRPJ(Excl.) section 198 TKM of Ajmer Division of North western Railway Package-1
S. No. Description of Item Qty Unit Rate in
Rs.
Amount in Rs.
5053 Alumino thermit welding of 60kg/52 kg rail joints or combination joints of 60kg/52kg rail by
pre-heat (SKV) welding technique using compressed air petrol/LPG for preheating, three piece
moulds and automatic tapping thimbles with all labour, materials including supply of portion,
tools and plants, aligning of rails, placing & fixing of mould, preheating, welding, mechanised
trimming, grinding with profile grinder (including riser), testing, marking, painting with one
coat of high build epoxy paint (two pack conforming to RDSO specification no. M&C/PCN-
111/88) on the welded area up to 10 cm on either side. The work is to be completed in all
respects as per IRS: T-19-1994 with latest updates and in accordance with “RDSO Manual for
Fusion Welding of Rails by Alumino Thermic Process with up to date correction Slips. The work
to be done under supervision of trained welding supervisor and carried out by trained welder
having valid competency certificate from RDSO/TPP, Lucknow. Ultrasonic testing of welded
joints shall be paid separately under relevant items.
Note: 1) In case only portion is supplied by the contractor but welding is not done the rate
shall be payable @ 60% of the item rate.
2) In case welding portion is supplied free of cost by RVNL, the rate shall be payable @ 40% of
the item rate.
3) The above provision in note (1) & (2) shall be operated with the specific approval of CPM.
90 Each 3292 296280
296280
BILL No.5 : PERMANENT WAY LINKING
Bill No. 5B : P.Way Linking (Supply and Installation works)
Total for Bill No. 5B (Carried forward)
Page 12 of 20
BOQ for Railway Electrification works between RANI(Excl.) -SRPJ(Excl.) section 198 TKM of Ajmer Division of North Western Railway Package-1
S.No. Description of Item Qty Unit Rates in Rs Amount in Rs6001 a Service building of single storey (foundation to be designed to take load of double storey) with
open foundation upto 1.2 m depth from ground level and plinth height upto 0.6m from ground
level with floor height upto 3.35m.
712.5 Sqm 15750 11221875
6001 e Extra payment for provision of internal sanitary and water supply installations
265.5 Sqm 630 167265
6001 f Extra for every 0 .3 m or part thereof higher plinth over normal plinth height of 0.6m(on ground
floor area only) 0 Sqm 283.5 0
6002 Construction of residential buildings for staff accommodation near railway stations, level crossings
or any other nominated location as per layout drawings and standard railway plans for each type of
staff quarters, provided by the employer and detailed specifications provided in para 4.3 of
section 5: works requirements of the bidding documents including structural design and
preparation of detailed structural drawings. Rate includes cost of cement steel, internal water
supply and sanitary installations and all other materials and labour.
6002 a Type I,II,III Single storeyed floor height upto 2.9 m 663 Sqm 12180 8075340
6002 b Type IV Single storeyed floor height upto 2.9 m 227.5 Sqm 13440 3057600
6002 l Extra for every 0 .3 m or part thereof higher plinth over normal plinth height of 0.6m (on ground
floor area only) 0 Sqm 283.5 0
6002 a Type I,II,III double storeyed floor height upto 2.9 m 663 Sqm 11865 7866495
NS 6006 Extra payment for provision of internal sanitary and water supply installations for (A)
Type I,II,III Single storeyed floor height upto 2.9 m663 Sqm 1461.6 969040.8
NS6007 Extra payment for provision of internal sanitary and water supply installations for staff qtrs( B) Type
IV Single storeyed floor height upto 2.9 m227.5 Sqm 1612.8 366912
31724527.8
BILL No.6 : BUILDINGS
TOTAL VALUE FOR BILL No.6
Page 13 of 20
BOQ for Railway Electrification works between RANI(Excl.)-SRPJ (Excl.) section 198 TKM of Ajmer Division of North Westetn Railway Package-1
S. No. Description of Item Qty Unit Rate in
Rs.
Amount in Rs.
7002 Providing and laying 1:3:6 cement concrete in foundation and floor using well graded stone
aggregate of 40 mm/20 mm nominal size.550 Cum 2188 1203400
7003 Cement Concrete 1:2:4 (cast in-situ/precast ) for Rail level platform wall, coping of platforms,
drains and in other miscellaneous works.400 Cum 2058 823200
7004 Earth work in filling with contractor's earth of approved quality in platform, circulating area,
level crossing and other areas including all lead and lift in layers not exceeding 30 CM in depth
including mechanical compaction and watering to achieve the desired compaction as per
specifications.
2500 Cum 175 437500
7005 Earth work in cutting in foundation, trenches, drains, etc in all kinds of soil including dressing of
sides, ramming of bottoms, back filling of trenches, getting out the excavated soil and disposal of
surplus excavated soil with all lead and lift as directed by the Engineer.
7005 a In all kinds of soil 1750 Cum 131 229250
7016 Providing and fixing pre-painted galvanised sheet 0.6 MM thick with corrugated or trafford
design on previously erected purlins or wall frame work for roofing. The colour coating shall be
polyester coating over hot dipped galvanised sheet and the sheets will be of minimum high tensile
strength of 275 MPa variety. The fixtures used for fixing the sheets shall be as per manufacturer's
specifications. Measurement shall include area of MS sheet, valley gutter, ridges etc excluding
overlaps. The rate includes provision of 110 MM dia PVC rain water pipes, j bolts & other fixtures,
painting of station name on both ends of COP in tri-lingual format.
527.5 SqM 659 347622.5
7017 Providing GI pipes including laying & jointing with all fittings making connections to water
hydrants including connection to source along with excavation & refilling etc. complete. (External
Water supply only)
7017 a 15 MM Dia 112.5 Meter 118 13275
7017 b 20 MM Dia 112.5 Meter 146 16425
7017c 25 MM Dia 35 Meter 197 6895
7021 Brick work with bricks of class designation 75 for miscellaneous works in:
7021 a Cement motor 1 : 6 (1 cement : 6 coarse sand) 100 Cum 2310 231000
3308567.5
Note :
BILL No.7: PLATFORM, PASSENGER AMEINITIES AND MISCELLANEOUS WORKS
TOTAL VALUE FOR BILL No.7A (Carried forward to summary)
1. All materials, equipment, labour, casting beds, stress frames, form work staging, scaffolding, etc. is to be arranged by the contractor within the
quoted rates.
2. All design mix concrete shall be machine batched with automatic weight batcher, machine mixed and machine vibrated or ready mix concrete
prepared in depot and transported by transit mixer to the site of work.
3. Prior to demolishing of any structure measurements have to be taken, scheme of dismantling has to be got approved from the Engineer.
Page 14 of 20
BOQ for Railway Electrification works between RANI(Excl.)-SRPJ (Excl.) section 198 TKM of Ajmer Division of North Westetn Railway Package-1
4. Wherever, cement, Reinforcement steel are required to be consumed in the item, the rates are exclusive of cost of these materials unless otherwise
specified and the same shall be paid separately under relevant items for supply of these materials.
Page 15 of 20
BOQ for Railway Electrification works between RANI(Excl.)-SRPJ(Excl.) section 198 TKM of Ajmer Division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in
Rs.
Amount in Rs.
7061 Providing FOB, platform shelters, height gauge, columns, beams, trusses and other steel
components of miscellaneous works duly launched in position with or without traffic block as
directed by Engineer with contractors steel conforming to IS:2062-1999 including fabrication,
assembly, erection, launching, riveting/welding, bolting, initial coats of zinc chromate priming
conforming to relevant IS specification and three subsequent coats of aluminum paint of approved
quality conforming to IS:2339 after final erection on all surfaces complete. Rate is inclusive of
supply and fixing of MS holding down bolts for IRS type platform shelters and FOBs with required
angles.
170 MT 85128 14471760
14471760
Note :
BILL No.7: PLATFORM, PASSENGER AMEINITIES AND MISCELLANEOUS WORKS
Bill No. 7B: Platform, Passenger amenities and miscellaneous works (Steel items)
5. Wherever, cement, Reinforcement steel are required to be consumed in the item, the rates are exclusive of cost of these materials unless
otherwise specified and the same shall be paid separately under relevant items for supply of these materials.
TOTAL VALUE FOR BILL No.7B (Carried forward to summary)
1. All materials, equipment, labour, casting beds, stress frames, form work staging, scaffolding, etc. is to be arranged by the contractor within the
quoted rates.
2. 1:4:8, 1:3:6 and 1:2:4 indicate, concrete prepared using volumetric mix in proportion of cement : coarse sand : stone aggregate of specified size
respectively.
3. All design mix concrete shall be machine batched with automatic weight batcher, machine mixed and machine vibrated or Ready mix concrete
prepared in depot and transported by transit mixer to the site of work.
4. Prior to demolishing of any structure measurements have to be taken, scheme of dismantling has to be got approved from the Engineer.
Page 16 of 20
BOQ for Railway Electrification works between RANI(Excl.) - SRPJ(Excl.) section 198 TKM of Ajmer division of North Western Railway Package-1
S. No. Description of Item Qty Unit Rate in Rs. Amount in Rs.
8001 Supply of 43 grade cement OPC conforming to IS: 8112 with latest amendments and using
the same in the work as per RVNL's approved mix design as per RVNL's prescribed rates of
consumption including all lead lift, labour, loading unloading, ascent, descent, crossing of
Railway lines(s), royalty, taxes, transport (contractor's own), tools and plant complete.
5000 Bag of 50kg. 312 1560000
8002 Supply of 53 grade cement OPC conforming to IS: 12269 with latest amendments and using
the same in the work as per RVNL's approved mix design as per RVNL's prescribed rates of
consumption including all lead lift, labour, loading unloading, ascent, descent, crossing of
Railway lines(s), royalty, taxes, transport (contractor's own), tools and plant complete.
4000 Bag of 50kg. 312 1248000
2808000
Bill No.8 : Supply of Cement
TOTAL VALUE FOR BILL No.8 (Carried forward to summary)
Note : OPC cement has to be supplied as per requirement of the work in terms of RVNL standard specifications for material and works. Payment against
supply will be made only after consumption of cement in the relevant items of work.
Page 17 of 20
BOQ of RaNI -SRPJ Package -1
9001 Providing site offices for Employer with Contractor's material, Labour,
Tools and Plant, Equipment etc. including provision of Water Supply,
Drainage, Power arrangements, office maintenance as per the details
mentioned in clauses 3.1 to 3.2.8 & 3.5 to 3.5.2 of Chapter 3 (Site Facilities
for the Employer and the Engineer) of Section 5 (Work's Requirement) of
Tender Documents.
Note 1: This item is provided with the contention that new site offices will
be constructed for this purpose and 75% payment of the accepted rates will
be made after making available functional office, balance 15% payment
shall be made at the end of the completion period and the remaining 10%
will be paid after clearance of site by the contractor .
Note 2: Alternatively if suitable accommodation is available on hire basis at
suitable location acceptable to the employer, the contractor can arrange the
same under the item but in such a case the payment shall be regulated as
below.
(a) 10% payment shall be made on completion of one month from the date
of making available the office fit for functioning.
b) Remaining 90% payment shall be paid in equal monthly instalments that
is (0.9xQuoted rate) / (Stipulated Completion period in months + defect
liability period in months). In case stipulated period gets extended on any
account no additional payment shall be made for the item.
Per Sq.m.
of Plinth
area
10657 204 2174028
9002 Providing Furniture as given under clauses 3.3, 3.3.1 of Chapter 3 (Site
Facilities for the Employer ) of Section 5 (work's Requirement) of Tender
Documents.
Note : Payment shall be made @ 75% of the accepted rate after making
available the furniture items in functional office, balance 15% payment shall
be made at the end of the completion period and the remaining 10% will be
paid after clearance of site by the contractor.
L S Per
Site Office827760 1 827760
9003 Providing Road Vehicle mentioned below for the use of
Engineer/Employer as per the Conditions mentioned in Clause 3.4.3, i.e
3.4.3.1 to 3.4.3.3 of Chapter 3 (Site Facilities for the Employer and the
Engineer) of Section 5 Work's Requirement) of Tender Documents.
9003a Tavera , Innova or similar Vehicle
months
44492 813603852
9003b Tata Sumo, Bolero or similar Vehicle
months
38284 225 8613900
9003c Extra for running and maintenance of Every additional Km over and
above Kms included under item 9000-3aPer km 10.35 2386 24695
9003d Extra for running and maintenance of every additional Km over and
above Kms included under item 9000-3bPer km 8.28 5660
46864.8
15291100
Grand total carried forward to summary 15291100
Total value for bill no. 9
BRIEF DESCRIPTION OF ITEMS Unit
BOQ for Railway Electrification works between RANI (Excl.) - SRPJ (Excl) Section 198 TKM of Ajmer
Division of North Western Railway
SITE FACILITIES
Rates as
per SBDQty
Total Cost in
Rs.
Page 18 of 20
BOQ of RaNI -SRPJ Package -1
Page 19 of 20
Package-1
BOQ for Railway Electrification works between RANI (Excl.) - SRPJ(Excl.) section 198 TKM of Ajmer division of North western Railway
Item No.DESCRIPTION of North-Western Railways Unified Standard Schedule of
Rates 2010 Quantity Unit
Rate in %age
above
Amount in
Rs
10001
Execution of item(s) of works covered by chapter 1 to 25 of USOR -2010
of North Western Railway.
Note: This bill will be operated for only those works wwhich can not be
executed by operation of BOQ items in bill no. 1 to 9.
562151 Rs 12.1 630172
630172
630172
Bill No. 10 (Other items of work not covered in Bill No. 1 to 9
Total
Total for Bill no.10 ( Carried forward)
Bill of Quantities
(Signal & Telecom
Engineering)
S.No. ITEM NO DESCRIPTION OF WORK UNIT Rate QTY. total Amount
Group - C
1 38651 Supply of underground Jelly filled 0.9 mm dia 6 Quad Telecom cable. Kms 245057.79 14 3430809.06
2 38653 Supply of PIJF cable of size: 10 PAIR X 0.63 MM. Kms 63470.81 18 1142474.58
3 38654 Supply of PIJF cable of size: 20 PAIR X 0.63 MM. Kms 95087.39 18 1711573.02
4 38657 Supply of 24 Fibre armoured Optical fiber cable as per SPEC No.IRS.TC-
55/2006 ver.-1 with ammendments.
Kms 57079.00 60 3424740.00
5 38701 Supply of RCC pipes 150mm dia, 2 Mtr long along with collars Mtrs. 119.35 682 81396.70
6 38702 Supply of DWC pipe of size 120 mm outer dia & 102 mm inner dia. Mtrs. 189.92 682 129525.44
7 38703 Supply of SPLIT DWC pipe of size 200 mm outer dia & 175 mm inner dia. Mtrs. 236.62 27273 6453337.26
8 38704 Supply of Galvanized Iron pipe 100 mm dia `B' class with end clamps Mtrs. 820.90 455 373509.50
9 38705 Supply and jointing of Quad cables with theromoshrinkable jointing kits Nos. 4077.52 14 57085.28
10 38902 Supply of Electronic magneto telephone desk type. Nos. 2407.70 10 24077.00
11 40004 Supply of 4 wire way station equipment as per Spec. no. TC. 38/97 or latest. Nos. 4630.21 41 189838.61
12 40005 Supply of Power Supply for telecom installation at way side equipment as per
TEC Spcn. IRS.TC-72/97 Amdt.1 or latest.
Nos. 3623.41 41 148559.81
13 40006 Supply of portable Emergency telephone 4 wire as per spec. no. IRS TC:75-99
with latest amendment
Nos. 2205.55 18 39699.90
14 40008 Supply of Emergency Socket Box with socket six pin flat to RDSO Spec No.
IRS: TC. 42/87. Amdt. 1 or latest.
Nos. 2205.55 9 19849.95
15 40009 Supply of VF Tapping Transformer to RDSO Spec. No. IRS.TC-22-76 of type
470:1120, 600:470, 600:1120. exact break up to be decided in consultation
with engineer.
Nos. 580.26 182 105607.32
16 40102 Supply of FCPC To SCPC 10 meter long patch cords with 0db adaptors as
TEC spec G/OJC-01/03 JAN99 Or latest.
Nos. 1473.55 68 100201.40
17 40103 Supply of managed Expendable rack type STM-1 ADM L 1.1 as per
Technical Spec. No. TEC GR No. GR/SDH-04/02 Mar 02 with amendment 1 ,
2 ,3 & 4 or latest with STM-1 aggregate interface , 21 E1S and 4 Numbers of
10/100 Base T Ethernet Port order wire, power supply unit, sub rack
installation material and accessories manual etc.The equipment should be fully
wired for its ultimate capacity and provide redundency for power supply and
synchronisation and other detail as given in chapter 3 (model - TJ 100 MC1).
Nos. 154131.91 15 2311978.65
18 40104 Supply of SMPS based battery chargers for telecom use 48v, 25 amps in N+1
configuration using 2 modules of 25 A (FR/BC) with automatic switching
between the modules N=2.
Nos. 55184.04 15 827760.60
19 40105 Supply of 200 AH capacity LM batteries 24 Nos. at each station with required
no. of porcelene insulator. The suitable wooden rack for keeping batteries
shall also be supplied and it should be painted with 2 coats acid resistnt paint.
Nos. 49860.40 15 747906.00
BOQ OF S&T ARRANGEMENT IN CONNECTION WITH RE WORK OF RANI - SWARUP GANJ (PKG-I) OF NWR
S.No. ITEM NO DESCRIPTION OF WORK UNIT Rate QTY. total Amount
Group - C
BOQ OF S&T ARRANGEMENT IN CONNECTION WITH RE WORK OF RANI - SWARUP GANJ (PKG-I) OF NWR
20 40356 Supply of Speaker cable 2 Core Shielded & screened of size 47/0,193 as per
IS-694Cable for modification of existing PA System
Mtrs. 41.21 12273 505770.33
Total of SOR Items (Group C) 21825700.41
NS Items:
21 NS 3 Supply, Installation and commissioning of 4 wire DTMF Control Office
equipment and emergency control office equipment and connecting to the
power supply equipment.
Nos. 14870.65 5 74353.25
22 NS 7 Supply of Earth tester - Digital Motwane make Nos. 14468.00 2 28936.00
23 NS 8 Supply & fixing of PVC Conduit pipe 25 mm dia and thickness 1.5 mm with
suitable clamps at interval of 1 mtr.
Mtrs. 44.85 1227 55030.95
24 NS 9 Supply of Network Monitoring System (NMS) including associated application
software for 2 mb drop insert mux and its associated item as per technical
spec. and office stipulation detailed with all accessories incl. Power supply as
well as one soft copy of software. (Refer. Telecom special conditons : Chapter-
3).
Nos. 106030.00 1 106030.00
25 NS 10 Supply of Network Monitoring System (NMS) including associated application
software for STM-1 and its associated item as per technical spec. and office
stipulation detailed with all accessories incl. Power supply as well as one soft
copy of software. (Refer. Telecom special conditons : Chapter-3).
Nos. 106030.00 1 106030.00
26 NS 11 Supply of local craft terminal as per technical spec. and other stipulations
complete with all accessories compataible with NMS.(Refer. Telecom special
conditons : Chapter-3).
Nos. 54970.00 1 54970.00
27 NS 12 Supply of remote service terminal as per tech. Spec.and other stipulations with
all accessories compataible with NMS. It should be possible to plug in remote
service terminal at any of the station. It should be capable to programme any
network element from any location of network and read the full status of any
element in the network from remote service terminal, as well as one soft copy
of the software .(Refer. Telecom special conditons : Chapter-3)
Nos. 129668.25 1 129668.25
28 NS 13 Supply & Provision of Surge protection device for AC Power line incoming,
complete for Single phase power protection
Nos 24955.00 12 299460.00
29 NS 14 Supply of 2T Transformer . Nos. 1008.00 23 23184.00
Total Cost of NS Items (Group-C) 877662.45
TOTAL (Group-C) carried forward to summary 22703362.86
S.NO
.
ITEM
NO
DESCRIPTION OF WORK UNIT Rate QTY. Total Amount
Group - D
1 39652 Excavation of cable trench of 1 m. depth & 300 mm.
wide across the track crossing, road crossing, level
crossing, platform & refilling.
Kms. 51262.94 40 2050517.60
2 39653 Providing chase in hard rock. Mtrs. 94.98 4545 431684.10
3 39654 Perforation and Fixing of GI pipes on girder bridges,
RCC bridges, drains, culverts, rocky places
tunnels/deep cutting.
Mtrs. 36.44 455 16580.20
4 39655 Fixing/ laying of DWC/RCC pipes(FOR SIGNALING
& TELECOM WORK)
Kms. 30018.70 2 60037.40
5 39656 Laying of signaling / power / telecom / quad/OFC
cable of various sizes in trench and pipes.include
Testing of point to point insulation / continuity test for
all laid out cables, Measuring Parameters and
preparing the records
Kms. 4115.00 41 168715.00
6 39657 Placing of half round ( Split DWC ) pipe over the laid
cable in open trenches.
Kms. 2669.33 20 53386.60
7 39658 Supply and Fixing of 20 pair CTB and termination of
quad/ jelly filled cable.
Nos. 3324.24 27 89754.48
8 39901 Supply and Installation of Maintenance Free
Earthing and Bonding System as per RDSO
specification
Nos. 33770.34 20 675406.80
9 40502 Installation and commissioning of 4 wire way station
equipments, power supply unit at SP/SSP/Station/
TSS/AEN/PWI/SI offices/ Residences. The
installation of way station equipment and power
supply unit (supply covered under a separate item)
shall be mounted on a MS angle rack. All the
materials for installation, commissioning of 4 W
equipment and power supply unit shall be provided
by contractor.
Nos. 2331.19 41 95578.79
BOQ OF S&T ARRANGEMENT IN CONNECTION WITH RE WORK OF RANI - SWARUP GANJ (PKG-I) OF NWR
S.NO
.
ITEM
NO
DESCRIPTION OF WORK UNIT Rate QTY. Total Amount
Group - D
10 40503 Installation of emergency socket box including
socket on the Rail Post in the section and yard at
every one Km distance as pertapping chart supplied
by the survey team. this will include wiring and
termination of quad cable on the socket box
mounted at 1 mtr hight, clamped with 2 nos. U-
Clamps, provision of concreate foundation of rail
post in such a way that the rail post is one meter
above the earth level. The concrete shall be in ratio
of 1:3:6 of cement, sand & stone chips. The
contractor shall jointly test with RVNL Engineer for
its satisfactory operation. This includes painting of
emergency socket post with alternate yellow and
black strip of 6" width and paiting of the socket box
with gray colour paint and painting of arrows on the
telephone posts/cable markers to show the nearest
Emergency socket as instructed by engineer at site.
Rail Posts and MS pipes of required lengths for
fixing Emergency sockets will also be supplied and
installed by the Contractor.
Nos. 1858.19 10 18581.90
11 40601 Supply and installation of OFC cable joint enclosure
as per TEC No. G/OJC-01/03 Jan 99 or latest and
splicing o optical fibre cables (24 Fibre) and testing.
Nos. 8649.87 45 389244.15
S.NO
.
ITEM
NO
DESCRIPTION OF WORK UNIT Rate QTY. Total Amount
Group - D
12 40603Supply of 2 MB programmable primary digital drop
insert multiplexer with conference facility as per
specifications IRS:TC/68/2004 with latest
amendments & other stipulations of tender
document fully wired for 30 channels complete with
power supply unit, remote control supervision facility
& all other accessories installation materials,
manuals etc. It should have facility to accomodate
data interface cards in multi drop mode & should be
able to support card needed for video conference.
NOTE : 1) in case the cards contain less than 8
circuits or 6 circuits as mentioned above suitable
number of cards to equal the total requirements of
circuits must be supplied. 2) If the card contains
more than 2/6/8 ports per card as mentioned in the
schedule, the tenderer shall still supply the number
of cards asked for. The number shall not be scaled
down as per the number of ports.
Nos. 92372.01 11 1016092.11
13 40604 (i) 4 wire, E&M, VF interface cards (8 circuits per
card).
Nos. 30712.42 0 0.00
14 40604 (ii) subscriper loop interface cards (6 circuits per
card).
Nos. 27487.94 11 302367.34
15 40604 (iii) ISDN Interface (Two BRI Ports per card) Nos. 19761.66 11 217378.26
16 40604 (iv) Exchange loop interface cards (6 circuits per
card).
Nos. 23993.54 11 263928.94
17 40604 (v) G 703, 64 kbps data interface cards with a
minimum of 8 ports per card.
Nos. 29453.54 11 323988.94
S.NO
.
ITEM
NO
DESCRIPTION OF WORK UNIT Rate QTY. Total Amount
Group - D
18 40605Supply, installation testing & commisning including
earthing of 42 u 19" covered racks for housing SDH
and P- MUX equipments, DDF, FMS, MDF, using
krone module etc. Complete with all fittings, wired
and equipped with integrated protection modules
for all channels and adequate numbers of cooling
fans ,AC/DC power supply distribution panels, U-
Link panels and other hardware like runway, ladders
etc. It should be possible to lock all the equipments
with only order wire telephone remaining outside the
rack. The rack should be of APW President/Rittal
make. The components of the rack are specified
below. Broad description of rack is detailed below
.Rack size 2200(mm) H x 600(mm) W x 600( mm)
D. Fixed side panels 42 U x 600 (mm) D front glass
door plain 42 U x 600 (mm) D rear MS door plain 42
U x 600 (mm) D leveling screws - 4 numbers .Fan
directly mounted on top 48 V DC 90 CFM - 2 Nos.
earth connectivity kit - 1 No. Cable manager with
cable loops-2nos.
Nos. 35779.77 11 393577.47
19 40106 Blowing of armoured Optical Fiber Cable into duct
by using blowing machine and associated works
.Before blowing the duct integrity shall be tested .If
any defect shall be found during duct integrity test ,
the entire length of HDPE duct from one chamber to
another chamber chamber is to be replaced by
Contractor at free of cost.
Kms. 9901.92 30 297057.60
20 40806 Supply and placing of second class bricks of size
225x100x75 mm (9 bricks per mtr) horizentally
breath wise in the trench after covering the laid
cable with soft soil of 50 mm thickness.
Nos. 4.85 327273 1587274.05
Total Cost of SOR Item (Group D) 8451151.73
NS Items:
S.NO
.
ITEM
NO
DESCRIPTION OF WORK UNIT Rate QTY. Total Amount
Group - D
21 NS-18 Excavation of cable trench 1.2m deep x 300mm
width as per Technical Specifications 51.2, at track
& roads crossing, laying of DWC pipes, as per Drg.
No. RVNL/S&T/SG 024/2005, refilling of trench,
ramming. HDPE pipe shall be laid at the bottom of
the trench and after refilling with seived earth by 150-
200 mm, 6 quad cable shall be laid and restoring the
earth to original condition.
Kms. 67620.00 51 3448620.00
22 NS-19Horizontal directional drilling for laying of HDPE
125/200mm dia pipe 1.4 Meter to 2.1 meter below
the formation of Earth level below ballast, As per
drawing and instruction of Engineer at site. Terms &
Conditions A) The rate shall include Horizontal
direction drilling at any intermediate obstruction,
either natural or manmade any boundary strata. B)
The rate is inclusive of all material equipments and
labour required during trench less horizontal
directional drilling under. C) The pipes are to be laid
under Railway track/Platform/Pucca Circulating area
etc. Necessary arrangement to be provided and all
precautions are to be taken so that bore coming out
at either end is not deviated from the Horizontal
level by more than 250mm in horizontal. D) The rate
is inclusive of detection and protection of
underground utility encountered during boring. E)
The payment shall be made for boring only when
HDPE pipe is provided in the above
Mtrs. 1500.00 1700 2550000.00
23 NS-20 Testing & commissioning of complete OFC system. System
(Nos.)
230000.00 1 230000.00
24 NS-25 Initial charging of Secondary cells:- 0.00
25 NS-28 2 Volts, 200 AH Nos. 266.00 360 95760.00
26 NS-29 Supply of 20 Pair Krone terminal complete with
mounting arrangements.
Nos. 850.00 23 19550.00
S.NO
.
ITEM
NO
DESCRIPTION OF WORK UNIT Rate QTY. Total Amount
Group - D
27 NS-30 Supply of Krone insertion/ extrusion tool Krone
make
Nos. 1150.00 5 5750.00
28 NS-31 Supply & installation of wire insulator for wire
operating, Level Crossing Lifting barriers/Signals as
per Specification No. IRS S-47-74
No.of wire
Insulator
(Nos.)
555.00 90 49950.00
29 NS-32 supply and installation of Insulator of Point rodding
at function end and lever end as per Technical
specification.
No.of rod
insulator
(Nos.)
591.00 90 53190.00
30 NS-33 Provision of GPS Clock in Stations Nos. 20000.00 10 200000.00
Total Cost of NS Item 6652820.00
Grand Total of Group D(Carried forward to summary) 15103971.73
Bill of Quantities
(Electrical
Engineering)
BOQ of RANI-SRPJ Package-1
16001 OHE-1
Preparation and submission of designs and drawings
for Overhead Equipment, Switching Station,
Sectioning diagram,Power supply diagram,
Schematic diagram of Switching Stations, Traction
working rule diagram and Instructions etc. required
for commissioning of OHE
TKM 198 996 14440 197208 2859120 3056328
Supply and Erection of large Span wire (130 sq.mm)
including its fittings with insulators:
(a) With Porcelain Insulators 1050mm CD Mtr 1500 439 36 658500 54000 712500
(b) With Composite Insulators 1050mm CD Mtr 444 415 36 184260 15984 200244
Supply and Erection of materials for Termination of
single conductor of overhead equipment or a
terminating wire
(a) With Porcelain Insulators 1050mm CD Each 275 5871 538 1614525 147950 1762475
(b) With Composite Insulators 1050mm CD Each 78 4704 538 366912 41964 408876
Supply and Erection of materials for Termination of
all aluminum 25 KV feeder conductor single (spider)
including feeder wire
(a) With Porcelain Insulators 1050mm CD Mtr 1600 293 118 468800 188800 657600
(b) With Composite Insulators 1050mm CD Mtr 473 275 118 130075 55814 185889
Supply and Erection of material for Termination of
copper cross feeder with gantries including cross
feeder wire
(a) With Porcelain Insulators 1050mm CD Set 12 24874 631 298488 7572 306060
(b) With Composite Insulators 1050mm CD Set 5 22540 631 112700 3155 115855
16006 OHE-6Supply and Erection of Terminal boards in control
cubicles,Each 5 5985 269 29925 1345 31270
16007 OHE-7Supply and Erection of iron clad 240V AC and 110V
D.C. board with fuse box in control cubicles,Set 5 3967 123 19835 615 20450
16008 OHE-8Supply and Erection of Lead Acid Batteries 40 AH
with Battery Chargers:Set 5 142372 5061 711860 25305 737165
Supply, Erection, Oil Filtration, Testing and
Commissioning of 25 KV/240 Volt, 5 KVA, LT supply
transformer with 25 KV D. O. fuse switch assembly,
anticlimbing device, post insulators, copper jumper
and earth electrode etc:
(a) With Porcelain Insulators 1050mm CD Set 15 58472 8586 877080 128790 1005870
(b) With Composite Insulators 1050mm CD Set 3 57305 8586 171915 25758 197673
Supply, Erection, oil Filtration, Testing and
Commissioning of 25 KV/240 Volt, 25 KVA, LT
supply transformer with 25 KV D. O. fuse switch
assembly, anticlimbing device ,post insulators,
copper jumper and earth electrode etc:
(a) With Porcelain Insulators 1050mm CD Set 1 165899 16387 165899 16387 182286
(b) With Composite Insulators 1050mm CD Set 1 164732 16387 164732 16387 181119
16011 OHE-10 Modification to existing OHE Mtr 0 0 22 0 0 0
16012 OHE-11 Manning of switching station i.e. SP/SSP and TSS:Per
month155 0 25265 0 3916075 3916075
16013 OHE-12(a)Electrification of switching station building as per
specification Each 4 0 21660 0 86640 86640
16014 OHE-12(b) Supply & Erection of Earthing arrangement at
switching stationJob 4 10420 4952 41680 19808 61488
16015 OHE-13
Loading/Unloading transportation and handing over
of all type of materials etc. other than contractor
material
MT/KM 0 0 38 0 0 0
Total 6214394 7611469 13825863
Grand Total carried forward to summary 13825863
16010
OHE-5
OHE-9(a)
OHE- 9(b)
OHE-4
OHE-3
Unit Qty Supply
(In Rs)
Grand total in
Rs
16003
16004
16005
16009
Erection
(In Rs)
Schedule 16000
RE General
OHE-216002
Item No SOR ITEM DescriptionTotal supply in
Rs
Total Erection
(In Rs)
BOQ for Railway Electrification works between RANI(Excl.) -SRPJ(Excl.) section 198 TKM of Ajmer Division of North Western Railway
OHE-16 Page 1 of 25
BOQ of RANI-SRPJ Package-1
17001 OHE-15
Construction of Switching Station building, RCC work
,plastering, brick masonry, retaining wall, filling,
compacting and leveling work etc as per RDSO
standard drawing and supply and erection of name
board of switching station
Each 5 140394 701970
17001(a) OHE-15(a)
Extra for every 0.3 m or part there of higher plinth
over normal plinth height (On ground floor area only) Sq.m 1 174
174
17001(b) OHE-15(b)
Extra for every 0.3 m or part there of deeper
foundations over normal depth (On ground floor area
only)
Sq.m 1 174 174
17001(c) OHE-15(c)
Extra for open foundation on poor soil having every
0.3 m or part there of higher plinth over normal
plinth height (On ground floor area only) Sq.m 1 331 331
Total cost 702649
Grand Total carried forward to summary 702649
BOQ for Railway Electrification works between RANI(Excl.) -SRPJ(Excl.) section 198 TKM of Ajmer Division
of North Western Railway
Schedule 17000
Switching Post building
Item No SOR ITEM Description UnitRate (In
Rs.)Qty
Grand Total
Rs.
OHE-17 2 of 25
BOQ of RANI-SRPJ Package-1
19001 OHE-16 Supply and Erection of a guy rod assembly. Each 641 4651 722 2981291 462802 3444093
19002 OHE-17 Supply and Erection of protective screen on FOBs/ROBsSq M 28 2408 260 67424 7280 74704
Supply and Erection of bracket assembly with insulators
as per OHE plan:
(a) With Porcelain stay & bracket Insulators 1050mm
CDEach 5000 11104 622 55520000 3110000 58630000
(b) With Composite stay & bracket Insulators 1050mm
CDEach 1653 9937 622 16425861 1028166 17454027
19004 OHE-19 Supply and Erection of regulating equipment (3 pulley
type) with counter weight assembly for conventional
OHE
Each 345 36645 2690 12642525 928050 13570575
Supply and Erection of material for termination of double
Overhead Equipment conductor
(a) With Porcelain Insulators 1050mm CD Each 40 7784 679 311360 27160 338520(b) With Composite Insulators 1050mm CD Each 12 6617 679 79404 8148 87552Supply and Erection of anti-creep with galvanized steel
wire(a) With Porcelain Insulators 1050mm CD Each 125 18268 1908 2283500 238500 2522000(b) With Composite Insulators 1050mm CD Each 30 15934 1908 478020 57240 535260
19007 OHE-22 Supply and Erection of a structure bond/longitudinal
bond/ transverse and special bond:. TKM 198 13039 4160 2581722 823680 3405402
Total93371107 6691026 100062133
Grand total carried forward to summary
100062133
19006
OHE-20
OHE-21
OHE-18
Item NoSOR
ITEM
Schdule 19000
OHE - Ferrous other than steel structures and SPS
19003
19005
Description Unit Qty Supply
(In Rs)
Erection
(In Rs)
Total
supply in
Rs
Total
Erection
In Rs
Grand
Total In Rs
BOQ for Railway electrification works between RANI (Excl.) -SRPJ(Excl.) section 198 TKM Of Ajmer Division of North Western Railway
OHE-19 3 of 25
BOQ of RANI-SRPJ Package-I
20001 OHE-23(a)
Supply and Erection of Over Head
Equipment i.e. contact & catenary wire
(excluding cost of supply of contact &
catenary wires), jumper wire, dropper
wire, contact/catenary clips, fasteners
and all other material required at turn
out/overlaps/diamond crossings etc.
Final checking of OHE and adjustment,
inspection to be done by tower wagon
for commissioning of conventional OHE.
TKM 198 0 41112 0 8140176 8140176
20002 OHE-23(b)Supply of contact wire (HDGCC 107
Sq.mm) only. MT 215 629859 0 135419685 0 135419685
20003 OHE-23(c)Supply of cadmium copper catenary wire
(65 Sq. mm) only MT 135 629859 0 85030965 0 85030965
Total 220450650 8140176 228590826
Grand total carried forward to summary 228590826
Schedule 20000
OHE - Non Ferrous 'A'
Item No SOR ITEM Description Unit QtyTotal Supply
in Rs
Total
Erection
in Rs
Grand Total in
Rs
Supply (In
Rs)
Erection
(In Rs)
BOQ For Railway Electrification works between RANI(Excl.)- SRPJ(Excl.) section 198 TKM of Ajmer Division of North
Western Railway
OHE-20 4 of 25
BOQ of RANI-SRPJ Package-1
Supply and Erection of anti-creep with cadmium copper
catenary wire.
