WADP System Protection
Zainoren B. Shukri
Blackout Prevention Task Force
Tenaga Nasional Berhad
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
1
Content
• Previous Blackouts
• Reliability Standards Requirements
• Technology R&D
• Implementation Road Map
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
2
TNB Blackout Experiences
• TNB had 4 major blackouts over last 16 years (1996 - 2012)
– 03-Aug-1996 - National blackout
– 18-Nov-1998 - System split
– 01-Sept-2003 - Northern area system collapse
– 13-Jan-2005 - Southern-Central area system collapse
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
3
TNB Blackout Experiences (continue)
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
4
Conditions 3 Aug 1996 18 Nov 1998 1 Sep 2003 13 Jan 2005
Total load loss 5,760 MW (99% of initial load)
2,168 MW (29% of initial load)
1,900 MW (28% of initial load)
6,230 MW (54% of initial load)
Total no. of customers affected
Almost 100% customers
1.345 million customers
(information not available)
3.5 million customers
Initial event & contingency level
Flashover during opening of line isolator on stuck breaker pole
Flashover to vegetation and did not trip due to stuck breaker
Flashover to vegetation and trip; (n-1)
Sectionalising of busbar due to faulty circuit breaker
Response to the initial event
Mal-tripping of interconnection to an IPP
Stuck breaker lead to (n-7) contingencies.
Remaining circuit tripped.
Had series of tripping of transmission lines due to overloading.
Subsequent contingencies
Tripping of gas turbines (GT) due to control system
System split. Problems of GT tripping persisted.
Generator units did not start in time. Followed by tripping of other circuits (n-5).
System split. Generator units tripped inadvertently
Fault Extension Protection / System Integrity Protection Scheme
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
5
A single fault
(a circuit fault)
Failure in high
speed fault
clearance
A su
dd
en p
ow
er flow
chan
ge
and
large po
wer sw
ings
cau
sed
by fau
lt
Out-of-step
Pow
er System
Black-o
ut
A su
dd
en sh
ortage
or exce
ss of p
ow
er
generatio
n An interrupted
fault of a major
trunk line
A fault in both
Circuit on the
same tower
(double-circuit fault)
Overload
Abnormal voltage
Abnormal
frequency
Primary protection
+ 3.5 cycles
+ Multi-phase AR
Backup protection
+ Local Backup
+ Remote Backup
Multi-phase AR
+Dead time 0.8 to 1 sec
Load shedding
scheme
Voltage instability
prevention relaying
system
Under/Over
frequency prevention
relaying system
Out-of-step
relaying system
Overload
relaying system
Refn: Cigre WG B5.19 Protection Relay Coordination
Generator shedding
scheme
Reliability Standard’s Requirement
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
6
Paragraph 3.2.3.3 of the Transmission System Reliability Standard (TSRS) mandated that:
“….. the grid system is and shall continue to be planned and developed such that special protective measures and defense mechanisms are included not only to prevent a total system shutdown but also to facilitate rapid recovery to normal system operation….. “
Planned Security & Planned Robustness
Level of Designed Operational & Protective
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
7
Source: TSRS, Version2, Edition 1, TNB January 2006
WADP System Protection
• Wide Area Defense Plan is a Blackout Prevention Scheme
• A “Planned Security” scheme – design and operational measures put in place to ensure that the
power System continues to operate normally after the occurrence of the specific pre-defined sudden disturbances such as electric short circuits or unanticipated loss of System facilities designated in the Security Criteria
• A “Planned Robustness” scheme – design and operational measures put in place to ensure that the
power System quickly recovers from disturbances developing to beyond those specified in the Security Criteria, the performance benchmark being the avoidance of total blackout
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
8
WADP 4-Layer Defense Strategy
Equipment & Substation Protection
• Fault Clearing System
Prevent Cascade Outages
• Event-based Sys. Integrity Prot. & Overload
Minimize Impact of Extreme Contingency
• UFLS, UVLS, Out-of-Steps, Controlled Islanding
Self Preservation
• Generator UF & Unit Protection
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
9
Existing SIPS
Risk Assessment of Present System Protection Scheme
• The risk assessment on the existing TNB’s Special Protection Scheme (SPS) reveals the following: – There are a few control schemes in TNB which function as the Second
Defense Line but they do not cover all defined contingencies as stipulated in TSRS.
– For the Third Defense Line, TNB does not have a dedicated OOS separation scheme.
