+ All Categories
Home > Documents > WEEKLY CONSTRUCTION PROGRESS REPORT Project: Mary Lin … · 2014. 3. 24. · WEEKLY CONSTRUCTION...

WEEKLY CONSTRUCTION PROGRESS REPORT Project: Mary Lin … · 2014. 3. 24. · WEEKLY CONSTRUCTION...

Date post: 07-Mar-2021
Category:
Upload: others
View: 11 times
Download: 0 times
Share this document with a friend
2
WEEKLY CONSTRUCTION PROGRESS REPORT Project: Mary Lin Elementary School This Week’s Activities March 17 – March 21 I. Phase 1 - Site Work Site utilities demolition ongoing. Site work/grading ongoing. Existing Detention Pond expansion completed. New Storm System installation off Candler Park ongoing. II. Phase 2B – Interior Kitchen/Cafeteria demolition ongoing. Interior demolition at lower level Stucco building ongoing. Figure 2- New Storm System – Candler Park Dr. Figure 1- New Storm System – Candler Park Dr.
Transcript
Page 1: WEEKLY CONSTRUCTION PROGRESS REPORT Project: Mary Lin … · 2014. 3. 24. · WEEKLY CONSTRUCTION PROGRESS REPORT . Project: Mary Lin Elementary School This Week’s Activities .

WEEKLY CONSTRUCTION PROGRESS REPORT Project: Mary Lin Elementary School This Week’s Activities March 17 – March 21 I. Phase 1 - Site Work

• Site utilities demolition ongoing. • Site work/grading ongoing. • Existing Detention Pond expansion completed. • New Storm System installation off Candler Park ongoing.

II. Phase 2B – Interior

• Kitchen/Cafeteria demolition ongoing. • Interior demolition at lower level Stucco building ongoing.

Figure 2- New Storm System – Candler Park Dr. Figure 1- New Storm System – Candler Park Dr.

Page 2: WEEKLY CONSTRUCTION PROGRESS REPORT Project: Mary Lin … · 2014. 3. 24. · WEEKLY CONSTRUCTION PROGRESS REPORT . Project: Mary Lin Elementary School This Week’s Activities .

WEEKLY CONSTRUCTION PROGRESS REPORT

Figure 3- Interior Demolition Figure 4- Interior Demolition

Figure 3 – Interior Demolition Figure 4 – Cooler/Freezer Demoed.

Next Week’s Activities – Site Work March 24 – March 28

• Parking lot- dirt excavation to continue. • Interior demolition to continue. • Installation of new storm system off Candler Park Dr. to continue.


Recommended