Volume I-A
Operations and Maintenance Plan
PRIMARY TREATMENT SYSTEM (PTS)
OPERATING INFORMATION
Illinois Central Spring Treatment Facility
1550 W. Third Street
Bloomington, IN 47403
Prepared for:
CBS
20 Stanwix Street, 10th
Floor
Pittsburgh, PA 15222
Prepared by:
PSARA Technologies, Inc.
10925 Reed Hartman Highway, Suite 220
Cincinnati, OH 45242
May 2013
PSARA Project # 30500.69
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System ii
Illinois Central Spring Treatment Facility May 2013
Volume I-A
OPERATIONS AND MAINTENANCE PLAN
Primary Treatment System (PTS) Operating Information
Illinois Central Spring Treatment Facility
1550 W. Third Street
Bloomington, Indiana 47403
Prepared for:
CBS
20 Stanwix Street, 10th Floor
Pittsburgh, PA
15222
Prepared by:
PSARA Technologies, Inc.
10925 Reed Hartman Highway
Cincinnati, OH
45242
May 2013
PN 30500.69
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System iii
Illinois Central Spring Treatment Facility May 2013
T A B L E O F C O N T E N T S
Section 1: Introduction ................................................................................................................ 1
1.1 Operations and Maintenance Plan Organization............................................... 1
1.2 Indiana NPDES Substantive Requirements ...................................................... 2
Section 2: General Basis of Design............................................................................................. 4
Section 3: Site Work ................................................................................................................... 5
Section 4: General System Overview ......................................................................................... 6
4.1 Spring Receiving Sump .................................................................................... 6
4.2 Primary Treatment System (PTS) ..................................................................... 7
4.3 Excess Flow Treatment System (EFTS) ........................................................... 8
4.4 PTS Monitoring and Control ............................................................................ 8
4.5 PLC GUI Function Keys ................................................................................... 9
Section 5: Process Operation and Control Description ............................................................. 10
5.1 Spring Receiving Sump .................................................................................. 10
5.1.1 Auto Mode .......................................................................................... 10
5.1.1.1 Water Level .......................................................................... 10
5.1.1.2 Flow Meters ......................................................................... 11
5.1.1.3 Pressure-Indicating Transmitters ......................................... 11
5.1.1.4 Analyzers ............................................................................. 12
5.1.2 Manual Mode ...................................................................................... 12
5.2 SRS Storage Tanks ......................................................................................... 12
5.2.1 Auto Mode .......................................................................................... 12
5.2.1.1 Water Level .......................................................................... 12
5.2.1.2 Tank Drain Valves ............................................................... 13
5.2.1.3 Flow Meter ........................................................................... 14
5.2.2 Manual Mode ...................................................................................... 14
5.3 Inclined Plate Clarifier .................................................................................... 14
5.3.1 Auto Mode .......................................................................................... 14
5.3.1.1 Water Level .......................................................................... 14
5.3.1.2 Flow Meter ........................................................................... 14
5.3.2 Manual Mode ...................................................................................... 15
5.4 Process Water Floor Sump.............................................................................. 15
5.4.1 Auto Mode .......................................................................................... 15
5.4.1.1 Water Level .......................................................................... 15
5.4.1.2 Flow Meter ........................................................................... 15
5.4.2 Manual Mode ...................................................................................... 15
5.5 Wastewater Floor Sump .................................................................................. 16
5.6 Effluent/Backwash Supply Tank .................................................................... 16
5.6.1 Auto Mode .......................................................................................... 17
5.6.1.1 Water Level .......................................................................... 17
5.6.1.2 Pumps ................................................................................... 17
5.6.1.3 Flow Meter ........................................................................... 18
5.6.2 Manual Mode ...................................................................................... 18
continued
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System iv
Illinois Central Spring Treatment Facility May 2013
T A B L E O F C O N T E N T S ( C O N T I N U E D )
5.7 Filter Feed Tank .............................................................................................. 18
5.7.1 Auto Mode .......................................................................................... 18
5.7.1.1 Water Level .......................................................................... 19
5.7.1.2 Flow Meter ........................................................................... 19
5.7.2 Manual Mode ...................................................................................... 20
5.8 Multimedia Filters ........................................................................................... 20
5.8.1 Auto Mode .......................................................................................... 20
5.8.1.1 Normal Mode ....................................................................... 20
5.8.1.2 Backwash Mode ................................................................... 22
5.8.1.3 Recycle Mode (Not Installed) .............................................. 24
5.8.1.4 Analyzers (Not Installed) ..................................................... 24
5.8.2 Manual Mode ...................................................................................... 24
5.9 Bag Filters ....................................................................................................... 25
5.10 GAC Filters ..................................................................................................... 25
5.10.1 Auto Mode (Normal Mode) ................................................................ 26
5.10.2 Backwash Mode (Manual Mode) ........................................................ 26
5.10.3 GAC Vessel Change-out ..................................................................... 27
5.11 Clarifier Sludge Thickener .............................................................................. 27
5.11.1 Auto Mode .......................................................................................... 27
5.11.1.1 Water Level .......................................................................... 27
5.11.2 Manual Mode ...................................................................................... 28
5.12 GAC and Multimedia Filter Sludge Thickener ............................................... 29
5.12.1 Auto Mode .......................................................................................... 29
5.12.1.1 Water Level .......................................................................... 29
5.12.2 Manual Mode ...................................................................................... 29
5.13 Filter Press ...................................................................................................... 30
5.14 Air Compressor ............................................................................................... 30
Section 6: Process Start/Stop Conditions .................................................................................. 32
6.1 Process Feed Pumps ........................................................................................ 32
6.2 SRS Storage Tank Pumps ............................................................................... 32
6.3 Filter Feed Pumps ........................................................................................... 33
6.3.1 During Normal Operation ................................................................... 33
6.3.2 During Backwashing ........................................................................... 34
6.4 Backwash Feed Pumps ................................................................................... 34
6.5 Process Water Sump Pump ............................................................................. 35
Section 7: Process Alarm Response .......................................................................................... 36
Section 8: Standard Operating Procedures................................................................................ 37
Section 9: Sampling and Analysis ............................................................................................ 38
9.1 Sampling ......................................................................................................... 38
9.1.1 Governmental Parameters ................................................................... 38
9.1.2 Operational Parameters ....................................................................... 38
9.1.3 Methods............................................................................................... 38
continued
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System v
Illinois Central Spring Treatment Facility May 2013
T A B L E O F C O N T E N T S ( C O N T I N U E D )
9.1.3.1 Sample Collection, Preservation, and Decontamination
Procedures ............................................................................ 38
9.1.3.2 Sample Labeling Procedures................................................ 39
9.1.3.3 Sample Storage and Shipment ............................................. 39
9.1.3.4 Field Chain-of-Custody Procedures ..................................... 39
9.2 Analysis........................................................................................................... 39
9.3 Sample Parameters and Potential Locations ................................................... 40
9.3.1 PCBs and TSS ..................................................................................... 40
9.3.2 TSS Only ............................................................................................. 41
9.3.3 DO ....................................................................................................... 42
9.3.4 pH ........................................................................................................ 42
9.3.5 Turbidity and Conductivity ................................................................. 42
9.3.6 Temperature ........................................................................................ 42
9.3.7 Percent Moisture Content ................................................................... 42
9.3.8 Particle Size Distribution .................................................................... 43
Section 10: Equipment Maintenance .......................................................................................... 44
10.1 System Component Contacts .......................................................................... 44
10.2 Spare Parts ...................................................................................................... 44
10.3 Preventative Maintenance ............................................................................... 44
Section 11: Reporting Requirements .......................................................................................... 45
11.1 Routine Reporting ........................................................................................... 45
11.2 Nonroutine Reporting ..................................................................................... 45
Section 12: Contingency Plans ................................................................................................... 46
12.1 Fire and Security ............................................................................................. 46
12.2 Emergency Response ...................................................................................... 46
12.3 System Upset/Bypass ...................................................................................... 46
Section 13: As-built Record Drawings ....................................................................................... 47
List of Tables
Table 1. Storage Tank Draining Time
Table 2. Instrumentation Summary
Table 3. System Alarms
Table 4. System Component Contacts
Table 5. Equipment Maintenance – Spare Parts List
Table 6. Preventive Maintenance Schedule
Appendices
Appendix A. Standard Operating Procedures
Appendix B. As-Built Sump and Tank Sketches
Appendix C. Process & Instrumentation Drawings
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 1
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 1 : I N T R O D U C T I O N
1.1 OPERATIONS AND MAINTENANCE PLAN ORGANIZATION
This Operations and Maintenance (O&M) Plan is separated into 10 volumes, each contained
within a separate binder. The volumes are summarized as follows:
Volume I-A – Primary Treatment System Operating Information: This volume
describes in detail the operation, maintenance, and associated best management practices
(BMPs) for the original Primary Treatment System (PTS) completed in 2000.
Volume I-B – Excess Flow Treatment System Operating Information: This volume
describes in detail the operation, maintenance, and associated BMPs for the Excess Flow
Treatment System (EFTS) completed in 2011.
Volume II – Equipment Literature A through E: This volume contains the first binder of
equipment manufacturer operations and maintenance manuals.
Volume III – Equipment Literature F: This volume contains the second binder of
equipment manufacturer operations and maintenance manuals.
Volume IV – Equipment Literature G through N: This volume contains the third binder
of equipment manufacturer operations and maintenance manuals.
Volume V – Equipment Literature O through X: This volume contains the fourth binder
of equipment manufacturer operations and maintenance manuals.
Volume VI – Equipment Literature Y: This volume contains the fifth binder of equipment
manufacturer operations and maintenance manuals. This volume also includes PLC ladder
logic diagrams for the PTS.
Volume VII – Contractor/Vendor Submittals – Process Piping: This volume contains
process piping layout shop drawings as submitted by the mechanical contractor.
Volume VIII – Contractor/Vendor Submittals – Process Equipment: This volume
contains process equipment vendor shop drawings.
Volume IX – Contractor/Vendor Submittals – Electrical, Plumbing, HVAC: This
volume contains submittals by the electrical and mechanical contractors.
Volumes X-XI – Excess Flow Treatment System (EFTS) Equipment Literature: These
volumes contain equipment manufacturer operations and maintenance manuals for the EFTS,
including PLC ladder logic diagrams.
This O&M Plan is a dynamic document that will be updated as necessary to reflect significant
changes in operating conditions, equipment, and/or procedures.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 2
Illinois Central Spring Treatment Facility May 2013
1.2 INDIANA NPDES SUBSTANTIVE REQUIREMENTS
In accordance with the Consent Decree Amendment (CDA), this O&M plan has been expanded
to include the State of Indiana National Pollution Discharge Elimination System (NPDES)
substantive requirements. The treatment facility does not need to obtain an NPDES permit
because onsite remedial actions are specifically exempt from such administrative requirements
under Section 121(e) of CERCLA, 42 U.S.C. 96219(e). Nevertheless, certain regulations
enacted by the State of Indiana under its federally approved NPDES program are relevant and
appropriate to discharges from the facility.
The following is a summary of applicable or relevant and appropriate requirements (ARARs)
and how they are incorporated into this O&M plan:
Surface Water Quality Criteria for Specific Substances – 327 IAC 2-1-6, Table 1:
The State of Indiana has stated in correspondence that it sets an effluent limit of 0.3 ppb for
polychlorinated biphenyls (PCBs) discharged by treatment plants into waters other than the
Great Lakes system. Notwithstanding the designation of 327 IAC 2-1-6, Table 1, as an
ARAR, only the discharge limit of 0.3 ppb for PCBs is designated as a performance standard.
Conditions Applicable to All Permits – 327 IAC 5-2-8 (3), (5) - (14):
327 IAC 5-2-8 (3) regarding adverse environmental impacts – The procedures and practices
outlined in this plan are intended to minimize or address any adverse environmental impacts
resulting from noncompliance.
327 IAC 5-2-8 (5) regarding effluent standard changes – The discharge limit of 0.3 ppb for
PCBs is the only applicable effluent standard at this time.
327 IAC 5-2-8 (6) regarding rights and privileges – No property rights or exclusive
privileges are assumed in conjunction with system operation.
327 IAC 5-2-8 (7) regarding government access – The U.S. Environmental Protection
Agency (USEPA), the Indiana Department of Environmental Management (IDEM), and
authorized representatives will be provided access to the treatment facility for records
review, inspections, or testing as required.
327 IAC 5-2-8 (8) regarding system operation and maintenance – This plan establishes the
procedures and practices for maintaining the treatment facility in good working order and
operating it efficiently.
327 IAC 5-2-8 (9) regarding general monitoring, recordkeeping, and reporting require-
ments – Routine monitoring and recordkeeping practices are summarized in Section 9.0 of
this plan. Routine reporting practices are summarized in Section 11.1.
327 IAC 5-2-8 (10) regarding nonroutine reporting requirements – Nonroutine reporting
practices are summarized in Section 11.2 of this plan.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 3
Illinois Central Spring Treatment Facility May 2013
327 IAC 5-2-8 (11) regarding bypass provisions – This plan outlines system design features
that minimize the potential for bypass. Section 11.2 of this plan summarizes notification
practices for bypass conditions, whereas Section 12.3 summarizes response practices and
other requirements.
327 IAC 5-2-8 (12) regarding upset provisions – This plan outlines system design features
that minimize the potential for upset conditions. Section 12.3 summarizes response practices
and other requirements for system upset conditions.
327 IAC 5-2-8 (13) regarding enforcement action defense – It is understood that halting
operation of the treatment system will not be considered an appropriate defense for
maintaining compliance in the event of an enforcement action.
327 IAC 5-2-8 (14) regarding signatures and certifications – Appropriate signatures and
certifications will continue to be provided with all submittals to USEPA and/or IDEM.
Considerations in the Calculation and Specification of Effluent Limitations – 327 IAC
5-2-11 (a) (1), (2), (3), (4), (5)(C); (c)(2); (d), (e), (f), (g), (h)
The discharge limit of 0.3 ppb for PCBs is the only applicable effluent standard at this time.
Establishment of Water Quality-based Effluent Limitations for Dischargers Not
Discharging Water to Within the Great Lakes System – 327 IAC 5-2-11.1 (a), (b), (d),
(f), (g), (h)
The discharge limit of 0.3 ppb for PCBs is the only applicable effluent standard at this time.
Applicability of Best Management Practices (BMPs) – 327 IAC 5-9-2 (a) – (j)
The only pollutants currently handled and/or potentially discharged from this system are
PCBs and suspended solids. This plan outlines system design features that minimize the
potential for discharge of PCBs into waters of the State. BMPs for system operation and
maintenance are established throughout this O&M plan via standard operating procedures
(SOPs), maintenance schedules, etc. Subsequently, this plan is intended to meet the
requirement for a BMP program in 327 IAC 5-9-2. Additional BMPs will be developed as
needed to address the use of any future maintenance chemicals that could result in other
pollutants being discharged.
Monitoring – 327 IAC 5-2-13 (a), (c), (d), (e), (f)
System monitoring practices are summarized in Section 9.0 of this plan.
Permit Modification, Revocation, Reissuance, and Termination – 327 IAC 5-2-16 (c)(2),
(d)(2)
This O&M plan will be revised as necessary if the conditions specified in 327 IAC 5-2-16
(c)(2) or (d)(2) regarding more stringent effluent limitations and/or requirements become
applicable in the future.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 4
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 2 : G E N E R A L B A S I S O F D E S I G N
Earth Tech (now AECOM) designed the original treatment system. The most important
elements that formed the basis of design were the following assumptions: the plant would be
designed to address a simulated 25yr-6hr (hereinafter 25-year) storm event; the solids loading to
the plant during the first flush of the storm event would be reasonably managed by the plant; and
4 acre-feet of storage would be provided with at least two independent structures (tanks).
Earth Tech modeled a 25-year storm event based on a SCS unit hydrograph that was modified to
mirror data collected at the location during lesser storm events. The change in the hydrograph’s
configuration to mirror actual storm events was believed to be necessary due to the potential of
storage, pressure conduits, and other such features that may be unique to the karst features.
Earth Tech’s review of the data indicated that the majority of the total suspended solids (TSS) is
generated during hours 6 through 18 within a 36-hour elevated flow period as a result of the
6-hour storm event. Earth Tech therefore selected this 12-hour design period for managing
solids and the total 4 acre-feet storage volume to maximize capture of TSS and capture peak TSS
concentrations. The modeled 25-year storm event was used to develop a system TSS mass
balance.
During a storm event, the primary treatment system is capable of processing at a maximum flow
of 1,000 gpm. The storage tanks will fill at a nominal rate of 2,500 or 5,000 gpm depending on
the developed head and number of pumps online. Once the capacity of the Spring Receiving
Sump (SRS) tanks has been exceeded, they will overflow to the Excess Flow Treatment System
(EFTS, completed in March of 2011). Should an event exceed the peak discharge of the SRS
pumps (6,000 gpm combined), the overflow will bypass through the SRS directly to the original
streambed. This potential bypass condition is addressed in Section 12.3 of this plan.
After the elevated spring flows subside to below 900 gpm, the SRS tanks can be drained back to
the SRS. A spreadsheet detailing a singular event of the storage tanks draining back to the spring
receiving sump is provided as Table 1. The design event is based on the premise that the
pumping/sump capacity is sufficient to handle the peak flow of the storm event and that the SRS
storage tanks can be drained within 7 days for the given design event (25yr-6hr).
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 5
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 3 : S I T E W O R K
Substantial site work was undertaken to provide two access roads, one to the north side of the
site where the spring surfaces, and one that serves to access the process treatment building and
SRS located at the south side of the site. Substantial grading occurred on the south side to
accommodate the treatment building and tanks.
Additional site work was completed in 2010 to address the Swallow Hole and Quarry Springs
area immediately south of the treatment building. Aside from contaminated soils/sediment
removal and disposal, the Illinois Central Spring Treatment Facility (ICSTF) effluent line was
extended to downstream of both areas to prevent potential recontamination of clean effluent
water.
Additional site work was also completed in 2010 at the Illinois Central Emergence (ICE) area to
improve the efficiency of the existing collection system and to facilitate better separation of
noncontaminated surface runoff.
The plant is supplied with electricity to power the process components, as well as to provide
lighting, air conditioning in the office, heating in the SRS building, and automated ventilation in
both buildings. Natural gas is supplied to heat the process building and to supply hot water.
Potable water and sewer are supplied for the facility and for limited process needs.
Communications lines are provided for personal computer (PC) connections, phones including
an auto-dialer (MMI), faxes, fire alarms, and data transfer.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 6
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 4 : G E N E R A L S Y S T E M O V E R V I E W
Earth Tech designed the PTS to treat TSS and PCBs. The process may remove other
constituents within the waste steam, but this function is not a design component. During design,
a single sample was collected and tested for typical landfill pollutants and discharges that could
originate from such facilities. The test results from this sample were reviewed for possible
interferences with the various processes. No specific or general concerns were identified.
On the north side of the site, north of the railroad track currently owned by the Indiana Railroad
Company, a berm was installed to separate uncontaminated surface runoff from contaminated
spring water. A culvert was installed under this railroad track in two locations. One culvert was
placed at the mouth of the spring to direct contaminated water to the SRS, and a second culvert
was located just east of the berm to allow uncontaminated surface runoff to bypass the treatment
system.
4.1 SPRING RECEIVING SUMP
Contaminated spring water enters the spring receiving sump (SRS) from a 24-in.-diameter
culvert that was placed near the mouth of the spring. From the SRS, water can be pumped to the
treatment process at the preset rates of 200 gpm, 800 gpm, or 1,000 gpm. As a practical matter
and within each pump’s capacity, the flow rate can be changed to any combination of flows
using the variable frequency drives. Water can be simultaneously pumped to the SRS storage
tanks from a separate bank of three pumps at a rate of 2,500 gpm for a single pump or 5,000 gpm
using two pumps. The two storage tanks are nominally sized to hold 644,740 gallons
(approximately 2 acre-feet) of water each. Water stored in the storage tanks can be drained back
to the SRS when a storm event has diminished to the point where the total flow into the sump is
below an operator-defined rate (typically 900 gpm or less). The SRS tanks also act as passive
clarifiers for settleable solids. Design parameters for the SRS tanks are based only on the
holding capacity without the benefit of any trapping efficiency. Initial results indicated that the
tanks are capable of retaining some PCB-laden sediments (settleable solids). In the event the
flow rates into the SRS exceed 6,000 gpm, spring water will overflow the SRS and pass
downstream as untreated flow. All process pumps in the treatment system, including the SRS
pumps, have redundant control systems (i.e., ultrasonic level transmitters and level switches) that
are digitally controlled.
In order to purge the SRS or the SRS tanks of settled sediments, a direct bypass was installed
from the SRS to Thickener #1 (T-301A). The bypass would take heavily laden sediment (high
solids > 2%) directly to the thickener. There is no need to process this waste stream through the
plant since it is already a concentrated load. The bypass operation would typically be scheduled
during low flow events when the system is capable of transporting up to 200 gpm.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 7
Illinois Central Spring Treatment Facility May 2013
4.2 PRIMARY TREATMENT SYSTEM (PTS)
The process flow for the entire treatment system is diagrammed in the as-built piping and
instrumentation drawings included in Appendix C. In order to treat spring water for TSS and
PCBs, the primary treatment system (PTS) includes clarification followed by various stages of
filtration. After passing through a clarifier, water overflows to a filter feed tank and is then
pumped through multimedia, bag, and granular activated carbon (GAC) filter vessels. The
process is driven by 300-gpm and 900-gpm pumps that are controlled based on level in the filter
feed tank. The final effluent, after GAC filtration, flows through an effluent/backwash storage
tank before discharging by gravity to an area downstream of the Quarry Springs monitoring
locations. A 1,000-gpm pump (with backups) transfers effluent from the effluent/backwash tank
to the filter feed tank for backwashing the multimedia filters (automated) and directly to the
GAC filters for GAC filter backwash (manual only operation).
Sludge from the clarifier, the multimedia filters, and the carbon vessels (during backwash) is
directed to two sludge thickeners (intended to operate in parallel) and from there to a filter press
for final dewatering. Two diaphragm pumps transfer sludge from the clarifier to the smaller of
the two thickeners (Thickener #1, T-301A). Multimedia filters are automatically backwashed
based on a differential pressure set point, with backwash water directed to the larger of the two
thickeners (Thickener #2, T-301B). All GAC filters are manually backwashed, with the
backwash water also directed to Thickener #2.
The thickeners are fitted to drain the supernatant (clarified water) from the tanks at four different
levels. With each backwash, the solids are allowed to settle and the water is decanted from the
tank when the clarity is visually observed to be acceptable. Sight glasses are fitted to the drain
manifold for this purpose. After decanting is complete, solids left in the thickeners are pumped
via diaphragm pump (with backup) to the filter press for dewatering. A lime slurry is introduced
to each thickener in order to improve the dewatering process. After each dewatering cycle, dry
filter cakes are removed from filter press and stored within a rolloff box located directly beneath
the filter press. Once the rolloff box is full (by weight), the container is removed for disposal
and then returned for reuse. The weight of dewatered sludge has been estimated to be 105 lb/ft3.
Filtrate from the filter press flows to the process floor sump where it is pumped to the filter feed
tank for processing through the treatment system. The supernatant from the thickeners is drained
to the same process sump. The entire process is designed to operate automatically except for the
following tasks:
• Bag filters must be manually changed;
• GAC filter backwash process is entirely manual;
• Filter press operation is initiated manually with the thickened backwash solids delivered
by semiautomated features. The addition of lime slurry is manually introduced to the
thickener prior to pressing. Air is used to provide a consistent batch mix.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 8
Illinois Central Spring Treatment Facility May 2013
4.3 EXCESS FLOW TREATMENT SYSTEM (EFTS)
In order to treat spring flows resulting from larger storm events, an Excess Flow Treatment
System (EFTS) was constructed in late 2010 and early 2011. This system was designed to treat
all overflows from the SRS tanks at a rate of up to 5,000 gpm. This increases the total system
capacity to 6,000 gpm. All pertinent operation and maintenance information for the EFTS is
included in Volume I-B of the O&M plan.
4.4 PTS MONITORING AND CONTROL
Operators control the PTS via a control panel and programmable logic controller (PLC) located
in the office area. A graphical user interface (GUI) monitor (and backup) is provided to enable
the operator to monitor system operation and to control system functions as necessary.
An MMI system (automated voice system) is also provided to place call-outs to operators under
alarm conditions. The transmitting units continuously transfer operating data to the PLC, which
in turn transfers data to a dedicated data PC and to the MMI. A second office PC is used to
generate necessary reports from the operating data. Hard copies of reports are maintained on
file, and both PCs are backed up weekly to an external hard drive. The external hard drive is
stored off-site at the PSARA Bloomington office.
Many of the instruments, including flow meters, level elements, pressure sensors and differential
pressure sensors, are provided with local indicators and/or transmitters. These features enable
system monitoring from the field, the control panel in the office, and remote locations. Solenoid-
operated valves, which can be opened or closed from the control panel, have local indicators to
visually observe the status of each valve. Local control of some valves is not possible without
pulling the circuit or fuse that powers the control circuitry.
A compressor is installed to provide air for carbon transfers, operation of diaphragm pumps,
mixing within the thickeners, and operation of the filter press. The operating pressure is
maintained at 100 psi.
A diesel generator was originally installed to provide backup power for the PTS, but was sized
with excess capacity for future system expansion. Based upon system operating loads, the
generator has sufficient capacity to also provide backup power for the EFTS. The generator has
user-defined limits for starting and powering the generator down. Under current settings, an
automatic throw switch will transfer power to the generator if main line power is lost for more
than 20 seconds. Once main line power has been reestablished and remains on for 15 minutes,
the automatic throw switch will transfer power back to the main line and the generator will begin
a shutdown routine. Changes to the time intervals described above may be made at the generator
panel located inside the treatment building.