– Additional defense plan to cover for these risks, hence, the blackout prevention scheme
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
11
Technology R&D
• The followings are technologies assessed and some under-development
• Others will be under Request for Proposals
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
12
WIDE AREA INTELLIGENT INFRASTRUCTURE
PMU PMU PMU PMU PMU PMU
W A M S
L T M
G D P M
3rd
P A R T Y
Applications
Infrastructure
PMU Network
P O M
F U T U R E
H I T O R I C A L
Phase I – Wide Area Monitoring System
** PMU – Phasor Measurement Unit
Real Time Situational Awareness
Advance Overload Protection System For Central Pahang
Ethernet on E1 channel
(2 Mbps)
RTAP
(Central Processor)
Synchrophasor
SynchrophasorRTAP
(SS Processor)
I/O Unit
JNKA
RTAP
(SS Processor)
I/O Unit
JTUT
RTAP
(SS Processor)
I/O Unit
KLIP
SynchrophasorRTAP
(SS Processor)
I/O Unit
BNTG
RTAP
(SS Processor)
I/O Unit
RBDR
RTAP
(SS Processor)
I/O Unit
BNTA
Synchrophasor
KAWA
Intelligent system that sense overload situation and
automatically take control action (load shedding, generator shedding) to control
the power flow
Status – Tender for equipment on going
40% completion as of December 2011
Trip Signal
Circuit Breaker
Determination Logic
CB statuses
TKLG
KAWA PAKA KNYR
Definite Time
Overcurrent
Sum
mation o
f B
oth
Lin
e C
urr
ents
GT1A
GT1B
GT2A
GT2B
GT3A
GT3B
GT4A
GT4B
PA
KA
GA
S T
UR
BIN
ES
OR
Manual FGTS
Arming
Switches
Based on
Operators
Instructions
KTNN
Out Of Step Protection
Intelligent system that perform
generator tripping to prevent wide spread blackout
Status – Tender for equipment on going
40% completion as of December 2011
PAKA – KAWA Angle
6-line Trip
5-line Trip
4-line Trip
2-line Trip
Acceleration vs Slip Frequency
Adaptive Undervoltage Load Shedding
RTAP
UVLS UVLS
UVLS
RTVSM Applications
Trip Signal Trip Signal
Trip Signal
VT LS VT LS
VT LS
V < Vset
ARM Signal & LS
Intelligent system that continuously calculates
voltage stability margin and provide arming signal to
local undervoltage relays to shed optimal amount of load to prevent voltage
collapse
Status – Tender for equipment on going
40% completion as of December 2011
Real Time Voltage Stability Margin
P+jQ
Y=G+jBaE E d|| VV
Load Area
Source line
Source line
Power transfer limit
Operating
point
P
Q
Pmargin
Qm
arg
in
Qmax < Q < 0
Qmax > Q > 0
Pmax
Operating
point
|Qm
ax|
Qm
arg
in
Pmargin
Pmax
|Qm
ax|
Power transfer limit
critical
2
max
2
max
1
2 1 cos( )
cos
2 1 cos( )
sin
2 1 cos( )
V E
P E Y
Q E Y
Real Time Application Platform (RTAP)
• Formerly known as Phasor Data Processor (PDP)
• Objective
– To provide robust real time platform to build WAIS applications
• Scope
– Development of RTAP software engine
– Development of various communication interfaces to sensors and actuators
– Specification for suitable hardware
Real Time Application Platform (RTAP) formerly known as Phasor Data Processor (PDP)
RTDB
IEC61850 Synchrophasor
Network Control Center
RTU
Math
Logic
RTAP
IEEE C37.118 MMS & GOOSE IEC 101 or IEC 104 or Modbus TCP
Clock
IRIG-B000 & IEEE1588 IEC 101 or WISP+
Inter RTAP for distributed application
Synchrophasor Client
IEEE C37.118
PDC
Micro Historian
RTDB
C37.118 Int.
Math Sync
Logic IEC
61131-3
IEC 61850 •MMS Client
•GOOSE IEC 61850
To Archiving Server &
Application LAN
Data from PMU
Network
Data from Relay
Network
RTAP Architecture
WIDE AREA INTELLIGENT SYSTEM INFRASTRUCTURE
Sensors Sensors Sensors Sensors
Out of Step Protection
Adaptive Under
Voltage Load
Shedding
Coordinated
Voltage Control
F U T U R E
Advance Overload
Sensors – Synchrophasor, IEC61850 devices, RTU, Remote I/O, Power plant Distributed Control System, SCADA/EMS, HVDC control system etc
Actuators Actuators Actuators
Actuators –IEC61850 devices, RTU, Remote I/O, Loads, Power plant Distributed Control System, HVDC control system etc
Control
Islanding (Blackout
Prevention System)
APPLICATIONS
2011 2012 2013 2015
2011 SYSTEM
Implementation Road Map
Summary
• TNB is adopting 4-level Defense Strategy
• Enabling Blackout Prevention System utilizing Wide-area Phasor-Measurement and IEC61850 technologies
• Preparing High Level Functional Specifications, Request for Proposals & Pre-Qualification
• Future works on Integrated Situational Awareness and Blackout Prevention System (Wide Area Intelligent System - WAIS)
AORC CIGRE – Sunway Lagoon, Malaysia 2-4 May 2012
24