+ All Categories
Home > Documents > documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any...

documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any...

Date post: 11-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
91
Bangladesh Economic Zones Authority (BEZA) Private Investment and Digital Entrepreneurship (PRIDE) Project Environmental and Social Management Framework (ESMF) Package No. BEZA S-135 Final Report Annexes to ESMF Report
Transcript
Page 1: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Bangladesh Economic Zones Authority (BEZA)

Private Investment and Digital Entrepreneurship (PRIDE) Project

Environmental and Social Management Framework (ESMF)

Package No. BEZA S-135

Final ReportAnnexes to ESMF Report

January 2020

Page 2: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Annex A: Terms of Reference (ToR) of the ESIA Study (Full Assessment)

Objective

The objective of the assignment is to assist the Government of Bangladesh in preparing Environmental and Social Impact Assessment (ESIA) including an Environmental and Social Management Plan (ESMP) for the sub-project which was assessed based on the environmental and social screening to involve potential higher environmental and social risks and impacts through their implementation.

Scope of Work

Task 1. Review of project and existing technical studies

1. The consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical documents on environment and social, economic benefits related to the proposed infrastructure investments (Pre-Feasibility and Feasibility studies, preliminary designs, Environmental and Social Screening result, relevant field investigations and other surveys, modelling results, etc.).

Task 2: Baseline Environmental and Social Conditions

2. The Consultant will review, evaluate and update baseline data on the relevant environmental, social, economic and physical cultural heritage characteristics within the project area. Specifically, the baseline conditions should include information on:

a. Physical environment: geology, topography, sediments/soils, surface and ground water hydrology, land pollution, water quality, air quality and sources of air emissions, noise emissions, utilities and sewage networks;

b. Biological environment: existing flora and fauna at the site; natural habitats; waterbodies

c. Social and economic: community structure; pedestrian and commuter activities; residential and commercial activities; description of direct and indirect livelihoods)

d. Information on disadvantaged groups or persons for whom special provisions may have to be made, if affected, and in the context of developing mitigation measures;

e. Assess whether there will be any displacements as a result of the physical works; f. Physical cultural property: Cultural heritage assets such as cultural, religious, historical or

archaeological sites, including sacred and/or burial places, that might be affected during construction.

3. Baseline data shall include but not limited to following:

Primary data/monitoring shall define characteristics of the existing natural environment including soil, water, air, noise, land use, cultural properties and flora & fauna. o Monitoring to be carried at critical locationso Identification of specific areas for monitoring o Air and Noise Monitoring at junctions, major settlements, school and hospitals etc. o Water and soil monitoring. o Tree inventory to be carried out, in consultation with relevant Government Department. o Inventory of Cultural Property Resources shall be done along with measurements, details

and photographs; consultation shall be done for gathering public opinion.

1

Page 3: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Secondary Data to define meteorology, geology, climate change (flooding potential) quarries, borrow areas, disposal sites etc.

Baseline conditions of ambient air and noise should be analysed by comparing with not only national standards but also WBG EHS guidelines values

Task 3: Legislative Framework

4. The Consultant shall analyse the existing relevant laws/regulations, and add any new legislations, decisions and/or guidance notes relevant to the environment quality, health and safety, cultural property, waste management, hazardous substance storage and handling; noise emissions; protection of sensitive areas and endangered species, land-use planning, involuntary resettlement and expropriation; public information; environmental liability, etc. determining their relevance to the project.

5. The Consultant shall also assess the institutional arrangements and institutional capacity for supervision and enforcement of ESMP during construction and operation. The consultant shall reference any international relevant legislation and treaties applicable to the project, including World Bank ESF and Occupational Health and Safety Guidelines.

Task 4: Determination of potential environmental and social impacts

6. The Consultant shall update the existing documents to determine impacts, direct, indirect and cumulative impacts, and immediate and long-term impacts related to the construction phase of the proposed works as well as once the works are finalized (operational phase). The Consultant shall propose mitigation measures and affiliated costs for each of the above identified impacts that will represent the content/summary of an Environmental and Social Mitigation Plan for the overall project during its construction as well as the operation phases. The Mitigation Plan is part of the overall project Environmental and Social Management Plan.

Task 5: Analysis of Alternatives

7. The Consultant shall review the available technical documents and summarize alternatives proposed during the project development, including the alternative of not constructing the proposed project. Such alternatives could be related to different options in terms of design of structures and facilities, selection of technologies, construction techniques, and project phasing, operating and maintenance activities. These alternatives must be compared on technical, economic, environment, and social merits and to the extent possible, with costs and benefits of each alternative. The concept of alternatives extends to siting and design, technology selection, rehabilitation/construction techniques and phasing, and operating and maintenance procedures. The alternative should also emphasize analysis of secondary/induced impacts and potential conflicts. The Consultant shall briefly compare these alternatives in terms of potential environmental and social impacts, cost and benefits.

Task 6: Preparation of Environmental and Social Management Plan (ESMP)

8. The ESMP shall be prepared in such a manner that environmental and social requirement (mitigation measures and monitoring, technical specifications) related to the construction phase could be incorporated in the bidding/contract documents. The ESMP should include proposed enhancements such as landscaping and “greening” of the sub-project area. The World Bank Environmental and Social Framework (ESF) and Environmental and Social Standards (ESS) should be complied with in the ESMP.

9. The ESMP should propose the criteria, procedures, and responsibilities for monitoring and enforcing all of the environmental measures included in the alignment sheets and the construction

2

Page 4: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

practices included on the construction specifications. The consultant shall review the authority and capability of institutions responsible for implementation of this project and recommend steps to strengthen or expand them, including proposals for intersectoral arrangements, management procedures and training, staffing, operation and maintenance training, budgeting, and financial support. This must include the institutional arrangement which needs to be set in place to implement the ESMP and the monitoring framework. The ESMP should clearly present estimated budget associated with proposed mitigation and monitoring actions as well as the institutions responsible for implementation.

10. In addition to the World Bank Operational Policies, the consultant will refer to the following key documents:

(i) Guidelines for Managing the risks of adverse impacts on communities from temporary project induced Labor influx

(ii) Environmental Health and Safety Guidelines

11. The mitigation measures and environmental management plan should be sufficiently specific to provide clear guidance to the Contractors for enforcement by the engineer. The contract clauses should be focused towards specifications to be complied and enforcement with built in mechanism to take recourse on failure of implementation. For supervision, the ESMP will provide comprehensive checklists for the verification of compliance of environmental specifications by contractors and checklists for the reception of final works. The ESMP will also include a monitoring program.

12. The mitigation measures and monitoring framework required during operations should also be prepared, in an Operations Manual and/or ESMP format for operations phase.

Task 7: Stakeholder Consultations

13. The Consultant will assist the Client in undertaking at the minimum two structured consultations, during the preparation of the ESIA and ESMP. In addition, such consultations with primary and secondary stakeholders will continue throughout project implementation, as necessary to address EA related issues that affect them. For meaningful consultations with project-affected groups, communities, women of various age, persons with disabilities, elderly people, local NGOs and rights groups, all relevant documents must be provided in a timely manner prior to consultation and in a form and language that are understandable and accessible to the groups being consulted. Stakeholders should be consulted at least twice during ESIA preparation: shortly after E&S screening and before ToR is finalized, and once a draft ESIA report is prepared. Please also note the result of the stakeholder consultation should be reflected in ESIA report as well as in the project design and in implementation and operational approaches. The consultant shall be responsible for keeping a record of all such consultation meetings, for obtaining the informed views of the stakeholders.

Deliverables

After commencement, separate reports will be submitted in as follows:

1) An Inception and scoping report, including initial findings of environmental and social risks and impacts, proposed definition of project study area, full outline of ESIA, detailed workplan and schedule. the reports will be submitted within 1 month of signing of contract in 6 copies.

3

Page 5: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

2) Separate complete reports on Draft ESIA report will be submitted in at the end of 4th month of signing the contract, prior to disclosure and preparation of consultations on the drafts in 6 copies.

3) Separate reports on Final ESIA report, taking into account feedback from consultations, will be submitted in by the end of 6th month of signing the contract in 6 copies.

4) The reports summarizing the outcome of each stakeholder consultation opportunity according will be provided within one month upon completion

Duration and Timing

The ESIA Report should be completed within 6 months from commencement. All draft deliverables should be presented in English, with final deliverables also translated into Bangla at the Consultant’s expense. The final presentation workshop should be held within 8 months of commencement of the contract.

Staffing Requirements

The consultants should propose a comprehensive team composition with task assignments for each key staff along with sufficient support staffs to meet the objectives and scope of the services. The estimated staff months for key professional staff is 30 and those of non-key staffs is 60. These staff-months are indicative and the consultants are free to propose their estimate supported by methodology proposed for the implementation of the service.

Key professional experts to be evaluated during technical evaluation process for the assignment is given below. The consultant must propose suitable individuals as experts in these key positions; and submit their own estimate of the required number of person-months against each of these key positions to carry out the assignment in conformity with the scope of services and proposed methodology.

Qualification and Input for Key Professional Staffs:

Position Academic qualification

Desirable years of professional experience

Specific Experience Indicative No. of position

Team Leader Graduation in relevant field

12 years a) 3 years of experience as Team Leader.

b) Experience of environmental and social impact assessment preferably of infrastructure specially road, building and water supply & sanitation.

c) Experience in World Bank project or similar Financier’s project.

1

Environmental Specialist/Scientist, or Ecologist

B.Sc. Engineering (Civil)/Ecology/r

8 years a) 3 years of experience in the impacts assessment of infrastructure activities on

1

4

Page 6: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Position Academic qualification

Desirable years of professional experience

Specific Experience Indicative No. of position

elevant field natural habitats, water, land and biodiversity.

b) Experience in Bangladesh terrestrial and aquatic ecosystems is desirable.

c) Experience in World Bank project or similar Financier’s project.

Social Development Specialist

Graduation in Social Science

8 years a) 3 years of experience of direct and indirect social impacts (positive and negative) assessment of infrastructure development-related activities including water supply & sanitation.

b) Proven experience in anthropological studies of indigenous populations preferably in Bangladesh.

c) Experience in World Bank project or similar Financier’s project.

1

In addition to above listed positions of professionals; the consultant should make arrangements for other experts and support staff with adequate experience in relevant fields. Indicative list of other staffs / experts / support professionals who may be required for the assignment is given below but shall not be limited to those. During technical evaluation process, these staffs will not be evaluated individually.

9. Responsibilities of BEZA

For smooth completion of the study; the Project Director, PRIDE (BEZA) shall assist the consultant, as far as possible, in collection of data, services and facilities.