Data from all process instrument transmitters are logged to the PLC and then stored on the MMI
and dedicated data PC. This data includes the date and time stamp for all records that are
maintained. This data may be transferred by various means including any electronic format that
is currently available.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 9
Illinois Central Spring Treatment Facility May 2013
The variable frequency drives (VFDs) on the pump motors are provided to ramp flows to the
prescribed rates for the purpose of improving the efficiency of the clarifier and filters. The
VFDs also prolong the life of the pumps, provide automated variable and constant flow rates,
and allow various processes to run at predefined rates for a given time. The VFDs eliminate the
need for throttling valves and also increase the pump efficiency.
4.5 PLC GUI FUNCTION KEYS
The PLC GUI has several different menu screens that show critical information about various
parts of the system. The GUI also has 21 different function keys that control access to the menu
screens and certain system functions. The following is a list of all GUI function keys and their
purpose:
Menu Keys
F9: Menu screen for SRS, SRS pumps, clarifier, and sludge pumps
F10: Menu screen for SRS storage tanks/pumps
F11: Menu screen for filter feed tank/pumps, multimedia and bag filters
F12: Menu screen for GAC filters
F13: Menu screen for sludge thickeners
F14: Menu screen for effluent/backwash tank/pumps and floor sumps/pumps
F15: Menu screen for alarms
F16: Main menu screen
Command Keys
F1-F8: Select or highlight components in each menu screen
F17: Pump/valve automatic mode
F18: Valve off
F19: Pump/valve manual mode
F20: Start pump or open valve
F21: Stop pump or close valve
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 10
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 5 : P R O C E S S O P E R A T I O N A N D C O N T R O L
D E S C R I P T I O N
The following subsections describe the sequence of operation for each system component. All
PLC analog and digital input information, including input address, scaling and set points, are
detailed in Table 2: Instrumentation Summary. PLC ladder logic is included in Volume VI.
5.1 SPRING RECEIVING SUMP
Contaminated flows to be treated are directed from the Illinois Central Spring directly into the
SRS. The sump is a below-grade concrete structure that is equipped with two different sets of
pumps: process feed pumps (200 gpm and 800 gpm) and SRS storage tank feed pumps
(2,500 gpm). Pump motors are located above-grade and are protected by a concrete block
building that also houses pump electrical components.
5.1.1 Auto Mode
When the flow into the SRS is less than 200 gpm, the 200-gpm process feed pump cycles based
on the water level in the sump and on the set points of the level element that controls the pumps.
When a rain event occurs and the flow rate exceeds 200 gpm, the 800-gpm process feed pump
also cycles. Under normal operating conditions, the total pumping rate to the treatment process
is 0, 200, or 1,000 gpm. If the pumps are manually manipulated, a flow rate of 800 gpm can be
set without adjusting the VFDs.
When flow into the SRS exceeds 1,000 gpm, a third pump cycles at a nominal rate of 2,500 gpm
and transfers water to the SRS storage tanks. Should the flow into the SRS exceed 2,500 gpm,
the second 2,500-gpm pump comes online to pump more water to the SRS storage tanks. When
the flow into the SRS exceeds 6,000 gpm, all pumps run continuously at 6,000 gpm until such
time that the spring flow rate drops below 6,000 gpm. In the unlikely event that the influent rate
exceeds 6,000 gpm, the SRS will eventually overflow. However, this condition has never been
observed during the more than ten years of operation of the plant.
Activation of the 800-gpm or 2,500-gpm pumps is indicative of a rainfall event or a malfunction
of the pumps. Normal flows are dependent on the ambient conditions, including the antecedent
moisture conditions and the time interval between rainfall events. Typical non-storm flows from
the spring vary between a low of 30 gpm to median range of 60 gpm.
5.1.1.1 Water Level
All SRS pumps and their backups are controlled by the PLC via control set points measured by a
level element and indicating transmitter (LE/LIT-200). LE/LIT-200 has “high-level” and “low-
level” alarm set points as well as “on” and “off” set points for the SRS pumps.
LE/LIT-200 has two other set points. The low set point overrides any other PLC commands and
turns off all seven pumps. The PLC then generates an alarm message on the GUI that reads
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 11
Illinois Central Spring Treatment Facility May 2013
“Low level in SRS.” At the high set point, the PLC verifies that all four primary SRS pumps are
on. If any are not, then they are turned on. The PLC then generates an alarm message on the
GUI that reads “High level in SRS.”
Two separate float switches are also installed in the SRS. The high-high float switch (LSH-200)
generates an alarm at the PLC to indicate that the SRS is overflowing. The LSH-200 set point
corresponds with the same elevation as the invert of the SRS overflow. The low-low float switch
(LSL-200) provides redundant protection to prevent the pumps from running dry. LSL-200 does
not operate when the non-VFD SRS pumps (i.e., the 2,500-gpm pumps) are placed in manual
mode. LSL-200 does operate when the VFD SRS pumps (i.e., 200- and 800-gpm pumps) are
placed in manual mode. The operator must be careful not to run the 2,500-gpm pumps dry
when operating in manual mode.
The level element LE/LIT-200 indicates locally, and in the control room, both the level of water
in the SRS (to the nearest hundredth of a foot) and the number of gallons in the main part of the
sump.
The LE/LIT-200 continuously transmits water level data to the PLC . Trending charts can be
generated by the PC, with records of this data stored for the entire operating history of the plant.
5.1.1.2 Flow Meters
There is a flow meter on the combined discharge from process feed pump P-101 and its backup
P-102 (FE/FIT-100). Similarly, there is a flow meter on the combined discharge from process
feed pump P-103 and its backup P-104 (FE/FIT-101). There is also a flow meter on the
combined discharge from SRS storage tank feed pumps P-201 and P-202 and their backup P-203
(FE/FIT-200). These flow meters are programmed to display instantaneous flow rate in gpm and
totalized flow in gallons. They indicate this data locally and remotely to the GUI via the PLC,
with the data used for both monitoring and control. During initial system startup, the VFD-
controlled motor speed required to produce the necessary discharge flow rates from the pumps
were programmed into the PLC. Manual adjustments may be necessary to increase or decrease
the drive speeds to adjust corresponding flow rates as needed.
These flow meters are also involved in a second control sequence. Their input regarding
discharge flow rate is used by the PLC, along with input from LE/LIT-200 regarding the sump
fill/empty rate, to calculate the volumetric flow rate of water into the SRS.
The PLC continuously transmits flow rate and totalized flow data to the data PC and MMI.
Charts of flow rate and totalized flow versus time can be generated by the office PC for trending
purposes. Daily flow reports are also generated by the office PC, and these records are stored for
the entire operating history of the plant (hard copy and electronic versions).
5.1.1.3 Pressure-Indicating Transmitters
There are three pressure-indicating transmitters (PIT) that serve each manifold for the respective
pump discharges (PIT-100 through PIT-200). These transducers are programmed to display
instantaneous pressure in psi. They indicate this data locally and remotely to the PLC and GUI.
This data is for monitoring only, and there is no control by the PLC based on the data. The PLC
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 12
Illinois Central Spring Treatment Facility May 2013
continuously transmits pressure data to the data PC and MMI. Trending charts can be generated
by the office PC, with records of this data stored for the entire operating history of the plant.
5.1.1.4 Analyzers
AE/AIT-200 is an in-line turbidity meter that collects a slipstream from the combined discharge
of the 200-gpm pumps to the treatment building. It indicates this data locally and remotely to the
PLC and GUI. This data is for monitoring only, and there is no control by the PLC based on the
data. The PLC continuously transmits turbidity data to the data PC and the MMI. [Note: The
transmission of data from the turbidity meter is problematic. Apparently, the transmitter for the
unit is not of sufficient quality or design to transmit the data from the SRS to the PLC. There is a
possibility that line interference due to placement may contribute to the problem. As a result, the
turbidity meter is not currently used.]
5.1.2 Manual Mode
All SRS pumps can be run manually for troubleshooting or maintenance activities. Each pump
can be isolated, and the backup pumps can be put into service by adjusting manual valves located
on the discharge of each pump and on combined discharge piping [refer to process and
instrumentation drawings (P&IDs) in Appendix C]. A 2,500-gpm pump can be used to
manually backflush another 2,500 gpm pump through discharge valve manipulation. Note: The
operator must be careful to throttle discharge flow when backflushing a 2,500-gpm pump
to avoid damaging the impeller. This should only be done to remove debris if needed after
a heavy storm event.
The SRS is inspected annually for sediment buildup and is typically cleaned every two years.
Refer to Appendix A for SOPs related to SRS maintenance activities.
5.2 SRS STORAGE TANKS
The SRS storage tanks have a capacity of 632,000 gallons each and are designed to store water
when spring flows exceed the PTS flow capacity of 1,000 gpm. The tanks are of welded-steel
panel construction with a cone-shaped bottom set inside a concrete foundation. The tanks have
protective coatings on both the interior and exterior.
5.2.1 Auto Mode
5.2.1.1 Water Level
The three SRS pumps (P-201, P-202, and P-203) discharge to the SRS storage tanks (T-201 and
T-202). The bulk storage pump system is programmed to begin transferring water to the tanks
once the influent flow rate exceeds the process pumping rate of 1,000 gpm. A maximum of two
of three pumps can operate simultaneously at any given time. The SRS tanks are configured for
parallel operation only. Either tank may be taken offline to allow for repair or inspection while
the other remains in operation or in standby. In parallel operation, the water levels are
maintained at the same elevation in both tanks including any overflow to the EFTS.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 13
Illinois Central Spring Treatment Facility May 2013
The SRS storage tank feed pumps are vertical turbine pumps that are programmed to begin
pumping once predefined water levels are exceeded in the SRS. The pumping rates are fixed and
are nominally designed to pump at 2,500 gpm for a single pump and 5,000 gpm for two pumps.
In order to exercise the pumps and maintain a uniform degree of wear, the pumps automatically
alternate between the three. When the SRS influent flow exceeds 1,000 gpm and the sump level
rises to the first set point, a single 2,500-gpm pump is automatically brought online. This pump
will be able to maintain the sump level until the SRS inflow exceeds 3,500 gpm, at which point
the level will rise to the second set point. At this level, a second pump is automatically brought
online to provide a total pumping capacity of 6,000 gpm (1,000 gpm to the plant and 5,000 gpm
to the SRS tanks). The SRS tanks will continue to receive water from one or two of these pumps
until the SRS level drops and influent flow decreases to below 1,000 gpm.
In automatic mode and once the SRS tanks are full (31.0 ft or 644,744 gallons each @ overflow),
the tanks begin to overflow to the EFTS at either 2,500 gpm or 5,000 gpm depending on pump
status. The SRS storage tank feed pumps are not fitted with VFDs and may only be adjusted by
manipulating manual valves. The operator may exercise some control over the system by
placing the pumps in manual operation, changing the valve settings, and taking a tank on- or
offline.
The SRS tanks are fitted with level elements and transmitters (LE/LIT-201 and LE/LIT-202) that
display locally and on the GUI via the PLC. They display water level in feet (to the nearest tenth
of a foot) and in gallons. The reference point for the tank level is at the top of the cone where it
meets the vertical sidewall. This corresponds to an elevation of “0 feet” relative to the SRS tank
levels.
As in the SRS, the PLC uses the data from LE/LIT-201 and LE/LIT-202 to display tank levels
and storage volumes. This data may be compared to data from flow meters to verify the
accuracy of instruments. All water entering and leaving the SRS tanks is metered. SRS tank
overflow volume is measured by the EFTS effluent flow meter.
The PLC continuously transmits water level elevation and volume data to the data PC and MMI.
Charts of volume versus time can be generated from the PC for trending purposes.
5.2.1.2 Tank Drain Valves
In the event that the SRS tanks receive water, they will continue to hold water (or overflow to the
EFTS) until the SRS influent flow rate drops below 1,000 gpm. When the flow rate drops below
900 gpm, the tanks can be drained back to the SRS through manual valve manipulation. The
SRS drain valve (ZSC 206) was originally intended to provide automatic control of SRS tank
draining; however, it is now only operated in manual mode because of functionality issues. A
butterfly valve located upstream of the ZSC 206 is left normally closed and is only opened
during the tank draining process. The SRS drain valve is then manually adjusted to achieve the
desired draining rate, as indicated by a flow meter installed in the drain line. Note: The
operator must be careful to balance the SRS tank draining rate with the calculated SRS
influent flow rate so that the combined flow does not exceed the 1,000 gpm capacity of the
PTS.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 14
Illinois Central Spring Treatment Facility May 2013
5.2.1.3 Flow Meter
There is a flow element and indicating transmitter (FE/FIT-201) installed on the drain line from
the SRS storage tanks. As described above, this flow data is used by the Operator to control the
SRS tank draining process through manual valve manipulation. The flow meter is programmed
to display instantaneous flow rate in gpm and totalized flow in gallons. The meter indicates this
data locally and transmits the data to the PLC and GUI. The PLC continuously transmits water
flow rate and totalized flow data to the data PC and MMI. Trending charts can be generated by
the office PC, with records of this data stored for the entire operating history of the plant.
5.2.2 Manual Mode
It is possible to use Hand-Off-Auto (HOA) switches to manually control the 2,500-gpm SRS
pumps that discharge to the storage tanks. The SRS tanks themselves can be managed through
manual valve changes so that the tanks can be operated together in parallel or individually. As
previously mentioned, manual draining of the SRS tanks is now standard practice.
5.3 INCLINED PLATE CLARIFIER
The inclined plate clarifier (T-101) is the first treatment component in the PTS that removes
solids and sediment. SRS process feed pumps discharge directly to the clarifier at flow rates of
200, 800, or 1,000 gpm. When the water level in the clarifier reaches the invert elevation of its
overflow pipe, clarified water overflows by gravity to the filter feed tank. Solids collect in the
bottom of the clarifier unit and are periodically transferred to sludge thickener T-301A.
5.3.1 Auto Mode
The clarifier sludge pumps (P-301, P-302) are automatically controlled by a timer within the
system PLC. The timer cycles a sludge pump on for a specific timeframe and then off for a
specific timeframe, both of which are configurable through the GUI. Refer to the Clarifier
Sludge Pump Settings SOP in Appendix A for specific guidelines on timer settings.
5.3.1.1 Water Level
The level element and level indicating transmitter (LE/LIT-100) was originally installed to
monitor clarifier water level; however, this unit was removed from service. It is not necessary
for effective operation of the clarifier, so it has never been replaced.
LSH-100 is a high-level switch that is set above the top of the pipe that overflows from the
clarifier to the filter feed tank. When the PLC notes this alarm condition, it shuts down all SRS
process feed pumps.
5.3.1.2 Flow Meter
A flow element and indicating transmitter (FE/FIT-300) is located on the discharge pipe of the
sludge pumps. It is programmed to display instantaneous flow rate in gpm and totalized flow in
gallons. It will indicate this data locally and remotely to the PLC and GUI. The PLC
continuously transmits water flow rate and totalized flow data to the data PC and MMI.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 15
Illinois Central Spring Treatment Facility May 2013
Trending charts can be generated by the office PC, with records of this data stored for the entire
operating history of the plant.
5.3.2 Manual Mode
The clarifier can be bypassed, if needed, by adjusting manual valves on the inlet side of the
clarifier. Also, each clarifier sludge pump can be isolated for maintenance or put into service as
needed by manually adjusting valves located on the inlet and discharge sides of each pump.
5.4 PROCESS WATER FLOOR SUMP
The process floor sump (S-301) has three inputs including the following: manual-only
discharges of supernatant from the thickener tanks to a floor drain; manual-only discharges of
filtrate from the filter press to a floor drain; and gravity overflows of process water from the
filter feed tank (T-102). Note that all these inputs are of process water that contains PCBs. The
sump has two outputs including an overflow back to the SRS and a pumped discharge to the
filter feed tank. A backup pump was placed in inventory at the site. The base, wiring, and
plumbing (with modification) are available for the unit or it may replace the existing installation.
5.4.1 Auto Mode
5.4.1.1 Water Level
Four level switches provide input to the PLC for automatic control of the sump discharge pump
P-309 and its backup P-310. Level switch LSL-300 turns the pump off, and LSH-300 turns the
pump on. LSLL-300 provides redundant protection against running the pump dry and turns the
pump off; it also represents an alarm condition. LSHH-300 provides redundant protection
against overflowing the sump to the SRS and also represents an alarm condition. The set point
for LSHH-300 should correspond with the invert elevation of the sump overflow to the SRS.
These four level switches are all hardwired to sump pumps P-309 and P-310.
5.4.1.2 Flow Meter
There is a flow element and flow indicating transmitter (FE/FIT-301) on the combined discharge
of the sump pumps to the filter feed tank. It is programmed to display instantaneous flow rate in
gpm and totalized flow in gallons. It indicates this data locally and remotely to the PLC and
GUI. The PLC continuously transmits water flow rate and totalized flow data to the data PC and
MMI. Trending charts can be generated by the office PC, with records of this data stored for the
entire operating history of the plant.
5.4.2 Manual Mode
The sump pumps do not have VFDs, and their throttling valves are not automated. Therefore,
the operator must use data from flow meter FE/FIT-301 to determine the pump discharge rate
and manually adjust the throttling valve as needed. Note: The maximum flow rate from the
sump to the filter feed tank should not exceed 200 gpm.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 16
Illinois Central Spring Treatment Facility May 2013
Using H-O-A switches, the operator can override the automatic, PLC-controlled operation of the
sump pump (P-309 or P-310) and can run it manually. The pump can be manually controlled by
adjusting the throttling valve located on the discharge side of the pump.
5.5 WASTEWATER FLOOR SUMP
The wastewater floor sump (S-501) has one input. It is the open drain that runs the full length of
the building combined with the floor drains at all building entrances. The sump has three outlets:
the sanitary sewer (valved off and not used), the process water floor sump, and the overflow to
the SRS. It has two level switches that provide data to the PLC. LSH-500 has a set point
corresponding to the invert elevation of the sanitary sewer discharge line. LSHH-500 has a set
point corresponding to the invert elevation of the sump overflow pipe to the SRS.
Both LSH-500 and LSHH-500 provide input to the PLC that controls visual alarms on the GUI.
The LSH-500 alarm will indicate “Potential sanitary sewer discharge from wastewater sump.”
The LSHH-500 alarm will indicate “Wastewater sump overflow to SRS.” When the PLC
receives a signal from LSHH-500, it shuts down the SRS process feed pumps. This is necessary
since the cause of the high water level in the sump may be a leak or break in the process pipe or
treatment vessels.
The discharge from the wastewater floor sump to the sanitary sewer was specifically designed to
be completely manual to guard against inadvertent discharges of PCBs to the sanitary sewer.
The sanitary sewer discharge valve is kept closed at all times and is not used. The inflatable plug
between the two sumps has been removed to increase the working volume of the process water
floor sump.
If the sanitary sewer discharge valve is ever needed in the future, the inflatable plug would have
to be re-installed to separate the two sumps. Wastewater floor sump contents would then have to
be transferred to the process water floor sump for treatment, and the sump would have to be
thoroughly decontaminated. Prior to discharge of any water to the sanitary sewer, sampling and
analyses would be required to ensure that there are no PCBs in the water. Note: PCBs must not
be discharged to the sanitary sewer under any circumstances.
5.6 EFFLUENT/BACKWASH SUPPLY TANK
The effluent/backwash supply (EBS) tank (T-401) has a working capacity of 30,000 gallons. It
has two inputs. It receives fully treated effluent from the GAC filters as well as potable water.
The EBS tank has two outputs (plus a drain valve). Fully treated water from the GAC filters
overflows the EBS tank and drains by gravity to the new outfall downstream of the Swallow
Hole and Quarry Springs areas. The EBS tank also supplies treated water for backwashing the
GAC and multimedia filters (if required) using pumps P-401, P-402, and P-403 (added with the
EFTS). The backwash feed pumps each supply up to 1,000 gpm of flow during a GAC
backwash or a multimedia filter backwash, but the pumps cannot backwash these systems
simultaneously. These pumps can also supply water to the thickeners to break up solidified
sludge if needed, though this is an entirely manual process. The normal operating mode for this
tank is to be full so that water is always available for backwashing.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 17
Illinois Central Spring Treatment Facility May 2013
5.6.1 Auto Mode
Effluent from the GAC filters is generated when the system is in automatic mode. Influent from
the potable water supply occurs only manually. The discharge from the backwash feed pumps to
the filter feed tank is an automated function, whereas the discharge for GAC backwashing and
the discharge to the thickeners are completely manual operations.
5.6.1.1 Water Level
The level element and level-indicating transmitter (LE/LIT-400) displays output locally and on
the GUI via the PLC. In both locations, LE/LIT-400 displays the tank contents in feet (to the
nearest tenth of a foot) and gallons. As with the SRS and other tanks, the PLC uses the data from
LE/LIT-400 to compute and display tank fill and drain rates. This data can be compared to the
flow meter data to verify instrument accuracy.
LE/LIT-400 has two set points. When the PLC receives input from the low set point, it overrides
any other commands and turns off P-401, P-402, and P-403. This alarm condition displays
locally and on the GUI and reads “Low level in effluent/backwash supply tank.” When the PLC
receives input from the high set point, it overrides any other commands and shuts down the filter
feed pumps P-105, P-106, P-107, and P-108 that discharge to the EBS tank via the three filtration
systems (multimedia, bag, and GAC). This alarm condition is displayed locally and on the GUI
and reads “High level in effluent/backwash supply tank.”
Separate level switches (LSH-401 and LSL-401) are installed in the EBS tank to provide
redundancy for pump and spill protection. Each has one set point. When the PLC receives input
from LSH-401, the low-level set point, it overrides any other commands and turns off P-401,
P-402, and P-403. This alarm condition is displayed on the GUI and reads “Low level in
effluent/backwash supply tank.” When the PLC receives input from LSH-401, the high set
point, it overrides any other commands and shuts down the filter feeds pumps P-105, P-106,
P-107, and P-108 that discharge to the EBS tank via the three filter systems. This alarm
condition is displayed on the GUI and reads “High level in effluent/backwash supply tank.”
LSH-401 and LSL-401 elevations correspond to the elevations of the high-level and low-level
alarm points of LE/LIT-400. LSH-401 and LSL-401 are hardwired to the pumps that they
control.
The PLC continuously transmits data from these water level instruments to the storage device
and the MMI. Trending charts can be generated by the office PC, with records of this data stored
for the entire operating history of the plant.
5.6.1.2 Pumps
As described above, the backwash feed pumps (P-401, P-402, and P-403) are shut down by the
PLC when it receives low-level alarm signals from LE/LIT-400 or LSL-401. Normally, these
pumps are controlled manually to backwash the GAC filters or automatically by level switches in
the filter feed tank to ensure sufficient backwash volume for the multimedia filters. The system
is not designed to provide water to the GAC and multimedia filters simultaneously from the
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 18
Illinois Central Spring Treatment Facility May 2013
backwash feed pumps. These pumps are supplied with VFDs in case the actual required
backwash flow rates differ from the design backwash flow rates.
5.6.1.3 Flow Meter
There are two flow elements with indicating transmitters related to the EBS tank. One flow
meter (FE/FIT-102) measures effluent discharge through a Parshall flume in the floor at the
northwest interior corner of the plant. FE/FIT-102 is for monitoring purposes only and has no
control function. FE/FIT-400 is located on the discharge of P-401, P-402, and P-403. FE/FIT-
400 is for monitoring backwash flow rates only and has no control function. Over time, VFD
speeds may have to be manually adjusted to maintain the desired flow rates during backwashing.
These flow meters are programmed to display instantaneous flow rate in gpm and totalized flow
in gallons. They indicate this data locally and remotely to the GUI via the PLC. The PLC
continuously transmits the data to the data PC and the MMI. Trending charts can be generated
by the office PC, with records of this data stored for the entire operating history of the plant.
5.6.2 Manual Mode
The backwash feed pumps (P-401, P-402, and P-403) are controlled manually to backwash the
GAC filters. Manual operation is performed using H-O-A switches. Manual operation of these
pumps incorporates functions applied by the VFD (i.e., in manual mode, these pumps should
ramp up to 1,000 gpm). Each pump can be throttled, isolated for maintenance, or placed into
service as needed by adjusting the manual valves located on the inlet and outlet of each pump.
These pumps can also be manually diverted to add water to the thickeners to break up solidified
sludge. Putting potable water into the EBS tank is an exclusively manual operation. It is
possible to bypass the EBS tank and pump water directly to the ICS outfall by adjusting
exclusively manual valves.
5.7 FILTER FEED TANK
The main purpose of this tank is to provide a way to pump through the three filter systems in the
treatment train (multimedia, bag, and GAC). The volume of the filter feed tank is
11,000 gallons, and the working volume is 8,300 gallons. The filter feed tank has three inputs
and three outputs, plus a drain valve. The inputs include the following: overflow from, or
bypass around, the clarifier; discharge from the process water floor sump; and discharge from the
backwash feed pumps. The outputs include the gravity overflow to the process water floor
sump, one output to the 300-gpm pumps (P-105 and P-106), and one output to the 900-gpm
pumps (P-107 and P-108).
5.7.1 Auto Mode
Auto mode means that the entire system is controlled automatically by the PLC. In auto mode,
the multimedia filters, which receive flow from the filter feed tank, have three operating modes:
normal mode (forward flow through the filter for processing), backwash mode (reverse flow for
cleaning the media), and recycle mode (not currently installed). These operational modes are
discussed in more detail in Section 5.8 Multimedia Filters below.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 19
Illinois Central Spring Treatment Facility May 2013
5.7.1.1 Water Level
The level element and indicating transmitter (LE/LIT-102) displays output locally and on the
GUI via the PLC. In both locations, the tank contents are displayed in feet (to the nearest tenth
of a foot) and gallons. As with the SRS and other tanks, the PLC uses the data from LE/LIT-102
to compute and display tank fill and drain rates. This data may be compared to flow meter data
to verify instrument accuracy.