(a) With Porcelain Insulators 1050mm CD Each 8 55520 3970 444160 31760 475920
(b) With Composite Insulators 1050mm CD Each 2 53186 3970 106372 7940 114312
Supply and erection of section insulator assembly and
associated fittings & fasteners for OHE with Bar
Insulator
(a) With Porcelain Insulators 1050mm CD and Bar
InsulatorEach 55 64506 4241 3547830 233255 3781085
(b) With Composite Insulators 1050mm CD and
Porcelain Bar InsulatorEach 14 63339 4241 886746 59374 946120
21003 OHE-26Supply and Erection of PTFE type short neutral section
assemblyEach 4 761250 4349 3045000 17396 3062396
21004 OHE-27Supply and Erection of 25 KV, S.P Isolators and with
insulator with/without earth contact assembly:Each 72 66512 4386 4788864 315792 5104656
21005 OHE-28Supply and Erection of 25 KV double pole isolator and
with insulator with/without earth contact assembly:Each 19 103400 4803 1964600 91257 2055857
21006 OHE-29 Supply and Erection of all types of copper jumpers Each 130 5790 320 752700 41600 794300
21007 OHE-30Supply and Erection of insulated catenary cable in the
span under over-line structure.Mtr 261 2634 82 687474 21402 708876
21008 OHE-31
Supply of materials and erection of a large copper
jumper (160sqmm) between aluminium bus / OHE and
cross feeder with all associated fittings:
Each 63 7452 320 469476 20160 489636
21009 OHE-32Supply and Erection of solid copper busbar 18 mm dia.
Mtr 358 1523 138 545234 49404 594638
21010 OHE-33
Supply and Erection of all types of connectors for
aluminium/copper bus bar required for commissioning of
switching stations with fasteners.
Each 285 4081 56 1163085 15960 1179045
21011 OHE-34Dismantling of traction structure, portals,TTC and
associated SPS by cutting: MT 0 0 1197 0 0 0
21012 OHE-35
Supply and Erection of safety items i. e. Fire
extinguishers, set of fire bucket with stand and first aid
box, key box with suitable key chain, locks and other
misc items required for commissioning of switching
station.
Set 6 10844 1796 65064 10776 75840
21013 OHE-36
Supply and Erection of 25 KV AC OHE danger
board/danger board for height gauge, public/staff caution
board and special boards required for commissioning of
OHE/SWSs
Each 267 122 107 32574 28569 61143
21014 OHE-37
Supply, Erection and commissioning of light weight
section insulator assembly 25 KV as per drawing
no.6.2758.0 RDSO spec.no. TI/Spec/OHE/LWDSI/007Each 1 265310 23882 265310 23882 289192
21015 OHE-38
Supply, installation and commissioning of the
maintenance free earth as per RDSO specification No.
RDSO/PE/SPEC/PS/0109(REV.O)-2008
Each 1 0 324501 0 324501 324501
Total 18764489 1293028 20057517
Grand total carried forward to summary 20057517
21002
21001 OHE-24
OHE-25
Unit QtySupply
(In Rs)
Erection
(In Rs)
TotalSupply
(In Rs)
Total
Erection
(In Rs)
Grand
Total in
Rs
Schedule 21000
OHE - Non Ferrous ''B'
DescriptionItem NoSOR
ITEM
BOQ for Railway Electrification works between RANI(Excl.) - SRPJ ( Excl.) section 198 TKM of Ajmer Division of North Western Railway
OHE-21 5 of 25
BOQ of RANI-SRPJ Package-1
24001 TSS-1
Design and drawings for 220/27 or 132/27 KV or
110/27 KV traction sub-station including feeding post
and capacitor bank
Each 1 0 80242 0 80242 80242
24002 TSS-2 DELETED 0 0 0
24003 TSS-3Construction of baffle wall complete with
reinforcement, brick work, plastering etcCum 0 2420 761 0 0 0
24004 TSS-4(a)
Supply, erection, testing & commissioning of 132 KV
double pole SF-6 gas circuit breakers with interlock Each 0 581714 5118 0 0 0
24005 TSS-4(b)
Supply, erection, testing & commissioning of 220 KV
double pole SF-6 gas circuit breakers with interlock Each 1 1096604 5118 1096604 5118 1101722
24006TSS-
5(a)
Supply and erection of 132 KV double pole isolators
(manually operated)Each 0 235013 2220 0 0 0
24007TSS-
5(b)
Supply and erection of 220 KV double pole isolators
(manually operated)Each 2 235013 2220 470026 4440 474466
24008 TSS-6(a)Supply & erection of 132 KV current transformer
assembly (400-200/5A) Each 0 197215 1145 0 0 0
24009 TSS-6(b)Supply & erection of 220 KV current transformer
assembly (200-100/5A) Each 3 197215 4327 591645 12981 604626
24009A TSS-6(c )Supply & erection of 110 KV current transformer
assembly (400-200/5A) Each 0 131033 1145 0 0 0
24009B TSS-6(d)Supply & erection of 132 kV current transformer
assembly (1200-800-400/5-5-5A)Each 0 246611 1145 0 0 0
24010 TSS-7 (a) Supply & erection of 120 KV lightning arrestors Each 0 115399 811 0 0 0
24011 TSS-7 (b) Supply & erection of 198 KV lightning arrestors Each 4 115399 1414 461596 5656 467252
24011A TSS-7 (c ) Supply & erection of 96 KV lightning arrestors Each 0 48045 811 0 0 0
24012 TSS -8(a)
Supply, erection, testing & commissioning of 25 KV
single pole Vacuum circuit breaker with interlocking of
rating 1600 ampsEach 4 303780 3594 1215120 14376 1229496
24012A TSS -8(b)
Supply, erection, testing & commissioning of 25 KV
single pole Vacuum circuit breaker with interlocking of
rating 2000 ampsEach 0 359578 3594 0 0 0
24013 TSS -9(a)Supply & erection of 25 KV current transformers
(1500-750/5A)Each 4 55163 473 220652 1892 222544
24013A TSS -9(b)Supply & erection of 25 kV current transformers
(3000-1500/5 Amps)Each 0 63755 473 0 0 0
24013B TSS -9(c )Supply & erection of 25 KV current transformers (200-
100/5A)Each 0 41645 2790 0 0 0
24014 TSS-10 Supply, erection, testing and commissioning of
control & relay numeric panel suitable for double
transformer traction sub -stations of 220/27 or
132/27 KV or 110/27 KV
Each
1 1477300 9279 1477300 9279 1486579
24015 TSS-11 Supply & erection of tubular aluminum bus bars
50mm x 39mm dia
Mtr180 417 32 75060 5760 80820
24016 TSS-12 Supply & erection of ‘Zebra’ ACSR conductor Mtr 350 257 7 89950 2450 92400
24017 TSS-13
Supply & erection of all type of connectors, bus splice
& TEE connectors etc required for commissioning of
TSS equipments
Each 160 1595 20 255200 3200 258400
24018 TSS-14Supply & erection of copper jumper with fittings and
fasteners required for TSSEach 35 2396 331 83860 11585 95445
24019 TSS-15(a)Supply & erection of 110/132 KV support insulators
with fittings and fastenersEach 0 24072 384 0 0 0
24020 TSS-15(b)Supply & erection of 220 KV support insulators with
fittings and fastenersEach 10 24072 600 240720 6000 246720
24021 TSS-16Supply & erection of 25 KV support insulators with
fittings and fastenerEach 20 2943 110 58860 2200 61060
24022 TSS-17(a)Supply & erection of 110/132 KV termination
with/without adjuster complete with disc insulatorsEach 0 8726 200 0 0 0
24023 TSS-17(b)Supply & erection of 220 KV termination with/without
adjuster complete with disc insulatorsEach 14 8726 306 122164 4284 126448
24024 TSS-18Supply & erection of low maintenance lead acid
batteries set with 2 nos. of suitable battery chargerSet 1 612306 6736 612306 6736 619042
24025 TSS-19Supply & erection of 240Volt AC and 110 V DC
Distribution boards in the control roomEach 3 22548 479 67644 1437 69081
24026 TSS-20 Supply and erection of earth electrode Each 30 1885 734 56550 22020 78570
24027 TSS-21Supply and erection of earth leads 75 x 8 mm mild
steel flat laid in the ground or exposed as per site
requriment
Mtr 900 133 39 119700 35100 154800
24028 TSS-22
Supply and erection of earth leads 50 x6 mm mild
steel flat laid in the ground or exposed as per site
requriment
Mtr 1200 65 31 78000 37200 115200
24029 TSS-23 Supply and erection of 8 SWG GI Wire for earthing Mtr 100 12 13 1200 1300 2500
24030 TSS-24Supply and erection of 32mm dia MS rod for earth
matMtr 2000 153 13 306000 26000 332000
Schedule-24000
TRACTION SUB- STATION
Item No SOR ITEM Description Unit qty Supply
(In Rs)
Erection
(In Rs)
Total
supply in
Rs
Total
Erection
(In Rs)
BOQ for Railway Electrification works between RANI(Excl.) - SRPJ ( Excl.) section 198 TKM of Ajmer Division of North Western Railway
Grand total in
Rs
TSS 6 of 25
BOQ of RANI-SRPJ Package-1
24031 TSS-25Supply & erection of earth screen wire including
terminationMtr 250 169 9 42250 2250 44500
24032 TSS-26(a)
Suppy, erection, testing & commissioning of 132/27
KV, 21.6/30.24 MVA, ONAN/ONAF, single phase
traction power transformers
Each 0 24091345 184047 0 0 0
24033 TSS-26(b)
Suppy, erection, testing & commissioning of 220/27
KV, 21.6/30.24 MVA, ONAN/ONAF, single phase
traction power transformers
Each 1 33895503 184047 33895503 184047 34079550
24033A TSS-26(c )
Suppy, erection, testing & commissioning of 110/27
KV, 21.6/30.24 MVA, ONAN/ONAF, single phase
traction power transformers
Each 0 17228475 184047 0 0 0
24033B TSS-26(d)
Suppy, erection, testing & commissioning of 132/27
KV, 30/42 MVA, ONAN/ONAF, single phase traction
power transformers
Each 0 27838617 184047 0 0 0
24034 TSS-27(a)Supply and erection of 25 Kv double pole isolator
1600 Amp with insulatorsEach 5 66784 2127 333920 10635 344555
24034A TSS-27(b)Supply and erection of 25 Kv double pole isolator
3150 Amp with insulatorsEach 0 133680 2127 0 0 0
24035 TSS-28(a)Supply and erection of single pole isolator 1600 Amp
with insulatorsEach 8 36927 2127 295416 17016 312432
24035A TSS-28(b)Supply and erection of single pole isolator 3150 Amp
with insulatorsEach 0 67826 2127 0 0 0
24036 TSS-29
Supply, erection, testing & commissioning of 25 KV
shunt capacitor bank of 2400 KVAR rating at 25 KV
including lowloss sereis reactor, 25 KV neutral current
transformer, and other accessories etc.,
Each 1 2018938 42292 2018938 42292 2061230
24037 TSS-30
Excavation of Earth to the depth of 2 meter below
ground level for burying 13mtrs long rail and
connecting it as per RDSO drawing (Rail will be
supplied by RVNL)
Each 0 0 2184 0 0 0
44286184 555496 44841680
44841680
NOTE: 1 Provision of cross track, control room building and approach road shall be made in the civil portion of the estimate. 2. Provision of yard lighting and water jet pump shall be made in the general electrical portion of the estimate.
2
Total
Grand total carried forward to summary
Provision of yard lighting and water jet pump shall be made in the general electrical portion of the estiate.
TSS 7 of 25
BOQ of RANI-SRPJ Paackage-1
Item No Description of item Unit Qty SOR rates in Rs Total supply in Rs
27001 SF-6 Gas Cylinder with filling arrangement Each 0 29590 0
27002 25KV CB Bushing Each 1 31527 31527
27003 Interruptor Bushing Each 1 11298 11298
27004 Earth fault Relay Each 1 7209 7209
27005 Buchholz Relay Each 1 16140 16140
27006 Relay Testing Kit Set 1 146334 146334
27007 HRC fuse 2A, 4A, 10A, 15A, 32 Amp Set 10 1076 10760
27008 Transformer Oil Litre 5000 28 140000
27009 Capacitor unit of capacitor bank Set 1 550265 550265Total 913533
913533
Schedule 27000
TSS Spares
Grand total carried forward to summary
BOQ for Railway Electrification works between RANI(Excl.)-SRPJ (Excl.) section 198 TKM of Ajmer Division of North
Western Railway
BOQ of RANI-SRPJ Package-1
Item No Description Unit Qty Rate Total supply
28001 Tirfor 2.5T/1.5T Nos 1 6672 6672
28002 Trifor 5T/3T Nos 1 9118 9118
28003 Pull lift 3 T Nos 1 8285 8285
28004 Pull lift 3/4 T Nos 1 3670 3670
28005 Aluminium / Light weight metal conduit Platform ladder trolley Nos 1 9453 9453
28006 Rail jumpers with clamps at both ends Nos 3 1023 3069
28007 Earthing discharge rod complete Nos 6 7228 43368
28008 Aluminium Straight ladder extensive (11 M) Nos 2 4893 9786
28009Portable Electric Drill 21mm, single phase, 230V (for drilling) Ralli
Wolf, Hitachi, Black & Decker makes only
Nos 1 94539453
28010 First aid box filled with medicines as per standard Nos 1 1112 1112
28011 Stretcher Nos 1 722 722
28012Fire bucket (10 Ltrs) capacity with one stand and cover for set of 4/6
buckets at each switching station/TSS
Nos 5 134670
28013 Portable fire extinguisher dry chem. Powder (10 Ltr) Nos 2 3892 7784
28014 Portable fire extinghuisher foam type (cap 9 Ltr) Nos 2 4226 8452
28015 D' Shackles set of on each (1", 3/4", 5/8", 1/2") Nos 2 1112 2224
28016 Set of Steel sling with Eye each end of 2 M & 3 M Nos 8 1390 11120
28017 Micro meter Mitutoyo make/ as required by Railway Nos 1 1501 1501
28018 Bench Vice 6" Nos 1 1112 1112
28019 Canvass Tarpaulin 12 m x 12m Nos 2 2224 4448
TESTING AND MEASURING EQUIPMENTS 0
28020 Insulation Megger 250V Nos 1 5561 5561
28021 Binoculars Nos 1 556 556
28022 Vernier Callipers Mitutoyo make/ as required by Railway Nos 1 834 834
28023 Walkie Talkie Sets (2W output) Nos 4 5561 22244
28024 Digital Multimeter Nos 3 4448 13344
28025 Magic Pole ladder 8' Nos 1 6672 6672
28026 Drop out fuse pull rod Nos 2 1112 2224
280271/2" square drive socket set containing 19 sockets with 6 attachments Nos 2 1112
2224
28028 Transformer oil Acidity testing Kit Nos 1 5561 5561
28029 Motor operated insulation tester 5 Kv Nos 1 4671 4671
28030 Pocket size clip on Tong tester Nos 1 1669 1669
28031 A.C. Voltmeter 0 - 150 V Nos 2 890 1780
28032 A.C Voltmeter 0 - 500 V Nos 2 1669 3338
28033 Digital time interval meter 15 - 1000 seconds Nos 2 1112 2224
28034 Insulation tester 2.5 KV Nos 1 2780 2780
28035 Earth tester Nos 2 4448 8896
28036 Insulation Megger 500 V Nos 1 7228 7228
28037 Transformer Oil BDV testing Kit Nos 1 14456 14456
28038 125 Litre cap oil filtration plant Nos 1 111207 111207
28039 Auto transformer 2 A capacity Nos 1 1669 1669
28040 Load cell tester suitable for 40 AH and 200 AH battery Nos 1 1112 1112
28041 Emergency Telephone Nos 3 5005 15015
28042Spanner set double ended, 24 size 12 pieces set (6mm to 42mm)
Gedore or Tapraia make with ISI Mark
Set 4 534721388
28043 Cogex or Similar 52 pieces socket set (box spanners) Set 1 4010 4010
28044 Primary current injection testing kit (0 - 3000 amps) Each 0 789735 0
28045 Digital Insulation testing meter (5 KV Megger) Each 1 290615 290615
28046 Digital earth resistance meter Each 2 58123 116246
28047 Thermal Imaging camera with software Each 0 1076933 0
28048 Tan delta field test set Each 0 796547 0
28049
Supply, installation, testing & commissioning of GPS based OHE
monitoring & current collection system as per RDSO spec No.
TI/SPC/OHE/OLIVIR/0050(01/06) or latest
Each 0 398800
0
Total(schedule items) 809543
NON SCHEDULE ITEMS
NS-1 Dielectric tester 0 to 75 kv with accessories. Each 1 45835 45835
NS-2Digital thermometer (Motwani/Meco/Testica or similar reputed make)
Each 1 1790 1790
NS-3 Cutting plier (Good Quality) 9 inches Each 5 158 790
NS-4 Nose plier (Good Quality) 9 inches long Handle insulated for 2 KV Each 5 158 790
Total (Non schedule items) 49205
858748
SCHEDULE -28000
Tools & Plants (OHE & PSI)
BOQ for Railway Electrification works between RANI(Excl.) - SRPJ(Excl.) section 198 TKM of Ajmer Division of North Western Railway
Grand total (schedule & non schedule items) carried forward to Summary
Page 9 of 25
BOQ of RANI-SRPJ Package-1
29001 SCADA-1Preparation and supply of Design & Drawing for
SCADA at RCC,TSS,SP & SSP. Job 1 0 736096 0 736096 736096
29002 SCADA-2 Supply of SCADA equipments & Software for RCC. Set 1 3710933 0 3710933 0 3710933
29003 SCADA-3(a) Supply of RTUs for FP/TSS Each 2 347373 0 694746 0 694746
29004 SCADA-3(b) Supply of RTU for SP. Each 3 223178 0 669534 0 669534
29005 SCADA-3(c) Supply of RTUs for SSP. Each 5 223178 0 1115890 0 1115890
29006 SCADA-4(a)Supply of Maintenance Free/Low Maintenance type
Lead Acid battery.Set 1 192502 0 192502 0 192502
29007 SCADA-4(b) Supply of UPS. Set 1 198711 0 198711 0 198711
29008 SCADA-5 Supply of furniture. Set 1 186292 0 186292 0 186292
29009 SCADA-6Supply of Data logging Printer for Remote Control
Centre.Nos. 2 31049 0 62098 0 62098
29010 SCADA-7(a)Erection, testing & commissioning charges for
items SCADA-2 to SCADA-6.Job 1 0 436502 0 436502 436502
29011 SCADA-7(b)Integration of new SCADA system to existing
system at RCC.Job 1 0 220828 0 220828 220828
29012 SCADA-8(a)Erection, integration, testing & commissioning for
existing and new equipments for TSS.Job 1 0 176661 0 176661 176661
29013 SCADA-8(b)Erection, integration, testing & commissioning for
existing and new equipments for SSP.Job 1 0 58887 0 58887 58887
29014 SCADA-8(c)Erection, integration, testing & commissioning for
existing and new equipments for SP.Job 1 0 147218 0 147218 147218
29015 SCADA-9Supply of Equipment and Components (As per list
B)Set 1 371342 0 371342 0 371342
29016 SCADA-10 Supply of Spl. T & P (As per list C) Set 1 453310 0 453310 0 453310
Total 7655358 1776192 9431550
Grand total carried forward to summary 9431550
Schedule-29000
SCADA
Item No SOR ITEM Description UnitSupply (In
Rs)
Grand
total (In
Rs)
QtyErection
in Rs
Total
supply in
Rs
Total
erection
in Rs
BOQ for Railway Electrification works between RANI (Excl.) - SRPJ (Excl.) section 198 TKM of Ajmer Division of North Western Railway
SCADA 10 of 25
BOQ of RANI-SRPJ Package-1
30001 CS-1Supply and erection of 25 KV,1600 Amp vacuum
InterruptorEach 16 241008 2755 3856128 44080 3900208
30002 CS-2Supply and erection of 25 KV Potential Trasformer
Type-I or Type-IIEach 16 49111 518 785776 8288 794064
30003 CS-3Supply and erection of 42 KV Lightning Arrestor
with surge monitor, counter and cableEach 19 17710 363 336490 6897 343387
30004 CS-4 Supply and installation of cables for SWS/TSS Mtr 3758 137 11 514846 41338 556184Supply, erection, oil filteration, testing &
commissioning of 25KV/240V 10 KVA Auxiliary
(LT) Supply Transformers oil type with DO fuse
switch, anti climbing device, pedestal insulators,
copper jumper and earth electrode etc.
(a) With Porcelain Insulators 1050mm CD Set 19 63719 8506 1210661 161614 1372275(b) With Composite Insulators 1050mm CD Set 6 62552 8506 375312 51036 426348
30006 CS-6 Providing and laying of Concrete For Foundation
and Plinth In Other Than Hard and Rocky soilCUM 12696 3102 1004 39382992 12746784 52129776
30007 CS-7 Providing and laying of Concrete For Foundation
and Plinth In all types of soils and soft rock.CUM 125 3205 1493 400625 186625 587250
30008 CS-8
Providing and laying of Reinforced Concrete for
Pier/Coloumn/Pile, Cable Trench and Trench
Cover
CUM 57 263340
30009 CS-9Supply and erection of all types of galvanised
Steel Structures, Small Parts Steel etc. MT 2382 66552 2103 158526864 5009346 163536210
30010 CS-10Supply and erection of Fencing Panels, Uprights,
Gate and Anti-Climbing device Mtr 1783 1956 66 3487548 117678 3605226
30011 CS-11Supply and erection of Aluminium Jumper with
FastnersEach 21 1540 163 32340 3423 35763
30012 CS-12Supply and erection of Copper Strips for
equipment earthingMtr 106 929 98 98474 10388 108862
30013 CS-13Supply and erection of Aluminium Bus Bar
36mmx28mmMtr 239 229 34 54731 8126 62857
30014 CS-14Supply and spreading of gravel/ ballast in the
swich yard (TSS/SP/SSP)Cum 284 698 5 198232 1420 199652
30015 CS-15
Dismantling of redunant foundation with
compressor powered machines/manually with
contractor's own men and material including
consumables like Diesel Oil etc.
Nos 10 0 1875 0 18750 18750
30016 CS-16
Monthly charges for one crane operator for full
time operation for one crane including Monthly
charges for one Watch&Ward for one crane.
Per-
Month15 0 15548 0 233220 233220
30017 CS-17
Supply and Erection of anti theft transformer 240
volt/2.2 KV 5 KVA, with DO Fuse switch
excavation of cable trench, laying of cables,
earthing, jumpering, DG set including dismantling
of above equipments.
each
location2 49677 34545 99354 69090 168444
Total 209623713 18718103 228341816
Grand total carried forward to summary 228341816
4620 263340
30005 CS-5
Item NoSOR
ITEM Description Qty
BOQ for Railway Electrical works between RANI(Excl.)- SRPJ(Excl.) section 198 TKM of Ajmer Division of North Western Railway
Common Schedule of OHE/TSS
UnitSupply
(In Rs)
Grant total
(In Rs)
Erection in
Rs
Total
Supply in
Rs
Total
Erection in
Rs
Common OHE 11 of 25
BOQ of RANI-SRPJ Package-1
Supply Erection Total supply Total Erection Grant total
1 2 3 4 5 6
33001
Electrification of staff quarter complete with point wirings, circuit wirings,
sub main wirings etc. with Fire Retardant (FR) PVC insulated,
multistranded, copper conductor, single core cable on surface /in
recessed PVC conduits, along with provision of luminaries with lamps,
call bells, ceiling & exhaust fans, distribution boards, loose wire box,
geyser, energy meters in M.S. box including earthing with G.I. pipe
electrode etc. as per Scale of fittings,and cable sizes, nos. of points
permissible in each circuit and sub main/s etc.for each type of quarter as
indicated in Explanatory Notes.
i) Type - I quarter Each 0 0 23379 0 0 0
ii) Type - II quarter Each 16 0 24591 0 393456 393456
iii) Type - III quarter Each 4 0 30867 0 123468 123468
iv) Type - IV quarter Each 1 0 57106 0 57106 57106
v) Type - V quarter Each 0 0 78371 0 0 0
vi) Extra for stair case light point controlled with two nos. two way switches Each 10 0 502 0 5020 5020
33002
Electrification of gate man lodge complete with point wirings, circuit
wirings etc. with Fire Retardant (FR), PVC insulated, multistranded,
copper conductor, single core cable on surface/in recessed PVC
conduits including provision of luminaries with lamps, ceiling fan,
distribution board, earthing with G.I.pipe electrode etc. as per Scale of
fittings, Cable sizes, no. of points permissible in each circuit and sub
mains as indicated in Explanatory Notes.
Each 2.00 0.00 14546.00 0 29092 29092
33003 (i)
Wiring for light/ceiling fan/exhaust fan/call bell/light plug/group etc. points
including circuit wiring, sub-main wiring with Fire Retardant (FR), PVC
insulated, multistranded, copper conductor, single core cable on
surface/in recessed PVC conduits, distribution boards, sub distribution
boards, earthing etc as required. Wiring shall be done as per sizes of
cables, no. of points permissible in each circuit and sub main as
indicated in Explanatory Notes.
Point 490.00 0.00 908.00 0 444920 444920
BOQ for Railway Electrification works of between RANI(Excl.)-SRPJ(Excl.) section 198 TKM of Ajmer Division of North Western Railway
SCHEDULE -33000
Bill No.33 :GENERAL SERVICES ELECTRICAL WORKS
This schedule shall be read in conjunction with its Explanatory Notes and Technical Specifications for detailed description for various items included therein.
Amount in Rs
SECTION - A :
BOQ item No. Description of Items Unit Qty
Rate (in Rs.)
ELECTRIFICATION OF STAFF QUARTERS
ELECTRIFICATION OF GATE MAN LODGES AT LEVEL CROSSINGS
ELECTRIFICATION OF SERVICE BUILDINGS & PASSENGER SHELTER AND SHED
GEW Page 12 of 25
BOQ of RANI-SRPJ Package-1
33003 (ii)
Wiring for power plug point including circuit wiring, sub main wiring, with
Fire Retardant (FR) PVC insulated, multistranded, copper conductor,
single core cable on surface/in recessed PVC conduits, distribution
boards, sub distribution boards, earthing with G.I.pipe electrode etc as
required. Wiring shall be done as per sizes of cables, no. of points
permissible in each circuit and sub main as indicated in Explanatory
Notes.
Point 54.00 0.00 1666.00 0 89964 89964
33003 (iii)Extra for provision of industrial type iron clad plug socket with 32A DP
MCB in M.S.Box Point 10.00 0.00 455.00 0 4550 4550
ELECTRIFICATION OF PASSENGER SHELTER AND SHEDS
33004 (i)
33004 (ii)
33004 (iii)
SECTION -B :PROVISION OF LUMINARIES,FANS,WATER COOLERS ETC.
33005 (i)
Supply, installation, testing and commissioning of prewired 1x28watt, T-5,
energy efficient, surface type luminary with epoxy powder coated CRCA
sheet steel housing with reflector cover, complete with electronic ballast,
T-5 tube etc. & earthing etc. as required.
No. 286 1214 191 347204 54626 401830
33005 (ii)
Supply, installation, testing and commissioning of prewired 2x28watt, T-5,
energy efficient, surface type luminary with epoxy powder coated
CRCA sheet steel housing with reflector cover, complete with electronic
ballast, T-5 tube etc. & earthing etc. as required.
No. 16 1657 414 26512 6624 33136
33006 (i)
Supply, installation, testing and commissioning of prewired 2x28watt, T-5,
energy efficient street light luminary , complete with T-5 tubes, electronic
ballast etc.on bracket pipe of erected pole or on wall bracket of GI class
"B" pipe & connections from junction box/overhead line/light point etc. to
luminary with 1.5 sq.mm FRLS PVC insulated multistranded copper
conductor single core/three cable as instructed & earthing etc as
required.
No. 0 2456 386 0 0 0
33006 (ii)
Supply, installation, testing and commissioning of prewired 1x28watt, T-5,
energy efficient street light luminary , complete with T-5 tubes,
electronic ballast etc.on bracket pipe of erected pole or on wall bracket of
GI class "B" pipe & connections from junction box/overhead line/light
point etc. to luminary with 1.5 sq.mm FRLS PVC insulated multistranded
copper conductor single core/three cable as instructed & earthing etc as
required.
No. 0 1703 426 0 0 0
33006 (iii)
Supply, installation, testing and commissioning of prewired 2x14 watt, T-
5, energy efficient street light luminary complete with T-5 tubes,
electronic ballast etc.on bracket pipe of erected pole or on wall bracket of
GI class "B" pipe & connections from junction box/overhead line/light
point etc. to luminary with 1.5 sq.mm FRLS PVC insulated multistranded
copper conductor single core/three cable as instructed & earthing etc as
required.
No. 125 3132 783 391500 97875 489375
Deleted
GEW Page 13 of 25
BOQ of RANI-SRPJ Package-1
33006 (iv)
Supply, installation, testing and commissioning of prewired 4x14 watt, T-
5, energy efficient street light luminary , complete with T-5 tubes,
electronic ballast etc.on bracket pipe of erected pole or on wall bracket of
GI class "B" pipe & connections from junction box/overhead line/light
point etc. to luminary with 1.5 sq.mm FRLS PVC insulated multistranded
copper conductor single core/three cable as instructed & earthing etc as
required.
No. 0 5810 1452 0 0 0
33006 (v)
Supply, installation, testing and commissioning of prewired 4x24 watt, T-
5, energy efficient street light luminary complete with T-5 tubes,
electronic ballast etc on bracket pipe of erected pole or on wall bracket of
GI class "B" pipe & connections from junction box/overhead line/light
point etc. to luminary with 1.5 sq.mm FRLS PVC insulated multistranded
copper conductor single core cable & earthing etc as required.
Nos. 0 6207 1552 0 0 0
33007
Supply, installation, testing and commissioning of metal halide street light
luminary complete with MH/HPSV lamp, on bracket pipe of erected pole
or on wall bracket of class"B"G.I.pipe & connections from junction
box/overhead line/ light point etc. to luminary with 1.5 sq.mm FRLS PVC
insulated multistranded copper conductor, single core/three cable as
instructed & earthing etc as required.
(i) 1 x 70 Watt. No. 5 4453 699 22265 3495 25760
(ii) 1 x 150 Watt No. 0 5196 815 0 0 0
33008
Supply, installation, testing and commissioning of 230V A.C. ceiling fan
with double ball bearing and suitable capacitor complete with wiring with
1.5sq.mm FR, PVC insulated, copper conductor, single/three core
cable as instructed, etc. as required.
i) 1200 mm (without Regulator) No. 65 1255 196 81575 12740 94315
ii) 1400 mm (without Regulator) No. 5 1363 214 6815 1070 7885
33009
Supply and fixing of stepped type, electronic fan regulator, 300 watts,
on the existing phenolic laminated sheet cover plate/modular plate of
switch box, including connections,testing & commissioning as required.
No. 70 256 57 17920 3990 21910
33010
Supplying, installation, testing and commissioning of 11-23 watts, 250
volts, 2 pin, compact fluorescent lamp (CFL) complete with electronic
ballast etc. as required.
No. 23 134 21 3082 483 3565
33011
Supplying, erection, testing and commissioning of exhaust fan suitable
for 1-phase, 230 volts, AC supply system complete with capacitor, louver
shutters, grouting bolts with nuts, making opening/modification in the wall
to suit the size of the fan, making good the damages, connections with
1.5sq.mm, FR, PVC insulated, multistranded copper conductor, single
core /three cable as instructed, earthing etc. as required.
(i) AC exhaust fan 300 mm 900 rpm with/without louver shutters. No. 20 2024 317 40480 6340 46820
GEW Page 14 of 25
BOQ of RANI-SRPJ Package-1
33012
Supply, installation, testing and commissioning of self contained drinking
water cooler 150 liters capacity complete with all connected standard
fittings, accessories etc. and 5KVA , wall mounted, I.C. controlled
electronic auto-voltage corrector with time delay relay, connection to
earthing system etc as required.
Each 4 51938 8157 207752 32628 240380
SECTION - C: L.T.SWITCH BOARDS AND FEEDER PILLAR
33013Supply, installation, testing & commissioning of cubical type, wall
mounted, dust & vermin proof, LT switch board of different capacities,.
LT Switch Board 125 Amp comprising of the items indicated as
under:
i) Incoming MCCB 125A, 4 pole, 35kA, fixed type (Ics=100%Icu) - 1 No
ii) Outgoing MCCB 63A, 25kA, fixed type (Ics=100%Icu) - 4 Nos
iii) Outgoing MCB 40A, 4 pole, 10kA - 4 Nos
iv) Outgoing MCB 32A, double pole, 10kA - 6 Nos
v) Sleeved/Epoxy coated copper bus-bar 250 A in bus bar chamber
vi) CT's, Indication lights
LT Switch Board 63 Amp comprising items indicated as under:
(i) Incoming MCCB 63A, 4 pole, 35kA, fixed type (Ics=100%Icu) - 1 No
(ii) Outgoing MCCB 40A, 4 pole, 25kA, fixed type (Ics=100%Icu) - 3 Nos
(iii) Outgoing MCB double pole, 6-32A, 10kA - 20 Nos
(iv) Sleeved/Epoxy coated copper bus-bar 200A in bus bar chamber
(V) Indication Lights
33014 Deleted
33015Supply, installation, testing & commissioning of weather proof, L.T.
feeder pillar of different capacities
LT Feeder Pillar 63 Amp comprising of the items indicated as under:
(i) Incoming MCCB 63A, 4 pole, 35kA, fixed type (Ics=100%Icu) - 1 No
(ii) Outgoing MCCB 40A, 4 pole, 25kA, fixed type (Ics=100%Icu) - 4 Nos
(iii) Outgoing MCB double pole, 40A, 10 KA - 4 Nos
(iv) Sleeved/Epoxy coated copper bus-bar 200A in bus bar chamber -
2 set .
(v) Indication lights
17550 129282No.
(a)
111732
(b) No
2 55866 8775
No. 1 57765
2 50929 7999
9072
(i)
101858 15998 117856
57765 9072 66837
GEW Page 15 of 25
BOQ of RANI-SRPJ Package-1
LT Feeder Pillar 125 Amp comprising of the items indicated as
under:
(i) Incoming MCCB 125A, 4 pole, 35kA (Ics=100%Icu) - 1 No
(ii) Outgoing MCCB 63A, 4 pole, 25kA (Ics=100%Icu ) - 4 Nos
(iii) Outgoing MCB 40A, 4 pole, 10kA - 4 Nos
(iv) Outgoing MCB 32A, DP, 10kA - 6 Nos
(v) Modular digital time switch and 3 phase contactor 63 A -- 2 set.
(vi)Sleeved/Epoxy coated copper bus-bar 250 A in bus bar chamber
(vii) Indication lights
LT Feeder Pillar 250 Amp comprising of the items indicated as
under:
i)Incoming MCCB 250 A FP 35KA(Ics=100%Icu) Fixed Type-1 No
ii)Outgoing MCCB 125 A FP 35KA(Ics=100%Icu) Fixed Type- 2 Nos
iii) Outgoing MCCB 63 Amps FP 25KA (Ics=100%Icu) Fixed Type - 4 Nos
iv) Outgoing MCB 40 Amps FP 10 KA -4 Nos
v) Outgoing MCB 32 Amps DP 10 KA-6 Nos
(vi) Modular digital Time switch and3 phase contractor 63 A- 2 set
(vii) Sleeved / Epoxy coated Copper bus-bar 400 A in Bus Bar chamber
(viii)Indication lights
33016 Deleted
Supply and erection of different length , swaged type steel tubular pole ,
complete with the following:
a) Double door, weather proof M.S. junction box (degree of protection not
less than IP54) complete with MCB 6 amps, copper bus bar for looping 4-
core, 3 nos. LT cables and clamping with pole, as required.
b) Casting of foundation with concrete of M10 grade and providing
muffing up to 300 mm above ground level,as required
c) Erection of GI pipe class 'B' ISI marked up to junction box for passing
cable.
(Payment of G.I. pipe shall be made against the relevant BOQ item).
i)7 Meter long pole with canopy type single pipe bracket (for one
luminary)No. 0 8677 1363 0 0 0
ii)7 Meter long pole with canopy type double pipe bracket (for two
luminaries)No. 0 8955 1407 0 0 0
iii) 9 Meter long pole with canopy type single pipe bracket No. 0 13025 2047 0 0 0
(iii) No. 0 106892 16788
1 68942 10828 (ii) No. 68942 10828 79770
0 0 0
SECTION - D : EXTERNAL ELECTRIFICATION WORKS
33017
GEW Page 16 of 25
BOQ of RANI-SRPJ Package-1
33018 Deleted
33019
Supply of GI pipe - class' B' ISI marked with accessories including bends
etc. for support of cable with erected pole/recessing in wall/floor/passing
earth strip OR passing cable as required:
i) 32 mm dia Meter 0 173 28 0 0 0
ii) 40 mm dia Meter 250 206 32 51500 8000 59500
iii) 50 mm dia Meter 400 267 42 106800 16800 123600
iv) 65 mm dia Meter 0 337 54 0 0 0
v) 80mm dia Meter 0 448 70 0 0 0
vi) 100mm dia Meter 150 631 99 94650 14850 109500
vii) 150mm dia Meter 50 1027 162 51350 8100 59450
33020
Supply, erection, testing & commissioning of control and distribution
panel for colour light signalling supply in 25kV AC traction system as per
RDSO technical specifications No.TI/SPC/PSI/CLS/0023 including latest
amendment.