The consultant shall work under the direct supervision of the Project Director, PRIDE, BEZA. In case of any unforeseen events, be it in terms of physical or social obstacles at field levels; BEZA field office will take initiatives to solve them and ensure good working environment.

Technical and project management issues shall be discussed in tri-partite meeting between BEZA, World Bank and the consultants.

5

Page 7: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Annex B1: Structure of the ESIA Report (Full Assessment)

Contents

Chapter 1. Introduction

1.1 Background

1.2 The Proposed Project

1.3 Objectives of the Study

1.4 Scope of Study

1.5 Study Area

1.6 Approach and Methodology

1.7 Structure of the Report

1.8 Limitation of the Study

1.9 The ESIA Study Team

Chapter 2. Legal and Regulatory Compliance Consideration

2.1 Introduction

2.2 National Environmental Laws

2.2.1 National Environmental Policy, 1992

2.2.2 National Environmental Management Action Plan, 1995

2.2.3 The Environment Conservation Rules, 1997 & Subsequent Amendments

2.2.4 The Environment Court Act, 2000

2.2.5 National Conservation Strategy, 1992

2.2.6 The Environment Conservation Act, 1995 & Subsequent Amendments

2.3 Relevant National Policies, Strategies and Plans

2.3.1 National Forest Policy, 1994

2.3.2 National Agriculture Policy, 2013

2.3.3 National Water Policy, 1999

2.3.4 National Fisheries Policy, 1999

2.4 The Protection and Conservation of Fish Act, 1950

2.4.1 National Land Use Policy, 2001

2.4.2 National Land Transport Policy, 2004

2.5 National Water Management Plan, 2001 (approved in 2004)

2.5.1 National Strategy for Waste Management

6

Page 8: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

2.5.2 The National Biodiversity Strategy & Action Plan, 2004

2.5.3 Bangladesh National Building Code (BNBC), 2015 (final draft)

2.5.4 The Energy Policy, 1996

2.5.5 Industrial Policy, 1999

2.6 Other Relevant Acts, Laws and Rules

2.6.1 Noise Pollution (Control) Rules, 2006

2.6.2 National Water Act, 2013

2.6.3 The Groundwater Management Ordinance, 1985 (Ordinance No. xxvii of 1985)

2.6.4 Bangladesh Labour Act, 2006

2.6.5 The Penal Code, 1860

2.6.6 Wildlife Conservation (Protection and Safety) Act, 2012

2.6.7 The Forest Act, 1927 and the Forest (Amendment) Act, 2000

2.6.8 Private Forests Ordinance Act, 1959

2.6.9 Vehicle Act, 1927, the Motor Vehicle Ordinance, 1983

2.6.10 BEZA Act 2010 (Compliance to laws connect with environment)

2.7 World Bank’s Environmental and Social Safeguards Polices

2.8 Other Relevant National Plans

2.8.1 The GoB Seventh Five Year Plan 2016-2020

2.8.2 Environmental Standards

2.8.3 Procedure for obtaining ECC from DoE, Bangladesh

Chapter 3. Project Description

3.1 Location of the Project

3.2 Master Plan for BSMSN

3.3 Planned Activities under PRIDE Project

3.3.1 Land development

3.3.2 Green Areas/Open Spaces/Water Bodies

3.3.3 Administrative and Institutional Infrastructure

3.3.4 Industrial plots and related infrastructure

3.3.5 Public facilities

3.3.6 Transport and communication

3.3.7 Utility services

7

Page 9: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

3.4 Associated Facilities

3.5 Present Status of the area

3.6 Implementation Schedule

Chapter 4. Environmental and Social Baseline

4.1 Introduction

4.2 Baseline Data Collection

4.2.1 Ambient Air Quality measurement

4.2.2 Surface Water Quality

4.2.3 Ground Water Quality

4.2.4 Ambient Noise Level

4.2.5 Soil and Sediment Quality

4.3 Physico-Chemical Environment

4.3.1 Climate

4.3.2 Ambient Air Quality

4.3.3 Water Resources

4.3.4 Ambient Noise Level

4.3.5 Land Resources

4.3.6 Seismicity

4.4 Biological Environment

4.4.1 Aquatic Flora and Fauna

4.4.2 Terrestrial Flora and Fauna

4.4.3 Ecological Resources

4.5 Social Environment

4.6 Demographic Profile

4.6.1 Population

4.7 Literacy rate and educational facilities

4.8 Income & Poverty

4.8.1 Employment Status

4.8.2 Labour Market (wages)

4.9 Infrastructure facilities

4.10 Gender & Women

8

Page 10: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

4.11 Historical, Cultural and Archaeological sites

Chapter 5. Analysis of Alternatives

5.1 Introduction

5.2 “No-Project” Alternative

5.3 Alternative Site Consideration

5.4 Design Alternative

Chapter 6. Public Consultations

6.1 Introduction

6.2 Approach and Methodology for Consultation

6.3 Information disclosure and consultation for the Updating ESIA

6.4 Key Informants Interview (KII)

6.5 Public Consultation Meeting

6.6 Focus Group Discussion (FGD)

Chapter 7. Environmental and Social Impacts

7.1 Introduction

7.2 Rational for Applied Strategy of Impact Assessment

7.3 Determination of Impact Significance

7.4 Identification and Analysis of Significant Environmental and Social Issues

7.5 Assessment of Environmental and Social Impacts

7.6 Impact during Pre-construction and Construction Phase

7.6.1 Impact on Air Quality

7.6.2 Impact on Water Resources (Surface and Ground Water) and Quality

7.6.3 Impact on Land Resources (Soil)

7.6.4 Sediment Pollution

7.6.5 Impact on Noise

7.6.6 Impact on Ecosystem and Biodiversity (Aquatic & Terrestrial Ecology)

7.6.7 Impacts on Drainage Pattern and Hydrology

7.6.8 Community Health and Safety

7.6.9 Traffic & Transportation

7.6.10 Social Conflict

7.6.11 Impacts on Indigenous People

9

Page 11: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

7.6.12 Vulnerable Group

7.6.13 Physical Cultural Resources

7.6.14 Occupational Health and Safety

7.6.15 Generation of Employment

7.6.16 Skill Enhancement of Local people

7.6.17 Land Acquisition, Resettlements on Land Use and Involuntary Resettlement

7.6.18 Gender Based Violence (GBV)

7.7 Impacts during Operation Phase

7.7.1 Impact on Land Use

7.7.2 Impact on Land Resources and Soil Quality

7.7.3 Impact on Air

7.7.4 Impact on Noise Quality

7.7.5 Impacts on Ground a Surface Water Resources

7.7.6 Impact on Ecosystem and Biodiversity (Both Aquatic and Terrestrial)

7.7.7 Impact on Community Health and Safety

7.7.8 Poverty alleviation and diversification in livelihood

7.7.9 Education for children including Girls’ Education

7.7.10 Women’s empowerment

7.7.11 Access to civic amenities and communication

7.7.12 Social mobility

7.8 Cumulative Impact

7.8.1 Cumulative Impact of all EZ Interventions

7.8.2 Other Projects nearby EZ Site

Chapter 8. Environmental and Social Management Plan (ESMP)

8.1 Objectives

8.2 Mitigation Measures

8.3 Responsible Party for Effecting ESMP

8.4 Environmental and Social Management Plan

8.5 Environmental and Social Monitoring Plan

8.6 Monitoring Indicators

8.7 Grievance Redress Mechanism

10

Page 12: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

8.8 Enhancement Plan

8.9 Emergency Response and Disaster Management Plan

8.10 Traffic Management Plan

8.12 Waste Management Plan

8.13 Management of Contractors and Code of Practice

8.14 Guidelines on environmental and social conditions in the BOQ/contract documents

8.15 Third Party Monitoring

8.16 Estimated Budget for Implementing the EMP

Chapter 9. Institutional Capacity Assessment and Implementation Arrangement

9.1 Key Tasks for Environmental and Social Risk Management

9.2 Institutions and Roles in Program Implementation

9.3 Institutional Setting and Implementation Arrangement

9.4 Assessment of Capacity of BEZA

9.5 Action Plan to Strengthen Staffing, Capacity, Systems and Implementation

Chapter 10. Recommendation for Environmental and Social Commitment Plan (ESCP)

10.1 Environmental and Social Commitment Plan

Chapter 11. Conclusion and Recommendations

11.1 Conclusion

11.2 Recommendation

References

Appendices

11

Page 13: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Annex B2: Structure of Environmental and Social Assessment

An Environmental and Social Assessment (ESA) describes the process of analysis and planning (used by a World Bank Borrower) to ensure that the environmental and social impacts and risks of a project are identified, avoided, minimized, reduced or mitigated.

The ESA needs to meet the requirements of the World Bank’s Environmental and Social Standard (ESS) 1. Based on the requirements of ESS Section B, the recommended structure of the ESA is as follows:

1. Introduction – description of project background and objectives2. Project Description – components, locations, cost estimate, implementation plan3. Summary of Project’s Technical Analyses4. Summary of Project’s Financial Analyses5. Description of Project Area – baseline environmental (physical and biological) and socio-

economic condition6. Scoping of Potential Environmental and Social Issues – based on project description and

baseline conditions, range and extent of potential issues should be described. Initial consultations with key stakeholders can be useful for the scoping exercise.

7. Stakeholder Engagement - consultation with affected people and other interested parties to potentially significant environmental and social risks and impacts are identified

8. Additional Assessment Requirements - Identification of specific assessment tools to carry out the environmental and social assessment and to document the results of such assessment, including the mitigation measures to be implemented. These can include Environmental and Social Impact Assessment (ESIA), Environmental and Social Audit, Hazard or Risk Assessment, Cumulative Impact Assessment, Social and Conflict Analyses, Environmental and Social Management Plan (ESMP), Environmental and Social Management Framework (ESMF), Strategic Environmental and Social Assessment (SESA)

9. Institutional Capacity – description of strengths and weaknesses of implementing agency’s environmental and social safeguards track record, capacity and training requirements.

12

Page 14: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Annex C: Guidelines for ESMP

An Environmental and Social Management Plan (ESMP) is a document that details:

(a) the measures to be taken during the pre-construction, construction and operation phases of a project to mitigate adverse environmental and social impacts and/or enhance the project benefits

(b) who is responsible for carrying out the measures and also supervision responsibilities(c) monitoring and reporting activities required to ensure that the measures are implemented

and working properly.(d) allocation of resources including capacity building and training requirements(e) contingency plans

The following table provides more guidelines for preparing an ESMP.

ESMP Component Guideline

Summary of impacts

The predicted adverse environmental and social impacts for which mitigation is required should be identified and briefly summarised.