LE/LIT-102 has several set points: those that control the filter feed pumps and two set points for
pump/overflow protection. When the PLC receives input from the low-level set point, it
overrides any other commands and turns off all filter feed pumps (P-105, P-106, P-107, and
P-108). This alarm condition is displayed locally and on the GUI and reads “Low level in filter
feed tank.”
When the PLC receives input from the high-level set point, it overrides any other commands and
shuts down the SRS process feed pumps (P-101, P-102, P-103, and P-104) that discharge to the
filter feed tank via the clarifier. This alarm condition is displayed locally and on the GUI and
reads “High level in filter feed tank.”
Separate level switches (LSH-103 and LSL-103) are installed in the filter feed tank to provide
redundancy for pump/overflow protection. Each level switch has one set point. When the PLC
receives input from the low-level switch (LSL-103), it overrides any other commands and turns
off the filter feed pumps. This alarm condition is displayed on the GUI and reads “Low level in
filter feed tank.” When the PLC receives input from LSH-103, the high-level switch, it overrides
any other commands and shuts down the SRS process feed pumps. This alarm condition is
displayed on the GUI and reads “High level in the filter feed tank.” LSH-103 and LSL-103
elevations correspond to the elevations of the high-level and low-level alarm points of LE/LIT-
102. LSH-103 and LSL-103 are also hardwired to the pumps that they control.
The PLC continuously transmits data from these water level instruments to the data PC and the
MMI. Trending charts can be generated by the office PC, with records of this data stored for the
entire operating history of the plant.
5.7.1.2 Flow Meter
A flow meter (FE/FIT-103) is located on the combined discharge of the filter feed pumps. It
provides input to the PLC that controls the speed of the filter feed pumps through the VFDs.
When a 300-gpm pump (P-105 or P-106) is operating alone, the flow rate is 250 gpm. When a
900-gpm pump (P-107 or P-108) is operating alone, the flow rate is 850 gpm. In auto mode, the
larger pump only runs when the smaller pump is on, such that the discharge flow rate is either
250 gpm or 1,100 gpm. The PLC controls the filter feed pumps based on input from FE/FIT-103
in the same way whether the multimedia filter is in normal or backwash mode. This could
change, however, if operating experience indicates that the backwash flow rate should be
different than the forward flow rate.
During initial system startup, the VFD-controlled motor speed required to produce the necessary
discharge flow rates from the pumps was programmed into the PLC. Over time, the VFD speeds
may have to be manually adjusted to maintain the desired flow rates. The VFDs on the SRS
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 20
Illinois Central Spring Treatment Facility May 2013
process feed pumps and filter feed pumps are useful in balancing the influent and effluent flow
rates from the filter feed tank to minimize the potential for tank level alarms, as well as to avoid
excessive pump starts. They are also useful in addressing small process flow changes that could
occur over time.
The flow meter is programmed to display instantaneous flow rate in gpm and totalized flow in
gallons. It indicates this data locally and remotely to the GUI via the PLC. The PLC
continuously transmits the data to the data PC and the MMI. Trending charts can be generated
by the office PC, with records of this data stored for the entire operating history of the plant.
5.7.2 Manual Mode
The filters feed pumps may be controlled manually using H-O-A switches. Manual operation of
these pumps incorporates functions applied by the VFD (i.e., in manual mode, these pumps will
ramp up to their desired discharge rate). Each pump can be throttled, isolated for maintenance,
or placed into service as needed by adjusting the manual valves located on the inlet and outlet of
each pump.
5.8 MULTIMEDIA FILTERS
The multimedia filters are pressurized vessels that can operate in the following two automatic
modes: normal mode (“A” and “B” modes with forward flow when process water is being
treated) and backwash mode (back flow for cleaning the filter media). In normal mode, flow
enters the top of the unit and discharges from the bottom, whereas in backwash mode the flow is
reversed to enter the bottom and discharge from the top. The PLC controls which mode the filter
is in based on input from pressure transmitters. The GUI indicates which mode the filter is in at
any given time based on input from the PLC. Head pressures are automatically monitored and
recorded by the PLC and displayed on the GUI. Note: Filter automated features are based on
differential pressure and not head pressure. A correlation exists between the two, but only
the differential pressure controls system function.
Head pressure data is continuously transmitted from the multimedia filters to the PLC. The PLC
continuously transmits the data to the data PC and the MMI. Trending charts can be generated
by the office PC, with records of this data stored for the entire operating history of the plant.
5.8.1 Auto Mode
5.8.1.1 Normal Mode
The filter feed pumps (P-105, P-106, P-107, and P-108) are sized to provide different process
flow rates through the system. P-105 and P-106 are 300-gpm pumps that provide an actual flow
rate of 250 gpm, whereas P-107 and P-108 are 900-gpm pumps that provide an actual flow rate
of 850 gpm. As a result, the flow rates through the multimedia filters are 0, 250, or 1,100 gpm in
normal (forward-flow) mode depending on the influent flow rate to the filter feed tank.
When the flow rate into the filter feed tank is 0 gpm, it does not fill and the filter feed pumps do
not turn on. When the influent flow rate is 200 gpm from the clarifier or process sump, the filter
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 21
Illinois Central Spring Treatment Facility May 2013
feed tank fills to the “on” level set point for the 300-gpm filter feed pump. This pump is
activated and the tank level drops until the pump “off” level set point is reached. This pump will
continue to cycle on and off as needed.
The flow rate into the filter feed tank is 400 gpm when both the 200-gpm SRS process feed
pump and the 200-gpm process floor sump pump are on. The flow rate is 1,000 gpm when both
the 200-gpm and 800-gpm SRS process feed pumps are on. At these flows, the filter feed tank
fills past the “on” set point for 300-gpm pump and also activates the 900-gpm pump. The total
flow rate with both filter feed pumps operating is 1,100 gpm, which causes the tank level to drop
until the 900-gpm pump “off” level set point is reached. The 300-gpm pump stays on during this
time and the tank begins to fill until the 900-gpm pump cycles on again.
In the event that both SRS process feed pumps turn off soon after the 300-gpm and 900-gpm
filter feed pumps turn on, the net discharge rate from the filter feed tank will be 1,100 gpm and
the tank level will drop to the pump “off” level set points very quickly (4 to 5 minutes).
The flow rate into the filter feed tank is 1,200 gpm when both the 200-gpm and 800-gpm SRS
process feed pumps are on and the 200-gpm process floor sump pump is on. At this flow rate,
the filter feed tank fills past the set point for 300-gpm pump and also activates the 900-gpm
pump. The total flow rate with both filter feed pumps operating is 1,100 gpm, which causes the
tank level to rise slowly. The tank level continues to rise until either the SRS process feed
pumps or the process floor sump pump turns off (either on their own or due to a filter feed tank
high-level set point).
Under normal conditions, the manual valves on the discharge of the EBS tank need to be
properly set such that flow from these pumps is directed to the filter feed tank. Backwashing the
GAC filters to the thickeners is not a normal operation and can only be performed manually
when the multimedia filters are not in backwash mode.
“A” Operational Mode
In mode “A,” the multimedia filters operate as originally designed. All three filter units are
continuously online, except when a backwash cycle occurs. If the differential pressure between
the inlet and discharge piping of a unit exceeds the system set point, then that unit is
automatically sent into backwash mode. Backwash mode involves an automatic change of
valves such that the flow is reversed through the unit to clean the media. Only one unit at a time
can be backwashed. If a second unit requires backwashing during a backwash cycle already in
progress, the second unit will continue to process water until the first backwash cycle is complete
and that unit is brought back online.
With the automatic change of valves, the backwash water for the unit to be cleaned is taken from
the two units that remain online. In this mode of operation, two units are always online while the
third unit is in backwash mode. The backwash water is directed to Thickener #2 (T-301B).
During backwash, there is no flow to the bag filters. Once the backwash cycle is complete, the
unit is automatically put back into service. Alarms have been dampened with delays to
overcome pressure spikes that develop when the valves change the direction of flow. Based on
operating experience, mode “A” is the normal and preferred configuration.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 22
Illinois Central Spring Treatment Facility May 2013
“B” Operational Mode
In mode “B,” the multimedia filters operate with two units online and a third in reserve. In this
mode of operation, the units alternate with each backwash cycle. The unit held in reserve is
automatically brought online when backwash is required. Alarm conditions due to hydraulic
pressure spikes are avoided due to the sequence in which the valves operate with two units
online.
5.8.1.2 Backwash Mode
During backwash mode, solids accumulating on the filter media create a pressure drop between
the inlet and discharge sides. Differential pressure transducers and indicators (PDI-100 located
on T-103C, PDI-107 located on T-103B, and PDI-108 located on T-103A) monitor this pressure
drop across each unit. The differential pressure is not displayed on the GUI, nor is it recorded
through the PLC. Instead, the units have been fitted to display the head pressure in psi both
locally and remotely to the GUI and PLC.
Each of the three filter vessels also has a differential pressure switch (PDSH-100, PDSH-107,
and PDSH-108), which have been set to trigger at the same predefined set point. When the set
point of the transducer is exceeded, there is an output to the PLC that causes the GUI to indicate
“High differential pressure on multimedia filter X.” The PLC then sends a signal to
automatically backwash that vessel.
When a unit differential pressure transducer or switch calls for backwash mode, the PLC
automatically initiates a backwash cycle. A backwash cycle in automatic mode requires that
manual valves on the discharge of the backwash feed pumps (P-401, P-402, and P-403) are
properly positioned to transfer water to the filter feed tank. Other manual valves must be
positioned to valve off flow to the GAC filters and thickeners. These valves are normally
positioned in this manner because GAC filter backwashing is an entirely manual process. Prior
to manual backwashing of a GAC filter, the operator must disable the multimedia filter
automatic backwash mode.
Backwash mode requires a total volume of 7,500 gallons of water for each cycle. Backwash
mode may occur under a variety of conditions. When both SRS process feed pumps are
operating, the normal (forward) flow rate into the filter feed tank is 1,000 gpm. This provides
sufficient water in the filter feed tank to supply backwash needs, assuming that the filter feed
pumps do not shut off during the backwash cycle. If the filter feed pumps do shut down during
the backwash cycle, then supplemental water is required in the filter feed tank. Supplemental
water is required in the filter feed tank at other times as well, such as when a backwash cycle is
initiated and one or both of the 200-gpm pumps (i.e., the SRS process feed pump and/or process
water floor sump pump) are on. Supplemental water is also needed when one of these pumps
shuts down in the middle of a backwash cycle and there is no longer influent flow to the filter
feed tank.
Supplemental water to the filter feed tank, when required by backwash mode, is supplied from
the EBS tank via the backwash feed pumps (P-401, P-402, and P-403). Level set points in the
filter feed tank control these pumps automatically. When the appropriate set point is triggered
during backwash mode, one of the pumps delivers 1,000 gpm of flow to the filter feed tank to
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 23
Illinois Central Spring Treatment Facility May 2013
ensure that there is sufficient water to complete a backwash cycle. The EBS tank is always kept
full to provide adequate water for backwashing the multimedia filters.
In the filter feed tank, the “on” level set point for supplemental water is located above the “off”
level set point for the filter feed pumps. This ensures that the backwash supply pumps begin to
fill the filter feed tank with supplemental water before the filter feed pumps are automatically
shut down. This also ensures that the available backwash supply flow is always 1,000 gpm.
In multimedia filter backwash mode, both SRS process feed pumps, the process floor sump
pump, and the backwash feed pump can all be running simultaneously. This is considered the
“worst-case” operating scenario, with the flow rate into the filter feed tank being 2,200 gpm. As
soon as the water level rises above the “off” level set point for the backwash feed pump, which is
set above the “on” set point for the filter feed pump, the backwash feed pump turns off. This
ensures that the backwash feed pump only turns off when the filter feed tank is full and also
ensures that the backwash cycle can run to completion.
In multimedia filter backwash mode, the PLC enables a backwash feed pump to turn on and off
in accordance with level set points in the filter feed tank (monitored by LE/LIT-102). However,
the PLC will shut down the backwash feed pumps, regardless of filter feed tank level, if the EBS
tank level drops to the pump “off” set point (monitored by LE/LIT-400).
The multimedia filter backwash control sequence performed by the PLC is summarized as
follows:
1) The PLC initiates backwash mode for a specific filter unit as long as a GAC filter is not
being backwashed manually. The PLC indicates “Multimedia filter backwash mode” on
the GUI.
2) When the filter feed tank is filled to the “on” level set point for the 900-gpm filter feed
pump (monitored by LE/LIT-102), both the 300-gpm and 900-gpm pumps will run to
provide a backwash flow rate of 800 gpm.
3) The PLC initiates valve changes required for backwash of the specific unit (inlet valve
closed, backwash valves opened, and system outlet valve to bag filters closed).
4) A flow of 800 gpm is processed through two units while the other one is backwashed
with the filtrate from those units.
5) The backwash water is directed to Thickener #2 (T-301B) and there is no flow to the
GAC or bag filters.
6) The timer tells the PLC to terminate the backwash cycle, reverse position on the unit and
system valves, and reestablish normal operating mode.
7) The PLC controls the operation of the backwash feed pump based on level input from the
filter feed tank (LE/LIT-102) and the EBS tank (LE/LIT-400). This ensures that the filter
feed tank stays full of water and that the backwash cycle proceeds with an uninterrupted
flow rate of 800 gpm.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 24
Illinois Central Spring Treatment Facility May 2013
When backwash mode is complete, the PLC returns to the normal operational mode (“A” or
“B”). In normal mode, forward flow is reestablished through the multimedia filters to the bag
and GAC filters.
5.8.1.3 Recycle Mode (Not Installed)
Recycling of filtrate back to the filter feed tank is not anticipated but can be accomplished in this
mode. The multimedia filters are provided with a blind flange for a recycle line, but there is
currently no piping to finish the connection back to the filter feed tank. Should operation in
recycle mode become desirable, this piping can be added. If used in the future, the recycle mode
feature will enable the multimedia filter to receive continuous flow in the normal, forward-flow
direction without interruption during periods when insufficient flow is available. It is possible
that running the multimedia filters with continuous flow rather than intermittent (as it currently
functions) would improve their performance. It is important to note that that the only time this
feature would be useful is when the flow rate into the filter feed tank is 0 to 200 gpm. In these
situations, however, there may be no need for enhancement since TSS concentrations are likely
to be very low. No additional PLC programming to accommodate recycle mode is anticipated.
Since the system has operated well without this feature, it does not appear to be necessary and
there are no current plans to implement it.
5.8.1.4 Analyzers (Not Installed)
AE/AIT-100 is intended to be an in-line turbidity meter that collects a slipstream from the
combined discharge of the filter feed pumps to the multimedia filters. AE/AIT-101 is intended
to be an in-line turbidity meter that collects a slipstream from the piping between the multimedia
and bag filters. Although these analyzers are indicated on the P&IDs, neither has been installed
at this time. Retrofitting the system to include them should be a simple matter, since the wiring
and PLC programming are already in place.
The PLC is programmed to compare the turbidity at these two locations and make an assessment
of the performance of the multimedia filters. If the assessment indicates that there is inefficient
turbidity removal in the multimedia filters, the PLC would cause an alarm condition display on
the GUI indicating “High turbidity in multimedia filter effluent.” If the turbidity in the
multimedia filter influent exceeds a predetermined NTU level, the PLC would cause an alarm
condition display on the GUI indicating “High turbidity in clarifier effluent.” Eventually, it may
be possible for the PLC to use input from the turbidity meters to initiate backwash cycles or to
determine the proper cycle of the clarifier sludge pumps.
5.8.2 Manual Mode
The operator may be able to determine through operating experience that the multimedia filters
can be bypassed during periods of base flow in the ICS or during times that the multimedia
filters are in need of repair. Manual valve adjustments would make this possible. Manually
overriding the automated valves on the multimedia filters makes it possible to take one or more
filter units out of service.
The filter feed pumps (P-105, P-106, P-107, and P-108) can all be controlled manually at the
PLC. Manual operation of these pumps incorporates functions applied by the VFD (i.e., in
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 25
Illinois Central Spring Treatment Facility May 2013
manual mode, these pumps will ramp up to their desired discharge rate). Each pump can be
throttled, isolated for maintenance, or placed into service as needed by adjusting the manual
valves located on the inlet and outlet of each pump.
5.9 BAG FILTERS
During normal operation, the filter feed pumps discharge through the multimedia filters to one of
two bag filters piped in parallel. Flow enters the top of the bag filter units and discharges from
the bottom. The bag filters are pressurized vessels without backwash capabilities. Instead, these
units rely on disposable filter bags that must be changed periodically as solids accumulate and
create a pressure drop across the unit. Refer to the Bag Filter Change SOP in Appendix A for
specific procedures.
As with the multimedia filters, differential pressure is monitored by a transducer and indicator
located on each vessel (PDI-101 located on T-104A and PDI-102 located on T-104B). Head
pressure is also monitored and this data is transmitted to the GUI via the PLC. Head pressure
instrumentation is located on piping connected to both the inlet and discharge sides of each
vessel; consequently, either head or tail pressure can be monitored depending on how isolation
valves are arranged. Note: If both isolation valves are open, they will cause a partial bypass
of the bag filters through the ½-inch piping.
Each of the two vessels has a differential pressure switch (PDSH-101 on T-104A and PDSH-102
on T-104B). These switches have differential pressure set points that generate an alarm message
on the GUI via the PLC. When this alarm condition occurs, the GUI indicates “High differential
pressure on bag filter,” which prompts the operator to change out the filter bags in the
appropriate unit. The operator isolates the unit needing filter bag replacement through manual
valve changes, which allows the other unit to continue operating. The operator must be careful
not to isolate both units, as this will dead-head the filter feed pumps. Note: Back pressure
from the GAC units may create an abnormally low differential pressure across the bag
filters, indicating that the high system pressures are related to the GAC units.
Head pressure data is continuously transmitted from the bag filters to the PLC. The PLC
continuously transmits the data to the data PC and the MMI. Trending charts can be generated
by the office PC, with records of this data stored for the entire operating history of the plant.
5.10 GAC FILTERS
There are four 20,000-pound GAC vessels in the treatment process, which is the final treatment
step prior to discharge. The four GAC vessels are grouped into two sets operating in parallel,
each with a lead and lag vessel arrangement. The vessels are designated as T-105A1, T-105A2,
T-105B1, and T-105B2, with “A” and “B” representing the two parallel trains and “1” and “2”
representing the lead and lag vessels in each train. During normal operation, flow enters the top
of each vessel and discharges from the bottom; the flow is reversed in backwash mode.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 26
Illinois Central Spring Treatment Facility May 2013
Note: The GAC in carbon vessel “1” of each train was replaced in 2010. As a result,
carbon vessel lead/lag arrangement was changed such that “2” is now the lead vessel in
each train to maximize the treatment capacity of the available GAC.
Since the two GAC filter trains operate in parallel, the flow is split between them. For example,
when the 300-gpm filter feed pump is on (operating at 250 gpm), each train receives 125 gpm of
flow. Only one vessel can be manually backwashed at a time, so the flow must be managed
appropriately through the other vessels. Note: Each train can only handle a maximum of 600
gpm. Beyond this flow, the back pressure across the multimedia filters will activate the
pressure-relief valves and create an alarm condition.
There is one pressure differential transducer and indicator (PDI) and one pressure differential
switch (PDSH) associated with each vessel. PDI-103 and PDSH-103 are located on T-105B1.
PDI-104 and PDSH-104 are located on T-105B2. PDI-105 and PDSH-105 are located on
T-105A1. PDI-106 and PDSH-106 are located on T-105A2. The original PDI analog gauges
have been replaced with digital readouts and sending units. The pressures measured by these
gauges are recorded on the data logger and displayed on the GUI.
5.10.1 Auto Mode (Normal Mode)
In auto mode, the filter feed pumps discharge through the multimedia filters, the bag filters, and
the GAC filters, all of which are pressurized systems. Normal forward-flow operation of the
GAC vessels is completely automated, with no operator involvement required. All other GAC
filter operations, including backwashing and changing out carbon, is completely manual.
5.10.2 Backwash Mode (Manual Mode)
When sediment accumulates on the GAC filters, the pressure drop across each unit increases;
this is measured by a pressure differential transducer (with indicator) located on each vessel.
The pressure differential transducers are programmed to display differential pressure in psi and
to transmit this data remotely to the GUI via the PLC.
Each of the vessels also has a pressure differential switch (PDSH). These switches have
differential pressure set points that create an alarm condition on the GUI indicating “High
differential pressure across GAC vessel X.” At this time, the operator responds by manually
adjusting valves to isolate the vessel with high differential pressure. Only one GAC vessel can
be backwashed at a time. Note: Backpressure across the GAC is reflected as an increase in
pressure in the upstream bag filter gauges, which can provide a false high pressure reading
for the bag filter.
When the operator receives the high GAC differential pressure alarm, the EBS tank is filled with
potable water to make up any difference in level if the tank is not already full. When filled, the
operator initiates a backwash cycle, which is a completely manual operation. No part of the
GAC backwash procedure is automated in any way, since backwashes are typically completed
after each rainfall event. Manual valves are adjusted to divert flow from the EBS tank to the
GAC filters instead of the multimedia filters. Also, manual valves are adjusted to isolate the
GAC vessel that requires backwashing. When the backwash procedure is initiated, the backwash
pump is throttled to yield 600 gpm and the pump remains on in manual mode until the procedure
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 27
Illinois Central Spring Treatment Facility May 2013
is completed and the pump is manually turned off. This procedure may then be repeated for a
second, third, and fourth GAC vessel as needed. Refer to the Carbon Backwash SOPs in
Appendix A for procedure details.
Pressure data is continuously transmitted from the GAC filters to the PLC. The PLC
continuously transmits the data to the data PC and the MMI. Trending charts can be generated
by the office PC, with records of this data stored for the entire operating history of the plant.
5.10.3 GAC Vessel Change-out
Removing spent carbon from a GAC vessel and replacing it with virgin carbon (i.e., a carbon
change-out) is a totally manual operation. It requires that the operator adjust manual valves to
isolate the vessel receiving the change-out. Carbon change-out is indicated when the vessel
cannot be adequately cleaned by backwashing or if PCB levels in plant effluent consistently rise
above 0.3 ppb.
5.11 CLARIFIER SLUDGE THICKENER
Sludge thickener T-301A receives sludge from the bottom of the clarifier and from the SRS
when the clarifier is bypassed. There are six pressurized inputs and six outputs. The six inputs
include the following: sludge from the bottom of the clarifier, sludge directly from the SRS
(during clarifier bypass), thickening aid (lime) from the thickening aid storage tank, core purge
from the filter press, fully treated water from the EBS tank (for breaking up solidified sludge),
and air (for mixing during filter press operations). The six outputs include the following: an
underflow at the base of the cone bottom from which sludge is pumped to the filter press; an
unvalved overflow outlet at the top of the tank that discharges by gravity to the process water
floor sump; and four mid-level decant lines from different tank levels (2 feet apart). These four
decant lines are controlled by manual valves to send flow to either the filter press suction line or
the process water floor sump. This thickener operates independently or in parallel (not series)
with the other thickener.
5.11.1 Auto Mode
The only automated feature of the thickener involves level controls that prevent potential
overflows from pumps that automatically transfer water and/or solids to this vessel.
5.11.1.1 Water Level
The level element and indicating transmitter (LE/LIT-301) displays output locally and on the
GUI via the PLC. In both locations, the tank level is displayed in feet above the top of the cone
(to the nearest tenth of a foot) and in gallons. As with the SRS and other tanks, the PLC uses the
data from LE/LIT-301 to compute and display tank fill and drain rates. This data is compared to
flow meter data to verify instrument accuracy.
When the PLC receives input from the high-level set point, it overrides any other commands and
shuts down the backwash feed pumps (P-401, P-402, P-403) and the clarifier sludge pumps
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 28
Illinois Central Spring Treatment Facility May 2013
(P-301, P-302) to prevent the thickener from overflowing. This alarm condition is displayed
locally and on the GUI as “High level in thickener tank A.”
A separate level switch (LSH-301) is installed in the thickener tank to provide redundancy for
overflow protection. When the PLC receives input from LSH-301, it overrides any other
commands and shuts down the backwash feed pumps (P-401, P-402, P-403) and the clarifier
sludge pumps (P-301, P-302) to prevent the thickener from overflowing. This alarm condition is
also displayed on the GUI as “High level in thickener tank A.” The LSH-301 elevation
corresponds to the elevation of the high-level set point for LE/LIT-301.
Level data is continuously transmitted from the thickener to the PLC. The PLC continuously
transmits the data to the data PC and the MMI. Trending charts can be generated by the office
PC, with records of this data stored for the entire operating history of the plant.
5.11.2 Manual Mode
There are many manually operated valves associated with the thickener. The inlet from the
clarifier has a manual valve that is normally open during auto mode, since the clarifier sludge
pumps may automatically pump to the thickener. This valve has a chain wheel actuator so that it
can be operated from the floor level. The inlet from the filter press (air core purge) and the inlet
from the EBS tank are also manually controlled through operator valve changes. The four
supernatant overflow lines have manual valves with chain actuators so that the operator can open
and close them from the floor. Refer to the Decanting Thickeners SOP in Appendix A for
specific operational procedures.
As the thickener supernatant is decanted, additional sludge can be transferred to the thickener.
With each transfer operation, the solids concentration within the thickener increases. Once the
solids reach a concentration of approximately 2% by weight, the thickener is ready to transfer
solids to the filter press for dewatering. Previous bench-scale and full-scale filter press tests have
shown that this solids concentration results in acceptable filter press cakes.
After all the solids from the thickener are processed and the thickener is empty, the operator
must flush the underflow lines between the bottom of the thickener and the filter press. This
action ensures that sludge inside these pipes does not accumulate and compact itself into
immovable plugs that inhibit system operation during subsequent storm events. To accomplish
this, the operator must manually open the valve from the EBS tank and partially fill the thickener
with treated effluent via the backwash feed pumps (P-401, P-402, or P-403). This water can then
be run through the filter press to clean out its pipes in the process.