(i) For 10kVA AT No 10 47669 7487 476690 74870 551560
(ii) For 25kVA AT No 1 101421 15929 101421 15929 117350
ELECTRIFICATION OF FOOT OVER BRIDGE
33021
Electrification of foot over bridge complete with 3.5 meter long, 50 mm
dia, G.I. pipe pole with GI pipe bracket, luminary with lamp, M.S. junction
box, connection from junction box to luminary with 1.5 sq.mm, Flame
Retardant (FR), PVC insulated, copper conductor cable and connection
to earthing system. etc. and as per scale of fittings indicated in
Explanatory Notes.
No 2.00 0.00 8451.00 0 16902 16902
SECTION - E: POWER SUPPLY DISTRIBUTION ARRANGEMENT
33022
Supply, installation, testing and commissioning of 11kV/415 Volt,
Delta/Star connected, copper wound, power distribution transformer
(outdoor type) conforming to IS:2026 (Latest Version) complete with all
accessories as required.
(i) 100 kVA No. 2 172543 31565 345086 63130 408216
(ii) 250 kVA No. 1 279389 51112 279389 51112 330501
(iii) 500 kVA No. 0 359714 65806 0 0 0
(iv)Extra for providing fencing /enclosure for above item as indicated in
Explanatory Notes. Kg 200 53 12 10600 2400 13000
(v)Extra for construction of foundation for transformer installation as
required Cu.M 25 3339 944 83475 23600 107075
GEW Page 17 of 25
BOQ of RANI-SRPJ Package-1
33023
Supply, erection, testing and commissioning of 3 pole, 11kV, 400amps,
gang operated switch complete with drop out fuses etc. as required. No. 2 20391 3731 40782 7462 48244
33024
Supply, installation, testing and commissioning of 11kV, 350 MVA, 630 A
draw out type manually operated, 3 panel HT VCB board complete
with CTs, PTs etc as required.
Set 0 1143754 209240 0 0 0
Supply, installation , testing & commissioning of , 17 panel LT switch
board comprising of following:
i) Incoming ACB 800A, 4 pole, 50kA (manual draw out type) with CTR
400/5A - 2 Nos
ii) ACB bus coupler 800A, 4 pole, 50kA (fixed type) - 1 No
iii) On load change over switch 400A, 4 pole, utilisation cat. AC 23 - 1
No.
iv) Out going switch fuse unit/fuse switch unit cat AC23 (TPN) with HRC
fuses (250 Amp) - 4 Nos
v) Out going switch fuse unit/fuse switch unit cat AC 23 (TPN) with HRC
fuses 125 Amp - 4 Nos.
vi) Out going switch fuse unit/fuse switch unit cat AC 23 (TPN) with HRC
fuses 63 Amp - 5 Nos.
vii) Sleeved/epoxy coated copper bus-bar - 800A for phases and 400A
for neutral.
Supply, erection, testing & commissioning of 20 panel LT switch
board comprising of the following:
i). Incoming ACB 800A, 4 pole, 50kA (manual draw out type) with CTR
800/5A - 2 Nos
ii). ACB bus coupler 1600A, 4 pole, 50kA (fixed type) - 1 No
iii). On load change over switch 800A, 4 pole, cat AC 23 - 1 No.
iv). Out going switch fuse unit/fuse switch unit cat AC 23 (TPN) with HRC
fuses 400 Amp) - 3 Nos
v). Out going switch fuse unit/fuse switch unit cat AC 23 (TPN) with HRC
fuses 250 Amp) - 4 Nos
vi) Out going switch fuse unit/fuse switch unit cat AC 23 (TPN) with HRC
fuses 125 Amp - 4 Nos.
vii) Out going switch fuse unit/fuse switch unit cat AC 23 (TPN) with HRC
fuses 63 Amp - 5 Nos.
Sleeved/epoxy coated copper bus-bar - 1600A for phases and 800A for
neutral.
33027(i) Deleted
33027(ii) Deleted
33028 Deleted
33025 No. 0 765235 75673
0 0 00 1180859 11677333026 No.
0 0 0
GEW Page 18 of 25
BOQ of RANI-SRPJ Package-1
33029
Supply, erection/fixing of Fire extinguishing equipments (ISI)
Marked,Rubber mat (ISI marked) ,GI fire buckets filled with clean dry
sandheld on free standing steel stand,First Aid Box with medicines (ISI
marked) and associated materials,shock treatment chart on aluminum
frame,Schematic diagram of HT/LT installation & transformer data on
white hylem sheet with aluminium frame & fixing / providing in the sub
stationarea as per details in explanatory notes.
Set 5 45449 7138 227245 35690 262935
33030
Supply, installation, testing and commissioning of DG set with acoustic
enclosure, complete with AMF panel and all other accessories and
construction of plinth etc,
(i)82.5 kVA DG set with 160 amp, 4-pole, MCCB 50kA (Ics=100%Icu), 250
amps copper bus-bars, 4 pole contactors 250amp.Set 1 863493 85389 863493 85389 948882
(ii)160 kVA DG set with 250 amp, 4-pole MCCB 50 KA(Ics=100%Icu), 400
amps copper bus-bars, 4 pole contactors 400amps Set 1 1367729 135252 1367729 135252 1502981
(iii)250 kVA DG set with 400 amp, 4-pole MCCB 50kA (Ics=100%Icu), 600
amp copper bus-bars, 4 pole contactors 600amps. Set 0 1961462 193966 0 0 0
33031
Supply, erection, testing & commissioning of 125 kVAR Automatic Power
Factor Controller panel (capacitor bank) complete and connection with
the main panel as per site requirement.
No. 1 363114 35907 363114 35907 399021
SECTION - F: EARTHING ARRANGEMENT
33032
Earthing with 3 meter long, 50 mm dia, G.I. pipe class 'B' earth
electrode, adding of charcoal or coke and salt , providing masonry
enclosure and cover plate with lifting arrangement etc. including
connections with 4mm G.I.wire from earth electrode to switch
board/electrical equipment as required.
Job 56 1907 300 106792 16800 123592
33033
Earthing with 600mmx600mmx6mm thick G.I. earth plate, adding of
charcoal or coke and salt , providing masonry enclosure and cover plate
with lifting arrangement, watering pipe etc. as required.
Job 30 2118 332 63540 9960 73500
33034
Earthing with 600mmx600mmx3mm thick copper earth plate, adding of
charcoal or coke and salt , providing masonry enclosure and cover plate
with lifting arrangement, watering pipe etc. as required.
Job 16 3742 587 59872 9392 69264
EARTH CONNECTIONS
33035(i)Supply and laying 25 mm x 6 mm G. I. strip at not less than 0.50 meter
below ground or in recess as required.Meter 400 43 8 17200 3200 20400
33035(ii)Supply and laying 40 mm x 6 mm G. I. strip at not less than 0.50 meter
below ground or in recess as required.Meter 10 70 11 700 110 810
33035(iii)Supplying and fixing 40 mm x 5 mm copper strip on surface or in recess
or in 50 mm dia G.I. pipe as required. Meter 160 555 87 88800 13920 102720
GEW Page 19 of 25
BOQ of RANI-SRPJ Package-1
SECTION - G : CABLING
33036
Supply, laying . 1.1 KV grade LT XLPE insulated armoured, aluminum
conductor cable , making good the damages, end terminations with
aluminium crimping sockets/lugs, provision of cable route markers,
testing and commissioning etc. as required as per Technical
specifications: i) 2 Core 16 Sq.mm Meter 250 185 42 46250 10500 56750
ii) 2 core 25sq.mm meter 500 213 50 106500 25000 131500
iii) 2 Core 70 Sq.mm Meter 0 364 58 0 0 0
iv) 2 Core 185 Sq.mm Meter 100 752 74 75200 7400 82600
v) 4 Core 16 Sq.mm Meter 8500 238 53 2023000 450500 2473500
vi) 3.5 Core 35 Sq.mm Meter 1517 337 54 511229 81918 593147
vii) 3.5 Core 70Sq.mm Meter 500 537 85 268500 42500 311000
viii) 3.5 Core 120Sq.mm Meter 250 848 84 212000 21000 233000
ix) 3.5 Core 185Sq.mm Meter 250 1187 118 296750 29500 326250
x) 3.5 Core 300Sq.mm Meter 50 1923 90 96150 4500 100650
xi) single core 400 sq.mm Meter 0 618 98 0 0 0
xii) Extra for provision of cable route marker No. 500 224 11 112000 5500 117500
SECTION - H : ELECTRIFICATION BY HIGH MASTS
33037
Supply, erection, testing & commissioning of hot dipped galvanised , high
mast system complete with all accessories, foundation, carriage
arrangement suitable for 9 luminaries symmetrically arranged & control
gear boxes and lighting finial etc., twin dome aviation obstruction lights,
control panel, multi core flexible copper conductor cable, connection to
earthing system and fencing panel as per requirement.
i)16 Meter high mast system with 6 nos. 2x400 watts MH luminaries and
MH lamps Job 2 613453 60664 1226906 121328 1348234
ii)16 Meter high mast system with 9 nos. 2x400 watts MH luminaries and
MH lamps Job 0 654135 64685 0 0 0
SECTION - I : LAYING OF 11 KV / 33 KV CABLES
33038Supply and laying of following sizes XLPE (E) insulated, armoured,
aluminium conductor HT cable .
(i) 11 KV, 3 core 70 sq mm Meter 50 970 153 48500 7650 56150
(ii) 11 KV, 3 core 185 sq mm Meter 400 1655 164 662000 65600 727600
(iii) 33 KV, 3 core 300 sq mm Meter 125 3679 173 459875 21625 481500
(iv) 33 KV, 3 core 400 sq mm Meter 0 5189 173 0 0 0
33039 Deleted
GEW Page 20 of 25
BOQ of RANI-SRPJ Package-1
33040
Supply of outdoor type, heat shrinkable, end termination kit, suitable for
following cable sizes XLPE(E) insulated, armoured aluminium conductor
cable and making termination, connections with overhead conductor,
testing & commissioning etc. (i) 3 core 11 KV 70 to 185 sq mm No. 9 7469 1173 67221 10557 77778
(ii) 3 core 33 KV 240 to 400 sq mm No. 2 23425 2317 46850 4634 51484
33041 Deleted
33042
Supply and erection of pre-stressed, cement concrete (PSCC) double
pole structure 9-11 meters long suitable for 330 KG working load with top
section 200 mm X 105 mm and bottom section 410 mm X 140 mm
complete with 4 nos. channel cross arms & 2 nos. cross bracing angles,
clamps, bolts, nuts , galvanized stay set , anti climbing devices,
Danger plates on the erected pole galvanised stay rod, casting of
foundation for poles & stays etc. as required.
No. 4 45127 4462 180508 17848 198356
33043
Supply and erection of 11 KV Porcelain Disc insulator complete with
galvanised iron hardware etc. including terminating with 11KV / 33 KV
overhead conductor and dismantelling, handing over works as required.
No. 18 813 80 14634 1440 16074
33044 (i)
Supply and laying of 200 mm dia RCC hume pipe, ISI marked, NP-4
under the Railway track/road etc, digging of trench and back filling
with excavated earth after laying of pipe and making good the damages
as required.
Meter 300 301 30 90300 9000 99300
33044 (ii)
Supply and laying 200 mm dia RCC hume pipe, ISI marked , NP-4
under the Railway track with trench less method and making good the
damages as required
Meter 150 301 1210 45150 181500 226650
SECTION - J: PROVISION OF PUMPS
33045
Supply, installation, testing & commissioning of submersible pump set
suitable to operate on 3 phase, 415V, 50 Hz AC supply along with control
panel etc complete for supplying water at suitable discharge and head as
per site requirements:
(i) 7.5 HP pump set Job 2 52952 5236 105904 10472 116376 (ii) 5 HP pump set Job 0 48492 4796 0 0 0
33046
Co-ordination/liasoning and chasing with State Utility Company for
availing new electrical connection/augmentation of sanctioned load at
stations, level crossings etc. including applying for load, collection of
estimates for loads, modification of power line crossings, arranging
payment from RVNL, depositing payment to State Utility Company,
arranging release of load & other related works. Payment to be made to
SEB for new connection, load augmentation, modification of power line
crossings etc. shall be made by RVNL .
Each Location 5 0 5650 0 28250 28250
SECTION - K: MISC. WORKS
GEW Page 21 of 25
BOQ of RANI-SRPJ Package-1
33047
Design and preparation of working & completion drawings of all HT/LT
electrical installations of the project section where work is carried out
such as platform lighting, internal electrification of staff quarters, level
crossings, station building, offices, power line crossings, power supply
distribution arrangements of stations /sub stations, electrification of sub-
station buildings etc.& approval from the competent authority.
Job 1 0 116451 0 116451 116451
Conducting check survey of the complete project section to compile
details of all the existing LT, HT and EHT Power Line Electrical overhead
and underground power/telegraphic/other lines running along or accross
the track and recording measurements of horizontal distances of
structures from the existing & proposed tracks, vertical clearances of
conductors & guard wire from rail level, angle of crossings w.r.t. track,
height and type of towers/poles and preparation of lists as below:
i) List of Overhead/Underground Crossings infringing and requiring
modification. Proposed modification may also be indicated.
ii) List of Overhead/Underground Parallel Alignments infringing and
requiring modification. Proposed modification may also be indicated.
iii) List of Overhead/Underground Crossings/Parallel Alignments in
conformity with the rules/regulations and not requiring modification
.
SECTION - L : GLOW SIGN BOARDS
33049
Supply, installation, testing & commissioning of out door type, single
side, /Double side Glow sign boards/Pictorial signage boards with
suspension /side mounting/wall mounting type arrangements as
required,. (Payment for Double sided glow sign board shall be made @
150% of the rate of single sided glow sign boards)
Sq.Feet 750 236 36 177000 27000 204000
SECTION - M BATTERY CHARGING & PRE - COOLING ARRANGEMENT
33050
Supply, installation, testing & commissioning of Silicon rectifier battery
charging set conforming to relevant IS (latest), suitable for operation on
3 phase 4 wire, 415 volts AC supply system, 125 Volts to 150 Volts DC
output, 200 Amps. capacity as per Tech. Specification including
earthing, etc. as required.
No. 1 79175 12435 79175 12435 91610
33051
Fabrication, supply, installation, testing and commissioning of 110 volts
Battery charging point suitable for operation on 150 volts DC supply
system including erection on MS channel, foundation etc complete.
Job 1 2863 450 2863 450 3313
33052Fabrication, supply, installation, testing and commissioning of , pre-
cooling point as per details given in explanatory notes. Job 0 7747 1217 0 0 0
SECTION -N : DISMANTLING WORKS
9193533048 Job 0 919351 0 91935
GEW Page 22 of 25
BOQ of RANI-SRPJ Package-1
33053
Dismantling of wiring installations of buildings, sheds, quarters etc.
complete with luminaries, fans, distribution boards, L.T. Panels and
associated cables including accountal,stocking, transportation and
handing over of released materials to Electrical department as directed
by the Engineer and making temporary arrangements if required.
Each Station/ gate lodge/ 3 0 5358 0 16074 16074
33054(i)
Dismantling of erected pole/overhead conductor, GI wire, cross arm
brackets, insulators, stay, luminary etc including accountal , stocking,
handing over the released material to railway’s authorized official as
instructed by the Engineer and making temporary arrangements if
required.
No. 100 0 536 0 53600 53600
33054 (ii)
Dismantling of Sub-Station equipments such as transformers, DG Set,
HT & LT Panels, cables etc. at site including transporting, stocking and
handing over to Electrical department as instructed by the Engineer and
making temporary arrangements if required.
Job 1 0 10175 0 10175 10175
SECTION -O : (N.I.Works)
33055 (i)
Provision of temporary lighting arrangement with 1x40 watt F.L. tube light
fittings/CFL fittings /flood light/halogen fittings and pedestral/ceiling fans,
desert coolers in temporary tents, buildings, goomties, on tracks, in yard
area including wiring, cabling, earthing etc.as directed by the Engineer
and as per site requirement for pre/post/during non - interlocking period,
including providing stand by D.G set of suitable capacity and deployment
of staff for operation of DG set as per site requirement.
Note: Normal power supply may be used, up to sanctioned load, if
surplus available at site.
Per day 5 0 16073 0 80365 80365
33055 (ii)
Extra for operation and maintenance of temporary wiring installations,
replacement of consumables, supply of diesel oil, lub oil etc for operation
of DG set etc.
Per day 25 0 3189 0 79725 79725
33056
Supply, installation, testing and commissioning of A.C.Unit, complete with
LCD display cordless remote suitable for 1-phase 230 ± 10% voltage AC
supply including supply & installation of 5 KVA, wall mounted, I.C.
controlled electronic auto voltage corrector
(a) 2.0 Tonne window type AC (Not less than 3 star energy rating) No 5 31108 2143 155540 10715 166255
(b) 1.5 Tonne split type AC (5 star rating) No 5 30562 2143 152810 10715 163525
33057
Supply & erection of G.I Octogonal pole including digging of pit, making
foundation with cement, sand & concrete in ratio 1:2:6, muffing,
accomodating G.I. Pipe in foundation for cable loop-in-loop out of
suitable size as required
i) 5 meters long No 100 6898 1693 689800 169300 859100
ii) 7 meters long No 0 9562 2347 0 0 0
iii) Additional cost of single arm bracket suitable for street light fixture No 90 288 71 25920 6390 32310
iv) Additional cost of double arm bracket suitable for street light fixture No 10 341 84 3410 840 4250
GEW Page 23 of 25
BOQ of RANI-SRPJ Package-1
33058
Supply installation testing & commissioning of cubical type mast mouted,
dust & vermin proof, L.T control switch board conforming to IS:8623
(latest version), complete.
i)a) with TPN MCCB 32A, 35KA, fixed type (Ics=100%Icu) - 1 No
b) copper busbars 200A (for 5 KVA AT)No 14 8723 2141 122122 29974 152096
ii)a) with TPN MCCB 63A, 35KA, fixed type (Ics=100%Icu) - 1 No
b) copper busbars 200A (for 10 KVA AT)No 22 10217 2507 224774 55154 279928
iii)a) with TPN MCCB 150A, 35KA, fixed type (Ics=100%Icu) - 1 No
b) copper busbars 300A (for 25 KVA AT)No 2 12138 2979 24276 5958 30234
Total (A) 14638747 4005148 18643895
Section -P Non Schedule Items
NS-1
Supply, erection ,testing & commissioning of control and distribution
panel for colour light signalling supply in 25 KV AC traction system as per
RDSO technical specifications No. TI/SPC/PSI/CLS/0023 includind latest
amendment for 5 KVA AT
No 7 32133 5670 224931 39690 264621
NS-2
Supply, installation, testing & commissioning of fabricated Double door
distribution board confirming to IS ; 13031,IS:8623 With degree of
protection not less than IP 42 as per IS 13947/Pt.1/1993 with powder
coated finish for Non Emergency Load complete with MCB's ,Copper bus
bar of 100 Amps , Neutral link,inter
connections,ammeter,Voltmeter,Indication lights etc,and shall be suitable
for operation on three phase 4 wire 415 volts AC supply system
,comprising
No 1 4651 1163 4651 1163 5814
(i)MCB FP 63 Amps --- 1 No. incomming
(ii)MCB TPN 40 Amps -- 1 No. outgoing
(iii) MCB SP 16 Amps - 3 No. outgoing
(iv) MCB SP 10 Amps - 5 No. outgoing
NS-3
Supply,fixing,testing & commissioning of energy efficient light fittings
model MAR 114 FTL HF (l1612) of GE with Tube rod complete in all
respect with clear Polycorbonate cover with high frequency warm start
electronic ballast and wide input voltage range as per spec- Make-
Bajaj/Philips/ Cromption/GE
No 34 1523 381 51782 12954 64736
Total (NON Schedule Items) (B) 281364 53807 335171
G. Total ( SOR AND NON SCHEDULE ITEMS) (A+B) 14920111 4058955 18979066
Grand total carried forward to summary 18979066
GEW Page 24 of 25
BOQ of RANI-SRPJ Package-1
Misc Items
ITEM Description Unit QTY Supply (In
Rs)
Erection
(In Rs)
TOTAL
SUPPLY
(In Rs)
TOTAL
ERECTION
(In Rs)
GRAND
TOTAL
(In Rs)
M-1Drilling of 50mm dia holes in the existing RCC tresle
beam/pier/mass concrete beam to the depth between
450mm to 1000mm with pneumatic drillers, compressor
etc. and making the hole surface fit insertion of bolts with
all lead and lift. Manufacture and supply of galvanized MS
bolts of size 32/25 mm dia with threaded at both ends of
varying lengths including nuts, check nuts, washers etc.,
(All labour and materials by the contractor). Pressure
Grouting the drilled holes (50mm dia) by epoxy grouting at
a minimum pressure of 7Kg/sqcm of approved quality of
epoxy resin hardner and thinner Payment for bolts and
nuts will be paid under separate item.
Loc 100 19182 4796 1918200 479600 2397800
M-2
Shifting of mast along with foundation block by excavating
surrounding earth, un-supporting the OHE and pushing
the foundation manually using Hydraulic jack of required
capacity, alignment of mast back filling of earth, supporting
OHE and compaction (Maximum shift of 60 cm)
Nos 10 0 11270 0 112700 112700
M-3Supply, fixing, connecting and commissioning of Street
light energy efficient flourescent tube light fitting single
phase 50Hz, 230 Volt supply conforming to IS:10322 part -
5 section 3 or latest and as per IP - 65 protection with 2
feet 4 x 24 watt (T-5) day light tube rod and premium
control control gears one control gear for each tube rod
and aluminium body with clear acrylic cover UV treated
similar to CGL,OSRAM,BAJAJ, PHILLIPS
Nos 1 7263 6537 7263 6536.7 13800
M-4Clearing of Ballast/rails/sleepers stacked to enable to cast
foundations.
Each 50 0 960 0 48000 48000
M-5Manning of anti theft transformer in Night
Man
Month
36 0 12000 0 432000 432000
M-6Landscape filling of specified arears with 1:3 mixture of
farmyard manure to red earth, for a minimum depth of 0.3
m, including levelling, making to required shape, grading,
tamping, soddig, with Mexican carpet grass in 0.6x0.3 m
pieces, ensuring no visible joints and proper slope for
surface water drainage maintenance upto six months with
free replacement of any mortality including watering upto
22 ltrs per sq.m per day including materials, labour, tools,
plant, all lead and lift, water etc. complete as per
specifications and as directed by the Engineer.
Sq.Mtr 250 700 53 175000 13250 188250
M-7Excavation of earth to the depth of 2 mtrs below ground
level for buring 13 meter long rail and connecting it as per
RDSO drawing(Rail will supplied by RVNL)
Each 1.00 0 2148 0 2148 2148
Total 2100463 1094235 3194698
Grand total carried forward to summary 3194698
BOQ for Railway Electrification works between RANI (Excl.) - SRPJ (Excl) Section 198 TKM of Ajmer Division of North Western Railway
Page 25 of 25
Explanatory Notes
( Signal & Telecom
Engineering)
S.No ITEM NO EXPLAINATORY NOTES INSPECTION
AGENCY
Group - C
1 38651 Supply of Railway underground jelly filled , 0.9 mm dia, 6 Quad cable as
per spec. No. TC/30/2005 Amndt-2 or latest.
RDSO
2 38653 Supply of PIJF-Polythene insulated polythene sheathed jelly filled
telephone cable with poly-AL moisture barrier with armoured of size: 10
PAIR X 0.63 MM. as per specification IRS:TC-41/97 amendment no. 1 or
latest
RDSO
3 38654 Supply of PIJF-Polythene insulated polythene sheathed jelly filled
telephone cable with poly-AL moisture barrier with armoured of size: 20
PAIR X 0.63 MM. as per specification IRS:TC-41/97 amendment no. 1 or
latest
RDSO
4 38657 Supply of 24 Fibre armoured Optical fiber cable as per SPEC No.IRS.TC-
55/2006 ver.-1 with ammendments.
RDSO
5 38701 Supply of RCC pipes 150mm dia, 2 Mtr long along with collars as per
Specn. No. IS/458/1971 for use near OHE Substation for cable
protection.
RITES
6 38702 Supply of DWC pipe with one snap fit coupler and 'O' ring conforming to
IS 14930 (part 2 : 2001), Non metallic, corrugated, multiwalled, normal
duty, pliable, without protection against chemical attack and Non flame
propagating in 6 meter length of size 120 mm outer dia & 102 mm inner
dia.( Permitted tolerance in dia = +/- 2 mm).
RITES
7 38703 Supply of SPLIT DWC pipe conforming to IS 14930 (part 2 : 2001), Non
metallic, corrugated, multiwalled, normal duty, pliable, without protection
against chemical attack and Non flame propagating in 2 meter length of
size 200 mm outer dia & 175 mm inner dia.( Permitted tolerance in dia =
+/-2 mm) ( TWO half round pipe constitute one split pipe)
RITES
8 38704 Supply of Galvanized Iron pipe 100 mm dia medium grade with screw
end both side and fitted with sockets as per specn. No.IS-1239, part 1 /
1990 in length of approx 6 meters
RITES
9 38705 Supply and jointing of Quad cables with theromoshrinkable jointing kits.
This includes:
RDSO
a Supply of theromoshrinkable jointing kits as per RDSO Spec.
No. IRS. TC77-2000/Amdt.1 ( or latest) suitable for 6 quad cable
RDSO
b Supply of 2T type small VF transformer (470:1120) for quad derivation
joints suitable for 6 quad cable - required only for derivation joints.
ENGINEER
MODIFICATION OF S&T ARRANGEMENT IN CONNECTION WITH RE WORK OF RANI - SWARUP GANJ
(PKG-I) OF NWR
S.No ITEM NO EXPLAINATORY NOTES INSPECTION
AGENCY
Group - C
MODIFICATION OF S&T ARRANGEMENT IN CONNECTION WITH RE WORK OF RANI - SWARUP GANJ
(PKG-I) OF NWR
c Making of Joint on Quad cable as Straight through joint with out
transformer or derivation joint with 2T Transformer as directed by
engineer at site.The derivation joint includes tapping of nominated quad
of 6 quad cable at specific location to 10 pair PIJF cable already laid in
the ground. This also includes supply of all other materials required for
the work. After jointing the cable thorough test such as insulation test,
continuity test etc., to be carried out jointly with Engineer and in case of
defective joints, same will be rejected along with jointing material.
ENGINEER
10 38902 Supply of Electronic magneto telephone desk type as per specn.No.IRS
:TC79/2000.with latest amendment
ENGINEER
11 40004 Supply of 4 wire way station equipment as per Spec. no. TC. 38/97 or
latest.
RDSO
12 40005 Supply of Power Supply for telecom installation at way side equipment as
per TEC Spcn. IRS.TC-72/97 Amdt.1 or latest.
ENGINEER
13 40006 Supply of portable Emergency telephone 4 wire as per spec. no. IRS
TC:75-99 with latest amendment
RDSO
14 40008 Supply of Emergency Socket Box with socket six pin flat to RDSO Spec
No. IRS: TC. 42/87. Amdt. 1 or latest.
ENGINEER
15 40009 Supply of VF Tapping Transformer to RDSO Spec. No. IRS.TC-22-76 of
type 470:1120, 600:470, 600:1120. exact break up to be decided in
consultation with engineer.
RDSO
16 40102 Supply of FCPC To SCPC 10 meter long patch cords with 0db adaptors
as TEC spec G/OJC-01/03 JAN99 Or latest.
ENGINEER
17 40103 Supply of managed Expendable rack type STM-1 ADM L 1.1 as per
Technical Spec. No. TEC GR No. GR/SDH-04/02 Mar 02 with
amendment 1 , 2 ,3 & 4 or latest with STM-1 aggregate interface , 21
E1S and 4 Numbers of 10/100 Base T Ethernet Port order wire, power
supply unit, sub rack installation material and accessories manual
etc.The equipment should be fully wired for its ultimate capacity and
provide redundency for power supply and synchronisation and other
detail as given in chapter 3 (model - TJ 100 MC1).
RDSO
18 40104 Supply of SMPS based battery chargers for telecom use 48v, 25 amps in
N+1 configuration using 2 modules of 25 A (FR/BC) with automatic
switching between the modules N=2. RDSO/SPN/TC/ 102-2013 Ver0.0
with Amendments.
RDSO
19 40105 Supply of 200 AH capacity LM batteries 24 Nos. at each station with
required no. of porcelene insulator. The suitable wooden rack for keeping
batteries shall also be supplied and it should be painted with 2 coats acid
resistnt paint. (IRS: S 88/2004 Version 1.0 or latest)
RDSO
20 40356 Supply of Speaker cable 2 Core Shielded & screened of size 47/0,193 as
per IS-694Cable for modification of existing PA System
ENGINEER
S.No ITEM NO EXPLAINATORY NOTES INSPECTION
AGENCY
Group - C
MODIFICATION OF S&T ARRANGEMENT IN CONNECTION WITH RE WORK OF RANI - SWARUP GANJ
(PKG-I) OF NWR
NS Items:
21 NS 3Supply of DTMF based headquarter equipment (2/4 wire) with all accessories
for control office as per RDSO spec no. IRS TC:60/2007 or latest including
12V power supply unit to suit RDSO spec. no. IRS TC 72/97 with latest
amendments and to be procured from RDSO approved firms only.
RDSO
22 NS 7 Supply of Earth tester - Digital Motwane make ENGINEER
23 NS 8 Supply & fixing of PVC Conduit pipe 25 mm dia and thickness 1.5 mm
with suitable clamps at interval of 1 mtr.
ENGINEER
24 NS 9 Supply of Network Monitoring System (NMS) including associated
application software for 2 mb drop insert mux and its associated item
as per technical spec. and office stipulation detailed with all accessories
incl. Power supply as well as one soft copy of software. (Refer. Telecom
special conditons : Chapter-3).
ENGINEER
25 NS 10 Supply of Network Monitoring System (NMS) including associated
application software for STM-1 and its associated item as per
technical spec. and office stipulation detailed with all accessories incl.
Power supply as well as one soft copy of software. (Refer. Telecom
special conditons : Chapter-3).
ENGINEER
26 NS 11 Supply of local craft terminal with minimum intel core i5 - 4210U
Processor, windows 8.1 OS, 4GB RAM/1TB HDD, Sparkling Black / 15.6,
2GB Graphic Card as per technical spec. and other stipulations complete
with all accessories compataible with NMS (Refer. Telecom special
conditons : Chapter-3).
ENGINEER
27 NS 12 Supply of remote service terminal as per tech. Spec.and other
stipulations with all accessories compataible with NMS. It should be
possible to plug in remote service terminal at any of the station. It should
be capable to programme any network element from any location of
network and read the full status of any element in the network from
remote service terminal, as well as one soft copy of the software .(Refer.
Telecom special conditons : Chapter-3)
ENGINEER
28 NS 13 Supply & Provision of Surge protection device for AC Power line
incoming, complete for Single phase power protection as per RDSO
specification RDSO/SPN/244/2004 or latest shall be procured from
RDSO approved/recommended sources only.
ENGINEER
29 NS 14 Supply of 2T Transformer small transformer (470:1120) for quad
derivation joints suitable for 6 quad cable as per RDSO Spen No.
IRS:TC:76/2000 with latest amendments.
ENGINEER
S.No ITEM
NO
EXPLAINATORY NOTES INSPECTION
AGENCY
Group - D
1 39652Trenching up to depth of 1000mm with 300mm wide base in all
types of soil and backfilling after laying of HDPE pipe / OFC cable
and 6 quad/PIJF cable etc. at 1000mm & 800 mm depth
respectively. Ramming and consolidation of soil in trenches as well
as disposal of the soil if any. This includes supply & provision of all
protective works as per specifications, drawings and stipulations of
tender documents and as per cable route plan such as GI pipe with
socket, RCC pipe/RCC split pipe, M.S. cable route markers and
bricks etc. This also includes cutting of armour of cable as per para
17 of Section III, chapter III of Tender document.
ENGINEER
2 39653 Providing chase in hard rock deep enough to fix GI pipe for laying of
S&T cable and minimum 100 mm concreting over GI pipe after
providing suitable U clamp to GI pipe. Chase to be provided where
optimum depth(minimum 0.6 mtrs) is not possible and which is
verified and agreed by engineer in charge of the work or his
representative NOTE: Where digging of depth as specified is not
possible, the depth can be reduced with the approval of the
engineer in charge and the payment shall be made proportionately
ENGINEER
3 39654 Perforation ( 24 to 36 perforation in a pipe) and Fixing of GI pipes
for entry of cable on girder bridges, RCC bridges, drains, culverts,
rocky places tunnels/deep cutting or at places as advised by the
engineer in charge of the work & concreting the ends with brick
channeling at both ends as per drg. The pipes are to be fixed on the
bridges by suitable bridge fixtures or MS clamps or brick support at
an interval of 3.0 mts (max) or as per approved drawing and
directives of Railway Engineers. On masonry bridges or in rocky
place if required the entire length of the pipe by cement, sand and
15-25 mm chips. All the fixing materials nut & bolts, clamps,
materials for construction of pillars. MS channel etc. will be supplied
by the contractor.
ENGINEER
4 39655 Fixing/Laying of RCC pipe(at TSS/SP/SSP), DWC pipes with
collars for laying of cables in open trench or underneath the track,
road, platform etc. as directed by Engineer and drg. Issued.
ENGINEER
MODIFICATION OF S&T ARRANGEMENT IN CONNECTION WITH RE WORK OF RANI - SWARUP
GANJ (PKG-I) OF NWR
S.No ITEM
NO
EXPLAINATORY NOTES INSPECTION
AGENCY
Group - D
5 39656 Laying of various sizes and types of cables in trenches: Laying of
signaling / power / telecom / quad/OFC cable of various sizes in the
excavated trench and through laid pipes. This includes
loading/unloading & transportation of cables to site. Whenever
several cables are to be laid separation of cables should be as
advised by site engineer. This includes unwinding of cable drum
using proper jigs without causing damage to cable.
ENGINEER
6 39657 Placing of half round ( Split DWC ) pipe over the laid cable in open
trenches in yards between Home signal to Home signal and tieing
pipe with cable with loose armouring as per Drg.
ENGINEER
7 39658 Supply of 20 pair CT Box and fixing on Hylam board on wall and
termination of quad/ telecom cable at station/ SP/ SSP/ TSS/ LC
gate/ Relay room/ office/ residences as per requirement and details
given by engineer at site. The CT box after termination shall be
sealed by pouring paraffin wax.
ENGINEER
8 39901 Supply and Installation of Maintenance free Earthing and Bonding
System as per RDSO specification. This includes:
ENGINEER
a Supply of MAINTENANCE FREE EARTHING AND BONDING
SYSTEM (Two Earth Pit) as per RDSO specification no:
RDSO/SPN/197/2008 consisting of (a) Earth electrodes made of
high tensile low carbon steel circular rods, molecular bonded with
copper on outer surface as per RDSO spn - 2 no. (b) RDSO
approved Earth Enhancing compound (c) (MEEB) Main
equipotential earth busbar of Copper of 300x25x6 mm (Min) and
(SEEB) Sub equipotential earth busbar of copper 150x25x6 mm
(Min) (d) Multistrand single core PVC insulated copper cable as per
IS:694 -(i) of size 10 sqmm to connect individual equipment to
SEEB using copper lugs with stainless steel nuts and bolts, (ii) of
size 16 sqmm to connect SEEB to MEEB using copper lugs with
stainless steel nut and bolts (iii) of size 16sqmm to connect Surge
protection devices (SPD) to MEEB using copper lugs with stainless
steel nut and bolts (iv) of size 35 sqmm (duplicated) to connect
MEEB to main earth electrode (e) Copper tape of size 25x2mm to
connect the two earth pits, (f) Earthpits x 150 mm to terminate on
earth electrode.
RDSO
b Construction of earthpit and making of earth as per RDSO
specification no. RDSO/SPN/197/2008 and drawing no:
SDO/RDSO/E&B/001, Equipotential Earth bus bar and its
connection to equipments and surge protection devices in the
equipment room as RDSO Drg. no. SDO/RDSO/E&B/002.
Provision of Exothermic weld connections, fixtures for mounting the
Copper tape in the relay room, weld materials, tools & fixtures for
the weld shall be arranged by the contractor.
Engineer
S.No ITEM
NO
EXPLAINATORY NOTES INSPECTION
AGENCY
Group - D
9 40502 Installation and commissioning of 4 wire way station equipments,
power supply unit at SP/SSP/Station/ TSS/AEN/PWI/SI offices/
Residences. The installation of way station equipment and power
supply unit (supply covered under a separate item) shall be
mounted on a MS angle rack. All the materials for installation,
commissioning of 4 W equipment and power supply unit shall be
provided by contractor.
ENGINEER
10 40503 Installation of emergency socket box including socket on the Rail
Post in the section and yard at every one Km distance as
pertapping chart supplied by the survey team. this will include wiring
and termination of quad cable on the socket box mounted at 1 mtr
hight, clamped with 2 nos. U-Clamps, provision of concreate
foundation of rail post in such a way that the rail post is one meter
above the earth level. The concrete shall be in ratio of 1:3:6 of
cement, sand & stone chips. The contractor shall jointly test with
RVNL Engineer for its satisfactory operation. This includes painting
of emergency socket post with alternate yellow and black strip of 6"
width and paiting of the socket box with gray colour paint and
painting of arrows on the telephone posts/cable markers to show
the nearest Emergency socket as instructed by engineer at site.
Rail Posts and MS pipes of required lengths for fixing Emergency
sockets will also be supplied and installed by the Contractor.
ENGINEER
11 40601 Supply and installation of OFC cable joint enclosure as per TEC No.
G/OJC-01/03 Jan 99 or latest and splicing o optical fibre cables (24
Fibre) and testing.