Description of mitigation measures

Each mitigation measure should be briefly described with reference to the impact to which it relates and the conditions under which it is required.

Description of monitoring programme

The monitoring program should clearly indicate the linkages between impacts identified, measurement indicators, detection limits (where appropriate), and definition of thresholds that will signal the need for corrective actions.

Institutional arrangements

Responsibilities for mitigation and monitoring should be clearly defined, including arrangements for co-ordination between the various actors responsible for mitigation.

Implementation schedule & reporting procedures

The timing, frequency and duration of mitigation measures should be specified in an implementation schedule, showing links with overall project implementation.

Cost estimates and sources of funds

These should be specified for both the initial investment and recurring expenses for implementing all measures contained in the ESMP, integrated into the total project costs.

The tables below show example ESMP and monitoring plans.

13

Page 15: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Table 1: Example Environmental and Social Management Plan

Sub-Projects/ Activities Environmental and Social Impacts

Suggested Mitigation Measures/Enhancement Measures/

Environmental Design Considerations

Responsible parties

Land Development

Demolition of existing infrastructure

Land cleaning

Transportation n of debris

Land filling/raising land level

Land Acquisition

Physical or social disruption to the existing and nearby communities

Temporary loss of income from street venting at the selected economic zone

Unhygienic/unsanitary environment due to demolition of old latrines and construction of camps in the development site

Soil erosion/ dust pollution/siltation/water pollution/

Loss of vegetation Traffic congestion due to transportation of

debris. Uneven land filling causing soil erosion Loss of Agricultural land Destruction of mangrove forest Loss of water bodies

(surface/ ground) Barrow pit Over flowing of canal water can cause of

flooding

Engage the community members in the construction work Transport/handle debris from toilet in a hygienic manner Compaction of developed or raised land Tree plantation at the economic zone boundary/slope/open

space Placement of construction equipment in a proper place

to avoid traffic congestion and compaction of soils. Collection and disposal of construction debris in

a designated dumping place. There should be installation of latrine and campaign on

social awareness to stop the open defecation. Afforestation with indigenous tree/ plant species within

the project influence area Ensure proper compensation to the PAPs Attempt to avoid the forest area as much as possible Construction labor should be restricted from polluting the

source or misusingthe source.

Shifting of source to be completed prior to disruption of the actual source.

Alternate arrangements shall be made to all the water users prior to the

Dam are to be prepared to protect the flooding if necessary;construction activity for the identified (during Design stage) water sources(surface and ground sources) that fall in the project site

No borrow pit will be opened without the permission of the supervision consultant.

Contractor

Monitoring by BEZA

14

Page 16: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Sub-Projects/ Activities Environmental and Social Impacts

Suggested Mitigation Measures/Enhancement Measures/

Environmental Design Considerations

Responsible parties

Design, Construction, and Operation of Project Interventions

Multipurpose building for official work

Noise and pollution due to construction The waste form the camps during the

construction of building Water pollution due to unplanned

discharge of domestic wastewater Unplanned disposal of domestic solid waste Drainage congestion/waterlogging Greater demand of bricks and cement puts

pressure on fossil fuel and timber which in turn reduces the forest areas and pollute air

Using locally available construction materials Rooftop plantation and gardening may reduce the excess

local temperature Accommodate a drainage of wastewater Design and incorporate latrine Keep an arrangement of shelter during any disaster Consider rainwater harvesting Consider solar panel for electricity supply Keeping adequate provisions (including fire/emergency exits)

for fire safety in accordance with National Building Code Ensure materials recovery facility (MRF); Recycling of grey

water & black water. Promote air tightness and vapor barrier in building walls and

surfaces. Use low solar heat gain coefficient of glass and use of natural

light For energy saving daylight-controlled lighting systems and use

of LED lighting is preferable Ensure roof top gardening as a part of green building Zero emissions of polluted air & liquid from industries

Contractor

Monitoring by BEZA

15

Page 17: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Sub-Projects/ Activities Environmental and social Impacts

Suggested Mitigation MeasuresEnhancement Measures/

Environmental Design Considerations

Responsible Parties

DTW and Pump house

Water logging condition/drainage congestion. Depletion of ground water table through over

extraction of water. Land subsidence and increase of salinity due to

over pumping of water. Arsenic contamination or degrading water quality

Design and construction drains with appropriate outlets Encourage water use efficiency/ demand management

through awareness Facilitate groundwater recharge, protect natural system. Water filtration/treatment/rain water harvesting The digging of soil should follow the proper design to avoid

the pollution and water logging.

Contractor

Monitoring by

BEZA

Water Distribution Network

Water logging condition/drainage congestion. Dust from excavated pit Air and noise pollution during constriction Leakage or failure of distribution network

Design and construction WDN with appropriate slope Ensure water spraying to reduce dust Ensure proper supervision during laying of pipe Generation less noise during construction

Contractor

Monitoring by

BEZA

Sewer Network

Noise and soil pollution during the construction. Microbial contamination to the ground water

from the failure of sewer line Disturb the top soil Soil erosion and siltation Accident can occur from laying of pipe

Ensure effective design and supervision to control the failure of sewer line

Frequent monitoring the line Ensure careful operation of mechanical equipment Restore the top soil Ensure proper compaction Keep provision of PPEs and first aid kit

Contractor

Monitoring by BEZA

Drains/ Drainage system

Clogging/ stagnation of flow in the storm drain Backflow of water through drain (e.g., due to high

water level at downstream discharge point, such as Khal/ river)

Discharge from drain pollute downstream water body

Designing drain considering the downstream discharge point; adequate slope and x-section; RCC cover for drain, where appropriate

Not allowing direct connection to drain from toilet

Contractor

Monitoring by BEZA

Internal road Loss of agricultural and housing lands Dust and noise pollution from construction work Drainage Congestion/ Water logging due to road Soil erosion /Sedimentation of reservoir and loss

of storage capacity Damage of natural drainage system due to new

road construction Risk of accidents due to vehicular traffic and

transport

Soil compaction Proper slope of road surface Watering to reduce dust pollution Avoid construction of roads and transportation facilities

which might harm cultural or historical sites Construction of drain and culvert with appropriate designs to

avoid water logging/drainage congestion. Improvement and widening of roads for fire protection

Contractor

Monitoring by BEZA

16

Page 18: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Sub-Projects/ Activities Environmental and social Impacts

Suggested Mitigation MeasuresEnhancement Measures/

Environmental Design Considerations

Responsible Parties

Power Lines Short circuit and improper electrical connection may cause potential health and safety risk.

Connections of line may interrupts the community people since main line will stop during connection

Ensure use of proper PPEs Switch off before electrical connection Inform the local people about the concern prior to work start

Contractor

Monitoring by BEZA

Gas lines Disturb the top soil Soil erosion and siltation Dust and noise problem from trench cutting work

for pipe laying Health hazard due to use of mechanical equipment Community health and safety may fall in risk for

the trenching work

Restore the top soil Ensure proper compaction Water spraying to reduce dust control Carefully use of hydraulic hammer and mechanical equipment Inform the local people prior to start the trenching work Ensure provision of fencing at trenching site

Contractor

Monitoring by BEZA

Solid Waste Management

Uncollected wastes blocked the drainage and sewage system.

Air, water and soil pollution during the waste collection

Smoke from the open burning of uncollected waste.

The loading and unloading of waste at transfer station pollutes the air and soil.

Odor from waste disposal site and composting system.

Contamination of ground water by leachate.

Encourage 4R (reduce, reuse, recycle, recovery) Encourage composting of organic waste Construct/supply garbage bin and secondary transfer station Adequate distance between waste bin and water body. Adequate distance should be maintained between the waste

collection point and residence or office space Provision of Plasma gasification

Contractor

Monitoring by BEZA

Green and open spaces

Tree plantation

Landscaped areas

Compensate and enhance the ecological condition and improve the aesthetic beauty of landscape

Urban tree canopy Green belts at the periphery (to act as buffer) of the project

site; Landmark area with signature architecture; Amphitheater/auditorium Provision of tree plantation along the internal road Ensure roof top gardening

Contractor

Monitoring by BEZA

Lake / waterbeds

Slurry will generate form the excavation of lake or water body

Lake excavation may responsible for air, noise, dust and soil pollution for use heavy of construction vehicles and equipment

Generated waste should be disposed in designated dump site Ensure use of PPEs for associates labor health and safety; Effective use of machines to complete the work in short time, Selection of lake in the BSMSN 2A & 2Bshould select in such a

way that no industry is sited at adjacent to the lake

Contractor

Monitoring by BEZA

17

Page 19: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Sub-Projects/ Activities Environmental and social Impacts

Suggested Mitigation MeasuresEnhancement Measures/

Environmental Design Considerations

Responsible Parties

Additional habitat for flora and fauna may create for provision of lake

It can act as storm water retention lake

Created green buffer around the lake to attract thebiodiversity to use their habitat

Proper maintenance and clearing the lake to livable environment for aquatic fauna

Before disposal of excavating slurry, pollution of slurry needs to be determined

18

Page 20: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Table 2: Typical Impact and Mitigation Measures for ESMF Sub-Projects

Sub-project Typical Impacts Typical Mitigation MeasuresSub-project I.1: Land elevationSub-project I.2: Desalination plantSub-project I.3: Rain water captureSub-project I.4: Water resource managementSub-project I.5: Solid waste managementSub-project I.6: Waste pyrolysis/energySub-project I.7: Solar energy productionSub-project I.8: Sewage managementSub-project I.9: Waste water treatmentSub-project I.10: Flood management

Physico-chemical environment:o Air pollutiono Noise pollutiono Water pollutiono Soil pollutiono Water resources alterations

Biological environment:o Terrestrial and aquatic flora

changeso Terrestrial and aquatic fauna

changes Socio-economic environment:

o Occupational Health and Safety issues

o Community impactso Labour influxo Traffic impacts

Storage sites of construction materials must be covered with shed so that no dust or small, particles from the stored cement, brick, sand or other materials mix into the open air.

When land will be filled or excavated, regular watering on the excavated land would minimize the amount of dust produced from the land.

Water-logging resulting from land filling and excavation must be mitigated. No runoff from storage areas is allowed to be discharged into water bodies. Tree plantation is required for overall environmental benefits in the area.

Compensatory afforestation shall be at the rate of 2 to 4 times of the trees cut. Preferably same varieties of trees as are cut; shall be used for afforestation.