Each of the filter press feed pumps (P-305 and P-306) can be throttled, isolated for maintenance,
or put into service as needed by manually adjusting the valves located on the inlet and outlet of
each pump.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 29
Illinois Central Spring Treatment Facility May 2013
5.12 GAC AND MULTIMEDIA FILTER SLUDGE THICKENER
The GAC and multimedia filter backwash sludge thickener (T-301B) has five pressurized inputs
and six outputs. The five inputs include the following: sludge from backwashing the multimedia
filters, sludge from backwashing the GAC filters (including the EFTS GAC units), thickening
aid (lime) from the thickening aid storage tank, treated water from the EBS tank (for breaking up
solidified sludge), and air for mixing. The six outputs include the following: an underflow at the
base of the cone bottom from which sludge is pumped to the filter press; an unvalved overflow
outlet at the top of the tank that flows by gravity to the process water floor sump; and four mid-
level decant lines at four different tank levels (2 feet apart). These decant lines are controlled by
manual valves that direct flow to either the filter press or the process water floor sump. This
thickener operates independently of the other thickener.
5.12.1 Auto Mode
Two automated features are provided for the thickener. The multimedia filter backwash cycle,
which directs flow to the thickener, is fully automated. In addition, level controls in the
thickener automatically shut down system pumps to prevent overflow.
5.12.1.1 Water Level
The level sensor and indicating transmitter (LE/LIT-302) displays output locally and on the GUI
via the PLC. In both locations, tank contents are displayed in feet above the top of the cone (to
the nearest tenth of a foot) and in gallons. As with the SRS and other tanks, the PLC uses the
data from LE/LIT-302 to compute and display tank fill and drain rates. This data is compared to
flow meter data to verify instrument accuracy.
When the PLC receives input from the high-level set point of LE/LIT-302, it overrides any other
commands and shuts down the filter feed pumps (P-105, P-106, P-107, P-108) and the backwash
feed pumps (P-401, P-402, P-403) to prevent the thickener from overflowing. This alarm
condition is displayed locally and on the GUI as “High level in thickener tank B.”
A separate level switch (LSH-302) is installed in the thickener tank to provide redundancy for
overflow protection. When the PLC receives input from LSH-302, it overrides any other
commands and shuts down the filter feed pumps (P-105, P-106, P-107, P-108) and the backwash
feed pumps (P-401, P-402, P-403) to prevent the thickener from overflowing. This alarm
condition is displayed on the GUI as “High level in thickener tank B.” The LSH-302 elevation
corresponds to the elevation of the high-level set point for LE/LIT-302.
Level data is continuously transmitted from the thickener to the PLC. The PLC continuously
transmits the data to the data PC and the MMI. Trending charts can be generated by the office
PC, with records of this data stored for the entire operating history of the plant.
5.12.2 Manual Mode
There are many manually operated valves associated with the thickener. The inlet from the
multimedia and GAC filter backwashes has a manual valve that is normally open during auto
mode since the filter feed pumps automatically pump to the thickener during multimedia filter
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 30
Illinois Central Spring Treatment Facility May 2013
backwashing. This valve has a chain wheel actuator so that it can be operated from the floor
level. The inlet from the EBS tank is manually valved since transferring effluent from the EBS
tank for breaking up sludge is entirely manual. The four supernatant overflow lines have manual
valves with chain actuators so that the operator can open and close them from the floor. Refer to
the Decanting Thickeners SOP in Appendix A for specific operational procedures.
After all the solids from a storm event are processed and the thickener is empty, the operator
must flush the underflow lines between the bottom of the thickener and the filter press. This
action ensures that sludge inside these pipes does not accumulate and compact itself into
immovable plugs that prevent operation of the system during a subsequent storm event. To
accomplish this, the operator must manually open the valve from the EBS tank and partially fill
the thickener with treated effluent via the backwash feed pumps (P-401, P-402, P-403). This
water can then be run through the filter press, cleaning out those pipes in the process.
Each of the filter press feed pumps (P-305, P-306) can be throttled, isolated for maintenance, or
placed into service as needed by manually adjusting the valves located on the inlet and outlet of
each pump.
5.13 FILTER PRESS
The filter press is the primary dewatering device for sludge stored in the thickening tanks. It
allows the sludge to be dewatered from approximately 2% solids by weight to >50% solids by
weight. The press is a plate-and-frame type with a capacity of 50 cubic feet. It has no
connection to the system PLC; however, it has its own internal PLC to control each dewatering
cycle. The filter press is only operated when sufficient sludge has collected in the thickeners to
warrant a full load.
Sludge is pumped from the thickeners by the filter press feed pumps (P-305, P-306) and is
deposited into void spaces between the press plates. As the feed pumps continue to operate, the
pressure inside the plate void spaces increases and forces water out through the filter cloths and
into the filtrate piping. The press PLC automatically increases the pumping pressure in timed
stages throughout the cycle to maximize dewatering. Filter press filtrate is discharged back to
the process floor sump for retreatment through the system. At the end of the cycle, air is
automatically blown through the press core to remove any remaining solids or liquids. This
material is automatically directed to the clarifier sludge thickener (T-301A). When each
dewatering cycle is complete, the press plates are separated by the operator with the assistance of
a semiautomatic plate shifter, and the dry cakes fall into the rolloff box below. Prior to
transporting full rolloff boxes off-site, an additional dewatering step is taken. A small
submersible pump attached to a screened PVC tube is placed in the north side of the rolloff box
and used to pump out any remaining free water. Refer to the Filter Press SOP in Appendix A for
specific operating procedures.
5.14 AIR COMPRESSOR
The air compressor is fully automated and only communicates with the system PLC for
monitoring and alarm purposes. There is a set of contacts on the compressor control panel that
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 31
Illinois Central Spring Treatment Facility May 2013
can transmit any one of 14 different alarm conditions to the main system PLC. When this
occurs, the PLC indicates an alarm condition on the GUI, and the MMI initiates the call-out
sequence. The alarm message on the GUI and MMI is “Compressor alarm condition.” The
alarm condition alerts the operator to the fact that the compressor is malfunctioning but does not
specify the problem. In order to troubleshoot, the operator must physically inspect the
compressor and its local control panel. Compressor pressure data is continuously transmitted to
the main system PLC. The PLC continuously transmits the data to the data PC and the MMI.
Trending charts can be generated by the office PC, with records of this data stored for the entire
operating history of the plant.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 32
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 6 : P R O C E S S S T A R T / S T O P C O N D I T I O N S
Pump start/stop conditions are based on the original system programming by Frakes
Engineering. All system set points are listed in Table 2: Instrumentation Summary.
6.1 PROCESS FEED PUMPS
Start conditions for both 200-gpm (P-101, P-102) and 800-gpm (P-103, P-104) pumps:
1) SRS not low level by LE/LIT-200 or LSL-200F.
2) Clarifier not high level by LSH-100.
3) Filter feed tank not high level by LE/LIT-102 or LSH-103.
Stop conditions for both 200-gpm (P-101, P-102) and 800-gpm (P-103, P-104) pumps:
1) SRS low level by LE/LIT-200 or LSL-200F.
2) Clarifier high level by LSH-100.
3) Filter feed tank high level by LE/LIT-102 or LSH-103.
Start condition for only the 200-gpm (P-101, P-102) pump:
1) SRS level equal to or greater than LE/LIT-200 “on” set point for P-101 and P-102.
Stop condition for only the 200-gpm (P-101, P-102) pump:
1) SRS level equal to or less than LE/LIT-200 “off” set point for P-101 and P-102.
Start condition for only the 800-gpm (P-103, P-104) pump:
1) SRS level greater than or equal to LE/LIT-200 “on” set point for P-103 and P-104.
Stop condition for only the 800-gpm (P-103, P-104) pump:
1) SRS level equal to or less than LE/LIT-200 “off” set point for P-103 and P-104.
6.2 SRS STORAGE TANK PUMPS
Start conditions for lead and lag 2,500-gpm (P-201 – P-203) pumps:
1) SRS not low level by LE/LIT-200 or LSL-200F.
2) Lead pump starts at its LE/LIT-200 “on” set point.
3) Lag pump starts at its LE/LIT-200 “on” set point.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 33
Illinois Central Spring Treatment Facility May 2013
Stop conditions for lead and lag 2,500-gpm (P-201 – P-203) pumps:
1) SRS low level by LE/LIT-200 or LSL-200F.
2) Lag pump stops at its LE/LIT-200 “off” set point.
3) Lead pump stops at its LE/LIT-200 “off” set point.
Start condition for only the lead pump:
1) SRS level greater than or equal to LE/LIT-200 “on” set point.
Start condition for only the lag pump:
1) SRS level greater than or equal to LE/LIT-200 “on” set point.
6.3 FILTER FEED PUMPS
6.3.1 During Normal Operation
Start conditions for 300-gpm (P-105, P-106) and 900-gpm (P-107, P-108) pumps:
1) Filter feed tank not low level by LE/LIT-102 or LSL-103.
2) No GAC or multimedia filter vessels indicating high differential pressure.
3) EBS tank not high level by LE/LIT-400 or LSH-401.
Stop conditions for 300-gpm (P-105, P-106) and 900-gpm (P-107, P-108) pumps:
1) Filter feed tank low level by LE/LIT-102 or LSL-103.
2) GAC or multimedia filter vessels indicating high differential pressure.
3) EBS tank high level by LE/LIT-400 or LSH-401.
Start condition for only the 300-gpm (P-105, P-106) pumps:
1) Filter feed tank level greater than or equal to LE/LIT-102 “on” set point.
Stop condition for only the 300-gpm (P-105, P-106) pumps:
1) Filter feed tank level below LE/LIT-102 “off” set point.
Start condition for only the 900-gpm (P-107, P-108) pumps:
1) Filter feed tank level greater than or equal to LE/LIT-102 “on” set point.
Stop condition for only the 900-gpm (P-107, P-108) pumps:
1) Filter feed tank level below LE/LIT-102 “off” set point.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 34
Illinois Central Spring Treatment Facility May 2013
6.3.2 During Backwashing
Start condition for 300-gpm (P-105, P-106) and 900-gpm (P-107, P-108) pumps:
1) Filter feed tank not low level by LE/LIT-102 or LSL-103.
Stop condition for 300-gpm (P-105, P-106) and 900-gpm (P-107, P-108) pumps:
1) Filter feed tank low level by LE/LIT-102 or LSL-103.
Start conditions for multimedia filter backwashing:
1) Multimedia filter (T-103A-C) indicating high differential pressure.
2) 300-gpm filter feed pump (P-105 or P-106) in Auto.
3) 900-gpm filter feed pump (P-107 or P-108) in Auto.
4) Backwash feed pumps (P-401, P-402, P-403) in Auto.
5) EBS tank level greater than or equal to set point by LE/LIT-400.
6) Sludge thickener T-103B level less than or equal to set point by LE/LIT-302.
Stop conditions for multimedia filter backwashing:
1) 300-gpm filter feed pump (P-105 or P-106) not in Auto.
2) 900-gpm filter feed pump (P-107 or P-108) not in Auto.
3) Backwash feed pumps (P-401, P-402, P-403) not in Auto.
4) EBS tank level less than set point by LE/LIT-400.
5) Sludge thickener T-103B level greater than set point by LE/LIT-302.
6) Backwash process done.
“Backwash Process Done” conditions after 3 minutes:
1) Multimedia filter unit inlet valve closed.
2) Multimedia filter unit backwash valve opened.
3) Multimedia filter system discharge valve closed.
4) 300-gpm filter feed pump (P-105 or P-106) running.
5) 900-gpm filter feed pump (P-107 or P-108) running.
6.4 BACKWASH FEED PUMPS
Start conditions for P-401, P-402, P-403:
1) EBS tank not low level by LE/LIT-400 or LSL-401.
2) EBS tank level greater than or equal to set point by LE/LIT-400.
3) Filter feed tank not high level by LE/LIT-102 or LSH-103.
4) Filter feed tank less than or equal to set point by LE/LIT-102.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 35
Illinois Central Spring Treatment Facility May 2013
Stop conditions for P-401, P-402, P-403:
1) EBS tank low level by LE/LIT-400 or LSL-401.
2) EBS tank level less than set point by LE/LIT-400.
3) Filter feed tank high level by LE/LIT-102 or LSH-103.
4) Filter feed tank level greater than set point by LE/LIT-102.
6.5 PROCESS WATER SUMP PUMP
Start conditions for P-309, P-310:
1) Filter feed tank not high level by LE/LIT-102 or LSH-103.
2) Filter feed tank level less than or equal to set point by LE/LIT-102.
3) Sump high level by LSH-300.
4) Sump high-high level by LSHH-300.
Stop conditions for P-309, P-310:
1) Filter feed tank high level by LE/LIT-102 or LSH-103.
2) Filter feed tank level greater than set point by LE/LIT-102.
3) Sump low level by LSL-300.
4) Sump low level by LSLL-300.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 36
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 7 : P R O C E S S A L A R M R E S P O N S E
The PLC receives and transmits the date, time, and description of alarm conditions to the data PC
and the MMI. Reports can be generated from the office PC for review and printing. During
alarm conditions, the MMI calls the operator (via the preprogrammed call list) to relay alarm
conditions and initiate response. If the operator is unavailable, the backup operator is called. If
the backup operator is unavailable, the tertiary operator is called and the cycle repeats until the
alarm is acknowledged. All alarm conditions, set points, and resulting actions are presented in
Table 3.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 37
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 8 : S T A N D A R D O P E R A T I N G P R O C E D U R E S
Standard operating procedures have been developed for the system over the past several years.
The SOPs are intended to supplement equipment manufacturer manuals included in Volumes II –
X of this O&M plan. The SOPs address both routine operations (filter press, carbon vessel
backwashing, etc.) as well as nonroutine maintenance activities (SRS cleaning, SRS pump
removal/installation, etc.). All current SOPs are included in Appendix A; additional SOPs are
added as they are developed. These SOPs are also intended to serve as BMPs required by
applicable Indiana NPDES regulations.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 38
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 9 : S A M P L I N G A N D A N A L Y S I S
9.1 SAMPLING
All samples collected from the treatment system fall into one of two categories: government-
required samples that are reported to USEPA on a regular basis, and operational samples that are
used by the operator to evaluate system performance and troubleshoot when necessary.
9.1.1 Governmental Parameters
Effluent samples are collected weekly for PCB analysis by an outside contract laboratory. In
addition, an effluent sample is collected monthly for TSS analysis, which is performed by the
operator in the treatment building lab.
Sludge sampling is conducted at two locations to ensure proper characterization for disposal.
Samples are collected from the thickener tanks and are analyzed by an outside laboratory for
PCB content. This allows for accurate characterization under TSCA regulations, since the
samples are collected prior to the addition of lime (used as a dewatering aid for the filter press).
Composite samples of filter cake are also collected from the roll-off box after dewatering in the
filter press and are analyzed for RCRA parameters prior to transport.
9.1.2 Operational Parameters
Operational parameters that are analyzed for each effluent sample include turbidity, temperature,
pH, dissolved oxygen (DO), and conductivity. These parameters help the operator evaluate
system operation and also provide a basis for system troubleshooting when necessary.
Additional PCB samples may be collected during major storm events to evaluate the
effectiveness of individual system components. Sample ports are located on the inlet and outlet
sides of all major system components. Wipe and solid PCB samples can also be collected at the
operator’s discretion.
Refer to the system P&IDs in Appendix C for the locations of all sample ports.
9.1.3 Methods
For all sampling events, the operator performs the manual flow calculation previously described
to determine the influent flow rate. In addition, effluent flow meters from both the PTS and the
EFTS are used to determine daily totals (gallons) of water treated through the system. When the
operator prepares summary reports of analytical data for submission to USEPA, the influent flow
rate and the daily treated volumes are always included. This allows flows to be taken into
consideration when evaluating effluent results.
9.1.3.1 Sample Collection, Preservation, and Decontamination Procedures
Effluent samples are collected from the Parshall flume prior to discharge from the PTS or from
other sample ports during troubleshooting as necessary. Collected samples are placed into
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 39
Illinois Central Spring Treatment Facility May 2013
properly prepared sample bottles. All sample collection procedures are in accordance with Part
1060 of the 22nd edition of “Standard Methods for the Examination of Water and Wastewater”.
For personal protection equipment requirements during sampling, refer to the latest Master
Health and Safety Plan for the facility. Except for the automated sampler, all sampling
equipment comprises dedicated or disposable materials. Where decontamination is required, the
appropriate protocols are followed as specified by the Health & Safety Plan or by common
industry standards.
9.1.3.2 Sample Labeling Procedures
The outside of each container is wiped clean and allowed to dry after sample collection. Legible,
complete, and securely attached labels are placed on each sample container at the time of
collection. The sample label includes the following information:
• Sample identification (sample location)
• Name or initials of sampler
• Date and time of collection
• Site identification
• Preservation technique
Waterproof writing utensils are used to avoid running or smearing of label information. The
operator gives each sample a unique identification (i.e., sample ID) that contains information
about both the location and date of sampling.
9.1.3.3 Sample Storage and Shipment
Upon sample collection and preservation, the filled sample containers are packed into a cooler of
sturdy construction or transferred to the site refrigerator until they are picked up for shipment
and analysis. For shipping purposes, the samples are packed to protect against damage and iced
to maintain samples at or near 4°C. Due to the potential for breakage during transportation,
samples are shipped with a duplicate for analysis if problems occur with the initial sample.
9.1.3.4 Field Chain-of-Custody Procedures
Possession of samples from the time of collection through delivery to the laboratory is
documented by a chain-of-custody (COC) form. The original COC follows the samples with
copies maintained indefinitely at the site or as otherwise directed by USEPA. Information
contained on the COC will include sample name/location, sampling date and time, analysis to be
performed, preservation methods, analytical laboratory, and any other information pertinent to
the sampling event.
9.2 ANALYSIS
All outside lab analyses are performed using the latest edition of “Standard Methods for the
Examination of Water and Wastewater” or as listed in 40 CFR 136.3, Appendix A. The lab is
responsible for the receipt, log-in, and storage of all client samples. Each sample is labeled with
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 40
Illinois Central Spring Treatment Facility May 2013
a unique number that is entered into the sample receiving log system. The samples are placed
into appropriate storage within an access-controlled location. All samples are to be maintained
under proper storage conditions for 30 days past generation of the analytical report.
TSS analysis is performed by the operator in the treatment building laboratory using appropriate
standard methods.
In-house laboratory analyses, including pH, DO, turbidity, temperature, and conductivity, are
performed using a single or a multi-parameter probe. Manufacturer’s instructions are followed
explicitly for proper use and calibration of this equipment. Except for continuous reading
monitors, the probes and/or sensors are calibrated prior to use. DO is corrected for temperature
and pressure. Temperature is measured with a non-mercury thermometer. pH measurements are
corrected for temperature and the pH meters are calibrated with two reference buffer solutions.
Instrument calibrations are recorded and maintained on-file.
The analytical data is reviewed for possible errors and inconsistencies, with quality
assurance/quality control (QA/QC) data reviewed as needed. Analytical data (both in-house and
laboratory-generated data) is maintained on site and forwarded to USEPA on a regular basis as
required. The operators use all analytical data to evaluate and optimize the performance of the
treatment system. This data is also used to identify potential system improvements.
9.3 SAMPLE PARAMETERS AND POTENTIAL LOCATIONS
The following sections outline the importance of each parameter analyzed as well as the benefits
of collecting samples at specific locations for troubleshooting purposes.
9.3.1 PCBs and TSS
PCB and TSS data is important for the following reasons:
1) Verify PCB levels meet effluent standards;
2) Evaluate the performance of individual unit processes;
3) Perform mass balance calculations to understand how PCBs and TSS move through the
system;
4) Understand how storm events and ICS influent flow rates affect system performance;
5) Estimate current and future solids handling needs and disposal costs; and
6) Estimate future GAC use rates and replacement costs.
7) Provide characterization of sludge for disposal in accordance with TSCA regulations.
The following is a summary of potential sampling locations and their benefits:
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 41
Illinois Central Spring Treatment Facility May 2013
Building Influent
• Compare against final effluent data to evaluate overall system performance.
• Determine the effect of storm events and ICS influent flow on effluent results.
• Determine how concentrations vary during storm events.
• Confirm concentrations present at low-flow conditions and evaluate trends.
Clarifier Effluent
• Compare against building influent data to evaluate the effectiveness of the clarifier.
Multimedia Filter Effluent
• Compare against clarifier effluent data to evaluate the effectiveness of the multimedia
filters.
Bag Filter Effluent (also PTS GAC Influent)
• Compare against multimedia filter effluent data to evaluate the effectiveness of the bag
filters.
EFTS GAC Influent (at EFTS Receiving Tank)
• Allow for evaluation of GAC vessel effectiveness.
GAC Vessel Effluent (PTS or EFTS)
• Compare against GAC influent data to evaluate the effectiveness of the GAC vessel.
• Gauge when backwash of units may be required.
• Gauge when carbon is losing effectiveness and needs to be changed out.
Thickener Tanks (Sludge)
• Provide characterization for proper disposal under TSCA regulations.
9.3.2 TSS Only
Clarifier Influent
• Determine influent solids loading and concentration to the PTS.
Clarifier Sludge Outlet to Thickener (T-301A)
• Compare against clarifier influent data to evaluate the effectiveness of the clarifier.
Thickener Supernatant
• Compare against various thickener inflow data to evaluate settling efficiency.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 42
Illinois Central Spring Treatment Facility May 2013
SRS Storage Tank Influent, Under Drain, and Overflow (EFTS Influent at Receiving Tank)
• Evaluate solids settling effectiveness of the storage tanks.
Carbon Vessel Backwash
• Determine solids loading removed by GAC vessels.
Multimedia Filter Backwash
• Determine solids loading removed by multimedia filters.
9.3.3 DO
PTS Effluent
• DO is a measured parameter of system influent. Although DO is not believed to have
any significant influence on system operations, testing the effluent and comparing it
against influent levels can determine if treatment results in any significant oxygen
depletion that could affect aquatic life at the outfall.
9.3.4 pH
PTS Effluent
• pH is a measured parameter of system influent. Although pH is not anticipated to change
significantly during treatment, testing the effluent pH can be done to ensure it is within
the proper pH range for aquatic life downstream.
9.3.5 Turbidity and Conductivity
Turbidity and conductivity are good indicators of the water source (i.e. groundwater or runoff).
These parameters can also be used as a marker or indicator of PCB concentrations, which allows
the operator to proactively manage system operation during storm events.
9.3.6 Temperature
Temperature may be measured at all of the sample locations listed. This can show how
temperature changes affect the treatment process at various stages and assist with
troubleshooting problems.
9.3.7 Percent Moisture Content
Filter Cake
• Evaluate effectiveness of the filter press.
• Determine appropriate filter cake management requirements.
• Minimize offsite disposal volume of filter cake by optimizing solids content.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 43
Illinois Central Spring Treatment Facility May 2013
9.3.8 Particle Size Distribution
• Determine the particle sizes that comprise TSS for troubleshooting.
• Determine how storm water flows affect particle size distribution. This could potentially
improve treatment system performance during storm events.
• Provide estimates of settling rates.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 44
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 10 : E Q U I P M E N T M A I N T E N A N C E
This section summarizes recommendations for spare parts to keep on site and also
recommendations for routine preventative maintenance to be performed on the equipment.
10.1 SYSTEM COMPONENT CONTACTS
There may be instances when the operator cannot address a specific equipment malfunction,
even after review of the appropriate manufacturer manuals. Table 4 was compiled to provide a
system component contact list. The specified contact should be able to help resolve any
component problems in order to minimize potential system downtime.
10.2 SPARE PARTS
Refer to Table 5 for a list of spare parts originally developed by Earth Tech. The list was
intended to focus on parts that have a high potential for failure based on equipment vendor
manuals and guidance. Spare parts are generally stored on site when normal use typically causes
failure (e.g., filters bags), when failure would cause critical system components to be inoperable,
or when acquisition of a new part would take a long period of time. The presence of functional
backups for most process equipment is also taken into account when deciding whether or not to
stock certain spare parts. Critical spare parts are stored on site in an organized location and are
inventoried periodically.
10.3 PREVENTATIVE MAINTENANCE
An effective preventive maintenance program maximizes equipment reliability, increases
equipment life, and minimizes repair costs. Table 6 contains manufacturer-recommended
preventive maintenance schedules for major system components. The maintenance schedule
specifies all the recommended maintenance required to keep the equipment in good operating
condition. A permanent record is kept for all equipment inspections and maintenance. A backup
copy of this record is stored at the PSARA Bloomington office.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 45
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 11 : R E P O R T I N G R E Q U I R E M E N T S
11.1 ROUTINE REPORTING
Routine reporting currently consists of a monthly summary report submitted to USEPA. The
report summarizes all critical data for the month, including:
• Precipitation amounts (monthly total and daily maximum);
• Volume of water treated (monthly total and average monthly flow rate);
• Weekly effluent sample PCB results (with volume of water treated on each sample date
and average flow rate for those days); and
• Summary of system O&M activities for the month.
11.2 NONROUTINE REPORTING
In the event of a nonroutine condition (system upset/bypass, effluent limit exceedance, etc.), the
operator notifies the Bloomington Branch Manager of PSARA Technologies and CBS
immediately. Appropriate information/data is compiled and evaluated to confirm the incident.
After confirmation, CBS provides an initial notification to USEPA immediately. A detailed
investigation of the incident is initiated and results are verbally reported to USEPA as they
become available. In addition, a summary written report is submitted to USEPA to address
potential causes and corrective actions. Any necessary follow-up actions are specified by
USEPA and are implemented as soon as possible.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 46
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 12 : C O N T I N G E N C Y P L A N S
A comprehensive contingency plan is not required for the site; however, provisions have been
made for addressing various emergencies. Provisions have also been made for system bypass or
upset conditions that could recontaminate previously remediated areas.