ENGINEER
12 40603 Supply of 2 MB programmable primary digital drop insert
multiplexer with conference facility as per specifications
IRS:TC/68/2004 with latest amendments & other stipulations of
tender document fully wired for 30 channels complete with power
supply unit, remote control supervision facility & all other
accessories installation materials, manuals etc. It should have
facility to accomodate data interface cards in multi drop mode &
should be able to support card needed for video conference. NOTE
: 1) in case the cards contain less than 8 circuits or 6 circuits as
mentioned above suitable number of cards to equal the total
requirements of circuits must be supplied. 2) If the card contains
more than 2/6/8 ports per card as mentioned in the schedule, the
tenderer shall still supply the number of cards asked for. The
number shall not be scaled down as per the number of ports.
RDSO
13 40604 (i) 4 wire, E&M, VF interface cards (8 circuits per card). RDSO
14 40604 (ii) subscriper loop interface cards (6 circuits per card). RDSO
15 40604 (iii) ISDN Interface (Two BRI Ports per card) RDSO
S.No ITEM
NO
EXPLAINATORY NOTES INSPECTION
AGENCY
Group - D
16 40604 (iv) Exchange loop interface cards (6 circuits per card). RDSO
17 40604 (v) G 703, 64 kbps data interface cards with a minimum of 8 ports
per card.
RDSO
18 40605 Supply, installation testing & commisning including earthing of 42 u
19" covered racks for housing SDH and P- MUX equipments, DDF,
FMS, MDF, using krone module etc. Complete with all fittings, wired
and equipped with integrated protection modules for all channels
and adequate numbers of cooling fans ,AC/DC power supply
distribution panels, U-Link panels and other hardware like runway,
ladders etc. It should be possible to lock all the equipments with
only order wire telephone remaining outside the rack. The rack
should be of APW President/Rittal make. The components of the
rack are specified below. Broad description of rack is detailed
below. Rack size 2200(mm) H x 600(mm) W x 600( mm) D. Fixed
side panels 42 U x 600 (mm) D front glass door plain 42 U x 600
(mm) D rear MS door plain 42 U x 600 (mm) D leveling screws - 4
numbers .Fan directly mounted on top 48 V DC 90 CFM - 2 Nos.
earth connectivity kit - 1 No. Cable manager with cable loops-2nos.
ENGINEER
19 40106 Blowing of armoured Optical Fiber Cable into duct by using blowing
machine and associated works .Before blowing the duct integrity
shall be tested .If any defect shall be found during duct integrity test
, the entire length of HDPE duct from one chamber to another
chamber chamber is to be replaced by Contractor at free of cost.
ENGINEER
20 40806 Supply and placing of second class bricks of size 225x100x75 mm
(9 bricks per mtr) horizentally breath wise in the trench after
covering the laid cable with soft soil of 50 mm thickness.
ENGINEER
NS Items:
21 NS-18 Excavation of cable trench 1.2m deep x 300mm width as per
Technical Specifications 51.2, at track & roads crossing, laying of
DWC pipes, as per Drg. No. RVNL/S&T/SG 024/2005, refilling of
trench, ramming. HDPE pipe shall be laid at the bottom of the
trench and after refilling with seived earth by 150- 200 mm, 6 quad
cable shall be laid and restoring the earth to original condition.
ENGINEER
S.No ITEM
NO
EXPLAINATORY NOTES INSPECTION
AGENCY
Group - D
22 NS-19 Horizontal directional drilling for laying of HDPE 125/200mm dia
pipe 1.4 Meter to 2.1 meter below the formation of Earth level below
ballast, As per drawing and instruction of Engineer at site. Terms &
Conditions A) The rate shall include Horizontal direction drilling at
any intermediate obstruction, either natural or manmade any
boundary strata. B) The rate is inclusive of all material equipments
and labour required during trench less horizontal directional drilling
under. C) The pipes are to be laid under Railway
track/Platform/Pucca Circulating area etc. Necessary arrangement
to be provided and all precautions are to be taken so that bore
coming out at either end is not deviated from the Horizontal level by
more than 250mm in horizontal. D) The rate is inclusive of detection
and protection of underground utility encountered during boring. E)
The payment shall be made for boring only when HDPE pipe is
provided in the above
ENGINEER
23 NS-20 Testing & commissioning of complete OFC system. ENGINEER
24 NS-25 Initial charging of Secondary cells:- ENGINEER
25 NS-28 2 Volts, 200 AH ENGINEER
26 NS-29 Supply of 20 Pair Krone terminal complete with mounting
arrangements.
ENGINEER
27 NS-30 Supply of Krone insertion/ extrusion tool Krone make ENGINEER
28 NS-31 Supply & installation of wire insulator for wire operating, Level
Crossing Lifting barriers/Signals as per Specification No. IRS S-47-
74
ENGINEER
29 NS-32 supply and installation of Insulator of Point rodding at function end
and lever end as per Technical specification.
ENGINEER
30 NS-33 Provision of GPS Clock in Stations RDSO
Explanatory Notes
(Electrical Engineering)
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 1 of 48
EXPLANATORY NOTES OVER HEAD EQUIPMENTS
SOR ITEM OHE-1
PREPARATION AND SUBMISSION OF DESIGNS AND DRAWINGS FOR
OVERHEAD EQUIPMENT SWITCHING STATION, SECTIONING DIAGRAM,
POWER SUPPLY DIAGRAM, SCHEMATIC DIAGRAM OF SWS, TRACTION
WORKING RULE DIAGRAM AND INSTRUCTIONS etc REQUIRED FOR
COMMISSIONING OF OHE
The price shall cover preparation and submission of overhead equipment plans indicating
location of structures in stages, and preparation of all drawings and designs relevant to the
tendered works and required to be finalized by the Contractor. The price shall include the
following:
(i) Preparation and submission of pegging plans layout plans incorporating span, height,
chainage, curves, gradients, type of masts/portals, foundations, ATD locations, stagger,
location of cut-in-insulators, signal locations etc, making minor modifications with the
approval of the Employer/Engineer to the layout of the structures and overhead
equipment, if necessary.
(ii) Preparation and submission of cross section drawings and structure erection drawings
for each structure location.
(iii) Choice of type and size of foundations to suit soil and loading conditions
(iv) Preparation and submission of long section drawings of overhead equipment
where such drawings are required including detailed study of over line structures such
as foot over bridges, road over bridges etc. for maintaining the specified height of
contact wire and requisite clearances.
(v) Preparation and submission of other designs and drawings including drawings of small
parts steel work (other than those for which RDSO standard drawings
are available) and detailed designs for LT. Supply Transformer stations, design of
OHE structures for bridges etc.
(vi) Supply of requisite number of copies of Bonding Plan drawings.
(vii) Design, preparation and submission of switching station drawings including
survey, investigation of soil bearing pressure from NABL accredited agency,
preparation of cross section drawings, preparation of general arrangement drawings,
detailed layout of equipment, bus-bar connections and insulators, layout of earthing
system and earth connections, cable run layout, detailed designs and drawings for steel
work and structural support, excluding the ones for which supply is made by the
Employer/Engineer, suitable concrete plinths for equipment and drawings for
equipments, components, fitting and materials supplied by the Contractor. The price
shall include supply of requisite number of copies of all drawings, including
completion drawings.
(viii) Preparation, supply and fixing of Sectioning / Schematic / TSWR diagram boards for
stations / Cabins / SWS / RCC and 25 Kv AC Traction Station Working Rule
instructions including supply & fixing of shock treatment chart etc.
(ix) Supply of requisite no. of soft (in Auto Cad) and hard copies of all drawings, including
completion/approved/as erected drawings for OHE and Switching stations.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 2 of 48
SOR ITEM OHE-2
SUPPLY AND ERECTION OF A LARGE SPAN WIRE (130 Sq.mm)
INCLUDING ITS FITTINGS WITH INSULATORS:
The price shall cover supply of all components including large span wire, , adjusters,
terminal fittings and mast attachments required to attach a large span wire or a Head
span wire or Cross span wire or Steady span wire or a Support span wire for
supporting contact wire only, at both ends, to traction masts/structures or special
brackets, solid core insulators The price shall cover erection of all components
including mounting arrangements, span wire, 9 Ton solid core insulators and all small
part steel work if any.
SOR ITEM OHE-3
SUPPLY AND ERECTION OF MATERIALS FOR TERMINATION OF
SINGLE CONDUCTOR OF OVERHEAD EQUIPMENT OR A TERMINATING
WIRE WITH INSULATORS:
The price shall cover supply of all material necessary for the termination of single
conductor of overhead equipment or terminating wire on a traction mast or structure, all
SPS work as required including appropriate mast anchor fittings, clevis assembly,
NOTES FOR MEASUREMENTS: For the purpose of payment against this item,
the length of track shall be measured as under :-
1. General: By the difference in the chainages of the length under consideration, as
incorporated in the layout plans.
2. Turnouts: The track taking off shall be deemed as starting from the SRJ of the
Turnout.
3. Cross-over’s: The length of track shall be taken as the difference in the
chainages of the toes of switches of the two turnouts constituting the crossover.
4. Diamond crossing with or without slips: The two tracks crossing each other
shall be measured independently as per note 1 above as though there were no
crossing. No extra payment shall be provided for slip points.
5. Dead ends and tops of loops: The lengths for payment under this item shall be
up to the chainage of anchor mast of the terminating OHE.
6. Feeders and return feeders from grid sub-station to feeding station: This item
will also be applicable independently in case of feeders / return feeders / conductors
from grid substation to overhead equipment feeding stations or in a case of feeders
/ conductors running on independent structures (not supporting OHE) along or
across tracks.
In such a case the length of line to be considered for purpose shall be measured by
(a) the distance between the center of gantries of the grid sub-station and feeding
stations in case of feeder / return feeders / conductors line from grid sub-station, or
(b) by the distance between the center line of the two structures to which the feeders
/ return feeders / conductors are anchored in case of feeders running along the track
if such feeder / return feeders / conductors are running completely on independent
structures or (c) by the distance between the center of the two structures supporting
the OHE on either side of the first and last independent structure or (d) in case of
feeders / return feeders / conductors running along the track supporting OHE.
7. No extra payment shall be made for any revision/changes/Modification in
OHE/PSI drawings on account of changes in ESP/SIP/L-section etc.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 3 of 48
adjuster, anchor double straps, ending clamp for the catenary or contact wire or
terminating wire and fittings including 9-tonne insulators. The price shall cover erection
of all materials including 9-tonne insulator assembly and terminating wire, if any.
Note: In case of “V” type anchorage is adopted for terminating a single conductor such
an arrangement would be counted as two off under this item for the purpose of
payment.
SOR Item OHE-4
SUPPLY AND ERECTION OF MATERIALS FOR TERMINATION OF ALL
ALUMINUM 25 KV FEEDER (SPIDER) INCLUDING FEEDER WIRE WITH 9-
TONNE INSULATORS:
The price shall cover supply of all materials required for the termination of an all-
aluminum 25 KV feeder (SPIDER), all SPS work as required including appropriate
mast anchor fittings, adjuster, strain clamp and fittings including feeder wire and 9-
tonne insulators. The price shall cover erection of all materials including 9-tonne
insulators assembly.
SOR Item OHE-5
SUPPLY AND ERECTION OF MATERIAL FOR TERMINATION OF COPPER
CROSS FEEDER WITH GANTRIES INCLUDING CROSS FEEDER WIRE
WITH 9-TONNE INSULATORS:
The price shall cover the supply of all materials required for termination of copper cross
feeder wire (37/2.25mm HDBC) all SPS work as required including appropriate mast
anchor fitting (3231), 18mm single clevis (5040), 9-tonne adjuster (5020-2), feeder
ending clamp (1130), double clevis (3010) and other components as necessary
including feeder wire (37/2.25 mm HDBC) and 9- tonne insulator assembly. The price
shall also cover the erection of all these materials/components including 9 ton insulator
and termination of cross feeder at either ends. Fittings/Components required for
termination of one cross feeder at both ends constitute one set.
SOR Item OHE-6
SUPPLY AND ERECTION OF TERMINAL BOARDS IN CONTROL
CUBICLES:
The price shall cover supply and erection of a wall mounted terminal boards with six
numbers of two way terminal blocks for connecting the cables from the outdoor
equipment of a switching station as per RDSO Drawing.
SOR Item OHE-7
SUPPLY AND ERECTION OF AN IRON CLAD 240V AC AND 110V D.C.
BOARD WITH FUSE BOX IN CONTROL CUBICLES:
The price shall cover supply and erection of a 15A, 240V, A.C. iron clad 4 way
fuse box and a 15A, 110V DC iron clad two way fuse box on the wall inside the
remote control cubicles. The fuse boxes shall be complete with four fuses and two
fuse carriers‟ and bases respectively.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 4 of 48
SOR Item OHE-8
SUPPLY AND ERECTION OF LEAD ACID BATTERIES 40 AH WITH
BATTERY CHARGERS:
The price shall cover supply and erection of 110V, 40AH, lead acid batteries with
two no. of suitable battery chargers for 110V 40 AH lead acid battery complete
with stand of approved design, accessories, tool board with hydrometer,
thermometer, connecting lead and plug for connection to 230V AC supply to the
battery charger. The price for erection shall include installation and connecting up
of the battery, filling up of electrolyte, initial/final charging, mounting of the
charger in position and connecting it up to 230V AC distribution board including
the cost of connecting cables.
SOR item OHE-9(a) & (b)
SUPPLY, ERECTION, OIL FILTRATION, TESTING AND
COMMISSIONING OF 25 KV/240 VOLT, 5/25 KVA, LT SUPPLY
TRANSFORMER WITH 25 KV D.O. FUSE SWITCH ASSEMBLY,
ANTICLIMBING DEVICE, INSULATOR, COPPER JUMPER AND
EARTH ELECTRODES etc:
The price shall cover Supply of 25KV/240V, 5/25 KVA LT supply transformer
with suitably filled transformer oil, DO fuse assembly (including fuse carrier) and
all other mounting accessories, SPS as required at site, as per the RDSO‟s latest
specification and erection of the same complete with terminal connectors on a mast
or gantry. The price shall also be applicable for transformers mounted on steel
pedestals at switching stations also. The price shall cover supply and erection of an
enameled number plate of approved design. The price shall also cover oil filtration
and pre- commissioning tests as approved by the Employers or Engineer. The
contractor shall make his own arrangement for oil filtration equipments, as well as
power supply required for the same. All necessary tools, equipments, instruments
required for carrying out oil filtration/checks/tests/commissioning shall be arranged
by the contractor. The price shall also cover supply & erection of a DO fuse switch
assembly complete with all mounting accessories, post/pedestal insulator for DO
fuse switch assembly.
The price shall also cover on a lump sum basis the supply and erection of anti-
climbing device consisting of galvanized steel fixtures mounted on the masts below
the transformer.
The price shall also cover supply and erection of conductor/ jumper wires and the
supply of all components including parallel clamps, bi-metallic and Aluminium-
copper Al-Cu strips wherever required. The price shall also cover the erection of
complete jumper assembly including conductor/jumper wire to be provided
between the Over Head Equipment and L.T. Transformers, drop out switch
assembly.
The price shall also cover supply and erection of an earthing station with a single
pipe embedded into the ground by driving or otherwise complete with protective
concrete box and lugs suitable for directly connecting two mild steel flats of
minimum size 50 mm x6 mm and copper earthing strip 25X3 mm at LT side
earthing point to mast.
The price shall not include cost of and supply and provision of structure bond
connecting LT transformer with structure and then to rails which will be paid for
under item OHE-22.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 5 of 48
NOTE: 1.Contractor at his own cost shall do the replacement of the transformer oil
on account of testing and leakages during the warranty period.
SOR Item OHE-10
MODIFICATION TO EXISTING OVERHEAD EQUIPMENT:
The item price covers all inclusive cost of all the associated works of OHE
modification including transfer, dismantling/erection, slewing/re-
slewing/readjustment, extension of OHE by providing splices or otherwise etc of
all the components of OHE including brackets, insulators, feeder wire/return
conductor, terminations, ATDs, isolators, traction bonds cross over OHE etc in a
particular length of track except items which are excluded specifically under this
schedule.
The price shall cover transfer of overhead equipment to a bracket assembly on a
new mast or support and dismantling of the existing erected bracket assembly from
old mast or support, supply and provision of a multiple cantilever cross arm
wherever required and erection of bracket assemblies on the multiple cantilever
cross arm, and consequent adjustment to overhead equipment required such as re-
spacing of droppers, leveling etc.
The price shall not include supply and erection of an additional bracket assembly,
which will be paid for under item OHE-18.
Dismantling of masts/portals/TTC/DA are covered under item OHE-34.
The price shall also cover the re-adjustment of the head span polygon to enable the
additional equipments to be suspended from the head span. Payment for the
suspension of additional overhead equipment shall be made for under item OHE-2
as extra to this item.
The price shall also cover the cost of dismantling of overhead equipment including
terminations, auto tensioning devices, guy rod assemblies, anti-creep, suspension
assemblies, super masts, feeder, return conductor, section insulator, an isolator,
single or gang operated, including dismantling of connections to the overhead
equipment, a pedestal/ pin insulator including dismantling of jumper connections
and traction bonds if any, temporary slewing or lowering of erected OHE adjusted
and/or unadjusted to ground for special works and restoration and readjustment of
the equipment after completion of special works and associated small parts steel
work.
The price shall also cover the cost of splicing of terminated overhead equipment for
extension and consequent adjustment of the affected equipment. The extended
overhead equipment shall be deemed as starting from the centre line of the structure
preceding the old terminating structure and the extended overhead equipment shall
be paid for under item OHE 23 (a).
The price under this item shall cover various modifications required to be carried
out to the existing overhead equipment, under power block, on account of
electrification of the section provided such modifications are not on account of
non-compliance of specifications, approved drawings and instructions given by the
Employer for the execution of the work from time to time, during the progress of
the work.
All the prices are on a flat rate all inclusive basis and cover only the important and
most frequent type of modifications required to compensate the contractor for the
work involved. No extra payments shall be admissible for any other associated
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 6 of 48
work, minor modifications, which may be necessary in the course of work. All
work done shall be paid for at normal rates as per BOQ.
In all these cases, the dismantled equipment shall be handed over by the contractor
to the Employer‟s Engineer at the Employer‟s godown/depot as required by
Engineer. The cost of loading / unloading and transportation shall be paid under
item OHE-13.
Where prices under this item are applicable, the contractor shall finalise the
quantities of work jointly with the Engineer before taking the work in hand.
NOTES:
1. In case modification / dismantling is carried out at particular location i.e.
dismantling of an isolator, bracket assembly, pin/ post insulator, guy rod etc.,
for the purpose of payment, half of the span on both ends will be considered.
2. All claims under this item have to be supported by the following certificate to
be furnished by the contractor on the connected bill.
a) The modifications are not on account of non-compliance of specifications
approved and instructions given by the Engineers for execution of works.
b) The quantities of work involved for modification have been finalised jointly
with the Engineer-in-charge before taking the work in hand.
c) The dismantled materials shall be/has been handed over to
Engineer‟s/Railway‟s representative.
3. The price of SPS work complete with bolts & nuts wherever required, is not
included in the item and will be payable under Item CS-9.
SOR Item OHE-11
MANNING OF SWITCHING STATION INCLUDING TSS:
The prices shall cover the payment/wages to the staff to be deployed at each
switching station including TSS as directed by Employer‟s Engineer on flat rate
basis per month per location. Manning shall be done round the clock. The staff,
holding minimum ITI qualification, shall be deployed in each shift. They shall be
fully conversant with operation of various equipments installed in the switching
station. The staff shall be deployed after test and trial by Employer/Engineer and on
issue of competency certificate. The staff deployed shall act in accordance with
instructions / directions given by Traction Power Controller (TPC)/representative
of Employer. The staff shall not leave the working place (Switching station) in any
case without permission of Employer‟s representative. The price shall cover
conveyance charges to the staff for going and coming to the working place. The
period of manning shall be decided by the Employer during the execution of
contract and manning shall commence on receipt of intimation in writing from the
Employer one month in advance.
Note: Unit of the item shall be „per month each location‟.
SOR Item OHE-12(a)
ELECTRIFICATION OF SWITCHING STATION (SP/SSP) BUILDING AS
PER SPECIFICATION:
The price shall cover all cost of supply, erection, testing and commissioning of
wiring work as per approved wiring diagram. Wiring work shall be done in
accordance with IE rules, IS-732, RVNL tech specifications The various activities
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 7 of 48
involved in the work are as follows:-
i) Fixing of PVC conduits in recess on wall and drawing of wires for circuit
and point wiring.
ii) Provision of MS switch boxes of appropriate size concealed in wall
at appropriate height with modular PVC/fibre sheet for fixing of
switches, plugs etc.
iii) Provision of main board and distribution boards and connection thereof.
iv) Provision of light fittings, exhaust fan, outdoors luminaries complete with
tubes and lamps.
v) Provision of earthing station and connection between earthing station to
main board with the help of 8 SWG GI wires. Earthing work shall be
done in accordance with IS: 3043/1987.
vi) Materials such as light fittings, ceiling fan, exhaust fan, switches, sockets,
ceiling rose, socket outlets all shall be with ISI mark and shall be one of the
make mentioned in technical specification. Light fittings shall be 1X28W
T5 energy efficient or equivalent LED fitting as decided by engineer. All
switches, plug points and sockets shall be modular type. Ceiling fan and
exhaust fan shall have min 3 star energy rating.
vii) Provision of switches, sockets out lets, ceiling roses on respective switch
boards and points in appropriate numbers and connection thereof.
viii) Provision of 150 watts HPSV street light fitting/other energy efficient
luminaries with better luminosity as decided by engineer, complete in all
respect including lamp on the wall of the building.
ix) After completion of wiring work necessary testing of wiring and
earthing station shall be done and results submitted to the site-in-charge
duly signed by representatives of both the contractor and purchaser.
Note: - Scale of fitting shall be as per latest RDSO guidelines and RVNL
specifications. Drawing/fittings shall be got approved by the Engineer
before taking up the work.
SOR Item OHE-12(b)
SUPPLY & ERECTION OF EARTHING ARRANGEMENT AT
SWITCHING STATION
The price shall cover supply and erection of an earth bus, earthing stations with a
single pipe embedded into the ground by driving or otherwise complete with
protective concrete box & lugs suitable for directly connecting two mild steel flats
of minimum size 50mm x 6mm.
The price shall also cover supply of all materials including 50 mm x 6 mm mild
steel flats for providing earth bus. The price shall also cover erection of earth bus
either buried at a depth of 300 mm below ground level painted with 02 coats of red
oxide zinc chromate primer and 02 finishing coats of bitumen or fixed on wooden
gutties on walls. It shall include connecting the earth bus to earth electrodes and to
various floor-or-wall-mounted equipment‟s or structures to be earthed and also
connections to non-track-circuited rails, wherever required. It shall also cover the
cost of making recesses in concrete foundation blocks for floor or cubicles and
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 8 of 48
covering them up. The connection of earth strips to each other shall be made either
by riveting or by welding. The connection of earth strips to various equipment,
structures or fencing post shall be made with G.I. bolts and nuts and spring
washers/locknuts.
The price shall cover supply and erection of 8 SWG G.I. wire used for earthing for
all LT electrical equipments including remote control cubicles and fencing panels.
Price shall also cover measuring and painting of earth values of all the earth pits,
combined earth value etc as per standard.
SOR Item OHE-13
LOADING/UNLOADING TRANSPORTATION AND HANDING OVER OF
ALL TYPE OF MATERIALS ETC. OTHER THAN CONTRACTOR
MATERIAL
The price shall cover loading/unloading and transportation charges to (from)
site/depot and handing over of material (if required) for all type of steel structures,
portals, copper/ aluminum conductors, SPS, CBs, BMs, ATs, PTs, CTs, LAs and
other electrical equipments etc. into/from BFR/ trailer/ truck for other than
contractor‟s material for the completion of the present work as instructed by the
engineer.
SOR Item OHE-14
EXTRA ON ERECTION RATE OF WORK UNDER POWER BLOCK:
Deleted.
SOR item OHE-15, 15(a), (b), (c)
CONSTRUCTION OF SWITCHING STATION BUILDING, RCC WORK,
PLASTERING, BRICK MASONARY, RETAINING WALL, FILLING,
COMPACTING AND LEVELLING WORK PITCHING WORK etc. &
SUPPLY AND ERECTION OF NAME BOARD FOR SWITCHING
STATION.
The price shall cover the construction of Control room of SP/SSP building and will
include labour/erection and material cost for the entire work all inclusive including
following works:
i) RCC, PCC, masonry work, including earthwork, leveling, stone pitching
in high embankment (if required).
ii) RCC work in plinth, lintels, chhajja, Roof slab.
iii) Pre-cast RCC Slab, RCC jali.
iv) Cement concrete in flooring and cable trenchs.
v) Brick masonry in walls.
vi) Plastering works.
vii) Provision of Doors, Windows, Grills, Rolling shutters, Water pipe line ,
Ventilators and painting thereof.
viii) White washing and colour washing and painting of doors/windows.
ix) Acid proof or painting of floor and wall in battery room.
x) Supply and spreading of stone metal shall be payable under CS-14.
xi) Provision of RCC pipe etc.
xii) Any other item of work required to complete the work which has not
been mentioned/included above shall also be done by the contractor and
nothing extra shall be paid for the same.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 9 of 48
Construction of Switching station shall be done as per RDSO‟s drawing No:
ETI/C/0067(Mod- B) or latest and Technical specifications.
The price shall cover the provision of all shuttering, frame works, arrangement of
water, all tools and plants required for the work, consumable, materials etc.
The materials used for the work such as brick, sand, stone aggregates, steel for door
frame, grill / rolling shutters; RCC Pipe shall be of best quality in accordance with
Railway‟s specification.
The price shall cover the cost of concreting required for foundation with 40 mm
stone ballast rammed in layers of 15 mm thick in cement and sand ratio 1:4:8, RCC
work for construction of column, brick work, retaining wall drainage etc required
for building.
The price shall also cover the provision of opening on the wall of suitable size, for
installation of exhaust fan in the battery room.
The price shall also cover the cost of supply and erection of name board for
switching station.
The payment shall be on uniform basis. The price shall also include supply of
necessary clamps, nuts, and bolts etc., required for the erection of the boards. Name
boards shall be made in bi-lingual or Hindi/English and vernacular language. The
boards to be supplied shall be as per the standard size and standard specification of
RDSO/Railways.
However, keeping in view local soil type and its bearing pressure, firm may adopt
different design for foundation/plinth adhering to the min inside dimensions as per
RDSO drawing and taking prior approval of the engineer. No extra payment is
payable for such redesigned basic structure except as detailed under 15(a) to (c).
SOR Item OHE-16
SUPPLY AND ERECTION OF A GUY ROD ASSEMBLY:
The price shall cover supply and erection of a guy rod assembly of various lengths
for traction masts/Portals/TTC, feeder line towers or supports etc complete with
mast guy rod fittings, guy rod with adjustments and part/s to be grouted in the
anchor block. The price shall not include the cost of supply and erection of a dwarf
or stub mast with anchor plates drilled and welded in position, where required for
anchorage, and small parts steel work, complete with bolts and nuts etc., if any for
attaching the mast guy rod fittings to the mast/structure which shall be paid for
separately under the relevant item.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 10 of 48
COMPONENTS REQUIREMENT
Rly. Id No.
Description of components
Qty. for unit
1 2 3
3232 Mast guy rod fitting (welded) complete
with 4 short bolts, nuts, lock nuts and
washers for attachment to mast/S.P.S
including appropriate fittings
1 off
5001/5001-1
or
5001-3
Anchor bolts (complete with nuts, lock
nuts and split pins)
1 Set
5002 Guy rod stirrup 1 off
5004 or
5005 or 5006-
1 or
5070 or 5071
Guy rod with nut, washer and split pin
1 off
5007-1 Anchor 'v‟ bolt 1 off
5008 Anchor loop 1 off
5220 Guy rod double strap assembly 1 off or 2 off (as
required )
NOTE : 1. In case the Contractor desires to adopt a different design for guy rod assembly,
the same shall be indicated by him in the Tender and the components required
should be clearly listed under this item as deviation.
2. Supply and erection of guy rod assembly at anticreep portals will also be paid for
under this item.
SOR Item OHE-17
SUPPLY AND ERECTION OF PROTECTIVE SCREEN ON FOBS/ROBS:
The price shall cover the cost of supply and erection of protective screen on
ROBs/FOBs/ etc. The price shall cover the cost of all material required for
fabrication of protective screen including MS Angle, Tee, expanded metal (Jali), GI
sheet, paints, suitable fixtures for fixing on the ROB/FOB etc. The price shall also
include the labour cost for fabrication, erection on ROB/FOB and painting. The
fabrication and erection work shall be done as per RDSO Drg.. No. ETI/C/0068
(07/09) Rev-H.
SOR Item OHE-18
SUPPLY AND ERECTION OF BRACKET ASSEMBLY WITH
INSULATORS AS PER OHE PLAN: The price shall cover on a flat rate basis for supply and erection of any bracket
assembly on a traction mast or support or drop arm and shall include those on
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 11 of 48
high/low level platform, in the vicinity of turnouts, over bridges or over-laps and at
locations with reduced encumbrance or terminating wires. The price shall include
the cost of supply of all components including galvanized steel tube, dropper wires
and small parts steel work complete with bolts and nuts etc., if any. The price
shall cover erection of all components including solid core insulators and dropper
wires, small parts steel work, if any. However, this does not include the anticreep
arrangement at masts/ structures.
The price shall include the cost of following components:
Rly. Id No. Description of components Qty.
for unit
1 2 3
3020 Mast fitting for hook insulator with 2 off
bolts, nuts, lock nuts and washers of 16 mm
dia.
1 set
2400 Tubular stay arm assembly (including
galvanised steel tube).
1 set
2110/
2130/2380
Catenary suspension bracket assembly or
hook bracket
1 off
1160 Suspension clamp 1 off (as
required)
2120/2140/
2040/2080
Bracket tube assembly complete with tube
cap and sleeve where required (including
galvanised steel tube).
1 set
3070-1/2 Mast bracket fitting assembly including 2
off bolts, nuts, lock nuts and washers of 16
mm for attachment to structure or to small
part steel work.
1 set
2150-1 &
2160-1
Register arm hook assembly complete with
bolts, nuts and lock nuts.
1 off
2420 or
2430
Register arm assembly or raised register arm
assembly (including galvanised steel
tube).
1 set
2270-4 or 5,
2460 Style- 02
or
2470 Style 02
Register arm dropper assembly including
dropper wire complete with bolts, nuts etc.
1 set
2390/2540/
2520
BFB steady arm or bent steady arm ( As
required)
2360/2490-2 25 mm steady arm drop bracket/clamp -do-
1220/1370/-1 Contact wire swivel clip or raised register
arm
1 off
2550-1/2 Anti wind clamp As
required
7mm/5mm inclined copper/steel dropper
(on girder bridges use steel wire droppers)
As
required
Bracket insulator/Stay arm insulator one set
The price is also applicable for the provision of any additional fitting & required to
support an additional OHE on a single bracket assembly payable under this item.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 12 of 48
The price shall include supply of all extra fittings including the double contact wire
swivel clip.
SOR Item OHE-19
SUPPLY AND ERECTION OF REGULATING EQUIPMENT (3 PULLEY
TYPE) WITH COUNTER WEIGHT ASSEMBLY FOR CONVENTIONAL
OHE:
The price shall cover supply and erection of a 3-Pulley type counter weight
assembly including 9 ton adjuster with double strap assembly and normal/anti-theft
guide tube assembly, the supply of regulating equipment, provision of adequate
length pipe on Hex-Tie rod at crossovers and short tension length ATDs wherever
required and stainless steel wire rope required for the regulating equipment, anti
slipping device assembly (Spacer Angles as per RDSO DRAWING NO.
TI/DRG/OHE/ATD/RDSO/00009 and small part steel work, if any. The price shall
also cover adjustment of the entire regulating equipment. The price shall not
include supply and erection of termination, which will be paid under SOR item
OHE-20.
SOR ITEM OHE-20
SUPPLY AND ERECTION OF MATERIAL FOR TERMINATION OF
DOUBLE OVERHEAD EQUIPMENT CONDUCTOR WITH INSULATORS:
The price shall cover supply of all material necessary for the yoked termination of
two overhead equipment conductors on a traction mast or structure , including all
SPS such as appropriate mast anchor fittings, clevis assembly , two adjusters,
ending clamps for catenary and contact wires, anchor double strap assembly,
equalizing/compensating plates, and double eye distance rods (if required) and
fittings and terminating wire ,if any including 9- ton insulators assembly The price
shall also cover erection of all materials with 9 ton insulator.
SOR Item OHE-21
SUPPLY AND ERECTION OF ANTI CREEP WITH GALVANIZED STEEL
WIRE INCLUDING INSULATORS.
The price shall cover supply of all materials for an anti-creep including adjusters,
galvanized steel wire, mast anchor fittings at its terminations on either side of
structures, ending clamps, fittings and including 9- ton insulators assembly
conforming to RDSO specification.
The price shall cover erection of all materials including 9- ton insulator assembly
with small parts steel work, if any.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 13 of 48
Rly. Id No.
Description of components
Qty. for unit
1 2 3 3
- Galvanized steel wire (19/2.50 mm As required
1360 Steel wire ending clamp 2 off
5020-1/
5020-2
9 -ton adjuster 2 off
5030 Anchor double strap assembly As required
3010/5040 Clevis assembly 2 off
3231 Mast anchor fitting with bolts, nuts etc. 2 sets.
1170 Double suspension clamp 1 off
Less 1160 Suspension clamp (-) 1 off
5183 Double eye distance rod As required.
NOTE -1.In case the anti-creep extends beyond one span on either side of anti
creep center, payment for the supply and erection of extra length shall be paid
additionally at the rate of 20% of the rate per extra span.
SOR ITEM OHE-22
SUPPLY AND ERECTION OF A STRUCTURE BOND/ A LONGITUDINAL
BOND/ TRANSVERSE AND SPECIAL BOND:
The price shall cover supply of all materials including mild steel flats size 40 x 6
mm required to provide all kinds of bonds such as a structure bond connecting a
traction mast or structures to the nearest non-track-circuited rail, or earth electrode,
including all fastenings at both ends. The price shall include shaping and drilling of
the bond and erection of all materials including provision of heat shrinkable PVC
tube for structure bond under track circuit rail. This would also cover connection or
earthing terminals of equipments like LT Transformers with structure and then to
rails as per relevant drawings.
The price shall cover provision of connection of buried rails to running rail as per
RDSO drawing No. ETI/OHE/G/05306 & shall include supply, fabrication and
erection of all connections (including drilling at both ends) and refilling of buried
rail pit.
The price shall cover the supply of all materials including mild steel flats size 40 x
6 mm, fasteners etc. required to provide longitudinal bond / transverse bonds
connecting to rails at the rail joint at the locations to be specified by the Employer.
The price shall include shaping and drilling of the bond and erection of all
materials including the bonds.
The price shall also cover the supply of all materials including mild steel flats size
40 x 6 mm to provide special bonds at level crossings, foot over/road over
bridge/protective screen, girder bridge, metallic sheds, fencing etc. for which the
location will be specified by the Employer. The price shall include shaping and
drilling of the bond and erection of all materials including the bond.
The item covers the new bonds to be provided in the yard due to modifications
involved as per revised bonding plan of the station.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 14 of 48
SOR ITEM OHE 23 (a)
SUPPLY AND ERECTION OF OVER HEAD EQUIPMENT i.e. CONTACT
AND CATENARY WIRE (EXCLUDING COST OF CONTACT AND
CATENARY WIRES), JUMPER WIRE, DROPPER WIRE,
CONTACT/CATENARY CLIPS, FASTENERS AND ALL OTHER MATERIAL
REQUIRED AT TURN OUT/OVERLAPS/DIAMOND CROSSINGS etc FINAL
CHECKING OF OHE AND ADJUSTMENT, INSPECTION TO BE DONE BY
TOWER WAGON FOR COMMISSIONING OF CONVENTIONAL OHE.
The price shall cover supply & erection of complete overhead equipment with all
components and wire and conductors including contact wire, catenary wire droppers, all
types of jumpers including anti-theft jumpers (50/65/105 sq mm), and terminating
wires at turn outs/ overlaps/ diamond crossings/ cross overs etc, if any. [Excluding the
cost of contact & Catenary which will be paid under Item No. 23(b) & (c)].
The price shall also cover supply & erection of contact wire as false contact wire (if
demanded by zonal Railways in place of insulated catenary wire) under overline
structures with all associated components [Cost of contact wire shall be payable under
SOR OHE 23(b). Provision of insulated catenary shall be payable under OHE-30)]
Provision of long cross type G-jumper on parallel run side instead of cross-over/turn out
side as per RDSO drawing No ETI/OHE/G/02141 Rev „C‟ or latest shall be ensured.
The price shall also cover supply of all components including dropper clips, parallel
clamps for jumpering and splices (where their use is approved), dropper wire, jumper
wire and terminating wire/small parts steel works complete with bolts and nuts etc. for
attachment of number plates to mast/structure, if any.
The price shall include provision of enameled/retro reflective number plates,
enameled/retro reflective sigma boards on masts before stop signals, different types of
boards required to be provided as per ACTM (caution/warning, DJ ON/OFF, DJ
ON/OFF for MEMU, 500m, 250m neutral section boards, unwired section, engine stop
board, power block limit board etc on traction masts or structures. Sigma
marking/boards shall be provided before signals on OHE masts/structures as per Rly
Board letter no 2001/Elect(G)/170/1 pt dt.7.5.2012 as decided by engineer.