Proposed building should be equipped with amenities of green building infrastructures

Prepare and implement RAP to acquire land (if required) Prepare an effective traffic management plan Encourage engagement of PAPs in the development works Training PAPs for their livelihoods restoration

Sub-project A.8: Construction of sewer network and waste water/sewage treatment plant

Physico-chemical environment:o Air pollutiono Noise pollutiono Water pollutiono Soil pollution

Biological environment:o Terrestrial and aquatic flora

changeso Terrestrial and aquatic fauna

changes Socio-economic environment:

o Occupational Health and Safety issues

o Labour influxo Traffic impacts

Storage sites of construction materials must be covered with shed so that no dust or small, particles from the stored cement, brick, sand or other materials mix into the open air.

When land will be filled or excavated, regular watering on the excavated land would minimize the amount of dust produced from the land.

Water-logging resulting from land filling and excavation must be mitigated. No runoff from storage areas is allowed to be discharged into water bodies. Covered vans or vehicles must be used to carry the wastes from the project

area. No runoff from storage areas is allowed to be discharged into water bodies. Proposed building should be equipped with amenities of green building

infrastructures The sewer network will consider green and resilient features and designs Prepare an effective traffic management plan Encourage engagement of PAPs in the development works

Sub-project B.2: Construction of a desalination plant

Physico-chemical environment:o Air pollutiono Noise pollutiono Water pollution

Storage sites of construction materials must be covered with shed so that no dust or small, particles from the stored cement, brick, sand or other materials mix into the open air.

When land will be filled or excavated, regular watering on the excavated land would minimize the amount of dust produced from the land.

19

Page 21: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Sub-project Typical Impacts Typical Mitigation Measureso Soil pollution

Biological environment:o Terrestrial and aquatic flora

changeso Terrestrial and aquatic fauna

changes Socio-economic environment:

o Occupational Health and Safety issues

o Labour influx

Water-logging resulting from land filling and excavation must be mitigated. No runoff from storage areas is allowed to be discharged into water bodies. Tree plantation is required for overall environmental benefits in the area.

Compensatory afforestation shall be at the rate of 2 to 4 times of the trees cut. Preferably same varieties of trees as are cut; shall be used for afforestation.

Proposed building should be equipped with amenities of green building infrastructures

Sub-project B.3: Construction of a Rooftop and floating solar power system

Physico-chemical environment:o Air pollutiono Noise pollution

Biological environment:o Terrestrial and aquatic flora

changes Socio-economic environment:

o Occupational Health and Safety issues

Integrate rooftops systems with green roof and rainwater harvesting facilities During construction as well as operation phases of floating solar power

systems, special care should be taken to minimize water pollution

Sub-project B.4: Construction of high‐pressure steam pipelines connecting tenant firms

Physico-chemical environment:o Air pollutiono Noise pollutiono Water pollutiono Soil pollution

Biological environment:o Terrestrial and aquatic flora

changeso Terrestrial and aquatic fauna

changes Socio-economic environment:

o Occupational Health and Safety issues

o Labour influxo Traffic impacts

No runoff from storage areas is allowed to be discharged into water bodies. Any organic wastes from construction camp site or any source at construction

site should be properly collected and composted Encourage use of renewable energy, such as solar, wind or biomass energy, to

meet energy requirements to reduce carbon footprints of buildings during construction and operation phases.

Restriction of project works during migratory bird season Emission of dust can be mitigated by a number of measures together or

separately, e.g. install dust covers on vehicles, dust suppression using water spray, etc.

Noise pollution may be mitigated to certain degrees through minimizing work during night time, construction of sound barriers, etc.

Prepare and implement RAP to acquire land (if required) Prepare an effective traffic management plan Encourage engagement of PAPs in the development works Training PAPs for their livelihoods restoration

20

Page 22: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Table 3: Example Environmental and Social Monitoring Plan

Project Stage/ Affected Component

Environmental/social Issue

Parameters to be Monitored

Location Measurements Standards/ Guidelines

Frequency Responsible Agency

Implemented by

Supervised by

Construction PhaseConsultation with affected PAPs

RAP Implementation

Affected PAPs Affected Households

Monitoring World Bank Daily Assigned Consultant

BEZA

Employment Engaging local labor

Associates project worker

Camp site Consultation with local labor

World Bank and GoB

Weekly Supervision Engineer &

BEZA

Dredge materials Soil and water pollution of the project and surrounding area

Lead (Pb), Cadmium (Cd),Chromium (Cr), Copper (Cu), Zinc (Zn), Manganese (Mn), Arsenic (As), Selenium (Se) and Mercury (Hg)

Proposed dredgingsites

Monitoring Government of Bangladesh (GoB) and internationalstandard

Before starting the

dredging

Contractor BEZA

Ambient Air Quality

Dust generation

Dust Project activity areas and construction workers camp

Visual inspection of all active work areas

Monitoring Daily Contractor BEZA

Ambient Air Pollutant

SPM, PM 2.5, PM10, CO, SO2, NOx

2 samples at Project site (one at 2A and other one at 2Bsite)

24-hour Air quality standard by DOE, Bangladesh

Quarterly Contractor byEngaging Environmental Firm

BEZA

Noise Increase in ambient noise levels

Noise levels in Leq, Leq day, Leq night

6 locations Project site at high noise generation location and adjacent sensitive receptor

24-hour Noise Pollution Control Rules (2006)

Quarterly Contractor by Engaging Environmental Firm

BEZA

Water Quality Contamination of surface

Turbidity, pH, DO, Total dissolved solids,

Two samples form Canal

Monitoring Surface water quality

Quarterly Contractor by Engaging

BEZA

21

Page 23: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project Stage/ Affected Component

Environmental/social Issue

Parameters to be Monitored

Location Measurements Standards/ Guidelines

Frequency Responsible Agency

Implemented by

Supervised by

water oil & grease, BOD5, COD, NH3

standard as per Schedule 3 of ECR 1997

Environmental Firm

Contamination of Groundwater quality

pH, Alkalinity, Cl, Fe, As, TSS, Salinity, Pb etc.

2 Locations Project site and Closest borehole of the project site

Monitoring Drinking water quality standard as per Schedule 3 of ECR 1997

Quarterly Contractor by Engaging Environmental Firm

BEZA

Top Soil Soil Pollution Check liquid waste is carried out by experienced personnel and in proper way

Careful and proper handling of oil and other hazardous liquids

Project Site Visual inspection of all active work areas

Monitoring Daily Contractor BEZA

Sediment of Khal Sediment Pollution

Heavy Metal Project site Monitoring International Standard

Quarterly Contractor BEZA

Waste Liquid waste, Solid Waste

Check storage, transportation, disposal, handling of hazardous waste

Waste and effluents to be collected and disposed safely of camp.

Wastes and garbage from construction sites to be disposed safely

Project Site Visual inspection of all active work areas

Monitoring Daily Contractor BEZA

Ecology Terrestrial and Tree and Aquatic Canals and Forest Visual Monitoring Once for Contractor BEZA

22

Page 24: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project Stage/ Affected Component

Environmental/social Issue

Parameters to be Monitored

Location Measurements Standards/ Guidelines

Frequency Responsible Agency

Implemented by

Supervised by

aquatic flora and fauna

Species inspection tree prior to starting construction and yearly aquatic monitoring

Occupational Health and Safety

Workers Health & Safety

Check quality of food and accommodation at construction camp;

Check safe water supply, hygienic toilet at camp, construction of drain at campsite;

Check toilets are close to construction site;

First Aid Box with required tools and medicines;

The heavy construction material to handled and stored safely putting due care on public safety;

Heavy construction materials at construction site to be stored and handled safely; and

Construction Camp & Construction area

Visual inspection of all active work areas

Monitoring Daily Contractor BEZA

23

Page 25: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project Stage/ Affected Component

Environmental/social Issue

Parameters to be Monitored

Location Measurements Standards/ Guidelines

Frequency Responsible Agency

Implemented by

Supervised by

Check of personal protective equipment (PPE) for worker at the sites

Community Health and Safety

Community disturbance and potential safety hazard due to road traffic

Accidents, incidents, and complaints

Approach Road Incidents, accidents, and community complaints

Monitoring Based on occurrence

Contractor BEZA

Operational PhaseNoise Increase in

ambient noise levels

Noise levels in Leq, Leq day, Leq nigh and hourly Leq

3 locationsProject site at high noise generation location and adjacent sensitive receptor

24-hour Noise Pollution Control Rules (2006)

1/year O&M Unit byEngaging Environmental Firm

BEZA

Water Quality Contamination of surface water

Turbidity, pH, DO, Total dissolved solids, oil & grease, BOD5, COD, NH3, Tc, Fc

Canals inside the project area

Monitoring Surface water quality standard as per Schedule 3 of ECR 1997

1/year O&M Unit byEngaging Environmental Firm

BEZA

Contamination of Groundwater quality

pH, Alkalinity, Cl-, Fe, As, TSS, Pb etc.

2 Locations Project site and Closest borehole of the project site

Monitoring Drinking water quality standard as per Schedule 3 of ECR 1997

1/year O&M Unit byEngaging Environmental Firm

BEZA

Soil Quality Soil Pollution Heavy Metal Project site soil Monitoring - 1/year O&M Unit byEngaging Environmental

BEZA

24

Page 26: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project Stage/ Affected Component

Environmental/social Issue

Parameters to be Monitored

Location Measurements Standards/ Guidelines

Frequency Responsible Agency

Implemented by

Supervised by

FirmSoil Quality Soil Pollution Heavy Metal Project site soil Monitoring - 1/year O&M Unit by

Engaging Environmental Firm

BEZA

Biological Environment

Horticulture and Greenbelt Development

Survival rate ofplants and shrubs

Green belt Monitoring number successful growth

Quarterly BEZA BEZA

Disaster Management Plan (DMP) Monitoring

Earthquake Structure Design Project Area As to be defined in the DMP to be prepared contractor

Not Specific Continuous Operation & Maintenance Unit

BEZA

Flooding Structure Design Project Area As to be defined in the DMP to be prepared contractor

Not Specific Continuous Operation & Maintenance Unit

BEZA

Cyclone /Tornado

Project Structure Design

Project Area As to be defined in the DMP to be prepared contractor

Not Specific Continuous Operation & Maintenance Unit

BEZA

25

Page 27: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Annex D: List of Attendees in the Stakeholder Consultations

Date Stakeholder Details Details of participants

05.11.19 Department of Fisheries Mahmudul Islam Chowdhury, Sr. Upazilla Fisheries Officer, Mirsharai Upazilla

05.11.19 Department of Agriculture Raghu Nath Agriculture Officer, Mirsharai Upazila

05.11.19 Department of LGED Upazila Engineer

Mirsharai Upazila

05.11.19 Upazila Forest Bit/ Range office

Md. Ikram Uddin Bhumik, Range officers, Mirsharai Upazila

05.11.19 Department of BWDB SM. Abdul Mannan

DGM, IMI Project

BWDB

05.11.19 Department of Fisheries and Live-stock

Dr. Shamol Chandra Poddar

Upazila Live-stock officer, Mirsharai

05.11.19 UNO Office, Upazilla Mr. Md. Ruhul Amin

UNO, Mirsharai Upazilla

26

Page 28: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Annex E: Proposed geographical area coverage

Figure: Geographical Location of BSMS within Bangladesh

27

Page 29: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Figure: Geographical Location of Project Area within BSMSN

28

Page 30: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Figure: Land use Map of study area

29

Page 31: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Annex F: ECoPs for the Contractors

This Environmental Code of Practice (ECoP) is a guideline to reduce or eliminate environment risks due to various activities during planning, design, construction, operation and maintenance phases associated with each subproject to be implemented under this project.