12.1 FIRE AND SECURITY
The treatment system building is equipped with a fire alarm system. Smoke detectors are
strategically located throughout the building and are connected to the main control panel. The
fire alarm system is connected to a dedicated phone line for automatic call-out of alarm
conditions to both the operator and the Bloomington Fire Department. A private security
company monitors the system and performs a complete inspection annually.
The treatment building is surrounded by chain-link fencing with an entrance gate that is kept
closed and locked when the operator is not present. In addition, the SRS and treatment buildings
are kept closed and locked when the operator is not present.
12.2 EMERGENCY RESPONSE
Emergency response guidance was developed for the site by EFS, the original contract operating
company. This guidance addresses various emergencies and provides specific response
procedures. The operator was trained by EFS on these procedures, and they are still in use. A
copy of this guidance is maintained on file at the ICSTF building.
12.3 SYSTEM UPSET/BYPASS
In the event of a major system upset or bypass that causes untreated water to come into contact
with any area outside of the ICSTF buildings, USEPA will be notified immediately per Section
11.2 of this plan. Soil/sediment sampling will be conducted to determine if PCBs have
recontaminated the affected areas to levels exceeding the applicable cleanup criteria. CBS will
develop and submit a Sampling and Analysis Plan (SAP) for evaluating the affected areas. Upon
approval of the SAP, CBS will conduct the necessary sampling and submit a report of findings to
USEPA. In the event that PCB levels are found to exceed the applicable cleanup criteria,
USEPA will determine whether or not additional cleanup actions are necessary.
Operations and Maintenance Plan, Volume 1-A: Primary Treatment System 47
Illinois Central Spring Treatment Facility May 2013
S E C T I O N 13 : A S - B U I L T R E C O R D D R A W I N G S
The as-built record drawings for the PTS and EFTS are maintained in the ICSTF building. The
drawings are annotated as necessary to note any significant changes, revisions, or corrections.
As-built sump and tank sketches, originally prepared by Earth Tech, are included in Appendix B
of this plan. System P&IDs are included in Appendix C of this plan for reference purposes.
Item Input Description Input Address Scaling Alarm Setpoints
16 Multi Media FilterFlowrate (FIT-103) I:5.3 0 to 1200 GPM
----------
----------
----------
15 Turbidity Meter(AIT-200) I:5.2 0 to 1000 NTU
14Tank T201 & T202
UnderdrainFlowrate (FIT-201)
I:5.1 0 to 2000 GPM
----------
12 Bag Filter 104BPressure (PIT-104B)
13 SpareInput I:5.0 Spare
I:4.3 0 to 75 PSI
High Alarm = 45 PSI
----------
----------
11 Bag Filter 104APressure (PIT-104A) I:4.2 0 to 75 PSI
10 Media Filter 103CPressure (PIT-103C) I:4.1 0 to 75 PSI
High Alarm = 45 PSI
8 Pump 201, 202 & 203Flowrate (FIT-200)
9 Media Filter 103BPressure (PIT-103B) I:4.0 0 to 75 PSI
I:3.3 0 to 5,500 GPM
High Alarm = 15.5 ftLow Alarm = 3.0 ft
High Alarm = 9.0 ftLow Alarm = 0.0 ft
----------
7Sludge Thickener
Tank-1Level (LIT-301)
I:3.2 0 to 10.0 Feet
6 Backwash TankLevel (LIT-400) I:3.1 0 to 15.0 Feet
High Alarm = 6.9 ftLow Alarm = 1.25 ft
4 SRS Influent Flow(FIT-000)
5 Filter Feed TankLevel (LIT-102) I:3.0 0 to 8.0 Feet
I:2.3 0 to 8000 GPM
High Alarm = 30.6 ft
High Alarm = 30.6 ft
----------
3 Storage Tank T202Level (LIT-202) I:2.2 0 to 31.5 Feet
2 Storage Tank T201Level (LIT-201) I:2.1 0 to 31.5 Feet
PLC Analog Inputs
1 Spring ReceivingSump Level (LIT-200) I:2.0 0 to 12.0 Feet High Alarm = 11.0 ft
Low Alarm = 0.8 ft
Illinios Central SpringFlow Treatment System
Table 2: Instrumentation Summary
1 of 11
Item Input Description Input Address Scaling Alarm Setpoints
PLC Analog Inputs
Illinios Central SpringFlow Treatment System
Table 2: Instrumentation Summary
32 SpareInput I:9.3 Spare
----------
----------
----------
31Feed Pumps101 & 102
Flowrate In (FIT-100)I:9.2 0 to 225 GPM
30Feed Pumps103 & 104
Flowrate In (FIT-101)I:9.1 0 to 900 GPM
----------
28Clarifier Output
Sludge Flow(FIT-300)
29 SpareInput I:9.0 Spare
I:8.3 0 to 225 GPM
High Alarm = 35 PSI
High Alarm = 35 PSI
----------
27 GAC Filter 105BPressure (PIT-105B) I:8.2 0 to 75 PSI
26 GAC Filter 105APressure (PIT-105A) I:8.1 0 to 75 PSI
----------
24 Media Filter 103APressure (PIT-103A)
25Storage Tank
Feed Pump HeaderPressure (PIT-200)
I:8.0 0 to 60 PSI
I:7.3 0 to 75 PSI
High Alarm = 7.0 ftLow Alarm = 0.0 ft
----------
High Alarm = 45 PSI
23 Input Pressure toClarifier (PIT-100) I:7.2 0 to 40 PSI
22Sludge Thickener
Tank-2Level (LIT-302)
I:7.1 0 to 8.0 Feet
----------
20 SpareInput
21 Parshall FlumeFlowrate (FIT-102) I:7.0 0 to 4000 GPM
I:6.3 Spare
----------
----------
----------
19 SpareInput I:6.2 Spare
18 Backwash WaterFlowrate (FIT-400) I:6.1 0 to 2000 GPM
----------17 SpareInput I:6.0 Spare
2 of 11
Item Input Description Input Address Scaling Alarm Setpoints
PLC Analog Inputs
Illinios Central SpringFlow Treatment System
Table 2: Instrumentation Summary
34 SpareInput I:10.1 Spare
35 SpareInput I:10.2 Spare
33Process Water Sump
PumpFlowrate (FIT-301)
I:10.0 0 to 225 GPM
Comments
Signature: Date:
36 SpareInput I:10.3 Spare ----------
----------
----------
----------
3 of 11
Item Input Description Input Address Device Alarm Setpoints
7
8
9
10
11
12
2
4
5
6
13
15
16
14
Process Water FloorSump Low Low Level I:13/14
Process Water FloorSump Low Level I:13/15
Level Switch(LSLL-300)
6 in. abovepump intake **
12 in. abovepump intake **
Waste WaterSump High Level I:13/13 Level Switch
(LSH-500)
3 in. above top ofoverflow pipe **
----------
invert of sanitarysewer discharge **
SpareInput I:13/12
SpareInput I:13/10
Backwash TankHigh Level I:13/11
---------- ----------
Filter Feed TankHigh Level I:13/9
Filter Feed TankLow Level I:13/8 Level Switch
(LSL-103)
Level Switch(LSH-103)
3 in. above top ofoverflow pipe **
SpareInput
Tank #104A HighDifferential Pressure I:13/7
I:13/6 ----------
Pressure Differential SwitchPDSH/PDI-101
----------
30 in. wc
ClarifierHigh Level I:13/4
SpareInput I:13/5
Level Switch(LSH-100F)
----------
6 in. above top ofoverflow pipe **
----------
Waste WaterSump High High Level I:13/2
I:13/3
Level Switch(LSHH-500)
----------
Digital Inputs
1
3
SpareInput
Spring ReceivingSump Low Level I:13/0
Spring ReceivingSump High Level I:13/1
Illinios Central SpringFlow Treatment System
Table 2: Instrumentation Summary
Level Switch(LSL-200F)
Level Switch(LSH-200F)
6 in. above top ofdischarge pipe **
Level Switch(LSL-300)
Level Switch(LSH-401)
----------
6 in. above pump intakes **
at bottom of overflow weir **
invert of overflowpipe to SRS **
----------
4 of 11
Item Input Description Input Address Device Alarm Setpoints
Digital Inputs
Illinios Central SpringFlow Treatment System
Table 2: Instrumentation Summary
17 Process Water FloorSump High Level I:14/0 6 in. below
invert of overflow **Level Switch(LSH-300)
invert of overflowpipe to SRS **
----------
----------
----------
18 Process Water FloorSump High High Level I:14/1 Level Switch
(LSHH-300)
I:14/3 Digital input fromcompressor controller
19 SpareInput I:14/2 ----------
----------
21 Incomming ControlPower Lost I:14/4 Digital input from
control relay ----------
20 Air CompressorFault
23 Backwash TankLow Level I:14/6 Level Switch
(LSL-401)6 in. above top ofdischarge pipe **
22 SpareInput I:14/5
24 Tank #104B HighDifferential Pressure I:14/7 Pressure Differential Switch
PDSH/PDI-102
25 in. wc
25 Sludge ThickenerTank-1 High Level I:14/8 Level Switch
(LSH-301F)
30 in. wc
6 in. above overflowweir of tank **
6 in. above overflowweir of tank **
26 Tank #103C HighDifferential Pressure
27 Sludge ThickenerTank-2 High Level I:14/10 Level Switch
(LSH-302)
I:14/7 Pressure Differential SwitchPDSH/PDI-100
28 SpareInput I:14/11 ----------
----------
29 SpareInput I:14/12 ----------
----------
----------
----------
30 SpareInput
31 SpareInput I:14/14 ----------
I:14/13 ----------
32 SpareInput I:14/15 ---------- ----------
5 of 11
Item Input Description Input Address Device Alarm Setpoints
Digital Inputs
Illinios Central SpringFlow Treatment System
Table 2: Instrumentation Summary
33 Pump 201Running I:15/0 Digital input
from field
----------
----------
----------
----------
35 Pump 203Running
36 Pump 310Running I:15/3 Digital input
from field
I:15/2 Digital inputfrom field
37 Pump 309Running I:15/4 Digital input
from field
18 in. wc
38 Tank #105A1 HighDifferential Pressure I:15/5 Pressure Differential Switch
PDSH/PDI-105
----------
18 in. wc
18 in. wc
39 Tank #105B1 HighDifferential Pressure
40 Tank #105A2 HighDifferential Pressure I:15/7 Pressure Differential Switch
PDSH/PDI-106
I:15/6 Pressure Differential SwitchPDSH/PDI-103
41 Tank #105B2 HighDifferential Pressure I:15/8 Pressure Differential Switch
PDSH/PDI-104
25 in. wc
42 Tank #103B HighDifferential Pressure I:15/9 Pressure Differential Switch
PDSH/PDI-107
18 in. wc
25 in. wc
I:15/11 Digital inputfrom field
I:15/10 Pressure Differential SwitchPDSH/PDI-10843 Tank #103A High
Differential Pressure
44 Running onGenerator Power
----------
----------
----------
Digital inputfrom field
SpareInput I:15/13 ----------
----------
48 SpareInput I:15/15 ---------- ----------
47 SpareInput I:15/14 ----------
46
34 Pump 202Running I:15/1 Digital input
from field
45 IncommingPower On I:15/12
6 of 11
Item Input Description Input Address Device Alarm Setpoints
Digital Inputs
Illinios Central SpringFlow Treatment System
Table 2: Instrumentation Summary
51
52
53
61
62
49
58
59
60
54
55
56
57
---------- ----------
I:16/14SpareInput
Limit switchon valve V107
Limit switchon valve V107
----------
Switch closes whenvalve is full open
Switch closes whenvalve is full closed
I:16/11T103C BackwashValve Closed
T103C BackwashValve Open I:16/10 Limit switch
on valve V102Switch closes when
valve is full open
Switch closes whenvalve is full closed
Limit switchon valve V102
64
Filter OutputValve Open I:16/12
SpareInput I:16/15
63
I:16/13Filter OutputValve Closed
T103C InputValve Open I:16/8
I:16/9
Limit switchon valve V101
Limit switchon valve V101
Switch closes whenvalve is full open
Switch closes whenvalve is full closed
T103C InputValve Closed
I:16/7T103B BackwashValve Closed
Switch closes whenvalve is full open
Switch closes whenvalve is full closed
Limit switchon valve V104
Limit switchon valve V104
I:16/5T103B InputValve Closed
Limit switchon valve V103
Limit switchon valve V103
Switch closes whenvalve is full open
Switch closes whenvalve is full closed
T103A BackwashValve Closed I:16/3
Switch closes whenvalve is full open
Switch closes whenvalve is full closed
T103A InputValve Open I:16/0 Switch closes when
valve is full open
Limit switchon valve V106
Limit switchon valve V105
Limit switchon valve V106
Switch closes whenvalve is full closed50 T103A Input
Valve Closed I:16/1 Limit switchon valve V105
----------
T103A BackwashValve Open I:16/2
T103B InputValve Open I:16/4
T103B BackwashValve Open I:16/6
7 of 11
Item Input Description Input Address Device Alarm Setpoints
Digital Inputs
Illinios Central SpringFlow Treatment System
Table 2: Instrumentation Summary
Signature: Date:
Comments
developed by the original engineer. Actual lnstallation of each level switch cannot be determined from within the PLC code.
** Actual installation elevation for all level switches must be field verified. This document references what was stated in the spread sheet
8 of 11
Item Pump Description Pump Tag No. Control Description
15 Filter Pumps P-105 & P-106Backwashing
Pump OnPump Off
14 Filter Pumps P-105 & P-106P-107 & P-108
OK to ActivateFilter Pumps
12
13 Filter Pumps P-105 & P-106P-107 & P-108 Filter Feed Tank Level OK
11 Clarifier Sludge Pumps P-301 & P-302 Timer Mode: Off SetpointTimer Mode: On Setpoint
10 Clarifier Sludge Pumps P-301 & P-302 OK to ActivateSludge Pumps
P-201 & P-202P-203
Lag Pump OnLag Pump Off8 Storage Tank Feed
Pumps
9
7 Storage Tank Feed Pumps
P-201 & P-202P-203
Lead Pump OnLead Pump Off
6 Storage Tank Feed Pumps
P-201 & P-202P-203
OK to Activate StorageTank Feed Pumps
P-103 & P-104 Pump OnPump Off4 Process Feed Pumps
5
5.0 ft1.0 ft
6.0 ft1.75 ft
1.) Incoming power is on2.) Clarifier not High Level3.) Filter Feed Tank less than 6.9 ft.4.) Filter Feed Tank not High Level
1.) Incoming power is on2.) Spring Receiving Sump Level OK
7.0 ft2.25 ft
8.0 ft2.75 ft
1.) Sludge Thickener Tank-1 not High Level2.) Sludge Thickener Tank-1 less than 9.0 ft.
3 Process Feed Pumps P-101 & P-102 Pump OnPump Off
2 Process Feed Pumps P-101 & P-102P-103 & P-104
OK to Activate ProcessFeed Pumps
Pump Control
1 Process Feed Pumps P-101 & P-102P-103 & P-104 Spring Receiving Sump Level OK
Setpoint / Condition
1.) Not Low Level2.) Level greater than 0.8 ft.
Illinios Central SpringExcess Flow Treatment System
Table 2: Instrumentation Summary
240 minutes15 minutes
1.) Not Low Level2.) Level greater than 1.25 ft.
1.) Filter Feed Tank not Low Level2.) Backwash Tank less that 15.5 ft.3.) Backwash Tank not High Level4.) GAC Tank not high Differential Pressure
6.0 ft3.75 ft
9 of 11
Item Pump Description Pump Tag No. Control Description
Pump ControlSetpoint / Condition
Illinios Central SpringExcess Flow Treatment System
Table 2: Instrumentation Summary
30
28
29
27 Sump Pumps P-309 & P-310 Pump Off
26 Sump Pumps P-309 & P-310 Pump On
P-309 & P-310 OK to ActivateSump Pumps
24
25 Sump Pumps
23 Backwash Pumps P-401 & P-402P-403 Pump Sequence selected by operator
22 Backwash Pumps P-401 & P-402P-403 Pump Off
P-401 & P-402P-403 Pump On
P-401 & P-402P-403
OK to ActivateBackwash Pumps20 Backwash Pumps
21 Backwash Pumps
19 Backwash Pumps P-105 & P-106P-107 & P-108 Backwash Tank Level OK
18
P-107 & P-108 Pump OnPump Off
P-105 & P-106Not Backwashing
Pump OnPump Off
16 Filter Pumps
17 Filter Pumps
1.) Filter Feed Tank not less than 4.0 ft.and
2.) Backwash Tank Level greater than 6.0 ft.
8.0 ft2.75 ft
1.) Not Low Level2.) Level greater than 3.0 ft.
1.) P-101, 102, 103, 104 not Running2.) Filter Feed Tank not High Level.3.) Backwash Tank Level OK4.) Incoming Power is On
1.) Filter Feed Tank not greater than 6.5 ft.or
2.) Backwash Tank Level less than 3.0 ft.
1 = 1-2-32 = 2,3,13 = 3,1,2
1.) Filter Feed Tank greater than 6.9 ft.or
2.) Process Water Sump Low Level.
1.) Incoming power is on2.) Filter Feed Tank less than 6.5 ft.3.) Filter Feed Tank not High Level
1.) Filter Feed Tank less than 7.0 ft.and
2.) Process Water Sump not High Level.
5.75 ft2.0 ft
10 of 11
Item Pump Description Pump Tag No. Control Description
Pump ControlSetpoint / Condition
Illinios Central SpringExcess Flow Treatment System
Table 2: Instrumentation Summary
Comments
Signature: Date:
32
31
11 of 11
TABLE 3
ICS ALARMS LIST
HMI ALARM
IDENTIFIER
ICS TREATMENT SYSTEM
ALARM DESCRIPTION
ALARM
SETPOINT
ACTIVATE
ALARM HORN
ACTIVATE
ALARM LIGHT
CALL OUT
ON WIN-911
1 PROCESS FEED PUMP #101 FAILURE x x
2 PROCESS FEED PUMP #102 FAILURE x x
3 PROCESS FEED PUMP #103 FAILURE x x
4 PROCESS FEED PUMP #104 FAILURE x x
5 STORAGE TANK FEED PUMP #201 FAILURE x x
6 STORAGE TANK FEED PUMP #202 FAILURE x x
7 STORAGE TANK FEED PUMP #203 FAILURE x x
8 FILTER FEED PUMP #105 FAILURE x x
9 FILTER FEED PUMP #106 FAILURE x x
10 FILTER FEED PUMP #107 FAILURE x x
11 FILTER FEED PUMP #108 FAILURE x x
12 BACKWASH FEED PUMP #401 FAILURE x x
13 BACKWASH FEED PUMP #402 FAILURE x x
14 PROCESS WATER SUMP PUMP #309 FAILURE x x
15 PROCESS WATER SUMP PUMP #310 FAILURE x x
16 BACKWASH FAILURE x x
17 GAC FILTER #105A HIGH PRESSURE 35 psi x x x
18 GAC FILTER #105B HIGH PRESSURE 35 psi x x x
19 SPRING RECEIVING SUMP LOW LEVEL x x x
20 SPRING RECEIVING SUMP HIGH LEVEL x x x
21 PIT-104A FAILURE x x
24 STORAGE TANKS HIGH LEVEL 30.6 ft or 31.2 ft x x x
25 EFFLUENT/BACKWASH TANK LOW LEVEL 3.0 ft x x x
26 EFFLUENT/BACKWASH TANK HIGH LEVEL 15.5 ft x x x
27 FILTER FEED TANK LOW LEVEL 1.25 ft x x x
28 FILTER FEED TANK HIGH LEVEL 6.9 ft x x x
29 WASTE WATER SUMP HIGH HIGH LEVEL x x x
30 CLARIFIER TANK HIGH LEVEL x x x
31 SLUDGE THICKENING TANK #1 LOW LEVEL 0.0 ft x
32 SLUDGE THICKENING TANK #1 HIGH LEVEL 9.0 ft x x x
33 SLUDGE THICKENING TANK #2 LOW LEVEL 0.0 ft x
34 SLUDGE THICKENING TANK #2 HIGH LEVEL 7.0 ft x x x
35 PUMP #101 AND #102 FAILURE x x x
36 PUMP #103 AND #104 FAILURE x x x
37 PROCESS WATER FLOOR SUMP LOW LOW LEVEL x x x
38 STORAGE TANKS PUMPS ALL IN ALARM x x x
39 PROCESS WATER FLOOR SUMP HIGH HIGH LEVEL x x x
40 PUMP #105 AND #106 FAILURE x x x
41 AIR COMPRESSOR ALARM x x
42 CONTROL POWER LOST x x x
43 BAG FILTER A HIGH DIFFERENTIAL PRESSURE x x x
44 BAG FILTER B HIGH DIFFERENTIAL PRESSURE x x x
45 SAND FILTER C HIGH PRESSURE 45 psi x x
46 SAND FILTER B HIGH PRESSURE 45 psi x x
47 SAND FILTER A HIGH PRESSURE 45 psi x x
48 GAC FILTER A1 HIGH PRESSURE x x x
49 GAC FILTER A2 HIGH PRESSURE x x x
50 GAC FILTER B1 HIGH PRESSURE x x x
51 GAC FILTER B2 HIGH PRESSURE x x x
52 VALVE #101 FAILURE x x x
53 VALVE #102 FAILURE x x x
54 VALVE #103 FAILURE x x x
55 VALVE #104 FAILURE x x x
56 VALVE #105 FAILURE x x x
Table 3: ICS Alarm List 1 of 2 May 2013
TABLE 3
ICS ALARMS LIST
HMI ALARM
IDENTIFIER
ICS TREATMENT SYSTEM
ALARM DESCRIPTION
ALARM
SETPOINT
ACTIVATE
ALARM HORN
ACTIVATE
ALARM LIGHT
CALL OUT
ON WIN-911
57 VALVE #106 FAILURE x x x
58 VALVE #107 FAILURE x x x
59 LIT-200 FAILURE x x x
60 LIT-201 FAILURE x x x
61 LIT-202 FAILURE x x x
62 LIT-100 FAILURE x x x
63 LIT-102 FAILURE x x x
64 LIT-400 FAILURE x x x
65 LIT-301 FAILURE x x x
66 FIT-200 FAILURE x x
67 PIT-103B FAILURE x x
68 PIT-103C FAILURE x x
70 PIT-104B FAILURE x x
71 FIT-301 FAILURE x x
72 FIT-201 FAILURE x x
73 AIT-200 FAILURE x x
74 FIT-103 FAILURE x x
75 FIT-203 FAILURE x x
76 FIT-400 FAILURE x x
77 FIT-102 FAILURE x x
78 LIT-302 FAILURE x x x
79 PIT-100 FAILURE x x
80 PIT-103A FAILURE x x
81 PIT-200 FAILURE x x
82 PIT-105A FAILURE x x
83 PIT-105B FAILURE x x
84 FIT-300 FAILURE x x
85 FIT-101 FAILURE x x
86 FIT-100 FAILURE x x
87 SPRING RECEIVING SUMP FLOAT ALARM x x
88 WASTEWATER FLOOR SUMP FLOAT PROBLEM x x
89 FILTER FEED TANK FLOAT PROBLEM x x
90 BACKWASH TANK FLOAT PROBLEM x x
91 PROCESS WATER SUMP FLOAT PROBLEM x x
92 PUMP #107 AND PUMP #108 FAILURE x x x
93 PUMP #401 AND PUMP #402 AND PUMP #403 FAILURE x x x
94 GENERATOR ACTIVATED x x
97 CONTROL VALVE #206 MALFUNCTION x x x
98 BACKWASH FEED PUMP #403 FAILURE x x
Table 3: ICS Alarm List 2 of 2 May 2013
TABLE 4
SYSTEM COMPONENT CONTACTS
SYSTEM COMPONENTS COMPANY CONTACT(S) PHONE/MOBILE/FAX ADDRESS
Electrical Components A1 ElectRicks, Inc Rick Crouch (812) 332-6951
(812) 325-4737
P.O. Box 6462
Bloomington. IN 47407
Mechanical Components Bowen Engineering Corp. Jon Rauschkolb
Ron Hutchins
(317) 842-2626
(317) 841-4257
10315 Allisonville Rd.
Fishers, IN 46038
Yard Piping/ Site Work Crider & Crider Contractors Brad Bredeweg (812) 336-4452
(812) 287-2317
1900 Liberty Drive
Bloomington, IN 47403
Building Earth Tech, Inc. Chris Wilson (616) 975-4647
(616) 940-4397
5555 Glenwood Hills Parkway SE
Grand Rapids, MI 49588
Process Controls Frakes Engineering Dave Bash (317) 577-3000 ext 259
(317) 577-3005
7950 Castleway Drive, Suite 160
Indianapolis, In 46250
Clarifier Enprotec Don Bzdyl (606) 689-4300
(606) 689-4322
4465 Limaburg Rd.
Hebron, KY 41084
Multi-Media Filters Enprotec Don Bzdyl (606) 689-4300
(606) 689-4322
4465 Limaburg Rd.
Hebron, KY 41084
Bag Filters Werner-Todd Pump Company Mike Brown (317) 875-6900
(317) 452-4331
5381 West 86th Street
Indianapolis, In 46268
Carbon Adsorbers Calgon Corporation Ken McGuire
Vince Lamberti
(412) 787-5692
(412) 787-6749
400 Calgon Carbon Drive
Pittsburgh, PA 15205
Vertical Turbine Pumps BBC Pump & Equipment Jack Tinder (317) 636-1111
(317) 636-5467
1125, W. 16th St., P.O. Box 22098
Indianapolis, IN 46222
End Suction Centrifugal Pumps Werner-Todd Pump Company Mike Brown (317) 875-6900
(317) 452-4331
5381 West 86th Street
Indianapolis, In 46268
Filter Press US Filter JWI Scott Hardy (765) 737-6260
(317) 501-7128
11057 Allisonville Rd. #333
Indianapolis, In 46038
Air Compressor/ Air Dryer Tri State Compressor Air Systems (219) 533-8671
(219) 533-0711
1309 Eisenhower Drive South
Goshen, In 46526
Process Valves Bertsch Company Dan Foster (616) 452-3251
(616) 452-3707
1655 Steele, SW
Grand Rapids, MI 49507
Flow Meters/ Ultrasonic Level
Devices
Endress& Hauser Sara Croucher (317) 535-7138
(317) 835-8498
2350 Endress Place
Greenwood, IN 46143
Large Storage Tanks Kennedy Tank an d Manufacturing
Company
Brian Lunsford (317) 780-3544 833 East Sumner Avenue
Indianapolis, Indiana 46227
Filter Feed Tank Colombian Steel Tank Company Dave Davis
Curtis Crabtree
(913) 621-3700
(913) 621-2145
5400 Kansas Ave., P.O. Box 2907
Kansas City, Kansas 66110
Effluent/ Backwash Supply Tank Colombian Steel Tank Company Dave Davis
Curtis Crabtree
(913) 621-3700
(913) 621-2145
5400 Kansas Ave., P.O. Box 2907
Kansas City, Kansas 66110
Thickener Tanks Pekay Specialty Contracting, Inc. Jim Woelfel (920) 439-1001
(920) 439-1002
112 N. Military Rd., P.O. Box 266
Stockbridge, WI 53088
Emergency Generator McAllister Machinery Co., Inc. Marvin Barkes (317) 543-0405/
(317) 543-0433
7515 E. 30th Street
Indianapolis, IN 46219
Filter Press Feed Pumps Werner-Todd Pump Company Mike Brown (317) 875-6900
(317) 452-4331
5381 West 86th Street
Indianapolis, In 46268
TABLE 5
EQUIPMENT MAINTENANCE - SPARE PARTS LIST
SYSTEM EQUIPMENT EQUIPMENT SPARE PARTS LIST
PART
FAILURE =
SHUT
DOWN? Y/N
REPLACEMENT
SCHEDULE
SHUT DOWN
REQUIRED TO
REPLACE PART
TIME
REQUIRED TO
REPLACE
PART
PART
AVAILABILITY/
DELIVERY
SCHEDULE
STOCK QUANTITY
RECOMMENDED
BY COMPANY
MODEL #/
PART #
ORDERING INFORMATION /
CONTACT
Wet End Kit for pump model # EB2SM, TB3A N As needed N D / 3 weeks 1 476.065.360 Contact Don Bzdyl
CLARIFIER Air End Kit for pump model # EB3SM, TB3A N As needed N A 1 476.102.000 at: (606) 689-4300
Enprotec J600 3/4 Solenoid Valve for Air Station Y As needed Y A 1 8210G095
MULTI-MEDIA TRIAC ET 1300 120V Electric Actuator for 8" Actuated
ValveY As needed N* D / 1-3 weeks 1 already on site
Contact Don Bzdyl
FILTRATION SYSTEMTRIAC ET 2600 120V Electric Actuator for 10"
Actuated ValveY As needed N* D / 1-3 weeks 1 already on site
at: (606) 689-4300
Enprotec J3396-150 Differential Pressure Switch Y As needed N* 1-2 hours A 1
Swing Bolt, 3/4 10 UNC (SA193 B7 Steel) N* As needed N* A 12150286 Warner-Todd Pump Company
BAG FILTERS Pin (SA 193 B7 Steel) N* As needed N* A 12 350140 Contact Mike Brown
Strainrite Eye Nut, 3/4 10 UNC (SA 194 2H Steel) N* As needed N* A 12 150298 at: (317)875-6900
Vendor: Washer (Steel) N* As needed N* A 12 5X2X2
Warner-Todd Cover gasket N* 1 x per year N* A 12 150672
Basket gasket N* 1 x per year N* A 12 363
Basket (#10 woven wire cloth) N* As needed N* D / 3 weeks 2 350153
Filter Bags (10 micron) N* 24
Filter Bags (5 micron) N* 24
Filter Bags (0.5 micron) N*Regularly, when diff.
pressure = 25-30 psidN*
15-20 min. per
bagA 100 already on site
PE 1P25-530
Carbon Changeout N As needed N 0
GAC FILTERS Rupture Disk (pressure relief) Y As needed Y 1-2 hours 24-hour 1 already on site
Model 10 GAC
Rupture Disk
Contact Ken McGuire, (412) 787-
5692, or Mike Stenzel,
Calgon All other parts N As needed Varies 24-hour 0 Varies (412) 787-6809
Plate 1200 CGR LHV 32MM HH6 #1 INT 100 N As needed N 15 min. D / 8 weeks 1111 381 93 Contact Scott Hardy (H&T) at
FILTER PRESS Plate 1200 CGR LHV 32MM HH6 #3 INT 100 N As needed N 15 min. D / 8 weeks 1 111 381 94 (765) 737-6260
US Filter, F1200-100 Cloth 1200 CGR LHV 46409-4 END N As needed N 1-2 days D /4 weeks 2 115 280 14 (317) 501-7128
Cloth 1200 CGR LHV 46409-4 INT NEO NECK N As needed N 1-2 days D / 4 weeks 38 117 350 88
Filter Oil 0.75 FNPT SPIN-ON 25 MICRONS N As needed N 15 min. A 1 111 265 07
Filter Coalescing .25 Tube PARKER N As needed N 15 min. A 1 100 425 15
FILTER PRESS FEED PUMPS Fluid Section Sevice Kit N As needed Use back-up pump A1 637303-GG Warner-Todd Pump Company
Ingersoll-Rand Air Section Service Kit N As needed Use back-up pump A 1 637302 Contact Mike Brown
Model PD30A-AAP-GGG-B at: (317)875-6900
Air Filter Element Y As needed Y 1-2 hours A2 39588777 Tri State Copressor Air System
AIR COMPRESSOR Coolant Filter Element YEvery 2000 hours of
operation. **Y 1-2 hours
A 4 39907175 ph: (219) 533-8671
Ingersoll Rand SSR, Separator Element Y As needed Y 1-2 hours A 1 39831888 fx: (219) 533-0711
EP50-SE V-Belt 67" Y As needed Y 1-2 hours A 5 39160908
Rotary Screw Air Ultra Coolant, 5 gallon Y As needed Y 1-2 hours A 1 39433735
Compressor
IR250CHEE Filter Element Y As needed
Possible shut down
(depending on
location)
1-2 hours A
1 39240932
Start-Up Kit EP50-SE (Includes all of the above) As needed Y 1/2 day A 1 EP50-SE
INSTRUMENTATION Complete electronics for Promag N As needed Y 1/2 day D / 1-2 weeks0
33X MOD-
D21A
Jason Jones, ph: (317) 535-
7138, fx: (317) 535-1489
Endress+Hauser Complete shelf unit 1 N As needed Y 1/2 day D / 1-2 weeks0
FMU 860- R1E
1B8
Complete shelf unit 2 N As needed Y 1/2 day D / 1-2 weeks 0 PMC 731-051
P6M 12N1
Table 5: Spare Parts 1 of 3 May 2013
TABLE 5
EQUIPMENT MAINTENANCE - SPARE PARTS LIST
SYSTEM EQUIPMENT EQUIPMENT SPARE PARTS LIST
PART
FAILURE =
SHUT
DOWN? Y/N
REPLACEMENT
SCHEDULE
SHUT DOWN
REQUIRED TO
REPLACE PART
TIME
REQUIRED TO
REPLACE
PART
PART
AVAILABILITY/
DELIVERY
SCHEDULE
STOCK QUANTITY
RECOMMENDED
BY COMPANY
MODEL #/
PART #
ORDERING INFORMATION /
CONTACT
CENTRIFUGAL PUMPS
ITT A-C 3x2x9 2000 Impeller Trim 8.5" N As needed Use back-up pump D / 3-5 weeks0 52-226-001-229 Warner-Todd Pump Company
250 gpm filter feed pump Impeller Nut N As needed Use back-up pump D / 3-5 weeks 0 52-119-899-002 Contact Mike Brown
Impeller Washer N As needed Use back-up pump D / 3-5 weeks 0 CP-661-001-300 at: (317)875-6900
Shaft Sleeve N As needed Use back-up pump D / 3-5 weeks 0 52-118-010-001
Casing O-Ring N As needed Use back-up pump D / 3-5 weeks 0 CP-751-531-377
Slinger N As needed Use back-up pump D / 3-5 weeks 0 52-117-840-006
Mechanical Seal N As needed Use back-up pump D / 3-5 weeks 0 52-118-510-801
Spacer Sleeve N As needed Use back-up pump D / 3-5 weeks 0 52-105-350-001
Shaft N As needed Use back-up pump D / 3-5 weeks 0 52-226-500-001
Bearings N As needed Use back-up pump D / 3-5 weeks 0 CP-811-005-229
Bearing Caps N As needed Use back-up pump D / 3-5 weeks 0 52-121-337-001
Shaft Retention Ring N As needed Use back-up pump D / 3-5 weeks 0 CP-673-171-118
Retention Ring - OB N As needed Use back-up pump D / 3-5 weeks 0 CP-673-157-281
Retention Ring - IB N As needed Use back-up pump D / 3-5 weeks 0 CP-673-151-281
ITT A-C 4x3x9 2000 Impeller Trim (full) N As needed Use back-up pump D / 3-5 weeks0 52-226-091-229 Warner-Todd Pump Company
850 gpm filter feed pump Impeller Nut N As needed Use back-up pump D / 3-5 weeks 0 52-119-899-001 Contact Mike Brown
Impeller Washer N As needed Use back-up pump D / 3-5 weeks 0 CP-651-001-413 at: (317)875-6900
Shaft Sleeve N As needed Use back-up pump D / 3-5 weeks 0 52-118-013-001
Casing O-Ring N As needed Use back-up pump D / 3-5 weeks 0 CP-751-531-377
Slinger N As needed Use back-up pump D / 3-5 weeks 0 52-117-840-003
Mechanical Seal N As needed Use back-up pump D / 3-5 weeks 0 52-118-510-820
Spacer Sleeve N As needed Use back-up pump D / 3-5 weeks 0 52-118-017-001
Shaft N As needed Use back-up pump D / 3-5 weeks 0 52-226-501-001
Bearings N As needed Use back-up pump D / 3-5 weeks 0 CP-811-007-295
Bearing Caps N As needed Use back-up pump D / 3-5 weeks 0 52-120-465-001
Shaft Retention Ring N As needed Use back-up pump D / 3-5 weeks 0 CP-673-171-156
Retention Ring - OB N As needed Use back-up pump D / 3-5 weeks 0 CP-673-157-354
Retention Ring - IB N As needed Use back-up pump D / 3-5 weeks 0 CP-673-151-354
ITT A-C 6x6x13L 2000 Impeller Trim 11.4" N As needed Use back-up pump D / 3-5 weeks0 52-226-091-331 Warner-Todd Pump Company
1,000 gpm backwash feed pump Impeller Nut N As needed Use back-up pump D / 3-5 weeks 0 52-119-899-001 Contact Mike Brown
Impeller Washer N As needed Use back-up pump D / 3-5 weeks 0 CP-651-001-413 at: (317)875-6900
Shaft Sleeve N As needed Use back-up pump D / 3-5 weeks 0 52-118-013-001
Casing O-Ring N As needed Use back-up pump D / 3-5 weeks 0 CP-751-531-383
Slinger N As needed Use back-up pump D / 3-5 weeks 0 52-117-840-003
Mechanical Seal N As needed Use back-up pump D / 3-5 weeks 0 52-118-510-802
Spacer Sleeve N As needed Use back-up pump D / 3-5 weeks 0 52-118-017-001
Shaft N As needed Use back-up pump D / 3-5 weeks 0 52-226-501-001
Bearings N As needed Use back-up pump D / 3-5 weeks 0 CP-811-007-295
Bearing Caps N As needed Use back-up pump D / 3-5 weeks 0 52-120-465-001
Shaft Retention Ring N As needed Use back-up pump D / 3-5 weeks 0 CP-673-171-156
Retention Ring - OB N As needed Use back-up pump D / 3-5 weeks 0 CP-673-157-354
Retention Ring - IB N As needed Use back-up pump D / 3-5 weeks 0 CP-673-151-354
Table 5: Spare Parts 2 of 3 May 2013
TABLE 5
EQUIPMENT MAINTENANCE - SPARE PARTS LIST
SYSTEM EQUIPMENT EQUIPMENT SPARE PARTS LIST
PART
FAILURE =
SHUT
DOWN? Y/N
REPLACEMENT
SCHEDULE
SHUT DOWN
REQUIRED TO
REPLACE PART
TIME
REQUIRED TO
REPLACE
PART
PART
AVAILABILITY/
DELIVERY
SCHEDULE
STOCK QUANTITY
RECOMMENDED
BY COMPANY
MODEL #/
PART #
ORDERING INFORMATION /
CONTACT
VERTICAL TURBINE
PUMPS
Peerless 16MC-1 stage None recommended N Use back-up pump BBC Pump & Equip.
2,500 gpm storage tank feed pump Jack Tinder
ph: (317) 636-1111
Peerless 12LD-1 stage None recommended N Use back-up pump fx: (317) 636-5467
1,000 gpm process feed pump
Peerless 8LB - 3 stage None recommended N Use back-up pump
200 gpm process feed pump
Peerless 7LB - 5 stage None recommended N Use back-up pump
Process water sump pump
Ingersoll-Rand Fluid Section Sevice Kit N As needed Use back-up pump637303-GG Tri State Copressor Air System
Model PD30A-AAP-GGG-B Air Section Service Kit N As needed Use back-up pump 637302 ph: (219) 533-8671
Filter Press Feed Pumps Spacer N As needed Use back-up pump 92876 fx: (219) 533-0711
MISCELLANEOUS
EQUIPMENT
Generator Fuel Filter 2 1R0749 MacAllister Engine Power
Oil Filter 2 1R0716 Marvin Barkes
Air Cleaner 2 7E1571 ph: (317) 543-0405
Fan Belt Set 1 6N9158
Safety Switches Bussman Fuse for Pump P-101, P-102 2 FRS-R-15 A1 ElectRicks, Inc
Bussman Fuse for Pump P-103, P-104 2 FRS-R-50 Rick Crouch
Bussman Fuse for Pump P-105, P-106 2 FRS-R-60 ph: (812) 332-6951
Bussman Fuse for Pump P-107, P-108, P-201, P-202, P-
203 2 FRS-R-200 fax: (812) 325-4737
Bussman Fuse for Pump P-301, P-302 2 FRS-R-40
Bussman Fuse for Pump P-309, P-310 2 FRS-R-12
Bussman Fuse for Pump P-401, P-402 2 FRS-R-80
Control Panel Control Relay 2 AB700-PK400A1
Fuse 2 LPS-RK-20SP
Fuse 2 FNQ-20
Fuse 5 FNQ-4
Fuse 5 FNQ-1
PLC Power Supply 1 1746-P4
PLC 13-Slot Chassis 1 1746-A13
PLC Processor 1 1747-L553
PLC Rio Scanner Card 1 1747-SN
PLC Analog Input Card 1 1746-NI4
PLC Analog Output Card 1 1746-NO4
PLC 120V Input Card 1 1746-IA16
PLC 120V Output Card 1 1746-OA16
VFDs
Level Float Switches 2 already on site
NOTES:
Part Availability A = Available, delivery anticipated to be within a week * Stock basket for Bag Filtration System only if system is used for rough duty.
D = Delayed availability ** Replace the air compressor coolant filter element after the first 150 hours of operation (1-2 weeks), then every 2000 hours after that.
N = No Y= Yes
N* = No shut down, send all flow to other filters
Table 5: Spare Parts 3 of 3 May 2013
TABLE 6
PREVENTIVE MAINTENANCE SCHEDULE
TIME INTERVAL (1)
EQUIPMENT ID / PART ID ACTION
RUNNING
HOURS (1)
ONE
DAY
ONE
WEEK
ONE
MONT
H
THREE
MONTH
S
SIX
MONTH
S
YEARL
Y
TWO
YEARS
THREE
YEARS
Ingersoll Rand Air Compressor
Coolant level Inspect Weekly X
Discharge air temperature Inspect Weekly X
Separator element differential Inspect Weekly X
Air filter Delta P (at full load) Inspect Weekly X
Coolant filter Replace 150X (initial
only)
Temperature Sensor Check 1,000 X
Hoses Inspect 1,200 X
Coolant filter Replace 2,000X (after
initial)
V-belt/Belt tension Inspect 2,000 X
Separator scavenge screen and orifice Clean 4,000 X
Cooler Cores Clean 4,000 X
Air filter Replace 4,000 X
Separator Element Replace when delta P is 3X the initial delta P or max delta P of 12 PSI at full load or upon warning display
SSR coolant Replace 6,000 X
Ultra coolant Replace 8,000 X
Starter contactors Inspect 8,000 X
Drive motor lubrication Service - See Section 5.15 of O&M Manual
AirCel Air Dryer
Refrigerant gauges Check X
Condensate drain separator Check/clean/drain X
Valve Positions Inspect X
Condenser Coils Clean X
Gauge Readings Check X
Oil Removal Filter (Coalescer) Check/replace as nec. X
Hot Gas Bypass Check X
Table 6: Preventative Maintenance Schedule 1 of 6 May 2013
TABLE 6
PREVENTIVE MAINTENANCE SCHEDULE
TIME INTERVAL (1)
EQUIPMENT ID / PART ID ACTION
RUNNING
HOURS (1)
ONE
DAY
ONE
WEEK
ONE
MONT
H
THREE
MONTH
S
SIX
MONTH
S
YEARL
Y
TWO
YEARS
THREE
YEARS
Caterpillar Emergency Generator
Insulation Check X
Grease for bearing lubrication Add X
Grease for bearing lubrication Replace X
Clutch Check/adjust 125 X
Valve Lash Check/adjust 250 (initial)
Engine Crank Case - Before starting engine Check/ add oil X
Cooling System - Before starting engine Check/ add coolant X
General walk-around - Before starting engine Inspection X
Air Cleaner Indicator - Before starting engine Check X
Belts - Before starting engine Inspection X
Batteries - Before starting engine Clean 250 X
Block Heater -Before starting engine Check X
Governer - Before starting engine Check/ add fluid X
Gauges condition of - Before starting engine Inspection X
Air System (if equipped) - Before starting engine Check X
Control Panel - Before starting engine Inspection X
Generator - Before starting engine Inspection X
Generator space heaters - Before starting engine Check X
Oil pressure gauge - While engine running Check X
Fuel pressure gauge - While engine running Check X
Engine Crank Case - While engine running Check/ add fluid X
Frequency - While engine running Check X
Generated voltage - While engine running Check X
Generator louvers - While engine running Check X
Generator air inlet filter - While engine running Check X
Leaks and noises - While engine running Check X
Starter Winding Temp. - While engine running Check X
Bearing Bracket Temp. - While engine running Check X
Automatic Switch Positions - Engine stopped Check X
Fuel Tank - After engine stopped Check/ fill X
Battery charger amps- After engine stopped Check X
Malfunction Report - After engine stopped Document X
Walk Around Inspection - Before starting engine Check X
Cooling System Element - Before starting engine Replace X
Table 6: Preventative Maintenance Schedule 2 of 6 May 2013
TABLE 6
PREVENTIVE MAINTENANCE SCHEDULE
TIME INTERVAL (1)
EQUIPMENT ID / PART ID ACTION
RUNNING
HOURS (1)
ONE
DAY
ONE
WEEK
ONE
MONT
H
THREE
MONTH
S
SIX
MONTH
S
YEARL
Y
TWO
YEARS
THREE
YEARS
Fuel System - Before starting engine Drain water & sed. 250 X
Air Cleaner Element - Before starting engine Clean/Replace X
Engine Crank Case - Before starting engine Check/ add oil X
Crankcase Breather - Before starting engine Clean 250 X
Valve Lash - Before starting engine Check/adjust X
Linkages - Before starting engine Check/adjust/lube 1,000 X
Engine Protective Devices - Before starting engine Check/test 1,000 X
Batteries - Before starting engine Clean/check X
Engine - Before starting engine Wipe down/clean X
Generator - Before starting engine Check/clean X
Generator bearing/bracket - Before starting engine Inspect/lube X
Generator Start Check X
Engine Crank Case - While engine running Check/ add fluid X
Generator louvers - While engine running Check X
Generator air inlet filter - While engine running Check X
Engine Mounts - While engine running Inspection X
Leaks and noises - While engine running Check X
Load Test - While engine running Perform X
Starter Winding Temp. - While engine running Check X
Bearing Bracket Temp. - While engine running Check X
Walk Around Inspection - After engine stopped Inspection X
Scheduled Oil Sampling - After engine stopped Collect 250 X
Engine oil and Filter - After engine stopped Change/replace 250 X
Generator Air inlet filter - After engine stopped Clean/recharge X
Fuel Tank - After engine stopped Check/fill X
Battery charger amps- After engine stopped Check X
Automatic Switch Positions - Engine stopped Inspection X
Space heater - Before engine started Inspection X
Generator - Before starting engine Inspection X
Cooling System - Before starting engine Drain/clean/replace X
Hoses and belts - Before starting engine Replace X
Batteries - Before starting engine Replace X
Turbocharger - Before starting engine Inspect/check 3,000 X
Engine - Before starting engine Adjust-tune up X
Generator bearing/bracket - Before starting engine Inspection X
Table 6: Preventative Maintenance Schedule 3 of 6 May 2013
TABLE 6
PREVENTIVE MAINTENANCE SCHEDULE
TIME INTERVAL (1)
EQUIPMENT ID / PART ID ACTION
RUNNING
HOURS (1)
ONE
DAY
ONE
WEEK
ONE
MONT
H
THREE
MONTH
S
SIX
MONTH
S
YEARL
Y
TWO
YEARS
THREE
YEARS
Generator Start Inspection X
Engine Crank Case - While engine running Check/ add fluid X
Generator louvers - While engine running Check X
Generator air inlet filter - While engine running Check X
Exhaust System - While engine running Leak check/repair X
Leaks and noises - While engine running Check X
Load Test - While engine running Perform X
Starter Winding Temp. - While engine running Check X
Walk Around Inspection - After engine stopped Inspection X
Scheduled Oil Sampling - After engine stopped Sample X
Engine oil and filter - After engine stopped Change/replace X
Coolant analysis - After engine stopped Sample X
Fuel Tank - After engine stopped Check/fill X
Battery charger amps- After engine stopped Check X
Automatic Switch Positions - Engine stopped Inspection X
Coolant/Antifreeze SAC Test/add SAC 250
Fuel System - Clean primary filters Clean 250
Fuel System - Replace final filters Replace 250
Belts/ Hoses/ Clamps Inspect/replace 250
Fan drive bearing (if equipped) Lube 250
Radiator fins/ aftercare Inspect/check 250
Coolant/Antifreeze Drain/clean/replace 3,000
Thermostats Replace 3,000
Crankshaft vibration damper Inspect 3,000
Valve lash, valve bridge, valve rotators Check/adjust 3,000
Fuel ratio control, set point and low idle Check/adjust 3,000
Fuel injection nozzles Test/exchange 5,000
Alternator, air compressor Inspect/exch. 5,000
Water pump, starter, turbocharger Inspect/exch. 5,000
Overhaul Perform 10,000
Table 6: Preventative Maintenance Schedule 4 of 6 May 2013
TABLE 6
PREVENTIVE MAINTENANCE SCHEDULE
TIME INTERVAL (1)
EQUIPMENT ID / PART ID ACTION
RUNNING
HOURS (1)
ONE
DAY
ONE
WEEK
ONE
MONT
H
THREE
MONTH
S
SIX
MONTH
S
YEARL
Y
TWO
YEARS
THREE
YEARS
U.S. Filter / JWI Filter Press
Cylinder Boot Inspect/repair/replace X
Electro-Hydraulic Power Unit - Clamp pressure Check/adjust X
Electro-Hydraulic Power Unit - Oil level Check/ add fluid X
Electro-Hydraulic Power Unit - Relief valve Check/adjust X
Electro-Hydraulic Power Unit - Hydraulic oil & filter Change/replace X
Process Manifold - Plumbing Inspect X
Process Manifold - Process Valves Inspect X
Process Manifold - Process Valves Remove/inspect seals X
Plate shifter - Lift Cylinder Clean X
Plate shifter - Push cylinders Clean X
Plate shifter - Lift Cylinder Operate w/o plates X
Plate shifter - Push cylinders Operate w/o plates X
K/M Specialty Pumps/ Filter Press Feed Pumps
Flush Sludge Pumps with Water Between Uses
Invert Pump Prior to Dissassembly To Drain Prior To Servicing
Keystone Valve Electric Actuator
Fixing Screws Check X
Wiring Terminal Block Screws Check X
Wiring Disconnect Terminations Check X
Torque and Travel Limit Switch Operating Cams Check X
Electrical Compartment Check X
Cover O-ring Check X
Indicator Shaft O-ring Check X
Ground Terminal Check X
ITT End Suction Centrifugal Pumps
Bearing Temperature Check X
Bearing Grease Check/replace X
Packing Check/replace X
Shaft/shaft sleeve (scoring of) Check X
Pump Alignment Check X
Motor Alignment Check X
Rotating Elements Inspect X
Wearing clearances Check X
Table 6: Preventative Maintenance Schedule 5 of 6 May 2013
TABLE 6
PREVENTIVE MAINTENANCE SCHEDULE
TIME INTERVAL (1)
EQUIPMENT ID / PART ID ACTION
RUNNING
HOURS (1)
ONE
DAY
ONE
WEEK
ONE
MONT
H
THREE
MONTH
S
SIX
MONTH
S
YEARL
Y
TWO
YEARS
THREE
YEARS
Stuffing Box Piping Clean Out X
Total dynamic suction and discharge head Measure/record X
Peerless Vertical Turbine Pumps
Water Flow to Pump Seats Check X
Hach Surface Scatter 6 Turbidimeter
Standardization Check Check X
Calibration Perform X
Calgon Model 10 GAC System
Backwash Perform backwash before the differential pressure across a vessel reaches 20 psi.