The price shall also include the cost of painting the setting distance of masts/structures,
rail level on masts/structures, stenciling of symbol for direction of emergency telephone
socket and Y marking at BWA locations as per temperature and local instructions. This
price also includes supply and erection of different type caution warning boards on
OHE Structure.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 15 of 48
All the warning boards provided on OHE structure shall be of retro reflective type as
per latest Rly. Board/RDSO guidelines. Similarly structure Number plates on OHE
mast at specific locations should be retro reflective types as per latest Rly. Board/RDSO
guidelines.
Separate DJ close Boards to be provided for MEMU/EMU wherever required for
MEMU/EMU operation.
The price shall cover supply of all components required for a pull-off arrangement to
pull one equipment only including head-span mast fittings complete with M.S. angle,
equalizing plate assembly, steady-arm, catenary wire dropper clip, contact wire swivel
clip and fittings including solid core insulators. The price shall cover erection of all
components including solid core insulators, small jumper wire, large jumper wire and
conductors.
The price shall cover supply and erection of all additional fittings required including the
supply of required conductors/jumper wires, in case the pull off pulls more than one
equipment.
The price shall cover final checking, adjustment and inspection of OHE by tower car.
Further details are given in Section 5 Chapter 2 of Volume-1 of bid document
Rly. Id No. Description of components
Qty. for
unit
1 2 3
1040-2 or SK-534/1 & SK-575/2 or SK-576/1 & SK-535/2 or 1041-3
Contact wire parallel clamp small As required
1180/SK-572/1 & SK-572/2
Contact wire dropper clip(107) -do-
1192 Catenary dropper clip complete with bolts, nuts etc.
-do-
7501 Enameled number plates complete with 2 Galva. MS. bolts m 10x35/30, nuts and lead washer for m 10 bolts but excluding SPS for attachment of number plate to masts/structures.
-do-
1110-2 Contact wire ending clamp -do-
1120 Catenary ending clamp -do-
1140 Large span wire clamp (130) -do-
5020-1/5020-2 Adjuster -do-
5030 Anchor double strap assembly -do-
5191/5192 Compensating plate/Equalizing plate. -do-
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 16 of 48
SOR ITEM OHE 23 (b)
SUPPLY OF HDGCC 107 SQ MM COPPER CONTACT WIRE The price shall cover the cost of supply of hard drawn grooved continuous cast copper
contact wire 107 sq mm for overhead equipment. The cost of erection of contact wire
shall be payable under Item No. 23(a). Reconciliation of material should be done as per
actual use taking into account anchor and overlap. The measurement will be from centre
line of anchoring mast. Unused contact wire pieces/drums shall be on the contractor
account.
SOR ITEM OHE-23 (c)
SUPPLY OF 65 SQ MM COPPER CATENARY WIRE
The price shall cover the cost of supply of stranded copper catenary wire for overhead
equipment. The cost of erection of catenary wire shall be payable under Item No. 23(a).
Reconciliation of material should be done as per actual use taking into account anchor
and overlap. The measurement will be from centre line of anchoring mast. Unused
catenary wire pieces/drums shall be on the contractor account.
SOR ITEM OHE-24
SUPPLY AND ERECTION OF ANTI CREEP WITH CADMIUM COPPER
CATENARY WIRE INCLUDING INSULATORS.
The price shall cover supply and erection of all materials for anti-creep including
cadmium copper catenary wire, adjusters, mast anchor at its terminations on either side
of structure, ending clamps & fittings, 9 ton insulators assembly and SPS work if any.
The price shall cover erection of all materials for anti-creep including 9 ton insulators
assembly and SPS work if any.
RDSO drawing No. TI/DRG/OHE/GENL/RDSO/00001/12/0 REV „0‟ or latest,
Ref.ETI/OHE/G/02111 Rev-A dt.23.10.2012 or latest is to be followed for use of
catenary wire in place of GI wire at ACC locations in polluted area as decided by zonal
Railways.
SOR ITEM OHE-25
SUPPLY AND ERECTION OF A SECTION INSULATOR ASSEMBLY WITH
INSULATORS AND ASSOCIATED FITTINGS & FASTENERS FOR OHE:
The price shall cover supply, erection and adjustment of all components required for a
standard section insulator assembly (serving both the overhead equipment conductors)
including 9 ton insulator, bar insulator special droppers etc. for supporting the
equipment and all terminal fittings for conductors and the section insulator assembly,
dropper wires as required,.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 17 of 48
Rly. Id No Description of components Qty. for unit 1 2 3
1120/or SK/436 or 1122
&
1123
Catenary ending clamp 2 off
1192/ETI/OHE/SK/333 Catenary dropper clip assembly As required
6170 Parallel clamp for double contact
wire
12 off
6180 Section insulator dropper
assembly
3 sets
6100 Section insulator assembly To be supplied bythe
contractor
6020 9 ton insulator assembly
6110 Bar insulator -do-
SOR ITEM OHE-26
SUPPLY AND ERECTION OF PTFE TYPE SHORT NEUTRAL SECTION
ASSEMBLY:
The price shall cover supply, erection and adjustment of PTFE type short neutral
sections assembly. The price shall also cover supply and erection of, all fittings for
contact and catenary wire as necessary including supply of required dropper wire.
SOR ITEM OHE-27
SUPPLY AND ERECTION OF 25 KV S.P ISOLATORS WITH INSULATOR
WITH/ WITHOUT EARTH CONTACT ASSEMBLY, WITH/WITHOUT
INTERLOCK:
The prices shall cover supply and erection of isolator switches of approved make 1250
Amp capacity, complete with arcing horns, operating rods, operating rod guides, and
mounting base including supply and erection of 25 KV Solid Core Post and Operating
rod insulator.
The price shall also cover supply and erection of a number plate of approved design,
supply and erection of small parts steel work complete with bolts and nuts etc. for
support of each isolator and for support of operating rods on gantries/ masts, jumper
connectors and post insulator to support jumper. The price shall also cover supply and
erection of pad lock, integral lock and interlock if required. The price excludes
provision of pipe electrode earthing.
Note: Payment of jumper shall be payable under SOR item OHE-29
SOR ITEM OHE-28
SUPPLY AND ERECTION OF 25 KV DOUBLE POLE ISOLATOR WITH
INSULATOR WITH/WITHOUT EARTH CONTACT ASSEMBLY WITH/
WITHOUT INTERLOCK:
The price shall cover supply and erection of a double pole isolator 1250 Amp capacity
complete with mounting base, operating rod, operating rod guides required for the
operation of the isolator, jumper connectors. The price shall also cover supply and
erection of alluminium-copper strips, a pad–lock, integral lock and interlock if required,
a number plate of approved design for each isolator, supply and erection of small parts
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 18 of 48
steel works for support of isolators and for support of operating rods on gantries masts
including supply and erection of 25 KV Solid Core Post and Operating rod insulator.
The price shall also cover for supply and erection of an earth contact assembly in the
isolator. The price shall cover the cost of supply and erection of 3 x 25 mm copper
connections between earth contact assembly and the structures.
The price shall cover supply and erection of an inter locking mechanism on an
isolator along with small parts steel if any, to permit working of two or more isolators.
The price excludes provision of pipe electrode earthing.
Note :
1. All Isolators are to be supplied with required numbers of 25 kV operating rod
insulators with complete accessories and small parts steel. Isolator key box of
appropriate size shall be provided for at each station on the section, one number at
the nearby OHE depot in charge of the section and one number at SSP/SP, as
desired by the Engineer at site.
2. Payment of jumper shall be payable under SOR item OHE-29
SOR ITEM OHE-29
SUPPLY AND ERECTION OF ALL TYPES OF COPPER JUMPERS :
The price shall cover the supply of large jumper wire size 105 sq. mm (19/7/1.02mm),
small copper jumper size 50 sq. mm (19/1.80mm), 65 sq. mm Cadmium copper
conductor, 5 mm dia. dropper wire made of annealed 100% pure copper conductor as
per RDSO‟s spec No. ETI/OHE/3 (2/94) with „A‟ & „C‟ Slip No.1 and on a flat rate
basis, the supply of all components and fittings required for providing a flexible, and
bolted type terminal connectors wherever required for connection, including supply of
parallel clamps, bi-metallic and aluminum-copper strips, wherever required, and bolted
type terminal connectors wherever required.
The prices shall also cover the erection of the complete jumper assembly including
jumper wire. The price shall not, however, be applicable for jumper connections already
included under a particular item (e.g. OHE-23, OHE-9(a) & (b), CS-3, CS-5 etc), but
shall be applicable for any jumper connection in any combination between feeders,
isolators and booster stations. Continuity jumper at boom anchor anti-creep will be
payable under this item.
SOR ITEM OHE-30
SUPPLY AND ERECTION OF INSULATED CATENARY CABLE IN THE
SPAN UNDER OVER-LINE STRUCTURE:
The price shall cover supply of insulated catenary wire, catenary wire splice (1090) for
each location and required dropper clip and erection of the same for each location. The
prices shall also cover erection and adjustment of special droppers wherever required.
The insulated catenary wire to be supplied shall be as per RDSO‟s specification No.
TI/SPC/OHE/INSCAT/0000 (04/00) or latest. The work shall be executed in
accordance with drawing No.ETI/OHE/ SK/570. The price shall also cover the cutting
of existing Catenary wire, supply and erection of all materials and components
including adjustment of dropper wires. Insulated catenary is to be provided under all
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 19 of 48
ROB/FOB as per RDSO maintenance instruction No. TI/MI/0036 (09/99) Rev „0 as
directed by RVNL/ Zonal Railway.
SOR ITEM OHE-31
SUPPLY OF MATERIALS AND ERECTION OF A LARGE COPPER JUMPER
(160 SQMM) BETWEEN ALUMINIUM BUS/OHE AND CROSS FEEDER
WITH ALL ASSOCIATED FITTINGS:
This jumper shall be provided between 36 mm aluminium bus/OHE and the copper
cross feeder at SSP, SP and FP.
The price shall cover the supply of 160 sq. mm flexible copper jumper wire made of
annealed stranded 100% pure copper conductor as per RDSO‟s spec No. ETI/OHE/3
(2/94) with A & C Slip No.1 or latest, all components and fittings required for
providing a flexible copper jumper 160 sq. mm and connection between 36 mm
aluminium bus/OHE & copper cross feeder including terminal connector 19 mm
multiple hole bolted type (1009), parallel clamp (1050-3) aluminium-copper bimetallic
strips fasteners etc.
The price shall also cover the erection of the complete jumper assembly including
jumper wire, connectors and fasteners etc.
SOR ITEM OHE-32
SUPPLY AND ERECTION OF SOLID COPPER BUSBAR 18 MM DIA:
The price shall cover supply and erection of solid copper bus bar 18 mm and its
terminal connector. The price shall include bending and shaping of bus bar.
SOR ITEM OHE-33
SUPPLY AND ERECTION OF ALL TYPES OF CONNECTORS REQUIRED
FOR ALUMINIUM/COPPER BUS BAR REQUIRED FOR COMMISSIONING
OF SWITCHING STATIONS WITH FASTENERS.
The price shall cover supply and erection of solid copper bus bar junction and
connectors of various type specified including bolts, nuts etc. required at junction or
termination of aluminum bus bars/solid copper bus bar etc.
SOR ITEM OHE-34
DISMANTLING OF TRACTION STRUCTURES, PORTALS, TTC AND
ASSOCIATED SPS BY CUTTING
The price shall cover on flat rate basis dismantling of OHE structures or portals by
cutting the same from the top of the foundation and handing over the same to the
Employer‟s Depot. The price shall also include dismantling of drop arms and booms of
the portal and their all associated fittings like SPS, bonds etc. Crane charges for the
purpose are included in the flat rate. The transportation of dismantled structures shall be
payable under item no OHE-13.
SOR ITEM OHE-35
SUPPLY AND ERECTION OF SAFETY ITEMS i. e. FIRE EXTINGUISHERS,
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 20 of 48
SET OF FIRE BUCKET WITH STAND AND FIRST AID BOX, KEY BOX
WITH SUITABLE KEY CHAIN, LOCKS AND OTHER MISC ITEMS
REQUIRED FOR COMMISSIONING OF SWITCHING STATION:
The price shall cover supply and erection of fire extinguishers, as per details given
below including mounting arrangements. Each set would consist of following and each
of 4-litre capacity.
i. CO-2 type - 01 Nos.
The fire extinguishers supplied shall be of approved brand and as per relevant
specification.
The price shall also cover supply and erection of standard first Aid box of made of GI
Sheet with pad lock as approved by the Employer. The list of items/medicines to be
supplied along with in the first aid box shall be obtained from employer/engineer.
The price shall cover supply and erection of six number of fire buckets with stand of
standard size, cover shed, and locking arrangement as per standard practice of
concerned Railway and as approved by the Employer.
The price shall also covers Supply and installation of key box in SSP/SP with suitable
key chains and locks, associated registers of appropriate size in printed profarma (if
required in newly electrified section and as per local Railway practice), 1 no wooden
stool of appropriate size,1 no steel arm cushion chair, gum boots- 1 pair, rubber gloves-
1 pair etc as directed by Employer/Engineer in charge.
The key box shall be of teak wood plank made of size 12inchesx18 inchesx5 inches.
SOR ITEM OHE-36
SUPPLY AND ERECTION OF 25 KV AC DANGER BOARD/DANGER BOARD
FOR HEIGHT GAUGE, PUBLIC/ STAFF CAUTION AND SPECIAL BOARDS
BOARD REQUIRED FOR COMMISSIONING OF OHE/SWSs.
The payment under this item shall cover supply and erection of 25 KV AC danger
board, danger board for height gauge, public/ staff caution boards and special boards
on uniform basis as decided by the engineer. Purchaser will advise the requirement of
the various types of boards and location to contractor. The above payment shall also
include supply of necessary clamps, nuts, and bolts etc., required for the erection of the
boards. Caution boards shall be made in bi-lingual or Hindi/English and vernacular
language, where ever required and same will be advised to contractor. The various
types of above boards to be supplied shall be as per the standard size and standard
specification of Railways/RDSO.
This item shall also cover special caution boards to be provided on all departmental
vehicles, track machines, platform shelters as per Railway board letter No.
2009/RE/161/4 FTS-748 dtd.26-08-14 as per directions of the engineer.
SOR ITEM OHE-37
SUPPLY, ERECTION AND COMMISSIONING OF LIGHT WEIGHT
SECTION INSULATOR ASSEMBLY 25 KV AS PER DRAWING NO.6.2758.0
RDSO SPEC.NO. TI/SPEC/OHE/LWDSI/007
The price shall cover supply, erection and commissioning of light weight section
insulator assembly of 25 KV including all accessories as per drawing no. 6.2758.0
RDSO spec. No. TI/Spec/OHE/LWDSI/007
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 21 of 48
SOR ITEM OHE-38
SUPPLY, INSTALLATION AND COMMISSIONING OF THE MAINTENANCE
FREE EARTH AS PER RDSO SPECIFICATION NO.
RDSO/PE/SPEC/PS/0109(REV.O)-2008 INCLUDING ALL MATERIALS etc.
The price shall cover supply, erection and commissioning of a maintenance free earth
system as per RDSO specification no. RDSO/PE/SPEC/PS/0109(REV.O)-2008.The
price shall cover the cost of all the materials required for the earthing system including
bond strip size 40x6 mm and civil works. The price shall include the testing of earth
value and painting the particulars on the concrete box as decided by the engineer.
TRACTION SUBSTATION
SOR ITEM TSS-1
DESIGN AND DRAWINGS FOR 220/27 or 132/27 KV or 110/27 KV TRACTION
SUB-STATIONS INCLUDING FEEDING POST AND CAPACITOR BANK:
The price shall cover on a flat rate basis for preparation and submission of design and
drawings per sub-station, new or existing, including provision of additional bay, for
erection of transformer and associated equipments, replacement of existing transformer
with new one, augmentation of existing bus bars and various type of connectors and
terminals, per feeding station in addition to site survey, investigation of soil bearing
pressure and soil resistivity, preparation and submission of cross section drawings,
preparation and submission of general arrangement drawings, detailed layout of
equipment, bus-bar connections and insulators, layout of cable trenches outdoor and
inside the control room, layout of earthing system and earth connections, layout of earth
screen wire, design of supporting structures for 132 kV/27 kV equipments, detailed
designs and drawings for steel work and structural support, suitable concrete pedestals,
and foundation plinths for equipment and drawings for equipments, components,
fittings and materials and approval of the same by the Employer.
The prices shall also cover on a flat rate basis for preparation of all designs and
drawings required in connection with supply, erection, testing and commissioning of
Shunt Capacitor equipment at the traction sub-stations. The price shall cover on a flat
rate basis cost of site survey, investigation of soil bearing pressure and soil resistivity,
preparation of cross section drawings, general arrangement drawings, detailed layout of
equipments, bus bar connections and insulators, layout of cable trenches out door and
inside the control room, earthing system and earth connection layout, and design of
supporting structures.
The price shall also include supply of required number of copies in soft and hard copies
in Auto Cad with one tracing on RTF paper of designs, drawings, technical booklets of
proposed/approved and completion drawings (as erected) per substation, feeding station
and capacitor bank as mentioned in the tender specifications.
The price shall also cover supply of associated maintenance/record registers of
appropriate size in printed pro-farma (if required in newly electrified section and as per
local Railway practice) etc as directed by Employer/Engineer in charge.
NOTE: The design for Oil Soak pit and drain water sump will also be got approved
from the Employer.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 22 of 48
SOR ITEM TSS-2 : DELETED
SOR ITEM TSS-3
CONSTRUCTION OF BAFFLE WALL COMPLETE WITH
REINFORCEMENT, BRICK WORK, PLASTERING ETC.:
The price shall cover excavation and construction of brick baffle wall as per RDSO
Drg. No. ETI/C/0213 for wind pressure upto 112.5 kgf/sqm.. The price shall include
supply of steel for reinforcement and other materials. The price shall also include
bending/binding and laying of reinforcement, shoring, shuttering and scoff-folding
arrangement, required for the construction of baffle wall and its curing. The price shall
include dismantling of all connected temporary arrangements, back filling required and
removal of soil. The price shall also include the plaster (12mm thickness with cement
mortar 1:4 mix) on the baffle wall. The price shall also include dismantling of all
connected temporary arrangements and removal of soil. The price shall include the cost
of cement also. For RCC baffle wall as per RDSO Drg. No. ETI/C/0214 for wind
pressure upto 150 kgf/sqm, the payment shall be made under CS-8.
Note for TSS- 3 (1) The prices under this item shall be the same for any shape or size of concrete blocks,
& brick wall. In calculating the individual volume of concrete and brick wall
fraction of a cubic meter beyond the third decimal shall be rounded off to the
nearest third decimal.
(2) For purpose of computation of volume of concrete and brick wall under this item, the
volume of steel work embedded in the foundation block or muff shall be ignored.
(3) The prices shall include cost of embedded drain pipes, conduits for cable or earthing
flats wherever necessary.
(4) Dowel bars in special foundations and nominal reinforcement in other foundations
will be necessary. Such nominally reinforced in other foundation will be payable
under Item TSS-3. The steel for nominal reinforcement and dowel bars will be
supplied by the Contractor and the concrete mixture in such a case shall be same as
for the normal foundations i.e. 1:3:6.
(5) At each Traction substation one number Oil soak pit for main transformer and one
drain water sump for the cable trenches will be provided by the contractor.
SOR ITEM TSS-4 (a)
SUPPLY, ERECTION, TESTING & COMMISSIONING OF 132 KV DOUBLE
POLE SF-6 GAS CIRCUIT BREAKER WITH INTERLOCK:
The price shall cover erection of 132 kV double pole SF-6 Gas Circuit Breakers,
complete with operating mechanism, all fittings and accessories including terminal
connectors. The price shall cover grouting the supporting frame and Mechanism box on
the foundation block and mounting of other accessories in their respective places. It
shall also cover the testing and commissioning of the Circuit Breaker. The price shall
also cover the supply and erection of an enamelled number plate. The Contractor shall
make his own arrangement for filling of the SF-6 gas and power supply required for
testing purpose. All necessary tools, equipments, instruments required for carrying out
necessary checks, tests and commissioning shall be arranged by the Contractor.
The price shall cover erection of an Interlocking Mechanism on an Isolator to permit
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 23 of 48
working of an Isolator and or earthing blade assembly in a desired sequence. The price
shall include supply and erection of interlock for Circuit Breaker.
SOR ITEM TSS-4 (b)
SUPPLY, ERECTION, TESTING & COMMISSIONING OF 220 KV DOUBLE
POLE SF-6 GAS CIRCUIT BREAKER WITH INTERLOCK:
Same as for item TSS-4(a) except that the price shall cover supply, erection, testing &
commissioning of 220 KV Double Pole SF-6 gas Circuit Breaker with Interlock.
SOR ITEM TSS-5(a)
SUPPLY AND ERECTION OF 132 KV DOUBLE POLE ISOLATORS
(MANUALLY OPERATED):
The price shall cover supply & erection and connecting of a 132 KV Double Pole
Isolator with a manually operated mechanism complete with mounting base and all
accessories required for its operation including terminal connectors. The price shall
include supply and erection of an enamelled number plate and padlock. The price shall
include mounting of the Isolator and the operating rod in position and their alignment
for smooth and trouble free operation. The prices shall also include the cost of 132 kV
solid core post insulator, operating rod and earthing blade assembly for 132 kV
Isolators.
SOR ITEM TSS-5(b)
SUPPLY AND ERECTION OF 220 KV DOUBLE POLE ISOLATORS
(MANUALLY OPERATED):
Same as for item TSS-5(a) except that the price shall cover supply and erection of 220
KV Double Pole Isolators (Manually operated).
SOR ITEM TSS-6(a)
SUPPLY & ERECTION OF 132 KV CURRENT TRANSFORMER ASSEMBLY
(400-200/5A):
The price shall cover supply & erection and commissioning of a 132 kV Current
Transformer (400-200/5A) complete with all fittings and accessories including terminal
connectors. It shall also include mounting of the transformer in position, and supply and
erection of an enamelled number plate as per the drawing ETI/PSI/P/7528.
SOR ITEM TSS-6(b)
SUPPLY & ERECTION OF 220 KV CURRENT TRANSFORMER ASSEMBLY
(200-100/5A):
Same as for item TSS-6(a) except that the price shall cover supply and erection of 220
KV Current Transformer assembly (200-100/5A).
SOR Item TSS- 6(c)
SUPPLY & ERECTION OF 110 KV Current Transformer (400-200/5A):
Same as for item TSS-6(a) except that the price shall cover supply and erection of 110
KV Current Transformer assembly (400-200/5A).
SOR Item TSS- 6(d)
SUPPLY & ERECTION OF 132 KV CURRENT TRANSFORMER ASSEMBLY
(1200-800-400/5-5-5A
Same as for item TSS-6(a) except that the price shall cover supply and erection of 132
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 24 of 48
KV Current Transformer assembly (1200-800-400/5-5-5A) as per RDSO‟s specification
ETI/PSI/117 (7/88) with A&C Slip no 1 to 9.
SOR ITEM TSS-7(a)
SUPPLY & ERECTION OF 120 KV LIGHTNING ARRESTOR:
The price shall cover supply & erection and connecting up of a 120kV Lightning
arrestor with surge counters and leakage current monitor complete with all fittings and
accessories including terminal connector. It shall also include mounting of the
Lightning arrestor in position and supply and erection of enamelled number plate.
SOR ITEM TSS-7(b)
SUPPLY & ERECTION OF 198 KV LIGHTNING ARRESTOR
Same as for item TSS-7(a) except that the price shall cover supply and erection of 198
KV Lightning Arrestor.
SOR Item TSS- 7(c)
SUPPLY, ERECTION, TESTING & COMMISSIONING OF 96 KV,
LIGHTNING ARRESTOR
Same as for item TSS-7(a) except that the price shall cover supply and erection of 96
KV Lightning Arrestor.
SOR ITEM TSS -8(a)
SUPPLY, ERECTION, TESTING & COMMISSIONING OF 25 KV SINGLE
POLE VACUUM CIRCUIT BREAKER WITH INTERLOCKING:
The price shall cover supply and erection of 25 kV Vacuum Circuit Breaker (1600 Amp
Rating) complete with operating mechanism, all fittings, and accessories including
terminal connectors. The price shall cover grouting the supporting frame and
mechanism box on foundation block and mounting of other accessories in their
respective places. It shall also cover, testing and commissioning of the circuit breaker.
The price shall also cover the supply and erection of an enamelled number plate. The
Contractor shall make his own arrangement for power supply required for testing
purpose. The price shall also include supply of interlocks and shall be applicable
individually for each, Circuit Breaker. The supply of vacuum circuit breaker shall be as
per RDSO specification No. TI/SPC/PSI/CB/0000 with A&C slip No. 1 to 5 or latest.
SOR Item TSS- 8(b)
SUPPLY, ERECTION, TESTING & COMMISSIONING OF 25 KV SINGLE
POLE VACUUM CIRCUIT BREAKER (2000 Amps rated current) WITH
INTERLOCKING:
Same as SOR item TSS-8(a) except current rating of CB shall be 2000 amps with
relevant RDSO specifications.
SOR ITEM TSS -9(a)
SUPPLY & ERECTION OF 25 KV CURRENT TRANSFORMERS (1500-
750/5A):
The price shall cover supply & erection and connecting of a 25 kV Current Transformer
(ratio 1500-750/5A) complete with all fittings and accessories including terminal
connectors. It shall include mounting of the transformer in position and supply and
erection of an enamelled number plate. The price shall also include the cost of small
parts steel work if any.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 25 of 48
SOR Item TSS-9(b)
SUPPLY & ERECTION OF 25 KV CURRENT TRANSFORMERS (3000-
1500/5A):
Same as TSS-9(a) except rating of CT shall be 3000-1500/5A.
SOR Item TSS- 9(c)
Supply & erection of 25 kV Current Transformers (200-100/5A):
Same as TSS-9(a) except rating of CT shall be 200-100/5A as per RDSO‟s specification
ETI/PSI/90(6/95) Rev. 4(Jan‟03).
SOR ITEM TSS-10
SUPPLY, ERECTION, TESTING AND COMMISSIONING OF NUMERICAL
CONTROL & RELAY PANEL SUITABLE FOR DOUBLE TRANSFORMER
TRACTION SUB -STATIONS OF 220/27 or 132/27 KV or 110/27 KV:
The price shall cover supply, erection, testing and commissioning of Control & Relay
Panel complete with RDSO approved Numerical Type protective relays for Control,
monitoring and protection in the traction sub-station comprising of 132 and 25 KV
circuit breakers, 25 KV interrupters and 132/25 Kv single phase transformers, sub-
station equipments, 25 KV over head equipment (OHE) feeders, shunt capacitor banks
and transmission lines (if applicable) as per RDSO specification No
TI/SPC/PSI/PROTCT/6070 (9/08) with latest version.
The prices shall also include protective relays for 132 Kv and 25 Kv circuit breakers,
interrupters, isolators complete with all wiring, control switches, meters, protective and
auxiliary relays, mimic panels and suitable size rubber mat in front and back etc.
including erection , alignment, grouting and earthing of the panel in position and all
connection for its commissioning. The control panel shall cater for a TSS having two
bays of HV & LV side associated equipments along with 02 feeder circuit breakers.
SOR ITEM TSS-11
SUPPLY & ERECTION OF TUBULAR ALUMINUM BUS BARS 50MM X
39MM DIA:
The price shall cover supply and erection per meter length of 50x39mm dia. Aluminum
tube to serve as bus bar or equipment to equipment bus bar connection in the traction
sub-station, wherever required. The price shall include bending, shaping and connecting
/clamping of the Aluminium tube to the equipment terminals/ bus bar supports as
required.
NOTE- For purpose of payment for this item fraction of a meter in the total length used
at a sub-station shall be rounded off to the nearest meter (0.5 m and below being
ignored).
SOR ITEM TSS-12
SUPPLY & ERECTION OF ‘ZEBRA’ ACSR CONDUCTOR:
The price shall cover supply and erection per meter length of 61/3.18 mm (ZEBRA
ACSR) conductor to serve as bus bar or equipment to equipment bus bar connection in
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 26 of 48
the traction sub-station, wherever required. The price shall include straightening,
shaping and connecting / clamping of the conductor to the equipment terminals /bus bar
supports as required.
NOTE: For purpose of payment, the length of aluminum conductor strung as bus-bar
between gantries shall be taken as horizontal distance between the interfaces of the
gantries. The total length used at a sub-station shall be rounded off to the nearest meter
(0.5 m and below being ignored).
SOR ITEM TSS-13
SUPPLY & ERECTION OF ALL CONNECTORS, BUS SPLICE & TEE
CONNECTORS etc REQUIRED FOR COMMISSIONING OF TSS
EQUIPMENTS:
The price shall cover supply and erection of a busbar junction and connector of the type
specified, including bolts, nuts, lock nuts, washers etc. required at the junction of bus
bars. The price shall also include supply and erection of ALCU bimetallic strip, if
required, to be provided at the junction.
NOTE:
1) For purpose of payment for this item fraction of a meter in the total length used at a
sub-station shall be rounded off to the nearest meter (0.5 m and below being
ignored).
SOR ITEM TSS-14
SUPPLY & ERECTION OF COPPER JUMPER WITH FITTINGS AND
FASTENER REQUIRED FOR TSS:
The price shall cover, on a flat rate basis, the supply and erection of jumper wire
complete with all components and fittings required for providing a flexible copper
jumper connection, including parallel clamps, bi-metallic and Aluminum -Copper
strips, wherever required, and terminal or Tee clamps at either end, including jumper
wire.
The price shall be applicable for any jumper connection in any combination between
feeders, L.T. Transformers drop out switch, lightening arrestors for overhead
equipments, isolators for overhead equipment and out going bus bars for switching
stations.
SOR ITEM TSS-15 (a)
SUPPLY & ERECTION OF 110/132 KVKV SUPPORT INSULATORS WITH
FITTINGS AND FASTENERS:
The price shall cover supply and erection of 132 kV support insulators complete with
fixing bolts, nuts and studs, Busbar jumper, clamps for clamping the busbar and SPS, if
required .
SOR ITEM TSS-15 (b)
SUPPLY & ERECTION OF 220 KV SUPPORT INSULATORS WITH
FITTINGS AND FASTENERS:
Same as for item TSS-15(a) except that the price shall cover supply and erection of 220
KV Support insulators with fittings and Fasteners.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 27 of 48
SOR ITEM TSS-16
SUPPLY & ERECTION OF 25 KV SUPPORT INSULATORS WITH FITTINGS
AND FASTENERS:
The price shall cover the supply and erection of a 25 kV solid core post insulator to
support Aluminum bus bars. It shall include supply of fixing bolts, nuts, locknuts,
washers and studs etc.
It shall also cover-erection of all components required for the assembly including post
insulator, Busbar jumper, clamps for clamping the busbar and SPS, if required.
SOR ITEM TSS-17(a)
SUPPLY & ERECTION OF 110/132 KV TERMINATION WITH/WITHOUT
ADJUSTER COMPLETE WITH DISC INSULATORS:
The price shall cover supply and erection of all materials for the termination of a single
ACSR conductor (61/3.18 mm ZEBRA) strung between gantries/portals, including
anchor fittings, single clevis assembly, adjuster, anchor double straps, string of 12 nos.
of 280mm (11”) Disc Insulators, strain clamps and arcing ring and other fittings to
complete the assembly. The assembly shall be of breaking strength of not less than
11500 kgf.
SOR ITEM TSS-17(b)
SUPPLY & ERECTION OF 220 KV TERMINATION WITH / WITHOUT
ADJUSTER COMPLETE WITH DISC INSULATORS:
Same as for item TSS-17(a) except that the price shall cover supply and erection of 220
KV Termination with/without adjuster complete with suitable number of disc
insulators.
SOR ITEM TSS-18
SUPPLY, ERECTION AND COMMISSIONING OF LOW MAINTENANCE
LEAD ACID BATTERIES SET WITH 2 NOs. OF SUITABLE BATTERY
CHARGER:
The price shall cover supply and erection of a 110 V, 200 AH low maintenance type
lead acid battery complete with stand as approved by engineer and accessories as
mentioned in relevant specification and a tool board with thermometer, hydro meter.
The price for erection shall include installation, connecting up, filling up of electrolyte,
initial/final charging, and commissioning of the battery.
The price for erection shall also include grouting of the chargers in position or
mounting it on the wall and connecting it to 240V single phase AC supply.
SOR ITEM TSS-19
SUPPLY, ERECTION AND COMMISSIONING OF 240V AC AND 110 V D.C.
DISTRIBUTION BOARDS IN THE CONTROL ROOM:
The price shall cover supply and erection of a 240V AC distribution board in the
control room. It shall include the grouting of the framework of the distribution board in
position or mounting it on the wall and necessary connections.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 28 of 48
The price shall also cover supply and erection of a 110 VDC distribution board in the
control room. The price shall include the grouting of the frame work of the distribution
board in position or mounting it on the wall and necessary connections.
SOR ITEM TSS-20
SUPPLY AND ERECTION OF EARTH ELECTRODE:
The price shall cover supply and erection of an earth electrode, a typical drawing of
which is included in RVNL‟s technical specification. The price shall cover the
provision of a protective concrete box with removable cover as shown in the drawing.
The price shall include the testing of earth value and painting the particulars on the box.
SOR ITEM TSS-21
SUPPLY AND ERECTION OF EARTH LEADS 75 X 8 MM MILD STEEL
FLAT LAID IN THE GROUND OR EXPOSED AS PER SITE REQURIMENT:
The price shall cover supply and installation per meter length of 75x8mm mild steel
flat, buried at a depth of 60 cm below ground level. The price shall also cover
connections of the steel flats to the earth electrodes to constitute the main earth ring and
to the earthed terminals of the 132/25 kV transformers etc. as required.
The price shall also cover supply and installation per meter length of 75x8 mm mild
steel flat, painted all around with two coats of painting with red oxide and two coats of
colour grass green shade-218 of IS:5 passing through cable trench or exposed above
ground level. The price shall also cover the connections of the steel flats to the earth
electrodes, to constitute the main earth ring and to the earthed terminals of the various
equipments as required.
SOR ITEM TSS -22
SUPPLY AND ERECTION OF EARTH LEADS 50 X6 MM MILD STEEL FLAT
LAID IN THE GROUND OR EXPOSED AS PER SITE REQURIMENT:
The price shall cover supply and installation per meter length of 50x6mm mild steel flat
buried at a depth of 60cm below ground level. The price shall also cover connections of
the steel flats to the main earth ring and to the steel structures and metallic frame work/
terminals of various equipments, as required.
The price shall cover supply and installations per meter length of 50x6 mm mild steel
flat painted all around with two coats of painting with red oxide and two coats of colour
grass green shade-218 of IS:5 passing through cable trench or exposed above ground
level. The price shall also cover the connections of the steel flats to the main earth ring
and to the steel structures and metallic frame work/terminals of various outdoor
equipments as required.
SOR ITEM TSS-23
SUPPLY AND ERECTION OF 8 SWG G.I. WIRE FOR EARTHING:
The price shall cover supply, shaping and erection of 8 SWG G.I wire per metre used
for earthing of control panels, LT, AC and DC distribution boards, battery chargers, etc.
at sub-station control rooms. The requirement of fencing panel earthing to the nearest
fencing upright shall also be included and paid for under this item.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 29 of 48
SOR ITEM TSS -24
SUPPLY AND ERECTION OF 32 MM DIA MS ROD FOR EARTH MAT:
The price shall cover supply and installation per meter length of bare mild steel rod of
dia 32mm to be buried at a depth of 60cm, below the ground level to form the earthing
grid & connected to earth electrodes. The price shall also cover jointing of the MS. rods
to form earthing grid and connection to MS. flats for system earthing.
NOTE FOR SOR ITEM TSS-21,22,23 and 24: For the purposes of payment, fraction
of a meter in the total length of earth lead of each type used at a substation shall be
rounded off to the nearest metre (0.5m and below being ignored).
SOR ITEM TSS -25
SUPPLY & ERECTION OF EARTH SCREEN WIRE INCLUDING
TERMINATION:
The price shall cover supply and stringing per meter length of 19/2.5mm (70 Kg/mm2)
galvanized steel stranded wire. It shall include the supply and erection of suitable
terminations using strain clamps adjuster (on one side only) etc. It shall also include
connecting by means of suitable terminal spades, the end of the earth screen wire to the
main members of the columns of portals gantries across which these wires are strung or
to 50x6mm MS. flat earth leads. For purposes of payment the clear span between the
structures on which earth wire is run shall be adopted. The clear span will be rounded
off to the nearest meter (0.5m and below being ignored).
SOR ITEM TSS-26 (a)
SUPPY, ERECTION, TESTING & COMMISSIONING OF 132/27 KV, 21.6/30.24
MVA ONAN/ONAF, SINGLE PHASE TRACTION POWER
TRANSFORMERS:
The price shall include the cost of supply, erection, testing and commissioning of
transformer with all accessories, 132 and 25 KV side bushings, cooling fans etc as per
latest RDSO specifications. Price includes loading, unloading of transformer and
bringing it to the erection site for commissioning. The Contractor shall bring the
transformer on to its correct position on the foundation and erect all the accessories,
check up the alignment and make connections of HV and LV terminals to the 132 kV
and 27 kV busbars. The Contractor shall carry out oil filtration and pre-commissioning
tests as approved by the Employer and commission the transformers strictly in
accordance with the instructions of the transformer manufacturer or his commissioning
Engineer at site to the complete satisfaction of the Employer. The Contractor shall be
held responsible to ensure that the work is carried out to the highest standards, in
accordance with the relevant codes of practice and any special
conditions/guidelines/requirements as laid down by the manufacturer of the transformer
are properly complied with. Contractor shall notify the manufacturer regarding likely
date of commissioning, one month in advance, so that the manufacturer can depute his
representative if so desired by him at his own cost, for warranty obligation purposes.