ECoP 1.0: Planning and Design Phases of subprojects

These guidelines discuss the issues to be considered during project preparation to avoid/address environmental concerns through modifications in project design and incorporation of mitigation measures. Finalization of Alignment/Project Location

Adequate consultations with the communities to identify the concerns and preferences need to be taken up during selection of the different subprojects.

Consultations with the local communities are to be conducted to obtain their suggestions and incorporate their concerns to address the potential environmental impacts.

Compliance to Legal Requirements The bid document shall include the various applicable clearances pertaining to environmental management and shall contain the necessary procedures for compliance of the same. Cost Estimation Some activities included in ECoP 1.0 have certain monetary involvement. These activities are outlined below:

There will be one Focus Group Discussion (FGD), with at least 15 participants from different communities of the society, for adequate consultations to identify the concerns and preferences related to a particular infrastructure development project.

Two surveyors will carry out walk in interview of at least 50 participants from different communities of the society affected by the infrastructure development project.

ECoP 2.0: Site Preparation

The preparation of site for construction involves: Existing land of proposed project is mostly equipped by the forest and agricultural land

with some fishing cultivating pond thus to clear the forest as part of site preparation BEZA will inform the regional forest officer and will also asked them to suggestion for effective preservation of biodiversity of forest especially deer.

Marking and clearance of the required project area of all encroachments by the PMU of BEZA prior to mobilization of Contractor;

Informing the local community about construction schedule; and Site preparation by the contractor prior to commencement of construction. Scope of this

ECoP includes only the measures to address environmental concerns expected during the site preparation.

Site Preparation Activities Informing the local community and local ward councils about the likely schedule of

construction

After obtaining the consent of the community, the PMU of BEZA shall be responsible to stake out the subproject locations.

30

Page 32: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Site Preparation Activities by the Contractor The contractor shall submit the schedules and methods of operations for various items

during the construction operations to the PMU for approval. The clearance of site shall involve the removal of all materials such as trees, bushes,

shrubs, stumps, roots, grass, weeds, part of topsoil and rubbish. Towards this end, the Contractor shall adopt the following measures:

In locations where erosion or sedimentation is likely to be a problem, clearing and grubbing operations should be so scheduled and performed that grading operations and permanent erosion and sedimentation control features can follow immediately, if the project conditions permit.

The disposal of wastes shall be in accordance with the provisions of ECoP 4: Waste Management.

All regulatory clearances shall be obtained before actual start of work.

ECop 3: Construction Camp

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Siting and Location of construction camps

Campsites for construction workers are the important locations that have significant impacts such as health and safety hazards on local resources and infrastructure of nearby communities.

The Contractor shall Locate the construction camps at areas

which are acceptable from environmental, cultural or social point of view.

Consider the location of construction camps away from communities in order to avoid social conflict in using the natural resources such as water or to avoid the possible adverse impacts of the construction camps on the surrounding communities.

Local authorities responsible for health, religious and security shall be duly informed on the set up of camp facilities so as to maintain effective surveillance over public health, social and security matters.

Construction Camp Facilities

Lack of proper infrastructure facilities such as housing, water supply and sanitation facilities will increase pressure on the local services and generate substandard living standards and health hazards.

Contractor shall provide the following facilities in the campsites

A perimeter security fence at least 1.5m in height constructed from appropriate materials.

Adequate housing for all workers A sickbay and first aid station Safe and reliable water supply. Water

supply from deep tube wells of 150 m depth that meets the national standards

Hygienic sanitary facilities and sewerage system. The toilets and domestic wastewater will be collected through a

31

Page 33: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

common sewerage. Provide separate latrines and bathing places for males and females with total isolation by wall or by location. The minimum number of toilet facilities required is one toilet for every ten persons.

Provide in-house community/common entertainment facilities. Dependence of local entertainment outlets by the construction camps to be discouraged/prohibited to the extent possible.

All camp facilities shall be maintained in a safe clean and or appropriate condition throughout the construction period.

Disposal of wastes

Management of wastes is crucial to minimize impacts on the environment

The Contractor should Ensure proper collection and disposal of

solid wastes within the construction camps Insist waste separation by source; organic

wastes in one pot and inorganic wastes in another pot at household level.

Store inorganic wastes in a safe place within the household and clear organic wastes on daily basis to waste collector. Establish waste collection, transportation and disposal systems with the manpower and equipment/vehicles needed.

Dispose organic wastes in a designated safe place on daily basis. At the end of the day cover the organic wastes with a thin layer of sand so that flies, mosquitoes, dogs, cats, rats, are not attracted.

Locate the garbage pit/waste disposal site min 500 m away from the residence so that peoples are not disturbed with the odor likely to be produced from anaerobic decomposition of wastes at the waste dumping places. Encompass the waste dumping place by fencing and tree plantation to prevent children to enter and play with.

Do not establish site specific landfill sites. All solid waste will be collected and removed from the work camps and disposed in approval waste disposal sites.

Health and Hygiene

There will be a potential for diseases to be

The Contractor shall Provide adequate health care facilities

32

Page 34: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

transmitted including malaria, exacerbated by inadequate health and safety practices.

within construction sites. Provide first aid facility round the clock.

Maintain stock of medicines in the facility and appoint fulltime designated first aider or nurse.

Provide ambulance facility for the laborers during emergency to be transported to nearest hospitals.

Initial health screening of the laborers coming from outside areas.

Train all construction workers in basic sanitation and health care issues and safety matters, and on the specific hazards of their work.

Provide adequate drainage facilities throughout the camps to ensure that disease vectors such as stagnant water bodies and puddles do not form. Regular mosquito repellant sprays during monsoon.

Carryout short training sessions on best hygiene practices to be mandatorily participated by all workers. Place display boards at strategic locations within the camps containing messages on best hygienic practices.

Safety In adequate safety facilities to the construction camps may create security problems and fire hazards

The Contractor shall Provide appropriate security personnel

(police/home guard or private security guards) and enclosures to prevent unauthorized entry into the camp area.

Maintain register to keep a track on a head count of persons present in the camp at any given time.

Encourage use of flameproof material for the construction of labor housing/site office. Also, ensure that these houses/rooms are of sound construction and capable of withstanding wind storms/cyclones.

Provide appropriate type of firefighting equipment suitable for the construction camps.

Display emergency contact numbers clearly and prominently at strategic places in camps.

Communicate the roles and responsibilities of laborers in case of emergency in the

33

Page 35: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

monthly meetings with contractors.

Site Restoration

Restoration of the construction camps to original condition requires demolition of construction camps

The Contractor shall Dismantle and remove from the site all

facilities established within the construction camp including the perimeter fence and lockable gates at the completion of the construction work.

Dismantle camps in phases and as the work gets decreased and not wait for the entire work to be completed.

Give prior notice to the laborers before demolishing their camps/units.

Maintain the noise levels within the national standards during demolition activities.

Different contractors shall be hired to demolish different structures to promote recycling or reuse of demolished material.

Reuse the demolition debris to a maximum extent. Dispose remaining debris at the designated waste disposal site.

Handover the construction camps with all built facilities as it is if agreement between both parties (contactor and land-owner) has been made so.

Restore the site to its condition prior to commencement of the works or to an agreed condition with the landowner.

Not make false promises to the laborers for future employment in O&M of the project.

ECoP 4: Waste Management

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

General Waste Soil, air and water pollution from the improper management of wastes and excess materials from the construction sites.

The Contractor shall Develop waste management plan for

various specific waste streams (e.g., reusable waste, flammable waste, construction debris, food waste etc.) prior to commencing of construction and submit to PMU for approval.

Organize disposal of all wastes generated during construction in an environmentally acceptable manner. This will include consideration of the nature and location of disposal site, so

34

Page 36: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

as to cause less environmental impact. Adopt national 3R (Reduce, Recycle and

Reuse) approach to minimize the production of wastes.

Segregate and reuse/recycle of all the wastes, wherever practical.

Prohibit burning of solid wastes at the construction site.

Collect and transport non-hazardous wastes to all the approved disposal sites. Vehicles transporting solid wastes shall be covered with tarps or nets to prevent spilling wastes or liquid along the route during transport.

Train and instruct all personnel in waste management practices and procedures as a component of the environmental induction process.

Provide refuse containers at each worksite.

Request suppliers to minimize packaging where practicable.

Place a high emphasis on good housekeeping practices.

Maintain all construction sites in a cleaner, tidy and safe condition and provide and maintain appropriate facilities as temporary storage of all wastes before transportation and final disposal.

Hazardous Waste

Health hazards and environmental impacts due to improper waste management practices.

The Contractor shall Collect chemical wastes in 200 liter

drums (or similar sealed container), appropriately labeled for safe transport to an approved chemical waste depot.

Store, transport and handle all chemicals avoiding potential environmental pollution.

Store all hazardous wastes appropriately in bounded areas away from water courses.

Make available Material Safety Data Sheets (MSDS) for hazardous materials on-site during construction.

Collect hydrocarbon wastes, including lube oils for safe transport off-site for reuse, recycling, treatment or disposal at approved locations.

Construct concrete or other impermeable flooring to prevent

35

Page 37: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

seepage in case of spills.

Construction Wastes

Health hazards, air and water pollution and environmental impacts due to improper waste management practices.

The contractor shall either re-use or dispose the waste

generated during construction depending upon the nature of waste.

The contractor shall dispose off the wastes in designated place that could not be re-used safely.

The waste management practices adopted by the Contractor shall be reviewed by the PMU during the progress of construction.

ECoP 5: Fuels and Hazardous Goods Management

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Fuels and hazardous goods.

Materials used in construction have a potential source of contamination. Improper storage and handling of fuels, lubricants, chemicals and hazardous goods/materials on-site, and potential spills from these goods may harm the environment or health of construction workers.

The Contractor shall Prepare spill control protocol and

submit the plan to PMU for approval. Train the relevant construction

personnel in handling of fuels and spill control procedures.

