+ All Categories
Home > Documents > WEEKLY CONSTRUCTION REPORTWEEKLY CONSTRUCTION REPORT December 7, 2012 PROJECT NAME: INDOT CONTRACT...

WEEKLY CONSTRUCTION REPORTWEEKLY CONSTRUCTION REPORT December 7, 2012 PROJECT NAME: INDOT CONTRACT...

Date post: 19-Mar-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
4
WEEKLY CONSTRUCTION REPORT December 7, 2012 PROJECT NAME: INDOT CONTRACT B-30069 POPLAR LANE OVER HART DITCH (LAKE COUNTY BRIDGE 364) PROJECT NUMBER: 0600753 DESIGNER: UNITED CONSULTING CONSTRUCTION INSPECTION: UNITED CONSULTING - CHRIS COFFEY CONTRACTOR: ELLAS CONSTRUCTION CO., INC. LETTING DATE: JULY 11, 2011 NTP ISSUED: AUGUST 8, 2011 INTERMEDIATE COMPLETION: NOVEMBER 1, 2012 ADJUSTED INTERMEDIATE COMPLETION: NOVEMBER 20, 2012 (MET ON NOVEMBER 2, 2012) FINAL COMPLETION: JUNE 1, 2013 ADJUSTED FINAL COMPLETION: JUNE 1, 2013 ORIGINAL CONTRACT AMOUNT: $1,070,554.88 ADJUSTED CONTRACT AMOUNT: $1,070,554.88 PERCENT PROJECT COMPLETE: 61.33% (NEXT PAY ESTIMATE PROCESSED 12/9/2012) _________________________ Summary of Activities This Past Week (12/1/12 – 12/7/12) o Approaches poured for Phase 2 o Asphalt for Phase 2 (remainder to be placed in the spring when the plant re-opens) o Phase 2 sidewalk on bridge and approaches o Curb and Gutter/Sidewalk on North side of Poplar Lane Anticipated Activities for the Upcoming Week (12/10/12 – 12/14/12) o Water main installation in North side of bridge o Field Drilled Holes and Reinforcing Steel for Phase 3
Transcript
Page 1: WEEKLY CONSTRUCTION REPORTWEEKLY CONSTRUCTION REPORT December 7, 2012 PROJECT NAME: INDOT CONTRACT B-30069 POPLAR LANE OVER HART DITCH (LAKE COUNTY BRIDGE 364) PROJECT NUMBER: 0600753

WEEKLY CONSTRUCTION REPORT December 7, 2012

PROJECT NAME: INDOT CONTRACT B-30069

POPLAR LANE OVER HART DITCH (LAKE COUNTY BRIDGE 364)

PROJECT NUMBER: 0600753

DESIGNER: UNITED CONSULTING

CONSTRUCTION INSPECTION: UNITED CONSULTING - CHRIS COFFEY

CONTRACTOR: ELLAS CONSTRUCTION CO., INC.

LETTING DATE: JULY 11, 2011

NTP ISSUED: AUGUST 8, 2011

INTERMEDIATE COMPLETION: NOVEMBER 1, 2012

ADJUSTED INTERMEDIATE COMPLETION: NOVEMBER 20, 2012 (MET ON NOVEMBER 2, 2012)

FINAL COMPLETION: JUNE 1, 2013

ADJUSTED FINAL COMPLETION: JUNE 1, 2013

ORIGINAL CONTRACT AMOUNT: $1,070,554.88

ADJUSTED CONTRACT AMOUNT: $1,070,554.88

PERCENT PROJECT COMPLETE: 61.33% (NEXT PAY ESTIMATE PROCESSED 12/9/2012)

_________________________ � Summary of Activities This Past Week (12/1/12 – 12/7/12)

o Approaches poured for Phase 2

o Asphalt for Phase 2 (remainder to be placed in the spring when

the plant re-opens)

o Phase 2 sidewalk on bridge and approaches

o Curb and Gutter/Sidewalk on North side of Poplar Lane

� Anticipated Activities for the Upcoming Week (12/10/12 – 12/14/12)

o Water main installation in North side of bridge

o Field Drilled Holes and Reinforcing Steel for Phase 3

Page 2: WEEKLY CONSTRUCTION REPORTWEEKLY CONSTRUCTION REPORT December 7, 2012 PROJECT NAME: INDOT CONTRACT B-30069 POPLAR LANE OVER HART DITCH (LAKE COUNTY BRIDGE 364) PROJECT NUMBER: 0600753

Construction Photos

Phase 2 Approaches Poured

12/1/2012

Phase 2 Wedge and Level Asphalt

Page 3: WEEKLY CONSTRUCTION REPORTWEEKLY CONSTRUCTION REPORT December 7, 2012 PROJECT NAME: INDOT CONTRACT B-30069 POPLAR LANE OVER HART DITCH (LAKE COUNTY BRIDGE 364) PROJECT NUMBER: 0600753

Sidewalk on Bridge and Approaches

Page 4: WEEKLY CONSTRUCTION REPORTWEEKLY CONSTRUCTION REPORT December 7, 2012 PROJECT NAME: INDOT CONTRACT B-30069 POPLAR LANE OVER HART DITCH (LAKE COUNTY BRIDGE 364) PROJECT NUMBER: 0600753

Curb and Gutter with Sidewalk


Recommended