Notwithstanding availability of manufacturer‟s representative or otherwise, it shall be
contractor‟s responsibility to ensure that the equipment is commissioned as per laid
down procedure. However, in case of any extra cost being incurred in this regard, due to
delay on the part of the Contractor the same shall be recovered from the Contractor. The
Contractor shall make his own arrangements for oil filtration equipment as well as
power supply required for the same. All necessary tools, equipment, instruments
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 30 of 48
required for carrying out necessary checks and tests and commissioning of the
transformer shall be arranged by the Contractor.
SOR ITEM TSS-26 (b)
SUPPY, ERECTION, TESTING & COMMISSIONING OF 220/27 KV, 21.6/30.24
MVA ONAN/ONAF, SINGLE PHASE TRACTION POWER
TRANSFORMERS:
Same as for item TSS-26(a) except that the price shall cover supply, erection, testing
and commissioning of 220/27 KV, 21.6/30.24 MVA ONAN/ONAF, single phase
Traction Power Transformer.
SOR Item TSS- 26(c)
SUPPY, ERECTION, TESTING & COMMISSIONING OF 110/27 KV, 21.6/30.24
MVA ONAN/ONAF, SINGLE PHASE TRACTION POWER
TRANSFORMERS:
Same as for item TSS-26(a) except that the price shall cover supply, erection, testing
and commissioning of 110/27 KV, 21.6/30.24 MVA ONAN/ONAF, single phase
Traction Power Transformer. The transformer should be as per RDSO specification No.
ETI/PSI/118 A&C-10 or latest.
SOR Item TSS- 26(d)
SUPPY, ERECTION, TESTING & COMMISSIONING OF 132/27 KV, 30/42
MVA ONAN/ONAF, SINGLE PHASE TRACTION POWER TRANSFORMERS
Same as for item TSS-26(a) except that the price shall cover supply, erection, testing
and commissioning of 132/27 KV, 30/42 MVA ONAN/ONAF, single phase Traction
Power Transformer as per RDSO Specification No.TI/SPC/PSI/30TRN/2070 or latest
with latest amendments.
SOR ITEM TSS-27(a)
SUPPLY AND ERECTION OF 25 KV DOUBLE POLE ISOLATORS (1600A)
WITH INSULATORS:
The price shall cover the supply and erection, alignment and connecting up 25 kV
Double Pole Isolator (1600Amp capacity) complete with mounting base, operating rod,
operating mechanism and all accessories required for its smooth and trouble free
operation. The price including solid core Post Insulator, operating rod insulator etc.
Price shall also cover supply and erection of an enamelled number plate and a pad lock
for each Isolator, Bus bar connector provided for making connection to Isolator
terminal pad shall be paid under Item TSS-13.
SOR Item TSS- 27(b)
SUPPLY AND ERECTION OF 25 KV DOUBLE POLE BUS COUPLER
ISOLATORS (3150A) WITH INSULATORS:
Same as for item TSS-27(a) except that the DP isolator shall be of 3150 amps capacity.
SOR ITEM TSS-28(a)
Supply & erection of 25 kV Single Pole Isolators (1600A) with insulator:
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 31 of 48
Same as for item TSS-27(a) except that the price shall cover supply and erection of
single pole Isolator 1600 amps capacity instead of double pole Isolator
SOR Item TSS-28(b)
SUPPLY & ERECTION OF 25 KV SINGLE POLE ISOLATORS (3150A) WITH
INSULATORS :
Same as for TSS-27(a) except that the price shall cover supply and erection of single
pole Isolator of 3150 amps capacity instead of double pole Isolator.
SOR ITEM TSS-29
Supply, Erection, Testing & Commissioning of 25KV shunt capacitor bank of 2400
KVAR rating including low loss series reactor, 25KV Neutral Current
Transformer (NCT) etc.
The lump sum price shall cover supply, erection, testing and commissioning of 2400
KVAR (i.e.6600 KVAR at 40 KV) shunt capacitor bank at Traction substations,
complete with capacitor unit internal fuses, discharge devices, rack insulator assembly,
interconnector between units, insulators, suitable earthing lugs including terminal
connectors and other material and hard ware required for satisfactory working of the
unit. It shall also include mounting of the capacitor bank on the supporting structures
and its connecting up to other equipments. Payment for supporting structures shall
be made under item no CS-9 of schedule 30. The contractor shall carry out pre-
commissioning tests as approved by the purchaser and commission the shunt capacitor
bank strictly in accordance with the instructions of the shunt capacitor bank
manufacturer or his commissioning Engineer at site to the complete satisfaction of the
purchaser. The contractor shall be held responsible to ensure that the work is carried out
to the highest standards, in accordance with relevant code of practice and any special
conditions/ guidelines/ requirements as laid down by the manufacturer of the shunt
capacitor bank are properly complied with. The contractor shall notify the manufacturer
regarding likely date of commissioning, one month in advance so that the manufacturer
can depute his representative, if so desired by him, at his own cost, for warranty
obligation purposes. Notwithstanding availability of manufacturer‟s representative or
otherwise it shall be contractor‟s responsibility to ensure that the equipment is
commissioned as per laid down procedure. All necessary tools, equipments, instruments
required for carrying out necessary checks and commissioning of the shunt capacitor
bank shall be arranged by the contractor.
The price shall cover supply, erection & connecting up of series reactor suitable for
6600 KVAR rating (at 40KV) capacitor bank complete with all fittings and accessories
including connectors. It shall include mounting of the series reactor in position.
The price shall cover supply, erection of 25kv neutral current transformer for protection
of the capacitor bank. The price shall also cover connecting of neutral current
transformer with capacitor bank and control and relay panel. It shall also cover
mounting of the neutral current transformer on the supporting frame.
The price shall cover connecting up of control panel with protective and auxiliary relays
for circuit breakers, instrument transformers and capacitor bank as per RDSO latest
specifications with all wirings control switches and mimic diagram. LEDs annunciation
labels, alarm cancellation push buttons and local/remote switches. It shall also include
cost of wiring/terminal blocks required for providing the facility of remote operation.
The price for erection shall include alignment and grouting of the panels in positions
and all necessary connection to bring the control panel in operation. It shall also include
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 32 of 48
the cost of connecting the frame of each control panel to the earth bus inside the control
room and suitable size rubber mat in front and back. The price of control and relay
panel for shunt capacitor bank is included in TSS-10.
SOR Item TSS- 30
EXCAVATION OF EARTH TO THE DEPTH OF 2 METERS BELOW
GROUND LEVEL FOR BURYING 13 METERS LONG RAIL.
The price under this item shall cover the cost of excavation of earth 13 meters in length
and two (02) meters in depth below ground level. The price shall also cover the cost of
burying 13 meters long rail and connecting it with mat in TSS as per latest RDSO
drawing (Rail will be supplied by RVNL). The price shall also cover the cost of
loading, unloading and transportation to site of work of rail.
SCHEDULE 29000 (SCADA)
1. Supply, erection, testing, protocol of hardware, software, communication
cable, colour codes of cable and various parameters of each of the
schedule item, shall conform to RDSO‟s Specification No.
TI/SPC/RCC/SCADA/0130/Rev.1 (04/2014) or latest with up to date
amendment issued by RDSO and shall be obtained by the contractor.
SCADA shall be suitable to match and interface with existing SCADA of
RCC centre. Data transfer speed of Traction SCADA system should be
min 9600 bps as per RDSO instructions No. TI/IN/022(02/10) Rev 0.
2. The complete SCADA system shall be supplied, erected and
commissioned through Railway‟s approved vendors. The vender‟s list is
updated by RDSO/CORE Allahabad and shall be valid for the contractual
period. Vendors under trial period shall not be considered for this project.
3. Supply of furniture as per RDSO specifications equipments and
components (List B) and supply of special tools and plants (List C) as per
the schedule rate shall be done in consultation with the Engineer/RVNL
at site/RCC Centre. Items and costs are as per explanatory notes under
relevant items.
4. The work of SCADA of Supply, Erection, Testing & Commissioning
including maintenance & Warrantee shall govern by RDSO‟s
Specification No. TI/SPC/RCC/SCADA/0130/Rev.1 (04/2014) or latest.
SOR Item SCADA-1
Preparation and supply of Design & Drawing for SCADA at RCC, TSS,
SP & SSP.
Price shall cover the cost of Design & Drawing for SCADA and shall give
all details of various items of equipment at remote control center and the
controlled stations with updated equipment numbering and shall comply
with details of RCC center corresponding mimic panel, the various
interface with the main computer and the monitor/console on which
traction power controllers will monitor status and execute the commands
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 33 of 48
and ensure correct execution and tele-signals from control centre to various
remote controlled posts and vice-versa. The drawing shall show the details
of TSSs, SPs & SSPs with details of RTUs, layout of equipments, cable
colour codes, tag numbers, terminals numbers, in addition to various tele-
commands & tele-signals and panel indication. All drawings shall be got
approved by the client/engineer and Railways before commencement of
execution. All the „as erected‟ drawing & design in soft copies in CDs and
hard copies six numbers of each drawing shall be handed over to the
purchaser for final approval.
SOR Item SCADA-2
Supply of SCADA equipment at RCC. The lump sum price shall include the supply of standard Supervisory
Control and Data Acquisition system as per RDSO‟s Specification No.
TI/SPC/RCC/SCADA/0130/Rev.1 (04/2014) or latest with up to date
amendment issued by RDSO. There shall be two work station (first of 3
PCs and second of 2 PCs) and main & standby computer and FEP process.
The price shall include supply of one supervisory console PC, one coloured
LAPTOP (Dual Core Intel Pentium Processor at 3.2 GHz or Higher) and
associated MODEMS for remote SCADA monitoring through a DOT Link
as per RDSO specification. The price shall also include the cost of any
steel cabinets required for housing the equipments and also the material
required for internal wiring and mounting the cabinets in the position. The
cost shall also cover testing of the system at the manufacturer‟s works. The
latest version of hardware shall be considered at the time of supply.
The price shall also cover the license fee for the supply and installation of
Standard Electric Traction SCADA software. The successful bidder has to
purchase this from the RDSO approved supplier for standard software as
per RDSO Specification No. TI/SPC/RCC/SCADA/0130/Rev.1 (04/2014)
or latest.
SOR Item SCADA-3(a)
Supply of RTUs for FP/TSS.
The price includes the cost of RTU supplied for the controlled posts and
shall include necessary transducers, summation CTs, PT, supply change
over arrangement, digital/analog modules, limit setting, modems, CPU
cards. Power supply, surge arrestors, relay and contactors etc. at Traction
Sub-stations and feeding post for different analog parameters and
measurements. A tentative list of different telecommands, telesignals and
measurands are given in annexure as per RDSO‟s Specification No.
TI/SPC/RCC/SCADA/0130/Rev.1 (04/2014) or latest.
SOR Item SCADA-3 (b)
Supply of RTUs for SP.
The price shall cover supply of RTUs for SP. The details given in Item
SCADA-3(a) above are applicable to the SP also except that the different
analog parameters and measurands required have to be suitable for SP.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 34 of 48
SOR Item SCADA-3 (c)
Supply of RTU for SSP.
The price shall cover supply of RTUs for SSPs. The details given in Item
SCADA-3(a) above are applicable to the SSPs also, the different analog
parameters and measurands required have to be suitable for SSPs.
SOR Item SCADA-4(a)
Supply of maintenance free type Lead Acid Battery
The price shall cover supply of Maintenance Free or low maintenance (if
former not available in approved list) Lead Acid type Battery of 110V DC
with adequate Amp. Hour capacity to work with UPS. The battery shall
meet the requirements as RDSO‟s standard specification No.
TI/SPC/RCC/SCADA/0130/Rev.1 (04/2014) or latest and shall be
complete with all parts and accessories including stand, terminal board and
accessories required for its efficient operation.
SOR Item SCADA-4 (b)
Supply of UPS
The price shall cover supply of dual on-line UPS of 5 KVA capacity
suitable to work in standalone mode at remote control centre, so as to meet
the requirements, as enumerated in TI/SPC/RCC/SCADA/0130/Rev.1
(04/2014) or latest. The price shall not include the cost of Batteries which is
covered under item SCADA-4(a) above.
SOR Item SCADA-5
Supply of furniture
The lump sum price shall cover the supply of furniture at work station to
work independently and shall meet requirement as mentioned in RDSO
standard specification No. TI/SPC/RCC/SCADA/0130/Rev.1 (04/2014) or
latest. The price shall also include furniture for switching posts as per
requirement.
SOR Item SCADA-6
Supply of Data logging Printer for control centre
The price shall cover, supply of diagnostic data logging printer, 2 nos. of
HP DeskJet, 1125C/Ink jet A3 size coloured and two DOT Matrix (132
column) A3 size printer for the section suitable to work as input output
terminal to computer for data logging purposes. The price shall also cover
the equipment (printer server etc.) needed to put these printers on LAN or
latest printer, standard accessories suitable to work with the existing data
logger at RCC, complete with spare black and colour ink cartridge,
connecting power plug and cable to connect the data logger.
SOR Item SCADA-7 (a)
Erection charges for items SCADA-2 to SCADA-6.
The price shall cover the cost of erection of various items of equipments the
supply of which is covered under above mentioned items at remote control
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 35 of 48
center and the controlled stations. The cost of erection shall cover the cost
of transportation of equipments, their positioning, fixing and their
alignment for smooth trouble free operation. The price shall also cover the
cost of inter connecting cables, laying of cable in trenches of approved size,
wiring connection to batteries, UPS, surge arrestors, operator‟s console etc.
and all other works necessary for proper functioning of the equipments.
The price for erection shall also include carrying out liasion with software
supplier or at the site work to finalise any matching details between the
RCC software and the hardware vendor. The price for erection shall also
include the cost of adjustments, testing after erection at site, testing to work
all items or equipments specified, integration and commissioning as
considered necessary by the purchaser. The price for erection shall also
cover all cost of administration of the contract, insurance premia, bankers
charges for guarantee cost stamps, loading and unloading, handling of the
materials and for any road transport which the contractor use to carry the
materials between their depot and site of work. It shall also include cost of
erection of separate earthing, if required as per RDSO standard
specification No. TI/SPC/RCC/ SCADA/0130/Rev.1 (04/2014) or latest.
The price shall include complete finishing work at Remote Control Centre,
TSS, SP & SSPs to the satisfaction of the Employer.
SOR Item SCADA-7(b)
Integration of new SCADA system to existing system at RCC.
The price shall cover the integration of entire new SCADA system with
existing SCADA system at RCC. This shall also include the cost of any
hardware and software required to complete the work. The item covers the
administrative work of supply, transport, execution of contractual items of
work, liasoning, testing and commissioning as per specified protocol
mentioned in RDSO standard specification No.
TI/SPC/RCC/SCADA/0130/Rev.1 (04/2014) or latest as well as for the
efficient working of complete SCADA installation and trouble free
commissioning of the above work in all respects.
SOR Item SCADA-8
Erection, integration, testing & commissioning for existing and new
equipments
(a) TSS RTU (b) SSP RTU (c) SP RTU
The price shall cover the adjustment charges (modification/upgradation in
existing RTUs and SCADA system) required during the execution and final
testing on RTUs at TSS, SP & SSP with remote control centre for final
commissioning.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 36 of 48
SOR Item SCADA- 9
Supply of Equipment and Components (List B) Schedule of item for spare equipments and components
Note: The above list is provisional and may be updated as per zonal railway or
specific sectional requirement within overall cost.
SOR Item SCADA-10
Supply of Special T&P (List C)
List of Maintenance Tools and Instrument for SCADA system
Sr.No. Description Qty.
1. 4-1/2Digit Multi meter MECO Model 235
MK-11
4 Nos.
2. Tong Tester 2 Nos.
3. Electrician Plier 8” 3 Set
4. Electrician Plier 6” 3 Set
5. Cutting Plier 3 Nos.
6. Nose Plier 3 Nos.
7. I.C. Extractor 3 Nos.
Sr.No. Description Qty. Unit
1. Transducers:
i) Current 1 Nos
ii) Voltage 1 Nos.
iii) Power Factor 2 Nos.
2. 8 Port serial Card 1 Nos.
3. Contactors/Interposing Relays 28 Nos.
4. RETI Modules :
i) PR-80 (Power supply module) 2 Nos.
ii) CPU Module 2 Nos.
iii) DO Module 3 Nos.
iv) AI Module 1 Nos.
v) DI Module 3 Nos.
vi) Modem Card 1 Nos.
vii) Input conditions PCB_ 3 Nos.
viii) Cat UV/PT fuse fail Module 6 Nos.
ix) CVT 1 Nos.
x) DC-DC convertor 1 Nos.
5. Key Board 1 Nos.
6. Power Supply Unit for servers
FEP
1 Nos.
7. Power Supply Unit for Work
Station
1 Nos.
8. 18 GB wide ULTRA-2 SCI-HDD 1 Nos.
9. 20 GB IDE HDD 1 Nos.
10. 16 port 10/100 Ethernet LAN
HUB
1 Nos.
11. Surge Arrestor (Set of 3) 1 Nos.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 37 of 48
8. Card Extenders 3 Nos.
9. Level meter – APLAB Model 2031A 2 Nos.
10. Wire Stripper 1 Nos.
11. Fault Analyser 1 Nos.
12. Dual trace oscilloscope (0-30 Mhz) 2 Nos.
13. Remote Terminal Test Unit (In P-IV Laptop
Computer kit)
2 Nos.
14. Tool kit consisting of -
a) Brief Case 1 Nos.
b) Stripper & Cutter 1 Nos.
c) Crimping Tool 1 Nos.
d) Screw Driver Kit (6 Blades) 1 Nos.
e) Screw Driver Kit (1 Set Start type 6
Blades)
1 Nos.
f) Desolding Pump 1 Nos.
g) Brush (To clean the RTU) 1 Nos.
h) Soldering wire (18 SWG) 100 gms.
i) Solder Sucker 3 Nos.
j) Soldering Iron 3 Nos.
k) Nose Plier 1 Nos.
l) Spanner 1 Nos.
COMMON ITEMS OHE/TSS
SOR Item CS-1
SUPPLY AND ERECTION OF 25 KV VACUUM INTERRUPTER:
The price shall cover supply of a 25 Kv AC 50 Hz Single Pole, Outdoor type 1600 Amp
rating vacuum interrupter with all accessories and components as per RDSO‟s latest
Specification at site and erection of the same with supporting framework and terminal
connectors with interlock .
The price for erection shall include preparation of its foundation alignment and grouting
of the interrupter on its foundation block and mounting of accessories, if any in their
respective positions. The price shall also cover supply and erection of enameled number
plates. All necessary tools, equipments, instruments, including power supply required
for carrying out necessary checks, tests and commissioning shall be arranged by the
contractor.
The supply of vacuum interruptor shall be as per RDSO specification No.
ETI/S/PSI/167(09/97) with A&C slip No. 1 & 2.
SOR Item CS-2
SUPPLY AND ERECTION OF A 25 KV POTENTIAL TRANSFORMER TYPE-
I OR TYPE -II:
The price shall cover supply and erection of a 25 KV Potential transformer Type-I or
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 38 of 48
Type -II complete with all fittings and accessories as per relevant latest specification,
including terminal connectors and fixing bolts. The price for supply and erection shall
include proper alignment of the transformer in position. The price shall also cover the
supply and erection of an enameled number plate and fixing bolts. The price shall not
include the cost of any small parts steel work.
SOR Item CS-3
SUPPLY AND ERECTION OF A 42 KV LIGHTNING ARRESTOR:
The price shall cover supply and erection of a 42 kV lightning arrestor complete with
all fittings and accessories as per relevant latest specification including terminal
connectors. The cost of erection shall include proper alignment of the lighting arrestor
in position. The price shall cover supply and erection of cadmium copper jumper (65),
which will be paid under item OHE-29. The price shall not include the cost of any small
part steel work. The price shall also include supply and erection of surge counter with
leakage current monitor along with cable (unarmored PVC insulated copper cable size
35 Sq. mm 1100 volts grade). The surge counter shall be mounted on the structure at a
convenient height as per. Specification No. ETI/PSI/71 revision-1(1/87), A&C slip
No.1 to 7 or latest.
SOR Item CS-4
SUPPLY AND INSTALLATION OF CABLES FOR SWS/TSS:
The price shall cover supply, installation, and connecting-up the cable for control and
indication, (PVC 1100 V grade 2.5 sq mm copper conductor 7 core), from the
interruptor to the terminal board, supply and erection of terminal connectors at ends
if required and conduits wherever necessary, heater supply cable, (1100 V grade
PVC insulated heavy duty 2 core 4 sq mm aluminium conductor), from interruptor
to the 230 V fuse box mounted on wall inside the control cubicle and from this box
to LT distribution board inside the control cubicle, supply and erection of terminal
connector at each end, if required, conduit if any at the interruptor end, catenary
indication (240 V AC circuit cable, PVC1100 V grade 2.5 sq mm Copper conductor
2 core), between potential transformer Type-I and terminal board inside the control
cubicle and supply and erection of terminal connectors at both ends, if required and
conduit to be embedded between the steel work base and the cable trench and shall
include all fastenings on masts and structural members to support them, LT power
supply cable, (1100 V grade aluminium conductor XLPE insulated PVC sheathed
and steel armoured heavy duty cable conforming to IS7098/Pt.I/1988 2x25 sq mm
for 5 KVA AT, 2x70 sq mm for 10 KVA AT, 2x185 sq mm for 25 KVA AT),
between L T supply transformer at switching station and LT distribution board
provided in control cubicle and suitable cable boxes and connectors at both ends if
required, cable between 110V battery charger and battery, between battery and the
DC fuse box and between the DC fuse box and terminal board and etc. The price
shall include supply and erection of terminal connectors wherever required.
NOTES:
1 In case of feeding stations which are located within the traction sub-station
premises, the cables shall be run from individual equipment and terminated inside
the sub-station control room.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 39 of 48
2 Notwithstanding the sizes of cables given above, the bidder shall assure himself that
various cables would suit the ratings of equipments offered by him.
3 Price shall be payable on flat rate basis per meter irrespective of size of cable for
different types of cables used switching stations/TSS.
SOR item CS-5
SUPPLY, ERECTION, OIL FILTRATION, TESTING AND COMMISSIONING
OF 25 KV/240 VOLT, 10 KVA, AUXILIARY (LT) SUPPLY TRANSFORMER
OIL TYPE WITH 25 KV D. O. FUSE SWITCH, ANTICLIMBING DEVICE,
INSULATOR, COPPER JUMPER AND EARTH ELECTRODES etc:
The price shall cover Supply of 25KV/240V, 10 KVA LT supply transformer at site
with DO fuse assembly (including fuse carrier) and all other mounting accessories, as
per the RDSO‟s latest specification and its erection complete with terminal connectors
on a mast or gantry. The price shall also be applicable for transformers mounted on
steel pedestals at switching stations. The price shall also cover supply and erection of an
enameled number plate of approved design.
The price shall also cover oil filtration and pre- commissioning tests as approved by the
Employers or Engineer. The contractor shall make his own arrangement for oil filtration
equipments, as well as power supply required for the same. All necessary tools,
equipments, instruments required for carrying out oil filtration / checks / tests /
commissioning shall be arranged by the contractor. The price shall also cover supply &
erection of a DO fuse switch assembly complete with all mounting accessories,
post/pedestal insulator for DO fuse switch assembly.
The price shall also cover on a lump sum basis the supply and erection of anti-climbing
device consisting of galvanized steel fixtures mounted on the masts below the
transformer.
The price shall also cover supply of conductor / jumper wires on a flat rate basis and the
supply of all components including parallel clamps, bi-metallic and Aluminium copper
Al-Cu strips wherever required. The price shall also cover the erection of complete
jumper assembly including conductor/jumper wire to be provided between the Over
Head Equipment and L.T. Transformers, drop out switch assembly.
The price shall also cover supply and erection of an earthing station/ stations with a
pipe/pipes required to achieve permissible earth resistance value embedded into the
ground by drilling or otherwise complete with protective concrete box and lugs suitable
for directly connecting two mild steel flats of minimum size 50 mm x6 mm and copper
earthing strip 25X3 mm at LT side earthing point to mast.
The price shall not include cost of supply and provision of structure bond connecting
LT transformer with structure and then to rails which will be paid for under item
OHE-22.
NOTE:1. Contractor at his own cost shall do the replenishment of the transformer oil
on account of testing and leakages during the warranty period.
SOR Item CS-6
PROVIDING AND LAYING OF CONCRETE FOR FOUNDATION AND
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 40 of 48
PLINTH IN ALL TYPES OF SOILS AND SOFT ROCK
The price shall cover excavation, supply and handling of all materials and accessories,
temporary arrangements for excavation in all types of soils and soft rock,
concrete/masonry drains/walls, shoring wherever necessary, casting concrete including
frame work wherever necessary, tamping of concrete, grouting of masts and finishing
the top of concrete foundation or anchor blocks. The price also includes dismantling of
all connected temporary arrangements, back filling with excavated earth and
compacting the same to the required height and width as per drawing to ensure safety of
foundation, confining the exposed height of foundation block to within 10 cm., and
removal of spoil. The price shall also include the cost of supply of cement.
Notes for measurement
1. The payable volume of the foundations under the above item shall be the designed
one as shown in the drawings for which the hole has been made, irrespective of the
actual configuration.
2. The depth of the excavation shall be measured from the formation level to the
maximum excavated point.
3. The prices shall be calculated for the individual volume of concrete, fraction of a
cubic metre beyond the third decimal shall be rounded off to the next nearest third
decimal.
4. The prices shall apply for concreting of all foundations for mast, gantries, portals,
anchor blocks for guy rods, and fencing uprights.
5. For purposes of computation of volume of concrete, the volume of steel work
embedded in the foundation block shall be ignored.
6 For the purpose of computation of volume of concrete, the volume of concrete shall
include the volume of sand and bitumen in sand cored foundation. However, for the
purpose of computation of quantity of cement utilised in sand core foundations, the
volume of the sand and bitumen used in core hole should be deducted from the
total volume of the foundation.
7 For purposes of computation of volume of concrete, the volume of each muff for all
masts shall be taken as 0.02 cu.m. except for masts with balance weights and for
each column of portal, mast, 2 or 3 track cantilever masts, and special fabricated
masts for which the volume of muff shall be taken as 0.08 cum. irrespective of the
size and shape of muff, on a flat basis.
8. The item shall also be applicable to include the concrete of equipments, at the
switching stations/traction sub-station (except building foundations) as well as
embedded drain pipes, wherever required.
9. The prices shall also cover the cost of diversion of masonry/earth drain wherever
necessary for casting of foundations.
10. (a)RDSO guidelines shall be followed for grade of concrete, type of foundations etc.
Generally concrete for foundation shall be nominal mix of Grade-M-10 and for
grouting, muffing, embedding of structure in foundation concrete of M-15 Grade as
per latest RDSO guidelines shall be used.
(b) In Soft/Hard rock, Foundation in contact/Buried under Non-aggressive soil/ground
water:
Foundation concrete shall be of M-15 grade and core concrete shall be of M-20
grade.
(c) In Soft/Hard rock Foundation in coastal area: Foundation as well as core concrete
shall be of M-20 grade.
11. No extra payment shall be made for foundation casted with steel reinforcement as
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 41 of 48
per RDSO drawing. Similarly, no extra payment shall be made for foundations
casted as per 10(b), (c).
SOR Item CS-7
PROVIDING AND LAYING OF CONCRETE FOR FOUNDATION AND
PLINTH IN HARD AND ROCKY SOIL REQUIRING CHISELING/BLASTING:
The price shall cover excavation, supply and handling of all materials and accessories,
temporary arrangements for excavation in hard rock requiring chiseling/blasting and
concrete / masonry drains / walls. Shoring wherever necessary, casting concrete
including frame work where necessary, tamping of concrete, grouting of masts and
finishing the top of concrete foundation or anchor blocks.
The price also includes dismantling of all connected temporary arrangements, back
filling with earth and compacting the same to the required height and width as per
drawing to ensure safety of foundation, confining the exposed height of foundation
block to within 10 cm., and removal of spoil.
The Employer's Engineer shall certify where use of chisel and hammer or blasting has
been necessary. The contractor shall arrange for supply of explosives and all tools and
plants for blasting operations at his own cost. The price shall also include the cost of
supply of cement.
Notes for measurement
1. The payable volume of the foundations under the above item shall be the designed
one as shown in the drawings for which the hole has been blasted, irrespective of
the actual configuration assumed by the latter due to the blasting.
2. The depth of the excavation shall be measured from the formation level to the
maximum excavated point.
3. The prices shall be same for any shape or size of concrete blocks. In calculating the
individual volume of concrete, fraction of a cubic metre beyond the third decimal
shall be rounded off to the next nearest third decimal.
4. The prices shall apply for concreting of all foundations for mast, gantries, portals,
anchor blocks for guy rods, and fencing uprights.
5. If half or more of the volume of excavation is in hard rock requiring
chiseling/blasting, entire foundations shall be paid for under this item.
6. For purposes of computation of volume of concrete the volume of steel work
embedded in the foundation block shall be ignored.
7. For the purpose of computation of volume of concrete, the volume of concrete shall
include the volume of sand and bitumen in sand cored foundation. However, for the
purpose of computation of quantity of cement utilised in sand core foundations, the
volume of the sand and bitumen used in core hole should be deducted from the
total volume of the foundation.
8. For purposes of computation of volume of concrete, the volume of each muff for all
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 42 of 48
masts shall be taken as 0.02 cu.m. except for masts with balance weights and for
each column of portal, each head span mast, 2 or 3 track cantilever masts, and
special fabricated masts for which the volume of muff shall be taken as 0.08 cum.
Irrespective of the size and shape of muff, on a flat basis.
9. The price under this item shall also include in cost of concrete at the switching
stations as well as embedded of drain pipes, wherever required.
10. The prices shall also cover the cost of diversion of masonry/earth drain wherever
necessary for casting of foundations.
11.(a) RDSO guidelines shall be followed for grade of concrete, type of foundations etc.
Generally Concrete for foundation shall be nominal mix of Grade-M-10 and for
grouting, muffing, embedding of structure in foundation concrete of M-15 Grade
as per latest RDSO guidelines shall be used.
(b) In Soft/Hard rock, Foundation in contact/Buried under Non-aggressive soil/ground
water:
Foundation concrete shall be of M-15 grade and core concrete shall be of M-20
grade.
(c) In Soft/Hard rock Foundation in coastal area: Foundation as well as core concrete
shall be of M-20 grade.
12. No extra payment shall be made for foundation casted with steel reinforcement
as per RDSO drawing. Similarly, no extra payment shall be made for foundations
casted as per 11(b), (c)
SOR Item CS-8
PROVIDING AND LAYING OF REINFORCED CONCRETE FOR
PIER/COLUMN/PILE, CABLE TRENCH AND TRENCH COVER
The price shall cover excavation and providing and laying of all reinforced
concrete work for pier/column/pile, cable trench and trench cover and other materials
including bending, binding, laying of the reinforcement, shoring where necessary,
casting concrete including frame work where necessary, grouting and finishing the tops
of foundation blocks with the required slope/muff but excluding supply of steel
for reinforcement. The price shall also include dismantling of all connected temporary
arrangements, back filling as required and removal of spoil. The price shall also include
the cost of supply of cement.
Notes for measurement
1. The Concrete for cable trenches/trench cover/pier/column/pile shall be nominal mix
of 1:2:4(M-15 grade)
2. The prices shall be same for any shape or size of concrete blocks. In calculating the
individual volume of concrete, fraction of a cubic metre beyond the third decimal
shall be rounded off to the next nearest third decimal.
3. The prices shall apply for concreting of all foundations for mast, gantries, portals,
anchor blocks for guy rods, and fencing uprights.
4. For purposes of computation of volume of concrete the volume of steel work
embedded in the foundation block shall be ignored.
5. The price under this item shall also include the cost of concrete cable trenches and
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 43 of 48
trench covers at the switching stations/traction sub-station as well as embodiment of
drain pipe, where required.
6. The prices shall also cover the cost of diversion of masonry/earth drain wherever
necessary for casting of concrete.
7. The payment for required steel shall be made under Civil Engineering BOQ Item
2076. However cost of cable support and trays is payable under BOQ item CS-9
SOR Item CS-9
SUPPLY AND ERECTION OF ALL TYPES OF GALVANISED STEEL
STRUCTURES, SMALL PARTS STEEL etc:
The price shall cover the cost of supply, erection, alignment and setting before grouting
of individual mast of finished traction mast fabricated from rolled mild steel beam
(BFB) 152 mm x 152mm x 37.1Kg/m. designated SC-150, table 3.1 of IS-808/1989
duly drilled as per RDSO‟s Specification No. ETI/OHE/C/00144 Mod- B or latest and
galvanized as per speciation No. ETI/OHE/13(4/84) with A&C slip No. 1 to 3 or latest.
The length of mast will be 9.5 or 8.5 meter as required.
The price shall also cover the cost of supply, erection, alignment and setting before
grouting of individual traction masts and main masts of switching stations including
those for head spans. of traction mast, main mast of switching stations fabricated from
Rolled Mild Steel Joist (RSJ) 203 mmX152 mm x 52.0 Kg/m designation WB-200,
Table 2.2 of IS- 808/1989 duly drilled as per RDSO drawing nos. given below for
various type of masts and galvanized as per specification No. ETI/OHE/13(4/84) with
A & C slip No.1 to 3 or latest. The price shall also cover the cost of supply of any other
structures fabricated out of RSJ beam.
Drg. Nos. (i) ETI/OHE/C/0000144 Mod- 09.5 M long
(ii) ETI/C/0030 Mod-F 11.4 m (S1)
(iii) ETI/C/0031 Mod-D 11.4 m (S2)
(iv) ETI/C/0036 Mod-E 08.0 m (S4)
(v) ETI/C/0181 Mod-C 12.4 m (S6)
(vi) ETI/C/0184 Mod-B 09.4 m (S9)
The price shall also cover the cost of supply of O, N and R type portals with necessary
components as per following RDSO Drawing Nos., cost of erection, alignment and
setting before grouting, wherever required, of portals assembly of boom components
and erection of the same. The prices shall also include supply and erection of
galvanized bolts, nuts washers etc. wherever required as per approved designs and
drawings. The price shall cover assembling, adjustment and erection of all types of
booms including TTC booms and any special structures across the track, not covered
under this item.
The structures shall be fabricated and galvanized from steel conforming to IS-2062 or
„A‟ as per concerned specification i.e. IS:2062/1984, IS-808/1989 and RDSO
specification No. ETI/OHE/13 (4/84) with A&C slip Nos 1 to 3 or latest.
(i) ETI/C/0008 Sheet No. 2 to 6 latest Mod for „N‟ type
(ii) ETI/C/0017 Sheet No. 2 to 6 latest Mod for „O‟ type
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 44 of 48
(iii) ETI/C/0011/69 Sheet No. 2 to 6 latest Mod for „R‟ type
The price shall also cover the cost of supply of B-Series traction mast 9.5 m long i.e. B-
150, B-175 and B-200 etc fabricated and galvanized as per RDSO Drg No. ETI/C/0071
(Mod-E) and specification No. ETI/OHE/13 (4/84) or latest. The price shall also cover
the supply of any other size of B-series or K-Series mast required, that has not been
mentioned in this item.
Note : For the purpose of payment, the weights of individual traction mast and
masts of head span shall be determined for each type on the basis of the payable
weight per meter length shown below for standard types, For special types, the
payable weight per meter length will be indicated by the Employer at the time of
approval of designs.
PAYABLE UNIT WEIGHTS FOR STANDARD MASTS
S. No. Type of masts Weight in Kg per meter
including galvanization
1 2 3
1 6"x6" BFB 38.03
2 162x154 BFB 38.00
3 200x200 BFB 51.20
4 8"x6" RSJ 53.39
5 S1 53.30
6 S3 76.40
7 S4 53.39
8 S5 111.53
9 S6 53.39
10 S7 76.40
11 S8 111.53
12 K 100 23.70
13 K 125 30.30
14 K150 38.18
15 K175 43.72
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 45 of 48
16 K200 49.87
17 K225 57.50
18 K250 66.72
19 B100 27.71
20 B125 32.47
21 B150 39.07
22 B175 44.61
23 B200 50.76
24 B225 61.50
25 B250 70.72
26 S 100 23.72
27 S101 19.98
28 Other Sections As & when issued by
RDSO/market survey etc
The price shall also cover the cost of supply of special fabricated and galvanized steel
structures (other than BFB/RSJ/‟B‟ Series Masts and Portals). The structure to be
supplied under this item TTC, „G‟ Type, BFB Type portals, Bridge masts, Emergency
masts and Double/Fabricated „S‟ Series masts such as S-3, S-5, S-7, S-8, S-100, S-101,
T-150, cable trays etc., Any other similar structure required during the execution of
work shall also be supplied under this item.
The price shall also include the cost of steel, fabrication, galvanization and supply at
site for erection. Steel shall be conforming to IS:2062 Grade „A‟ SK 1984 (Latest), Zinc
conforming to IS:209/1997 (Latest) and galvanization to RDSO‟s specification
No.ETI/OHE/13 (4/84) with „A‟ & „C‟ slip No. 1 to 3 or latest. The various structures
covered under this item are .