Store dangerous goods in bounded areas on a top of a sealed plastic sheet away from watercourses.

Refueling shall occur only within bounded areas.

Make available MSDS for chemicals and dangerous goods on-site.

Transport waste of dangerous goods, which cannot be recycled to a designated disposal site approved by DoE.

Provide absorbent and containment material (e.g., absorbent matting) where hazardous material are used and stored and personnel trained in the correct use.

Provide PPEs like protective clothing, safety boots, helmets, masks, gloves, goggles etc. to the construction personnel assigned to handle the wastes.

Make sure all containers, drums, and tanks that are used for storage are in good condition and are labeled with expiry date. Any container, drum, or tank that is dented, cracked or rusted might eventually leak. Check for leakage

36

Page 38: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

regularly to identify potential problems before they occur.

Store hazardous materials above flood plain level.

Put containers and drums in temporary storages in clearly marked areas, where they will not be run over by vehicles or heavy machinery. The area shall preferably slope or drain to a safe collection area in the event of a spill.

Put containers and drums in permanent storage areas on an impermeable floor that slopes to a safe collection area in the event of a spill or leak.

Take all precautionary measures when handling and storing fuels and lubricants, avoiding environmental pollution.

Avoid the use of material with greater potential for contamination by substituting them with more environmentally friendly materials.

Return the gas cylinders to the supplier. However, if they are not empty prior to their return, they must be labeled with the name of the gas, they contained, information of the supplier, cylinder serial number, pressure, their last hydrostatic test date, and any additional identification marking that may be considered necessary.

ECoP 6: Water Resources Management

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Hazardous Material and Waste

Water pollution from the storage, handling and disposal of hazardous materials and general construction waste and accidental spillage.

The Contractor shall Follow the wastes management

guidelines proposed in ECoP 5 and 6. Minimize the generation of sediment,

slurry, oil and grease, organic matter, litter, debris and any form of waste (particularly petroleum and chemical wastes). These substances must not enter into waterways, storm water systems or underground water table.

Discharge from construction

During construction both surface and groundwater

The Contractor shall Install temporary drainage works

37

Page 39: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

sites quality may be deteriorated due to construction activities. The construction works will modify ground cover and topography changing the surface water drainage patterns of the area including infiltration and storage of storm water. These changes in hydrological regime lead to increased rate of runoff, increase in sediment and contaminant loading, increased flooding, groundwater contamination, and effect habitat of fish and other aquatic biology.

(channels and bunds) in areas required for sediment and erosion control and around storage areas for construction materials.

Install temporary sediment basins, where appropriate, to capture sediment-laden run-off from site.

Divert runoff from undisturbed areas around the construction site.

Stockpile materials away from drainage lines.

Prevent all solid and liquid wastes entering waterways by collecting solid waste, oils, chemicals, bitumen spray waste and wastewaters from brick, concrete and asphalt cutting where possible and transport to an approved waste disposal site or recycling depot.

Wash out ready-mix concrete agitators and concrete handling equipment at washing facilities off site or into approved bounded areas on site. Ensure that tires of construction vehicles are cleaned in the washing bay (constructed at the entrance of the construction site) to remove the mud from the wheels. This shall be done in every exit of each construction vehicle to ensure the local roads are kept clean.

Soil erosion and siltation

Soil erosion and dust from the material stockpiles will increase the sediment and contaminant loading of surface water bodies.

The Contractor shall Stabilize the cleared areas not used for

construction activities with vegetation or appropriate surface water treatments as soon as practicable following earthwork to minimize erosion.

Ensure that roads used by construction vehicles are swept regularly to remove sediment.

Spray water on material stockpiles, access roads and bare soils at required basis to minimize dust. Increase the watering frequency during periods of high risk (e.g. high winds, high temperature, etc.).

ECoP 7: Drainage Management

38

Page 40: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Excavation and earthworks and construction yards

Lack of proper drainage for rainwater/liquid waste or wastewater owing to the construction activities harms environment in terms of water and soil contamination and mosquito growth.

The Contractor shall Prepare a program for prevent/avoid

standing waters, which PMU will verify in advance and confirm during implementation.

Provide alternative drainage for rainwater if the construction works/earth-fillings cut the established drainage line.

Establish local drainage line with appropriate silt collector and silt screen for rainwater or wastewater connecting to the existing established drainage lines already there

Rehabilitate road drainage structures immediately if damaged by contractors’ road transports.

Build new drainage lines as appropriate and required for wastewater from construction yards connecting to the available nearby recipient water bodies. Ensure wastewater quality conforms to the relevant standards provided by DoE, before it being discharged into the recipient water bodies.

Ensure the internal roads/hard surfaces in the construction yards/construction camps that generate storm water drainage to accommodate high runoff during downpour and that there is no stagnant water in the area at the end of the downpour.

Construct wide drains instead of deep drains to avoid sand deposition in the drains that require frequent cleaning.

Provide appropriate silt collector and silt screen at the inlet and manholes and periodically clean the drainage system to avoid drainage congestion.

Protect natural slopes of drainage channels to ensure adequate storm water drains.

Regularly inspect and maintain all drainage channels to assess and alleviate any drainage congestion problem.

Reduce infiltration of contaminated drainage through storm water management design.

39

Page 41: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Ponding of water

Health hazards due to mosquito breeding.

Do not allow ponding of water especially near the waste storage areas and construction and labor camps.

Discard all the storage containers that are capable of storing of water, after use or store them in inverted position.

ECoP 8: Erosion and Sediment Control

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Clearing of construction sites

Cleared areas and slopes are susceptible for erosion of top soils.

Reinstate and protect cleared areas as soon as possible.

Mulch to protect batter slopes before planting.

Cover unused area of disturbed or exposed surfaces immediately with mulch/grass turnings/tree plantations.

Construction activities and material stockpiles

The impact of soil erosion are (i) increased run off and sedimentation causing a greater flood hazard to the downstream, (ii) destruction of aquatic environment in nearby lakes, streams, and reservoirs caused by erosion and/or deposition of sediment damaging the spawning grounds of fish, and (iii) destruction of vegetation by burying or gullying.

The Contractor shall Locate stockpiles away from drainage

lines. Protect the toe of all stockpiles, where

erosion is likely to occur, with silt fences, straw bales or bunds.

Remove debris from drainage paths and sediment control structures.

Cover the loose sediments and then spray water, if required.

Divert natural runoff around construction areas prior to any site disturbance.

Install protective measures on site prior to construction, for example, sediment traps

Control drainage through a site in protected channels or slope drains.

Install ‘cut off drains’ on large cut/fill batter slopes to control water runoff speed and hence erosion.

Make sure to clean the sediment deposits and vegetation from the drainage structures before rainy season.

ECoP 9: Air Quality Management

40

Page 42: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Construction vehicular traffic

Air quality can be adversely affected by vehicle exhaust emissions and combustion of fuels.

The Contractor shall Fit vehicles with appropriate exhaust

systems and emission control devices. Maintain these devices in good working condition.

Operate the vehicles in a fuel-efficient manner

Cover hauls vehicles carrying dusty materials moving outside the construction site.

Impose speed limits on all vehicle movement at the worksite to reduce dust emissions.

Control the movement of construction traffic.

Spray water on construction materials prior to loading and transport.

Service all vehicles regularly to minimize emissions.

Limit the idling time of vehicles not more than 2 minutes.

Construction machinery

Air quality can be adversely affected by emissions from machinery and combustion of fuels.

The Contractor shall Fit machinery with appropriate exhaust

systems and emission control devices. Maintain these devices in good working condition in accordance with the specifications defined by their manufacturers to maximize combustion efficiency and minimize the contaminant emissions. Undertake servicing of all equipment regularly to minimize emissions

Provide filtering systems, duct collectors or humidification or other techniques (as applicable) to the concrete batching and mixing plant to control the particle emissions in all its stages, including unloading, collection, aggregate handling, cement dumping, circulation and others.

Construction activities

Dust generation from construction sites, material stockpiles and access roads are a nuisance in the environment, cause air pollution and can be health hazard of the workers and surrounding

Water the material stockpiles, access roads and bare soils as required to minimize the potential for environmental nuisance due to dust. Increase the watering frequency during periods of high risk (e.g. high winds, high temperature). Stored materials such as gravel and sand shall be covered and confined to avoid their being wind-drifted.

41

Page 43: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

local communities. Minimize the extent and period of exposure of the bare surfaces.

Reschedule earthwork activities or vegetation clearing activities, where practical, if necessary to avoid during periods of high wind and if visible dust is blowing off-site.

Restore disturbed areas as soon as practicable by vegetation/grass-turfing.

Store the cement in silos and minimize the emissions from silos by equipping them with filters.

Establish adequate locations for storage, mixing and loading of construction materials, in a way that dust dispersion is prevented because of such operations.

Crushing of rocky and aggregate materials shall be wet-crushed, or performed with particle emission control systems.

ECoP 10: Noise and Vibration Management

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Construction vehicular traffic

Noise quality will be deteriorated due to vehicular traffic

The Contractor shall Maintain all vehicles in good working

condition in accordance with manufactures maintenance procedures/protocols.

Make sure all drivers will comply with the traffic codes concerning maximum speed limit, driving hours, etc.

Organize the loading and unloading of trucks, and handling operations for the purpose of minimizing construction noise on the work site.

Construction machinery

Noise and vibration may have an impact on people, property, fauna, livestock and the natural environment.

The Contractor shall Appropriately site for all noise generating

activities to avoid noise pollution of local residents.

Use the quietest available plant and equipment

Modify equipment to reduce noise (for example, noise control kits, lining of truck trays or pipelines).

Maintain all equipment in good working condition in accordance with

42

Page 44: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

manufactures maintenance procedures/protocols. Equipment suppliers and contractors shall present the proof of maintenance register of their equipment.

Install acoustic enclosures around generators to reduce noise levels.

Fit high efficiency mufflers to appropriate construction equipment.

Avoid the unnecessary use of alarms, horns and sirens in the construction sites.

Construction activity

Noise and vibration may have an impact on people, property, fauna, livestock and the natural environment.

The Contractor shall Notify adjacent landholders prior any

typical noise events outside of daylight hours.

Educate the operators of construction equipment on potential noise problems and the techniques to minimize noise emissions.

Employ best available work practices on-site to minimize occupational noise levels.

Install temporary noise control barriers where appropriate.

Notify affected people if major noisy activities will be undertaken, e.g. pile driving.

Plan activities on site and deliveries to and from site to minimize impact.

Monitor and analyze noise and vibration results and adjust construction practices as required.