Vessel Internal Parts Inspection X
Carbon Transfer Perform as needed
Enprotec Multi-Media Filters
Backwash Perform/Record DP X
Top Media Level Inspection Add media as needed X
Wash Media Perform as needed
Media Transfer Perform as needed
Enprotec Clarifier
Inspect Clarifier Monthly X
Clean Plates by Draining and Powerwashing Annually X
Remove and Clean Plates Individually Perform as needed
Flush Sludge Pumps with Water Between Uses
Sludge Pump Check Valve Inspect/Repair As Nec.
Sludge Pump Diaphragm Inspect/Repair As Nec.
Pekay/Alstor - Thickeners
Vessel Integrity Inspection Empty/clean/inspect X
Earth Tech - Bar Screen (North of RR)
Flow Through Screen Inspect/Clean X
Clean Screen of Obstructions Clean X
NOTES:
(1) Maintenance task should be performed in accordance with the indicated time interval or the specific "Running Hours" time period, whichever occurs first.
(2) Plumbing and HVAC equipment were not evaluated for preventive maintenance purposes.
Table 6: Preventative Maintenance Schedule 6 of 6 May 2013
APPENDIX A
Standard Operating Procedures
Index of SOPs
1 SRS Spring Diversion……………………………………………….…………………1
2 SRS Atmospheric Testing…………………...…………………………………………5
3 SRS Cleaning…………………………………………………………………………10
4 SRS Pump Change Out………………………………………….……………………17
5 SRS Daily Flow Report…………………………………….…………………………24
6 PTS Clarifier Sludge Pump Settings……….…………………………………………27
7 PTS Bag Filter Change……………………………..…………………………………29
8 PTS Carbon Backwash A1 and B1 Lead…...…………………………………………31
9 PTS Carbon Backwash A2 and B2 Lead…………………...…………………………33
10 PTS Decanting Thickeners……………………………………………………………35
11 PTS Filter Press……………………………………….………………………………37
12 PTS Carbon Exchange Procedure………………………………………………….....40
13 2500gpm SRS Pump Back Flush Procedure……………………………………….....44
- 1 -
ICSTF Standard Operating Procedure (SOP)
Spring Diversion
(Revised June 2011)
- 2 -
Purpose
The purpose of this procedure is to prevent spring water from flowing into the Spring
Receiving Sump (SRS). This will facilitate entry into the sump for maintenance and cleanup
activities. Spring waters will be diverted from the SRS inflow
Summary
The spring inlet pipe immediately upstream of the SRS must be blocked to prevent inflow of
spring water into the SRS while personnel are performing work inside the sump. Spring water
will be captured and diverted to the main Illinois Central Spring Treatment Facility (ICSTF)
building for treatment. Water must be pumped from the spring inlet pipe manhole to the floor
sump in the main building.
Preparations and Planning
Scheduling and Prerequisite Conditions
For safety and in consideration of limited pumping capacities, spring diversion operations
should be scheduled to occur during minimum spring flow periods and when no storm events
are likely. Spring flow rates no greater than 100 gpm are required for this spring water
diversion procedure. When favorable conditions are obtained, work may proceed. For
routine quarterly inspections or as-needed removal of accumulated sediment and debris from
the SRS, no subcontractors will be needed.
Safety
The spring inlet pipe manhole is a permit required confined space. A four-gas meter will be
used to confirm adequate oxygen level before entry into the manhole. Entry into the manhole
will conform to the PSARA Standard Operating Procedure for Confined Space, SP-012.
Testing to determine PCB concentration in the manhole atmosphere will be performed prior to
implementation of this procedure. Adequate breathing protection will be used as needed
based on the results of testing. It is anticipated that adequate ventilation will obviate the need
for respirators.
Equipment and Materials List
a. 3-inch gasoline powered trash pumps or pneumatic diaphragm pump, 2 (1 for backup).
b. 3-inch discharge hose with cam-lock fittings, 500 feet.
c. 3-inch suction hose, 2, each at least 20 feet in length.
d. 1-inch air hose with Chicago fittings, 500 feet, for diaphragm pump, if used.
e. Two panels of ¾-inch plywood laminated with compressible gasket material for sealing
off the spring water inflow to the SRS (see sketch, Figure 1).
f. Mounting hardware (4-anchor bolts with nuts, u-channel or flat bar)
g. Four-gas meter.
h. Fuel, if using gas-driven pumps.
i. PPE, Level B; plus waders and nitrile gloves.
- 3 -
j. Rotary hammer drill (only needed for initial panel hardware installation)
k. Electric extension cord (to be used with ground fault interrupter)
Note: Pumps and hoses must be tested and verified operational and leak-free prior to use in
this procedure.
Procedure
1. Conduct safety briefing with all personnel involved in the Spring Diversion
operations. Review permit-required confined space operations as described in PSARA
SP-012, and assign entrant and attendant duties to appropriate personnel.
2. Lay out hoses from main ICSTF floor sump to the spring inlet pipe manhole and
connect to main diversion pump. Position the back-up pump where it can most
quickly be put into use if needed.
3. Remove manhole cover from spring inlet pipe. Measure oxygen level. If oxygen level
safe, proceed to insert suction hoses from both the primary and the backup pumps into
the manhole.
4. Start main diversion pump.
5. Entrant will then enter the manhole and attendant will pass him the first panel section
to cover the lower half of the spring inlet pipe leading into the SRS.
Note: Prior to diverting water for the first time, the hardware to secure the panels in
place must be installed. This involves marking and drilling holes into the concrete
face wall of the SRS inlet opening and installation of anchor bolts. Then the panels
and securing hardware must be test fitted and adjusted as necessary.
6. Entrant positions the first panel, secures in place, observes for effective sealing, then
confirms effective pumping as water depth increases to cover the pump intake.
7. Second panel is passed to the entrant, who mounts and secures it in position to
completely cover the inlet opening into the SRS.
requires the presence of an attendant.
9. A single person will be required to constantly monitor pumping operations and water
levels within the spring inlet pipe manhole until spring diversion is no longer needed.
If the primary pump fails, the attendant will quickly disconnect the discharge line from
the primary pump and connect it to the backup pump. The backup pump will be
started and normal operations resumed. A backup pump type that does not require
priming is highly desirable.
8. Entrant then exits the confined space. Note: Any re-entry into the confined space
- 4 -
10. After completion of all work within the SRS Sump, permit-required confined space
entry procedures will be used to enter the manhole for removal of diversion panels.
11. After all personnel have exited the manhole, pumping will be terminated, suction hose
will be removed and the manhole cover replaced.
12. Remove all tools and equipment from area.
- 5 -
ICSTF Standard Operating Procedure (SOP)
Spring Receiving Sump (SRS)
Atmospheric Testing
(Revised June 2011)
- 6 -
Purpose
Atmospheric testing for the presence of Polychlorinated Byphenols (PCBs) of the ICSTF
Spring Receiving Sump (SRS) is to be performed to determine proper level of personal
protective equipment (PPE) needed to perform various actions within the sump. This
procedure should be undertaken initially and whenever modifications to the sump system are
made or when changes in the PCB content of the incoming water are detected. This procedure
and attachments detail the steps necessary for safe testing of the atmosphere inside the SRS.
Summary
The SRS Sump atmospheric testing procedures described herein detail the preparations for
procedural setup, safe entry, sample collection, sample analysis and result interpretation.
Preparations and Planning
Scheduling
For safety and in consideration of limited pumping capacities, all SRS atmospheric testing
operations should be scheduled to occur during minimum spring flow periods and when no
storm events are likely. Spring flow rates no greater than 100 gpm are required for
implementation of this procedure.
Safety
Personnel involved with atmospheric testing activities will be OSHA HAZWOPER and
confined space trained. The Spring Receiving Sump is a permit-required confined space. A
four-gas meter will be used to confirm adequate oxygen level before entry into the SRS. Air
monitoring will be performed every 15 minutes while workers are in the SRS. Entry into the
SRS will conform to PSARA Technologies’ Standard Operating Procedure for Confined
Space, SP-012. Please see attached copy.
Equipment and Materials List
a. PSARA Confined Space Entry Permits
b. PSARA Air Monitoring Forms
c. Level C PPE with organic vapor cartridges
d. Flashlight
e. Tripod and harness system for fall arrest
f. Two-way radio communication system
g. Multi-RAE (or similar) real time gas monitor
h. Dry-Cal flow calibrator (or similar)
i. Two SKC low flow personnel pumps (or similar) and associated tubing
j. 100mg/50mg Florisil media and 13mm glass fiber filter media suitable for NIOSH
Method 5503
k. Two pump stands or tripods
l. Plastic pool or similar
m. Garbage bags
- 7 -
Procedure
1. Conduct safety briefing with all personnel involved in the sump atmospheric testing
operations. Assign entrant and attendant duties to appropriate personnel.
2. Initiate spring water inflow diversion. See Spring Diversion Procedures.
3. Pump SRS Sump to lowest level by SRS Process Pumps.
4. Set pump controls to manual operation at PLC panel (plant operator)
5. Set disconnect(s) to off position at main motor control panel(s) in SRS building. (See
table 1 for disconnect locations for each SRS pump)
6. Follow Lock Out Tag Out (LOTO) procedures in accordance with ICSTF HASP to
safely isolate the SRS pumps/motors from all potentially hazardous energy sources.
7. For each process pump, close and lock out butterfly valve located closest to the
effluent side of the pump flange. (See Table 2 for valve number) This is to prevent the
inadvertent or unexpected release of backflow and/or back flush water from the main
pump line leading to the main ICSTF plant. Lock Out/Tag Out required.
8. Remove sump access cover located in northwest corner of SRS building.
9. Set up Tripod and harness system over the access point.
10. Use four-gas meter to determine oxygen levels. Do not enter until safe levels are
obtained. Confine Space Entry required. First entrant will use oxygen meter to
confirm adequate oxygen at working level in the sump before any other personnel
enter the SRS. Oxygen level monitoring will be performed every 15 minutes while
personnel are present inside the sump area.
11. One entrant wearing level C PPE and organic vapor cartridges will be in the sump
working to set up and remove monitors as needed. One attendant will be continually
observing the entrant for safety monitoring.
Baseline Testing (no ventilation)
12. Calibrate and assemble two personnel pumps for use according to the procedures in
NIOSH Method 5503 for Polychlorobiphenyls.
a. Set flow by opening waste gate and adjusting gross controls to approximately 1
L/min; place low flow adapter and media in line and adjust the fine control
until desired flow rate is reached.
- 8 -
b. Flow rates should be set to close to 0.2 L/min for an approximate total volume
of 36 L for a 3 hour sample. Do not exceed 0.2 L/min.
c. Initial flow rate should be recorded as the average of 3 readings with no
adjustments made.
13. Lower both stands into the sump area and place them at a wide interval within the
sump area.
14. Position the two pumps on the stands at approximately 5 feet above floor level and
start them.
15. Allow the pumps to sample for a total of three hours, recording the start and stop times
of each pump.
16. Stop and remove the pumps.
17. Prepare the samples for shipment.
a. Use the air flow calibrator to read the current flow rate 3 times, average this
and then again with the initial readings to determine average flow rate for the
entire sample period.
b. Multiply the total time in minutes that the pump ran by the average flow rate to
determine total volume of the sample.
c. Cap the florisil tube ends and place the filter media in a glass vial with clean
forceps.
Ventilated Sampling
18. Turn on the SRS ventilation system and allow it to run for a minimum of one hour
before continuing to the next step.
a. Allow the ventilation system to continually run throughout the next sampling
procedure.
19. Calibrate and assemble two personnel pumps for use according to the procedures in
NIOSH Method 5503 for Polychlorobiphenyls as outlined in step 12.
20. Position the sampling pumps as before and allow them to sample for three hours,
recording the start and stop times for each pump.
21. Stop and remove the pumps.
- 9 -
22. Prepare the samples for shipment to the lab as outlined in step 16.
23. Label and catalog all samples on PSARA Air Monitoring Forms.
24. Submit one unused set of florisil and glass fiber filter media to the lab as a blank.
25. Ship all samples to an ACGIH accredited lab for analysis by Gas Chromatography and
Electron Capture Detection as detailed in NIOSH 5503.
26. Final PCB concentration is determined by dividing the lab data result by the sample
volumes obtained in steps 17 and 22.
27. Remove all equipment from the SRS sump.
28. Upon exiting from the SRS sump, personnel will step into a plastic wading pool and
remove PPE. Used PPE and dirty disposable materials will be collected and disposed
in the rolloff in the main building. Contaminated tools and rubber boots will be
decontaminated in a designated area over the floor sump in the main facility.
29. Remove all tools, equipment and other cleanup materials from the SRS building area.
30. Recover from LOTO condition - Remove lock(s) from pump power supply at
electrical panel. Remove locks and open discharge butterfly valves at each previously
locked out pump.
31. Halt spring water inflow diversion. See Spring Diversion Procedures.
32. Reset pump(s) to automatic mode at the PLC panel.
33. The plant operator will restart the treatment system and verify normal plant operations.
- 10 -
ICSTF Standard Operating Procedure (SOP)
Spring Receiving Sump (SRS) Cleaning
(Revised June 2011)
- 11 -
Purpose
Cleaning of the ICSTF Spring Receiving Sump (SRS) is performed as needed and determined
by periodic inspection. This procedure and attachments detail the steps necessary for the
removal of foreign materials from the SRS.
Summary
The SRS Sump cleaning procedures described herein detail the preparations for SRS cleaning,
safety measures, SRS process pumps shutdown and foreign material removal, as well as the
preparations for pumps restart.
Preparations and Planning
Scheduling
For safety and in consideration of limited pumping capacities, all SRS cleaning operations
should be scheduled to occur during minimum spring flow periods and when no storm events
are likely. Spring flow rates no greater than 100 gpm are required for implementation of this
procedure.
Safety
Personnel involved with sump cleaning activities will be OSHA HAZWOPER and confined
space trained.
The Spring Receiving Sump is a permit-required confined space. A four-gas meter will be
used to confirm adequate oxygen level before entry into the SRS. Air monitoring will be
performed every 15 minutes while workers are in the SRS. Entry into the SRS will conform
to PSARA Technologies’ Standard Operating Procedure for Confined Space, SP-012. Please
see attached copy. Ventilation to reduce PCBs in the SRS atmosphere below levels requiring
entrants to wear respirators with organic vapor cartridges may be possible. PSARA
Technologies defines this limit as 0.125 mg/m3, which is more stringent than the OSHA
permissible exposure limit of 1 mg/m3. Testing to determine adequate ventilation will be
designed and performed prior to implementation of these SRS cleaning procedures.
Equipment and Materials List
a. 1.5-inch discharge hose with cam-lock fittings, 200 feet
b. 1.5-inch suction hose, 5 feet
c. 1.5-inch pneumatic diaphragm pump
d. air hose, 200 feet, for diaphragm pump
e. air hose Y-adaptor if using another diaphragm pump as spring diversion backup
f. 1.5 inch discharge hose for diaphragm pump, 200 feet
g. 50 feet garden hose with spray nozzle
h. 8-12 plastic 5-gal buckets
i. 2 flat blade shovels
j. pool skimmer net
- 12 -
k. 2-3 30-gallon garbage cans
l. 30 feet rope
m. Tripod for confined space rescue
n. Safety harnesses for all entrants, 3 minimum
o. Four-gas meter
p. Pickup truck with lift gate
q. Two-wheel dolly
r. PPE, Level D (Level C if organic vapor breathing protection is needed) with Tyvek
overalls, protective gloves and waterproof boots
s. Plastic wading pool
Note: Pumps and hoses must be tested and verified operational and leak-free
prior to use in this procedure.
SRS Inspection
Entry into the SRS for cleaning provides the opportunity to inspect the SRS and equipment in
it for problems and general condition. An Inspection Checklist is attached.
Procedure
1. Conduct safety briefing with all personnel involved in the sump cleaning operations.
Assign entrant and attendant duties to appropriate personnel.
2. Initiate spring water inflow diversion. See Spring Diversion SOP.
3. Pump SRS Sump to lowest level by SRS Process Pumps.
4. Set pump controls to manual operation at PLC panel (plant operator).
5. Set disconnect(s) to off position at main motor control panel(s) in SRS building. (See
table 1 for disconnect locations for each SRS pump).
6. Follow Lock Out Tag Out (LOTO) procedures in accordance with ICSTF HASP to
safely isolate the SRS pumps/motors from all potentially hazardous energy sources.
7. For each process pump, close and lock out butterfly valve located closest to the
effluent side of the pump flange. (See Table 2 for valve number) This is to prevent the
inadvertent or unexpected release of backflow and/or back flush water from the main
pump line leading to the main ICSTF plant. Lock Out/Tag Out required.
8. Remove sump access cover located in northwest corner of SRS building.
9. Turn on SRS Sump ventilation fan; the switch is located on north wall next to ISCO
equipment. PSARA Technologies’ Standard Operating Procedure for Confined Space,
SP-012, section IV Preparation for Entry will be followed. Pre-entry ventilation
- 13 -
duration will be determined by specific testing in the SRS, and may be longer than the
30 minutes rule-of-thumb specified in SP-012.
10. Use four-gas meter to determine oxygen levels. Do not enter until safe levels are
obtained. Confine Space Entry required. First entrant will use oxygen meter to
confirm adequate oxygen at working level in the sump before any other personnel
enter the SRS. Oxygen level monitoring will be performed hourly for the duration of
sump cleaning activities.
11. Lower garden hose into sump and spray upper sump floor sediment into the lower
sump area.
12. Remove any live animals, e.g. turtles, frogs, snakes, etc. using pool skimmer net.
Release animals at some distance away from SRS building.
13. Position the 1.5-inch pneumatic diaphragm pump inside the sump. Connect both
discharge and suction hoses, then the air supply hose to the diaphragm pump and use
pump to move remaining water from SRS to the spring diversion manhole. Once all
standing water has been evacuated from the sump, work to remove sediment and
debris can begin.
14. One or two people will be in the sump working to remove sediment and debris using
shovels and buckets. One attendant will be continually observing the entrant(s) for
safety monitoring.
15. Additional staffing needed: One person will be constantly monitoring the spring
diversion pumps. Two people will be involved in manually raising buckets of sediment
out of the SRS by rope and placing material in the 30-gallon garbage cans. The
garbage cans will be transported to the disposal rolloff in the main facility building
using a truck with lift gate. Excess water will be decanted out of the rolloff by the
plant operator when needed. It is not anticipated that solidification will be required.
16. Prior to personnel leaving the SRS sump the following should be inspected: sump
lighting, pump assembly columns, pump intake screens, debris accumulation
characteristics, float switches, and sump floor & walls for cracks. An inspection form
(attached) should be completed by the plant operator or on-site field supervisor.
17. Upon exiting from the SRS sump, personnel will step into a plastic wading pool and
remove PPE. Used PPE and dirty disposable materials will be collected and disposed
in the rolloff in the main building. Contaminated tools and rubber boots will be
decontaminated in a designated area over the floor sump in the main facility.
- 14 -
18. Remove all tools, equipment and other cleanup materials from the SRS building area.
19. Recover from LOTO condition - Remove lock(s) from pump power supply at
electrical panel. Remove locks and open discharge butterfly valves at each previously
locked out pump.
20. Halt spring water inflow diversion. See Spring Diversion Procedures.
21. Reset pump(s) to automatic mode at the PLC panel.
22. The plant operator will restart the treatment system and verify normal plant operations.
- 15 -
Table 1
SRS Pumps Electrical Disconnect Locations
Pump/Motor # Pump HP Pump Size Disconnect Location Panel/Breaker Number
# P-101 5 200 GPM SRS building west wall # MMC P-101
# P-102
5 200 GPM SRS building west wall # MMC P-102
# P-103
25 800 GPM SRS building west wall # MMC P-103
# P-104
25 800 GPM SRS building west wall # MMC P-104
# P-201 100 2500 GPM SRS building west wall # MMC P-201
# P-202 100 2500 GPM SRS building west wall # MMC P-202
# P-203 100 2500 GPM SRS building west wall # MMC P-203
Table 2
SRS Pumps Butterfly Valve Number
Pump/Motor # Butterfly Valve Number
# P-101 # 3VY1 100A
# P-102 # 3VY1 100B
# P-103 # 6VY2 100A
# P-104 # 6VY2 100B
# P-201 # 10VY2 100A
# P-202 # 10VY2 100B
# P-203 # 10VY2 100C
- 16 -
ICSTF SRS Inspection Checklist
Item
OK
or
Note #
Check for:
Lighting Broken or dead bulbs, condition of fixture
Debris Accumulation, unusual materials
Float switches (2) Free movement, general condition
Pump assembly columns Looseness, corrosion, general condition
Pump intake screens Looseness, corrosion, holes, obstruction by debris
Sump floor and walls Cracks, any other signs of deterioration
Notes
Inspected by:
Date:
- 17 -
ICSTF Standard Operating Procedure (SOP)
Spring Receiving Sump (SRS) Pump Change-Out
(Revised June 2011)
- 18 -
Introduction and Background
The Illinois Central Spring Treatment Facility (ICSTF) receives influent flow from the spring
emergence area via a 24-inch below ground pipe which gravity discharges directly into the
Spring Receiving Sump (SRS). The SRS is a rectangular, poured concrete pit, approximately
20 feet in depth and measuring 24 x 38 feet in outside dimension. It is covered by a standard
metal frame protective structure, the SRS building.
The SRS building houses 7 vertical turbine pumps (SRS Pumps) which pump water to the
process feed tank in the main ICS treatment plant or to the two large outside storage tanks.
The 7 pumps (2 each 5 HP 200 GPM, 2 each 25 HP 800 GPM, and 3 each 100 HP 2500
GPM) are controlled automatically by the Programmable Logic Controller (PLC) in the
ICSTF control room. The pump operating parameters may be varied by operator input at the
PLC and may also be switched to manual operation mode. Switching to manual mode
overrides automatic control of the pumps, provides for flexibility in configuration and permits
safe maintenance activities.
Purpose
Routine preventive maintenance of the SRS pumps is performed in accordance with the
ICSTF Operations and Maintenance Plan and with pump manufacturer’s installation,
operation and maintenance manuals. However, occasional non-routine maintenance of one or
more of the SRS pumps may be necessary and may require the physical removal of the
pump(s) from the SRS.
Summary
This procedure details the steps necessary for the removal and re-installation of the SRS
pumps. It details work preparations, system shutdown, skylight removal, motor disconnect
and removal, pump removal, pump and motor re-installation, safety measures, and system
restart.
Pump removal and replacement is described herein as a two day procedure. On Day 1, pumps
to be removed are disconnected and preparations are made for Day 2 activities. The crane
arrives on Day 2. Also on Day 2, the replacement pumps are delivered, accompanied by the
pump manufacturer’s representative. Existing pumps are removed and temporarily placed on
the ground. The new pumps are taken by the crane directly from their shipping skids and
installed in position in the SRS building. The pumps just removed are placed into the
shipping skids by the crane and returned to the pump dealer for inspection and service as
needed.
The plant operator completes installation, adjustment and restart of the new pumps according
to Peerless Pump Company’s Vertical Turbine Pump Installation, Operation and
Maintenance Manual, Publication B-263319 (Rev. 11/08) and guidance of the pump
manufacturer’s representative.
- 19 -
Preparations and Planning
Prerequisite Conditions
Pump removal operations can be performed during conditions of moderate spring flows, i.e.
less than 100 gpm. Do not schedule pump removal operations during high flow events, i.e.
storm periods or during typical high flow periods of the year, unless absolutely necessary.
The duplicate pump of the same capacity as the pump being removed should be in good
working order.
Contact subcontractors and obtain necessary parts and equipment
a. Contact and schedule all subcontractors, i.e. crane service, aerial lift rental source, pump
manufacturer’s representative, etc. at least 4 weeks prior to the anticipated work date.
b. To minimize pump down time, obtain or confirm availability of all necessary repair and
replacement parts before scheduling the work date.
Safety
a. The plant operator and one or two PSARA technicians will perform all work involving
contact with potentially contaminated equipment. These personnel all are OSHA
Hazwoper trained.
b. Lock Out / Tag Out procedures in accordance with ICSTF Health And Safety Plan
(HASP) will be followed as needed to safely isolate pumps, motors and valves from
energy sources.
c. Fall Protection measures will be followed as needed in accordance with ICSTF HASP.
d. The crane contractor will be responsible for operating in compliance with OSHA
guideline 29 CFR Part 1926.550.
Equipment and Materials
1. Pressure washer and hose
2. Replacement pump assemblies
3. Gaskets, packing and other small pump and piping parts
4. Plastic sheeting
5. Wooden blocks & chocks
6. Rental crane & operator; crane must be capable of lifting 1100 lb., 20 ft. long pump
assembly 35 feet vertically to clear the roof opening.
7. Rental aerial lift
8. Safety harness and lanyard
9. Lock Out/Tag Out (LOTO) supplies
10. PPE, Level D, with Tyvek suits, and nitrile gloves
- 20 -
Procedure
Day 1
1. Conduct safety briefing with all personnel involved in the pump removal operations.
Pumps to be removed will be tagged by the plant operator to clearly identify pumps to
be locked out and to distinguish them from the pumps that will remain in service.
2. At the main PLC panel, operator will set SRS pump controls to MANUAL operating
mode for the pump(s) to be repaired/removed. All other pumps will remain in normal
or AUTO operating mode.
3. At main motor control (MMC) panel(s) in SRS building, set disconnect(s) to OFF
position. (See table 1 for disconnect locations for each SRS pump).
4. Lockout power to SRS pump motor(s) to be removed. Lock Out/Tag Out required.
5. Disconnect wiring and conduit from motor housing of pump(s) to be removed. Label
each wire as it is disconnected. This assures proper spin direction when the motor is
re-connected.