S.No
Description
Drawing No
Mod.
1 2 3 4
1 TTC with 5.5/8.0 mtrs boom ETI/C/0009
Sheet 2 to 5
„B‟
2 „G‟ type Portal Up right and End Pieces ETI/C/0056 „C‟
3 BFB Portal ETI/C/0026
Sheet 2
„A‟
4 S-7, 12.4 MTRS Length ETI/C/0182 „C‟
5 S-8, 12.4 Mtrs Length ETI/C/0183 „C‟
6 S-100, for LT Transformer at SWS ETI/C/0043 „B‟
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 46 of 48
7 S-101, for Isolators inside SWS ETI/C/0180 „A‟
8 S-3, 11.4 Mtrs ETI/C/0180 „C‟
9 S-5, 11.4 Mtrs ETI/C/0042 „E‟
10 T-150, for LT Supply Transformer ETI/PSI/037 „C‟
The price shall cover cost of erection, alignment and setting before grouting, wherever
required, gantries, including tower / steel tower / steel work for feeders for traction sub-
station, drop arms, standard super masts and suspension brackets for feeders and return
conductors. Dwarf masts of stub masts for anchoring, complete with anchor plates
drilled and welded in position multiple cantilever cross arm, chairs, adopters for bracket
assemblies and all other small part steel works, the erection of which is carried out by
the contractor irrespective of whether they are supplied by purchaser/contractor. The
prices shall also include supply and erection of galvanized bolts, nuts washers etc.,
wherever required as per approved designs and drawings.
The steel shall be conforming to IS-2062/1992 (latest) Gr „A‟ SK zinc conforming to
IS-209/1992 or latest.
The price shall also include the cost of repairing of platform shelters in case the shelter
is dismantled/removed/damaged during the course of erection of a mast / portal at
platforms.
Note:
(i) The prices for the items shall also include the cost of stenciling of location number
on masts/portal uprights in the manner as directed by the Purchaser.
(ii) The price shall also include straightening of masts/portals uprights wherever
approved by the purchaser and cutting of mast/portals/upright to suit the site
condition.
(iii)The payment shall be made on the basis of the final lengths/weight of the
structures, in case the same are cut or modified as indicated above before erection.
The price shall also cover the cost of supply of all fabricated steel work excluding
fasteners which are required to be supplied by the Contractor. The cost of erection for
such steel work, if carried out by the Contractor shall be paid for under relevant item
For standard fabricated steel work for which RDSO'S approved drawings are available,
the weight of steel work as specified in RDSO'S drawings shall be considered for
payment. However, in case the unit sectional weight of any member indicated in
RDSO's drawing is not in conformity with the unit sectional weight as per the latest IS
specification, the weight of the fabricated steel work shall be calculated on the basis of
latest IS specification and the same will be considered for payment. For the non-
standard fabricated steel work, the calculated weight to be considered for payment
under this item shall be included in the relevant drawing based on, latest IS sectional
weight at the time of submitting the designs for approval of the Employer.
NOTES :
1 For the purpose of payment against items, weight of structures or fabricated steel
work will be calculated according to the weight of black steel given in section
books for the lengths of various members shown in the approved drawings. There
will be no addition for increased weight due to galvanizing or painting or weld
material or reduction for holes or skew cuts.
2 The rates against item shall be applicable to the erection of small part steel work
which are not covered under the various other items of work.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 47 of 48
SOR Item CS-10
SUPPLY AND ERECTION OF FENCING PANELS, UPRIGHTS, GATE, AND
ANTI-CLIMBING DEVICE:
The price shall include supply and erection of fencing panels painted with two coats of
red oxide zinc chromate primer to IS: 2074 and finished with two coats of aluminium
paint. The prices shall also include supply and erection of fencing upright, anti-climbing
devices including the cost of fasteners and the price shall be for a meter length of the
panels 2.4 m height measured in the plan view of the appropriate approved drawings.
The prices shall be on the basis of black weight of the steel with no deduction for holes
or skew cuts or no increase for weld materials.
The price shall also cover supply and erection of an anti-climbing device consisting of
galvanized steel fixtures mounted on the fencing panels as per approved design. The
price shall be per meter length of the panel. Fencing panel shall be manufactured with 8
SWG GI wire as per CORE drawing no CORE/ALD/PSI/001 Mod „B‟.
SOR Item CS-11
SUPPLY AND ERECTION OF ALUMINUM JUMPER WITH FASTENERS:
The price shall cover on flat rate basis the supply and erection of an aluminum jumper
complete with all components and fittings required for providing jumper connection
including parallel clamps, bi-metallic Aluminium-Copper strips wherever required and
terminal or tee clamps at either end. The price shall be applicable for any aluminum
jumper/ connection in any combination between feeders, return conductors, overhead
equipment, isolators, and out-going bus bars or switching stations and booster stations.
Jumper connections for 25 kV feeding stations will also be paid under this item.
SOR Item CS-12
SUPPLY AND ERECTION OF COPPER STRIPS FOR EQUIPMENT
EARTHING:
The price shall cover supply and erection of 25mm x 3mm copper strips to connect the
earth terminals of equipment like potential transformers, lighting arrestor, and LT
supply transformers to the main masts of the gantries on which they are mounted. The
price shall also cover all fastenings required for fixing the copper strip along any
structure member of the gantry.
SOR ITEM CS-13
SUPPLY AND ERECTION OF ALUMINIUM BUS BAR 36MMx28MM:
The price shall cover supply and erection of aluminium bus bar 36mmx 28 mm including bending, shaping and clamping on to insulators, connectors or equipment terminals. SOR ITEM CS-14
SUPPLY AND SPREADING OF GRAVEL/ BALLAST IN THE SWITCH YARD
(SP/SSP/TSS):
The price shall be per cubic metre rate and shall cover supply and spreading of
uniformly graded gravel/ballast of size 20mm as per IS:383-1970 in the outdoor switch
yard/TSS after completing all the works and levelling the switch yard area, but before
commissioning of the sub-station. The gravel/ballast shall be of good quality and free
from any dust and dirt. Prior approval of ballast shall be taken from the Employer for
the gravel samples. The gravel/ballast shall be spread out uniformly to a depth of
minimum 10cm. over the area indicated by the Employer‟s Engineer.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 48 of 48
SOR Item CS-15
DISMANTLING OF REDUNDANT FOUNDATIONS WITH COMPRESSOR
POWERED MACHINES:
The price under this item shall cover the cost of breaking of redundant foundations with
compressor powered machines or manually with required tools. The price shall also
cover the cost of any required material including consumables like HSD Oil etc
required for breaking of foundation block and shifting the broken material from site to
a place/location and refilling the excavated pit with earth as directed by employer at
site of work. No price is payable for dismantling of any foundation due to fault of
contractor.
SOR Item CS-16
MONTHLY CHARGES FOR ONE CRANE OPERATOR, WATCH AND WARD
STAFF FOR ONE CRANE/UTV.
The price under this item shall cover monthly charges on lump sum basis to be paid for
one crane operator in day/night time as per work requirement for OHE mast/structure
erection, loading/unloading of material etc. Price shall also cover monthly charges to be
paid to Watch & Ward staff to be deputed for the crane round the clock at site of work
for security and miscellaneous works as per requirement. The deployment shall be done
as per directions of the engineer at site.
Note: Unit of the item shall be „per month’.
SOR Item CS-17
SUPPLY AND ERECTION OF ANTI-THEFT TRANSFORMER 240 VOLT/2.2
KV 5 KVA , DO FUSE SWITCH ASSEMBLY, EXCAVATION OF CABLE
TRENCH, LAYING OF CABLES, EARTHING, JUMPERING, DG SET,
INCLUDING DISMANTLING OF ABOVE EQUIPMENTS.
The price under this item shall cover all items required for anti theft arrangement of
OHE at each location including supply and erection of a Anti-theft single phase
transformer of 230 volt/2.2 KV, 5 KVA capacity at site, mounting it on structure or
gantry with suitable mounting and tripping arrangement as per the RDSO specification.
Price shall also cover supply and erection of a DO Fuse switch assembly complete with
all mounting accessories, post/pedestal insulators, DG set of 5 KVA capacity. The price
shall also cover the supply and erection of anti-climbing device consisting of galvanized
steel wire with fixtures mounted on the mast below the transformer. The price shall also
cover supply and erection of a copper jumper along with suitable clamps and bi-
metallic strips wherever required between OHE/cable and transformer, drop out switch
assembly. The price shall also cover supply, mounting of a 230 Volt 63 Amp. ICDP
switch on transformer structure and its connections. The price shall also cover
excavation of cable trench from supply point to transformer structure wherever
required, supply and laying of suitable size cables. The price shall also cover
dismantling of the complete system when advised by the Engineer. The price shall not
cover the provision of structure bond connecting anti-theft transformer with structure
and then to rails which will be paid for under item OHE-22. Local electricity if
available at station may be used for the purpose free of charge after approval. The price
shall cover cost of diesel, lub oil etc required for running of DG set when electricity is
not available.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 1 of 40
Schedule-33000(GENERAL ELECTRICAL WORKS) (Quarters, Service buildings, Pumps, Track crossings etc.)
1. Explanatory notes for various items of work in Electrical General Services Schedule are given below:
i All electrical works should comply with Indian Electricity Act 2003 and Rules framed there under.
ii All electrical installations shall conform to the relevant Indian Standard and shall be carried out as per the relevant safety Code of
Practices and guidance for Safety Procedures in Electrical Works as per IS:5216/Pt I & II/1982.
iii Notwithstanding the ratings specified in the BOQ, all components proposed to be used in the installations, shall be of appropriate
rating of voltage, current and frequency without any additional financial implication on RVNL. Discrepancies, if any, in this regard,
shall be brought to the notice of the Engineer by the Contractor.
iv All minor items viz. hardware items, foundation bolts, termination lugs for electrical connections etc. as required and necessary for
proper working of the equipment shall be deemed to have been included in the Bill of Quantities, whether such items are
specifically mentioned or not.
v (a) The basic quantities of components & materials required to make up a unit of work for selected items are approximate. The Contractor shall plan the work, estimate the actual quantities required and get the same approved by the Engineer before placing orders.
(b) In estimating the prices for various items of work, provision for loss or wastage in transit and erection including freight, handling, taxes and duties, insurance if any etc. should be taken into account and firm unit price offered for a complete unit of work to be done by the contractor.
vi The various items to be supplied/provided/erected should be as per the list of approved suppliers included in RVNL‘s Technica l Specifications/list followed by concerned zonal Railway. Items not appearing in the approved list shall be procured from good quality sources in line with best industries practices and shall be either ISI marked or conforming to latest IS (if any). Before procurement, vendor approval shall be obtained from the Employer.
vii Good workmanship and total compliance with safety and other statutory rules and regulations, shall invariably be observed by the Contractor.
viii All approvals from the relevant and appropriate government & statutory authorities shall be the total responsibility of the Contractor
unless specified otherwise.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 2 of 40
ix All quoted rates shall cover supply of materials, handling of materials, labour required, civil works, taxes and duties, fabrication,
installation, testing and commissioning, training and free maintenance till handing over to the Employer‘s representative.
x If any activity of work is essential for the satisfactory completion of the work but is not mentioned specifically in the Bill of Quantities
or elsewhere in the bidding documents, the same shall be deemed to be included In the scope of work and shall be executed by the
contractor within the accepted cost. The work shall be handed over in a functional manner complete in all respects.
xi
The inspection of various items shall be carried out by the agencies as specified in RVNL specifications. The prices quoted also
include RITES/RDSO representative inspection and testing charges unless otherwise specified in the bill of quantities or Technical
Specification. In case of change of inspection from RDSO/RITES to RVNL/CONSIGNEE, 1% of the cost of material will be
deducted by RVNL as inspection charges.
xii The inspection of above items will be done at the manufacture‘s works/place decided by the Employer based on item, its quantity,
Inspecting Authority etc.
2. DRAWINGS
2.1 The contractor shall prepare drawings in Auto Cad for all LT/HT installations, indicating proposed works and shall obtain approval of Engineer prior to taking up the work. Such drawings shall be prepared in coordination with all other agencies executing works at the same site and a maximum of 10(ten) copies as are required by RVNL with one tracing on RTF paper.
2.2 After commissioning, these drawings shall be duly updated as per erection work at site and submitted in six copies and one tracing in RTF paper, as Completion Drawings, along with a soft copy to the Employer.
2.3 Where the contractor proposes to use an item of equipment, other than that specified or detailed on the drawings, which requires any re-design of the structure, partitions, foundation, piping, wiring or any other part of the mechanical, electrical or architectural layouts, he shall inform the Engineer well in advance and obtain his approval. Delays resulting from such re-design shall be On Contractor’s account.
He shall also submit all related information as may be required for approval of such redesign, to the Engineer.
2.4 Where the work of the Contractor has to be executed in close proximity to or will interfere with work of other agencies, the Contractor shall work out space/time adjustments in coordination with other agencies. If the contractor installs his work before coordinating with other agencies, so as to cause any interference with their work, he shall make the necessary changes without extra cost to the owners of the installation.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 3 of 40
3. EXPLANATORY NOTES FOR BOQ ITEMS
The descriptions of all items are self explanatory. These Explanatory Notes are supplementary to the BOQ description. Further details are
available in latest booklet of RVNL‘s STANDARD SPECIFICATIONS FOR MATERIAL AND WORKS Volume-II(GENERAL
ELECTRIFICATION AND RAILWAY ELECTRIFICATION WORKS) as amended from time to time.
NOTE: Following particular requirements shall be followed for wiring works:
1 No conduit shall be of size less than 20 mm. 2 Occupancy of wiring cable in conduit shall not exceed 45% of the capacity of conduit. 3 Switch boxes shall be of galvanized sheet metal of suitable sizes from approved sources: 4. Separate conduit shall be laid for each circuit/sub main/main wiring. 5 Water cooler/AC Points and other such inductive loads shall be controlled with ―C‖ series MCBs. 6 Neutral cable shall be brought into each switch box. 7 Earth cable shall be brought into each switch box. 8 Fan point wiring shall include supply & fixing of fan box. 9 Approx.150 mm long wiring cable shall be kept loose in switch box/SDB/DB etc. 10 Conduits laid in sheds shall be clamped with the shed structure with clamps made from GI. strips of 25x1.6mm and spaced at
about 1000mm interval, fixed with 8mm dia bolts with nuts. 11 Brass screw and cup washers shall be used for fixing sheets on the front of switch box . 12 All the wiring work shall be in conformity with IS732/1989 (Latest Version) CODE OF PRACTICE FOR ELECTRICAL WIRING
INSTALLATIONS & IS 4648/1968 (Latest Version) Guide for Electrical Wiring in Residential Buildings. 13 The equipments which are available with ISI mark in Indian market, they shall be supplied having ISI mark only whether
specifically mentioned in BOQ & its explanatory notes or not. 14 All the energy consuming equipments which are available in Indian market with energy star rating issued by BEE, shall be
supplied with minimum 3 star energy rating only whether specifically mentioned in BOQ & its explanatory notes or not.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 4 of 40
ITEM NO 33001 (i) to (vi) ELECTRIFICATION OF STAFF QUARTERS
(a) The item price includes cost of labour & all materials required to electrify the quarter in all respect complete with ceiling and exhaust fans,
luminaries with lamps and other items indicated in the scale of fittings for each type of quarter. It also includes the cost of wiring cables
(sizes indicated for point wiring, circuit wiring and sub main wiring), PVC conduits with accessories, junction boxes, modular switches,
sockets, metal boxes, lamp holders and ceiling roses, modular plates, pre-wired sub distribution boards and meter boards with meters,
MCBs, earth electrodes etc.
The work of staircase wiring covers complete work of wiring and all the materials required including conduit, wiring cable of size for point wiring, two nos of two way switches etc. Payment for this item shall be in addition to the one point wiring covered under Item No-33003 (i).
(b) Scale of fittings, wiring points, fans, luminary etc. for each type of quarter, Cable sizes, no. of wires permissible in each circuit and sub main, meters, etc has been indicated here under.
SCALE OF ELECTRICAL FITTINGS FOR QUARTERS
Details of Points to be provided in each type of quarter
Type of
Qtr.
LP Tube Total FP PP 5A PP 15A Call Bell Ex. Fan Geyser AC (32A) Total
Points
I
No. of
Points
6 2 8 2 2 2 0 0 0 0 14
II
6 2 8 2 3 2 1 0 0 0 16
III
7 3 10 3 3 3 1 0 0 0 20
IV
11 5 16 3 4 4 1 1 1 1 31
V 15 6 21 5 6 5 1 1 2 2 43
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 5 of 40
Sizes of single core (copper conductor) cable for point wiring, circuit wiring and sub main wiring, circuits, distribution board/s, etc. for Qrs.
Nos. of points and size of wiring cables Nos. of circuits and size of wiring
cables
Size of Sub main wiring
cable
Size of point wiring cable
(copper conductor)
Size of circuit wiring cable
(copper conductor) For L & F Load
For Power
load
LP TLP FP CBP EFP PP5A PP
15A
GP PP32A
(ACP)
For L&F For 5A
Plug
For
15A.
Plug
For
32A.
AC
For geyser
Phases
and
neutral
1.5 sq.mm 2.5s
q.
mm
4sq
mm
6sq
mm
6sq
mm
2.5 sq.
mm
4sq.
mm
4sq.
mm
6sq.
mm
6 sq.mm 4 sq mm 10 sq mm
Continuo
us earth
1.5 sq.mm 2.5s
q
mm
4
sq
mm
6
sq
mm
6sq
mm
2.5sq
mm
4sq
mm
4 sq
mm
6sq
mm
6 sq.mm 4 sq mm 10 sq mm
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 6 of 40
Nos. of points
Nos. of circuits Single phase Double
Door Distribution board
(4 incomer +8 outgoing)
Earth Electrode Type of
Quarter
LP TL
P
FP CBP EFP PP5A PP
15A
GP PP32A
(ACP)
For
Lights
Fans &
call bell
For 5A
Plug
For 15A.
Plug
For 32A
AC
For
geyser
Total
Ckt. Qty Details
I 6 2 2 0 0 2 2 0 0 2 1 2 0 0 5 1 No.
Incoming MCB DP-20 Amp with RCCB 100 mA and O/G --- 6-16amps. MCB
SP -5 Nos.
(a) Single unit Quarter - 1 No (b) two units Quarter - 1 No,
(c)Three/four units quarter - 2 Nos. II 6 2 2 1 0 3 2 0 0 2 2 2 0 0 6 1 No.
Incoming MCB DP-20 Amp with RCCB 100 mA and O/G --- 6-16amps. MCB
SP -6 Nos
III 7 3 3 1 0 3 3 0 0 3 2 3 0 0 8 1 No.
I/C MCB DP-20 Amp with RCCB
100 mA and O/G --- 6-
16amps. MCB SP - 8 Nos.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 7 of 40
IV
11
5
3
1
1
4
4
1
1
4
2
4
1
1
12
1 No.
( for
L&F)
I/C MCB DP-32Amp with
RCCB 100 mA and Outgoing - (i) MCB SP 6-
16amps ---6 Nos,
One Number for
each quarter
1 No.
( for
power
circuit)
I/C MCB DP-32Amp with
RCCB 100 mA and Outgoing - (i) MCB SP 16amps ---4 Nos,(PP15A)
(ii) MCB SP 20 amps -- 1
No.(Geyser) (iii) MCB SP 32
amps -- 1 No(AC/WC)
V
15
6
5
1
1
6
5
2
2
6
3
5
2
2
18
1no.(for L&F)
I/C MCB SPN-32Amp with RCCB 100mA and Outgoing –(i) MCB SP 6-16 amps – 12 Nos,
Two Numbers
for each quarter 1.No. (for Power circuits)
I/C MCB TPN-40 Amp with RCCB 100 MA mA and Outgoing – (i) MCB SP
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 8 of 40
16amps -6 nos, (PP15A) (ii) MCB SP 20 amps – 2 nos (Geyser) (iii) MCB SP 32 amps – 2 No (AC)
Abbreviations
LP Light point with 18 watt CFL PP5A Light plug point complete with socket and switch
TLP Tube light point with 1x28 watt T-5 Luminary and T-5 lamp PP15A Power plug point complete with socket and switch
FP Ceiling Fan point with 1200/1400 mm fan with 300 watts
electronic regulator
PP32A
(ACP)
Air Conditioner point with Industrial type iron clad plug
32 amps & 20A DP MCB in metal clad box
CBP Call bell point with ding dong type call bell GP Geyser point with 25 liters storage geyser
EFP Exhaust fan point with 300 mm Exhaust fan
Details of Meter board
(A) Electronic Energy Meter with LCD display and outgoing MCB for quarters
Type of Qtr Block of one unit Block of two units Block of three units Block of four units Capacity
Meter Outgoing DP MCB
Meter Outgoing DP MCB
Meter Outgoing DP MCB
Meter Outgoing DP MCB
Meter DP MCB
I 1 No. 1 No. 2 Nos. 2 Nos. 3 Nos. 3 Nos. 4 Nos. 4 Nos. 10-40 A 20 A
II 1 No. 1 No. 2 Nos. 2 Nos. 3 Nos. 3 Nos. 4 Nos. 4 Nos. 10-40 A 20 A
III 1 No. 1 No. 2 Nos. 2 Nos. 3 Nos. 3 Nos. 4 Nos. 4 Nos. 10-40 A 20 A
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 9 of 40
Note: - Outgoing MCB and meter for individual unit shall be housed in separate chamber .Sealing arrangement for individual unit shall be made.
(B). Incoming MCBs in meter Boards (in separate chamber for each unit)
Qtr Block of one
unit
Block of two
units
Block of three
units
Block of four units Bus bar chamber
Type Rating MCB Rating MCB Rating MCB Rating DP MCB Copper Bus bars Type
I 32 A DP 40 A DP 63 A DP 63 A DP 100A Double door
II 32 A DP 40 A DP 63 A DP 63 A DP 100A Double door
III 32 A DP 40 A DP 63 A DP 63 A DP 100A Double door
IV 40 A DP 63 A DP 63 A TPN 63A TPN 100A Double door
V 40 A TPN 63 A TPN 100 A TPN 100A TPN 200A Double door
Note: - Bus bar chamber required only beyond two units quarter block.
IV 1 No. 1 No. 2 Nos. 2 Nos. 3 Nos. 3 Nos. 4 Nos. 4 Nos. 10-40 A 40 A
V 1 No. 1 No. 2 Nos. 2 Nos. 3 Nos. 3 Nos. 4 Nos. 4 Nos. 10-40 A single phase (for
L&F) 10-40 A, 3
Phase (for Power load)
40 A
40 A TPN
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 10 of 40
ITEM NO: 33002: ELECTRIFICATION OF GATE MAN LODGE AT LEVEL CROSSING
(a) The item price includes cost of labour & all materials required to electrify the gate man lodge in all respect complete with ceiling fans, luminary with lamps and other items indicated in scale of fittings including cost of wiring cables (sizes indicated for point wiring, circuit wiring), PVC conduits with accessories, junction boxes, switches, metal boxes, lamp holders and ceiling roses, phenolic laminated sheet covers, pre wired sub distribution board, earth electrodes etc.
(b) Scale of fittings, wiring points, fans, luminary etc. and Cable sizes, no. of wires permissible in each circuit and sub main, etc has been indicated below.
(c) Payment for providing bracket on wall is included under item for GI pipe and shall be made on measurement of length basis. SCALE OF ELECTRICAL FITTINGS
Details of
Points
LP
TLP (T-5) F P STL PP5A Total Points D B EE
Quantity 2 No. 2 No. 1No. 1No. 1No. 7 Nos. 1No. 1No.
Abbreviations
LP Light point with 18 watt CFL STL light point with 1x28 watt street light (aluminium sheet) T-5 luminary with lamp and G.I.pipe bracket grouted on wall
FP Ceiling Fan point with 1200 mm
fan & 300watt stepped type
Electronic regulator
D B Pre wired Distribution board comprising of following:-
Incoming DP MCB32A with 100mA RCCB --- 1No.
Outgoing SP MCB 6-16A – 4Nos.
100A copper bus bars
TLP T-5 light point with 1x28 watt
surface type(metal sheet) T-5
luminary with lamp
EE G.I.pipe earth electrode
PP5A Light plug point complete with
socket and switch
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 11 of 40
Sizes of single core (copper conductor) cable for point wiring, circuit wiring,
Size of point wiring cable
Size of
circuit
wiring
cable
Nos. of circuits
LP T-5 FP STL PP5A LP, FP & PP5A STL
Phases
and neutral 1.5 sq.mm 2.5 sq.mm
1 No. 1 No. Continuous
earth
1.5 sq.mm 2.5 sq.mm
ITEM NO.33003: ELECTRIFICATION OF SERVICE BUILDINGS &PASSENGER SHELTER AND SHEDS
a) The item price includes cost of labour & all materials required to electrify the buildings in all respects in surface/recess (excluding supply and erection of fans, luminaries, air conditioners, water coolers, geyser which are covered elsewhere under BOQ). The cost includes wiring cables (sizes indicated for point wiring, circuit wiring and sub main wirings), PVC conduits with accessories, junction boxes, modular switches, metal boxes, lamp holders and ceiling roses, modular plates sub distribution boards, distribution boards and earth electrodes etc.
b) Service buildings shall also include buildings at isolated locations such as relay huts at level crossings etc.
c) Wiring for essential and non essential load and their control shall be carried out separately at station buildings and other locations as
required.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 12 of 40
d) The payment for provision of industrial type iron clad plug socket with 32A DP MCB in M.S.Box [Item 33003(iii)] shall be paid in addition to
one power point work covered under 33003(ii).
NOTES: -
i) Earth Electrode shall be provided for each building as per IE rules.
ii) Single phase distribution system is permitted up to 10 KW load calculated on the basis of load of points as indicated here under.
iii) Three phase distribution system shall be carried out for the buildings having load above 10 KW calculated on the basis of load of
points as indicated here under.
iv) Separate SDB‘s shall be provided for L&F and Power loads as per site requirements.
v) Each SDB shall be provided with RCCB 100 mA with incoming DP MCB.
vi) Each Distribution Board and Sub Distribution board shall be designed based on the requirement of load as per site conditions and
considering 25% additional circuits (minimum- 1 No.) as spare (MCB) on outgoing and minimum 50% additional load on Incoming
(for future requirements)
vii) Approval for design shall be obtained from the Engineer, prior to ordering boards on the basis of sample calculation for assessment
of electrical load, circuits and wattage of points as indicated below.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 13 of 40
A) Sample Calculation for Assessment of Electrical load, Circuits and wattage of points
A-1) Wattage of points
Light Point /Call Bell
point
Ceiling
Fan Point
Exh. Fan
Point
Light Plug
point
5A
Power plug
point
15A
Geyser
Point
PP 32A Air Conditioner Point /Water Cooler
60 Watts. 100
Watts.
200 watts 100 Watts 500 Watts 1500 Watts 2000 Watts
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 14 of 40
A-2) Sample Calculation for Assessment of Electrical load and Circuits:-
Building with load as detailed here under
LIGHT & FAN CIRCUIT POWER CIRCUIT
Light Point /Call Bell
point
Ceiling Fan Point
Exh. Fan Point
Light Plug point 5A
Power plug point
15A
Geyser Point
PP 32A Air Conditioner Point /Water Cooler
Wattage of points 60 Watts. 100 Watts 200 watts 100 Watts 500 Watts 1500 Watts 2000 Watts
No. of points 25 10 4 5 4 1 2
Total watts 1500 1000 800 500 2000 1500 4000
Total Load 3800 watts 7500 watts
Nos. of points permitted in a circuit
8 Nos 3 Nos 1 No 1 No 1 No
No. of circuits 5 Circuits 2 Circuits 4 Circuits 1 Circuit 2 Circuits
Total circuits 7 Circuits 7 Circuits
Sub Distribution
Board
Incoming 40 A DP MCB with RCCB --- 1 No Outgoing SP MCB 6--16amps—9 Nos (including spares)
Incoming 63 A DP MCB with RCCB—1 No, Outgoing (including spares) (i) SP MCB 32A -- 3 Nos for (AC/WC) (ii) SP MCB 20A – 2 Nos. For Geyser (iii) SP MCB 16A – 5 Nos. for 15A plugs
Distribution Board
Incoming 63 A TPN MCB --- 1 No Outgoing (including spares)
DP MCB 63 amps --2 Nos DP MCB 40 amps -- 2 Nos
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 15 of 40
A-3) Size/s of single core (copper conductor) cable for point wiring, circuit wiring and sub main wiring, circuits, Sub Distribution Board/s,
etc.for buildings, offices etc.
Nos. of points and size of wiring cables
Nos. of circuits and size of wiring cables
Minimum size of Sub main wiring cable
Minimum size of main wiring cable
G.I.pipe Earth Electrode
Size of point wiring cables Size of circuit wiring cables
Light Point/Fan Point/Call Bell point/ PP5A etc.
Group point wiring/5A wiring
PP 15A
GP
PP32A (ACP/WC)
For L&F and 5A Plug
For 15A. Plug
For Geyser
For 32A. (AC/WC etc)
10 sq.mm
16 sq.mm
Phase/s and neutral
1.5 sq.mm
2.5 sq. mm
4 sq mm
6 sq. mm
6sq mm
2.5 sq.mm
4 sq. mm
4 sq. mm
6 sq. mm
10 sq. mm
16 sq. Mm (i) One No. for
Each single Phase SDB/DB (ii) two Nos. for each three phase SDB/DB
continuous earth
1.5 sq. mm
2.5 sq. mm
4 sq mm
6 sq. mm
6sq mm
2.5 sq. mm
4 sq. mm
4 sq. mm
6 sq. mm
10 sq. mm
16 sq. mm
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 16 of 40
Nos. of points permitted in a circuit
No.of circuits permited in a Distribution Board
Light Point/Fan Point/Call Bell point/ PP5A etc.
PP5A PP 15A
GP PP32A (ACP/WC)
For L&F and 5A plug
For 15 A plug
For Geyeser
For 32A (AC/WC etc)
8 Nos. 4 Nos 1 No 1 No 1 No 12 Nos. 12 Nos 10 sq.mm
16 sq.mm
Abbreviations
LP Light point PP5A Light plug point complete with socket and switch
FP Ceiling Fan point. PP15A Power plug point complete with socket and switch
CBP Call bell point PP32A
(ACP/WC)
Air Conditioner/Water cooler point with Industrial type iron clad plug
32 amps & 20A DP MCB in metal clad box
EFP Exhaust fan point GP Geyser point
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 17 of 40
ITEM NO 33004: DELETED
ITEM NO 33005: Supply, installation, testing and commissioning of prewired T-5, energy efficient luminaries.
The item price includes labour & cost of all materials including cost of luminary complete with accessories, T-5 tube, FR PVC insulated multistranded single core copper conductor cable, earthing etc. Requirements of this item shall be as per technical details furnished here under and as per instructions of Engineer.
Installation of luminary on wall/ceiling Luminary shall be fixed properly on ceiling or on the wall with wooden/ roll plugs and
screws. Installation of luminary on Passenger shelter/sheds -Luminary shall be fixed with structure of shed with 2 No clamps of GI.strips of 25x1.6mm and nut & bolts, 33005(i) Fitting & arrangement shall be similar to Havell's Cat. Ref. No.LHIT12128032 complete with electronic ballast, T-5 tube. & earthing etc. as required. 33005(ii) Fitting & arrangement shall be similar to Havell's Cat. Ref. No.LHIT11228033 complete with electronic ballast, T-5 tube & earthing etc. as required.
ITEM NO.33006: Supply, installation, testing and commissioning of street light luminary with prewired T-5 energy efficient tubes.
The item price includes labour & cost of all materials including cost of FR PVC insulated multistranded single core copper
conductor cable, earthing etc. Luminary shall be provided on the bracket of pole / on wall / as required. For provision of luminary
on wall, G.I.Pipe bracket is payable under G.I.Pipe item on measurement of length basis. It also includes
33006 (i): Fitting & arrangement shall be similar to Havell's Cat. Ref. No. LHRT05228033, complete with T-5 tubes, electronic
ballast etc.
33006 (ii): Fitting & arrangement shall be similar to Havell's Cat. Ref. No. LHRT05128032, complete with T-5 tubes, electronic
ballast etc.
33006 (iii): Fitting & arrangement shall be similar to Havell's Cat. Ref. No. LHRT15214040, complete with T-5 tubes, electronic
ballast etc.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 18 of 40
33006 (iv): Fitting & arrangement shall be similar to Havell's Cat. Ref. No. LHRT18414040, complete with T-5 tubes, electronic
ballast etc.
33006 (v): Fitting & arrangement shall be similar to Havell's Cat. Ref. No. LHRT18424034, complete with T-5 tubes, electronic
ballast etc. OR similar to Bajaj Cat Ref No BGEST 85 RF CFL FG E40 complete with 85W CFL as required by Railway.
CFL luminary shall be Integral, powder coated die-cast aluminium housing, pot optics reflector with full glass cover, accessories
complete.
ITEM NO.33007: Supply, installation, testing and commissioning of Metal Halide/HPSV Street light luminary with lamp.
The item price includes labour & cost of all materials including cost of Metal halide/HPSV street light luminary complete with
lamp, FR PVC insulated multistranded single core copper conductor cable earthing etc.
Luminary shall be provided on the bracket of pole / on wall / as required. For provision of luminary on wall, G.I.Pipe bracket is
payable under G.I.Pipe item on measurement of length basis.
33007(i) Fitting & arrangement shall be similar to Crompton cat. ref MHSGN1107IH.
33007(i) Fitting & arrangement shall be similar to Crompton cat. ref MHSG2115IH/FG.
ITEM NO 33008: Supply, installation, testing and commissioning of A.C. ceiling fan. (Without Regulator)
The item price includes supply & erection cost of all materials including cost of 230V A.C. ceiling fan having 3/4 blades, double ball bearing, copper wound motor, suitably sized down rod, canopies and capacitor etc complete with all accessories including fixing phenolic laminated sheet cover on the fan box, FR PVC insulated multistranded single/three core copper conductor cable wiring and connecting with earthing system etc. Fan should have ISI mark and as per IS-374/1979, min 3 star energy rating issued by BEE.
Fan point wiring is covered under item 33003.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 19 of 40
ITEM NO 33009: Supply, installation, testing and commissioning of stepped type, electronic fan regulator on
the existing phenolic laminated sheet.
The item price includes labour & cost of all materials including cost of stepped type, electronic regulator 300W and connecting cables etc.
ITEM NO 33010: Supplying, installation, testing and commissioning of 11-23 watts, compact fluorescent lamp
complete with electronic ballast
The item price includes labour & cost of all materials including cost of compact fluorescent lamp of suitable wattage complete with electronic ballast of approved make etc as advised by Engineer.
ITEM NO 33011: Supplying, installation, testing and commissioning of Exhaust fan
The item price includes labour & cost of all materials including cost of Exhaust fan (ISI marked, as per IS-2312), min 3 star
energy rating issued by BEE(if available in Indian market), grouting bolts & nuts, FR PVC insulated multistranded single core
copper conductor cable, connection to earthing system and making opening in the wall/modifications as required. The exhaust
fan should be preferably with louvers if available in Indian market.
ITEM NO 33012: Supply, installation, testing and commissioning of stationary vertical storage type drinking
water cooler complete with Supply and installation of Auto Voltage Corrector.
The item price includes labour & cost of self contained drinking water cooler 150 liters capacity (cooling capacity 150 Lts. per
hour) water cooler [conforming to IS-1475 (part-1)/2001, ISI marked, min 3 star rated], suitable for operation on 230 volts+/-10%,
50Hz, AC supply system complete with all connected standard fittings, accessories etc. and 5KVA , wall mounted, I.C. controlled
electronic auto-voltage corrector conforming to relevant IS (latest version), suitable for operation on single phase 180 to 260
volts, 50Hz incoming AC supply and output 200 to 230 volts A.C. supply, complete with time delay relay, voltmeter, instant start
provision with push button switch, connection to earthing system etc as required.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 20 of 40
ITEM NO 33013 (a), (b):Supplying, installation, testing and commissioning of LT Switch Boards different
capacities
The item price includes labour & cost of all materials including cost of LT switch board, connection of cables for incoming and
outgoing etc. LT switch board shall be cubical type, wall mounted, dust & vermin proof, conforming to IS:8623 (latest version). LT
switch board shall be suitable for operation on 3 phase, 4 wire, 415 volt, AC supply system, fabricated with 16 SWG M.S. sheet,
powder coated and complete with inter connections, instrument connections with copper conductor cable, copper bus bars
200/250 amps. (as per capacity of switch board 63/125A), CT's, voltmeter, ammeter, LED type indication lights, cable glands,
earthing studs etc.
ITEM NO.33014: DELETED
ITEM NO.33015 (i),(ii) & (iii):Supply, installation, testing and commissioning of L.T. Feeder pillars of different
capacities
The item price includes labour & cost of all materials including cost of L.T. Feeder pillar, construction of brick masonry platform
450 mm high, inter connections, connection of cables for incoming and outgoing etc. L.T. feeder pillar shall be weather proof
(degree of protection not less than IP54), fabricated with 2 mm thick CRCA sheet, conforming to IS:8623 (latest version), powder
coated, suitable for operation on 3 phase, 4 wire, 415 volt, AC supply system., copper bus bars of 200/250/400 amps (as per
capacity of feeder pillar 63/125/250A), LED type indication lights, cable glands, earthing studs etc.