Avoid undertaking the noisiest activities, where possible, when working at night near the residential areas.

ECoP 11: Road Transport and Road Traffic Management

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Construction vehicular traffic

Increased traffic use of road by construction vehicles will affect the movement of normal road traffics and the safety of the road-users.

The Contractor shall Prepare and submit a traffic management

plan to the PMU for approval at least 30 days before commencing work on any project component involved in traffic diversion and management.

Include in the traffic management plan to ensure uninterrupted traffic movement during construction: detailed drawings of traffic arrangements showing all detours,

43

Page 45: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

temporary road, temporary bridges temporary diversions, necessary barricades, warning signs/lights, and road signs.

Provide signs at strategic locations of the roads complying with the schedules of signs contained in the Bangladesh Traffic Regulations.

Install and maintain a display board at each important road intersection to be used during construction, which shall clearly show the following information in Bangla:

Location and types of construction of ongoing works

Duration of construction period Period of proposed detour/alternative

route Suggested detour route map Name and contact address/telephone

number of the concerned personnel Name and contact address/telephone

number of the Contractor Inconvenience is sincerely regretted.

Accidents and spillage of fuels and chemicals

Restrict truck deliveries, where practicable to day time working hours.

Restrict the transport of oversize loads. Operate road traffics/transport vehicles, if

possible, to non-peak periods to minimize traffic disruptions.

Enforce on-site speed limit.

44

Page 46: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

ECoP 12: Cultural and Religious Issues

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Construction activities near religious and cultural sites

Disturbance from construction works to the cultural and religious sites, and contractors lack of knowledge on cultural issues cause social disturbances.

The Contractor shall Communicate to the public through

community consultation and newspaper announcements regarding the scope and schedule of construction, as well as certain construction activities causing disruptions or access restriction.

Do not block access to cultural and religious sites, wherever possible

Restrict all construction activities within the foot prints of the construction sites.

Stop construction works that produce noise (particularly during prayer time) should there be any mosque/religious/educational institutions close to the construction sites and users make objections.

Take special care and use appropriate equipment when working next to a cultural/religious institution.

Show appropriate behavior with all construction workers especially women and elderly people

Resolve cultural issues in consultation with local leaders and supervision consultants

Establish a mechanism that allows local people to raise grievances arising from the construction process.

ECoP 13: Occupational Health and Safety

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

Best practices Construction works may pose health and safety risks to the construction workers and site visitors leading to severe injuries and deaths. The population in the proximity of the construction site and the construction workers will be exposed to a number

The Contractor shall Implement suitable safety standards for all

workers and site visitors which should not be less than those laid down on the international standards (e.g. International Labor Office guideline on ‘Safety and Health in Construction; World Bank Group’s ‘Environmental Health and Safety Guidelines’) and contractor’s own national standards or statutory regulations, in addition to complying with the national

45

Page 47: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

of (i) biophysical health risk factors, (e.g. noise, dust, chemicals, construction material, solid waste, wastewater, vector transmitted diseases etc.), (and (ii) road accidents from construction traffic.

standards of the Government of Bangladesh (e.g. `The Bangladesh Labor Code, 2006’)

Provide the workers with a safe and healthy work environment, taking into account inherent risks in its particular construction activity and specific classes of hazards in the work areas,

Provide personal protective equipment (PPE) for workers, such as safety boots, helmets, masks, gloves, protective clothing, goggles, full-face eye shields, and ear protection. Maintain the PPE properly by cleaning dirty ones and replacing them with the damaged ones.

Safety procedures include provision of information, training and protective clothing to workers involved in hazardous operations and proper performance of their job

Appoint an environment, health and safety manager to look after the health and safety of the workers.

Accidents Lack of first aid facilities and health care facilities in the immediate vicinity will aggravate the health conditions of the victims

Provide health care facilities and first aid facilities are readily available. Appropriately equipped first-aid stations should be easily accessible throughout the place of work

Document and report occupational accidents, diseases, and incidents.

Prevent accidents, injury, and disease arising from, associated with, or occurring in the course of work by minimizing, so far as reasonably practicable, the causes of hazards. In a manner consistent with good international industry practice.

Identify potential hazards to workers, particularly those that may be life-threatening and provide necessary preventive and protective measures.

Provide awareness to the construction drivers to strictly follow the driving rules

Provide adequate lighting in the construction area and along the roads.

Water and sanitation facilities at the construction sites

Lack of Water sanitation facilities at construction sites cause inconvenience to the construction workers and affect their personal hygiene.

The contractor should provide portable toilets at the construction sites, if about 25 people are working the whole day for a month. Location of portable facilities should be at least 6m away from storm drain system and surface waters. These portable toilets should be cleaned once a day and all the sewerage should be pumped from the collection tank once a day and

46

Page 48: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project activity/ Impact source

Environmental Impact Mitigation Measures/ Management Guidelines

should be brought to the common septic tank for further treatment. Contractor should provide bottled drinking water facilities to the construction workers at all the construction sites.

ECoP 14: Community/Public Health and Safety

The safety and health of the public is impacted due to the hazards created during the construction period. This code of practice describes the measures that need to be taken to mitigate the impacts. Pre-construction Stage In order to incorporate public health and safety concerns, the PMU and the Contractor shall disseminate the following information to the community:

Location of subproject activities, Borrow areas, Extent of work Time of construction Involvement of local labors in subproject construction Health issues - exposure to dust, communicable diseases etc.

Construction Stage Proper safety/warning signs are to be installed by the contractor to inform the public of

potential health and safety hazard situations during the construction phase in the vicinity of the project.

The PMU shall carry out periodic inspections in order to ensure that all the measures are being undertaken as per this ECoP.

Post-construction Stage The construction site shall be cleaned of all debris, scrap materials and machinery on

completion of construction for the safety of public and users.

47

Page 49: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

ECoP 15: Accident and Emergency Plan

Tractors, Motor Vehicles and other Self-Propelled Implements: These and all other vehicles must be immobilized when not in use.

Machinery, Plant and Equipment Sharp points, spikes and sharp edges must be protected. Adequate support must be given

to prevent moving or tipping up. Cutter bars, knives or other cutters must have their blades removed or approved guards covering them. Belts, gearing and other moving parts must be guarded so that there is no danger whatsoever and the public must be kept well clear. Hydraulics must be immobilized.

Hydraulics Any equipment operated by hydraulics, i.e. trailers, tractor buckets, fork lifts, chutes must

be suitably propped with steel props and at separate stages if in multi-stage rams. Any steam or pressure vessel or lifting appliance used must have undergone a recent inspection by a competent person.

Tower Cranes and Hoists The area over which the crane is exhibited must be protected in case of collapse.

Digging of Holes and Other Excavations No post holes are to be bored nor is any other digging or excavation to take place

anywhere without written authorization

Fencing Single rope or post and rail fencing will normally suffice as providing minimum protection

however, where there is a need to prevent total public access to a site or part thereof, secure wire mesh or vertical barrier rail type fences should be used.

Storage of Flammable Liquids and Gas Storage of these materials will not normally be permitted. These must be secured to

prevent theft or misuse, they should be supported so that they cannot fall over and valves and pipes are to be kept clear of obstructions and free from external pressures.

Protective Clothing Standardized protective clothing should be used wherever there is a requirement.

Electricity The contractor will inspect all pre-wired installations when connecting the supply and a

charge will be made should further testing be required. Contractors will be held responsible for the safekeeping of fittings and installations on their sites.

Traffic All vehicles used must comply with the relevant safety and road traffic regulations.

Site safety rules for contractors Appropriate personnel protective equipment (PPE) e.g. hard hats, vests, ear protection

and safety boots to be worn when required. No persons are to use lifting equipment of any description unless they have undergone

the relevant training All lifting equipment to be accompanied by current certificate of inspection Exclusion zones are to be put into place around all heavy and or awkward lifting

operations All tools and equipment to be kept in good working order and only to be used for the

purpose for which they were intended, any defects in tools or equipment should be reported as soon as possible to the relevant contractor’s supervisor, or if deemed

48

Page 50: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

necessary to the site office immediately. All equipment and tools not in use must be safely and securely stored in the appropriate

area, so that they may only be accessed by authorized persons and do not pose any danger to other workers or members of the public.

All walkways, access points and emergency exits to be free from obstruction at all times. All contractors should ensure that they do not obstruct any emergency exits,

thoroughfares or access points with any articles or materials. All contractors, sub-contractors and other staff are to ensure they are familiar with

procedures to be followed in the event of an emergency or major incident. All incidents resulting in injury and any near misses to be reported to relevant project

manager. Exclusion zones to be established around areas where work at height is being carried out,

or where overhead loads are being slung. Any worker found, or suspected to be, under the influence of alcohol or illegal drugs will

be asked to leave the site. Health & safety compliance will be monitored by designated safety manager of the

contractor who will liaise with suppliers, site management to ensure that the above rules are being followed.

Fire Safety All workers should be aware of the location of firefighting equipment, fire alarm points

and the locations of emergency exits and routes in the area in which they are working.

Noise at Work The contractor has a duty to ensure that their staff are adequately protected against the

harmful effects of noise. The contractor will supply their staff with appropriate noise projection gear.

Loading/Unloading of Vehicles ALL vehicles must observe the site speed limit at all times. All workers and visitors to wear hi-vis waistcoats at all times whilst on site. All goods vehicles must have their vehicle height clearly marked if in doubt of height

clearance, should be seen to the site by a competent person from the contractor’s team. All delivery vehicles should be seen into and away from their unloading position by a

competent person to avoid collisions, particularly with people. All workers should be aware of traffic in the vicinity of the unloading areas and on the

roadways. Make sure when lifting articles and materials or equipment from vehicles or trailers, and

or releasing load bars/straps/ties be aware that other equipment may have become dislodged which could fall.

Be aware of slippery areas and trip hazards Try to ensure that adequate lighting is available both inside and out of the immediate

loading/unloading area. An exclusion zone should be made around unloading areas to avoid unnecessary danger

to crew and or public. Continual monitoring of ramps and loading bays should be carried out to alleviate the

potential of harm. Equipment must not block any designated fire/ambulance lanes at any time. Appropriate signage should be used to make people aware of the dangers of the area.

Mechanical Handling Vehicles must observe the site speed limit at all times. All vehicles must comply with any current and or relevant standards

49

Page 51: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Vehicles must be parked in a safe place ensuring that no emergency routes are blocked.

Construction and Dismantling of Structures Be aware of other work going on around you.