6. Remove motor shaft assembly, then remove motor mounting bolts. Manually remove
the motor body and place on the floor or on a pallet nearby. These weigh
approximately 20-50 pounds, not too heavy to handle but require careful handling and
safe lifting technique.
7. Close and lock out butterfly valve located closest to the effluent side of the pump
flange. (See Table 2 for valve number) This hydraulically isolates the pump from the
rest of the system. Lock Out/Tag Out required.
8. Disconnect pump from discharge piping.
9. Place appropriately sized wooden block inside top of housing and secure in place to
prevent shaft from moving longitudinally when the pump assembly is removed and
transported.
10. Stage pressure washer for use on Day 2.
Day 2
11. Conduct safety briefing with all personnel, including contractors, involved in the pump
removal and installation operations.
12. Verify LOTO are still in place.
- 21 -
13. Access roof of SRS building by aerial lift and remove skylight(s) as necessary for
access and removal of SRS pump(s). Fall Protection required.
14. Coordinate with crane operator to setup crane in correct position for pump removal.
15. Pumps delivery vehicle moves into position.
16. Plastic sheeting is spread and secured on the lay-down area where pulled pumps will
be temporarily placed after removal and prior to loading onto the transport vehicle.
17. Lower crane lifting rig through skylight access and attach securely to pump to be
removed.
18. Slowly raise pump turbine and housing assembly while power washing external
components to remove silt and accumulated grime, etc. Wash water will be directed
back into the sump through the floor opening.
19. Remove pump from building through skylight access and place in the temporary lay-
down area. Chock as necessary to prevent accidental movement.
20. The crane crew will then lift the new pump from its shipping skid on the pump
transport vehicle and lower into position in the SRS building.
21. The pump earlier removed is then lifted by crane, placed into the shipping skid on the
pump transport vehicle and secured for transport.
22. Repeat for second or subsequent pump(s).
23. Verify power source to pump motor is still off and butterfly valve closed and both are
in locked configuration. Lock Out/Tag Out required.
24. Re-connect pump discharge to effluent pipe. Important: Before re-connecting,
inspect inside piping for foreign objects.
25. Re-install motor and pump shaft assembly per pump manufacturer’s IOM manual
(Peerless Pump Co. publication B-2633119).
26. Re-connect wiring/conduit to motor consistent with wire labeling applied when pump
was originally disconnected.
27. Remove lock(s) and open discharge butterfly valve.
28. Remove lock(s) from pump power supply at Main Motor Control (MMC) panel.
29. Check for correct motor spin direction (counter-clockwise when looking down from
above). At the pumps Variable Frequency Drive (VFD) control box (interior north
- 22 -
wall of SRS building), press the JOG button to briefly send power to the pump motor.
The spin direction should be observable by watching the exposed shaft or the top of
motor fins, if the motor cover is still off.
30. If OK, move to the PLC panel in the main building and check for expected pump
yield. With pump mode still set to MANUAL, turn pump ON and observe flow rate
displayed on PLC panel. Flow rate readings should be equal to or greater than the
nominal pump rating, 200 gpm or 800 gpm.
31. The plant operator and pump manufacturer’s representative should return to the SRS
building while the newly installed pump is running and check for unusual or excessive
noise or vibration. If no problems are detected, the pumps can be set to AUTO
operating mode at the PLC.
32. If all systems operating normally, release crane crew.
33. Re-install skylight covers. Fall Protection required.
34. Remove all tools and equipment from area.
Table 1
SRS Pumps Electrical Disconnect Locations
Pump/Motor # Pump HP Pump Size Disconnect Location Panel/Breaker Number
# P-101 5 200 GPM SRS building west wall # MMC P-101
# P-102
5 200 GPM SRS building west wall # MMC P-102
# P-103
25 800 GPM SRS building west wall # MMC P-103
# P-104
25 800 GPM SRS building west wall # MMC P-104
# P-201 100 2500 GPM SRS building west wall # MMC P-201
# P-202 100 2500 GPM SRS building west wall # MMC P-202
# P-203 100 2500 GPM SRS building west wall # MMC P-203
- 23 -
Table 2
SRS Pumps Butterfly Valve Number
Pump/Motor # Butterfly Valve Number
# P-101 # 3VY1 100A
# P-102 # 3VY1 100B
# P-103 # 6VY2 100A
# P-104 # 6VY2 100B
# P-201 # 10VY2 100A
# P-202 # 10VY2 100B
# P-203 # 10VY2 100C
- 24 -
ICSTF Standard Operating Procedure (SOP)
Daily Flow Report
(Revised June 2011)
- 25 -
Summary
This procedure covers daily SRS flow calculations, which are done in Microsoft Excel based
on an equation developed by Earth Tech (now AECOM). It calculates the SRS influent flow
based upon level and flow data collected by system instrumentation.
Procedure
1. Open Microsoft Excel program
2. Open File Folder in My Documents
3. Open EFS ICS Folder
4. Open ICS-SRS Flow Rate
5. Open Current Calendar Year
6. Open Current Month
7. Open Last Flow Rating
8. Enable Macros (If an error occurs ensure network connections are correctly set, see
Internet and Network Operations SOP for set up)
9. Click on Tools to Run Macros
a. Click on run:
i. Click on TAG to pick Column Name:
1. SPRING FLOW RATE Time ( Never Changes)
2. SPRING RECEVING SUMP LEVEL Value (FT)
3. FLOW FROM PROCESS FEED PUMPS #101 & #102 Value (GPM)
4. FLOW FROM PROCESS FEED PUMPS #103 & #104 Value (GPM)
5. TOTAL FLOW FROM SRS TO CLARIFIER Value (GPM)
6. FLOW TO SRS STORAGE TANKS Value (GPM)
7. TOTAL FLOW OUT OF THE SRS Value (GPM)
8. FLOW FROM SRS STORAGE TANKS TO SRS Value (GPM)
9. SPRING FLOW RATE Value (GPM)
10. SRS RATE (GPM) Self Calculate and do not move
11. SRS 15 MIN AVG (GPM) Calculate and do not move
ii. Click on to change Date From (for date or dates need) and Time (12:00 AM)
iii. Click on to change Date To (for date or dates need) and Time (11:59 PM)
- 26 -
iv. Click on Get Data to gather Data for each column
10. Click on Chart 1 on bottom of spread sheet
a. Double Click on Date and Time at bottom of Chart
b. Click on Scale and add 1 to both the minimum and maximum numbers
c. Click OK to change date on chart
11. After gathering Data for each column and changing date, do a SAVE AS to save data and
chart for that date
- 27 -
ICSTF Standard Operating Procedure (SOP)
Primary Treatment System (PTS)
Clarifier Sludge Pump Settings
(Revised June 2011)
- 28 -
Summary
This procedure covers adjustments to clarifier sludge pump timer settings that are required
after storm events. Sediment loading increases with increasing flow, so solids will need to be
pumped out of the clarifier more frequently after storm events. The Operator should make the
necessary setting changes within 2 hours after the start of a storm event.
Procedure
1. Can use either PLC screen. Starts with screen F9.
2. Once screen F9 is displayed selects Function F6.
3. To change length of time pump is on, select F1.
(a) Once blue bar appears, use #s keys to enter the time you want pump to be on.
(b) Press the “enter” arrow below the “0” key to enter new value.
(c) Press the “cancel” key to reset screen.
4. To change the length of time the pump is off, select F2.
(a) Once blue bar appears, use #’s keys to enter the time you want the pump to be off.
(b) Press the “enter” arrow below the “0” key to enter new value.
(c) Press the “cancel” key to reset screen.
5. Press key F9 to return to original screen on PLC.
Note: All changes in time are in minutes (i.e. 1 hour = 60 minutes)
Suggested settings based on spring flow:
Flow of Spring
(gpm)
Time ON
(min)
Time OFF
(min)
<50 10 360
<100 10 240
100-300 20 120
300-500 20 60
500-1000 15 30
>1000 15 15
Water flowing in clarifier should look like “weak tea” when settings are correct. Operator
should be able to see circles in bottom of weir.
- 29 -
ICSTF Standard Operating Procedure (SOP)
Primary Treatment System (PTS)
Bag Filter Change
(Revised June 2011)
- 30 -
Summary
Change out of bag filters is a manual procedure. Each vessel contains 12 bags with a pore
size of 0.5 micron. The bag filter inventory should not be allowed to drop below 50 bags
without placing an order for more. It takes almost 1 month for the vendor to manufacture and
ship 100 bags. The system alarm for the bag filter units is set at a differential pressure of 22
psi or a head pressure of 35 psi (report given over MMI is head pressure).
Safety
Operator must wear Tyvek suit, gloves, and safety glasses. Footwear needs to be washable or
dedicated to the job. Respirators are not required.
Procedure
1. Upon receiving alarm condition or operator determining that change out is needed,
influent and effluent valves are closed to isolate vessel.
2. The vessel bottom drain valve is opened to allow water to drain into containment.
3. After water has drained (20-25 minutes), the lid of vessel is unbolted. A chain hoist is
used to lift lid and it is swung aside.
4. Holding ring is unbolted and removed. Ring is set aside inside containment area.
5. Bags are removed and placed inside containment area to allow drainage of any water.
6. Once all bags are removed, new bags are installed. Personnel should make sure that
the plastic seal ring on each bag seats in each basket. New bags can be found in gray
cabinets or on pallet next to cabinet.
7. After bags are installed, holding ring is put back in place.
8. Lid of vessel is put in place. Ensure that o-ring seal is in place on vessel before
lowering lid. Lid might stick and operator will have to push it down. Lids sometimes
will “free fall”. Ensure all hands and fingers are back prior to handling lid. Once lid
is in place, tighten bolts.
9. Bottom drain valve is closed. Influent and effluent valves are opened.
10. Air is bled off through the pressure relief valve.
11. Used bags are transferred into the PCB roll-off box under press for disposal. Work
area is washed down with water and squeegee used to dry.
12. PPE is placed in roll-off for disposal.
- 31 -
ICSTF Standard Operating Procedure (SOP)
Primary Treatment System (PTS)
Carbon Filter Backwash
A1 and B1 Vessels Lead
A2 and B2 Vessels Lag
(Revised June 2011)
- 32 -
Summary
Granulated Activated Carbon (GAC) filter backwashing is a manual operation. This SOP
outlines the correct way to accomplish a backwash of the vessels when A1 and B1 are in the
lead position (A2 and B2 in the lag position). Differential pressures will read approximately
25 psi when backwash of GAC is needed.
Procedure
1. The operator needs to ensure that system will only run at 200 gpm by putting the 800
gpm SRS pumps and 900 gpm filter feed pumps in “MANUAL” mode by highlighting
each pump and then pressing key F19 on screens F9 and F11.
2. Once the larger pumps are in “MANUAL” mode, locate and access valves 8VY2-400,
8VY2-402 (B vessels) and 8VY2-403 (A vessels). Valve 400 is normally open and
needs to be closed. Valves 402 and 403 are normally closed and only one needs to be
opened depending on which vessel is being backwashed (A or B).
3. Go to gray valves between GAC vessels. Need to close all valves IN ORDER V-1, V-
3, and then V-10).
4. Once valves are closed, open the “Backwash Inflow” valve (V-8 for vessel A1/B1 and
V-7 for vessel A2/B2).
5. Now open the “Backwash Outflow” valve (V-5 for vessel A1/B1 and V-6 for vessel
A2/B2).
6. Return to office area and select PLC screen F14.
7. Highlight backwash pump P-401, P-402, or P-403. Once highlighted, press key F19 to
place in manual mode.
8. Use pump in manual mode to backwash the GAC at 600 gpm by key F20 to start the
pump and F21 to stop it.
9. Once the operator completes backwashes, close all gray valves.
10. Open valves IN ORDER V-10, V-3, and then V-1.
11. Open valve 400 and close valve 402 (B vessels) or 403 (A vessels) depending on
which vessel is being backwashed.
12. Return to PLC screens and place all pumps in auto mode by highlighting the pumps
put in “MANUAL” mode and pressing key F17.
Length of backwash is 30 minutes for each vessel.
- 33 -
ICSTF Standard Operating Procedure (SOP)
Primary Treatment System (PTS)
Carbon Filter Backwash
A2 and B2 Vessels Lead
A1 and B1 Vessels Lag
(Revised June 2011)
- 34 -
Summary
Granulated Activated Carbon (GAC) filter backwashing is a manual operation. This SOP
outlines the correct way to accomplish a backwash of the vessels when A2 and B2 are in the
lead position (A1 and B1 in lag position). Differential pressures will read approximately 25
psi when backwash of GAC is needed.
Procedure
1. The operator needs to ensure that system will only run at 200 gpm by putting the 800
gpm SRS pumps and 900 gpm filter feed pumps in “MANUAL” mode by highlighting
each pump and then pressing key F19 on screens F9 and F11.
2. Once the larger pumps are in “MANUAL” mode, locate and access valves 8VY2-400,
8VY2-402 (B vessels) and 8VY2-403 (A vessels). Valve 400 is normally open and
needs to be closed. Valves 402 and 403 are normally closed and only one needs to be
opened depending on which vessel is being backwashed (A or B).
3. Go to gray valves between GAC vessels. Need to close all valves IN ORDER V-2, V-
4, and then V-9).
4. Once valves are closed, open the “Backwash Inflow” valve (V-8 for vessel A1/B1 and
V-7 for vessel A2/B2).
5. Now open the “Backwash Outflow” valve (V-5 for vessel A1/B1 and V-6 for vessel
A2/B2).
6. Return to office area and select PLC screen F14.
7. Highlight backwash pump P-401, P-402, or P-403. Once highlighted, press key F19 to
place in manual mode.
8. Use pump in manual mode to backwash the GAC at 600 gpm by key F20 to start the
pump and F21 to stop it.
9. Once the operator completes backwashes, close all gray valves.
10. Open valves IN ORDER V-9, V-4, and then V-2.
11. Open valve 400 and close valve 402 (B vessels) or 403 (A vessels) depending on
which vessel is being backwashed.
12. Return to PLC screens and place all pumps in auto mode by highlighting the pumps
put in “MANUAL” mode and pressing key F17.
Length of backwash is 30 minutes for each vessel.
- 35 -
ICSTF Standard Operating Procedure (SOP)
Primary Treatment System (PTS)
Decanting Thickeners
(Revised June 2011)
- 36 -
Summary
Decanting water in Thickener T-301A and T-301B after sedimentation is a manual operation
that must be carefully managed to prevent the thickeners from being full when a storm event
is in progress. Thickener T-301A is fed by the removal of sludge from the clarifier or
cleaning of the SRS sump. Thickener T-301B receives backwash waste from the Multimedia
and GAC filters. Both thickeners have manual decant valves which are identical, so this SOP
works for both.
Procedure
1. Use either PLC screen to determine fluid levels in thickeners. Use F13 function to
select screen with thickener levels.
2. Open top decant and drain. Ball valve on drain pipe should be open no more than 30%
due to Process sump pump can not keep up with drain flow.
3. Once water has drained, you can close the valve and open the next valve below.
4. Steps 1 thru 3 are repeated until the water level in the thickener is at its lowest stage.
Thickener 301A will have a water level of 2.3 ft. and Thickener 301B water level of
0.5 ft.
Thickener #1 (T-301A) has capacity of 19,802 gal. It can hold the clarifier sludge pump
discharge at a rate of 10 gpm for 12 hrs.
Thickener #2 (T-301B) has a capacity of 36,320 gal. It can hold 3 multi-media filter
backwashes or 2 GAC filter backwashes.
- 37 -
ICSTF Standard Operating Procedure (SOP)
Primary Treatment System (PTS)
Filter Press
(Revised July 2012)
- 38 -
Summary
Operation of the filter press / pressing sludge is a mostly manual process that takes an entire
week. The filter press does have an internal PLC that automatically controls the dewatering
cycle.
Safety
Personnel should wear tyvek suits, gloves, safety glasses, and dust masks while handling lime.
Procedure
Day 1
1. Fill lime mixing tank with 300 gal. of water. Turn on mixer. Slowly add lime to tank.
8 bags of lime can be mixed at once.
2. Use small pneumatic pump to transfer lime slurry from mixing tank to thickener to be
pressed.
3. If any lime is still present in the tank, add additional water and repeat step 2.
4. Open valve at base of thickener to allow air to mix thickener.
5. Clean up area were lime dust is. This will consist of washing down floor and
equipment. Squeegee floor dry.
6. Hang plastic sheeting around base of press so “slop” will be contained when filter cake
falls.
Day 2
7. Start filter press. Shut off air mixing prior to pressing. Follow prompts on processor
screen on press. Press is programmed and runs an automatic cycle which last 1.5 to
2.5 hrs. Shuts off automatically.
8. After press shuts off, open valve and bubble sludge in thickener. Personnel need to
wear Tyvek suit, gloves, safety glasses, and washable/dedicated boots.
9. Open press and allow filter cake to fall off. Cake sometimes needs to be scraped
loose. If it free falls, check edges of plates and clean off any cake in corners or along
edges.
- 39 -
10. Ensure that all hands are clear before using spreader to move plates.
11. Repeat steps 9 & 10 until all plates are clean (42 plates).
12. Close press & Repeat step 7.
A total of 3 pressings a day can be completed. Repeat steps 7 through 12 until all sludge is
processed.
After all sludge is pressed, the filter cake and miscellaneous PCB-contaminated filtration
equipment are analyzed for the parameters necessary to generate the appropriate, current
waste profile for the disposal vendor. Plastic sheeting is placed in roll-off and tarp cover
replaced. Press area is to be washed down and squeegee dry.
Prior to transporting full roll-off boxes off-site, an additional dewatering step is taken. A
small submersible pump attached to a screened PVC tube is placed in the north side of the
roll-off box and used to pump out any remaining free water.
- 40 -
Illinois Central Springs Treatment Facility
PTS Carbon Exchange Procedures
(Revised June 2011)
- 41 -
Purpose
The carbon adsorption units filter PCBs and other contaminants from the influent water
stream. When adsorptive capacity of the carbon is exhausted, the spent carbon must be
removed and replaced. This procedure and attachments detail the steps necessary for the
carbon exchange.
Summary
Preparations and Planning
Scheduling
a. All carbon exchange operations should be scheduled to occur during minimum spring
flow periods. Do not schedule carbon exchange operations during high flow periods, i.e.
storm periods or during typical high flow seasons of the year.
b. Develop a contingency schedule should a high flow “storm” event occur or be forecast
just prior to or during the scheduled carbon exchange.
c. Verify that the roadway to the Illinois Central Spring Treatment Facility (STF) is capable
of supporting the carbon tanker and the waste disposal roll-offs.
d. Obtain a waste disposal approval for the spent carbon (pending analysis) at both Heritage
and Southside landfills. Note: Final approval can only be received after the samples are
analyzed, which can only be accomplished after the carbon change. However, we wish to
ship promptly upon receipt of analytical results, so a profile should discussed and
submitted in advance.
e. Arrange for delivery to the site of five 25 cubic yard de-watering roll-off boxes and five
filter liners. Three boxes may be adequate if carbon exchange is performed on one vessel,
and the boxes are used for transport, returned to the site and re-lined before the second
vessel carbon exchange is performed.
The carbon exchange procedures described herein detail the preparations, safety measures,
system shutdown, carbon removal and replacement, and the post-operations checks for system
restart. The carbon vendor (Calgon) will deliver new carbon, empty the carbon vessel, inspect
the carbon vessel and repair if necessary, then charge the vessel with new carbon and
collaborate with the plant operator to put the vessel back in service. This procedure does not
specifically describe those portions of the operation that will be performed by Calgon. It is
presumed that they have their own procedures. Rather, this document addresses their utility
and support requirements which will be handed by PSARA. This include providing sufficient
compressed air and water, providing an adequate number of de-watering boxes, capturing and
treating drainage water, and disposal of the spent carbon.
- 42 -
Contact subcontractors and obtain necessary parts and equipment
a. Contact and schedule all subcontractors necessary for the performance of carbon
exchange. These include Calgon, the filter box supplies, and he transporter and disposal
facility(ies).
.
Review Safety Requirements
a. Review all necessary safety requirements anticipated for carbon exchange and assure that
all scheduled work personnel and contractors have the necessary training, equipment, and
documentation required to perform the scheduled tasks.
b. Required training and equipment should all be obtained and verified prior to start of
project.
c. Proper personnel protective equipment (PPE) MUST be worn due to the possibility of
contact with PCBs or other contaminants.
d. Inspect the roll-off to insure that tailgate seals are in good condition and that the bed is
lined to prevent liquid from leaking out of the roll-off.
Equipment Required
a. Approximately 200 foot of 4-inch discharge/suction hose.
b. 100 feet of garden hose for wash-down.
c. Five 25 cubic yard de-watering roll-off boxes (for two vessels).
d. At least two manway gaskets to replace the ones being removed. (by Calgon as necessary)
e. An air supply system capable of 100 cfm at 90 psig. A fitting should be available to
connect air to the carbon delivery truck.
f. 50 feet of two-inch suction hose for spent water return
g. 150 feet of two-inch lay flat discharge hose for spent water return
h. A two-inch gasoline trash pump and adequate fuel for 8 hours use
Calgon Requirements (to be provided by PSARA)
Calgon will deliver the new carbon via a carbon transfer service vehicle, available with
capacities for one or two complete carbon vessel exchanges. Equipment specifications
required for the use of the Calgon carbon trailer include:
a. Flat area to support the trailer
b. Water line, 4-inch male Kamlock connector, 100 gpm at 15 psig max
c. Air line, 3/4-inch male Kamlock connector, 100 scfm at 90 psig max
d. Drain and transfer line, 4-inch male Kamlock connection, 20 ft. long
- 43 -
Procedure
PSARA Activities:
1. Conduct safety briefing prior to the procedure with all maintenance and contractor
personnel involved in the carbon exchange operation.
2. Locate the required roll-offs outside the Illinois Central Spring Treatment (see
attached map) Facility and set up necessary pumps and hose to transfer so that any
water in the carbon can be drained into the plant floor drain for processing.
3. Set Plant Process pump controls for P-107 and P-108 to manual operation at PLC
panel to prevent automatic start (plant operator).
4. Set disconnect(s) to off position at main motor control panel(s) next to the Plant
Process pumps P-107 and P-108. Lock Out/Tag Out required.
5. Connect the 4-inch suction hose from the vessel discharge pipe to the roll-off. Secure
the cam lock fittings to prevent an accidental release of the carbon/water.
6. Run the 2-inch water hose from the filter box through the trash pump and on to the
sump at the west end of the plant. Set this up with the two-inch trash pump. Be sure
the exhaust from the pump is not vented into the building.
7. Install filter liners in all filter boxes.
8. As the carbon is transferred to the filter boxes, pump the excess water from beneath
the filter fabric back to the plant sump using the trash pump.
9. When the first box is nearly full, transfer the discharge to the second filter box. Each
vessel is expected to fill between two and two-and-a-half filter boxes.
10. Collect a composite sample of the spent carbon for waste characterization analysis.
Submit the sample to Heritage Laboratories for the quickest turnaround available.
11. Removal all possible water from the filter boxes.
12. Tarp the boxes.
13. Submit the analytical results to the appropriate disposal facility (Heritage for TSCA
waste, Southside for non-TSCA waste), and complete the profiling process.
14. Prepare appropriate manifests, and ship the spent carbon to the appropriate facility.
15. Decontaminate the filter boxes at the ICS facility and return them to the supplier.
Note: This procedure does not address the actual carbon change process, as that process
will be performed by Calgon, using their own procedure. This procedure presumes that
Calgon will return the vessels to a ready condition, including wetting the carbon and
removing any entrained air.
- 44 -
Illinois Central Springs Treatment Facility
2500 gpm SRS Pump Back Flush Procedure
(Revised July 2012)
- 45 -
Purpose
The 2500 gpm SRS pumps are provided to help the PTS handle spring flows over 1000 gpm,
usually associated with a rainfall event. Because these pumps are infrequently used, they
require regular maintenance in order to ensure continued successful operation. One of these
maintenance activities includes back-flushing each pump to remove any solids that have
accumulated on the pump screen. This procedure details the steps necessary to perform this
task.
Procedure
1. Determine the pump that needs to be back flushed and select the appropriate pump to
provide flow for back flushing. If pump P-201 or P-203 need to be back flushed, P-
202 should be used to provide flow. If pump P-202 needs to be back flushed, either P-
201 or P-203 may be used to provide flow.
2. Manually open the valve connecting the back flushed pump and the flowing pump
approximately 1/8th
of the way.
3. Turn on the flowing pump.
4. Gradually open the valve between the two pumps until it is fully open to provide back
flushing flow to the designated pump.
5. Allow flow to continue for five minutes to ensure that all debris is removed from the
pump screen.
6. Turn off the flowing pump.
7. Return the valve between the two pumps to a closed position.
APPENDIX B
As-built Sump and Tank Sketches
APPENDIX C
System Piping and Instrumentation Drawings
PR
OC
ES
S &
INS
TRU
ME
NTA
TIO
N D
IAG
RA
M
DRAWING 9 OF 34 DRAWINGS
PR002
DESIGNED BY: AWB/OAGDRAWN BY: CSH/CWLCHECKED BY: RLVDATE CHECKED: 07/10
A
B
C
D
1 2 3 4 5 6
C0850030
NOTE: DIMENSIONAL DATAIS NOT TO BE OBTAINED BY SCALING ANY PORTION OF THIS DRAWING.
DATE REVISION
PROJECT No.
DRAWING No.
PROJECT TITLE
DRAWING TITLE
125 WEST CHURCH STREETCHAMPAIGN, IL 61820PHONE : 217.373.8900FAX : 217.373.8923
ENGINEERS
ILLI
NO
IS C
EN
TRA
L S
PR
ING
BLO
OM
ING
TON
, IN
EX
CE
SS
FLO
WTR
EA
TME
NT
SY
STE
M
07/10 BID SET09/10 FOR CONSTRUCTION07/11 RECORD DRAWING