ITEM NO.33016: DELETED
ITEM NO 33017 (i), (ii), (iii): Supply and erection of different length Tubular pole with Junction box etc.
The item price includes labour & cost of all materials including cost of swaged type steel Tubular pole 7/9 meters long conforming
to IS-2713 /Part I to III/1980 (latest version) (designation 410 SP – 3/ 410 SP - 30), canopy type with suitable length and diameter
brackets, Junction box, erection of pole, casting of foundation, muffing and painting of pole, connection to the earthing system
etc.
Entire Work shall be in conformity with IS 2713/Part 1-3 and specifications of RVNL.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 21 of 40
ITEM NO.33018: DELETED
ITEM NO.33019: Supply and erection of class‘B’ G.I.Pipe with bends, accessories etc.
The item price includes labour & cost of cost of G.I.Pipe class' B', ISI marked with bends, accessories etc.
ITEM NO.33020: Supply, installation, testing and commissioning of automatic changeover panel complete.
The item price includes labour & cost of all materials including cost of automatic changeover panel complete as per RDSO specification No.TI/SPC/PSI/CLS/0023 with amendment No.3 dated 21.03.07 or latest, connections as required. Note: Make of panel shall be on the approved list of manufacturers issued by RDSO/Lucknow.
ITEM NO.33021: ELECTRIFICATION OF FOB
The item price includes labour & cost of all materials required to electrify the FOB complete with G.I.pipe pole with bracket of
suitable length and diameter, luminary with lamp, suitable connection to the earth with GI wire M.S. junction box, connection with
1.5 sq.mm, FR PVC insulated, single core, copper conductor cable etc. Pole shall be clamped with FOB structure with clamps
manufactured with galvanized MS flat 50x50x6mm, Nut & bolts 16 mm dia at not less than two locations.
Junction box shall be Double door, weather proof (degree of protection not less than IP 54) complete with MCB 6 amps, copper
bus bars 100A for looping 4 core 3 nos. LT cables , as required. Payment for Earthing shall be covered under relevant BOQ Item.
The price includes following scale of fittings:
SCALE OF FITTINGS
Details ‗B‘class, ISI marked 50mm dia ,3.5
meters long G.I.pipe pole complete
with bracket
G.I.Flat clamp of
50x50x6mm with G.I.bolts &
nuts etc
STL Jn. box EE
Quantity
1No.
2 Nos. 1No. 1No. 1No.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 22 of 40
Abbreviations
STL 2X24W street light T5 luminary complete with T5 tube OR CFL fitting with CFL. Luminary shall be powder
coated die-cast aluminium housing, pot optics reflector with full glass cover, accessories for 85W CFL
similar to Bajaj Cat Ref No BGEST 85 RF CFL FG E40 as required by Railway.
Jn. Box M.S. junction box (1-phase 230 volts) complete with wiring including following:-
MCB SP 6 A
4 Nos. 100A copper bus bars for looping 3 cables
EE Connection to earthing system with GI wire
ITEM NO.33022: Supply, installation, testing and commissioning of 100/250/500 KVA Power Distribution
Transformer, fencing and foundation
The item price includes labour & cost of all materials including cost of Transformer, erection testing and commissioning as per
standard code of practice.
Extra payment shall be made for construction of foundation for transformer, providing fencing enclosure and Iron Gate (if
directed by the employer).
Requirements shall be as per details given here under:-
(i) Foundation
M10 grade cement concrete foundation shall be constructed with 20 mm coarse aggregate The size of foundation shall be as
per approved drawing based on size of transformer but shall not be less than 2 x1.5 mt (Length x breadth) and 600mm above
ground level duly plastered and finished surface. Curing shall be done as per code applicable. Excavation shall be done
complying with Code of Safety as per IS 3764/1992(Latest Version).
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 23 of 40
(ii) Fencing
Fabrication of enclosure for housing transformer shall be made in rectangular formation as required with M.S. Angle iron
50x50x8mm spaced at about 2 meters and 12 SWG GI wire mesh GI wire shall be cut according to size and welded with the
angle frame. MS strip not less than 15x3mm size shall be provided and welded above GI wire along the angle frame to hold the
GI wire mesh. Height of enclosure shall be 2 meter above ground level. The portion of MS angle to be grouted in foundation
shall be 500mm.
The fencing panels shall be erected on foundation constructed of size 200mmx200mmx500mm deep with cement, & concrete of
M10 grade.
(iii ) Iron Gate
Iron gate shall be fabricated with 50mm x 50mm x 8mm MS angle iron frame with iron grill etc.as approved. The size of the gate shall be 2mt (height) x 3.5mt (width ) and fabricated in two parts of 1.75 mt each. Gate shall be provided with sliding Lockable bolt with Pad lock. Gate shall be fixed on channels of size not less than100x50mm, weighing 7.90 Kg per meter with bolts & Nuts and welded. Channels shall be erected on foundation constructed of size 300mmx300mmx500mm deep with cement, concrete M10 grade Complete enclosure including Gate and angles (except galvanized portion) shall be painted with approved shade enamel paint over two coats of red oxide primer. Installation shall be as per IS 10028 (Pt. II/1981) Latest Version.
Drawing of the enclosure with Iron Gate etc. shall be got approved from the Engineer.
ITEM NO.33023: Supply, installation, testing and commissioning of 3 pole 11 KV, 400 amps Gang Operated
Switch complete with drop out fuses etc.
The item price includes labour & cost of all materials including cost of 3 poles 11 KV, 400amps. Gang Operated Switch complete
with drop out fuses, operation system, clamps, connections with ACSR conductor, sleeves, etc. as required. All the materials
used for manufacturing Gang Operated Switch shall conform to IS-2544, IS-5340 (Part-III) and IS-9921 (Part-I to V).
ITEM NO.33024: Supply, installation, testing and commissioning of 11 KV 3 Panel HT Vacuum Circuit Breaker
board and end termination etc.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 24 of 40
The item price includes labour & cost of all material including cost of 11 KV 3 Panel (one incoming and two outgoings) HT
VCB board, conforming to IS:13118/1991 & IS:3427/97, erection, testing, commissioning as per RVNL specifications. VCB panel
shall be 11kV, 350MVA, 630 Amps, draw out type, manually operated, 3 panel HT VCB board comprising of 1 No. Incoming: 3
Pole, Vacuum Circuit Breaker complete with PT, relays, electronic metering devices including ammeter, voltmeter, frequency
meter, power factor meter and trivector meter (with 30 minutes integration) for maximum demand indicator of suitable range for
unbalanced loads, clustered LED type indication lights, double ratio copper wound current transformer (ratio 80/40/5A -- for
500KVA & 60/30/5A for 250 KVA) and 2 Nos. Outgoing: 3 Pole, Vacuum Circuit Breaker complete with relays, Digital Ammeter,
LED type Indication light, double ratio copper wound current transformer ( ratio 60/30/5A -- for 500KVA & 30/15/5A for 250 KVA)
complete.
ITEM NO.33025 & 33026: Supply, installation, testing and commissioning of LT Switch board.
The item price includes labour & cost of all material including cost of LT Switch board, erection, connections of cables, testing,
and commissioning etc. as per RVNL specifications. LT panel shall be cubical type, floor mounted, dust & vermin proof, multi-tier
construction, fabricated with 2mm thick CRCA sheet with base MS channel 100x50x7.5mm (nominal size), and powder coated.
The LT switchboard shall conform to IS:8623 (latest version) and shall be suitable for operation on 3 phase, 4 wire, 415 volt, AC
supply system. The switch board shall be complete with inter connections, instrument connections with copper conductor cable,
copper bus bars, front operated switchgears, selector switches, ammeter, voltmeter etc. on each incoming and ammeter on each
outgoing with LED type indication lights, cable glands, earthing studs etc. Each panel shall be in segregated compartment.
ITEM NO.33027 : DELETED
ITEM NO.33028 : DELETED
ITEM NO.33029: Supply, installation, testing and commissioning of safety items in the substation.
The item price shall cover cost of fire extinguishing equipments (ISI marked), Rubber mat (ISI marked), GI fire buckets filled with
dry sand held on free standing steel stand, First aid box with medicines (ISI marked) and associated materials, Shock treatment
chart suitably laminated on aluminium frame, schematic diagram of HT & LT installation & transformer data on white hylem sheet
with aluminium frame & fixing/providing in the sub-station area as directed by Engineer-in-charge of the work at site.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 25 of 40
Stand for holding of fire buckets shall be free standing, manufactured with MS angle frame 50x50x6mm with base angle frame,
shade and hanging arrangements for buckets as per approved drawing.
Details of items are as under:
i) Fire extinguisher, dry chemical powder type (ISI marked) suitable for electric fire,10kg capacity - 2 Nos
ii) Rubber mat (ISI marked) non-skid type suitable for 11kV AC supply of size 3600x1000x25mm - 2 nos
iii) 6 nos. GI fire buckets of 10 Ltrs. capacity (24 gauge) duly fitted on MS angle 50x50x6mm stand, shade and filled
with clean dry ordinary sand -1set
iv) First Aid Box (ISI marked) complete with medicines of approved make - 1 set
v) Electric shock treatment chart (large size) with aluminum frame and laminated as approved. - 2 Nos.
vi) 11kV/415 Volt danger plates conforming to relevant IS. - 8 Nos.
vii) Schematic diagram of HT/LT installation on white hylem sheet with aluminium frame of size 1200x600 mm. computer printed and suitably laminated - 1 No.
viii) Data of transformer on white hylum sheet with aluminum frame of size 900x600mm. - 2 Nos
ITEM NO. 33030: Supply, installation, testing & commissioning of DG set with acoustic enclosure with all
other accessories etc.
The item price includes labour & cost of all materials including cost of DG set with acoustic enclosure , AMF panel and all other
accessories, construction of plinth with materials as per OEM recommendations and approved drawing, first filling of lubricating
oil, supply of High speed Diesel oil required for testing, commissioning at site etc as per details given in RVNL specifications. DG
set shall be complete with diesel engine, copper wound alternator, battery set, anti-vibration pads, fuel tank and all other
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 26 of 40
accessories/equipments/protective devices etc and AMF control panel conforming to relevant IS, fabricated with CRCA, 16 SWG
sheet, powder coated and comprising of incoming 4 pole, MCCB 50kA, copper bus-bars, 4 pole, heavy duty contactors,
multifunction panel meter for display of current and voltage on phases and lines, power factor, frequency, kWH, MD etc, LED
indications lights including connections with single core 1.1 kV grade LT XLPE insulated copper conductor control cable
between LT panel, AMF panel and alternator for auto and manual operation etc.
ITEM NO. 33031: Supply, installation, testing and commissioning of 125 KVAR APFC Panel. The item price includes Supply, erection, testing & commissioning of 125 kVAR (10x12.5) Automatic Power Factor Controller panel (capacitor bank) complete with low loss capacitors similar to MD-XL type of L&T make, 250 amp MCCB incomer (Ics=100%Icu), with auto and manual option, suitable for 3 phase, 415 Volt, 50 Hz AC supply & switching ratio1:2:3:4, conforming to relevant IS (latest version). APFC Panel shall be similar to L&T make cat.ref.A1256A10CMM. APFC panel shall be connected with the main panel as per site requirement. Cable for providing connections are payable under relevant BOQ item.
ITEM NO.33032: Earthing with 3 meter long, 50 mm dia G.I. Pipe class 'B' earthing electrode:
The item price includes labour & cost of all materials including cost of GI pipe, masonry enclosure, cover plate with lifting handle, charcoal/coke and salt, etc.
Earthing shall be in conformity to IS 3043/1987 (Latest Version) and as per approved drawing. Excavation shall be done
complying with Code of Safety as per IS 3764/1992(Latest Version). Earth resistance shall not be greater than 5 ohm in normal
soil and 8 ohm in rocky area.
ITEM NO. 33033 Earthing with 600mmx600mmx6mm thick G.I. earth plate
The item price includes labour & cost of all material including cost of supply of GI earth Plate, masonry enclosure, cover plate
with lifting handle, G. I. watering pipe, charcoal or coke and salt etc.The price shall also cover erection including digging of
earth pit in any kind of soil at the specified location. The work shall also cover the earth treated to obtain earth resistance of less
than 1 ohm. Connection of earth electrode should be made by providing GI clamps nuts, bolts.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 27 of 40
Work shall be in conformity to IS 3043/1987 (Latest Version) and as per approved drawing. Excavation shall be done complying with Code of Safety as per IS 3764/1992. Earth resistance shall not be greater than 1 ohm in normal soil and 2 ohm in rocky area. Payment of G.I.strips to be laid for connections are payable under relevant BOQ item
ITEM NO. 33034 : Earthing with 600mmx600mmx3mm thick copper plate earth plate
The item price includes labour & cost of all material including cost of supply of copper earth Plate, masonry enclosure, cover
plate with lifting handle, G. I. watering pipe, charcoal or coke and salt etc. The price shall also cover erection including digging
of earth pit in any kind of soil at the specified location. The work shall also cover the earth treated to obtain earth resistance of
less than 1 ohm. Connection of earth electrode should be made by providing cadmium plated brass bolts & nuts. Earth resistance
shall not be greater than 1 ohm in normal soil and 2 ohm in rocky area.
Work shall be in conformity to IS 3043/1987 (Latest Version) and as per approved drawing. Excavation shall be done complying
with Code of Safety as per IS 3764/1992
Payment of copper strips to be laid for connections are payable under relevant BOQ item.
ITEM NO. 33035 (i&ii): Supply and laying of G.I. strip below ground or surface/in recess.
The item price includes labour & cost of all materials including cost of G.I. strip on surface or recess or digging in ground/making
chase in wall/floor and making good the damages, connections including soldering/riveting etc as required.
ITEM NO. 33035 (iii): Supply and laying copper strip on surface or in recess or in 50 mm dia G.I. pipe
The item price includes labour & cost of all materials including cost of copper strip on surface or recess or digging in ground 0.50
meter below ground/ making suitable holding arrangements on transformer /D.G. Set end, making good the damages,
Connections of strip including soldering/riveting etc as required.
Rates for G.I.pipe are payable separately under relevant BOQ item.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 28 of 40
ITEM NO.33036: Supply, laying, testing and commissioning of LT cable.
The item price includes labour & cost of all material including cost of LT XLPE cable conforming to IS:7098/Pt I (latest version),
bricks, sand, cement, termination lugs/crimping socket, supply and erection of cable route markers of size not less than
200x150x5mm thick M.S.Plate and bolted to 40x40x6mm M.S angle iron of suitable length to hold the laid cable including fixing.
Inscription on the plate shall be as specified in RVNL tech. spec. Cable markers shall be provided as instructed by Engineer at
not more than 50 m interval and at locations where cable route is changing or cable joint provided.
In substation area, laying of cable includes construction of suitable trench. Trench shall be filled with dry sand up to 300 mm
above the cable after it is laid. ‗U‘ frame shall be manufactured with MS angle 50x50x6mm & grouted vertical in floor for holding
cable on transformer end. Cable shall be held vertical with clamps of MS flat 50x6mm at two places on frame on transformer and
panel side. Painting of U‘ frame and clamps shall be done with approved shade paint. Cables shall be terminated with LT panel &
on the transformer side with aluminium crimping sockets & tested and commissioned as required.
Rates for RCC/G.I/HDPE pipe are payable separately under relevant BOQ item.
ITEM NO.33037 (I & II) : Supply and erection of high mast system complete with accessories,
The item price includes labour & cost of Supply, erection, testing & commissioning of hot dipped galvanised (inside & outside),
16m high mast system (in two sections), complete with accessories, foundation bolts with nuts, washers, anchor plates &
templates etc. manufactured from special steel, head frame, 2-point suspension system with steel wire rope 6mm dia (7/19
construction), double drum winch, galvanised lantern carriage arrangement suitable for 9 luminaries symmetrically arranged &
control gear boxes and lighting finial etc. The mast shall have integral type power tool at the base compartment for its rais ing and
lowering operation, twin dome aviation obstruction lights with 100 watt lamp, control panel etc. High mast shall be supplied
complete with 2x400 watts MH luminaries (degree of protection IP-65) with control gear boxes, MH lamps, multi core flexible
copper conductor cable of suitable rating, connection with earthing system etc. as required.
Control panel shall consist of:
(a) 1X63 A TPN MCB for incoming supply
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 29 of 40
(b) 3X32 A SPN MCB for outgoing (50% lighting, 100% lighting, motor)
(c) Automatic timer with contactor for controlling above lights of suitable capacity.
(d) 1 no multi plug socket 16A
High mast shall be provided with fencing panel of size 2Mx2Mx1.5M in square shape for protection of erected high mast tower wherever required as directed by Engineer. The cost shall also include construction of foundation as per recommendation of manufacturer and approved drawing and its fixing arrangements etc. Note: Pipe electrode earthing is payable extra under relevant SOR.
ITEM NO 33038 (i) to (iv): Supply, laying, testing and commissioning of 33 /11 KV XLPE (E) insulated, armoured aluminium conductor cable.
The item price includes the cost of supply of cable conforming to IS:7098/Pt.II/85 and all other materials including bricks, sand and cement. The item price also includes laying of cable, , miscellaneous works such as digging of trench, provision of suitable clamps as per site requirements and testing & commissioning. Laying of cable shall cover all type of pipes, horizontally or vertically, underground, on wall or in air or under the Railway track/road. It also includes coordination for arranging shut down from state Electricity authorities and returning/ transporting of released materials to state electricity authorities. In substation area, laying of cable includes construction of suitable trench. Trench shall be filled with dry sand up to 300 mm above cable after laying. ‗U‘ frame shall be manufactured with MS angle 50x50x6mm & grouted vertical in floor for holding cab le on transformer and HT panel end. Cable shall be held vertical with clamps of MS flat 50x6mm at two places on frame on transformer and panel side. Painting of U‘ frames and clamps shall be done with approved shade paint. The cable shall be laid as per RVNL‘s technical specifications. The cost of GI/RCC/HDPE pipe and cable route markers is payable under separate BOQ items.
ITEM NO.33039 : DELETED
ITEM NO. 33040 : Supply, termination, testing & commissioning of 33 KV/11KV outdoor types, heat shrinkable
end termination kit.
The item price includes labour & cost of all materials including cost of 33KV/11KV outdoor type, heat shrinkable end termination
kit, making termination and connecting to the overhead lines.
ITEM NO.33041 : DELETED
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 30 of 40
ITEM NO 33042: Supplying and erection of pre-stressed, cement concrete (PSCC) double pole structure 9-11
meters long complete with galvanized stay set, anti climbing devices and fixing of Danger
plates on the erected pole.
The item price includes coordination with SEB/concerned authorities, labour & cost of all materials including cost of pre-
stressed, cement concrete (PSCC)/RSJ (As per site requirement) double pole structure(H-pole) 9-11 meters long, 4 nos. channel
cross arms & 2 nos cross bracing angles, clamps, bolts, nuts etc. including erection, casting of foundation , muffing etc. The item
price also includes supply and erection of galvanized stay set with 19/20 mm dia x1.8 meters long stay rod, anchor plate of size
45cm.x45cm x 7.5mm thick, thimble, stay clamp of galvanised MS flat 50 x 6 mm, turn buckle (20mmx600 mm), 7/4.00 mm dia G
I stay wire conforming to IS 2141-1968, 11KV strain insulators etc. including digging of pit, casting of foundation for poles & stays
with cement, concrete M10 grade and refilling, supply and erection of anti climbing devices, and danger plates on the erected
poles. Above items are for guidelines purpose. The entire work has to be done in coordination and as per standards of concerned
State Electricity Board.
ITEM NO. 33043:Supply and erection of 11 KV Porcelain Disc insulators complete with galvanized iron
hardware etc. including terminating with 11KV/ 33 KV overhead conductors as required.
The item price includes labour & cost of all materials including cost of 11 KV porcelain Disc insulators complete with galvanized
iron hardware, terminations with overhead with PG clamps, dismantling of materials transporting and handing over to concerned
authorities wherever required, etc.
ITEM NO. 33044: (i): Supply and laying of RCC Hume pipe under the Railway track /Road.
The item price includes labour & cost of all materials including cost of RCC Hume pipe, ISI marked, NP-4 class, digging of trench,
laying of pipe and back filling of trench with excavated earth etc.
Prior to start of excavation works under track/road, proper permission shall be obtained from the concerned authorities.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 31 of 40
ITEM NO. 33044 (ii): Supply and laying RCC Hume pipe under the Railway tracks with trench less method.
The item price includes labour & cost of all material including cost of RCC Hume pipe ISI marked, NP-4 class, making trench with
trenchless method with suitable machines etc and making good the damages..
Prior to start of works, proper permission shall be obtained from the concerned authorities.
Due care should be taken to avoid damage to tracks alignment, existing cables, pipes or other such installations during Drilling/Boring. Horizontal distance of the proposed trench from the existing and proposed electric mast shall not be less than
5.0 meters and shall be away from the track joints.
ITEM NO. 33045 (I & II):Supply, installation, testing & commissioning of Submersible pump set, control panel
etc
The item price includes labour & cost of all material including cost of Submersible pump set ISI marked and min 3 star energy
rating with control panel, cable etc suitable for supplying water at required head and discharge as per site conditions and as
directed by Engineer. The horse power of the motor is approximate. Suitable motor has to be installed keeping in view the site
conditions. However, all items required for the safe and efficient operation whether stated or not, shall be deemed to be included.
Control panel shall be wall mounted cubicle type, dust & vermin proof, suitable for operation on 415 volts AC supply system, with
degree of protection not less than IP 54, fabricated with 16SWG thick CRCA sheet steel, duly powder coated.
Details of accessories etc are as under:-
1 Flat, water submersible, 3 core cable of size as recommended by the manufacturer and of the required length.
2 Cable ties for clamping of flat cable to pipe at every 1 mtr interval through out the length.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 32 of 40
3 Two pairs of MS suspension clamps made of suitable size of MS flat - 1 set.
4 Full way valve of suitable size ISI mark - 1 No.
5 Pressure gauge of required capacity - 1 No.
6 Bore cover - 1 No.
7 GI bend of suitable size - as required
8 BCH/L&T make Cubicle type, weather proof control panel with degree of protection not less than IP54, complete with the following :-
i) TPN MCB 32A 10kA - 1 No.
ii) Direct On Line starter (DOL) suitable to the above - 1 No.
iii) Suitable pump set measurement and protection system as approved by engineer - 1 set
iv) MINILEC current based dry run protection - 1 No.
v) Suitable capacitors to improve PF to min 0.99.
ITEM NO. 33046:Co-ordination/ Liaisoning and chasing with State Electricity Board authorities for availing
New Electric Connection / augmentation of load/modification of crossings etc.
The item price includes cost for Co-ordination/Liasoning /chasing with State Electricity Board authorities for various activities
involved for availing new connections, augmentation of loads, including collection of estimates for New connections, additional
load & crossings modifications, arranging payment from RVNL, depositing payment to SEB's authority, release of load & other
connected works etc.as required.
Note: Payments made for application forms will be reimbursed by RVNL on proof of documents.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 33 of 40
ITEM NO. 33047: Design and preparation of working & completion drawings of the installations.
The item price includes cost for design of electrical works and preparation of working & completion drawings of the installat ions
covered under general electrical services work of the complete project including internal electrification of quarters, level
crossings, station buildings, offices, buildings, Power line crossings, Power supply distribution arrangements of stations with
platform lightings, sub stations, Electrification of Sub stations building, etc as required on Auto Cad & arranging approval from
competent authority.
On award of contract, survey of all the installations (Excluding Power line crossings which are covered under other BOQ item)
shall be carried out and drawings indicating existing & proposed works, schematic layout /arrangements etc. shall be prepared on
Auto Cad based on Zonal Railway‘s and SEB‘s norms & requirements and shall be got approved from the competent authorities
i.e. RVNL/Zonal Railways/SEB‘s etc. as required. All the drawings shall be speaking with conventional signs and symbols.
After completion of entire work, as executed drawings shall be prepared and supplied while handing over the completed works to
the Zonal Railways.
Design and Drawings will be the property of Railways.
Following drawings shall be prepared and submitted.
WORKING DRAWINGS
1 Soft Copy One set of each drawing prepared on Autocad.
2 Hard Copy Three set of each drawing of not less than A-3 size on RTF (Re-producible Tracing Film) and four
sets on paper
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 34 of 40
COMPLETION DRAWINGS
1 Soft Copy One set of each drawing prepared on Autocad.
2 Hard Copy Three set of each drawing of not less than A-3 size on RTF (Re-producible Tracing Film) and four
sets on paper.
NOTES:
1) Drawing for all HT installations are to be got approved from the Chief Electrical Engineer of the zonal railway in his capacity as
Electrical Inspector to Govt.of India.
2) Drawings for LT/11kV/33kV crossings of State Utility Company, that are being modified, are to be got approved from the
concerned Utility Company, prior to taking up the work.
ITEM NO. 33048 : Conducting check survey for the existing LT, HT and EHT Power line Electrical crossings on
the section and measurements of clearances to identify modification required/not required
The item price includes cost for conducting check survey of complete section for all the existing LT, HT and EHT Power line Electrical crossings, power lines running parallel to track from the proposed track route and requiring modification keeping in view Regulations for Electrical crossing of Railway Track 1987 and IRSOD-2004 with latest amendments , measurements of horizontal distances of structures (up to next two structures on each side) from the existing & proposed tracks etc, vertical clearances of lowest conductors & guard wires from existing & proposed rail level, angle of crossings, height and type of towers/poles, preparation of ―list of crossings requiring modification‖ & ― list of crossings not requiring modifications‖ etc. (Height/ clearances shall be accurate with zero tolerances) Measurements shall be recorded on a format as approved and be submitted considering all aspects including details required as indicated above. Proposal for modification arrangement of infringing power line crossing shall also be submitted.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 35 of 40
ITEM NO. 33049 : Supply, erection, testing & commissioning of outdoor type, single side and double side
Glow sign board /Pictorial signage board with suspension/ mounting arrangement. The item price includes Supply, installation, testing & commissioning of outdoor type, single side, /Double side Glow sign
boards/Pictorial signage boards with suspension /side mounting/wall mounting type arrangements as required, complete
including internal wiring with 2x1.5sq mm FR PVC insulated, multistrand, copper conductor single core cable on surface PVC
conduit, earthing with 1.5 sq mm FR PVC insulated multi strand copper conductor single core cable conforming to IS 694(latest
version) etc, acrylic sheet of thickness not less than 4mm on front side, G.I /Aluminium Sheet of 24 SWG on all 5 / 4 sides with
louvers etc.as required. Depth of board shall not be less than 200mm. Erection arrangement shall be as approved by Railways.
Matter to be written / displayed on signboards shall be got approved before manufacturing of board. Glow sign board shall have
degree of protection not less than IP 54.
Prewired 1x28 watts T-5 surface type Luminary complete with electronic ballast etc. shall be provided. Provision of Nos. of
luminary shall be based on one No.28 watts T-5, surface type luminary per 8 Sq. ft area.
Note: 1. Boards of smaller dimensions/area which may not accommodate 28 watt luminary shall be provided with 1x14 watt luminary per 4 sq.feet area.
2. Payment for Double sided glow sign board shall be made @ 150% of the total rate of single sided glow sign boards.
Wiring shall conform to relevant IS and code of practice as applicable.
ITEM NO. 33050: Supply, installation, testing & commissioning of Silicon rectifier battery charging set 200
Amps capacity including connections.
The item price includes labour & cost of all materials including cost of battery charging set as per RVNL tech specifications.
Payment for L.T. cable shall be made under relevant BOQ item. .
ITEM NO. 33051: Supply, erection, testing and commissioning of weather proof, outdoor type, dust and
vermin, floor mounted, 110 volts battery charging point.
110 V DC battery charging points shall be manufactured as per RVNL technical specification OR as per approved Drawing of
Zonal Railway / RVNL.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 36 of 40
The item price includes labour & cost of all material including cost of Fabrication, supply, installation, testing and commissioning
of cubicle type, weather proof, outdoor type, dust & vermin proof, 110 volts Battery charging point conforming to IS 8623 (latest
version) with degree of protection not less than IP54. Battery Charging point shall be suitable for operation on 150 volts DC
supply system and fabricated with 14 SWG galvanised MS sheet, M.S. channel size 100x50mm (weight 7.914kg/metre)
1200mm long, powder coated, inter-connections with single core, PVC insulated, multi stranded, copper conductor cable of size
10 sqmm, 3 nos. aluminum bus bar of size 25x10mm, complete with one no. MCB DP 63 Amps (DC series) 10kA, including
vertical grouting of channel 300mm deep in ground for erection with cement concrete M10 grade as per standard drawing of
zonal railway/as approved by the Engineer. .
ITEM NO. 33052: Supply, erection, testing & commissioning of weather proof, dust & vermin proof, Pre- cooling point The item price includes labour & cost of all material including cost of Fabrication, supply, installation, testing and commissioning
of cubicle type, weather proof, outdoor type, dust & vermin proof, pre- cooling point conforming to IS 8623 (latest version) with
degree of protection not less than IP54. Pre-cooling point shall be manufactured with 3.15mm CRCA sheet with 4 pedestals (on
corners) of M.S. angle size 65x65x8mm (900mm long) with base frame of M.S. angle size 40x40x5mm, duly powder coated
including vertical grouting of MS. angles 300mm deep in ground for erection with cement concrete M10 grade as per standard
drawing of zonal railway/as approved by the Engineer. Pre-cooling point shall be complete including following:.
i) One no. 100 A, 4 pole, MCCB 35 kA (Fixed type ) ii) One no. 63A industrial type, iron clad 5 pin (3P +N+E) 415 V plug socket with spring locked cover. iii) One No. 32 A Industrial type iron clad 3 pin (P+N+E) 250 V plug socket with spring locked cover. iv) Batten Holder fixed on Bakelite sheet base plate with suitable lamp and controlled by 5 A piano type switch. v) 300 A Aluminium bus bar for Phases & 200 A for Neutral, with epoxy coating/ PVC colour coded sleeves. vi) Cable entry glands of suitable size vi) LED indication lights. The connections from bus bars to MCCB and from MCCB to the feeding terminal (Iron Clad Sockets) shall be done with single core, copper conductor cable of suitable rating with suitably sized galvanized MS bolts, nuts and washers.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 37 of 40
Fluorescent screen printed indication plates on the front shall be provided for clear indication of 415 Volts, AC pre-cooling point. Pre cooling points shall be manufactured as per RVNL technical specification OR as per approved Drawing of Zonal Railway /
RVNL.
ITEM NO. 33053: Dismantling of wiring installations
The item price includes cost of labour for dismantling of complete electrical/solar and wiring installations as per site conditions, stocking, accountal, transporting and handing over the released material to electrical department. Buildings, offices, sheds, gate lodges etc. infringing the new works may also require dismantling of Electrical installations. The item covers dismantling of wiring installation, lamp /tube fittings, street light fittings, fans, Distribution boards, mains, sub mains, L.T.Panel(s), solar panels and associated cables etc and other such accessories of Railway station building/service building/sheds/gate lodges etc, removal from site, transportation or shifting to new location and handing over of released materials to Electrical department as instructed and if required making temporary arrangements as per instructions of the engineer.
ITEM NO. 33054 (i): Dismantling of erected pole and its associated overhead conductor, GI wire, cross arms
brackets, insulators, Stay, luminary.
The item price includes cost of labour for dismantling of erected pole and its associated overhead conductor, GI wire, cross arms
brackets, insulators, Stay, luminary etc as are at site including stocking , transporting and handing over released material to
concerned official as instructed and if required making temporary arrangements as per instructions of the engineer.
ITEM NO. 33054 (ii): Dismantling of Sub Station Equipments.
Dismantling of Sub Station Equipments including Transformers, DG Sets, HT & LT Panels, cables, etc as are at site including
stocking , transporting and handing over to concerned official as instructed. Prior to dismantling of work, it shall be ensured that
the temporary power supply to the feeders shall be arranged to meet the requirements as per instructions of the engineer.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 38 of 40
ITEM NO. 33055 (i&II): Providing temporary wiring/cabling arrangements for lights & fans with stand by
D.G.Sets.
The item price includes labour & cost of all materials required for temporary arrangements in adequate quantity distributed over
entire station area as decided by the engineer including wiring, cabling, luminaries with lamps, Pedestal fans, cost of
consumables for replacement, deployment of staff for maintaining temporary arrangements during pre/post/during non -
interlocking period as required, arrangement of DG sets for Power supply to temporary installations including operation and
Supply of required Diesel oil, lube oil,, provision of earthing arrangement as required.
D.G. Sets including spare DG set should be of suitable capacity as decided by Engineer in charge to meet the load required
during non interlocking period.
Work of temporary wiring installation shall comply with latest code of practices and IE. Rules.
After completion of requirements of non interlocking work, installation shall be dismantled and material shall be taken away from
the site as directed by the Engineer.
NOTE: Normal power supply, if spare load is available, may be used up to sanctioned load with prior approval free of cost.
Item No.33056 (a): Supply, installation, testing and commissioning of 2.0Tonne window type A.C.unit (3 star
rating) complete with Supply and installation of Auto Voltage Corrector.
The item price includes labour & cost of Supply, installation, testing and commissioning of window type A.C.Unit ISI marked and
min 3 star energy rated conforming to IS-1391 Pt-I/1992 (amdt 1,2), complete with LCD display cordless remote (for control of
functions, on/off, timer, selecting fan speed (three speeds) and setting up of temperature), rotary compressor, 3/3 speed
cooling/fan, air ventilator, air bacteria filter, condensor (type - GOLD), suitable for 1-phase 230 ± 10% voltage AC supply including
supply & installation of 5 KVA, wall mounted, I.C. controlled electronic auto voltage corrector conforming to relevant IS (latest
version), suitable for operation on single phase 180 to 260 volts, 50 Hz incoming AC supply and output 200 to 230 volts A.C
supply, with time delay relay, voltmeter, instant start provision with push button switch, earthing etc as required.
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 39 of 40
NOTE: AC unit shall be fixed in the space available and shall be provided with the frame in approved manner (polished hard
wood or other material as approved).
Item No. 33056 (b): Supply, installation, testing, & commissioning of Split type, 1.5 Tonne Cap. AC unit (5star
rating) complete with Supply and installation of Auto Voltage Corrector.
The item price includes of Supply, installation, testing and commissioning of split type A.C.Unit ISI marked and 5 star energy
rated conforming to IS-1391 Pt-II/1992 (amdt 1), complete with LCD display, cordless remote [for control of functions, on/off,
timer, selecting fan speed (three speeds) and setting up of temperature], rotary compressor, 3/3 speed cooling/fan, air ventilator,
air bacteria filter, condensor (type - GOLD), suitable for 1-phase 230 ± 10% voltage AC supply complete with stand (as approved)
for fixing outdoor unit, provision of rubber pads below the outdoor unit, heavy duty PVC flexible pipe (ISI marked) for drain,
interconnecting cable and refrigerant copper pipes with thermal insulation, including supply & installation of 5 KVA, wall mounted,
I.C. controlled electronic auto voltage corrector conforming to relevant IS (latest version), suitable for operation on single phase
180 to 260 volts, 50 Hz incoming AC supply and output 200 to 230 volts A.C supply, with time delay relay, voltmeter, instant start
provision with push button switch, earthing etc as required.
The item price also includes labour & cost of extra copper refrigerant pipes with insulation as required (in addition to standard
length supplied with the unit), electric cable for connection etc as required
Item No.33057: SUPPLY & ERECTION OF G.I. OCTAGONAL POLE
Item price includes labour & cost of all materials including cost of G.I. octagonal pole, single/Double arm bracket, foundation etc
as per details given in RVNL tech specifications.
Item No.33058:Supply, installation, testing & commissioning of cubical type, Mast mounted, dust & vermin
proof, L.T control switch board for AT.
Item price includes supply, installation, testing & commissioning of L.T control switch board for AT. Switch board shall be cubical
type mast mouted, dust & vermin proof, conforming to IS:8623 (latest version), suitable for operation on single phase, 2 wire, 415
Railway Electrification & General Electrical Works (Explanatory Notes) for RANI-SRPJ/RE
Page 40 of 40
volt, AC supply system, fabricated with 16 SWG, CRCA sheet, powder coated and complete with inter connections with copper
conductor cable, copper bus bars in bus chamber, clustered LED type indication lights, cable glands for incoming and outgoing
clamping with mast with 50x50x6 mm MS flat clamps, earth studs etc., complete with TPN MCCB, copper busbars etc. as per
details given in RVNL tech specifications.
Item. NS -1: Supply, installation, testing & commissioning of control and distribution panel for colour light
signal.
Item price includes supply, installation, testing & commissioning of L.T control and distribution panel for colour light signalling
supply in 25 KV AC traction system as per RDSO tech. Specification No. TI/SPC/CLS/0023 ( latest amendment) for
5 KVA AT
Item NS- 2 : Supply, installation, testing & commissioning of fabricated double door distribution board for non
emergency load.
Item price includes supply, installation, testing & commissioning of fabricated double door distribution board confirming to IS
13031, IS 8623 with degree of protection not less than IP 42 aas per IS 13947/Pt. 1/1993 with power coated finish for non
emergency load with MCB‘s etc.
Item NS-3: Supply, installation, testing & commissioning of energy efficient 1x14 watt T-5 type light fitting.
Item price includes supply, installation, testing & commissioning of Lumanariry with lamp (Rod ) 1x14 watt T-5 type light
complete in all respect with clear Polycorbonate cover with high frequency warm start electronic ballast and wide input voltage
range with IP -65 protection to be fixed fitting including connection from light point with 3x1.5 sqmm FRP insulated copper
conductor single core cable etc.