Accident Procedure If an accident occurs firstly make sure that nobody is in any immediate danger i.e. from

electrocution, traffic, falling truss etc. Do not move the patient unless they are in further danger. Send someone to call for medical help. If trained, administer first aid, or otherwise summon a trained first-aider. Clear by-standers and onlookers from the area

50

Page 52: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Annex G: Sample Environmental Screening Form

Sub Project Name

Sub Project Details in Brief:

Sub Project location/s:

Project Details

Sl.no Components Details

1 Sub Project components

2 Details of Alignment / Components (main components including construction activities)

3 Location of the sub project Sites &

Current Land use (Provide information for all sites involved in the project), any historic land use (related to heritage, or contamination)

Site Survey No:/s (with ownership), Geographical co-ordinates of the site location [including any off-site sub components [attach map]

Proposed Resource Use

Resource Use

Sl.no Proposed Resources Area/

Quantity

Unit Details

(i). Land Area proposed to be used: Location wise (in sq km / sq m)

51

Page 53: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

(ii). Estimated energy consumption for the project activities – Source wise

(iii). Estimated usage of water quantity for the project: Ground Water and Surface water?

Baseline Environmental Conditions

Sl.no Environmental Aspects Yes No Details

1 Is the project site located on or adjacent to any of the following (Provide information for all sites and alignment of the project components/subcomponents, associated activities; mention distance to these features in meters/kilometers)

i) Critically Vulnerable Coastal Areas, Eco-sensitive Areas

ii) Cultural Heritage site, Protected monuments

iii) Natural Forests / Protected Areas

Is the sub project in an eco- sensitive or adjoining an eco-sensitive area?

If Yes, provide details.

iv) Any other Wetlands/ Mangrove/ Estuarine Region?

v) Any Natural Habitat areas, areas with natural features?

vi) Any other Sensitive Environmental Components?

vii) Any Residences, schools, hospitals, sensitive receptors?

viii) Any culturally – socially important paths, areas/religious occupancies, burial grounds, tourist or pilgrim congregation areas, borders, etc?

ix) Any Drinking water source, upstream and downstream uses of rivers, etc?

x) Any Low-lying areas prone to flooding/areas

52

Page 54: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

of Tidal Influence?

xi) Any areas affected by other disasters?

2 Is the site in Critical / Over Exploited condition?

3 Is the area disaster-prone? If yes; list all disaster zone categories applicable

4 Describe the soil and vegetation on site n/a n/a

5 Is the site area and condition suitable for proposed development?

6 Describe existing pollution or degradation in the site(s)

n/a n/a

7 Any other remark on baseline condition?

Anticipated Environmental Impacts: Impacts on Land, Geology and Soils

Sl.no Impacts Yes/

May create

No Details

8. Will the proposed project cause the following on Land / Soil:

i) Impact on Surrounding Environmental Conditions including Occupation on Low lying lands/flood plains

ii) Substantial removal of Top Soil (mention area in sqm)

iii) Any degradation of land / eco-systems expected due to the project?

iv) Loss or impacts on Cultural/heritage properties

v) Does the project activity involve cutting and filling/ blasting etc?

vi) Will the project cause physical changes in the project area (e.g., changes to the topography) due to earth filling, excavation, earthwork or any other activity?

53

Page 55: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

vii) Will the project involve any quarrying/

mining etc?

viii Will the project / any of its component contaminate or pollute the Land?

ix) Will the project contribute to any long- term significant adverse (negative), large scale, irreversible, sensitive impact at a regional scale or area broader than the project sites?

Impacts on Water Environment

Sl.no Impacts Yes/ May Create

No Details

9 Will the subproject or its components cause any of the following impact on Water sources (Quantity or Quality):

i) Will the activities proposed at the site(s) impact water quality (surface or u n d e r ground) and water resource availability and use? Will this sub-project involve the dredging of water bodies, sea, canals, etc.

ii) Impacts on Water Resources

iii) Pollution of Water bodies/ground water nearby or downstream

iv) Will the project affect the River /cannel flow pattern, stream pattern or any other irrigation canal?

v) Will the project result in stagnation of water flow or pondage or weed growth

54

Page 56: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Impacts on Biodiversity and Host Communities

Sl.no Environmental Impacts Yes/ May Create

No Details

10 Will the subproject or its components cause any of the following impacts on Biodiversity or the neighbourhood

i) Will the project necessitates cutting of?

Trees / Loss of Vegetation

ii) Will the project result in Health & Safety Risks in the neighbourhood including the release of toxic gases, accident risks

iii) Potential risk of habitat fragmentation due to the clearing activities? (e.g. Hindrance to the local biodiversity like disturbing the migratory path of animals/ birds etc.)

iv) Potential Noise and Light Pollution or disturbance to surrounding habitats/communities

v) Potential disruption to common property, accessibility, traffic disruptions, conflicts or disruption to the local community within the subproject area?

Impacts due to Storage and Wastes: Pollution and Hazards

Type Yes No Details

11 Will the subproject or its components cause any impact due to storage of materials, wastes or pollution due to releases during various project activities

i) Will the project use or store dangerous substances (e.g., large quantities of hazardous chemicals/ materials like Chlorine, Diesel, Petroleum products; any other?

55

Page 57: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

ii) Will the project produce solid or liquid wastes; including construction/demolition wastes (including dredging, de-weeding wastes, muck/silt, dust); polluted liquids?

iii) Will the project cause or increase air pollution or odor nuisance?

iv) Will the project generate or increase noise levels which will impact surrounding biodiversity or communities?

v) Will the project generate or increase visual blight or light pollution?

vi) Will the project cause water pollution?

(of waterbodies/ groundwater)?

vii) Will the project involve dangerous construction activities which may be a safety concern to workers/ host communities

viii Is there a potential for release of toxic gases or accident risks (e.g. potential fire outbreaks)

12 Describe any other features of the project that could influence the ambient environment

13 Were the probable environmental impacts discussed with stakeholders?

Suggested Environmental Enhancement Measures

Enhancement Measures Yes No Details

14 Has the subproject design considered the following enhancement measures?i) Energy conservation measures/ energy

recovery options incorporated in subproject design

ii) Considered waste minimization or waste reuse/recycle options

iii) Rainwater harvesting, water recycling and other water resource enhancement measures

56

Page 58: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

iv) Considerations for extreme events, drought, flood, other natural disasters

vi) NOC for water withdrawal from surface water source

vii) Mining Permit (for dredging)

viii) NOC for transportation and storage of diesel, oil and lubricants, etc.

ix) Others (Mention)

This Screening sheet must be completed for each of the proposed subproject and forwarded to the Environment Specialist in Respective PMU along with the following enclosures.

Enclosures: Provide maps with the geographical location of the project; and an appropriately-scaled map clearly showing the project area and project sites with land use, existing buildings, infrastructure, vegetation, adjacent land use, utility lines, access roads and any planned construction, and any other information to describe the project, locations and possible impact as required.

Project Categorization and Need for Safeguards Instruments, Oversight

Project Category □ Low □ Moderate □ Substantial □ High

Key Reasons

Safeguards Instruments Required □ Detailed ESIA and ESMP

□ ESA

□ RAP

□ Site-specific ESMP

Status Agency / Official Name, Signature with Date and SealPrepared by Environmental

SpecialistEnvironmental E x p e r t - in

57

Page 59: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Checked and Categorized as (low, moderate, substantial, high) by

PMU

Environmental

Specialist

Reviewed & accepted by

PMU

Environmental

Specialist

58

Page 60: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Annex H: Sample Social Screening Form

Subproject Name …………………………………

Subproject location …………………………….

Land Use, Resettlement, and/or Land Acquisition

Sl.no Components Yes No Details

1 Does the project involve acquisition of private land?

2 Alienation of any type of Government land including that owned by Urban Local Body?

3 Clearance of encroachment from

Government/ Local body Land?

4 Clearance of squatters/hawkers from

Government/ Local Body Land?

5 Number of structures, both authorized and/or unauthorized to be acquired/ cleared/

6 Number of households to be displaced?

7 Village common properties to be alienated Pasture Land (acres) Acquisition / burial ground and others specify?

8 Existing land uses on and around the project area (e.g., community facilities, agriculture, tourism, private property) will be affected?

9 Will the project result in construction workers or other people moving into or having access to the area (for a long-time period and in large numbers compared to permanent residents)?

10 Are financial compensation measures expected to be needed?

Loss of Crops, Fruit Trees, Household Infrastructure and livelihood

11 Will the project result in the permanent or temporary loss of the following?

59

Page 61: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

11.1 Crops?

11.2 Fruit trees? Specify with numbers

11.3 Petty Shops

11.4 Vegetable/Fish/Meat vending

11.5 Cycle repair shop11.6 Garage11.7 Tea stalls11.8 Grazing11.9 Loss of access to forest produce (NTFP)11.10 Any others - specifyWelfare, Employment, and Gender12 Is the project likely to provide local

employment opportunities, including employment opportunities for women?

13 Is the project being planned with sufficient attention to local poverty alleviation objectives?

14 Is the project being designed with sufficient local participation (including the participation of women) in the planning, design, and implementation process?

Historical, Archaeological, or Cultural Heritage SitesBased on available sources, consultation with local authorities, local knowledge and/or observations, could the project alter:15 Historical heritage site(s) require

excavation near the same?16 Archaeological heritage site(s) require

excavation near the same?17 Cultural heritage site(s) require excavation

near the same?18 Graves or sacred locations require

excavations near the same?Tribal Population/Indigenous People19 Does this project involve acquisition of any

land belonging to Tribal people?Beneficiaries20 Population proposed to be benefitted by

the proposed projectApprox. no.:

21 No. of Females proposed to be benefitted by the proposed project

Approx. no.:

22 Vulnerable households /population to be benefitted

Approx. no.:

23 No. of Families to be benefitted Approx. no.:

60

Page 62: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

This Screening sheet must be completed for each of the proposed subproject by respective social team and forwarded to the Social Specialist in Respective PMU along with the following enclosures.

(Enclosures: Land details for the project sites, location, survey numbers, extent available and required, land use classification, current use of the site, land ownership, alienation/acquisition status, as required along with a certificate giving availability of sites required for the project by the borrower.)

61

Page 63: documents.worldbank.org€¦  · Web viewThe consultant will define project activities and any linked and/or associated activities. The consultant will review and analyse the technical

Project Categorisation and Need for Safeguards Instruments, Oversight

Project Category □ Low □ Moderate □ Substantial □ HighKey Reasons

Safeguards Instruments Required □ Detailed ESIA and ESMP

□ ESA

□ RAP

Status Agency / Official Name, Signature with Date and SealPrepared by Social Specialist

Social Expert / in –

charge

Checked and Categorized as (low, moderate, substantial, high) by

PMU

Social Specialist

Reviewed & accepted by

NPMU

Social Specialist

62


Recommended